Reliability Assessment of the Whistler Propane Vaporizers

Size: px
Start display at page:

Download "Reliability Assessment of the Whistler Propane Vaporizers"

Transcription

1 Reliability Assessment of the Whistler Propane Vaporizers Prepared for: Terasen & Fransen Engineering Prepared by: ClearSky Risk Management Inc rd Ave East Vancouver, BC V6B 5Z3 Phone: Fax: June 2005

2 Table of Contents 1.0 Summary of the Reliability Assessment Method Resources Results Lack of Spare Vaporizer During Peak Demand Failure of Propane Supply to the Vaporizers During Peak Demand Generalized System Failures... 7 Tables Table 1. Study Team Members...3 Table 2. Preventative Recommendations for Vaporizer Failure During Peak Demand...4 Table 3. Mitigative Recommendations for Vaporizer Failure During Peak Demand...5 Table 4. Recommendations for Loss of Liquid Propane Feed to the Vaporizers...6 Table 5. General Recommendations for System Reliability...7 Appendix A: Worksheets Appendix B: Recommendations Appendices i

3 1.0 Summary of the Reliability Assessment This summarizes the results from the reliability assessment of the Whistler Propane Plant Vaporizers. The study was conducted on June 6, 2005 at the Terasen office in Whistler, BC. The scope of the study was the equipment downstream of the propane tanks at the North and South Plants, through the propane vaporizers and into the propane distribution header. The objective of the study was to evaluate the potential reliability hazards in the existing system, relating to the ability to provide propane to the customers at all times of the year, during all ranges of demand. As part of a long-term plan, the propane storage system is expected to be decommissioned when a proposed pipeline is built from Squamish to Whistler to introduce natural gas to the community. However, in the interim, the reliability of the existing system is paramount. This review was undertaken to determine if there are any portions of the vaporization system that is prone to failure, in the time prior to the system changes. The primary purpose of the study was to identify equipment or procedures at the site that require attention in order to maintain the integrity of the process. The secondary purpose was to document any obvious safety concerns brought up during the course of the reliability assessment. However, this evaluation did not explicitly review safety hazards, and does not take the place of a Process Hazard Analysis. The study was conducted with the participation of two Terasen staff members from the Whistler Plant, one Terasen technician (instrumentation and controls), a project engineer from Fransen Engineering. A process safety and risk management expert from ClearSky Risk Management facilitated the study. A total of nineteen recommendations relating to operational and safety improvements to the facility were made. These recommendations were made with a team consensus, and are the product of this evaluation. ClearSky Risk Management has expended its best professional efforts in performing this work. However it should be noted that this report describes a work effort where Terasen personnel provided design, operations and maintenance information for the scope of equipment evaluated. This information was not field-verified or confirmed by ClearSky Risk Management. In addition, Terasen personnel were responsible for the assessment of hazards and the development of recommendations. Consequently, ClearSky Risk Management can accept no liability for any use that Terasen may make of the information contained herein. 1

4 2.0 Method The reliability assessment is a subjective evaluation which follows a standardized method for hazard identification, commonly used for process hazard analysis. In this case, the What-If? hazard analysis method was tailored to suit the scope and objectives of the study, which was to focus on reliability concerns at the Nesters site. The system was divided into 3 subsystems:. 1. Liquid supply system from Propane Storage tank through the Vaporizer Feed pumps 2. Tank Vapor header from Propane Storage tanks to the propane distribution header. 3. Liquid propane feed into the Vaporizers, including the glycol/water bath and burners. In each subsystem, the study team brainstormed possible scenarios that would lead to a loss or reduced function of the propane distribution network, stemming from problems at the Vaporizers. For each hazard identified, the potential consequences were documented. The worst-case consequence was evaluated without the benefit of operator or instrumentation interaction. This is typical in hazard evaluation, as both human action and instrumented systems are fallible and prone to fail on demand at some frequency. The existing controls, or safeguards, for each hazard scenario was documented. If the study team felt that the hazards outweighed the existing controls, then recommendations were made to reduce the risk of occurrence. The study was facilitated by a trained hazard analysis expert; however it was the input of the team members from Terasen that primarily guided the outcome of this study. Members from ClearSky and Fransen used their experience at other similar sites to provide advice during the course of the study, but are not solely responsible for the work product. Note a risk evaluation method was not used in this study. The purpose of the study was primarily to identify potential reliability weak spots. The study team recognized that the recommendations put forth during the study would not necessarily receive equal priority, nor be implemented. 2

5 3.0 Resources The PHA study was a team effort, consisting of a trained facilitator, Terasen operations personnel, and an engineering representative from Fransen Engineering. The team members who participated in this PHA are as follows: Table 1. Study Team Members Name Title Company Leslie Parchomchuk Facilitator ClearSky Risk Management Mark Abbott Mechanical Engineer Fransen Engineering Wayne Cankovic Frode Hansen Al Rumbel Operations Manager, Whistler Instrumentation Technician District Service Agent, Whistler Terasen Terasen Terasen The team members from Fransen and ClearSky conducted a site tour of the North Plant, to become familiar with equipment layout, prior to the study. The study team referenced drawings available at the Terasen offices, including: K : Rail Car Unloading & Nesters Propane Plant K : Nesters Propane Plant Liquids System In addition, electrical one-line diagrams and inspection reports were referenced as needed. All worksheets and reference drawings for this short study are appended. 3

6 4.0 Results The review focused on aspects of the equipment and the operating procedures that could reasonably lead to operational upsets in the next few years, prior to the conversion of the grid to natural gas. There were several areas of generalized concern: 4.1 Lack of Spare Vaporizer During Peak Demand The major concern was that during peak demand, all four vaporizers are required to supply the demand. Should a vaporizer, or any of its components, fail for any reason, there would be two consequences of concern: a) Reduced supply of propane to the end users, which can likely be mitigated by increased bath temperatures and increased natural vaporization from the propane tanks. b) Potential for the demand on the distribution header to increase the flow of liquid propane into the remaining vaporizers; the inability of the vaporizers heat input to keep up with the inflowing liquid could cause the vaporizers to flood and trip on high level, which would trip out all vaporizers, and cause a major upset due to loss of supply. The recommendations made to combat this concern focused on both on prevention as well as mitigation of the event, as follows: Table 2. Preventative Recommendations for Vaporizer Failure During Peak Demand Recommendation 16. Inventory spare parts for the entire system, and provide spare parts for critical equipment, such as: Fire eyes Level switches High Temperature switches Bath temperature control switches Flame guard ignition system Microswitches Liquid inlet solenoid valve.. e.g. PRV-1120 (& similar) Comment At a minimum, stocking spare parts and having the knowledge to repair or replace equipment will minimize downtime for vaporizers. 4

7 Table 3. Mitigative Recommendations for Vaporizer Failure During Peak Demand Recommendation 17. Consider developing a procedure to unload the demand on the system, while a vaporizer is down during peak demand. Sacrificing the supply to some customers may be required in order to prevent a total outage. 18. Calculate (estimate) how long it would take at peak demand for the vaporizers to flood and trip on high level, if one of the vaporizers trip. If the time to react is low (.e.g less than one hour), consider implementing options that would mitigate the sudden pressure surge due to losing a vaporizer at peak times, such as: Comment It is expected that a procedure to cut off supply to some users will be an unpopular move. However, having a documented protocol for use in the case of emergency is preferred over leaving the operators to make last-minute decisions. There has been experience with remaining vaporizers flooding if one vaporizer goes down during peak demand. If it happens while the site is unmanned, the time to respond may be too long before a total outage occurs. a) Install temperature controller, remotely activated. Increasing vaporizer temperatures temporarily will allow for increased propane generation. b) Remote start/stop of the Vaporizer Feed pumps. Stopping a pump would reduce the flow of liquid to the vaporizers to minimize the potential for high level trips, and would decrease the system pressure but not stop the flow. 19. Develop an operating procedure to deal with a loss of one Vaporizer during peak demands, to assist in decision-making whether to fix the problem or to reduce the throughput. The first evaluation is to check the demand, and to determine if the existing number of vaporizers can match that demand. The procedure should include a reference table of how much each vaporizer can produce at certain temperature/pressure profiles, for an 'at a glance' reference. In addition to providing operators with a tool to make difficult decisions, this would also provide an understanding between the site and the head office as to how to deal with outages. If existing vaporizers cannot keep up, then reducing the demand or throughput would be necessary to prevent tripping out the remaining vaporizers. 5

8 4.2 Failure of Propane Supply to the Vaporizers During Peak Demand There are two Vaporizer Feed Pumps, run at the same time during peak demands, with a larger Pipeline Evacuation Pump that may be used as a spare on its own. During peak demand time, the vaporizers require liquid feed in order to sustain the propane header pressure. There are various weak points in the liquid delivery process between the Propane Tanks up to Vaporizers, as follows: Pump failures while running are not explicitly monitored, alarmed, and mitigated (e.g. there are no remote or auto-starts). Tank isolation valves are prone to failure, either through loss of pneumatic signal or failure of a microswitch. The following recommendations are concerned with preventing, detecting and mitigating loss of liquid feed into the Vaporizers: Table 4. Recommendations for Loss of Liquid Propane Feed to the Vaporizers Recommendation 1. Consider providing a discreet local pump status indication (e.g. light) for Vaporizer Feed pumps. The location of the feed pumps under the awning makes it difficult to assess if the pump motor is on, especially if there is snow. 2. Consider providing a page status for pump failure. 3. Consider providing remote start/stop of the Vaporizer Feed pumps. This would allow operators to respond to a pump failure quickly, to start a spare pump. Stopping a pump would reduce the flow of liquid to the vaporizers to minimize the potential for high level trips, and would decrease the system pressure but not stop the flow. 4. Verify and ensure that the gen-set is function tested on full load, to ensure it can handle maximum load. Comment Note - history of operators not noticing that pumps were not running. Light would aid in detection. Currently, there is no remote notification of pump status, and the pump(s) are required in winter to sustain pressure. Pumps have been reliable; however as the demand is increased, the pumps will be required more often. As well, when they are needed, they are more critical as losing a pump in peak demand could mean a system outage. The gen-set is function tested, but the inspection reports were unclear if it was tested under a full load. 6

9 5. Lock and tag closed the bypass valve around the liquid supply solenoid valves to each propane vaporizer. These are safety systems which should not be bypassed, except under controlled circumstances. 7. Verify and ensure that that the nitrogen supply header is not vulnerable to snow/ice load, especially the section upstream of the restriction orifice. 8. Implement a formal program for checking and testing the microswitches on the nitrogen system to the tank ESVs. To be treated like any other safety system, e..g. PSV. Icing and snow load have the potential to cause failure of tubing. Informal program in place, but needs to be made standard. 4.3 Generalized System Failures There were a number of generalized operational efficiencies that could be gained from minor modifications to the system. The root cause of these concerns relates back to the detection and response to problems at an unstaffed site. Operators may not be at the plant site, and are required to respond to pages transmitted via a modem on site. There are several opportunities for failure between the alarm system, the modem communication system, and operator response time. Each opportunity for failure has the potential to be coupled with a peak demand time. The following recommendations would limit the potential exposure of the site to failures of the equipment or alert systems: Table 5. General Recommendations for System Reliability Recommendation 6. Consider providing a UPS (battery backup) to the power supply to the Vaporizers and Lighting panel 9. Include both the pump internal relief valves and the safety relief valves on the Vaporizer Feed Pump discharge on the PSV maintenance system. on a maintenance schedule. Comment 15 kva transformer causes loss of power to the instrumentation panel, which would cause the vaporizers to trip. The pumps have gen-set backup, but the vaporizer instrumentation does not, but the required level of reliability would be the same. Since the outlet of the pump discharge PSVs can be blocked in (e.g. valve #221 and 222 can be closed), then the pump internal PSVs are the only reliable form of overpressure protection. 7

10 10. Consider an increased reliability system for alarms and indication. The current system relies on the phone/modem system, and is not self-diagnostic and no immediate alarms if it fails. 11. Consider running the Vaporizer baths at a lower percentage of glycol to improve the heat transfer. 12. Consider implementing a propane vapour temperature control system on the Vaporizers. (only if an RTU is added for information). 13. Consider modifying the temperature control set for the Vaporizer at Function Junction, to provide faster feedback/control tuning. 14. Verify that the safety systems function as designed: e.g. that the loss of flame trip causes the liquid inlet solenoid valve to close. 15. Label the operators in the field, to minimize the likelihood of the setpoints being incorrectly adjusted, or adjusted on the wrong operator. Operators not always on site, and rely on pager system to alert them to problems. The percentage of glycol in water required for maximum heat transfer efficiency is not documented for the site. This would provide more direct control over propane header pressure, as bath temperature control is a delayed control. As well, the provides the potential for remote control, allowing the operators to increase vaporization temperature in the peak demand times in the case of an upset. It has historically had problems with delayed response, causing bath temperatures to drop significantly before the temperature controller turns back on, which results in inefficient propane vaporization. Unable to confirm during the evaluation that a loss of flame trip condition causes the inlet solenoid valve to go closed directly, rather than waiting for the high level trip to happen. One specific area of concern is the South Plant, which is not as well known to operators. In the case that another person, less familiar with the Whistler Sites, needs to respond, the labeling is either unclear or not present. All recommendations are also appended to this report. 8

11 Appendix A Worksheets

12 Appendix B Recommendation List

13 Terasen Whistler, BC Recommendations Whistler Propane Plant Reliability HAZOP Recommendations Comment CAT Resolution 1. Consider providing a discreet local pump status indication (e.g. light) for Vaporizer Feed pumps. The location of the feed pumps under the awning makes it difficult to assess if the pump motor is on, especially if there is snow. 2. Consider providing a page status for pump failure. 3. Consider providing remote start/stop of the Vaporizer Feed pumps. This would allow operators to respond to a pump failure quickly, to start a spare pump. Stopping a pump would reduce the flow of liquid to the vaporizers to minimize the potential for high level trips, and would decrease the system pressure but not stop the flow. 4. Verify and ensure that the gen-set is function tested on full load, to ensure it can handle maximum load. 5. Lock and tag closed the bypass valve around the liquid supply solenoid valves to each propane vaporizer. These are safety systems which should not be bypassed, except under controlled circumstances. 6. Consider providing a UPS (battery backup) to the power supply to the Vaporizers and Lighting panel 7. Verify and ensure that that the nitrogen supply header is not vulnerable to snow/ice load, especially the section upstream of the restriction orifice. 8. Implement a formal program for checking and testing the microswitches on the nitrogen system to the tank ESVs. 9. Include both the pump internal relief valves and the safety relief valves on the Vaporizer Feed Pump discharge on the PSV maintenance system. on a maintenance schedule. Note - history of operators not noticing that pumps were not running. Light would aid in detection. Currently, there is no remote notification of pump status, and the pump(s) are required in winter to sustain pressure. Pumps have been reliable; however as the demand is increased, the pumps will be required more often. As well, when they are needed, they are more critical as losing a pump in peak demand could mean a system outage. The gen-set is function tested, but the inspection reports were unclear if it was tested under a full load. To be treated like any other safety system, e..g. PSV. 15 kva transformer causes loss of power to the instrumentation panel, which would cause the vaporizers to trip. The pumps have gen-set backup, but the vaporizer instrumentation does not, but the required level of reliability would be the same. Icing and snow load have the potential to cause failure of tubing. Informal program in place, but needs to be made standard. Since the outlet of the pump discharge PSVs can be blocked in (e.g. valve #221 and 222 can be closed), then the pump internal PSVs are the only reliable form of overpressure protection. SAF Prepared by ClearSky Risk Management Evaluation Date: June 6, 2005 Page 1 of 3

14 Terasen Whistler, BC Recommendations Whistler Propane Plant Reliability HAZOP Recommendations Comment CAT Resolution 10. Consider an increased reliability system for alarms and indication. The current system relies on the phone/modem system, and is not self-diagnostic and no immediate alarms if it fails. 11. Consider running the Vaporizer baths at a lower percentage of glycol to improve the heat transfer. 12. Consider implementing a propane vapour temperature control system on the Vaporizers. (only if an RTU is added for information). Operators not always on site, and rely on pager system to alert them to problems. The percentage of glycol in water required for maximum heat transfer efficiency is not documented for the site. This would provide more direct control over propane header pressure, as bath temperature control is a delayed control. 13. Consider modifying the temperature control set for the Vaporizer at Function Junction, to provide faster feedback/control tuning. 14. Verify that the safety systems function as designed: e.g. that the loss of flame trip causes the liquid inlet solenoid valve to close. 15. Label the operators in the field, to minimize the likelihood of the setpoints being incorrectly adjusted, or adjusted on the wrong operator. 16. Inventory spare parts for the entire system, and provide spare parts for for critical equipment, such as: Fire eyes Level switches High Temperature switches Bath temperature control switches Flame guard ignition system Microswitches Liquid inlet solenoid valve.. e.g. PRV-1120 (& similar) As well, the provides the potential for remote control, allowing the operators to increase vaporization temperature in the peak demand times in the case of an upset. It has historically had problems with delayed response, causing bath temperatures to drop significantly before the temperature controller turns back on, which results in inefficient propane vaporization. Unable to confirm during the evaluation that a loss of flame trip condition causes the inlet solenoid valve to go closed directly, rather than waiting for the high level trip to happen. One specific area of concern is the South Plant, which is not as well known to operators. In the case that another person, less familiar with the Whistler Sites, needs to respond, the labeling is either unclear or not present. At a minimum, stocking spare parts and having the knowledge to repair or replace equipment will minimize downtime for vaporizers. SAF Prepared by ClearSky Risk Management Evaluation Date: June 6, 2005 Page 2 of 3

15 Terasen Whistler, BC Recommendations Whistler Propane Plant Reliability HAZOP Recommendations Comment CAT Resolution 17. Consider developing a procedure to unload the demand on the system, while a vaporizer is down during peak demand. Sacrificing the supply to some customers may be required in order to prevent a total outage. 18. Calculate (estimate) how long it would take at peak demand for the vaporizers to flood and trip on high level, if one of the vaporizers trip. If the time to react is low (.e.g less than one hour), consider implementing options that would mitigate the sudden pressure surge due to losing a vaporizer at peak times, such as: a) Install temperature controller, remotely activated. Increasing vaporizer temperatures temporarily will allow for increased propane generation. It is expected that a procedure to cut off supply to some users will be an unpopular move. However, having a documented protocol for use in the case of emergency is preferred over leaving the operators to make last-minute decisions. There has been experience with remaining vaporizers flooding if one vaporizer goes down during peak demand. If it happens while the site is unmanned, the time to respond may be too long before a total outage occurs. b) Remote start/stop of the Vaporizer Feed pumps. Stopping a pump would reduce the flow of liquid to the vaporizers to minimize the potential for high level trips, and would decrease the system pressure but not stop the flow. 19. Develop an operating procedure to deal with a loss of one Vaporizer during peak demands, to assist in decision-making whether to fix the problem or to reduce the throughput. The first evaluation is to check the demand, and to determine if the existing number of vaporizers can match that demand. The procedure should include a reference table of how much each vaporizer can produce at certain temperature/pressure profiles, for an 'at a glance' reference. If existing vaporizers cannot keep up, then reducing the demand or throughput would be necessary to prevent tripping out the remaining vaporizers. In addition to providing operators with a tool to make difficult decisions, this would also provide an understanding between the site and the head office as to how to deal with outages. Prepared by ClearSky Risk Management Evaluation Date: June 6, 2005 Page 3 of 3

NORMAL OPERATING PROCEDURES Operating Parameter Information

NORMAL OPERATING PROCEDURES Operating Parameter Information Operating Parameter Information Each operator performing the normal operating procedures (routine checks) of the facility should be familiar with the current normal operating parameters of all systems

More information

A large Layer of Protection Analysis for a Gas terminal scenarios/ cause consequence pairs

A large Layer of Protection Analysis for a Gas terminal scenarios/ cause consequence pairs A large Layer of Protection Analysis for a Gas terminal 2000+ scenarios/ cause consequence pairs Richard Gowland European process Safety Centre The scope of the study was a large gas terminal handling

More information

Safety Engineering - Hazard Identification Techniques - M. Jahoda

Safety Engineering - Hazard Identification Techniques - M. Jahoda Safety Engineering - Hazard Identification Techniques - M. Jahoda Hazard identification The risk management of a plant 2 Identification of the hazards involved in the operation of the plant, due to the

More information

OPERATING PROCEDURES

OPERATING PROCEDURES OPERATING PROCEDURES 1.0 Purpose This element identifies Petsec s Operating Procedures for its Safety and Environmental Management System (SEMS) Program; it applies to all Petsec operations. Petsec is

More information

AUSTRALIA ARGENTINA CANADA EGYPT NORTH SEA U.S. CENTRAL U.S. GULF. SEMS HAZARD ANALYSIS TRAINING September 29, 2011

AUSTRALIA ARGENTINA CANADA EGYPT NORTH SEA U.S. CENTRAL U.S. GULF. SEMS HAZARD ANALYSIS TRAINING September 29, 2011 AUSTRALIA ARGENTINA CANADA EGYPT NORTH SEA U.S. CENTRAL U.S. GULF SEMS HAZARD ANALYSIS TRAINING September 29, 2011 Purpose The purpose of this meeting is to provide guidelines for determination of hazard

More information

Every things under control High-Integrity Pressure Protection System (HIPPS)

Every things under control High-Integrity Pressure Protection System (HIPPS) Every things under control www.adico.co info@adico.co Table Of Contents 1. Introduction... 2 2. Standards... 3 3. HIPPS vs Emergency Shut Down... 4 4. Safety Requirement Specification... 4 5. Device Integrity

More information

(C) Anton Setzer 2003 (except for pictures) A2. Hazard Analysis

(C) Anton Setzer 2003 (except for pictures) A2. Hazard Analysis A2. Hazard Analysis In the following: Presentation of analytical techniques for identifyin hazards. Non-formal, but systematic methods. Tool support for all those techniques exist. Techniques developed

More information

CASE STUDY. Compressed Air Control System. Industry. Application. Background. Challenge. Results. Automotive Assembly

CASE STUDY. Compressed Air Control System. Industry. Application. Background. Challenge. Results. Automotive Assembly Compressed Air Control System Industry Automotive Assembly Application Savigent Platform and Industrial Compressed Air Systems Background This automotive assembly plant was using over 40,000 kilowatt hours

More information

Inherently Safer Design Analysis Approaches

Inherently Safer Design Analysis Approaches Inherently Safer Design Analysis Approaches There are a number of ways inherent safety can be analyzed. In any case, the intent is to formalize the consideration of inherent safety rather than to include

More information

SAFETY PLAN REVIEW ITM

SAFETY PLAN REVIEW ITM ITM Power (#4) Hydrogen Fueling Station Safety Plan Review Submission for the California Energy Commission General Funding Opportunity GFO-15-605 Background At the request of the California Energy Commission,

More information

Unit 24: Applications of Pneumatics and Hydraulics

Unit 24: Applications of Pneumatics and Hydraulics Unit 24: Applications of Pneumatics and Hydraulics Unit code: J/601/1496 QCF level: 4 Credit value: 15 OUTCOME 2 TUTORIAL 9 ACCUMULATORS The material needed for outcome 2 is very extensive so there are

More information

Identification and Screening of Scenarios for LOPA. Ken First Dow Chemical Company Midland, MI

Identification and Screening of Scenarios for LOPA. Ken First Dow Chemical Company Midland, MI Identification and Screening of Scenarios for LOPA Ken First Dow Chemical Company Midland, MI 1 Layers of Protection Analysis (LOPA) LOPA is a semi-quantitative tool for analyzing and assessing risk. The

More information

Digester Processes. 1. Raw Sludge Pumping System

Digester Processes. 1. Raw Sludge Pumping System Digester Processes 1. Raw Sludge Pumping System Removes accumulated sludge from the primary clarifiers, pumped through 1 of 2 pipes either 150 or 200mm in diameter (Fig. 1.1). Fig 1.1 Pipes feeding Digesters

More information

Improve Reliability of Turbomachinery Lubrication and Sealing Systems

Improve Reliability of Turbomachinery Lubrication and Sealing Systems Improve Reliability of Turbomachinery Lubrication and Sealing Systems Fisher Pressure Control Solutions For Turbomachinery Applications Protect the integrity of your Turbomachinery support system Turbomachinery

More information

Ingersoll Rand. X-Series System Automation

Ingersoll Rand. X-Series System Automation Ingersoll Rand -Series System Automation Energy Savings on Demand! Ingersoll Rand As much as 20% to 60% of the energy used to operate compressed air systems is wasted. This is primarily due to operating

More information

Drain Splash Back Burns Operator

Drain Splash Back Burns Operator Purpose To share lessons learned gained from incident investigations through a small group discussion method format. To understand lessons learned through a Systems of Safety viewpoint. This material was

More information

Operator Exposed to Chlorine Gas

Operator Exposed to Chlorine Gas Operator Exposed to Chlorine Gas Lessons Learned Volume 04 Issue 29 2004 USW Operator Exposed to Chlorine Gas Purpose To conduct a small group lessons learned activity to share information gained from

More information

Using LOPA for Other Applications

Using LOPA for Other Applications 10 Using LOPA for Other Applications 10.1. Purpose LOPA is a tool used to perform risk assessments. Previous chapters described its use in assessing the risk level of process hazards scenarios and in evaluating

More information

MANUAL GAS MANIFOLDS

MANUAL GAS MANIFOLDS MANUAL GAS MANIFOLDS Phoenix Pipeline Products Limited. Unit 8, McKenzie Industrial Park, Tel No.: 44 (0) 161 428 7200 Bird Hall Lane, Fax No.: 44 (0) 161 428 7010 Stockport, Email: info@p3-phoenix.com

More information

Fisher DVI Desuperheater Venturi Inline

Fisher DVI Desuperheater Venturi Inline Instruction Manual DVI Desuperheater Fisher DVI Desuperheater Venturi Inline Contents Introduction... 1 Scope of Manual... 1 Description... 1 Principle of Operation... 2 Installation... 3 Operating Instructions...

More information

SAFETY SEMINAR Rio de Janeiro, Brazil - August 3-7, Authors: Francisco Carlos da Costa Barros Edson Romano Marins

SAFETY SEMINAR Rio de Janeiro, Brazil - August 3-7, Authors: Francisco Carlos da Costa Barros Edson Romano Marins SAFETY SEINAR Rio de Janeiro, Brazil - August 3-7, 2009 Using HAZOP and LOPA ethodologies to Improve Safety in the Coke Drums Cycles Authors: Gilsa Pacheco onteiro Francisco Carlos da Costa Barros Edson

More information

MWEA MAINTENANCE SEMINAR SPECIALTY VALVES POWER GLOBES

MWEA MAINTENANCE SEMINAR SPECIALTY VALVES POWER GLOBES MWEA MAINTENANCE SEMINAR SPECIALTY VALVES POWER GLOBES J O H N G. H U N T E R Types of Valves P A U L M A R C H I Accessories Principals of Operation Maintenance Control Valve Types Common Problems Key

More information

COLLEGE OF ENGINEERING LABORATORY SAFETY MANAGEMENT SYSTEM (SMS) & HAZOP PROTOCOL January 2018

COLLEGE OF ENGINEERING LABORATORY SAFETY MANAGEMENT SYSTEM (SMS) & HAZOP PROTOCOL January 2018 COLLEGE OF ENGINEERING LABORATORY SAFETY MANAGEMENT SYSTEM (SMS) & HAZOP PROTOCOL January 08 CONTENTS SUMMARY OF RESPONSIBILITIES... Policy for Creating Research Standard Operating Procedures (SOPs)...

More information

Before You Fix the Relief Valve Problem

Before You Fix the Relief Valve Problem Before You Fix the Relief Valve Problem Careful considerations when mitigating inadequate relief systems designs Jason Spearow, P.E Presenter Biography Jason Spearow, P.E. Smith & Burgess LLC Senior Process

More information

DATA ITEM DESCRIPTION Title: Failure Modes, Effects, and Criticality Analysis Report

DATA ITEM DESCRIPTION Title: Failure Modes, Effects, and Criticality Analysis Report DATA ITEM DESCRIPTION Title: Failure Modes, Effects, and Criticality Analysis Report Number: Approval Date: 20160106 AMSC Number: N9616 Limitation: No DTIC Applicable: Yes GIDEP Applicable: Yes Defense

More information

Module No. # 01 Lecture No. # 6.2 HAZOP (continued)

Module No. # 01 Lecture No. # 6.2 HAZOP (continued) Health, Safety and Environmental Management in Petroleum and Offshore Engineering Prof. Srinivasan Chandrasekaran Department of Ocean Engineering Indian Institute Of Technology, Madras Module No. # 01

More information

PSM TRAINING COURSES. Courses can be conducted in multi-languages

PSM TRAINING COURSES. Courses can be conducted in multi-languages Courses can be conducted in multi-languages One set of hardcopy course notes will be sent to client for printing and distribution to course participants. The courses will be held at the client s training

More information

SAFETY PLAN REVIEW. FirstElement Safety Plan Review Submission for the California Energy Commission General Funding Opportunity GFO

SAFETY PLAN REVIEW. FirstElement Safety Plan Review Submission for the California Energy Commission General Funding Opportunity GFO FirstElement Safety Plan Review Submission for the California Energy Commission General Funding Opportunity GFO-15-605 Background At the request of the California Energy Commission, members of the Hydrogen

More information

Emergency Situation Assessment

Emergency Situation Assessment Appendix 1 Emergency Situation Assessment Emergency Situation Assessment In-coming mains electricity failure sites with generator backup Useful Information: Severity 2 Risk Rating Low / 10 Likelihood 5

More information

Pressure Gauge Failure Causes Release

Pressure Gauge Failure Causes Release Pressure Gauge Failure Causes Release Lessons Learned Volume 04 Issue 02 2004 USW Pressure Gauge Failure Causes Release Purpose To conduct a small group lessons learned activity to share information gained

More information

OIL SUPPLY SYSTEMS ABOVE 45kW OUTPUT 4.1 Oil Supply

OIL SUPPLY SYSTEMS ABOVE 45kW OUTPUT 4.1 Oil Supply OIL SUPPLY SYSTEMS ABOVE 45kW OUTPUT 4.1 Oil Supply 4.1.1 General The primary function of a system for handling fuel oil is to transfer oil from the storage tank to the oil burner at specified conditions

More information

Fuel Gas Pressure Control Solutions for Fired Heaters and Boilers

Fuel Gas Pressure Control Solutions for Fired Heaters and Boilers Fuel Gas Control Solutions for Fired Heaters and Boilers Solutions for safer and more reliable operation of fired heater fuel gas systems. Prevent process downtime by keeping your critical heaters online.

More information

TESCOM 50-4X Series Safety, Installation & Start-Up Procedures

TESCOM 50-4X Series Safety, Installation & Start-Up Procedures Operations & Service Manual TESCOM 50-4X Series Safety, Installation & Start-Up Procedures Do not attempt to select, install, use or maintain this product until you have read and fully understood this

More information

MAHB. INSPECTION Process Hazard Analysis

MAHB. INSPECTION Process Hazard Analysis Number 5 2016 seveso common MAHB INSPECTION s e r i e s criteria Process Hazard Analysis Major Accident Hazards Bureau Security Technology Assessment Unit This publication of the European community on

More information

FLUID POWER FLUID POWER EQUIPMENT TUTORIAL ACCUMULATORS. This work covers part of outcome 2 of the Edexcel standard module:

FLUID POWER FLUID POWER EQUIPMENT TUTORIAL ACCUMULATORS. This work covers part of outcome 2 of the Edexcel standard module: FLUID POWER FLUID POWER EQUIPMENT TUTORIAL ACCUMULATORS This work covers part of outcome 2 of the Edexcel standard module: UNIT 21746P APPLIED PNEUMATICS AND HYDRAULICS The material needed for outcome

More information

COMMON MISUNDERSTANDINGS ABOUT THE PRACTICAL APPLICATION OF IEC 61508

COMMON MISUNDERSTANDINGS ABOUT THE PRACTICAL APPLICATION OF IEC 61508 COMMON MISUNDERSTANDINGS ABOUT THE PRACTICAL APPLICATION OF IEC 61508 Helen Pearce, James Catmur and Geoff Stevens The use of IEC 61508 for determination of the Safety Integrity Level (SIL) of Safety Interlock

More information

CONTROL OF HAZARDOUS ENERGY IN THE WORKPLACE

CONTROL OF HAZARDOUS ENERGY IN THE WORKPLACE Office of Environmental Health & Safety CONTROL OF HAZARDOUS ENERGY IN THE WORKPLACE LOCK OUT/TAG OUT OSHA 29 CFR 1910.147 rev. 3 2014 Director of Environmental Health & Safety Control of Hazardous Energy

More information

The Future of Hydraulic Control in Water-Systems

The Future of Hydraulic Control in Water-Systems The Future of Hydraulic Control in Water-Systems A. Heimann Manager of R&D and of Technical Support & Applications Engineering departments at Dorot Automatic Control Valves Dorot Control Valves, Kibbutz

More information

Advanced Pump Control for Irrigation Applications

Advanced Pump Control for Irrigation Applications Advanced Pump Control for Irrigation Applications Paul Nistler VFD Applications Engineer And Julian Atchia Director of Research and Development SJE Rhombus 22650 County Hwy 6 Detroit Lakes MN 56502 Executive

More information

BERMAD Fire Protection Hydraulic Control Valves

BERMAD Fire Protection Hydraulic Control Valves BERMAD Fire Protection Hydraulic Control Valves Control Solutions with the Power to Protect BERMAD - The Company Since its foundation in 1965, BERMAD has focused its efforts on innovation, quality and

More information

Copeland Discus with CoreSense Diagnostics January 2011

Copeland Discus with CoreSense Diagnostics January 2011 Copeland Discus with CoreSense Diagnostics January 2011 Slide 1 1/27/2011 5:48 PM Discus with CoreSense Diagnostics Case Studies Supermarket In Columbus, Ohio Saves $4,500 With Discus with CoreSense Diagnostics

More information

Incorrect Relief Valve Material Causes Release

Incorrect Relief Valve Material Causes Release Incorrect Relief Valve Material Causes Release Lessons Learned Volume 04 Issue 18 2004 USW Purpose Incorrect Relief Valve Material Causes Release To conduct a small group lessons learned activity to share

More information

USE A RELIABLE A INNOVATIVE A COST EFFICIENT GAS EQUIPMENTS AND GAS SYSTEMS

USE A RELIABLE A INNOVATIVE A COST EFFICIENT GAS EQUIPMENTS AND GAS SYSTEMS USE A RELIABLE A INNOVATIVE A COST EFFICIENT GAS EQUIPMENTS AND GAS SYSTEMS Air & Opp. Pudumjee Paper Mills, Thergaon, Chinchwad, Pune, Maharashtra State, India-411033 Telephone. ++91 20 27273809 Telefax

More information

Control of Energy - Isolation Process

Control of Energy - Isolation Process Issue Date: 24/03/17 Last Reviewed: 24/03/17 Next Review Date: 24/03/18 Authorised By: Mike Muir Safe Operating Procedure Control of Energy - Isolation Process Purpose: This SOP is based on a Generic 12-step

More information

ACV-10 Automatic Control Valve

ACV-10 Automatic Control Valve ACV-10 Automatic Control Valve Installation, Operation & Maintenance General: The Archer Instruments ACV-10 is a precision automatic feed rate control valve for use in vacuum systems feeding Chlorine,

More information

Quantitative Risk Analysis (QRA)

Quantitative Risk Analysis (QRA) Quantitative Risk Analysis (QRA) A realistic approach to relief header and flare system design Siemens AG 2017, All rights reserved 1 Quantitative Risk Analysis Introduction Most existing pressure relief

More information

General Duty Clause. Section 112(r)(1) of CAA. Chris Rascher, EPA Region 1

General Duty Clause. Section 112(r)(1) of CAA. Chris Rascher, EPA Region 1 General Duty Clause Section 112(r)(1) of CAA Chris Rascher, EPA Region 1 Background on the General Duty Clause General Duty Clause 112(r)(1) of CAA Prevention of Accidental Releases Purpose and General

More information

Raw Material Spill. Lessons Learned. Volume 05 Issue USW

Raw Material Spill. Lessons Learned. Volume 05 Issue USW Raw Material Spill Lessons Learned Volume 05 Issue 14 2005 USW Raw Material Spill Purpose To conduct a small group lessons learned activity to share information gained from incident investigations. To

More information

THE BAKER REPORT HOW FINDINGS HAVE BEEN USED BY JOHNSON MATTHEY TO REVIEW THEIR MANUFACTURING OPERATIONS

THE BAKER REPORT HOW FINDINGS HAVE BEEN USED BY JOHNSON MATTHEY TO REVIEW THEIR MANUFACTURING OPERATIONS THE BAKER REPORT HOW FINDINGS HAVE BEEN USED BY JOHNSON MATTHEY TO REVIEW THEIR MANUFACTURING OPERATIONS Colin P. Lynas, Elizabeth Campbell and Hendrik J. Koornhof Johnson Matthey Catalysts This paper

More information

Thank You for Attending Today s Webinar. Today s Featured Speaker

Thank You for Attending Today s Webinar. Today s Featured Speaker Thank You for Attending Today s Webinar Your Host Mike DeLacluyse President Lesman Instrument Company miked@lesman.com Today s Featured Speaker A.J. Piskor Combustion & Controls Specialist Lesman Instrument

More information

AUTOMATIC GAS MANIFOLDS

AUTOMATIC GAS MANIFOLDS AUTOMATIC GAS MANIFOLDS Phoenix Pipeline Products Limited. Unit 8, McKenzie Industrial Park, Tel No.: 44 (0) 161 428 7200 Bird Hall Lane, Fax No.: 44 (0) 161 428 7010 Stockport, Email: info@p3-phoenix.com

More information

INOGATE Technical Secretariat UK Experience European Standards Implementation Key Expert Phil Winnard Session 2 Georgia, October 2015

INOGATE Technical Secretariat UK Experience European Standards Implementation Key Expert Phil Winnard Session 2 Georgia, October 2015 INOGATE Technical Secretariat UK Experience European Standards Implementation Key Expert Phil Winnard Session 2 Georgia, October 2015 BUILDING PARTNERSHIPS FOR ENERGY SECURITY www.inogate.org EN 12186

More information

EXPERIMENT 1 AIR PRESSURE CONTROL SYSTEM

EXPERIMENT 1 AIR PRESSURE CONTROL SYSTEM EXPERIMENT 1 AIR PRESSURE CONTROL SYSTEM 1.0 OBJECTIVE To study the response of gas pressure control using PID controller. 2.0 INTRODUCTION TO THE APPARATUS a) The process plant consists of two air vessels

More information

I. Subject: Medical Gas Systems Utility Failure Interim Procedure III. Purpose:

I. Subject: Medical Gas Systems Utility Failure Interim Procedure III. Purpose: I. Subject: Medical Gas Systems Utility Failure Interim Procedure II. Purpose: To provide a systematic response to medical gas system failure and restoration of this critical utility. III. Procedure: Systems

More information

Requirements for Reduced Supervision of Power Plants, Thermal Liquid Heating Systems, and Heating Plants

Requirements for Reduced Supervision of Power Plants, Thermal Liquid Heating Systems, and Heating Plants the pressure equipment safety authority Requirements for Reduced Supervision of Power Plants, Thermal Liquid Heating Systems, and Heating Plants AB-528 Edition 2, Revision 1 Issued 2016-09-12 Table of

More information

FIRE PROTECTION PRODUCTS

FIRE PROTECTION PRODUCTS AGF Manufacturing Inc. FIRE PROTECTION PRODUCTS PRODUCT CATALOG CAT-AGF_V002 1/15 Reliability, Versatility, Code Compatibility AGF Product Catalog Table of Contents COLLECTa ndrain Auxiliary Drains Model

More information

FIRE SPRINKLER PRODUCTS PRODUCT CATALOG

FIRE SPRINKLER PRODUCTS PRODUCT CATALOG AGF Manufacturing Inc. FIRE SPRINKLER PRODUCTS PRODUCT CATALOG CAT-AGF_2018 3/18 Reliability, Versatility, Code Compatibility All orders MUST be received by AGF Manufacturing, Inc. in a written format

More information

BPZM-MRD Nitrogen Injection System

BPZM-MRD Nitrogen Injection System BPZM-MRD Nitrogen Injection System (Transformer protector) Overview BPZM-MRD Nitrogen Injection Explosion Prevention & Fire Protection System became more advanced fire protection and explosion prevention

More information

CT433 - Machine Safety

CT433 - Machine Safety Rockwell Automation On The Move May 16-17 2018 Milwaukee, WI CT433 - Machine Safety Performance Level Selection and Design Realization Jon Riemer Solution Architect Safety & Security Functional Safety

More information

Gas Check. Short testing time, with automatic start-up if no leakage was detected from previous operation.

Gas Check. Short testing time, with automatic start-up if no leakage was detected from previous operation. Quality Products at Competitive Prices Gas Check Automatic testing of the down-stream installation to check that all valves are closed and that pipework and fittings are gas tight before each system start-up.

More information

DUPLEX PRESSURE REDUCING SET

DUPLEX PRESSURE REDUCING SET DUPLEX PRESSURE REDUCING SET Phoenix Pipeline Products Limited. Unit 8, McKenzie Industrial Park, Tel No.: 44 (0) 161 428 7200 Bird Hall Lane, Fax No.: 44 (0) 161 428 7010 Stockport, Email: info@p3-phoenix.com

More information

MEDICAL EQUIPMENT CATALOG

MEDICAL EQUIPMENT CATALOG THE MOST TRUSTED MEDICAL EQUIPMENT IN NORTH AMERICA MEDICAL EQUIPMENT CATALOG Total Components Including Bulk Oxygen Supply, Back up and Delivery Equipment Designs for High Pressure, Liquid or Bulk Applications

More information

WELL TEST HAZOP CAPABILITY STATEMENT

WELL TEST HAZOP CAPABILITY STATEMENT WELL TEST HAZOP CAPABILITY STATEMENT INTRODUCTION Hazard and Operability (HAZOP) is a hazard analysis method used to identify hazards and operational problems. The standard HAZOP methodology is process-based

More information

How to Define Your Systems and Assets to Support Reliability. How to Define Your Failure Reporting Codes to Support Reliability

How to Define Your Systems and Assets to Support Reliability. How to Define Your Failure Reporting Codes to Support Reliability BACKFED RELIABILITY How to Define Your Systems and Assets to Support Reliability How to Define Your Failure Reporting Codes to Support Reliability How to Generate Risk Prioritization Numbers (RPN) from

More information

BUBBLER CONTROL SYSTEM

BUBBLER CONTROL SYSTEM BUBBLER CONTROL SYSTEM Description: The HDBCS is a fully automatic bubbler system, which does liquid level measurements in water and wastewater applications. It is a dual air compressor system with, air

More information

BACK PRESSURE / SUSTAINING

BACK PRESSURE / SUSTAINING In many liquid piping systems, it is vital that line pressure is maintained within relatively narrow limits. This is the function of the 108 Pressure Relief / Back Pressure Series of the OCV control valves.

More information

BACK PRESSURE / SUSTAINING

BACK PRESSURE / SUSTAINING SPECIFICATIONS DIMENSIONS In many liquid piping systems, it is vital that line pressure is maintained within relatively narrow limits. This is the function of the 108 Pressure Relief / Back Pressure Series

More information

Pressure management for Large

Pressure management for Large Pressure management for Large diameter pipe systems Case Study Scottish Water Muirhouse PRV David Humphrey Water treatment works Control in Water networks Booster pumps Reservoirs Pump Fed Gravity Fed

More information

Water Mist Systems Inspection, Testing, and Maintenance of Water Mist Systems

Water Mist Systems Inspection, Testing, and Maintenance of Water Mist Systems Water Mist Systems Inspection, Testing, and Maintenance of Water Mist Systems Name of Property: Address: Phone Number: Inspector: Contract No.: Date: This Report Covers: Monthly Quarterly Annual Other

More information

Knowledge, Certification, Networking

Knowledge, Certification, Networking www.iacpe.com Knowledge, Certification, Networking Page :1 of 71 Rev 01 Sept 2016 IACPE No 19, Jalan Bilal Mahmood 80100 Johor Bahru Malaysia The International of is providing the introduction to the Training

More information

RESILIENT SEATED BUTTERFLY VALVES FUNCTIONAL SAFETY MANUAL

RESILIENT SEATED BUTTERFLY VALVES FUNCTIONAL SAFETY MANUAL Per IEC 61508 and IEC 61511 Standards BRAY.COM Table of Contents 1.0 Introduction.................................................... 1 1.1 Terms and Abbreviations...........................................

More information

Frequently Asked Questions Directive 056 Facilities Technical

Frequently Asked Questions Directive 056 Facilities Technical Frequently Asked Questions Directive 056 Facilities Technical October 2017 This document clarifies and supports some of the technical requirements related to Directive 056: Energy Development Applications

More information

4m Blanco Glycol Chiller system: history, recent events, present status and plans

4m Blanco Glycol Chiller system: history, recent events, present status and plans 4m Blanco Glycol Chiller system: history, recent events, present status and plans Brooke Gregory, Esteban Parkes, Chris Smith 22 May 2012 Background Information: Original configuration (from ~1975) of

More information

Wrench Slip Causes Laceration

Wrench Slip Causes Laceration Purpose To share lessons learned gained from incident investigations through a small group discussion method format. To understand lessons learned through a Systems of Safety viewpoint. This material was

More information

Manual Actuated Boiler Blowdown Valves

Manual Actuated Boiler Blowdown Valves Manual Actuated Boiler Blowdown Valves Installation and Maintenance Instructions 1. Safety information 2. General product information 3. Installation 4. Operation 5. Maintenance 6. Spare parts p.1 1. Safety

More information

GeQuip Joule Thomson Plant. Process Description (see Figure 1) Standard Control Instrumentation

GeQuip Joule Thomson Plant. Process Description (see Figure 1) Standard Control Instrumentation Process Description (see Figure 1) The purpose of the process configuration of a Joule Thomson plant is to refrigerate the gas by expanding the gas across a restriction (commonly referred to as a choke

More information

TECHNICAL DATA. the Viking Pilot Pressure Regulating Valve 1 Model A-1 Speed Control Assembly: OBSOLETE. the Viking Speed Control Assembly 1

TECHNICAL DATA. the Viking Pilot Pressure Regulating Valve 1 Model A-1 Speed Control Assembly: OBSOLETE. the Viking Speed Control Assembly 1 November 30, 1994 534 a 1. PRODUCT NAME VIKING 2" (50mm), 3" (75mm), 4" (100mm), 6" (150mm) 2. MANUFACTURER THE VIKING CORPORATION 210 N. Industrial Park Road Hastings, Michigan 49058 U.S.A. Telephone:

More information

Safety in Petroleum Industry

Safety in Petroleum Industry Chemical ( Industrial ) Disaster Management Conference, Bangalore 30 January 2014 Safety in Petroleum Industry Refineries and Petrochemical plants are highly energyintensive Handle highly inflammable and

More information

HOW TO MANAGE VAPORIZATION IN AN ANALYTICAL SYSTEM By Dean Slejko and Tony Waters

HOW TO MANAGE VAPORIZATION IN AN ANALYTICAL SYSTEM By Dean Slejko and Tony Waters HOW TO MANAGE VAPORIZATION IN AN ANALYTICAL SYSTEM By Dean Slejko and Tony Waters If the analyzer in your analytical system requires gas but your sample is liquid, the only option is to convert the liquid

More information

Types 749B and R130 Changeover Manifolds

Types 749B and R130 Changeover Manifolds Instruction Manual MCK-1179 Types 749B and R130 June 2012 Types 749B and R130 Changeover Manifolds TYPE HSRL-749B TYPE 64SR/122 TYPE R130/21 TYPE 749B/21 Figure 1. Changeover Manifolds and Regulator Assemblies

More information

Performance Monitoring Examples Monitor, Analyze, Optimize

Performance Monitoring Examples Monitor, Analyze, Optimize Performance Monitoring Examples Monitor, Analyze, Optimize BETA's Performance Assessment service is a low cost remote monitoring service for reciprocating compressors, centrifugal compressors, engines,

More information

USING HAZOP TO IDENTIFY AND MINIMISE HUMAN ERRORS IN OPERATING PROCESS PLANT

USING HAZOP TO IDENTIFY AND MINIMISE HUMAN ERRORS IN OPERATING PROCESS PLANT USING HAZOP TO IDENTIFY AND MINIMISE HUMAN ERRORS IN OPERATING PROCESS PLANT Chris Lyth, Tracerco, Billingham, Cleveland, UK Ian Bradby, ABB Engineering Services, Billingham Cleveland, UK This joint paper

More information

23.1 Functions, Basic Configuration, and Interfaces

23.1 Functions, Basic Configuration, and Interfaces 23 (6.6.D) SF 6 and Other Special Gases 23.1 Functions, Basic Configuration, and Interfaces 23.1.1 Functions The primary function performed by the SF 6 and other special gases system is to provide SF 6

More information

SAFE AND ENVIRONMENTALLY FRIENDLY

SAFE AND ENVIRONMENTALLY FRIENDLY SAFE AND ENVIRONMENTALLY FRIENDLY Thanks to our company s strong focus on innovation and development, we have developed the INERT-SIEX TM CFT-01 (Constant Flow Technology) system, one of the greatest advances

More information

Tirpur Area Water Supply Project A Report on Transient Modeling Study

Tirpur Area Water Supply Project A Report on Transient Modeling Study y February 2008 1 of 81 y INTRODUCTION: The report presents results from a transient modeling study conducted on the clear water transmission main of Tirpur Areas Water Supply Project, Tamilnadu, India.

More information

Impact on People. A minor injury with no permanent health damage

Impact on People. A minor injury with no permanent health damage Practical Experience of applying Layer of Protection Analysis For Safety Instrumented Systems (SIS) to comply with IEC 61511. Richard Gowland. Director European Process Safety Centre. (Rtgowland@aol.com,

More information

How to Optimize the Disposal System With Staggered Analysis Using BLOWDOWN Technology. Jump Start Guide

How to Optimize the Disposal System With Staggered Analysis Using BLOWDOWN Technology. Jump Start Guide How to Optimize the Disposal System With Staggered Analysis Using BLOWDOWN Technology Jump Start Guide Problem Statement In this guide, you will be introduced to the tools in BLOWDOWN that can be used

More information

RELIEF VALVES IN PARALLEL

RELIEF VALVES IN PARALLEL RELIEF VALVES IN PARALLEL Mary Kay O'Connor Process Safety Center International Symposium BEYOND REGULATORY COMPLIANCE MAKING SAFETY SECOND NATURE October 26-28, 2010 James R. Lawrence Sr. Why use a Relief

More information

Session One: A Practical Approach to Managing Safety Critical Equipment and Systems in Process Plants

Session One: A Practical Approach to Managing Safety Critical Equipment and Systems in Process Plants Session One: A Practical Approach to Managing Safety Critical Equipment and Systems in Process Plants Tahir Rafique Lead Electrical and Instruments Engineer: Qenos Botany Site Douglas Lloyd Senior Electrical

More information

Title: Pressure Relieving and Venting Devices Function: Ecology & Safety No.: BC Page: 1 of 7 Reviewed: 6/30/12 Effective: 7/1/12 (Rev.

Title: Pressure Relieving and Venting Devices Function: Ecology & Safety No.: BC Page: 1 of 7 Reviewed: 6/30/12 Effective: 7/1/12 (Rev. Preparer: Team Member, North America, Process Safety Center of Expertise No.: BC032.020 Page: 1 of 7 Owner: Manager, North America Process Safety Center of Expertise Approver: Sr. Vice President, Ecology

More information

Transient Analyses In Relief Systems

Transient Analyses In Relief Systems Transient Analyses In Relief Systems Dirk Deboer, Brady Haneman and Quoc-Khanh Tran Kaiser Engineers Pty Ltd ABSTRACT Analyses of pressure relief systems are concerned with transient process disturbances

More information

Avoiding Short Term Overheat Failures of Recovery Boiler Superheater Tubes

Avoiding Short Term Overheat Failures of Recovery Boiler Superheater Tubes Avoiding Short Term Overheat Failures of Recovery Boiler Superheater Tubes Dr. Andrew K. Jones International Paper Tim Carlier Integrated Test and Measurement 2017 International Chemical Recovery Conference

More information

Understanding safety life cycles

Understanding safety life cycles Understanding safety life cycles IEC/EN 61508 is the basis for the specification, design, and operation of safety instrumented systems (SIS) Fast Forward: IEC/EN 61508 standards need to be implemented

More information

Modeling a Pressure Safety Valve

Modeling a Pressure Safety Valve Modeling a Pressure Safety Valve Pressure Safety Valves (PSV), Pressure Relief Valves (PRV), and other pressure relieving devices offer protection against overpressure in many types of hydraulic systems.

More information

Temperature Controllers

Temperature Controllers IM0004 April 2013 CONTENTS T-12 Thermostat PAGE Introduction 1 Scope 1 Description 1 Specification 1 Temperature Controllers 2 INTRODUCTION CAUTION Prior to installing, the instructions provided herein

More information

my SYSTEM A guide to common applications in water distribution systems

my SYSTEM A guide to common applications in water distribution systems my SYSTEM A guide to common applications in water distribution systems WWW.SINGERVALVE.COM INDEX This short guide is intended to offer guidance on some of the common problems, applications and questions

More information

22. Specialty Valves.

22. Specialty Valves. 22. Specialty Valves. a. Types of Specialty Valves. 1) Use of the following specialty valves is covered in this section: Altitude Valve, Pressure Reducing Valve, Pressure Relief Valve, Swing Check Valve,

More information

Type R622 Pressure Reducing Regulator

Type R622 Pressure Reducing Regulator Type R622 Pressure Reducing Regulator June 2010 Compact Design Protective Inlet Screen High Capacity Internal Relief Light Weight W8806 Inlet and Outlet Pressure Gauge Taps Figure 1. Type R622 Pressure

More information

IS YOUR FLAP VALVE IN COMPLIANCE WITH NFPA ?

IS YOUR FLAP VALVE IN COMPLIANCE WITH NFPA ? IEP Technologies 417-1 South Street, Marlborough, MA, 01752 ph 855.793.8407 fax 508.485.3115 www.ieptechnologies.com IS YOUR FLAP VALVE IN COMPLIANCE WITH NFPA 69-2014? Introduction Dust explosions can

More information

Improving Accuracy of Frequency Estimation of Major Vapor Cloud Explosions for Evaluating Control Room Location through Quantitative Risk Assessment

Improving Accuracy of Frequency Estimation of Major Vapor Cloud Explosions for Evaluating Control Room Location through Quantitative Risk Assessment Improving Accuracy of Frequency Estimation of Major Vapor Cloud Explosions for Evaluating Control Room Location through Quantitative Risk Assessment Naser Badri 1, Farshad Nourai 2 and Davod Rashtchian

More information