STAGE 1 FINAL HAZARD ANALYSIS FOR BETHUNGRA LINE VALVE TO BOMEN

Size: px
Start display at page:

Download "STAGE 1 FINAL HAZARD ANALYSIS FOR BETHUNGRA LINE VALVE TO BOMEN"

Transcription

1 STAGE 1 FINAL HAZARD ANALYSIS FOR THE YOUNG TO BOMEN PIPELINE - FROM 8 KILOMETRES NORTH OF BETHUNGRA LINE VALVE TO BOMEN Prepared for: APA Group Document Number: APAGRO\ Revision B Prepared by: Karin Nilsson 22 June 2010 PO Box 248 Berowra Heights NSW 2082 Telephone: [02] Facsimile: [02] Planager@bigpond.net.au

2 Stage 1 Final Hazard Analysis for the Young to Bomen Pipeline - From 8 kilometres north of Bethungra Line valve to Bomen Acknowledgment The author would like to thank Rehan Bukhari for his assistance in preparing this report. Disclaimer This report was prepared by Planager Pty Ltd (Planager) as an account of work for the APA Group. The material in it reflects Planager's best judgement in the light of the information available to it at the time of preparation. However, as Planager cannot control the conditions under which this report may be used, Planager and its related corporations will not be responsible for damages of any nature resulting from use of or reliance upon this report. Planager's responsibility for advice given is subject to the terms of engagement with APA Group. Rev Date Description Prepared By Reviewed By Authorised By A 21/06/2010 Draft for Comment Karin Nilsson Maarten Tentij Rehan Bukhari B 22/06/2010 Final Report Karin Nilsson Maarten Tentij Rehan Bukhari Stage 1 Final Hazard Analysis For The Young To Bomen Pipeline - From 8 Kilometres North Of Bethungra Line Valve To Bomen

3 CONTENTS EXECUTIVE SUMMARY... I GLOSSARY... III 1 INTRODUCTION Background Scope and Aim of Study Input into the FHA The Project DESIGN AND OPERATION Main Changes Made to the Pipeline Since the Preliminary Hazard Analysis Evaluation Against PHA Assumptions MAIN SAFETY RISKS IDENTIFIED Safety Related Hazards and Risks Identified Comparison with Issues Raised in the Preliminary QRA REVIEW OF THE MAIN PREVENTATIVE AND PROTECTIVE SAFEGUARDS PROPOSED FOR THE PIPELINE IMPLICATIONS OF THE RESULTS OF THE HAZOP STUDY Results IMPLICATIONS OF THE RESULTS FROM THE SAFETY MANAGEMENT STUDY CONCLUSIONS AND DISCUSSIONS REFERENCES Stage 1 Final Hazard Analysis For The Young To Bomen Pipeline - From 8 Kilometres North Of Bethungra Line Valve To Bomen

4 EXECUTIVE SUMMARY To meet the rising demand for natural gas to the towns in the central south of NSW and to a new power station at Uranquinty, the East Australian Pipeline Pty Ltd (EAPL), a wholly owned subsidiary of APA Group, is proposing to loop the existing 12 Young to Bomen pipeline with an 18 pipeline which would run parallel to the existing pipeline. Due to the potentially hazardous nature of natural gas, the pipeline is classified as potentially hazardous as per the definition by the NSW Department of Planning. As one element of the planning approval process, a Preliminary Hazard Analysis (PHA) was prepared in October 2009 in accordance with the requirements of the NSW Department of Planning as stated in their Hazardous Industry Planning Advisory Paper (HIPAP) No. 6: Guidelines for Hazard Analysis (Reference 1) and for the risk to be evaluated and compared with their risk criteria, as specified in their HIPAP No. 4: Risk Criteria for Landuse Planning (Reference 2). The Department of Planning requires the risk to be re-evaluated at the final design stage and for a Final Hazard Analysis (FHA) to be prepared for the project. The aim of the FHA is to analyse and assess the hazards and resultant residual risk associated with the pipeline at the final design stage. As such, the FHA complements the PHA which was conducted at the early design stage. This FHA has been prepared as a Supplement to the PHA, and as such focuses on the differences that have evolved during the development of the project through its design phases. The scope of the PHA was to assess the risk associated with the natural gas pipeline from the point where the pipeline leaves the compressor station at Young up to the point where the pipeline enters the metering station at Bowmen amounting to a 131 km long pipeline. The pipeline from Young to Bomen will be constructed in two stages. Stage 1 is currently being undertaken, in which the pipeline is being constructed from Bomen metre station to 8 kilometres north of Bethungra Line valve, a total length of 61 kilometres. The present report summarises the results of the FHA for the Stage 1 pipeline from Bomen metre station to 8 kilometres north of Bethungra Line valve. Stage 1 Final Hazard Analysis For The Young To Bomen Pipeline - From 8 Kilometres North Of Bethungra Line Valve To Bomen i

5 If and when Stage 2 is constructed, the FHA will need to be re-validated based on the detailed design risk review for the pipeline from the tie-in point 8km north of the Bethungra Line valve up to the compressor station at Young. By conducting a thorough review of all studies subsequent to the PHA it is possible to determine whether the design has altered sufficiently to warrant a comprehensive re-evaluation of the risk assessed, or whether the design basis has remained basically intact. Three studies were reviewed in detail: The PHA (completed in October 2009), The Hazard and Operability (HAZOP) Study (completed in December 2009) for Stage 1 only and The Pipeline Safety Management Study (completed in November 2009) for Stage 1 only. The HAZOP and SMS have been undertaken for Stage 1 looping only. In the future, as and when Stage 2 looping is undertaken, a separate HAZOP and SMS for Stage 2 will be conducted. The FHA will need to be re-validated once the Stage 2 HAZOP and SMS have been conducted During the PHA process, a number of potential hazards were identified with possible major consequences. The subsequent studies (above) did not uncover any further hazards or risks associated with this pipeline. The safety management study further concluded that the risk of a rupture for the pipeline in this location is virtually negligible through design and layout. The result of these hazard and risk assessment studies conducted subsequent to the PHA have had the effect of further reducing the likelihood of events with potentially major consequences compared with what was assumed in the PHA. Hence, the result of these subsequent studies is to somewhat reduce the risk associated with the pipeline. As the quantitative risk calculations in the PHA are based on historic incident data, such reduction in risk can only be expressed on a qualitative basis and the quantitative risk assessment in the PHA remains valid though slightly conservative. Based on the hazard and risk reviews carried out as part of the Young to Bomen pipeline project it can be concluded that, at the final design stage, the fire and explosions risks associated with the proposed Stage 1 pipeline remain acceptable with regards to all current definitions of the tolerability of risk. Specifically, the pipeline within it s easement is well within the criteria for risk of fatality for both residential and industrial areas. Stage 1 Final Hazard Analysis For The Young To Bomen Pipeline - From 8 Kilometres North Of Bethungra Line Valve To Bomen ii

6 GLOSSARY APT HAZID HAZOP HIPAP LFL MAOP MPa MSDS MW NG OH&S PHA QRA Australian Pipelines Trust Hazard Identification Hazard and Operability Study Hazardous Industry Planning Advisory Paper Lower Flammable Limit Maximum Allowable Operating Pressure Mega Pascal (unit for pressure) Material Safety Data Sheet Mega Watt (unit for energy output) Natural gas Occupational Health and Safety Preliminary Hazard Analysis Quantitative Risk Analysis Stage 1 Final Hazard Analysis For The Young To Bomen Pipeline - From 8 Kilometres North Of Bethungra Line Valve To Bomen iii

7 d REPORT 1 INTRODUCTION 1.1 BACKGROUND To meet the rising demand for natural gas the towns in the central south of NSW and to a new power station at Uranquinty, the East Australian Pipeline Pty Ltd (EAPL), a wholly owned subsidiary of APA Group, is proposing to loop the existing 12 Young to Bomen Pipeline with an 18 Pipeline which would run parallel to the existing pipeline. Due to the potentially hazardous nature of natural gas, the pipeline is classified as potentially hazardous as per the definition by the NSW Department of Planning. One of these Conditions relate to the need to undertake a Final Hazard Analysis (FHA) at the conclusion of the design phase for the project but before construction: Prior to the commencement of commissioning of the project upgrade, the Proponent shall prepare and submit for the approval of the Director-General, a Final Hazard Analysis prepared in accordance with the Department s Hazardous Industry Advisory Paper No. 6 Guidelines for Hazard Analysis The pipeline from Young to Bomen will be constructed in two stages. Stage 1 is currently being undertaken, in which the pipeline is being constructed from Bomen metre station to 8 kilometres north of Bethungra Line valve, a total length of 61 kilometres. The present report summarises the results of the FHA for the Stage 1 pipeline from Bomen metre station to 8 kilometres north of Bethungra Line valve. If and when Stage 2 is constructed, the FHA will need to be re-validated based on the detailed design risk review for the pipeline from the tie-in point 8km north of the Bethungra Line valve up to the compressor station at Young. 1.2 SCOPE AND AIM OF STUDY The scope of this FHA (as for the PHA) is to assess the risk associated with the natural gas pipeline from Bomen metre station to 8 kilometres north of Bethungra Line valve, a total length of 61 kilometres. Stage 1 Final Hazard Analysis For The Young To Bomen Pipeline - From 8 Kilometres North Of Bethungra Line Valve To Bomen 1

8 d This document was prepared in accordance with the Department of Planning s Hazardous Industry Planning Advisory Paper (HIPAP) number 6 Guidelines Hazard Analysis (Ref 3) and the risks were compared with the criteria in use by the Department for land use planning as per HIPAP number 4 (Ref 4). The aim of a FHA is to analyse and assess the hazards and resultant residual risk associated with the plant and processes at the final design stage. The types of risks considered in this FHA are: Risk of acute human injury or fatality; Risk of acute damage to the natural environment. By agreement with the NSW Department of Planning, and in line with the guidelines on Hazard Analysis, this FHA has been prepared as a Supplement to the PHA, and as such focuses on the differences that have evolved during the development of the project through its design phase and its review and amendment by the process hazard and risk reviews subsequent to the PHA process. 1.3 INPUT INTO THE FHA The following hazard and risk reviews are used as inputs to the FHA: Preliminary Hazard Analysis (Ref 5) Young to Bomen (131 km); Young - Wagga Looping HAZOP Study (Ref 6) Stage 1: 8 kilometres north of Bethungra Line valve to Bomen (61 kilometres); Pipeline Safety Management Study Young - Wagga Loop Stage 1 (Ref 7) Stage 1: 8 kilometres north of Bethungra Line valve to Bomen (61 kilometres);. 1.4 THE PROJECT The pipeline will run south west from the Young Compressor Station towards the Bowmen Meter Station. The pipeline will be constructed in two Stages with the present FHA covering Stage 1 only. The existing pipeline is bi-directional also enabling Moomba gas from South Australia to flow to Victoria and Bass Strait gas from Longford to flow to Sydney. The new (parallel) pipeline will also be bi-directional. The pipeline route traverses the Young, Cootamundra, Harden and Junee Shire Council areas in NSW. The area is predominantly used for grazing and cropping. An aerial photograph is presented below. The pipeline will be entirely located inside the existing easement. The pipeline construction will require a working width slightly wider than the easement. Stage 1 Final Hazard Analysis For The Young To Bomen Pipeline - From 8 Kilometres North Of Bethungra Line Valve To Bomen 2

9 Figure 1 Corridor for Pipeline Route Stage 1 Final Hazard Analysis For The Young To Bomen Pipeline - From 8 Kilometres North Of Bethungra Line Valve To Bomen 3

10 2 DESIGN AND OPERATION 2.1 MAIN CHANGES MADE TO THE PIPELINE SINCE THE PRELIMINARY HAZARD ANALYSIS There have been no substantial changes in the proposed design and operation of the Stage 1 pipeline since the early design stage and as assumed in the PHA. Compared with the design of the proposed development which was known (and assumed) at the time of the PHA (Ref 5), the only differences are: The design of pipeline and equipment is now finalised. The control and protective systems have been determined for the pipeline. Note that since the new pipeline will run within an existing easement, the pipeline layout was determined also at the PHA stage. 2.2 EVALUATION AGAINST PHA ASSUMPTIONS There have been no changes to the main assumptions with regards to the Stage 1 pipeline design and operation made in the PHA. Table 1 Summary of Preliminary Assumptions Made in the PHA for the Pipeline Design Item Percent operational Pipe Diameter Pipe Length Maximum Allowable Operating Pressure (MAOP) Actual operating pressure Temperature Class Location to AS2885 Pipe Thickness Pipeline Design All data used in the present risk assessment are for a pipeline pressurised 100% of the time. 450 mm NB (nominal bore) 130 kilometre 10.2 MPa, ANSI Class MPa 25 o C R1 (broadly rural) with 40 hectare blocks with some R2 (rural residential) as per AS2885 definitions. 6.8 mm to 9.7mm Stage 1 Final Hazard Analysis For The Young To Bomen Pipeline - From 8 Kilometres North Of Bethungra Line Valve To Bomen 4

11 Table 1 Summary of Preliminary Assumptions Made in the PHA for the Pipeline Design Item Depth of Cover Number of flanges Features Design Standard Pipeline Design At least 900mm (or 450mm in rock if encountered) 5 flange joints per mainline valve (MLV) with four MLVs along the pipeline. Pressure indication and Actuator Line Break (ALB) on each MLV. As per AS2885 requirements The assumptions in the PHA remain valid with regards to design assumptions for the Stage 1 pipeline. Stage 1 Final Hazard Analysis For The Young To Bomen Pipeline - From 8 Kilometres North Of Bethungra Line Valve To Bomen 5

12 3 MAIN SAFETY RISKS IDENTIFIED 3.1 SAFETY RELATED HAZARDS AND RISKS IDENTIFIED The main risk associated with the pipeline relates to the transport of natural gas which is flammable when released into the atmosphere. The PHA concluded that a leak of flammable natural gas would generally only have the potential to cause injury or damage if there was ignition, which resulted in a fire or (in case of confinement) an explosion incident. The factors involved are: - The pipeline must fail in a particular mode causing a release. There are several possible causes of failure, with the main ones being corrosion and damage by external agencies. - The released material must come into contact with a source of ignition. In some cases this may be heat or sparks generated by mechanical damage while in others, the possible ignition source could include non-flame proof equipment, vehicles, or flames some distance from the release. - Depending on the release conditions, including the mass of flammable material involved and how rapidly it ignited, the results may be a localised fire (for example a jet fire), a flash fire or an explosion of the vapour cloud formed through the release. - Finally, for there to be a risk, people must be present within the harmful range (consequence distance) of the fire or explosion. How close the people are will determine whether any injuries or fatalities result. Environmental damage from gas fire incidents are generally associated with a failure to control fire water used. Natural gas is a buoyant, flammable gas which is lighter than air (relative density of 0.6). On release into the open the non-ignited gas tends to disperse rapidly at altitude. Ignition at the point of release is possible, in which case the gas would burn as a jet (or torch) flame. On release in an enclosed area an explosion or a flash fire is possible. The gas is non-toxic, posing only an asphyxiation hazard. Due to its buoyancy, any release of credible proportions from operations of this scale, in the open, would not present an asphyxiation hazard. With standard confined space entry procedures and appropriate security arrangements to prevent unauthorised access to any of the facilities the risk associated with asphyxiation from natural gas is be minimal. Locally, the pressure of the compressed gas may be hazardous in case of an uncontrolled release. These hazards, while of importance for people working with the gas pipeline, do not have implications beyond the immediate location of Stage 1 Final Hazard Analysis For The Young To Bomen Pipeline - From 8 Kilometres North Of Bethungra Line Valve To Bomen 6

13 the release unless the released gas is ignited. Therefore, the risk associated with of non-ignited compressed gas does not form part of the scope of the present risk assessment. This potential risk would, however, need to be closely managed through job safety analysis (JSA) and/or other risk assessment practices used by management and maintenance workers (in accordance with NSW Occupational Health and Safety Act and its associated legislation (Reference 8)). A total of 10 potentially hazardous scenarios were identified in the PHA for the gas pipeline, as listed in Table 2 below. These remain valid also at this final design of Stage 1 pipeline. Table 2 - Summary of Identified Hazards Number Hazardous Event Potential 1 Mechanical damage to the pipeline 2 Corrosion 3 Nearby explosion at neighbouring natural gas pipeline 4 Pressure excursion 5 Spontaneous loss of integrity of pipe (rupture) 6 Erosion 7 Land subsidence 8 Aircraft, train or heavy vehicle crash 9 Damage to pipeline through terrorism / vandalism 10 Neighbouring bush fire 3.2 COMPARISON WITH ISSUES RAISED IN THE PRELIMINARY QRA Comparing the issues and concerns listed above with those raised in subsequent studies (HAZOP and SMS) show that while the HAZOP (Ref 6) and the SMS (Ref 7) detail the threats which could potentially lead to the above hazards, the studies did not identify any further hazardous incident scenarios requiring analysis. The studies undertaken at the more detailed stage of the design of the pipeline have not revealed any major changes (to the installations, material, or systems) that could seriously increase or change the risk associated with the pipeline in Stage 1 compared with that assessed in the PHA. Stage 1 Final Hazard Analysis For The Young To Bomen Pipeline - From 8 Kilometres North Of Bethungra Line Valve To Bomen 7

14 4 REVIEW OF THE MAIN PREVENTATIVE AND PROTECTIVE SAFEGUARDS PROPOSED FOR THE PIPELINE The Hazard Identification Word Diagram in Table 8 in the PHA summarises the potential hazards identified for the pipeline, their initiating causes, consequences, together the manner in which they are prevented and/or their impact is mitigated. When comparing the hazards and control mechanisms reported in the PHA (Ref 5) with what has been described in the HAZOP (Ref 6) and the SMS (Ref 7), for Stage 1 pipeline, the main control systems remain valid though the SMS and the HAZOP have identifies some further control mechanisms in place. The table from the PHA can be used to describe the situation at the Stage 1 pipeline in it s final design. The quality and effectiveness of the safeguards listed in the PHA are periodically reviewed and checked by internal and external auditors using the APA Group and the Department of Industry & Investment audit procedures. These audits include engineering, safety, process and quality audits. Stage 1 Final Hazard Analysis For The Young To Bomen Pipeline - From 8 Kilometres North Of Bethungra Line Valve To Bomen 8

15 5 IMPLICATIONS OF THE RESULTS OF THE HAZOP STUDY 5.1 RESULTS The HAZOP Study for the Stage 1 pipeline assessed the hazard and operability of the pipeline from the point near Bethungra up to the point where it comes into Bomen (total of 61km). It also assessed the hazard and operability of a typical line valve bypass which is used to allow flow either to blowdown vent for depressurisation or around closed Main Line Valve for repressurisation. The recommendations for further improvements of the pipeline design and operation coming out of the HAZOP were very minor in nature and included some small design changes and some changes to the Piping and Instrument Diagrams. Stage 1 Final Hazard Analysis For The Young To Bomen Pipeline - From 8 Kilometres North Of Bethungra Line Valve To Bomen 9

16 6 IMPLICATIONS OF THE RESULTS FROM THE SAFETY MANAGEMENT STUDY The Safety Management Study (SMS) (Ref 7) was carried out in accordance with the requirements in AS and as required by the Conditions of Consent for the Stage 1 pipeline. The SMS is, in it s nature, highly detailed and assesses the threats and hazards to the pipeline at each location along it s full length. A total of 234 threats were identified, many of which were repeated for several locations along the pipeline. Particular attention was given to external interference threats as these are seen as by far dominating the causes of incidents relating to pipelines. The most serious threat which could be anticipated for a pipeline in this location, as identified in the SMS, includes excavators, rippers, and post hole augers. However, the SMS determined that it would be rare for anything other than light machinery (backhoes, graders) to be used near the pipeline, particularly at short notice. The SMS calculated the resistance of then pipeline to penetration from external interference. The SMS concluded that no pipe can be punctuated by an excavator fitted with general purpose teeth. Further, is concluded that penetration by drill bit is possible but will not result in rupture. The SMS also concluded that while penetration of the thinner (standard) 6.8mm thick pipe by both points of a tiger tooth on a 32 tonnes excavator may create a hole larger than the critical defect length, this is a limiting case and as such is barely credible. The SMS determined that the only possible threat to the pipeline which may result in rupture is a large ripper. However, the study concluded that provided that the thicker walled pipeline (9.7 mm wall thickness) is used in the industrial area near Bomen and provided that the pipeline is buried at 1200mm depth at this point, the rupture scenario is not credible. The PHA assumed that, while highly unlikely, the rupture scenario is still possible and the quantitative risk calculations included the rupture scenario. The risk calculations in the PHA remain valid though somewhat conservative. The FHA will need to be re-validated for the Stage 2 pipeline after conducting the SMS for this portion of the pipeline. Stage 1 Final Hazard Analysis For The Young To Bomen Pipeline - From 8 Kilometres North Of Bethungra Line Valve To Bomen 10

17 7 CONCLUSIONS AND DISCUSSIONS The findings in the Stage 1 FHA confirmed the conclusions in the PHA (Ref 5), that the proposed Young to Bomen pipeline does will not introduce undue risk, and that there is no reason, on land use safety planning grounds, why the proposed development should not be approved. From a land use safety point of view, only minor changes have been made to the pipeline since the stage of the PHA. These changes are related to improvements of the operation and the safety of the proposed pipeline. They result in a somewhat reduced risk from the pipeline compared with the risk assumed at the stage of the PHA. In conclusion, the risk calculations made in the PHA remain valid and the risk contours and risk profiles determined in PHA are still applicable for the Young to Bomen pipeline. The FHA will need to be re-validated for the Stage 2 pipeline if and when it is constructed. The assessments made in the various safety related studies (HAZOP, Safety Management Study) have demonstrated the importance of ensuring continued good practice for operating and maintenance standards, ensuring that the procedures and systems are kept up to date and that training and drills in emergency response are undertaken regularly. Stage 1 Final Hazard Analysis For The Young To Bomen Pipeline - From 8 Kilometres North Of Bethungra Line Valve To Bomen 11

18 8 REFERENCES 1 Hazardous Industry Planning Advisory Paper No. 6 (HIPAP No. 6): Guidelines for Hazard Analysis, NSW Department of Planning 2 Hazardous Industry Planning Advisory Paper No. 4 (HIPAP No. 4): Risk Criteria for Landuse Planning, NSW Department of Planning 3 Department of Planning, Hazardous Industry Planning Advisory Paper Nº 6: Guidelines for Hazard Analysis; NSW Government, Sydney, Hazardous Industry Planning Advisory Paper No. 4 (HIPAP No. 4): Risk Criteria for Landuse Planning, NSW Department of Planning 5 Nilsson K, Preliminary Hazard Analysis of the Natural Gas Delivery Pipeline between Young and Bomen in NSW, Planager Pty Ltd, 13 October Tuft P, Young - Wagga Looping HAZOP Study, Peter Tuft & Associates, 2 December Tuft P, Pipeline Safety Management Study Young - Wagga Loop Stage 1, Peter Tuft & Associates, 30 November NSW Occupational Health and Safety Act and its associated legislation, including but not limited to the Dangerous Goods Regulations, Construction Safety Regulations, and the Factories Shops and Industries Regulations Stage 1 Final Hazard Analysis For The Young To Bomen Pipeline - From 8 Kilometres North Of Bethungra Line Valve To Bomen 12

Title of Paper Interpretation of IP15 in Process Plant Design: a Commonsense Approach ---------------------------------------------------------------------------------------------------------------------------

More information

Identification and Screening of Scenarios for LOPA. Ken First Dow Chemical Company Midland, MI

Identification and Screening of Scenarios for LOPA. Ken First Dow Chemical Company Midland, MI Identification and Screening of Scenarios for LOPA Ken First Dow Chemical Company Midland, MI 1 Layers of Protection Analysis (LOPA) LOPA is a semi-quantitative tool for analyzing and assessing risk. The

More information

PRELIMINARY HAZARD AND RISK ASSESSMENT OF ARROW ENERGY'S SURAT GAS PROJECT, QLD

PRELIMINARY HAZARD AND RISK ASSESSMENT OF ARROW ENERGY'S SURAT GAS PROJECT, QLD PRELIMINARY HAZARD AND RISK ASSESSMENT OF ARROW ENERGY'S SURAT GAS PROJECT, QLD Prepared for: Coffey Environments Document Number: COFENV \ 01-B198 Revision E2 Prepared by: Karin Nilsson 12 December 2011

More information

Item ID: Rev.: 00 Status: Final Effective Date: 29-Feb-2015 EXECUTIVE SUMMARY

Item ID: Rev.: 00 Status: Final Effective Date: 29-Feb-2015 EXECUTIVE SUMMARY EXECUTIVE SUMMARY The objective of this report is to demonstrate that sections of pipeline between MLV 401 and MLV 402 on the Canadian Mainline Line 400-2 meet the applicable requirements in CSA Z662-15

More information

Pipeline Integrity Valve Spacing Engineering Assessment (CDN) Grande Prairie Mainline Loop 2 (Progress Section) NPS 36

Pipeline Integrity Valve Spacing Engineering Assessment (CDN) Grande Prairie Mainline Loop 2 (Progress Section) NPS 36 APPROVALS Library: EDMS General Page 1 of 10 TABLE OF CONTENTS APPROVALS 1 1. PURPOSE... 3 2. BACKGROUND... 3 3. VALVE SPACING ASSESSMENT APPROACH... 6 4. OPERATIONS AND MAINTENANCE CONSIDERATIONS... 6

More information

Practical Modelling & Hazard Assessment of LPG & LNG Spills

Practical Modelling & Hazard Assessment of LPG & LNG Spills Practical Modelling & Hazard Assessment of LPG & LNG Spills UKELG 3 rd April 2012 Tony Ennis Introduction Refrigerated or pressurised Release scenarios & release rate Vaporisation Gas dispersion Consequences

More information

IGEM/TD/2 Edition 2 with amendments July 2015 Communication 1779 Assessing the risks from high pressure Natural Gas pipelines

IGEM/TD/2 Edition 2 with amendments July 2015 Communication 1779 Assessing the risks from high pressure Natural Gas pipelines Communication 1779 Assessing the risks from high pressure Natural Gas pipelines Founded 1863 Royal Charter 1929 Patron: Her Majesty the Queen Communication 1779 Assessing the risks from high pressure Natural

More information

Application of pipeline risk assessment to proposed developments in the vicinity of high pressure Natural Gas pipelines

Application of pipeline risk assessment to proposed developments in the vicinity of high pressure Natural Gas pipelines Communication 1737 Application of pipeline risk assessment to proposed developments in the vicinity of high pressure Natural Gas pipelines Founded 1863 Royal Charter 1929 Patron: Her Majesty the Queen

More information

PRAGMATIC ASSESSMENT OF EXPLOSION RISKS TO THE CONTROL ROOM BUILDING OF A VINYL CHLORIDE PLANT

PRAGMATIC ASSESSMENT OF EXPLOSION RISKS TO THE CONTROL ROOM BUILDING OF A VINYL CHLORIDE PLANT PRAGMATIC ASSESSMENT OF EXPLOSION RISKS TO THE CONTROL ROOM BUILDING OF A VINYL CHLORIDE PLANT L.P. Sluijs 1, B.J. Haitsma 1 and P. Beaufort 2 1 Vectra Group Ltd. 2 Shin-Etsu (contact details: Vectra Group

More information

Engineering Safety into the Design

Engineering Safety into the Design Engineering safety into the design Peter Scantlebury P.Eng Technical Safety Manager Amec Foster Wheeler, Oil & Gas Canada Abstract Safety by design is Amec Foster Wheeler s systematic approach to engineering

More information

Decant Filling of Gas Cylinders

Decant Filling of Gas Cylinders Safety Advice No. 18 Document No. 142-018 (Version 06) Decant Filling of Gas Cylinders ANZIGA ANZIGA is the peak industry group for the manufacture and distribution of gases in Australia and New Zealand.

More information

Purpose. Scope. Process flow OPERATING PROCEDURE 07: HAZARD LOG MANAGEMENT

Purpose. Scope. Process flow OPERATING PROCEDURE 07: HAZARD LOG MANAGEMENT SYDNEY TRAINS SAFETY MANAGEMENT SYSTEM OPERATING PROCEDURE 07: HAZARD LOG MANAGEMENT Purpose Scope Process flow This operating procedure supports SMS-07-SP-3067 Manage Safety Change and establishes the

More information

Introduction to HAZOP Study. Dr. AA Process Control and Safety Group

Introduction to HAZOP Study. Dr. AA Process Control and Safety Group Introduction to HAZOP Study Dr. AA Process Control and Safety Group A scenario You and your family are on a road trip by using a car in the middle of the night. You were replying a text message while driving

More information

Understanding safety life cycles

Understanding safety life cycles Understanding safety life cycles IEC/EN 61508 is the basis for the specification, design, and operation of safety instrumented systems (SIS) Fast Forward: IEC/EN 61508 standards need to be implemented

More information

GAS PIPELINE SAFETY GUIDE.

GAS PIPELINE SAFETY GUIDE. GAS PIPELINE SAFETY GUIDE. Date of issue 27/02/2017 Date of next review 27/02/2018 Page 1 Vector Limited 2017 Gas Pipeline Safety Guide February 2017 CONTENTS CONTENTS...2 WORKING SAFELY... 3 Your Legal

More information

Guidance on piling, heavy loads, excavations, tunnelling and dewatering

Guidance on piling, heavy loads, excavations, tunnelling and dewatering Guidance on piling, heavy loads, excavations, tunnelling and dewatering thameswater.co.uk/developerservices Contents 1 Introduction... 3 2 Works That Can Impact Our Assets And Cause Damage... 3 3 What

More information

Bogo Operations Pollution Incident Response Management Plan

Bogo Operations Pollution Incident Response Management Plan Bogo Operations Pollution Incident Response Management Plan Rhyolite Hard Rock Aggregate Quarry 134 Paynes Road BOOKHAM NSW 2582 PO Box 426 COWRA NSW 2794 p: 02 6227 7260 p: 02 6345 4253 e: info@bogoquarry.com.au

More information

Improving Accuracy of Frequency Estimation of Major Vapor Cloud Explosions for Evaluating Control Room Location through Quantitative Risk Assessment

Improving Accuracy of Frequency Estimation of Major Vapor Cloud Explosions for Evaluating Control Room Location through Quantitative Risk Assessment Improving Accuracy of Frequency Estimation of Major Vapor Cloud Explosions for Evaluating Control Room Location through Quantitative Risk Assessment Naser Badri 1, Farshad Nourai 2 and Davod Rashtchian

More information

Long Island Point Fractionation Plant & Crude Storage Tank Farm Safety Case Summary

Long Island Point Fractionation Plant & Crude Storage Tank Farm Safety Case Summary Long Island Point Fractionation Plant & Crude Storage Tank Farm Safety Case Summary 2 Table of Contents Glossary 4 Message from the Long Island Point Plant Manager 5 Esso Australia 6 Introduction 7 Safety

More information

AN APPROACH TO THE PROBLEMS OF PROCESS HAZARDS IN PLANT DESIGN

AN APPROACH TO THE PROBLEMS OF PROCESS HAZARDS IN PLANT DESIGN AN APPROACH TO THE PROBLEMS OF PROCESS HAZARDS IN PLANT DESIGN By A. D. THACKARA, M.A., A.M.I.Mech.E.,* R.M. ROBB, B.Sc.,* and R. B. T. HALL-CRAGGS, M.A., A.M.I.Mech.E. * SUMMARY This paper deals with

More information

MINE SAFETY TARGETED ASSESSMENT PROGRAM. Ground or strata failure NSW metalliferous mines. April

MINE SAFETY TARGETED ASSESSMENT PROGRAM. Ground or strata failure NSW metalliferous mines. April MINE SAFETY TARGETED ASSESSMENT PROGRAM Ground or strata failure NSW metalliferous mines April 2017 www.resourcesandenergy.nsw.gov.au Document control Publication title: Ground or strata failure NSW metalliferous

More information

Operational Risk Using BowTie Methodology

Operational Risk Using BowTie Methodology Operational Risk Using BowTie Methodology Richard Emery, MMI Engineering Ltd, The Brew House, Wilderspool Park, Greenall s Avenue, Warrington, WA4 6HL. Management of risk on COMAH sites relies on diverse

More information

# Post Consultation and Submissions Resource Consent Conditions for Surfing Impact Mitigation August 2016

# Post Consultation and Submissions Resource Consent Conditions for Surfing Impact Mitigation August 2016 # Post Consultation and Submissions Resource Consent Conditions for Surfing Impact Mitigation August 2016 Surf Mitigation Management Plan 1 1 Not less than 6 months prior to the commencement of the construction

More information

IGO GROUP SAFETY STANDARD 30 - WORKPLACE VENTILATION INDEPENDENCE GROUP NL

IGO GROUP SAFETY STANDARD 30 - WORKPLACE VENTILATION INDEPENDENCE GROUP NL IGO GROUP SAFETY STANDARD 30 - WORKPLACE VENTILATION INDEPENDENCE GROUP NL CONTENTS 1. INTENT... 3 2. APPLICATION... 3 3. UNDERGROUND VENTILATION... 3 3.2 Underground Ventilation Officer... 3 3.3 Risk

More information

Responding to Natural Gas Pipeline Emergencies

Responding to Natural Gas Pipeline Emergencies Responding to Natural Gas Pipeline Emergencies Who is Florida Gas Transmission? Florida Gas Transmission operates nearly 5,000-miles of interstate natural gas transmission pipelines, a system that extends

More information

GUIDELINE: Roadside Worksites

GUIDELINE: Roadside Worksites Title: GUIDELINE: Roadside Worksites Version 1.0 Short description Relevant to Authority Responsible officer Responsible office A guideline on ensuring a safe method of works on or near roadways within

More information

THE BAKER REPORT HOW FINDINGS HAVE BEEN USED BY JOHNSON MATTHEY TO REVIEW THEIR MANUFACTURING OPERATIONS

THE BAKER REPORT HOW FINDINGS HAVE BEEN USED BY JOHNSON MATTHEY TO REVIEW THEIR MANUFACTURING OPERATIONS THE BAKER REPORT HOW FINDINGS HAVE BEEN USED BY JOHNSON MATTHEY TO REVIEW THEIR MANUFACTURING OPERATIONS Colin P. Lynas, Elizabeth Campbell and Hendrik J. Koornhof Johnson Matthey Catalysts This paper

More information

Absorption - The process of contacting a vapor and gas stream with an absorbing liquid to remove specific materials from the gas stream.

Absorption - The process of contacting a vapor and gas stream with an absorbing liquid to remove specific materials from the gas stream. Sufe Design and Optvation ofpi-oc.ess Vents and Emission Contid $wteins by Center for Chemical Process Safety Copyright 0 2006 John Wiley & Sons, Tnc. APPENDIX B GLOSSARY Absorption - The process of contacting

More information

15. PRELIMINARY HAZARD AND RISK

15. PRELIMINARY HAZARD AND RISK Supplementary Report to the EIS 15. PRELIMINARY HAZARD AND RISK This chapter summarises the findings of the supplementary preliminary hazard and risk assessment undertaken to address changes made to the

More information

BSR GPTC Z TR GM References and Reporting Page 1 of 8

BSR GPTC Z TR GM References and Reporting Page 1 of 8 Page 1 of 8 PRIMARY: 192.605 SECONDARY: 191.23 PURPOSE: Review guide material added by TR 2009-17 to 5.1(e) and consider restructuring the guide material under 192.605 as discussed further below. ORIGIN/RATIONALE

More information

Gulfstream Natural Gas System

Gulfstream Natural Gas System Website: www.gulfstreamgas.com Gulfstream has prepared this fact sheet as a guide for emergency response officials who may be asked to respond to an incident involving a Gulfstream natural gas pipeline

More information

ANNEX AMENDMENTS TO THE INTERNATIONAL CODE FOR FIRE SAFETY SYSTEMS (FSS CODE) CHAPTER 15 INERT GAS SYSTEMS

ANNEX AMENDMENTS TO THE INTERNATIONAL CODE FOR FIRE SAFETY SYSTEMS (FSS CODE) CHAPTER 15 INERT GAS SYSTEMS Annex 3, page 2 ANNEX AMENDMENTS TO THE INTERNATIONAL CODE FOR FIRE SAFETY SYSTEMS (FSS CODE) CHAPTER 15 INERT GAS SYSTEMS The text of existing chapter 15 is replaced by the following: "1 Application This

More information

Marine Risk Assessment

Marine Risk Assessment Marine Risk Assessment Waraporn Srimoon (B.Sc., M.Sc.).) 10 December 2007 What is Risk assessment? Risk assessment is a review as to acceptability of risk based on comparison with risk standards or criteria,

More information

RISK ASSESSMENT & DISASTER MANAGEMENT PLAN

RISK ASSESSMENT & DISASTER MANAGEMENT PLAN PAGE - 1 RISK ASSESSMENT & DISASTER MANAGEMENT PLAN 1.1 RISK ASSESSMENT A major accident in an industry has the potential to cause serious injury or loss of life and extensive damage to environment or

More information

HAZARDOUS SUBSTANCE AND DANGEROUS GOODS

HAZARDOUS SUBSTANCE AND DANGEROUS GOODS The Barro Group is committed to continuously improving the management and standards of Occupational Health and Safety. This commitment extends to minimising exposure of employees, contractors, visitors

More information

Rockhampton Office Brisbane Office Tarong Site. Barron Gorge Hydro PS Kareeya Hydro PS Mica Creek PS

Rockhampton Office Brisbane Office Tarong Site. Barron Gorge Hydro PS Kareeya Hydro PS Mica Creek PS Business Procedure Hot Work Document Number OHS-PROC-128 This document applies to the following sites: All Sites Rockhampton Office Brisbane Office Tarong Site Barron Gorge Hydro PS Kareeya Hydro PS Mica

More information

1.0 PURPOSE 2.0 REFERENCES

1.0 PURPOSE 2.0 REFERENCES Page 1 1.0 PURPOSE 1.1 This Advisory Circular provides Aerodrome Operators with guidance for the development of corrective action plans to be implemented in order to address findings generated during safety

More information

SAFETY STUDY OF HYDROGEN SUPPLY STATIONS FOR THE REVIEW OF HIGH PRESSURE GAS SAFETY LAW IN JAPAN

SAFETY STUDY OF HYDROGEN SUPPLY STATIONS FOR THE REVIEW OF HIGH PRESSURE GAS SAFETY LAW IN JAPAN SAFETY STUDY OF HYDROGEN SUPPLY STATIONS FOR THE REVIEW OF HIGH PRESSURE GAS SAFETY LAW IN JAPAN Komori, M., Yoshida, T., Onoue, K. and Kikukawa, S., Mori, T., Takagi, K. Japan Petroleum Energy Center,

More information

Using LOPA for Other Applications

Using LOPA for Other Applications 10 Using LOPA for Other Applications 10.1. Purpose LOPA is a tool used to perform risk assessments. Previous chapters described its use in assessing the risk level of process hazards scenarios and in evaluating

More information

A study on the relation between safety analysis process and system engineering process of train control system

A study on the relation between safety analysis process and system engineering process of train control system A study on the relation between safety analysis process and system engineering process of train control system Abstract - In this paper, the relationship between system engineering lifecycle and safety

More information

Assessing Permeation of Gas through Polyethylene Pipe

Assessing Permeation of Gas through Polyethylene Pipe Assessing Permeation of Gas through Polyethylene Pipe REPORTS Introduction Gas Distribution Networks (GDNs) regularly review the Shrinkage and Leakage model (SLM) to further enhance the reporting of Shrinkage

More information

AUSTRALIA ARGENTINA CANADA EGYPT NORTH SEA U.S. CENTRAL U.S. GULF. SEMS HAZARD ANALYSIS TRAINING September 29, 2011

AUSTRALIA ARGENTINA CANADA EGYPT NORTH SEA U.S. CENTRAL U.S. GULF. SEMS HAZARD ANALYSIS TRAINING September 29, 2011 AUSTRALIA ARGENTINA CANADA EGYPT NORTH SEA U.S. CENTRAL U.S. GULF SEMS HAZARD ANALYSIS TRAINING September 29, 2011 Purpose The purpose of this meeting is to provide guidelines for determination of hazard

More information

Every things under control High-Integrity Pressure Protection System (HIPPS)

Every things under control High-Integrity Pressure Protection System (HIPPS) Every things under control www.adico.co info@adico.co Table Of Contents 1. Introduction... 2 2. Standards... 3 3. HIPPS vs Emergency Shut Down... 4 4. Safety Requirement Specification... 4 5. Device Integrity

More information

Process Safety Management Of Highly Hazardous Chemicals OSHA 29 CFR

Process Safety Management Of Highly Hazardous Chemicals OSHA 29 CFR Process Safety Management Of Highly Hazardous Chemicals OSHA 29 CFR 1910.119 PSM - Definition Not all refining hazards are caused by the same factors or involve ve the same degree of potential damage.

More information

Journal of Applied Fluid Transients, Vol 1-1, April 2014 (3-1)

Journal of Applied Fluid Transients, Vol 1-1, April 2014 (3-1) Modeling and Field Verification Study of Air Slam Conditions on kalanit Pipeline System By Yiftach Brunner & Sathish Kumar ir valves are integral part of long water transmission mains and are essential

More information

Protocol for Confined Space Entry Requirements

Protocol for Confined Space Entry Requirements Occupational Health and Safety (OHS) Policy Document Number # QH-PTL-275-12-1:2012 Protocol for Confined Space Entry Custodian/Review O fficer: Director Safety and Wellbeing Version no: 1.0 Applicable

More information

Berwick Health and Education Precinct: Casey Amendment C207 (Part 1) Submission to Planning Panels Victoria

Berwick Health and Education Precinct: Casey Amendment C207 (Part 1) Submission to Planning Panels Victoria Berwick Health and Education Precinct: Casey Amendment C207 (Part 1) Submission to Planning Panels Victoria August 2018 CONTENTS 1 Executive summary... 1 2 Summary of the amendment... 2 3 Submission...

More information

Compliance with Health & Safety legislation

Compliance with Health & Safety legislation Compliance with Health & Safety legislation The following is a brief description of some of the main duties required by the more generic safety legislation applicable to businesses, which the employers

More information

QUANTIFYING THE TOLERABILITY OF POTENTIAL IGNITION SOURCES FROM UNCERTIFIED MECHANICAL EQUIPMENT INSTALLED IN HAZARDOUS AREAS

QUANTIFYING THE TOLERABILITY OF POTENTIAL IGNITION SOURCES FROM UNCERTIFIED MECHANICAL EQUIPMENT INSTALLED IN HAZARDOUS AREAS QUANTIFYING THE TOLERABILITY OF POTENTIAL IGNITION SOURCES FROM UNCERTIFIED MECHANICAL EQUIPMENT INSTALLED IN HAZARDOUS AREAS Steve Sherwen Senior Consultant, ABB Engineering Services, Daresbury Park,

More information

HAZARDOUS SUBSTANCES / DANGEROUS GOODS

HAZARDOUS SUBSTANCES / DANGEROUS GOODS HAZARDOUS SUBSTANCES / DANGEROUS GOODS Golden Brown is committed to continuously improving the management and standards of Occupational health and Safety. This commitment extends to minimising exposure

More information

Risk Management Qualitatively on Railway Signal System

Risk Management Qualitatively on Railway Signal System , pp. 113-117 The Korean Society for Railway Ya-dong Zhang* and Jin Guo** Abstract Risk management is an important part of system assurance and it is widely used in safety-related system. Railway signal

More information

Work Health and Safety Risk Management Procedures

Work Health and Safety Risk Management Procedures Work Health and Safety Risk Management Procedures Table of Contents 1. Governing Policy 2. Purpose 3. Scope 4. Definitions 5. Responsibilities 6. Risk Management Process 6.1. Process summary 6.2. Hazard

More information

A quantitative risk analysis method for the natural gas pipeline network

A quantitative risk analysis method for the natural gas pipeline network PI-195 A quantitative risk analysis method for the natural gas pipeline network Y.-D. Jo1, K.-S. Park1, H.-S. Kim1, J.-J. Kim1, J.-Y. Kim2 & J. W. Ko3 1 Institute of Gas Safety Technology, Korea Gas Safety

More information

EXPLOSIVE ATMOSPHERES - CLASSIFICATION OF HAZARDOUS AREAS (ZONING) AND SELECTION OF EQUIPMENT

EXPLOSIVE ATMOSPHERES - CLASSIFICATION OF HAZARDOUS AREAS (ZONING) AND SELECTION OF EQUIPMENT EXPLOSIVE ATMOSPHERES - CLASSIFICATION OF HAZARDOUS AREAS (ZONING) AND SELECTION OF EQUIPMENT OVERVIEW ASSESSING THE RISK RELATIONSHIP BETWEEN FIRES AND EXPLOSIONS CLASSIFYING HAZARDOUS AREAS INTO ZONES

More information

USE OF THE EXCEEDANCE CURVE APPROACH IN OCCUPIED BUILDING RISK ASSESSMENT

USE OF THE EXCEEDANCE CURVE APPROACH IN OCCUPIED BUILDING RISK ASSESSMENT USE OF THE EXCEEDANCE CURVE APPROACH IN OCCUPIED BUILDING RISK ASSESSMENT Kieran J Glynn, Advisor Major Accident Risk, BP, UK The exceedance curve approach was developed following the issue of the 2003

More information

Confined Spaces. This procedure applies to all workers of the Diocese of Maitland Newcastle (DoMN).

Confined Spaces. This procedure applies to all workers of the Diocese of Maitland Newcastle (DoMN). Purpose To provide guidance in controlling the risks associated with confined spaces including identifying confined spaces, working in a confined space and issuing confined space entry permits. Scope This

More information

Tema Pressure Reduction Station

Tema Pressure Reduction Station The Quantitative Risk Assessment QRA Study For Tema Pressure Reduction Station Prepared By Petroleum Safety and Environmental Services Company January 2016 EGAS.HSE.QRA.Study.PRS.02/Tema.No.02/2015/QRA/MG/MS/DNV-PHAST.7.0--Final

More information

METHOD 21 - DETERMINATION OF VOLATILE ORGANIC COMPOUND LEAKS. 1.2 Scope. This method is applicable for the

METHOD 21 - DETERMINATION OF VOLATILE ORGANIC COMPOUND LEAKS. 1.2 Scope. This method is applicable for the 1151 METHOD 21 - DETERMINATION OF VOLATILE ORGANIC COMPOUND LEAKS 1.0 Scope and Application. 1.1 Analytes. Analyte Volatile Organic Compounds (VOC) CAS No. No CAS number assigned 1.2 Scope. This method

More information

SAFETY PLAN REVIEW ITM

SAFETY PLAN REVIEW ITM ITM Power (#4) Hydrogen Fueling Station Safety Plan Review Submission for the California Energy Commission General Funding Opportunity GFO-15-605 Background At the request of the California Energy Commission,

More information

Procedure: Permit Activities-Work in Confined Spaces and Hot Works

Procedure: Permit Activities-Work in Confined Spaces and Hot Works Procedure: Permit Activities-Work in Confined Spaces and Hot Works 1. Purpose Provide a safe working environment when working in confined spaces or whilst performing hot works in any GSCC building. 2.

More information

Hazardous material transport accidents: analysis of the D.G.A.I.S. database

Hazardous material transport accidents: analysis of the D.G.A.I.S. database Environmental Health Risk II 131 Hazardous material transport accidents: analysis of the D.G.A.I.S. database S. Bonvicini & G. Spadoni Department of Chemical, Mining Engineering and Environmental Technologies,

More information

SH&E Work Method Statement Concrete Cutting & Drilling Fast Cut Qld Pty Ltd, 91 Basalt, GEEBUNG PH M ABN

SH&E Work Method Statement Concrete Cutting & Drilling Fast Cut Qld Pty Ltd, 91 Basalt, GEEBUNG PH M ABN SH&E Work Method Statement Concrete Cutting & Drilling Fast Cut Qld Pty Ltd, 91 Basalt, GEEBUNG PH 07 3265 6537 M 0411 756 719 ABN 45 081 359 613 OHS-FRM-100 Rev 11 (07/18) Page 1 SH&EWMS No.: F-C-QLD-30

More information

DIGITAL SOLUTIONS TRAINING CATALOGUE. QRA and CFD simulation. Phast, Safeti and KFX SAFER, SMARTER, GREENER

DIGITAL SOLUTIONS TRAINING CATALOGUE. QRA and CFD simulation. Phast, Safeti and KFX SAFER, SMARTER, GREENER DIGITAL SOLUTIONS TRAINING CATALOGUE QRA and CFD simulation Phast, Safeti and KFX SAFER, SMARTER, GREENER 02 PHAST, SAFETI AND KFX Training catalogue Global training Our increased focus on global training,

More information

Integrated Design for Demonstration of Efficient Liquefaction of Hydrogen (IDEALHY) Fuel Cells and Hydrogen Joint Undertaking (FCH JU)

Integrated Design for Demonstration of Efficient Liquefaction of Hydrogen (IDEALHY) Fuel Cells and Hydrogen Joint Undertaking (FCH JU) Integrated Design for Demonstration of Efficient Liquefaction of Hydrogen (IDEALHY) Fuel Cells and Hydrogen Joint Undertaking (FCH JU) Grant Agreement Number 278177 Title: Qualitative Risk Assessment of

More information

Risks Associated with Caissons on Ageing Offshore Facilities

Risks Associated with Caissons on Ageing Offshore Facilities Risks Associated with Caissons on Ageing Offshore Facilities D. Michael Johnson, DNV GL, Peter Joyce, BG Group, Sumeet Pabby, BG Group, Innes Lawtie, BG Group. Neil Arthur, BG Group, Paul Murray, DNV GL.

More information

STTM EVENT: CONTINGENCY GAS TRIGGER GAS DAY 1 OCTOBER 2016 AT SYDNEY HUB

STTM EVENT: CONTINGENCY GAS TRIGGER GAS DAY 1 OCTOBER 2016 AT SYDNEY HUB STTM EVENT: CONTINGENCY GAS TRIGGER GAS DAY 1 OCTOBER 2016 AT SYDNEY HUB PREPARED BY: Market Monitoring and Change DOCUMENT REF: STTM ER 16/004 VERSION: 1.0 DATE: 11 November 2016 FINAL Australian Energy

More information

DETERMINATION OF SAFETY REQUIREMENTS FOR SAFETY- RELATED PROTECTION AND CONTROL SYSTEMS - IEC 61508

DETERMINATION OF SAFETY REQUIREMENTS FOR SAFETY- RELATED PROTECTION AND CONTROL SYSTEMS - IEC 61508 DETERMINATION OF SAFETY REQUIREMENTS FOR SAFETY- RELATED PROTECTION AND CONTROL SYSTEMS - IEC 61508 Simon J Brown Technology Division, Health & Safety Executive, Bootle, Merseyside L20 3QZ, UK Crown Copyright

More information

DET NORSKE VERITAS. Report Corrib Onshore Pipeline QRA. Shell E&P Ireland Ltd. Report no/dnv Reg No.: 01/ 12LKQW5-2 Rev 01,

DET NORSKE VERITAS. Report Corrib Onshore Pipeline QRA. Shell E&P Ireland Ltd. Report no/dnv Reg No.: 01/ 12LKQW5-2 Rev 01, DET NORSKE VERITAS Report Corrib Onshore Pipeline QRA Shell E&P Ireland Ltd. Report no/dnv Reg No.: 01/ 12LKQW5-2 Rev 01, 2010-05-18 EPA Export 19-02-2014:23:33:57 DET NORSKE VERITAS Report for Shell E&P

More information

Our Approach to Managing Level Crossing Safety Our Policy

Our Approach to Managing Level Crossing Safety Our Policy Our Approach to Managing Level Crossing Safety Our Policy Our policy towards managing level crossing risk is: that we are committed to reducing the risk at level crossings where reasonably practicable

More information

Procedure: Pressure equipment safety

Procedure: Pressure equipment safety Procedure: Pressure equipment safety Purpose The purpose of this procedure is to define the method for safe operation and inspection of pressure equipment and the collection and recording of associated

More information

IGEM/TD/1. Background, Development, Changes J V Haswell

IGEM/TD/1. Background, Development, Changes J V Haswell IGEM/TD/1 Background, Development, Changes J V Haswell TD/1 Background Development, Changes Technical and Safety Philosophy History of Development Key Code Requirements:- Rou?ng, BPDs Design parameters

More information

The Protection of Silos From Over. Pressurisation During Filling

The Protection of Silos From Over. Pressurisation During Filling SHAPA Technical Bulletin No.11 The Protection of Silos From Over Pressurisation During Filling Page 1 of 8 August 2005 The Protection of Silos From Over Pressurisation During Filling By James Duggleby,

More information

SUP 15 Health & Safety Management Pressure Systems. Unified procedures for use within NHS Scotland

SUP 15 Health & Safety Management Pressure Systems. Unified procedures for use within NHS Scotland SUP 15 Health & Safety Management Pressure Systems Unified procedures for use within NHS Scotland September 2015 Contents Page Acknowledgements... 3 1. Introduction... 4 2. Purpose of this Procedure...

More information

Gerga Pressure Reduction Station

Gerga Pressure Reduction Station The Quantitative Risk Assessment QRA Study For Gerga Pressure Reduction Station Prepared By Petroleum Safety and Environmental Services Company December 2015 Page 2 of 151 CONTENTS Executive Summary 12/151

More information

7TH ANNUAL MEETING OF THE COMMISSION

7TH ANNUAL MEETING OF THE COMMISSION 7TH ANNUAL MEETING OF THE COMMISSION 23-27 January 2019, The Hague, The Netherlands COMM7-Prop15.1 Background document: A Proposal for a research fishing Conservation and Management Measure for SPRFMO

More information

Safety assessments for Aerodromes (Chapter 3 of the PANS-Aerodromes, 1 st ed)

Safety assessments for Aerodromes (Chapter 3 of the PANS-Aerodromes, 1 st ed) Safety assessments for Aerodromes (Chapter 3 of the PANS-Aerodromes, 1 st ed) ICAO MID Seminar on Aerodrome Operational Procedures (PANS-Aerodromes) Cairo, November 2017 Avner Shilo, Technical officer

More information

SANDRINGHAM GOLF LINKS PROJECT

SANDRINGHAM GOLF LINKS PROJECT SANDRINGHAM GOLF LINKS PROJECT STAKEHOLDER ENGAGEMENT BACKGROUND INFORMATION PAPER SEPTEMBER 2017 This paper provides information regarding the context for the concept proposal for the Sandringham Golf

More information

innova-ve entrepreneurial global 1

innova-ve entrepreneurial global 1 www.utm.my innova-ve entrepreneurial global Safety Integrity Level (SIL) is defined as: Relative level of risk-reduction provided by a safety function to specify a target level of risk reduction. SIL is

More information

Impact on People. A minor injury with no permanent health damage

Impact on People. A minor injury with no permanent health damage Practical Experience of applying Layer of Protection Analysis For Safety Instrumented Systems (SIS) to comply with IEC 61511. Richard Gowland. Director European Process Safety Centre. (Rtgowland@aol.com,

More information

General Duty Clause. Section 112(r)(1) of CAA. Chris Rascher, EPA Region 1

General Duty Clause. Section 112(r)(1) of CAA. Chris Rascher, EPA Region 1 General Duty Clause Section 112(r)(1) of CAA Chris Rascher, EPA Region 1 Background on the General Duty Clause General Duty Clause 112(r)(1) of CAA Prevention of Accidental Releases Purpose and General

More information

Improvement in Release Frequencies for Quantitative Risk Assessment

Improvement in Release Frequencies for Quantitative Risk Assessment Improvement in Release Frequencies for Quantitative Risk Assessment Andrew Crerand, Simon Chynoweth and Steve Richardson, Shell Research Ltd, Shell Technology Centre Thornton, P.O. Box 1, Chester, CH1

More information

Part 2.5 Dispersion Modeling Using ALOHA

Part 2.5 Dispersion Modeling Using ALOHA Part 2.5 Dispersion Modeling Using ALOHA Dr. Arshad Ahmad Email: arshad@utm.my 1 Software Commonly used for Risk Analysis Software SAFETI SFU CAFTAN ETRA HAZSEC. HAZTRAC. PHAST. WHAZAN EFFECTS. DAMAGE

More information

A Generic Model To Assess Major Incident Frequencies For Offshore Assets

A Generic Model To Assess Major Incident Frequencies For Offshore Assets A Generic Model To Assess Major Incident Frequencies For Offshore Assets Richard Emery, MMI Engineering Ltd, The Brew House, Wilderspool Park, Greenall s Avenue, Warrington, WA4 6HL. Quantitative risk

More information

AIDGC PRESENTATION MARCH 2006 HAZARDOUS AREAS STANDARDS & CLASSIFICATION

AIDGC PRESENTATION MARCH 2006 HAZARDOUS AREAS STANDARDS & CLASSIFICATION AIDGC PRESENTATION MARCH 2006 HAZARDOUS AREAS STANDARDS & CLASSIFICATION Jeff Strath Principal Engineer Paterson Flood Engineers Pty Ltd www.pfe.com.au INTRODUCTION This presentation provides an overview

More information

Abstract. 1 Introduction

Abstract. 1 Introduction Risk assessment study of the mutual interactive influence of working procedures on terminals handling dangerous goods in port of Koper (Slovenia) L. Battelino Water Management Institute, Maritime Engineering

More information

E PGN-11. Part of NTW (O)32 Estates Operations and Maintenance Policy Paul McCabe Head of Estates and Facilities-NTW Solution Ltd

E PGN-11. Part of NTW (O)32 Estates Operations and Maintenance Policy Paul McCabe Head of Estates and Facilities-NTW Solution Ltd Estates Operations and Maintenance Practice Guidance Note Management of Pressure Systems V01 Date Issued Planned Review PGN No: Issue 1 - Nov 2015 Issue 2 Nov 2017 Author / Designation Responsible Officer

More information

PSM TRAINING COURSES. Courses can be conducted in multi-languages

PSM TRAINING COURSES. Courses can be conducted in multi-languages Courses can be conducted in multi-languages One set of hardcopy course notes will be sent to client for printing and distribution to course participants. The courses will be held at the client s training

More information

SAFE WORK METHOD STATEMENT WORKING IN CONFINED SPACE HSE NET NAT SWMS APAND00030

SAFE WORK METHOD STATEMENT WORKING IN CONFINED SPACE HSE NET NAT SWMS APAND00030 SAFE WORK METHOD STATEMENT WORKING IN CONFINED SPACE HSE NET NAT SWMS APAND00030 HIGH RISK APT AM Holdings Pty. Ltd. [ABN] 95124754383 Principal Contractor (PC) APA Group Level 19, HSBC Building 580 George

More information

gaf traffic 2015 capability statement

gaf traffic 2015 capability statement gaf traffic 2015 capability statement www.gaftraffic.com.au INTRODUCING GAF TRAFFIC GAF Traffic is a people-centred traffic engineering consultancy serving new and existing projects in Western Australia.

More information

Health & Safety Policy & Plan. Rightway Roofing.

Health & Safety Policy & Plan. Rightway Roofing. Health & Safety Policy & Plan. Rightway Roofing. Valid: 02/2012-02/2013 Contents ( 1 ) Policy Statement. ( 2 ) Hazard Identification. ( 3 ) Hazard Management. ( 4 ) Induction & Training. ( 5 ) Monitoring

More information

WHS PROCEDURE P Confined Spaces. Approved by: Ruth Hampton Review Date: 6 th December 2015

WHS PROCEDURE P Confined Spaces. Approved by: Ruth Hampton Review Date: 6 th December 2015 5 WHS PROCEDURE P21-01 Page 1 of 7 Issue: 2 1. Intent The Salvation Army Australia Eastern Territory (TSA-AUE) is committed to the provision of a safe, healthy and injury free environment for all persons

More information

Isolation Lockout and Tagging

Isolation Lockout and Tagging PURPOSE To define the minimum system requirements for isolation of plant and equipment from hazardous substances, mechanical, electrical or other energy sources to protect all workers from personal injury

More information

Environmental Management Strategy

Environmental Management Strategy Appin Surface Gas Management Project Appin Mine Surface Gas Management Project Environmental Management Strategy Page 1 Appin Surface Gas Management Project Review History Revision Description of Changes

More information

Acland Street, St Kilda

Acland Street, St Kilda Acland Street, St Kilda Traffic Redistribution Client: Yarra Trams Project No. 122531 Draft_4 Report 16/09/13 Suite 1, 1 st Floor 132 Upper Heidelberg Road Ivanhoe Vic 3079 PO Box 417 Ivanhoe Vic 3079

More information

MATERIAL SAFETY DATA SHEET. ACTION LANOSPRAY Commercial Grade Lanolin Protection

MATERIAL SAFETY DATA SHEET. ACTION LANOSPRAY Commercial Grade Lanolin Protection 1. Material Data Safety sheet - Action Lanospray MATERIAL SAFETY DATA SHEET Section 1: IDENTIFICATION ACTION LANOSPRAY Commercial Grade Lanolin Protection Recommended Use: Lubricant, Rust Inhibitor and

More information

ESCONDIDO FIRE DEPT TRAINING MANUAL Section Truck Module Page 1 of 5 Utilities Gas Emergencies Revised

ESCONDIDO FIRE DEPT TRAINING MANUAL Section Truck Module Page 1 of 5 Utilities Gas Emergencies Revised Truck Module Page 1 of 5 GAS EMERGENCIES Introduction Natural gas and Liquid Propane Gas (LPG) are flammable gases. Many households and commercial buildings utilize these gases for everything from heating

More information

MATERIAL SAFETY DATA SHEET

MATERIAL SAFETY DATA SHEET MATERIAL SAFETY DATA SHEET COMPRESSED ARGON Product Name 1. IDENTIFICATION OF THE MATERIAL AND SU 1. IDENTIFICATION OF THE MATERIAL AND SUPPLIER Supplier Name Global Gases Australia Pty Ltd Address 3 Halley

More information

Flammable Environments Guideline

Flammable Environments Guideline GUIDE Flammable Environments Guideline 2014-0004 The Canadian Association of Petroleum Producers (CAPP) represents companies, large and small, that explore for, develop and produce natural gas and crude

More information

Australian/New Zealand Standard

Australian/New Zealand Standard AS/NZS 1716:2012 AS/NZS 1716:2012 Australian/New Zealand Standard Respiratory protective devices AS/NZS 1716:2012 This Joint Australian/New Zealand Standard was prepared by Joint Technical Committee SF-010,

More information

Material Safety Data Sheet. Helmar Crystal Kote Picture Varnish Gloss

Material Safety Data Sheet. Helmar Crystal Kote Picture Varnish Gloss IDENTIFICATION OF THE MATERIAL AND SUPPLIER Company Name Helmar Australia Pty Ltd ABN 28 003 425 796 Address 54-56 Brisbane Road, Riverstone NSW 2765 Emergency Tel: 0418 230 719 Tel / Fax: (02) 9627 4666

More information