Technical vs. Process Commissioning Final Exam: Functional Performance Testing

Size: px
Start display at page:

Download "Technical vs. Process Commissioning Final Exam: Functional Performance Testing"

Transcription

1 ASHRAE Used with permission from ASHRAE Journal, June 2014 at This article may not be copied nor distributed in either paper or digital form without ASHRAE s permission. For more information about ASHRAE, visit Technical vs. Process Commissioning Final Exam: Functional Performance Testing BY DAVE MCFARLANE, MEMBER ASHRAE So far in this series on technical commissioning, we have examined commissioning functions and practices associated with the planning, design, and construction phases of a new building project. We have outlined the owner s expectations in the Owner s Project Requirements (OPR) document, and we have reviewed and approved the Basis of Design (BOD) document, which shows how the design meets the requirements of the OPR. In addition, we have created a plan that outlines the tasks everyone involved in the project must complete to ensure the project meets its OPR. We have also monitored the construction process to ensure that all equipment and systems were properly installed, and we have verified that all equipment and systems can be properly started and run. The next phase of technical commissioning functional performance testing (FPT) is the final exam a new building must pass before it can graduate and be turned over to a satisfied owner. This is the seventh in a series of bimonthly articles that explain the technical commissioning process for new buildings. Some of these articles content is based on ASHRAE Guideline , The Commissioning Process (published 2005) and the National Environmental Balancing Bureau (NEBB) publication Procedural Standards for Whole Building Systems Technical Commissioning for New Construction (revised April 2013). In addition, some of the information in this article series has been adapted from an unpublished NEBB standard titled NEBB Standard Owner s Project Requirements (OPR) Guideline (draft dated June 20, 2011); and from NEBB s Procedural Standards for Building Enclosure Testing (March 2013). Dave McFarlane is principal project director at Atkins in Fort Myers, Fla. Importance of the Issue Log Up til now, at each step in the commissioning process either the commissioning authority (CxA) or the contractor has carefully documented issues of concern in the project issue log (which we have not discussed previously due to space limitations). But the issue log is more than just a chronicle of problems. It also should include the date the issue was first identified (and by whom), a description of possible solutions, who is responsible to correct the issue, and the date the issue was corrected (and by whom). The CxA must maintain the issue log, and a significant part of all commissioning-related meetings should be devoted to discussing possible resolutions, assignments, costs, and completion dates for the items in the log. These discussions are vital, because the CxA should resolve 14 ASHRAE JOURNAL ashrae.org JUNE 2014

2 issues as they come up, during any phase of the construction process, before moving to the next phase. For example, FPT cannot begin until all equipment and systems are verified to start up and function properly during pre-functional testing. So when key startuprelated items are entered into the issue log but not corrected, FPT will probably fail and need to be repeated after the issues are corrected. So pay careful attention to the issue log, and make sure all issues are resolved before FPT begins. Role of Functional Performance Testing It s important to note that ASHRAE Guideline requires functional performance testing. But the Guideline does not describe the number or type of tests to perform, nor does it define how stringent the tests must be or even who should conduct them. This article is an attempt to flesh out the Guideline in a practical manner, and from a technical commissioning perspective. This article also assumes that every issue in the issue log has been corrected, all pre-functional tests have been verified complete and successful, all building systems and components are properly installed and functional, and all valves and dampers open and close as required. At this point, you may ask, OK, if everything is well designed, installed correctly, and fully functional and all known issues have been corrected what else is there to do? This is an important question, as my experience indicates that a traditional process-commissioning CxA would give a very different answer than would a technical-commissioning CxA. I ve found that a traditional process-commissioning CxA would likely answer: You re right. We ve prepared the FPT forms, and the contractors have informed us that all of their testing was successful. We ve verified that all of the commissioning forms have been completed, and we ve randomly sampled the building s equipment and systems to verify correct installation and proper operation. If our project employed traditional process commissioning, it would be complete; and we would be ready to turn over the new building to its owner. But when faced with the same question, a technical commissioning CxA will likely answer: Our commissioning team has done a great job so far! We ve verified that the design satisfies the OPR. We ve corrected every issue in the issue log, and we ve personally confirmed that all equipment and systems have been properly installed and are fully functional. We re now ready for the project s final exam: real-world, functional performance testing of every building system. Our goal is to ensure that the building itself (not just the design) satisfies the OPR, so we must ensure that the occupants find the internal environment to be efficient, healthy, and comfortable. We ve given all relevant contractors their FPT forms, and we ll now work with them during FPT, observing and assisting as they perform every test. This test-and-verify-everything perspective is a big difference between process commissioning and technical commissioning. Process commissioning permits contractors to serve as their own SMEs, and allows them to perform their own tests. However, technical commissioning requires the CxA to serve as the SME and as such the CXA either performs or supervises all functional performance testing. Test Example: A Variable Air Volume Box To illustrate how the FPT process works, this article uses the example of a single variable air volume (VAV) box serving a single space. But note: Proper technical commissioning requires that the CxA measure and verify the correct operation of all control loops not just a sample. It is true that the CxA is permitted to perform limited sampling during pre-functional testing (refer to the previous article in this series). But no sampling is allowed during FPT. Instead, all systems and equipment must be actively verified for real-world operation. You may ask, What s wrong with sampling? It can save time and potentially reduce overall costs. The problem is sampling can work well for homogenous systems such as a batch of well-mixed concrete: Every sample taken has a high probability of having the same chemical composition as any other sample. So if one sample meets specifications, the rest of the batch should also meet the specs. But mechanical systems are never homogenous. Why? Every system has probably been touched by multiple contracting firms and multiple technicians. Our sample VAV box, for example, has had electrical, piping, sheet metal, control, test-and-balance, and chemical-treatment contractors involved in its installation. Also, different employees of the same firm may build or install each of their components and systems differently. So it is likely that every VAV box will respond differently to control inputs. JUNE 2014 ashrae.org ASHRAE JOURNAL 15

3 During the final exam, each control loop FIGURE 1 VAV box control sequence is too tight. of every system is checked to make sure its 80 control sequence actually does what it is supposed to do. This is much more than 76 simply testing to see if a valve opens in 72 response to a call for heat, or a reheat valve closes in response to a call for cooling. In 68 fact, from a technical commissioning perspective, those tests would have already been performed during the operational performance testing (OPT) phase. Instead, the FPT phase calls for hands-on FIGURE 2 VAV box control sequence is too loose. verification that every controlled device 80 performs all of the functions it is required to 76 perform, including: The performance of all required steps it 72 is supposed to perform. 68 A controller/actuator response speed that is appropriate for the application. A stable response. All events are controllable to the setpoint. All adjustments take place automatically FIGURE 3 Properly adjusted VAV box control sequence. through the building automation system. Figure 1 illustrates a control sequence that 80 is too tight. The figure shows a temperature that fluctuates hourly between 76 F 76 and 68 F (24 C to 20 C). The problem is 72 that when the temperature drifts from its 68 setpoint, the controller causes the temperature to cycle unacceptably. If a thermostat controls this VAV box, the air flow damper and heating control valve responses are too rapid, which causes the cycling and I can practically guarantee that the occupants will complain that it s too hot or too cold. But when called to resolve the problem, the building maintenance staff may not be able to properly diagnose it because the temperature is fairly close to the setpoint much of the time. So the maintenance staff leaves, having done nothing except to accuse the occupants of being oversensitive. Figure 2 illustrates a different challenge: A controller that does not respond quickly enough. The problem is when the room temperature is below its setpoint, the reheat valve or air flow damper does not change quickly enough to meet the setpoint; and when the temperature is above its setpoint, the heating valve does not close Temperature ( F) Temperature ( F) Temperature ( F) Time (Minutes) Time (Minutes) Time (Minutes) quickly enough nor does the airflow increase at a rate sufficient to maintain the setpoint. In this case, when occupants complain, the maintenance staff may simply see the temperature as too high or too low. So to resolve overcooling, they reduce air flow; to resolve overheating, they throttle back valves. But neither of those solutions is the proper fix. Figure 3 reflects proper system calibration, adjustment, and tuning: When the setpoint is adjusted, the VAV airflow damper and the reheat control valve respond correctly, the temperature reaches the control setpoint within a reasonable time interval, and afterward the temperature is stable. In this case, most occupants would feel comfortable, as OPRs often call for a temperature of 72 F (22 C), ±2 F (1 C). 16 ASHRAE JOURNAL ashrae.org JUNE 2014

4 Advertisement formerly in this space.

5 Advertisement formerly in this space.

6 So for the final exam for our sample VAV box involves verifying that: Control sequences generate the appropriate temperature control responses; Control sequences adjust the temperature to the setpoint; All sequences yield stable results; All sequences occur automatically through the control system; The box reacts properly to a power failure; and Room occupancy/co 2 sensors are properly set to open the air inlets in order to maintain proper CO 2 levels and room temperature. Under the process commissioning model, I have seen a contractor simply set a thermostat to full heat and then to full cool; and that was submitted as the FPT. But this kind of test does not measure response time or stability, which is why such tests are unacceptable for technical commissioning. Space limitations do not permit me to describe the FPT requirements and processes for all of the systems and components for an entire project. Suffice it to say that the CxA must perform functional performance tests on every control loop in the project, which encompasses all of a building s major systems and equipment, including boilers, chillers, air handlers, cooling towers, pressurization systems, and so forth. controllers with pneumatic differential-pressure sensors, thermostats, and control valves. In one of the processes I oversaw, an explosion could result if the chemical mixture got too hot. If the temperature were too cold, the proper reaction would not occur. In another process, the final result was a material that could be either too brittle or too soft, depending on chemical flow rates. Advertisement formerly in this space. Importance of Control Loop Adjustments In the 1970s, I worked as a chemical process engineer. Part of my job was to ensure pumps started and valves opened and closed as required. We used tuned control loops to maintain chemical flows, pressures, and temperatures within tight constraints. This was before the advent of computerized controls, so we used JUNE 2014 ashrae.org ASHRAE JOURNAL 19

7 My coworkers and I became adept at checking and tuning control loops, which measured and controlled three parameters, together known as PID: 1. The proportional (P) parameter, which measures present error; 2. The integral (I) parameter, representing the accumulation of past errors; and 3. The derivative (D) parameter, predicting future errors. We were required to maintain our control loops within specific ranges; and our PID tuning resulted in quick adjustments. We controlled temperatures, pressures, and flow rates to the appropriate setpoints and stability requirements thus yielding materials that met the quality standards. Today, computerized controls are commonplace in HVAC systems, but the same tuning of control loops is still essential. That s because technical commissioning is about minimizing energy consumption as well as improving occupant comfort. However, the tuning of control loops is normally not performed during traditional process commissioning. It is common for the manufacturer s standard control loops to be left in place until there s a complaint. I would be a rich man if I had a dollar for every time I heard a control technician say, We don t need to adjust the PID loops; they re preset at the factory. PID Loop Testing Process It is important to ensure that a system s control loops are properly tuned. But because PID loop tuning is done so infrequently, it may be necessary for the CxA to brush up on how it s done, in order to help the controls contractor properly test the equipment and systems they ve installed. As previously noted, proper technical commissioning calls for the CxA to oversee the measurement and verification of all control loops. This objective is accomplished by making minor system setpoint changes and then data-logging the controlled event. For the VAV box example, the controlled event is the space temperature, so the CxA must ensure these five data points are logged: Space temperature; Damper position; Reheat valve position; Discharge air temperature; and Airflow volume from the box. For each loop, the tests involve subjecting the controller to small but definitive changes from the wall thermostat setpoint and measuring the results. In our VAV box example, the system is started and run at a setpoint of 72 F (22 C) until stable. Next, the setpoint is adjusted to 75 F (24 C), which should cause the box to begin heating, and the system s response is measured by readings taken every minute. In a typical VAV box, the damper position should throttle back, the airflow should be reduced to the heating (or minimum) setpoint, and the reheat valve should open. The CxA then makes sure the required data points are logged, ensures that the temperature has adjusted to 75 F (24 C), and verifies that the system s response time conforms to either the OPR or to acceptable responses as described in the Commissioning Plan. Finally, the setpoint is lowered to 69 F (20 C), which should cause the box to begin cooling. As before, the system s response is measured via readings taken every minute. In a typical VAV box, the damper position should open to the maximum or cooling airflow, the airflow should increase, and the reheat valve should close. As previously, the CxA also makes sure the required data points are logged, ensures that the temperature has adjusted to 69 F (20 C), and verifies that the response time conforms to either OPR or Commissioning Plan standards. If performance is unsatisfactory in any way, the CxA collaborates with the contractor to investigate the problem, determine the cause, and adjust the control loops as needed. Testing all control loops is another difference between FPT in technical and process commissioning. A typical process commissioning approach calls for the CxA to sample 10% to 15% of a building s control loops and by extrapolation conclude that all systems work properly. In contrast, under technical commissioning the CxA verifies that 100% of a building s control loops work properly. Identifying and Resolving Problems As noted in the previous article in this series, project contractors have the ultimate responsibility for their own quality control. Therefore, all contractors need to perform their own tests before the CxA either conducts or witnesses FPT. For our sample VAV box, multiple contractors would be involved in a successful testing process. It s worth noting that each contractor should have verified their work during pre-functional testing. However, that is an insufficient level 20 ASHRAE JOURNAL ashrae.org JUNE 2014

8 Advertisement formerly in this space.

9 of testing in the world of technical commissioning if for no other reason than the amount of time that often elapses (weeks or months) between pre-functional testing and FPT. While our sample VAV box may have passed prefunctional testing, conditions can change in the weeks or months before FPT. For example, the box will fail FPT if there is an insufficient flow of hot water to the reheat coil; and there are many reasons why the flow might be reduced Advertisement formerly in this space. during the time that passes since pre-functional testing, including: A plugged strainer (responsibility: chemical treatment contractor); A manual valve having been closed (mechanical piping contractor); Improper testing and balancing (testing, adjusting, and balancing contractor); The control valve failing to open (controls contractor); or The VAV box fan failing to start properly (electrical contractor). In a previous article, I noted how a project s contract documents should permit the owner to financially penalize a contractor for testing beyond a specified limit; and retests required during FPT would fall under the financial-penalty stipulations. But contractors can avoid those penalties by ensuring their systems work properly before the CxA shows up on site to oversee the final tests. Fully Tested = Fully Confident Functional performance testing is the final exam that verifies all of a building s systems work in the real world. After all project issues are resolved and functional performance testing is complete, the technical-commissioning CxA can look the owner in the eye and confidently state: Your building works as you ve intended. We ve verified that your project requirements have been fully satisfied. Through careful and detailed hands-on testing, we ve made certain that the building functions as designed. All known issues have been corrected, and we ve personally verified that 100% of the building s equipment has passed every test. Congratulations! Your building has been through a comprehensive technical commissioning process. And we know this because we ve overseen or conducted all of the tests in person. 22 ASHRAE JOURNAL ashrae.org JUNE 2014

2005 CERTIFICATE OF ACCEPTANCE (Part 1 of 3) MECH-1-A

2005 CERTIFICATE OF ACCEPTANCE (Part 1 of 3) MECH-1-A 2005 CERTIFICATE OF ACCEPTANCE (Part 1 of 3) MECH-1-A PROJECT ADDRESS TESTING AUTHORITY TELEPHONE Checked by/date Enforcement Agency Use GENERAL INFORMATION OF BLDG. PERMIT PERMIT # BLDG. CONDITIONED FLOOR

More information

HAP e-help. Obtaining Consistent Results Using HAP and the ASHRAE 62MZ Ventilation Rate Procedure Spreadsheet. Introduction

HAP e-help. Obtaining Consistent Results Using HAP and the ASHRAE 62MZ Ventilation Rate Procedure Spreadsheet. Introduction Introduction A key task in commercial building HVAC design is determining outdoor ventilation airflow rates. In most jurisdictions in the United States, ventilation airflow rates must comply with local

More information

Application Block Library Fan Control Optimization

Application Block Library Fan Control Optimization Application Block Library Fan Control Optimization About This Document This document gives general description and guidelines for wide range fan operation optimisation. Optimisation of the fan operation

More information

Process Control Loops

Process Control Loops In this section, you will learn about how control components and control algorithms are integrated to create a process control system. Because in some processes many variables must be controlled, and each

More information

SECTION TESTING ADJUSTING AND BALANCING FOR HVAC

SECTION TESTING ADJUSTING AND BALANCING FOR HVAC SECTION 23 05 93 - TESTING ADJUSTING AND [Note to PSC: Existing System Coordination When connecting to an existing system, it is the PSC s Responsibility to examine existing documents, field verify existing

More information

Hydronic Systems Balance

Hydronic Systems Balance Hydronic Systems Balance Balancing Is Misunderstood Balancing is application of fundamental hydronic system math Balance Adjustment of friction loss location Adjustment of pump to requirements By definition:

More information

TESTING OF BELIMO PRESSURE INDEPENDENT CHARACTERIZED CONTROL VALVES

TESTING OF BELIMO PRESSURE INDEPENDENT CHARACTERIZED CONTROL VALVES TESTING OF BELIMO PRESSURE INDEPENDENT CHARACTERIZED CONTROL VALVES November, 25 Submitted by: Iowa Energy Center Address: DMACC, 26 S. Ankeny Blvd. Ankeny, IA 521 Phone: 515.965.755 Fax: 515.965.756 Web

More information

The Advancement of Pressure Independent Technology

The Advancement of Pressure Independent Technology The Advancement of Pressure Independent Technology This session will look at the new pressure independent technology and its energy savings potential. Topics include: A brief review of the differences

More information

Installation Guide - C01202 & C01203 Thermostatic Mixing Valve TMV2

Installation Guide - C01202 & C01203 Thermostatic Mixing Valve TMV2 The following information is required for use when the Saracen range of thermostatic mixing valves is used in a TMV2 Applications under the requirements of BS EN 1111: 1999 Sanitary tap ware Thermostatic

More information

Practical Guide. By Steven T. Taylor, P.E., Member ASHRAE

Practical Guide. By Steven T. Taylor, P.E., Member ASHRAE ractical Guide The following article was published in ASHRAE Journal, March 2003. Copyright 2003 American Society of Heating, Refrigerating and Air- Conditioning Engineers, Inc. It is presented for educational

More information

Model-Independent Fault Detection and Diagnostics For VAV Terminal Units

Model-Independent Fault Detection and Diagnostics For VAV Terminal Units Model-Independent Fault Detection and Diagnostics For VAV Terminal Units Christopher C. Schroeder, Schiller Associates James D. Bradford, Schiller Associates ABSTRACT A new tool for performing fault detection

More information

REQUIREMENTS AND HAND-OVER DOCUMENTATION FOR ENERGY-OPTIMAL DEMAND-CONTROLLED VENTILATION

REQUIREMENTS AND HAND-OVER DOCUMENTATION FOR ENERGY-OPTIMAL DEMAND-CONTROLLED VENTILATION REQUIREMENTS AND HAND-OVER DOCUMENTATION FOR ENERGY-OPTIMAL DEMAND-CONTROLLED VENTILATION Mads Mysen* 1, Axel Cablé 1, Peter G. Schild 1, and Kari Thunshelle 1 1 SINTEF Building and Infrastructure Forskningsveien

More information

2. Determine how the mass transfer rate is affected by gas flow rate and liquid flow rate.

2. Determine how the mass transfer rate is affected by gas flow rate and liquid flow rate. Goals for Gas Absorption Experiment: 1. Evaluate the performance of packed gas-liquid absorption tower. 2. Determine how the mass transfer rate is affected by gas flow rate and liquid flow rate. 3. Consider

More information

COMPARISON OF DIFFERENTIAL PRESSURE SENSING TECHNOLOGIES IN HOSPITAL ISOLATION ROOMS AND OTHER CRITICAL ENVIRONMENT APPLICATIONS

COMPARISON OF DIFFERENTIAL PRESSURE SENSING TECHNOLOGIES IN HOSPITAL ISOLATION ROOMS AND OTHER CRITICAL ENVIRONMENT APPLICATIONS COMPARISON OF DIFFERENTIAL PRESSURE SENSING TECHNOLOGIES IN HOSPITAL ISOLATION ROOMS AND OTHER CRITICAL ENVIRONMENT APPLICATIONS APPLICATION NOTE LC-136 Introduction Specialized spaces often times must

More information

Space Pressurization: Concept and Practice ASHRAE Distinguished Lecture Series

Space Pressurization: Concept and Practice ASHRAE Distinguished Lecture Series Space Pressurization: Concept and Practice ASHRAE Distinguished Lecture Series Jim Coogan Siemens Building Technologies ASHRAE, St. Louis Chapter November10, 2014 Agenda Introduction (concept, purpose,

More information

Fisher DVI Desuperheater Venturi Inline

Fisher DVI Desuperheater Venturi Inline Instruction Manual DVI Desuperheater Fisher DVI Desuperheater Venturi Inline Contents Introduction... 1 Scope of Manual... 1 Description... 1 Principle of Operation... 2 Installation... 3 Operating Instructions...

More information

A Semi-Automated Functional Test Data Analysis Tool

A Semi-Automated Functional Test Data Analysis Tool A Semi-Automated Functional Test Data Analysis Tool Peng Xu, Philip Haves, Moosung Kim Lawrence Berkeley National Lab Synopsis The growing interest in commissioning is creating a demand that will increasingly

More information

ASHRAE WILL ILL GIVE Y OU THE W ORLD This ASHRAE Distinguished Lecturer is brought to you by the Society Chapter Technology Transfer Committee Complete the Distinguished Lecturer Event Summary Critique

More information

Gerald D. Anderson. Education Technical Specialist

Gerald D. Anderson. Education Technical Specialist Gerald D. Anderson Education Technical Specialist The factors which influence selection of equipment for a liquid level control loop interact significantly. Analyses of these factors and their interactions

More information

Outside Air Nonresidential HVAC Stakeholder Meeting #2 California Statewide Utility Codes and Standards Program

Outside Air Nonresidential HVAC Stakeholder Meeting #2 California Statewide Utility Codes and Standards Program 1 Outside Air Nonresidential HVAC Stakeholder Meeting #2 California Statewide Utility Codes and Standards Program Jim Meacham, CTG Energetics Agenda 2 In Situ Testing Results Reduced Ventilation after

More information

Installation, commissioning and servicing instructions

Installation, commissioning and servicing instructions www.reece.com.au Tempering valve 38550.08 5213 series Installation, commissioning and servicing instructions The tempering valve is used to regulate the set temperature of mixed hot and cold water even

More information

Scald Protection Three-Way Thermostatic Mixing Valve

Scald Protection Three-Way Thermostatic Mixing Valve CALEFFI www.caleffi.com 383.04 Scald Protection Three-Way Thermostatic Mixing Valve Copyright 00 Caleffi 3 Series Installation, commissioning and servicing instructions Function Scald Protection Three-Way

More information

Index. Batch processing 56 Branching xiii 52 62

Index. Batch processing 56 Branching xiii 52 62 Index A Accessibility electronic 40 105 of emergency operating procedures 85 of procedures 15 32 Accidental chemical release xiii Administrative procedures xiii 27 Alignment 75 American Petroleum Institute

More information

GM Series Dual-Block Multi-Function Gas Control Valves

GM Series Dual-Block Multi-Function Gas Control Valves Installation Sheets Manual 121 Gas Combustion Combination Controls and Systems Section G Technical Bulletin GM Issue Date 0297 GM Series Dual-Block Multi-Function Gas Control Valves Figure 1: GM Series

More information

Intamix Thermostatic Mixing Valve

Intamix Thermostatic Mixing Valve Intamix Thermostatic Mixing Valve TMV2 & TMV3 Installation Guide Intatec Ltd Airfield Industrial Estate Hixon Staffordshire ST18 0PF In this procedure document we have endeavoured to make the information

More information

RESILIENT SEATED BUTTERFLY VALVES FUNCTIONAL SAFETY MANUAL

RESILIENT SEATED BUTTERFLY VALVES FUNCTIONAL SAFETY MANUAL Per IEC 61508 and IEC 61511 Standards BRAY.COM Table of Contents 1.0 Introduction.................................................... 1 1.1 Terms and Abbreviations...........................................

More information

553 Series.

553 Series. 38467.03 www.caleffi.com Pre-adjustable filling units Copyright 01 Caleffi 3 Series Function The automatic filling valve is a device consisting of a pressure reducing valve with compensating seat, visual

More information

LOCKOUT/TAGOUT PROGRAM

LOCKOUT/TAGOUT PROGRAM LOCKOUT/TAGOUT PROGRAM HOW CLIMATE ENGINEERS INC. COMPLIES WITH THELO/TO STANDARD It is the intent of Climate Engineers Inc. to comply with OSHA s Control of Hazardous Energy Standard (1910.147). The following

More information

This test shall be carried out on all vehicles equipped with open type traction batteries.

This test shall be carried out on all vehicles equipped with open type traction batteries. 5.4. Determination of hydrogen emissions page 1 RESS-6-15 5.4.1. This test shall be carried out on all vehicles equipped with open type traction batteries. 5.4.2. The test shall be conducted following

More information

Hill PHOENIX Second Nature Medium Temperature Secondary Refrigeration Start-Up Guide

Hill PHOENIX Second Nature Medium Temperature Secondary Refrigeration Start-Up Guide Hill PHOENIX Second Nature Medium Temperature Secondary Refrigeration Start-Up Guide Secondary Coolant System Start-Up Procedures June 2006 Produced by the Hill PHOENIX Learning Center DISCLAIMER This

More information

Module No. # 01 Lecture No. # 6.2 HAZOP (continued)

Module No. # 01 Lecture No. # 6.2 HAZOP (continued) Health, Safety and Environmental Management in Petroleum and Offshore Engineering Prof. Srinivasan Chandrasekaran Department of Ocean Engineering Indian Institute Of Technology, Madras Module No. # 01

More information

Installation, commissioning and servicing instructions

Installation, commissioning and servicing instructions 38512.08 Tempering valve www.caleffi.com 5213 series Copyright 2018 Caleffi Installation, commissioning and servicing instructions The tempering valve is used to regulate the set temperature of mixed hot

More information

Title: Standard Operating Procedure for Elemental and Organic Carbon (EC and OC) using Non-Dispersive Infrared Detection (NDIR)

Title: Standard Operating Procedure for Elemental and Organic Carbon (EC and OC) using Non-Dispersive Infrared Detection (NDIR) Procedure No: SOP-025 Revision No: 1.0 (January 21, 2011) Page No.: 1 of 8 1. INTRODUCTION AND SCOPE To obtain timely data for the purpose of air quality assessment, air quality trend reporting and to

More information

TRI LOK SAFETY MANUAL TRI LOK TRIPLE OFFSET BUTTERFLY VALVE. The High Performance Company

TRI LOK SAFETY MANUAL TRI LOK TRIPLE OFFSET BUTTERFLY VALVE. The High Performance Company TRI LOK TRI LOK TRIPLE OFFSET BUTTERFLY VALVE SAFETY MANUAL The High Performance Company Table of Contents 1.0 Introduction...1 1.1 Terms and Abbreviations... 1 1.2 Acronyms... 1 1.3 Product Support...

More information

SEQUENTIAL SHOWER VALVE INSTRUCTION MANUAL PLEASE LEAVE THIS MANUAL WITH THE END USER

SEQUENTIAL SHOWER VALVE INSTRUCTION MANUAL PLEASE LEAVE THIS MANUAL WITH THE END USER SEQUENTIAL SHOWER VALVE INSTRUCTION MANUAL PLEASE LEAVE THIS MANUAL WITH THE END USER CONTENTS 1. INTRODUCTION & SAFETY 1 2. DIMENSIONS 2 3. TECHNICAL DATA 3 4. OPERATION 4 5. COMPONENTS 5 6. SITE INSTALLATION

More information

DeZURIK. KGC Cast Knife Gate Valve. Safety Manual

DeZURIK. KGC Cast Knife Gate Valve. Safety Manual KGC Cast Knife Gate Valve Safety Manual Manual D11036 August 29, 2014 Table of Contents 1 Introduction... 3 1.1 Terms... 3 1.2 Abbreviations... 4 1.3 Product Support... 4 1.4 Related Literature... 4 1.5

More information

Improving distillation tower operation

Improving distillation tower operation Improving distillation tower operation Measuring differential pressure across long sections of distillation columns has always been challenging, but purpose-built sensor systems provide a solution Fast

More information

How to Define Your Systems and Assets to Support Reliability. How to Define Your Failure Reporting Codes to Support Reliability

How to Define Your Systems and Assets to Support Reliability. How to Define Your Failure Reporting Codes to Support Reliability BACKFED RELIABILITY How to Define Your Systems and Assets to Support Reliability How to Define Your Failure Reporting Codes to Support Reliability How to Generate Risk Prioritization Numbers (RPN) from

More information

Twin & Triple Control Concealed Thermostatic Shower Valve

Twin & Triple Control Concealed Thermostatic Shower Valve Twin & Triple Control Concealed Thermostatic Shower Valve Installation & Operating Guide Please leave this installation & user guide with the end user CONTENTS: 1. Introduction & Safety 1 2. Dimensions

More information

Significant Change to Dairy Heat Treatment Equipment and Systems

Significant Change to Dairy Heat Treatment Equipment and Systems Significant to Dairy Heat Treatment September 2008 Page 1 Significant to Dairy Heat Treatment Equipment and Systems September 2008 1 Background Requirements for the assessment of dairy heat treatment equipment

More information

SECTION TESTING, ADJUSTING, AND BALANCING CONTRACT NO SECTION TESTING, ADJUSTING, AND BALANCING

SECTION TESTING, ADJUSTING, AND BALANCING CONTRACT NO SECTION TESTING, ADJUSTING, AND BALANCING SECTION 15990 TESTING, ADJUSTING, AND BALANCING PART 1 -GENERAL 1.01 GENERAL A. This section of the Specifications covers testing and balancing of environmental systems, including, but not limited to distribution

More information

2600T Series Pressure Transmitters Plugged Impulse Line Detection Diagnostic. Pressure Measurement Engineered solutions for all applications

2600T Series Pressure Transmitters Plugged Impulse Line Detection Diagnostic. Pressure Measurement Engineered solutions for all applications Application Description AG/266PILD-EN Rev. C 2600T Series Pressure Transmitters Plugged Impulse Line Detection Diagnostic Pressure Measurement Engineered solutions for all applications Increase plant productivity

More information

SPIROVENT VACUUM DEGASSERS

SPIROVENT VACUUM DEGASSERS SPIROVENT VACUUM DEGASSERS S P I R O V E N T A I R S U P E R I O R FLUID AND GAS There are always a certain amount of gasses in a fluid, dependent on pressure and temperature. The British physicist William

More information

Iteration: while, for, do while, Reading Input with Sentinels and User-defined Functions

Iteration: while, for, do while, Reading Input with Sentinels and User-defined Functions Iteration: while, for, do while, Reading Input with Sentinels and User-defined Functions This programming assignment uses many of the ideas presented in sections 6 and 7 of the course notes. You are advised

More information

ANNEX AMENDMENTS TO THE INTERNATIONAL CODE FOR FIRE SAFETY SYSTEMS (FSS CODE) CHAPTER 15 INERT GAS SYSTEMS

ANNEX AMENDMENTS TO THE INTERNATIONAL CODE FOR FIRE SAFETY SYSTEMS (FSS CODE) CHAPTER 15 INERT GAS SYSTEMS Annex 3, page 2 ANNEX AMENDMENTS TO THE INTERNATIONAL CODE FOR FIRE SAFETY SYSTEMS (FSS CODE) CHAPTER 15 INERT GAS SYSTEMS The text of existing chapter 15 is replaced by the following: "1 Application This

More information

Rate of Flow Valve Series 120

Rate of Flow Valve Series 120 SPECIFICATIONS Rate of Flow Valve Series DIMENSIONS The OCV Series 120 Rate of Flow control valve is designed to control or limit flow to a predetermined rate, regardless offl uctuations in downstream

More information

INSTALLATION & OPERATION MANUAL. Dual Duct VAV Terminals. Redefine your comfort zone.

INSTALLATION & OPERATION MANUAL. Dual Duct VAV Terminals. Redefine your comfort zone. INSTALLATION & OPERATION MANUAL Dual Duct VAV Terminals IOM Dual Duct VAV Terminals IMPORTANT! READ BEFORE PROCEEDING! GENERAL SAFETY GUIDELINES This equipment is a relatively complicated apparatus. During

More information

DB 61 Dolphin TMV3 Integrated Thermostatic Mixing Valve

DB 61 Dolphin TMV3 Integrated Thermostatic Mixing Valve INSTALLATION AND MAINTENANCE GUIDE DB 61 Dolphin TMV3 Integrated Thermostatic Mixing Valve Saving water, saving power, promoting hygiene Important: Read carefully before installing product DOLPHIN Revision

More information

GeQuip Joule Thomson Plant. Process Description (see Figure 1) Standard Control Instrumentation

GeQuip Joule Thomson Plant. Process Description (see Figure 1) Standard Control Instrumentation Process Description (see Figure 1) The purpose of the process configuration of a Joule Thomson plant is to refrigerate the gas by expanding the gas across a restriction (commonly referred to as a choke

More information

OHD L-47. Guidelines for Resolving Differences in Test Results

OHD L-47. Guidelines for Resolving Differences in Test Results Guidelines for Resolving Differences in Test Results Page 1 of 21 1 SCOPE 1.1 The guidelines provided are as follows: 1.1.1 Standard Practice for the Evaluation of Different Superpave Gyratory Compactors

More information

Scald Protection 3-Way Thermostatic Mixing Valve

Scald Protection 3-Way Thermostatic Mixing Valve 383.06 www.caleffi.com Scald Protection 3-Way Thermostatic Mixing Valve Copyright 06 Caleffi 3 Series Installation, commissioning and servicing instructions Function Scald Protection Three-Way Thermostatic

More information

GN 2 CONSTANT FLOW REGULATORS. GUIDANCE NOTE GN 2 Constant Flow Regulators. Page 1 COMMISSIONING SPECIALISTS ASSOCIATION.

GN 2 CONSTANT FLOW REGULATORS. GUIDANCE NOTE GN 2 Constant Flow Regulators. Page 1 COMMISSIONING SPECIALISTS ASSOCIATION. GUIDANCE NOTE GN 2 Constant Flow Regulators Page 1 2017 Edition GUIDANCE NOTE GN2 CONSTANT FLOW REGULATORS Written By M. Lowe, Hattersley Newman Hender Ltd COMPILED BY THE TECHNICAL SUB-COMMITTEE OF THE

More information

User Manual for the Mars Calibration Bench

User Manual for the Mars Calibration Bench User Manual for the Mars Calibration Bench Fall 2013 Table of Contents Table of Contents Table of Contents... iii Introduction... v Chapter 1: The Mars Calibration Bench... 1 What Is the Mars Calibration

More information

DeZURIK. KSV Knife Gate Valve. Safety Manual

DeZURIK. KSV Knife Gate Valve. Safety Manual KSV Knife Gate Valve Safety Manual Manual D11035 August 29, 2014 Table of Contents 1 Introduction... 3 1.1 Terms... 3 1.2 Abbreviations... 4 1.3 Product Support... 4 1.4 Related Literature... 4 1.5 Reference

More information

CSC-2000 SERIES. Reset Volume Controllers MADE IN U.S.A. DESCRIPTION MODELS SPECIFICATIONS ORDERING

CSC-2000 SERIES. Reset Volume Controllers MADE IN U.S.A. DESCRIPTION MODELS SPECIFICATIONS ORDERING CSC-2000 SERIES Reset Volume Controllers MADE IN U.S.A. DESCRIPTION The CSC-2000 series are designed for use on VAV terminal units in HVAC systems. These are submaster air velocity controllers whose velocity

More information

Technical Service Bulletin March 2015 TSB142.01

Technical Service Bulletin March 2015 TSB142.01 Technical Service Bulletin March 2015 TSB142.01 Commissioning Procedure for HYDRAcap This Technical Service Bulletin provides information for commissioning of a HYDRAcap membrane system in a water treatment

More information

Tempering valve for solar and instantaneous applications Installation, commissioning and servicing instructions 2522HP series

Tempering valve for solar and instantaneous applications Installation, commissioning and servicing instructions 2522HP series www.reece.com.au 28255.01 Tempering valve for solar and instantaneous applications 2522HP series Installation, commissioning and servicing instructions The tempering valve is used to regulate the set temperature

More information

This portion of the piping tutorial covers control valve sizing, control valves, and the use of nodes.

This portion of the piping tutorial covers control valve sizing, control valves, and the use of nodes. Piping Tutorial A piping network represents the flow of fluids through several pieces of equipment. If sufficient variables (flow rate and pressure) are specified on the piping network, CHEMCAD calculates

More information

Rotary Abreast Automatic Teat Sprayer User Manual. Technical Manual Revision 0.01

Rotary Abreast Automatic Teat Sprayer User Manual. Technical Manual Revision 0.01 Rotary Abreast Automatic Teat Sprayer Technical Manual 006911 Revision 0.01 Contents Contents... 2 Important information - read this first... 3 Icons... 3 1. Introduction... 4 2. Intended Use... 4 3. General

More information

HVAC Hydronic Pumps: B&G Triple Duty Valve for Proportional Balance

HVAC Hydronic Pumps: B&G Triple Duty Valve for Proportional Balance Monday, April 2, 2018 HVAC Hydronic Pumps: B&G Triple Duty Valve for Proportional Balance Monday Morning Minutes by Norm Hall, April 2, 2018 The ASHRAE Standard 90.1-2013 and the State of Michigan 2015

More information

PH01 Perfusion Cannula Manual

PH01 Perfusion Cannula Manual PH01 Perfusion Cannula Manual Information in this document is subject to change without notice. No part of this document may be reproduced or transmitted without the express written permission of Multi

More information

Burner Management System DEMO Operating instructions

Burner Management System DEMO Operating instructions Burner Management System DEMO Operating instructions Burner Management System DEMO Operating Instructions Startup Summary - Normal startup is accomplished in four basic steps: 1. Leak Test a. Safety Valve

More information

MANUAL DIRECT PURGE OPTION. UNION Instruments GmbH CWD2005 PLUS. General information, safety standards and regulations for direct purge option

MANUAL DIRECT PURGE OPTION. UNION Instruments GmbH CWD2005 PLUS. General information, safety standards and regulations for direct purge option MANUAL DIRECT PURGE OPTION UNION Instruments GmbH CWD2005 PLUS General information, safety standards and regulations for direct purge option Version: V1.00 Stand: 24.03.2010 Union Instruments GmbH Zeppelinstr.

More information

CSC-2000 SERIES. Reset Volume Controllers MADE IN U.S.A. DESCRIPTION MODELS SPECIFICATIONS ORDERING

CSC-2000 SERIES. Reset Volume Controllers MADE IN U.S.A. DESCRIPTION MODELS SPECIFICATIONS ORDERING CSC-2000 SERIES Reset Volume Controllers MADE IN U.S.A. DESCRIPTION The CSC-2000 series are designed for use on VAV terminal units in HVAC systems. These are submaster air velocity controllers whose velocity

More information

This manual provides necessary requirements for meeting the IEC or IEC functional safety standards.

This manual provides necessary requirements for meeting the IEC or IEC functional safety standards. Instruction Manual Supplement Safety manual for Fisher Vee-Ball Series Purpose This safety manual provides information necessary to design, install, verify and maintain a Safety Instrumented Function (SIF)

More information

CHEMICAL ENGINEERING LABORATORY CHEG 239W. Control of a Steam-Heated Mixing Tank with a Pneumatic Process Controller

CHEMICAL ENGINEERING LABORATORY CHEG 239W. Control of a Steam-Heated Mixing Tank with a Pneumatic Process Controller CHEMICAL ENGINEERING LABORATORY CHEG 239W Control of a Steam-Heated Mixing Tank with a Pneumatic Process Controller Objective The experiment involves tuning a commercial process controller for temperature

More information

IE098: Advanced Process Control for Engineers and Technicians

IE098: Advanced Process Control for Engineers and Technicians IE098: Advanced Process Control for Engineers and Technicians IE098 Rev.001 CMCT COURSE OUTLINE Page 1 of 6 Training Description: Advanced Process Control and Loop Tuning and Analysis is designed to provide

More information

MANAGEMENT PROCEDURE FOR LABORATORY VENTILATION

MANAGEMENT PROCEDURE FOR LABORATORY VENTILATION UNIVERSITY OF ALASKA FAIRBANKS SAFETY SYSTEM POLICY AND PROCEDURE DOCUMENT NUMBER: 508 ISSUE DATE: SEPTEMBER 1996 SUBJECT: Management Procedure for Laboratory Ventilation MANAGEMENT PROCEDURE FOR LABORATORY

More information

Standard Pneumatic Test Procedure Requirements for Piping Systems

Standard Pneumatic Test Procedure Requirements for Piping Systems the pressure equipment safety authority Standard Pneumatic Test Procedure Requirements for Piping Systems AB-522 Edition 2, Rev. 1 Issued 2016-10-24 Table of Contents FOREWORD... 1 1.0 INTRODUCTION...

More information

GRUNDFOS industry GRUNDFOS CR MONITOR. Intelligent warning

GRUNDFOS industry GRUNDFOS CR MONITOR. Intelligent warning GRUNDFOS industry GRUNDFOS CR MONITOR Intelligent warning Look into the future with the CR monitor Tired of having to overhaul your pumps on a regular basis only to find that they are operating flawlessly?

More information

HOW TO MANAGE VAPORIZATION IN AN ANALYTICAL SYSTEM By Dean Slejko and Tony Waters

HOW TO MANAGE VAPORIZATION IN AN ANALYTICAL SYSTEM By Dean Slejko and Tony Waters HOW TO MANAGE VAPORIZATION IN AN ANALYTICAL SYSTEM By Dean Slejko and Tony Waters If the analyzer in your analytical system requires gas but your sample is liquid, the only option is to convert the liquid

More information

Risk Management Series Article 8: Risk Control

Risk Management Series Article 8: Risk Control Risk Management Series Foreword MEDIcept presents this ongoing series of articles focused on the implementation and practical conduct of risk management in the medical device industry to provide practitioners

More information

Operating Manual Body fat balance

Operating Manual Body fat balance KERN & Sohn GmbH Ziegelei 1 D-72336 Balingen email: info@kern-sohn.com Phone: +49-[0]7433-9933-0 Fax: +49-[0]7433-9933-149 Internet: www.kern-sohn.com Operating Manual Body fat balance KERN MFB Version

More information

OPERATING PROCEDURES

OPERATING PROCEDURES OPERATING PROCEDURES 1.0 Purpose This element identifies Petsec s Operating Procedures for its Safety and Environmental Management System (SEMS) Program; it applies to all Petsec operations. Petsec is

More information

Manual of SF6 Comprehensive Tester

Manual of SF6 Comprehensive Tester Manual of SF6 Comprehensive Tester Important Description All the staff taking in charge of the usage or maintenance of this product should carefully read this manual. The same as any other complicated

More information

Safety manual for Fisher GX Control Valve and Actuator

Safety manual for Fisher GX Control Valve and Actuator Instruction Manual Supplement GX Valve and Actuator Safety manual for Fisher GX Control Valve and Actuator Purpose This safety manual provides information necessary to design, install, verify and maintain

More information

Important considerations for use of Cembrane

Important considerations for use of Cembrane Important considerations for use of Cembrane Content Civil Works Handling Measuring Instruments Hydraulic System Installation & Start-up Others Civil works Accuracy of tank Fixation of position holder

More information

Installation Instructions and User Guide 15mm & 22mm Thermostatic Mixing Valve

Installation Instructions and User Guide 15mm & 22mm Thermostatic Mixing Valve Installation Instructions and User Guide 15mm & 22mm Thermostatic Mixing Valve TMV3 / TMV2 Combined Valve C85079 C85081 C85080 C85082 It is important that these guidance notes are read and fully understood

More information

bathrooms.com Concentric Thermostatic Shower Mixers Cleaning and Care Installation Manual Contents

bathrooms.com Concentric Thermostatic Shower Mixers Cleaning and Care Installation Manual Contents bathrooms.com Concentric Thermostatic Shower Mixers Contents Page 3 - General Information & Safety Page 4 - Installation Page 5 - Concentric Valve Set-up Page 6 - Exposed fitting of Concentric Mixer Valves

More information

Discharge Relief Valve Operation & Maint.

Discharge Relief Valve Operation & Maint. Relief Valve Operation & Maint. CZ Series Centrifugal Fire Relief svalve Operation and Maintenance Instructions 1410 Operation and Maintenance Form No. F-1031 Section 2302.6 2111 Issue Date 04/90 11/95

More information

Lockout/Tagout Training Overview. Safety Fest 2013

Lockout/Tagout Training Overview. Safety Fest 2013 Lockout/Tagout Training Overview Safety Fest 2013 Purpose of Lockout/Tagout The standard covers the servicing and maintenance of machine and equipment in which the unexpected energization or start up of

More information

Exercise 2-2. Second-Order Interacting Processes EXERCISE OBJECTIVE DISCUSSION OUTLINE. The actual setup DISCUSSION

Exercise 2-2. Second-Order Interacting Processes EXERCISE OBJECTIVE DISCUSSION OUTLINE. The actual setup DISCUSSION Exercise 2-2 Second-Order Interacting Processes EXERCISE OBJECTIVE Familiarize yourself with second-order interacting processes and experiment with the finer points of controller tuning to gain a deeper

More information

Code Basic module and level control complete with optionals code

Code Basic module and level control complete with optionals code AUTOMATION AND PROCESS CONTROL MPCT - Modular Process Control Trainer Code 916960 Basic module and level control complete with optionals code 916961-916962-916963-916964-916965 1. General Didacta proposes

More information

TExT Thorough Examination & Test of LEV Local Exhaust Ventilation Systems

TExT Thorough Examination & Test of LEV Local Exhaust Ventilation Systems ILEVE -Institute of LEV Engineers CPD & Information Day TExT Thorough Examination & Test of LEV Local Exhaust Ventilation Systems Jane Bastow CMIOSH Chartered Safety and Health Practitioner OSCHR Registered

More information

Drift-Chamber Gas System Controls Development for the CEBAF Large Acceptance Spectrometer

Drift-Chamber Gas System Controls Development for the CEBAF Large Acceptance Spectrometer Drift-Chamber Gas System Controls Development for the CEBAF Large Acceptance Spectrometer M. F. Vineyard, T. J. Carroll, and M. N. Lack Department of Physics University of Richmond, VA 23173 ABSTRACT The

More information

Safe management of industrial steam and hot water boilers A guide for owners, managers and supervisors of boilers, boiler houses and boiler plant

Safe management of industrial steam and hot water boilers A guide for owners, managers and supervisors of boilers, boiler houses and boiler plant Health and Safety Executive Safe management of industrial steam and hot water boilers A guide for owners, managers and supervisors of boilers, boiler houses and boiler plant Background Accidents involving

More information

Ingersoll Rand. X-Series System Automation

Ingersoll Rand. X-Series System Automation Ingersoll Rand -Series System Automation Energy Savings on Demand! Ingersoll Rand As much as 20% to 60% of the energy used to operate compressed air systems is wasted. This is primarily due to operating

More information

Solenoid Valves used in Safety Instrumented Systems

Solenoid Valves used in Safety Instrumented Systems I&M V9629R1 Solenoid Valves used in Safety Instrumented Systems Operating Manual in accordance with IEC 61508 ASCO Valves Page 1 of 7 Table of Contents 1 Introduction...3 1.1 Terms and Abbreviations...3

More information

CTC 1000 Series One-Pipe, Pneumatic Room Thermostat, Single Temperature

CTC 1000 Series One-Pipe, Pneumatic Room Thermostat, Single Temperature Thermostats CTC 1000 Series One-Pipe, Pneumatic Room Thermostat, Single Temperature Description The CTC 1000 series room thermostats are for use in HVAC systems for the control of pneumatic valves and

More information

Simple Set. Pressure Independent Control Valves 2 Way 1/2-2

Simple Set. Pressure Independent Control Valves 2 Way 1/2-2 The Bray Simple Set is a threaded pressure independent control (PIC) valve designed for a wide variety of hot water and chilled water control applications. The SS Series combines high rangeability control

More information

Four common PRESSURE CALIBRATION PAIN POINTS

Four common PRESSURE CALIBRATION PAIN POINTS Four common PRESSURE CALIBRATION PAIN POINTS Pressure calibration is often critical to process control systems, helping to optimize operations and ensure plant safety. While pressure instrumentation can

More information

How to Do Flight Testing for TARC. Trip Barber NAR TARC Manager

How to Do Flight Testing for TARC. Trip Barber NAR TARC Manager How to Do Flight Testing for TARC Trip Barber NAR TARC Manager The TARC Cycle Learn the rules and basic rocketry Design and fly your rocket on the computer Build your rocket to your design with real hardware

More information

Ultima. X Series Gas Monitor

Ultima. X Series Gas Monitor Ultima X Series Gas Monitor Safety Manual SIL 2 Certified " The Ultima X Series Gas Monitor is qualified as an SIL 2 device under IEC 61508 and must be installed, used, and maintained in accordance with

More information

Pressure Systems Safety Regulation

Pressure Systems Safety Regulation Pressure Systems Safety Regulation Introduction This document informs Faculty of the key requirements of the UK and Chinese Pressure Systems Safety regulations. The aim of these regulations is to prevent

More information

TMV3 Requirements IMPORTANT Installer:

TMV3 Requirements IMPORTANT Installer: TMV3 Requirements IMPORTANT Installer: This Manual is the property of the customer and must be retained with the product for maintenance and operational purposes. 1 1173533-W2-C General The information

More information

Eutectic Plug Valve. SIL Safety Manual. SIL SM.015 Rev 0. Compiled By : G. Elliott, Date: 19/10/2016. Innovative and Reliable Valve & Pump Solutions

Eutectic Plug Valve. SIL Safety Manual. SIL SM.015 Rev 0. Compiled By : G. Elliott, Date: 19/10/2016. Innovative and Reliable Valve & Pump Solutions SIL SM.015 Rev 0 Eutectic Plug Valve Compiled By : G. Elliott, Date: 19/10/2016 Contents Terminology Definitions......3 Acronyms & Abbreviations...4 1. Introduction..5 1.1 Scope 5 1.2 Relevant Standards

More information

CAST IRON SAFETY VALVE TYPE 6301

CAST IRON SAFETY VALVE TYPE 6301 CHARACTERISTICS The 6301 safety valve is dedicated to protect the equipment from potential overpressure. This is an automatic device that closes when the pressure conditions are back to normal. It is a

More information

STICTION: THE HIDDEN MENACE

STICTION: THE HIDDEN MENACE STICTION: THE HIDDEN MENACE How to Recognize This Most Difficult Cause of Loop Cycling By Michel Ruel Reprinted with permission from Control Magazine, November 2000. (Most figures courtesy of ExperTune

More information

M-06 Nitrogen Generator (Nitrogen Making Machine)

M-06 Nitrogen Generator (Nitrogen Making Machine) Guideline No.M-06 (201510) M-06 Nitrogen Generator (Nitrogen Making Machine) Issued date: 20 th October, 2015 China Classification Society Foreword This Guideline is a part of CCS Rules, which contains

More information

29th Monitoring Research Review: Ground-Based Nuclear Explosion Monitoring Technologies

29th Monitoring Research Review: Ground-Based Nuclear Explosion Monitoring Technologies IMPROVED CALIBRATION AND OPERATION OF A STABLE-GAS QUANTIFICATION MANIFOLD AS PART OF A RADIOXENON COLLECTION SYSTEM ABSTRACT Richard M. Williams, James C. Hayes, and Randy R. Kirkham Pacific Northwest

More information