Item ID: Rev.: 00 Status: Final Effective Date: 29-Feb-2015 EXECUTIVE SUMMARY

Size: px
Start display at page:

Download "Item ID: Rev.: 00 Status: Final Effective Date: 29-Feb-2015 EXECUTIVE SUMMARY"

Transcription

1 EXECUTIVE SUMMARY The objective of this report is to demonstrate that sections of pipeline between MLV 401 and MLV 402 on the Canadian Mainline Line meet the applicable requirements in CSA Z clause for the section with the change of class. The class location change is as a result of residential and commercial development in the area, which is located just south of Ile Des Chènes, Manitoba. According to CSA Z662-15, Clause , if there is a class location change for a pipeline, the conformance or non-conformance to the requirements of clause must be documented. Clause requires the following items to be verified for the new location class: a) Design factor or location factor b) Valve spacing c) Depth of cover and clearance d) Pressure testing, and e) Evaluation and repair of imperfections TransCanada PipeLines Limited (TransCanada) has reviewed the class location change sites and determined that the location factor, depth of cover and clearance, and pressure testing for Line meet the requirements of the new class locations. However as the depth of cover survey was done some time ago, a new survey is proactively recommended. The metal-loss corrosion features identified in the class location change site for Line were evaluated using the location factor corresponding to the new class location. The features were found to be acceptable as per Clause of CSA Z No dents and gouges were found in the 2013 Caliper in-line inspection (ILI) for the class location change site on Line The review of the existing mainline block valves identified that valves MLV and MLV are equipped with automatic isolation capabilities. The existing valve spacing for the class location change sites do not meet the default valve spacing requirement for the new class location as specified in CSA Z Clause Therefore, a valve spacing Engineering Assessment (EA) was conducted. The valve spacing EA addressed both Lines and and was submitted to the National Energy Board (NEB) on 16 July This valve spacing EA has been reformatted to include only Line and it is provided in Appendix A of this report. The following actions are recommended by this class change assessment and the valve spacing EA for Line 400-2: 1. By March 31, 2016, complete depth of cover survey for the class change site on Line to confirm that the depth of cover is still adequate and that the requirements outlined in Table 4.9 of CSA Z are met. 2. The inspection frequency of MLV and MLV isolation valves was increased in 2015 to semi-annual (every 6 months), including the associated tie-over valves. This increase in inspection frequency resulted in an increased assurance in the reliability of isolation valves and appropriate valve closure times. 3. The valve spacing will be maintained at km. TransCanada will perform the actions identified and continue to manage the integrity of the class location change site according to the TransCanada s integrity management program (IMP). Page 1 of 15

2 APPROVALS Page 2 of 15

3 Table of Contents 1.0 INTRODUCTION Class Location Change Sites CSA Z Requirements EVALUATION OF CONFORMANCE TO THE NEW CLASS LOCATION REQUIREMENTS Design Factor or Location Factor Valve Spacing Depth of Cover and Clearance Pressure Testing Evaluation and Repair of Imperfections RECOMMENDATIONS REFERENCES APPENDIX A Page 3 of 15

4 1.0 INTRODUCTION 1.1 CLASS LOCATION CHANGE SITES TransCanada identified class location change sites for Lines 400-1, and between MLV 401 and MLV 402 on the Canadian Mainline System. The class location change sites are located just south of Ile Des Chènes, Manitoba. The class location change is a result of new residential and commercial development in the area. Note that the scope of this report is limited to only the class location change site on Line 400-2, as a previous class change assessment report covering Lines and was filed with the NEB on 15 December 2015 (Filing no. A74759). For the detailed location of the class location change sites for Line 400-2, see Table 1. For an image showing the location of the class location change sites, see Figure 1. Table 1: Pipeline Sections with the Class Location Designation Change Line Name Start chainage End chainage Class Location (m) (m) Change MLV 401 to 402 Line (NPS 36) Class 2 to Class 3 MLV 401 to 402 Line (NPS 36) Class 1 to Class 3 MLV 401 to 402 Line (NPS 36) Class 1 to Class CSA Z REQUIREMENTS CSA Z Clause 10.7 Change of Class Location describes the requirements for class location changes Where class locations change, the pipeline system in such locations shall be subject to the following requirements for the new class location: a) design factor or location factor, as applicable; b) valve spacing;j c) depth of cover and clearance; d) pressure testing; and e) evaluation and repair of imperfections as specified in Clause and Clause Conformance or non-conformance to the requirements of the new class location shall be documented, as applicable Where the affected portion of the pipeline does not conform to the requirements of the new class location, as described in Clause , either the non-conformance(s) shall be corrected in accordance with the requirements of Clause 4 or an engineering assessment (see Clause 10.1) shall be carried out to determine the suitability for continued service at the new class location designation in consideration of the: a) design, construction, and testing procedures followed in the original construction, compared with the applicable requirements of this Standard; b) condition of the pipeline system as determined by field inspections, examinations of operating and maintenance records, or other appropriate means; and c) type, proximity, and extent of the development that has increased the class location, giving consideration to concentrations of people, such as those associated with schools, hospitals, small subdivisions, and recreation areas built near existing pipelines. Page 4 of 15

5 Note: Annex O provides guidance on reliability-based design and assessment that can be a useful approach for an engineering assessment. Figure 1: Class Location Change Sites in Lines 400-1, and near Ile Des Chènes, Manitoba Page 5 of 15

6 Where the engineering assessment (see Clause ) indicates that the section of the pipeline system is satisfactory for the changed class location, no change to the pipeline system shall be required Where the engineering assessment (see Clause ) indicates that the portion of the pipeline system is not satisfactory for the changed class location, corrective actions shall be taken so that the affected portion of the pipeline system is suitable for continued service at the new class location designation Pipeline systems that can be subject to changes in class location, unless previously designed, tested, operated, and maintained for a Class 4 location, shall be inspected annually by the operating company to determine whether any change in class location has occurred. Records of such inspections and of any corrective action taken shall be retained. Note: CSA PLUS 663 provides guidance related to land use planning near to or surrounding existing pipeline. 2.0 EVALUATION OF CONFORMANCE TO THE NEW CLASS LOCATION REQUIREMENTS The following aspects on the class location change sites were reviewed to determine if the pipeline segments at the class location change sites are in conformance with the applicable requirements for the new class location in CSA Z Clause a) design factor or location factor b) valve spacing c) depth of cover d) pressure testing e) evaluation and repair of imperfections Identified non-conformances and corresponding corrective actions are detailed below. 2.1 DESIGN FACTOR OR LOCATION FACTOR According to the Clause of CSA Z662-15, the design pressure for a given design wall thickness or the design wall thickness for a given design pressure shall be determined by the following equation: St P = 2 F L J T (1) D where P design pressure, MPa S specified minimum yield strength, MPa t design wall thickness, mm D outside diameter of pipe, mm F design factor as per the Clause of CSA Z Page 6 of 15

7 L location factor as per the Clause of CSA Z J joint factor as per the Clause of CSA Z T temperature factor as per the Clause of CSA Z Therefore, the value of location factor corresponding to the design of a pipeline segment can be calculated as follows: PD L = 2 St F J T (2) For each class location change site, the location factor was calculated based on Eq. (2), using F = 0.8, J = 1.0 (submerged arc welded pipe), T = 1.0 (maximum operating temperature less than 120 degree Celsius), and other pipe properties listed in Table 2. The comparison between the calculated location factor values and the maximum allowable location factor values as per CSA Z Clause Table 4.2 is summarized in Table 2. It should be noted that due to the class change, Line has been de-rated to a revised operating pressure of 5374 kpa for an indefinite period. At this de-rated pressure, the pipeline segments for Line meet the location factor requirements for the new classes as shown in the parentheses in Table 2. Table 2: Location Factor Review Summary Line Name Start chainage (m) End chainage (m) (road) (road) MOP (Reduced Operating Pressure) (kpa) 7030 OD (mm) WT (mm) Grade (MPa) New Location Class (5374) (5374) (5374) (5374) (5374) (5374) (5374) Design Location Factor Maximum Allowable Location Factor (0.625) (0.625) 1 (General) (0.622) 2 (Roads) (0.625) (0.625) (General) (0.521) (Roads) (0.750) 2 1 Reduced operating pressure is currently in place to restrict the operating pressure to location Class 3 requirements. Page 7 of 15

8 2.2 VALVE SPACING Due to the class location change, the requirements for valve spacing have also changed, according to Clause and Table 4.7 of CSA Z The current isolation valve spacing and the required valve spacing as per Table 4.7 of CSA Z are given in Table 3 for Line As shown in this table, the existing valve spacing does not meet the valve spacing requirement for the new class location. Therefore, a valve spacing EA was conducted. A valve spacing EA addressing both Line and Line was submitted to NEB on 16 July This valve spacing EA has been reformatted to include only Line 400-2, and it is provided in Appendix A of this report. Line Name Start Valve Table 3: Valve Section Details Start Chainage (m) End Valve End Chainage (m) Valve Section Length (km) Required Valve Spacing for Class 3 (km) Line MLV MLV DEPTH OF COVER AND CLEARANCE TransCanada performed a depth of cover survey for Line in The survey showed that the minimum depth of cover in general locations was higher than the required minimum depth of cover of 0.6 m. The minimum depth of cover in the road crossing was also found to be higher than the required minimum depth of cover of 1.2 m. Given that the depth of cover survey was last performed over 10 years ago, it is recommended that a new survey be completed by March 31, 2016 for the class change site on Line to ensure that the depth of cover is still adequate and meets the requirements outlined in Table 4.9 of CSA Z According to the as-built alignment drawing, the clearance of Line from other underground structures and utilities are higher than the minimum required clearance of 300 mm, as specified in Table 4.9 of CSA Z Furthermore, TransCanada requires on-site supervision of all third party crossings, thus ensuring that this requirement is met for all third party crossings which ensures underground structures and utilities installed subsequently. 2.4 PRESSURE TESTING Table 4 shows the comparison between the minimum test pressure required by Table 8.1 of CSA Z and the minimum hydrostatic test pressure applied to the test section, which includes the class change site. Under the reduced operating pressure, the class change site meets the minimum hydrostatic test requirements for Class 3. The comparison shows that the minimum test pressure for the class change site meets the requirement for a Class 3 Location. Page 8 of 15

9 Line New Class Table 4: Hydrostatic Pressure Test Summary MOP (Reduced Operating Pressure) (kpa) Minimum Test Pressure (kpa) Minimum Test Pressure (% MOP) Required Minimum Test Pressure (%MOP) Class (5374) (1.64) EVALUATION AND REPAIR OF IMPERFECTIONS According to the Clause e) of CSA Z662-15, the identified imperfections in the class location change sites are required to be evaluated and repaired, as necessary, according to the requirement specified in Clause and Clause of CSA Z According to these clauses, the class location change affects the safety factor for metal-loss corrosion anomalies. As such, the metal-loss corrosion hazard has been evaluated for the identified class location change sites. TransCanada manages corrosion imperfections identified by in-line inspection (ILI) using the ILI Corrosion program, which employs both a deterministic criteria, provided in CSA Z Clause 10.10, and a reliability based criteria as provided in TransCanada s TEP-INT-ILI-CDN Analysis of MFL In-Line Inspection for CDN Pipelines (CDN) procedure. Line was last inspected with Rosen AFD and CDG (MFL) tools on 24 June The metal-loss corrosion features identified in the class location change site for Line were evaluated using the location factor corresponding to the new class location, and the features were found to be acceptable as per Clause of CSA Z Furthermore, CP is continuously and effectively managed on the Line in accordance with TransCanada s CP criteria specifications, which adhere to CSA Z Clause 9.9, and Canadian Gas Association (CGA) recommended practice OCC The annual test lead CP survey data from 2005 to 2015 were reviewed as an indication of the CP maintenance history for the affected segments of Line The data showed no persistent sub-criteria pipe-toelectrolyte potentials, which is indicative of a CP system that is performing well and therefore minimizing the corrosion hazard in the class change site. No dents or gouges were found in the 2013 Caliper ILI for the class location change site on Line Reduced operating pressure is currently in place to restrict the operating pressure to location Class 3 requirements. Page 9 of 15

10 3.0 RECOMMENDATIONS The review of class location change sites in accordance with CSA Z Clause a) through e) has determined that the location factor, depth of cover and clearance, and pressure testing for the class location change sites in Line meet the requirement of the new class location. However as the depth of cover survey was done some time ago, a new survey is proactively recommended. The metal-loss corrosion features identified in the class location change site for Line were evaluated using the location factor corresponding to the new class location, and there are currently no known unrepaired metal-loss anomalies that require mitigation for the new class location under the reduced operating pressure. The existing valve spacing for the class location change sites does not meet the default valve spacing requirement for the new class location. Therefore, a valve spacing EA was conducted. The following actions are recommended by the class change assessment and the valve spacing EA: 1. By March 31, 2016, complete depth of cover survey for the class change site on Line to confirm that the depth of cover is still adequate and that the requirements outlined in Table 4.9 of CSA Z are met. 2. The inspection frequency of MLV and MLV isolation valves was increased in 2015 to semi-annual (every 6 months), including the associated tie-over valves. This increase in inspection frequency resulted in an increased assurance in the reliability of isolation valves and appropriate valve closure times. 3. The valve spacing will be maintained at km. 4.0 REFERENCES CSA Z Oil and Gas Pipeline Systems. Rexdale, Ontario. Eiber, R. et al (2000), Valve Spacing Basis for Gas Transmission Pipelines, Pipeline Research Council International, Report no. L51817 TransCanada. Gas Control Overpressure Procedure. Internal document. TransCanada. TransCanada Engineering Procedure: Analysis of MFL In-Line Inspection for CDN Pipelines. Internal Document TransCanada. TransCanada Engineering Procedure: External Corrosion Threat Management Program. Internal Document TransCanada. TED-MECH-VS-GAS Gas Valve Spacing Directive (CDN US MEX). Internal document. TransCanada. TER-RISK-CON Thermal Radiation Consequence Models for Natural Gas Pipelines (CDN US MEX. Internal document. TransCanada. TOP Pipeline Operations (Gas Handling) (CDN US MEX). Internal document. TransCanada TransCanada Operating Procedure: Pipeline Restriction Procedure. Internal document Page 10 of 15

11 APPENDIX A Valve Spacing Engineering Assessment Page 11 of 15

12 A.1 Valve Spacing Engineering Assessment The valve spacing engineering assessment for valves MLV 401 and MLV 402 on Line was carried out in accordance with CSA Z Clause 4.4.4, which states that in order to determine the proper valve spacing, the following factors are to be considered: a. The nature and amount of fluid released due to a blowdown or a failure b. The time to blowdown the isolated section c. The effects on the inhabitants of the area from gas release d. Continuity of service e. Operating and maintenance flexibility f. Future development within the valve spacing section g. Significant conditions that could adversely affect the operation and security of the pipeline In addition to these Operations and Maintenance considerations, it is also necessary to consider the effect of increased valve spacing on public safety. This effect is evaluated primarily by determining the Individual Risk (IR) and Societal Risk (SR). IR is the annual probability of a fatality to an individual located on top of the pipeline. It is a baseline risk assessment performed for every pipeline. On the other hand, SR is the annual risk to a group of structures, or a settlement, due to its proximity to the pipeline. Combined, IR and SR will capture the acceptability of risk from a safety perspective for both sparsely and densely populated areas. Both of these risk measures are then compared to the industry accepted risk criteria to determine the acceptability of risk. For more background on IR and SR, as well as the IR and SR criteria, please refer to TER-RISK-CON. In the following sections, the above-mentioned considerations were addressed for the section of pipeline on Line between valves MLV 401 and MLV 402. A.2 Operation and Maintenance Considerations a) The nature and amount of fluid released due to a blowdown or a failure The service fluid in the pipelines is sweet natural gas. If a blowdown is required for planned maintenance activities, a transfer compressor will be utilized to draw the valve section down to 1000kPa. The remaining gas would then be vented to the atmosphere. At this pressure, the volume of gas vented for the two compared valve spacings would be: o km valve spacing: 165 x 10 3 m 3 o km valve spacing: 88 x 10 3 m 3 In the event of an emergency blowdown, the volume of the gas released from the line would be dependent on the pressure in the line. At 90% of the MOP, the volume the gas vented for the two compared valve spacings, assuming that the isolation valves have closed, would be: o km valve spacing: 1076 x 10 3 m 3 o km valve spacing: 573 x 10 3 m 3 Page 12 of 15

13 b) The time to blowdown the isolated section For both the actual valve spacing of approximately km and the required Class 3 valve spacing of 13 km, the blowdown times would be less than eight hours. It should be noted that this applies to both blowdowns with and without silencers. The implication of the blowdown time being less than eight hours is that the blowdown could be performed during normal daylight working hours, which would prevent undue disturbance to residents during non-working night time hours. Time to blow down an isolated section is also associated with emergency response, which is discussed in Section A3. c) The effects on the inhabitants of the area from gas release A silencer would be installed (if planned maintenance is to occur) on MLV 401 vent piping at Compressor Station 41 (near Ile Des Chènes), due to the proximity of the structures to the station. The closest residence from MLV 402 is approximately 500 meters away. Local landowners and relevant government agencies will be advised at least 48 hours prior to the planned blowdown operation according to the TransCanada Pipeline Operations Gas Handling TOP. These installations will be implemented in order to minimize effects to inhabitants in the area of the blowdown gas release. d) Continuity of service In the case of either planned or unplanned maintenance activities, the continuity of service would not be affected due to the redundancy of the design. All of these pipelines have a tie-over to a parallel pipeline, so the service would not be interrupted by taking any of the lines temporarily out of service for maintenance activities. In addition, the sales meter stations in this valve section are supplied from multiple lines, therefore adding redundancy if one of the lines is temporarily taken out of service. e) Operating and maintenance flexibility Current system design allows sales meter stations to be fed from both Lines and 400-2, which offers operating and maintenance flexibility. In addition, tie-over valves are present at each isolation valve location on Line and Line 400-2; therefore, allowing for isolation of a single valve section without affecting the delivery of gas and continuity of service. f) Future development within the valve spacing section It is not anticipated that any section of the pipe in this valve section will undergo a further class location upgrade in the foreseeable future, as there is no anticipated multi-floor building construction in this area. Thus, it is not anticipated that further development in the area will have additional impacts on the class location designation of this valve section. g) Significant conditions that could adversely affect the operation and security of the pipeline Conditions that may affect pipeline operation are addressed above in sections (d) and (e) above. In addition, if MLV 401 and MLV 402 on Line and the associated tie-over valves fail to operate properly, that could adversely affect the operation of the pipeline for this valve section. It is thus recommended to increase the valve maintenance/inspection from an annual to a semiannual (every 6 months) frequency to reduce the probability of isolation valves MLV 401 and MLV 402 on Line and the associated crossover valves failing to operate properly. Page 13 of 15

14 A.3 Effect on the Public Safety The effects of changing the valve spacing on public safety are minimal if the valve spacing is more than 10 km, as shown in Pipeline Research Council International (PRCI) report entitled Valve Spacing Basis for Gas Transmission Pipelines. This is because the greatest consequence of a pipeline rupture occurs within the first 30 seconds after the failure and the subsequent ignition. This initial stage following the failure will be independent of the valve spacing, therefore making the effects on the population independent of valve spacing. The following three arguments are proposed by Valve Spacing Basis for Gas Transmission Pipelines report as to why the impact of valve spacing is minimal on the population: 1. The primary consequence of a natural gas pipeline failure is related to the effects of thermal radiation exposure of the fire ball following ignition. The hazard zone is largest immediately following ignition. Reduction of valve spacing does not diminish the size of the hazard zone immediately following ignition. 2. The jet fire that follows the initial release phase after ignition has a smaller hazard zone. This jet fire could hinder emergency personnel from entering the site so it is important to reduce the duration of a fire. A key factor in reducing jet fire duration is cutting off fuel supply by quickly closing proximate valves. Automatic shutoff valves (ASVs) close more quickly than remotely controlled valves and manual valves. MLV 401 and MLV 402 on Line are both ASVs. 3. According to the PRCI study: as the valve closure time increases beyond 7.5 minutes (10 minutes is the practical minimum valve closure time), the risk level is independent of valve spacing and thus valve spacing does not affect the risk to the public. Changing the valve spacing, therefore, will not affect the risk in this case. This has been reinforced by first determining the individual risk for both the current valve spacing of km and the Class 3 compliant valve spacing of 13 km. This comparison demonstrated that there is no appreciable difference if the individual risk resulted from decreasing the valve spacing. Furthermore, the Individual Risk is acceptable and below the IR tolerance limit for both cases and for both of these pipelines. In addition to Individual Risk, the Societal Risk was also evaluated for the Class 3 segments with both the actual valve spacing of km and the Class 3 compliant valve spacing of 13 km. The evaluation demonstrated that there is no appreciable difference if the societal risk resulted from decreasing the valve spacing. Furthermore, the Societal Risk is acceptable and below the SR tolerance limit for both valve spacing cases and for both pipelines. A.4 Conclusion An isolation valve spacing EA was performed for sections of pipeline between isolation valves MLV 401 and MLV 402 on Line due to a change in class location. In accordance with Clause of CSA Z662-15, an EA has been conducted to demonstrate that the current valve spacing of approximately km is safe for the surrounding population and will not adversely affect the operation and maintenance activities on these pipelines. This EA demonstrated that: Page 14 of 15

15 There is no increased risk to the population due to the current valve spacing compared to the Clause compliant valve spacing. Both individual and societal risk changes were insignificant due to reduction of isolation valve spacing. There is no adverse impact to operation and maintenance activities on the pipelines with regard to the higher valve spacing. A.5 Recommendations TransCanada has determined the appropriate approach to maintain safety for the valve sections. The following actions will be implemented for the sites to achieve satisfactory levels of safety and reliability: 1. The inspection frequency of MLV and MLV isolation valves was increased in 2015 to semi-annual (every 6 months), including the associated tie-over valves. This increase in inspection frequency resulted in an increased assurance in the reliability of isolation valves and appropriate valve closure times. 2. The valve spacing will be maintained at km. Page 15 of 15

Pipeline Integrity Valve Spacing Engineering Assessment (CDN) Grande Prairie Mainline Loop 2 (Progress Section) NPS 36

Pipeline Integrity Valve Spacing Engineering Assessment (CDN) Grande Prairie Mainline Loop 2 (Progress Section) NPS 36 APPROVALS Library: EDMS General Page 1 of 10 TABLE OF CONTENTS APPROVALS 1 1. PURPOSE... 3 2. BACKGROUND... 3 3. VALVE SPACING ASSESSMENT APPROACH... 6 4. OPERATIONS AND MAINTENANCE CONSIDERATIONS... 6

More information

BSR GPTC Z TR GM References and Reporting Page 1 of 8

BSR GPTC Z TR GM References and Reporting Page 1 of 8 Page 1 of 8 PRIMARY: 192.605 SECONDARY: 191.23 PURPOSE: Review guide material added by TR 2009-17 to 5.1(e) and consider restructuring the guide material under 192.605 as discussed further below. ORIGIN/RATIONALE

More information

Application of pipeline risk assessment to proposed developments in the vicinity of high pressure Natural Gas pipelines

Application of pipeline risk assessment to proposed developments in the vicinity of high pressure Natural Gas pipelines Communication 1737 Application of pipeline risk assessment to proposed developments in the vicinity of high pressure Natural Gas pipelines Founded 1863 Royal Charter 1929 Patron: Her Majesty the Queen

More information

Enbridge Pipelines Inc. PIPELINE INTEGRITY AXIAL CRACK THREAT ASSESSMENT

Enbridge Pipelines Inc. PIPELINE INTEGRITY AXIAL CRACK THREAT ASSESSMENT Enbridge Pipelines Inc. Line 9B Reversal and Line 9 Capacity Expansion Project Appendix A to Updated Pipeline Engineering Assessment PIPELINE INTEGRITY AXIAL CRACK THREAT ASSESSMENT Table of Contents 1.

More information

Standard Pneumatic Test Procedure Requirements for Piping Systems

Standard Pneumatic Test Procedure Requirements for Piping Systems the pressure equipment safety authority Standard Pneumatic Test Procedure Requirements for Piping Systems AB-522 Edition 2, Rev. 1 Issued 2016-10-24 Table of Contents FOREWORD... 1 1.0 INTRODUCTION...

More information

NATURAL GAS MAINTENANCE. Part 192 Subpart "M"

NATURAL GAS MAINTENANCE. Part 192 Subpart M NATURAL GAS MAINTENANCE Part 192 Subpart "M" CONTACT INFORMATION Pamela West Pipeline Safety Specialist U.S. Department of Transportation PHMSA Inspector Training and Qualifications Main: (405) 686-2310

More information

IGEM/TD/2 Edition 2 with amendments July 2015 Communication 1779 Assessing the risks from high pressure Natural Gas pipelines

IGEM/TD/2 Edition 2 with amendments July 2015 Communication 1779 Assessing the risks from high pressure Natural Gas pipelines Communication 1779 Assessing the risks from high pressure Natural Gas pipelines Founded 1863 Royal Charter 1929 Patron: Her Majesty the Queen Communication 1779 Assessing the risks from high pressure Natural

More information

Regulated Oil and Gas Companies under National Energy Board Jurisdiction

Regulated Oil and Gas Companies under National Energy Board Jurisdiction File 185-A000-41 8 August 2003 Regulated Oil and Gas Companies under National Energy Board Jurisdiction Dear Sir / Madam: Guidance Notes for Pressure Equipment under National Energy Board Jurisdiction

More information

PROPOSED CHANGE TO THE 2015 ONTARIO FIRE CODE (O. Reg. 213/07, as amended current to January 1, 2015)

PROPOSED CHANGE TO THE 2015 ONTARIO FIRE CODE (O. Reg. 213/07, as amended current to January 1, 2015) PROPOSED CHANGE TO THE 2015 ONTARIO FIRE CODE (O. Reg. 213/07, as amended current to January 1, 2015) CHANGE NUMBER: N/A CODE REFERENCE: Division B, Subsection 6.4.3. DESCRIPTION OF PROPOSED CHANGE: Subsection

More information

Guide for Evaluating Your Hose Assembly Supplier

Guide for Evaluating Your Hose Assembly Supplier Guide for Evaluating Your Hose Assembly Supplier Supplier Evaluation Checklist, and How to Clearly Define Application Requirements Safe, reliable hose assemblies require appropriate specification work

More information

PROCEDURES FOR REPAIRS TO ASME NV STAMPED PRESSURE RELIEF DEVICES OF NUCLEAR SAFETY RELATED PRESSURE RELIEF VALVES

PROCEDURES FOR REPAIRS TO ASME NV STAMPED PRESSURE RELIEF DEVICES OF NUCLEAR SAFETY RELATED PRESSURE RELIEF VALVES NB16 0603 NR Task Group 1 9 16 1. One update by NR task group page 3: 7/17/19 2. Two updates to S6.1 and S6.3 on page 1: 7/19/17 SUPPLEMENT 6 PROCEDURES FOR REPAIRS TO ASME NV STAMPED PRESSURE RELIEF DEVICES

More information

UNPIGGABLE NO MORE! PRACTICAL SOLUTIONS FOR CHALLENGING PIPELINES

UNPIGGABLE NO MORE! PRACTICAL SOLUTIONS FOR CHALLENGING PIPELINES UNPIGGABLE NO MORE! PRACTICAL SOLUTIONS FOR CHALLENGING PIPELINES Markus Ginten, Thomas Beuker, Tom Steinvoorte PPSA Seminar Aberdeen, 20 th November 2013 CONTENT 1. Evolutional Process 2. Managing Complexity

More information

ERCBH2S Frequently Asked Questions.

ERCBH2S Frequently Asked Questions. ERCBHS Frequently Asked Questions. Issue: Sweet pipeline tie-in to a sour gathering system A company is tying a sweet pipeline into one containing HS. Since the model assumes flow from either end of the

More information

IGEM/TD/1. Background, Development, Changes J V Haswell

IGEM/TD/1. Background, Development, Changes J V Haswell IGEM/TD/1 Background, Development, Changes J V Haswell TD/1 Background Development, Changes Technical and Safety Philosophy History of Development Key Code Requirements:- Rou?ng, BPDs Design parameters

More information

PIPELINE SAFETY. Darin Burk, Manager Pipeline Safety. January 28, 2014

PIPELINE SAFETY. Darin Burk, Manager Pipeline Safety. January 28, 2014 PIPELINE SAFETY Darin Burk, Manager Pipeline Safety January 28, 2014 Congressional Delegation of Authority Pipeline Safety Act of 1968 Congress Delegated Inspection and Enforcement Authority to the Secretary

More information

Kiefner & Associates, Inc.

Kiefner & Associates, Inc. Kiefner & Associates, Inc. KAPA FAQs What does KAPA stand for? KAPA is an acronym for Kiefner & Associates Pipe Assessment. What does KAPA do? KAPA calculates an estimated failure pressure of a pipe affected

More information

New Hampshire Public Utilities Commission CFR 49 Part 192 Regulations. MINIMUM Pipeline Safety Regulations

New Hampshire Public Utilities Commission CFR 49 Part 192 Regulations. MINIMUM Pipeline Safety Regulations New Hampshire Public Utilities Commission CFR 49 Part 192 Regulations MINIMUM Pipeline Safety Regulations Application for Jurisdictional LPG Operators 1 Pipeline Safety Regulations 49 CFR Part 192 (NOTE:

More information

Date of Issue: July 2016 Affected Publication: API Specification 16C, Choke and Kill Equipment, Second Edition, March 2015 ADDENDUM 1

Date of Issue: July 2016 Affected Publication: API Specification 16C, Choke and Kill Equipment, Second Edition, March 2015 ADDENDUM 1 Date of Issue: July 2016 Affected Publication: API Specification 16C, Choke and Kill Equipment, Second Edition, March 2015 ADDENDUM 1 Page 16, Section 4.6, delete the entire section and renumber all subsequent

More information

ACCREDITATION OF ON-LINE LEAK SEAL ORGANIZATIONS

ACCREDITATION OF ON-LINE LEAK SEAL ORGANIZATIONS ACCREDITATION OF ON-LINE LEAK SEAL ORGANIZATIONS TSSA GUIDE FOR SURVEY TEAMS The Technical Standards and Safety Authority Boilers and Pressure Vessels Safety Division 3300 Bloor Street West 14th Floor,

More information

Becker* Products Below Ground Ball Valve Regulators

Becker* Products Below Ground Ball Valve Regulators GE Oil & Gas Becker* Products Below Ground Ball Valve Regulators Reduce Noise Levels at Large Volume Regulator Stations GE s Becker* Below Ground ball valve regulator has the long-term proven reliability,

More information

INSPECTION OF MULTI-DIAMETER PIPELINES OPERATING AT LOW PRESSURE. Stefan Vages > ROSEN Group

INSPECTION OF MULTI-DIAMETER PIPELINES OPERATING AT LOW PRESSURE. Stefan Vages > ROSEN Group INSPECTION OF MULTI-DIAMETER PIPELINES OPERATING AT LOW PRESSURE Stefan Vages > ROSEN Group PIPELINE TECHNOLOGY JOURNAL 7 ABSTRACT Particularly in the 1940s and 1950s, gas pipeline systems were not necessarily

More information

Safety. April 2018 Supersedes all previous publications 2018 Chevron Phillips Chemical Company LP

Safety. April 2018 Supersedes all previous publications 2018 Chevron Phillips Chemical Company LP Technical Note 802 Leak Testing of Polyethylene Pipe For Municipal and Industrial Applications Part 1 Pre-Test Considerations Leak testing may be used to find leaks in a newly constructed or newly modified

More information

Pressure Equipment Directive PED 2014/68/EU Commission's Working Group "Pressure"

Pressure Equipment Directive PED 2014/68/EU Commission's Working Group Pressure H. INTERPRETATION OF OTHER ESSENTIAL SAFETY REQUIREMENTS Guideline H-02 Guideline related to: Annex I Section 3.2.2 and 7.4 Final assessment (Annex I Section 3.2.2) of pressure equipment must include a

More information

UKOPA Dent Management Strategy

UKOPA Dent Management Strategy UKOPA Dent Management Strategy 1 Background Pipelines are thin shell structures which are susceptible to geometric distortions and dents during handling, construction, and operation. These dents and distortions,

More information

Lockout Tagout Policy

Lockout Tagout Policy Office of Environmental Health & Safety www.moreheadstate.edu/ehs 606-783-2584 Lockout Tagout Policy PURPOSE To establish procedures for the de-energization and isolation of energy sources or the lockout

More information

O&M MANUAL HIGHLIGHTS

O&M MANUAL HIGHLIGHTS O&M MANUAL HIGHLIGHTS GENERAL PROVISIONS Each pipeline must be operated according to this SUBPART 192.603(a) RECORDS 192.603(b) Keep records necessary to administer the procedures of 192.605 RECORDS Life

More information

PIP PNE00012 Piping Examination and Leak Test Guide

PIP PNE00012 Piping Examination and Leak Test Guide October 2017 Piping PIP PNE00012 Piping Examination and Leak Test Guide PURPOSE AND USE OF PROCESS INDUSTRY PRACTICES In an effort to minimize the cost of process industry facilities, this Practice has

More information

HYDROSTATIC LEAK TEST PROCEDURE

HYDROSTATIC LEAK TEST PROCEDURE This information is proprietary and shall not be disclosed outside your organization, nor shall it be duplicated, used or disclosed for purposes other than as permitted under the agreement with Kinetics

More information

VI.D AIR DISCONNECT SWITCHES

VI.D AIR DISCONNECT SWITCHES VI.D AIR DISCONNECT SWITCHES DMS #568451 Page 1 of 20 Revised: 02/01/2011 GUIDE FOR DETERMINATION OF DISCONNECT SWITCH RATINGS PJM INTERCONNECTION Heritage MAAC Group A task force of the Transmission and

More information

Anomaly Evaluation, Response, and Repair Summit. Presentation by INGAA June 3, 2008

Anomaly Evaluation, Response, and Repair Summit. Presentation by INGAA June 3, 2008 Anomaly Evaluation, Response, and Repair Summit Presentation by INGAA June 3, 2008 Context of Today s Meeting Basis for Anomaly evaluation and response has become an issue on: Enforcement Integrity Management

More information

INTEGRITY MANAGEMENT OF STRESS CORROSION CRACKING IN GAS PIPELINE HIGH CONSEQUENCE AREAS

INTEGRITY MANAGEMENT OF STRESS CORROSION CRACKING IN GAS PIPELINE HIGH CONSEQUENCE AREAS Designator: Meta Bold 24/26 Revision Note: Meta Black 14/16 INTEGRITY MANAGEMENT OF STRESS CORROSION CRACKING IN GAS PIPELINE HIGH CONSEQUENCE AREAS Date of Issuance: October 31, 2008 This report was prepared

More information

TRAFFIC IMPACT STUDY CRITERIA

TRAFFIC IMPACT STUDY CRITERIA Chapter 6 - TRAFFIC IMPACT STUDY CRITERIA 6.1 GENERAL PROVISIONS 6.1.1. Purpose: The purpose of this document is to outline a standard format for preparing a traffic impact study in the City of Steamboat

More information

FUNDAMENTALS OF PRESSURE RELIEF VALVES IN NATURAL GAS INSTALLATION - OPERATION - MAINTENANCE. Gary S. Beckett

FUNDAMENTALS OF PRESSURE RELIEF VALVES IN NATURAL GAS INSTALLATION - OPERATION - MAINTENANCE. Gary S. Beckett FUNDAMENTALS OF PRESSURE RELIEF VALVES IN NATURAL GAS INSTALLATION - OPERATION - MAINTENANCE Gary S. Beckett Flow Safe Supply 10727 Tower Oaks Boulevard Houston, Texas 77070 What Are They and Why Are They

More information

ASSE International Product (Seal) Listing Program

ASSE International Product (Seal) Listing Program ASSE International Product (Seal) Listing Program ASSE 1070-2015 / ASME A112.1070-2015 / CSA B125.70-15 Performance Requirements for Water Temperature Limiting Devices Manufacturer: Contact Person: E-mail:

More information

John Gurden, J P Kenny Ltd Onshore Pipeline and the Landfall Valve Installation (LVI) Design. Knowledge of the Corrib Onshore Pipeline Project

John Gurden, J P Kenny Ltd Onshore Pipeline and the Landfall Valve Installation (LVI) Design. Knowledge of the Corrib Onshore Pipeline Project STATEMENT OF EVIDENCE ABP Ref. No: PL16.GA0004 John Gurden, J P Kenny Ltd Onshore Pipeline and the Landfall Valve Installation (LVI) Design Qualifications and Experience 1. My name is John Gurden and I

More information

INSTALLATION INSTRUCTIONS FOR SSI WIDEBAND DIFFUSER

INSTALLATION INSTRUCTIONS FOR SSI WIDEBAND DIFFUSER INSTALLATION INSTRUCTIONS FOR SSI WIDEBAND DIFFUSER Comment Sheet: 1. Installation, Operation and Maintenance Manual contains detailed information on the SSI-Cap Diffuser unit. This manual covers start-up,

More information

EASTERN ENERGY SERVICES PTE LTD. 60 Kaki Bukit Place #02-19 Eunos Tech Park Singapore, SG Singapore Telephone: Fax:

EASTERN ENERGY SERVICES PTE LTD. 60 Kaki Bukit Place #02-19 Eunos Tech Park Singapore, SG Singapore Telephone: Fax: 2 Table Of Contents 1. Introduction 3 2. About this Manual 3 3. Contacting YZ Systems 3 4. Vessel Components 4 5. Specifications 5 6. Application 6 7. Theory of Operation 7 8. DuraSite Installation & Use

More information

IAPMO GUIDE CRITERIA FOR BALL VALVES IAPMO IGC PURPOSE

IAPMO GUIDE CRITERIA FOR BALL VALVES IAPMO IGC PURPOSE INTERNATIONAL ASSOCIATION OF PLUMBING AND MECHANICAL OFFICIALS IAPMO GUIDE CRITERIA FOR BALL VALVES IAPMO IGC 157-20067 1 PURPOSE 1.1 The purpose of this standard is to establish an acceptable standard

More information

Energy Control. Suite 2A, 55 Frid Street Hamilton, ON L8P 4M3 office: cell:

Energy Control. Suite 2A, 55 Frid Street Hamilton, ON L8P 4M3 office: cell: Energy Control Suite 2A, 55 Frid Street Hamilton, ON L8P 4M3 office: 905.577.0303 cell: 905.977.0210 consultant@staffaid.ca www.staffaid.com Safety, Energy Control, Power Lockout & Function Test Procedures

More information

CEPA Initiative: Response Time Guideline 2015 EMERGENCY SECURITY MANAGEMENT WORK GROUP

CEPA Initiative: Response Time Guideline 2015 EMERGENCY SECURITY MANAGEMENT WORK GROUP CEPA Initiative: Response Time Guideline 2015 EMERGENCY SECURITY MANAGEMENT WORK GROUP Response Time Guideline aboutpipelines.com 1 of 8 Contents Table of Contents 1.0 Background 3 Purpose 3 Scope 3 Definitions

More information

Purpose. Scope. Process flow OPERATING PROCEDURE 07: HAZARD LOG MANAGEMENT

Purpose. Scope. Process flow OPERATING PROCEDURE 07: HAZARD LOG MANAGEMENT SYDNEY TRAINS SAFETY MANAGEMENT SYSTEM OPERATING PROCEDURE 07: HAZARD LOG MANAGEMENT Purpose Scope Process flow This operating procedure supports SMS-07-SP-3067 Manage Safety Change and establishes the

More information

Overview Assessment of the 16 Inch Diameter Olympic Pipeline Integrity

Overview Assessment of the 16 Inch Diameter Olympic Pipeline Integrity Report on Overview Assessment of the 16 Inch Diameter Olympic Pipeline Integrity to City-County Pipeline Safety Consortium of Washington November, 2001 by Bob Eiber Robert J. Eiber, Consultant Inc. 4062

More information

NORMAL OPERATING PROCEDURES Operating Parameter Information

NORMAL OPERATING PROCEDURES Operating Parameter Information Operating Parameter Information Each operator performing the normal operating procedures (routine checks) of the facility should be familiar with the current normal operating parameters of all systems

More information

Wedge Type Flow Meter Installation and Operation Manual

Wedge Type Flow Meter Installation and Operation Manual Wedge Type Flow Meter Installation and Operation Manual 358-EN Please read and save these instructions. Wedge Type Flow Meter PLEASE READ THIS FIRST! The purpose of this document is to provide guidance

More information

TN-20/2007. Special Precautions for Fusing Saddle Fittings to Live PE Fuel Gas Mains Pressurized on the Basis of a 0.

TN-20/2007. Special Precautions for Fusing Saddle Fittings to Live PE Fuel Gas Mains Pressurized on the Basis of a 0. TN-20/2007 Special Precautions for Fusing Saddle Fittings to Live PE Fuel Gas Mains Pressurized on the Basis of a 0.40 Design Factor Special Precautions for Fusing Saddle Fittings to Live PE Fuel Gas Mains

More information

Committee Input No. 59-NFPA [ Section No. 5.9 ]

Committee Input No. 59-NFPA [ Section No. 5.9 ] Committee Input No. 59-NFPA 54-2012 [ Section No. 5.9 ] 5.9 Overpressure Protection Devices. 5.9.1 General 1 Where required. Overpressure Where the serving gas supplier delivers gas at a pressure greater

More information

Best Practice RBI Technology Process by SVT-PP SIMTECH

Best Practice RBI Technology Process by SVT-PP SIMTECH Best Practice RBI Technology Process by SVT-PP SIMTECH We define the best practice in RBI as a proactive technology process which is used to formally and reliably optimise the inspection efforts for each

More information

Pressures MAOP MOP OP

Pressures MAOP MOP OP MAOP Pressures MAOP MOP OP MAOP "Maximum Allowable Operating Pressure" means the maximum pressure at which a pipeline or segment of a pipeline may be operated under this part. 192.3 MOP "Maximum Actual

More information

ANNEX AMENDMENTS TO THE INTERNATIONAL CODE FOR FIRE SAFETY SYSTEMS (FSS CODE) CHAPTER 15 INERT GAS SYSTEMS

ANNEX AMENDMENTS TO THE INTERNATIONAL CODE FOR FIRE SAFETY SYSTEMS (FSS CODE) CHAPTER 15 INERT GAS SYSTEMS Annex 3, page 2 ANNEX AMENDMENTS TO THE INTERNATIONAL CODE FOR FIRE SAFETY SYSTEMS (FSS CODE) CHAPTER 15 INERT GAS SYSTEMS The text of existing chapter 15 is replaced by the following: "1 Application This

More information

An Urgent Bulletin from CSA Group

An Urgent Bulletin from CSA Group An Urgent Bulletin from CSA Group Gas Products No. 335 (Supersedes Notice Gas Products No. 270, Ref No: N12-055) Effective Date: October 1, 2015 Date: July 21, 2014 Apply Before February 2, 2015 Announcing:

More information

UTAS EH&S INSTRUCTION No. 036 June 2012 Revision No. 3. Purging of Flammable Gas Equipment and/or Piping (Explosion Hazard)

UTAS EH&S INSTRUCTION No. 036 June 2012 Revision No. 3. Purging of Flammable Gas Equipment and/or Piping (Explosion Hazard) Purging of Flammable Gas Equipment and/or Piping (Explosion Hazard) APPLICABILITY: This EH&S Instruction applies to UTAS sites worldwide, including contractors working at UTAS facilities. The document

More information

Ontario ENGINEERING STANDARD SPECIFICATION 1.0 PURPOSE

Ontario ENGINEERING STANDARD SPECIFICATION 1.0 PURPOSE SPEC-5044 1/6 1.0 PURPOSE This specification describes the minimum requirements for the cleaning, handling and packaging of oxygen service piping and components. This applies to new installations, repairs,

More information

TITAN FLOW CONTROL, INC.

TITAN FLOW CONTROL, INC. PREFACE: This manual contains information concerning the installation, operation, and maintenance of Titan Flow Control (Titan FCI) Simplex Basket Strainers. To ensure efficient and safe operation of Titan

More information

GAS SAFETY Information Bulletin

GAS SAFETY Information Bulletin GAS SAFETY Information Bulletin June 2016 G-03-11-ABSA [Rev2] Page 1 of 7 Fuel Gas Pressure Piping in Plants This bulletin has been jointly developed by Safety Services, the Pressure Equipment Sub- Council,

More information

Identification and Screening of Scenarios for LOPA. Ken First Dow Chemical Company Midland, MI

Identification and Screening of Scenarios for LOPA. Ken First Dow Chemical Company Midland, MI Identification and Screening of Scenarios for LOPA Ken First Dow Chemical Company Midland, MI 1 Layers of Protection Analysis (LOPA) LOPA is a semi-quantitative tool for analyzing and assessing risk. The

More information

T e l N o : F a x N o : E m a i l : a i s h c m c - m e. c o m w w w. c m c - m e.

T e l N o : F a x N o : E m a i l : a i s h c m c - m e. c o m w w w. c m c - m e. MU047: Practical Valve Technology: Selection, Installation, Upgrading, Inspection & Troubleshooting MU047 Rev.002 CMCT COURSE OUTLINE Page 1 of 7 Training Description: This five-day intensive course covers

More information

RECOMMENDED GOOD PRACTICE

RECOMMENDED GOOD PRACTICE RECOMMENDED GOOD PRACTICE EMERGENCY SHUTDOWN PROCEDURE (ESP) AND PROCEDURE FOR TESTING ESP SYSTEM FOR BLACK LIQUOR RECOVERY BOILERS THE BLACK LIQUOR RECOVERY BOILER ADVISORY COMMITTEE October 2009 Table

More information

Requirements for Reduced Supervision of Power Plants, Thermal Liquid Heating Systems, and Heating Plants

Requirements for Reduced Supervision of Power Plants, Thermal Liquid Heating Systems, and Heating Plants the pressure equipment safety authority Requirements for Reduced Supervision of Power Plants, Thermal Liquid Heating Systems, and Heating Plants AB-528 Edition 2, Revision 1 Issued 2016-09-12 Table of

More information

Lockout / Tag out Program

Lockout / Tag out Program Lockout / Tag out Program Presented by DOSHTI www.doshti.com You will learn Purpose of Lockout- Tag out Requirements for LOTO Types of Hazardous Energy Procedures for LOTO The OSHA Standard for the Control

More information

ASSESSMENT AND ANALYSIS OF PIPELINE BUCKLES

ASSESSMENT AND ANALYSIS OF PIPELINE BUCKLES ASSESSMENT AND ANALYSIS OF PIPELINE BUCKLES GE Oil & Gas PII Pipeline Solutions Inessa Yablonskikh Principal Consultant Aberdeen, November, 14 th 2007 Assessment And Analysis Of Pipeline Buckles Introduction

More information

SECTION PRESSURE TESTING OF PIPING

SECTION PRESSURE TESTING OF PIPING SECTION 15044 PRESSURE TESTING OF PIPING PART 1 - GENERAL 1.01 DESCRIPTION A. Scope of Work: This section specifies the leakage and pressure testing of piping. B. Testing Records: PART 2 - PRODUCTS 2.01

More information

PRESSURE RETEST. 49 CFR, (g) Co#: Vin#: DOT Spec: MAWP:

PRESSURE RETEST. 49 CFR, (g) Co#: Vin#: DOT Spec: MAWP: PRESSURE RETEST 49 CFR, 180.407(g) Co#: Vin#: Spec: MAWP: Retest Date: Location: *External Inspection Performed: *Internal Inspection Performed: Test Pressure: psig Held for: min. (Must be at least 10

More information

Charlottetown Marine Terminal Pipeline Decommissioning Project Description

Charlottetown Marine Terminal Pipeline Decommissioning Project Description Charlottetown Marine Terminal Pipeline Decommissioning Project Description 69 Marr Road Unit B Rothesay NB, E2E 3J9 Tel (506) 848-1920 Fax (506) 848-1929 Charlottetown Marine Terminal Pipeline Decommissioning

More information

Continental Industries TRANSITION FITTINGS or FAX Visit

Continental Industries TRANSITION FITTINGS or FAX Visit Continental Industries TRANSITION FITTINGS 1-800-558-1373 or FAX 1-800-788-1668 Visit www.conind.com ABOUT US Our Company Continental Industries, headquartered in Tulsa, Oklahoma, was formed in 1958 and

More information

Lockout/Tagout Training Overview. Safety Fest 2013

Lockout/Tagout Training Overview. Safety Fest 2013 Lockout/Tagout Training Overview Safety Fest 2013 Purpose of Lockout/Tagout The standard covers the servicing and maintenance of machine and equipment in which the unexpected energization or start up of

More information

Manual Actuated Boiler Blowdown Valves

Manual Actuated Boiler Blowdown Valves Manual Actuated Boiler Blowdown Valves Installation and Maintenance Instructions 1. Safety information 2. General product information 3. Installation 4. Operation 5. Maintenance 6. Spare parts p.1 1. Safety

More information

MAINTENANCE AND SAFETY OF CNG REFUELLING STATIONS

MAINTENANCE AND SAFETY OF CNG REFUELLING STATIONS ISSN 1172-3416 NZ GCP 2 : 1993 NEW ZEALAND GAS CODE OF PRACTICE for MAINTENANCE AND SAFETY OF CNG REFUELLING STATIONS Issued by the Secretary of Commerce in accordance with the Gas Act 1992 THE GAS ACT

More information

Pressure Regulators. Operating Instructions. Instrumentation

Pressure Regulators. Operating Instructions. Instrumentation Pressure Regulators Operating Instructions FAILURE OR IMPROPER SELECTION OR IMPROPER USE OF THIS PRODUCT CAN CAUSE DEATH, PERSONAL INJURY AND PROPERTY DAMAGE. This document and other information from the

More information

ASME and PED Requirements for Drum Level Instrumentation. Presented by: Amir Hedayatnia Clark-Reliance Corp.

ASME and PED Requirements for Drum Level Instrumentation. Presented by: Amir Hedayatnia Clark-Reliance Corp. ASME and PED Requirements for Drum Level Instrumentation 2017 Presented by: Amir Hedayatnia Clark-Reliance Corp. Topics Gage Glasses and Remote Reading Instruments ASME Code Section I Requirements for

More information

Residential and Small Commercial

Residential and Small Commercial Page 1 of 7 Companies Affected: NIPSCO CGV CMD CKY COH CMA CPA REFERENCE 49 CFR Part 192.353, 192.355, 192.357 1. GENERAL The purpose of this standard is to provide requirements for the inspection or installation

More information

5 HUMAN BEINGS ELECTRICAL AND MAGNETIC FIELDS

5 HUMAN BEINGS ELECTRICAL AND MAGNETIC FIELDS 5 HUMAN BEINGS ELECTRICAL AND MAGNETIC FIELDS 5.1 INTRODUCTION 1 This chapter of the (EIS) presents an evaluation of the proposed development as set out in Chapter 6, Volume 3B of the EIS, in relation

More information

Inspection Credit for PWSCC Mitigation via Peening Surface Stress Improvement

Inspection Credit for PWSCC Mitigation via Peening Surface Stress Improvement Inspection Credit for PWSCC Mitigation via Peening Surface Stress Improvement Glenn A. White, Kyle P. Schmitt, Kevin J. Fuhr, Markus Burkardt, and Jeffrey A. Gorman Dominion Engineering, Inc. Paul Crooker

More information

Irrigation System Winterization and Pressurization Procedures

Irrigation System Winterization and Pressurization Procedures Irrigation System Winterization and Pressurization Procedures Introduction Any time that an irrigation system is filled and pressurized, or when the system is drained and water flushed from the system,

More information

STANDARD SPECIFICATION FOR SPLIT TEES (HOT TAP MATERIAL)

STANDARD SPECIFICATION FOR SPLIT TEES (HOT TAP MATERIAL) STANDARD SPECIFICATION FOR SPLIT TEES (HOT TAP MATERIAL) TEE (HOT TAPPING MATERIAL) S-04-02-040 Page 1 of 7 1.0 SCOPE This specification covers the basic requirements for the design, manufacture and supply

More information

Responding to Natural Gas Pipeline Emergencies

Responding to Natural Gas Pipeline Emergencies Responding to Natural Gas Pipeline Emergencies Who is Florida Gas Transmission? Florida Gas Transmission operates nearly 5,000-miles of interstate natural gas transmission pipelines, a system that extends

More information

WHEATLEY Series 822/820 Swing Check Valve

WHEATLEY Series 822/820 Swing Check Valve Document Number: TC003001-12 Revision: 02 WHEATLEY Series 822/820 Swing Check Valve Installation, Operation, and Maintenance Manual TABLE OF CONTENTS BILL OF MATERIALS...3 SCOPE...4 INSTALLATION AND OPERATION

More information

Pressure Equipment Directive PED 2014/68/EU Commission's Working Group "Pressure"

Pressure Equipment Directive PED 2014/68/EU Commission's Working Group Pressure C. ASSEMBLIES Guideline C-03 Guideline related to: Article 4 paragraph 2 The effect of the derogation in Article 4 paragraph 2 from the introductory paragraph in the same article is not clear. In the circumstances,

More information

Annex 1 to Decision 2009/007/R

Annex 1 to Decision 2009/007/R Annex 1 to Decision 2009/007/R AMC to Part 145 A new AMC 145.A.45(e) is added: AMC 145.A.45(e) Maintenance data The maintenance organisation should transcribe accurately the maintenance data onto such

More information

WHEATLEY Series 500 Swing Check Valve

WHEATLEY Series 500 Swing Check Valve Document Number: TC003001-13 Revision: 02 WHEATLEY Series 500 Swing Check Valve Installation, Operation, and Maintenance Manual TABLE OF CONTENTS BILL OF MATERIALS...3 SCOPE...5 INSTALLATION AND OPERATION

More information

DUQUESNE UNIVERSITY LOCKOUT/TAGOUT PROGRAM

DUQUESNE UNIVERSITY LOCKOUT/TAGOUT PROGRAM DUQUESNE UNIVERSITY LOCKOUT/TAGOUT PROGRAM Prepared by: Environmental Health and Safety Department TABLE OF CONTENTS Page Purpose 1 Scope 1 Introduction 2 Regulatory Requirements 2 Protective Materials

More information

Reliability of Safety-Critical Systems Chapter 4. Testing and Maintenance

Reliability of Safety-Critical Systems Chapter 4. Testing and Maintenance Reliability of Safety-Critical Systems Chapter 4. Testing and Maintenance Mary Ann Lundteigen and Marvin Rausand mary.a.lundteigen@ntnu.no RAMS Group Department of Production and Quality Engineering NTNU

More information

49 CFR 195 Regulatory Overview

49 CFR 195 Regulatory Overview 49 CFR 195 Regulatory Overview Overview DOT PHMSA OPS Relates to public safety, governs materials, design, construction, operations and maintenance Applies to either transmission, distribution or jurisdictional

More information

APPENDIX B PHMSA 57 Special Conditions for Keystone XL and Keystone Compared to 49 CFR 195

APPENDIX B PHMSA 57 Special Conditions for Keystone XL and Keystone Compared to 49 CFR 195 APPENDIX B PHMSA 57 Special Conditions for Keystone XL and Keystone Compared to 49 CFR 195 -This page intentionally left blank- PHMSA 57 SPECIAL CONDITIONS FOR KEYSTONE XL COMPARED TO 49 CFR 195 1 Steel

More information

Gas Cabinets and Valve Manifold Boxes: Applying CGA G13- Rev 2015 to Gas Delivery Equipment

Gas Cabinets and Valve Manifold Boxes: Applying CGA G13- Rev 2015 to Gas Delivery Equipment Gas Cabinets and Valve Manifold Boxes: Applying CGA G13- Rev 2015 to Gas Delivery Equipment The Standard Governing the Storage & Use of Silane: Compressed Gas Association s Publication CGA G-13 2015: Storage

More information

SPR - Pneumatic Spool Valve

SPR - Pneumatic Spool Valve SIL SM.008 Rev 7 SPR - Pneumatic Spool Valve Compiled By : G. Elliott, Date: 31/08/17 Contents Terminology Definitions:... 3 Acronyms & Abbreviations:... 4 1.0 Introduction... 5 1.1 Purpose & Scope...

More information

Subpart E. Pressure Testing

Subpart E. Pressure Testing Subpart E Pressure Testing 195.300 Scope This subpart prescribes minimum requirements for pressure testing of steel pipelines. However, this subpart does not apply to movement of pipe covered by 195.424.

More information

High-Pressure Boiler Inspection Procedures: A Complete Checklist

High-Pressure Boiler Inspection Procedures: A Complete Checklist High-Pressure Boiler Inspection Procedures: A Complete Checklist Inspecting high-pressure boilers is a complex process requiring preparation, planning, and a multitude of safety precautions. Regular inspections

More information

Notice for Pressure Special Equipment Manufacture Licensing

Notice for Pressure Special Equipment Manufacture Licensing AQSIQ Notice No.151 (2012) Notice for Pressure Special Equipment Manufacture Licensing To further enhance the implementation of the manufacture licensing system to imported pressure special equipment,

More information

Every things under control High-Integrity Pressure Protection System (HIPPS)

Every things under control High-Integrity Pressure Protection System (HIPPS) Every things under control www.adico.co info@adico.co Table Of Contents 1. Introduction... 2 2. Standards... 3 3. HIPPS vs Emergency Shut Down... 4 4. Safety Requirement Specification... 4 5. Device Integrity

More information

QUANTIFYING THE TOLERABILITY OF POTENTIAL IGNITION SOURCES FROM UNCERTIFIED MECHANICAL EQUIPMENT INSTALLED IN HAZARDOUS AREAS

QUANTIFYING THE TOLERABILITY OF POTENTIAL IGNITION SOURCES FROM UNCERTIFIED MECHANICAL EQUIPMENT INSTALLED IN HAZARDOUS AREAS QUANTIFYING THE TOLERABILITY OF POTENTIAL IGNITION SOURCES FROM UNCERTIFIED MECHANICAL EQUIPMENT INSTALLED IN HAZARDOUS AREAS Steve Sherwen Senior Consultant, ABB Engineering Services, Daresbury Park,

More information

GUIDELINES. Systems. Pressure. Guidelines Acceptance of equipment, establishment of safe operating limits and fitness for service

GUIDELINES. Systems. Pressure. Guidelines Acceptance of equipment, establishment of safe operating limits and fitness for service GUIDELINES Pressure Systems Guidelines Acceptance of equipment, establishment of safe operating limits and fitness for service Document Reference: PSG 16 Issue 04 Dated 13/09/16 The Safety Assessment Federation

More information

INSTALLATION & OPERATION MANUAL FOR Teppan-Yaki Griddles

INSTALLATION & OPERATION MANUAL FOR Teppan-Yaki Griddles INSTALLATION & OPERATION MANUAL FOR Teppan-Yaki Griddles MODELS MLS TYG48C ML-769368-Z1 TYG60C ML-766505-Z www.wolfrange.com TYG48C ITW Food Equipment Group, LLC An Illinois Tool Works Company 3600 North

More information

HOT OILING OPERATIONS ALL HSE PRC 172. Approved By: Manager, HSE Performance Assurance. Table of Contents

HOT OILING OPERATIONS ALL HSE PRC 172. Approved By: Manager, HSE Performance Assurance. Table of Contents Owner: HSE Performance Assurance ALL HSE PRC 172 Approved By: Manager, HSE Performance Assurance Retention Code: CG01 CA Revised: March 2015 Review Frequency: Five years or less Table of Contents 1.0 Purpose...

More information

SAFETY PLAN REVIEW ITM

SAFETY PLAN REVIEW ITM ITM Power (#4) Hydrogen Fueling Station Safety Plan Review Submission for the California Energy Commission General Funding Opportunity GFO-15-605 Background At the request of the California Energy Commission,

More information

Aquashield to Mitigate Water Ingress of Gas Pipes

Aquashield to Mitigate Water Ingress of Gas Pipes IGEM Young Persons Paper Competition 2017 Aquashield to Mitigate Water Ingress of Gas Pipes Assistant Engineer Technical Development Section, Distribution Operation Department The Hong Kong and China Gas

More information

Valve Replacement: Using Non-Intrusive Isolation Technology to Minimize Production Downtime

Valve Replacement: Using Non-Intrusive Isolation Technology to Minimize Production Downtime CASE STUDY CS15-02 >> Valve Replacement: Using Non-Intrusive Isolation Technology to Minimize Production Downtime What s Inside:» Explore Double Block & Monitor» Increase Operational Safety» Achieve Double

More information

PROCEDURE. April 20, TOP dated 11/1/88

PROCEDURE. April 20, TOP dated 11/1/88 Subject: Effective Date: page 1 of 2 Initiated by: Failure Modes and Effects Analysis April 20, 1999 Supersedes: TOP 22.019 dated 11/1/88 Head, Engineering and Technical Infrastructure Approved: Director

More information

Risk Analysis using Corrosion Rate Parameter on Gas Transmission Pipeline

Risk Analysis using Corrosion Rate Parameter on Gas Transmission Pipeline IOP Conference Series: Materials Science and Engineering PAPER OPEN ACCESS Risk Analysis using Corrosion Rate Parameter on Gas Transmission Pipeline To cite this article: B Sasikirono et al 2017 IOP Conf.

More information

Monitoring or Inspection

Monitoring or Inspection Comparison of Corrosion Monitoring Systems Monitoring or Inspection Date: September 2016 There is often some confusion between the words monitoring and inspection when used in reference to measuring metal

More information

American Society of Sanitary Engineering PRODUCT (SEAL) LISTING PROGRAM

American Society of Sanitary Engineering PRODUCT (SEAL) LISTING PROGRAM American Society of Sanitary Engineering PRODUCT (SEAL) LISTING PROGRAM ASSE STANDARD #1048 - REVISED: 2009 Double Check Detector Fire Protection Backflow Prevention Assemblies Separate, complete laboratory

More information