THE LOVIISA NUCLEAR POWER PLANT DECOMMISSIONING PLAN UPDATE Matti Kaisanlahti NKS-R Decommissioning Seminar, Halden, Norway, November 2013

Size: px
Start display at page:

Download "THE LOVIISA NUCLEAR POWER PLANT DECOMMISSIONING PLAN UPDATE Matti Kaisanlahti NKS-R Decommissioning Seminar, Halden, Norway, November 2013"

Transcription

1 THE LOVIISA NUCLEAR POWER PLANT DECOMMISSIONING PLAN UPDATE 2012 Matti Kaisanlahti NKS-R Decommissioning Seminar, Halden, Norway, November 2013

2 Agenda Background Licensing Decommissioning schedule Decommissioning work plan Decontamination of primary circuit Needs for personal protective equipment Final disposal Risks of decommissioning work Decommissioning costs Conclusions 2

3 Background Revised every 6th year Studies for the decommissioning plan 2012: - Licensing - The influence of primary circuit decontamination - The needs for personal protective equipment - Risks of decommissioning Immediate dismantlement Disposal at the plant site 3

4 Licensing 4

5 Decommissioning schedule 5

6 Decommissioning work plan 1/2 The dismantling and treatment of the plant s radioactive components can be carried out with currently available technology and methods Large components, such as the reactor pressure vessels and steam generators, as whole components Other decommissioning waste will be mainly packed into concrete and wooden containers The total volume of the decommissioning waste will be m 3, when packed 6

7 Decommissioning work plan 2/2 7

8 Decontamination of primary circuit Decontamination of the primary circuit will be carried out during the preparatory phase First time simulated by MCNP 5-modeling program (Monte Carlo N-Particle) 8

9 Needs for personal protective equipment The dismantling of the activated material will mostly be done by remote-control A lot of different kind of cutting work, so the migration of the dust must be prevented by isolating the working object The personal protective equipment for dismantling will be finally selected according to the work object In the decommissioning work plan the effects of protective equipment on work has been taken into account when estimating the time needed for different works 9

10 Final disposal 10

11 Risks of decommissioning Availability of experienced people Loviisa 2 power plant unit will still be in power generation while the decommissioning of the power plant unit 1 starts The consequences of potential accidents are that the contamination could spread to the environment, or personnel dismantling the power plant could be exposed to high levels of radiation. The risk study showed that there is no need for evacuation or any other restrictions for people living near the power plant The decommissioning of the power plant needs a preparedness plan, which is based on the accident and risk analyses Scope and schedule 11

12 Decommissioning costs Cost item Costs, euros Preparatory phase Main equipment, constructions and materials Dismantling works (contracts) Handling of wastes and final disposal Surveillance, guarding, maintenance and utilities at the site Project administration and design Other costs (personnel and insurances) Costs in all Reserve to cover unspecified costs, 10% Total costs Round total costs 359 M 12

13 Conclusions The decommissioning of the Loviisa power plant units is designed to start in So the licensing of decommissioning should start early 2020's Decontamination of the primary circuit will be carried out during the preparatory phase. The calculations show that decontamination will significantly reduce the collective doses caused by handling of the contaminated material The dismantling and treatment of the plant s radioactive components can be carried out with currently available technology and methods. Still an important part of planning the decommissioning is to follow various technological improvements and decommissioning projects around the world The decommissioning waste will be disposed of in the extension of the existing repository for operating waste. The licensing of the extension of the L/ILW repository should start early 2020s Next decommissioning plan update will be at

14 Thank you for your attention! 14

Safety Standards for Decommissioning Activities

Safety Standards for Decommissioning Activities Safety Standards for Decommissioning Activities Koji OKAMOTO The University of Tokyo (Chair of AESJ Decommissioning Standard Committee) Status of decommissioning in Japan Nuclear Power Plant (NPP) under

More information

CONTENTS OF THE PCSR CHAPTER 1 - INTRODUCTION AND GENERAL DESCRIPTION

CONTENTS OF THE PCSR CHAPTER 1 - INTRODUCTION AND GENERAL DESCRIPTION PAGE : 1 / 8 CONTENTS OF THE PCSR CHAPTER 1 - INTRODUCTION AND GENERAL DESCRIPTION SUB-CHAPTER 1.1 INTRODUCTION SUB-CHAPTER 1.2 GENERAL DESCRIPTION OF THE UNIT SUB-CHAPTER 1.3 COMPARISON WITH REACTORS

More information

R2D2P. Working group report

R2D2P. Working group report R2D2P Working group report Working group members: Clédola Cassia Oliveira de Tello (Brazil), Farouk Abdel-Rahman (Egypt), Ibrahim Muhamad (Malaysia), Milan Vujovic (Serbia), Quang Huy Pham (Vietnam) Team

More information

Management of Reactor Decommissioning

Management of Reactor Decommissioning Management of Reactor Decommissioning Tom McCool Project Manager Sellafield Ltd 9/24/2008 1 Introduction/ Background Managed the decommissioning of two research reactors in the UK Scottish Universities

More information

Transportation Emergency Preparedness Program (TEPP) Model First Responder Procedure for Transportation Accidents Involving Radiological Materials

Transportation Emergency Preparedness Program (TEPP) Model First Responder Procedure for Transportation Accidents Involving Radiological Materials Transportation Emergency Preparedness Program (TEPP) Model First Responder Procedure for Transportation Accidents Involving Radiological Materials This Transportation Emergency Preparedness Program (TEPP)

More information

The Regulatory Framework Improvement for Safe Decommissioning of Nuclear Power Plants in Korea

The Regulatory Framework Improvement for Safe Decommissioning of Nuclear Power Plants in Korea The Regulatory Framework Improvement for Safe Decommissioning of Nuclear Power Plants in Korea Sangmyeon Ahn 17th February 2016 Title ~ February 2016 ~ 1 Major Nuclear Facilities Nuclear Power Plants (NPP)

More information

IAEA Regional Workshop Legal and Regulatory Aspects of Decommissioning of Research Reactors June Manila, Philippines

IAEA Regional Workshop Legal and Regulatory Aspects of Decommissioning of Research Reactors June Manila, Philippines IAEA Regional Workshop Legal and Regulatory Aspects of Decommissioning of Research Reactors 26 30 June 2006 Manila, Philippines Monday, 26 June 2006 09:00 09:45 Opening (A. Dela Rosa, B. Batandjieva) Welcoming

More information

Evaluation and Demonstration of Safety of Decommissioning of

Evaluation and Demonstration of Safety of Decommissioning of Evaluation and Demonstration of Safety of Decommissioning of Research Reactors Borislava Batandjieva, IAEA Research Reactor Decommissioning Demonstration Project (R2D2P) 26-30 June 2006, Manila, Philippines

More information

Each year, the United States produces many tons of nuclear

Each year, the United States produces many tons of nuclear 36 Storing Waste TA L K I N G I T O V E R Each year, the United States produces many tons of nuclear waste. For more than forty years, scientists have been considering different ways to store this waste.

More information

OBJECTIVE 22: EMERGENCY WORKERS, EQUIPMENT, AND VEHICLES - MONITORING AND DECONTAMINATION

OBJECTIVE 22: EMERGENCY WORKERS, EQUIPMENT, AND VEHICLES - MONITORING AND DECONTAMINATION OBJECTIVE Demonstrate the adequacy of procedures for the monitoring and decontamination of emergency workers, equipment, and vehicles. INTENT This objective is derived from NUREG-0654 which provides that

More information

Dismantling of Fuel Flask Group B

Dismantling of Fuel Flask Group B Dismantling of Fuel Flask Group B Evangelos Maragkos; Gabor Toth; John Marquez; Lucian Leonido Biro; Mitica Dragusin; Yuri Lobach; Phuong Hoai Pham Bruce Watson List of hazards when using A) mechanical

More information

Università di Pisa Facoltà di Ingegneria Dipartimento di Ingegneria Meccanica, Nucleare e della Produzione. Emergency Planning.

Università di Pisa Facoltà di Ingegneria Dipartimento di Ingegneria Meccanica, Nucleare e della Produzione. Emergency Planning. Università di Pisa Facoltà di Ingegneria Dipartimento di Ingegneria Meccanica, Nucleare e della Produzione Emergency Planning Marino Mazzini Professore Ordinario nel s.s.d. Impianti Nucleari DOCUMENTAZIONE

More information

WHS record keeping - general (Local areas responsible for keeping these records)

WHS record keeping - general (Local areas responsible for keeping these records) WHS record keeping - general (Local areas responsible for keeping these records) Records Examples Retention period Records relating to risk assessment and management of hazards (except particular requirements

More information

Regulatory Review of Safety Assessment for Decommissioning of Facilities Using Radioactive Material

Regulatory Review of Safety Assessment for Decommissioning of Facilities Using Radioactive Material SAFETY ASSESSMENT FOR DECOMMISSIONING Annex III Regulatory Review of Safety Assessment for Decommissioning of Facilities Using Radioactive Material INTERNATIONAL ATOMIC ENERGY AGENCY VIENNA CONTENTS 1.

More information

Contractor Control Procedures. Contractor Control Procedures. Working Together. November Borders College 24/11/2014.

Contractor Control Procedures. Contractor Control Procedures. Working Together. November Borders College 24/11/2014. Working Together Contractor Control Procedures November 2014 Borders College 24/11/2014 1 Working Together 1. Introduction This procedure aims to control the health and safety of contractors working on

More information

Naturally Occurring Radioactive Material (NORM) Supersedes: 05/30/08 (Rev.01) Preparer: Owner: Approver: EHS Team Member EHS Team Member EHS Manager

Naturally Occurring Radioactive Material (NORM) Supersedes: 05/30/08 (Rev.01) Preparer: Owner: Approver: EHS Team Member EHS Team Member EHS Manager Procedure No.: PA-020-0021 Page: 1 of 8 Preparer: Owner: Approver: EHS Team Member EHS Team Member EHS Manager Document Revision Change Table Revision Number Revision Description Revised By Revision Date

More information

Competency type. positions. All workers (including contractors), higher degree students and volunteers

Competency type. positions. All workers (including contractors), higher degree students and volunteers Appendix A Training Required for Work Health & Safety Training WHS general and/or site/work specific induction of the emergency procedures and assembly areas Local first aid provisions. of hazards and

More information

MSE CONTROLLED DOCUMENT. Radiological HS&E Precautions for NORM Contaminated Tanks, Vessels & Separators

MSE CONTROLLED DOCUMENT. Radiological HS&E Precautions for NORM Contaminated Tanks, Vessels & Separators MSE CONTROLLED DOCUMENT Radiological HS&E Precautions for NORM Document No: Supersedes Revision no: 1 Date:1/10/2004 Custodian: MSE/32 Revision no: 1 Date: 1/10/2006 Filename: NORMMGT. DOC Administered

More information

Ionising Radiations Code of Practice & Guidance Contingency Arrangements

Ionising Radiations Code of Practice & Guidance Contingency Arrangements Ionising Radiations Code of Practice & Guidance Contingency Arrangements Where any radiation user uses a source of ionising radiations, which may for example include working with sealed (closed) sources,

More information

4.1 The Vice-Chancellor and University Executive Committee

4.1 The Vice-Chancellor and University Executive Committee UON Key Risk Area: KRA 1.4 Plant and Equipment 1. Purpose This procedure describes how the University meets its obligation to ensure the health and safety of people, through the processes of selection,

More information

Approved for public release; distribution is unlimited.

Approved for public release; distribution is unlimited. EMERGENCY RESPONSE TO HAZARDOUS SUBSTANCE SPILLS AND RELEASES IN ARMY MILITARY TREATMENT FACILITIES TECHNICAL INFORMATION PAPER NO. 59-040-0915 PURPOSE. To provide compliance strategies for responding

More information

Yucca Mountain. Los Alamos National Laboratory. Presented to: DOE-EM Performance Assessment Community of Practice Technical Exchange Meeting

Yucca Mountain. Los Alamos National Laboratory. Presented to: DOE-EM Performance Assessment Community of Practice Technical Exchange Meeting Status of the Repository at Yucca Mountain Presented to: DOE-EM Performance Assessment Community of Practice Technical Exchange Meeting Presented by: Dr. Paul R. Dixon Nuclear Waste Program Manager Los

More information

Complementarity between Safety and Physical Protection in the Protection against Acts of Sabotage of Nuclear Facilities

Complementarity between Safety and Physical Protection in the Protection against Acts of Sabotage of Nuclear Facilities Complementarity between Safety and Physical Protection in the Protection against Acts of Sabotage of Nuclear Facilities Robert Venot Institut de Radioprotection et de Sûreté Nucléaire 77-83, avenue du

More information

QUALITY ASSURANCE SPECIFICATION NONDESTRUCTIVE EXAMINATION PAGE 1 OF 7

QUALITY ASSURANCE SPECIFICATION NONDESTRUCTIVE EXAMINATION PAGE 1 OF 7 QUALITY ASSURANCE SPECIFICATION REVISION: 0 DATE: 08/29/14 NONDESTRUCTIVE EXAMINATION PAGE 1 OF 7 1.0 Purpose The purpose of this specification is to establish the minimum quality assurance requirements

More information

OCCUPATIONAL SAFETY AND ENVIRONMENTAL HEALTH GUIDELINE

OCCUPATIONAL SAFETY AND ENVIRONMENTAL HEALTH GUIDELINE OCCUPATIONAL SAFETY AND ENVIRONMENTAL HEALTH GUIDELINE Date: 04-22-2009 Revision: 02 Page: 1 of 6 SUMMARY: SCOPE: REFERENCE REGULATIONS: Employees using laboratory fume hoods shall observe all applicable

More information

Energiewerke Nord GmbH

Energiewerke Nord GmbH Energiewerke Nord GmbH CEG-Meeting Speaker Venue : Workshop JAEA : Holger Schmidt : Oxford, England Date : 05 th -07 th March 2008 1 Visualisation 2 Regional centre at Sayda Bay for conditioning and long-term

More information

TEPP Planning Products Model Procedure

TEPP Planning Products Model Procedure TEPP Planning Products Model Procedure for First Responder Initial Response to Radiological Transportation Accidents 02B00215-13.p65 Prepared for the Department of Energy Office of Transportation and Emergency

More information

! Subpart D - Contingency Plans and Emergency Procedures (40 CFR to ) (EPA regulations adopted by NJDEP); and

! Subpart D - Contingency Plans and Emergency Procedures (40 CFR to ) (EPA regulations adopted by NJDEP); and APPENDIX D EMERGENCY PROCEDURES IN PUBLIC SECONDARY SCHOOLS IN THE EVENT OF A CHEMICAL SPILL There are five major sources of regulations that are potentially applicable to emergencies involving a chemical

More information

WM2012 Conference, February 26 March 1, 2012, Phoenix, Arizona, USA. Treatment of G1 Baskets at the CEA Marcoule Site 12027

WM2012 Conference, February 26 March 1, 2012, Phoenix, Arizona, USA. Treatment of G1 Baskets at the CEA Marcoule Site 12027 Treatment of G1 Baskets at the CEA Marcoule Site 12027 Line Fourquet, Didier Boya CEA Marcoule, France ABSTRACT In the dismantling program for the first-generation French reactors in accordance with the

More information

New Licensed Asbestos Manager Training

New Licensed Asbestos Manager Training TRAINING SYLLABUS LICENSED WORK WITH ASBESTOS New Licensed Asbestos Manager Training This unit has twenty-three learning outcomes. 1. Recognise the types, uses and risks of asbestos containing materials

More information

IEM on Severe Accident Management in the light of the accident at the Fukushima Daïchi NPP

IEM on Severe Accident Management in the light of the accident at the Fukushima Daïchi NPP IEM on Severe Accident Management in the light of the accident at the Fukushima Daïchi NPP Progress, challenges and perspectives in the field of design features, as regards SAMG IAEA, March 2014 Introduction

More information

Safety Procedures on Vacating Premises

Safety Procedures on Vacating Premises Safety Procedures on Vacating Premises Policy From time to time Departments, Units and Centres of HKU vacate accommodation as a result of relocation or major refurbishment. When any accommodation is vacated,

More information

HAZARDOUS WASTE OPERATIONS AND EMERGENCY RESPONSE (HAZWOPER)

HAZARDOUS WASTE OPERATIONS AND EMERGENCY RESPONSE (HAZWOPER) SECTION 28 HAZARDOUS WASTE OPERATIONS AND EMERGENCY RESPONSE (HAZWOPER) 28.A. GENERAL. 28.A.01 This Section applies to: a. Hazardous waste site cleanup operations performed under the Comprehensive Environmental

More information

Equipment Decommissioning and Removal

Equipment Decommissioning and Removal Hard copy of this document, if not marked CONTROLLED in red, is by definition uncontrolled and may be out of date. Doc. No. & Rev. Procedure for Equipment Decommissioning and Removal Rev No. REVISION DCN

More information

SPECIALIZED ONLINE TRAINING COURSE LIST

SPECIALIZED ONLINE TRAINING COURSE LIST SPECIALIZED ONLINE TRAINING COURSE LIST Grainger Online Safety Manager provides you with access to online training courses covering today's most relevant safety topics. The training content is designed

More information

CBRN Academy. Assistance and Protection Training Course PROGRAMME PLAN

CBRN Academy. Assistance and Protection Training Course PROGRAMME PLAN CBRN Academy Assistance and Protection Training Course PROGRAMME PLAN TRAINING PROGRAMME CONTENTS PAGE ASSISTANCE AND PROTECTION TRAINING COURSE 3 PREVIOUS KNOWLEDGE 3 PREREQUISITES 3 TIME ALLOCATION 4

More information

Safety of Decommissioning: International Cooperation under the IAEA Coordination

Safety of Decommissioning: International Cooperation under the IAEA Coordination Safety of Decommissioning: International Cooperation under the IAEA Coordination Vladan Ljubenov WM 09, Session 68 - Panel discussion IAEA Mission The IAEA serves as an intergovernmental forum for scientific

More information

Nuclear safety Lecture 4. The accident of the TMI-2 (1979)

Nuclear safety Lecture 4. The accident of the TMI-2 (1979) Nuclear safety Lecture 4. The accident of the TMI-2 (1979) Ildikó Boros BME NTI 27 February 2017 The China Syndrome Opening: 16 March 1979 Story: the operator of the Ventana NPP tries to hide the safety

More information

POLICY FOR COSHH (CONTROL OF SUBSTANCES HAZARDOUS TO HEALTH) POLICY

POLICY FOR COSHH (CONTROL OF SUBSTANCES HAZARDOUS TO HEALTH) POLICY POLICY FOR COSHH (CONTROL OF SUBSTANCES HAZARDOUS TO HEALTH) POLICY Written By: Nursery Manager Date approved by Directors: Signature: Date for Review: November 2018 COSHH (CONTROL OF SUBSTANCES HAZARDOUS

More information

Hazardous Materials Spill Response

Hazardous Materials Spill Response Hazardous Materials Spill Response The University of Iowa Rev. 02/10 Department Lab/Room Number PI/Lab Coordinator After Hours Contact Number University Public Safety (Phone 911) Fire, Police, Ambulance

More information

What are the benefits of the best practice: New PAAA Enforcement Coordinators will have a better understanding of the associated CFR.

What are the benefits of the best practice: New PAAA Enforcement Coordinators will have a better understanding of the associated CFR. Facility: Hanford Tank Farm/Hanford Best Practice Title: for Point of Contact: Barry Thom 509-376-1814 charles_thom@rl.gov Brief Description of Best Practice: The Price Anderson Amendment Act (PAAA) involves

More information

Refresher Licensed Asbestos Supervisor Training

Refresher Licensed Asbestos Supervisor Training TRAINING SYLLABUS LICENSED WORK WITH ASBESTOS Refresher Licensed Asbestos Supervisor Training This unit has nineteen learning outcomes. 1. Recognise the types, uses and risks of asbestos containing materials

More information

IC67 - Pre-Instructional Survey

IC67 - Pre-Instructional Survey IC67 - Pre-Instructional Survey 1. What does the term code refer to in the installation of power plant piping? a. National welders code b. Fire protection code c. ASME Boiler and Pressure Vessel Code Section

More information

Technical Specification Bases Update to the NRC for Period Dated

Technical Specification Bases Update to the NRC for Period Dated ...~Entergy Entergy Operations, Inc. 7003 Bald Hill Road PO. Box 756 Port Gibson, MS 39150 Tel 601 437 6299 Christina L. Perino Manager Licensing GNRO-2009/00017 March 4, 2009 U.S. Nudear Regulatory Commission

More information

Hazardous Materials Spill Response

Hazardous Materials Spill Response Hazardous Materials Spill Response The University of Iowa Rev. 01/2019 Department: Lab/Room Number: PI/Lab Coordinator: After-hours Contact Number: University Public Safety - 911 Fire, Police, Ambulance

More information

Procedure: Pressure equipment safety

Procedure: Pressure equipment safety Procedure: Pressure equipment safety Purpose The purpose of this procedure is to define the method for safe operation and inspection of pressure equipment and the collection and recording of associated

More information

Comprehensive dismantlement of the Lepse technical floating base

Comprehensive dismantlement of the Lepse technical floating base Comprehensive dismantlement of the Lepse technical floating base M. Kashka, Deputy Technical Director of the Nuclear Icebreaker Fleet, Murmansk Shipping Company, Russia 1. General specifications of the

More information

Hunters Point Naval Shipyard

Hunters Point Naval Shipyard Hunters Point Naval Shipyard Radiological Data Retesting Update HPS CAC Environmental & Reuse Subcommittee Meeting November 7, 2018 Derek J. Robinson, P.E. Navy Base Realignment and Closure (BRAC) BRAC

More information

Page 1 of 5 UC Santa Barbara Policy 5400 Policies Issuing Unit: Administrative Services Date: June 1, 1989 ENVIRONMENTAL HEALTH AND SAFETY I. REFERENCES (Available at the Environmental Health and Safety

More information

Review and Assessment of Engineering Factors

Review and Assessment of Engineering Factors Review and Assessment of Engineering Factors 2013 Learning Objectives After going through this presentation the participants are expected to be familiar with: Engineering factors as follows; Defense in

More information

Emergency Response Code CODE BROWN HAZARDOUS SPILLS. Purpose & Authority. Definitions

Emergency Response Code CODE BROWN HAZARDOUS SPILLS. Purpose & Authority. Definitions CODE BROWN HAZARDOUS SPILLS Purpose & Authority This plan addresses the procedures to be followed in the event of a spill involving a hazardous substance. All hazardous substance spills shall be reported

More information

IAEA SAFETY STANDARDS for protecting people and the environment

IAEA SAFETY STANDARDS for protecting people and the environment IAEA SAFETY STANDARDS for protecting people and the environment DESIGN OF REACTOR CONTAINMENT STRUCTURE AND SYSTEMS FOR NUCLEAR POWER PLANTS DRAFT SAFETY GUIDE DS 482 STATUS: STEP 11 Submission to Review

More information

Introduction to Emergency Response & Contingency Planning

Introduction to Emergency Response & Contingency Planning & Contingency Planning Rationale Why is it important for you to learn this material? Designed for those who may witness a release, this is an introductory course designed to help ensure those who are likely

More information

The «practical elimination» approach for pressurized water reactors

The «practical elimination» approach for pressurized water reactors The «practical elimination» approach for pressurized water reactors V. TIBERI K.HERVIOU International Conference on Topical Issues in Nuclear Installation Safety: Safety Demonstration of Advanced Water

More information

Yucca Mountain Update and Transportation Impacts Robert J. Halstead Office of the Governor Nevada Agency for Nuclear U.S. Conference of Mayors Winter

Yucca Mountain Update and Transportation Impacts Robert J. Halstead Office of the Governor Nevada Agency for Nuclear U.S. Conference of Mayors Winter Yucca Mountain Update and Transportation Impacts Robert J. Halstead Office of the Governor Nevada Agency for Nuclear U.S. Conference of Mayors Winter Meeting Washington, DC January 24, 2018 Visit our website:

More information

Planned reference and intervention levels in Finland

Planned reference and intervention levels in Finland Radioprotection 2013 Vol. 48, n o 5, pages S85 à S92 DOI: 10.1051/radiopro/20139913 Case studies in national experiences Planned reference and intervention levels in Finland Abstract In Finland, Radiation

More information

HAZARDOUS MATERIALS INCIDENTS EMERGENCY RESPONSE PLAN

HAZARDOUS MATERIALS INCIDENTS EMERGENCY RESPONSE PLAN HAZARDOUS MATERIALS INCIDENTS EMERGENCY RESPONSE PLAN November 2014 UNIVERSITY OF NORTHERN COLORADO HAZARDOUS MATERIALS INCIDENTS EMERGENCY RESPONSE PLAN TABLE OF CONTENTS I. INTRODUCTION... 3 II. HAZARDOUS

More information

IAEA SAFETY STANDARDS for protecting people and the environment

IAEA SAFETY STANDARDS for protecting people and the environment Date: 2016-08-31 IAEA SAFETY STANDARDS for protecting people and the environment STATUS: STEP 8a For Submission to Member States DESIGN OF REACTOR CONTAINMENT STRUCTURE AND SYSTEMS FOR NUCLEAR POWER PLANTS

More information

PLANNED LIGHTING MAINTENANCE LTD METHOD STATEMENT & RISK ASSESSMENT REPLACEMENT OF LAMPS OR REPAIRS TO HIGH LEVEL LIGHT UNITS

PLANNED LIGHTING MAINTENANCE LTD METHOD STATEMENT & RISK ASSESSMENT REPLACEMENT OF LAMPS OR REPAIRS TO HIGH LEVEL LIGHT UNITS PLANNED LIGHTING MAINTENANCE LTD METHOD STATEMENT & RISK ASSESSMENT REPLACEMENT OF LAMPS OR REPAIRS TO HIGH LEVEL LIGHT UNITS Project: (insert Client) Replacement/ Repair of high level light units/ high

More information

Policy Redesign Project. Plant Safety Policy. Table of Contents

Policy Redesign Project. Plant Safety Policy. Table of Contents Policy Redesign Project All policies and procedures are being reviewed as part of this project. This document is pending review, but remains in effect until the review is carried out. Plant Safety Policy

More information

/16/05 11:24 PM Page 1 DECON IN A BAG. Printed on waterproof paper.

/16/05 11:24 PM Page 1 DECON IN A BAG. Printed on waterproof paper. 46003 9/16/05 11:24 PM Page 1 DECON IN A BAG Printed on waterproof paper. 46003 9/16/05 11:24 PM Page 2 1 Contents of Decon-In-A-Bag Decon-In-A-Bag is designed for emergency response personnel such as

More information

DEPARTMENT SCHOOLS OF HEALTH

DEPARTMENT SCHOOLS OF HEALTH PATIENT LIFTING: Work with patients/human subjects may involve lifting and moving of patients. Exposure to physical injury from lifting and moving of patients/human subjects. Avoid unnecessary exposures.

More information

Development of a technology to investigate inside the Reactor Primary Containment Vessel (PCV)

Development of a technology to investigate inside the Reactor Primary Containment Vessel (PCV) Development of a technology to investigate inside the Reactor Primary Containment Vessel (PCV) - Results of follow up check after the site test - [For April 18 and 19, 2015] April 20, 2015

More information

The Role of Modeling and Simulation in Extreme Engineering Projects. Jon Berkoe Bechtel National, Inc. San Francisco, California

The Role of Modeling and Simulation in Extreme Engineering Projects. Jon Berkoe Bechtel National, Inc. San Francisco, California The Role of Modeling and Simulation in Extreme Engineering Projects Jon Berkoe Bechtel National, Inc. San Francisco, California Introduction Extreme environments add Design Complexity and Risk to Engineering

More information

Severe Accident Management Programmes for Nuclear Power Plants

Severe Accident Management Programmes for Nuclear Power Plants DS 483: Mode 2 27 March 2017 IAEA SAFETY STANDARDS for protecting people and the environment STEP 11: Approval by the relevant review Committees Reviewed in NSOC (Asfaw) Severe Accident Management Programmes

More information

ERIC LAFFORGUE. The Atomic surfers from Fukushima

ERIC LAFFORGUE. The Atomic surfers from Fukushima ERIC LAFFORGUE The Atomic surfers from Fukushima On 11 March 2011, at 2.46 pm, Japan was hit by a magnitude 9.0 earthquake which generated a tsunami on the coast. Here, on Futaba beach, the giant wave

More information

New Licensed Asbestos Operative Training

New Licensed Asbestos Operative Training TRAINING SYLLABUS LICENSED WORK WITH ASBESTOS New Licensed Asbestos Operative Training This unit has twenty-two learning outcomes. 1. Recognise the types, uses and risks of asbestos containing materials

More information

in84061.txt at Page 1 of 6 2/25/00

in84061.txt at  Page 1 of 6  2/25/00 in84061.txt at www.nrc.gov Page 1 of 6 UNITED STATES NUCLEAR REGULATORY COMMISSION OFFICE OF INSPECTION AND ENFORCEMENT WASHINGTON, D.C. 20555 SSINS No.: 6835 IE INFORMATION NOTICE NO. 84-61: OVEREXPOSURE

More information

Instructions in the Use of Radiation Protection. Equipment and Radiation Measuring Instruments by. Disaster Response Personnel in a Nuclear Emergency

Instructions in the Use of Radiation Protection. Equipment and Radiation Measuring Instruments by. Disaster Response Personnel in a Nuclear Emergency Instructions in the Use of Radiation Protection Equipment and Radiation Measuring Instruments by Disaster Response Personnel in a Nuclear Emergency April 1,2018 (First edition:april 1,2017) (Second edition:april

More information

Decommissioning International Network

Decommissioning International Network Potential demands & contributions of Enresa to the Decommissioning International Network SOMETHING ABOUT ENRESA State-owned company Responsible, by law, of a) The management of all the radioactive waste

More information

RISKAUDIT GRS - IRSN Safety assessment of the BELENE NPP

RISKAUDIT GRS - IRSN Safety assessment of the BELENE NPP RISKAUDIT GRS - IRSN Safety assessment of the BELENE NPP Bulatom Conference 2010 Bulgarian Nuclear Energy National, Regional and World Energy Safety 9th -11th June 2010, Riviera complex, Varna Système

More information

TEMPLE UNIVERSITY ENVIRONMENTAL HEALTH AND RADIATION SAFETY

TEMPLE UNIVERSITY ENVIRONMENTAL HEALTH AND RADIATION SAFETY Page 1 of 9 ISSUED: 5/00 REVISED: 08/06 Introduction Purpose: In accordance with applicable regulations and Temple University, this policy was developed to minimize exposure to Ethylene Oxide. Applicability

More information

Instructions: Use this format to prepare the security plans for ACP contracts. EVERY point has to be covered; if they do not apply, write N/A.

Instructions: Use this format to prepare the security plans for ACP contracts. EVERY point has to be covered; if they do not apply, write N/A. APPENDIX F - RISK CONTROL PLAN FORMAT FOR CONTRACTORS OF THE PANAMA CANAL Instructions: Use this format to prepare the security plans for ACP contracts. EVERY point has to be covered; if they do not apply,

More information

Standard Test Procedures Manual

Standard Test Procedures Manual STP 204-6 Standard Test Procedures Manual Section: 1. SCOPE This procedure determines the density of asphalt concrete in place by using the backscatter position (the gamma radiation source remains on the

More information

OBJECTIVE 6: FIELD RADIOLOGICAL MONITORING - AMBIENT RADIATION MONITORING

OBJECTIVE 6: FIELD RADIOLOGICAL MONITORING - AMBIENT RADIATION MONITORING OBJECTIVE 6: FIELD RADIOLOGICAL MONITORING - AMBIENT RADIATION MONITORING OBJECTIVE Demonstrate the appropriate use of equipment and procedures for determining field radiation measurements. INTENT This

More information

AUSTRALIA ARGENTINA CANADA EGYPT NORTH SEA U.S. CENTRAL U.S. GULF. SEMS HAZARD ANALYSIS TRAINING September 29, 2011

AUSTRALIA ARGENTINA CANADA EGYPT NORTH SEA U.S. CENTRAL U.S. GULF. SEMS HAZARD ANALYSIS TRAINING September 29, 2011 AUSTRALIA ARGENTINA CANADA EGYPT NORTH SEA U.S. CENTRAL U.S. GULF SEMS HAZARD ANALYSIS TRAINING September 29, 2011 Purpose The purpose of this meeting is to provide guidelines for determination of hazard

More information

PLANNED LIGHTING MAINTENANCE LTD METHOD STATEMENT & RISK ASSESSMENT REPLACEMENT OF LAMPS OR REPAIRS TO LOW LEVEL LIGHT UNITS

PLANNED LIGHTING MAINTENANCE LTD METHOD STATEMENT & RISK ASSESSMENT REPLACEMENT OF LAMPS OR REPAIRS TO LOW LEVEL LIGHT UNITS PLANNED LIGHTING MAINTENANCE LTD METHOD STATEMENT & RISK ASSESSMENT REPLACEMENT OF LAMPS OR REPAIRS TO LOW LEVEL LIGHT UNITS Project: Insert Client Repair/ Replacement of low level light units/ low level

More information

SH&E Training Matrix (Americas, all Business Groups)

SH&E Training Matrix (Americas, all Business Groups) SH&E Training Matrix (Americas, all Business Groups) Employee Name: Location: Employee Number: Date: Table 1: All Employees 10 Hour Outreach Course (OSHA General Industry or Construction) 30 Hour Outreach

More information

Decommissioning Regulatory Process

Decommissioning Regulatory Process Decommissioning Regulatory Process Deanna Toy June 27, 2018 Diablo Canyon Decommissioning Engagement Panel 1055 Monterey St. San Luis Obispo County Government Building June 27, 2018 Safety Moment AED CPR

More information

The Energy Seminar The Discussion: Nuclear Energy

The Energy Seminar The Discussion: Nuclear Energy The Energy Seminar The Discussion: Nuclear Energy Amory B. Lovins Chief Executive Officer and Chairman of the Board Rocky Mountain Institute MAP/Ming Professor, Stanford University, Spring Qtr. Burton

More information

GEOS 5311 Lecture Notes: Numerical Modeling Example, Yucca Mountain, Nevada

GEOS 5311 Lecture Notes: Numerical Modeling Example, Yucca Mountain, Nevada GEOS 5311 Lecture Notes: Numerical Modeling Example, Yucca Mountain, Nevada Dr. T. Brikowski Spring 2010 file:yuccamtn.tex,v (1.11, January 26, 2010), printed March 30, 2011 Introduction 1 Introduction:

More information

DESIGN OF REACTOR CONTAINMENT STRUCTURE AND SYSTEMS FOR NUCLEAR POWER PLANTS

DESIGN OF REACTOR CONTAINMENT STRUCTURE AND SYSTEMS FOR NUCLEAR POWER PLANTS SAFETY STANDARDS SERIES No. NS-G-1.10 DESIGN OF REACTOR CONTAINMENT STRUCTURE AND SYSTEMS FOR NUCLEAR POWER PLANTS SAFETY GUIDE DS 482 2016-04-20 INTERNATIONAL ATOMIC ENERGY AGENCY VIENNA, C-41 (May 13)

More information

Northern Kentucky University Issue Date: 11/02/2018 Revised Date: Title: PERSONAL PROTECTIVE EQUIPMENT PROCEDURE OBJECTIVE AND PURPOSE

Northern Kentucky University Issue Date: 11/02/2018 Revised Date: Title: PERSONAL PROTECTIVE EQUIPMENT PROCEDURE OBJECTIVE AND PURPOSE Northern Kentucky University Issue Date: 11/02/2018 Revised Date: Policy Link: Occupational Safety Policy Title: PERSONAL PROTECTIVE EQUIPMENT PROCEDURE OBJECTIVE AND PURPOSE The objective of this procedure

More information

Level 4 Certificate in Asbestos Removal for Contract Managers

Level 4 Certificate in Asbestos Removal for Contract Managers Level 4 Certificate in Asbestos Removal for Contract Managers January 2012 This qualification has a Credit Value of SEVENTEEN Guided Learning Hours: 94 Ofqual Qualification Number: 600/4478/0 Description

More information

24 Hour HAZWOPER 29 CFR (e) The Official Site of Environmental Health & Safety Training. Course Description

24 Hour HAZWOPER 29 CFR (e) The Official Site of Environmental Health & Safety Training. Course Description NATIONAL ENVIRONMENTAL TRAINERS, INC. 3812 SHOAL CREEK COURT MARTINEZ, GEORGIA 30907 1.888.877.7130 WWW.NATIONALENVIRONMENTALTRAINERS.COM The Official Site of Environmental Health & Safety Training 24

More information

Overview. OPIPOH10 - SQA Unit Code HG Operate an Oil and Gas Process ( Gas Treatment)

Overview. OPIPOH10 - SQA Unit Code HG Operate an Oil and Gas Process ( Gas Treatment) OPIPOH10 - SQA Unit Code HG21 04 Overview This process involves the removal of impurities from the gas stream to reach the specified quality. The process boundary is from the inlet such as separator, compressor

More information

LOCKOUT SYSTEM AND POLICIES

LOCKOUT SYSTEM AND POLICIES LOCKOUT SYSTEM AND POLICIES Lockout System Purpose Employees health and safety takes top priority. Isolating hazardous energy to prevent sudden and unexpected energisation of machines, equipment, and processes

More information

Section 33 TABLE OF CONTENTS Hazardous Waste Operations and Emergency Response (HAZWOPER) 33.A General

Section 33 TABLE OF CONTENTS Hazardous Waste Operations and Emergency Response (HAZWOPER) 33.A General Section 33 TABLE OF CONTENTS Hazardous Waste Operations and Emergency Response (HAZWOPER) Section: Page 33.A General... 33-1 33.B Site Safety and Health Plan (SSHP)... 33-1 33.C Responsibilities... 33-4

More information

EMPLOYEE SAFETY ORIENTATION - PHYSICAL PLANT, RESIDENCE

EMPLOYEE SAFETY ORIENTATION - PHYSICAL PLANT, RESIDENCE Name Department Initial Orientation Date Supervisor Review Instructions: Check off each section once you have read and discussed it with your Supervisor. EMPLOYEE SAFETY ORIENTATION - PHYSICAL PLANT, RESIDENCE

More information

Clearing a recent building a chance to get as much material out as indistinguishable from background

Clearing a recent building a chance to get as much material out as indistinguishable from background Clearing a recent building a chance to get as much material out as indistinguishable from background A rare opportunity Pete Burgess 3/4/2014 Winfrith EAST building Built to treat 300 m 3 of sludge from

More information

Council CNL(16)31. Annual Progress Report on Actions Taken Under the Implementation Plan for the Calendar Year EU - Finland

Council CNL(16)31. Annual Progress Report on Actions Taken Under the Implementation Plan for the Calendar Year EU - Finland Agenda item 6.1 For information Council CNL(16)31 Annual Progress Report on Actions Taken Under the Implementation Plan for the Calendar Year 2015 EU - Finland CNL(16)31 Annual Progress Report on Actions

More information

MSE CONTROLLED DOCUMENT. Radiological HS&E Precautions for Dismantling Equipment

MSE CONTROLLED DOCUMENT. Radiological HS&E Precautions for Dismantling Equipment MSE CONTROLLED DOCUMENT Radiological HS&E Precautions for Dismantling Equipment Document No: Supersedes Revision no: 1 1/10/2004 Custodian: MSE/32 Revision no: 1 1/10/2006 Filename: NORMMGT. DOC Administered

More information

Laboratory Preparedness Checklists for Advanced Planning, Preparing to Close & Safe Re-Entry

Laboratory Preparedness Checklists for Advanced Planning, Preparing to Close & Safe Re-Entry Laboratory Preparedness Checklists for Advanced Planning, Preparing to Close & Safe Re-Entry Disruptions, utility outages, and severe weather events may require a laboratory closure. These events have

More information

PART P CONTINGENCY PLANNING FOR RESPONSE TO RADIOACTIVE MATERIAL EMERGENCIES

PART P CONTINGENCY PLANNING FOR RESPONSE TO RADIOACTIVE MATERIAL EMERGENCIES Sec. P.1 - P.3 SSRCR Volume I - August 2001 PART P CONTINGENCY PLANNING FOR RESPONSE TO RADIOACTIVE MATERIAL EMERGENCIES Sec. P.1 - Purpose. This Part provides for preparedness and response to events involving

More information

Hazardous Materials Management. Presented by. James E. Roughton, MS, CSP, CRSP, CHMM.

Hazardous Materials Management. Presented by. James E. Roughton, MS, CSP, CRSP, CHMM. Hazardous Materials Management Presented by. James E. Roughton, MS, CSP, CRSP, CHMM. Hazardous Waste Operations And Emergency Response (HAZWOPER) 29 CFR 1910.120 Scope Clean-up Operations At Uncontrolled

More information

Temporary Increase in the Emergency Exposure Dose Limit in Response to the TEPCO Fukushima Daiichi NPP Accident December 3, 2014

Temporary Increase in the Emergency Exposure Dose Limit in Response to the TEPCO Fukushima Daiichi NPP Accident December 3, 2014 ひと くらし みらいのために 厚生労働省 Temporary Increase in the Emergency Exposure Dose Limit in Response to the TEPCO Fukushima Daiichi NPP Accident December 3, 2014 Shojiro Yasui,, PhD Office for Radiation Protection

More information

PROCEDURES FOR REPAIRS TO ASME NV STAMPED PRESSURE RELIEF DEVICES OF NUCLEAR SAFETY RELATED PRESSURE RELIEF VALVES

PROCEDURES FOR REPAIRS TO ASME NV STAMPED PRESSURE RELIEF DEVICES OF NUCLEAR SAFETY RELATED PRESSURE RELIEF VALVES NB16 0603 NR Task Group 1 9 16 1. One update by NR task group page 3: 7/17/19 2. Two updates to S6.1 and S6.3 on page 1: 7/19/17 SUPPLEMENT 6 PROCEDURES FOR REPAIRS TO ASME NV STAMPED PRESSURE RELIEF DEVICES

More information

Safety and efficiency go hand in hand at MVM Paks NPP

Safety and efficiency go hand in hand at MVM Paks NPP International Forum Atomexpo 2018 Safety and efficiency go hand in hand at MVM Paks NPP József Elter MVM Paks Nuclear Power Plant Ltd. Hungary Start up Four of the VVER-440/V213 unit Power units up-rate

More information

FUNDAMENTAL SAFETY OVERVIEW VOLUME 2: DESIGN AND SAFETY CHAPTER F: CONTAINMENT AND SAFEGUARD SYSTEMS 7. CONTAINMENT HEAT REMOVAL SYSTEM (EVU [CHRS])

FUNDAMENTAL SAFETY OVERVIEW VOLUME 2: DESIGN AND SAFETY CHAPTER F: CONTAINMENT AND SAFEGUARD SYSTEMS 7. CONTAINMENT HEAT REMOVAL SYSTEM (EVU [CHRS]) PAGE : 1 / 16 7. CONTAINMENT HEAT REMOVAL SYSTEM (EVU [CHRS]) 7.0. SAFETY REQUIREMENTS 7.0.1. Safety functions The main functions of the EVU system [CHRS] are to limit the pressure inside the containment

More information

TA10A and TA10P Steam Tracing Temperature Control Valves Installation and Maintenance Instructions

TA10A and TA10P Steam Tracing Temperature Control Valves Installation and Maintenance Instructions 3500032/2 IM-P350-02 CH Issue 2 TA10A and TA10P Steam Tracing Temperature Control Valves Installation and Maintenance Instructions 1. Safety information 2. General product information 3. Installation 4.

More information