LEV Inspection & Test Report
|
|
- Darren Casey
- 5 years ago
- Views:
Transcription
1 LEV Inspection & Test Report CLIENT: SITE: XXXXXXX LTD XXXXXXX Report Reference: Hinge Room-LEV System Identification: BeCu ESTA Survey Conducted By: Name: Position: Signed: XXXX Environmental Consultant Visit Date: 7 th December 2015 Issue Date: December 2015 Assessment of Level of Control Satisfactory
2 System: BeCu ESTA Executive Summary: At the request of Mr XXXX, Engineering Manager with XXXXX Ltd, XXXXX Ltd were contracted to conduct a thorough examination and test of the of the various Local Exhaust Ventilation (LEV) systems at the XXXXX Ltd production facility at XXXXX. Site works were undertaken on 7 th & 8 th December by XXXXX of XXXXX Ltd without supervision. XXXXX is an Environmental Consultant with XXXXX Ltd. This report covers the following system: BeCu ESTA, located within the Hinge Room The performance of the system was seen to be satisfactory; however a number of improvements are recommended. Fitting of air flow or pressure indicators to system to aid operators in confirming the system is performing satisfactorily Locating LEV logbook for system. Ensure logbook is filed in a suitable location accessible to all relevant parties Updating the method statement for the process to include operator pre-checks to LEV system prior to beginning the process
3 System: BeCu ESTA Introduction: The site comprises a purpose built facility for the manufacture and testing of components to be used in the aerospace industry. The site was originally established in the 1940 s and has undergone extensive expansion and modernisation since opening. The system is understood to have been installed in January initial report or LEV logbook for the system could be located; discussions with site indicate that that these records may currently be in storage while the engineering department is being relocated to a different area on site. The most recent test to the system was undertaken in June 2015; again this report could not be located at the time of survey. The LEV system is located in the ground floor Hinge Room and is designed to control Beryllium and copper dust/particulates and fume generated during the polishing, soldering and drilling of hinge plates for use on a number of products manufactured in other areas of the factory. It is understood that the system is normally in use approximately 10 to 15 hours per week. System of Work: Site induction and walk round of the area was conducted with the engineering manager. The XXXXX LEV testing risk assessment document for the Hinge Room was reviewed and seen not to require any amendments before works could start. A copy of this risk assessment is attached. It was not necessary to disable the fire alarm sounders during the survey. Findings and, recommendation resulting from the examination and test of the system were discussed with the engineering manager at the completion of the survey. Existing Records: LEV logbook could not be located Previous thorough examination and test report (June 2015) could not be located
4 System: BeCu ESTA LOCAL EXHAUST VENTILATION PLANT COSHH REG. 9 EXAMINATION AND TEST 1: Client: XXXXX 2: System ID: BeCu ESTA Location: Hinge Plate Room Process: Hinge Plate Manufacture (polishing and drilling) Initial thorough examination: 3: Assessment of Level of Control: 4: Interval Between Routine Examinations: LEV 1 Satisfactory LEV 2 Satisfactory 6 monthly 5: Date of Previous Examination and Test: June : Hazard(s) to be Controlled: 7: Restrictions/Precautions: 8: Instruments Used & Ser.. Beryllium and copper Standard PPE Airflow LCA501 Vane dust/particulates and fume Safety Glasses anemometer Nitrile gloves S/N LCA Airflow Pitot tube TSI 8386 Manometer S/N Testo 425 hot wire anemometer S/N : Summary Action Plan Item in LEV Action Required system 1 - LEV System Fit appropriate visual indictors to system to enable operator to confirm system is operating satisfactorily 2- LEV Logbook Locate system logbook and file in a suitable location. Ensure logbook is includes user manual for system, prevouis test reports etc 3-Process Ensure method statement for Method process includes operators Statement pre-check instructions for LEV system Priority * 2 2 Person to take action Target Date Examiner name Signature Client name Signature 2 Date Completed Date December 2015 *Priority e.g. 1 = high, 2 = medium, 3 = routine Examiner: green boxes Employer: yellow boxes I accept this report YES /NO Date
5 HOODS/ENCLOSURES System: BeCu ESTA 10:(a) Hood(s) Type/Description: LEV 1 - Partial enclosure booth LEV 2 Capture hood 10:(b) Visual Examination Report: Partial enclosure in a clean and satisfactory condition with no visible damage. Capture hood has mesh grill across face very slight deposits observed 11: Hood Sash or Face Velocity Capture Distance Hood Hood ID Open Area Opening ht. Actual Mean Measured Required Static Pressure Volumetric Flow Rate LEV 1 (Fume cupboard) m 2 m m/s m/s m m Pa m 3 /h , 2.76, , 2.26, 2.18, 2.15 LEV 2 (Capture hood) , 21.50, 21.38, 24.65, LEV x 0.445m LEV m diameter 12: Date of Installation: January 2015 System Total Volume: m 3 /h 13:. of Hoods on System: 2 14: Process Conditions at Time of Test: Max. to be used at any time: 1 t in process 15:(a) Hood Static Pressure Gauges 15:(b) Hood Pass/Fail Stickers Fitted? Fitted? Yes 16: Qualitative Containment Test Report: Method Used: Smoke Release Smoke testing showed satisfactory smoke capture around the perimeter and across the face of partial enclosure LEV 1. Smoke testing of capture hood LEV 2 showed satisfactory smoke capture beyond the required minimum of 0.1m.
6 DUCTING System: BeCu ESTA 17:(a) Type/Description: G/S cylindrical dusting and 18: Visual Examination Report: plastic flexi-hose 17:(b) Air Temp in Ducts: TP o C; TP o C Ducting in good condition with no visible damage observed 17:(c) Barometric Pressure: 19: Diameter/ Test Dimension Point ID LEV 1 (T.P-01) Duct Area Static Pressure Velocity Pressures on Traverse Duct Velocity Actual Measured Mean Transport Velocity Duct Volume Flow (mm) (m 2 ) (Pa) (Pa) (m/s) (m/s) (m 3 /h) , 21.20, 20.20, 20.40, 21.30, LEV 2 (T.P-02) , 20.70, 20.40, 20.90, 21.30, Hood volume data Total m 3 /h 20: Damper Settings: 21: Stack height (m) and Termination Type: Since prevouis test dampers now fitted to LEV1 and LEV2 to allow one hood to operate at a time. Testing conducted with LEV 1 damper open and LEV 2 damper closed and with LEV 2 damper open and LEV 1 damper closed 22: Fan Motor Data: 23: Filter/Air Cleaning Devices: Make/Model ESTA SRF K-10 FM Make/Model ESTA SRF K-10 FM N/A Type Centrifugal Type Volume Flow 950 (m 3 /h) Volume Flow Static Pressure P Drop Motor 230v / 1.3Kw Filter Media Carbon filter plus pleated cylindrical cloth filter Rating / Current 50Hz / 8.3A Filter Cleaning Annual service Motor Speed Variable Function Check Transmission Electrical Monitoring Gauges etc. - Operational Check Rotation Direction Correct anticlockwise Recirculation of Filtered Air? Yes
7 System: BeCu ESTA 24: Return of Exhaust Air to Workroom Filter Efficiency t assessed Measurement Technique Static Pressure at Inlet, Pa Estimate of concentration of contaminant in returned air Comments Recommendations and priority* t assessed t assessed ne ne * e.g. 1 = high, 2 = medium, 3 = routine 25: Make-up air Adequate quantity Yes Measurement Technique Induced draughts Comments Recommendations ne ne 26: Alarms Hood / enclosure Duct Air cleaner Air mover Returned air Comments Recommendations ne ne 27: Statement of System Performance Specification: Smoke testing of LEV 1 showed satisfactory smoke capture around the perimeter and across face of hood. Face velocities complied with the recommended 0.5m/s for this type of hood containment system. Duct velocities for LEV 1 ducting complied with the recommended ~20m/s for grinding dust. Smoke testing of LEV 2 showed satisfactory smoke capture up to 0.28m from the hood face beyond the required 0.1m minimum to point of process. Face velocities complied with the minimum 2.5m/s-10m/s required for these types of contaminant. Satisfactory protection provided to operators. Duct velocities ducting complied with the recommended ~20m/s guideline for this type of process contaminant. The filters to the system were examined and were seen to be in a clean and satisfactory condition
8 400mm System: BeCu ESTA 28 Schematic Drawing of System: BeCu ESTA G/S DUCT 140mm DIA Damper Damper BENCH TP01 ESTA FAN/ 445mm FILTER UNIT LEV 1 TP02 G/S DUCT 60mm DIA PLASTIC FLEXIHOSE 65mm DIA LEV 2 MINI PILLAR DRILL FACE 60mm DIA BENCH
9 System: BeCu ESTA 29 Inspection Photographs: Inspection Photographs LEV 1 LEV 2 New dampers fitted to system LEV fan / filter unit Filters seen to be in a clean and satisfactory condition Motor confirmed running in correct direction (anticlockwise)
10 System: BeCu ESTA 30: Conclusions Thorough examination and testing is currently undertaken every six months as required The inclusion of dampers in the system has improved the overall system performance Smoke release showed adequate contaminant capture for LEV1 and LEV 2 Duct velocities were seen to be above the recommended speed of 20m/s which will prevent the settlement of contaminant in the system duct work Currently no monitoring equipment fitted to system to aid operator in confirming the system is operating satisfactorily. Hoods, filters and duct work were inspected and were seen to be in a clean and satisfactory condition. LEV logbook could be located at the time of the visit. It is understood that the folder may currently be in storage due to the relocation of the engineering department. It is a requirement that all LEV systems have a logbook so as to keep a record of regular examination, maintenance and repair activities to the system. The log book should be kept in a location where it can be easily accessed by all relevant parties involved in the operation, examination and maintenance of the LEV system. The logbook should contain the following: Schedules for regular examination and maintenance of the system Records of examination of the system Records of any maintenance activities carried out to the system and if applicable any repairs or modifications undertaken to the system Checks of compliance with the correct way of working with / operating the LEV System including sign off signature by person undertaking the checks The method statement for the process was reviewed and was seen not to include any information on prechecks the operator should undertake to the LEV system prior to starting the process. June 2015 thorough examination and test report could not be located 31: Recommendations Fit appropriate air flow or pressure indicators to the system to enable operators to confirm system is operating satisfactory. Ensure operators are adequately trained in reading of indicators and aware of what values show the system is operating unsatisfactory. Locate LEV log book for system and file in an easily accessible area for use by all relevant parties involved with the LEV system. Ensure book contains examination, maintenance and repair schedules and records for the LEV system. Locate June 2015 report and file in the LEV logbook. If report be located cannot contact XXXXXX Ltd client support for the issue of a replacement report.
11 Pre Inspection Risk Assessment: XXXXX Ltd Client XXXXXX Ltd Address XXXXXX Department Hinge Room Hazard Applies Risk Control and Precautions Further Action Required Exposure to hazardous Yes Low risk. Follow procedures given in substances in Hinge Room Client requested to ensure method statement and processes, where practicable, are not taking place during LEV examination and test COSHH guidelines. awareness Disposable overalls/ppe should be worn to protect normal clothing, where necessary. XXX Engineers fully trained in COSHH awareness procedures. Electrical hazards Yes Low Risk. Access not required to areas of equipment/machinery containing live electrics All testing equipment uses low voltage batteries. Access and egress to Yes Low Risk: working area XXX Engineers made aware of client policy on access and egress during site induction. Chemical hazards Yes Low Risk: hazardous chemicals are used during survey but these may be present in the area of work. Appropriate PPE to be worn where necessary. XXX Engineers receive COSHH awareness training. ise Yes Low Risk: Process does not create significant noise level ise created by survey activities is unlikely to be significant. Ear protection available if required to control noise exposure from plant activities. ne If engineer deems access unsafe the task shall be halted and the Engineering Manager informed Check with client before commencing work if other activities in area create significant hazard. If so, follow specified precautions given in client s COSHH assessment. Check with client before commencing work if other activities in area create significant noise hazard. If so, follow specified precautions given in client s noise assessment. ise meters and trained operators are available to carry out monitoring if required. XXX Engineers receive noise awareness training
12 Manual handling Yes Low Risk: Survey tools and equipment are lightweight. Stepladders and ladders are suitable for carrying by one person unaided. Moving of plant or manufactured items to be undertaken by XXXXX Ltd employees Manual handling awareness training provided to XXX Engineers Mechanical Low Risk: machinery to be operated, with the exception of the LEV, during the examination and test. ne. LEV to be isolated during examination of filters. Test of fan direction to be undertaken by site engineer Fire Yes Low Risk: Follow site fire safety rules. Cuts from sharp edges Yes Low Risk: Moving of plant or manufactured items to be undertaken by XXXXX Ltd employees Appropriate PPE to be worn where necessary. Slips, Trips and Falls Yes Low Risk: XXXXX Ltd policy for all production areas to be kept clean and tidy Check location of fire exits and escape routes before commencing work. Be aware of the risk of sharp edges, etc being present in survey area Engineering Manager to be informed if poor housekeeping observed Assessment prepared Name XXX Date: 07/12/15 by: Signature Survey Team Name XXX Date: 07/12/15 Signature Before carrying out any task the engineer shall carry out a last minute risk assessment. Any hazards observed should be recorded overleaf
13 Last Minute Risk Assessment Hazard Applies Risk Control and Precautions Further Action Required Review/ Amendment by: Name Date: Signature
TExT Thorough Examination & Test of LEV Local Exhaust Ventilation Systems
ILEVE -Institute of LEV Engineers CPD & Information Day TExT Thorough Examination & Test of LEV Local Exhaust Ventilation Systems Jane Bastow CMIOSH Chartered Safety and Health Practitioner OSCHR Registered
More informationThorough Examination and Test of Local Exhaust Ventilation Systems to Regulation 9 of the COSHH Regulations 2002 (as amended)
Thorough Examination and Test of Local Exhaust Ventilation Systems to Regulation 9 of the COSHH Regulations 2002 (as amended) Test of LEV Systems 6 Monthly Test Report Ref: LEV16012014 Date: 16 th January
More informationThe routine maintenance and inspection of local exhaust ventilation (LEV)
The routine maintenance and inspection of local exhaust ventilation (LEV) This document details the standards for inspection and maintenance that should be achieved for all local exhaust ventilation owned
More informationProficiency Module Syllabus. P601 - Thorough Examination and Testing of Local Exhaust Ventilation Systems
Proficiency Module Syllabus P601 - Thorough Examination and Testing of Local Exhaust Ventilation Systems Aim To provide the methodology, theoretical and practical knowledge to enable candidates to: Understand
More informationGSA POLICY ON LOCAL EXHAUST AND OTHER VENTILATION (FUME CUPBOARDS)
GSA POLICY ON LOCAL EXHAUST AND OTHER VENTILATION (FUME CUPBOARDS) Local Exhaust Ventilation Inspection & Maintenance 1 LOCAL EXHAUST AND OTHER VENTILATION Contents 1. Introduction 2. Design specifications
More informationVertex VP Operation and Maintenance
AIRBENCH LTD Vertex VP Operation and Maintenance This Edition: 2 October 2018 AirBench Ltd, 14 Grange Farm Road, Colchester CO2 8JW www.airbench.com +44 (0) 1206 791191 Copyright AirBench Ltd 2016 Page
More informationLEV Issues. Local Exhaust Ventilation. A Salesman Approaches! Why is LEV important? What is it supposed to do? What comprises an LEV system?
LEV Issues Local Exhaust Ventilation Practical Applications Tim Prestage CMIOSH Richard Prestage TechIOSH Size of the Problem. Engineering Controls. The standards that apply. Important Design Features.
More informationWork Equipment: LOCAL EXHAUST VENTILATION
Health & Safety Services Safety Code of Practice 46: Part 4 2 nd Edition, September 2014 Work Equipment: LOCAL EXHAUST VENTILATION University of Reading 2015 Page 1 Contents 1 Scope... 3 2 Introduction...
More informationESTATES OFFICE OPERATIONS WORKS INSTRUCTIONS WI 6. Fume Cupboards, Ventilated Cabinets, Local Exhaust Ventilation
ESTATES OFFICE OPERATIONS WORKS INSTRUCTIONS WI 6 ISSUE RECORD Revision Description Updated Date Compiled by Review date 01 Modified Mar 2010 J Cummins Mar 2011 02 Reviewed Aug 2011 J Cummins Aug 2012
More informationB S Glass Ltd Safety procedures- outsourced Workplaces
B S Glass Ltd Jan 17 B S Glass Ltd Safety procedures- outsourced Workplaces Index - - - - - - - - Page No On Site safety - - - - - - - - - - - - - - - - - - - Content 3. 1.00 Health and Safety Mission
More informationContractor / Exhibitor Handbook
Contractor / Exhibitor Handbook Health and Safety This booklet outlines the basic rules that must be followed by contractors and other visitors working on Live Promotions Events sites. The contractors
More informationLaboratory Self Inspection Checklist LAB01
Laboratory Self Inspection Checklist LAB01 General Chemical/Biological Laboratories Location Assessor Date This core checklist is provided by the Health and Safety Department as a template, which provides
More informationLaboratory Ventilation. Environmental, Health, and Safety
No.: BCF020.054 Page: 1 of 7 RECORD OF REVISIONS Date Rev # Details of Change 09/13 1 Updated job titles to reflect ICON job descriptions. Added a definition for Approved Ventilation Contractor and included
More informationLEV GUIDANCE FOR SAFE USAGE, TESTING AND MAINTENANCE OF LOCAL EXHAUST VENTILATION SYSTEMS WITHIN ANGLIA RUSKIN UNIVERSITY RISK MANAGEMENT
2016 LEV GUIDANCE FOR SAFE USAGE, TESTING AND MAINTENANCE OF LOCAL EXHAUST VENTILATION SYSTEMS WITHIN ANGLIA RUSKIN UNIVERSITY RISK MANAGEMENT This guidance is in addition to AR-RMD-HSMS38 ANGLIA RUSKIN
More informationVision Painting Inc Safety Management System
Abrasive Blasting 1. PURPOSE The purpose of this program is to provide training and qualification guidelines for the safe operation of Abrasive Blasting. The Safety Officer is responsible for facilitating
More informationSCOPE OF WORK, SAFETY METHOD STATEMENT & RISK ASSESSMENT
SCOPE OF WORK, SAFETY METHOD STATEMENT & RISK ASSESSMENT Prepared for:- Date:- Work Scheduled:- SCOPE OF WORK Carry out installation of flow meters / pressure sensors. Installation of flow meter procedure
More informationHampstead Hill School Health and Safety Policy: Confined Spaces
All Hampstead Hill School Policies are always to be read and considered in conjunction with Equal Opportunities, Race Equality and Inclusion Policies. This Policy of Hampstead Hill School applies to all
More informationRisk Assessment for: Fume cupboards
School of Design Faculty of Performance, Visual Arts and Communications Risk Assessment for: Fume cupboards Assessment No: 117 PROCESS / ACTIVITY LOCATION ASSESSED BY DATE(S) Carrying out activities that
More informationMott Manufacturing Limited
Mott Manufacturing Limited 452 Hardy Road, Brantford, Ontario, Canada, N3T 5L8. Telephone: 519-752-7825 Fax: 519-752-2895 Web Site: www.mott.ca Fume Hood Performance Test Test Date: 9-Sep-08 Model Number:
More informationControl of Allergies to Laboratory Animals
Health and Safety Policy Control of Allergies to Laboratory Animals UHSP/21/CALA/03 This document sets out in more detail the arrangements for compliance with University Health and Safety Policy at Budget
More informationA Checklist for a Health and Safety Risk Assessment
A Checklist for a Health and Safety Risk Assessment Business Information Factsheet BIF376 July 2016 Introduction All employers, and certain self-employed workers and contractors, are required to assess
More informationRISK ASSESSMENT A UNIVERSITY GUIDE TO PRACTICAL RISK ASSESSMENT UNDER THE MANAGEMENT OF HEALTH AND SAFETY AT WORK REGULATIONS 1992
RISK ASSESSMENT A UNIVERSITY GUIDE TO PRACTICAL RISK ASSESSMENT UNDER THE MANAGEMENT OF HEALTH AND SAFETY AT WORK REGULATIONS 1992 PERSONNEL DIVISION REVIEWED AUTUMN 1999 CONTENTS Page 1 INTRODUCTION 1
More informationBGC HOLDINGS LTD RESPIRATORY PROTECTIVE EQUIPMENT (RPE) POLICY
BGC HOLDINGS LTD RESPIRATORY PROTECTIVE EQUIPMENT (RPE) POLICY Introduction This document sets out the Health & Safety arrangements we have established for BGC Holdings Ltd, and all subsidiary and associated
More informationMaintenance, examination and testing of local. exhaust ventilation
Maintenance, examination and testing of local exhaust ventilation Maintenance, examination and testing of local exhaust ventilation Crown copyright 1998 First published 1990 Second edition 1998 Reprinted
More informationUnit PS1. Element 3: Common Hazards, Risks and Controls in the Chemical Industry. (Material correct Summer 2013)
NEBOSH Award in Health, Safety and Environment for the Process Industries Unit PS1 process safety Element 3: Common Hazards, Risks and Controls in the Chemical Industry Sample material (Material correct
More informationTitle: Abrasive Blasting Effective Date: 11/17/2014 Control Number: THG_0034 Revision Number: 1 Date: 10/22/2015 Annual Review Completed: 5/13/2015
Title: Abrasive Blasting Effective Date: 11/17/2014 Control Number: THG_0034 Revision Number: 1 Date: 10/22/2015 Annual Review Completed: 5/13/2015 Abrasive Blasting CONTENTS I. PURPOSE II. SCOPE III.
More informationContractor Control Procedures. Contractor Control Procedures. Working Together. November Borders College 24/11/2014.
Working Together Contractor Control Procedures November 2014 Borders College 24/11/2014 1 Working Together 1. Introduction This procedure aims to control the health and safety of contractors working on
More informationSafe Work Practices / Procedures / Instruction CONFINED SPACE
CONFINED SPACE Entry into and work in a confined space poses health and safety problems which may include: Presence or possible build up of a hazardous atmosphere Unexpected movement of equipment or materials
More informationSAFE WORK METHOD STATEMENT
SAFE WORK METHOD STATEMENT WATER PUMP - PETROL Prepared for Client: Rural Construction & Maintenance Pty Ltd Project No: 1 Site: 660 Great Ocean Road, Bellbrae Date Prepared: 29/07/2015 1. RESPONSIBILITIES
More informationCONTROL OF SUBSTANCES HAZARDOUS TO HEALTH PROCEDURE
CONTROL OF SUBSTANCES HAZARDOUS TO HEALTH PROCEDURE 1. INTRODUCTION The University uses substances hazardous to health in many of its operations, and accepts that it has a duty of care to reduce exposure
More informationSAFE WORK METHOD STATEMENT
SAFE WORK METHOD STATEMENT AUGER / POST HOLE DIGGER Prepared for Client: Rural Construction & Maintenance Pty Ltd Project No: 1 Site: 660 Great Ocean Road, Bellbrae Date Prepared: 29/07/2015 1. RESPONSIBILITIES
More informationHazard Identification and Risk Assessment Form. Risk Assessment
Identification and Assessment Form Assessment Tool & Machine Work General Various injuries (including potential fatalities) All staff complete safety induction programme at the start of the module. instructed
More informationSite Details. Comments / Corrective Actions Required. Preliminary Requirements Y N N/A SITE MONITORING PROCEDURE ASBESTOS AUDIT FORM.
Site Details Site Address Client and Address Name of Project Supervisor Licensed Contractor Name and Address Description of removal project (ACM) & size of project Project Number Auditor Date Time on site
More information2005 CERTIFICATE OF ACCEPTANCE (Part 1 of 3) MECH-1-A
2005 CERTIFICATE OF ACCEPTANCE (Part 1 of 3) MECH-1-A PROJECT ADDRESS TESTING AUTHORITY TELEPHONE Checked by/date Enforcement Agency Use GENERAL INFORMATION OF BLDG. PERMIT PERMIT # BLDG. CONDITIONED FLOOR
More informationDesign & Technology Department Health & Safety Policy. Outwood Academy Ripon
Design & Technology Department Health & Safety Policy Outwood Academy Ripon Document control table Document title: Author (name & job title): Version number: DT Health and Safety Policy Katy Bradford,
More informationSAFE WORK METHOD STATEMENT
SAFE WORK METHOD STATEMENT EXCAVATION OR TRENCHING Prepared for Client: Rural Construction & Maintenance Pty Ltd Project No: 1 Site: 660 Great Ocean Road, Bellbrae Date Prepared: 29/07/2015 1. RESPONSIBILITIES
More informationWH&S Act 2011 & Regulations 2011, Environmental Protection Act and Regulations
Workplace Address: Page 1 of PART 1: TASK DETAILS Client: JOB/TASK: Using Water blaster PART 2: RESOURCES Relevant Legislation/Codes Practice: Training Required: Equipment Used: Materials Used: Substances
More informationUniversity College Dublin Machinery/Equipment Risk Assessment Template
1. General Information Name of Person(s) carrying out assessment and their position Principal Investigator / Supervisor / Head of School or Unit (Person responsible for ensuring safety) Date of assessment
More informationLABORATORY FUME HOOD SPECIFICATION AND MAINTENANCE PROGRAM
LABORATORY FUME HOOD SPECIFICATION AND MAINTENANCE PROGRAM Last Updated: Tuesday, January 31, 2006 1. INTRODUCTION AND SCOPE 2. RESPONSIBILITIES 3. USER GUIDELINES 4. SYSTEM DESIGN SPECIFICATIONS o The
More informationFUME CUPBOARD PERFORMANCE CHECK
WS2 FUME CUPBOARD PERFORMANCE CHECK This exercise is adapted from Appendices E & F of Australian Standard 2243.8 Safety in laboratories: Fume cupboards. 1. PURPOSE This exercise determines how well a fume
More informationEXHIBITION Guide. Roles and Responsibilities OS11. A handbook for exhibitors and contractors
Appendix 1 Health & Safety Declaration, Roles and Responsibilities Each exhibitor and Informa appointed contractor must complete the Health and Safety Declaration form provided below to confirm they have
More informationReviewed: November 2013 POLICY AND GUIDELINES THE DESIGN INSTALLATION AND ONGOING MAINTENANCE & TESTING OF LOCAL EXTRACT VENTILATION
Reviewed: November 2013 POLICY AND GUIDELINES THE DESIGN INSTALLATION AND ONGOING MAINTENANCE & TESTING OF LOCAL EXTRACT VENTILATION Contents 1 Introduction & Scope 2 Legislation 3 Responsibilities 4 Design
More informationDraft. Equipment/Instrument
Heating Ventilation Air Conditioning (HVAC) Technical Platform Recommended specialist equipment including instruments for those working with Healthcare Ventilation Systems Those working with Healthcare
More informationKansas State University Fume Hood Operation
FUME HOODS 2009, PAGE 1 FUME HOODS Kansas State University Fume Hood Operation One of the primary safety devices in a laboratory is a chemical fume hood. A well-designed hood, when properly installed and
More informationP N J CLEANERS LTD. Ventilation only Risk Assessments and Method Statements
Church Farm Wychor, Alrewas, Burton on Trent, Staffordshire. DE13 8BY P N J CLEANERS LTD Telephone 01283791953 Mobile 07585127242 Email admin@pnjcleaning.co.uk Ventilation only Risk Assessments and Method
More informationSection J. How to develop safety elements for project safety management system. How to develop safety elements for project SMS
Section J How to develop safety elements for project safety management system 1. Once the project management has developed or adopted a safety policy, it needs to develop safety elements to meet the objectives
More informationCONSTRUCTION HEALTH AND SAFETY MANAGEMENT SYSTEM BASELINE HIRA
RECOMMENDED ADDITIONAL CONTROLS TASK / ACTIVITY/ EQUIPMENT/ FACILITY HAZARDS UNWANTED EVENT MINIMUM CONTROLS REQUIRED RISK NO. LIKELI-HOOD CONSE-QUENCE RISK VALUE Project Risk Assessment Page 1 of 16 All
More informationPERSONAL PROTECTIVE EQUIPMENT GUIDANCE
Legislation requires a workplace to identify and assess significant hazards (via a risk assessment) associated with workplace activities. The purpose of the assessment is to enable a valid decision about
More informationSAFE WORK METHOD STATEMENT Part B
SAFE WORK METHOD STATEMENT Part B SWMS No.: 01 WORK ACTIVITY DESCRIPTION: Door Installation All FORESEEABLE OHS & ENVIRONMENTAL HAZARDS & RISKS ASSOSSIATED WITH THE WORKS MUST BE ASSESSED & ALLOCATED CONTROLS
More informationHAZARD RECOGNITION EVALUATION and CONTROL
What is a hazard? HAZARD RECOGNITION EVALUATION and CONTROL Hazard - a dangerous object, event, behaviour or condition (in the workplace) which has the potential to cause injury, illness or property damage.
More informationPART 4: IMPLEMENTATION & OP
TITLE PART 4: IMPLEMENTATION & OPERATION Prepared by: 4.2 Personal Protective Equipment (PPE) Learning Objectives To define what is Personal Protective Equipment (PPE). To describe the management & legal
More informationTo comply with the OHS Act, the responsible manager must carry out and document the following:
Owner: Manager Health, Wellbeing and Safety Last Update: 10 January 2018 Contents 1. Purpose... 1 2. Minimum Compliance Requirements... 1 3. Definitions... 2 4. Legislative requirements under the OHS Act
More informationAirborne Activity Sampling and Monitoring at Hinkley Point A Site. David Williams, Hinkley Point A Site
Airborne Activity Sampling and Monitoring at Hinkley Point A Site David Williams, Hinkley Point A Site Presentation objectives Ventilation controls in use at Hinkley Point A Site The air sampling and monitoring
More informationPLANT HAZARD REPORT. Plant Description: Element Aspect Plant Hazards and Controls Advice. Circular Saw
PLANT HAZARD REPORT Plant Description: Circular Saw PLEASE NOTE This plant information has been prepared to assist the purchaser in identifying hazards associated with the plant prior to the purchaser
More informationSWMS No 012 Samark North Qld Pty Ltd ABN : Electrical Contractors License C37121 Page 2 of 6
Samark North Qld Pty Ltd SWMS SWMS No 0 Samark North Qld Pty Ltd ABN : 99 08 98 87 Electrical Contractors License C37 Page of 6 Safe Work Method Statement Title: SWMS:0 INSTALLING LIGHT POLES Work Method
More informationTitle: Plant and Equipment Risk Management Form Issue Date: Review Date: Page Number: 1 of 11
Issue Date: Review Date: Page Number: 1 of 11 1. Hazard Management Details General Plant/Equipment Item: WOOD LATHE Make/Model No.: Serial No.: School: Work Location: Name of Person(s) Conducting Activity:
More informationPOLICY ON THE PROVISION & USE OF PERSONAL PROTECTIVE EQUIPMENT
POLICY ON THE PROVISION & USE OF PERSONAL PROTECTIVE EQUIPMENT June 2013 Lead Manager John Green, Health & Safety Service Manager Responsible Director Director of Human Resources Approved By Health and
More informationPresented by John Whale Control Banding as a Potential Alternative to Risk Assessment
Presented by John Whale Control Banding as a Potential Alternative to Risk Assessment AUSA National Conference Sydney 2009 Background Monash s current risk control program has been in place for over 6
More informationPLANNED LIGHTING MAINTENANCE LTD METHOD STATEMENT & RISK ASSESSMENT REPLACEMENT OF LAMPS OR REPAIRS TO LOW LEVEL LIGHT UNITS
PLANNED LIGHTING MAINTENANCE LTD METHOD STATEMENT & RISK ASSESSMENT REPLACEMENT OF LAMPS OR REPAIRS TO LOW LEVEL LIGHT UNITS Project: Insert Client Repair/ Replacement of low level light units/ low level
More informationIndex to the Control Guidance Sheets
ndex to the Control Guidance Sheets 0 0- Easy steps to control chemicals. C 230 Control approach 1 - - ~~ General ventilation Solids 1 Liquids Unit operations Sheet title Small lmedium Large Small Medium
More informationHazard Identification and Risk Assessment Form. Risk Assessment
Identification and Form Tool & Machine Work General Various (including potential fatalities) All staff complete safety induction programme at the start of the module. instructed in safe operation of each
More informationThe Yorkshire Waterways Museum, Dutch River Side, Goole, POND AND NATURE TRAIL RISK ASSESSMENT SHE/RA/00
The Sobriety Project The Yorkshire Waterways Museum, Dutch River Side, Goole, DN14 5TB POND AND NATURE TRAI RISK ASSESSMENT SHE/RA/00 Title of Activity: ocation(s) of Work: Using the pond area and nature
More informationRecognition, Evaluation, and Control of Hazards
Recognition, Evaluation, and Control of Hazards Latest revised date: October 26, 2011 Page 1 of 8 1.0 Introduction Memorial University has established a system for the recognition, evaluation, and control
More informationFLYING OBJECTS MANUAL HANDLING EXCESSIVE NOISE
JOB NO: PROJECT: DATE: SWMS NO: SWMS 002 PREPARED BY: Ian Hartley REVISED BY: Nick Bragg & Cameron McNeil ACTIVITY: STUMP REMOVAL SUPERVISED BY: REVISION DATE: April 2016 MINIMUM PERSONAL PROTECTIVE EQUIPMENT
More informationOutside Air Nonresidential HVAC Stakeholder Meeting #2 California Statewide Utility Codes and Standards Program
1 Outside Air Nonresidential HVAC Stakeholder Meeting #2 California Statewide Utility Codes and Standards Program Jim Meacham, CTG Energetics Agenda 2 In Situ Testing Results Reduced Ventilation after
More informationLABORATORY SAFETY SERIES: Laboratory Hoods
ERI Safety Videos Videos for Safety Meetings 2956 LABORATORY SAFETY SERIES: Laboratory Hoods Leader s Guide Marcom Group Ltd. 1 INTRODUCTION TO THE PROGRAM Structure and Organization Information in this
More informationUGRacing Formula Student Garage Risk Assessment
UGRacing Formula Student Garage Risk Assessment University of Glasgow School of Engineering Location: Formula Student Workshop Building: Rankine Building, Oakfield Avenue Glasgow G12 8LT Summary of activities
More informationEHS Workplace Inspection Checklist (Ref. SOP QMS-080; EHS-010)
(Ref. SOP QMS-080; EHS-010) Form-445 Inspected by: Date of inspection Date of Report Report # Pages Area Manager: Area Inspected: General This EHS Workplace Inspection was conducted by: Scope of the Inspection:
More informationMethod Statement Author
Plan Bee Limited 3.3 Etna Industrial estate Clamp Road Motherwell Scotland ML2 7XQ Tel: 01698580572 Method Statement Method Statement Details Method Statement Number 7 Method Statement Date Monday 3rd
More informationCollision Repair Shop Inspection Checklist
Collision Repair Shop Inspection Checklist Note: This is a sample inspection chesklist only, and may mot include all appropriate inspection items. The Occupational Health and Safety Regulation specifies
More informationUHSE. Bath University HR Department UHSE. Safe Use of Fume Cupboards. Document Information
Bath University HR Department UHSE Document Information Author Revised By Debbie Robarts N/A Date 13-09-2016 Version 1 Status Approved UHSC 13-09-16 Copyright University of Bath This document can be used
More informationPLANNED LIGHTING MAINTENANCE LTD METHOD STATEMENT & RISK ASSESSMENT REPLACEMENT OF LAMPS OR REPAIRS TO HIGH LEVEL LIGHT UNITS
PLANNED LIGHTING MAINTENANCE LTD METHOD STATEMENT & RISK ASSESSMENT REPLACEMENT OF LAMPS OR REPAIRS TO HIGH LEVEL LIGHT UNITS Project: (insert Client) Replacement/ Repair of high level light units/ high
More informationRisk assessment. Assessment details. Task. Introduction. Please complete the form as fully and accurately as you can. Assessors job title
Risk assessment Introduction Please complete the form as fully and accurately as you can. Assessment details Name of organisation Assessor's name Assessors job title Any Company John Smith Manager Date
More informationLABORATORY SAFETY INSPECTION
LABORATORY SAFETY INSPECTION DATE: P.I./LAB MANAGER(S): PHONE(S): DEPARTMENT: BUILDING: ROOM(S) INSPECTED: INSPECTOR(S): TIME IN: TIME OUT: TOTAL TIME: LAB TYPE: DISCIPLINE: General Laboratory Safety S
More informationBIOSAFETY SELF AUDIT PRINCIPAL INVESTIGATOR/PERMIT HOLDER: CONTAINMENT LEVEL: 1 2 (Shaded) RISK GROUP: 1 2 AUDIT TO BE COMPLETED BY (DATE):
Page 1 of 5 BIOSAFETY PROGRAM BIOSAFETY SELF AUDIT PRINCIPAL INVESTIGATOR/PERMIT HOLDER: SELF AUDIT COMPLETED BY: LABORATORY ROOM NUMBER: CONTAINMENT LEVEL: 1 2 (Shaded) RISK GROUP: 1 2 DATE OF AUDIT:
More informationPOLICY FOR COSHH (CONTROL OF SUBSTANCES HAZARDOUS TO HEALTH) POLICY
POLICY FOR COSHH (CONTROL OF SUBSTANCES HAZARDOUS TO HEALTH) POLICY Written By: Nursery Manager Date approved by Directors: Signature: Date for Review: November 2018 COSHH (CONTROL OF SUBSTANCES HAZARDOUS
More informationFinishing Surfaces by Applying Treatments A/508/5116
Unit Title Ofqual unit reference number (code) Organisation Reference Finishing Surfaces by Applying Treatments A/508/5116 QU051751 Unit Level Level 2 Unit Sub Level None GLH 41 Unit Credit Value 9 Sector
More informationWorking Environment Safety Assessment
For your own safety and/or safety of your workforce, and to improve the efficiency of your business practices, you should be aware of, and be up to date with, the key safety issues and good practices relevant
More informationTHE CONTROLLED COPY OF THIS DOCUMENT IS ON THE COMPUTER NETWORK PRINTED COPIES ARE ONLY CURRENT FOR THE DATE AT THE BOTTOM OF THE PAGE.
TE CONTROLLED COPY OF TIS DOCUMENT IS ON TE COMPUTER NETWORK PRINTED COPIES ARE ONLY CURRENT FOR TE DATE AT TE BOTTOM OF TE PAGE. Title Using Angle Grinders SWMS No. 8 Authorized and email Signed by the
More informationNew Licensed Asbestos Operative Training
TRAINING SYLLABUS LICENSED WORK WITH ASBESTOS New Licensed Asbestos Operative Training This unit has twenty-two learning outcomes. 1. Recognise the types, uses and risks of asbestos containing materials
More informationPOLICY ON THE PROVISION & USE OF PERSONAL PROTECTIVE EQUIPMENT
POLICY ON THE PROVISION & USE OF PERSONAL PROTECTIVE EQUIPMENT August 2017 Important Note: The Version of this policy found on the HR Connect web page is the only version that is controlled. Any other
More informationThe following were determined to be confined spaces; they may not be permit required that employees of the Division of Facilities may encounter:
Confined Space Classifications The following were determined to be confined spaces; they may not be permit required that employees of the Division of Facilities may encounter: Utility Tunnels, Crawl Spaces,
More informationNew Licensed Asbestos Manager Training
TRAINING SYLLABUS LICENSED WORK WITH ASBESTOS New Licensed Asbestos Manager Training This unit has twenty-three learning outcomes. 1. Recognise the types, uses and risks of asbestos containing materials
More informationRECORD OF DESIGNATED SUBSTANCE ASSESSMENT
RECORD OF DESIGNATED SUBSTANCE ASSESSMENT SUBSTANCE: MERCURY (liquid) DATE: March 13, 2007 COMPANY: McMaster University DEPARTMENT OPERATIONS: Mechanical Engineering LOCATIONS: John Hodgins Engineering
More informationPOLICY FOR THE CONTROL OF SUBSTANCES HAZARDOUS TO HEALTH (COSHH)
POLICY FOR THE CONTROL OF SUBSTANCES HAZARDOUS TO HEALTH (COSHH) INTRODUCTION & LEGISLATION Using chemicals or other hazardous substances at work can put people s health at risk. The law requires employers
More informationElectrical Machines & Drives Group Safety Policy 2018/2019
Electronic & Electrical Engineering. Electrical Machines & Drives Group Safety Policy 2018/2019 1 Introduction This Safety Policy provides the safety information and procedures that must be followed to
More information"LABORATORY SAFETY SERIES"
PRESENTER'S GUIDE "LABORATORY HOODS" Part of the "LABORATORY SAFETY SERIES" Quality Safety and Health Products, for Today...and Tomorrow OUTLINE OF MAJOR PROGRAM POINTS OUTLINE OF MAJOR PROGRAM POINTS
More informationHealth and Safety Program Inspections
POLICY: It is CPP s policy to maintain a program of safety inspections. The objective of this program is to control and mitigate hazards in the workplace and worksite. All CPP s facilities and worksites
More informationTEMPLE UNIVERSITY ENVIRONMENTAL HEALTH AND RADIATION SAFETY
Page 1 of 9 ISSUED: 5/00 REVISED: 08/06 Introduction Purpose: In accordance with applicable regulations and Temple University, this policy was developed to minimize exposure to Ethylene Oxide. Applicability
More informationHarbour Town Gold Coast Site Induction
Harbour Town Gold Coast Site Induction At Harbour Town Gold Coast we believe that safety is integral to the way we do business. We are committed to operating a safe environment for all where we are incident
More informationOCCUPATIONAL SAFETY AND ENVIRONMENTAL HEALTH GUIDELINE
OCCUPATIONAL SAFETY AND ENVIRONMENTAL HEALTH GUIDELINE Date: 04-22-2009 Revision: 02 Page: 1 of 6 SUMMARY: SCOPE: REFERENCE REGULATIONS: Employees using laboratory fume hoods shall observe all applicable
More informationPLANT/EQUIPMENT/ASSET HAZARD REPORT
Asset Description: EL-08001-011 : Harrison 550 CNC Lathe Large Sale Type For what use is this asset being sold? Re-Use þ Spare Parts Scrap Note 1: Assets are sold only for the use indicated. Any other
More informationContractor handbook. Purpose
Page no: 1 / 6 Contractor handbook Purpose Mitie aims to ensure that the highest levels of performance are achieved by all persons working for us or on our behalf. We require the same level of performance
More informationMott Manufacturing Limited
Mott Manufacturing Limited 452 Hardy Road, PO Box 1120, Brantford, Ontario, Canada, N3T 5T3. Telephone: 519-752-7825 Fax: 519-752-2895 Web Site: www.mott.ca Fume Hood Performance Test Test Date: January
More informationSafe Work Method Statement
Company Name: Safe Work Method Statement Site Address: Other Details: Contractor: Activity/Trade: Electrician Date: TASKS List the tasks required to perform the activity in sequence carried out. Entry
More informationThe primary purpose of laboratory fume hoods is to keep toxic or irritating vapors out of the general laboratory working area.
Introduction Welcome to the Biosafety Cabinets and Fume Hoods Training Course (OHS_BIO304). This training is required for anyone that will be conducting work and/or research that requires the use of a
More informationIMMANUEL CHURCH, CHICHESTER HEALTH AND SAFETY POLICY
IMMANUEL CHURCH, CHICHESTER HEALTH AND SAFETY POLICY Approved by the Trustees: November 2016 Health and Safety Policy Introduction The main piece of health and safety legislation is the Health and Safety
More informationSafe Work Method Statement LRB TREE SERVICES 6 Behland St, Kearneys Spring QLD, 4350 ABN
JOB NO: PROJECT: DATE: 1/1/2018 SWMS NO: SWMS 001.1 PREPARED BY: LUKE BLINCO REVISED BY: ACTIVITY: TREE REMOVAL & PRUNING SIGNED BY: REVISION DATE: MINIMUM PERSONAL PROTECTIVE EQUIPMENT (PPE) REQUIREMENTS
More informationManagement Plan for Confined Spaces
IEA, INC. W A S ECA P U B L I C S C H O O L S I S D # 829 Contact Us: BROOKLYN PARK OFFICE 9201 W. BROADWAY, #600 BROOKLYN PARK, MN 55445 763-315-7900 MANKATO OFFICE 610 N. RIVERFRONT DRIVE MANKATO, MN
More informationOperation of Embrey Excavator Shears Safe Work Procedure PTES_HSE_SWP_039. Name Date Signature. Author Jarred Hearle 27/11/2015
Operation of Embrey Excavator Shears Safe Work Procedure PTES_HSE_SWP_039 Name Date Signature Author Jarred Hearle 27/11/2015 Reviewed FMG Site Team 27/11/2015 ---------- Approved Geoff Selfe 27/11/2015
More information