MOD Risk Assessment Form

Size: px
Start display at page:

Download "MOD Risk Assessment Form"

Transcription

1 Introduced April 2008 ART/AICT 026 : Section/Department: ART /AICT1 Type Activity/Process: Manual Handling Name: G. Dunning Name: TJ Smalley Rank/Grade: Rank/Grade: Major (Include Hazard Survey Number where applicable) Muscular injuries? and students and students (Specific existing ) a. PTI to supervise throughout. b. Full brief given by PTI. Dehydration students c. students to have access to water throughout activity. Rating Additional (Each Control Measure is to be specific Adequate 1 x 1 =1 ad equate Rating Owner 1 x 1 =1 Art 1 1 x 1 = 1 Art 1 1 x 2 = 2 Art 1

2 d. First aid trained instructors on hand Equipment and students e. All equipment to be checked for serviceability prior to activity. Art 1 Clothing and students and students f. trained personal only to move equipment. g. correct footwear and clothing to be worn throughout activity Adequate 1 x 1 = 1 Art 1 Art 1 Line Manager Review (See Notes 2 and 5) Review : Review : Review : Review : Name: Name: Name: Name: Rank/Grade: Rank/Grade: Rank/Grade: Rank/Grade: Notes: 1 If using a Generic risk assessment, Assessors and Line Managers are to satisfy themselves that the assessment is valid for the task and that all significant hazards have been identified and assessed. If additional hazards are identified they are to be recorded and attached to the Generic assessment. 2 Line Managers are to note that they are responsible for production of the risk assessment and that they are signing to indicate that the risk assessment is suitable and sufficient and they consider the risks to be acceptable. 3 High Common, regular or frequent occurrence. 3 3 Med 6 High 9 High Medium Occasional occurrence. 2 2 Low 4 Med 6 High Low Rare or improbable occurrence. 1 1 Low 2 Low 3 Med Matrix Likelihood X Consequence Minor injury or illness. Serious injury or illness. Fatalities, major injury or illness. Low Medium High

3 When recording the Rating ensure that both the Likelihood and Consequence scores are included. High Medium Low Improve control measures; consider stopping work. Conducting work at this level of risk is to be reported up the Line Management / Command chain. Review control measures and improve if reasonably practicable to do so, consider alternative ways of working. Maintain control measures and review if there are any changes. 4 Record the residual Rating to demonstrate that the risk has been reduced to an acceptable level; record Likelihood and Consequence scores. 5 s are to be reviewed: Annually. If there is reason to doubt the effectiveness of the assessment. Following an accident or near miss. Following significant changes to the task, process, procedure or Line Management. Following the introduction of more vulnerable personnel. If Generic prior to use. ART : Section/Department: ART 1 Type Activity/Process: Use of portable generators Name: G Dunning Name: TJ Smalley Rank/Grade: Rank/Grade: Major (Include Hazard Survey number where applicable)? (Specific existing Control Measures) Rating Additional (Each Control Measure is to be Rating Owner

4 Injury during handling All personnel to receive manual handling training Burns from hot components or fire All staff to receive first aid training for burns Electric shock All personnel to receive first aid training for electric shock Fire during normal operation or when refuelling Pollution from leaks or spillages All personnel to receive fire training and training on safe operation of generators Checks to be carried out before during and after use for any leaks. Refuelling is to be done only by issued fuel cans with fitted hoses rehensive training is to be carried out annually and as part of WIP specific 1 x 3 = 3 1 x 3 = 3 ART 1 ART : Section/Department: ART 1 Type Activity/Process: Use of the recruiting caravan. Name: G Dunning Name: TJ Smalley

5 Rank/Grade: Rank/Grade: Major (Include Hazard Survey number where applicable) Slipping and tripping Head injury Eye strain Fire hazard? (Specific existing Control Measures) Rating Additional (Each Control Measure is to be specific a. Set of metal steps in use b. Public to be supervised entering and exiting the caravan. c. Time restriction on playing the WII. d. All staff fire trained e. Fire extinguisher on hand. f. Generator outside the caravan. g. First aid trained personnel on hand. h. Public to be supervised at all times. Rating Owner ART : Section/Department: ART 1 Type

6 Activity/Process: Use of the inflatable assault course. Name: G Dunning Name: TJ Smalley Rank/Grade: Rank/Grade: Major (Include Hazard Survey number where applicable) Muscular injuries Fire hazard? (Specific existing Control Measures) a. Trained personnel only to monitor participants. b. Participants to be monitored at all times.. c. A warm up to be given to participants.. Rating Additional (Each Control Measure is to be specific d. Staff fire trained. e. Fire extinguisher on hand. f. First aid trained personnel on hand. Rating Owner

7 Dehydration g. Water available. h. First aid trained personnel on hand. ART : Section/Department: ART 1 Type Activity/Process: Use of the command tasks. Name: G Dunning Name: TJ Smalley Rank/Grade: Rank/Grade: Major (Include Hazard Survey number where applicable) Tripping and falling? (Specific existing Control Measures) a. Public supervised at all times. b. First aid personnel on hand. Rating Additional (Each Control Measure is to be specific Rating Owner

8 Muscular injuries Head injury c. Full brief given by the directing staff. d. First aid personnel on hand. e. Public supervised at all times. f. All tasks completed on grassed areas. g. Protective equipment to be worn at all times. h. First aid personnel on hand.

Volunteer Cadet Corps Royal Naval and Royal Marines Cadets

Volunteer Cadet Corps Royal Naval and Royal Marines Cadets RMVCC activities require a risk assessment. Use this form where a generic risk assessment does not already exist or is not sufficient. Insert more rows or sheets if required. Do not complete the shaded

More information

RISK ASSESSMENT FOR ACTIVE SCHOOLS ACTIVITIES

RISK ASSESSMENT FOR ACTIVE SCHOOLS ACTIVITIES RISK ASSESSMENT FOR ACTIVE SCHOOLS ACTIVITIES Site Forrester/St Augustine s Campus Pool Date of last assessment: Date of new assessment: Activity/Situation: Water Polo Leader/Contact: Gael Logan Identified

More information

Basketball Risk Assessment for AoC Sport National Championships 2018 Nottingham University

Basketball Risk Assessment for AoC Sport National Championships 2018 Nottingham University Trivial Minor Moderate Serious Very Serious Basketball Risk Assessment for AoC Sport National Championships 2018 Nottingham University The assessor can assign values for the hazard severity (a) and likelihood

More information

Safe Work Method Statements (SWMS)

Safe Work Method Statements (SWMS) Safe Work Method Statements (SWMS) The purpose of a SWMS is to list the steps of a particular task in your workplace, identify the hazards and associated risks in each step and recommend key safety controls

More information

Risk Assessment Form

Risk Assessment Form Assessment Form Oil Salvage Limited Assessment Record Activity: Loading of tankers (Collection and Deliveries) Ref Number: RA03 Having assessed the and risks, I believe that if the control measures identified

More information

Standing Risk Assessment: HARBOUR, DINGHY PARK & SLIPWAYS ANNEX B TO Club HEALTH & SAFETY MANAGEMENT PLAN

Standing Risk Assessment: HARBOUR, DINGHY PARK & SLIPWAYS ANNEX B TO Club HEALTH & SAFETY MANAGEMENT PLAN Sheet 1 of 5 ANNEX B TO CLUB HEALTH & SAFETY MANAGEMENT PLAN Standing Risk Assessment: HARBOUR, DINGHY PARK & SLIPWAYS ANNEX B TO Club HEALTH & SAFETY MANAGEMENT PLAN L = Likelihood scale: 5 = High 3 =

More information

WH&S Act 2011 & Regulations 2011, Environmental Protection Act and Regulations

WH&S Act 2011 & Regulations 2011, Environmental Protection Act and Regulations Workplace Address: Page 1 of PART 1: TASK DETAILS Client: JOB/TASK: Using Water blaster PART 2: RESOURCES Relevant Legislation/Codes Practice: Training Required: Equipment Used: Materials Used: Substances

More information

RNAS CULDROSE WORK EXPERIENCE BOOKLET SEP 14 JUL 15

RNAS CULDROSE WORK EXPERIENCE BOOKLET SEP 14 JUL 15 RNAS CULDROSE WORK EXPERIENCE BOOKLET SEP 14 JUL 15 CONTENTS Introduction Page 3 Correspondance Page 3 Student Placements at RNAS Culdrose Page 4 Application Procedure Page 5 Selection of Students for

More information

JOB SAFETY ANALYSIS. How to use the Risk Assessment Charts. Likelihood A (Almost Certain) B (Likely) C (Possible)

JOB SAFETY ANALYSIS. How to use the Risk Assessment Charts. Likelihood A (Almost Certain) B (Likely) C (Possible) Page 1 of 6 How to use the Assessment Charts 1. Determine the Likelihood on the Qualitative Assessment Process Chart (pick a letter applicable to the task). 2. Determine the Consequence on the Qualitative

More information

JOB SAFETY ENVIRONMENT ANALYSIS (JSEA) Working With In Situ Testing Rigs

JOB SAFETY ENVIRONMENT ANALYSIS (JSEA) Working With In Situ Testing Rigs Personnel Involved Manager Project Operators Assistant Notes re Operator/Off-Sider Training Allan McConnell In situ testing is a niche business with very few rigs in Australia. There are no specific training

More information

University of Lincoln Students Union Annual Risk Assessment for Activities

University of Lincoln Students Union Annual Risk Assessment for Activities University of Lincoln Students Union Annual Assessment for Activities Activity Details Activity Name Sailing Date Of risk Assessment Completion 10/07/16 Assessment Review Date Ongoing Assessment The Assessment

More information

ABBEYFIELD STAIR AND CHAIR LIFT RISK ASSESSMENT

ABBEYFIELD STAIR AND CHAIR LIFT RISK ASSESSMENT ABBEYFIELD STAIR AND CHAIR LIFT RISK ASSESSMENT Name /Location of House Chair Lift Make and Model: Date of Installation: Name of Service/Inspection Contractors: House Manager Date of Risk Assessment: Name

More information

TASK DAY RISK ASSESSMENT FORM

TASK DAY RISK ASSESSMENT FORM TASK DAY RISK ASSESSMENT FORM Assessment date Location and Activity details: Site Address Step One - Identify the activity and hazards Consider the activity or work area and identify if any of the hazards

More information

ACTIVITY RISK ASSESSMENT

ACTIVITY RISK ASSESSMENT ACTIVITY RISK ASSESSMENT Activity Name and Description: Child Activity Risk Assessment Template normally you would describe the activity here Activity Location: Where is the activity to be held? Activity

More information

ESSENTIAL SAFETY RESOURCES

ESSENTIAL SAFETY RESOURCES ESSENTIAL SAFETY RESOURCES GS-3018 HAZARD IDENTIFICATION AND RISK ASSESSMENT Originator: Safety Advisor s Signature: Type Name Approval: HSE Manager s Signature: Type Name Approval: Operations Manager

More information

Instructions for the Use of the Excel Spreadsheet. There are Three tabs at the bottom of this worksheet. Instructions tab is the one you are reading

Instructions for the Use of the Excel Spreadsheet. There are Three tabs at the bottom of this worksheet. Instructions tab is the one you are reading Instructions for the Use of the Excel Spreadsheet There are Three tabs at the bottom of this worksheet Instructions tab is the one you are reading H&S Plan Tab The Plan Tab is the front cover pages of

More information

CIRCUIT BREAKER TESTING - JOB SAFETY ANALYSIS

CIRCUIT BREAKER TESTING - JOB SAFETY ANALYSIS Title: Circuit Breaker Testing Purpose and Scope: Provide guidelines for testing of Circuit Breakers. Staffing Resources: Staff will have the minimum requirement of an Electrical Fitter/Mechanic Licence

More information

Risk Assessment Examples

Risk Assessment Examples Central Council of Church Bell Ringers "Registered Charity number 270036" Tower Stewardship Committee Risk Assessment Examples Two examples of a risk assessment, compiled specifically for use in a church

More information

Management of risk. Definition of terms. Managing risks. Risk

Management of risk. Definition of terms. Managing risks. Risk Definition of terms Risk Management of risk Risk is the possibility that harm (death, injury or illness) might occur when exposed to a hazard. A hazard is anything with the potential to cause injury or

More information

SAFE WORK METHOD STATEMENT WORKING IN CONFINED SPACE HSE NET NAT SWMS APAND00030

SAFE WORK METHOD STATEMENT WORKING IN CONFINED SPACE HSE NET NAT SWMS APAND00030 SAFE WORK METHOD STATEMENT WORKING IN CONFINED SPACE HSE NET NAT SWMS APAND00030 HIGH RISK APT AM Holdings Pty. Ltd. [ABN] 95124754383 Principal Contractor (PC) APA Group Level 19, HSBC Building 580 George

More information

Hazards Requiring Attention: AS AT Friday, 29 January Next Review Saturday, 28 January Total Hazards Recorded 39. Critical Risk Hazards 0

Hazards Requiring Attention: AS AT Friday, 29 January Next Review Saturday, 28 January Total Hazards Recorded 39. Critical Risk Hazards 0 EF26 Risk Assessment CAT Excavator Hazards Requiring Attention: AS AT Friday, 29 January 2016 0 Next Review Saturday, 28 January 2017 Total Hazards Recorded 39 Critical Risk Hazards 0 High Risk Hazards

More information

Pre-control risk estimate. Likelihood Risk

Pre-control risk estimate. Likelihood Risk Activity Consequence s mitigation measures Site Access & Egress Slips, trips & falls al injury by falling. Sprains & broken bones. Site operatives 3 4 12 Ensure access to site is kept clear of plant &

More information

Risk Assessment. Appendix A contains

Risk Assessment. Appendix A contains Risk Assessment Department The Cockpit Risk Assessment number AM/09/01 Date. 1 st July 01 Review due date 0 th July 01 Activity Maintenance and support service working Location The Cockpit Name of Assessor/s

More information

Employ The Risk Management Process During Mission Planning

Employ The Risk Management Process During Mission Planning Employ The Risk Management Process During Mission Planning TSG 154-6465 Task(s) TASK NUMBER TASK TITLE Taught or 154-385-6465 Employ The Risk Management Process During Mission Planning Supported Task(s)

More information

FIRE HYDRANT TESTING METHOD STATEMENT.

FIRE HYDRANT TESTING METHOD STATEMENT. SUBJECT: TASK: FIRE HYDRANT INSPECTION & TESTING. 1. Location....1 2. The Scope of Works.... 1 3. Description of Task.... 1 4. Access & Egress to & from Work Area.... 2 5. Safety Hazard Identification....

More information

Very unlikely (VU) Unlikely (U) Likely (L) Very likely (VL) Typically experienced once during the working lifetime of an individual

Very unlikely (VU) Unlikely (U) Likely (L) Very likely (VL) Typically experienced once during the working lifetime of an individual Risk estimation Using the form provided to evaluate the main health and safety risks in your sport. Use the guidance and tables below to help you: Table 1: risk estimation Severity of impact Likelihood

More information

IIUM EVENT SAFETY RISK ASSESSMENT

IIUM EVENT SAFETY RISK ASSESSMENT INTERNATIONAL ISLAMIC UNIVERSITY MALAYSIA HAZARD IDENTIFICATION OCCUPATIONAL WORKPLACE SAFETY, HEALTH AND BUILT ENVIRONMENT DEPARTMENT (OSHBE) PRESENTED BY: YBHG. DATO IR. SHAFFEI MOHAMAD IIUM EVENT SAFETY

More information

Safety Risk Assessment Worksheet Title of Risk Assessment Risk Assessment Performed By: Date: Department:

Safety Risk Assessment Worksheet Title of Risk Assessment Risk Assessment Performed By: Date: Department: Title of Risk Assessment Risk Assessment Performed By: Date: Department: Choose the appropriate type of change from the list below: Revision To Existing New Choose the appropriate system/task from the

More information

QUEENSLAND UNIVERSITY OF TECHNOLOGY

QUEENSLAND UNIVERSITY OF TECHNOLOGY QUEENSLAND UNIVERSITY OF TECHNOLOGY SITE SPECIFIC SAFETY MANAGEMENT PLAN FOR SAMFORD HOUSE SAMFORD ECOLOGICAL RESEARCH FACILITY SAMFORD VALLEY 2007 Dylan Randall SN: 06305466 dylan.randall@student.qut.edu.au

More information

SAFE WORK METHOD STATEMENT (SWMS) All Trades Abseiling ABN: Ph:

SAFE WORK METHOD STATEMENT (SWMS) All Trades Abseiling ABN: Ph: PCBU: ALL TRADES ABSEILING ABN: 42 137 576 035 PO Box 774 NEWPORT NSW 2106 LIC: 123517C P: 0412 227 578 Principal Contractor (PC): Date SWMS provided to PC: Work activity: Workplace location: High risk

More information

Risk Assessment Form

Risk Assessment Form Risk Assessment Form School Activity Risk Assessment conducted by: Consultation occurred with: (names & role) Description of activity being assesses Batchelor Outdoor Education Centre High and Low Ropes

More information

RISK Assessment & Management Plan

RISK Assessment & Management Plan Provider Outdoor Learning Schools CIC Location: Cherry Garth Assessment Ref: OLS/001/Archery Assessment by: C.Carr Last Assessment:: 02/07/13 of risk Arrows Archery Target shooting through using arrows

More information

Rock Climbing Risk Management Plan Lutanda Yarramundi

Rock Climbing Risk Management Plan Lutanda Yarramundi Rock Climbing Risk Management Plan Lutanda Yarramundi School: Year: Dates: Program: Supervising Staff: Activity Context The rock climbing wall at Lutanda Yarramundi is located next on the side of the Activity

More information

Risk assessment guidelines for centres and resorts

Risk assessment guidelines for centres and resorts Risk assessment guidelines for centres and resorts Contents Topic Page Contents 1 Introduction 2 Codes of practice 2 Conducting a risk assessment 2 Five steps to risk assessment 2 Step 1 Identify the hazards

More information

Team Building /Leadership Challenge Risk Assessment - Management Plan

Team Building /Leadership Challenge Risk Assessment - Management Plan Content Team Building /Leadership Challenge Assessment - Management Plan Team Building and Leadership Challenge are adventure based learning activities that require the team to work together to solve a

More information

SAFE WORK METHOD STATEMENT Part 1 CONCRETE SAWING

SAFE WORK METHOD STATEMENT Part 1 CONCRETE SAWING SAFE WORK METHOD STATEMENT Part 1 CONCRETE SAWING Personal Protective Equipment Foot Hearing High Visibility Head Eye Face Hand Protective Clothing Breathing Normal Requirements: Safety footwear, hearing

More information

Environmental-Related Risk Assessment

Environmental-Related Risk Assessment Environmental-Related Risk Assessment *GTA 05-08-002 DISTRIBUTION: U.S. Army Training Support Centers. DISTRIBUTION RESTRICTION: Approved for public release; distribution is unlimited. Headquarters, Department

More information

Controls to either eliminate or reduce the risk of an accident happening.

Controls to either eliminate or reduce the risk of an accident happening. Risk Assessment: Pond Dipping Assessment to be agreed and signed for by: Position: Date: What task, activity or environment is being assessed? POND DIPPING (SMALL PONDS, WATER MARGINS & SHALLOW, SLOW MOVING

More information

RISK ASSESSMENT Date Of Assessment:

RISK ASSESSMENT Date Of Assessment: RISK ASSESSMENT Assessment Scope/Title: St James the Great, Hanslope Date Of Assessment: 27/08/2018 Date For Review: 27/08/2021 Details Who May Be Harmed & Control Measures Person Record details of what

More information

Abseiling Risk Management Plan Lutanda Yarramundi

Abseiling Risk Management Plan Lutanda Yarramundi Abseiling Risk Management Plan Lutanda Yarramundi School: Year: Dates: Program: Supervising Staff: Activity Context Abseiling at Lutanda Yarramundi is located on the activity tower on the wall facing the

More information

RISK ASSESSMENT 2017 READING TOWN REGATTA, THAMES VALLEY PARK REGATTA

RISK ASSESSMENT 2017 READING TOWN REGATTA, THAMES VALLEY PARK REGATTA RISK ASSESSMENT 07 READING TOWN REGATTA, THAMES VALLEY PARK REGATTA Hazard Risk Existing Control Measures Severity Freq. Action Outstanding Timescale Serial Serial Those associated with boating -Racing

More information

Risk Assessment Guidance

Risk Assessment Guidance Risk Assessment Guidance The assessor can assign values for the hazard severity (a) and likelihood of occurrence (b) (taking into account the frequency and duration of exposure) on a scale of 1 to 5, then

More information

RISK ASSESSMENT FOR THE CHIMERA CLIMBING CENTRE DATE LAST UPDATED: 25 AUGUST STUART HOWARD

RISK ASSESSMENT FOR THE CHIMERA CLIMBING CENTRE DATE LAST UPDATED: 25 AUGUST STUART HOWARD ASSESSMENT FOR THE CHIMERA CLIMBING CENTRE DATE LAST UPDATED: 2 AUGUST 201 - STUART HOWARD ASSESSMENT PROCESS: Likelihood of occurrence x Severity, L X S Likelihood of occurrence 1 Highly unlikely to ever

More information

THE CONTROLLED COPY OF THIS DOCUMENT IS ON THE COMPUTER NETWORK PRINTED COPIES ARE ONLY CURRENT FOR THE DATE AT THE BOTTOM OF THE PAGE.

THE CONTROLLED COPY OF THIS DOCUMENT IS ON THE COMPUTER NETWORK PRINTED COPIES ARE ONLY CURRENT FOR THE DATE AT THE BOTTOM OF THE PAGE. TE CONTROLLED COPY OF TIS DOCUMENT IS ON TE COMPUTER NETWORK PRINTED COPIES ARE ONLY CURRENT FOR TE DATE AT TE BOTTOM OF TE PAGE. Title Using Angle Grinders SWMS No. 8 Authorized and email Signed by the

More information

SAFE WORK METHOD STATEMENT

SAFE WORK METHOD STATEMENT SAFE WORK METHOD STATEMENT WATER PUMP - PETROL Prepared for Client: Rural Construction & Maintenance Pty Ltd Project No: 1 Site: 660 Great Ocean Road, Bellbrae Date Prepared: 29/07/2015 1. RESPONSIBILITIES

More information

RISK ASSESSMENT POLICY

RISK ASSESSMENT POLICY RISK ASSESSMENT POLICY Document created: 30 April 2015, last modified: 12 May 2015 Next review: 30 April 2016 Sherfield School Risk Assessmemt Policy 2 RISK ASSESSMENT Purpose of this Section 1. The purpose

More information

Summer Scrambling / Mountaineering

Summer Scrambling / Mountaineering Company: Thistle Trekking LTD Location: UK Description of Work Activity or Area of the Workplace Assessed: Summer Scrambling Summer Scrambling / Mountaineering All RA s should be reviewed if changes are

More information

WORK METHOD STATEMENT STRUCTURAL STEEL

WORK METHOD STATEMENT STRUCTURAL STEEL ORGANISATION DETAILS Organisation Name: Gedoun Constructions Pty Ltd Contact Name: Joe Gedoun ACN/ABN: 52 284 873 581 Contact Position: Director Address: PO Box 1138, Townsville QLD 4810 Contact Phone

More information

SAFE WORK METHOD STATEMENT Part 1 EXCAVATOR AUGER ATTACHMENT

SAFE WORK METHOD STATEMENT Part 1 EXCAVATOR AUGER ATTACHMENT SAFE WORK METHOD STATEMENT Part 1 EXCAVATOR AUGER ATTACHMENT Personal Protective Equipment Foot Hearing High Visibility Head Eye Day Operations Normal Requirements: Safety footwear, hearing protection,

More information

EHS Workplace Inspection Checklist (Ref. SOP QMS-080; EHS-010)

EHS Workplace Inspection Checklist (Ref. SOP QMS-080; EHS-010) (Ref. SOP QMS-080; EHS-010) Form-445 Inspected by: Date of inspection Date of Report Report # Pages Area Manager: Area Inspected: General This EHS Workplace Inspection was conducted by: Scope of the Inspection:

More information

POSITION OF PERSON COMPLETING REPORT: IN CONSULTATION WITH: David Radolovic POSITION: HSR/ Program Coordinator

POSITION OF PERSON COMPLETING REPORT: IN CONSULTATION WITH: David Radolovic POSITION: HSR/ Program Coordinator YMCA CENTRE: Parks Recreation Centre ASSESSMENT DATE: 04/08/2015 PROGRAM / AREA: Climbing Wall TASK / ITEM: Climbing Wall PERSON COMPLETING REPORT: Anthony Bates POSITION OF PERSON COMPLETING REPORT: Camping

More information

Risk Assessment Form

Risk Assessment Form Risk Assessment Form School Activity Risk Assessment conducted by: Consultation occurred with: (names & role) Description of activity being assesses Batchelor Outdoor Education Centre Bush Walking Michelle

More information

Buchanan. Approved: John Downes

Buchanan. Approved: John Downes Severity Site triio Activity Vacuum Excavator Persons conducting assessment SHEQ DEPT Assessment No triio 21 Review Date 11/01/2021 Revision No. 10 Name: Paul Disley/Ian Buchanan Signature Date: 11/01/2019

More information

District Risk Assessment: Grass Sledging - Rhydd Covert Campsite

District Risk Assessment: Grass Sledging - Rhydd Covert Campsite HAZARD OBSERVED RISK BEFORE CONTROL MEASURES PERSONS AT RISK CONTROL MEASURES COMMENTS ACTIONS Lifting weighted objects Muscle strain When lifting and carrying sledges to and from store room Leaders Storage

More information

SAFETY MANAGEMENT SYSTEM

SAFETY MANAGEMENT SYSTEM Equipment Location: Hazard Hired From All Master Hire Stores Entanglement Can anyone s hair, clothing, gloves, necktie, jewellery, cleaning brushes, rags or other materials become entangled with moving

More information

SAFETY MANAGEMENT SYSTEM

SAFETY MANAGEMENT SYSTEM Equipment Location: Hazard Hired From All Master Hire Stores Entanglement Can anyone s hair, clothing, gloves, necktie, jewellery, cleaning brushes, rags or other materials become entangled with moving

More information

Risk Assessment for the Hexagon Theatre Schools Visit

Risk Assessment for the Hexagon Theatre Schools Visit Before your visit Risk Assessment for the Hexagon Theatre Schools Visit Before you come to the Hexagon, your school, club or organisation will wish to conduct its own risk assessment. Whilst the Hexagon

More information

Exercise IARD. Risk Assessment & Management Plan

Exercise IARD. Risk Assessment & Management Plan Risk Assessment & Management Plan Approved by Exercise Director: Senior Sergeant A Bennett Date:../ /.. Prepared by SRCTU Version 1 1 Contents 1. Introduction... 3 1.1. Phase 1:... 3 1.2. Phase 2:... 3

More information

FIELDWORK RISK ASSESSMENT FORM FORM TO BE FILLED IN BY FIELDTRIP LEADER PRIOR TO ANY FIELDWORK AND MUST BE SIGNED OFF BY HEAD OF DEPARTMENT

FIELDWORK RISK ASSESSMENT FORM FORM TO BE FILLED IN BY FIELDTRIP LEADER PRIOR TO ANY FIELDWORK AND MUST BE SIGNED OFF BY HEAD OF DEPARTMENT FIELDWORK RISK ASSESSMENT FORM FORM TO BE FILLED IN BY FIELDTRIP LEADER PRIOR TO ANY FIELDWORK AND MUST BE SIGNED OFF BY HEAD OF DEPARTMENT Contents Page: Description and Methodology of Fieldwork Risk

More information

Risk Assessment Form

Risk Assessment Form Risk Assessment Form School Activity Risk Assessment conducted by: Consultation occurred with: (names & role) Description of activity being assesses Batchelor Outdoor Education Centre Artificial Climbing

More information

University of Lincoln Students Union Annual Risk Assessment for Activities

University of Lincoln Students Union Annual Risk Assessment for Activities Activity Details Activity Name Paintball Date Of risk Assessment Completion 17/05/2018 Risk Assessment Review Date 17/05/2019 Ongoing Assessment The Risk Assessment process must be on-going and dynamic.

More information

PLANNED LIGHTING MAINTENANCE LTD METHOD STATEMENT & RISK ASSESSMENT REPLACEMENT OF LAMPS OR REPAIRS TO HIGH LEVEL LIGHT UNITS

PLANNED LIGHTING MAINTENANCE LTD METHOD STATEMENT & RISK ASSESSMENT REPLACEMENT OF LAMPS OR REPAIRS TO HIGH LEVEL LIGHT UNITS PLANNED LIGHTING MAINTENANCE LTD METHOD STATEMENT & RISK ASSESSMENT REPLACEMENT OF LAMPS OR REPAIRS TO HIGH LEVEL LIGHT UNITS Project: (insert Client) Replacement/ Repair of high level light units/ high

More information

innova-ve entrepreneurial global 1

innova-ve entrepreneurial global 1 www.utm.my innova-ve entrepreneurial global Safety Integrity Level (SIL) is defined as: Relative level of risk-reduction provided by a safety function to specify a target level of risk reduction. SIL is

More information

RISK ASSESSMENT Installation of electrically operated service lifts (non passenger type)

RISK ASSESSMENT Installation of electrically operated service lifts (non passenger type) RISK ASSESSMENT 2011 WALLINGTON LIFT MAINTENANCE CO LTD Installation of electrically operated service lifts (non passenger type) 1 1 L a k e s i d e, W a l l i n g t o n, S u r r e y, S M 6 7 J Y T e l

More information

Risk Management Guide

Risk Management Guide What is health and safety risk management? Risk Management Guide Risk Management is a proactive, logical and systematic approach of managing the uncertainty relating to potential risk, rather than responding

More information

Hazard & Risk Management

Hazard & Risk Management Hazard & Risk Management Introduction The Church recognises WHS hazards and risks must be appropriate managed to ensure, so far as reasonably practicable, the health and safety of all workers at Church

More information

EXECUTIVE SHIP MANAGEMENT PTE LTD M 24 Q 4 SINGAPORE QI 19 Page 1 of 5 (9/05 Rev 2) Decision. Implement

EXECUTIVE SHIP MANAGEMENT PTE LTD M 24 Q 4 SINGAPORE QI 19 Page 1 of 5 (9/05 Rev 2) Decision. Implement SINGAPORE QI 19 Page 1 of 5 RISK ASSESSMENT Ships Name Ships No Work Activity Activity / Operation Analyse/review/Assess WHAT IF? MAIN AIR COMPRESSOR OVERHAUL Possible Consequence / Hazard / Impact Monitor

More information

PLANNED LIGHTING MAINTENANCE LTD METHOD STATEMENT & RISK ASSESSMENT REPLACEMENT OF LAMPS OR REPAIRS TO LOW LEVEL LIGHT UNITS

PLANNED LIGHTING MAINTENANCE LTD METHOD STATEMENT & RISK ASSESSMENT REPLACEMENT OF LAMPS OR REPAIRS TO LOW LEVEL LIGHT UNITS PLANNED LIGHTING MAINTENANCE LTD METHOD STATEMENT & RISK ASSESSMENT REPLACEMENT OF LAMPS OR REPAIRS TO LOW LEVEL LIGHT UNITS Project: Insert Client Repair/ Replacement of low level light units/ low level

More information

Extreme Adventure Ltd Risk Assessment

Extreme Adventure Ltd Risk Assessment Extreme Adventure Ltd Risk Assessment Activity Street Slide What are the Injury due to inflatable moving in wind /Spectators/Staff Inflatable weighted down at various points along the length of the slide.

More information

General travel activity overseas on MPS ICCU business

General travel activity overseas on MPS ICCU business Appendix Forms MPS RA BOX 1 Service Branch: SCD1 Names of Assessors: Richard Pooley Assessment No: 1 Assessment Date: 6/7/06 Date of Last Assessment: Review Date: /07/06 Type of Assessment Corporate BOX

More information

Hazard and Risk Assessment Guide

Hazard and Risk Assessment Guide Page 1 Safety legislation in Canada (Occupational Health & Safety Act, Sec. 25) entails employers to do everything that is reasonable to ensure their workers have a healthy and safe workplace. The first

More information

Hazards Requiring Attention: AS AT Friday, 1 April Next Review Saturday, 1 April Total Hazards Recorded 43. Critical Risk Hazards 0

Hazards Requiring Attention: AS AT Friday, 1 April Next Review Saturday, 1 April Total Hazards Recorded 43. Critical Risk Hazards 0 EF26 Risk Assessment Kubota U35-4 s Requiring Attention: AS AT Friday, 1 April 2016 0 Next Review Saturday, 1 April 2017 Total s Recorded 43 Critical Risk s 0 High Risk s 0 Moderate Risk s 10 Low Risk

More information

Risk assessment. Assessment details. Task. Introduction. Please complete the form as fully and accurately as you can. Assessors job title

Risk assessment. Assessment details. Task. Introduction. Please complete the form as fully and accurately as you can. Assessors job title Risk assessment Introduction Please complete the form as fully and accurately as you can. Assessment details Name of organisation Assessor's name Assessors job title Any Company John Smith Manager Date

More information

High Ropes Management Plan

High Ropes Management Plan High Ropes Management Plan Lutanda Mt Victoria School: Year: Dates: Program: Supervising Staff: Activity Context High Ropes is fun way to challenge participants in their confidence, teamwork, decision

More information

Workplace health and safety questions

Workplace health and safety questions Workplace health and safety questions Question 1 (1 Mark) The purpose of Workplace Health and Safety legislation is to promote workplaces: a. free of risk from the of injury or disease b. with only minor

More information

COMPLETION OF PROCEDURE ASSESSMENT FORM (COSHH RELATED) GUIDANCE NOTES (Version 3)

COMPLETION OF PROCEDURE ASSESSMENT FORM (COSHH RELATED) GUIDANCE NOTES (Version 3) COMPLETION OF PROCEDURE ASSESSMENT FORM (COSHH RELATED) GUIDANCE NOTES (Version 3) The following guidance notes accompany the College Procedure Assessment form (COSHH-related). Please complete all applicable

More information

Temporary load-bearing support for structural alterations or repairs

Temporary load-bearing support for structural alterations or repairs CRITICAL NOTE This document only becomes a Safe Work Method Statement where the High Risk Construction Work section of this document is completed Company: ABN: Contact Person: Ph: Project/Site: Principal

More information

Step 3 Existing Control Measures. Step 4 Risk Score & Rating (Table 1) Risk

Step 3 Existing Control Measures. Step 4 Risk Score & Rating (Table 1) Risk RISK ASSESSMENT Department: Serial No: TMED0004 Date: 15/02/2018 Activity/Situation: Below is a general risk assessment for use by school groups visiting the Tank Museum. Museum staff are present in the

More information

Work Health & Safety Event Safety Checklist Small Event

Work Health & Safety Event Safety Checklist Small Event Note: This checklist relates to the Bedford Park site and contains information specific to that site. Other sites can use the checklist but may need to adapt the information. This documentation must be

More information

Health & Safety Risk Assessment (RA) Use of Church facilities by/for: Working & Cleaning Parties

Health & Safety Risk Assessment (RA) Use of Church facilities by/for: Working & Cleaning Parties GJM/DTM Cole Street Assessment Assessment No: RA 008 Health & Safety Assessment (RA) Use of Church facilities by/for: Working & Cleaning Parties For completion by event/group organiser(s)/supervisor(s)

More information

Torridon Giants Trek

Torridon Giants Trek Company: Thistle Trekking LTD Description of Work Activity or Area of the Workplace Assessed: Torridon Area, North West Scotland Compiled by: Oliver Mentz Location: UK Torridon Giants Trek All RA s should

More information

Age Concern Hounslow Manual Handling Risk Assessment PART ONE PRELIMINARY RISK ASSESSMENT

Age Concern Hounslow Manual Handling Risk Assessment PART ONE PRELIMINARY RISK ASSESSMENT Age Concern Hounslow Manual Handling Risk Assessment PART ONE PRELIMINARY RISK ASSESSMENT This checklist is to be used as a preliminary assessment of the work area. If the answer is yes or possibly, then

More information

SAFE WORK METHOD STATEMENT

SAFE WORK METHOD STATEMENT SAFE WORK METHOD STATEMENT AUGER / POST HOLE DIGGER Prepared for Client: Rural Construction & Maintenance Pty Ltd Project No: 1 Site: 660 Great Ocean Road, Bellbrae Date Prepared: 29/07/2015 1. RESPONSIBILITIES

More information

Bogo Operations Pollution Incident Response Management Plan

Bogo Operations Pollution Incident Response Management Plan Bogo Operations Pollution Incident Response Management Plan Rhyolite Hard Rock Aggregate Quarry 134 Paynes Road BOOKHAM NSW 2582 PO Box 426 COWRA NSW 2794 p: 02 6227 7260 p: 02 6345 4253 e: info@bogoquarry.com.au

More information

TEARFUND RISK ASSESSMENT

TEARFUND RISK ASSESSMENT TEARFUND RISK ASSESSMENT Note: Read the guidance notes before you proceed with this risk assessment and do get in touch with your local Tearfund staff member for assistance. Name of volunteer Contact details

More information

Faculty/School: Faculty of Pharmacy Initial Issue Date: Oct 2016

Faculty/School: Faculty of Pharmacy Initial Issue Date: Oct 2016 Use this form to assist you to complete risk assessments for hazardous activities and processes. Any serious or ongoing hazards should be reported via RiskWare to ensure that appropriate corrective actions

More information

Risk Assessment Sheet - Zorb

Risk Assessment Sheet - Zorb isk Assessment Sheet - Zorb Hazard Effec t Possible Cause Notes PS PL F Action Seams parting, tears in the walls of unit or inadequate pressure in the unit 2,3 Improper maintenance When units are packed

More information

Safe Work Method Statement. Hook up and Towing - Risk Assessment

Safe Work Method Statement. Hook up and Towing - Risk Assessment Hook up and Towing - Risk Assessment WORK STRUCTURES ABN: 97142401501 Work Activity/ Task: Hook up & Towing Caravan Address: 4 KAMHOLTZ CRT ASHMORE 4214 QLD Phone: 0404600001 Email: sales@caravans-australia.com.au

More information

University of Lincoln Students Union Annual Risk Assessment for Activities

University of Lincoln Students Union Annual Risk Assessment for Activities University of Lincoln Students Union Annual Assessment for Activities Activity Details Activity Name Climbing Date Of risk Assessment Completion 05/06/16 Assessment Review Date 22/10/16 Ongoing Assessment

More information

COSAO26 Identify workplace health and safety hazards and control risks in asbestos surveying and analysis

COSAO26 Identify workplace health and safety hazards and control risks in asbestos surveying and analysis Identify workplace health and safety hazards and control risks in Overview This unit is about identifying hazards and assessing risks. You will also need to verify and implement methods and procedures

More information

Activity Hazard Analysis (AHA) EM A.13 FIGURE 1-2 CONTRACTOR REQUIRED AHA TRAINING

Activity Hazard Analysis (AHA) EM A.13 FIGURE 1-2 CONTRACTOR REQUIRED AHA TRAINING Activity Hazard Analysis (AHA) EM 385 2008 01.A.13 FIGURE 1-2 CONTRACTOR REQUIRED AHA TRAINING Activity Hazard Analysis (AHA) AHAs: Risk Assessment Tool Defines the Activity or Work to be Performed Identifies

More information

ALIGNING MOD POSMS SAFETY AND POEMS ENVIRONMENTAL RISK APPROACHES EXPERIENCE AND GUIDANCE

ALIGNING MOD POSMS SAFETY AND POEMS ENVIRONMENTAL RISK APPROACHES EXPERIENCE AND GUIDANCE ALIGNING MOD POSMS SAFETY AND POEMS ENVIRONMENTAL RISK APPROACHES EXPERIENCE AND GUIDANCE R. L. Maguire MIMechE MSaRS RS2A Limited Swindon, UK 07505 743 725 rlm@rs2a.com Keywords: POSMS, POEMS, Alignment,

More information

SCHNEIDER AUTOMATIC CIRCUIT RECLOSER JOB SAFETY ANALYSIS

SCHNEIDER AUTOMATIC CIRCUIT RECLOSER JOB SAFETY ANALYSIS Title: Schneider Automatic Circuit Recloser Job Safety Analysis Purpose and Scope: This document describes the tests to be carried out before accepting a new or repaired N and W series Schneider Automatic

More information

Swimming Competition Events

Swimming Competition Events Guidance Notes The setup of any Swimming Competition is generally the responsibility of the Pool Operator and this activity is covered by his Swimming Pool Operating Procedures. There may be a limited

More information

Archery Risk Management Plan Lutanda Yarramundi

Archery Risk Management Plan Lutanda Yarramundi Archery Risk Management Plan Lutanda Yarramundi School: Year: Dates: Program: Supervising Staff: Activity Context The archery range at Lutanda Yarramundi is located next to River Lodge on the left end

More information

Extreme Adventure Ltd Risk Assessment

Extreme Adventure Ltd Risk Assessment Extreme Adventure Ltd Risk Assessment Activity Spider Mountain What are the Fall from height through webbing rings Descend one level at a time. Use webbing levels to halt rapid descent. Matting provided

More information

SAFE WORK METHOD STATEMENT Part 1. Company Details. Company Name: Contact Name, Position and Phone number: Address: Project details.

SAFE WORK METHOD STATEMENT Part 1. Company Details. Company Name: Contact Name, Position and Phone number: Address: Project details. SAFE WORK METHOD STATEMENT Part 1 Company Details Company Name: ABN: Contact Name, Position and Phone number: Address: Project details Project: Area: Job Address: Job Description: Activity: Installation

More information

Risk Assessment for Radio Rogaine

Risk Assessment for Radio Rogaine Risk Assessment for Radio Rogaine Reviews Completed By Revision Date Approved By Approval Date R Shanks 24/07/2018 A Daykin 24/07/2018 171 Nojoor Road Twin waters QLD 4564 P: 1300 122677 Apexcamps.com.au

More information

Safety in Precast Erection

Safety in Precast Erection Safety in Precast Erection C. Kirubakaran R Star Consultants Pte Ltd, Singapore Abstract: Construction industry is known to be one of the most hazardous among different industries all over the world. The

More information

Group Guidance Risk Assessment Form

Group Guidance Risk Assessment Form Group Guidance Risk Assessment Form The following Risk Assessment Form is provided to members only as a template to give ideas of how to fill out your own farm s specifications in this Form. This Form

More information