Tullis Russell Machinery Safety Conference. David Robinson - Process Control Manager
|
|
- George Mason
- 6 years ago
- Views:
Transcription
1 Tullis Russell Machinery Safety Conference David Robinson - Process Control Manager
2 Contents 1. Introduction to Tullis Russell 2. Major Issues Confronting Tullis Russell 3. History of MPS on our Site Internal Procedures 5. Example of Recent Upgrade to our Auchmuty No4 Paper Machine
3 Background Established 1809 Largest Independent Fine Papermaker in UK Operate on a 230 Acre Site in Fife, Scotland 530 Employees who are all Shareholders Operate a wide range of Machinery Oldest Newest
4 Major Issues Today Health Safety and Welfare of our Employees Environmental Performance Legislation Becoming Increasingly Stringent. Energy Costs Combined Fuel Bill now Double 2002 Costs Price and Quality Competition From Far East now a major Issue
5 Making Paper Safely at Tullis Russell In Response to the PABIAC Document Making Paper Safely GAP Teams were set up for all Paper Machines within the Mills to identify areas of noncompliance. All Production Areas Were Included in the Projects Projects and Associated Costs Were Defined Overall Plans Created and Targets For Completion Set Reporting GAP Project Progress was routed through local Safety Committees to Central Safety Committees and Senior Managers Safety Committee
6 Making Paper Safely at Tullis Russell MPS endeavours to restrict Operator interventions Interventions are typically created by Breaks Accumulation - broke, debris, size & stock Fault finding Quality inspection
7 Making Paper Safely at Tullis Russell Sample Projects Fixed Guarding Improved Tail Feeding systems Dual Edge Cutters on the Wire Part Install Break Monitoring Cameras Install On Line Quality Inspection Systems Install Safety Related Control Systems
8 Making Paper Safely at Tullis Russell Basic Principles Applied Remove the Operator from the Danger Zone Completely if Possible. Implement Projects to Reduce Operator Interventions. Install Fixed Distance Guarding where Appropriate. Install Safety Related Control System as a Last Resort.
9
10 Improved Rope Runs and Pulley Arrangements Remote Points For Condition Monitoring Use of Paper Pickers/air lances Lubrication Points Piped out SRCS System with Key Exchange System/Standstill Monitor/Overspeed and Crawl
11
12 Single Nip Configuration Fixed Distance Guarding Easier Feeding Better Quality Fewer Breaks Fewer Interventions
13 Frequency - Paper Breaks 00/01 01/02 02/03 03/04(ytd)
14 Breaks/1000Tonne 00/01 01/02 02/03 03/04(ytd)
15 Minutes/Breaks 00/01 01/02 02/03 03/04(ytd)
16 Downtime % 00/01 01/02 02/03 03/04(ytd)
17 Making Paper Safely - SRCS Systems Issues Understanding the Requirements New Technology for Maintenance Staff New Procedures for Maintenance Staff Problems With Sensitivity of Systems Causing Nuisance Stoppages on Plant Operator Accessing Machinery using Key Exchange System. Re-Training Operators on new Procedures.
18 Making Paper Safely - SRCS Systems Benefits Removal of Operators From Danger Zones. More Aware of Risks Posed by Machinery. Sanity Check Time Before Making an Intervention. Focus Shifted onto Break Reduction and More Effective Tail Feeding Systems. Safer Working Environment.
19 Making Paper Safely In 2004 A decision was made to Implement a Site wide procedure for the Application of Safety Related Control Systems to our Existing Machinery and New Projects. The Procedure Should Ensure a Consistent Approach to the Application of Safety Related Systems. External Expertise from PILZ UK was used to Provide Training and Support to set up Procedure.
20 Making Paper Safely SEP built on IEC61508 principles System Lifecycle Approach In Conjunction with a Risk Assessment the Procedure allows us to Examine Consequence of Dangerous Occurrence Frequency of Exposure, Possibility of Avoidance Probability of Failure Occurring Uses Risk graph method Safety Integrity Levels Issue Safety Requirements Specification to Vendors
21 Tullis Russell Engineering/Process
22 W3 W 2 W 1 C 1 Starting point for risk reduction determination C 2 F 1 P 1 P 2 a a a F 2 P P C 3 F F C 4 b 4 3 Consequence Frequency of Exposure Figure (3) Risk Graph Possibility of Avoidance Probability
23 Personnel Environmental Asset C1 M inor injury (first aid treatment) M inor release contained on site < 10k (non reportable) < 1 day C2 Calibrating our Risk Graph M ajor injury (e.g. fractures, loss of sight, dislocation, injuries leading to unconsciousness or hospitalisation > 24 hours) M inor release offsite (reportable) C3 Single death in im m ediate area Release off site causing reversible damage requiring significant clean up C4 M any deaths Release off site causing permanent damage or requiring major clean up costs Table (4) Consequence M atrix 10k to < 100K 1 day to < 1 week 100K to < 1M 1 w eek to < 1 month 1 months 1M F1 F2 Exposure less once per shift Exposure more once per shift
24 Calibrating our Risk Graph P1 Personnel Environment al Asset Warning to Possible for operator to take Possible for operator to take permit escape action to negate or reduce action to negate or reduce affect of event P2 No prior warning Unlikely operator will be able of event to take mitigating action Table (6) Possibility of Avoidance Matrix affect of event Unlikely operator will be able to take mitigating action W1 W2 W3 Probability of occurrence [W] Very slight (less than once every 30 years) Slight (betw een once a year and once every 30 years) Frequent demand (at least once per year)
25 Example In 2004 Capital was approved to install a new Voith Calendar and Tail Feeding System. In Parallel to the Overall Engineering Design the Risk Assessments and Operating Procedures Were Produced. Visits to other Plants allowed us to Visualise Plant and Create Operational Procedures and Safe Systems of Work prior to Installation of Kit. From the Risk Assessments a SIL Level was allocated.
26 MPS RISK ASSESSMENT DEPARTMENT AUCHMUTY A4 Activity Changing calender doctor blades ASSESSOR 0 DATE SSOW No. A4 Calenders 3 Likelyhood of occurance / contact with hazard Frequency of exposure to the hazard Degree of possible harm taken into account the worst case Number of persons exposed to the hazard Almost immpossible Annualy 0.5 Scratch/ bruise 0.1 One/two persons 1 Highly unlikely 1 Monthly 1 Lacerations / mild effect 0.5 Thre / seven Weekly 1.5 Break minor bone or 2 Eighjt/ fifteen 4 Unlikely ilness 2 Daily 2.5 Break major bone or 4 Sixteen/ fifty 8 Possible ilness 5 Hourly 4 Loss of one limb eye 6 Fifty/plus 12 hearing loss (permanent) Even chance 8 Constant 5 Loss of two limbs eyes 10 Probable (permanent) Likely 10 Fatality 15 Certain 15 Score Revised score Copy No. 1 RISK RATING Score 100 CONTROL MEASURES Fixed close fitting guards at the back side. Fixed guard below the bottom roll of nip 2 to prevent access between the nips. Fixed distance guard before nip 1 to prevent access between the nips and from the ingoing nip 1, but allow access to tear off wraps and clean stamps. Interlocked gates as per the cylinders at the front side, allows operation in "hold to run" mode only and an interlock on the frame gate between nip 1 and 2 which when open does not allow the calenders to operate in any mode. REVISED RATING SCORE
27 P2 = No Possibility of Avoidance W2 Slight Possibility (1-30 Years) C2 Consequence = Major Injury C 1 W3 W 2 W 1 Starting point for risk reduction determination C 2 F 1 P 1 P 2 a a a F 2 P C 3 F 1 P F C 4 b 4 3 Figure (3) Risk Graph Frequency more than once per Shift
28 With Calendar safety gates CLOSED, an alarm will operate audibly and visually for 20 seconds and visually only, for a further 10 seconds, prior to a 5 second 'permit to start' window being available to the operator. An operator s indicator will show that a start-up sequence has been initiated from the Calendar section, and will flash when the 'permit to start' window is available to the operator. Failure by operator to start-up the Calendar section on Crawl or 'Hold to run' within the 'permit' period will result in cancellation of the window, and require this prestart sequence initiation again. With Calendar safety gates OPEN, an alarm will operate audibly and visually for 2 seconds and visually only, for a further 2 seconds, prior to a 5 second 'permit to start' window being available to the operator. Only the 'hold to run' function will be available to the operator. Crawl and Run functions will both be disabled. Attempting to operate these functions will result in cancellation of the 'permit to run ' window, and require this 'prestart' sequence initiation again. An operator s indicator will function as above. Failure by operator to start-up the Calendar section within the 'permit' period will result in cancellation as above. ALL 'prestart' timers will be safety monitored, as per MPS requirement. This prestart system shall operate to Category 2 according to EN (SIL 1 according to EN61508) Overspeed of Crawl, Run, Maximum m/c speed, and non-retained, 'hold to run (forward and reverse ' if applicable), Calendar section surface speeds will be safety monitored. Any Overspeed detected will shut down the Calendar in a safe manner. Overspeed 'threshold' settings will be set on commissioning, due to unknown drives electromechanical factors.
29 Summary of Safety Requirements Distance Guarding will Protect Operators from coming into contact with Moving Parts Access to Protected Area is by means of a Solenoid Key Exchange System with Access only Possible When Equipment under Control is at Standstill, Main Contactor Open and Section Not Isolated. A 20 Second Pre-start alarm will Sound followed by a 5 Second Permit to start Window. All Other Machine Sections Are locked out from Starting at this time. Emergency Stop will be a Regenerative Stop until Standstill is Achieved the Power will be Removed From Drive. With Gates Open the Crawl Function is available only on Hold to run at 15 M/Min. Deviation from 15 M/Min will stop the drive. System Should be Designed to Meet SIL2 or Better
30 L1 L2 L3 PE Control Desk E-Stop Drives PLC Drive Safety PLC Key release System Spd Monitoring Motor Audiovisual Alarm
31
32
33
34 SRCS Next Steps Fully Implement Supporting Procedures Control of Contractors Software/Hardware Change Procedures Technical Training and Authority (Competence) Levels Auditing our Performance Environmental Performance Protection
Why do I need dual channel safety? Pete Archer - Product Specialist June 2018
Why do I need dual channel safety? Pete Archer - Product Specialist June 2018 To answer this, we need some basic background information. First why is safety needed? Here are 4 good reasons. 1. To Protect
More informationManaging for Liability Avoidance. (c) Lewis Bass
Managing for Liability Avoidance (c) Lewis Bass 2005 1 Staying Safe in an Automated World Keys to Automation Safety and Liability Avoidance Presented by: Lewis Bass, P.E. Mechanical, Industrial and Safety
More informationPL estimation acc. to EN ISO
PL estimation acc. to EN ISO 3849- Example calculation for an application MAC Safety / Armin Wenigenrath, January 2007 Select the suitable standard for your application Reminder: The standards and the
More informationRisk Assessment Form
Risk Assessment Form School Activity Risk Assessment conducted by: Consultation occurred with: (names & role) Description of activity being assesses Batchelor Outdoor Education Centre Artificial Climbing
More informationUltima. X Series Gas Monitor
Ultima X Series Gas Monitor Safety Manual SIL 2 Certified " The Ultima X Series Gas Monitor is qualified as an SIL 2 device under IEC 61508 and must be installed, used, and maintained in accordance with
More informationImplementing Emergency Stop Systems - Safety Considerations & Regulations A PRACTICAL GUIDE V1.0.0
Implementing Emergency Stop Systems - Safety Considerations & Regulations A PRACTICAL GUIDE V1.0.0 ~ 2 ~ This document is an informative aid only. The information and examples given are for general use
More informationRISK ASSESSMENT. White Paper.
RISK ASSESSMENT White Paper www.leuze.com White Paper RISK ASSESSMENT IN HARMONY The European Machinery Directive as well as its implementations on a national level (in Germany ProdSG and 9 ProdSV) require
More informationIPLOCA. Novel Construction Spring Plenary Session Amsterdam 5-6 April 2017
IPLOCA Novel Construction Spring Plenary Session Amsterdam 5-6 April 2017 Delta Machinery Macarten McGroder (Mac) C.Eng,MIQ.FIMQS Machinery Solutions Moerdijk Netherlands Deurne Netherlands Mombasa Kenya
More informationThe Best Use of Lockout/Tagout and Control Reliable Circuits
Session No. 565 The Best Use of Lockout/Tagout and Control Reliable Circuits Introduction L. Tyson Ross, P.E., C.S.P. Principal LJB Inc. Dayton, Ohio Anyone involved in the design, installation, operation,
More informationHazard Assessment & Control. Faculty of Veterinary Medicine
Hazard Assessment & Control Faculty of Veterinary Medicine Emergency Evacuation In the event of an emergency Primary exit is to the. Secondary exit is to the. Assembly point is at. Campus Security Emergency
More informationIS YOUR FLAP VALVE IN COMPLIANCE WITH NFPA ?
IEP Technologies 417-1 South Street, Marlborough, MA, 01752 ph 855.793.8407 fax 508.485.3115 www.ieptechnologies.com IS YOUR FLAP VALVE IN COMPLIANCE WITH NFPA 69-2014? Introduction Dust explosions can
More informationSafe Work Method Statement LRB TREE SERVICES 6 Behland St, Kearneys Spring QLD, 4350 ABN
JOB NO: PROJECT: DATE: 1/1/2018 SWMS NO: SWMS 001.1 PREPARED BY: LUKE BLINCO REVISED BY: ACTIVITY: TREE REMOVAL & PRUNING SIGNED BY: REVISION DATE: MINIMUM PERSONAL PROTECTIVE EQUIPMENT (PPE) REQUIREMENTS
More informationThe following gives a brief overview of the characteristics of the most commonly used devices.
SAFETY RELATED CONTROL SYSTEMS In a previous article we discussed the issues relating to machine safety systems focusing mainly on the PUWER regulations and risk assessments. In this issue will take this
More informationRisk Assessment Form
Risk Assessment Form School Activity Risk Assessment conducted by: Consultation occurred with: (names & role) Description of activity being assesses Batchelor Outdoor Education Centre High and Low Ropes
More information4 Staff Selection, Appraisal and Development. To prevent harm by identifying and controlling potential hazards.
OTAGO POLYTECHNIC MANAGEMENT POLICY Number: MP0403.04 Title: Hazard Management ITPNZ Standard: 4 Staff Selection, Appraisal and Development Chief Executive Approval: Approval Date: 17 Apr 12 Effective
More informationHazard Management Making your workplace safer
Hazard Management Making your workplace safer A Guide to Hazard Identification, Risk Assessment, Control and Reviewing 1 What is a hazard? A hazard is something which has the potential to harm the health,
More informationFLYING OBJECTS MANUAL HANDLING EXCESSIVE NOISE
JOB NO: PROJECT: DATE: SWMS NO: SWMS 002 PREPARED BY: Ian Hartley REVISED BY: Nick Bragg & Cameron McNeil ACTIVITY: STUMP REMOVAL SUPERVISED BY: REVISION DATE: April 2016 MINIMUM PERSONAL PROTECTIVE EQUIPMENT
More informationCodex Seven HACCP Principles. (Hazard Identification, Risk Assessment & Management)
Codex Seven HACCP Principles (Hazard Identification, Risk Assessment & Management) Logic sequence for application of HACCP Assemble the HACCP team Describe product Identify intended use Construct a flow
More informationElements of a Lockout/Tagout Program OSHA
September 15, 2015 Elements of a Lockout/Tagout Program OSHA 1910.147 Dayna Noble Industrial Safety Consultant Specialist Ohio BWC 567-204-8917 Dayna.noble@bwc.state.oh.us Top 10 most frequently cited
More informationIntroduction to Machine Safety Standards
Introduction to Machine Safety Standards Jon Riemer Solution Architect Safety & Security Functional Safety Engineer (TÜV Rheinland) Cyber Security Specialist (TÜV Rheinland) Agenda Understand the big picture
More informationWork Health and Safety Risk Management Procedures
Work Health and Safety Risk Management Procedures Table of Contents 1. Governing Policy 2. Purpose 3. Scope 4. Definitions 5. Responsibilities 6. Risk Management Process 6.1. Process summary 6.2. Hazard
More informationSEMS II: BSEE should focus on eliminating human error
SEMS II: BSEE should focus on eliminating human error How US companies can prevent accidents on start-ups and shut-downs by using valve interlocks The proposed changes to BSEE s SEMS (Safety and Environmental
More informationSafe High Pressure Water Washing (HPWW) Requirement
Safe High Pressure Water Washing (HPWW) Requirement Index Page Introduction 3 Flow chart of process steps 4-5 Responsibilities 6 Risk assessment process 7-9 Job safety analyses considerations 10-11 Compliance
More informationPartial Stroke Testing. A.F.M. Prins
Partial Stroke Testing A.F.M. Prins Partial Stroke Testing PST in a safety related system. As a supplier we have a responsibility to our clients. What do they want, and what do they really need? I like
More informationTo comply with the OHS Act, the responsible manager must carry out and document the following:
Owner: Manager Health, Wellbeing and Safety Last Update: 10 January 2018 Contents 1. Purpose... 1 2. Minimum Compliance Requirements... 1 3. Definitions... 2 4. Legislative requirements under the OHS Act
More informationHAZARD IDENTIFICATION & RISK ASSESSMENT
Clearheart Construction Co., Inc. Hazard Identification & Risk Assessment HAZARD IDENTIFICATION & RISK ASSESSMENT If all employees and subcontractors followed established OSHA compliant procedures to accomplish
More informationSession: 14 SIL or PL? What is the difference?
Session: 14 SIL or PL? What is the difference? Stewart Robinson MIET MInstMC Consultant Engineer, Pilz Automation Technology UK Ltd. EN ISO 13849-1 and EN 6061 Having two different standards for safety
More informationWorkshop Functional Safety
Workshop Functional Safety Nieuwegein 12 March 2014 Workshop Functional Safety VDMA 4315 Part 1 page 1 Agenda VDMA Working Group on Functional Safety Functional Safety and Safety Lifecycle Functional Safety
More informationSolenoid Valves used in Safety Instrumented Systems
I&M V9629R1 Solenoid Valves used in Safety Instrumented Systems Operating Manual in accordance with IEC 61508 ASCO Valves Page 1 of 7 Table of Contents 1 Introduction...3 1.1 Terms and Abbreviations...3
More informationThis document provides guidance to conducting health and safety inspections at the University, to ensure Hazards are identified and controlled.
Health and Safety Guideline: HSG 10.1 Health and Safety Inspections and Testing 1. Purpose This document provides guidance to conducting health and safety inspections at the University, to ensure Hazards
More informationPermit-Required Confined Space Entry Program
Safety & Health Program Permit-Required Confined Space Entry Program General Company Policy 10627 Midwest Industrial Boulevard, St. Louis, MO Phone: 314-785-6425 Fax: 314-785-6426 The purpose of this program
More informationBhadwasi Gypsum Mine, Rajasthan State Mines & Minerals Limited CHAPTER VII Additional studies
Bhadwasi Gypsum Mine, Rajasthan State & Minerals Limited 7.0.0 CHAPTER VII Additional studies 7.3.0 Risk assessment and safety management Plan: 7.3.1 Risk assessment has been done covering following aspects:
More informationLockout/Tagout Program
Lockout/Tagout Program Control of Hazardous Energy Subpart J - 29 CFR 1910.147 29 CFR 1926.417 OSHA Standard All industries must comply Estimated to prevent Approximately 120 fatalities per year 28,000
More informationRisk Assessment Form
Risk Assessment Form School Activity Risk Assessment conducted by: Consultation occurred with: (names & role) Description of activity being assesses Batchelor Outdoor Education Centre Bush Walking Michelle
More informationCT433 - Machine Safety
Rockwell Automation On The Move May 16-17 2018 Milwaukee, WI CT433 - Machine Safety Performance Level Selection and Design Realization Jon Riemer Solution Architect Safety & Security Functional Safety
More informationDefinition of Safety Integrity Levels and the Influence of Assumptions, Methods and Principles Used
Definition of Safety Integrity Levels and the Influence of Assumptions, Methods and Principles Used H. Schäbe TÜV InterTraffic, Am Grauen Stein, 51105 Köln, Germany 1 Introduction Methods for derivation
More informationb
Empirically Derived Breaking Strengths for Basket Hitches and Wrap Three Pull Two Webbing Anchors Thomas Evans a and Aaron Stavens b a Montana State University, Department of Earth Sciences, PO Box 173480,
More informationNew Thinking in Control Reliability
Doug Nix, A.Sc.T. Compliance InSight Consulting Inc. New Thinking in Control Reliability Or Your Next Big Headache www.machinerysafety101.com (519) 729-5704 Control Reliability Burning Questions from the
More informationESSENTIAL SAFETY RESOURCES
ESSENTIAL SAFETY RESOURCES GS-3018 HAZARD IDENTIFICATION AND RISK ASSESSMENT Originator: Safety Advisor s Signature: Type Name Approval: HSE Manager s Signature: Type Name Approval: Operations Manager
More informationSharing practice: OEM prescribed maintenance. Peter Kohler / Andy Webb
Sharing practice: OEM prescribed maintenance Peter Kohler / Andy Webb Overview 1. OEM introduction 2. OEM maintenance: pros and cons 3. OEM maintenance: key message 4. Tools to help 5. Example 6. Takeaway
More informationIsolate/Lock off? Learning's/objectives of today: - Improve the safety standard for employees working on machinery.
Isolate/Lock off? Learning's/objectives of today: - Improve the safety standard for employees working on machinery. Why do we need to do this? - As we further improve health and safety on site, our ways
More informationSafety in pneumatic automation
Safety in pneumatic automation Pharm connect congress 2014 Budapest Feb. 26. 27. Thomas Schulz Head of ISM and KAM Biotech/Pharma Phone: +49-711/347-52192 Mail: thss@de.festo.com Thomas Schulz / CP-KB
More informationPLANT RISK ASSESSMENT REPORT
PLANT RISK ASSESSMENT REPORT SECTION 1: PLANT IDENTIFICATION Report Number: 407/201-03 Assessment Date: 5 th June 2012 Company: Wacker Neuson Plant Type: Twin Drum Rollers Assessment Purpose: Operational
More informationCOMPLETION OF PROCEDURE ASSESSMENT FORM (COSHH RELATED) GUIDANCE NOTES (Version 3)
COMPLETION OF PROCEDURE ASSESSMENT FORM (COSHH RELATED) GUIDANCE NOTES (Version 3) The following guidance notes accompany the College Procedure Assessment form (COSHH-related). Please complete all applicable
More informationIdentify Hazards, Before They Identify You! ~Jayson Stoddard~
2015 Mine Safety Welcome! Identify Hazards, Before They Identify You! ~Jayson Stoddard~ Working Together to Achieve 0 Incidents Report All Incidents This would be any and all injuries as well as near miss
More informationAccident Investigation and Hazard Analysis
Accident Investigation and Hazard Analysis June 18, 2015 Objectives: Accident Investigation Define accidents Review why accident investigations are important Review the purpose of accident investigations
More informationb
Empirically Derived Breaking Strengths for Basket Hitches and Wrap Three Pull Two Webbing Anchors Thomas Evans a and Aaron Stavens b a Montana State University, Department of Earth Sciences, PO Box 173480,
More informationProposal title: Biogas robust processing with combined catalytic reformer and trap. Acronym: BioRobur
Proposal title: Biogas robust processing with combined catalytic reformer and trap Acronym: BioRobur Initiative: Fuel Cells and Hydrogen Joint Undertaking (FCH-JU) Funding scheme: Collaborative project
More informationMP15 Jockey Pump Controller
Setup and Operating Instructions MP15 Jockey Pump Controller This manual provides general information, installation, operation, maintenance, and system setup information for Metron Model MP15 Jockey Pump
More informationPermit-Required Confined Spaces...29CFR
(Compliance Audit) Section (c) General Requirements 1) Has the employer performed a workplace inspection to determine if there are Yes No NA permit-required confined spaces (PRCS) present? 2) If the workplace
More informationAnnual Inspection Came &
Annual Inspection Came & Company @ Marchwood under 12's Play Area,,,,, t: 01202 590675 f: 0870 428 3942 e: info@playinspections.co.uk w: www.playinspections.co.uk Risk Assessment Matrix Probability>> 5
More informationCIRCUIT BREAKER TESTING - JOB SAFETY ANALYSIS
Title: Circuit Breaker Testing Purpose and Scope: Provide guidelines for testing of Circuit Breakers. Staffing Resources: Staff will have the minimum requirement of an Electrical Fitter/Mechanic Licence
More informationHazardous Energy Control
Lockout Tagout This program has been prepared to provide assistance in compliance with USA OSHA standards and/or Best Management Practices. It should not be used without consideration of the unique conditions
More informationManagement of risk. Definition of terms. Managing risks. Risk
Definition of terms Risk Management of risk Risk is the possibility that harm (death, injury or illness) might occur when exposed to a hazard. A hazard is anything with the potential to cause injury or
More informationThe IEC61508 Operators' hymn sheet
The IEC61508 Operators' hymn sheet A few key points for those Operators of plant or equipment that involve SIL rated safety functions*, trips or interlocks by The 61508 Association SAFETY INSTRUMENTED
More informationLockout. HealthandSafetyOntario.ca. What is Lockout? How is a Lockout Done? Why is a Lockout Necessary?
What is Lockout? Lockout means to physically neutralize all energies in a piece of equipment before beginning any maintenance or repair work. Lockouts generally involve: Stopping all energy flows (for
More informationDrain Splash Back Burns Operator
Purpose To share lessons learned gained from incident investigations through a small group discussion method format. To understand lessons learned through a Systems of Safety viewpoint. This material was
More informationA study on the relation between safety analysis process and system engineering process of train control system
A study on the relation between safety analysis process and system engineering process of train control system Abstract - In this paper, the relationship between system engineering lifecycle and safety
More informationHealth and Safety Inspection Procedure
Template v4 WILTSHIRE POLICE FORCE PROCEDURE Health and Safety Inspection Procedure Effective from: 25.03.2012 Last Review Date: 10.05.2015 Version: 2.0 Next Review Date: 10.05.2018 TABLE OF CONTENTS PROCEDURE
More informationAccidents and accident prevention
Accidents and accident prevention What is an accident? 1. Oxford Dictionary An unforeseeable event often resulting in injury. 2. British Safety Council A management error; the result of errors or omissions
More informationProcedure: Work health and safety hazard management
Procedure: Work health and safety hazard management Purpose This procedure describes how the Australian National University (ANU) manages Work Health Safety hazards for the health, safety, rehabilitation
More informationCopeland Discus with CoreSense Diagnostics January 2011
Copeland Discus with CoreSense Diagnostics January 2011 Slide 1 1/27/2011 5:48 PM Discus with CoreSense Diagnostics Case Studies Supermarket In Columbus, Ohio Saves $4,500 With Discus with CoreSense Diagnostics
More informationHazard Identification
Hazard Identification Most important stage of Risk Assessment Process 35+ Techniques Quantitative / Qualitative Failure Modes and Effects Analysis FMEA Energy Analysis Hazard and Operability Studies HAZOP
More informationUsing LOPA for Other Applications
10 Using LOPA for Other Applications 10.1. Purpose LOPA is a tool used to perform risk assessments. Previous chapters described its use in assessing the risk level of process hazards scenarios and in evaluating
More informationLockout Tagout Policy
Office of Environmental Health & Safety www.moreheadstate.edu/ehs 606-783-2584 Lockout Tagout Policy PURPOSE To establish procedures for the de-energization and isolation of energy sources or the lockout
More informationCOMMON MISUNDERSTANDINGS ABOUT THE PRACTICAL APPLICATION OF IEC 61508
COMMON MISUNDERSTANDINGS ABOUT THE PRACTICAL APPLICATION OF IEC 61508 Helen Pearce, James Catmur and Geoff Stevens The use of IEC 61508 for determination of the Safety Integrity Level (SIL) of Safety Interlock
More informationPLANNED LIGHTING MAINTENANCE LTD METHOD STATEMENT & RISK ASSESSMENT REPLACEMENT OF LAMPS OR REPAIRS TO HIGH LEVEL LIGHT UNITS
PLANNED LIGHTING MAINTENANCE LTD METHOD STATEMENT & RISK ASSESSMENT REPLACEMENT OF LAMPS OR REPAIRS TO HIGH LEVEL LIGHT UNITS Project: (insert Client) Replacement/ Repair of high level light units/ high
More informationPrevention of Falls and Working at Heights
Workplace Safety Schools Cleaning Prevention of Falls and Working at Heights It is the policy of the Company to avoid working at heights above 2 metres wherever practical. When avoidance is not an option,
More informationScope: This plan applies to all personnel, including contractors, who enter or work in confined spaces, or supervise such activities.
11/13/1995 4 5/20/2013 1 of 10 Authority and Scope Regulation: 29 CFR 1910.146 Scope: This plan applies to all personnel, including contractors, who enter or work in confined spaces, or supervise such
More informationA Checklist for a Health and Safety Risk Assessment
A Checklist for a Health and Safety Risk Assessment Business Information Factsheet BIF376 July 2016 Introduction All employers, and certain self-employed workers and contractors, are required to assess
More informationSession 2: Machine Safety in Hazardous Areas
Session 2: Machine Safety in Hazardous Areas Ross De Rango Hazardous Area Systems Manager NHP Electrical Engineering Pty Ltd Introduction Icarus, Daedalus, and risk management The ancient Greek story of
More information2523-LDG-E. Leader s Guide
2523-LDG-E LOCKOUT/TAGOUT TRAINING FOR EMPLOYEES Leader s Guide 2008 ERI Safety Videos LOCKOUT/TAGOUT TRAINING FOR EMPLOYEES This easy-to-use Leader s Guide is provided to assist in conducting a successful
More informationHAZARD RECOGNITION EVALUATION & CONTROL. Procedure No. HR-405-PR-2 Division Human Resources. Supersedes n/a Board Policy Ref.
COLLEGE OF THE NORTH ATLANTIC OPERATIONAL PROCEDURE TOPIC: HAZARD RECOGNITION EVALUATION & CONTROL Procedure No. Division Human Resources Supersedes n/a Board Policy Ref. GP-GR-805 Related Policy HR-405
More informationAbseiling Risk Management Plan Lutanda Yarramundi
Abseiling Risk Management Plan Lutanda Yarramundi School: Year: Dates: Program: Supervising Staff: Activity Context Abseiling at Lutanda Yarramundi is located on the activity tower on the wall facing the
More informationSafe Work Method Statement
Title Skid Steer Operation (Bobcat) SWMS No. 14 Authorized and email Signed by the (Managing Director / CEO / Partner / Proprietor) on Date 01/08 /2016 Safe Work Procedure for the Work:- Yes No Employees
More informationIntegrating Safety and Automation
866-522-2300 / www.asesafety.com Integrating Safety and Automation Presented by: Dennis Aulbrook Safeguarding of Automated Machinery A safeguard is a solution or a combination of solutions that eliminate
More informationLOCKOUT SYSTEM AND POLICIES
LOCKOUT SYSTEM AND POLICIES Lockout System Purpose Employees health and safety takes top priority. Isolating hazardous energy to prevent sudden and unexpected energisation of machines, equipment, and processes
More informationTelco Antennas SWMS Working At Height Above 2m
Telco Antennas SWMS Working At Height Above 2m A SWMS shall be developed for a task where the risk has been assessed as Medium or Higher Division: Date: SWMS No: (e.g. Installation, Engineering Workshop)
More informationUser Information Sheet 015
User Information Sheet 015 Formerly LPGA Guidance NO.84 March 2007 Inspection and Maintenance of LPG Pipework at Commercial and Industrial Premises 1. Introduction LPG pipework may, under certain conditions,
More informationRock Climbing Risk Management Plan Lutanda Yarramundi
Rock Climbing Risk Management Plan Lutanda Yarramundi School: Year: Dates: Program: Supervising Staff: Activity Context The rock climbing wall at Lutanda Yarramundi is located next on the side of the Activity
More informationRisk Management Guide
What is health and safety risk management? Risk Management Guide Risk Management is a proactive, logical and systematic approach of managing the uncertainty relating to potential risk, rather than responding
More informationAnnual Inspection. Boddington Parish Council. Boddington Village Hall Play Area. Warwick Road, Upper Boddington, Northamptonshire, NN11 6DH
Annual Inspection Boddington Parish Council Boddington Village Hall Play Area Warwick Road, Upper Boddington, Northamptonshire, NN11 6DH Risk Assessment Matrix Probability>> 5 Very High VL L M H VH 4 High
More informationEngineering Safety into the Design
Engineering safety into the design Peter Scantlebury P.Eng Technical Safety Manager Amec Foster Wheeler, Oil & Gas Canada Abstract Safety by design is Amec Foster Wheeler s systematic approach to engineering
More informationLockout/Tagout. Page. Introduction. Purpose. 2 Background. 2 Who s Covered?... 3 Responsibilities. 3 Explanation of Key Terms. 4.
Lockout/Tagout Page Introduction Purpose. 2 Background. 2 Who s Covered?... 3 Responsibilities. 3 Explanation of Key Terms. 4 How It Works General Lockout/Tagout Procedure. 5 General Lock/Tag Removal Procedure.
More informationQUANTIFYING THE TOLERABILITY OF POTENTIAL IGNITION SOURCES FROM UNCERTIFIED MECHANICAL EQUIPMENT INSTALLED IN HAZARDOUS AREAS
QUANTIFYING THE TOLERABILITY OF POTENTIAL IGNITION SOURCES FROM UNCERTIFIED MECHANICAL EQUIPMENT INSTALLED IN HAZARDOUS AREAS Steve Sherwen Senior Consultant, ABB Engineering Services, Daresbury Park,
More informationGuidelines on Surveys for Dynamic Positioning System
Guidelines on Surveys for Dynamic Positioning System (2002) BEIJING 1 CONTENTS Chapter 1 GENERAL 1.1 General requirements 1.2 Class notation 1.3 Definitions 1.4 Plans and documents 1.5 Failure mode and
More informationCOMMISSIONING TESTS FOR NEW HV CABLES (UP TO 33 KV) JOB SAFETY ANALYSIS
COMMISSIONING TESTS FOR NEW HV CABES (UP TO 33 KV) JOB SAFETY ANAYSIS Title: Carry Out Field Testing Purpose and Scope: To identify the hazards and control measures associated with testing and commissioning
More informationHazardous Waste Training Plan. Supersedes: 02/15/16 (Rev.02) Preparer: Owner: Approver: EHS Team Member EHS Team Member EHS Manager
Procedure No.: PA-033-0006 Page: 1 of 19 Port Arthur, TX. Reviewed: 02/18 Effective: 02/06/18 (Rev.03) Supersedes: 02/15/16 Preparer: Owner: Approver: EHS Team Member EHS Team Member EHS Manager Document
More informationImplementing IEC Standards for Safety Instrumented Systems
Implementing IEC Standards for Safety Instrumented Systems ABHAY THODGE TUV Certificate: PFSE-06-607 INVENSYS OPERATIONS MANAGEMENT What is a Safety Instrumented System (SIS)? An SIS is designed to: respond
More informationinnova-ve entrepreneurial global 1
www.utm.my innova-ve entrepreneurial global Safety Integrity Level (SIL) is defined as: Relative level of risk-reduction provided by a safety function to specify a target level of risk reduction. SIL is
More informationCONFINED SPACE WRITTEN PROGRAM
CONFINED SPACE WRITTEN PROGRAM Maple River Public Schools ISD#2135 Confined Space Entry Plan (Permit Required) Maple River Public School Plan last updated: October, 2014 Authority and Scope Regulation:
More informationSAINT MARY S COLLEGE OF CALIFORNIA STANDARD HAZARDOUS ENERGY CONTROL PROGRAM INCLUDING LOCKOUT/TAGOUT. Prepared by
SAINT MARY S COLLEGE OF CALIFORNIA STANDARD 1.1.4 HAZARDOUS ENERGY CONTROL PROGRAM INCLUDING LOCKOUT/TAGOUT Prepared by SAINT MARY S COLLEGE OF CA MORAGA, California KAREN LAURICELLA Original Date: 1 JULY
More informationConducting An Effective. Welcome!
Conducting An Effective An introduction to the Five Step Process of Job Hazard Analysis JHA-JSA-SWMS-AHA Introductions Welcome! What do you know about Job Hazard Analysis (JHA s)? Does OSHA require JHA
More informationImpact on People. A minor injury with no permanent health damage
Practical Experience of applying Layer of Protection Analysis For Safety Instrumented Systems (SIS) to comply with IEC 61511. Richard Gowland. Director European Process Safety Centre. (Rtgowland@aol.com,
More informationUnderstanding safety life cycles
Understanding safety life cycles IEC/EN 61508 is the basis for the specification, design, and operation of safety instrumented systems (SIS) Fast Forward: IEC/EN 61508 standards need to be implemented
More informationEvery things under control High-Integrity Pressure Protection System (HIPPS)
Every things under control www.adico.co info@adico.co Table Of Contents 1. Introduction... 2 2. Standards... 3 3. HIPPS vs Emergency Shut Down... 4 4. Safety Requirement Specification... 4 5. Device Integrity
More informationSpiratec ST14, ST16 and ST17 Sensor Chambers and sensors
0862050/1 IM-P086-18 MI Issue 1 Spiratec ST14, ST16 and ST17 Sensor Chambers and sensors Installation and Maintenance Instructions 1. Safety Information 2. General product information 3. Installation 4.
More informationAnnual Inspection. Mid Suffolk District Council. Beyton. The Green, Suffolk, IP30 9AF
Annual Inspection Mid Suffolk District Council Beyton The Green, Suffolk, IP30 9AF Risk Assessment Matrix Probability>> 5 Very High VL L M H VH 4 High VL L M H H 3 Moderate VL L L M M 2 Low VL L L L L
More informationControl of Hazardous Energy. Environmental Health and Safety
Control of Hazardous Energy Environmental Health and Safety 11/01/2014 1 CONTROL OF HAZARDOUS ENERGY (LOCKOUT-TAGOUT) OSHA CFR 1910.147 Revised Date: November 2014 STATEMENT OF POLICY Ball State University
More informationBogo Operations Pollution Incident Response Management Plan
Bogo Operations Pollution Incident Response Management Plan Rhyolite Hard Rock Aggregate Quarry 134 Paynes Road BOOKHAM NSW 2582 PO Box 426 COWRA NSW 2794 p: 02 6227 7260 p: 02 6345 4253 e: info@bogoquarry.com.au
More information