SAFETY REQUIREMENTS FOR CARRIAGE OF LIQUEFIED HYDROGEN IN BULK. Risk assessment of liquefied hydrogen carriers. Submitted by Japan SUMMARY

Size: px
Start display at page:

Download "SAFETY REQUIREMENTS FOR CARRIAGE OF LIQUEFIED HYDROGEN IN BULK. Risk assessment of liquefied hydrogen carriers. Submitted by Japan SUMMARY"

Transcription

1 E SUBCOMMITTEE ON CARRIAGE OF CARGOES AND CONTAINERS rd session Agenda item 4 CCC /INF.0 July 06 ENGLISH ONLY SAFETY REQUIREMENTS FOR CARRIAGE OF LIQUEFIED HYDROGEN IN BULK Risk assessment of liquefied hydrogen carriers Submitted by Japan SUMMARY Executive summary: This document introduces the outline of the risk assessment of liquefied hydrogen carriers conducted by Japan Strategic direction: 5. Highlevel action: 5.. Output: Action to be taken: Paragraph 7 Related documents: CCC /4; CCC /4 and CCC /4/ Background In the Correspondence Group on Development of Safety Requirements for Carriage of Liquefied Hydrogen in Bulk, it was recommended by some participants to conduct a risk assessment of liquefied hydrogen carriers prior to the development of the safety requirements for such ships. Japan considers that the risk assessment should be conducted in the design spiral. Hazard Identification studies As part of the safety risk assessment, Hazard Identification (HAZ) studies were carried out using a preliminary design of liquefied hydrogen carrier based on the existing LNG carrier technologies, practices and the revised IGC Code requirements, to identify additional hazards for liquefied hydrogen carriers in the Front End Engineering Design (FEED) stage. For the purpose of the studies, it was assumed that Gas Combustion Units (GCUs) would be permitted by the Administration.

2 Page The HAZ studies were performed using two different approaches and with participants from different areas of expertise to cover all the potential hazards. As a result of the risk assessment (i.e. HAZ) several hazards were identified, some of which were found to require additional risk reducing measures. The outline of the HAZ is set out in the annex to this document. 4 A detailed analysis of these additional measures was conducted at a later stage separate from the HAZ studies. The outline of the analysis is set out in the annex. Findings 5 This analysis revealed that, while most of the additional measures were properly covered by the special requirements proposed in the annex to CCC /4, an additional risk reducing measure to minimize the number of bolted flange connections of hydrogen piping could be incorporated into the draft interim recommendations for carriage of liquefied hydrogen in bulk. 6 Furthermore, through the analysis, it was found that the following issues can be incorporated into the draft interim recommendations as the items to be considered in the risk assessment at the design stage:. venting release scenarios which might catch fire by lightning to be identified;. fire suppression system (e.g. snuffing system) of vent mast for fire by lightning to be investigated;. LNG numerical models for liquefied hydrogen release scenarios to be verified for elimination of sources of ignitions;.4 Human Factor Engineering for designing access route to critical equipment;.5 theoretical assessment on Boiling Liquid Expanding Vapour Explosion and Rapid Phase Transitions to be investigated;.6 congestions of piping (turbulence which may cause detonation) Compressor house/pipe racks/pressurized Gas Combustion Unit to be studied; and.7 implication of small volume spill on Emergency Shut Down disconnection to be considered. Actions requested of the SubCommittee 7 The SubCommittee is invited to note the outline of the risk assessment set out in the annex. ***

3 Annex, page ANNEX OUTLINE OF THE HAZARD ENTIFICATION STUDIES OF LIQUEFIED HYDROGEN CARRIERS AND ANALYSIS Introduction Kawasaki Heavy Industries, Ltd. has been in charge of research and development of a,500 m liquefied hydrogen carrier, which is expected to be the first vessel to carry bulk liquefied hydrogen in the world. As part of the safety risk assessment, Hazard Identification (HAZ) studies were carried out using a Front End Engineering Design of liquefied hydrogen carrier based on the existing LNG carrier technologies, practices and the IGC Code requirements, to identify additional hazards for liquefied hydrogen carriers in the Front End Engineering Design stage. The HAZ studies were performed by two different approaches with participants from different areas of expertise to cover all the potential hazards. The primary purpose of the first HAZ study was to identify and classify potential hazards. For this purpose, brainstorming was conducted to identify cause, location and consequence related to the cargo handling system and cargo containment system in each operational stage with a particular focus put on the differences in the physical features of cargoesrelated systems of conventional LNG carriers and the project liquefied hydrogen carrier. This HAZ study was performed under the premise that the requirements in the revised IGC Code and the draft requirements proposed in the annex to document CCC /4 were satisfied. The purpose of the second HAZ study * was to enumerate wider hazards based on the knowledge of experts to the fullest extent possible. For this purpose, another brainstorming was conducted to identify hazards associated with onshore facilities, e.g. mooring system, loading arm system, and natural hazards, e.g. earthquake, lightning, more extensively by a small number of experts, without considering the above mentioned requirements in the Code and the annex to document CCC /4. After the second HAZ study, the safety measures identified in the study were compared with the above mentioned requirements. Then additional safety measures which may be incorporated into the draft interim recommendations were identified. First HAZ study. Participants The first HAZ study was held from 5 to 7 of October 05, attended by the following experts from various fields related to seaborne carriage of liquefied gas in Japan: From ClassNK Consulting Service Co., Ltd.: Facilitator (expert in risk assessment); and A secretary; From Nippon Kaiji Kyokai (ClassNK): An expert in ship hull design; An expert in cargo containment system; and An expert in cargo handling systems; * This HAZ study was conducted as part of Shell's riskbased approach associated with liquefied hydrogen project (ship & terminal)

4 Annex, page From Japan Marine Science Inc.: Three experts in the deck operation of gas carriers (including a captain); From National Maritime Research Institute: Three experts in risk analysis; From Kawasaki Heavy Industries, Ltd.: Eight experts in ship design; Two experts in risk assessment; and An expert in cryogenic engineering. Some more members from Kawasaki Heavy Industries, Ltd. attended the study for the explanation on the Front End Engineering Design and its operation.. Scope of study A,500 m liquefied hydrogen carrier, as illustrated in Figure, was utilized as a baseline specification for hazard identification and risk evaluation. The main particulars of the vessel were as follows; Ship principal particulars Dimensions: Gross tonnage: Maximum continuous output: Speed: Persons on board Endurance L PP : m x B: 9.00 m x D: 0.60 m abt. 8,000 tons,650 kw x 40 rpm abt..0 knots (including 50% sea margin) 5 persons abt. 0,000 nautical miles Cargo containment system Total capacity:,500 m (No. & No. :,50 m each) Tank type: IMO independent cylindrical type C Max. design pressure: 0.4 MPaG Min. design temperature: 5 C (0 K) Tank material: Austenitic stainless steel Insulation system: Vacuum insulation + panel pnsulation Press. & temp. control system: Pressure accumulation. Procedures of study In the study, so called "SWIFT", i.e. Structured What If Technique, which is commonly utilized for this kind of study in various industries, was applied. The procedures utilized in the HAZ were; Step Define area of assessment Step Brief the design/operation of the area Step Identify possible hazards by brainstorming for each operational stage Step 4 Consider possible consequences based on existing safeguards Step 5 Assign frequency and severity of each hazard Step 6 Evaluate whether or not additional safeguards are needed Step 7 Record the discussion

5 Annex, page Relevant hazards were discussed by considering various hazardous scenarios in the following operational stages one by one during the study:. Loading;. Seagoing;. Unloading;.4 Dock in; and.5 Dock out; These operational stages were further classified into 'Study nodes' (i.e. substages) based on the sequence of each cargo operation to promote the efficiency of the study as shown in figure. Guidewords shown in table were used to aid the identification of hazards. The frequency and severity of each hazard scenario identified were evaluated, and indices of frequency (FI) and severity (, and risk ranking matrix were determined based on the scale given in table, table and figure respectively. To evaluate frequency of each scenario, statistical incident data of maritime and oil and gas industries were used. The risk of each scenario was evaluated to determine the necessity of additional risk reducing measures..4 Results Table 4 shows the hazards identified in the study. Figure 4 shows the risk category of each of these hazards. Second HAZ study. Participants The second HAZ study was held from to 4 December 05, attended by the following 7 experts of liquefied natural gas carriers: From Shell International Trading and Shipping Company Limited: Facilitator (expert in risk assessment); An expert in cryogenic engineering; An expert in instrumentation and control engineering; and Two experts on the deck operation of gas carriers (including a captain); From Nippon Kaiji Kyokai (ClassNK): An expert in ship hull design; An expert in cargo containment system; and An expert in cargo handling systems; From Kawasaki Heavy Industries, Ltd.: Six experts in ship design; Two experts in risk assessment; and An expert in cryogenic engineering; IHS Maritime World Casualty Statistics; Offshore reliability data.

6 Annex, page 4. Procedures of study In this study, 'SWIFT' was applied as described in section. considering various scenarios in the operational stages in figure. The following guidewords in addition to those in table were used: Natural and environmental hazards Extreme weather conditions (e.g. wave, wind, temperature, snow, blizzards, fog) Lightning Earthquake Manmade hazards (terrorism, security threat) Environmental impact of facilities to the environment The definitions of Frequency Index (FI), Severity Index ( and risk ranking matrix, which are Shell engineering standard, are shown in table 5, table 6 and figure 5, respectively. According to Shell engineering standard, those identified as "S: SERIOUS" and "H: HIGH" in figure 5 are recommended to reduce the risk to "M: MEDIUM" or lower.. Results In the study, 89 hazards were identified as listed in table 7. Figure 6 shows the hazard risk rankings determined after the HAZ study based on the above mentioned definitions without taking into account any safety measures in the revised IGC Code and the annex to document CCC /4. 4 Analysis of results of HAZ studies 4. Result of Correspondence Group Special requirements Nos. to were proposed in the annex to document CCC /4, prior to the establishment of the Correspondence Group on Development of Safety Requirements for Carriage of Liquefied Hydrogen in Bulk (CG). Then, draft special requirements Nos. to 7 were proposed in the CG as set out in the annex to document CCC /4. 4. First HAZ study The risk reducing measures identified in the first HAZ study were compared with the draft special requirements proposed in the CG. Table 8 shows the result of comparison. In this table SR No. means the number of the draft special requirements proposed in the CG. As shown in the table, no additional requirements were identified. 4. Second HAZ study The risk reducing measures identified in the second HAZ study were analysed in relation to the safety requirements in the revised IGC Code and in the annex to document CCC /4, for the reason that the safety requirements had not been considered in the second HAZ study. Through the analysis, risk reducing measures additional to the safety requirements were identified. The additional risk reducing measures were compared with the draft special requirements proposed in the CG. Table 9 shows the result of comparison.

7 Annex, page 5 As shown in the table, the following risk reducing measure is not covered in the result of the CG: Reducing number of flange connections (preferable for more welded pipe systems) to be considered for hydrogen leakage. Therefore, the following new special requirement can be incorporated into the draft interim recommendations: Minimize number of bolted flange connections of hydrogen piping. The following are deemed as the issues to be considered in the risk assessment at the design stage required by SR No.5: Venting release scenarios which might catch fire by lightning to be identified. Fire suppression system (e.g. snuffing system) of vent mast for fire by lightning to be investigated. LNG numerical models for liquefied hydrogen release scenarios to be verified for elimination of sources of ignitions. Human factor engineering for designing access route to critical equipment. Theoretical assessment on boiling liquid expanding vapour explosion and rapid phase transitions to be investigated. Congestions of piping (turbulence which may cause detonation) compressor house/pipe racks/ pressurized gas combustion unit to be studied. Implication of small volume spill on Emergency Shut Down disconnection to be considered. Therefore, the above mentioned issues can be incorporated into the draft interim recommendations as the items to be considered in the risk assessment at the design stage required by SR No.5 Figure : General arrangement

8 Annex, page 6. Unloading 4. Dock in Unloading Warm Up Piping Cool Down Drain off / Purge Inerting (GH > GN) Tank Pressure Drop off Aeration (GN > Air). Seagoing Laden Voyage Ballast Voyage Dry Dock*. Loading 5. Dock out Tank Pressure Drop off Inerting (Air > GN) Piping Cool Down Ballast Voyage* Drain off / Purge Tank Cool down Gassing Up (GN > GH) Loading Initial Cool Down * not considered in these studies Figure : Operational stages and study nodes (common to the first and the second HAZ studies)

9 Frequency Index (FI) CCC /INF.0 Annex, page 7 6 H H H H 5 M H H H 4 M M H H M M M H L M M M L L M M 4 Severity index ( Notes: H: High Risk shall be reduced M: Medium Risk should be reduced as reasonably practicable L: Low No risk reduction measures are required. Figure : Risk ranking matrix (first HAZ study) Frequency Index (FI) , 8, 6, 6,,, 4,,, 54, 55 7, 0, 6, 9, 0,,, 9, 40, 48, 50,, 0, 5, 6, 4 5, 4, 56 8, 9, 4, 7, 5, 8, 6 4, 6, 7 4 Severity Index ( Figure 4: Risk category of each hazard (first HAZ study) Frequency Index (FI) E L M H S S S D L M H H S S C L M M H H S B L L M M H H A L L L M M H Severity Index ( Notes: S: SERIOUS Identify and implement controls and recovery measures to reduce risk to ALARP and provide a document demonstration of ALARP by a bowtie or equivalent methodology. H: HIGH Identify and implement controls and recovery measures to reduce risk to ALARP. M: MEDIUM Manage for continuous improvement through the effective implementation of the HSSE management system. L: LOW Manage for continuous improvement, although businesses may set lower priority for further risk reduction. HSSE Health, Safety, Security and Environment Figure 5: Risk ranking matrix (second HAZ study)

10 Annex, page 8 Frequency Index E D 48 C B,,,, 87 5, 40, 67, 68 90, A 57, 80, 8, 5, 75 84, 85 9, 4, 45, 7, 7, 74, 77 0, 46, 47, 49, 70, 7, 78 4, 7, 8, 9 6, 8, 5, 9, 6 50, 5, 54, 55, 58, 59, 60, 6, 6, 64, 76 4, 7, 8, 9,, 6, 7, 8,, 6, 4, 5, 6, 4, 5, 56, 65, 79, 8, 86, 9 66, 69, 8 88, 89 0, 7, 0,,,, 4, Severity Index Figure 6: Risk ranking matrix without safety measures (second HAZ study) Table : Guidewords used for identification of hazards (first HAZ study) LH CH FGH DH EFH HE Guidewords Layout hazards Gas dangerous zone Ignition source Access/maintenance Escape/evacuation/rescue Cryogenic hazards Low temperature property changes Low temperature embrittlement Thermal contraction Cold burn Flammable gas/liquid hazards Flammable limit Dispersion Fire (flash, jet and pool fire) Explosion Asphyxiation Deterioration hazards Vacuum Erosion and corrosion Equipment failure hazards Leakage (e.g. piping/valve/flange/diaphragm/gasket/seal) Instrumentation air/hydraulic Sensors Control System Human errors Operational error Lack of maintenance

11 Annex, page 9 Table : Definition of Frequency Index (first HAZ study) FI Frequency Definition (per ship year) 6 Occurs several times per year per ship 0 < P 5 Occurs several times per year per operator 0 < P < 0 4 Has been experienced by most operators 0 < P < 0 Some accidents have occurred in the industry 0 4 < P < 0 Never heard of in the industry 0 5 < P < 0 4 Failure is not expected P < 0 6 Table : Definition of Severity Index (first HAZ study) SI Severity 4 Catastrophic Severe Significant Minor Definition Effect on humans (conversion to death toll) Effect on the vessel (required repair) Multiple fatalities Total lost (0 ) (in dock) Single fatality or multiple Severe damage severe injuries (0 0 ) (in dock) Multiple or severe injuries Nonsevere ship damage (0 ) (at berthing) Single or minor injuries Local equipment damage (0 ) (on board)

12 Annex, page 0 Table 4: List of identified hazards (first HAZ) Hazard Guide Possible Cause (FI/ word consequences Measures (Prevention) Operational stage: Loading Loading (Ship / Shore interface procedure after berthing) Manifold of HE Gas sampling during cargo line FGH manifold purging Residual GH Observation of (FI:,SI:) Operation Manual Insufficient manifold purging by GN due to misoperation when disconnecting the cargo piping after unloading GH leakage from shore connection around loading station when a blind flange is disconnected Formation of flammable atmosphere due to GH leakage Risk of gas ignition if ignition source is within flammable atmosphere Measures (Mitigation) Hazardous area to be designed around manifold including provision of safety apparatus to prevent thermal or mechanical explosion Dry chemical powder fireextinguishing system to be installed Water spray system to be installed Portable gas detector to be provided Personal protection equipment to be provided according to ISO/TR 596 requirements Risk Reducing Measures In accordance with ISO/TR 596, the Operation Manual shall state that generally a hydrogen fire is not extinguished until the hydrogen source has been eliminated, because of the danger of ignition of a large combustible cloud that could form from the unburned hydrogen Operation manual shall state that cleaning and purging of the manifold should be carried out periodically during voyage

13 Annex, page Hazard Guide Possible Cause (FI/ word consequences Measures (Prevention) Manifold of hot HE Same as GH leakage from shore Observation of GH line FGH connection around Operation Manual Residual GH loading station when a (FI:,SI:) blind flange is disconnected Formation of flammable atmosphere due to GH leakage Risk of gas ignition if ignition source is within the flammable atmosphere Operational stage: Loading Manifold Purging (Air to N Gas) No specific hazards are identified, for the reason that the operation is the same as the operation of LNG. Operational stage: Loading Manifold Purging (N Gas to Hot H Gas) No specific hazards are identified, for the reason that the operation is similar to the operation of LNG. Operational stage: Loading Inner shell Pressure Drop Off No specific hazards are identified, for the reason that the operation is similar to the operation of LNG. Risk Reducing Measures (Mitigation) Measures Same as Same as

14 Annex, page Hazard Guide (FI/ word Cause Operational stage: Loading Cool Down (Cargo Piping) 6 Cargo liquid line HE Malfunction of Significant EFH shore LH facilities thermal stress CH Flow rate from the due to a shore supply is too thermal high gradient Low temperature outside of the from shore supply allowable Nonobservance of range Operation Manual (FI:,SI:) Insufficient monitoring of temperature Possible consequences Damage to cargo liquid line due to significant thermal stress on cargo liquid line between shore connection and cargo Loss of vacuum in cargo piping vacuum insulation system Formation of LO/LN around out side of double wall piping Cryogenic damage to ship structure due to exposure through dripping/contact with LO/LN Measures (Prevention) Stress calculations for cargo piping including thermal stress to be carried out and approved by class Monitoring devices to be provided (temperature sensors on cargo lines, flow meters on shore facilities) SUS to be applied for external side of double wall piping Observation of Operation Manual GH and LH to be controlled on shore to avoid thermal gradient exceeding allowable range Measures (Mitigation) Early detection of ice on outer side of double wall piping to avoid formation of LO/LH Detection of vacuum loss in double wall piping due to rupture of a seal off valve Risk Reducing Measures

15 Annex, page Hazard (FI/ 7 Cargo liquid line Significant thermal stress due to a thermal gradient outside of the allowable range (FI:,SI:) Guide word HE EFH CH Cause Same as 6 Operational stage: Loading Cool Down (Cargo Tank) 8 Cargo Significant thermal stress due to a thermal gradient outside of the allowable range (FI:,SI:) HE EFH CH Misscommunication between ship and shore Malfunction of shore LH facilities Nonobservance of Operation Manual Insufficient monitoring of temperature Possible consequences Damage to cargo liquid line due to significant thermal stress on cargo liquid line between shore connection and cargo Cargo leakage from outer side to inner side in double wall piping Overpressure in outer side of double wall piping due to vaporization of leaked cargo Risk of fire on deck due to damage in outer side of double wall piping Damage to inner shell of cargo LH/GH leakage to outer shell from inner shell of cargo at the damaged part Loss of vacuum in cargo vacuum insulation system Overpressure in cargo due to large BOG Measures (Prevention) Measures (Mitigation) Dry chemical powder fireextinguishing system to be installed Water spray system to be installed Personal protection equipment to be provided according to ISO/TR 596 requirements Monitoring devices to be provided (temperature sensor in cargo ) Allowable thermal gradient to be stated in Operation Manual Observation of Operation Manual Cargo to be designed in consideration of shrinkage Insulation panel on outer shell of cargo to be provided to avoid loss of vacuum PRV to be installed considering volume of BOG during loss of vacuum Vent to be safety positioned Risk Reducing Measures Same as Alarm system to be provided to detect problematic thermal gradients in inner shell of cargo s

16 Annex, page 4 Hazard Guide (FI/ word Cause Operational stage: Loading Loading 9 Manifold for CH Malfunction of cargo liquid line mooring device LH leakage Drastic change in (FI:,SI:) sea and weather conditions Unexpected external force and/or damage to shore connections Small gap due to thermal differences 0 Manifold for cargo liquid line LH leakage (FI:,SI:) Possible consequences Equivalent LH leakage volume from shore connection until ESD valve is closed Cryogenic damage of ship structure due to dripping of/contact with LO/LN at flanges FGH Same as 9 Equivalent LH leakage volume from shore connection until ESD valve is closed Generation of GH due to evaporation of LH Risk of fire/explosion if flammable atmosphere forms around the manifold Measures (Prevention) ESD valve to be automatically activated when deviation from normal conditions is detected ERS to be activated Measures (Mitigation) Drip tray and water curtain to be installed on manifold ESD valve to be closed within 0 sec according to class rules SUS to be applied Hazardous area to be designed around manifold including provision of safety apparatus to prevent thermal or mechanical explosion Dry chemical powder fireextinguishing system to be installed Water spray system to be installed ESD valve to be closed within 0 sec according to class rules Portable gas detector to be provided Personal protection equipment to be provided according to ISO/TR 596 requirements Risk Reducing Measures

17 Annex, page 5 Hazard (FI/ Manifold for Gas line GH leakage (FI:,SI:) Outer side of double wall piping Formation of LO/LH (FI:,SI:) Guide Cause word FGH Malfunction of mooring device Drastic change in sea and weather conditions Unexpected external force and damage to shore connections Small gap due to thermal differences at flanges CH Insufficient insulation procedures Loss of vacuum in double wall piping Possible consequences Equivalent GH leakage volume from shore connection taking into consideration all piping lines Risk of fire/explosion if flammable atmosphere forms around the manifold Cryogenic damage of ship structure due to dripping/contact with LO/LN Risk of ignition due to rich supply of LO Measures (Prevention) ESD system to be automatically activated when deviation from normal condition is detected ERS to be activated Leak test to be carried out using He gas Measures (Mitigation) Same as 0 Portable gas detector to be provided Personal protection equipment to be provided according to ISO/TR 596 requirements Dry chemical powder fireextinguishing system to be installed Water spray system to be installed Detection of vacuum loss in double wall piping due to rupture of a seal off valve Early detection of ice on outer side of double wall piping to avoid formation of LO/LH Risk Reducing Measures ESD valve to be provided for seal gas supply line ERS to be provided for seal gas supply line also or a procedure to manually isolate ship/shore interface for seal gas supply line to be detailed in Operation Manual

18 Annex, page 6 Hazard (FI/ Cargo Overfilling (FI:,SI:) 4 Instruments Loss of power (FI:,SI:) Guide word HE EFH EFH FGH HE Cause Malfunction of overflow system Override of overflow system High supply rate Low return rate Fire in Engine Room/ Cargo Control Room Black out due to misoperation Black out due to failure Possible consequences Flow of LH to vapour line from cargo vapour lines Damage of cargo compressor due to suction of LH Cryogenic damage of ship structure due to dripping/contact with LH in cargo machinery room Risk of fire/explosion due to formation of flammable atmosphere in cargo machinery room No monitoring of pressure, temperature, liquid level, or vacuum in cargo Possibility of overfilling in cargo Possibility of overpressure in cargo Measures (Prevention) Sensors for high level alarm and overflow system to be installed independently Level gauge to be type approved for LH Observation of Operation Manual Interlock system to be provided for override system Fire detector/alarm system Fire extinguishing system Observation of Operation Manual Measures (Mitigation) Fixed gas detector to be provided in cargo machinery room Hazardous area to be designed in cargo machinery room including provision of safety apparatus to prevent thermal or mechanical explosion Dry chemical powder fireextinguishing system to be installed Water spray system to be installed CO gas fireextinguishing system to be installed in cargo machinery room Ventilation system to be installed in cargo machinery room Personal protection equipment to be provided according to ISO/TR 596 requirements Loading to be stopped due to ESD system Electric power to be supplied by battery and Uninterruptible Power Supply Electric power to be recovered by standby generator or emergency generator Risk Reducing Measures Adequate fire detector to be provided to detect initial H fire outbreak in cargo machinery room

19 Annex, page 7 Hazard (FI/ 5 Instruments Loss of power (FI:,SI:) Guide word EFH FGH HE Cause Same as 4 Possible consequences Discontinued supply of seal GN to cargo compressor Seal GH leakage from cargo compressor Risk of fire/explosion due to formation of flammable atmosphere in cargo machinery room Measures (Prevention) Measures (Mitigation) Fixed gas detector to be provided in cargo machinery room Hazardous area to be designed in cargo machinery room including provision of safety apparatus to prevent thermal or mechanical explosion Personal protection equipment to be provided according to ISO/TR 596 requirements Dry chemical powder fireextinguishing system to be installed Water spray system to be installed CO gas fireextinguishing system to be installed in cargo machinery room Ventilation system to be installed in cargo machinery room Risk Reducing Measures ESD valve to be provided for seal gas supply line Adequate fire detector to be provided to detect initial H fire outbreak in cargo machinery room

20 Annex, page 8 Hazard Guide (FI/ word Operational stage: Loading Drain Off 6 Cargo liquid line Overpressure (FI:,SI:) 7 Cargo liquid line Overpressure (FI:,SI:) 8 Cargo liquid line Significant thermal stress due to thermal gradient outside of the allowable range (FI:,SI:) HE LH EFH CH HE LH EFH FGH HE LH EFH Cause Drain residue due to improper piping installation LH in cargo liquid line due to misoperation of valves Vaporization of LH in cargo liquid line Same as 6 Nonobservance of Operation Manual No temperature monitoring Hot GH supplied at cryogenic conditions Possible consequences Damage to cargo liquid line Loss of vacuum in cargo line vacuum insulation system Formation of LO/LN around outside of double wall piping Cryogenic damage of ship structure due to dripping of/contact of LO/LN Damage to cargo liquid line Cargo leakage from inner side to outer side of double wall piping Overpressure in outer side on double wall piping due to vaporization of leaked cargo Possibility of fire on deck due to damage to outer side on double wall piping Damage of cargo liquid line due to significant thermal stress on cargo liquid line Measures (Prevention) Pressure indicator to be fitted on cargo liquid line Drain valve to be provided Observation of Operation Manual Measures (Mitigation) PRV to be fitted on cargo liquid lines Early detection of ice on outer side of double wall piping to avoid formation of LO/LH Detection of loss of vacuum in double wall piping Dry chemical powder fireextinguishing system to be installed Water spray system to be installed Portable gas detector to be provided Personal protection equipment to be provided according to ISO/TR 596 requirements Stress calculations of cargo piping including thermal stress to be approved by class Observation of Operation Manual PRV to be fitted on cargo liquid lines Risk Reducing Measures

21 Annex, page 9 Hazard (FI/ 9 Cargo liquid line Significant thermal stress due to thermal gradient outside of the allowable range (FI:,SI:) Guide word HE LH EFH Cause Same as 8 Possible consequences Cargo leakage from inner side to outer side of double wall piping Overpressure in outer side on double wall piping due to vaporization of leaked cargo Risk of fire on deck due to damage of outer side of double wall piping Operational stage: Loading Manifold Purging (Hot H Gas to N Gas) 0 Manifold for cargo lines Solidified/ liquefied N gas (FI:,SI:) HE CH No temperature monitoring GN supplied in cryogenic conditions in cargo lines Solidified N fitted with valve seat Insufficient GH purging due to a blockage of solidified N Operational stage: Loading Ship / Shore interface procedure before berthing Manifold for cargo lines Residual H gas (FI:,SI:) HE FGH Nonobservance of Operation Manual Insufficient purging Same as Manifold for gas lines Residual H gas (FI:,SI:) HE FGH Nonobservance of Operation Manual Insufficient purging Same as Measures (Prevention) Measures (Mitigation) Detection of vacuum loss in double wall piping Dry chemical powder fireextinguishing system to be installed Water spray system to be installed Portable gas detector to be provided Personal protection equipment to be provided according to ISO/TR 596 requirements Observance of Operation Manual Proper inspections Risk Reducing Measures

22 Annex, page 0 Hazard Guide (FI/ word Cause Operational stage: Seagoing BOG management Cargo EFH Loss of vacuum in Increase in FGH cargo vacuum heat input insulation system (FI:,SI:) due to leakage from pipe joints 4 Cargo Increase in heat input (FI:,SI:) 5 Cargo Inability to operate GCU (FI:,SI:) 6 Cargo Accumulated days exceed the design maximum (FI:,SI:) EFH FGH EFH FGH HE EFH Possible consequences Increase in BOG Overpressure in cargo Fire on deck Increase in a large volume of BOG Overpressure in cargo Discontinued supply of steam to cargo heater Malfunction of temperature control valve in cargo heater Collision/grounding Changes to original voyage plan due to severe weather etc. Operational stage: Seagoing Cargo Safety Storage Small leakage of EFH Damage of ballast ballast water from ballast to cargo hold due to cracks in welded parts Inability to treat BOG Overpressure in cargo Overpressure in cargo Measures (Prevention) Welded joints for piping to be applied in cargo vacuum system Vacuum insulation systems of dome to be separated from those if cargo s Use certified safe type equipment in Hazardous area Measures (Mitigation) Cargo to be a pressure accumulation design BOG to be treated using GCU PRV to be fitted on cargo Vent to be safety positioned Same as Cargo to be a pressure accumulation design PRV to be fitted on cargo Vent to be safety positioned BOG to be treated using GCU Cargo mixing system to be installed in cargo PRV to be fitted on cargo Vent to be safety positioned Exclude from study for the reason that the operation is the same as the operation of LNG. Risk Reducing Measures Flange joints to be considered to mitigate leakage in vacuum exhaust line

23 Annex, page Hazard (FI/ Large leakage of ballast water from ballast to cargo hold 0 Very small leakage of GN in cargo hold to cargo vacuum system (FI:,SI:) Small leakage of GN in cargo hold of cargo vacuum system (FI:,SI:) Guide Cause word EFH Collision with other vessels (damage of side shell and inner hull) EFH DH EFH DH Damage of cargo outer shell due to welding cracks Crack in bellows in dome Collision with other vessels (damage to side shell and inner hull, cargo outer shell) Possible consequences Measures (Prevention) Measures (Mitigation) Risk Reducing Measures Exclude from study for the reason that the operation is the same as the operation of LNG. Decrease in performance of insulation systems due to LN/Solidified N Decrease in performance of insulation systems due to loss of vacuum Overpressure in cargo s due to formation of BOG Decrease in performance of insulation systems due to LN/Solidified N Decrease in performance of insulation systems due to loss of vacuum Overpressure in cargo s due to formation of BOG Welding Procedure Specification to be observed, including inspection Use reliable bellows and take into consideration materials, method of fitting and inspection Cargo to be a pressure accumulation design PRV to be fitted on cargo assuming loss of vacuum in insulation system BOG to be treated using GCU Vent to be safety positioned Monitoring of vacuum in cargo vacuum system Cargo to be a pressure accumulation design PRV to be fitted on cargo considering loss of vacuum in insulation system BOG to be treated using GCU Vent to be safety positioned Monitoring of vacuum in cargo vacuum system

24 Annex, page Hazard (FI/ Large leakage of GN in cargo hold to cargo vacuum system (FI:,SI:4) Very small leakage of LH from cargo inner shell (FI:,SI:) Guide word EFH DH EFH DH CH Cause Same as High permeability of welding, seal parts Fatigue cracks on welding parts due to sloshing loads, cycle loads Possible consequences Decrease in performance of insulation systems due to rapid loss of vacuum Rapid overpressure in cargo Partial blockage of vent line due to two phase flow Decrease in performance of insulation systems due to loss of vacuum Overpressure in cargo due to increase in BOG Significant thermal stress due to shrinkage, and embrittlement on cargo outer shell Measures (Prevention) Measures (Mitigation) Cargo to be a pressure accumulation PRV to be fitted on cargo considering loss of vacuum insulation system BOG to be treated by GCU Vent mast to be safety located Monitoring of vacuum for cargo vacuum system Double gasket to be Leak test to be carried applied out using He gas Cargo to be Cargo to be a designed as a Type C pressure accumulation based on IGC Code design PRV to be fitted on cargo considering loss of vacuum insulation system BOG to be treated using GCU Vent to be safety positioned SUS to be applied for cargo outer shell Cargo to be designed considering thermal stress Monitoring of vacuum for cargo vacuum system Risk Reducing Measures

25 Annex, page Hazard (FI/ 4 Small leakage of LH from cargo inner shell (FI:,SI:4) 5 Small leakage of LH from cargo inner shell (FI:,SI:) Guide word EFH DH CH EFH DH CH Cause Collision with other vessels (damage to side shell and inner hull cargo outer shell) Grounding (Damage of double bottom, cargo outer shell) Possible consequences GH flow to cargo hold, residual GN, air changed to solidified N Decrease in performance of insulation system due to rapid loss of vacuum Rapid increase in BOG and overpressure in cargo Partial blockage of vent due to two phase flow Rise in temperature due to sea water flow to cargo hold and vacuum space in cargo vacuum insulation system Decrease in performance of cargo vacuum insulation system due to rapid loss of vacuum Overpressure in cargo due to rapid increase in BOG Partial blockage of vent due to two phase flow Measures (Prevention) Measures (Mitigation) Leak test to be carried out using He gas Cargo to be a pressure accumulation design PRV to be fitted on cargo considering loss of vacuum in insulation system BOG to be treated using GCU Vent to be safety positioned SUS to be applied in cargo outer shell Cargo designed considering thermal stress Monitoring of vacuum in cargo vacuum system Cargo PRV Cargo hold PRV Risk Reducing Measures

26 Annex, page 4 Hazard (FI/ 6 Moderate leakage of LH from cargo inner shell (FI:,SI:4) 7 Large leakage of LH from cargo inner shell (FI:,SI:4) Guide word EFH DH CH EFH DH CH Cause Collision with other vessels (damage to side shell and inner hull, cargo outer shell) Collision with other vessels (damage of side shell and inner hull, cargo outer shell) Possible consequences Decrease in performance of cargo vacuum insulation system due to rapid loss of vacuum Overpressure in cargo due to rapid increase in BOG Partial blockage of vent line due to two phase flow Diffusion of GH to cargo hold and deck Possibility of jet fire Decrease in performance of cargo vacuum insulation system due to rapid loss of vacuum Rapid overpressure in cargo due to rapid increase in BOG Partial blockage of vent due to two phase flow Diffusion of GH to cargo hold and deck Possibility of pool fire Spread of pool fire to other vessels Measures (Prevention) Measures (Mitigation) Heat radiation to be reduced by cargo cover Tank dome to be cooled by water spray systems PRV (50% x ) to be fitted Risk Reducing Measures

27 Annex, page 5 Hazard (FI/ 8 Leakage of GN to cargo vacuum insulation space at piping connections in the space (FI:,SI:) 9 Leakage of LH to cargo vacuum insulation space at pipe connections in the space (FI:,SI:) Guide word EFH DH CH EFH DH CH Cause Damage of inner FRP support Excessive displacement of pipes in vacuum insulation space (Damage of connection part to cargo outer shell) Excessive deformation of pipes in vacuum insulation space due to damage of FRP support for cargo inner shell (Damage to connection part to cargo inner shell) Possible consequences Increase in BOG Overpressure in cargo Increase in BOG Overpressure in cargo Significant thermal stress due to shrinkage, embrittlement on cargo outer shell Measures (Prevention) Redundancy of FRP cargo inner shell support Redundancy of FRP cargo inner shell support Measures (Mitigation) Segregation of vacuum space between cargo and dome Monitoring of vacuum for dome vacuum insulation space Cargo to be a pressure accumulation design PRV to be fitted on cargo considering loss of vacuum in insulation system BOG to be treated using GCU Vent to be safety positioned Segregation of vacuum space between cargo and dome Monitoring of vacuum for dome vacuum insulation space SUS to be applied for cargo outer shell Cargo to be a pressure accumulation design Cargo to be designed considering thermal stress Risk Reducing Measures

28 Annex, page 6 Hazard (FI/ 40 Instruments (Laden voyage) Loss of power (FI:,SI:) 4 Cargo BOG release from vent (FI:,SI:) 4 Cargo (Ballast voyage) Excessive residual drain in cargo (FI:,SI:) Guide word EFH FGH HE EFH FGH HE HE EFH FGH Cause Fire in Engine Room/ Cargo Control Room Black out due to misoperation Black out due to failure GH leakage from seat of PRV Misoperation Level gauge malfunction Possible consequences No monitoring of pressure, temperature, level, vacuum in cargo Possibility of overpressure in cargo Formation of flammable atmosphere around the vent outlet Risk of fire due to lightening Vaporization of cargo heel Vaporization of residual drain in cargo liquid line Formation of BOG Overpressure in cargo Operational stage: Unloading Ship / Shore interface procedure after berthing Same as Operational stage: Loading Ship / Shore interface procedure after berthing Operational stage: Unloading Manifold Purging (Air to N gas) Same as Operational stage: Loading Ship / Shore interface procedure after berthing Operational stage: Unloading Manifold Purging (N Gas to Hot H gas) Same as Operational stage: Loading Manifold Purging (N Gas to Hot H gas) Operational stage: Unloading Inner shell Pressure Drop Off Same as Operational stage: Loading Inner shell Pressure Drop Off Measures (Prevention) Measures (Mitigation) Fire detector/alarm Electric power to be system supplied by battery and Fire extinguishing Uninterruptible Power system Supply Observation of Electric power to be Operation Manual recovered by standby generator or emergency generator Vent to be safety positioned N gas fire extinguishing system in vent Emergency isolation valve to be fitted between PRV and cargo Observation of Operation Manual Cargo to be a pressure accumulation design BOG to be treated using GCU PRV to be fitted on cargo Vent to be safety positioned Redundancy of level gauge Risk Reducing Measures PRV to be designed considering characteristics of GH Fixed gas detector to be fitted in vent

29 Annex, page 7 Hazard Guide (FI/ word Cause Operational stage: Unloading Cool Down (Cargo Piping) Same as Operational stage: Loading Cool Down (Cargo Piping) 48 Cargo HE Failure of EFH cargo spray pump (FI:,SI:) Solidified N is drawn into the spray pump due to residual N during the manifold purge solidifying and accumulating in the cargo Operational stage: Unloading Unloading Same as Node Operational stage: Loading Loading 50 Cargo HE Failure of EFH cargo pump (FI:,SI:) Solidified N drawn into spray pump due to residual N during manifold purge solidifying and accumulating in the cargo Possible consequences Impossible to conduct cool down procedure using cargo spray pump Unloading stopped by cargo pump Inability to conduct normal unloading Operational stage: Unloading Drain Off Same as Operational stage: Loading Drain Off Operational stage: Unloading Manifold Purging (Hot H Gas to N gas) Same as Operational stage: Loading Manifold Purging (Hot H Gas to N gas) Operational stage: Unloading Ship / Shore interface procedure before berthing Same as Operational stage: Loading Ship / Shore interface procedure before berthing Measures (Prevention) Strainer to be fitted on cargo spray pump suction Strainer to be fitted on cargo spray pump suction inlet Measures (Mitigation) Two cargo spray pumps per ship to be installed Two cargo pumps per to be installed Unloading by gas pressurization Risk Reducing Measures

30 Annex, page 8 Hazard Guide (FI/ word Cause Operational stage: Dock in Warm Up 54 Cargo HE Malfunction of Significant EFH temperature control thermal stress valve for cargo due to a heater thermal Temperature of gradient GH supplied too outside of the high allowable Insufficient range monitoring of (FI:,SI:) temperature 55 Inability to operate cargo compressor (FI:,SI:) HE EFH No supply of GH Seal function failure Operational stage: Dock in Inerting (H Gas to N Gas) 56 Cargo line Solidified/ liquefied N (FI:,SI:) HE CH EFH Insufficient warming up due to misoperation Temperature of cargo line/cargo Possible consequences Damage to inner shell of cargo due to excessive thermal stress LH/GH leakage from inner shell to outer shell of cargo at damaged part Loss of vacuum in the cargo vacuum insulation system Inability to perform warming up operations using the cargo compressor onboard Blockage in cargo line due to Solidified N Measures (Prevention) Monitoring devices to be provided (temperature sensor in cargo ) Observation of Operation Manual Cargo to be designed considering thermal stress Observation of Operation Manual Observation of Operation Manual Monitoring devices to be provided (temperature sensor in cargo ) too low Operational stage: Dock in Aeration(N Gas to Air) No specific hazards are identified, for the reason that the operation is the same as the operation of LNG. Operational stage: Dock out Inerting (Air to N Gas) No specific hazards are identified, for the reason that the operation is the same as the operation of LNG. Operational stage: Dock out Hydrogen Gas Filling (N Gas to Hot H Gas) No specific hazards are identified, for the reason that the operation is similar to the operation of LNG. Measures (Mitigation) Seal GH supplied by GH bottles on ship Hot GH supplied by shore without using the cargo compressor onboard Risk Reducing Measures

31 Annex, page 9 Hazard Guide Possible Cause (FI/ word consequences Operational stage: Dock out Cool Down (Cargo Piping) Cargo liquid line Same as Operational stage: Loading Cool Down (Cargo Piping) Significant thermal stress due to a thermal gradient outside of the allowable range 6 Cargo line HE Solidified/ EFH liquefied N CH (FI:,SI:) Improper piping installation that causes air pockets to develop Insufficient hydrogen gas filling Residual GN Damage to cargo valves, cargo compressor, cargo heater Blockage in the cargo line Malfunction of instruments (pressure gauges, temperatures) Operational stage: Dock out Cool Down (Cargo Tank) 6 Cargo Same as Operational stage: Loading Cool Down (Cargo Tank) Significant thermal stress due to a thermal gradient outside of the allowable range (FI:,SI:) Measures (Prevention) Purge valve to be fitted at air pockets Gas sampling during hydrogen gas filling Observance of Operation Manual Measures (Mitigation) Risk Reducing Measures

32 Annex, page 0 Hazard (FI/ 6 Cargo Solidified/ liquefied N (FI:,SI:) Guide word HE EFH CH Cause Insufficient hydrogen gas filling Residual GN Possible consequences Damage to cargo valves, cargo pump Malfunction of instruments (cargo liquid temperature gauge, wall temperature gauge, gas sampling line Measures (Prevention) Gas sampling during hydrogen gas filling Operation manual to be observed Measures (Mitigation) Risk Reducing Measures

33 Table 5: Frequency Index and Definitions (Second HAZ study) FI Frequency A Never heard of in the industry B Heard of in the industry C Has happened in the organization or more than once per year in the industry D Has happened at the location or more than once per year in the organization E Has happened more than once per year at the location FI: Frequency Index CCC /INF.0 Annex, page Table 6: Severity Index and Definitions (Second HAZ study) SI Effect on Peoples Assets Environment Reputation 5 More than fatalities No damage No effect No impact 4 Permanent total disability or up to Slight damage Slight effect Slight impact fatalities Major injury or health effect Minor damage Minor effect Minor impact Minor injury or health effect Moderate damage Moderate effect Moderate impact Slight injury or health effect Major damage Major effect Major impact 0 No injury or health effect Massive damage Massive effect Massive impact SI: Severity Index

34 Annex, page (FI:C, SI:) (FI:C, SI:) Natural, environmental and man created hazards Extreme weather conditions (e.g. wave, wind, temperature, snow, blizzards, fog ) Passing ship effects Table 7: List of Identified Hazards (Second HAZ study) 4 5 Weather conditions deteriorate resulting in exceedance of mooring capacity Passing ship effect on vessel loading/unloading. Weather conditions deteriorate resulting in exceedance of mooring capacity breakout/ Loss of containment Significant vessel movement or breakout Overstress or fracture of loading arm/ Loss of containment / Fatalities ) Design based on appropriate (location/route specific) metocean data ) Weather forecast ) Weather monitoring onboard 4) Adverse Weather Guidelines 5) LH Transfer Operations Checklist to include weather requirements. 6) Stop work policy 7) Emergency release system and linked ESD systems 8) Operations and Maintenance ) Design based on metocean data ) Weather forecast ) Weather monitoring onboard 4) Adverse Weather Guidelines 5) LH Transfer Operations Checklist to include weather requirements. 6) Stop Work Policy 7) Emergency Release System and linked ESD systems 8) SIL(Safety Integrity level) Assessment for transfer arm system and ESD functions Sheltered location being assessed ) Appropriate site selection ) Operations Philosophy to be developed

35 Annex, page (FI:B, SI:4) 4 SI:4) 5 (FI:B, SI:) 6 (FI:B, SI:) Lightning 4 5 Earthquake/ tsunami Manmade hazards (Terrorism, security threat) Environmental Impact of facilities to the environment Lightning strike during shore to ship transfer/ sea going/ dock in/dock out Due to the seismic nature of Japan, site location may be affected by earthquakes and/or Tsunamis Security breaches Leakage, discharges Injury/ fatality/ Asset damage Asset damage/ Loss of containment/ Injury / fatality Asset damage/ Loss of containment/ Injury/ fatality Asset damage/ Loss of containment/ injury/ fatality ) Design based on metocean data ) Weather forecast ) Weather monitoring onboard 4) Adverse Weather Guidelines 5) LH Transfer Operations Checklist to include weather requirements. 6) Approved procedures and stop work policy (e.g. no venting policy, ensure correct earthing) Site SelectionPossible occurrence of Seismic Activity to be factored into the site selection process so as to eliminate high activity areas. ) ISPS terminals and vessel ) Access control at terminal ) Crew and visitor declaration at terminal ) Detailed Site selection ) Environmental Impact Assessment Onshore facilities ) Emergency Response Plan ) Consider vapour return ) To conduct vent dispersion analysis. ) Vent stack design (e.g. location, height, heater) 4) Identify release scenarios which might catch fire. 5) To investigate fire suppression system (e.g. snuffing system) 6) Operations Philosophy to be developed ) Consider seismic effects on terminal, jetty and connections (arms). Terminal design considerations. Japanese codes for structural design ) Emergency separation ) Earthquake warning system to allow time to disconnect (refer to LNG terminals) ) Any additional security barriers to be considered as step out of LNG terminal ) Consider Local opposition ) Regular drills and training of crew Consider closed loading system.

ANNEX AMENDMENTS TO THE INTERNATIONAL CODE FOR FIRE SAFETY SYSTEMS (FSS CODE) CHAPTER 15 INERT GAS SYSTEMS

ANNEX AMENDMENTS TO THE INTERNATIONAL CODE FOR FIRE SAFETY SYSTEMS (FSS CODE) CHAPTER 15 INERT GAS SYSTEMS Annex 3, page 2 ANNEX AMENDMENTS TO THE INTERNATIONAL CODE FOR FIRE SAFETY SYSTEMS (FSS CODE) CHAPTER 15 INERT GAS SYSTEMS The text of existing chapter 15 is replaced by the following: "1 Application This

More information

RESOLUTION A.567(14) adopted on 20 November 1985 REGULATION FOR INERT GAS SYSTEMS ON CHEMICAL TANKERS

RESOLUTION A.567(14) adopted on 20 November 1985 REGULATION FOR INERT GAS SYSTEMS ON CHEMICAL TANKERS INTERNATIONAL MARITIME ORGANIZATION A 14/Res.567 16 January 1986 Original: ENGLISH ASSEMBLY - 14th session Agenda item lo(b) IMO RESOLUTION A.567(14) adopted on 20 November 1985 THE ASSEMBLY, RECALLING

More information

INTERNATIONAL ASSOCIATION OF CLASSIFICATION SOCIETIES. Interpretations of the. IGF Code

INTERNATIONAL ASSOCIATION OF CLASSIFICATION SOCIETIES. Interpretations of the. IGF Code INTERNATIONAL ASSOCIATION OF CLASSIFICATION SOCIETIES s of the IGF Code CONTENTS GF1 Test for gas fuel tank s high level alarm Rev.1 July 2017 GF2 Ship Steel Protection against Liquefied Gas Fuel (Part

More information

NEW IGC CODE AND IGF CODE

NEW IGC CODE AND IGF CODE NEW IGC CODE AND IGF CODE SAFETY ASPECTS Raffaele Piciocchi Gas Center - Greece SAFETY4SEAS - Athens 1 October 2014 Content NEW IGC CODE DRAFT IGF CODE 2 The New IGC Code A new IGC Code has been approved

More information

Installation of Ballast Water Management Systems

Installation of Ballast Water Management Systems (Sept 2015) (Rev.1 May 2016) Installation of Ballast Water Management Systems 1. Application In addition to the requirements contained in BWM Convention (2004), the following requirements are applied to

More information

Minimum standard of competence in advanced training for liquefied gas tanker cargo operations (STCW Reg V/1-2)

Minimum standard of competence in advanced training for liquefied gas tanker cargo operations (STCW Reg V/1-2) Minimum standard of in advanced training for liquefied gas tanker cargo operations (STCW Reg V/1-2) Column 2 Knowledge, understanding and proficiency Design and characteristics of a liquefied gas tanker

More information

RESOLUTION MSC.397(95) (adopted on 11 June 2015) AMENDMENTS TO PART A OF THE SEAFARERS' TRAINING, CERTIFICATION AND WATCHKEEPING (STCW) CODE

RESOLUTION MSC.397(95) (adopted on 11 June 2015) AMENDMENTS TO PART A OF THE SEAFARERS' TRAINING, CERTIFICATION AND WATCHKEEPING (STCW) CODE RESOLUTION MSC.397(95) (adopted on 11 June 2015) THE MARITIME SAFETY COMMITTEE, RECALLING Article 28(b) of the Convention on the International Maritime Organization concerning the functions of the Committee,

More information

Port: DISPORT Voyage No.:03 Date: 10-Aug-2016 No. Description Remarks [ ]

Port: DISPORT Voyage No.:03 Date: 10-Aug-2016 No. Description Remarks [ ] LNG Simulator LNG Carrier Rev. No.: 1 Discharging ARRIVAL loading &ballasting plan prepared & signed by all Deck and Engine officers and approved by Master operation monitoring record sheets printed out

More information

+Port: LOADPORT Voyage No.: 03 Date: 01-Aug-2016 No. Description Remarks [ ]

+Port: LOADPORT Voyage No.: 03 Date: 01-Aug-2016 No. Description Remarks [ ] ARRIVAL Cargo loading &de-ballasting plan prepared & signed by all Deck and Engine officers and approved by Master Cargo operation monitoring record sheets printed out and available Vessel s liquid header

More information

Periodical surveys of cargo installations on ships carrying liquefied gases in bulk

Periodical surveys of cargo installations on ships carrying liquefied gases in bulk (June 1999) (Rev.1 Mar 2006) (Rev.2 May 2007) (Rev.3 Mar 2010) (Corr.1 Feb 2011) (Rev.4 Oct 2013) Periodical surveys of cargo installations on ships carrying liquefied gases in bulk 1 General 1.1 Scope

More information

LNG Cargo Operations. Juan Manuel Martín Ordax

LNG Cargo Operations. Juan Manuel Martín Ordax Juan Manuel Martín Ordax If we consider that the gas carrier is coming directly from a shipbuilder or a drydock, the sequence of cargo operations would be as follows: Source: Liquefied Gas Handling Principles

More information

RESOLUTION MSC.420(97) (adopted on 25 November 2016) INTERIM RECOMMENDATIONS FOR CARRIAGE OF LIQUEFIED HYDROGEN IN BULK

RESOLUTION MSC.420(97) (adopted on 25 November 2016) INTERIM RECOMMENDATIONS FOR CARRIAGE OF LIQUEFIED HYDROGEN IN BULK ANNEX 18 RESOLUTION MSC.420(97) Annex 18, page 1 THE MARITIME SAFETY COMMITTEE, RECALLING Article 28(b) of the Convention on the International Maritime Organization concerning the functions of the Committee,

More information

Periodic Survey of Fuel Installations on Ships other than Liquefied Gas Carriers utilizing gas or other low flash point fuels

Periodic Survey of Fuel Installations on Ships other than Liquefied Gas Carriers utilizing gas or other low flash point fuels (Jan 2017) Periodic Survey of Fuel Installations on Ships other than Liquefied Gas Carriers utilizing gas or other low flash point fuels CONTENTS 1. Application 2. Special Survey 2.1 Schedule 2.2 Scope

More information

MOL LNG Transport (Europe) Ltd File: 02 Checklists 6 pages Rev. No. 1 Loading Plan Part Two (2) (Line UP) Loading Plan Part Two (2) (Line Up)

MOL LNG Transport (Europe) Ltd File: 02 Checklists 6 pages Rev. No. 1 Loading Plan Part Two (2) (Line UP) Loading Plan Part Two (2) (Line Up) Loading Plan Part Two (2) (Line Up) Arm Cool Down; Line Cool Down Line Up: Set up the port manifold as follows:. Open 20% No.1 tank filling valve CL100 Open 20% No. 2 tank filling valve CL200 Open 20%

More information

NORMAL OPERATING PROCEDURES Operating Parameter Information

NORMAL OPERATING PROCEDURES Operating Parameter Information Operating Parameter Information Each operator performing the normal operating procedures (routine checks) of the facility should be familiar with the current normal operating parameters of all systems

More information

RESOLUTION MEPC.86(44) adopted on 13 March 2000 AMENDMENTS TO THE GUIDELINES FOR THE DEVELOPMENT OF SHIPBOARD OIL POLLUTION EMERGENCY PLANS

RESOLUTION MEPC.86(44) adopted on 13 March 2000 AMENDMENTS TO THE GUIDELINES FOR THE DEVELOPMENT OF SHIPBOARD OIL POLLUTION EMERGENCY PLANS MEPC 44/20 RESOLUTION MEPC.86(44) THE MARINE ENVIRONMENT PROTECTION COMMITTEE, RECALLING Article 38(a) of the Convention on the International Maritime Organization concerning the function of the Committee,

More information

Abstract. 1 Introduction

Abstract. 1 Introduction Risk assessment study of the mutual interactive influence of working procedures on terminals handling dangerous goods in port of Koper (Slovenia) L. Battelino Water Management Institute, Maritime Engineering

More information

THE REPUBLIC OF LIBERIA LIBERIA MARITIME AUTHORITY

THE REPUBLIC OF LIBERIA LIBERIA MARITIME AUTHORITY Office of Deputy Commissioner of Maritime Affairs THE REPUBLIC OF LIBERIA LIBERIA MARITIME AUTHORITY Marine Notice POL-010 Rev. 04/10 TO: SUBJECT: ALL SHIPOWNERS, OPERATORS, MASTERS AND OFFICERS OF MERCHANT

More information

SLOP RECEPTION AND PROCESSING FACILITIES

SLOP RECEPTION AND PROCESSING FACILITIES RULES FOR CLASSIFICATION OF SHIPS NEWBUILDINGS SPECIAL SERVICE AND TYPE ADDITIONAL CLASS PART 5 CHAPTER 8 SLOP RECEPTION AND PROCESSING FACILITIES JANUARY 2011 CONTENTS PAGE Sec. 1 General Requirements...

More information

PSM TRAINING COURSES. Courses can be conducted in multi-languages

PSM TRAINING COURSES. Courses can be conducted in multi-languages Courses can be conducted in multi-languages One set of hardcopy course notes will be sent to client for printing and distribution to course participants. The courses will be held at the client s training

More information

SAFETY MANUAL PURGING, VENTING & DRAINING PROCEDURE TABLE OF CONTENTS 1. INTRODUCTION SCOPE DEFINITIONS PROCEDURE...

SAFETY MANUAL PURGING, VENTING & DRAINING PROCEDURE TABLE OF CONTENTS 1. INTRODUCTION SCOPE DEFINITIONS PROCEDURE... Page 1 of 11 TABLE OF CONTENTS 1. INTRODUCTION... 2 2. SCOPE... 2 3. DEFINITIONS... 2 4.... 3 5. RESPONSIBILTIES... 10 6. REFERENCES... 10 7. ATTACHMENTS... 11 8. APPENDICES... 11 Rev. Issue Date Amendment

More information

RULES PUBLICATION NO. 119/P

RULES PUBLICATION NO. 119/P RULES PUBLICATION NO. 119/P PERIODIC SURVEYS OF FUEL INSTALLATIONS ON SHIPS OTHER THAN LIQUEFIED GAS CARRIERS UTILIZING GAS OR OTHER LOW FLASH POINT FUELS 2019 January Publications P (Additional Rule Requirements)

More information

Identification and Screening of Scenarios for LOPA. Ken First Dow Chemical Company Midland, MI

Identification and Screening of Scenarios for LOPA. Ken First Dow Chemical Company Midland, MI Identification and Screening of Scenarios for LOPA Ken First Dow Chemical Company Midland, MI 1 Layers of Protection Analysis (LOPA) LOPA is a semi-quantitative tool for analyzing and assessing risk. The

More information

Safety in Petroleum Industry

Safety in Petroleum Industry Chemical ( Industrial ) Disaster Management Conference, Bangalore 30 January 2014 Safety in Petroleum Industry Refineries and Petrochemical plants are highly energyintensive Handle highly inflammable and

More information

STCW Code Table A-V/1-1-1 Specification of minimum standard of competence in basic training for oil and chemical tanker cargo operations

STCW Code Table A-V/1-1-1 Specification of minimum standard of competence in basic training for oil and chemical tanker cargo operations STCW Code Table A-V/1-1-1 Specification of minimum standard of in basic for oil and chemical tanker cargo operations Ref: https://www.edumaritime.net/stcw-code Source: IMO Contribute to Basic knowledge

More information

GAS FUELLED ENGINE INSTALLATIONS

GAS FUELLED ENGINE INSTALLATIONS RULES FOR CLASSIFICATION OF SHIPS NEWBUILDINGS SPECIAL EQUIPMENT AND SYSTEMS ADDITIONAL CLASS PART 6 CHAPTER 13 GAS FUELLED ENGINE INSTALLATIONS JANUARY 2001 CONTENTS PAGE Sec. 1 General Requirements...

More information

FLAMMABLE GASES AND FLAMMABLE CRYOGENIC FLUIDS

FLAMMABLE GASES AND FLAMMABLE CRYOGENIC FLUIDS CHAPTER 35 FLAMMABLE GASES AND FLAMMABLE CRYOGENIC FLUIDS SECTION 3501 GENERAL 3501.1 Scope. The storage and use of flammable gases shall be in accordance with this chapter. Compressed gases shall also

More information

GAS TANKER COMMITTEE #4

GAS TANKER COMMITTEE #4 GAS TANKER COMMITTEE #4 FSRU-Critical link in Global LNG Supply chain Singapore 12 th October 2017 Lian-Gee CHUA, DNV GL 12 October 2017 1 SAFER, SMARTER, GREENER ABOUT DNV GL - The leading classification

More information

Safety Engineering - Hazard Identification Techniques - M. Jahoda

Safety Engineering - Hazard Identification Techniques - M. Jahoda Safety Engineering - Hazard Identification Techniques - M. Jahoda Hazard identification The risk management of a plant 2 Identification of the hazards involved in the operation of the plant, due to the

More information

GAS FUELLED ENGINE INSTALLATIONS

GAS FUELLED ENGINE INSTALLATIONS RULES FOR CLASSICATION OF SHIPS / HIGH SPEED, LIGHT CRAFT AND NAVAL SURFACE CRAFT NEWBUILDINGS SPECIAL EQUIPMENT AND SYSTEMS ADDITIONAL CLASS PART 6 CHTER 13 GAS FUELLED ENGINE INSTALLATIONS JANUARY 2010

More information

SAFETY STUDY OF HYDROGEN SUPPLY STATIONS FOR THE REVIEW OF HIGH PRESSURE GAS SAFETY LAW IN JAPAN

SAFETY STUDY OF HYDROGEN SUPPLY STATIONS FOR THE REVIEW OF HIGH PRESSURE GAS SAFETY LAW IN JAPAN SAFETY STUDY OF HYDROGEN SUPPLY STATIONS FOR THE REVIEW OF HIGH PRESSURE GAS SAFETY LAW IN JAPAN Komori, M., Yoshida, T., Onoue, K. and Kikukawa, S., Mori, T., Takagi, K. Japan Petroleum Energy Center,

More information

REGASIFICATION VESSELS

REGASIFICATION VESSELS CLASSICATION NOTES No. 61.3 REGASICATION VESSELS MAY 2011 The content of this service document is the subject of intellectual property rights reserved by Det Norske Veritas AS (DNV). The user accepts that

More information

Tanker Familiarisation IMO Model Course Chapter 1-9

Tanker Familiarisation IMO Model Course Chapter 1-9 IMO Model Course 1.01 Chapter 1-9 - Courseware Specification - MarineSoft Entwicklungs- und Logistikgesellschaft mbh Friedrich-Barnewitz-Straße 2 18119 Rostock GERMANY +49 381 12835-0 +49 381 12835-55

More information

OPERATIONS SEAFARER CERTIFICATION

OPERATIONS SEAFARER CERTIFICATION Page 1 of 6 Compiled by Chief Examiner Approved by Qualifications Committee: 25 November 2013 OPERATIONS SEAFARER CERTIFICATION GUIDANCE NOTE SA MARITIME QUALIFICATIONS CODE Ancillary : Basic Training

More information

Every things under control High-Integrity Pressure Protection System (HIPPS)

Every things under control High-Integrity Pressure Protection System (HIPPS) Every things under control www.adico.co info@adico.co Table Of Contents 1. Introduction... 2 2. Standards... 3 3. HIPPS vs Emergency Shut Down... 4 4. Safety Requirement Specification... 4 5. Device Integrity

More information

OIL IN NAVIGABLE WATERS REGULATIONS [L.N. 101 of 1968.] under sections 5 and 7. [22nd April, 1968] [Comrnencernent.]

OIL IN NAVIGABLE WATERS REGULATIONS [L.N. 101 of 1968.] under sections 5 and 7. [22nd April, 1968] [Comrnencernent.] OIL IN NAVIGABLE WATERS REGULATIONS [L.N. 101 of 1968.] under sections 5 and 7 [Comrnencernent.] [22nd April, 1968] 1. Short title and interpretation (1) These Regulations may be cited as the Oil in Navigable

More information

Introduction to Emergency Response & Contingency Planning

Introduction to Emergency Response & Contingency Planning & Contingency Planning Rationale Why is it important for you to learn this material? Designed for those who may witness a release, this is an introductory course designed to help ensure those who are likely

More information

Liquefied gas cargo tanks and process pressure vessels

Liquefied gas cargo tanks and process pressure vessels .1 -.3 Liquefied gas cargo tanks and process pressure vessels.1 General.1.1 The present texts give the general principles which are applied by Classification Societies for approval and survey of the relevant

More information

TRAINING RECORD BOOK LNG SHIPPING

TRAINING RECORD BOOK LNG SHIPPING TRAINING RECORD BOOK LNG SHIPPING Training Record Book for LNG Shipping - Deck Training Record Book This document is provided as an example of a training record book. Users are free to modify this document

More information

Pressure Systems Safety Regulation

Pressure Systems Safety Regulation Pressure Systems Safety Regulation Introduction This document informs Faculty of the key requirements of the UK and Chinese Pressure Systems Safety regulations. The aim of these regulations is to prevent

More information

We re Going Global. Vessel Loss Control. Technical Notes #36

We re Going Global. Vessel Loss Control. Technical Notes #36 Technical Notes #36 We re Going Global Vessel Loss Control When the vessel loaded, the gauging reports showed x amount but when it arrived at its discharge port, why was the amount vastly different? In

More information

RESOLUTION MSC.365(93) (adopted on 22 May 2014) AMENDMENTS TO THE INTERNATIONAL CONVENTION FOR THE SAFETY OF LIFE AT SEA, 1974, AS AMENDED

RESOLUTION MSC.365(93) (adopted on 22 May 2014) AMENDMENTS TO THE INTERNATIONAL CONVENTION FOR THE SAFETY OF LIFE AT SEA, 1974, AS AMENDED RESOLUTION MSC.365(93) THE MARITIME SAFETY COMMITTEE, RECALLING Article 28(b) of the Convention on the International Maritime Organization concerning the functions of the Committee, RECALLING ALSO article

More information

GUIDELINES ON OPERATIONAL INFORMATION FOR MASTERS IN CASE OF FLOODING FOR PASSENGER SHIPS CONSTRUCTED BEFORE 1 JANUARY 2014 *

GUIDELINES ON OPERATIONAL INFORMATION FOR MASTERS IN CASE OF FLOODING FOR PASSENGER SHIPS CONSTRUCTED BEFORE 1 JANUARY 2014 * E 4 ALBERT EMBANKMENT LONDON SE1 7SR Telephone: +44 (0)20 7735 7611 Fax: +44 (0)20 7587 3210 MSC.1/Circ.1589 24 May 2018 GUIDELINES ON OPERATIONAL INFORMATION FOR MASTERS IN CASE OF FLOODING FOR PASSENGER

More information

AMENDMENTS TO THE IMSBC CODE AND SUPPLEMENTS. Supporting information for the proposed new individual schedule for Palm kernel shells

AMENDMENTS TO THE IMSBC CODE AND SUPPLEMENTS. Supporting information for the proposed new individual schedule for Palm kernel shells E SUB-COMMITTEE ON CARRIAGE OF CARGOES AND CONTAINERS 3rd session Agenda item 5 CCC 3/INF.21 1 July 2016 ENGLISH ONLY AMENDMENTS TO THE IMSBC CODE AND SUPPLEMENTS Supporting information for the proposed

More information

Interpretations of the IMCO code for the Construction and Equipment of Ships carrying Liquefied Gases in Bulk

Interpretations of the IMCO code for the Construction and Equipment of Ships carrying Liquefied Gases in Bulk INTERNATIONAL ASSOCIATION OF CLASSIFICATION SOCIETIES Interpretations of the IMCO code for the Construction and Equipment of Ships carrying Liquefied Gases in Bulk IACS Int. 2008 Contents, Page 1 CONTENTS

More information

EASTERN ENERGY SERVICES PTE LTD. 60 Kaki Bukit Place #02-19 Eunos Tech Park Singapore, SG Singapore Telephone: Fax:

EASTERN ENERGY SERVICES PTE LTD. 60 Kaki Bukit Place #02-19 Eunos Tech Park Singapore, SG Singapore Telephone: Fax: 2 Table Of Contents 1. Introduction 3 2. About this Manual 3 3. Contacting YZ Systems 3 4. Vessel Components 4 5. Specifications 5 6. Application 6 7. Theory of Operation 7 8. DuraSite Installation & Use

More information

Rules for Classification and Construction Ship Technology

Rules for Classification and Construction Ship Technology I Rules for Classification and Construction Ship Technology 1 Seagoing Ships 9 Oil Recovery Vessels Edition 1993 The following Rules come into force on 1st September, 1993. The respective latest edition

More information

RULES FOR THE CONSTRUCTION AND CLASSIFICATION OF MOBILE OFFSHORE DRILLING UNITS TITLE MOBILE OFFSHORE DRILLING UNITS SECTION 6 PIPING CHAPTERS SCOPE

RULES FOR THE CONSTRUCTION AND CLASSIFICATION OF MOBILE OFFSHORE DRILLING UNITS TITLE MOBILE OFFSHORE DRILLING UNITS SECTION 6 PIPING CHAPTERS SCOPE DE NAVIOS E AERONAVES of Mobile Offshore Drilling Units Hull Part II PIPING - Section 6 PART II RULES FOR THE CONSTRUCTION AND CLASSIFICATION OF MOBILE OFFSHORE DRILLING UNITS TITLE MOBILE OFFSHORE DRILLING

More information

API MPMS Chapter 17.6 Guidelines for Determining the Fullness of Pipelines between Vessels and Shore Tanks

API MPMS Chapter 17.6 Guidelines for Determining the Fullness of Pipelines between Vessels and Shore Tanks API MPMS Chapter 17.6 Guidelines for Determining the Fullness of Pipelines between Vessels and Shore Tanks 1. Scope This document describes procedures for determining or confirming the fill condition of

More information

LNG BOIL-OFF RE-LIQUEFACTION PLANTS AND GAS COMBUSTION UNITS

LNG BOIL-OFF RE-LIQUEFACTION PLANTS AND GAS COMBUSTION UNITS CASSIFICATION NOTES No. 61.2 NG BOI-OFF RE-IQUEFACTION PANTS AND GAS COMBUSTION UNITS MAY 2006 Veritasveien 1, NO-1322 øvik, Norway Tel.: +47 67 57 99 00 Fax: +47 67 57 99 11 FOREWORD (DNV) is an autonomous

More information

MAHB. INSPECTION Process Hazard Analysis

MAHB. INSPECTION Process Hazard Analysis Number 5 2016 seveso common MAHB INSPECTION s e r i e s criteria Process Hazard Analysis Major Accident Hazards Bureau Security Technology Assessment Unit This publication of the European community on

More information

Guidance for Gas-fuelled Ships

Guidance for Gas-fuelled Ships 2013 Guidance for Gas-fuelled Ships KOREAN REGISTER OF SHIPPING 2013 Guidance for Gas-fuelled Ships GC-09-E KOREAN REGISTER OF SHIPPING APPLICATION OF "GUIDANCE FOR GAS-FUELLED SHIPS " Unless expressly

More information

9.0 Equipment Cleaning and Repair

9.0 Equipment Cleaning and Repair 9.0 Equipment Cleaning and Repair Introduction The following sections provide an overview of procedures and techniques used to prepare phosgene equipment for maintenance and return the equipment to service,

More information

WATER HEATER THERMAL EXPANSION TANKS Owner s Manual. Safety Instructions Installation Maintenance Warranty. Models: 2-5 Gallon Capacity

WATER HEATER THERMAL EXPANSION TANKS Owner s Manual. Safety Instructions Installation Maintenance Warranty. Models: 2-5 Gallon Capacity WATER HEATER THERMAL EXPANSION TANKS Owner s Manual Safety Instructions Installation Maintenance Warranty Models: 2-5 Gallon Capacity Thank You for purchasing this Thermal Expansion Tank. Properly installed

More information

HARBOUR MASTER S WRITTEN INSTRUCTIONS FOR THE HANDLING OF BULK FLAMMABLE LIQUIDS...1

HARBOUR MASTER S WRITTEN INSTRUCTIONS FOR THE HANDLING OF BULK FLAMMABLE LIQUIDS...1 HARBOUR MASTER S WRITTEN INSTRUCTIONS, 2007 Issued in terms of the National Ports Act No. 12 of 2005, Section (74)(3) HARBOUR MASTER S WRITTEN INSTRUCTIONS FOR THE HANDLING OF BULK FLAMMABLE LIQUIDS...1

More information

Company Profile.. About Sammi Machinery

Company Profile.. About Sammi Machinery Company Profile.. About Sammi Machinery What is Line Blind Valve? Line blinding has been used to pipe lines in various indutries wherever either positive shut-off is most concerned or full flow should

More information

LNG Marine Loading Arms and Manifold Draining, Purging and Disconnection Procedure

LNG Marine Loading Arms and Manifold Draining, Purging and Disconnection Procedure LNG Marine Loading Arms and Manifold Draining, Purging and Disconnection Procedure i The Society of International Gas Tanker and Terminal Operators (SIGTTO) The Society of International Gas Tanker and

More information

NATURAL GAS MAINTENANCE. Part 192 Subpart "M"

NATURAL GAS MAINTENANCE. Part 192 Subpart M NATURAL GAS MAINTENANCE Part 192 Subpart "M" CONTACT INFORMATION Pamela West Pipeline Safety Specialist U.S. Department of Transportation PHMSA Inspector Training and Qualifications Main: (405) 686-2310

More information

Inert Air (N2) Systems Manual

Inert Air (N2) Systems Manual INSTRUCTION MANUAL Inert Air (N2) Systems Manual N2-MANUAL 2.10 READ AND UNDERSTAND THIS MANUAL PRIOR TO OPERATING OR SERVICING THIS PRODUCT. GENERAL INFORMATION Positive pressure nitrogen gas pressurizing

More information

SNS BL-13B NPDGamma Experiment

SNS BL-13B NPDGamma Experiment SNS BL-13B NPDGamma Experiment Hydrogen Supply to Cryogenic Target, Relief and Vent System Design Review April 7, 2010 C-156 9:00 10:30 PM Hydrogen System Block Diagram Diagram of Major System Components

More information

APPENDIX 4 STANDARD FORMAT FOR THE PROCEDURES AND ARRANGEMENTS MANUAL

APPENDIX 4 STANDARD FORMAT FOR THE PROCEDURES AND ARRANGEMENTS MANUAL Page 42 APPENDIX 4 STANDARD FORMAT FOR THE PROCEDURES AND ARRANGEMENTS MANUAL Note 1: Note 2: The format consists of a standardized introduction and index of the leading paragraphs to each section. This

More information

Air Eliminators and Combination Air Eliminators Strainers

Air Eliminators and Combination Air Eliminators Strainers Description Air Eliminators and Combination Air Eliminator Strainers are designed to provide separation, elimination and prevention of air in piping systems for a variety of installations and conditions.

More information

RESOLUTION MEPC.64(36) adopted on 4 November 1994 GUIDELINES FOR APPROVAL OF ALTERNATIVE STRUCTURAL OR OPERATIONAL ARRANGEMENTS AS CALLED FOR IN

RESOLUTION MEPC.64(36) adopted on 4 November 1994 GUIDELINES FOR APPROVAL OF ALTERNATIVE STRUCTURAL OR OPERATIONAL ARRANGEMENTS AS CALLED FOR IN MEPC 36/22 THE MARINE ENVIRONMENT PROTECTION COMMITTEE, RECALLING Article 38(a) of the Convention of the International Maritime Organization concerning the function of the Committee, NOTING resolution

More information

MST21 Stainless Steel Balanced Pressure Thermostatic Steam Trap

MST21 Stainless Steel Balanced Pressure Thermostatic Steam Trap 1250650/6 IM-P125-07 ST Issue 6 MST21 Stainless Steel Balanced Pressure Thermostatic Steam Trap Installation and Maintenance Instructions 1. Safety information 2. General product information 3. Installation

More information

CRYOGENIC EXPERTS, INC. World Wide Web Toll Free FOR CEXI Phone (805) Facsimile (805)

CRYOGENIC EXPERTS, INC. World Wide Web   Toll Free FOR CEXI Phone (805) Facsimile (805) CRYOGENIC EXPERTS, INC. World Wide Web http://www.cexi.com E-mail cexi@cexi.com Toll Free 1-800-FOR CEXI Phone (805) 981-4500 Facsimile (805) 981-4501 I. Installation Instructions Installation And Operating

More information

Using LOPA for Other Applications

Using LOPA for Other Applications 10 Using LOPA for Other Applications 10.1. Purpose LOPA is a tool used to perform risk assessments. Previous chapters described its use in assessing the risk level of process hazards scenarios and in evaluating

More information

FAILURE AND HAZARD ANALYSIS OF THE NPDGAMMA LH2 TARGET SYSTEM

FAILURE AND HAZARD ANALYSIS OF THE NPDGAMMA LH2 TARGET SYSTEM FAILURE AND HAZARD ANALYSIS OF THE NPDGAMMA LH2 TARGET SYSTEM Revision: 0.00 Edited by: Seppo Penttila, November 10, 2010 1. General The RSS 8305.0 Installation, Commissioning, and Operation of the NPDGamma

More information

Testing Procedures of Watertight Compartments

Testing Procedures of Watertight Compartments (1996) (Rev.1 Feb 2001) (Rev.2 May 2001) (Rev.3 May 2010) (Rev.4 Aug 2012) Testing Procedures of Watertight Compartments.1 Application Revision 4 of this UR is to be complied with in respect of the testing

More information

A Rationale for Pressure Relief Device(s) Qualification Requirements (LH2)

A Rationale for Pressure Relief Device(s) Qualification Requirements (LH2) UN-GTR PART A INSERTION Stand 09.02.2011, 17:20 Uhr A.3.3 HYDROGEN STORAGE SYSTEM The hydrogen storage system consists of all components that form the primary pressure boundary of the stored hydrogen in

More information

Report on Vessel Casualty of Accident (Form Casualty) Instructions:

Report on Vessel Casualty of Accident (Form Casualty) Instructions: Report on Vessel Casualty of Accident (Form Casualty) Tuvalu Ship Registry 10 Anson Road #25-16 International Plaza Singapore 079903 Tel: (65) 6224 2345 Fax: (65) 6227 2345 Email: info@tvship.com Website:

More information

Tanker Officer Training Standards (TOTS) 4C Product Tanker Simulator Training Course

Tanker Officer Training Standards (TOTS) 4C Product Tanker Simulator Training Course Tanker Officer Training Standards (TOTS) 4C Product Tanker Simulator Training Course Tanker Officer Training Standards (TOTS) 4C Product Tanker Simulator Training Course CONTENTS Prerequisites...1 TOTS

More information

Gas Cabinets and Valve Manifold Boxes: Applying CGA G13- Rev 2015 to Gas Delivery Equipment

Gas Cabinets and Valve Manifold Boxes: Applying CGA G13- Rev 2015 to Gas Delivery Equipment Gas Cabinets and Valve Manifold Boxes: Applying CGA G13- Rev 2015 to Gas Delivery Equipment The Standard Governing the Storage & Use of Silane: Compressed Gas Association s Publication CGA G-13 2015: Storage

More information

SAFETY MANUAL FOR FLAMMABLE PRODUCT TRANSFER

SAFETY MANUAL FOR FLAMMABLE PRODUCT TRANSFER SAFETY MANUAL FOR FLAMMABLE PRODUCT TRANSFER SUPPLIMENT TO eom IMPORTANT READ THIS MANUAL BEFORE PRODUCT INSTALLATION, OPERATION, INSPECTION & MAINTENANCE Tougher and more rigid guidelines are being established

More information

LNG REGASIFICATION VESSELS

LNG REGASIFICATION VESSELS Guide for Building and Classing Regasification Vessels GUIDE FOR BUILDING AND CLASSING LNG REGASIFICATION VESSELS APRIL 2017 American Bureau of Shipping Incorporated by Act of Legislature of the State

More information

Guidelines on Methanol Fueled Vessels

Guidelines on Methanol Fueled Vessels Guidelines on Methanol Fueled Vessels Guidelines Methanol Fueled Vessels Contents Sections 1. Introduction 2. General 2.1 Application 2.2 Definitions 2.3 Alternative Design 2.4 Documentation Requirements

More information

RULES FOR THE CONSTRUCTION AND CLASSIFICATION OF VESSELS IDENTIFIED BY THEIR MISSION SECTION 6 PIPING CHAPTER SCOPE

RULES FOR THE CONSTRUCTION AND CLASSIFICATION OF VESSELS IDENTIFIED BY THEIR MISSION SECTION 6 PIPING CHAPTER SCOPE PARTE II RULES FOR THE CONSTRUCTION AND CLASSIFICATION OF VESSELS IDENTIFIED BY THEIR MISSION TITLE 32 OIL TANKERS SECTION 6 PIPING CHAPTER A B C D E F G H I J K T SCOPE MATERIALS AND MANUFACTURE See Title

More information

DA-SAFE/17/ Nov 2017

DA-SAFE/17/ Nov 2017 Drawing No Rev. Title Cargo Drawings Approval stamp Comment status HT 500095 0 Holding Time 10bar - 40ft 46000L 02b Pending 500095-01 0 GENERAL ARRANGEMENT 01b (?) Pending 500095-02 0 INNER TANK ASSEMBLY

More information

Installation, Operation and Maintenance Instructions for Pacific PA Non-Storage Heat Exchanger

Installation, Operation and Maintenance Instructions for Pacific PA Non-Storage Heat Exchanger OM008 Installation, Operation and Maintenance Instructions for Pacific PA Non-Storage Heat Exchanger The operating and maintenance instructions contained within this package are for Pacific water/water

More information

Chapter 2 Preparations for Tank Cleaning Work

Chapter 2 Preparations for Tank Cleaning Work Chapter 2 Preparations for Tank Cleaning Work Preparatory Procedures for Tank Cleaning Work Make preparations for tank cleaning work according to the procedures given below. 1. Formulating the tank cleaning

More information

Manual Actuated Boiler Blowdown Valves

Manual Actuated Boiler Blowdown Valves Manual Actuated Boiler Blowdown Valves Installation and Maintenance Instructions 1. Safety information 2. General product information 3. Installation 4. Operation 5. Maintenance 6. Spare parts p.1 1. Safety

More information

SAFETY SEMINAR Rio de Janeiro, Brazil - August 3-7, Authors: Francisco Carlos da Costa Barros Edson Romano Marins

SAFETY SEMINAR Rio de Janeiro, Brazil - August 3-7, Authors: Francisco Carlos da Costa Barros Edson Romano Marins SAFETY SEINAR Rio de Janeiro, Brazil - August 3-7, 2009 Using HAZOP and LOPA ethodologies to Improve Safety in the Coke Drums Cycles Authors: Gilsa Pacheco onteiro Francisco Carlos da Costa Barros Edson

More information

CARRIAGE OF DIRECT REDUCED IRON (DRI) BY SEA CHANGES TO THE IMO CODE OF SAFE PRACTICE FOR SOLID BULK CARGO

CARRIAGE OF DIRECT REDUCED IRON (DRI) BY SEA CHANGES TO THE IMO CODE OF SAFE PRACTICE FOR SOLID BULK CARGO The Shipowners Protection Limited St Clare House, 30-33 Minories London EC3N 1BP TO ALL MEMBERS March 2010 Managers of The Shipowners Protection Mutual Protection Limited and Indemnity St Clare House,

More information

REVISED SOLAS REGULATION II-1/3-8 AND ASSOCIATED GUIDELINES (MSC.1/CIRC.1175) AND NEW GUIDELINES FOR SAFE MOORING OPERATIONS FOR ALL SHIPS

REVISED SOLAS REGULATION II-1/3-8 AND ASSOCIATED GUIDELINES (MSC.1/CIRC.1175) AND NEW GUIDELINES FOR SAFE MOORING OPERATIONS FOR ALL SHIPS E SUB-COMMITTEE ON SHIP DESIGN AND CONSTRUCTION 3rd session Agenda item 15 SDC 3/15/1 16 October 2015 Original: ENGLISH REVISED SOLAS REGULATION II-1/3-8 AND ASSOCIATED GUIDELINES (MSC.1/CIRC.1175) AND

More information

Circular China Classification Society (2014) Circ.No.54 Total No.538 Dec.31,2014 ( Total 25 Pages )

Circular China Classification Society (2014) Circ.No.54 Total No.538 Dec.31,2014 ( Total 25 Pages ) C C S 通函 Circular China Classification Society (2014) Circ.No.54 Total No.538 Dec.31,2014 ( Total 25 Pages ) To relevant departments of the Headquarters, Shanghai Rules & Research Institute, plan approval

More information

TSS21 Sealed Thermostatic Steam Tracer Trap

TSS21 Sealed Thermostatic Steam Tracer Trap 1255050/4 IM-P125-10 ST Issue 4 TSS21 Sealed Thermostatic Steam Tracer Trap Installation and Maintenance Instructions 1. Safety information 2. General product information 3. Installation 4. Commissioning

More information

Operating Instructions

Operating Instructions Operating Instructions Before operating the thin film evaporator, please be aware of all safety concerns associated with this experiment: Burn hazard from the column and steam lines, Chemical hazards associated

More information

Standard Pneumatic Test Procedure Requirements for Piping Systems

Standard Pneumatic Test Procedure Requirements for Piping Systems the pressure equipment safety authority Standard Pneumatic Test Procedure Requirements for Piping Systems AB-522 Edition 2, Rev. 1 Issued 2016-10-24 Table of Contents FOREWORD... 1 1.0 INTRODUCTION...

More information

Annual Report on Liquefied Petroleum Gas (LPG) Related Accidents

Annual Report on Liquefied Petroleum Gas (LPG) Related Accidents Annual Report on Liquefied Petroleum Gas (LPG) Related Accidents (13 version) The High Pressure Gas Safety Institute of Japan (KHK) Information Services & Research Department International Affairs Office

More information

GUIDELINES FOR SURVEY OF OIL FLOATING STORAGE VESSELS FIXED AT ANCHORAGE

GUIDELINES FOR SURVEY OF OIL FLOATING STORAGE VESSELS FIXED AT ANCHORAGE GUIDANCE NOTES GD03-2017 CHINA CLASSIFICATION SOCIETY GUIDELINES FOR SURVEY OF OIL FLOATING STORAGE VESSELS FIXED AT ANCHORAGE 2017 Effective from 1 March 2017 BEIJING Chapter 1 GENERAL 1.1 Application

More information

LNG TANDEM OFFLOADING A KEY ENABLING TECHNOLOGY TO MAKE LNG PRODUCTION OFFSHORE HAPPEN

LNG TANDEM OFFLOADING A KEY ENABLING TECHNOLOGY TO MAKE LNG PRODUCTION OFFSHORE HAPPEN LNG TANDEM OFFLOADING A KEY ENABLING TECHNOLOGY TO MAKE LNG PRODUCTION OFFSHORE HAPPEN Fabrice Dumortier 1, Jean-Pierre Queau 1, Jean-Robert Fournier 2 1. SBM Offshore 2. SBM Offshore Keywords: 1. LNG;

More information

Expert System for LOPA - Incident Scenario Development -

Expert System for LOPA - Incident Scenario Development - Expert System for LOPA - Incident Scenario Development - Adam Markowski a, Jaffee Suardin b, and M.Sam Mannan b a Process and Ecological Safety Division, Technical University of Lodz, Poland b Mary Kay

More information

POP Safety Valve. POP Safety Valve INTRODUCTION DEFINITIONS

POP Safety Valve. POP Safety Valve INTRODUCTION DEFINITIONS POP Safety Valve POP Safety Valve INTRODUCTION The effects of exceeding safe pressure levels in an unprotected pressure vessel or system, can have catastrophic effects on both plant and personnel. Safety

More information

A large Layer of Protection Analysis for a Gas terminal scenarios/ cause consequence pairs

A large Layer of Protection Analysis for a Gas terminal scenarios/ cause consequence pairs A large Layer of Protection Analysis for a Gas terminal 2000+ scenarios/ cause consequence pairs Richard Gowland European process Safety Centre The scope of the study was a large gas terminal handling

More information

Transport of gas tanks for motor vehicles

Transport of gas tanks for motor vehicles United Nations Secretariat ST/SG/AC.10/C.3/2016/51 Distr.: General 30 August 2016 Original: English Committee of Experts on the Transport of Dangerous Goods and on the Globally Harmonized System of Classification

More information

Spirax Compact FREME Flash Recovery Energy Management Equipment

Spirax Compact FREME Flash Recovery Energy Management Equipment IM-UK-cFREME UK Issue 1 Spirax Compact FREME Flash Recovery Energy Management Equipment Installation and Maintenance Instructions 1. Safety information 2. General product information 3. Installation 4.

More information

ST/SG/AC.10/C.3/2016/8. Secretariat. United Nations. Transport of gas tanks for motor vehicles. Introduction

ST/SG/AC.10/C.3/2016/8. Secretariat. United Nations. Transport of gas tanks for motor vehicles. Introduction United Nations Secretariat Distr.: General 29 March 2016 ST/SG/AC.10/C.3/2016/8 Original: English Committee of Experts on the Transport of Dangerous Goods and on the Globally Harmonized System of Classification

More information

Module No. # 01 Lecture No. # 6.2 HAZOP (continued)

Module No. # 01 Lecture No. # 6.2 HAZOP (continued) Health, Safety and Environmental Management in Petroleum and Offshore Engineering Prof. Srinivasan Chandrasekaran Department of Ocean Engineering Indian Institute Of Technology, Madras Module No. # 01

More information

Compiled by: B Beard. Approved by: SH Carstens. Description of requirements and procedures for compact provers to be used as verification standards.

Compiled by: B Beard. Approved by: SH Carstens. Description of requirements and procedures for compact provers to be used as verification standards. 1. Scope Description of requirements and procedures for compact provers to be used as verification standards. 2. Reference documents Trade Metrology Act SANS1698 3. Policy A. BASIC REQUIREMENTS Compact

More information

USER MANUAL. 1. Principle of operation. 2. Delivery condition. SPRING-LOADED SAFETY VALVES zarmak. Edition: 07/2016 Date: V (ex.

USER MANUAL. 1. Principle of operation. 2. Delivery condition. SPRING-LOADED SAFETY VALVES zarmak. Edition: 07/2016 Date: V (ex. ZETKAMA Sp. z o.o. ul. 3 Maja 12 PL 57-410 Ścinawka Średnia SPRING-LOADED SAFETY VALVES zarmak USER MANUAL 782V (ex. 782) Edition: 07/2016 Date: 01.07.2016 TABLE OF CONTENTS 1. Principle of operation 2.

More information