Figure 1 The LHC cryogenic islands and plants layout

Size: px
Start display at page:

Download "Figure 1 The LHC cryogenic islands and plants layout"

Transcription

1 The LHC cryogenic operation for first collisions and physics run Brodzinski K, Barth K, Benda V, Bremer J, Casas-Cubillos J, Claudet S, Delikaris D, Ferlin G, Fernandez Penacoba G, Perin A, Pirotte O, Soubiran M, Tavian L, van Weelderen R, Wagner U Technology Department, CERN, CH-1211 Geneva 23, Switzerland The Large Hadron Collider (LHC) cryogenic system was progressively and successfully run for the LHC accelerator operation period starting from autumn The paper recalls the cryogenic system architecture and main operation principles. The system stability during magnets powering and availability periods for high energy beams with first collisions at 3.5 TeV are presented. Treatment of typical problems, weak points of the system and foreseen future consolidations will be discussed. INTRODUCTION LHC CRYOGENIC SYSTEM ARCHITECTURE The Large Hadron Collider [1], successfully re-commissioned in 2009, makes an extensive use of superconducting magnets located in the underground tunnel of about 27-km length. The accelerator ring is divided into eight sectors, each of about 3.3 km long. The LHC cryogenic system is designed to reach an equivalent cooling power of 144 kw at 4.5 K and requires for operation about 130 tons of helium. Most of superconducting magnets are operated in superfluid helium at 1.9 K. The LHC refrigeration capacity is provided by using eight large cryogenic plants installed on five cryogenic islands which are placed around the LHC ring circumference see Figure 1. Because of the integration constrains and design optimization a part of the cryogenic plant equipment is installed on the surface and second part underground [2]. Figure 1 The LHC cryogenic islands and plants layout Each plant consist a warm compressor station, 4.5 K main refrigerator, 1.8 K refrigeration unit and makes use of a cryogenic interconnection box. A local helium distribution system allows for helium transfer between cryogenic equipments within a cryogenic plant area. To distribute the helium to the magnet cooling loops eight independent cryogenic distribution lines (QRL) are used [3]. The complete LHC cryogenic system architecture is presented in Figure 2. 1

2 Figure 2 The LHC cryogenic architecture OPERATIONAL STABILITY The cool down process consists of three main phases [4, 5]. The first phase from ambient temperature to 80 K is performed by vaporizing large quantities of liquid nitrogen which pre-cools the helium flow through the refrigerator towards sector. This phase takes now approximately 21 days with about 1200 t of liquid nitrogen consumption per sector. The second phase from 80 to 4.5 K is performed using the cooling capacity of the 4.5 K refrigerators. The last third phase from 4.5 K to 1.9 K is carried out using the cooling capacity of the 1.8 K refrigeration units. The LHC magnet temperature evolution from first cool down in 2007 to the first long term beam operation, particle collisions to the current physics run is presented in Figure 3. Figure 3 The LHC sector cool down and magnet temperature evolution between 2007 and

3 After more than one year of consolidation (due to the incident which took place on 19 September 2008 and caused damage to about 400 m of the accelerator [6]) the LHC was successfully re-commissioned and cooled to the nominal temperature. The temperature stability of the magnets operated with superfluid helium at 1.9 K remains within tolerance +10/-70 mk for the whole LHC. The gained experience over last 3 years and applied process optimizations, like improved sequencing and better use of the cooling capacity, allowed to reduce the total cool down time of one sector from 10 weeks to about 5 weeks. Following careful analysis CERN is confident that the present status of the LHC machine allows safe operation up to 50% of the nominal accelerator energy (present operation: 3.5 TeV per beam, nominal energy: 7 TeV per beam). This operation mode needs a reduced refrigeration capacity with respect to nominal operation. In order to minimize the electrical energy consumption, the cooling capacity for two sectors on cryogenic islands P6 and P8 may be provided by only one refrigeration plant. This is possible mainly by using redundant functions foreseen in the interconnection boxes. Stopping of two cryogenic plants allows to pull away the periodic maintenances of these installations. This optimization allows a saving of about 10 MW of the electrical power i.e CHF/day. Due to the specific architecture of P1 and P1.8 as well as to higher load at P4 related to the RF cavities cooling, the reduced refrigeration scheme cannot be applied for these cryogenic islands. AVAILABILITY The electrical powering of the superconducting magnets and by consequence the accelerator operation depends strongly on provided cryogenic conditions of different machine equipment. The LHC cryogenic availability is defined by two conditions: Cryo Start (CS) and Cryo Maintain (CM). CS allows to start the electrical circuits powering, CM allows to keep the LHC equipment electrically powered. The CS and CM conditions depends on operation limits defined for different cryogenic equipment e.g. liquid helium level in electrical feedboxes, maximum and minimum pressures or temperatures in the RF cavities or magnets etc. The limits are stricter for CS condition see Figures 4a and 4b. The requirements to obtain correct CS and CM conditions are defined for single cryogenic equipment and for specific groups of equipments such as e.g. a sector. The loss of one single CS causes loss of general CS condition in which it contributes (cascade principle). There are about 3500 single CS/CM conditions affecting the LHC operation. Figure 4a Simple CS and CM indicator Figure 4b Cryogenic availability for electrical powering with different CS and CM statuses. When discussing the cryogenic availability for the accelerator operation, more attention is paid on the continuity of CM condition. The CS has to be ensured only for starting period and then is more used as the system stability diagnostics. Simple loss of CS condition is automatically phone-reported to the cryogenic operator. The loss of CM condition leads to direct slow discharge of electrical circuits and consequently to dump of the beam (if any). The curves in Figure 5 present the cryogenic availability in terms of CM condition. Over last 6-month period the weekly availability increased from ~50% to ~90% and monthly availability from ~45% to ~85% (including periodical technical stops needed to perform the necessary machine 3

4 maintenance). This good system behaviour is a result of operation experience return as well as periodic corrective and preventive maintenance executed on the cryogenic equipment. The availability calculation is done for all eight LHC sectors. Single weekly sector availability is about 98.5% what gives a total weekly LHC cryogenics availability at about 90%. Figure 5 The cryogenic availability for the LHC physics over last 6-month period TYPICAL PROBLEMS AND THEIR TREATMENT The cryogenic operation of the LHC gives currently a very good feedback in terms of the process stability and availability for the beam operation. Nevertheless the plants still have to face with different operation difficulties. A few examples of typical problems or failures are presented and discussed below. Instrumentation failures The LHC cryogenic system is equipped with about thermometers, ~700 pressure transducers, ~500 level transducers, ~1400 cryogenic control valves, ~2500 electrical heaters and other instrumentation like flow meters or current lead valves. The observed progressive degradation of the instrumentation is followed by the operation team and instrumentation experts. The repair of the defective instrumentation is done periodically during the accelerator technical stops, with exceptions of the indispensable instrumentation failures which are repaired as soon as possible. The most frequent instrumentation failures are related to the electronic cards. Since the beginning of 2008 about 140 cards have been replaced what gives about 1% of the total instrumentation inventory. The replacement was done mostly on the beginning of the operation period treating starting weaknesses. Cold compressor filter clogging The function of the 1.8 K refrigeration units (QURC) is to pump on helium bath to guaranty a saturation temperature of 1.8 K. The very low pressure pumping line is working at ~16 mbar and has a length of ~ 3.3 km per sector. In order to protect the cold compressor itself from any impurities, helium guard systems have been put in place on all sensitive interfaces with the atmospheric pressure. Nevertheless a small part of the system, some small fully joint welded pipes or capillaries connecting low pressure line with diagnostics, calibration or purge ports, have a direct surrounding of the atmospheric pressure creating potential risk of the impurities aspiration. In order to protect the cold compressor inlet from any type of the impurities dedicated filters are installed upstream of the cold compressor station on each cryogenic plant. The progressive clogging 4

5 of these filters was observed due to unexpected entry of air impurities. Such impurities cause increase of the pressure drop over the filters and consequently increase of the magnet temperature. The periodic cleaning of the filters was required by means of local warm helium circulation. The increase of the temperature to about 80 K is enough to clean completely the filter. This type of cleaning requires the stop of the QURC and creates additional unavailability. The time related to the filter cleaning and recovery of the nominal conditions is about hours. The evolution of all QURC filters clogging over last few months period is presented in Figure 6. Figure 6 QURCs filter blockage over last 6-month period During periodical technical stops dedicated to machine maintenance the problem of the QURC filters clogging was progressively resolved on all LHC cryogenic plants see evolution on Figure 6. The present filters autonomies (max. allowable filter pressure drop is 15 mbar) is about 10 weeks, what is fully compatible with regular technical stops scheduled presently every 6 weeks. Further improvements are underway. Helium losses The helium losses since the first cool down in 2007 are estimated at about 40 t/year. This gives about 30% of the total LHC inventory and remains within the estimates: 50% of the total inventory during commissioning time and 25% during stable operation. The investigation and related actions to minimize the losses are underway. Electrical feedbox valves Another hardware problem of the LHC cryogenics appeared in the control of the cooling helium flow of the current leads. There are 1258 current leads in the LHC. Each lead is equipped with a valve which controls its cooling flow. The design of the valves turned out to be not adapted for LHC application already during the commissioning period. After a few weeks of operation, some of the valves develop excessive friction in the valve bearings, which makes difficult and in some cases impossible to achieve the control requirements. To follow the degradation and treat the problem with minimum impact on the availability a special valve degradation road map has been created. The road map includes 4 steps with corresponding instructions how to mitigate the effects of the progressive valves degradation. The main action is to apply specific PID parameters to the valve controller. This solution is applicable for the valves classified at step 1, 2 and 3 on the degradation roadmap. The actions for the first 3 steps can be performed without field 5

6 intervention, directly from the control system without any impact on the operational availability. The valves that reach degradation step 3 are classified to be replaced during the nearest technical stop. When the actions on the control parameters are not sufficient, before replacing the valve, an intermediate step involves a special hardware tuning of the valve electronics. This solution was validated but until now it was never applied as all cases could be treated at the control system level. In parallel to the mentioned short term treatment, the progressive definitive replacement of the valves with a new design is planned. A few valves with the new, friction free, design were tested with very good response in real LHC operation since February The general evaluation of the valves degradation is presented in Figure 7. Figure 7 The DFB valves degradation evolution over last 16-week period CONCLUSIONS The LHC cryogenic operation is successfully running since autumn The first long term operation with maximum beam energy of 3.5 TeV as well as related collisions has no visible impact on the cryogenic system stability and availability. The thermal stability is provided within tolerance +10/-70 mk regarding all LHC 1.9 K magnets (still being improved). After a few weeks of operation the weekly availability reached the target of 90% and remains at this level within ~5% of tolerance. For the time being, the periodical technical stops of 3-4 days duration are needed each 4-6 weeks in order to perform the necessary maintenance of the LHC technical systems including cryogenics to guaranty maximum availability during foreseen operation periods and physics run. The very positive response of the cryogenic system let us hope for reliable long time operation of the system with present beam energy and also for the future run at nominal beam and collision parameters. REFERENCES 1. LHC Design Report, CERN Claudet S., Design, construction, installation and first commissioning results of the LHC cryogenic system, 10 th European Particle Accelerator Conference, Edinburgh 2006, United Kingdom. 3. Brodzinski K., Chorowski M., Ciechanowski M., Fluder C., Fydrych J. et al., Reception tests of the cryogenic distribution line for the Large Hadron Collider, 21th International Cryogenic Engineering Conference, Praha 2006, Czech Republic. 4. Liu L., Riddone G., Serio L. And Tavian L., Cooldown of the first sector of the Large Hadron Collider: comparison between mathematical model and measurements, 2007 Cryogenic Engineering Conference and International Cryogenic Materials Conference, Chattanooga, Tennessee, USA. 5. Serio L., Bouillot A., Casas-Cubillos et al., Validation and performance of the cryogenic system through commissioning of the first sector, 2007 Cryogenic Engineering Conference and International Cryogenic Materials Conference, Chattanooga, Tennessee, USA. 6. Report of the Task Force on the incident of 19 th September 2008 at the LHC, CERN-LHC-PROJECT-Report

EXPERIENCE WITH A PRE-SERIES SUPERFLUID HELIUM TEST BENCH FOR LHC MAGNETS

EXPERIENCE WITH A PRE-SERIES SUPERFLUID HELIUM TEST BENCH FOR LHC MAGNETS EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH European Laboratory for Particle Physics Large Hadron Collider Project LHC Project Report 388 EXPERIENCE WITH A PRE-SERIES SUPERFLUID HELIUM TEST BENCH FOR LHC

More information

PRELIMINARY RISK ANALYSIS OF THE LHC CRYOGENIC SYSTEM

PRELIMINARY RISK ANALYSIS OF THE LHC CRYOGENIC SYSTEM EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH European Laboratory for Particle Physics Large Hadron Collider Project LHC Project Report 324 PRELIMINARY RISK ANALYSIS OF THE LHC CRYOGENIC SYSTEM M. Chorowski,

More information

QUALIFICATION OF SUB-ATMOSPHERIC PRESSURE SENSORS FOR THE CRYOMAGNET BAYONET HEAT EXCHANGERS OF THE LARGE HADRON COLLIDER

QUALIFICATION OF SUB-ATMOSPHERIC PRESSURE SENSORS FOR THE CRYOMAGNET BAYONET HEAT EXCHANGERS OF THE LARGE HADRON COLLIDER EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH European Laboratory for Particle Physics Large Hadron Collider Project LHC Project Report 980 QUALIFICATION OF SUB-ATMOSPHERIC PRESSURE SENSORS FOR THE CRYOMAGNET

More information

The LHC Cryogenic System and Operational Experience from the First Three Years Run

The LHC Cryogenic System and Operational Experience from the First Three Years Run Focused Review The LHC Cryogenic System and Operational Experience from the First Three Years Run Dimitri DELIKARIS *1 and Laurent TAVIAN *2 Synopsis: The LHC (Large Hadron Collider) accelerator helium

More information

SUMMARY OF THE EXPERIMENTAL STUDIES OF COLD HELIUM PROPAGATION ALONG A SCALE MODEL OF THE LHC TUNNEL

SUMMARY OF THE EXPERIMENTAL STUDIES OF COLD HELIUM PROPAGATION ALONG A SCALE MODEL OF THE LHC TUNNEL EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH European Laboratory for Particle Physics Large Hadron Collider Project LHC Project Report 684 SUMMARY OF THE EXPERIMENTAL STUDIES OF COLD HELIUM PROPAGATION ALONG

More information

REVIEW OF THE CONSOLIDATION WORKS SCHEDULED FOR THE LHC CRYOGENIC INSTALLATIONS DURING A LONG SHUTDOWN

REVIEW OF THE CONSOLIDATION WORKS SCHEDULED FOR THE LHC CRYOGENIC INSTALLATIONS DURING A LONG SHUTDOWN REVIEW OF THE CONSOLIDATION WORKS SCHEDULED FOR THE LHC CRYOGENIC INSTALLATIONS DURING A LONG SHUTDOWN O. Pirotte, on behalf of the CRG group, CERN, Geneva, Switzerland. Abstract The operation of the LHC

More information

Status on the DFBXF commissioning

Status on the DFBXF commissioning Status on the DFBXF commissioning Cryogenic Performance Panel C. Darve March 28th 2008 1 Procedure steps and checks Based on S78 commissioning (R. Rabehl 05 July 2007): Cool-down part 1 (cool-down from

More information

Available online at ScienceDirect. Physics Procedia 67 (2015 )

Available online at   ScienceDirect. Physics Procedia 67 (2015 ) Available online at www.sciencedirect.com ScienceDirect Physics Procedia 67 (2015 ) 1074 1082 25th International Cryogenic Engineering Conference and the International Cryogenic Materials Conference in

More information

RECENT PROGRESS IN POWER REFRIGERATION BELOW 2 K FOR SUPERCONDUCTING ACCELERATORS

RECENT PROGRESS IN POWER REFRIGERATION BELOW 2 K FOR SUPERCONDUCTING ACCELERATORS RECENT PROGRESS IN POWER REFRIGERATION BELOW 2 K FOR SUPERCONDUCTING AELERATORS S. Claudet, CERN, Geneva, Switzerland Abstract As a result of technico-economical optimization and quest for increased performance,

More information

Cryogenic Benches for Superfluid Helium Testing of Full-Scale Prototype Superconducting Magnets for the CERN LHC Project

Cryogenic Benches for Superfluid Helium Testing of Full-Scale Prototype Superconducting Magnets for the CERN LHC Project neun ~ R Y W EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH hk. R I+ 9 CERN LIBRARIES, GENEVA POO024685 CERN MT/94-02 LHC Note 275 Cryogenic Benches for Superfluid Helium Testing of Full-Scale Prototype Superconducting

More information

LARGE CRYOGENIC SYSTEMS AT 1.8 K

LARGE CRYOGENIC SYSTEMS AT 1.8 K LARGE CRYOGENIC SYSTEMS AT.8 K L. Tavian, CERN, Geneva, Switzerland Abstract Cryogenics is now widely present in large accelerator projects using applied superconductivity. Economical considerations permanently

More information

DEVELOPMENT OF LARGE-CAPACITY REFRIGERATION AT 1.8 K FOR THE LARGE HADRON COLLIDER AT CERN. Philippe Lebrun*, Laurent Tavian*, Gérard Claudet**

DEVELOPMENT OF LARGE-CAPACITY REFRIGERATION AT 1.8 K FOR THE LARGE HADRON COLLIDER AT CERN. Philippe Lebrun*, Laurent Tavian*, Gérard Claudet** EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH European Laboratory for Particle Physics Large Hadron Collider Project LHC Project Report 6 DEVELOPMENT OF LARGE-CAPACITY REFRIGERATION AT 1.8 K FOR THE LARGE

More information

Safety in Cryogenic Operations at RHIC *

Safety in Cryogenic Operations at RHIC * Safety in Cryogenic Operations at RHIC * Anthony Nicoletti, Dewey Lederle, Ahmed Sidi-Yehklef, Tom Tallerico, Roberto Than, Joe Tuozzolo Collider-Accelerator Department Brookhaven National Laboratory Upton,

More information

European Organization for Nuclear Research - Organisation européenne pour la recherche nucléaire

European Organization for Nuclear Research - Organisation européenne pour la recherche nucléaire European Organization for Nuclear Research - Organisation européenne pour la recherche nucléaire Safety Task Force SC, BE, EN, PH, TE, Staff Ass. [CERN-ATS-2009-002] External Advisory Committee [CERN-ATS-2009-003]

More information

Jaime Perez Espinos on behalf of all contributors to LHC insulation vacuum (TE/VSC, AL4030 and ICIT)

Jaime Perez Espinos on behalf of all contributors to LHC insulation vacuum (TE/VSC, AL4030 and ICIT) OLAV IV Jaime Perez Espinos on behalf of all contributors to LHC insulation vacuum (TE/VSC, AL4030 and ICIT) Contents Before LS1 Introduction to LS1 LHC insulation vacuum system overview LS1 activities

More information

RHIC CRYOGENIC SYSTEMS MAINTENANCE PROGRAM

RHIC CRYOGENIC SYSTEMS MAINTENANCE PROGRAM RHIC CRYOGENIC SYSTEMS MAINTENANCE PROGRAM Brookhaven National Laboratory Major Plant Equipment Categories / Locations Compressor Refrigerator Service Buildings The Maintenance program is based on the

More information

MODIFICATION OF THE LHC VENTILATION SYSTEM

MODIFICATION OF THE LHC VENTILATION SYSTEM MODIFICATION OF THE LHC VENTILATION SYSTEM M. Nonis EN/CV INTRODUCTION The aim of the present document is to review the current LHC ventilation configuration and evaluate the need to modify part of the

More information

CO 2. (R744) Service Station Presentation. Contents. Goals Basic functions Specification Recovery R477 Vacuum Charge Safety Other features Prototype

CO 2. (R744) Service Station Presentation. Contents. Goals Basic functions Specification Recovery R477 Vacuum Charge Safety Other features Prototype (R744) Service Station Presentation Contents Goals Basic functions Specification Recovery R477 Vacuum Charge Safety Other features Prototype Page 1 (R744) Service Station Goals Usability Full automatic

More information

SUMMARY AND RESULTS OF THE CRYOPLANT OPERATION FOR HERA

SUMMARY AND RESULTS OF THE CRYOPLANT OPERATION FOR HERA Proceedings of ICEC 22-ICMC 2008, edited by Ho-Myung CHANG et al. c 2009 The Korea Institute of Applied Superconductivity and Cryogenics 978-89-957138-2-2 SUMMARY AND RESULTS OF THE CRYOPLANT OPERATION

More information

LAr Filling and Commissioning of Cryogenics

LAr Filling and Commissioning of Cryogenics LAr Filling and Commissioning of Cryogenics K.T.Knöpfle MPI Kernphysik, Heidelberg ktkno@mpi-hd.mpg.de GERDA Collaboration Meeting at LNGS 28-30 September 2009 2 3 General conditions for cool down & filling

More information

First Experimental Data of the Cryogenic Safety Test Facility PICARD

First Experimental Data of the Cryogenic Safety Test Facility PICARD First Experimental Data of the Cryogenic Safety Test Facility PICARD C. Heidt, A. Henriques, M. Stamm and S. Grohmann 26 th International Cryogenic Engineering Conference 2016 in New Delhi, India KIT,

More information

Cooling Strings of Superconducting Devices below 2 K: The Helium II Bayonet Heat Exchanger. Ph. Lebrun, L. Serio, L. Tavian and R.

Cooling Strings of Superconducting Devices below 2 K: The Helium II Bayonet Heat Exchanger. Ph. Lebrun, L. Serio, L. Tavian and R. EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH European Laboratory for Particle Physics Large Hadron Collider Project LHC Project Report 144 Cooling Strings of Superconducting Devices below 2 K: The Helium

More information

Magnet and RF Cavity Test Stand Design. Tom Peterson, SLAC USPAS January, 2017

Magnet and RF Cavity Test Stand Design. Tom Peterson, SLAC USPAS January, 2017 Magnet and RF Cavity Test Stand Design, SLAC Outline Test dewars and test stands Saturated bath test dewars Double bath test dewars SRF test cryostats SRF cryomodule test stands Horizontal magnet test

More information

Series Environmental Chambers

Series Environmental Chambers 3119-600 Series Environmental Chambers Challenges in Non-Ambient Testing Testing at non-ambient temperatures adds another layer of challenges to your testing laboratory. Ensuring you get accurate and stable

More information

3-Stage ADR for the SXS Instrument on the Astro-H Mission

3-Stage ADR for the SXS Instrument on the Astro-H Mission National Aeronautics and Space Administration 3-Stage for the SXS Instrument on the Astro-H Mission Peter Shirron, Mark Kimball, Donald Wegel, Edgar Canavan, and Michael DiPirro NASA/Goddard Space Flight

More information

Short Introduction to Cryo-Pumps and Refrigerators. Dr Graham Rogers Leybold UK Ltd.

Short Introduction to Cryo-Pumps and Refrigerators. Dr Graham Rogers Leybold UK Ltd. Short Introduction to Cryo-Pumps and Refrigerators Dr Graham Rogers Leybold UK Ltd. Cryo Pumps Topics Physical principles of cryo-pumping Design and control of modern refrigerator cryo-pumps UHV and XHV

More information

PRELIMINARY PIPE STRESS ANALYSIS OF HIGH PRESSURE, HIGH TEMPERATURE EXPERIMENTAL HELIUM COOLING SYSTEM

PRELIMINARY PIPE STRESS ANALYSIS OF HIGH PRESSURE, HIGH TEMPERATURE EXPERIMENTAL HELIUM COOLING SYSTEM A.K. VERMA, B.K. YADAV, A. GANDHI, A. SARASWAT, S. VERMA, E.R. KUMAR PRELIMINARY PIPE STRESS ANALYSIS OF HIGH PRESSURE, HIGH TEMPERATURE EXPERIMENTAL HELIUM COOLING SYSTEM A.K.VERMA Institute for Plasma

More information

ANNEX AMENDMENTS TO THE INTERNATIONAL CODE FOR FIRE SAFETY SYSTEMS (FSS CODE) CHAPTER 15 INERT GAS SYSTEMS

ANNEX AMENDMENTS TO THE INTERNATIONAL CODE FOR FIRE SAFETY SYSTEMS (FSS CODE) CHAPTER 15 INERT GAS SYSTEMS Annex 3, page 2 ANNEX AMENDMENTS TO THE INTERNATIONAL CODE FOR FIRE SAFETY SYSTEMS (FSS CODE) CHAPTER 15 INERT GAS SYSTEMS The text of existing chapter 15 is replaced by the following: "1 Application This

More information

A Brief Introduction to Helium Liquefaction At ITER

A Brief Introduction to Helium Liquefaction At ITER ITER Cryogenic System LHe PLANTS A Brief Introduction to Helium Liquefaction At ITER ITER Organization PLANT ENGINEERING DIVISION CRYOGENIC SECTION LHe PLANTS TRO: Eric FAUVE A Brief Introduction to to

More information

FUNDAMENTAL SAFETY OVERVIEW VOLUME 2: DESIGN AND SAFETY CHAPTER I: AUXILIARY SYSTEMS. A high-capacity EBA system [CSVS] [main purge]

FUNDAMENTAL SAFETY OVERVIEW VOLUME 2: DESIGN AND SAFETY CHAPTER I: AUXILIARY SYSTEMS. A high-capacity EBA system [CSVS] [main purge] PAGE : 1 / 9 5. CONTAINMENT PURGE (EBA [CSVS]) The Reactor Building purge system comprises the following: A high-capacity EBA system [CSVS] [main purge] A low-capacity EBA system [CSVS] [mini-purge] 5.1.

More information

Spallation target cryogenic cooling design challenges at the European Spallation Source

Spallation target cryogenic cooling design challenges at the European Spallation Source IOP Conference Series: Materials Science and Engineering PAPER OPEN ACCESS Spallation target cryogenic cooling design challenges at the European Spallation Source To cite this article: J Jurns et al 2015

More information

MECHANICAL EQUIPMENTS: COMPRESSORS, PUMPS, SEALS, SPEED DRIVES, CONTROL VALVES & ACTUATORS & SAFETY RELIEF VALVES

MECHANICAL EQUIPMENTS: COMPRESSORS, PUMPS, SEALS, SPEED DRIVES, CONTROL VALVES & ACTUATORS & SAFETY RELIEF VALVES Training Title MECHANICAL EQUIPMENTS: COMPRESSORS, PUMPS, SEALS, SPEED DRIVES, CONTROL VALVES & ACTUATORS & SAFETY RELIEF VALVES Training Duration 5 days Training Venue and Dates REF Mechanical Equipments:

More information

Proposal for the Cryogenic Supply of a Single TTF / FEL - Cryomodule Test Bench

Proposal for the Cryogenic Supply of a Single TTF / FEL - Cryomodule Test Bench Proposal for the Cryogenic Supply of a Single TTF / FEL - Cryomodule Test Bench TESLA Report No. 2001-09 W.D.Moeller, B.Petersen, B.Sparr Deutsches Elektronen Synchrotron Abstract A test bench for the

More information

FAILURE SCENARIOS AND MITIGATIONS FOR THE BABAR SUPERCONDUCTING SOLENOID

FAILURE SCENARIOS AND MITIGATIONS FOR THE BABAR SUPERCONDUCTING SOLENOID SLAC-PUB-11601 December 2005 FAILURE SCENARIOS AND MITIGATIONS FOR THE BABAR SUPERCONDUCTING SOLENOID EunJoo Thompson, A. Candia, W. W. Craddock, M. Racine, J. G. Weisend II Stanford Linear Accelerator

More information

Fermilab MTF Cryogenic System & Vertical RF Cavity Test Facility. Yuenian Huang, on behalf of Fermilab, TD/TID May 11, 2006

Fermilab MTF Cryogenic System & Vertical RF Cavity Test Facility. Yuenian Huang, on behalf of Fermilab, TD/TID May 11, 2006 Fermilab MTF Cryogenic System & Vertical RF Cavity Test Facility Yuenian Huang, on behalf of Fermilab, TD/TID May 11, 2006 1 Magnet Test Facility (MTF) Tevatron magnet test stands Testing temperature range

More information

INTRODUCTION. The Quantum Technology system has the following advantages:, as it does not need plastic gas-bags which are volume-consuming,

INTRODUCTION. The Quantum Technology system has the following advantages:, as it does not need plastic gas-bags which are volume-consuming, 1 INTRODUCTION Quantum Technology is a leading scientific equipment supplier. For the last thirty years we served our customers by tailoring our products to each customer s unique requirements. Quantum

More information

AC : MEASUREMENT OF HYDROGEN IN HELIUM FLOW

AC : MEASUREMENT OF HYDROGEN IN HELIUM FLOW AC 2010-2145: MEASUREMENT OF HYDROGEN IN HELIUM FLOW Randy Buchanan, University of Southern Mississippi Christopher Winstead, University of Southern Mississippi Anton Netchaev, University of Southern Mississippi

More information

Oil-Lubricated Compressors for Regenerative Cryocoolers Using an Elastic Membrane

Oil-Lubricated Compressors for Regenerative Cryocoolers Using an Elastic Membrane Oil-Lubricated Compressors for Regenerative Cryocoolers Using an Elastic Membrane E.C. Luo, Z.H. Wu, G.Y. Yu, J.Y. Hu, and W. Dai Technical Institute of Physics and Chemistry Chinese Academy of Sciences

More information

RC102 & RC110 Sample in Vacuum Continuous Flow Cryogenic Workstation Cryostats

RC102 & RC110 Sample in Vacuum Continuous Flow Cryogenic Workstation Cryostats RC102 & RC110 Sample in Vacuum Continuous Flow Cryogenic Workstation Cryostats www.cryoindustries.com INDUSTRIES RC102 & RC110 Sample in Vacuum Continuous Flow Cryogenic Workstation Cryostats Designed

More information

High Efficiency SO2 Scrubber Design to Reduce Caustic Consumption

High Efficiency SO2 Scrubber Design to Reduce Caustic Consumption High Efficiency SO2 Scrubber Design to Reduce Caustic Consumption Paper # 35 Andrew C. Bartocci Envitech, Inc. 2924 Emerson Street- Suite 320 San Diego, CA 92106 Ph: 619-223-9925, ext. 203 ABSTRACT An

More information

Improve Reliability of Turbomachinery Lubrication and Sealing Systems

Improve Reliability of Turbomachinery Lubrication and Sealing Systems Improve Reliability of Turbomachinery Lubrication and Sealing Systems Fisher Pressure Control Solutions For Turbomachinery Applications Protect the integrity of your Turbomachinery support system Turbomachinery

More information

Helium recovery at the National High Magnetic Field Laboratory

Helium recovery at the National High Magnetic Field Laboratory IOP Conference Series: Materials Science and Engineering PAPER OPEN ACCESS Helium recovery at the National High Magnetic Field Laboratory Related content - Helium recovery and purification at CHMFL J Li,

More information

Hazard Operability Analysis

Hazard Operability Analysis Hazard Operability Analysis Politecnico di Milano Dipartimento di Energia HAZOP Qualitative Deductive (search for causes) Inductive (consequence analysis) AIM: Identification of possible process anomalies

More information

Design of Relief Valves/Devices/Systems for Cryogenic Apparatuses and Installations

Design of Relief Valves/Devices/Systems for Cryogenic Apparatuses and Installations Design of Relief Valves/Devices/Systems for Cryogenic Apparatuses and Installations Fridolin Holdener fridolin.holdener@shirokuma-gmbh.ch CERN Cryogenic Safety - HSE Seminar 21-22 September 2016 Agenda

More information

Title: Choosing the right nitrogen rejection scheme

Title: Choosing the right nitrogen rejection scheme Title: Choosing the right nitrogen rejection scheme Authors: Nicolas Chantant, Paul Terrien, Sylvain Gérard (Air Liquide Global E&C Solutions) Abstract: Nitrogen Rejection Units (NRU) are used to extract

More information

D R A F T. Operating Procedures for the NPDGamma Liquid Hydrogen Target at the BL 13. Version 1.00

D R A F T. Operating Procedures for the NPDGamma Liquid Hydrogen Target at the BL 13. Version 1.00 D R A F T Operating Procedures for the NPDGamma Liquid Hydrogen Target at the BL 13 Version 1.00 October 06, 2010 Operating Procedures for the NPDGamma Liquid Hydrogen Target V1.00 6/10/10 2 Table of Content

More information

2600T Series Pressure Transmitters Plugged Impulse Line Detection Diagnostic. Pressure Measurement Engineered solutions for all applications

2600T Series Pressure Transmitters Plugged Impulse Line Detection Diagnostic. Pressure Measurement Engineered solutions for all applications Application Description AG/266PILD-EN Rev. C 2600T Series Pressure Transmitters Plugged Impulse Line Detection Diagnostic Pressure Measurement Engineered solutions for all applications Increase plant productivity

More information

Measurement And Control Appreciation

Measurement And Control Appreciation Measurement And Control Appreciation Course Content Aim To provide an appreciation of the operation and application of process plant instrumentation used for the measurement and display of the main process

More information

Cryogenics of SRF Spoke Cavity Development at SMTF

Cryogenics of SRF Spoke Cavity Development at SMTF Cryogenics of SRF Spoke Cavity Development at SMTF Michael White SRF Development Technical Division Fermi National Accelerator Laboratory May 11, 2006 Overview of Topics SMTF Overview CTF Cryogen Supply

More information

Bulletin TCR-104 & 109 Filling and adding to the Glycol pressure system

Bulletin TCR-104 & 109 Filling and adding to the Glycol pressure system Bulletin 061013 TCR-104 & 109 Filling and adding to the Glycol pressure system 1. Glycol System and air On this model the glycol system is a closed system, the glycol is not exposed to the air. No external

More information

PRC CO ² -LASER PRESENTATION

PRC CO ² -LASER PRESENTATION Page 1 of 7 PRC CO ² -LASER PRESENTATION GENERAL CHARACTERISTICS - Embedded PC104 Electronics with exchangeable software allowing very easy integration of customer specified functions: such as eg. specific

More information

Cryogenics The Basics. Lesson 2 D. Kashy

Cryogenics The Basics. Lesson 2 D. Kashy Cryogenics The Basics Lesson 2 D. Kashy Lecture 1 Review Lesson 1 - Objectives Looked at common liquids and gases to get a feeling for their properties Looked at Nitrogen and Helium Discussed Pressure

More information

Microscopy Cryogenic WORKSTATION. Performance by Design

Microscopy Cryogenic WORKSTATION. Performance by Design CRYO Microscopy Cryogenic WORKSTATION Optical cryostat for use in microscopy and spectroscopy Performance by Design RC102-CFM Microscopy Cryostat offers fast cooldown, high efficiency, excellent temperature

More information

Vacuum Systems and Cryogenics for Integrated Circuit Fabrication Technology 01

Vacuum Systems and Cryogenics for Integrated Circuit Fabrication Technology 01 INAOE. Tonantzintla, Mexico. 2010-06-23. June 23 rd, 2010 Vacuum Systems and Cryogenics for Integrated Circuit Fabrication Technology 01 Joel Molina INAOE Microelectronics Group jmolina@inaoep.mx 1 Vacuum

More information

Overview of Earlier Lecture

Overview of Earlier Lecture 4 1 Overview of Earlier Lecture Hydrogen Helium Phase Diagram of Helium Super fluid Helium 2 Outline of the Lecture Uses of Helium 4 Thermomechanical, Mechanocaloric, Fountain, Rollin Film Effects. Sound

More information

RICK FAUSEL, BUSINESS DEVELOPMENT ENGINEER TURBOMACHINERY CONTROL SYSTEM DESIGN OBJECTIVES

RICK FAUSEL, BUSINESS DEVELOPMENT ENGINEER TURBOMACHINERY CONTROL SYSTEM DESIGN OBJECTIVES RICK FAUL, BUSINESS DEVELOPMENT ENGINEER TURBOMACHINERY CONTROL SYSTEM DESIGN OBJECTIVES The primary design objective for any turbomachinery control system should be to maintain or maximize machine and

More information

WMO LABORATORY INTERCOMPARISON OF RAIN INTENSITY GAUGES

WMO LABORATORY INTERCOMPARISON OF RAIN INTENSITY GAUGES WMO LABORATORY INTERCOMPARISON OF RAIN INTENSITY GAUGES Christophe ALEXANDROPOULOS and Muriel LACOMBE Météo-France, Direction des Systèmes d Observation, BP 202-78195 Trappes France christophe.alexandropoulos@meteo.fr

More information

LESER Deutschland Standard Functional Tightness Test (Cryo) Content

LESER Deutschland Standard Functional Tightness Test (Cryo) Content Page 1/10 Content 1 Purpose... 1 2 Scope... 1 3 Range of Application... 1 4 Normative Background... 2 5 Terms and Definitions... 2 6 Test Equipment... 3 7 Test Procedure... 5 8 Acceptance Criteria... 8

More information

ESS SPOKE CRYOMODULE AND TEST VALVE BOX

ESS SPOKE CRYOMODULE AND TEST VALVE BOX ESS SPKE CRYMDULE AND TEST VALVE BX Denis Reynet, Sylvain Brault, Patxi Duthil, Matthieu Pierens, Patricia Duchesne, Guillaume lry, Nicolas Gandolfo, Emmanuel Rampnoux, Sébastien Bousson, IPN, UMR 8608

More information

Research of Variable Volume and Gas Injection DC Inverter Air Conditioning Compressor

Research of Variable Volume and Gas Injection DC Inverter Air Conditioning Compressor Purdue University Purdue e-pubs International Compressor Engineering Conference School of Mechanical Engineering 2016 Research of Variable Volume and Gas Inection DC Inverter Air Conditioning Compressor

More information

Refrigeration Plants for the SSC

Refrigeration Plants for the SSC h. 5 i : i \ d Refrigeration Plants for the SSC c.>/

More information

The Discussion of this exercise covers the following points: Range with an elevated or suppressed zero Suppressed-zero range Elevated-zero range

The Discussion of this exercise covers the following points: Range with an elevated or suppressed zero Suppressed-zero range Elevated-zero range Exercise 4-3 Zero Suppression and Zero Elevation EXERCISE OBJECTIVE In this exercise, you will learn the effect that mounting a pressure transmitter above or below the reference level has on the hydrostatic

More information

UNITY 2 TM. Air Server Series 2 Operators Manual. Version 1.0. February 2008

UNITY 2 TM. Air Server Series 2 Operators Manual. Version 1.0. February 2008 UNITY 2 TM Air Server Series 2 Operators Manual Version 1.0 February 2008 1. Introduction to the Air Server Accessory for UNITY 2...2 1.1. Summary of Operation...2 2. Developing a UNITY 2-Air Server method

More information

DeZURIK. KGC Cast Knife Gate Valve. Safety Manual

DeZURIK. KGC Cast Knife Gate Valve. Safety Manual KGC Cast Knife Gate Valve Safety Manual Manual D11036 August 29, 2014 Table of Contents 1 Introduction... 3 1.1 Terms... 3 1.2 Abbreviations... 4 1.3 Product Support... 4 1.4 Related Literature... 4 1.5

More information

SHELL FLAGS INSPECTION CASE STUDY

SHELL FLAGS INSPECTION CASE STUDY SHELL FLAGS INSPECTION CASE STUDY J. Nonemaker, Solution Engineer, ROSEN T. Steinvoorte, Business Development, ROSEN R. Subramanian, Pipelines & Subsea Technical Support Engineer, Shell U.K. Limited Introduction

More information

AIR BEARINGS IN HIGH PRECISION SYSTEMS

AIR BEARINGS IN HIGH PRECISION SYSTEMS AIR BEARINGS IN HIGH PRECISION SYSTEMS I. Crăcăoanu 1 and F. Bremer 1 1 Royal Philips Electronics, Philips Innovation Services, Eindhoven, The Netherlands Abstract: In high precision system applications

More information

M-06 Nitrogen Generator (Nitrogen Making Machine)

M-06 Nitrogen Generator (Nitrogen Making Machine) Guideline No.M-06 (201510) M-06 Nitrogen Generator (Nitrogen Making Machine) Issued date: 20 th October, 2015 China Classification Society Foreword This Guideline is a part of CCS Rules, which contains

More information

ALICE SPD cooling system

ALICE SPD cooling system ALICE SPD cooling system Requirements: To remove a nominal power of 1380 W distributed per 60 staves (cooling channels) at a nominal duct temperature of C 1 To ensure as much as possible a temperature

More information

Maintenance handbook

Maintenance handbook Maintenance handbook ontents HPU IDENTIFIATION SHEET... 4 1. MAINTENANE... 5 1.1 Filling level... 5 1.2 Fluid top-up... 5 1.3 Fluid replacing... 5 1.4 Fluid temperature control... 6 1.5 Functional control...

More information

DeZURIK. KSV Knife Gate Valve. Safety Manual

DeZURIK. KSV Knife Gate Valve. Safety Manual KSV Knife Gate Valve Safety Manual Manual D11035 August 29, 2014 Table of Contents 1 Introduction... 3 1.1 Terms... 3 1.2 Abbreviations... 4 1.3 Product Support... 4 1.4 Related Literature... 4 1.5 Reference

More information

A NEW PROCESS FOR IMPROVED LIQUEFACTION EFFICIENCY

A NEW PROCESS FOR IMPROVED LIQUEFACTION EFFICIENCY WHITE PAPER A NEW PROCESS FOR IMPROVED LIQUEFACTION EFFICIENCY Author(s): Adam Jones and Grant Johnson, Costain Natural Resources First published: GPAE, September 2014 www.costain.com A New Process for

More information

Normal Cryogenic Fluid Behavior (emphasis on helium, but not superfluid, which will be covered later) Tom Peterson, SLAC January 2017

Normal Cryogenic Fluid Behavior (emphasis on helium, but not superfluid, which will be covered later) Tom Peterson, SLAC January 2017 Normal Cryogenic Fluid Behavior (emphasis on helium, but not superfluid, which will be covered later), SLAC January 2017 Outline Cooling modes for superconducting devices Forced flow cooling Two-phase

More information

hydro-pac, inc. Low-Pressure Gas Compressors 1500 to 6000 PSI

hydro-pac, inc. Low-Pressure Gas Compressors 1500 to 6000 PSI hydro-pac, inc. LX-SERIES Low-Pressure Gas Compressors 1500 to 6000 PSI hydro-pac, inc. LX-SERIES Features Hydro-Pac LX-SERIES Gas Compressors feature: Oil-free non lubricated gas pistons and cylinders

More information

OPERATING PROCEDURES

OPERATING PROCEDURES OPERATING PROCEDURES 1.0 Purpose This element identifies Petsec s Operating Procedures for its Safety and Environmental Management System (SEMS) Program; it applies to all Petsec operations. Petsec is

More information

STANDARD HIGH PRESSURE COMPRESSORS COMPACT PACKAGE FOR DEMANDING APPLICATIONS

STANDARD HIGH PRESSURE COMPRESSORS COMPACT PACKAGE FOR DEMANDING APPLICATIONS STANDARD HIGH PRESSURE COMPRESSORS COMPACT PACKAGE FOR DEMANDING APPLICATIONS 2 STANDARD HIGH PRESSURE COMPRESSORS BURCKHARDT COMPRESSION GLOBAL TECHNOLOGY LEADER IN THE RECIPROCATING COMPRESSOR WORLD

More information

RESILIENT SEATED BUTTERFLY VALVES FUNCTIONAL SAFETY MANUAL

RESILIENT SEATED BUTTERFLY VALVES FUNCTIONAL SAFETY MANUAL Per IEC 61508 and IEC 61511 Standards BRAY.COM Table of Contents 1.0 Introduction.................................................... 1 1.1 Terms and Abbreviations...........................................

More information

TRI LOK SAFETY MANUAL TRI LOK TRIPLE OFFSET BUTTERFLY VALVE. The High Performance Company

TRI LOK SAFETY MANUAL TRI LOK TRIPLE OFFSET BUTTERFLY VALVE. The High Performance Company TRI LOK TRI LOK TRIPLE OFFSET BUTTERFLY VALVE SAFETY MANUAL The High Performance Company Table of Contents 1.0 Introduction...1 1.1 Terms and Abbreviations... 1 1.2 Acronyms... 1 1.3 Product Support...

More information

FAST EVAPORATION AT NORMAL PRESSURE

FAST EVAPORATION AT NORMAL PRESSURE FAST EVAPORATION AT NORMAL PRESSURE FAST EVAPORATION BY BLOWING-DOWN... The VAPORNADO Plus blow-down system is an innovative and efficient instrument for the evaporation of samples and fractions at normal

More information

Research activities on cryogenic safety

Research activities on cryogenic safety Research activities on cryogenic safety Steffen Grohmann, Carolin Heidt, Andre Henriques (CERN), Christina Weber European Cryogenics Days, CERN, June 9-10, 2016 INSTITUTE OF TECHNICAL PHYSICS (ITEP) INSTITUTE

More information

EU minimum requirements. Training and certification for personnel and companies

EU minimum requirements. Training and certification for personnel and companies EU_AREA_EC842CERTIF EU minimum requirements on Training and certification for personnel and companies involved in installation, maintenance, inspection and repair of refrigeration, air conditioning and

More information

GRUNDFOS industry GRUNDFOS CR MONITOR. Intelligent warning

GRUNDFOS industry GRUNDFOS CR MONITOR. Intelligent warning GRUNDFOS industry GRUNDFOS CR MONITOR Intelligent warning Look into the future with the CR monitor Tired of having to overhaul your pumps on a regular basis only to find that they are operating flawlessly?

More information

Specifications of Cryogenic vacuum jacketed valves

Specifications of Cryogenic vacuum jacketed valves TECHNICAL SPECIFICATIONS OF STORES AND DRAWINGS. SECTION - C Technical Specifications for Supply of Cryogenic Vacuum ed Control Valves Specifications of Cryogenic vacuum jacketed valves Contents 1 INTRODUCTION

More information

FUNDAMENTAL SAFETY OVERVIEW VOLUME 2: DESIGN AND SAFETY CHAPTER P: REFERENCE OPERATING CONDITION STUDIES (PCC)

FUNDAMENTAL SAFETY OVERVIEW VOLUME 2: DESIGN AND SAFETY CHAPTER P: REFERENCE OPERATING CONDITION STUDIES (PCC) PAGE : 1 / 11 1. PASSIVE SINGLE FAILURE ANALYSIS The aim of the accident analysis in Chapter P is to demonstrate that the safety objectives have been fully achieved, despite the most adverse single failure.

More information

The Discussion of this exercise covers the following points:

The Discussion of this exercise covers the following points: Exercise 3-2 Orifice Plates EXERCISE OBJECTIVE In this exercise, you will study how differential pressure flowmeters operate. You will describe the relationship between the flow rate and the pressure drop

More information

HumiSys HF High Flow RH Generator

HumiSys HF High Flow RH Generator HumiSys HF High Flow RH Generator Designed, built, and supported by InstruQuest Inc. Versatile Relative Humidity Generation and Multi-Sensor System The HumiSys HF is a high flow version of the previously

More information

RAC 2200-X/Y-MV DOMESTIC WATER METER TEST BENCH UP TO DN 50 ( 2 ) MANUALLY OPERATED

RAC 2200-X/Y-MV DOMESTIC WATER METER TEST BENCH UP TO DN 50 ( 2 ) MANUALLY OPERATED RAC 2200-X/Y-MV DOMESTIC WATER METER TEST BENCH UP TO DN 50 ( 2 ) MANUALLY OPERATED Actaris DEC division 08170 Montornes del Valles (Barcelona) Page 1 Tel.: 34 93 565 36 48 1. DESCRIPTION The manually

More information

Best Practice Guide, Servomex 2700

Best Practice Guide, Servomex 2700 For full installations details refer to the. Best Practice Guide, Servomex 2700 Mounting: General Guidelines: Servomex 2700 Control Units and air supplies (utilities units) should, ideally, be mounted

More information

Hydro Plant Risk Assessment Guide

Hydro Plant Risk Assessment Guide September 2006 Hydro Plant Risk Assessment Guide Appendix E10: Compressed Air System Condition Assessment E10. 1 GENERAL Compressed air systems are key components at hydroelectric power plants. Compressed

More information

JANIS OPERATING INSTRUCTIONS FOR SUPERCONDUCTING MAGNET CRYOSTATS

JANIS OPERATING INSTRUCTIONS FOR SUPERCONDUCTING MAGNET CRYOSTATS OPERATING INSTRUCTIONS FOR SUPERCONDUCTING MAGNET CRYOSTATS INTRODUCTION The Janis Research Company's Superconducting Magnet/Cryostat System is one of the most versatile tools available to the scientist

More information

Pneumatic QEV. SIL Safety Manual SIL SM Compiled By : G. Elliott, Date: 8/19/2015. Innovative and Reliable Valve & Pump Solutions

Pneumatic QEV. SIL Safety Manual SIL SM Compiled By : G. Elliott, Date: 8/19/2015. Innovative and Reliable Valve & Pump Solutions SIL SM.0010 1 Pneumatic QEV Compiled By : G. Elliott, Date: 8/19/2015 Contents Terminology Definitions......3 Acronyms & Abbreviations..4 1. Introduction 5 1.1 Scope 5 1.2 Relevant Standards 5 1.3 Other

More information

Gianluca Gemme LN2 DISTRIBUTION PLANT

Gianluca Gemme LN2 DISTRIBUTION PLANT Gianluca Gemme LN2 DISTRIBUTION PLANT Design parameters Cryogen Liquid Nitrogen Volume 200 l (one trap) Heat load 300 W (one trap) Trap cold mass 500 Kg Number of traps 4 Liquid nitrogen input 7.10 l/h

More information

OIL SUPPLY SYSTEMS ABOVE 45kW OUTPUT 4.1 Oil Supply

OIL SUPPLY SYSTEMS ABOVE 45kW OUTPUT 4.1 Oil Supply OIL SUPPLY SYSTEMS ABOVE 45kW OUTPUT 4.1 Oil Supply 4.1.1 General The primary function of a system for handling fuel oil is to transfer oil from the storage tank to the oil burner at specified conditions

More information

Process Control Loops

Process Control Loops In this section, you will learn about how control components and control algorithms are integrated to create a process control system. Because in some processes many variables must be controlled, and each

More information

Solenoid Valves used in Safety Instrumented Systems

Solenoid Valves used in Safety Instrumented Systems I&M V9629R1 Solenoid Valves used in Safety Instrumented Systems Operating Manual in accordance with IEC 61508 ASCO Valves Page 1 of 7 Table of Contents 1 Introduction...3 1.1 Terms and Abbreviations...3

More information

PURCHASE AND DELIVERY OF A HELIUM CLOSED-CYCLE OPTICAL CRYOSTAT. The present tender is only an unofficial translation provided as a courtesy.

PURCHASE AND DELIVERY OF A HELIUM CLOSED-CYCLE OPTICAL CRYOSTAT. The present tender is only an unofficial translation provided as a courtesy. ICMCB - CNRS 87 avenue du Docteur Albert Schweitzer 33608 Pessac Cedex France PURCHASE AND DELIVERY OF A HELIUM CLOSED-CYCLE OPTICAL CRYOSTAT Contenu 1. General context... 1 1.1. Project presentation...

More information

Reliable System Performance PM valves

Reliable System Performance PM valves MAKING MODERN LIVING POSSIBLE Service manual Reliable System Performance PM valves Danfoss components are designed to give a high level of performance over an extended operating life. When Danfoss develops

More information

X-Flow Mass Flow Controller 授权代理 : 北京品超思瑞科技学院公司

X-Flow Mass Flow Controller 授权代理 : 北京品超思瑞科技学院公司 X-Flow Mass Flow Controller 2 Highlights Parker Hannifin Precision Fluidics Division is excited to introduce X-Flow, a new easy to use general purpose mass flow controller for your instrument, lab, or

More information

CO 2 refrigeration in warm climates. Copyright 2012 shecco All rights reserved.

CO 2 refrigeration in warm climates. Copyright 2012 shecco All rights reserved. CO 2 refrigeration in warm climates Copyright 2012 shecco All rights reserved. 1 Enex srl DRAVA ELBA NEVA AIRHEAT/ GEOHEAT MORE THAN 300 UNITS PRODUCED CO 2 AS THE ONLY REFRIGERANT - INSTALLED IN 15 COUNTRIES

More information

FAILURE AND HAZARD ANALYSIS OF THE NPDGAMMA LH2 TARGET SYSTEM

FAILURE AND HAZARD ANALYSIS OF THE NPDGAMMA LH2 TARGET SYSTEM FAILURE AND HAZARD ANALYSIS OF THE NPDGAMMA LH2 TARGET SYSTEM Revision: 0.00 Edited by: Seppo Penttila, November 10, 2010 1. General The RSS 8305.0 Installation, Commissioning, and Operation of the NPDGamma

More information

Design. Pompetravaini-NSB API SB Liquid Ring Compressor for Gas Processing. Working Principle

Design. Pompetravaini-NSB API SB Liquid Ring Compressor for Gas Processing. Working Principle SB Pompetravaini-NSB API SB Liquid Ring Compressor for Gas Processing A family of API liquid ring compressors has been developed and has been in the market for nearly a decade, they are specifically made

More information