EP WELLS DAILY OPERATIONS REPORT Report 19 05/26/2016

Size: px
Start display at page:

Download "EP WELLS DAILY OPERATIONS REPORT Report 19 05/26/2016"

Transcription

1 Report 19 5/26/216 Company Type WBS No/API No PERMIAN Exploration / Event Summary Event Type Drilling only Event Start Date 4/24/216 Days on Location Objective Drill - Wolfcamp Shale Beta Original Spud Date 4/28/216 Days Since Spud 14.1 Est. Days 32. Contractor PRECISION Work Unit PRECISION 565 Days To Release Rig Phone/FAX No. Status Supervisor BRYAN BOYLES Measured Depth 11,857. Engineer YERMEK TYNYSHBAYEV TVD 11, Other Supervisor JUSTIN HENSON 24 Hr Progress Depth Ref/Grd Elev/Water Depth DFE: 2,858.8 / 2,83.3 Hole size 8.75 THF Datum Rig Operating Rate. Last Casing MD 9.625in@5,6.ft Rig Zero Rate. Next Casing MD 7.in@12,1.ft Rig Reduced Rate. Current Fluid Density(ppg) 9.5 Rig Repair Rate. LOT/FIT EMW(ppg) Auxiliary/Secondary Work. Lithology NX Auxiliary Floor Not Available. Formation Actual cost to date/afe 1,737,579/2,964,96. Formation top MD Actual divided by AFE.59 Daily NPT(hr/%) / Daily Cost 456,855 Days Ahd(-) Bhnd(+)(5/5) Last Incident HSE Summary Date Days Last Incident Date Days KPI's LWC RWC MTC FAC Last casing pressure test PSI NII HPI GOAL ZERO DAYS PS BARRIER EVENT PS barrier bowtie review 8/24/ TRCF LWCF Safety Cards - Safe Safety Card - Unsafe SSE% Last casing pressure(psi) 2 Safety Comments: GOAL ZERO 286 DAYS NO LTI 286 DAYS LAST HIPO 33 DAYS LAST RAM 286 DAYS LAST SPILL 286 DAYS HSE Drills Drills/Tests Date Days Since Last Last Derrick Inspection Last BOP function test Last BOP Test Next BOP Test 5/26/216 5/26/216 6/16/216 JSA's/Toolbox Talks Days Since Last Drill Hour Summary Operations Summary Ran 7" casing to 11841', induced flow, cemented 7" casing, pressure tested BOP Update Since Report Time Finish cleaning mud tanks, M/U BHA #6, TIH to 1624' 24 Hour Forecast Finish R/U backyard, TIH, Displace, drill out shoe track, drill lateral 5/27/216 6:33:16 Report Version: R1 Generated from data in EDM/Opens/PROFILE 1

2 Report 19 5/26/216 Time Summary Start Hours PH OPN WS OPN Drilled Depth NPT level Rig Rate Description : 5. C9 CLR 11,857. Run 7" casing F/ ' Run, 7 " 29 lb/ft P-11 CY T-Blue casing F/ ' Run, 7 " 29 lb/ft P-11 CY LTC casing F/ ' Land at ft with 28.41' landing joint below DF Float collar ' Shoe ' 5: 2. C9 RUD 11,857. R/U casing crew, test hanger seal integrity 7: 1: 12:3 13: 15: 16: 17: 22: 22:3 23: 3. C9 RUD 11,857. PJSM, R/U cement tools, Induce flow: Fill backside w/14 bbl fresh water, bullhead 14 bbl freshwater backside, bullhead 5 bbl active mud drillstring. 2.5 C9 CLC 11,857. Pump 3 bbls type of gel spacer mixed at 8.34 ppg pumped at 5 bpm. Shut down and test lines to 323 psi. Lead Slurry: Pump 232 barrels of 11.8 ppg cement pumped at 5 bpm. Pumped slurry consisting of 51 sacks ( yield) ( 4 % excess) of type of econocem + Additives:.25 lbm D-Air 5 Pre-Mix Dry, 1% Bentonite Pre-Mix Dry, 8 lbm Salt Pre-Mix Dry,.5% SA-115 Pre-Mix Dry Tail Cement: Pump 53 barrels of 14.5 ppg cement pumped at 5 bpm. Pumped tail slurry consisting of 24 sacks ( 1.23 yield) ( 2 % excess) 5/5 Poz Premium Additives:.3% CFR-3 Pre-Mix Dry,.25% SA-115 Pre-Mix dry,.5% LAP-1 Pre-Mix Dry,.5% LAP-1 Pre-Mix Dry,.5 lbm D-Air 5, Pre-Mix Dry. Shut down and dropped top plug. Displacement Fluid: Start displacing with 427 barrels of 9.5 ppg at 8 bpm, Received no cement back to surface, bumped plug w/ 5 psi over and held for 5 minutes. Floats held, 2.5 bbls back after bleeding pressure and checking floats..5 C9 PRE 11,857. Pressure test casing 27 psi 3 min. After bleeding off, casing pressure increased to 124 psi. Casing valves closed while cement sets up. 2. C9 RUD 11,857. R/D cement tools, L/D landing joint w/running tool, washout above hanger 1. C9 PRE 11,857. Install bit guide bushing, test void 5k/1min, testseals 1k/1min 1. C9 RUD 11,857. Install combo running & testing tool 5. C9 BPT 11,857. R/U Frontier BOP testers and BOP test according to Shell testing procedures. Test all components to 25 psi low for 5 minutes and 1, psi high for 5 minutes, with exception to: Pumps and standpipe manifold- 25 low for 5 minutes, 7,5 psi high for 5 minutes Annular- 25 psi low and 3,5 psi high for 5 minutes.5 C9 RUD 11,857. Pull combo running & testing tool. R/D Frontier BOP testers..5 C9 BPT 11,857. Perform Koomey test 1. C9 RUD 11,857. Cont. cleaning mud tanks, L/D test joint, install stabbing guides on top drive, bleed off 6 bbl pressure from 19 psi to 48 psi. Pressure built back up 183 psi. Total 24. MD Inc. Azi. TVD N/S Deepest 5 Surveys E/W V.Sec DLeg ( /1ft) 11, , EPW MWD 11, , EPW MWD 11, , EPW MWD+SCC 11, , EPW MWD+SCC 11, , EPW MWD Tool 5/27/216 6:33:16 Report Version: R1 Generated from data in EDM/Opens/PROFILE 2

3 Report 19 5/26/216 Fluid Details Mud type NaCl Brine Oil/Water (%)./92.3 ph/pm (cc) 8.5/.25 MD 11,857. TS/HGS/LGS (%) 1.1// Pf/Mf (cc).1/.2 Mud Density (ppg) 9.5 Sand (%).1 Ca+ (ppm) Vis (s/qt) 28. Cl- (ppm) 115, PV/YP (cp/lbf/1ft²) 1./3. MBT (lbm/bbl) Gels 1 s/m (lbf/1ft²) 1./1. LCM (lbm/bbl) API/HTHP WL (cc/3min) 1./ ECD (ppg) 9.5 R6/3 FC/HTHP FC (32nd") 1./ H2S (gas unit) R2/1 KCl (%) R6/3 FL temp. ( F) FUEL ON HAND 915 GALLONS FUEL USED 43 GALLONS FUEL RECIEVED GALLONS Ditch Magnet in Last 24hrs/Cum. (gm) Remarks 5/27/216 6:33:16 Report Version: R1 Generated from data in EDM/Opens/PROFILE 3

4 Report 2 5/27/216 Company Type WBS No/API No PERMIAN Exploration / Event Summary Event Type Drilling only Event Start Date 4/24/216 Days on Location Objective Drill - Wolfcamp Shale Beta Original Spud Date 4/28/216 Days Since Spud 15.1 Est. Days 32. Contractor PRECISION Work Unit PRECISION 565 Days To Release Rig Phone/FAX No. Status Supervisor BRYAN BOYLES Measured Depth 12,59. Engineer YERMEK TYNYSHBAYEV TVD 11, Other Supervisor JUSTIN HENSON 24 Hr Progress 22. Depth Ref/Grd Elev/Water Depth DFE: 2,858.8 / 2,83.3 Hole size THF Datum Rig Operating Rate. Last Casing MD 7.in@11,841.ft Rig Zero Rate. Next Casing MD 4.5in@18,.ft Rig Reduced Rate. Current Fluid Density(ppg) 13.8 Rig Repair Rate. LOT/FIT EMW(ppg) Auxiliary/Secondary Work. Lithology NX Auxiliary Floor Not Available. Formation Actual cost to date/afe 1,833,94/2,964,96. Formation top MD Actual divided by AFE.62 Daily NPT(hr/%) / Daily Cost 99,296 Days Ahd(-) Bhnd(+)(5/5) Last Incident HSE Summary Date Days Last Incident Date Days KPI's LWC RWC MTC FAC Last casing pressure test PSI NII HPI GOAL ZERO DAYS PS BARRIER EVENT PS barrier bowtie review 8/24/ TRCF LWCF Safety Cards - Safe Safety Card - Unsafe SSE% Last casing pressure(psi) 2 Safety Comments: GOAL ZERO 287 DAYS NO LTI 287 DAYS LAST HIPO 34 DAYS LAST RAM 287 DAYS LAST SPILL 287 DAYS Drill Category Drill Type Detection (sec) Drills Complete (sec) Crew drilled Pass / Fail PIC Comments Control Crew On-Bottom 12. Day Pass Bryan Boyles Drills/Tests Date Days Since Last HSE Drills Last Derrick Inspection Last BOP function test Last BOP Test Next BOP Test 5/26/216 5/26/216 6/16/ JSA's/Toolbox Talks Days Since Last Drill /28/216 6:7:29 Report Version: R1 Generated from data in EDM/Opens/PROFILE 1

5 Report 2 5/27/ Hour Summary Operations Summary Finished R/U backyard, brought over SBM, TIH, displace hole to SBM while drilling out shoe track, built curve F/11857' ' Update Since Report Time Drilling Hour Forecast Drill production section 5/28/216 6:7:29 Report Version: R1 Generated from data in EDM/Opens/PROFILE 2

6 Report 2 5/27/216 Time Summary Start Hours PH OPN WS OPN Drilled Depth NPT level Rig Rate Description : 1.5 C9 RUD 11,875. Cont. cleaning mud tanks, suction pots under mud pumps, pull valve manifold off trip tank, R/D transfer lines on mud tanks for WBM 1:3 1.5 D6 DRT 11,875. M/U BHA #6 3: 4: 7: 7:3 1:3 11: 12: 12:3 14: 14:3 15:3 16: 18: 19: 21: 1. D6 DRT 11,875. TIH to 1624' 3. D6 RUD 11,875. Spot cuttings bin for closed loop, R/U transfer lines for SBM and base fluid, inspect tanks, transfer SBM to mud tanks, fill slug pit with fresh water.5 D6 DRT 11,875. Pressure drop across 1.4 agitator = 24 psi with fresh water 3. D6 DRT 11,875. TIH to 1482' filling pipe with fresh water.5 D6 RUD 11,875. Install rotating head w/dual rubber 1. D6 DRT 11,875. TIH to 11656'.5 D6 DRT 11,875. Start displacing to SBM while washing through cement stringers F/11656' ' 1.5 D6 DCM 11,875. Tag float collar at 11784' drill out to 11839', work through, observed hard cement, finish SBM displacement.5 D6 DCM 11,875. Drill through shoe 11839' ', work through same, wash/ream down to new formation 11857' 1. D6 DRR 11,88. ROTARY DRILLING F/11,857 T/11,88, (23 23 FPH) WOB: 15 K RPM: SURFACE 25 MOTOR 192 BIT 217 PSI & FLOW: SPP 455 GPM 3 TORQUE: ON BOTTOM 7.5 K OFF BOTTOM 4 K STRING WEIGHT: UP 2K DOWN 145K ROTATING 165K MW: 13.7 PPG MOTOR REVS/GAL:.64 Gas: Gas: BG 17, CG N/A Flare: N/A.5 D6 MNR 11,88. Service rig, grease C-frame track, recalibrate hook load 2. D6 DRM 11,925. SLIDING F/11,88 T/11,925, (45 22 FPH) WOB: 25K RPM: SURFACE MOTOR 192 BIT 192 PSI & FLOW: SPP 588 GPM 3 DIFF 35 STRING WEIGHT: UP 2K DOWN 145K MW: 13.5 PPG MOTOR REVS/GAL:.64 Gas: BG 125, CG N/A Flare: N/A 1. D6 DRM 11,933. SLIDING F/11,925 T/11,933, (8 8 FPH) WOB: 2K RPM: SURFACE MOTOR 17 BIT 17 PSI & FLOW: SPP 47 GPM 265 DIFF 2 STRING WEIGHT: UP 2K DOWN 145K MW: 13.5 PPG MOTOR REVS/GAL:.64 Gas: BG 12, CG N/A Flare: N/A **Drilling on 1 mud pump, tighten up liners** 2. D6 DRM 11,97. SLIDING F/11,933 T/11,97, (37 19 FPH) WOB: 1K RPM: SURFACE MOTOR 192 BIT 192 PSI & FLOW: SPP 59 GPM 3 DIFF 3 STRING WEIGHT: UP 2K DOWN 145K MW: 13.4 PPG MOTOR REVS/GAL:.64 Gas: BG 13, CG N/A Flare: N/A 3. D6 DRM 12,59. SLIDING F/11,97 T/12,59, (89 3 FPH) WOB: 2K RPM: SURFACE MOTOR 17 BIT 17 PSI & FLOW: SPP 48 GPM 265 DIFF 42 5/28/216 6:7:29 Report Version: R1 Generated from data in EDM/Opens/PROFILE 3

7 Report 2 5/27/216 Start Hours PH OPN WS OPN Total 24. Drilled Depth NPT level Rig Rate Time Summary Description STRING WEIGHT: UP 25K DOWN 15K MW: 13.4 PPG MOTOR REVS/GAL:.64 Gas: BG 14, CG N/A Flare: N/A **Drilling on 1 mud pump,c/o liner gasket. Kept gpm lower for better TF control** Deepest 5 Surveys MD Inc. Azi. TVD N/S E/W V.Sec DLeg ( /1ft) 11, , EPW MWD 11, , EPW MWD 11, , EPW MWD+SCC 11, , EPW MWD 11, , EPW MWD Fluid Details Mud type Oil Base (GTL) Oil/Water (%) 56./16. POM (cc) MD 11,857. TS/HGS/LGS (%) 26.// CaCl2 (%) Mud Density (ppg) 13.8 Sand (%). Caom/Clom (ppm) Vis (s/qt) 87. Oil/Water Ratio (%) 77.8/22.2 ACT PV/YP (cp/lbf/1ft²) 25./9. XS Lime(lbm/bbl).78 Gels 1 s/m (lbf/1ft²) 7./12. LCM (lbm/bbl) ES (Volts) 615. API/HTHP WL (cc/3min)./ ECD (ppg) R6/3 FC/HTHP FC (32nd")./8. H2S (gas unit) R2/1 WPS (ppm) 277,131 KCl (%) R6/3 FL temp. ( F) Ditch Magnet in Last 24hrs/Cum. (gm) Bit Details Bit no. Size Manufacturer Model no. Class IADC Serial Size MD in MD out IADC Dull Grade code no. (32nd") HALLIBURTON MM64D x16 11, Tool MD 11,88. 11, , ,97. 12,59. WOB Min/Max Current RPM (rpm) Flow rate (gpm) SPP (psi) P bit (psi) Bit Operations Bit HHP (hp) Hours ROP (ft/hr) Hours cum cum. 15./ , / , / , / , / , ROP cum. (ft/hr) Item description 4" DRILL PIPE 5" NOV AGITATOR W/ 1.4 PLATE 5" DRILL PIPE XT-39 x 3 1/2 IF CROSSOVER FLOAT SUB FILTER SUB # Jts Length Drillstring Components OD Max OD ID Connection Name Weight (ppf) Grade Serial no , XTM-39 RIG XTM-39 W , XTM-39 RIG XTM-39 DR /2 IF NESFS /2 IF DR2581 5/28/216 6:7:29 Report Version: R1 Generated from data in EDM/Opens/PROFILE 4

8 Report 2 5/27/216 Item description SLICK NON-MAG DRILL COLLAR SLICK NON-MAG DRILL COLLAR UBHO ORIENTING SUB CLAW 5" MUD MOTOR FBH 1.75 BIT #5 RUN # " SECURITY MM64D # Jts Length Drillstring Components OD Max OD ID Connection Name Weight (ppf) Grade Serial no /2 IF NESMS /2 IF NESMS /2 IF NESMS /2 IF C /2 REG Drillstring Details Date/Time in Date/Time out BHA no. BHA Length Min. ID Purpose 5/27/216 3: DRILL 6.125" PRODUCTION SECTION MD 11,88. SW Up 2. SW Down 145. SW Rotn 165. Drag 35. Tq On Btm (ft-lbf) 7,5. Tq Off Btm (ft-lbf) 4, , , ,97. 12, FUEL ON HAND 154 GALLONS FUEL USED 1114 GALLONS FUEL RECIEVED 7499 GALLONS Remarks 5/28/216 6:7:29 Report Version: R1 Generated from data in EDM/Opens/PROFILE 5

9 Report 21 5/28/216 Company Type WBS No/API No PERMIAN Exploration / Event Summary Event Type Drilling only Event Start Date 4/24/216 Days on Location 2.67 Objective Drill - Wolfcamp Shale Beta Original Spud Date 4/28/216 Days Since Spud 16.1 Est. Days 32. Contractor PRECISION Work Unit PRECISION 565 Days To Release Rig Phone/FAX No. Status Supervisor BRYAN BOYLES Measured Depth 13,146. Engineer YERMEK TYNYSHBAYEV TVD 11,96.6 Other Supervisor JUSTIN HENSON 24 Hr Progress 1,87. Depth Ref/Grd Elev/Water Depth DFE: 2,858.8 / 2,83.3 Hole size THF Datum Rig Operating Rate. Last Casing MD 7.in@11,841.ft Rig Zero Rate. Next Casing MD 4.5in@18,.ft Rig Reduced Rate. Current Fluid Density(ppg) 13.4 Rig Repair Rate. LOT/FIT EMW(ppg) Auxiliary/Secondary Work. Lithology NX Auxiliary Floor Not Available. Formation Actual cost to date/afe 1,943,886/2,964,96. Formation top MD Actual divided by AFE.66 Daily NPT(hr/%) / Daily Cost 78,11 Days Ahd(-) Bhnd(+)(5/5) Last Incident HSE Summary Date Days Last Incident Date Days KPI's LWC RWC MTC FAC Last casing pressure test PSI NII HPI GOAL ZERO DAYS PS BARRIER EVENT PS barrier bowtie review 8/24/ TRCF LWCF Safety Cards - Safe Safety Card - Unsafe SSE% Last casing pressure(psi) 6 4 Safety Comments: GOAL ZERO 288 DAYS NO LTI 288 DAYS LAST HIPO 35 DAYS LAST RAM 288 DAYS LAST SPILL 288 DAYS Weekend awareness Memorial Day reviewed fit for duty policy. Discussed common causes of accidents: hand/finger placement, work around 5 of rotary table, SSE s, slip/trips/falls. Discussed communication in the workplace and barriers related to effective communication, how to develop a transparent culture. Held short safety meetings every 2 hours on the rig floor to conduct step back 5x5 sessions. Held PAUSE to review primary well control: indicators, causes, methods of control, pressure relationships, gas in solution, mud SAG, barriers, and safe working pressure. Drill Category Drill Type Detection (sec) Drills Complete (sec) Crew drilled Pass / Fail PIC Comments Control Crew On-Bottom Night Pass JUSTIN HENSON Reviewed primary well 5/29/216 11:21:44 Report Version: R1 Generated from data in EDM/Opens/PROFILE 1

10 Report 21 5/28/216 HSE Drills Drills/Tests Date Days Since Last Last Derrick Inspection Last BOP function test Last BOP Test Next BOP Test 5/26/216 5/26/216 6/16/ JSA's/Toolbox Talks Days Since Last Drill Hour Summary Drill F/1259' ' Update Since Report Time Drilling ahead 13413' 24 Hour Forecast Continue drilling lateral to TD Operations Summary 5/29/216 11:21:44 Report Version: R1 Generated from data in EDM/Opens/PROFILE 2

11 Report 21 5/28/216 Time Summary Start Hours PH OPN WS OPN Drilled Depth NPT level Rig Rate Description : 1. D6 DRM 12,11. SLIDING F/12,59 T/12,11, (51 51 FPH) WOB: 15K RPM: SURFACE MOTOR 17 BIT 17 PSI & FLOW: SPP 49 GPM 265 DIFF 475 STRING WEIGHT: UP 25K DOWN 145K MW: 13.4 PPG MOTOR REVS/GAL:.64 Gas: BG 14, CG N/A Flare: N/A 1: 1. D6 DRR 12,149. ROTARY DRILLING F/12,11 T/12,149, (39 39 FPH) WOB: 18 K RPM: SURFACE 4 MOTOR 17 BIT 21 PSI & FLOW: SPP 5 GPM 265 TORQUE: ON BOTTOM 7.5 K OFF BOTTOM 5 K STRING WEIGHT: UP 25K DOWN 145K ROTATING 165K MW: 13.4 PPG MOTOR REVS/GAL:.64 Gas: BG 14, CG N/A Flare: N/A 2: 2. D6 DRM 12,199. SLIDING F/12,149 T/12,199, (5 25 FPH) WOB: 25K RPM: SURFACE MOTOR 17 BIT 17 PSI & FLOW: SPP 5 GPM 265 DIFF 45 STRING WEIGHT: UP 25K DOWN 145K MW: 13.4 PPG MOTOR REVS/GAL:.64 Gas: BG 115, CG N/A Flare: N/A 4: 1. D6 DRR 12,239. ROTARY DRILLING F/12,199 T/12,239, (4 4 FPH) WOB: 25 K RPM: SURFACE 4 MOTOR 192 BIT 21 PSI & FLOW: SPP 6 GPM 3 TORQUE: ON BOTTOM 8 K OFF BOTTOM 5 K STRING WEIGHT: UP 21K DOWN 14K ROTATING 165K MW: 13.4 PPG MOTOR REVS/GAL:.64 Gas: BG 11, CG 66 Flare: N/A 5:.5 D6 MNR 12,239. Service rig, inspect all clamps on stand pipe 5:3 7: 11:3 1.5 D6 DRR 12,329. ROTARY DRILLING F/12,239 T/12,329, (9 6 FPH) WOB: 25 K RPM: SURFACE 4 MOTOR 192 BIT 21 PSI & FLOW: SPP 6 GPM 3 TORQUE: ON BOTTOM 8 K OFF BOTTOM 4 K STRING WEIGHT: UP 21K DOWN 14K ROTATING 165K MW: 13.4 PPG MOTOR REVS/GAL:.64 Gas: BG 18, CG 122 Flare: N/A 4.5 D6 DRM 12,418. SLIDING F/12,329 T/12,418, (89 2 FPH) WOB: 25K RPM: SURFACE MOTOR 17 BIT 17 PSI & FLOW: SPP 5 GPM 265 DIFF 4 STRING WEIGHT: UP 21K DOWN 135K MW: 13.4 PPG MOTOR REVS/GAL:.64 Gas: BG 1, CG 79 Flare: N/A 2. D6 DRR 12,564. ROTARY DRILLING F/12,418 T/12,564, ( FPH) WOB: 25 K RPM: SURFACE 65 MOTOR 192 BIT 257 PSI & FLOW: SPP 59 GPM 3 TORQUE: ON BOTTOM 9 K OFF BOTTOM 5 K STRING WEIGHT: UP 21K DOWN 135K ROTATING 165K MW: 13.4 PPG 5/29/216 11:21:44 Report Version: R1 Generated from data in EDM/Opens/PROFILE 3

12 Report 21 5/28/216 Start Hours PH OPN WS OPN 13:3 14:3 16: Drilled Depth NPT level Rig Rate Time Summary Description MOTOR REVS/GAL:.64 Gas: BG 88, CG 283 Flare: N/A 1. D6 DRM 12,585. SLIDING F/12,564 T/12,585, (21 21 FPH) WOB: 15K RPM: SURFACE MOTOR 166 BIT 166 PSI & FLOW: SPP 47 GPM 26 DIFF 35 STRING WEIGHT: UP 25K DOWN 135K MW: 13.4 PPG MOTOR REVS/GAL:.64 Gas: BG 5, CG 283 Flare: N/A 1.5 D6 DRR 12,687. ROTARY DRILLING F/12,585 T/12,687, ( FPH) WOB: 25 K RPM: SURFACE 65 MOTOR 192 BIT 257 PSI & FLOW: SPP 59 GPM 3 TORQUE: ON BOTTOM 9 K OFF BOTTOM 5 K STRING WEIGHT: UP 215K DOWN 125K ROTATING 17K MW: 13.4 PPG MOTOR REVS/GAL:.64 Gas: BG 6, CG 223 Flare: N/A.5 D6 MNR 12,687. Service rig, DROPS inspection zone #1, grease RLA 16:3 22: 23: 5.5 D6 DRR 13,6. ROTARY DRILLING F/12,687 T/13,6, ( FPH) WOB: 25 K RPM: SURFACE 65 MOTOR 192 BIT 257 PSI & FLOW: SPP 6 GPM 3 TORQUE: ON BOTTOM 1 K OFF BOTTOM 7 K STRING WEIGHT: UP 215K DOWN 125K ROTATING 17K MW: 13.4 PPG MOTOR REVS/GAL:.64 Gas: BG 6, CG 223 Flare: N/A 1. D6 DRM 13,8. SLIDING F/13,6 T/13,8, (2 2 FPH) WOB: 28K RPM: SURFACE MOTOR 192 BIT 192 PSI & FLOW: SPP 47 GPM 3 DIFF 3 STRING WEIGHT: UP 215K DOWN 125K MW: 13.4 PPG MOTOR REVS/GAL:.64 Gas: BG 7, CG 29 Flare: N/A 1. D6 DRR 13,146. ROTARY DRILLING F/13,8 T/13,146, (66 66 FPH) WOB: 25 K RPM: SURFACE 65 MOTOR 192 BIT 257 PSI & FLOW: SPP 6 GPM 3 TORQUE: ON BOTTOM 1 K OFF BOTTOM 7 K STRING WEIGHT: UP 215K DOWN 125K ROTATING 17K MW: 13.4 PPG MOTOR REVS/GAL:.64 Gas: BG 7, CG 32 Flare: N/A Total 24. MD Inc. Azi. TVD N/S Deepest 5 Surveys E/W V.Sec DLeg ( /1ft) 12, , EPW MWD 12, , EPW MWD 12, , , EPW MWD 12, , , , EPW MWD 5/29/216 11:21:44 Report Version: R1 Generated from data in EDM/Opens/PROFILE 4 Tool

13 Report 21 5/28/216 Deepest 5 Surveys MD Inc. Azi. TVD N/S E/W V.Sec DLeg Tool ( /1ft) 13, ,98.9 1, , EPW MWD Fluid Details Mud type Oil Base (GTL) Oil/Water (%) 57./16. POM (cc) MD 12,4. TS/HGS/LGS (%) 25.// CaCl2 (%) Mud Density (ppg) 13.4 Sand (%). Caom/Clom (ppm) Vis (s/qt) 74. Oil/Water Ratio (%) 78.1/21.9 ACT PV/YP (cp/lbf/1ft²) 25./9. XS Lime(lbm/bbl) 3.24 Gels 1 s/m (lbf/1ft²) 9./12. LCM (lbm/bbl) ES (Volts) 65. API/HTHP WL (cc/3min)./ ECD (ppg) R6/3 FC/HTHP FC (32nd")./8. H2S (gas unit) R2/1 WPS (ppm) 284,841 KCl (%) R6/3 FL temp. ( F) Ditch Magnet in Last 24hrs/Cum. (gm) Bit Details Bit no. Size Manufacturer Model no. Class IADC Serial Size MD in MD out IADC Dull Grade code no. (32nd") HALLIBURTON MM64D x16 11, MD 12,11. 12, , , , , , , , ,6. 13,8. 13,146. WOB Min/Max Current RPM (rpm) Flow rate (gpm) SPP (psi) P bit (psi) Bit Operations Bit HHP (hp) Hours ROP (ft/hr) Hours cum cum. 15./ , / , / , / , / , / , / , / , / , / , , / , , / , , ROP cum. (ft/hr) Item description 4" DRILL PIPE 5" NOV AGITATOR W/ 1.4 PLATE 5" DRILL PIPE XT-39 x 3 1/2 IF CROSSOVER FLOAT SUB FILTER SUB SLICK NON-MAG DRILL COLLAR SLICK NON-MAG DRILL COLLAR UBHO ORIENTING SUB CLAW 5" MUD MOTOR FBH 1.75 BIT #5 RUN # " SECURITY MM64D # Jts Length Drillstring Components OD Max OD ID Connection Name Weight (ppf) Grade Serial no , XTM RIG XTM-39 W , XTM-39 RIG XTM-39 DR /2 IF NESFS /2 IF DR NESMS NESMS NESMS /2 IF C /2 REG /29/216 11:21:44 Report Version: R1 Generated from data in EDM/Opens/PROFILE 5

14 Report 21 5/28/216 Drillstring Details Date/Time in Date/Time out BHA no. BHA Length Min. ID Purpose 5/27/216 3: DRILL 6.125" PRODUCTION SECTION MD 12,11. SW Up 25. SW Down 145. SW Rotn. Drag 25. Tq On Btm (ft-lbf). Tq Off Btm (ft-lbf) , , , , , , , , ,6. 13,8. 13, ,5. 5, ,. 5, ,. 4, ,. 5, ,. 5, ,. 7, ,. 7,. 66. FUEL ON HAND GALLONS FUEL USED 2149 GALLONS FUEL RECIEVED GALLONS Remarks 5/29/216 11:21:44 Report Version: R1 Generated from data in EDM/Opens/PROFILE 6

15 Report 22 5/29/216 Company Type WBS No/API No PERMIAN Exploration / Event Summary Event Type Drilling only Event Start Date 4/24/216 Days on Location Objective Drill - Wolfcamp Shale Beta Original Spud Date 4/28/216 Days Since Spud 17.1 Est. Days 32. Contractor PRECISION Work Unit PRECISION 565 Days To Release Rig Phone/FAX No. Status Supervisor BRYAN BOYLES Measured Depth 14,482. Engineer YERMEK TYNYSHBAYEV TVD 11, Other Supervisor JUSTIN HENSON 24 Hr Progress 1,336. Depth Ref/Grd Elev/Water Depth DFE: 2,858.8 / 2,83.3 Hole size THF Datum Rig Operating Rate. Last Casing MD 7.in@11,841.ft Rig Zero Rate. Next Casing MD 4.5in@18,.ft Rig Reduced Rate. Current Fluid Density(ppg) 13.4 Rig Repair Rate. LOT/FIT EMW(ppg) Auxiliary/Secondary Work. Lithology NX Auxiliary Floor Not Available. Formation Actual cost to date/afe 2,3,254/2,964,96. Formation top MD Actual divided by AFE.68 Daily NPT(hr/%) / Daily Cost 59,368 Days Ahd(-) Bhnd(+)(5/5) Last Incident HSE Summary Date Days Last Incident Date Days KPI's LWC RWC MTC FAC Last casing pressure test PSI NII HPI GOAL ZERO DAYS PS BARRIER EVENT PS barrier bowtie review 8/24/ TRCF LWCF Safety Cards - Safe Safety Card - Unsafe SSE% Last casing pressure(psi) 2 Safety Comments: GOAL ZERO 289 DAYS NO LTI 289 DAYS LAST HIPO 36 DAYS LAST RAM 289 DAYS LAST SPILL 289 DAYS RSMT: After action review of intermediate section flat time, focused on how to alleviate solids build up in mud tanks while drilling surface and intermediate sections in an effort to limit time needed to clean mud tanks. Drills/Tests Date Days Since Last HSE Drills Last Derrick Inspection Last BOP function test Last BOP Test Next BOP Test 5/26/216 5/26/216 6/16/ JSA's/Toolbox Talks Days Since Last Drill Hour Summary Drilled F/13146' ' Update Since Report Time Drilling ahead 14655' Operations Summary 5/3/216 7:13:28 Report Version: R1 Generated from data in EDM/Opens/PROFILE 1

16 Report 22 5/29/ Hour Forecast Continue drilling lateral to TD 5/3/216 7:13:28 Report Version: R1 Generated from data in EDM/Opens/PROFILE 2

17 Report 22 5/29/216 Time Summary Start Hours PH OPN WS OPN Drilled Depth NPT level Rig Rate Description : 3.5 D6 DRR 13,45. ROTARY DRILLING F/13,146 T/13,45, ( FPH) WOB: 3 K RPM: SURFACE 65 MOTOR 192 BIT 257 PSI & FLOW: SPP 62 GPM 3 TORQUE: ON BOTTOM 1 K OFF BOTTOM 7 K STRING WEIGHT: UP 215K DOWN 145K ROTATING 17K MW: 13.4 PPG MOTOR REVS/GAL:.64 Gas: BG 85, CG 7 Flare: N/A 3:3.5 D6 MNR 13,45. Service rig 4: 12: 13:3 18:3 2:3 22:3 8. D6 DRR 13,958. ROTARY DRILLING F/13,45 T/13,958, ( FPH) WOB: 3 K RPM: SURFACE 65 MOTOR 192 BIT 257 PSI & FLOW: SPP 63 GPM 3 TORQUE: ON BOTTOM 11 K OFF BOTTOM 7 K STRING WEIGHT: UP 215K DOWN 14K ROTATING 17K MW: 13.4 PPG MOTOR REVS/GAL:.64 Gas: BG 18, CG 175 Flare: 2' 1.5 D6 DRM 13,982. SLIDING F/13,958 T/13,982, (24 16 FPH) WOB: 28K RPM: SURFACE MOTOR 166 BIT 166 PSI & FLOW: SPP 465 GPM 26 DIFF 3 STRING WEIGHT: UP 215K DOWN 14K MW: 13.4 PPG MOTOR REVS/GAL:.64 Gas: BG 15, CG 399 Flare: 2' 5. D6 DRR 14,225. ROTARY DRILLING F/13,982 T/14,225, ( FPH) WOB: 3 K RPM: SURFACE 65 MOTOR 192 BIT 257 PSI & FLOW: SPP 61 GPM 3 TORQUE: ON BOTTOM 12 K OFF BOTTOM 7 K STRING WEIGHT: UP 215K DOWN 14K ROTATING 17K MW: 13.5 PPG *weight up* MOTOR REVS/GAL:.64 Gas: BG 28, CG 268 Flare: 5' 2. D6 DRM 14,264. SLIDING F/14,225 T/14,264, (39 2 FPH) WOB: 24K RPM: SURFACE MOTOR 192 BIT 192 PSI & FLOW: SPP 59 GPM 3 DIFF 27 STRING WEIGHT: UP 215K DOWN 14K MW: 13.7 PPG *weight up* MOTOR REVS/GAL:.64 Gas: BG 29, CG 8 Flare: 2' 2. D6 DRR 14,392. ROTARY DRILLING F/14,264 T/14,392, ( FPH) WOB: 3 K RPM: SURFACE 65 MOTOR 192 BIT 257 PSI & FLOW: SPP 63 GPM 3 TORQUE: ON BOTTOM 12 K OFF BOTTOM 8 K STRING WEIGHT: UP 215K DOWN 14K ROTATING 17K MW: 13.7 PPG MOTOR REVS/GAL:.64 Gas: BG 18, CG 6 Flare: 3'.5 D6 MNR 14,392. Service rig 5/3/216 7:13:28 Report Version: R1 Generated from data in EDM/Opens/PROFILE 3

18 Report 22 5/29/216 Time Summary Start Hours PH OPN WS OPN Drilled Depth NPT level Rig Rate Description 23: 1. D6 DRR 14,482. ROTARY DRILLING F/14,392 T/14,482, (9 9 FPH) WOB: 3 K RPM: SURFACE 65 MOTOR 192 BIT 257 PSI & FLOW: SPP 645 GPM 3 TORQUE: ON BOTTOM 12 K OFF BOTTOM 8 K STRING WEIGHT: UP 215K DOWN 14K ROTATING 17K MW: 13.7 PPG MOTOR REVS/GAL:.64 Gas: BG 18, CG 9 Flare: 3' Total 24. MD Inc. Azi. TVD N/S Deepest 5 Surveys E/W V.Sec DLeg ( /1ft) 14, , , , EPW MWD 14, , , , EPW MWD 14, , , , EPW MWD 14, , , , EPW MWD 14, , , , EPW MWD Fluid Details Mud type Oil Base (GTL) Oil/Water (%) 57./16. POM (cc) MD 13,944. TS/HGS/LGS (%) 25.// CaCl2 (%) Mud Density (ppg) 13.4 Sand (%). Caom/Clom (ppm) Vis (s/qt) 67. Oil/Water Ratio (%) 78.1/21.9 ACT PV/YP (cp/lbf/1ft²) 25./11. XS Lime(lbm/bbl) 3.37 Gels 1 s/m (lbf/1ft²) 1./13. LCM (lbm/bbl) ES (Volts) 575. API/HTHP WL (cc/3min)./ ECD (ppg) R6/3 FC/HTHP FC (32nd")./6. H2S (gas unit) R2/1 WPS (ppm) 288,517 KCl (%) R6/3 FL temp. ( F) Ditch Magnet in Last 24hrs/Cum. (gm) Bit Details Bit no. Size Manufacturer Model no. Class IADC Serial Size MD in MD out IADC Dull Grade code no. (32nd") HALLIBURTON MM64D x16 11, Tool MD 13,45. 13, , , , , ,482. WOB Min/Max Current RPM (rpm) Flow rate (gpm) SPP (psi) P bit (psi) Bit Operations Bit HHP (hp) Hours ROP (ft/hr) Hours cum cum. 3./ , , / , , / , , / , , / , , / , , / , , ROP cum. (ft/hr) Item description 4" DRILL PIPE 5" NOV AGITATOR W/ 1.4 PLATE 5" DRILL PIPE XT-39 x 3 1/2 IF CROSSOVER # Jts Length Drillstring Components OD Max OD ID Connection Name Weight (ppf) Grade Serial no , XTM RIG XTM-39 W , XTM-39 RIG XTM-39 DR /3/216 7:13:28 Report Version: R1 Generated from data in EDM/Opens/PROFILE 4

19 Report 22 5/29/216 Item description FLOAT SUB FILTER SUB # Jts Length Drillstring Components OD Max OD ID Connection Name Weight (ppf) Grade Serial no /2 IF NESFS /2 IF DR2581 SLICK NON-MAG DRILL COLLAR SLICK NON-MAG DRILL COLLAR UBHO ORIENTING SUB CLAW 5" MUD MOTOR FBH 1.75 BIT #5 RUN # " SECURITY MM64D NESMS NESMS NESMS /2 IF C /2 REG Drillstring Details Date/Time in Date/Time out BHA no. BHA Length Min. ID Purpose 5/27/216 3: DRILL 6.125" PRODUCTION SECTION MD 13,45. SW Up 215. SW Down 145. SW Rotn 17. Drag 45. Tq On Btm (ft-lbf) 1,. Tq Off Btm (ft-lbf) 7, , , , , , , ,. 7, ,. 7, ,. 8, ,. 8,. 9. FUEL ON HAND 1116 GALLONS FUEL USED 291 GALLONS FUEL RECIEVED GALLONS Remarks 5/3/216 7:13:28 Report Version: R1 Generated from data in EDM/Opens/PROFILE 5

20 Report 23 5/3/216 Company Type WBS No/API No PERMIAN Exploration / Event Summary Event Type Drilling only Event Start Date 4/24/216 Days on Location Objective Drill - Wolfcamp Shale Beta Original Spud Date 4/28/216 Days Since Spud 18.1 Est. Days 32. Contractor PRECISION Work Unit PRECISION 565 Days To Release Rig Phone/FAX No. Status Supervisor BRYAN BOYLES / ARMANDO Measured Depth RAMIREZ 15,481. Engineer YERMEK TYNYSHBAYEV TVD 11, Other Supervisor JUSTIN HENSON 24 Hr Progress 999. Depth Ref/Grd Elev/Water Depth DFE: 2,858.8 / 2,83.3 Hole size THF Datum Rig Operating Rate. Last Casing MD 7.in@11,841.ft Rig Zero Rate. Next Casing MD 4.5in@18,.ft Rig Reduced Rate. Current Fluid Density(ppg) 13.7 Rig Repair Rate. LOT/FIT EMW(ppg) Auxiliary/Secondary Work. Lithology NX Auxiliary Floor Not Available. Formation Actual cost to date/afe 2,44,187/2,964,96. Formation top MD Actual divided by AFE.69 Daily NPT(hr/%) / Daily Cost 5,366 Days Ahd(-) Bhnd(+)(5/5) Last Incident HSE Summary Date Days Last Incident Date Days KPI's LWC RWC MTC FAC Last casing pressure test PSI NII HPI GOAL ZERO DAYS PS BARRIER EVENT PS barrier bowtie review 8/24/ TRCF LWCF Safety Cards - Safe Safety Card - Unsafe SSE% Last casing pressure(psi) 2 Safety Comments: GOAL ZERO 29 DAYS NO LTI 29 DAYS LAST HIPO 37 DAYS LAST RAM 29 DAYS LAST SPILL 29 DAYS Reviewed Permian incidents over the last 7 days. Reviewed focus areas for this week: heat exhaustion, spotters, tag-lines, travel risk, snakes/bees/spiders, focus on task at hand, and zone management. Reviewed LFI awareness alert DROPS: Casing elevator snagged Kelly hose. Drills/Tests Date Days Since Last HSE Drills Last Derrick Inspection Last BOP function test Last BOP Test Next BOP Test 5/26/216 5/26/216 6/16/ JSA's/Toolbox Talks Days Since Last Drill Hour Summary Drilled F14482' ' Update Since Report Time Operations Summary 5/31/216 7:5:7 Report Version: R1 Generated from data in EDM/Opens/PROFILE 1

21 Report 23 5/3/216 Drilling ahead 15699' 24 Hour Forecast Continue drilling lateral to TD 5/31/216 7:5:7 Report Version: R1 Generated from data in EDM/Opens/PROFILE 2

22 Report 23 5/3/216 Time Summary Start Hours PH OPN WS OPN Drilled Depth NPT level Rig Rate Description : 3. D6 DRR 14,621. ROTARY DRILLING F/14,482 T/14,621, ( FPH) WOB: 32 K RPM: SURFACE 65 MOTOR 192 BIT 257 PSI & FLOW: SPP 635 GPM 3 TORQUE: ON BOTTOM 12 K OFF BOTTOM 8 K STRING WEIGHT: UP 21K DOWN 14K ROTATING 17K MW: 13.7 PPG MOTOR REVS/GAL:.64 Gas: BG 19, CG 49 Flare: 2' 3: 2. D6 DRM 14,641. SLIDING F/14,621 T/14,641, (2 1 FPH) WOB: 16K RPM: SURFACE MOTOR 183 BIT 183 PSI & FLOW: SPP 565 GPM 285 DIFF 3 STRING WEIGHT: UP 215K DOWN 14K MW: 13.7 PPG MOTOR REVS/GAL:.64 Gas: BG 22, CG 49 Flare: 2' 5:.5 D6 DRR 14,661. ROTARY DRILLING F/14,641 T/14,661, (2 2 FPH) WOB: 3 K RPM: SURFACE 65 MOTOR 192 BIT 257 PSI & FLOW: SPP 635 GPM 3 TORQUE: ON BOTTOM 12 K OFF BOTTOM 8 K STRING WEIGHT: UP 21K DOWN 14K ROTATING 17K MW: 13.7 PPG MOTOR REVS/GAL:.64 Gas: BG 195, CG 49 Flare: 2' 5:3.5 D6 MNR 14,661. Service rig 6: 9:3 1:3 16: 16:3 3.5 D6 DRR 14,853. ROTARY DRILLING F/14,661 T/14,853, ( FPH) WOB: 3 K RPM: SURFACE 65 MOTOR 192 BIT 257 PSI & FLOW: SPP 645 GPM 3 TORQUE: ON BOTTOM 12 K OFF BOTTOM 8 K STRING WEIGHT: UP 21K DOWN 14K ROTATING 17K MW: 13.7 PPG MOTOR REVS/GAL:.64 Gas: BG 21, CG 8 Flare: 2' 1. D6 DRM 14,883. SLIDING F/14,853 T/14,883, (3 3 FPH) WOB: 24K RPM: SURFACE MOTOR 183 BIT 183 PSI & FLOW: SPP 57 GPM 285 DIFF 25 STRING WEIGHT: UP 22K DOWN 13K MW: 13.7 PPG MOTOR REVS/GAL:.64 Gas: BG 23, CG 39 Flare: 2' 5.5 D6 DRR 15,11. ROTARY DRILLING F/14,883 T/15,11, ( FPH) WOB: 32 K RPM: SURFACE 65 MOTOR 186 BIT 251 PSI & FLOW: SPP 612 GPM 29 TORQUE: ON BOTTOM 12 K OFF BOTTOM 8 K STRING WEIGHT: UP 23K DOWN 115K ROTATING 17K MW: 13.7 PPG MOTOR REVS/GAL:.64 Gas: BG 21, CG 11 Flare: 2'.5 D6 MNR 15,11. Service rig 7.5 D6 DRR 15,481. ROTARY DRILLING F/15,11 T/15,481, (371 5 FPH) WOB: 33 K RPM: SURFACE 65 MOTOR 186 BIT 251 5/31/216 7:5:7 Report Version: R1 Generated from data in EDM/Opens/PROFILE 3

23 Report 23 5/3/216 Start Hours PH OPN WS OPN Total 24. Drilled Depth NPT level Rig Rate Time Summary Description PSI & FLOW: SPP 615 GPM 29 TORQUE: ON BOTTOM 12 K OFF BOTTOM 8 K STRING WEIGHT: UP 23K DOWN 115K ROTATING 17K MW: 13.7 PPG MOTOR REVS/GAL:.64 Gas: BG 22, CG 8 Flare: 2' Deepest 5 Surveys MD Inc. Azi. TVD N/S E/W V.Sec DLeg ( /1ft) 14, , , , EPW MWD 15, , , , EPW MWD 15, , , , EPW MWD 15, , , , EPW MWD 15, , , , EPW MWD Fluid Details Mud type Oil Base (GTL) Oil/Water (%) 56./16. POM (cc) MD 14,869. TS/HGS/LGS (%) 26.// CaCl2 (%) Mud Density (ppg) 13.7 Sand (%). Caom/Clom (ppm) Vis (s/qt) 69. Oil/Water Ratio (%) 77.8/22.2 ACT PV/YP (cp/lbf/1ft²) 27./12. XS Lime(lbm/bbl) 3.24 Gels 1 s/m (lbf/1ft²) 1./14. LCM (lbm/bbl) ES (Volts) 65. API/HTHP WL (cc/3min)./ ECD (ppg) 15.5 R6/3 FC/HTHP FC (32nd")./8. H2S (gas unit) R2/1 WPS (ppm) 287,98 KCl (%) R6/3 FL temp. ( F) Ditch Magnet in Last 24hrs/Cum. (gm) Bit Details Bit no. Size Manufacturer Model no. Class IADC Serial Size MD in MD out IADC Dull Grade code no. (32nd") HALLIBURTON MM64D x16 11, Tool MD 14, , , , , ,11. 15,481. WOB Min/Max Current RPM (rpm) Flow rate (gpm) SPP (psi) P bit (psi) Bit Operations Bit HHP (hp) Hours ROP (ft/hr) Hours cum cum. 32./ , , / , , / , , / , , / , , / , , / , , ROP cum. (ft/hr) Item description 4" DRILL PIPE 5" NOV AGITATOR W/ 1.4 PLATE 5" DRILL PIPE XT-39 x 3 1/2 IF CROSSOVER FLOAT SUB # Jts Length Drillstring Components OD Max OD ID Connection Name Weight (ppf) Grade Serial no , XTM RIG XTM-39 W , XTM-39 RIG XTM-39 DR /2 IF NESFS /31/216 7:5:7 Report Version: R1 Generated from data in EDM/Opens/PROFILE 4

24 Report 23 5/3/216 Item description FILTER SUB # Jts Length Drillstring Components OD Max OD ID Connection Name Weight (ppf) Grade Serial no /2 IF DR2581 SLICK NON-MAG DRILL COLLAR SLICK NON-MAG DRILL COLLAR UBHO ORIENTING SUB CLAW 5" MUD MOTOR FBH 1.75 BIT #5 RUN # " SECURITY MM64D NESMS NESMS NESMS /2 IF C /2 REG Drillstring Details Date/Time in Date/Time out BHA no. BHA Length Min. ID Purpose 5/27/216 3: DRILL 6.125" PRODUCTION SECTION MD 14,621. SW Up 21. SW Down 14. SW Rotn 17. Drag 4. Tq On Btm (ft-lbf) 12,. Tq Off Btm (ft-lbf) 8, , , , , ,11. 15, ,. 8, ,. 8, ,. 8, ,. 8, FUEL ON HAND 915 GALLONS FUEL USED 2145 GALLONS FUEL RECIEVED GALLONS Remarks 5/31/216 7:5:7 Report Version: R1 Generated from data in EDM/Opens/PROFILE 5

25 Report 24 5/31/216 Company Type WBS No/API No PERMIAN Exploration / Event Summary Event Type Drilling only Event Start Date 4/24/216 Days on Location Objective Drill - Wolfcamp Shale Beta Original Spud Date 4/28/216 Days Since Spud 19.1 Est. Days 32. Contractor PRECISION Work Unit PRECISION 565 Days To Release Rig Phone/FAX No. Status Supervisor ARMANDO RAMIREZ Measured Depth 15,748. Engineer YERMEK TYNYSHBAYEV TVD 11, Other Supervisor JUSTIN HENSON 24 Hr Progress 267. Depth Ref/Grd Elev/Water Depth DFE: 2,858.8 / 2,83.3 Hole size THF Datum Rig Operating Rate. Last Casing MD 7.in@11,841.ft Rig Zero Rate. Next Casing MD 4.5in@18,.ft Rig Reduced Rate. Current Fluid Density(ppg) Rig Repair Rate. LOT/FIT EMW(ppg) Auxiliary/Secondary Work. Lithology NX Auxiliary Floor Not Available. Formation Actual cost to date/afe 2,189,919/2,964,96. Formation top MD Actual divided by AFE.74 Daily NPT(hr/%).5/2.8 Daily Cost 57,755 Days Ahd(-) Bhnd(+)(5/5) Last Incident HSE Summary Date Days Last Incident Date Days KPI's LWC RWC MTC FAC Last casing pressure test PSI NII HPI GOAL ZERO DAYS PS BARRIER EVENT PS barrier bowtie review 8/24/ TRCF LWCF Safety Cards - Safe Safety Card - Unsafe SSE% Last casing pressure(psi) 2 Safety Comments: GOAL ZERO 291 DAYS NO LTI 291 DAYS LAST HIPO 37 DAYS ID# NM DROPS HAMMER DESCENDS TO RIG FLOOR LAST RAM 291 DAYS LAST SPILL 291 DAYS Discussed well control for tripping, mud weight, trip speed, P&ID for force fill valve alignment, barrier ownership - checking drill string floats for BHA Drills/Tests Date Days Since Last HSE Drills Last Derrick Inspection Last BOP function test Last BOP Test Next BOP Test 5/26/216 5/26/216 6/16/ JSA's/Toolbox Talks Days Since Last Drill Hour Summary Operations Summary Drilled F/ , TOOH for ROP, spot 15 weighted pill, L/D BHA #6, Bit grade: 7-2-CR-C-X-IN-PN-PR, M/U BHA #7, wait on weather, TIH to 25 Update Since Report Time 6/1/216 6:41:2 Report Version: R1 Generated from data in EDM/Opens/PROFILE 1

26 Report 24 5/31/216 TIH to 96', slip and cut, function test BOP, circulated out 6 bbl pill, TIH 24 Hour Forecast TIH to bottom, circulate up remaining pill, continue drilling lateral to TD Time Summary Start Hours PH OPN WS OPN Drilled Depth NPT level Rig Rate Description : 5.5 D6 DRR 15,717. ROTARY DRILLING F/15,481 T/15,717, ( FPH) WOB: 33 K RPM: SURFACE 65 MOTOR 186 BIT 251 PSI & FLOW: SPP 615 GPM 29 TORQUE: ON BOTTOM 12 K OFF BOTTOM 8 K STRING WEIGHT: UP 23K DOWN 115K ROTATING 17K MW: 13.7 PPG MOTOR REVS/GAL:.64 Gas: BG 22, CG 97 Flare: 2' 5:3.5 D6 MNR 15,717. Service rig 6: 7: 9: 1:3 12: 14: 15: 17: 17:3 18: 19: 2:3 21: 21:3 22: 23: 1. D6 DRR 15,748. ROTARY DRILLING F/15,717 T/15,748, (31 31 FPH) WOB: 33 K RPM: SURFACE 65 MOTOR 186 BIT 251 PSI & FLOW: SPP 615 GPM 29 TORQUE: ON BOTTOM 12 K OFF BOTTOM 8 K STRING WEIGHT: UP 23K DOWN 115K ROTATING 17K MW: 13.8 PPG MOTOR REVS/GAL:.64 Gas: BG 21, CG 15 Flare: 2' 2. D6 PCD 15,748. Pump sweep, circulate hole clean, pump slug 1.5 D6 DRT 15,748. TOOH F/15748' - 119' Force fill with 13.8 ppg active mud 1.5 D6 PCD 15,748. Circulate B/U, spot 15 bbl 18. ppg pill for 15.2 ppg EMW 2. D6 DRT 15,748. TOOH F/119' - 786' on trip tank 1. D6 PCD 15,748. Circulate B/U, flow check, pump slug 2. D6 DRT 15,748. TOOH F/786' ' on trip tank.5 D6 RUD 15,748. Pull rotating head, monitor well on trip tank.5 D6 DRT 15,748. TOOH F/1684' - 85' on trip tank 1. D6 DRT 15,748. Crew change, clean rig floor, TOOH F/85' - 1' on trip tank 1.5 D6 DRT 15,748. PJSM, L/D BHA #6 Bit grade: 7-2-CR-C-X-IN-PN-PR.5 D6 DRT 15,748. M/U BHA #7.5 D6 SAF 15, NPT-Shut down for adverse weather lightning, monitor well on trip tank.5 D6 MNR 15,748. Service rig 1. D6 DRT 15,748. TIH to 165', pressure drop across agitator 52 psi w/13.8 ppg mud 1. D6 DRT 15,748. TIH F/165' to 25' on trip tank Total 24. 6/1/216 6:41:2 Report Version: R1 Generated from data in EDM/Opens/PROFILE 2

27 Report 24 5/31/216 NPT Summary Start Date/Time Responsible Company NPT Code Failure MD Ops Code Type* Equipment Type Net time Gross time Severity Status 5/31/216 21: SHELL Wait On Weather 15,748. SAF N.5.5 OPEN Description: Shut down for adverse weather lightning, monitor well on trip tank Title: WAIT ON WEATHER Total.5.5 MD Inc. Azi. TVD N/S Deepest 5 Surveys E/W V.Sec DLeg ( /1ft) 15, , , , EPW MWD 15, , , , EPW MWD 15, , , , EPW MWD 15, , , , EPW MWD 15, , , , EPW MWD Fluid Details Mud type Oil Base (GTL) Oil/Water (%) 56./16. POM (cc) MD 15,747. TS/HGS/LGS (%) 26.// CaCl2 (%) Mud Density (ppg) Sand (%). Caom/Clom (ppm) Vis (s/qt) 7. Oil/Water Ratio (%) 77.8/22.2 ACT PV/YP (cp/lbf/1ft²) 26./13. XS Lime(lbm/bbl) 2.98 Gels 1 s/m (lbf/1ft²) 1./14. LCM (lbm/bbl) ES (Volts) 625. API/HTHP WL (cc/3min)./ ECD (ppg) R6/3 FC/HTHP FC (32nd")./8. H2S (gas unit) R2/1 WPS (ppm) 287,98 KCl (%) R6/3 FL temp. ( F) Ditch Magnet in Last 24hrs/Cum. (gm) Bit Details Bit no. Size Manufacturer Model no. Class IADC Serial Size MD in MD out IADC Dull Grade code no. (32nd") HALLIBURTON MM64D x16 11, , CR-C-X-I-PN-PR Tool MD 15, ,748. WOB Min/Max Current RPM (rpm) Flow rate (gpm) SPP (psi) P bit (psi) Bit Operations Bit HHP (hp) Hours ROP (ft/hr) Hours cum cum. 33./ , , / , , ROP cum. (ft/hr) Item description 4" DRILL PIPE 5" NOV AGITATOR W/ 1.4 PLATE 5" DRILL PIPE XT-39 x 3 1/2 IF CROSSOVER FLOAT SUB FILTER SUB SLICK NON-MAG DRILL COLLAR SLICK NON-MAG DRILL COLLAR UBHO ORIENTING SUB # Jts Length Drillstring Components OD Max OD ID Connection Name Weight (ppf) Grade Serial no , XTM RIG XTM-39 W , XTM-39 RIG XTM-39 DR /2 IF NESFS /2 IF DR NESMS NESMS NESMS /1/216 6:41:2 Report Version: R1 Generated from data in EDM/Opens/PROFILE 3

28 Report 24 5/31/216 Item description CLAW 5" MUD MOTOR FBH 1.75 BIT #5 RUN # " SECURITY MM64D # Jts Length Drillstring Components OD Max OD ID Connection Name Weight (ppf) Grade Serial no /2 IF C /2 REG Drillstring Details Date/Time in Date/Time out BHA no. BHA Length Min. ID Purpose 5/27/216 3: 5/31/216 2: DRILL 6.125" PRODUCTION SECTION MD 15,717. SW Up 23. SW Down 115. SW Rotn 17. Drag 6. Tq On Btm (ft-lbf) 12,. Tq Off Btm (ft-lbf) 8, , ,. 8,. 31. Bit Details Bit no. Size Manufacturer Model no. Class IADC Serial Size MD in MD out IADC Dull Grade code no. (32nd") HALLIBURTON MM64D x16 15, Bit Operations MD WOB Min/Max Current RPM (rpm) Flow rate (gpm) SPP (psi) P bit (psi) Bit HHP (hp) Hours ROP (ft/hr) Hours cum cum. ROP cum. (ft/hr) Item description 4" DRILL PIPE 5" NOV AGITATOR W/ 1.4 PLATE 5" DRILL PIPE XT-39 x 3 1/2 IF CROSSOVER FLOAT SUB FILTER SUB # Jts Length Drillstring Components OD Max OD ID Connection Name Weight (ppf) Grade Serial no , XTM RIG XTM-39 W , XTM-39 RIG XTM-39 DR /2 IF NESFS /2 IF DR2581 SLICK NON-MAG DRILL COLLAR SLICK NON-MAG DRILL COLLAR UBHO ORIENTING SUB CLAW 5" MUD MOTOR FBH LOBE 7/8 STAGE BIT #6 RUN # " SECURITY MM64D SN: X NESMS NESMS NESMS /2 IF C /2 REG Drillstring Details Date/Time in Date/Time out BHA no. BHA Length Min. ID Purpose 5/31/216 2: DRILL 6.125" PRODUCTION SECTION FUEL ON HAND 7732 GALLONS FUEL USED 1283 GALLONS FUEL RECIEVED GALLONS Remarks 6/1/216 6:41:2 Report Version: R1 Generated from data in EDM/Opens/PROFILE 4

29 Report 25 6/1/216 Company Type WBS No/API No PERMIAN Exploration / Event Summary Event Type Drilling only Event Start Date 4/24/216 Days on Location Objective Drill - Wolfcamp Shale Beta Original Spud Date 4/28/216 Days Since Spud 2.1 Est. Days 32. Contractor PRECISION Work Unit PRECISION 565 Days To Release Rig Phone/FAX No. Status Supervisor ARMANDO RAMIREZ Measured Depth 16,298. Engineer YERMEK TYNYSHBAYEV TVD 11, Other Supervisor JUSTIN HENSON / ROSS GRAHAM 24 Hr Progress 55. Depth Ref/Grd Elev/Water Depth DFE: 2,858.8 / 2,83.3 Hole size THF Datum Rig Operating Rate. Last Casing MD Rig Zero Rate. Next Casing MD Rig Reduced Rate. Current Fluid Density(ppg) Rig Repair Rate. LOT/FIT EMW(ppg) Auxiliary/Secondary Work. Lithology NX Auxiliary Floor Not Available. Formation Actual cost to date/afe 2,244,75/2,964,96. Formation top MD Actual divided by AFE.76 Daily NPT(hr/%) / Daily Cost 5,36 Days Ahd(-) Bhnd(+)(5/5) 7.in@11,841.ft 4.5in@18,.ft Last Incident HSE Summary Date Days Last Incident Date Days KPI's LWC RWC MTC FAC Last casing pressure test PSI NII HPI GOAL ZERO DAYS PS BARRIER EVENT PS barrier bowtie review 8/24/ TRCF LWCF Safety Cards - Safe Safety Card - Unsafe SSE% Last casing pressure(psi) Safety Comments: GOAL ZERO 292 DAYS NO LTI 292 DAYS LAST HIPO 38 DAYS ID# NM DROPS HAMMER DESCENDS TO RIG FLOOR LAST RAM 292 DAYS LAST SPILL 292 DAYS OSHA training reviewed hearing protection. Drill Category Drill Type Detection (sec) Drills Complete (sec) Crew drilled Pass / Fail PIC Comments Control Crew Trip 8. Day Pass ARMANDO RAMIREZ 6/2/216 5:48:11 Report Version: R1 Generated from data in EDM/Opens/PROFILE 1

30 Report 25 6/1/216 HSE Drills Drills/Tests Date Days Since Last Last Derrick Inspection Last BOP function test Last BOP Test Next BOP Test 6/1/216 5/26/216 6/16/216 6 JSA's/Toolbox Talks Days Since Last Drill Hour Summary Operations Summary TIH F/25-96, slip and cut, function test BOP, circulated out 6 bbl pill, TIH to bottom, circulated out 85 bbl pill & B/U, drill F/ Update Since Report Time Drilling 16544' 24 Hour Forecast Continue drilling lateral to TD 6/2/216 5:48:11 Report Version: R1 Generated from data in EDM/Opens/PROFILE 2

31 Report 25 6/1/216 Time Summary Start Hours PH OPN WS Drilled NPT Rig Description OPN Depth level Rate : 2.5 D6 DRT 15,748. TIH F/25' - 96' on trip tank 2:3 3:3 4:3 5:3 6: 9: 1:3 13:3 16: 17: 17:3 1. D6 MNR 15,748. Slip and cut drill line 1. D6 PCD 15,748. Circulate out 6 bbl 18. ppg weighted pill 1. D6 DRT 15,748. TIH F/96' - 113' on trip tank.5 D6 MNR 15,748. Rig service 3. D6 DRT 15,748. TIH F/113' ' on trip tank (tight 1293', 3K) 1.5 D6 PCD 15,748. Circulate out 85 bbl 18. ppg weighted pill and B/U trip gas 3. D6 DRR 15,846. ROTARY DRILLING F/15,748 T/15,846, (98 33 FPH) WOB: 19 K RPM: SURFACE 65 MOTOR 2 BIT 265 PSI & FLOW: SPP 635 GPM 29 TORQUE: ON BOTTOM 12.5 K OFF BOTTOM 7 K STRING WEIGHT: UP 215K DOWN 9K ROTATING 165K MW: 13.9 PPG MOTOR REVS/GAL:.69 Gas: BG 17, CG 718 Flare: -5' 2.5 D6 DRM 15,876. SLIDING F/15,846 T/15,876, (3 12 FPH) WOB: 33K RPM: SURFACE MOTOR 197 BIT 197 PSI & FLOW: SPP 625 GPM 285 DIFF 21 STRING WEIGHT: UP 215K DOWN 11K MW: 13.9 PPG MOTOR REVS/GAL:.69 Gas: BG 14, CG 718 Flare: -2' 1. D6 DRR 15,919. ROTARY DRILLING F/15,876 T/15,919, (43 43 FPH) WOB: 19 K RPM: SURFACE 65 MOTOR 2 BIT 265 PSI & FLOW: SPP 635 GPM 29 TORQUE: ON BOTTOM 12.5 K OFF BOTTOM 7 K STRING WEIGHT: UP 215K DOWN 11K ROTATING 165K MW: 13.9 PPG MOTOR REVS/GAL:.69 Gas: BG 85, CG 12 Flare: -5'.5 D6 MNR 15,919. Rig service 6.5 D6 DRR 16,298. ROTARY DRILLING F/15,919 T/16,298, ( FPH) WOB: 19 K RPM: SURFACE 65 MOTOR 2 BIT 265 PSI & FLOW: SPP 635 GPM 29 TORQUE: ON BOTTOM 12.5 K OFF BOTTOM 7 K STRING WEIGHT: UP 21K DOWN 11K ROTATING 165K MW: 13.9 PPG MOTOR REVS/GAL:.69 Gas: BG 15, CG 6 Flare: -5' Total 24. MD Inc. Azi. TVD N/S Deepest 5 Surveys E/W V.Sec DLeg ( /1ft) 15, , , , EPW MWD 15, , , , EPW MWD 16, , , , EPW MWD Tool 6/2/216 5:48:11 Report Version: R1 Generated from data in EDM/Opens/PROFILE 3

EP WELLS DAILY OPERATIONS REPORT Report 1 02/02/2017

EP WELLS DAILY OPERATIONS REPORT Report 1 02/02/2017 Report 2/2/27 Company Type WBS No/API No PERMIAN Development 3259585 / 423337 Event Summary Event Type Drilling only Event Start Date 2/2/27 Days on Location.94 Objective Drill - Wolfcamp Shale Original

More information

EP WELLS DAILY OPERATIONS REPORT Report 29 04/21/2017

EP WELLS DAILY OPERATIONS REPORT Report 29 04/21/2017 4/22/217 8:23:32 Report Version: 4.1.16R9 Generated from data in EDM/Opens/PROFILE 1 RESTRICTED Report 29 4/21/217 Company Type bore WBS No/API No PERMIAN Development 3256997 / 42313354. Event Summary

More information

EP WELLS DAILY OPERATIONS REPORT Report 29 05/19/2017

EP WELLS DAILY OPERATIONS REPORT Report 29 05/19/2017 5/2/27 5:23:5 Report Version: 4..6R9 Generated from data in EDM/Opens/PROFILE Report 29 5/9/27 Company Type WBS No/API No PERMIAN Development UNIVERSITY 9 PW UNIT 56H UNIVERSITY 9 PW UNIT 56H 32656 / 4233326.

More information

EP WELLS DAILY OPERATIONS REPORT Report 38 07/18/2017

EP WELLS DAILY OPERATIONS REPORT Report 38 07/18/2017 1 Company Type bore WBS No/API No PERMIAN Development 30265014 / 4230133171.00 Event Summary Event Type Completion only Event Start Date 04/28/2017 Days on Location 37.00 Objective Install Completion Original

More information

Terrace Petroleum Corporation Cunning Wolf UL No. 602H, 1980 FNL and 467 FWL Section 6, Block 23, ULS Pecos County, Texas

Terrace Petroleum Corporation Cunning Wolf UL No. 602H, 1980 FNL and 467 FWL Section 6, Block 23, ULS Pecos County, Texas Terrace Petroleum Corporation Cunning Wolf UL No. 602H, 1980 FNL and 467 FWL Section 6, Block 23, ULS Pecos County, Texas 3-29-13 DAY 1 Previously built location, roads, built and lined reserve pits. Move

More information

University 31E 4. Ward County, TX. Rig: Union Drlg Rig 229. AFE: $1,393, DHC: $761, WI: Notes: Workover:

University 31E 4. Ward County, TX. Rig: Union Drlg Rig 229. AFE: $1,393, DHC: $761, WI: Notes: Workover: Zone: War-Wink Cherry Canyon TD: 7250' Rig: Union Drlg Rig 229 Status: WOC Spud Date: 1/26/2013 RR Date: 2/12/2013 First Sales: AFE: $1,393,293.00 DHC: $761,963.00 WI: Notes: Date Activity 11/14/2012 11/14/12

More information

AMERICAN ENERGY - PERMIAN BASIN, LLC UL Daily Drilling Partner Summary

AMERICAN ENERGY - PERMIAN BASIN, LLC UL Daily Drilling Partner Summary AEPB WELL NO. Report End Date: Report Number: 1 Rig: INTEGRITY, 3 Projected Days (days): 0 Drilling Days: : 70 : 0 Planned VS (ft): Current VS (ft): 42383383570000 MIRU MIRU INTEGRITY 3. 70 Longitude Orig

More information

EP WELLS DAILY OPERATIONS REPORT Report 1 08/03/2016

EP WELLS DAILY OPERATIONS REPORT Report 1 08/03/2016 Report 1 8/3/216 Company Type bore WBS No/API No PERMIAN Exploration / 424953375. Event Summary Event Type Completion only Event Start Date 8/3/216 Days on Location 1. Objective Install Completion Original

More information

Drilling Morning Report

Drilling Morning Report REPORT DATE 5/0/200 Report # AFE # Casing OD(in) WT(lbs/ft) Grade Btm MD(ft) Btm TVD(ft) DCRB04 TVD: 32 MD: 32 Progress: 32 Planned TD:,500 Current Hole Size: Days From Spud: Spud Date: 5//0 Days on Well:

More information

Niko Deepwater Weatherford MPD DODI Ocean Monarch Nelson Emery Niko Indonesia Drilling Superintendent

Niko Deepwater Weatherford MPD DODI Ocean Monarch Nelson Emery Niko Indonesia Drilling Superintendent Niko Deepwater Weatherford MPD DODI Ocean Monarch Nelson Emery Niko Indonesia Drilling Superintendent 26 Feb - 2014 SPE Thailand 1 Outline Drivers for MPD: 1. Safety of personnel in remote operations 2.

More information

PERMIAN RESOURCES, LLC UL Daily Drilling Partner Summary

PERMIAN RESOURCES, LLC UL Daily Drilling Partner Summary PRES WELL NO. Report End Date: 5/19/2016 Report Number: 3 Rig: INTEGRITY, 3 Projected Days (days): 0 Drilling Days: : : 0 Planned VS (ft): Current VS (ft): WOC WOC, CONTACTED TRRC, SPOKE TO ABRAHAM, ADVISED

More information

BP SIT Testing Franks Facility Lafayette

BP SIT Testing Franks Facility Lafayette BP SIT Testing Franks Facility Lafayette General Information Status: Franks test well Lafayette La. Rig: Franks Test Rig Casing: 13 3/8, 0 to 4,600 Workstring: 4 ½ IF Brine: Fresh Water Directional: Straight

More information

Wellwork Chronological Regulatory Report

Wellwork Chronological Regulatory Report Well Name: UNIVERSITY 49 #0808H Field: Lin (Wolfcamp) S/T/R: / / County, State: Location Desc: Operator: Enduring Resources, LLC Project Type: Completion District: Southern Project AFE: DV02151 AFE's Associated:

More information

D & V Oil Co. LP. Daily Completion Report - University CN A #6 API # /23/2016. Perfs ' ' Activity :

D & V Oil Co. LP. Daily Completion Report - University CN A #6 API # /23/2016. Perfs ' ' Activity : Daily Completion Report - University CN A #6 API # 42-105-42334 12/23/2016 Activity at Report Time: Perfs - 2512' - 2632' Depth at Report Time Put Well on Production 2655' - PBTD Activity : Arrive Location.

More information

BLACK HILLS PLATEAU PRODUCTION COMPANY

BLACK HILLS PLATEAU PRODUCTION COMPANY BLACK HILLS PLATEAU PRODUCTION COMPANY DRILLING PROGRAM Homer Deep Unit 9 11CH SHL: 300 FNL, 200 FWL, NWNW Sect. 9 T8S R98W BHL: 1350 FSL, 2100 FEL NWSE Sect. 15 T8S R98W Garfield & Mesa Counties, Colorado

More information

and and Norton J. Lapeyrouse CONTENTS

and and Norton J. Lapeyrouse CONTENTS and and Norton J. Lapeyrouse CONTENTS Chapter 1 Basic Formulas P. 3 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. 17. 18. 19. Pressure Gradient Hydrostatic Pressure Converting Pressure into Mud

More information

DUO-SQUEEZE H LCM Mixing Tables and Operating Procedures

DUO-SQUEEZE H LCM Mixing Tables and Operating Procedures BAROID DUO-SQUEEZE H LCM Mixing Tables and Operating Procedures Prepared for: Prepared by: Submitted by: Submittal Date: All Customers Sharath Savari, Donald L. Whitfill Halliburton January 2014 1 Copyright

More information

DAY ONE. 2. Referring to the last question, what mud weight would be required to BALANCE normal formation pressure?

DAY ONE. 2. Referring to the last question, what mud weight would be required to BALANCE normal formation pressure? DAY ONE 1. Normal formation pressure gradient is generally assumed to be: A..496 psi/ft B..564 psi/ft C..376 psi/ft D..465 psi/ft 2. Referring to the last question, what mud weight would be required to

More information

Chapter 5 HORIZONTAL DRILLING

Chapter 5 HORIZONTAL DRILLING Chapter 5 HORIZONTAL DRILLING Chapter 5 How much money am I about to put on the table for a horizontal well? Did I do sufficient planning? Keys to Successful Horizontal Wells Multi-disciplined teams working

More information

Deepwater Horizon Incident Internal Investigation

Deepwater Horizon Incident Internal Investigation Not all Information has been verified or corroborated. Subject to review based on additional information or analysis. Deepwater Horizon Incident Internal Investigation 1 Areas of Discussion Investigation

More information

IWCF Equipment Sample Questions (Surface Stack)

IWCF Equipment Sample Questions (Surface Stack) IWCF Equipment Sample Questions (Surface Stack) 1. During a well control operation 4000 psi was shut in below the middle pipe rams. Ram type BOP data: Model: Cameron U type Rated Working Pressure: 15000

More information

Casing Design. Casing Design. By Dr. Khaled El-shreef

Casing Design. Casing Design. By Dr. Khaled El-shreef Casing Design By Dr. Khaled El-shreef 1 Casing Design CONTENTS Function of Casing Casing Types & Tools Strength Properties Casing Specification Casing Design 2 1 RUNNING AND CEMENTING CASING Reasons for

More information

Study Guide IADC WellSharp Driller and Supervisor

Study Guide IADC WellSharp Driller and Supervisor Times to Flow Check: Before pulling out of the hole Before pulling BHA into the BOP When bit is pulled into the casing Increase in cuttings at shakers with same ROP On connections Upon abnormal trip tank

More information

Float Equipment TYPE 925/926

Float Equipment TYPE 925/926 Type 925 Float Collar Plunger Valve Float Equipment For less demanding well conditions, such as shallower depths or lower pressures, Top- Co offers economical float equipment certified to API RP 10F category

More information

float equipment OPERATING MANUAL TYPE 505/506 Float Equipment 1. INFORMATION & RECOMMENDATIONS Float Equipment

float equipment OPERATING MANUAL TYPE 505/506 Float Equipment 1. INFORMATION & RECOMMENDATIONS Float Equipment Contents 1. GENERAL INFORMATION & RECOMMENDATIONS 1 2. INSTALLATION FLOAT EQUIPMENT 2 2.1 PRE-USE FIELD INSPECTION 2 2.2 POSITION FLOAT ON CASING STRING 3 3. RUNNING OF FLOAT EQUIPMENT 3 3.1 CIRCULATION

More information

Wellwork Chronological Regulatory Report

Wellwork Chronological Regulatory Report Well Name: UNIVERSITY 09A #1003H Field: Lin (Wolfcamp) S/T/R: / / County, State: Location Desc: Operator: Enduring Resources, LLC Project Type: Completion District: Southern - ERPBU Project AFE: DV02251

More information

Daily Drilling Report

Daily Drilling Report Daily Drilling Report Well Name UTL 38-17-1H Report Date 05/05/2014 Field University Lands Supervisor Nate Baxter Report No. 97 Location 990' FNL & 300' FEL Supervisor 2 Kevin Evans DFS 94 County Ward

More information

ECD Reduction Tool. R. K. Bansal, Brian Grayson, Jim Stanley Control Pressure Drilling & Testing

ECD Reduction Tool. R. K. Bansal, Brian Grayson, Jim Stanley Control Pressure Drilling & Testing ECD Reduction Tool R. K. Bansal, Brian Grayson, Jim Stanley Control Pressure Drilling & Testing Drilling Engineering Association, Fourth Quarter Meeting November 20, 2008 1 Presentation outline Description

More information

BaraBlend -665 LCM Standard Field Application Procedure

BaraBlend -665 LCM Standard Field Application Procedure BAROID BaraBlend -665 LCM Standard Field Application Procedure Prepared for: Prepared by: Submitted by: Submittal Date: All Customers Sharath Savari, Donald L. Whitfill Halliburton Apr 2016 1 Copyright

More information

ENDEAVOR ENERGY RESOURCES

ENDEAVOR ENERGY RESOURCES ENDEAVOR ENERGY RESOURCES Lease WELL NO FIELD PBTD PERFORATIONS FOREMAN TOOLPUSHER API NUMBER DATE University 5-20-21 #1H 14,223' Tony Cody 07/02/13 OART WEATHER FLUID SUMMARY W/O UNIT DATA W/L UNIT DATA

More information

Post Job Summary Cement Intermediate Casing

Post Job Summary Cement Intermediate Casing EXXONMOBIL CORPORATION HOUSTON, Texas PCU 197-36A6 H&P 326 Post Job Summary Cement Intermediate Casing Prepared for: George McNary Date Prepared: November 16, 2010 Version: 1 Service Supervisor: ANDERSON,

More information

Hydraulic Optimization Worksheet for MS Excel All Versions subsequent to 5.0

Hydraulic Optimization Worksheet for MS Excel All Versions subsequent to 5.0 Hydraulic Optimization Worksheet for MS Excel All Versions subsequent to 5.0 1. Introduction. 2. Data Input. Header. Bit Information. Mud Information. Casing Program. P.D.M./Turbine. Drill String Design.

More information

Rig Math. Page 1.

Rig Math. Page 1. Page 1 The Calculator and Main Keyboard Display Numerical 10-key pad used for entering numerical values Trigonometric Functions These keys will be used where wellbore angle is an issue These are the keys

More information

HPHT Annular Casing Packer. Obex Annular Casing Packer

HPHT Annular Casing Packer. Obex Annular Casing Packer HPHT Annular Casing Packer Obex Annular Casing Packer Industry Challenge Casing packer to support second stage cement Reduce hydrostatic pressure on formation Get cement to surface Annular gas migration

More information

PowerDrive X6. Rotary Steerable System for high-performance drilling and accurate wellbore placement

PowerDrive X6. Rotary Steerable System for high-performance drilling and accurate wellbore placement Rotary Steerable System for high-performance drilling and accurate wellbore placement The PowerDrive X6 RSS maintains control under the most difficult conditions, bringing the benefits of rotary steerable

More information

BENEDUM (DEVONIAN, GAS) API # UPTON COUNTY, TX DRILLING PERMIT # DAILY REPORTS

BENEDUM (DEVONIAN, GAS) API # UPTON COUNTY, TX DRILLING PERMIT # DAILY REPORTS 11/17/2011 11/18/2011 11/19/2011 AFE dated 11/18/2011 - pull tbg out of hole and make a mill run. Run packer on tbg and attempt to reestablish production from Devonian Formation. MIRU Great Basin Pulling

More information

FORGE Energy UL 21 Freedom 1 API Number:

FORGE Energy UL 21 Freedom 1 API Number: FORGE Energy UL 21 Freedom 1 API Number: 42-371-39061 07/13/2013 RU E&P WL Open well RIH correlate GR log to get on depth. Run BL found cement to surface. Tag 7566' PBTD. RU Rising Star test lines to 5000

More information

Extended leak off testing

Extended leak off testing Extended leak off testing Rev: 1.0 03/01/01 Purpose To ensure minimal operational time and risk exposure to personnel, process, production and equipment. The following extended leak off test procedures

More information

MOCS. Multiple Opening Circulation Sub. Fluid Bypass Valve

MOCS. Multiple Opening Circulation Sub. Fluid Bypass Valve MOCS Multiple Opening Circulation Sub Fluid Bypass Valve 1 Applications BHA Protection o o Pumping LCM Spotting Acid Work-over and completions o o o Well bore cleanout Fluid displacements Bottoms-up circulation

More information

RIH intermediate section casing in Bazian-1 exploration oil well

RIH intermediate section casing in Bazian-1 exploration oil well Energy and Sustainability V 559 RIH intermediate section casing in Bazian-1 exploration oil well A. K. Darwesh Petroleum Engineering Department, Engineering Faculty, Koya University, Kurdistan Abstract

More information

W I L D W E L L C O N T R O L PRESSURE BASICS AND CONCEPTS

W I L D W E L L C O N T R O L PRESSURE BASICS AND CONCEPTS PRESSURE BASICS AND CONCEPTS Pressure Basics and Concepts Learning Objectives You will be familiarized with the following basic pressure concepts: Defining pressure Hydrostatic pressure Pressure gradient

More information

SUBSEA KILL SHEET EXERCISE No. 5

SUBSEA KILL SHEET EXERCISE No. 5 Subsea Kill Sheet Exercise No. 5 SUBSEA KILL SHEET EXERCISE No. 5 Name: Date: Complete the Subsea vertical kill sheet provided on pages 2 and 3. Then answer questions 1 to 12. Please round calculations

More information

Final Well Report. Revision: Version 0. Corp) Hole Name: Flat Bay Test Hole # 5 Rig: Duralite 800

Final Well Report. Revision: Version 0. Corp) Hole Name: Flat Bay Test Hole # 5 Rig: Duralite 800 Final Well Report Revision: Version 0 Operating Company: Vulcan Minerals Inc. (Investcan Energy Corp) Hole Name: Flat Bay Test Hole # 5 Rig: Duralite 800 Field: Flat Bay Location: Western Newfoundland,

More information

Type 967 Diamond Broaching Type 968 Sidewinder reamer shoe

Type 967 Diamond Broaching Type 968 Sidewinder reamer shoe Type 965 float collar Type 966 float shoe 1. GENERAL INFORMATION & RECOMMENDATIONS Type 967 Diamond Broaching Type 968 Sidewinder reamer shoe Type 969 Sidewinder reamer shoe Float Equipment Top-Co Float

More information

HydroPull. Extended-Reach Tool. Applications

HydroPull. Extended-Reach Tool. Applications Extended-Reach Tool HydroPull This tool incorporates a cycling valve that momentarily interrupts the flow to create water-hammer pressure pulses inside coiled or jointed tubing used in horizontal well

More information

SPE/IADC Abstract

SPE/IADC Abstract SPE/IADC 125311 Pressurized Mud Cap Drilling Drastically Reduces Non-Productive Time in Soka Field, South Sumatera Michael Runtuwene, Sanny Suprihono, and Dany Rizka, SPE, Medco E&P Indonesia, Andi Eka

More information

R.K. Bansal, Weatherford; P.A. Bern, BP Exploration; Rick Todd, Weatherford; R.V. Baker, BP America; Tom Bailey, Weatherford

R.K. Bansal, Weatherford; P.A. Bern, BP Exploration; Rick Todd, Weatherford; R.V. Baker, BP America; Tom Bailey, Weatherford AADE-07-NTCE-69 A Downhole Tool for Reducing ECD R.K. Bansal, Weatherford; P.A. Bern, BP Exploration; Rick Todd, Weatherford; R.V. Baker, BP America; Tom Bailey, Weatherford Copyright 2007, AADE This paper

More information

W I L D W E L L C O N T R O L CIRCULATION & WELL CONTROL

W I L D W E L L C O N T R O L CIRCULATION & WELL CONTROL CIRCULATION & WELL CONTROL Learning Objectives You will learn: The importance of pump rates and pressures during well control operations Pressure relationships Basic calculations necessary in well control

More information

Air and Gas Drilling

Air and Gas Drilling Air and Gas Drilling Air and Gas Drilling It is a technique in which the more common drilling fluids, (water or mud) are replaced by highly compressible Air or Natural gas. But Compressibility makes pressure

More information

Oil Well Potential Test, Completion or Recompletion Report, and Log

Oil Well Potential Test, Completion or Recompletion Report, and Log Tracking No.: 102948 Status: Submitted RAILROAD COMMISSION OF TEXAS Oil and Gas Division API No. 42- Oil Well Potential Test, Completion or Recompletion Report, and Log 1. FIELD NAME (as per RRC Records

More information

Debris Management Drilling Tools

Debris Management Drilling Tools Debris Management Drilling Tools Protecting BHA components during well construction Remove drilling debris from the wellbore before it creates expensive problems. Debris commonly causes downhole tool failure,

More information

RAILROAD COMMISSION OF TEXAS OIL WELL POTENTIAL TEST, COMPLETION OR RECOMPLETION REPORT, AND LOG

RAILROAD COMMISSION OF TEXAS OIL WELL POTENTIAL TEST, COMPLETION OR RECOMPLETION REPORT, AND LOG RAILROAD COMMISSION OF TEXAS 1701 N. Congress P.O. Box 12967 Austin, Texas 78701-2967 Status: Form W-2 OIL WELL POTENTIAL TEST, COMPLETION OR RECOMPLETION REPORT, AND LOG Date: Tracking No.: Approved 10/13/2015

More information

BANDAR PANJI-1 WELL CONTROL INCIDENT REPORT

BANDAR PANJI-1 WELL CONTROL INCIDENT REPORT BANDAR PANJI-1 WELL CONTROL INCIDENT REPORT EXECUTIVE SUMMARY I was requested by management to review the Banjar Panji-1 drilling operations from the conception of the Integrated Drilling Management approach

More information

PHE KE30-A8 WORKOVER PROGRAM

PHE KE30-A8 WORKOVER PROGRAM PHE WMO KE30-A8 WORKOVER PROGRAM PHE KE30-A8 WORKOVER PROGRAM Prepared by: Ross Webber. Hendra Wahyudi. Chandra Maulana. George Lattimore Adi Benanjaya Achmad Soendaroe. Tri Wiyono DRILLING ENGINEER SR.

More information

BaraShield -664 LCM Standard Field Application Procedure

BaraShield -664 LCM Standard Field Application Procedure BaraShield -664 LCM Standard Field Application Procedure Prepared for: Prepared by: Submitted by: Submittal Date: All Customers Sharath Savari, Donald L. Whitfill Halliburton March 2016 1 Copyright 2011

More information

Bridge Plugs, Ball Drop & Caged Ball Plugs For Zone Isolation

Bridge Plugs, Ball Drop & Caged Ball Plugs For Zone Isolation Bridge Plugs, Ball Drop & Caged Ball Plugs For Zone Isolation ADVANTAGE composite bridge plug, caged ball and ball drop (flow thru) frac plug provide a means to isolate multiple zones during high pressure

More information

FORGE Energy UL 21 Pahaska 1H API Number:

FORGE Energy UL 21 Pahaska 1H API Number: FORGE Energy UL 21 Pahaska 1H API Number: 42-495-33740 10/26/2016 07:00 HPJM 07:15 Install 1502 Adapter Flanges to Well Head. RU Pump Truck test lines to 1000 PSI no leaks. Load hole w/ 15 bbls fresh water.

More information

PROPOSED NEW SUB- CODE 1 RIG UP AND TEAR. Possibly Fits into Existing Code. 7/26/2018 Review PROPOSED NEW CODE EXISTING OPERATION

PROPOSED NEW SUB- CODE 1 RIG UP AND TEAR. Possibly Fits into Existing Code. 7/26/2018 Review PROPOSED NEW CODE EXISTING OPERATION NW NW 1 RIG UP AND TAR 1 no sub-code RIG UP AND TAR DOWN Start: Rig released from previous well, nd: Rig fully rigged up, acceptance tests successfully completed, and signed off. DOWN 1 1 Rig Under Tow

More information

North American sealing solutions Bridge Plug Ball Drop Frac Plug Caged Ball Frac Plug

North American sealing solutions Bridge Plug Ball Drop Frac Plug Caged Ball Frac Plug North American sealing solutions Bridge Plug Ball Drop Frac Plug Caged Ball Frac Plug The North American Sealing Solutions composite bridge plug, caged ball and ball drop (flow thru) frac plug provide

More information

2-7/8 TRIPLE PORTED PBL BYPASS SYSTEM

2-7/8 TRIPLE PORTED PBL BYPASS SYSTEM RECEIVING PBL AT RIG SITE TITLE: Operating Instructions for 2-7/8 Triple Port PBL 1-10-201 2-7/8 TRIPLE PORTED PBL BYPASS SYSTEM OPERATING INSTRUCTIONS 1. On receipt of PBL Bypass Tools at Rig site, the

More information

W I L D W E L L C O N T R O L AIR DRILLING

W I L D W E L L C O N T R O L AIR DRILLING AIR DRILLING Air Drilling Learning Objectives You will learn the basics of: Air drilling equipment Types of air drilling Differences between mud and air drilling You will learn how to apply well control

More information

Offshore Managed Pressure Drilling Experiences in Asia Pacific. SPE paper

Offshore Managed Pressure Drilling Experiences in Asia Pacific. SPE paper Offshore Managed Pressure Drilling Experiences in Asia Pacific SPE paper 119875 Authors: Steve Nas, Shaun Toralde, Chad Wuest, SPE, Weatherford Solutions Sdn Bhd, SPE, Weatherford Indonesia SPE, Weatherford

More information

Live well deployment of long perforating gun system using combined CT technologies

Live well deployment of long perforating gun system using combined CT technologies Live well deployment of long perforating gun system using combined CT technologies SPE ICoTA European Well Intervention Conference Aberdeen - 12 November, 2014 Simon Smith, Technical Support Manager Baker

More information

Horizontal Marmaton Wells in Beaver County, OK

Horizontal Marmaton Wells in Beaver County, OK Horizontal Marmaton Wells in Beaver County, OK Drilling Improvements & Lessons Learned Presented by: Michael Dunn Drilling Engineer Unit Petroleum Forward Looking Statement DISCLAIMER It is understood

More information

INTERMEDIATE CASING SELECTION FOR COLLAPSE, BURST AND AXIAL DESIGN FACTOR LOADS EXERCISE

INTERMEDIATE CASING SELECTION FOR COLLAPSE, BURST AND AXIAL DESIGN FACTOR LOADS EXERCISE INTERMEDIATE CASING SELECTION FOR COLLAPSE, BURST AND AXIAL DESIGN FACTOR LOADS EXERCISE Instructions Use the example well data from this document or the powerpoint notes handout to complete the following

More information

1. The well has been shut in on a kick and the kill operation has not started.

1. The well has been shut in on a kick and the kill operation has not started. Well Control Methods Day 2 1. The well has been shut in on a kick and the kill operation has not started. Shut in drill pipe pressure Shut in casing pressure 500 psi 700 psi After stabilization, both pressures

More information

DRILLSCENE PROACTIVE DRILLING DECISIONS

DRILLSCENE PROACTIVE DRILLING DECISIONS DRILLSCENE PROACTIVE DRILLING DECISIONS RISE TO THE CHALLENGE OF REAL-TIME DRILLING CONTROL Today s oil and gas drilling operations present significant technical challenges in remote locations and increasingly

More information

E NGINEERED C EMENTING S OLUTIONS

E NGINEERED C EMENTING S OLUTIONS DART CATCHER TOOL Blackhawk s Dart Catcher Tool provides indication of the exact location of downhole fluids during inner string cement jobs, cementing squeezes, or balanced cement plugs for temporary/permanent

More information

Proper Pump Installation Practices

Proper Pump Installation Practices Proper Pump Installation Practices 80-779, Rev. 10/08 There is a Reason Every Unit Comes With This Bright Orange Tag! Proper Alignment and Coupling Installation Do Not Drive Coupling Onto Shaft Pump Alignment

More information

August 21, Deepwater MPD / PMCD

August 21, Deepwater MPD / PMCD August 21, 2011 Deepwater MPD / PMCD Managed Pressure Drilling (MPD) Pressure held on top of riser while drilling. Drill in overbalance condition Pressurized Mud Cap Drilling (PMCD) Pressure of mud column

More information

SCORPION HIGH-QUALITY, FULLY COMPOSITE PLUGS

SCORPION HIGH-QUALITY, FULLY COMPOSITE PLUGS SCORPION HIGH-QUALITY, FULLY COMPOSITE PLUGS A DIFFERENT KIND OF ENERGY COMPANY Nine Energy Service isn t your typical oilfield services company. Our success stems from a culture driven by performance

More information

Blowout during Workover Operation A case study Narration by: Tarsem Singh & Arvind Jain, OISD

Blowout during Workover Operation A case study Narration by: Tarsem Singh & Arvind Jain, OISD 1. Introduction An incident of gas leakage from a well took place during workover operations. Subsequently, the gas caught fire on the fourth day in which twelve persons were injured. Two contract workers,

More information

Hydro-Mech Bridge Plug

Hydro-Mech Bridge Plug Manual No: 0620000303 Revision: F Approved By: Quality Engineer Date: 2014-9-9 Hydro-Mech Bridge Plug DESCRIPTION: Map Hydro-Mech Bridge Plug is hydraulically actuated and mechanically set. Compact, with

More information

WILD WELL CONTROL WARNING SIGNS OF KICKS

WILD WELL CONTROL WARNING SIGNS OF KICKS WARNING SIGNS OF KICKS Warning Signs of Kicks Learning Objectives You will learn the warning signs that indicate the well may be kicking: Warning signs of kicks False kick indicators You will also learn

More information

6-3/4 DUAL PORTED PBL BYPASS SYSTEM (Applicable to sizes 6-1/4 & 6-1/2 also)

6-3/4 DUAL PORTED PBL BYPASS SYSTEM (Applicable to sizes 6-1/4 & 6-1/2 also) RECEIVING PBL AT RIG SITE TITLE: Operating Instructions for -3/4 PBL -3/4 DUAL PORTED PBL BYPASS SYSTEM (Applicable to sizes -1/4 & -1/2 also) OPERATING INSTRUCTIONS 1. On receipt of PBL Bypass Tools at

More information

NeoProducts, LLC 1201 Dealers Ave. Harahan, LA Ph:

NeoProducts, LLC 1201 Dealers Ave. Harahan, LA Ph: Please read this entire document. It concerns all 9⅝ Vented Thru-tubing Bridge Plugs Read this document before proceeding to NeoProducts Recommended Best Practices for 9⅝ vented T- TBPs. Whenever running

More information

Dilution-Based Dual Gradient Well Control. Presented at the 2011 IADC Dual Gradient Workshop, 5 May 2011 by Paul Boudreau, Dual Gradient Systems LLC

Dilution-Based Dual Gradient Well Control. Presented at the 2011 IADC Dual Gradient Workshop, 5 May 2011 by Paul Boudreau, Dual Gradient Systems LLC Dilution-Based Dual Gradient Well Control Presented at the 2011 IADC Dual Gradient Workshop, 5 May 2011 by Paul Boudreau, Dual Gradient Systems LLC In this very short presentation, we will Review Dilution-based

More information

MPD Technique in Haynesville Shale Delivers Significant Value in Over Pressured Zones, A Case Study on Four Wells.

MPD Technique in Haynesville Shale Delivers Significant Value in Over Pressured Zones, A Case Study on Four Wells. AADE-11-NTCE-55 MPD Technique in Haynesville Shale Delivers Significant Value in Over Pressured Zones, A Case Study on Four Wells. Serkan Cenberlitas, Jim Crenshaw, and Ferhat Gumus, Weatherford International;

More information

A New and Simplified Method for Determination of Conductor Surface Casing Setting Depths in Shallow Marine Sediments (SMS)

A New and Simplified Method for Determination of Conductor Surface Casing Setting Depths in Shallow Marine Sediments (SMS) AADE-07-NTCE-41 A New and Simplified Method for Determination of Conductor Surface Casing Setting Depths in Shallow Marine Sediments (SMS) Paknejad, A., Texas A&M University; Schubert, J., Texas A&M University

More information

Hard or Soft Shut-in : Which is the Best Approach?

Hard or Soft Shut-in : Which is the Best Approach? HARD - SOFT shut-in? Hard or Soft Shut-in : Which is the Best Approach? March '93 INTRODUCTION There is now reasonable acceptance through-out the industry for the use of a hard shut-in procedure following

More information

Operations planning for optimal hole cleaning

Operations planning for optimal hole cleaning Operations planning for optimal hole cleaning Rev 1.0 14 th March 2004. Technical comments? info@kingdomdrilling.co.uk Page 1 Table of contents Operations planning for optimal hole cleaning... 1 Table

More information

SURFACE CASING SELECTION FOR COLLAPSE, BURST AND AXIAL DESIGN FACTOR LOADS EXERCISE

SURFACE CASING SELECTION FOR COLLAPSE, BURST AND AXIAL DESIGN FACTOR LOADS EXERCISE SURFACE CASING SELECTION FOR COLLAPSE, BURST AND AXIAL DESIGN FACTOR LOADS EXERCISE Instructions Use the example well data from this document or the powerpoint notes handout to complete the following graphs.

More information

OCEAN DRILLING PROGRAM

OCEAN DRILLING PROGRAM BIH OCEAN DRILLING PROGRAM www.oceandrilling.org Scientifi c Application Packers A packer is an inflatable rubber element that inflates to seal the annular space between the drill string and the borehole

More information

Understanding pressure and pressure

Understanding pressure and pressure CHAPTER 1 1-1 PRESSURE BASICS Remember to think downhole. The concepts provided in this section cover the foundations for good well control. Understanding pressure and pressure relationships is important

More information

"Sharing To Be Better. Influx through failed cement in shoetrack during completion operations

Sharing To Be Better. Influx through failed cement in shoetrack during completion operations "Sharing To Be Better Influx through failed cement in shoetrack during completion operations 2 Well status completion operations Seabed @ 364m 7" liner cemented across reservoir Well filled with 1.54 SG

More information

Abandonment Program for Paramount Fort Liard F 36

Abandonment Program for Paramount Fort Liard F 36 Abandonment Program for Paramount Fort Liard F 36 Well Name: Paramount et al Liard F 36 Area: 60 0 10 N, 123 0 15 W Location: Latitude: 60 0 05 27 Longitude: 123 0 22 00 UWI: 300F366010123150 WID: 1841

More information

Chapter 4 Key Findings. 4 Key Findings

Chapter 4 Key Findings. 4 Key Findings Chapter 4 Key Findings 211 4 Key Findings 212 Chapter 4 Key Findings This summarizes the key findings of the investigation team based on its extensive review of available information concerning the Macondo

More information

RPSEA UDW Forum June 22 & 23, Secure Energy for America

RPSEA UDW Forum June 22 & 23, Secure Energy for America RPSEA UDW Forum June 22 & 23, 2010 Secure Energy for America PROJECT TEAM RPSEA Operator Advisory Committee Anadarko Chevron Shell ConocoPhillips Subcontractors IntecSea NOV CTES General Marine Contractors

More information

Worked Questions and Answers

Worked Questions and Answers Worked Questions and Answers A Learning Document for prospective Candidates For the Rotary Drilling Well Control Test Programme Copyright, IWCF June 2000 Revision No.1, November 2000 IWCF 2000 page 1 of

More information

Well Control Drill Guide Example Only. Drill Guide is the list of drills, questions and attributes that are in DrillPad.

Well Control Drill Guide Example Only. Drill Guide is the list of drills, questions and attributes that are in DrillPad. Well Control Drill Guide Example Only Drill Guide is the list of drills, questions and attributes that are in DrillPad. This Well Control Drill Guide will be used in conjunction with the rig-specific well

More information

Practice Exam IADC WellSharp Driller and Supervisor

Practice Exam IADC WellSharp Driller and Supervisor Workover & Completion Day 4 1. In a workover operation of a shut in well a Lubricator is being used together with a Wireline BOP / Wireline Valve. Which Barrier is classified as the Primary Barrier? A.

More information

Investigation of Loss of Well Control Eugene Island Block 277 OCS-G Well A-2 Off the Louisiana Coast July 6, 2001

Investigation of Loss of Well Control Eugene Island Block 277 OCS-G Well A-2 Off the Louisiana Coast July 6, 2001 OCS Report MMS 2002-040 Investigation of Loss of Well Control Eugene Island Block 277 OCS-G 10744 Well A-2 Off the Louisiana Coast July 6, 2001 U.S. Department of the Interior Minerals Management Service

More information

RAILROAD COMMISSION OF TEXAS OIL WELL POTENTIAL TEST, COMPLETION OR RECOMPLETION REPORT, AND LOG

RAILROAD COMMISSION OF TEXAS OIL WELL POTENTIAL TEST, COMPLETION OR RECOMPLETION REPORT, AND LOG RAILROAD COMMISSION OF TEXAS 1701 N. Congress P.O. Box 12967 Austin, Texas 78701-2967 Status: Form W-2 OIL WELL POTENTIAL TEST, COMPLETION OR RECOMPLETION REPORT, AND LOG Date: Tracking No.: Approved 03/16/2016

More information

IWCF Equipment Sample Questions (Combination of Surface and Subsea Stack)

IWCF Equipment Sample Questions (Combination of Surface and Subsea Stack) IWCF Equipment Sample Questions (Combination of Surface and Subsea Stack) 1. Given the volumes below, how much hydraulic fluid will be required to carry out the following operations (no safety margin)?

More information

Optimising Hydraulic Energy to Dramatically Improve Lateral Reach

Optimising Hydraulic Energy to Dramatically Improve Lateral Reach Optimising Hydraulic Energy to Dramatically Improve Lateral Reach What Affects Reach? Build angle Size of completion CT size Drag Mechanical Fluid Debris in well BHA size End load CT size End load Buoyancy

More information

Coiled Tubing string Fatigue Management in High Pressure Milling Operation- Case Study

Coiled Tubing string Fatigue Management in High Pressure Milling Operation- Case Study Coiled Tubing string Fatigue Management in High Pressure Milling Operation- Case Study Abstract: Paper Presenter: Ebrahim Rabbani 1 e.rabbani@mehranservices.com Ebrahim Rabbani, Danial Davoodi 2, Fatemeh

More information

RAILROAD COMMISSION OF TEXAS OIL WELL POTENTIAL TEST, COMPLETION OR RECOMPLETION REPORT, AND LOG

RAILROAD COMMISSION OF TEXAS OIL WELL POTENTIAL TEST, COMPLETION OR RECOMPLETION REPORT, AND LOG RAILROAD COMMISSION OF TEXAS 1701 N. Congress P.O. Box 12967 Austin, Texas 78701-2967 Status: Form W-2 OIL WELL POTENTIAL TEST, COMPLETION OR RECOMPLETION REPORT, AND LOG Date: Tracking No.: Approved 06/29/2015

More information

Why Do Not Disturb Is a Safety Message for Well Integrity

Why Do Not Disturb Is a Safety Message for Well Integrity Why Do Not Disturb Is a Safety Message for Well Integrity Presented at the Practical Well Integrity Conference 9-10 December, 2014 in Houston By Ron Sweatman, Principal Advisor, Reservoir Development Services,

More information

IMPLEMENTATION DSIW-System ELDFISK ALPHA MARS 2011

IMPLEMENTATION DSIW-System ELDFISK ALPHA MARS 2011 IMPLEMENTATION DSIW-System ELDFISK ALPHA MARS 2011 Report: Wiping performance Pressure drop-rupture disc function-gas kick circulation Ketil Botnmark, Kjell Mikalsen 20.05.2011 This report resumes the

More information

JULY AUG 2010 INNOVATING WHILE DRILLING REGIONAL FOCUS: EUROPE & THE NORTH SEA

JULY AUG 2010 INNOVATING WHILE DRILLING REGIONAL FOCUS: EUROPE & THE NORTH SEA DRILLING C O N T R A C T O R OFFICIAL MAGAZINE OF THE INTERNATIONAL ASSOCIATION OF DRILLING S C O N T R A C T O R Multi-zone, expandable completions JULY AUG 2010 New technologies provide more options

More information