B2-17. December 6, & COURIER

Size: px
Start display at page:

Download "B2-17. December 6, & COURIER"

Transcription

1 B2-17 December 6, 2005 VIA: & COURIER Mr. Robert J. Pellatt Commission Secretary British Columbia Utilities Commission Sixth Floor, 900 Howe Street Box 250 Vancouver, BC, V6Z 2N3 Dear Mr. Pellatt: Re: ( Sea Breeze VCC ) Application for Certificate of Public Convenience and Necessity ( CPCN ) for Vancouver Island Cable Project ( VIC ) Please find enclosed Sea Breeze VCC s response to the BC Utilities Commission s Information Request No. 2 regarding the Vancouver Island Cable Project. Unless the context requires otherwise, the term Sea Breeze in the attached document refers to Sea Breeze VCC. Sincerely,

2 p.1 Reference: Exhibit B2-8, BCUC IR In response to BCUC IR 1.1.1, Sea Breeze states that it and its parent companies have not yet had a fiscal year-end. What will be the fiscal year end for these companies? December 31, 2005.

3 p.2 Reference: Exhibit B2-8, BCUC IR Please provide the most recent quarterly reports for Sea Breeze and Sea Breeze Pacific Juan de Fuca Cable, LP. If quarterly reports are not available, please provide a statement of Assets, Liabilities, Net Worth and Cash and Cash Equivalents for each company that are as current as possible. Please see statements for Sea Breeze and Sea Breeze Pacific Juan de Fuca Cable, LP, attached as Appendix A. APPENDIX A: Statements.

4 p.3 Reference: Exhibit B2-8, BCUC IR 1.3.6, Further to the responses to BCUC IR and 1.3.7, please confirm that (a) municipal operating or franchise fees and (b) property taxes or payments in lieu of taxes are separate and distinct matters. Although (a) municipal operating or franchise fees and (b) property taxes or payments in lieu of taxes may be separate and distinct matters, Sea Breeze uses these terms together to refer to the total payments to which Sea Breeze would be liable in respect of rights of way over, and access to, public and private property for VIC.

5 p.4 Reference: Exhibit B2-8, BCUC IR 1.3.6, Please explain why Sea Breeze believes that it is likely to pay the same amount of taxes as BCTC ($1.1 million annually). As indicated in Sea Breeze s responses to BCUC IRs and 1.3.7, the amount that Sea Breeze will ultimately pay in municipal operating or franchise fees and property taxes or payments in lieu of taxes is dependent on negotiation with relevant municipalities and the value of property rights to be acquired. At this time, Sea Breeze believes that the figure provided by BCTC provides the best estimate of the total amount of municipal operating or franchise fees and property taxes or payments in lieu of taxes to which VIC would also be subject.

6 p.5 Reference: Exhibit B2-8, BCUC IR 1.3.6, Can Sea Breeze confirm whether or not BCTC pays operating or franchise fees to the municipalities that it passes through? Sea Breeze cannot confirm at this time whether BCTC pays operating or franchise fees to the municipalities that it passes through.

7 p.6 Reference: Exhibit B2-8, BCUC IR 1.3.6, If Sea Breeze were required to pay an operating or franchise fee in the amount of, for example, 1 percent of the value of the electricity transported over its system, what would be the forecast annual amount of the fee in this example? Assuming that Sea Breeze is required to pay municipal operating or franchise fees and property taxes or payments in lieu of taxes, Sea Breeze does not believe that it would be subject to an additional franchise fee in the amount of 1 percent of the value of electricity transported over its system.

8 p.7 Reference: Exhibit B2-8, BCUC IR 1.3.6, In the response to BCUC IR 1.3.7, Sea Breeze states that franchise fees would be a pass through. Nevertheless, in the event that there is a difference in the amounts of operating and franchise fees that BCTC and Sea Breeze would pay, please discuss whether this is a difference that the Commission should consider in its comparison of the two applications. If there is a difference, it is something that the Commission should consider in its comparison. Because the VITR project would be effectively taxpayer and ratepayer financed versus the private equity and debt financing of VIC, it may be that any differences could be accounted for in the treatment of the VIC investors taxes. Also, depending upon the nature of any BCUC orders and subsequent lease/contractual arrangements with BCTC/BC Hydro, this issue may require further legal analysis and negotiation with affected municipal entities. Given that only one project will be deemed to be in the public convenience and necessity, that both projects will be effectively putting cables in existing rights of way, and that an equivalent rate of return impact will be applied, there should not be substantial difference in the level of franchise and/or operating fees.

9 p.8 Reference: Exhibit B2-8, BCUC IR Is Sea Breeze relying on BC Hydro s powers of expropriation to obtain Rights of Way which Sea Breeze would be otherwise unable to obtain? Sea Breeze appears to presume that BC Hydro will cooperate with it with respect to expropriation of property rights. Please provide any documentation that supports this presumption. Sea Breeze is investing considerable resources in negotiating acquisition of the necessary underground rights. Sea Breeze is confident that its proposal to compensate property owners for the current fair market value for the acquisition of a permanent right of way will greatly reduce the likelihood of resorting to expropriation. Sea Breeze understands that to the extent that expropriation of land could be necessary for the VIC Project, it needs to rely on BC Hydro for this action. Please see Sea Breeze s response to BCUC IR

10 p.9 Reference: Exhibit B2-8, BCUC IR As the relationships of BC Hydro to BCTC and Sea Breeze differ in a number of ways, please explain why Sea Breeze believes that BC Hydro would be legally entitled to use its expropriation rights with respect to a transmission facility that will be owned by Sea Breeze. Sea Breeze is investing considerable resources in negotiating acquisition of the necessary underground rights. Sea Breeze is confident that its proposal to compensate property owners for the current fair market value for the acquisition of a permanent right of way will greatly reduce the likelihood of resorting to expropriation. It is Sea Breeze's position that BC Hydro would be legally entitled to use its expropriation rights, if it became necessary for the purpose of construction or operation of the VIC facility, pursuant to the provisions of the Hydro and Power Authority Act.

11 p.10 Reference: Exhibit B2-8, BCUC IR In the event BC Hydro is unable or unwilling to use its expropriation rights for a Sea Breeze transmission facility, please describe how Sea Breeze will deal with such a contingency. Sea Breeze is investing considerable resources in negotiating acquisition of the necessary underground rights. Sea Breeze is confident that its proposal to compensate property owners for the current fair market value for the acquisition of a permanent right of way will greatly reduce the likelihood of resorting to expropriation. Please see Sea Breeze s response to BCUC IR Should BC Hydro be unwilling to use its expropriation rights for a Sea Breeze transmission facility, Sea Breeze would seek further directions, and may apply for an order, from the Commission.

12 p.11 Reference: Exhibit B2-8, BCUC IR Does Sea Breeze have any authority to expropriate access for its right of way? If yes, please explain the basis for this authority. Sea Breeze is investing considerable resources in negotiating acquisition of the necessary underground rights. Sea Breeze is confident that its proposal to compensate property owners for the current fair market value for the acquisition of a permanent right of way will greatly reduce the likelihood of resorting to expropriation. Please see Sea Breeze s response to BCUC IR

13 p.12 Reference: Exhibit B2-8, BCUC IR Has Sea Breeze obtained any advice with respect to its ability to expropriate? If so what advice was obtained? Any legal advice obtained by Sea Breeze with respect to its ability to expropriate is subject to solicitorclient privilege.

14 p.13 Reference: Exhibit B2-8, BCUC IR The response to BCUC IR refers to costs in SEK. Please identify this currency, and provide a list of the currency exchange rates to Canadian dollars by month for the past five years, and the current forecast exchange rate for at least the next three years. The SEK is the Swedish Krona and the table attached as Appendix shows the breakdown of the past month-to-month exchange rates between the Canadian Dollar and the Swedish Krona. Sea Breeze VCC has calculated the forward rates for hedging based on the spot rate of 6.82, for the next three years to mitigate the risk of foreign currency exchange. APPENDIX A: Table showing exchange rates between Canadian Dollar and Swedish Krona.

15 p.14 Reference: Exhibit B2-8, BCUC IR Further to the reference to a 20 month project schedule, please reconcile this with the 15 month construction schedule identified on page 171 of the VIC Application, and provide confirmation from ABB that the VIC Project Schedule in the VIC Application (Exhibit B2-1) is consistent with the cost estimate in the IR response. The 20 month project schedule provided in response to BCUC IR refers to lines 110 through 161 of Figure found in the VIC Application. This period includes procurement, detailed design, DMS, construction, and testing. Approximately five months prior to receiving the environmental authorizations to proceed with construction, procurement, early detailed design, and DMS for the cables and converter stations will take place. Following the receipt of environmental approvals, construction can begin, having a duration of approximately 15 months.

16 p.15 Reference: Exhibit B2-8, BCUC 1.8.5, 1.9.3, 1.9.6, Further to the statement that the ABB cost estimate has an accuracy of ± 15 percent, please explain why a contingency allowance of zero is appropriate for this amount, rather than 15 percent of $278.5 million. Upon signing the EPC contract the price becomes fixed and any potential cost over-runs are to be covered by EPC contract supplier. The EPC contract effectively provides a not to exceed price for the items within its scope. Therefore, a contingency allowance is only appropriate for the items outside the scope of the EPC contract.

17 p.16 Reference: Exhibit B2-8, BCUC 1.8.5, 1.9.3, 1.9.6, While Sea Breeze may eventually negotiate a fixed price for the project, the requirement at this stage of the review of the CPCN Application is a cost estimate that reasonably covers the uncertainties in the project. In the absence of sufficient independent cost estimates to provide a statistically significant probability distribution, in similar circumstances others have applied Monte Carlo concepts to generate a P90 estimate. Please provide a P90 estimate for VIC. Response forthcoming.

18 p.17 Reference: Exhibit B2-8, BCUC 1.8.5, 1.9.3, 1.9.6, If the Commission were to approve a CPCN for VIC subject to the final actual cost being within 10 percent of some specified cost forecast, with Sea Breeze s owners to be responsible for over-runs in excess of 10 percent, what is the amount of the specified cost forecast that would be appropriate for this purpose? Sea Breeze VCC is willing to meet with the Commission to negotiate this cost.

19 p.18 Reference: Exhibit B2-8, BCUC IR , Further to the response to BCUC IR , if one assumes that a HVDC Light facility built for BCTC would have the same cost as an identical facility built for Sea Breeze (and noting that BCTC would be expected to operate both facilities), would Appendix B represent the Annual Rate Impact of VIC if it were owned by BCTC? If not, please explain any differences. Sea Breeze believes this is a question better addressed to BCTC. There would be a difference in cost if VIC were built and owned by BCTC. The reason of such variation remains in the fact that two entities differ in terms of their ownership/governance that consequently affects their abilities/conditions to raise funds, maintain financial ratios, etc. We believe that the following factors, among others, will affect the cost variation: allowable rate of return; allowable debt/equity ratio; cost of debt; municipal tax treatment; insurance; and overheads.

20 p.19 Reference: Exhibit B2-8, BCUC IR , In response to BCUC IR 1.2.2, Sea Breeze states that BCUC may determine a revenue requirement for it in accordance with normal regulatory principals. As BCUC is under certain Special Directions with respect to the regulation of BCTC and BC Hydro, does Sea Breeze believe that the Commission s regulation of VIC would mimic its regulation of BCTC and BC Hydro? If yes, please explain the basis for this belief. See Breeze believes that the regulatory process and concepts will be the same, however, the regulation of VIC would not mimic that of a project built by BC Hydro or BCTC. There are few Special Directions issued by the Province of British Columbia that regulate BC Hydro and BCTC financial responsibilities, revenue requirements, Deferral Accounts, financial ratios and set the frameworks for BCUC to oversee the compliance of BC Hydro and BCTC with the above said directions. These are not applicable to Sea Breeze. Sea Breeze expects that conceptually the regulation of Sea Breeze VCC by BCUC should be the same as that of BCTC in regard to revenues requirements and establishment of Deferral Accounts; however, it cannot completely mimic the approach since BCTC and Sea Breeze VCC are entities with different types of ownership and mandate. We believe that in this aspect Sea Breeze is closer to FortisBC and expect that the application of governance of Sea Breeze will be consistent with the same approach BCUC exercise in regard to FortisBC.

21 p.20 Reference: Exhibit B2-8, BCUC IR , The response to BCUC IR , specifically Appendix B for VIC owned by Sea Breeze, uses a capital structure that initially is 28.4 percent equity, an equity charge of percent before tax and a debt cost of 6.70 percent. Further to the response to BCUC IR 1.2.1, what is the equity component and average cost of debt for each of the Path-15 Project and the Neptune Project? Neptune s cost of debt is approximately 6%, with 15% equity in the capital structure. However, Path-15 had a higher cost of debt of roughly 8 to 9% due to the higher interest rates in 2003, (compared to Neptune in 2005). Sea Breeze is of the understanding that Path 15 was financed on a 50/50 debt-equity ratio which is typical for investor-owned utility projects.

22 p.21 Reference: Exhibit B2-8, BCUC IR , If an approved equity change percentage has been established for either of the Path-15 Project or the Neptune Project, please provide this information. Sea Breeze VCC is not privy to this information.

23 p.22 Reference: Exhibit B2-8, BCUC IR , Please restate Appendix B in a form that assumes the debt/equity structure and return on equity that Sea Breeze would propose for regulation of VIC by BCUC, that depreciation will reduce both debt and equity pro rata and a cost of debt equal to what Sea Breeze forecasts that its actual cost of debt will be. Response forthcoming.

24 p.23 Reference: Exhibit B2-8, BCUC IR , Further to the response to BCUC IR 1.2.1, please provide non-confidential confirmations from Energy Investors Funds ( EIF ) and Société Générale ( SG ) that they are prepared to finance VIC under the terms set out in the proceeding question. Both EIF and SG have submitted letters dated December 6, 2005 to Sea Breeze on a confidential basis confirming their confidence in the project s financeability. In these letters, both confirmed to Sea Breeze their willingness to discuss the contents of their letters with BCUC and to permit their disclosure on a selective basis. In addition, it should be noted that to date, EIF has invested USD $2.5 million in transmission project development in British Columbia and has allocated an additional USD $1 million specifically for prosecution of the VIC CPCN.

25 p.24 Reference: Exhibit B2-8, BCUC IR , The response to BCUC IR identifies several conditions precedent to trigger full equity commitment and issuance of debt. Please provide confirmations from EIF and SG of the level of completeness and development of detail of each of the following that each funding party will require before agreeing to finance VIC: (a) CPCN approval, (b) Order directing BCTC to use VIC, (c) Sea Breeze service (lease and operating) agreement with BCTC, (d) BCUC approval of the revenue recovery mechanism for VIC, (e) BCUC determination of prudency of VIC incurred costs. Please see response to BCUC IR

26 p.25 Reference: Exhibit B2-8, BCUC IR , In the absence of a service (lease and operating) agreement between Sea Breeze and BCTC and an approved revenue mechanism for VIC that are acceptable to EIF and SG, how can the Commission have confidence that they will provide funding and that the project is feasible? Based on Energy Investors Funds experience as an equity investor and Société Générale s experience as advisor and lender to independent transmission projects that have been successfully developed in North America, we expect a similar revenue mechanism can be created to provide sufficient cash flows to cover debt service and equity returns. Using the Path 15 Upgrade project in California as an example, the Federal Energy Regulatory Commission approved a 13.5% after-tax rate of return that was also ultimately accepted by the California Public Utilities Commission. The 13.5% rate of return allowed for recovery of all eligible and prudent project development and construction costs, debt service based on a 50 / 50 debt/equity structure (typical for the US electric utilities), and taxes. A similar rate structure was recently approved for the TransBay Project, proposed to run between the City of Pittsburgh, California, and San Francisco.

27 p.26 Reference: Exhibit B2-8, BCUC IR , An obvious concern if the Commission approves a CPCN for VIC and denies one for VITR is the impact on customer service on Vancouver Island if Sea Breeze does not proceed with VIC. Is Sea Breeze prepared to put in place in favour of BCTC a sufficient performance bond (which could perhaps be drawn down as the project proceeds) to guarantee completion of the project? The risk of negative impact to customer service on Vancouver Island is not exclusive tovic. For example, continuing community opposition following issuance of a CPCN for the VITR proposal could equally result in delays, or non-completion, of the VITR project. One measure which could mitigate the risk of excessive delays or non-completion of the VIC project would be a reservation for capacity on the Juan de Fuca Cable (See BCUC IR ). Non-completion during construction under an EPC contract is customarily addressed by the contractor s guarantee or performance bond. Prior to commencement of construction, Sea Breeze would be agreeable to the posting of a Letter of Credit, or a performance bond that would allow for compensation related to lost deposits on capital orders, in the event of noncompletion.

28 p.27 Reference: Exhibit B2-8, BCUC IR , What does Sea Breeze believe would be the appropriate amount of such a performance bond? The Letter of Credit, or a performance bond would allow for compensation related to lost deposits on capital item orders, in the event of project non-completion prior to commencement of construction.

29 p.28 Reference: Exhibit B2-8, BCUC IR , In addition to approval of a CPCN, what steps would need to be completed prior to the posting of the performance bond and how long would these be expected to take after approval of the CPCN? Assuming the function of the performance bond is to protect against non-completion during development, the performance bond could be implemented immediately following issuance of the CPCN, and a corresponding rate making tariff being authorized.

30 p.29 Reference: Exhibit B2-8, BCUC IR , In response to BCUC IR , Sea Breeze states the relationship between Sea Breeze and BCTC would be governed by terms and conditions similar in principle to those existing between BC Hydro and BCTC. As discussed at the November 10, 2005 Pre-hearing Conference, it is essential that the Commission have a clear and complete understanding of the costs, risks and balancing of rights and obligations for BCTC and its ratepayers, in the event a CPCN is approved for VIC. As requested in BCUC IR , please file a draft or pro forma service agreement that Sea Breeze proposes for service to BCTC, which defines the relationship between the parties and sets out the terms and conditions of service and the rates for service. If the rates are expressed on a conceptual basis with the amounts to be determined by the Commission at a future date, please provide Sea Breeze s estimate of what this amount would be based on current information. Please include a schedule showing how the rates were calculated. Response forthcoming.

31 p.30 Reference: Exhibit B2-8, BCUC IR In the response to BCUC IR , Sea Breeze states that it will order an extra transformer as a stand by. What would be the cost of the extra transformer, does Sea Breeze expect its charges to BCTC would cover this cost, and is the cost included in the VIC cost estimate? The cost for HVDC converter stations includes one single phase spare transformer located at each site.

32 p.31 Reference: Exhibit B2-8, BCUC IR Further to the response to the proceeding question and to the responses to BCUC IR and regarding the cost of the converter station sites, please provide a revised VIC cost estimate that includes all updated cost information, and identify all changes in the cost estimate. Due to the latest change in exchange rate from to 0.15 between SK to $CDN, Sea Breeze revised the following estimates received from ABB in SK: Turnkey installation of HVDC converters $120,000,000 Submarine cables $54,800,000 Transport, Installation, Testing of cables $40,500,000 U/G cables $41,300,000 Additionally the cost of land for converter stations is estimated as follows: Ingledow $365,000 Pike Lake $

33 p.32 Reference: Exhibit B2-8, BCUC IR , Sea Breeze states in the response to BCUC IR that there may not be any cost to wheel power from the BC/US Border to Port Angeles if DSB agreements were amended to include Port Angeles as a delivery location for DSB. In response to BCUC IR , Sea Breeze states that Vancouver Island energy will be supplied from existing BC Hydro generation. If one assumes that delivery of DSB to Port Angeles is not feasible, what would it cost to wheel power from the BC/US Border to Port Angeles? It should be emphasized that Sea Breeze VCC is not aware of any practical reason why it would not be feasible (with the agreement and cooperation of the BC Government, BC Hydro, Powerex and BPA) to return a portion of the Province s Downstream Benefits through a new delivery point at Port Angeles via the Juan de Fuca Cable. Indeed, Sea Breeze VCC believes that, once the Juan de Fuca Cable is connected, the existing arrangements pertaining to the DSBs may be sufficient to allow Port Angeles to be considered as part of the western interconnection. And, even if that is not the case, BC Hydro and BPA both will have an incentive to enter into negotiations to ensure that Port Angeles can be used as a delivery point for DSBs: from BC Hydro s perspective, to ensure that when energy supply is needed on Vancouver Island in a contingency situation, it can be supplied from DSBs through the Juan de Fuca line; and, from BPA s perspective, because this will aid in addressing existing difficulties in delivering DSBs through the Blaine intertie during winter peaking resulting from BC Hydro s withdrawal from the Puget Sound area curtailment agreement. It should also be emphasized that, even if there were some unforeseen obstacle to returning the DSBs at Port Angeles, Powerex also regularly purchases additional energy from the US and wheels it through the BPA system as part of its usual operations, either for resale to the market at a time when the price is favourable (which Powerex can do by taking advantage of BC Hydro s storage capacity) or for the purpose of satisfying power deficit situations which arise from time to time on BC Hydro s Provincial system. There would be nothing to prevent Powerex from scheduling a portion of the energy it purchases in any event at Mid-C to be delivered at the Port Angeles-Juan de Fuca Cable interconnection point. Wheeling power from the BC-US border to Port Angeles provides a third option for ensuring south to north supply will be available on the Juan de Fuca line when it is needed to address a contingency situation on Vancouver Island. This will be a viable option because of the BPA system upgrades which are

34 p.33 contemplated between Blaine and Port Angeles as part of the Juan de Fuca Project (see response to BCUC IR ). BPA Transmission Rates as of October 1, 2005 are as follows: A. LONG-TERM FIRM PTP TRANSMISSION SERVICE: $1.216 per kilowatt per month B. SHORT-TERM FIRM AND NON-FIRM PTP TRANSMISSION SERVICE For each reservation, the rates shall not exceed: 1. Monthly, Weekly, and Daily Firm and Non-Firm Service a. Days 1 through 5 $0.056 per kilowatt per day b. Day 6 and beyond $0.043 per kilowatt per day 2. Hourly Firm and Non-Firm Service 3.50 mills per kilowatthour ($3.5/MWh) In any event, this third option would only rarely need to be used, in a Vancouver Island contingency situation, and only if power could not, for some reason, either be obtained through the return of DSBs, or purchased by Powerex, at a Port Angeles delivery point. However, to the extent additional costs might arise to wheel power from the BC-US border to Port Angeles, Sea Breeze accepts they should be taken into account in negotiating/determining the price to be paid by BCTC to purchase or lease firm south to north transmission capacity on the Juan de Fuca line, to ensure that ratepayers will realize the benefit of Sea Breeze s proposal to sell or lease that capacity at a negotiated price based in principle on a discount from BCTC s VITR revenue requirement, plus an additional credit for system benefits (see Sea Breeze s responses to BCUC IRs , , (VIC) and BCUC IR (VITR)).

35 p.34 Reference: Exhibit B2-8, BCUC IR , If BC Hydro were to purchase power for Vancouver Island at Mid-C, what would it cost to transport or wheel such power to Port Angeles (on a unit basis)? This qwuestion may be better addressed to BC Hydro/Powerex. Sea Breeze believes that if BC Hydro/Powerex were to purchase power at Mid-C for delivery to Vancouver Island via the Port Angeles- Juan de Fuca Cable interconnection, there should be no additional price payable to BPA for transmission service beyond what would be payable in any event for delivery of the same quantity of power to British Columbia via the Blaine intertie.

36 p.35 Reference: Exhibit B2-8, BCUC IR , In response to BCUC IR , Sea Breeze states that BPA has initiated an Interconnection Facilities Study. Will this study address all BPA system upgrades required to move power at the rated capacity both north and south on the Juan de Fuca system? BPA system upgrades required in connection with the Juan de Fuca line were identified in BPA s System Impact Study (see Sea Breeze s response to BCUC IR (VIC) and BCUC IR (VITR)). Sea Breeze expects the Interconnection Facilities Study to address the cost of those upgrades.

37 p.36 Reference: Exhibit B2-8, BCUC IR , When will the study be completed? The System Impact Study has been completed (see Sea Breeze s response to BCUC IR (VITR)). The Interconnection Facilities Study has not yet been completed, but Sea Breeze does not anticipate it causing in delays in the Juan de Fuca Project.

38 p.37 Reference: Exhibit B2-8, BCUC IR , At this time, what is the excess firm capacity that is available at Port Angeles that could flow to Vancouver Island if the Juan de Fuca line were in operation? The System Impact study for the Sea Breeze DC Interconnection completed by ABB for BPA details the firm capacity as it is currently as well as what is planned after the Olympic Peninsula network is reinforced. The actual capability may vary with the time of year as well as the area load.refer to Sea Breeze s response to BCUC IRs and (VIC), as well as BCUC IR (VITR) above. Olympic Peninsula Existing Network Summer Contingency Nomogram- All Limits

39 p.38 Olympic Peninsula Existing Network Winter Contingency Nomogram All Limits

40 p.39 Olympic Peninsula Level 2 Reinforcements Network Summer Contingency Nomogram- All Limits Base Nomogram - Summer: All Limits Considered DC Tie Export (MW) DC Tie Im port (MW) Peninsula Load (MW)

41 p.40 Olympic Peninsula Level 2 Reinforcements Network Winter Contingency Nomogram All Limits

42 p.41 Reference: Exhibit B2-1, pp , Exhibit B2-8, Response to IRs 1.2.1, 1.2.2, 1.2.3, Please further clarify the exact nature of the order that Sea Breeze is seeking, preferably by providing a draft Order. Response forthcoming.

43 p.42 Reference: Exhibit B2-1, pp , Exhibit B2-8, Response to IRs 1.2.1, 1.2.2, 1.2.3, In view of the timely resolution required for the Vancouver Island power supply challenge, please confirm what issues related to rates and terms of service, if any, Sea Breeze believes should be a part of this proceeding. Response forthcoming.

44 p.43 Reference: Exhibit B2-1, p. 202, Exhibit B2-8, Response to IR Please confirm whether the Sea Breeze cost of capital is relevant to the project selection. Sea Breeze VCC believes that the cost of capital is relevant to the project selection. However, Sea Breeze believes the project capital cost to be the dominant determining factor.

45 p.44 Reference: Exhibit B2-1, p. 202, Exhibit B2-8, Response to IR Please indicate over how many years Sea Breeze expects to recover its investment. In other words, what is the expected average annual depreciation rate? Sea Breeze VCC expects to match the investment recovery period with the life of debt facility. Currently, the annual depreciation charge is based on the 40 years life of debt and amounts to 2.5% per year.

46 p.45 Reference: Exhibit B2-1, p. 202, Exhibit B2-8, Response to IR Please indicate the term of the contract Sea Breeze expects to negotiate with BCTC. The term of the contract will be tied to the amortization life of the debt facility. The amortization life of the debt facility is expected to be 40 years.

47 p.46 Reference: Exhibit C31-10, BCUC IR 1.5.1, Appendix 1.5.1A, BCUC IR Appendix 1.5.1A is the Sea Breeze Market Rate Authority application to FERC. At page 4 it states: BPA is projecting a capacity deficiency to occur under an N- 1 reliability criterion around on the Olympic Peninsula, where the south end of the Juan de Fuca Project would interconnect and to which the Juan de Fuca Project could deliver power Please confirm that by 2008/09 BPA expects to be constrained in its capacity to deliver power to serve the existing load on the Olympic Peninsula, specifically in the Port Angeles area, or explain what the statement means. The statement as made by Sea Breeze is believed to have been correct. The ABB Interconnection System Impact Study has identified reinforcements that are necessary to implement the JdF project. See Sea Breeze s response to BCUC IR (VIC). BPA subsequently indicated in its August 19, 2005 FERC filing concerning the Juan de Fuca Project that it does not agree that it has projected a capability deficiency under N-1 reliability criterion around based on current planning assumptions for the Olympic Peninsula (page 2 of Appendix A of Sea Breeze s response to BCTC IR (VITR)). Sea Breeze Pacific Juan de Fuca Cable, LP commented further on BPA s filing in its August 24, 2005 FERC filing (Appendix B of Sea Breeze s response to BCTC IR (VITR)). See also Sea Breeze s response to BCUC IR (VIC).

48 p.47 Reference: Exhibit C31-10, BCUC IR 1.5.1, Appendix 1.5.1A, BCUC IR In the foregoing circumstances and without reinforcement of the BPA system, would it be possible for BC Hydro or others to contract firm capacity on the BPA system to deliver power to Port Angeles? If yes, please explain. If BPA were constrained in its capacity to deliver power to serve the existing load on the Olympic Peninsula, it would not be possible for BC Hydro or others to contract long-term firm capacity on the BPA system to deliver power to Port Angeles without reinforcement of the BPA system. However, short term firm and non-firm capacity could possibly be available.

49 p.48 Reference: Exhibit C31-10, BCUC IR 1.5.1, Appendix 1.5.1A, BCUC IR In the foregoing circumstances, please explain how the Juan de Fuca project will contribute to providing power to Vancouver Island under peak load conditions. All required upgrades to the BPA system needed to ensure that sufficient firm capacity will be available on the BPA system to allow power to be moved at the rated capacity both north and south on the Juan de Fuca line will be completed as part of the Juan de Fuca Project. This would include any capacity that BC Hydro/Powerex or others may wish to purchase or lease for the export of power to the United States through Port Angeles. (See also response to BCUC IR (VIC).)

50 p.49 Reference: Exhibit B2-8, IR Response In view of the sentiments expressed in Exhibit C19-1 for VITR does Sea Breeze wish to restate that it is confident that no material impediments exist with respect to municipal agencies? If yes please explain how Sea Breeze will satisfy the concerns of White Rock. Initial discussions with White Rock prior to submission of the Application indicated that there were no material impediments to the project. After the application was submitted, Sea Breeze undertook a presentation to White Rock City Council on September 26, In its letter marked as Exhibit C19-1 (VIC), now Exhibit C57-1, the City identifies its concerns with the VIC Project. The three concerns underlying the City Council s opposition to the VIC project are as follows: 1) Disruption to City streets; 2) Loss of parking space; and 3) Discussions and approvals with FREMP. Discussions with residents during the initial public meeting identified possible alternatives to the proposed route which would reduce the impact to City streets. Sea Breeze is currently reviewing these alternatives. Disruption to parking areas would be minimized by scheduling work during the non-peak fall or early spring period. See Sea Breeze s response to BCTC IR Since Sea Breeze s presentation to White Rock City Council, Sea Breeze has held discussions with FREMP which has advised that it would likely become an active participant in the environmental assessment process, which will be led by the BC Environmental Assessment Office. Accordingly, the City s concern that FREMP will oppose the project may be premature. In addition, Sea Breeze has met with members of several environmental non-governmental organizations (ENGOs) in the White Rock and Surrey area on November 23, 2005, including members of the Boundary Bay Conservation Committee, the White Rock Ratepayers Association, Friends of Semiahmoo Bay, and White Rock and Surrey Naturalists. Members of Sea Breeze s environmental team were in attendance including a marine biologist, wildlife biologist, civil engineer, and consultation consultant. This meeting focused on several issues of concern to these groups, and opportunities for information sharing were identified. Based on the above information, Sea Breeze believes that it will be able to address the City s concerns

51 p.50 such that there will not be any material impediments with respect to municipal agencies.

52 p.51 Reference: Exhibit B2-8, IR Response Does Sea Breeze have any alternate routes with respect to the landfall at White Rock? If so please describe. What additional costs would be incurred? Two other landfall sites were considered: Semiahmoo Park Adam/Beecher Road at Crescent Beach The landfall at Semiahmoo Park was considered less feasible due to: Construction in Semiahmoo Park Proximity to Cambell River Estuary Potential First Nations Archaelogical issues. First Nations consultation issues. The HDD drill length would be approximately 1400m to reach the same depth as the proposed White Rock HDD location. The estimated costs for HDD at this landfall location are estimated to be 50% to 100% greater than the current location. The landfall at Beecher/Adams Avenue was considered less feasible due to: The HDD drill length would be approximately 4920m to reach the same depth as the proposed White Rock HDD location. This length is unfeasible for HDD cable pullback and excavation in intertidal areas with high environmental and ecological issues would have to be considered. The costs for this option were not estimated by Sea Breeze in its evaluation of this potential landfall location since the HDD installation is not feasible.

53 p.52 Reference: Exhibit B2-8, IR Response Sea Breeze states that it is willing to negotiate a near term not-to-exceed turnkey price if the Commission wishes If the Commission were to set a cap on recoverable costs at the best estimate of Sea Breeze, would Sea Breeze be able to secure financing for the project? What is this estimate? Please see Sea Breeze s response to BCUC IR

54 p.53 Reference: Exhibit B2-8, IR Response Is Sea Breeze aware of any limitations for BC Hydro in returning the DSB s? If so please explain. It is Sea Breeze s understanding that: the DSBs are owned by the Province of British Columbia and managed/marketed by Powerex on the Province s behalf; Powerex has the option to take delivery of the Province s DSB entitlement either at the Canada-US border or at points in the United States; and there are certain restrictions governing the amount of power that can be delivered to the eastern and western interconnections, but it is believed that the majority of power is returned at the western interconnection. Sea Breeze believes the existing arrangements pertaining to the DSBs may be sufficient to allow Port Angeles to be considered as part of the western interconnection, and that, even if that is not the case, the parties involved could negotiate the return of a portion of the DSBs via a new delivery point Port Angeles, and in fact would have a strong incentive to do so (see responses to BCUC IRs and (VIC)).

55 p.54 Reference: Exhibit B2-8, IR Response In assuming that BC Hydro could return the DSB s through the Juan de Fuca route, has Sea Breeze considered what would be the additional costs for wheeling through BPA and the Sea Breeze Systems? If so, please provide an estimate (per MWH). If not, please explain why not. Assuming Port Angeles could be used as a western delivery point for DSBs, there should be no additional wheeling cost for DSBs returned via the Port Angeles-Juan de Fuca Cable interconnection. Should negotiations to include Port Angeles as a delivery location for DSB fail, Powerex can request transmission on direction Blaine/Port Angeles when actual delivery is required. The cost of wheeling power will be determined by BPA wheeling charges applicable at that time. Currently BPA wheeling charges are not to exceed USD 3.5/MWh for hourly firm and non-firm transmission and for long-term transmission USD / KW-month (USD 1.67 / 100% load factor).

56 p.55 Reference: Exhibit B2-8, IR Response Has Sea Breeze been made aware of any ongoing discussions between BPA, BC Hydro and BCTC with regard to the possible use of the Juan de Fuca project and in particular the return of the DSB s? Please explain. Sea Breeze has no firsthand knowledge of specific discussions in relation to the use of the Juan de Fuca Project and the return of downstream benefits on that line. However, given the benefits of another potential intertie between British Columbia and Washington State that will arise from the construction of the Juan de Fuca Project, and given that these parties continually interact in relation to inter-jurisdictional operational and planning issues, it is highly unlikely that discussions surrounding the Juan de Fuca line including issues relating to the DSBs have not been discussed. Sea Breeze has also received a news release indicating that Powerex has withdrawn from the Puget Sound Area curtailment protocol (a regional response to curtailment order needed when BPA is returning downstream benefits during winter peaking). Given this development it would be very advantageous for the parties to discuss the possibility of returning downstream benefits through the Juan de Fuca line to relieve congestion in the Puget Sound area.

57 p.56 Reference: Exhibit B2-8, IR Response Please explain the basis for Sea Breeze s belief that discussions between the parties above were concerning the DSB s. See response to BCUC IR

58 p.57 Reference: Exhibit B2-8, IR Response Does the response to this IR cover Sea Breeze s response to IR in Exhibit C31-10 regarding Intervenor Evidence in Exhibit C31-6? If not please explain what further response will be forthcoming. Sea Breeze s response to this IR augments Sea Breeze s answer to BCUC IR (VITR).

59 p.58 Reference: Exhibit B2-8, Response to BCUC IR Please describe the specific amounts and anticipated times of contributions by Sea Breeze Power Corp., Boundless Energy NW, Inc., and the United States Power Fund. Response forthcoming.

60 p.59 Reference: Exhibit B2-8, Response to BCUC IR What is the specific amount of the cumulative contribution made by United States Power Fund, and has it already been made? Please refer to BCUC IR United States Power Fund has made an unconditional commitment for an initial contribution of US$1 million to be applied towards completion of the CPCN for VIC. Receipt of funds by Sea Breeze is expected during the week of December 5, 2005.

61 p.60 Reference: Exhibit B2-8, Response to BCUC IR Considering the Juan de Fuca Cable Project appears to be technically capable of meeting the current needs of electrical supply to Vancouver Island, the two extremes of the transmission cost would be the market opportunity cost on the high end, and the recovery of investment and rate of return on the low end. Has Sea Breeze made an evaluation of what this range is likely to be, and if so, would it provide this information? Although it is technically correct that there are two potential "extremes of the transmission cost", Sea Breeze has not specifically evaluated the two extremes referred to in the question. Sea Breeze is proposing that BCTC acquire the south to north capacity on the Juan de Fuca Project to alleviate the transmission deficiency anticipated for Vancouver Island. An embedded cost analysis in these circumstances is not relevant. The opportunity costs to BCTC (deferral of VITR and other system costs) is a better measure, hence Sea Breeze's proposal that BCTC be charged a fraction of these costs.

62 p.61 Reference: Exhibit B2-8, Response to BCUC IR Please describe the negotiations and other steps that have been taken to contractually enable the interconnection of the Juan de Fuca Cable Project to BPA and the provincial transmission grid, and the remaining contractual steps, and their timelines, which need to be satisfied to realize the interconnection. The procedures for interconnecting the Juan de Fuca Cable project to the BPA and BCTC grids are detailed in the respective agencies OATTs and Interconnection Procedures. There is little or no negotiation involved other than in the study scopes that direct what interconnection and system upgrade alternatives are to be considered. At this point, the Project has completed the Interconnection System Impact Study with BPA and has started the Facilities Study process. Following the completion and acceptance by the Project of the Facilities Study it will be tendered an Interconnection Agreement. The BPA Facilities Study is tentatively scheduled to take from 90 to 120 days to complete. The same general procedures are followed by BCTC. The project has not as of this date entered into discussion with BCTC on the scope of the Interconnection System Impact Study. Once initiated, this study would take about 90 days to complete, and it would be followed shortly thereafter by a Facilities Study, also requiring about 90 days. BCTC s OATT makes provisions for combining the Interconnection and Facilities Studies into one process.

63 p.62 Reference: Exhibit B2-8, Response to BCUC IR On what principles would uncontracted available capacity on the Juan de Fuca Cable project be made available for post-contingency response purposes, and what capability would system operators have to dispatch this unused capacity? Any short term uncontracted capacity on the Juan de Fuca Cable Project would be made available on the OASIS systems of the interconnected utilities. In this regard, it would be presumed to be available to the operator for whatever purposes were deemed appropriate, whether for economy interchange, contingency response or other. Similarly, any short-term overload capacity would be made available for grid operating contingences on a priority basis. The project would seek to hold additional open seasons or contract negotiations for any long term uncontracted capacity.

64 p.63 Reference: Exhibit B2-8, Response to BCUC IR Please describe Sea Breeze s preferred method of real-time control of the proposed Juan de Fuca Cable Project. The daily exchange of power across the Port Angeles-Pike Lake link would be controlled in essentially the same way as the Ingledow-Custer link, by the control centres of BCTC and BPA. The general conditions of exchange, as far as MW flow in given periods, either seasonally or daily are concerned, and conditions for emergency exchange during contingencies in either of the two systems are concerned, will need to be governed by an agreement between BCTC, BPA and Sea Breeze. Sea Breeze is interested in negotiating an agreement to provide BCTC with real time control over the Juan de Fuca line.

65 p.64 Reference: Exhibit B2-8, Response to BCUC IR In the event of a supply shortage on either side of the proposed Juan de Fuca Cable Project due to multiple contingencies, please describe what would prevent any unused capacity of the project, if in service, from being dispatched, if technically possible, to relieve the supply shortfall. Consistent with the response to BCUC IR (VIC), the action taken by the respective control centres to provide mutual assistance during multiple or any other unforeseen contingencies, will need to be governed by an agreement between BCTC, BPA and Sea Breeze. Unlike AC technology, the HVDC Light technology is fully controllable and Sea Breeze would expect the operator to be able to abide by the contractual obligations in place.

66 p.65 Reference: Exhibit B2-8, Response to BCUC IR Please explain why the Converter Station Site value of Converter Station ID A (described as north of Ingledow) is so much less than the Converter Station Site values of Converter Station IDs B, C, and D (described as south of Ingledow). The difference in estimated value is related to the per hectare price for the parcels estimated from the total property area. For the parcel containing Site A, the per hectare value is $243,243/ha and for the parcel containing Sites B, C, and D the value is $737,156.53/ha. Sea Breeze does not know the underlying reasons for the difference in the 2005 Assessed Land Values.

67 p.66 Reference: Exhibit B2-8, Response to BCUC IR Please provide a detailed line item estimate showing labour, material, equipment and indirect costs for each line item for the $2.0 million cost of the interconnection to the Ingledow Substation. With reference to response to BCUC IR 1.7.4, the following is breakdown of the interconnection cost to the Ingledow Substation: Major electrical equipment $610,000 Other material and P&C equipment $400,000 Labour and contracts $540,000 Subtotal $1,550,000 Engineering $150,000 Contingencies $300,000 Total $2,000,000

68 p.67 Reference: Exhibit B2-8, Response to BCUC IR Has Sea Breeze prepared an estimate of the fibre optic line for internal purposes? If yes, please provide it. Sea Breeze VCC estimates for the fibre optic cable option, for internal purposes, is approximately $400,000.

69 p.68 Reference: Exhibit B2-8, Response to BCUC IR The cash flow profile shows considerable expenditures in April of 2006 and Are there corresponding performance bonds proposed to be posted by the contractor, to enable recovery of those expenditures for non-performance? Yes. The EPC contract will include an outline of performance guarantees and non-performance penalties.

70 p.69 Reference: Exhibit B2-8, Response to BCUC IR On what basis did Sea Breeze determine that 2010 was a reasonable time for replacement of all the VIT synchronous condensers? In the absence of better information from BCTC, the year 2010 was chosen based on the assumption that these old rotating machines, operating beyond their reasonable life expectancy, will be due for replacement in 2010 when two synchronous condensers will be 43 years old and the other two will be 33 years old. Sea Breeze has also assumed that it would be more economical to replace all of them at the same time with SVC of equivalent capacity to provide system support required to be available for VITR project.

R.H. Hobbs, Chair N.F. Nicholls, Commissioner October 6, 2006 L.A. O Hara, Commissioner O R D E R

R.H. Hobbs, Chair N.F. Nicholls, Commissioner October 6, 2006 L.A. O Hara, Commissioner O R D E R BRITISH COLUMBIA UTILITIES COMMISSION ORDER NUMBER G-124-06 SIXTH FLOOR, 900 HOWE STREET, BOX 250 VANCOUVER, B.C. V6Z 2N3 CANADA web site: http://www.bcuc.com TELEPHONE: (604) 660-4700 BC TOLL FREE: 1-800-663-1385

More information

B2-69. POLICy!MANAGEMENf PANEL SEA BREEZE CORPORATE PAUL MANSON BRIAN CHERNACK. DR. ZAK EL-RAML y

B2-69. POLICy!MANAGEMENf PANEL SEA BREEZE CORPORATE PAUL MANSON BRIAN CHERNACK. DR. ZAK EL-RAML y B2-69 OPENING SEA BREEZE CORPORATE STATEMENT OF POLICy!MANAGEMENf PANEL PAUL MANSON BRIAN CHERNACK DR. ZAK EL-RAML y OPENING STATEMENT OF SEA BREEZE CORPORATE POLlCy!MANAGEMENT PANEL My name is Paul Manson.

More information

BC hydro REGENERATION

BC hydro REGENERATION BC hydro REGENERATION sm Janet Fraser Chief Regulatory Officer Phone: 604-623-4046 Fax: 604-623-4407 bchydroregulatorvgroup@bchydro.com May 23,2012 Ms. Alanna Gillis Acting BCUC Secretary British Columbia

More information

AB AMBER GRID RULES FOR NATURAL GAS TRANSMISSION SYSTEM BALANCING I. GENERAL PROVISIONS

AB AMBER GRID RULES FOR NATURAL GAS TRANSMISSION SYSTEM BALANCING I. GENERAL PROVISIONS AB AMBER GRID RULES FOR NATURAL GAS TRANSMISSION SYSTEM BALANCING I. GENERAL PROVISIONS 1. AB Amber Grid Rules for Natural Gas Transmission System Balancing (hereinafter - the Rules) are designed to identify

More information

AB AMBER GRID RULES FOR NATURAL GAS TRANSMISSION SYSTEM BALANCING I. GENERAL PROVISIONS

AB AMBER GRID RULES FOR NATURAL GAS TRANSMISSION SYSTEM BALANCING I. GENERAL PROVISIONS AB AMBER GRID RULES FOR NATURAL GAS TRANSMISSION SYSTEM BALANCING I. GENERAL PROVISIONS 1. AB Amber Grid Rules for Natural Gas Transmission System Balancing (hereinafter - the Rules) are designed to identify

More information

Brookfield Asset Management O AK T R E E ACQUISITION M A R C H 1 3,

Brookfield Asset Management O AK T R E E ACQUISITION M A R C H 1 3, Brookfield Asset Management O AK T R E E ACQUISITION M A R C H 1 3, 2 0 19 Transaction Summary On March 13, 2019, Brookfield Asset Management ( BAM ) and Oaktree Capital Group ( OAK ) announced an agreement

More information

Attached as Exhibit B-2 is BC Hydro's presentation from the Stave Falls Spillway Gates Project Workshop held on January 18, 2010.

Attached as Exhibit B-2 is BC Hydro's presentation from the Stave Falls Spillway Gates Project Workshop held on January 18, 2010. BChydro CD FOR GEf\lE IONS B-2 Joanna Sofield Chief Regulatory Officer Phone: (604) 623-4046 Fax: (604) 623-4407 bchydroregulatorygroup@bchydro.com January 19, 2010 Ms. Erica M. Hamilton Commission Secretary

More information

SILK ROAD ENTERTAINMENT, INC. (A Development Stage Company) UNAUDITED BALANCE SHEET AT DECEMBER 31, 2018 ASSETS. CURRENT ASSETS: Cash $ 93,218

SILK ROAD ENTERTAINMENT, INC. (A Development Stage Company) UNAUDITED BALANCE SHEET AT DECEMBER 31, 2018 ASSETS. CURRENT ASSETS: Cash $ 93,218 (A Development Stage Company) UNAUDITED BALANCE SHEET AT DECEMBER 31, 2018 ASSETS CURRENT ASSETS: Cash $ 93,218 OTHER ASSETS: Intellectual Property 1,680,018 Total assets $ 1,773,236 LIABILITIES CURRENT

More information

Xcel Energy (Baa3/BBB-)

Xcel Energy (Baa3/BBB-) January 28, 2004 Fixed Income Research Recommendation: Market Perform Credit Trend: Improving Jacob P. Mercer, CFA Senior Research Analyst 612-303-1609 jacob.p.mercer@pjc.com Mark D. Churchill Associate

More information

INTERIM FINANCIAL STATEMENTS

INTERIM FINANCIAL STATEMENTS AMERICAN GREEN INC INTERIM FINANCIAL STATEMENTS (UNAUDITED) For the three and nine months ended March 31, 2016 and 2015 AMERICAN GREEN INC. UNAUDITED CONSOLIDATED BALANCE SHEET AT MARCH 31, 2016 ASSETS

More information

ASX Announcement. Corporate information. 28 September Target Energy enters Agreement to divest Fairway Project

ASX Announcement. Corporate information. 28 September Target Energy enters Agreement to divest Fairway Project Target Energy enters Agreement to divest Fairway Project Target Energy Limited (ASX:TEX) ( Target or the Company ) is pleased to announce that it has entered into a binding agreement ( Agreement ) to restructure

More information

AMERICAN GREEN INC INTERIM FINANCIAL STATEMENTS

AMERICAN GREEN INC INTERIM FINANCIAL STATEMENTS AMERICAN GREEN INC INTERIM FINANCIAL STATEMENTS (UNAUDITED) For the three months ended September 30, 2017 and 2016 AMERICAN GREEN INC. UNAUDITED CONSOLIDATED BALANCE SHEET AT SEPTEMBER 30, 2017 ASSETS

More information

OVERVIEW OF PRESENTATION

OVERVIEW OF PRESENTATION ACT RELATING TO REVENUE PROTECTION S 3001 AND H 8213 Joint Committee Meeting of the House and Senate Finance Committees Presentation by House and Senate Fiscal Staff May 29, 2012 OVERVIEW OF PRESENTATION

More information

Web.com Completes Acquisition of Yodle Deal strengthens Web.com s portfolio of products that help small businesses compete and succeed online

Web.com Completes Acquisition of Yodle Deal strengthens Web.com s portfolio of products that help small businesses compete and succeed online Web.com Group, Inc. 12808 Gran Bay Parkway West Jacksonville, FL 32258 T: (904) 680-6600 F: (904) 880-0350 NASDAQ: WEB Web.com Completes Acquisition of Yodle Deal strengthens Web.com s portfolio of products

More information

AMERICAN GREEN INC INTERIM FINANCIAL STATEMENTS (UNAUDITED)

AMERICAN GREEN INC INTERIM FINANCIAL STATEMENTS (UNAUDITED) AMERICAN GREEN INC INTERIM FINANCIAL STATEMENTS (UNAUDITED) For the six months ended December 31, 2017 and 2016 AMERICAN GREEN INC. UNAUDITED CONSOLIDATED BALANCE SHEET AT DECEMBER 31, 2017 ASSETS CURRENT

More information

Questions & Answers About the Operate within Operate within IROLs Standard

Questions & Answers About the Operate within Operate within IROLs Standard Index: Introduction to Standard...3 Expansion on Definitions...5 Questions and Answers...9 Who needs to comply with this standard?...9 When does compliance with this standard start?...10 For a System Operator

More information

Working Draft: Gaming Revenue Recognition Implementation Issue. Financial Reporting Center Revenue Recognition

Working Draft: Gaming Revenue Recognition Implementation Issue. Financial Reporting Center Revenue Recognition October 2, 2017 Financial Reporting Center Revenue Recognition Working Draft: Gaming Revenue Recognition Implementation Issue Issue # 6-12: Accounting for Racetrack Fees Expected Overall Level of Impact

More information

Pacific Pilotage Authority. submission to the. Canada Transportation Act Review Panel. January 2015

Pacific Pilotage Authority. submission to the. Canada Transportation Act Review Panel. January 2015 Pacific Pilotage Authority submission to the Canada Transportation Act Review Panel January 2015 This submission is respectfully submitted to the Canada Transportation Act Review Panel by the Pacific Pilotage

More information

STATE OF NEW YORK OFFICE OF THE STATE COMPTROLLER 110 STATE STREET ALBANY, NEW YORK September 2015

STATE OF NEW YORK OFFICE OF THE STATE COMPTROLLER 110 STATE STREET ALBANY, NEW YORK September 2015 THOMAS P. DiNAPOLI COMPTROLLER STATE OF NEW YORK OFFICE OF THE STATE COMPTROLLER 110 STATE STREET ALBANY, NEW YORK 12236 GABRIEL F. DEYO DEPUTY COMPTROLLER DIVISION OF LOCAL GOVERNMENT AND SCHOOL ACCOUNTABILITY

More information

November 14, Dulles To DC Loop Public-Private Partnership Proposal. Executive Summary

November 14, Dulles To DC Loop Public-Private Partnership Proposal. Executive Summary November 14, 2005 Dulles To DC Loop Public-Private Partnership Proposal Executive Summary Virginia Mobility Associates LLC, a newly established single purpose entity, proposes to privately finance the

More information

AMERICAN GREEN INC INTERIM FINANCIAL STATEMENTS

AMERICAN GREEN INC INTERIM FINANCIAL STATEMENTS AMERICAN GREEN INC INTERIM FINANCIAL STATEMENTS (UNAUDITED) For the nine months ended March 31, 2018 and 2017 AMERICAN GREEN INC. UNAUDITED CONSOLIDATED BALANCE SHEET AT MARCH 31, 2018 ASSETS CURRENT ASSETS:

More information

American Petroleum Institute Drawback / FTZ / Import Seminar

American Petroleum Institute Drawback / FTZ / Import Seminar American Petroleum Institute Drawback / FTZ / Import Seminar Crude Oil Imported from Canada Status of NAFTA Issues New Orleans, LA March 26, 2012 Why All the Fuss? Heavy crude oil / bitumen that requires

More information

ASSETS Swiss Francs Swiss Francs

ASSETS Swiss Francs Swiss Francs INTERNATIONAL SKATING UNION, LAUSANNE BALANCE SHEET AS OF DECEMBER 31, 2015 31.12.2015 31.12.2014 ASSETS Swiss Francs Swiss Francs Current Assets Cash 14'562.31 16'103.63 Post / Bank - current accounts

More information

REPORT General Committee

REPORT General Committee J Wohkirp foh you REPORT General Committee For Information DATE: FROM: Norma Trim, Chief Financial Officer and Commissioner of Corporate Services OBJECTIVE To provide Council with the options available

More information

Corporate and Investment Banking. Tariff Guide Domestic Business Effective 12 January 2017

Corporate and Investment Banking. Tariff Guide Domestic Business Effective 12 January 2017 Corporate and Investment Banking Tariff Guide Effective 12 January 2017 1 This Tariff Guide details hereunder the charges applicable to transactions offered by Standard Bank (Mauritius) Limited as from

More information

TO: FROM: SUBJECT: RECOMMENDATION

TO: FROM: SUBJECT: RECOMMENDATION February 8, 2018 TO: Park Board Chair and Commissioners FROM: General Manager Vancouver Board of Parks and Recreation SUBJECT: United 2026 Bid (FIFA) Training Site Agreement RECOMMENDATION A. THAT the

More information

CITY OF VANCOUVER ADMINISTRATIVE REPORT

CITY OF VANCOUVER ADMINISTRATIVE REPORT CITY OF VANCOUVER A14 ADMINISTRATIVE REPORT Report Date: March 17, 2009 Contact: Dave Rudberg Contact No.: 604.296.2860 RTS No.: 07659 VanRIMS No.: 01-1000-00 Meeting Date: March 24, 2009 TO: FROM: SUBJECT:

More information

110 Edgar Martinez Drive South P.O. Box Seattle, WA (206) August 15, 2018

110 Edgar Martinez Drive South P.O. Box Seattle, WA (206) August 15, 2018 WASHINGTON STATE MAJOR LEAGUE BASEBALL STADIUM PUBLIC FACILITIES DISTRICT 110 Edgar Martinez Drive South P.O. Box 94445 Seattle, WA 98124 (206) 664-3076 www.ballpark.org Metropolitan King County Council

More information

GENERAL ASSEMBLY OF NORTH CAROLINA SESSION SENATE BILL DRS45071-MQf-19. Short Title: Off-Track Pari-Mutuel Betting. (Public)

GENERAL ASSEMBLY OF NORTH CAROLINA SESSION SENATE BILL DRS45071-MQf-19. Short Title: Off-Track Pari-Mutuel Betting. (Public) S GENERAL ASSEMBLY OF NORTH CAROLINA SESSION 0 SENATE BILL DRS0-MQf- FILED SENATE Feb, 0 S.B. PRINCIPAL CLERK D Short Title: Off-Track Pari-Mutuel Betting. (Public) Sponsors: Referred to: Senator Fitch

More information

STATE OF NEW YORK OFFICE OF THE STATE COMPTROLLER 110 STATE STREET ALBANY, NEW YORK September 2015

STATE OF NEW YORK OFFICE OF THE STATE COMPTROLLER 110 STATE STREET ALBANY, NEW YORK September 2015 THOMAS P. DiNAPOLI COMPTROLLER STATE OF NEW YORK OFFICE OF THE STATE COMPTROLLER 110 STATE STREET ALBANY, NEW YORK 12236 GABRIEL F. DEYO DEPUTY COMPTROLLER DIVISION OF LOCAL GOVERNMENT AND SCHOOL ACCOUNTABILITY

More information

Finning Canada Investor Tour

Finning Canada Investor Tour Finning Canada Investor Tour Mining, Construction and Forestry Dave Primrose, EVP, Mining, Construction and Forestry June 26, 2013 Forward Looking Information This report contains statements about the

More information

The Bruce Mansfield Station, Units 1, 2 and 3

The Bruce Mansfield Station, Units 1, 2 and 3 BRUCE MANSFIELD UNIT 1 LEASES: By the Numbers, Version 1.0 The Bruce Mansfield Station, Units 1, 2 and 3 NOTE: There are many numbers and calculations in this compilation. The Complier is an attorney by

More information

WANAKA SWIMMING FACILITIES STATEMENT OF PROPOSAL

WANAKA SWIMMING FACILITIES STATEMENT OF PROPOSAL WANAKA SWIMMING FACILITIES STATEMENT OF PROPOSAL 17 October 2014 Contents Executive Summary Background National Guidelines The Status Quo Issue One Timing Issue Two Location Issue Three Size Issue Four

More information

U.S. Figure Skating Travel and Expense Policy (March 2012)

U.S. Figure Skating Travel and Expense Policy (March 2012) U.S. Figure Skating Travel and Expense Policy () U.S. Figure Skating is a Colorado nonprofit corporation with its mission to provide programs to encourage participation and achievement in the sport of

More information

SPECIAL DIVIDEND OF MUELLER INDUSTRIES, INC.

SPECIAL DIVIDEND OF MUELLER INDUSTRIES, INC. MUELLER INDUSTRIES, INC. SPECIAL DIVIDEND OF MUELLER INDUSTRIES, INC. This document is being provided to stockholders of Mueller Industries, Inc. (a corporation that we refer to as Mueller, we, our or

More information

SINGAPORE edevelopment LIMITED (Incorporated in Singapore) (Company Registration No W)

SINGAPORE edevelopment LIMITED (Incorporated in Singapore) (Company Registration No W) SINGAPORE edevelopment LIMITED (Incorporated in Singapore) (Company Registration No. 200916763W) PROPOSED ACQUISITION OF HOTAPPS INTERNATIONAL PTE. LTD. BY AN OTCBB-BOUND U.S. COMPANY WHICH WILL BECOME

More information

Norma Trim, Chief Financial Officer and Commissioner of Corporate Services

Norma Trim, Chief Financial Officer and Commissioner of Corporate Services 4 Worki~~ For y og REPORT Meeting Date: September 22, 204 4 Regional Council DATE: REPORT TITLE: 201 1 DEBENTURE BORROWING UPDATE - FROM: Norma Trim, Chief Financial Officer and Commissioner of Corporate

More information

Banksia Securities Limited ACN: (Receivers and Managers Appointed)(In Liquidation) ("BSL")

Banksia Securities Limited ACN: (Receivers and Managers Appointed)(In Liquidation) (BSL) Banksia Securities Limited ACN: 004 736 458 (Receivers and Managers Appointed)(In Liquidation) ("BSL") Circular to Debenture Holders: Trustee Fee Application 8 February 2016 The purpose of this circular

More information

U.S. Figure Skating Travel and Expense Policy (July 2018)

U.S. Figure Skating Travel and Expense Policy (July 2018) U.S. Figure Skating Travel and Expense Policy () U.S. Figure Skating is a Colorado nonprofit corporation with its mission to provide programs to encourage participation and achievement in the sport of

More information

Price to Public (1) % $99,765,625

Price to Public (1) % $99,765,625 OFFERING CIRCULAR SUPPLEMENT (to Offering Circular Dated September 13, 1995) $100,000,000 Federal Home Loan Mortgage Corporation 6.65% Fixed Rate Debentures Due 2003 Redeemable in accordance with amortization

More information

Summary of Proposal to Upgrade Swimming Facilities for the Wanaka Ward

Summary of Proposal to Upgrade Swimming Facilities for the Wanaka Ward Attachment B Summary of Proposal to Upgrade Swimming Facilities for the Wanaka Ward Introduction The Queenstown Lakes District Council is proposing to build an eight lane lap pool and a learners pool costing

More information

Administration Report Fiscal Year 2011/2012

Administration Report Fiscal Year 2011/2012 Administration Report Fiscal Year 2011/2012 Poway Unified School District Community Facilities District No. 3 June 20, 2011 Prepared For: Poway Unified School District Planning Department 13626 Twin Peaks

More information

Administration Report Fiscal Year 2010/2011

Administration Report Fiscal Year 2010/2011 Administration Report Fiscal Year 2010/2011 Poway Unified School District Community Facilities District No. 3 June 21, 2010 Prepared For: Poway Unified School District 13626 Twin Peaks Road Poway, CA 92064

More information

Session of HOUSE BILL No By Committee on Commerce, Labor and Economic Development 2-12

Session of HOUSE BILL No By Committee on Commerce, Labor and Economic Development 2-12 Session of 0 HOUSE BILL No. 0 By Committee on Commerce, Labor and Economic Development - 0 0 0 AN ACT concerning the Kansas expanded lottery act; relating to racetrack gaming facilities; relating to parimutuel

More information

BC Games Society 2016/ /19 SERVICE PLAN

BC Games Society 2016/ /19 SERVICE PLAN 2016/17 2018/19 SERVICE PLAN For more information on the BC Games Society contact: 200-990 Fort Street Victoria BC V8V 3K2 Kelly Mann, President and CEO kellym@bcgames.org or visit our website at www.bcgames.org

More information

TORONTO MUNICIPAL CODE CHAPTER 30, DEBENTURE AND OTHER BORROWING. Chapter 30 DEBENTURE AND OTHER BORROWING. ARTICLE I General

TORONTO MUNICIPAL CODE CHAPTER 30, DEBENTURE AND OTHER BORROWING. Chapter 30 DEBENTURE AND OTHER BORROWING. ARTICLE I General 30-1. Definitions. TORONTO MUNICIPAL CODE 30-2. Delegation and annual limit. 30-3. Additional Agreements. 30-4. Variable interest rate. 30-5. Application to regulatory bodies. 30-6. Debenture Committee.

More information

Interconnected Party (IP) Rights and Obligations. In relation to Interconnection Agreements (ICAs), the Final Assessment Paper (FAP) determined that:

Interconnected Party (IP) Rights and Obligations. In relation to Interconnection Agreements (ICAs), the Final Assessment Paper (FAP) determined that: MEMO From To Gas Industry Co GTAC Stakeholders Date 3 July 2018 Interconnected Party (IP) Rights and Obligations In relation to Interconnection Agreements (ICAs), the Final Assessment Paper (FAP) determined

More information

SPECIAL DIVIDEND OF MUELLER INDUSTRIES, INC.

SPECIAL DIVIDEND OF MUELLER INDUSTRIES, INC. MUELLER INDUSTRIES, INC. SPECIAL DIVIDEND OF MUELLER INDUSTRIES, INC. This document is being provided to stockholders of Mueller Industries, Inc. (a corporation that we refer to as Mueller, we, our or

More information

ISSUING AGENCY: New Mexico Department of Game and Fish. [ NMAC - Rp, NMAC, 01/01/2018]

ISSUING AGENCY: New Mexico Department of Game and Fish. [ NMAC - Rp, NMAC, 01/01/2018] TITLE 19 CHAPTER 30 PART 8 NATURAL RESOURCES AND WILDLIFE WILDLIFE ADMINISTRATION GUIDE AND OUTFITTER REGISTRATION 19.30.8.1 ISSUING AGENCY: New Mexico Department of Game and Fish. [19.30.8.1 NMAC - Rp,

More information

Washington Public Ports Association

Washington Public Ports Association May 17, 2017 Washington Public Ports Association Underwriting Process Lindsay Sovde MANAGING DIRECTOR Tel: +1 206-628-2875 Email: lindsay.a.sovde@pjc.com MINNEAPOLIS BOISE CHICAGO LONDON LOS ANGELES NEW

More information

LAKE BLUFF PARK DISTRICT BLAIR PARK SWIMMING POOL Questions and Answers OVERVIEW

LAKE BLUFF PARK DISTRICT BLAIR PARK SWIMMING POOL Questions and Answers   OVERVIEW LAKE BLUFF PARK DISTRICT BLAIR PARK SWIMMING POOL Questions and Answers www.lakebluffparks.org OVERVIEW Q: How did the community rate the pool on the Community Wide survey? A: The top three highest rated

More information

Aliso Canyon Gas-Electric Coordination Phase 3 Draft Final Proposal

Aliso Canyon Gas-Electric Coordination Phase 3 Draft Final Proposal Aliso Canyon Gas-Electric Coordination Phase 3 Draft Final Proposal Cathleen Colbert Senior Market Design and Regulatory Policy Developer Market & Infrastructure Policy June 23, 2017 Agenda Time Topic

More information

QLDC Council 29 October Report for Agenda Item: 3

QLDC Council 29 October Report for Agenda Item: 3 QLDC Council 29 October 2015 Department: Infrastructure Beach Street Pedestrianisation Purpose Report for Agenda Item: 3 1 The purpose of this report is to obtain Council approval to consult over options

More information

Exhibit #MH-156. ELECTRIC OPERATIONS (MH10-2) PROJECTED OPERATING STATEMENT (In Millions of Dollars) For the year ended March 31 REVENUES

Exhibit #MH-156. ELECTRIC OPERATIONS (MH10-2) PROJECTED OPERATING STATEMENT (In Millions of Dollars) For the year ended March 31 REVENUES PROJECTED OPERATING STATEMENT 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 REVENUES General Consumers at approved rates 1,194 1,223 1,235 1,254 1,265 1,279 1,296 1,307 1,320 1,336 additional * - 42

More information

25 April Sincerely,

25 April Sincerely, B-7 Marcel Reghelini or, Regulatory Affairs Phone: 604 699-7331 Fax: 604 699-7537 E-mail: marcel.reghelini@bctc.com 25 April 2007 Mr. Robert J. Pellatt Commission Secretary British Columbia Utilities Commission

More information

STATE OF NEW JERSEY. ASSEMBLY, No ASSEMBLY BUDGET COMMITTEE STATEMENT TO. with committee amendments DATED: DECEMBER 15, 2014

STATE OF NEW JERSEY. ASSEMBLY, No ASSEMBLY BUDGET COMMITTEE STATEMENT TO. with committee amendments DATED: DECEMBER 15, 2014 ASSEMBLY BUDGET COMMITTEE STATEMENT TO ASSEMBLY, No. 3969 with committee amendments STATE OF NEW JERSEY DATED: DECEMBER 15, 2014 The Assembly Budget Committee reports favorably Assembly Bill No. 3969,

More information

Order No. 55/18 CENTRA GAS MANITOBA INC.: PRIMARY GAS RATE APPLICATION, EFFECTIVE MAY 1, April 26, 2018

Order No. 55/18 CENTRA GAS MANITOBA INC.: PRIMARY GAS RATE APPLICATION, EFFECTIVE MAY 1, April 26, 2018 CENTRA GAS MANITOBA INC.: PRIMARY GAS RATE APPLICATION, EFFECTIVE MAY 1, 2018 BEFORE: Larry Ring, Q.C., Panel Chair Marilyn Kapitany, B.Sc.(Hon), M.Sc., Vice Chair Carol Hainsworth, C.B.A., Member Susan

More information

FortisBC Energy Inc. Annual Review for 2018 Delivery Rates Project No Final Order with Reasons for Decision

FortisBC Energy Inc. Annual Review for 2018 Delivery Rates Project No Final Order with Reasons for Decision Patrick Wruck Commission Secretary Commission.Secretary@bcuc.com bcuc.com Suite 410, 900 Howe Street Vancouver, BC Canada V6Z 2N3 P: 604.660.4700 TF: 1.800.663.1385 F: 604.660.1102 December 21, 2017 Sent

More information

Southwest Power Pool REGIONAL STATE COMMITTEE BYLAWS

Southwest Power Pool REGIONAL STATE COMMITTEE BYLAWS Southwest Power Pool REGIONAL STATE COMMITTEE BYLAWS Approved: October 30, 2017 ARTICLE I 1. NAME: The organization shall be known as the Southwest Power Pool Regional State Committee ( SPP RSC ). The

More information

Our Plan to Restore Manitoba Hydro and Protect Manitobans

Our Plan to Restore Manitoba Hydro and Protect Manitobans Manitoba Chambers of Commerce Our Plan to Restore Manitoba Hydro and Protect Manitobans H. Sanford Riley Chair, Manitoba Hydro Electric Board December 1, 2017 1 Review of Manitoba Hydro s financial challenge

More information

Golf Professional Services - Independent Contractor

Golf Professional Services - Independent Contractor Mount Brenton Golf Course Request For and Expression of Interest (RFEI) Golf Professional Services - Independent Contractor Issue Date: November 5, 2012 Email Address for Response Delivery: mtbrentonoffice@shaw.ca

More information

P.O. Box 1749 Halifax, Nova Scotia B3J 3A5 Canada Item No. Halifax Regional Council January 16, 2017

P.O. Box 1749 Halifax, Nova Scotia B3J 3A5 Canada Item No. Halifax Regional Council January 16, 2017 P.O. Box 1749 Halifax, Nova Scotia B3J 3A5 Canada Item No. Halifax Regional Council January 16, 2017 TO: Mayor Savage and Members of Halifax Regional Council SUBMITTED BY: Jacques Dubé, Chief Administrative

More information

EUROPEAN COMBINED EVENTS TEAM CHAMPIONSHIPS 701. PROMOTION AND RIGHTS

EUROPEAN COMBINED EVENTS TEAM CHAMPIONSHIPS 701. PROMOTION AND RIGHTS EUROPEAN COMBINED EVENTS TEAM CHAMPIONSHIPS 701. PROMOTION AND RIGHTS 701.1. The European Athletic Association (hereinafter European Athletics) shall promote a European Team Championships in Decathlon

More information

Europe June Craig Menear. Chairman, CEO & President. Diane Dayhoff. Vice President, Investor Relations

Europe June Craig Menear. Chairman, CEO & President. Diane Dayhoff. Vice President, Investor Relations Europe June 2016 Craig Menear Chairman, CEO & President Diane Dayhoff Vice President, Investor Relations Forward Looking Statements and Non-GAAP Financial Measurements Certain statements contained in today

More information

REAL ESTATE DEVELOPMENT LAW

REAL ESTATE DEVELOPMENT LAW REAL ESTATE DEVELOPMENT LAW By Rick Daley Senior Lecturer in Law The Moritz College of Law at The Ohio State University Also available on Law School Exchange at: http://exchange.westlaw.com/ AMERICAN CASEBOOK

More information

RECIPROCAL ACCESS AGREEMENT WITNESSETH

RECIPROCAL ACCESS AGREEMENT WITNESSETH RECIPROCAL ACCESS AGREEMENT THIS AGREEMENT, entered into this 1st day of February, 2017 by and between (NAME AND ADDRESS OF THE PARTICIPATING CLUB/PROPERTY), (hereinafter referred to as The Club ), and

More information

TULSA INTERNATIONAL AIRPORT ECONOMIC DEVELOPMENT PROJECT PLAN

TULSA INTERNATIONAL AIRPORT ECONOMIC DEVELOPMENT PROJECT PLAN Adopted, 2016 TULSA INTERNATIONAL AIRPORT ECONOMIC DEVELOPMENT PROJECT PLAN A PROJECT OF: THE CITY OF TULSA IN COOPERATION WITH: TULSA COUNTY TULSA INTERNATIONAL AIRPORT DEVELOPMENT TRUST TULSA AIRPORTS

More information

FAQs For Board of Outfitters Issues

FAQs For Board of Outfitters Issues FAQs Pat Tabor spearheaded a project when he was on the Board to have a source of information on the MBO website for frequently asked questions. Below are some excerpts for issues pertinent to existing

More information

IC Chapter 7. Conduct of Gambling Games at Racetracks

IC Chapter 7. Conduct of Gambling Games at Racetracks IC 4-35-7 Chapter 7. Conduct of Gambling Games at Racetracks IC 4-35-7-1 Gambling games authorized at racetracks Sec. 1. Gambling games authorized under this article may not be conducted anywhere other

More information

ENERGY FUELS INC. MANAGEMENT INFORMATION CIRCULAR JULY 5, 2016

ENERGY FUELS INC. MANAGEMENT INFORMATION CIRCULAR JULY 5, 2016 These materials require Debentureholders to make important decisions and require your immediate attention. If you are in doubt as to what decision to make, please contact your financial, legal, income

More information

2016 Electric Resource Plan Modeling Assumptions Update

2016 Electric Resource Plan Modeling Assumptions Update Page 1 of 16 Public Service Company of Colorado 2016 Electric Resource Plan Modeling Assumptions Update (CPUC ) August 2017 xcelenergy.com 2016 Xcel Energy Inc. Xcel Energy is a registered trademark of

More information

U.S. 1, , 2000 JANUARY

U.S. 1, , 2000 JANUARY ADVISORY REPORT Costs Claimed by the State of Maryland, Department of Natural Resources, Under Federal Aid Grants from the U.S. Fish and Wildlife Service from July 1, 1998 through June 30, 2000 JANUARY

More information

M A N I T O B A ) Order No. 123/13 ) THE PUBLIC UTILITIES BOARD ACT ) October 22, 2013

M A N I T O B A ) Order No. 123/13 ) THE PUBLIC UTILITIES BOARD ACT ) October 22, 2013 M A N I T O B A ) Order No. 123/13 ) THE PUBLIC UTILITIES BOARD ACT ) BEFORE: Régis Gosselin, B ès Arts, MBA, CGA, Chair Larry Soldier, Member Marilyn Kapitany, B.Sc. (Hon), M.Sc., Member CENTRA GAS MANITOBA

More information

May 23, 2018 Proposed No.:

May 23, 2018 Proposed No.: 1 May 23, 2018 Proposed No.: 18-004 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 RESOLUTION NO. A RESOLUTION of the Board of Directors of the Washington State Major League Baseball

More information

Number of the Issue. The Debentures represent the Company s first debenture issue. Total Issue Amount. The total Issue amount is up to two hundred

Number of the Issue. The Debentures represent the Company s first debenture issue. Total Issue Amount. The total Issue amount is up to two hundred MILLS ESTRUTURAS E SERVIÇOS DE ENGENHARIA S.A. Company Registry (NIRE): 33.3.0028974-7 Corporate Taxpayers ID (CNPJ/MF): 27.093.558/0001-15 MINUTES OF THE BOARD OF DIRECTORS MEETING HELD ON MARCH 24, 2011

More information

Each tournament s fi nancial commitment is composed of on-site prize money and tournament fee obligations unless otherwise approved by ATP.

Each tournament s fi nancial commitment is composed of on-site prize money and tournament fee obligations unless otherwise approved by ATP. 3.01 Composition of Commitment Each tournament s fi nancial commitment is composed of on-site prize money and tournament fee obligations unless otherwise approved by ATP. 3.02 Currency All references to

More information

Progress with the Road Investment Strategy

Progress with the Road Investment Strategy Report by the Comptroller and Auditor General Department for Transport and Highways England Progress with the Road Investment Strategy HC 1056 SESSION 2016-17 22 MARCH 2017 4 Key facts Progress with the

More information

Each tournament s fi nancial commitment is composed of on-site prize money and tournament fee obligations unless otherwise approved by ATP.

Each tournament s fi nancial commitment is composed of on-site prize money and tournament fee obligations unless otherwise approved by ATP. 3.01 Composition of Commitment Each tournament s fi nancial commitment is composed of on-site prize money and tournament fee obligations unless otherwise approved by ATP. 3.02 Currency All references to

More information

M a s t e r A g r e e m e n t

M a s t e r A g r e e m e n t M a s t e r A g r e e m e n t made between New Zealand Cricket NZC and Otago Cricket Association Canterbury Cricket Association Auckland Cricket Association Cricket Wellington Northern Districts Cricket

More information

MOTION NO. M Contract Amendment for Systems Construction Management Consultant Services

MOTION NO. M Contract Amendment for Systems Construction Management Consultant Services MOTION NO. M2017-74 Contract Amendment for Systems Construction Management Consultant Services MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Capital Committee PROPOSED ACTION 5/11/2017 5/25/2017 Recommend

More information

Sunset Beach Annexation LOCAL AGENCY FORMATION COMMISSION MEETING OCTOBER 11, 2017

Sunset Beach Annexation LOCAL AGENCY FORMATION COMMISSION MEETING OCTOBER 11, 2017 Sunset Beach Annexation LOCAL AGENCY FORMATION COMMISSION MEETING OCTOBER 11, 2017 History Sunset Beach is a beach-front community of approximately 970 people. It was an unincorporated area of the County

More information

Highlights of initial mapping and sampling completed by the Company on the La Chiva, Agua and the 5 Senores veins include:

Highlights of initial mapping and sampling completed by the Company on the La Chiva, Agua and the 5 Senores veins include: September 20, 2018 KOOTENAY SILVER REPORTS CONTINUED EXPLORATION SUCCESS AT COPALITO SILVER-GOLD PROJECT, MEXICO Sample Results in Southern Area of the Property Include 1.0 Meter of 1,155 gpt Silver and

More information

Community Update. Life in the Heartland Community Information Evening. Pembina Pipeline Corporation

Community Update. Life in the Heartland Community Information Evening. Pembina Pipeline Corporation Pembina Pipeline Corporation Community Update Life in the Heartland Community Information Evening Wayne Carey Manager, Field Projects, Redwater Facility October 23, 2017 Forward-Looking Statements This

More information

RFU REGULATION 5 FINANCIAL. 5.1 Finance

RFU REGULATION 5 FINANCIAL. 5.1 Finance RFU REGULATION 5 FINANCIAL 5.1 Finance 5.1.1 On or before 31 December each year, each Constituent Body shall send to the RFU s Chief Financial Officer for inspection a properly prepared Financial Statement

More information

LETTER OF TRANSMITTAL

LETTER OF TRANSMITTAL LETTER OF TRANSMITTAL Pursuant to the Offer to Purchase for Cash Up to $50 Million But Not Less than $20 Million Aggregate Principal Amount of Outstanding 0% Subordinated Debentures due 2015 (CUSIP No.

More information

Nova Scotia Annual Gaming Report

Nova Scotia Annual Gaming Report Nova Scotia Annual Gaming Report 2013-2014 Dear Reader: Presented herewith is the Annual Gaming Report, pursuant to Section 56 of the Gaming Control Act, for the year ending March 31, 2014. The Annual

More information

All TSOs of the Nordic Capacity Calculation Region Proposal for fallback procedures in accordance with Article 44 of Commission Regulation (EU)

All TSOs of the Nordic Capacity Calculation Region Proposal for fallback procedures in accordance with Article 44 of Commission Regulation (EU) All TSOs of the Nordic Capacity Calculation Region Proposal for fallback procedures in accordance with Article 44 of Commission Regulation (EU) 2015/1222 of 24 July 2015 establishing a guideline on capacity

More information

Tariff Guide - Resident

Tariff Guide - Resident Please find below the list of fees and charges applicable for Residents with effect as from 1 st October 2017. SAVINGS ACCOUNTS - MUR Minimum account opening balance Minimum credit balance to earn interest

More information

Fortnum Private Wealth Ltd Financial Services Guide Part 2

Fortnum Private Wealth Ltd Financial Services Guide Part 2 Fortnum Private Wealth Ltd Financial Services Guide Part 2 Fairway Financial Advice Fairway Financial Advice Ltd 1 (ABN 68 786 381 811) and Fairway Too Pty Ltd (ABN 82 601 766 581) trade together as Fairway

More information

PRESENTATION TO THE BRITISH COLUMBIA LEGISALTIVE STANDING COMMITTEE ON FINANCE September 26, 2013

PRESENTATION TO THE BRITISH COLUMBIA LEGISALTIVE STANDING COMMITTEE ON FINANCE September 26, 2013 PRESENTATION TO THE BRITISH COLUMBIA LEGISALTIVE STANDING COMMITTEE ON FINANCE September 26, 2013 On behalf of its 40,000 plus members, The BC Wildlife Federation welcomes the opportunity to address the

More information

Press Release New Bilateral Agreement May 22, 2008

Press Release New Bilateral Agreement May 22, 2008 Informational Report 3 June 2008 Press Release New Bilateral Agreement May 22, 2008 The Pacific Salmon Commission is pleased to announce that it has recommended a new bilateral agreement for the conservation

More information

PART 1: INFRASTRUCTURE OPPORTUNITIES

PART 1: INFRASTRUCTURE OPPORTUNITIES PART 1: INFRASTRUCTURE OPPORTUNITIES AUTHORS This article was authored by David Nancarrow (Partner, Perth), Alyson Eather (Senior Associate, Perth) and Celeste Koravos (Associate, Melbourne and Tokyo).

More information

CMM Conservation and Management Measure for the Management of New and Exploratory Fisheries in the SPRFMO Convention Area.

CMM Conservation and Management Measure for the Management of New and Exploratory Fisheries in the SPRFMO Convention Area. CMM 13-2016 1 Conservation and Management Measure for the Management of New and Exploratory Fisheries in the SPRFMO Convention Area. The Commission of the South Pacific Regional Fisheries Management Organisation;

More information

Report from the Council

Report from the Council Report from the Council NW Hydroelectric Association Spokane WA October 30, 2014 Tom Karier NW Power and Conservation Council Topics 1. Highlights of the 6 th Plan (2010) 2. What actually happened 3. What

More information

TITLE 11. DEPARTMENT OF JUSTICE NOTICE OF PROPOSED RULEMAKING

TITLE 11. DEPARTMENT OF JUSTICE NOTICE OF PROPOSED RULEMAKING TITLE 11. DEPARTMENT OF JUSTICE NOTICE OF PROPOSED RULEMAKING NOTICE IS HEREBY GIVEN that the Department of Justice (DOJ) proposes to adopt as permanent regulations the Attorney General s establishment

More information

Report to COUNCIL for decision

Report to COUNCIL for decision 17 152 Title: Section: Prepared by: Olympic Pool Business Case Community & Recreation Andrew White (Community & Recreation Manager) Meeting Date: 18 May 2017 Legal Financial Significance = Medium Report

More information

These General Terms and Conditions apply to Ski & Snowboard Schools operating in the Province of Salzburg

These General Terms and Conditions apply to Ski & Snowboard Schools operating in the Province of Salzburg These General Terms and Conditions apply to Ski & Snowboard Schools operating in the Province of Salzburg 1. General Provisions: Unless agreed otherwise, these General Terms and Conditions shall apply

More information

Implementing the New Fisheries Protection Provisions under the Fisheries Act

Implementing the New Fisheries Protection Provisions under the Fisheries Act Implementing the New Fisheries Protection Provisions under the Fisheries Act Part 1 Legislation and Policy * The information in this presentation represents concepts as they have been developed to this

More information

Invitation to express interest

Invitation to express interest CEREMONIES FOR UEFA EURO 2020, UEFA CLUB FINALS 2019-2021 AND UEFA NATIONS LEAGUE FINALS 2019 Invitation to express interest 1. Introduction 1.1 UEFA EURO 2020 UEFA EURO 2020 will be held in 12 different

More information

Annual Meeting of Shareholders May 8, Oyu Tolgoi: world-class asset, development optionality, significant cash flow potential

Annual Meeting of Shareholders May 8, Oyu Tolgoi: world-class asset, development optionality, significant cash flow potential Annual Meeting of Shareholders May 8, 2018 Oyu Tolgoi: world-class asset, development optionality, significant cash flow potential Forward-looking statements 2 This presentation includes certain forward-looking

More information