Monitoring for Transient Pressures in Pipelines. By Will Worthington, P.E. 1

Size: px
Start display at page:

Download "Monitoring for Transient Pressures in Pipelines. By Will Worthington, P.E. 1"

Transcription

1 From Proceedings of the Pipeline Division Specialty Conference, American Society of Civil Engineers Houston, TX, August 21 24, 2005 Monitoring for Transient Pressures in Pipelines By Will Worthington, P.E. 1 Abstract A change in the flow rate in a full pipeline will cause a change in the pressure within that pipeline. These changes are given careful attention in the well-designed pipeline; however, in the past it has been difficult to accurately measure these transient pressures after the pipeline is constructed and placed in service. Transient pressures exceeding the structural strength of the pipeline will cause damage in the form of rupture or, as is more frequently the case, in the form of latent damage that results in failure at a later date. Advances in digital data processing systems have significantly improved our ability to continuously monitor and record even the very-short waterhammer event. These improvements have facilitated monitoring for transient pressures under a wide variety of circumstances. Early detection of damaging transient pressure events is now more practicable, thus permitting the reduction of damage to pipelines resulting from these events. Introduction Pipeline failures are occasionally traced directly to the occurrence of transient pressures that have caused damage. Among the more familiar ruptures in this category are the failures in Dallas, TX; San Juan, Puerto Rico; Metropolitan Water District of Southern California; Houston, TX, Oigawa Penstock, Japan; and Bartlett Dam, AZ. The last mentioned caused catastrophic rupture at the outlet of the hydro generator, with fatal injuries to the operator. Countless other failures are believed to have resulted from transient pressures, but the evidence is not conclusive. In many cases the transient pressure events occurred repeatedly without detection prior to the failure. This paper will briefly describe the causes of transient pressures and improvements in tools available to detect transient pressures. It will conclude with suggestions to civil engineers and pipeline owners regarding what we can do to reduce damages from transient pressures President, Pipetech International and Pipeline Technologies, Inc.; North Mule Train Road, Carefree, AZ, ; phone ; worthington@earthlink.net

2 Figure 1 Transient-caused failure, Superaqueduct of Puerto Rico A transient pressure in a pipeline is a generic term for a wave phenomenon that accompanies a sudden change of the velocity of the fluid in the pipeline. Authors variously use the term surge pressure to denote a transient pressure that has no detrimental effect, whereas the term waterhammer may be used to denote a transient pressure that will have serious consequences if not properly addressed and mitigated. Pressure transients can be positive or negative. The magnitude of these surges is independent of the operating pressure, and can be many times normal operating pressure. Any event that causes a sudden change in the velocity of fluid in a pipeline will generate a transient pressure. The most common sources of transient pressures are Pump operation Pump power failure Control valve operation Sudden changes in demand Air release valve operation Pressure reducing valve operation Pipeline rupture Filter flushing operations Most transient pressures are repetitive and predictable. Examples include opening and closing an in-line valve, starting and stopping a pump, and operation of an air relief valve. Because these transients are predictable, they are readily accommodated in the pipeline design. A variety of methods are available to mitigate transient pressures, generally falling into three categories alteration of pipeline profile and diameter, valve and pump control procedures, and surge control devices. For instance, a main-line butterfly valve may be designed to close over a period of minutes to minimize the transient. Pump motors are designed to start against a closed valve, and that valve is gradually opened to minimize the transient pressure. Combination air valves are included in the pipeline design to discharge accumulated air pockets and to minimize the effects of negative pressures. Care is taken in the selection of the proper orifice size for air valves, - 2 -

3 to avoid the damaging air slam that may result from an improperly designed air valve, causing a transient pressure as much as 500 times the pressure before the slam. Often the most severe transient will be the sudden power outage in a pumped pipeline system, which will cause the abrupt cessation of flow in the pipeline and a large transient pressure. When this scenario results in cavitation within the pipeline, true waterhammer events may be generated that are very brief but very damaging. Hydraulic engineers have long understood the transient pressure phenomena and surge wave theory, and the pipeline designer will accommodate these events in the design. Great strides in hydraulic modeling have significantly facilitated the analysis of complex pipeline systems and the propagation of transients. Some transient pressures are the result of an abnormal and unpredicted condition, and they are not so readily accommodated in the pipeline design. These transients may also be more difficult to detect and measure. Several examples from case studies include improper installation of valve actuators during construction, improper placement of combination air valves, installation of unstable pressure relief valves, and the installation of unanticipated water diversion flows by pipeline customers. Figure 2 Surge Event Physical Model, Advantica Some transients are cyclic in nature, for example those caused by unstable pressure reducing valves, unsuitable pressure-relief valves, and reciprocating pumps. These transients may cause fatigue damage and should be eliminated or reduced to nondamaging pressure changes. Figure 3 is a pressure reduction valve that proved to be unstable at certain flows. It is imperative that these pressures be measured to assure design pressures are not exceeded

4 Figure 3 Pressure Reduction Valve So a strong case can be made for monitoring pressures carefully whether it is on a continuous basis, or in response to some particular need. Even the most rigorously modeled pipeline would warrant carefully monitoring of pressures immediately after construction if for no other reason than to confirm that it was built according to the designer s intent. Traditional Pressure Measurement Methods The most traditional method of method of measuring and recording transient pressures is a dial gage and a notebook. Figure 4 Typical pressure gauge with no negative pressure capability - 4 -

5 Mechanical pen-and-chart recorders have been in use for decades, and offer a good solution to many pressure-recording needs. They are relatively inexpensive, easy to use and continuously monitor all pressures. The disadvantages of the mechanical recorders are that they need to be manually reviewed and the charts need to be changed every day or every few days, are not typically designed for negative pressures, and they are not capable of providing detailed information on the duration of a transient since the width of the line drawn by the pen may cover up to 60 seconds of time. Figure 5 Circular graph recorder, with no negative pressure capability Several portable high-speed electronic data loggers are available. These do record negative pressures, and if set to record frequently enough can record the details of a specific surge event over a period of seconds to minutes. So if you know when the transient will occur and can set the data-recording rate accordingly, and can upload the data from storage immediately after the event, these devices may fulfill the need. Data recording intervals of 0.05 seconds (20 Hz) are available. Figure 6 Digital data logger for pressure measurement - 5 -

6 On the other hand, if there is a need to monitor over longer periods of time, the data interval will have to be set at a longer interval to stay within the memory capacity of the device. An interval of once per minute might be selected, which would provide 1440 pressure readings per day. Surely this would convince a pipeline owner that the pressure is rigorously and carefully monitored. But is this sufficient? Not necessarily, because many of the most damaging transients may last only a fraction of a second, and would not be detected at all. It has been difficult to detect and measure an unexpected transient that may last a fraction of a second, and that may be 100 times the operating pressure or more. Not only are these events difficult to detect, they may be the most damaging of all and may go unnoticed for long periods of time. Mathematicians will recognize this as the Nyquist principle. Figure 7 Digital data collection with insufficient sample rate A New Method of Pressure Measurement Within the last year, a system has been devised that overcomes several of the limitations of previous systems. It is capable of monitoring over extended period of time in a snoozing mode, recording background pressure at a user-set interval between once per second and once per day. Although the system appears to be snoozing, in reality it is very busy. It continuously samples the pressure 1000 times per second and computes a running average. Effectively the system algorithm has a built-in alarm clock that goes off when a pressure is detected that differs significantly from the average in other words when a transient is detected. When this occurs, the system wakes up and records all data at another user-set rate up to 100 Hz. This continues until the transient has passed, - 6 -

7 at which time the system goes back to the snoozing mode. The scheme is shown graphically in the figure below. Figure 8 The TP1 Transient Pressure Monitoring System algorithm The so-called TP-1 Transient Pressure Monitoring System is comprised of the following components: Personal Digital Assistant (PDA) TP1 Controller Communications Sensors Data Analysis Programs A Pocket PC PDA is the primary device for the user interaction. A laptop with a WiFi card can also be used. (Any desktop or laptop on a wired LAN can also be used, if the Controller is connected to the LAN.) The Controller processes all of the input signals, and performs all of the logic in the system. It also stores all of the historical data until it is retrieved using the PDA. WiFi is the primary communications mechanism. (A wired LAN can also be used.) Depending on the operating mode, 1 or 2 pressure sensors are used to measure the pressure in the pipe. PC programs that retrieve the stored data files from the PDA, and convert and display the data. The data is also stored in a database for analysis by other programs

8 Figure 9 TP1 Transient Pressure Monitoring System components The TP-1 has been under development for nearly 2 years, undergoing extensive bench testing and modification. One of the early examples of data recorded with the TP- 1 include the acceptance testing of a new Wastewater Treatment by the City of Glendale, AZ. They had experienced the rupture of several 8 (20.3 cm) ductile iron pipes in the course of testing, and had attempted to diagnose the problem with a chart recorder. The test data from the chart was not very revealing. Figure 10 Circular graph of sewage lift station discharge pressure - 8 -

9 They asked to install my demonstration model of the TP-1 to see if it could detect the transients at the discharge line of the lift pump station. Figure 11 TP1 installed at sewage lift station The results were such that when the City Engineer visited during the TP1 demonstration, his remark was Will, I m sorry, but I will not let you remove that system from City property. Send me a bill

10 Figure 12 TP1 graphic depiction of the lift station pump shutdown sequence pressure (Note negative pressures to psi) The data collected at the sewage lift station showed negative pressures approaching the cavitation range during the pump shutdown sequence. The system allowed the careful evaluation of surge reduction measures, and continues to monitor the dynamic pressures at this $30 million facility during its early months of operation as this is written. Reducing Transient Pressure Damage So, what can we do with this new technology? I suggest this technology opens the door to several testing programs that would benefit owners and engineers alike. And for the sake of discussion, I share the following observations and ideas: Who should require the testing? The transient pressure monitoring system is not difficult to learn to use. The system is available for lease or purchase from the developer. An hour of demonstration and a few hours getting familiar with the operation manual will be sufficient for an operator to learn to conduct valid tests. Whoever performs the testing should be familiar with the transients that might be expected in the pipeline, as there are several user-set parameters that will need to be tailored to the pipeline system. These parties might have a vested interest in having the test performed, and require the test The owner of the pipeline system The ENGINEER or hydraulic designer The contractor who constructs a new pipeline A manufacturer of critical components of pipelines, such as manufacturers of the pipe itself, control valves, valve actuators, and pressure tanks The testing could be done by any of the above parties, or it could be a third-party engineering firm. The advantage of third-party testing is gaining popularity in construction contracts because of the independent, unbiased nature of the test results. What testing should be done? The testing should be of sufficient detail to permit the detection and recording of the shortest duration and highest pressures that are reasonably characteristic of the pipeline system. For an acceptance test of a new facility constructed in a design-bid-build delivery system, I suggest a clause in the construction specification that might read, in so many words: o Hydrodynamic Pressure monitoring - The CONTRACTOR shall engage the services of a THIRD-PARTY ENGINEERING FIRM to conduct pressure monitoring of the pipeline at the points designated below. The pressure monitoring shall be continuous during the initial filling of the pipeline, and throughout the acceptance test, and for period of 30 days following substantial completion of the project. Pressure shall be recorded not less

11 frequently than once every minute throughout this period, except that any transient pressures shall be recorded not less than 50 times per second. A transient shall be defined as any sudden departure of more than 10 psi from the running 5-second average pressure. The THIRD-PARTY ENGINEERING FIRM shall submit interim reports following initial filling, and following the simulated power failure of the XYZ pumping plant; and a final report of all recorded pressures in graphic and tabular form. The graphic presentation shall depict a separate graph for each recorded transient in sufficient detail to observe each data point. The report shall compare the recorded pressures to the design pressures specified by the ENGINEER. The final report shall include calibration curves for the pressure transducers used in the test before the initiation of testing and upon completion of testing, and a certification that the equipment used is capable of meeting the requirements of this paragraph, and shall be sealed by a registered engineer. One copy of the final report shall be submitted to each the CONTRACTOR, the OWNER, and the ENGINEER. Points to be tested are: Pumping station discharge line at station + Combination air valves located at stations +, +, and + Butterfly valves located at stations + and + For new facilities constructed in design-build delivery systems, I suggest a similar clause should be included in the contract between the owner and the builder. Maintenance testing should be performed to the same criteria, and should be recorded for future reference. Where should this monitoring be done? The hydraulic designer should specify which points are most critical. Depending on the hydraulics of the system, these points might include: For a new pipeline, at multiple points such as pump discharge lines, on both sides of control valves, and at selected air release valves. On any new delivery lines near the connection to an existing line At selected air release valves following maintenance and during refill if the pipeline has been emptied At other locations identified by the hydraulic designer as being particularly prone to transient pressures When should transient pressure monitoring take place? Transient pressure monitoring should be accomplished: As part of the initial acceptance test of every new pipeline, beginning with the initial fill, during all maximum performance tests including simulated power failure, and for at least 30 days of normal operation Upon the completion of any modification to an existing pipeline, such as the addition of a new delivery point, or pressure booster station

12 Upon completion of any transient pressure mitigation measures Upon completion of any significant maintenance programs, such as air valve or blowoff valve maintenance Annually, at selected critical points in a pipeline system, as part of a routine maintenance program During any periods when temperatures may cause air release valves and pressure relief valves to freeze and malfunction How should the testing be performed? The testing should be done with advanced notice to any interested parties, and with ample opportunity for them to observe the testing. There should be opportunity to review the method of performance of the equipment, to ask questions, and to observe installation and establishment of test parameters. The ENGINEER responsible for the design of new facilities should be present during the initiation and critical points in the testing. Why should this be done? To prevent failures such as those described above. To protect the interests of owners, engineers, suppliers, and contractors who are interdependent on the performance of each other to construct our vital pipeline systems. To confirm that a pipeline system is fully functional following significant maintenance activities To identify negative pressures that may result in contamination of potable water mains To identify negative pressures that may result in collapse or partial collapse of flexible pipelines To extend the useful life of our pipeline infrastructure. And finally To protect the public interest and investment. Conclusion Advances in digital technology and equipment have opened the door to improved monitoring of hydrodynamic pipeline pressures. Owners, engineers, contractors, and operators no longer need to wonder whether phantom transient pressure events are plaguing their pipeline facilities; it is possible to continuously monitor, detect and record these events. The greatest benefit of this capability may be through the implementation of a hydrodynamic pressure test, in addition to the standard hydrostatic pressure test, as part of the acceptance testing for new pipeline facilities. References Advantica, Hydraulic Transients and Surge Control in Liquid Pipelines, 5177 Richmond Ave, Houston, TX 77056;

13 American Water Works Association, Manual of Water Supply Practices M9, Concrete Pressure Pipe, American Water Works Association, Dawn of the Replacement Era Reinvesting in Drinking Water Infrastructure, May 2001 Gullick, Richard W.; Mark W. Lechevallier; Richard C. Svindland; and Melinda J. Friedman; Occurrence of Transient Low and Negative Pressures in Distribution Systems, AWWA Journal, Nov 2004, p. 52. Hughes, David M. Assessing the Future: Water Utility Infrastructure Management, AWWA, 2002 Lingireddy, Srinivasa; Don J. Wood; and Naftali Zloczower; Pressure Surges in Pipeline Systems Resulting from Air Releases; AWWA Journal, July 2004, p. 88. Martin, C. Samuel; Chapter 6 - Hydraulic Transient Design for Pipeline Systems, AWWA Water Distribution Systems Handbook, edited by Larry W. Mays, McGraw-Hill, Moser, A. P., Buried Pipe Design, McGraw-Hill, 2001 Wylie, E. Benjamin, Fluid Transients in Systems, Prentiss Hall, 1997 Wylie, E. Benjamin; and Jim C. P. Liou; Transients in Pipeline Transmission and Distribution Systems, American Society of Civil Engineers Continuing Education, Summer

Monitoring for Negative and Transient Pressures in Distribution Mains

Monitoring for Negative and Transient Pressures in Distribution Mains Monitoring for Negative and Transient Pressures in Distribution Mains Will Worthington, P.E. President Pipeline Technologies Inc. and Pipetech International Carefree, Arizona Abstract Negative pressures

More information

Journal of Applied Fluid Transients, Vol 1-1, April 2014 (3-1)

Journal of Applied Fluid Transients, Vol 1-1, April 2014 (3-1) Modeling and Field Verification Study of Air Slam Conditions on kalanit Pipeline System By Yiftach Brunner & Sathish Kumar ir valves are integral part of long water transmission mains and are essential

More information

PROVING THAT BLADDER SURGE TANKS CURED EXCESSIVE SURGE CONDITIONS IN A 30 FORCE MAIN

PROVING THAT BLADDER SURGE TANKS CURED EXCESSIVE SURGE CONDITIONS IN A 30 FORCE MAIN Background PROVING THAT BLADDER SURGE TANKS CURED EXCESSIVE SURGE CONDITIONS IN A 30 FORCE MAIN Bo, P.E., Hazen and Sawyer, P.C. Sean FitzGerald, P.E., Hazen and Sawyer, P.C. The Sanitation District No.

More information

MITIGATING PIPE AND RISER HYDRAULIC PIPELINE ISSUES WITH THE I-RISER PLUS

MITIGATING PIPE AND RISER HYDRAULIC PIPELINE ISSUES WITH THE I-RISER PLUS 24 TH July 2013 MITIGATING PIPE AND RISER HYDRAULIC PIPELINE ISSUES WITH THE I-RISER PLUS Vern Costelow Business Development Consultant AWMA Water Control Solutions INTRODUCTION Surface irrigation is still

More information

Courses of Instruction: Controlling and Monitoring of Pipelines

Courses of Instruction: Controlling and Monitoring of Pipelines Courses of Instruction: Controlling and Monitoring of Pipelines Date December 2010 Dr. Peter Eschenbacher Partner Angergraben 4 85250 Altomünster Germany Tel. +49-(0)8254 / 99 69 57 Fax +49-(0)8254 / 99

More information

Tirpur Area Water Supply Project A Report on Transient Modeling Study

Tirpur Area Water Supply Project A Report on Transient Modeling Study y February 2008 1 of 81 y INTRODUCTION: The report presents results from a transient modeling study conducted on the clear water transmission main of Tirpur Areas Water Supply Project, Tamilnadu, India.

More information

SECTION PRESSURE TESTING OF PIPING

SECTION PRESSURE TESTING OF PIPING SECTION 15044 PRESSURE TESTING OF PIPING PART 1 - GENERAL 1.01 DESCRIPTION A. Scope of Work: This section specifies the leakage and pressure testing of piping. B. Testing Records: PART 2 - PRODUCTS 2.01

More information

PRESSURE SURGES IN PIPELINES

PRESSURE SURGES IN PIPELINES CHAPTER 4 PRESSURE SURGES IN PIPELINES 4.1 FEATURES OF PRESSURE SURGE In the past, water engineers were facing problems with repeated pipe bursts, failing seals etc. They termed the cause of failure as

More information

Sizing Pulsation Dampeners Is Critical to Effectiveness

Sizing Pulsation Dampeners Is Critical to Effectiveness Sizing Pulsation Dampeners Is Critical to Effectiveness Pressure variation is an important consideration when determining the appropriate size pulsation dampener needed for an application. by David McComb,

More information

Multiple Pressure Booster Systems With Variable Speed Controller Type BL

Multiple Pressure Booster Systems With Variable Speed Controller Type BL Multiple Pressure Booster Systems With Variable Speed Controller Type BL General Characteristics - Single or multistage pumps - Horizontal or vertical mounting - Total head 30m ~ 250m - Material construction:

More information

FIRE PROTECTION. In fact, hydraulic modeling allows for infinite what if scenarios including:

FIRE PROTECTION. In fact, hydraulic modeling allows for infinite what if scenarios including: By Phil Smith, Project Manager and Chen-Hsiang Su, PE, Senior Consultant, Lincolnshire, IL, JENSEN HUGHES A hydraulic model is a computer program configured to simulate flows for a hydraulic system. The

More information

2600T Series Pressure Transmitters Plugged Impulse Line Detection Diagnostic. Pressure Measurement Engineered solutions for all applications

2600T Series Pressure Transmitters Plugged Impulse Line Detection Diagnostic. Pressure Measurement Engineered solutions for all applications Application Description AG/266PILD-EN Rev. C 2600T Series Pressure Transmitters Plugged Impulse Line Detection Diagnostic Pressure Measurement Engineered solutions for all applications Increase plant productivity

More information

Every things under control High-Integrity Pressure Protection System (HIPPS)

Every things under control High-Integrity Pressure Protection System (HIPPS) Every things under control www.adico.co info@adico.co Table Of Contents 1. Introduction... 2 2. Standards... 3 3. HIPPS vs Emergency Shut Down... 4 4. Safety Requirement Specification... 4 5. Device Integrity

More information

my SYSTEM A guide to common applications in water distribution systems

my SYSTEM A guide to common applications in water distribution systems my SYSTEM A guide to common applications in water distribution systems WWW.SINGERVALVE.COM INDEX This short guide is intended to offer guidance on some of the common problems, applications and questions

More information

Pumping Systems for Landscaping Pumps, Controls and Accessories. Mark Snyder, PE

Pumping Systems for Landscaping Pumps, Controls and Accessories. Mark Snyder, PE October 21, 2010 Pumping Systems for Landscaping Pumps, Controls and Accessories Mark Snyder, PE Pump Station Design Purpose of Pump Stations Pump stations are designed to boost water pressure from a lower

More information

Installation and operation Manual. Bermad Surge Anticipation Valve. Model No 435

Installation and operation Manual. Bermad Surge Anticipation Valve. Model No 435 Instruction manual Bermad surge anticipation manual Model No 435 Installation and operation Manual Bermad Surge Anticipation Valve Model No 435 Bermad Water Technologies Rev 0 5/05/2015 7 Inglewood Drive,

More information

MIL-STD-883G METHOD

MIL-STD-883G METHOD STEADY-STATE LIFE 1. PURPOSE. The steady-state life test is performed for the purpose of demonstrating the quality or reliability of devices subjected to the specified conditions over an extended time

More information

EVT * -Pro Electronic Valve Tester

EVT * -Pro Electronic Valve Tester GE Oil & Gas Consolidated* Pressure Relief Valves EVT * -Pro Electronic Valve Tester In-Place Testing: No Problem Manages Global Safety Standards Tests All Manufacturers Pressure relief Valves Helps to

More information

Susceptibility of Distribution Systems to Negative Pressure Transients. Presenters: Kala Fleming and Mark Le Chevallier Moderator: Jian Zhang

Susceptibility of Distribution Systems to Negative Pressure Transients. Presenters: Kala Fleming and Mark Le Chevallier Moderator: Jian Zhang Susceptibility of Distribution Systems to Negative Pressure Transients Presenters: Kala Fleming and Mark Le Chevallier Moderator: Jian Zhang Housekeeping Please mute your phone lines Type in questions

More information

Reliability of Safety-Critical Systems Chapter 3. Failures and Failure Analysis

Reliability of Safety-Critical Systems Chapter 3. Failures and Failure Analysis Reliability of Safety-Critical Systems Chapter 3. Failures and Failure Analysis Mary Ann Lundteigen and Marvin Rausand mary.a.lundteigen@ntnu.no RAMS Group Department of Production and Quality Engineering

More information

M-06 Nitrogen Generator (Nitrogen Making Machine)

M-06 Nitrogen Generator (Nitrogen Making Machine) Guideline No.M-06 (201510) M-06 Nitrogen Generator (Nitrogen Making Machine) Issued date: 20 th October, 2015 China Classification Society Foreword This Guideline is a part of CCS Rules, which contains

More information

The Future of Hydraulic Control in Water-Systems

The Future of Hydraulic Control in Water-Systems The Future of Hydraulic Control in Water-Systems A. Heimann Manager of R&D and of Technical Support & Applications Engineering departments at Dorot Automatic Control Valves Dorot Control Valves, Kibbutz

More information

Training Fees 4,000 US$ per participant for Public Training includes Materials/Handouts, tea/coffee breaks, refreshments & Buffet Lunch.

Training Fees 4,000 US$ per participant for Public Training includes Materials/Handouts, tea/coffee breaks, refreshments & Buffet Lunch. Training Title CONTROL & SAFETY RELIEF VALVES Training Duration 5 days Training Venue and Dates Control & Safety Relief Valves 5 06-10 May, 2018 $4,000 Dubai, UAE Trainings will be conducted in any of

More information

TECHNICAL DATA Q= C. Table 1 - Specifications

TECHNICAL DATA Q= C. Table 1 - Specifications September 25, 2013 Pressure Regulation 537a 1. Description The Model B-3 Pilot Operated Pressure Control Valve is a factory assembled unit. The unit consists of a Model J-2 Halar coated Flow Control Valve,

More information

SECTION 25 TESTING AND DISINFECTING WATER MAINS General

SECTION 25 TESTING AND DISINFECTING WATER MAINS General SECTION 25 TESTING AND DISINFECTING WATER MAINS 25-1.01 Scope 25-1 General This section describes the requirements for pressure and leak testing, and disinfecting of water mains and appurtenances, including

More information

SEMATECH Provisional Test Method for Pressure Cycle Testing Filter Cartridges Used in UPW Distribution Systems

SEMATECH Provisional Test Method for Pressure Cycle Testing Filter Cartridges Used in UPW Distribution Systems Provisional Test Method for Pressure Cycle Testing Filter Cartridges Used in UPW Distribution Systems Technology Transfer 92010941B-STD and the logo are registered service marks of, Inc. 1996, Inc. Provisional

More information

Engineering / Technical Section

Engineering / Technical Section TABLE OF CONTENTS Valve Dimensions...E-2 ANSI Flange Data...E-3 Performance Charts...E-4 - E-8 Cavitation Information...E-9 Metric Valve Dimensions...E-10 DIN Flange Data...E-11 - E-12 Metric Conversion

More information

CHEMICAL ENGINEERING LABORATORY CHEG 239W. Control of a Steam-Heated Mixing Tank with a Pneumatic Process Controller

CHEMICAL ENGINEERING LABORATORY CHEG 239W. Control of a Steam-Heated Mixing Tank with a Pneumatic Process Controller CHEMICAL ENGINEERING LABORATORY CHEG 239W Control of a Steam-Heated Mixing Tank with a Pneumatic Process Controller Objective The experiment involves tuning a commercial process controller for temperature

More information

SIL explained. Understanding the use of valve actuators in SIL rated safety instrumented systems ACTUATION

SIL explained. Understanding the use of valve actuators in SIL rated safety instrumented systems ACTUATION SIL explained Understanding the use of valve actuators in SIL rated safety instrumented systems The requirement for Safety Integrity Level (SIL) equipment can be complicated and confusing. In this document,

More information

IT STARTS AT THE SOURCE - RE-CALIBRATING YOUR PLANT METERS

IT STARTS AT THE SOURCE - RE-CALIBRATING YOUR PLANT METERS IT STARTS AT THE SOURCE - RE-CALIBRATING YOUR PLANT METERS NYS AWWA Spring Conference Saratoga Springs, New York April 25, 2017 Robert Lucas, P.E. WHAT ARE WE TALKING ABOUT? Types of Flow Measuring Devices

More information

Discharge Relief Valve Operation & Maint.

Discharge Relief Valve Operation & Maint. Relief Valve Operation & Maint. CZ Series Centrifugal Fire Relief svalve Operation and Maintenance Instructions 1410 Operation and Maintenance Form No. F-1031 Section 2302.6 2111 Issue Date 04/90 11/95

More information

OIL SUPPLY SYSTEMS ABOVE 45kW OUTPUT 4.1 Oil Supply

OIL SUPPLY SYSTEMS ABOVE 45kW OUTPUT 4.1 Oil Supply OIL SUPPLY SYSTEMS ABOVE 45kW OUTPUT 4.1 Oil Supply 4.1.1 General The primary function of a system for handling fuel oil is to transfer oil from the storage tank to the oil burner at specified conditions

More information

Inflatable Packers for Grouting 11/10/00

Inflatable Packers for Grouting 11/10/00 Introduction Inflatable Packers for Grouting 11/10/00 Inflatable packers are frequently used for grout injection in geotechnical applications for structural reinforcement and/or water-proofing of foundations,

More information

Fail Operational Controls for an Independent Metering Valve

Fail Operational Controls for an Independent Metering Valve Group 14 - System Intergration and Safety Paper 14-3 465 Fail Operational Controls for an Independent Metering Valve Michael Rannow Eaton Corporation, 7945 Wallace Rd., Eden Prairie, MN, 55347, email:

More information

BACK PRESSURE / SUSTAINING

BACK PRESSURE / SUSTAINING In many liquid piping systems, it is vital that line pressure is maintained within relatively narrow limits. This is the function of the 108 Pressure Relief / Back Pressure Series of the OCV control valves.

More information

TROUBLESHOOTING GUIDELINES

TROUBLESHOOTING GUIDELINES TROUBLESHOOTING GUIDELINES PROBLEM: Performance 1. The most common problem in this area comes from inadequate flow to the LAKOS Separator(s). All LAKOS Separators operate within a prescribed flow range

More information

DAV - P. Product Catalogue DAV - P. Air release & Vacuum Break Valves. (Plastic Air Valves) DAV - P. Edition 2012

DAV - P. Product Catalogue DAV - P. Air release & Vacuum Break Valves. (Plastic Air Valves) DAV - P. Edition 2012 Product Catalogue DAV - P DAV - P Air release & Vacuum Break Valves Edition 1 DAV - P (Plastic Air Valves) DAV Series Overview General The presence of trapped air in a pressurized pipeline can have serious

More information

BACK PRESSURE / SUSTAINING

BACK PRESSURE / SUSTAINING SPECIFICATIONS DIMENSIONS In many liquid piping systems, it is vital that line pressure is maintained within relatively narrow limits. This is the function of the 108 Pressure Relief / Back Pressure Series

More information

Becker* Products Below Ground Ball Valve Regulators

Becker* Products Below Ground Ball Valve Regulators GE Oil & Gas Becker* Products Below Ground Ball Valve Regulators Reduce Noise Levels at Large Volume Regulator Stations GE s Becker* Below Ground ball valve regulator has the long-term proven reliability,

More information

TECHNICAL DATA. Table 1 - Specifications

TECHNICAL DATA. Table 1 - Specifications Page 1 of 6 1. DESCRIPTION Model A-3 Pilot Operated Pressure Control Valves are factory assembled units. Each unit consists of a Model H-2 Halar coated Flow Control Valve, a Speed Control Valve, a Model

More information

Laboratory studies of water column separation

Laboratory studies of water column separation IOP Conference Series: Materials Science and Engineering OPEN ACCESS Laboratory studies of water column separation To cite this article: R Autrique and E Rodal 2013 IOP Conf. Ser.: Mater. Sci. Eng. 52

More information

Experimental Study of Water Hammer Pressure in a Commercial Pipe

Experimental Study of Water Hammer Pressure in a Commercial Pipe IOSR Journal of Mechanical and Civil Engineering (IOSR-JMCE) Experimental Study of Water Hammer Pressure in a Commercial Pipe Ashish Kumar Patel 1 1 (School of Mechanical Engineering, Lovely Professional

More information

DESIGN DATA A WET PIPE BLADDER TANK FOAM/WATER SYSTEM WITH HYDRAULICALLY ACTUATED DELUGE CONCENTRATE CONTROL VALVE

DESIGN DATA A WET PIPE BLADDER TANK FOAM/WATER SYSTEM WITH HYDRAULICALLY ACTUATED DELUGE CONCENTRATE CONTROL VALVE February 9, 1998 Foam 101a A BLADDER TANK WITH 1. DESCRIPTION A Wet Pipe Bladder Tank Foam/Water System is a standard wet pipe automatic sprinkler system capable of discharging a foam/water solution automatically

More information

TECHNICAL DATA. the Viking Pilot Pressure Regulating Valve 1 Model A-1 Speed Control Assembly: OBSOLETE. the Viking Speed Control Assembly 1

TECHNICAL DATA. the Viking Pilot Pressure Regulating Valve 1 Model A-1 Speed Control Assembly: OBSOLETE. the Viking Speed Control Assembly 1 November 30, 1994 534 a 1. PRODUCT NAME VIKING 2" (50mm), 3" (75mm), 4" (100mm), 6" (150mm) 2. MANUFACTURER THE VIKING CORPORATION 210 N. Industrial Park Road Hastings, Michigan 49058 U.S.A. Telephone:

More information

LAKOS Waterworks. PWC Series Sand Separators. Installation & Operation Manual LS-829 (10/12)

LAKOS Waterworks. PWC Series Sand Separators. Installation & Operation Manual LS-829 (10/12) LAKOS Waterworks PWC Series Sand Separators Installation & Operation Manual LS-829 (10/12) Table of Contents Separator Operation... 3 Individual Model Details.... 4 Flow vs. Pressure Loss Chart 4 Installation

More information

AC : MEASUREMENT OF HYDROGEN IN HELIUM FLOW

AC : MEASUREMENT OF HYDROGEN IN HELIUM FLOW AC 2010-2145: MEASUREMENT OF HYDROGEN IN HELIUM FLOW Randy Buchanan, University of Southern Mississippi Christopher Winstead, University of Southern Mississippi Anton Netchaev, University of Southern Mississippi

More information

Hydraulic transients, also known as pressure

Hydraulic transients, also known as pressure FWRJ Surge Protections: Modeling vs. Design vs. Construction Jinsheng Huo Hydraulic transients, also known as pressure surge or water hammer, are the timevarying phenomena that occur when the equilibrium

More information

Pressure surge absorption

Pressure surge absorption Pressure surge absorption Product range for drinking water, waste water and the chemical industry With remote monitoring, everything is fully under control. Willy Zahnd, WARET AG PRESSURE SURGE ABSORPTION

More information

ANNEX AMENDMENTS TO THE INTERNATIONAL CODE FOR FIRE SAFETY SYSTEMS (FSS CODE) CHAPTER 15 INERT GAS SYSTEMS

ANNEX AMENDMENTS TO THE INTERNATIONAL CODE FOR FIRE SAFETY SYSTEMS (FSS CODE) CHAPTER 15 INERT GAS SYSTEMS Annex 3, page 2 ANNEX AMENDMENTS TO THE INTERNATIONAL CODE FOR FIRE SAFETY SYSTEMS (FSS CODE) CHAPTER 15 INERT GAS SYSTEMS The text of existing chapter 15 is replaced by the following: "1 Application This

More information

RESILIENT SEATED BUTTERFLY VALVES FUNCTIONAL SAFETY MANUAL

RESILIENT SEATED BUTTERFLY VALVES FUNCTIONAL SAFETY MANUAL Per IEC 61508 and IEC 61511 Standards BRAY.COM Table of Contents 1.0 Introduction.................................................... 1 1.1 Terms and Abbreviations...........................................

More information

Module No. # 01 Lecture No. # 6.2 HAZOP (continued)

Module No. # 01 Lecture No. # 6.2 HAZOP (continued) Health, Safety and Environmental Management in Petroleum and Offshore Engineering Prof. Srinivasan Chandrasekaran Department of Ocean Engineering Indian Institute Of Technology, Madras Module No. # 01

More information

TEST BENCH SAFETY VALVES ¼ - 5 DN10 DN125

TEST BENCH SAFETY VALVES ¼ - 5 DN10 DN125 TEST BENCH SAFETY VALVES ¼ - 5 DN10 DN125 Model: VC-40-VYC Table of contents 1. - Installing the test bench 1.1.1- Connecting the compressed air / nitrogen source 1.1.2- Maximum test pressure according

More information

UNIQUE ADVANTAGES OF PIPENET

UNIQUE ADVANTAGES OF PIPENET UNIQUE ADVANTAGES OF PIPENET TRANSIENT MODULE Sunrise Systems Limited Section 1: Unique Advantages of the leading hydraulic analysis software engineers prefer to use: PIPENET s schematic design is unique.

More information

The Protection of Silos From Over. Pressurisation During Filling

The Protection of Silos From Over. Pressurisation During Filling SHAPA Technical Bulletin No.11 The Protection of Silos From Over Pressurisation During Filling Page 1 of 8 August 2005 The Protection of Silos From Over Pressurisation During Filling By James Duggleby,

More information

CONTROL VALVE TESTING

CONTROL VALVE TESTING The optimal functioning of the Control valve not only exists of sufficient body & seat tightness, but more important, the total "performance" of the valve and its controls! For an accurate and reliable

More information

Operational Settings:

Operational Settings: instrucalc features more than 70 routines associated with control valves, ISO flow elements, relief valves and rupture disks, and calculates process data at flow conditions for a comprehensive range of

More information

TECHNICAL DATA. Page 1 of 12

TECHNICAL DATA. Page 1 of 12 Page 1 of 12 1. DESCRIPTION The Viking Regulating Valve is a direct-acting, single-seated, spring-loaded diaphragm valve. When installed as a pilot regulating valve on a Viking Model H or J Flow Control

More information

Advanced LOPA Topics

Advanced LOPA Topics 11 Advanced LOPA Topics 11.1. Purpose The purpose of this chapter is to discuss more complex methods for using the LOPA technique. It is intended for analysts who are competent with applying the basic

More information

Effect of Fluid Density and Temperature on Discharge Coefficient of Ogee Spillways Using Physical Models

Effect of Fluid Density and Temperature on Discharge Coefficient of Ogee Spillways Using Physical Models RESEARCH ARTICLE Effect of Fluid Density and Temperature on Discharge Coefficient of Ogee Spillways Using Physical Models M. SREENIVASULU REDDY 1 DR Y. RAMALINGA REDDY 2 Assistant Professor, School of

More information

Exercise 4-2. Centrifugal Pumps EXERCISE OBJECTIVE DISCUSSION OUTLINE DISCUSSION. Pumps

Exercise 4-2. Centrifugal Pumps EXERCISE OBJECTIVE DISCUSSION OUTLINE DISCUSSION. Pumps Exercise 4-2 Centrifugal Pumps EXERCISE OBJECTIVE Familiarize yourself with the basics of liquid pumps, specifically with the basics of centrifugal pumps. DISCUSSION OUTLINE The Discussion of this exercise

More information

Gas Accumulation Potential & Leak Detection when Converting to Gas

Gas Accumulation Potential & Leak Detection when Converting to Gas Gas Accumulation Potential & Leak Detection when Converting to Gas Coal to Gas / PCUG Conference Chattanooga, TN October 29, 2013 Robert G. Mudry, P.E. Airflow Sciences Corporation Introduction Coal to

More information

2 FUSION FITTINGS FOR USE WITH POLYETHYLENE PRESSURE PIPES DESIGN FOR DYNAMIC STRESSES

2 FUSION FITTINGS FOR USE WITH POLYETHYLENE PRESSURE PIPES DESIGN FOR DYNAMIC STRESSES Industry Guidelines Part 2 FUSION FITTINGS FOR USE WITH POLYETHYLENE PRESSURE PIPES DESIGN FOR DYNAMIC STRESSES ISSUE 5.1 Ref: POP10B 15 MAR 2010 Disclaimer In formulating this guideline PIPA has relied

More information

Theory, Application, and Sizing of Air Valves

Theory, Application, and Sizing of Air Valves VM AV/WP White Paper Theory, Application, and Sizing of Air Valves Table of Contents Introduction...................... 2 Three Basic Types of Air Valves....... 2 Air Release Valves................. 3

More information

OWNER S TECHNICAL MANUAL

OWNER S TECHNICAL MANUAL EL SERIES OWNER S TECHNICAL MANUAL DP7002 1 Air Operated Diaphragm Pump Description The DP7002 1 air operated diaphragm pump is the ideal device for the pumping, transfer and dispensing of chemical liquids,

More information

Practical Guide. By Steven T. Taylor, P.E., Member ASHRAE

Practical Guide. By Steven T. Taylor, P.E., Member ASHRAE ractical Guide The following article was published in ASHRAE Journal, March 2003. Copyright 2003 American Society of Heating, Refrigerating and Air- Conditioning Engineers, Inc. It is presented for educational

More information

AUTOMATIC HOSE TEST UNIT, TYPE SPU

AUTOMATIC HOSE TEST UNIT, TYPE SPU VALVES AND FITTINGS UP TO 14,000 BAR TEST AND CONTROL EQUIPMENT H IGH PRESSURE TECHNOLOGY AUTOMATIC HOSE TEST UNIT, TYPE SPU Pressure range from 1 up to 10,000 bar User-friendly touch panel operation HIGH-PRESSURE

More information

HYDROVEX TTT Membrane Flow Regulator

HYDROVEX TTT Membrane Flow Regulator HYDROVEX TTT Membrane Flow Regulator INSTALLATION, OPERATION AND MAINTENANCE MANUAL PROJECT EQUIPMENT LOCATION EQUIPMENT DESCRIPTION HYDROVEX TTT REFERENCE N OF THE SUPPLIER MODEL N SERIAL N DATE OF FABRICATION

More information

OPERATING PROCEDURES

OPERATING PROCEDURES OPERATING PROCEDURES 1.0 Purpose This element identifies Petsec s Operating Procedures for its Safety and Environmental Management System (SEMS) Program; it applies to all Petsec operations. Petsec is

More information

TRI LOK SAFETY MANUAL TRI LOK TRIPLE OFFSET BUTTERFLY VALVE. The High Performance Company

TRI LOK SAFETY MANUAL TRI LOK TRIPLE OFFSET BUTTERFLY VALVE. The High Performance Company TRI LOK TRI LOK TRIPLE OFFSET BUTTERFLY VALVE SAFETY MANUAL The High Performance Company Table of Contents 1.0 Introduction...1 1.1 Terms and Abbreviations... 1 1.2 Acronyms... 1 1.3 Product Support...

More information

LP Separator Level Control by Variable Speed and Multi Stage Brine Reinjection Pumps at Kawerau and Nga Awa Purua Geothermal Projects, New Zealand

LP Separator Level Control by Variable Speed and Multi Stage Brine Reinjection Pumps at Kawerau and Nga Awa Purua Geothermal Projects, New Zealand Proceedings World Geothermal Congress 2010 Bali, Indonesia, 25-29 April 2010 LP Separator Level Control by Variable Speed and Multi Stage Brine Reinjection Pumps at Kawerau and Nga Awa Purua Geothermal

More information

Evaluating Surge Potential in CSO Tunnels

Evaluating Surge Potential in CSO Tunnels 14 Evaluating Surge Potential in CSO Tunnels Karen E. Ridgway Tunnels are being proposed to control combined sewer overflow (CSO) in numerous cities in the United States and Canada. The tunnels are intended

More information

Water Hammer In Irrigation Systems 1

Water Hammer In Irrigation Systems 1 CIR828 1 G. A. Clark and D. Z. Haman 2 Irrigation system design includes pump sizing and selection, valve sizing and selection, and pipe sizing as well as the proper selection and placement of many other

More information

DIVERLESS SUBSEA HOT TAPPING OF PRODUCTION PIPELINES

DIVERLESS SUBSEA HOT TAPPING OF PRODUCTION PIPELINES DIVERLESS SUBSEA HOT TAPPING OF PRODUCTION PIPELINES Dale Calkins Senior Project Engineer, TD Williamson Inc Biography Dale Calkins joined TD Williamson Inc in November of 1999 after working as a consulting

More information

Appendix M. Hydraulic Transient Analysis

Appendix M. Hydraulic Transient Analysis Water Storage and Distribution Master Plan City of Barrie October 2013 Final Appendix M Hydraulic Transient Analysis Project Number: TP110135 Appendices 131-20095-00 Wednesday October 9th, 2013 Paul Smeltzer

More information

PMI ADVANCED AUTOMATED HYDRAULIC PRESSURE LEAK TESTER APCS-H-60K. Not just Products... Solutions!

PMI ADVANCED AUTOMATED HYDRAULIC PRESSURE LEAK TESTER APCS-H-60K. Not just Products... Solutions! PMI ADVANCED AUTOMATED HYDRAULIC PRESSURE LEAK TESTER APCS-H-60K Not just Products... Solutions! DESCRIPTION The PMI Automated Hydraulic Pressure Leak Tester provides precise pressure generation and control

More information

Reliability Assessment of the Whistler Propane Vaporizers

Reliability Assessment of the Whistler Propane Vaporizers Reliability Assessment of the Whistler Propane Vaporizers Prepared for: Terasen & Fransen Engineering Prepared by: ClearSky Risk Management Inc. 815 23 rd Ave East Vancouver, BC V6B 5Z3 Phone: 604.899.1470

More information

Standard Pneumatic Test Procedure Requirements for Piping Systems

Standard Pneumatic Test Procedure Requirements for Piping Systems the pressure equipment safety authority Standard Pneumatic Test Procedure Requirements for Piping Systems AB-522 Edition 2, Rev. 1 Issued 2016-10-24 Table of Contents FOREWORD... 1 1.0 INTRODUCTION...

More information

product manual HM-4140, HM-4150, HM-4160 HM-4160A HM-4150 Humboldt FlexPanels

product manual HM-4140, HM-4150, HM-4160 HM-4160A HM-4150 Humboldt FlexPanels 12.09 product manual HM-4140, HM-4150, HM-4160 HM-4160A HM-4150 Humboldt FlexPanels Introduction: This manual covers the installation and operation of Humboldt FlexPanels for Triaxial and Permeability

More information

DESIGN DATA OBSOLETE. C. Inspections - It is imperative that the system be inspected and tested on a regular basis. See Inspection

DESIGN DATA OBSOLETE. C. Inspections - It is imperative that the system be inspected and tested on a regular basis. See Inspection February 9, 1998 Foam 201a 1. DESCRIPTION A Deluge Bladder Tank Foam/Water System is a standard deluge system capable of discharging a foam/water solution automatically through open sprinklers, spray nozzles,

More information

Modelling Today for the Future. Advanced Modelling Control Techniques

Modelling Today for the Future. Advanced Modelling Control Techniques CwMAG 1 st Autumn Conference 2012 Modelling Today for the Future Advanced Modelling Control Techniques What are advanced modelling controls? Why do we have them? How can we use them? What are the differences

More information

Process Simulator Evaluates Blower and Valve Control Strategies for WWTP Aeration

Process Simulator Evaluates Blower and Valve Control Strategies for WWTP Aeration Process Simulator Evaluates Blower and Valve Control Strategies for WWTP Aeration inshare By Steve Kestel and Tilo Stahl (BioChem Technology) and Matthew Gray (Keystone Engineering Group) Introduction

More information

VALVES OPERATION, MAINTENANCE & TROUBLESHOOTING

VALVES OPERATION, MAINTENANCE & TROUBLESHOOTING Training Title VALVES OPERATION, MAINTENANCE & TROUBLESHOOTING Training Duration 5 days Training Venue and Dates Valves operation, Maintenance & Troubleshooting 5 02-06 Dec $3,750 Dubai, UAE In any of

More information

TECHNICAL DATA. than the water inlet pressure to the concentrate

TECHNICAL DATA. than the water inlet pressure to the concentrate Foam102a 1. DESCRIPTION The Viking Low Flow Foam/Water proportioning system, is a UL Listed and FM Approved system, for use with 3M foam concentrates. This system consists of a standard wet pipe sprinkler

More information

Waterous Relief Valve

Waterous Relief Valve Operating Instructions 1. Reduce pump discharge pressure with engine throttle. Make sure four way (On/Off) valve is OFF. 2. Open at least one discharge valve. Accelerate engine until pressure gage indicates

More information

Irrigation System Winterization and Pressurization Procedures

Irrigation System Winterization and Pressurization Procedures Irrigation System Winterization and Pressurization Procedures Introduction Any time that an irrigation system is filled and pressurized, or when the system is drained and water flushed from the system,

More information

Understanding safety life cycles

Understanding safety life cycles Understanding safety life cycles IEC/EN 61508 is the basis for the specification, design, and operation of safety instrumented systems (SIS) Fast Forward: IEC/EN 61508 standards need to be implemented

More information

Tube rupture in a natural gas heater

Tube rupture in a natural gas heater Tube rupture in a natural gas heater Dynamic simulation supports the use of a pressure safety valve over a rupture disk in the event of a tube rupture HARRY Z HA and PATRICK STANG Fluor Canada Ltd A fast

More information

The benefits of the extended diagnostics feature. Compact, well-proven, and flexible

The benefits of the extended diagnostics feature. Compact, well-proven, and flexible ABB MEASUREMENT & ANALYTICS TECHNICAL INFORMATION PositionMaster EDP300 Extended Diagnostics Compact, well-proven, and flexible The benefits of the extended diagnostics feature The PositionMaster EDP300

More information

HIPPS Development Project

HIPPS Development Project Hydraulic HIPPS HIPPS Development Project This presentation describes the Energy Equipment Corporation Hydraulic HIPPS control development project, and gives: Brief background information about Energy

More information

Effect of noise in the performance of the transducers in an ultrasonic flow meter of natural gas

Effect of noise in the performance of the transducers in an ultrasonic flow meter of natural gas 23rd World Gas Conference, Amsterdam 2006 Effect of noise in the performance of the transducers in an ultrasonic flow meter of natural gas Main author R. Villarroel Venezuela TABLE OF CONTENTS 1. Abstract

More information

Intelligent SUNTEX DC-5310(RS) Dissolved Oxygen Transmitter

Intelligent SUNTEX DC-5310(RS) Dissolved Oxygen Transmitter Intelligent SUNTEX DC-5310(RS) Dissolved Oxygen Transmitter Overview C % ppm 4~20mA Analog Output ppb Power Supply 100~240 VAC mg/l Dimensions 96 x 96 x 132mm RS-485 Digital Output (for DC-5310-RS only)

More information

Suppress Your Surges: Surge Suppression Fundamentals. April 13, 2017

Suppress Your Surges: Surge Suppression Fundamentals. April 13, 2017 Suppress Your Surges: Surge Suppression Fundamentals April 13, 2017 How Bad Can Waterhammer Really Be? 2 Workshop Agenda What is waterhammer? Causes of waterhammer Instantaneous surge pressures Surges

More information

Energy Control. Suite 2A, 55 Frid Street Hamilton, ON L8P 4M3 office: cell:

Energy Control. Suite 2A, 55 Frid Street Hamilton, ON L8P 4M3 office: cell: Energy Control Suite 2A, 55 Frid Street Hamilton, ON L8P 4M3 office: 905.577.0303 cell: 905.977.0210 consultant@staffaid.ca www.staffaid.com Safety, Energy Control, Power Lockout & Function Test Procedures

More information

Drilling Efficiency Utilizing Coriolis Flow Technology

Drilling Efficiency Utilizing Coriolis Flow Technology Session 12: Drilling Efficiency Utilizing Coriolis Flow Technology Clement Cabanayan Emerson Process Management Abstract Continuous, accurate and reliable measurement of drilling fluid volumes and densities

More information

Air Eliminators and Combination Air Eliminators Strainers

Air Eliminators and Combination Air Eliminators Strainers Description Air Eliminators and Combination Air Eliminator Strainers are designed to provide separation, elimination and prevention of air in piping systems for a variety of installations and conditions.

More information

AC : A LABORATORY EXERCISE TO DEMONSTRATE HOW TO EXPERIMENTALLY DETERMINE THE OPERATING POINT FOR A FAN

AC : A LABORATORY EXERCISE TO DEMONSTRATE HOW TO EXPERIMENTALLY DETERMINE THE OPERATING POINT FOR A FAN AC 2007-206: A LABORATORY EXERCISE TO DEMONSTRATE HOW TO EXPERIMENTALLY DETERMINE THE OPERATING POINT FOR A FAN Robert Edwards, Pennsylvania State University-Erie Robert Edwards is currently a Lecturer

More information

How to use the PBM Flow Calculator Spreadsheet (V2.04)

How to use the PBM Flow Calculator Spreadsheet (V2.04) How to use the PBM Flow Calculator Spreadsheet (V2.04) o Navigate to the F:\Common\ENGINEERING\Common Design Calculations folder o o Open PBM FLOW CALC 2.04.xlsm On the title page, the version, version

More information

RESOLUTION A.567(14) adopted on 20 November 1985 REGULATION FOR INERT GAS SYSTEMS ON CHEMICAL TANKERS

RESOLUTION A.567(14) adopted on 20 November 1985 REGULATION FOR INERT GAS SYSTEMS ON CHEMICAL TANKERS INTERNATIONAL MARITIME ORGANIZATION A 14/Res.567 16 January 1986 Original: ENGLISH ASSEMBLY - 14th session Agenda item lo(b) IMO RESOLUTION A.567(14) adopted on 20 November 1985 THE ASSEMBLY, RECALLING

More information

Quantitative Risk Analysis (QRA)

Quantitative Risk Analysis (QRA) Quantitative Risk Analysis (QRA) A realistic approach to relief header and flare system design Siemens AG 2017, All rights reserved 1 Quantitative Risk Analysis Introduction Most existing pressure relief

More information

CASE STUDY. Compressed Air Control System. Industry. Application. Background. Challenge. Results. Automotive Assembly

CASE STUDY. Compressed Air Control System. Industry. Application. Background. Challenge. Results. Automotive Assembly Compressed Air Control System Industry Automotive Assembly Application Savigent Platform and Industrial Compressed Air Systems Background This automotive assembly plant was using over 40,000 kilowatt hours

More information