1 CITY OF MANISTIQUE NON MOTORIZED TRANSPORTATION PLAN DEVELOPED BY: COLEMAN ENGINEERING COMPANY PREPARED FOR: THE CITY OF MANISTIQUE THIS PLAN WAS PAID FOR THROUGH A GRANT FROM THE SAULT TRIBE OF CHIPPEWA INDIANS STRATEGIC ALLIANCE FOR HEALTH PROJECT

2 THE PURPOSE OF THE NON MOTORIZED TRANSPORTATION PLAN IS TO PROVIDE SAFE, SCENIC ROUTES THROUGHOUT THE CITY OF MANISTIQUE THAT ENCOURAGE THE USE OF NON MOTORIZED MODES OF TRAVEL FOR DAILY TRANSPORTATION, HEALTH, AND TOURISM WHILE ENHANCING MANISTIQUE S ATTRIBUTES AND APPEAL FOR RESIDENTS AND VISITORS ALIKE.

3 City of Manistique Non-Motorized Transportation Plan 2012 Table of Contents 1.0 Introduction Scope Non-Motorized Transportation Vision Existing Non-Motorized Transportation System Definitions of Non-Motorized Transportation Infrastructure Types Current Non-Motorized Infrastructure Non-Motorized Points of Interest Proposed Non-Motorized Transportation Improvements Prioritized Improvements Additional Improvements Non-Motorized Transportation Plan Recommendations Infrastructure Development Education Conclusions... 8

4 City of Manistique Non-Motorized Transportation Plan Introduction 1.1 Scope In September of 2010, the City of Manistique passed a resolution in support of Complete Streets, acknowledging the need for an improved infrastructure network throughout the community for both motorized and non-motorized transportation users (see Appendix A for resolution). The need for a Non-Motorized Transportation Plan (NMTP) was critical for the community to improve their existing non-motorized transportation network. The purpose of the NMTP was to establish a plan to provide the citizens of Manistique with a non-motorized transportation system that connects neighborhoods, schools, businesses, and waterfront in a way to maximize mobility and provide a sense of safety for users. To assist with the development of the NMTP, a focus group was formed to help identify a need and vision for the future improvements to the non-motorized transportation network. The focus group consisted of non-motorized users, Engineers, Strategic Alliance for Health Community Coordinator, the City Manager, the City Recreation Director, and other interested parties. Two focus group meetings were held to identify and analyze proposed improvements to the non-motorized system. Agendas, associated handouts distributed at focus group meetings, and a list of attendees are shown in Appendix B. 1.2 Non-Motorized Transportation Vision The purpose of this plan is not to remove or diminish the use of motor vehicles within the City, but to make non-motorized transportation a more desirable transportation option. The established focus group helped identify interest points (destinations) for nonmotorized transportation users. The existing system was then analyzed to determine the deficiencies throughout the City. Future improvements were then identified that would create a complete transportation network for non-motorized users. The future non-motorized improvements offer recreational transportation by means of multi-use trails/paths and boardwalk improvements along the Lake Michigan waterfront. It is envisioned that the community and tourists will use the boardwalk and multi-use trail for walking, biking, running, and in-line skating. It is further envisioned the City s infrastructure will encourage more children to safely walk and bike to school. The City s new infrastructure will also be able to accommodate people with disabilities by providing compliant facilities adhering to the requirements of the Americans with Disabilities Act (ADA). With good non-motorized infrastructure in place, it is anticipated that citizens and visitors of Manistique will use non-motorized transportation for both leisure activities and general transportation. Coleman Engineering Company 1 City of Manistique Non-Motorized Transportation Plan February 2012

5 City of Manistique Non-Motorized Transportation Plan Existing Non-Motorized Transportation System 2.1 Definitions of Non-Motorized Transportation Infrastructure Types Throughout this plan, a variety of infrastructure types for non-motorized transportation will be discussed. These include: Sidewalks: When discussed in this report, refers to concrete path (minimum 4-feet width, 5-foot preferred width). Sidewalk Ramp: The portion of sidewalk adjoining the street to the sidewalk to ease passage to the street, especially for pedestrians with strollers, bicycles, and physically disabled people. Multi-Use Path: Paved path that can be adjacent to roadway or separated from roadway and available for all types of non-motorized users (minimum 10-foot width). Bike Lane: Portion of a paved road (minimum 4-feet wide) designated by striping, signing, and pavement marking for the exclusive use of bicyclists. Trail: Outside of road right-of-way, used for hiking, biking, or cross country skiing (minimum 10-foot width). 2.2 Current Non-Motorized Infrastructure The City currently has sidewalks throughout various neighborhoods. Streets with existing sidewalks are shown in Figure 1. A majority of these sidewalks are old and deteriorating. Some of the sidewalks often stop in the grass leaving pedestrians with no hard surface to walk on. This can be very difficult for a person in a wheel chair to maneuver across the grass to get to the next segment of sidewalk or to the street. The existing sidewalks often include large cracks and do not have sidewalk ramps to the street. Photographs of some existing sidewalks are shown below. Photo 1: Cracked Sidewalk in Manistique Photo 2: No Sidewalk Ramps to Cross Street Coleman Engineering Company 2 City of Manistique Non-Motorized Transportation Plan February 2012

6 City of Manistique Non-Motorized Transportation Plan 2012 An existing boardwalk starts at the Marina and traverses for approximately two miles along the Manistique River and Lake Michigan. The boardwalk offers a fishing pier, picnic areas and access to the East Breakwater Lighthouse. The boardwalk is wheelchair accessible; however bicycles are prohibited from using the boardwalk due to its narrow width. The boardwalk is starting to show signs of weakening, as nails are starting to come up from the boards. A photograph of the existing boardwalk is shown below. Photo 3: Existing Boardwalk along Lake Michigan Figure 1 illustrates the existing non-motorized transportation network in the City of Manistique. Approximately 22 miles of existing sidewalks were inventoried by the Strategic Alliance for Health and volunteers within the community. The inventoried sidewalks and notes are shown in Appendix C. Additionally, there are various non-motorized areas outside of the City limits of Manistique. Indian Lake is a popular non-motorized destination and features hiking trails surrounding the lake. Another recreational area outside Manistique is the Schoolcraft County Environmental Laboratory. The Environmental Lab features outdoor education and recreational trails for non-motorized users. 2.3 Non-Motorized Points of Interest As part of the first focus group meeting, the group helped to identify popular nonmotorized destinations throughout the City and surrounding areas. The points of interest within the City limits are shown on the non-motorized transportation map (see Figure 2). All major points of interest are listed below: Waterfront Downtown City Parks Boat Launch Historic Water Tower Middle/High School Emerald Elementary School Indian Lake Rodgers Park Hospital and Medical Care Facilities Cemetery Coleman Engineering Company 3 City of Manistique Non-Motorized Transportation Plan February 2012

7 8TH ST N 5TH ST N 4TH ST N 3RD ST N 2ND ST N 1ST ST N HOUGHTON AVE RANGE ST STEUBEN ST CATTARAGUS ST POTTER ST S 3RD ST NEW DELTA AVE DELTA AVE ALGER AVE SAGINAW ST SCHOOLCRAFT AVE N MACKINAC AVE AB 94 CLARK ST RIVER VIEW DR LEGEND CENTER ST INTAKE PARK!y Manistique River Highways Railroads Boardwalk RIVERDALE ST Inventory Sidewalks CO RD 442 STATE RD 7TH ST DEER ST 6TH ST!5 DENTON NELSON PARK S 5TH ST S 4TH ST BADGER ST CARIBOU ST W ELK ST S 2ND ST S 1ST ST FRONT ST MARQUETTE AVE AB 94 H ST OTTER ST BEAR ST BEAVER ST LINCOLN PARK!5 CHIPPEWA AVE WALNUT ST N MACKINAC AVE S MACKINAC AVE WOLF ST S HOUGHTON AVE DEER ST WESTON ST MANISTIQUE WATER TOWER RIVER ST SIPHON BRIDGE PEARL ST RIVER ST N CEDAR ST CITY INDUSTRIAL PARK PINE ST IRON ST E ELK ST MIDDLE & HIGH SCHOOL kj N MAPLE ST [_ CITY HALL QUARRY LANE DR MAIN ST ; JAIL WALNUT ST COUNTY INDUSTRIAL PARK NEW ELM ST LITTLE BEAR WEST ARENA Æq!5 LAKEVIEW CEMETERY SCHOOLCRAFT MEMORIAL HOSPITAL COUNTY ROAD COMMISSION CENTRAL PARK ACCESS ROAD GERO AVE ï EAST RD LAKESIDE RD EMERALD ELEMENTARY kj LAKESIDE RD WILSON ST TANNERY RD tu 2!y ï Ö [_ ; 4 ROLLING HILLS DR HILLTOP LN t Date: 2/13/2012 Map Size: 11 x 17" Æq ;òj!x!5!j kj City Limits Boat Launch Cemetery Chamber of Commerce City Hall Courthouse Fishing Locale Hospital Lighthouse Marina Park Public Parking School US 2 THOMPSON HWY PEDESTRIAN WALKWAY ARBUTUS AVE S CEDAR ST AB 94 S MAPLE ST LAKE ST TERRACE AVE OAK ST MANISTIQUE AVE MICHIGAN AVE CHERRY ST W LAKESHORE DR!j SOUTHTOWN CREEK CHIPPEWA AVE HARBORVIEW DR CHAMBER OF COMMERCE MACKINAC RD 4 Ö!y TRADERS POINT DR!x MANISTIQUE RIVER 4 4!j ARBUTUS AVE GARDEN AVE PARK AVE WASHINGTON AVE VETERANS DR LAKE MICHIGAN!j tu 2 tu 2!j LAKE MICHIGAN 0 1,250 2,500 Feet MANISTIQUE MARINA ;òj MANISTIQUE EAST BREAKWATER LIGHTHOUSE!5 LAKESHORE PARK FIGURE 1: CITY OF MANISTIQUE EXISTING NON-MOTORIZED TRANSPORTATION NETWORK

8 City of Manistique Non-Motorized Transportation Plan Proposed Non-Motorized Transportation Improvements The non-motorized transportation focus group helped identify a list of desired improvements to the existing network. Once the list was complete, the group helped identify the top priorities critical for the success of non-motorized transportation. 3.1 Prioritized Improvements After two successful focus group meetings, the group agreed upon a prioritized list of improvements, which are illustrated in Figure 2. These are the improvements that the focus group considered to be critical to the success of non-motorized transportation in Manistique. The priorities should be re-evaluated annually based on available funding and the analysis of projects already underway. The priorities can be separated into smaller projects based on types of funding available. Preliminary costs of the prioritized improvements are discussed in further detail in Table Additional Improvements The focus group identified numerous additional improvements that would help improve the non-motorized transportation network in Manistique and immediate surrounding areas. These improvements should be re-evaluated and prioritized in the future, once the above prioritized improvements are complete. All considered improvements identified by the non-motorized transportation focus group are listed below: Improvements for pedestrian safety at the intersection of Maple Street and Elk Street. Construct a separate bike path to connect the City to Rodgers Park to Thompson to Indian Lake and back to the City. Provide cross country ski/recreational trails near Central Park. Provide restrooms at key areas throughout the non-motorized network. Provide a swimming beach near Traders Point. Construct multi-use trail to the new hospital (near US-2 west of City limits). Explore possibility of using the Thompson Highway Route for a multi-use trail. Coleman Engineering Company 5 City of Manistique Non-Motorized Transportation Plan February 2012

9 N 5TH ST N 4TH ST N 3RD ST N 2ND ST N 1ST ST N HOUGHTON AVE RANGE ST STEUBEN ST CATTARAGUS ST DELTA AVE ALGER AVE SAGINAW ST POTTER ST SCHOOLCRAFT AVE S 3RD ST 8TH ST NEW DELTA AVE N MACKINAC AVE COUNTY R TO: INDIAN LAKE STATE RD AB 94 TO: MUNISING BEAR ST CLARK ST CENTER ST TO: INTAKE PARK INTAKE PARK RIVERDALE ST RIVER VIEW DR [_ CITY INDUSTRIAL PARK!y Manistique River COUNTY ROAD COMMISSION FIGURE 2: CITY OF MANISTIQUE NON-MOTORIZED TRANSPORTATION PLAN PRIORITIZED IMPROVEMENTS PRIORITY #1 PRIORITY #2 PRIORITY #3 PRIORITY #4 PRIORITY #5 - MULTI-USE PATH (LOOP) - US-2 SAFETY IMPROVEMENTS AT CEDAR ST, RANGE ST, VETERANS DRIVE, AND MANISTIQUE AVE - EXPAND EXISTING BOARDWALK WIDTH, ADD PEDESTRIAN BRIDGE ACROSS MANISTIQUE RIVER, AND EXTEND BOARDWALK TO WEST SIDE OF RIVER - REPAIR EXISTING SIDEWALKS AND RAMPS - ADD SIDEWALKS TO CONNECT TO THE EXISTING SIDEWALK NETWORKS HILLTOP LN BADGER ST PINE ST EAST RD TO: US-2 ROLLING HILLS DR CO RD 442 TO: THOMPSON TO: COOKS SOUTHTOWN CREEK 7TH ST DEER ST 6TH ST!5 DENTON NELSON PARK S 5TH ST THOMPSON HWY [_ S 4TH ST CARIBOU ST W ELK ST S 2ND ST S 1ST ST FRONT ST MARQUETTE AVE AB 94 H ST OTTER ST [_ BEAVER ST CHIPPEWA AVE LINCOLN PARK!5 CHIPPEWA AVE WALNUT ST S MACKINAC AVE HARBORVIEW DR CHAMBER OF COMMERCE WOLF ST [_ 4 Ö!y tu 2 tu 2!j LAKE MICHIGAN DEER ST MACKINAC RD WESTON ST MANISTIQUE WATER TOWER SIPHON BRIDGE TRADERS POINT DR 0 1,250 2,500 Feet N MACKINAC AVE S HOUGHTON AVE RIVER ST PEDESTRIAN WALKWAY [_ PEARL ST RIVER ST ARBUTUS AVE!x MANISTIQUE RIVER 4 ;òj N CEDAR ST [_ S CEDAR ST MANISTIQUE MARINA MIDDLE & HIGH SCHOOL [_ 4 IRON ST E ELK ST kj!j [_ AB 94 S MAPLE ST N MAPLE ST N CITY HALL QUARRY LANE DR MAIN ST JAIL ; WALNUT ST COUNTY INDUSTRIAL PARK LITTLE BEAR WEST ARENA LAKE ST NEW ELM ST MANISTIQUE EAST BREAKWATER LIGHTHOUSE!j Æq!5 [_ CENTRAL PARK LAKEVIEW CEMETERY SCHOOLCRAFT MEMORIAL HOSPITAL TERRACE AVE OAK ST MANISTIQUE AVE MICHIGAN AVE ARBUTUS AVE GARDEN AVE PARK AVE ACCESS ROAD GERO AVE WASHINGTON AVE [_ ï [_ LAKESIDE RD EMERALD ELEMENTARY [_ kj [_!5 LAKESIDE RD LAKESHORE PARK WILSON ST CHERRY ST VETERANS DR TANNERY RD TO: GULLIVER W LAKESHORE DR!j tu 2 LAKE MICHIGAN!y ï Ö N ; 4 Æq ;òj!x!5 [_!j kj LEGEND Highways Railroads Boat Launch Cemetery US 2 Existing Boardwalk Proposed Boardwalk Proposed Multi-Use Path Alternative Route for Multi-Use Path Existing Sidewalk Future Sidewalk / Path City Limits Chamber of Commerce t City Hall Courthouse Fishing Locale Hospital Lighthouse Marina Park Non-Motorized Point of Interest Public Parking School Date: 2/13/2012 Map Size: 11 x 17"

10 City of Manistique Non-Motorized Transportation Plan 2012 Table 1: Non-Motorized Transportation Prioritized Improvements Priority Improvement *Approximate Cost Improvement Rationale Assumptions #1 Multi-use path/loop (approximately 3 miles). $0.4 Million Recreational separated trail for walkers, in-line skaters, families, and cyclists. Completes loop around the east side of the City by connecting one end of the existing boardwalk to the other end of existing boardwalk. Assumed the proposed improvements would include a 10-foot wide paved path, signing, and marking. Cost does not include any property acquisition that may be required. #2 US-2 safety improvements at Cedar Street, Range Street, Veterans Drive, and Manistique Avenue intersections. #3 Expand existing boardwalk width, add pedestrian bridge across the Manistique River, and create pathway/boardwalk along west side of the Manistique River (approximately 2.5 miles of boardwalk and 850-foot pedestrian bridge). #4 Repair/replace existing sidewalks throughout the City of Manistique (approximately 22.7 miles). #5 Construct new sidewalks to connect existing sidewalk networks (approximately 15.7 miles) $ 1.3 Million The existing intersection is a safety concern for pedestrians crossing US-2 at Cedar Street. There is also a need for markings or signage of pedestrian crossings at the intersections of Range Street, Veterans Drive, and Manistique Avenue. Assumed the proposed improvements would include new intersection configuration including new sidewalk ramps, signing, and marking. $6.3 Million Existing boardwalk is not wide enough for multi purpose use. The widening of boardwalk would be a complete reconstruction due to the condition of the Assumed entire reconstruction of existing boardwalk at 10-foot width. existing boardwalk. The pedestrian bridge across the Cost does not include any Manistique River would connect the downtown and east side waterfront to the existing areas of interest property acquisition that may be required. on the west side of the river. The pedestrian bridge across the river would also create a sense of safety for non-motorized users to be separated from vehicular traffic on US-2. $3.8 Million Many of the existing sidewalks are in poor condition. ADA compliant sidewalk ramps need to be installed at a majority of sidewalk crossings. $2.6 Million The existing sidewalks do not connect to all areas of interest, often leaving pedestrians in the grass. There are apparent areas throughout the City which show "goat paths" where pedestrians walk through grass to get to next segment of sidewalk. Assumed that all existing sidewalks will need to be replaced at existing width. Assumed the proposed sidewalks will be constructed at 5-foot width. Proposed sidewalks will be "retrofitted" into existing areas and do not include any additional roadway improvements. *Please note that costs are for planning purposes only. Approximate cost only includes construction and engineering costs for proposed improvements at this time. Approximate cost does NOT include any property acquisition that may be required for improvements. Approximate cost also reflects cost to date and does not include inflation. Coleman Engineering Company 7 City of Manistique Non-Motorized Transportation Plan February 2012

11 City of Manistique Non Motorized Transportation Plan Non Motorized Transportation Plan Recommendations 4.1 Infrastructure Development To continue to develop Manistique as a pedestrian and bike friendly community, further improvements to the non motorized transportation network are recommended. Those recommendations were identified and prioritized in Table 1, as previously shown. The rationale for these improvements was based on the focus group discussions and feasibility of each improvement. Community surveys also supplement the aspiration for improvement of the existing non motorized transportation system. Appendix D includes walking and biking audit surveys completed by citizens of Manistique in Education In addition to infrastructure improvements, the focus group identified the need to educate the citizens of Manistique about a current sidewalk program offered by the City of Manistique. The City has a cost sharing program to help home owners pay for sidewalk replacement in front of their property. The City will construct the sidewalk if the homeowner agrees to pay for the concrete sidewalk materials. With increased education of the cost sharing program it is envisioned that more homeowners would take the opportunity to provide new sidewalk in their neighborhood. 4.3 Conclusions It is anticipated that the improvements identified in this plan for non motorized transportation will be implemented in the future. In order to implement these improvements, the Manistique Strategic Alliance for Health Non Motorized Transportation Committee should be expanded to identify and pursue possible funding sources for all or portions of projects within this plan under the guidance of the Manistique City Council. Finding grant funding for non motorized transportation should be a priority for the City and established committee. By obtaining funds for smaller projects, the City can work one step at a time to improve and build the non motorized transportation network in Manistique. Coleman Engineering Company 8 City of Manistique Non Motorized Transportation Plan February 2012

12 LIST OF APPENDICES Appendix A: Complete Streets Resolution Appendix B: NMTP Focus Group Materials Appendix C: Manistique Sidewalk Inventory Appendix D: Manistique Walking Audit and Manistique Biking Audit Appendix E: Complete Streets Survey Results

13 Appendix A: Complete Streets Resolution

14 Complete Streets Resolution for Manistique, Michigan Passed by unanimous vote of the Manistique City Council on September 13, 2010 WHEREAS, increasing walking and bicycling offers the potential for greater health of the population, and more livable communities; and WHEREAS, A Complete Street is safe, comfortable, and convenient for travel by automobile, foot, bicycle, and transit regardless of age or ability; and WHEREAS, The Michigan Legislature has passed Complete Streets legislation that requires the Michigan Department of Transportation and local governments to consider all users in transportation related projects; and WHEREAS, the Michigan Planning Enabling Act has been amended, requiring that all transportation improvements identified in a plan are appropriate to the context of the community and considers all legal users of the public right of way; and WHEREAS, Complete Streets support economic growth and community stability by providing accessible and efficient connections between home, school, work, recreation and retail destinations by improving the pedestrian and vehicular environments throughout communities; and WHEREAS, Complete Streets enhance safe walking and bicycling options for school-age children, in recognition of the objectives of the national Safe Routes to School program; and WHEREAS, the City of Manistique recognizes the importance of street infrastructure and modifications such as sidewalks, crosswalks, shared use paths, bicycle lanes, signage, narrow vehicle lanes and accessible curb ramps, that enable safe, convenient, and comfortable travel for all users; therefore BE IT RESOLVED, that the City of Manistique, to the extent feasible, will include Complete Streets design considerations and practices as a routine part of infrastructure planning and implementation; and BE IT FURTHER RESOLVED, that the City of Manistique supports the future development of a non-motorized transportation plan and a Complete Streets ordinance that supports ease of use and safety for all users of transportation systems within the City of Manistique.

15 Appendix B: NMTP Focus Group Materials

16 AGENDA Non-Motorized Transportation Plan Focus Group June 23 rd, Introductions 2. Purpose of Non-Motorized Transportation Plan: To establish a plan to provide the citizens of Manistique with a non-motorized transportation system that connects neighborhoods, schools, businesses, and waterfront in a way to maximize mobility and provide a sense of safety for users. 3. Goal of Focus Group Meeting #1: Identify and discuss need and vision for future improvements to the non-motorized transportation network in Manistique. a. Analyze existing non-motorized transportation network and identify deficiencies (existing conditions map); b. Identify areas of interest for non-motorized transportation users (waterfront, downtown, etc.); c. Identify potential improvements to non-motorized transportation system; d. Prioritize improvements. 4. Comments and Closing

17 Non-Motorized Transportation General Information Modes of Non-Motorized Transportation Walking Bicycling Wheelchair Travel Small-Wheeled Transport o Skates o Skateboards o Push Scooters Types of Non-Motorized Transportation Systems Sidewalks: Should be located on both sides of road, and ideally set back from roadway (4-foot min. width, 5-foot preferred width). Bike lanes/paved shoulders: Approximately 5 feet wide paved surface (4-foot min.) delineated by solid white stripe or bike icon. Shared use paths: Paved path can be adjacent to roadway and available for all types of non-motorized users (10-foot min. width). Off-Road Trail: Outside of road right-of-way, used for hiking and biking (10-foot min. width). Signed Shared Roadways: Used where a bike lane is not feasible. Indicates to motorists to expect bicyclists.

18 Non-Motorized Transportation Focus Group Comment Form NMTP Group Attendee: Areas/Points of Interest for Non-Motorized Users Non-Motorized Transportation Plan Priorities Other Comments:

19 RIV ER VIE W DR NOTES 94 N MACKINAC AVE CLARK ST Railroads Boardwalk DELTA AVE ALGER AVE CENTER ST Inventory Sidewalks RIVERDALE ST BEAR ST D City Limits BADGER ST N CEDAR ST IRON ST ST N W ELK ST ER ROLLING HILLS DR N TA S ES A RO D RY NE Cemetery Chamber of Commerce City Hall Courthouse Fishing Locale Hospital RD NEW ELM ST ST QUARRY LANE DR RI V SIPHON BRIDGE COUNTY INDUSTRIAL PARK C AC N MAPLE ST S HOUGHTON AVE S MACKINAC AVE CHIPPEWA AVE CITY HALL MANISTIQUE WATER TOWER DEER ST S 1ST ST S 2ND ST S 3RD ST S 4TH ST S 5TH ST DEER ST ES TO N MACKINAC AVE N 1ST ST N 2ND ST N 3RD ST N 4TH ST N 5TH ST 6TH ST 8TH ST 7TH ST 94 Boat Launch D ER E S ID LA K CO RD 442 LINCOLN PARK H ST W WOLF ST NEW DELTA AVE PINE ST CARIBOU ST Non-Inv. Sidewalks COUNTY ROAD COMMISSION CITY INDUSTRIAL PARK EAST RD R Highways iver ue R istiq Man INTAKE PARK N HOUGHTON AVE ST AT E Legend Lighthouse CENTRAL PARK E ELK ST Marina LITTLE BEAR WEST ARENA MIDDLE & HIGH SCHOOL BEAVER ST LAKEVIEW CEMETERY Park Public Parking S IDE T SCHOOLCRAFT MEMORIAL HOSPITAL RD S ER RIV 2 JAIL WALNUT ST GERO AVE RR TE PEARL ST OTTER ST WILSON ST E AC WALNUT ST School EMERALD ELEMENTARY MAIN ST MAR Q U ETTE ST LA KE SCHOOLCRAFT AVE FRONT ST DENTON NELSON PARK R HA BO MICHIGAN AVE DR RANGE ST EW NA C RD AD E EK N CR E RS PO IN T DR PARK AVE WASHINGTON AVE 2 MANISTIQUE MARINA 2 LAKE MICHIGAN NS DR TR ARBUTUS AVE GARDEN AVE R IVE ER TOW SOUTH CH IP PE W A U TIQ NI S MA AVE MAC KI STEUBEN ST I RV CHAMBER OF COMMERCE DR RE SH O LA KE W S MAPLE ST E AV MANISTIQUE AVE SAGINAW ST S PEDESTRIAN WALKWAY VE TE RA TU OAK ST CATTARAGUS ST U 94 LAKE ST B S CEDAR ST AR TH O Y POTTER ST E AV CHERRY ST HW ON MPS LAKESHORE PARK LAKE MICHIGAN MANISTIQUE EAST BREAKWATER LIGHTHOUSE CITY OF MANISTIQUE EXISTING NON-MOTORIZED TRANSPORTATION NETWORK

20 Joan Ecclesine S I G N I N S H E E T * * * * P L E A S E P R I N T C L E A R L Y * * * * City of Manistique Non-Motorized Transportation Plan Focus Group June 23 rd, 2011 Name Address George Ecclesine 201 Cattaragus Street Phone Number Manistique, MI jecclesine@mdsecp.com Carraragus Street Manistique, MI geccles@charter.mi.net Gary & Laurie Lindstrom Diane Stimac Connie Meade Cindy King Doug Smith Kathy Jerde Carla Cheuvront Gerry Reese Brian Ecclesine 235 Range Street Manistique, MI glindstrom@manistique.k12.mi.us llindstrom@manistique.k12.mi.us Oak Street Manistique, MI ddstimac@aol.com W. Glenwood Drive Manistique, MI cmeade29@charter.et S. Cedar Street Manistique, MI n/a N. Krummich Road Manistique, MI NEW doug@superiorplaymi.com S. Cedar Street Manistique, MI musseed@centurylink.net S. Cedar Street Manistique, MI itscarlache@yahoo.com W. Michigan Shores Rd. Gulliver, MI greese@centurylink.net (H) (C) 201 Cattaragus Street Manistique, MI n/a

21 S I G N I N S H E E T * * * * P L E A S E P R I N T C L E A R L Y * * * * City of Manistique Non-Motorized Transportation Plan Focus Group June 23 rd, 2011 Name Address Phone Number City Hall (O) Sheila Aldrich Manistique, MI saldrich@chartermi.net (C) 522 Park Avenue Kerry Ott Manistique, MI kott@saulttribe.net Kevin Trevillian Donna Lynts 635 Circle Drive Iron Mountain, MI ktrevillian@coleman-engineering.com Circle Drive Iron Mountain, MI dlynts@coleman-engineering.com Rick Stram (did not sign in)

22 AGENDA Non-Motorized Transportation Plan Focus Group October 18, Introductions 2. Purpose of Non-Motorized Transportation Plan: To establish a plan to provide the citizens of Manistique with a non-motorized transportation system that connects neighborhoods, schools, businesses, and waterfront in a way to maximize mobility and provide a sense of safety for users. 3. Goal of Focus Group Meeting #2: Discuss future improvements to the non-motorized transportation network in Manistique. a. Analyze prioritized improvements for non-motorized transportation network and identify deficiencies (non-motorized transportation map and table); b. Analyze other improvements for non-motorized transportation network (see comment sheet); 4. Future Steps for Non-Motorized Transportation Plan (see flow chart) 5. Comments and Closing

23 Non-Motorized Transportation Focus Group Priority #1 #2 #3 #4 #5 Improvement Repair/replace existing sidewalks throughout the City of Manistique (approximately 22.7 miles). Construct new sidewalks to connect existing sidewalk networks (approximately 15.7 miles). US-2 safety improvements at Cedar Street intersection. Multi-use path/loop (approximately 3 miles). Expand existing boardwalk width, add pedestrian bridge across Manistique River, and create pathway/boardwalk along west side of Manistique River (approximately 2.5 miles of boardwalk and 850-foot pedestrian bridge). Table 1: Prioritized Improvements *Approximate Improvement Rationale Cost $3.75 Million The existing sidewalks are in poor condition. ADA compliant sidewalk ramps need to be installed at a majority of sidewalk crossings. $2.6 Million The existing sidewalks do not connect to all areas of interest, often leaving pedestrians in the grass. There are apparent areas throughout the City, which show "goat paths" where pedestrians walk through the grass to get to the next segment of sidewalk. $0.31 Million The existing intersection is a safety concern for pedestrians crossing US-2. $0.38 Million Recreational separated trail for walkers, in-line skaters, families, and cyclists. Completes loop around the east side of the City by connecting one end of the existing boardwalk to the other end of existing boardwalk. $6.70 Million Existing boardwalk is not wide enough for multi-purpose use. The widening of the boardwalk would be a complete reconstruction due to the condition of the existing boardwalk. The pedestrian bridge across the Manistique River would connect the downtown and east side waterfront to the existing areas of interest on the west side of the river. The pedestrian bridge across the river would also create a sense of safety for non-motorized users to be separated from vehicular traffic on US-2. Assumptions Assumed that all existing sidewalks will need to be replaced at existing width. Assumed the proposed sidewalks will be constructed at 5-foot width. Proposed sidewalks will be "retrofitted" into existing areas and do not include any additional roadway improvements. Assumed the proposed improvements would include new intersection configuration including new sidewalk ramps, signing, and marking. Assumed the proposed improvements would include a 10-foot wide paved path, signing and marking. Cost does not include any property acquisition that may be required. Assumed entire reconstruction of existing boardwalk at 10' width. Cost does not include any property acquisition that may be required. *Please note that costs are for planning purposes only. Approximate cost only includes construction and engineering costs for proposed improvements at this time. Approximate cost does NOT include any property acquisition that may be required for improvements. Approximate cost also reflects cost to date and does not include inflation.

24 Non-Motorized Transportation Focus Group Other improvements to be included in Non-Motorized Transportation Plan Improvements for pedestrian safety at intersection of Maple Street and Elk Street; Provide separate bike path/lanes to connect the City to Rodgers Park to Thompson to Indian Lake and back to the City; Provide cross country ski trails near Central Park. These trails could be used for hiking/running during summer months; Provide restrooms at key areas throughout non-motorized network; Provide swimming beach near Traders Point. Comments (Please leave your comments/suggestions for Non-Motorized Transportation Plan)

25 Non-Motorized Transportation Focus Group Process of Non-Motorized Transportation Plan Existing Non-Motorized Transportation Network (COMPLETE) Focus Group #1 (06/23/11): Identified need for improvements & identified projects. (COMPLETE) Proposed Non-Motorized Transportation Network (DRAFT COMPLETE) Focus Group #2 (10/18/11): Analyze proposed improvements. (IN PROGRESS) Coleman Engineering to submit Non-Motorized Transportation Plan to City and Sault Tribe for review City and Sault Tribe to Review Plan Coleman to finalize Non- Motorized Transportation Plan City to formally adopt the Non-Motorized Transportation Plan Form Non-Motorized Transportation Committee or Group Committee or Group to seek out funding for projects Obtain funding for projects COMPLETE PROJECTS

26 BEAR ST N 3RD ST N 5TH ST N 4TH ST N HOUGHTON AVE N 2ND ST DELTA AVE ALGER AVE BADGER ST CLARK ST CARIBOU ST N 1ST ST H ST 8TH ST NEW ELM ST CO RD 442 DEER ST W ELK ST CHERRY ST MICHIGAN AVE CATTARAGUS ST SAGINAW ST POTTER ST NEW DELTA AVE N MACKINAC AVE DEER ST SCHOOLCRAFT AVE S 3RD ST BEAVER ST WALNUT ST LAKE MICHIGAN RIVERDALE ST MANISTIQUE MARINA LAKE MICHIGAN RANGE ST STEUBEN ST ARBUTUS AVE GARDEN AVE PARK AVE WASHINGTON AVE ROLLING HILLS DR W LAKESHORE DR [_!y!5 [_ [_!5 [_ [_ kj N ; Æq!5 [_ [_ ï [_ kj 4 [_ Ö!y!x 4 4!j [_!j ;òj [_!j!5!j RIVER VIEW DR AB 94 TO: INTAKE PARK Manistique River INTAKE PARK CENTER ST CITY INDUSTRIAL PARK COUNTY ROAD COMMISSION STATE RD EAST RD PINE ST TANNERY RD DENTON NELSON PARK LINCOLN PARK MANISTIQUE WATER TOWER SIPHON BRIDGE MIDDLE & HIGH SCHOOL CITY HALL JAIL COUNTY INDUSTRIAL PARK N CEDAR ST WESTON ST WOLF ST LAKESIDE RD ACCESS ROAD IRON ST N MACKINAC AVE N MAPLE ST AB 94 6TH ST 7TH ST QUARRY LANE DR S 1ST ST LITTLE BEAR WEST ARENA CENTRAL PARK CHIPPEWA AVE S 5TH ST S 4TH ST S 2ND ST RIVER ST S HOUGHTON AVE S MACKINAC AVE E ELK ST LAKEVIEW CEMETERY FRONT ST LAKESIDE RD SCHOOLCRAFT MEMORIAL HOSPITAL RIVER ST EMERALD ELEMENTARY MAIN ST OTTER ST GERO AVE WILSON ST TERRACE AVE WALNUT ST PEARL ST MARQUETTE ST THOMPSON HWY OAK ST AB 94 S CEDAR ST ARBUTUS AVE MANISTIQUE AVE LAKE ST S MAPLE ST HARBORVIEW DR MACKINAC RD CHAMBER OF COMMERCE MANISTIQUE RIVER CHIPPEWA AVE TRADERS POINT DR VETERANS DR SOUTHTOWN CREEK tu 2 tu 2 MANISTIQUE EAST BREAKWATER LIGHTHOUSE LAKESHORE PARK tu 2 COUNTY NOTES TO: THOMPSON TO: MUNISING TO: INDIAN LAKE TO: GULLIVER TO: COOKS PEDESTRIAN WALKWAY ,250 2,500 3,750 5,000 Feet CITY OF MANISTIQUE NON-MOTORIZED TRANSPORTATION PLAN PRIORITIZED IMPROVEMENTS PRIORITY #1 PRIORITY #2 PRIORITY #3 PRIORITY #4 PRIORITY #5 - REPAIR EXISTING SIDEWALKS AND RAMPS - ADD SIDEWALKS TO CONNECT TO THE EXISTING SIDEWALK NETWORKS - US-2 SAFETY IMPROVEMENTS AT CEDAR ST INTERSECTION - MULTI-USE PATH (LOOP) - EXPAND EXISTING BOARDWALK WIDTH, ADD PEDESTRIAN BRIDGE ACROSS MANISTIQUE RIVER, AND EXTEND BOARDWALK TO WEST SIDE OF RIVER TO: GULLIVER!y ï ; 4!x kj LEGEND Æq ;òj Hospital!j Highways Railroads Existing Boardwalk Boat Launch Cemetery Ö N City Hall Multi-Use Path Existing Sidewalk Future Sidewalk / Path Chamber of Commerce t Courthouse Fishing Locale Lighthouse Marina!5 Park Non-Motorized Point of Interest [_ Proposed Boardwalk Proposed City Limits Public Parking School Date: 10/17/2011 Map Size: 11 x 17"

27 S I G N I N S H E E T * * * * P L E A S E P R I N T C L E A R L Y * * * * City of Manistique Non-Motorized Transportation Plan Focus Group October 18, 2011 Name Address Phone Number City Hall (O) Sheila Aldrich Manistique, MI saldrich@chartermi.net (C) 522 Park Avenue Kerry Ott Manistique, MI kott@saulttribe.net Kevin Trevillian 635 Circle Drive Iron Mountain, MI ktrevillian@colemanengineering.com Donna Lynts Doug Smith 635 Circle Drive Iron Mountain, MI dlynts@coleman-engineering.com N. Krummich Road Manistique, MI doug@superiorplaymi.com Gary & Laurie Lindstrom Bill Pohlman 235 Range Street Manistique, MI 11689W Advaent Road Cooks, MI glindstrom@manistique.k12.mi.us llindstrom@manistique.k12.mi.us Manistiquerecreation@live.com

28 Appendix C: Manistique Sidewalk Inventory

29 Manistique Sidewalk Inventory December 2011 Update East - West Roads US-2 (fair to good) o North side - East edge of Michigan St. Police Post (just East of Arbutus) to just West of Arbutus. (.04) o North side - S. Cedar to Pedestrian Tunnel (.13) o South Side - Subway Shop through Pedestrian Tunnel (.37) o South Side - Bridge over Manistique River (does not connect to any sidewalk on either end of the bridge) (.15) Washington (fair) o Steuben to Range - North side of street (.12) o Steuben to Range - South side of street only partial from Range to the east (.03) Park (poor to fair; except new section) o *Veterans to Range South side (*Veterans to Cattaragus new in 2010) (.32) o Cattaragus to Range North side (.23) Garden (poor to fair) o Saginaw to Range both sides of street (.47 x 2) o Range to West - North side only (.02) Arbutus (fair to good) o Halfway between Saginaw and Cattaragus to US-2 North side (.48) o Halfway between Saginaw and Cattaragus to Lake St. South side (.43) o S. Maple to Pearl (.25 x 2) Michigan (poor to fair) o Cattaragus to Range South side (.23) o Just East of Cattaragus to Range North side (.24) Manistique (poor to fair) o Just West of Potter to Range South side (.31) o Cattaragus to Range North side (.23) Note: sidewalks on north side of Manistique Ave between Potter and Cattaragus start and stop several times, leaving pedestrians in the grass. Oak (fair to good) o Potter to Arbutus North side (.65) o Just West of Potter to Arbutus South side (.61) Cherry (fair to good) o Steuben to Terrace both sides (.05 x 2) o Terrace to Range South side (.07) Walnut (fair to good) o Range to Pearl St. both sides (.34 x 2) Main (fair to good) o Steuben to Terrace South side (.13) o Terrace (main door of SMH) to Lake St North side (.08) o Lake St to Pearl both sides (.25 x 2) Gero (fair to good) o Terrace to Steuben - north side only (.15) E. Elk (fair) o N. Maple to River both sides (mostly, small section missing on south side) (.20 South side;.21 North side) Elm (fair) o Just East of Maple to Cedar - South side (.10) Deer (fair to good) o H-Street (fair) o Short section from N. 1 st St - North side (.01) Wolf St. (poor) E. Elk to 5 th St. both sides (.81 South side;.80 North side)

30 o N. Houghton to N. Mackinac (incomplete and overgrown) South side (.06) Center St. (poor to fair) o Alger Ave to N. Houghton North side (.14) *Note: one piece of sidewalk starts at Delta Ave and goes west on South side only (.01) Bear St. (poor to fair) o Alger Ave to N. Houghton North side (in very bad shape West of Delta Ave.) (.13) W. Elk St. (fair) o S. Mackinac to Chippewa North side and incomplete (.06) o Chippewa to Schoolcraft South side (.08) o Chippewa to just beyond Schoolcraft North side (.11) Total sidewalk miles on East West Streets in Manistique: miles Manistique Sidewalk Inventory December 2011 Update North - South Roads *Veterans Dr. (good) o Pamida to Park West side (*New in 2010) (.10) Potter (fair) o Just South of Cherry to Oak East side (.04) Cattaragus (poor to fair) o Cherry to Oak West side (.05) o Oak to Manistique both sides (.05 x 2) o Manistique to Garden West side (.16) Steuben (very bad to poor) o Cherry to Oak both sides (.05 x 2) o Oak to Manistique West side (.05) o Manistique to Arbutus East side (.10) o Arbutus to Garden West side (.05) o Garden to Park both sides (.05 x 2) Terrace (fair) o Main to Gero - East side only (.05) Range St (Walnut to Oak = poor to fair; Oak to Washington & US-2 = good) o Walnut to just South of Washington East side (.42) o Walnut to US-2 West side (.46) Lake St (fair to good) o Just North of Main St. to Main East side (.01) o Main to Arbutus both sides (.35 x 2) N. Maple (fair) o Just North of City Hall to Elm West side (.08) o Elm/New Elm to Maple - East side (.11) o Elm/New Elm to Main St. West side (.39) o Little Bear West to Football Stadium Entrance (short section) (.09) S. Maple (poor to fair) o Main to Lakeshore Dr East side (.29) One section on East side by St. Francis school fence is missing or severely broken o Main to US-2 West side (.30) Pearl (good) o Main to Arbutus both sides (.13 x =.25) N. Cedar (poor to fair to good; worst conditions at the north end of street) o Just South of Pine to High School parking lot East side (.48) o Farther South of Pine to River Street - West side (.46) o Short section on East side from River - stops short of high school parking lot (.02)

31 S. Cedar (downtown area) (good) o Main to US-2 - West side (.26) o Main to just north of US-2 (stops at Funeral Home) - East Side (.25) River (fair to good) o Main to E. Elk both sides (.26 x 2) New Delta (fair) o Partial between Clark and Wolf - West side (.04) o Wolf to just North of Deer - West side (.10) o Clark to Deer - East side (.24) Weston (poor) o Deer to about ½ way West side. Extremely overgrown (.12) N. Houghton (poor to fair) o Just North of Center to Deer East side (.49) o Center to RR-Crossing North of Wolf West side (.23) o North of Wolf St. to Deer West side (.16) o Between Deer and Elk East side (.08) o Between Deer and Elk (with gaps) West side (.06) N. Mackinac (poor to fair) o Wolf to Deer East side (.11) o South of Wolf to Deer West side (.07) S. Mackinac (poor to fair) o Deer to Elk both sides (.11 x 2) Chippewa Ave (fair to good) o Deer to Elk both sides (.11 x 2) o Elk to Harborview West side (.45) Schoolcraft (fair to good) o W. Elk to Otter both sides (.25 x 2) N. 1 st St (poor to fair) o Badger to Deer West side (.23) o Badger to Deer East side (lots of disconnects and broken sections) (.16) S. 1 st St. (poor to fair) o Deer St. to W. Elk West side (.11) o Deer St. to W. Elk East side (badly broken and overgrown) (.08) N. 2 nd St. (poor to fair) o Badger to Deer West Side (.23) o South of Caribou to Deer East side (.09) S. 2 nd St (poor to fair) o Deer to W. Elk - Both sides (.11 x 2) N. 3 rd St. (poor, fair, good) o Caribou to Deer both sides (.11 x 2) S. 3 rd St. (poor to fair) o Deer to Elk both sides; badly overgrown on East side (.11 x 2) N. 4 th St. (fair) o Caribou to Deer both sides (.11 x 2) S. 4 th St. (fair) o Deer to Elk both sides (.11 x 2) N. 5 th St. (fair to good) o Badger to Deer East side (.23) o Caribou to Deer West side (.11) Total sidewalk miles on North - South Streets: miles Total sidewalk miles in Manistique: miles

32 Appendix D: Manistique Walking Audit and Manistique Biking Audit

33 Manistique - Walking Audit 1. Describe the location of your walk (such as street names, neighborhoods or other describing information). Response Count 62 answered question 62 skipped question 0 2. Did you encounter any problems on your walk? Response Percent Response Count Sidewalks or paths started and stopped 27.4% 17 Sidewalks broken, cracked, or uneven 41.9% 26 Sidewalks blocked by poles, signs, bushes, vehicles, etc 11.3% 7 No sidewalk, path, or shoulder 25.8% 16 Too much traffic 6.5% 4 Other (describe in comment box below) 9.7% 6 Did not encounter any problems 45.2% 28 Describe any other problems you encountered and the location of problems. 22.6% 14 answered question 62 skipped question 0 1 of 14

34 3. Did you encounter any problems in crossing streets or roads? Response Percent Response Count Road was too wide 3.2% 2 Needed a traffic signal 3.2% 2 Needed crosswalks and pedestrian signs to alert drivers 12.9% 8 Parked cars blocked view of traffic 1.6% 1 Trees or other objects blocked view of traffic 3.2% 2 Cars moving too fast 14.5% 9 Needed curb ramps or ramps needed repair 4.8% 3 Other (please describe below) 6.5% 4 No difficulty crossing streets/roads 66.1% 41 Describe other problems encountered with crossing streets/roads. Also describe the location of problems. 14.5% 9 answered question 62 skipped question 0 2 of 14

35 4. Did you encounter any problems with drivers? Response Percent Response Count Backed out of driveways without looking 3.2% 2 Did not yield to pedestrians 3.2% 2 Drove too fast 22.6% 14 Ran stop signs 8.1% 5 Other 1.6% 1 Did not encounter any problems with drivers 71.0% 44 Describe other problems you encountered with drivers 6.5% 4 answered question 62 skipped question 0 5. Other observations you would like to report from your walk. Response Count 62 answered question 62 skipped question 0 3 of 14

36 6. Please enter the address you use to log into the Community Challenge at Walking Works. Response Percent Response Count Name: 100.0% 62 City/Town: 100.0% 62 Address: 100.0% 62 answered question 62 skipped question 0 1. Describe the location of your walk (such as street names, neighborhoods or Response Text 1 Tannery Road to US-2 to Boardwalk May 7, :06 PM 2 Island Lake Rd May 7, :12 PM 3 Stanley Rd to Chvala Rd to M-149 to the cemetary and back home May 7, :38 PM 4 Door County Half-Marathon, WI Soleburner 5K in Appleton, WI Various routes through Schoolcraft County, in and out of the city limits of Manistique May 7, :00 PM 5 Riverview Drive at night; Lakeside area during lunch May 7, :23 PM 6 Boardwalk from Oak Street May 7, :41 PM 7 In my local neighborhood on Oak Street in Manistique May 7, :49 PM 8 West Elk, Fifth Street, Deer Street, Mackinaw Avenue, Deer Street May 8, :36 AM 9 From Cattaragus to Oak to Steuben. Up Steuben to Main and loop around back to Steuben via Gero. Back to Main from Steuben and down to Cedar. Cedar to Walnut, up Walnut to Range, Range to Cherry. Cherry to Steuben and back to Oak. Oak to Cattaragus and I am home again! May 8, :09 PM 10 County Road 441, Indian Lake May 9, :36 PM 11 Manistique Ave to Boardwalk, along boardwalk May 10, :28 AM 12 Boardwalk and vaious roads in town. May 10, :05 PM 13 Neighborhoods I walk down our street out on M 94 sometimes Sometimes I walk around our lake very pretty May 14, :32 PM 14 Boardwalk May 17, :05 PM 15 Across thye street from my house, in the woods. May 18, :38 PM 16 I walk on the main road called M-183, GArden Peninsula. May 18, :50 PM 4 of 14

37 1. Describe the location of your walk (such as street names, neighborhoods or Response Text 17 I usually walk the board walk in Manistique, I walk from my house on Garden Ave, through the Lakeview cemetary and to the Dairy Kream, than back home. My other loop, is from my house on Garden Ave, across the bridge on US-2, down Chippewa St, through town and back home. During those walks, if I have my kids, we stop at play grounds along the way. May 18, :01 PM 18 Along County Road 441 May 18, :14 PM 19 Manistique Ave. to Garden Ave. in Manistique May 18, :36 PM 20 Evergreen Rd, work May 18, :44 PM 21 To and from Oak and Range to Manistique high school. From Oak and Range to Pamida, down the boardwalk to Jack's old store and back to Oak and Range. 22 my neighborhood and these are the streets with no sidewalks or shoulder to walk on. My house no 15 th st Gladstone and I cross highway 35 and on 15th no again no sidewalks also 14th,16th,and 17 th st or the ave on the corners no sidewalks. May 18, :55 PM May 18, :07 PM 23 Lakeside Area of Manistique May 18, :19 PM 24 New Delta out to Intake Park road across highway to State Road and back May 18, :57 PM 25 Beckman Road to luduc Road and back on Becman Road May 18, :34 PM 26 Start at East end of boardwalk to home on Riverdale walking thru town, over bridge, down North Houghton, Bear Street, Alger Avenue to Riverdale 27 I walk down Oak Street to Cedar Street. I then go out to US 2 and continue to Chippewa and then back to Cedar Street and back up Oak. 28 I walk on a back trail along fields and woods and hope not to see a bear or wolf. which they are in the area May 19, :38 AM May 19, :48 AM May 19, :16 AM 29 Walked 1/2 block to Range St.,then the 7 block length of Range Street south, crossed US2 to the boardwalk. Walked east on the boardwalk to the end, crossed US2 again, and walked the length of Manistique Ave. to Range St, then turned north and walked back up Range to Walnut and the 1/2 to home. May 19, :45 AM 30 Manistique Board Walk, Manistique downtown area, Lakeside area, May 19, :35 AM 31 Townline road to corner, then back past my house to three houses down. May 19, :36 PM 32 golf course, new delta ave to cedar st. May 20, :48 AM 33 elm street then south on cedar to marina then the boardwalk on lake michigan. Or east on elm to lakeside road, go south on lakeside road to oak street to cedar st then go north back to elm street. May 20, :48 AM 34 Lake Michigan Boardwalk in Manistique May 22, :00 PM 35 Wawaushnosh DR Rural Indian Lake Manistiuqe 36 We live on 29 acres and my husband made a 1/2 mile loop around our back field. We try to walk it 3-4 times a day:) May 22, :28 PM May 22, :43 PM 37 counyt road 432 to Gulliver Lake and around the loop. May 24, :27 PM 38 Park to Range to Walnut to Lake to Main to Steuben to Oak to Cattaragus to Park to Range to Boardwalk. 39 Park to Cattaragus to Lakeside to New Elm to Elm to Maple to Oak to Range to Park 40 In the country, there are no sidewalks, we walk on the road because there is little traffic. May 27, :32 AM May 27, :42 AM May 27, :46 PM 41 Park Street to Emerald Elementary School and back again. May 27, :24 PM 5 of 14

38 1. Describe the location of your walk (such as street names, neighborhoods or Response Text 42 Down Reid road, on to Quarry Road and back around by the lake back to Reid Road May 28, :08 AM 43 Boardwalk May 28, :41 AM 44 City of Manistique, downtown area, main, maple, oak, cattaragus, park, cedar, river, deer, and local parks May 28, :35 PM 45 paved walkig path by lake May 28, :31 PM 46 Maple Street, Cedar Street, Alger Ave. May 28, :55 PM 47 Glenwood Dr, May 29, :58 AM 48 Boardwalk along Lake Michigan and walk on breakwall to lighthouse and back May 30, :59 AM 49 I walk before work north of my home, M94 past gun club to Hiawatha Station Rd, weather permitting. If raining/snowing or too dark, I walk on my treadmill in the basement. I have had close encounters with bears walking in the early morning outside, but love the day waking up. Jun 3, :26 AM 50 Regular weekly walk, aprox 2 hours Jun 17, :52 PM 51 walk down side streets, through town, then past hospital and through lakeside cemetary then back through town to home. 52 Manistique Ave to Cattargus to Michigan to Stuben to Arbutus across US 2 to boardwalk full length back to Manistique Jun 22, :24 PM Jun 22, :56 PM 53 Bear street to 5th street to deer street to N. Houghton and then back to bear street Jun 22, :57 PM 54 Oak St to Cattarugus to Michigan Ave to Stueben to Manistique Ave thence to City Hall and Back 55 HALF MY WALK IS DOWN A BACKROAD IN A RURAL NEIGHBORHOOD AND THE OTHER HALF IS ALONG THE SHOULDER OF A HIGHWAY. 56 County Road 441, N. to CCR 440 to LeDuc Road, W. to Golf course and retrace steps around Indian Lake. 57 Rivers Bend Drive to Cope Bridge or Rivers Bend Drive down Intake Park Road. All in Manistique Jun 22, :31 PM Jun 22, :03 PM Jun 23, :23 AM Jun 26, :34 PM 58 Manistique boardwalk Jun 29, :58 AM 59 Local street near my home Jun 30, :58 PM 60 country Jul 1, :09 AM 61 Started on Michigan Ave. Went down Oak St. around by the Court house (whatever st. that is) down through town to Mitchy Movies back through town up the hospital hill and back to Michigan Ave. Jul 1, :15 AM 62 Manistique Marina to the Quarry, Main St. Jul 3, :38 AM 2. Did you encounter any problems on your walk? Describe any other problems you encountered and the location of problems. 1 Boardwalk starting to get in rougher shape--nails sticking out all over. Bikes and dogs on path and most people but them considerate of runners. Bugs this time of year...but welcome to the UP! The pathway under the bridge is a great addition! May 7, :06 PM Cars could go slower on Tannery road because even though shoulder is wide, is is not packed down dirt and hard to get on and off of. 2 always an enjoyable walk down our country road, not only do we have our exercise but we catch up on neighborhood doings May 7, :12 PM 6 of 14

39 2. Did you encounter any problems on your walk? Describe any other problems you encountered and the location of problems. 3 The roads are also in very bad condition. May 18, :36 PM 4 I walk in my neighborhood and the only sidewalks are if I go into town to walk. To get to town I have to walk m35 and part of that doesn't have a sidewalk and in the winter no place to walk and I mean the sidewalks have snow so we can't walk then. May 18, :07 PM 5 Too hard to push a stroller on the sidewalks, so we need to walk on the road. May 18, :19 PM 6 I just walk on a parcial gravel trail May 19, :16 AM 7 mediocre golf score, back 9 of golf course! May 20, :48 AM 8 Lack of road signs. May 27, :32 AM 9 Bears, Mosquitoes and Black Flies...I live 8 miles N of Manistique on M94--no way to avoid the threat of nature, but that is the beauty of it. There are no street lights, so I only walk near my home during light hours. I have 2 treadmills, just in case one breaks down. Jun 3, :26 AM 10 Nothing that prevents walking in a particular area. Jun 17, :52 PM 11 USUALLY WALK ON ROAD BECAUSE SIDEWALKS ARE UNEVEN, CRACKED AND BROKEN 12 No cross walks anywhere including around school. Half a mile (about) to City Hall with nowhere to walk except in busy road. Jun 22, :24 PM Jun 22, :31 PM 13 USUALLY NO PROBLEMS Jun 22, :03 PM 14 Side walks in this town are horrible, streets are almost worse. Jul 1, :15 AM 3. Did you encounter any problems in crossing streets or roads? Describe other problems encountered with crossing streets/roads. Also describe the location of problems. 1 no difficulties May 7, :12 PM 2 Not applicable to the Boardwalk May 17, :05 PM 3 The roads are full of pot holes and loose gravel. Crossing the roads with strollers, wheelchairs, people with disabilities, and with small children (walking or with wagons, bikes, etc.) can be slow and cumbersome. Trying to hurry everyone across when there is traffic can be difficult. It is easy for someone to trip or loose footing on the roads. A 3-year old will often think nothing of stopping in the middle of the road to get loose gravel out of her shoe! I also worry about people on bikes and roller blades listening to music, diverting off of bad side walks and not seeing vehicles. There is potential for problems here. May 18, :36 PM 4 In front of Pamida they will need stoplights. May 18, :55 PM 5 The drivers don't enough courtesy to the pedestrians crossing the highbay. May 18, :07 PM 6 by sav-a-lot grocery store, deer st./new delta May 20, :48 AM 7 At times US 2 can be pretty busy and may be difficult to cross with the fast moving cars. 8 the crosswalk to get across us 2 for arbutus is down in front of the state police post and crosses to Hardees where there is no sidewalk so everyone just crosses at the roadway out of crosswalk at the Manistique end of the board walk there isn't any crosswalk and no sidewalk on Manistique for at least 2 blocks you have to walk in street May 28, :31 PM Jun 22, :56 PM 7 of 14

40 3. Did you encounter any problems in crossing streets or roads? Describe other problems encountered with crossing streets/roads. Also describe the location of problems. 9 Walked in an industrial area that would not be expected to have sidewalks necessarily, but our students walk to an elementary school on this route. Jun 22, :31 PM 4. Did you encounter any problems with drivers? Describe other problems you encountered with drivers 1 most everyone drives slowly May 7, :12 PM 2 Not applicable to the Boardwalk May 17, :05 PM 3 When I cross us 2 and 41 from us 35 eigther from the east or west of 2 and 41 the drivers that are turning from 35 don't give the walker the right away crossing the highway. 4 I walk on a fairly flat stretch, and find that some jerks will pass another car right where I am walking, instead of giving the walker the right of way and use caution to wait another 20 yards and then pass. There is very little traffic, so holding off to pass wouldn't be a problem. Sometimes cars will also cross the center line to get a better look at me from behind--not a problem, just reminds me there are a lot of idiots out there. May 18, :07 PM Jun 3, :26 AM 5. Other observations you would like to report from your walk. Response Text 1 For the most part, Manistique has some of the best running locations with the boardward, riverview drive and Indian Lake. Drivers are aware and curteous of runners. It is really tough to find locations to run outside all winter. 8 of 14 May 7, :06 PM 2 enjoying the various spring flowers May 7, :12 PM 3 N/A May 7, :38 PM 4 There are many beautiful, scenic areas to walk in Schoolcraft County and the city of Manistique! May 7, :00 PM 5 n/a May 7, :23 PM 6 beautiful view May 7, :41 PM 7 the sidewalks are heaved and exceptionally uneven. We tried to push a stroller and it was impossible with the broken and uneven sidewalks. May 7, :49 PM 8 n/a May 8, :36 AM 9 n/a May 8, :09 PM 10 n/a May 9, :36 PM 11 The boardwalk is starting to show signs of age. It could use some sprucing up. May 10, :28 AM 12 The scenery is gorgeous, especially along Lake Michigan. May 10, :05 PM 13 Beautiful country we live in very enjoyable May 14, :32 PM 14 Sand obcuring approach to Boardwalk from parking lot difficult to walk through. May 17, :05 PM 15 Saw 3 deer, 2 sandhill cranes, and the dogs tred a porcupine. May 18, :38 PM 16 the apple and other flowering trees are in full bloom, beautiful! May 18, :50 PM 17 In a few places there were loose dogs, none that approached us thank goodness! May 18, :01 PM

41 5. Other observations you would like to report from your walk. Response Text 18 Since it is a rural location I don't expect there to be sidewalks or traffic signals. It is a very peaceful and enjoyable walk. 19 Our sidewalks should be used more than they are. People that walk in the winter months walk on the road because the sidewalks are covered with snow. Kids walk those roads to school in the dark of winter mornings. Thanks for wanting to make a difference! Repairing our community can make lasting changes! 9 of 14 May 18, :14 PM May 18, :36 PM 20 none May 18, :44 PM 21 n/a May 18, :55 PM 22 n/a May 18, :07 PM 23 n/a May 18, :19 PM 24 Other than a few cars going fast, most were kind and courteous. Great run area. May 18, :57 PM 25 n/a May 18, :34 PM 26 Sidewalks on Bear Street are horrid. Otherwise this is my most frequent and a very enjoyable walk. May 19, :38 AM 27 I observe other people walking and riding their bikes. May 19, :48 AM 28 I stopped once in awhile to pick morels (mushrooms). May 19, :16 AM 29 It takes alot longer, walking with a curious dog. May 19, :45 AM 30 Lots of friendly people out walking in this beautiful weather! May 19, :35 AM 31 Good place for a walk, quiet road, with a few neighbors our walking too May 19, :36 PM 32 n/a May 20, :48 AM 33 too many people throw their trash on the roadways May 20, :48 AM 34 This is a great walking path. We always enjoy taking our visitors there as well! May 22, :00 PM 35 We have a stop sign outside of our home and many drivers do not observe it. This could be dangerous to walkers or other drivers. But otherwise there are many people who walk down our rural road. It is very pretty as the road runs along indian lake. 36 We love walking on our property! We do walk on the road sometimes but with traffic it is hard. 37 Beautiful afternoon no bugs. Hot for May! May 22, :28 PM May 22, :43 PM May 24, :27 PM 38 Too many people smoking on the sidewalks, boardwalk and around playgrounds. May 27, :32 AM 39 Maple is difficult because one lane is so narrow and cars get too close. May 27, :42 AM 40 Walking in the country is very peaceful, and you get to enjoy wildlife May 27, :46 PM 41 n/a May 27, :24 PM 42 Just a nice place to walk and enjoy the weather May 28, :08 AM 43 Just a beautiful day, and view of the lake May 28, :41 AM 44 missing wayfinding points; need appealing are to encourage walking May 28, :35 PM 45 n/a May 28, :31 PM 46 none May 28, :55 PM 47 Pleasant walk on quiet street May 29, :58 AM 48 Nails popping out on boards on boardwalk and loose boards May 30, :59 AM 49 There are few things better than walking as the sun is rising. Walk facing traffic, and make yourself as visible as possible. I oftenclean the road as I go. I am warmer all day (in the winter) when I get my blood going. Jun 3, :26 AM 50 No problems with walking in the city of Manistique Jun 17, :52 PM 51 no Jun 22, :24 PM

42 5. Other observations you would like to report from your walk. Response Text 52 n/a Jun 22, :56 PM 53 N/A Jun 22, :57 PM 54 It is unusual to a block with more than 50 percent intact sidewalks Jun 22, :31 PM 55 NICE WALK Jun 22, :03 PM 56 I walk with my dogs and there is a spring along the way where they always want to take a good drink. They get their water, too. 57 Since this is out of town slightly, I know we are walking on the shoulder of the road. It would be great to someday have another area to walk/ride bikes such as by the marina/lakeshore. Jun 23, :23 AM Jun 26, :34 PM 58 Great place to walk. Sometimes can be busy with people Jun 29, :58 AM 59 NA Jun 30, :58 PM 60 good walking Jul 1, :09 AM 61 Alot of streets need repairs, it is hard to push a stroller on any of the streets in the lakeside area. Jul 1, :15 AM 62 People need to trim their bushes and trees that hang over on the sidewalks Jul 3, :38 AM 6. Please enter the address you use to log into the Community Challenge Name: 1 Nancy Krusic May 7, :06 PM 2 Doris Norman May 7, :12 PM 3 Janet Peterson May 7, :38 PM 4 Linda levin May 7, :00 PM 5 Mary Ann Pawley May 7, :23 PM 6 Rick Pawley May 7, :41 PM 7 Cynthia Pawley May 7, :49 PM 8 Mary Messenger May 8, :36 AM 9 Joan Ecclesine May 8, :09 PM 10 Karrie Abbitt May 9, :36 PM 11 Kent LaCroix May 10, :28 AM 12 Jackie Burns May 10, :05 PM 13 Julie Richey May 14, :32 PM 14 Diana Nelson May 17, :05 PM 15 Robert K. Schwart May 18, :38 PM 16 jeani dalgord May 18, :50 PM 17 Jana May 18, :01 PM 18 Lauris Barr May 18, :14 PM 19 Val Mackie May 18, :36 PM 20 Jill Richey May 18, :44 PM 21 Laurie Lindstrom May 18, :55 PM 22 Betty Majestic May 18, :07 PM 23 Kristin Petrelius May 18, :19 PM 10 of 14

43 6. Please enter the address you use to log into the Community Challenge Name: 24 Donna Winkel May 18, :57 PM 25 Christine Carlson May 18, :34 PM 26 Pat Mickelson May 19, :38 AM 27 Kathy Dale May 19, :48 AM 28 Lyndell Farley May 19, :16 AM 29 Mindy Asp May 19, :45 AM 30 Colleen Hoholik May 19, :35 AM 31 Marjorie (Midge) Harlow May 19, :36 PM 32 polly bedwell May 20, :48 AM 33 cindy hyland May 20, :48 AM 34 Cathy Harris May 22, :00 PM 35 Bonnie Groh May 22, :28 PM 36 Beth Hopp May 22, :43 PM 37 Wanda McKenzie May 24, :27 PM 38 Kerry Ott May 27, :32 AM 39 Allan Ott May 27, :42 AM 40 Rebekah Weber May 27, :46 PM 41 Hannah Ott May 27, :24 PM 42 Donna Hansen May 28, :08 AM 43 Carolyn Blowers May 28, :41 AM 44 Doug May 28, :35 PM 45 David Partyka May 28, :31 PM 46 Christi Ryan May 28, :55 PM 47 Ron Annelin May 29, :58 AM 48 Sherry May 30, :59 AM 49 Shirley M Young Jun 3, :26 AM 50 Pam Forhart Jun 17, :52 PM 51 yvonne gould Jun 22, :24 PM 52 Gail Bremer Jun 22, :56 PM 53 Debra Tiglas Jun 22, :57 PM 54 jan jeffcott Jun 22, :31 PM 55 JANI GOULD Jun 22, :03 PM 56 Greer Fish Jun 23, :23 AM 57 Kathleen Schuetter Jun 26, :34 PM 58 Alicen Phillips Jun 29, :58 AM 59 Catherine Flores Jun 30, :58 PM 60 Bob Weber Jul 1, :09 AM 61 Lucy Graphos Jul 1, :15 AM 62 Shirley Reno Jul 3, :38 AM 11 of 14

44 6. Please enter the address you use to log into the Community Challenge City/Town: 1 Manistique May 7, :06 PM 2 Manistique May 7, :12 PM 3 Manistique May 7, :38 PM 4 Manistique May 7, :00 PM 5 Manistique May 7, :23 PM 6 Manistique May 7, :41 PM 7 Manistique May 7, :49 PM 8 Manistique May 8, :36 AM 9 Manistique, MI May 8, :09 PM 10 Manistique May 9, :36 PM 11 Manistique May 10, :28 AM 12 Manistique May 10, :05 PM 13 Manistique May 14, :32 PM 14 Manistique May 17, :05 PM 15 Manistique May 18, :38 PM 16 garden May 18, :50 PM 17 Manistique May 18, :01 PM 18 Manistique May 18, :14 PM 19 Manistique, MI May 18, :36 PM 20 Manistique May 18, :44 PM 21 Manistique May 18, :55 PM 22 Gladstone May 18, :07 PM 23 Manistique May 18, :19 PM 24 Manisitique May 18, :57 PM 25 Manistique May 18, :34 PM 26 Manistique May 19, :38 AM 27 Manistique May 19, :48 AM 28 Garden May 19, :16 AM 29 Manistique May 19, :45 AM 30 Manistique May 19, :35 AM 31 Manistique May 19, :36 PM 32 manistique May 20, :48 AM 33 manistique May 20, :48 AM 34 Manistique May 22, :00 PM 35 Manistique May 22, :28 PM 36 Manistique May 22, :43 PM 37 Manistique May 24, :27 PM 38 Manistique May 27, :32 AM 39 Manistique May 27, :42 AM 40 Manistique May 27, :46 PM 41 Manistique May 27, :24 PM 42 Gulliver, MI May 28, :08 AM 43 Manistique May 28, :41 AM 12 of 14

45 6. Please enter the address you use to log into the Community Challenge City/Town: 44 Manistique May 28, :35 PM 45 Manistique MI May 28, :31 PM 46 Manistique May 28, :55 PM 47 Manistique, Mi May 29, :58 AM 48 Manistique May 30, :59 AM 49 Manistique, MI Jun 3, :26 AM 50 Manistique Jun 17, :52 PM 51 manistique Jun 22, :24 PM 52 Manistique Jun 22, :56 PM 53 Manistique Jun 22, :57 PM 54 Manistique Jun 22, :31 PM 55 MANISTIQUE Jun 22, :03 PM 56 Manistique Jun 23, :23 AM 57 Manistique Jun 26, :34 PM 58 Manistique Jun 29, :58 AM 59 Manistique Jun 30, :58 PM 60 Manistique Jul 1, :09 AM 61 Manistique Jul 1, :15 AM 62 Manistique Jul 3, :38 AM 6. Please enter the address you use to log into the Community Challenge Address: 1 nkrusic@manistiquepapers.com May 7, :06 PM 2 bnorman_islake@juno.com May 7, :12 PM 3 jpeterson@manistique.k12.mi.us May 7, :38 PM 4 llevin@manistique.k12.mi.us May 7, :00 PM 5 mapawley@yahoo.com May 7, :23 PM spahr@gmail.com May 7, :41 PM 7 cfpawley@gmail.com May 7, :49 PM 8 mmess@centurytel.net May 8, :36 AM 9 jecclesine@mdsecp.com May 8, :09 PM 10 karrie_schem@hotmail.com May 9, :36 PM 11 lacroix@gmail.com May 10, :28 AM 12 jburns@manistique.k12.mi.us May 10, :05 PM 13 Jrichey@scmh.org May 14, :32 PM 14 nelsond10@michigan.gov May 17, :05 PM 15 rschwartz@manistique.k12.mi.us May 18, :38 PM 16 jeanidalgord@hotmail.com May 18, :50 PM 17 jswanson@scmh.org May 18, :01 PM 18 happyscrapper2@gmail.com May 18, :14 PM 19 jonnval00@yahoo.com May 18, :36 PM 13 of 14

46 6. Please enter the address you use to log into the Community Challenge Address: 20 May 18, :44 PM 21 May 18, :55 PM 22 May 18, :07 PM 23 May 18, :19 PM 24 May 18, :57 PM 25 May 18, :34 PM 26 May 19, :38 AM 27 May 19, :48 AM 28 May 19, :16 AM 29 May 19, :45 AM 30 May 19, :35 AM 31 May 19, :36 PM 32 May 20, :48 AM 33 May 20, :48 AM 34 May 22, :00 PM 35 May 22, :28 PM 36 May 22, :43 PM 37 May 24, :27 PM 38 May 27, :32 AM 39 May 27, :42 AM 40 May 27, :46 PM 41 May 27, :24 PM 42 May 28, :08 AM 43 May 28, :41 AM 44 May 28, :35 PM 45 May 28, :31 PM 46 May 28, :55 PM 47 May 29, :58 AM 48 May 30, :59 AM 49 Jun 3, :26 AM 50 Jun 17, :52 PM 51 Jun 22, :24 PM 52 Jun 22, :56 PM 53 Jun 22, :57 PM 54 Jun 22, :31 PM 55 Jun 22, :03 PM 56 Jun 23, :23 AM 57 Jun 26, :34 PM 58 Jun 29, :58 AM 59 Jun 30, :58 PM 60 Jul 1, :09 AM 61 Jul 1, :15 AM 62 Jul 3, :38 AM 14 of 14

47 Manistique - Biking Audit 1. Describe the location of your bike ride (such as street names, neighborhoods or other describing information). Response Count 24 answered question 24 skipped question 0 2. Did you encounter any problems on your bike ride when you were on streets/roads shared by other vehicles? Response Percent Response Count No space for bicyclists to ride 45.8% 11 Bicycle lane or paved shoulder stopped and started 12.5% 3 Heavy and/or fast moving traffic 29.2% 7 Too many trucks or buses 0.0% 0 No space for bicyclists to safely cross bridges/overpasses 16.7% 4 Poor lighting 4.2% 1 Other (describe in comment box below) 4.2% 1 Did not encounter any problems 37.5% 9 Describe any other problems you encountered and the location of problems. 37.5% 9 answered question 24 skipped question 0 1 of 10

48 3. Did you encounter any problems on your bike ride when you were on an off-road path or trail, where motor vehicles were not allowed? Response Percent Response Count Path ended abruptly 0.0% 0 Path didn't go to where I wanted/needed to go 0.0% 0 Path intersected with roads that were difficult to cross 0.0% 0 Path was crowded 0.0% 0 Path was poorly maintained 0.0% 0 Path was poorly lighted 0.0% 0 No signage 0.0% 0 Other (please describe in the text box below) 8.3% 2 No problems encountered 75.0% 18 Describe other problems encountered and the location of problems 25.0% 6 answered question 24 skipped question 0 2 of 10

49 4. How was the surface that you rode on? Response Percent Response Count Potholes 33.3% 8 Cracked or broken pavement 50.0% 12 Debris (such as broken glass, sand, gravel) 37.5% 9 Dangerous drain grates, utility covers, or metal plates 8.3% 2 Uneven surface or gaps between surfaces 33.3% 8 Slippery surfaces when wet 0.0% 0 Bumpy or angled railroad tracks 20.8% 5 Other (please describe in the text box below) 4.2% 1 Did not encounter any problems with the surface I rode on 33.3% 8 Describe other problems encountered with surfaces you rode on. Also describe the location of problems. 0.0% 0 answered question 24 skipped question 0 3 of 10

50 5. How were the intersections you crossed through? Response Percent Response Count Had to wait too long to cross 12.5% 3 Couldn't see crossing traffic due to parked cars or other obstacles 8.3% 2 No traffic signal for busy intersections 8.3% 2 Unsure where or how to cross certain roads 4.2% 1 Other (please describe in the text box below) 0.0% 0 Did not encounter any problems crossing intersections 75.0% 18 Describe other problems you encountered crossing intersections (please describe locations). 0.0% 0 answered question 24 skipped question 0 4 of 10

51 6. Did you encounter any problems with drivers? Response Percent Response Count Drove too fast 33.3% 8 Passed me too close 29.2% 7 Did not signal 4.2% 1 Harassed me 0.0% 0 Cut me off 0.0% 0 Ran stop signs 8.3% 2 Other (please describe in text box below) 0.0% 0 Did not encounter any problems with drivers. 50.0% 12 Desribe other problems you encountered with drivers. 0 answered question 24 skipped question 0 5 of 10

52 7. Any other problems you encountered on your ride? Response Percent Response Count No maps, signage, or road markings to help me find my way 0.0% 0 No safe or secure place to leave my bike at my destination 12.5% 3 No way to take my bicycle on the bus 0.0% 0 Dogs not properly restrained 20.8% 5 Other (please describe in text box below) 0.0% 0 No other problems encountered 70.8% 17 Describe any other problems you encountered on your ride. 4.2% 1 answered question 24 skipped question 0 6 of 10

53 8. What did you do to make your ride safer? Response Percent Response Count Wore a bicycle helmet 33.3% 8 Obeyed traffic rules 79.2% 19 Rode in a straight line (did not weave) 70.8% 17 Signaled my turns 12.5% 3 Rode with (not against)traffic 70.8% 17 Used lights if riding at night 4.2% 1 Wore reflective clothing 20.8% 5 Was courteous to other travelers (motorists, skaters, pedetrians, etc) 70.8% 17 Any other comments you would like to tell us about your ride? 5 answered question 24 skipped question 0 9. Please enter the address you use to log into the Community Challenge at Walking Works. Response Percent Response Count Address: 100.0% 24 answered question 24 skipped question 0 1. Describe the location of your bike ride (such as street names, neighborhoods Response Text 1 Fayette state park May 8, :46 AM 7 of 10

54 1. Describe the location of your bike ride (such as street names, neighborhoods Response Text 2 S down M94, up State Road, left at the Y, right at next stop sign, over the Cope Bridge, around Bishop Baraga Shrine, up to M94 back S on M94 to home May 9, :39 AM 3 Out around Indian Lake May 11, :02 PM 4 Bike ride along our street Island Lake road May 14, :36 PM 5 Out Tannery Road to the Glenwood Subdivision. There is a cut across to the power line road that I haven't explored yet. May 18, :13 PM 6 From blinking light in Gulliver to the lighthouse and back (15 miles) May 18, :37 PM 7 Thompson, into Manistique, thru town, out to Indian Lake, back to Thompson. aprox 16 miles May 18, :48 PM 8 County Road 441, Indian Lake area May 19, :26 AM 9 I ride down Lakeside Road to the Tannery Road and then back through town. May 19, :53 AM 10 Wawaushnosh Drive May 19, :07 AM to 149 to Palms Book State Park May 22, :57 PM 12 Went down Oak St through downtown up North Houghton around by Lincoln School to Second St. back through town and back up Oak st. May 25, :36 AM 13 tannery road, maple street, river street, deer street, cedar street, us-2 May 28, :38 PM 14 Rural Road (Townline Road) May 30, :04 AM 15 tannery road, glenwood drive, us2 Jun 1, :52 PM 16 M94, north of Manistique. I will leave my home, go north to turn on Dodge Lake Road, and take that road til it ends, return, then north again on 94 to Smith Lake Rd., turn and go to the private road around Smith Lake Rd (gravel), go around that. In May there is a stretch of lilacs on Smith Lake Rd that you can smell for a long ways. Jun 3, :35 AM 17 East side of Manistique. Neighborhoods. Jun 22, :09 PM 18 City of Manistique Jun 23, :48 AM 19 neighborhoods, out to cope bridge Jun 23, :47 PM 20 Woodland Drive through town to Cathlic Church by football field and out to Bowling Alley via Oak Street Jun 23, :21 PM 21 country Jun 25, :26 AM 22 Rivers Bend Drive to Cope Bridge and around Indian Lake area or from Rivers Bend Drive to Intake Park Road and Alger Avenue. Jun 26, :37 PM 23 Thompson, Michigan Jun 28, :23 PM 24 local neighborhood Jun 30, :03 PM 2. Did you encounter any problems on your bike ride when you were on Describe any other problems you encountered and the location of problems. 1 Do the walking trails on the bike while tourist season is low, bumpy, hard on the back. 2 Old U.S. 2 is very dangerous. No shoulder to ride on. Traffic is not cautious. Dangerous to go off into the gravel fast. May 8, :46 AM May 18, :48 PM 3 paved shoulder had tar and loose stone May 19, :26 AM 4 I expected to ride on the gravel shoulder and that is what is available. A paved bike lane would be great! May 22, :57 PM 8 of 10

55 2. Did you encounter any problems on your bike ride when you were on Describe any other problems you encountered and the location of problems. 5 The side walks are horrible to try to ride on. May 25, :36 AM 6 The shoulders are often too lose to ride a bike in, so you have to ride on the road itself, and traffic doesn't always give you room. It is scary. Jun 3, :35 AM 7 Lots of construction going on. Jun 22, :09 PM 8 Alot of potholes and drivers not real friendly Jun 23, :21 PM 9 dogs chasing the bike Jun 25, :26 AM 3. Did you encounter any problems on your bike ride when you were on an off- Describe other problems encountered and the location of problems 1 No paths in Schoolcraft County for bike riding. We must always ride the roads. May 11, :02 PM 2 No off-road trails in the area that I know of. The boardwalk indicates no bicycles. May 18, :48 PM 3 didn't go on a path. May 25, :36 AM 4 no paths to ride on Jun 1, :52 PM 5 we have no bike paths Jun 23, :47 PM 6 No bike path available Jun 30, :03 PM 7. Any other problems you encountered on your ride? Describe any other problems you encountered on your ride. 1 No bike path available; roads had no shoulders to safely ride along. Jun 30, :03 PM 8. What did you do to make your ride safer? Any other comments you would like to tell us about your ride? 1 My ride is on a very quiet road little traffic very enjoyable May 14, :36 PM 2 Our highways aren't bad when there is light traffice. Most of the summertime, roads are too busy and it doesn't feel safe enough. We need more bike trails. May 18, :48 PM 3 This is a one mile long dead end road. May 19, :07 AM 4 I enjoy going to the park about once a week on a day I don't run - the staff there are great! 5 Would like to see paved bike trails on state roads in Michigan...I think it would draw business, and provide safer riding for bicyclists. May 22, :57 PM Jun 3, :35 AM 9 of 10

56 9. Please enter the address you use to log into the Community Challenge Address: 1 lynnefurmanek@yahoo.com May 8, :46 AM 2 fjlamuth@chartermi.net May 9, :39 AM 3 mapawley@yahoo.com May 11, :02 PM 4 jrichey@scmh.org May 14, :36 PM 5 llindstrom@manistique.k12.mi.us May 18, :13 PM 6 rschwartz@manistique.k12.mi.us May 18, :37 PM 7 pam8438@yahoo.com May 18, :48 PM 8 karrie_schem@hotmail.com May 19, :26 AM 9 kdale@manistique.k12.mi.us May 19, :53 AM 10 ljemason@hotmail.com May 19, :07 AM 11 richcathy1@msn.com May 22, :57 PM 12 lucy_berry1@hotmail.com May 25, :36 AM 13 manistiquerecreation@live.com May 28, :38 PM 14 slhampton@centurytel.net May 30, :04 AM 15 cryan@manistique.k12.mi.us Jun 1, :52 PM 16 stalkerandwalker@hotmail.com Jun 3, :35 AM 17 jburns@manistique.k12.mi.us Jun 22, :09 PM 18 upreno@yahoo.com Jun 23, :48 AM 19 choholik@chartermi.net Jun 23, :47 PM 20 nkrusic@manistiquepapers.com Jun 23, :21 PM 21 jiaweber@yahoo.com Jun 25, :26 AM 22 kschuetter@charter.net Jun 26, :37 PM 23 hoholikl@cvm.msu.edu Jun 28, :23 PM 24 cflores@scmh.org Jun 30, :03 PM 10 of 10

57 Appendix E: Complete Streets Survey Results

58 Sault Ste Marie Tribe of Chippewa Indians Strategic Alliance for Health (SAH) Complete Streets Survey Results Manistique Baseline 2010 Introduction Between September and November 2010, the Sault Ste Marie Tribe of Chippewa Indians Strategic Alliance for Health project administered a survey to a random sample of residents in Manistique, Michigan. The purpose of the survey was to gather information about community members awareness and perceptions of the community as a place for walking and biking, as well as their habits related to physical activity, in order to promote project planning and evaluate long term outcomes of the SAH project. Methods Using address lists from the U.S. Postal Service, the Sault Tribe SAH project mailed a hard copy survey to a random sample of households in Manistique. The survey questionnaire had eight questions with forced choice answer options, and one open-ended opinion question to elicit respondent opinions about walking and biking in the community. A postage-paid envelope was provided for the return of the survey. The survey did not collect any personally identifying information and therefore, the survey was anonymous. Survey responses were entered into an electronic database for analysis. A total of 1,540 surveys were distributed to randomly selected households in Manistique. 183 completed surveys were returned, resulting in a 12% response rate. Results Awareness Results of the survey indicate that the majority of respondents from Manistique are unaware of the term or concept of Complete Streets. Around 20% (n=39) of respondents reported being aware of the concept of Complete Streets, while two-thirds (65.9%, n=118) said that they were not aware of it, and 12% (n=22) were unsure (Figure 1). Figure 1. Awareness of Complete Streets (N=179)

59 Physical Activity Community members surveyed were also asked about the amount of time they spent walking and biking outdoors during the past week. On average, respondents reported walking outdoors just over 2.5 total hours per week. Notably, approximately half (50.9%, n=86) of survey respondents reported having walked outside for up to two hours, and about one-fifth (19.5%, n=33) reported walking between 2 and 4 hours per week. Conversely, almost 10% (n=16) reported that they did not walk outdoors at all in the past week (reported zero total minutes of walking) (Figure 2). The most common reason for walking was for exercise, with 89.7% (n=136) reporting they do this at least some of the time (Figure 3a). Figure 2. Total Hours Spent Walking and Biking Outdoors Figure 3a. Amount of Time Spent Walking for Exercise (N=136)

60 Figure 3b. Amount of Time Spent Walking for Transportation (N=121) Figure 3c. Amount of Time Spent Walking for Fun or Socially (N=112) Figure 3d. Amount of Time Spent Walking for Another Reason (N=105) Biking was much less common than walking. The average time spent bicycling outdoors was just 30 minutes total per week. A little more than three-quarters (77.1%, n=135) of respondents reported having spent zero total minutes biking in the past week (Figure 2). Similar to reasons given for walking outdoors, 88.3% (n=30) of respondents who biked reported doing so for exercise, while 64.2% (n=18) did so for fun or social activities and nearly half (45.2%, n=14) said that they biked for transportation. However, it is important to note that due to the fact that so few respondents reported biking in the past week, only 19% (n=34) of all respondents from Manistique answered this question. Further breakdown of these responses can be found in Figures 4a-d below.

61 Figure 4a. Amount of Time Spent Biking for Exercise (N=34) Figure 4b. Amount of Time Spent Biking for Transportation (N=31) Figure 4c. Amount of Time Spent Biking for Fun or Socially (N=28) Perceptions of the Community and Safety The survey asked respondents to rate the community of Manistique as a place to walk and bike. The most common response for walking was somewhat pleasant, reported by approximately 48% (n=84), but very pleasant was nearly as common, with 43% (n=76) of responses. Responses were less favorable for rating the community as a place to bike. The largest percentage (38.4%, n=63)) rated the community as somewhat pleasant, while over one-third of respondents (36.6%, n=60) rated the community as not at all pleasant. A little over 12% (n=21) of respondents consider the community very pleasant for biking, and approximately the same amount answered this question as don t know or not applicable (12.2%, n=20). See Figure 5 for the full results to these questions.

62 Figure 5. Perceptions of the Community as a Place to Walk and Bike Respondents were asked about how many streets in the community are safe for bicyclists and walkers. Responses were somewhat mixed; approximately half (53.2%, n=93) of respondents reported that only some or none of the streets were safe for bicyclists and walkers, while the other half (46.8%, n=82) said that between half and all of the streets were safe. Only 2.3% (n=4) of respondents reported feeling that all of the streets in Manistique are safe for walkers and bicyclists (Figure 6). Figure 6. Amount of Streets Safe for Walkers and Bicyclists (N=175)

63 Community members were asked about their degree of satisfaction with sidewalks, bike lanes, and crosswalks, with regard to characteristics such as the number, location, condition, and connectedness of the infrastructure. Overall, feedback was relatively positive for crosswalks in Manistique with over half of respondents (54.2%, n=83) reporting satisfied or very satisfied (see Figures 7a-b). Figures 7a-b. Degree of Satisfaction with Crosswalks (N=165) However, with regard to sidewalks, the majority had negative feedback, with 77.8% (n=137) of respondents selecting unsatisfied or very unsatisfied (Figures 7c-d). In fact, almost one third of respondents were very satisfied with the sidewalks in Manistique. I am 70 years old. The sidewalks I walk on are the same ones my grandparents walked on. Tree roots have cracked and made them uneven. We need new ones. Figures 7c-d. Degree of Satisfaction with Sidewalks (N=176)

ACTIVE TRANSPORTATION/NONMOTORIZED TRANSPORTATION

ACTIVE TRANSPORTATION/NONMOTORIZED TRANSPORTATION ACTIVE TRANSPORTATION/NONMOTORIZED TRANSPORTATION BACKGROUND Active transportation, also known as nonmotorized transportation, is increasingly recognized as an important consideration when planning and

More information

NM-POLICY 1: Improve service levels, participation, and options for non-motorized transportation modes throughout the County.

NM-POLICY 1: Improve service levels, participation, and options for non-motorized transportation modes throughout the County. Transportation PRINCE WILLIAM COUNTY 2008 COMPREHENSIVE PLAN NON-MOTORIZED PLAN CONTENTS Goals, Policies, and Action Strategies Table 4 (Bike Facility Classifications and Descriptions) Table 5 (Bike Facility

More information

CITY OF BLOOMINGTON COMPLETE STREETS POLICY

CITY OF BLOOMINGTON COMPLETE STREETS POLICY CITY OF BLOOMINGTON COMPLETE STREETS POLICY POLICY OBJECTIVE: The City of Bloomington will enhance safety, mobility, accessibility and convenience for transportation network users of all ages and abilities,

More information

City of St. Ignace Non-Motorized Transportation Plan

City of St. Ignace Non-Motorized Transportation Plan City of St. Ignace Non-Motorized Transportation Plan S The purpose of the Non-Motorized Transportation Plan is to provide safe routes throughout the City of St. Ignace that encourage non-motorized transportation

More information

Perryville TOD and Greenway Plan

Perryville TOD and Greenway Plan Perryville TOD and Greenway Plan Greenway Glossary Pathway: A bicycle and pedestrian path separated from motorized vehicular traffic by an open space, barrier or curb. Multi-use paths may be within the

More information

Chapter 5. Complete Streets and Walkable Communities.

Chapter 5. Complete Streets and Walkable Communities. Chapter 5. Complete Streets and Walkable Communities. 5.1 Description of Complete Streets. Cities throughout the world, and specifically the United States, are coming to embrace a new transportation and

More information

Agenda. Overview PRINCE GEORGE S PLAZA METRO AREA PEDESTRIAN PLAN

Agenda. Overview PRINCE GEORGE S PLAZA METRO AREA PEDESTRIAN PLAN PRINCE GEORGE S PLAZA METRO AREA PEDESTRIAN PLAN May 28, 2008 Agenda Welcome and introductions Project overview and issue identification Planning context and strengths Design challenges and initial recommendations

More information

CONNECTING PEOPLE TO PLACES

CONNECTING PEOPLE TO PLACES CONNECTING PEOPLE TO PLACES 82 EAST BENCH MASTER PLAN 07 Introduction The East Bench transportation system is a collection of slow moving, treelined residential streets and major arteries that are the

More information

West Dimond Blvd Upgrade Jodhpur Street to Sand Lake Road

West Dimond Blvd Upgrade Jodhpur Street to Sand Lake Road West Dimond Blvd Jodhpur St to Sand Lake CSS Transportation Project Summary Municipality of Anchorage Project # 05 005 Project Manager: John Smith, P.E. (MOA PM&E) Project Administrator: Julie Makela,

More information

o n - m o t o r i z e d transportation is an overlooked element that can greatly enhance the overall quality of life for the community s residents.

o n - m o t o r i z e d transportation is an overlooked element that can greatly enhance the overall quality of life for the community s residents. N o n - m o t o r i z e d transportation is an overlooked element that can greatly enhance the overall quality of life for the community s residents. 84 Transportation CHAPTER 11 INTRODUCTION Transportation

More information

Land Use Bicycle Spaces Required Type Residential

Land Use Bicycle Spaces Required Type Residential SAMPLE ORDINANCES AND RESOLUTIONS APPENDIX B SAMPLE BICYCLE PARKING ORDINANCE Land Use Bicycle Spaces Required Type Residential Single Family/Two Family N/A N/A Apartment/Townhome 1 per unit plus 6 space

More information

ARLINGTON COUNTY, VIRGINIA

ARLINGTON COUNTY, VIRGINIA ARLINGTON COUNTY, VIRGINIA County Board Agenda Item Meeting of October 15, 2016 DATE: October 7, 2016 SUBJECT: Adoption of amendments to the Master Transportation Plan (MTP) to create a new Pedestrian

More information

CITY OF COCOA BEACH 2025 COMPREHENSIVE PLAN. Section VIII Mobility Element Goals, Objectives, and Policies

CITY OF COCOA BEACH 2025 COMPREHENSIVE PLAN. Section VIII Mobility Element Goals, Objectives, and Policies CITY OF COCOA BEACH 2025 COMPREHENSIVE PLAN Section VIII Mobility Element Goals, Objectives, and Policies Adopted August 6, 2015 by Ordinance No. 1591 VIII MOBILITY ELEMENT Table of Contents Page Number

More information

MPO Staff Report Technical Advisory Committee: September 13, 2017 MPO Executive Board: September 20, 2017

MPO Staff Report Technical Advisory Committee: September 13, 2017 MPO Executive Board: September 20, 2017 MPO Staff Report Technical Advisory Committee: September 13, 2017 MPO Executive Board: September 20, 2017 RECOMMENDED ACTION: Update on Near Southside Walkability Survey. Matter of the Near Southside Neighborhood

More information

ACTIVE TRANSPORTATION

ACTIVE TRANSPORTATION ACTIVE TRANSPORTATION Mobility 2040 Supported Goals Improve the availability of transportation options for people and goods. Support travel efficiency measures and system enhancements targeted at congestion

More information

Steps to Conducting a Complete Streets Assessment

Steps to Conducting a Complete Streets Assessment Steps to Conducting a Complete Streets Assessment Familiarize yourself with Complete Streets Read through the Complete Streets Assessment Guidelines. This will give you an idea of what Complete Streets

More information

Corpus Christi Metropolitan Transportation Plan Fiscal Year Introduction:

Corpus Christi Metropolitan Transportation Plan Fiscal Year Introduction: Introduction: The Safe, Accountable, Flexible, Efficient Transportation Equity Act: A Legacy for Users (SAFETEA-LU) has continued the efforts started through the Intermodal Surface Transportation Efficiency

More information

Chapter 3 DESIGN SPECIFICATIONS

Chapter 3 DESIGN SPECIFICATIONS Brampton PathWays Planning and Design Guidelines 27 Chapter 3 DESIGN SPECIFICATIONS 3.1 CLASS 1 MULTI-USE PATH Off-road multi-use trails are the backbone of the Brampton PathWays Network. They are typically

More information

Complete Streets. Designing Streets for Everyone. Sarnia

Complete Streets. Designing Streets for Everyone. Sarnia Complete Streets Designing Streets for Everyone Sarnia Complete Streets ~ Sarnia ~ 2018 Introduction Our City is made up of a network of streets that we use to go for a walk, cycle to work, drive to the

More information

Non-Motorized Transportation 7-1

Non-Motorized Transportation 7-1 Non-Motorized Transportation 7-1 Transportation facilities no longer mean just accommodating a vehicle powered by a combustion engine. Pedestrian and non-motorized facilities are important modes of travel

More information

1.0 EXECUTIVE SUMMARY

1.0 EXECUTIVE SUMMARY 1.0 EXECUTIVE SUMMARY The Active Transportation Plan is a guide to accomplish the Town s vision for developing a network of sidewalks, on-road bicycle facilities, and trails that allow for safe and convenient

More information

Living Streets Policy

Living Streets Policy Living Streets Policy Introduction Living streets balance the needs of motorists, bicyclists, pedestrians and transit riders in ways that promote safety and convenience, enhance community identity, create

More information

PRINCE GEORGE S PLAZA METRO AREA PEDESTRIAN PLAN

PRINCE GEORGE S PLAZA METRO AREA PEDESTRIAN PLAN PRINCE GEORGE S PLAZA METRO AREA PEDESTRIAN PLAN May 28, 2008 Agenda Welcome and introductions Project overview and issue identification Planning context and strengths Design challenges and initial recommendations

More information

INDOT Complete Streets Guideline & Policy

INDOT Complete Streets Guideline & Policy INDOT Complete Streets Guideline & Policy INTRODUCTION The Complete Streets guidelines build upon multiple efforts and promote a multimodal transportation system that is integrated and sustains land use

More information

Item No. 14 Town of Atherton

Item No. 14 Town of Atherton Item No. 14 Town of Atherton CITY COUNCIL STAFF REPORT CONSENT AGENDA TO: THROUGH: FROM: HONORABLE MAYOR AND CITY COUNCIL GEORGE RODERICKS, CITY MANAGER MICHAEL KASHIWAGI, COMMUNITY SERVICES DIRECTOR MARTY

More information

City of Davis East Covell Corridor Plan

City of Davis East Covell Corridor Plan Community Open House #2 January 22, 2014 6:00 8:00 p.m. Veterans Memorial Center, Club Room City of Davis Introduction The (ECCP) is a taking a comprehensive look at the existing transportation systems

More information

TABLE OF CONTENTS. Executive Summary

TABLE OF CONTENTS. Executive Summary Executive Summary Background... ES-1 Pedestrian Network... ES-2 Bikeway Network... ES-2 Collision History... ES-2 Public Input... ES-4 Conclusions and Recommendations... ES-4 1. Introduction and Setting

More information

Complete Streets Successes, Opportunities, and Challenges

Complete Streets Successes, Opportunities, and Challenges Complete Streets Successes, Opportunities, and Challenges Juliet Walker, Transportation Planner, City of Portsmouth Rob Houseman, Director of Planning and Development, Town of Wolfeboro Chris Parker, Director

More information

APPROVE A RESOLUTION ADOPTING A COMPLETE STREETS POLICY

APPROVE A RESOLUTION ADOPTING A COMPLETE STREETS POLICY STAFF REPORT MEETING DATE: September 13, 2016 TO: FROM: City Council Bob Brown, Community Development Director Russ Thompson, Public Works Director Patrick Filipelli, Management Analyst 922 Machin Avenue

More information

EXECUTIVE SUMMARY. Vision

EXECUTIVE SUMMARY. Vision Vision Walking and bicycling in Salt Lake City will be safe, convenient, comfortable, and viable transportation options that connect people to places, foster recreational and economic development opportunities,

More information

East Burke Transportation, Safety and Capacity Improvements

East Burke Transportation, Safety and Capacity Improvements East Burke Transportation, Safety and Capacity Improvements The purpose of this project is to increase mobility and improve safety for pedestrians, cyclists, and motor vehicles along VT Route 114 in the

More information

RESOLUTION NO A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF MENLO PARK ADOPTING A COMPLETE STREETS POLICY

RESOLUTION NO A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF MENLO PARK ADOPTING A COMPLETE STREETS POLICY RESOLUTION NO. 6123 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF MENLO PARK ADOPTING A COMPLETE STREETS POLICY WHEREAS, the term Complete Streets describes a comprehensive, integrated transportation

More information

DRAFT. Lecompton. Table of Contents. Background

DRAFT. Lecompton. Table of Contents. Background Lecompton Table of Contents Existing Infrastructure 98 Funding 100 Policy and Program Recommendations 102 Infrastructure Recommendations 104 Conclusion 109 Douglas County Lecompton Background Located at

More information

St. Francis Drive through the City of Santa Fe Corridor Study

St. Francis Drive through the City of Santa Fe Corridor Study VII. ENGINEERING AND ENVIRONMENTAL EVALUATION TRAIL CONNECTIVITY In the southern portion of the Corridor there is a lack of a sidewalk, trail or bicycle facility within the right-ofway. However, the City

More information

Table of Contents Introduction. 2 Purpose of the Plan...2 The Benefits of Walking and Bicycling...3 Vision and Goals of the Plan...

Table of Contents Introduction. 2 Purpose of the Plan...2 The Benefits of Walking and Bicycling...3 Vision and Goals of the Plan... BICYCLE AND This plan was created through a grant from the Healthy Communities Program with the cooperation of the City of Cynthiana, Cynthiana Main Street, Cynthiana-Harrison County-Berry Joint Planning

More information

Overview. Illinois Bike Summit IDOT Complete Streets Policy Presentation. What is a Complete Street? And why build them? And why build them?

Overview. Illinois Bike Summit IDOT Complete Streets Policy Presentation. What is a Complete Street? And why build them? And why build them? Overview Illinois Bike Summit IDOT Complete Streets Policy Presentation Aren Kriks, P.E. District One Bicycle Coordinator and Bureau of Programming Project Engineer History of Complete Streets IDOT Policy

More information

and older adults and people with disabilities still face barriers when using the pedestrian network and public transportation.

and older adults and people with disabilities still face barriers when using the pedestrian network and public transportation. Background Afterthe1980Olympics,theLakePlacid/NorthElbacommunityadoptedaneconomicstrategy ofdevelopingandmarketingeventstoincreaseareatourism.thisstrategyhasbeenvery successful.overrecentyearsthevolumeofvisitorshasincreased,andthelengthofthe

More information

General Design Factors

General Design Factors Chapter 3: 3-1.0 Introduction General Design Factors Mn/DOT s goals include encouraging and accommodating safe bicycling. From a design perspective, these goals are achieved by first having an understanding

More information

Draft. Lecompton. Table of Contents. Background

Draft. Lecompton. Table of Contents. Background Lecompton Table of Contents Existing Infrastructure 80 Funding 82 Policy and Program Recommendations 83 Infrastructure Implementation Scenarios 84 Conclusion 85 Douglas County Lecompton Background Located

More information

CITY OF KASSON TRANSPORTATION ALTERNATIVES KASSON SAFE ROUTES TO SCHOOL

CITY OF KASSON TRANSPORTATION ALTERNATIVES KASSON SAFE ROUTES TO SCHOOL ve ha 8t G B A Mantorville Ave N 240th Ave 16th St NE 11th Ave NE K-M HIGH SCHOOL SUNRISE TRAIL TO MANTORVILLE MNTH 57 SUNSET TRAIL TO MANTORVILLE NE PARK 16TH ST NE TRAIL K-M ELEMENTARY SCHOOL K-M MIDDLE

More information

Physical Implications of Complete Streets Policies

Physical Implications of Complete Streets Policies Presentation Overview Physical Implications of Complete Norm Cox, ASLA, LLA Landscape Architect Ann Arbor, Michigan, 10:45 to Noon What Are Complete Streets? What Matters to Bicyclists and Pedestrians

More information

REGIONAL BICYCLE AND PEDESTRIAN DESIGN GUIDELINES

REGIONAL BICYCLE AND PEDESTRIAN DESIGN GUIDELINES REGIONAL BICYCLE AND PEDESTRIAN DESIGN GUIDELINES November 16, 2011 Deb Humphreys North Central Texas Council of Governments Bicycle and Pedestrian Advisory Committee Snapshot of the Guide 1. Introduction

More information

APPENDIX A: Complete Streets Checklist DRAFT NOVEMBER 2016

APPENDIX A: Complete Streets Checklist DRAFT NOVEMBER 2016 APPENDIX A: Complete Streets Checklist DRAFT NOVEMBER 2016 Complete Streets Checklist MetroPlan Orlando s Complete Streets Checklist is an internal planning tool for staff to further implementation of

More information

MASTER BICYCLE AND PEDESTRIAN PLAN

MASTER BICYCLE AND PEDESTRIAN PLAN VILLAGE OF NORTHBROOK MASTER BICYCLE AND PEDESTRIAN PLAN DRAFT PLAN OPEN HOUSE May 2, 2018 AGENDA 1. Community Engagement 2. Vision and Goals 3. General Structure of Plan 4. Recommendations Overview 5.

More information

Goal 3: Foster an environment of partnerships and collaboration to connect our communities and regions to one another.

Goal 3: Foster an environment of partnerships and collaboration to connect our communities and regions to one another. Non-Motorized Transportation Plan (NMTP) Draft Vision, Goal and,, Tri-County Regional Planning Commission (TCRPC) Purpose The purpose of the Tri-County Regional Planning Commission (TCRPC) Non-Motorized

More information

TOWN OF PORTLAND, CONNECTICUT COMPLETE STREETS POLICY

TOWN OF PORTLAND, CONNECTICUT COMPLETE STREETS POLICY TOWN OF PORTLAND, CONNECTICUT COMPLETE STREETS POLICY I. VISION, GOALS & PRINCIPLES VISION To improve the streets of Portland making them safer and more accessible for all users including pedestrians,

More information

5 CIRCULATION AND STREET DESIGN

5 CIRCULATION AND STREET DESIGN 5 CIRCULATION AND STREET DESIGN This chapter describes circulation and streetscape improvements proposed for the Northwest Chico Specific Plan Area. It includes detailed design specifications for existing

More information

2014 Wisconsin Tribal Transportation Conference. Matt Halada Transportation Planner NE Region

2014 Wisconsin Tribal Transportation Conference. Matt Halada Transportation Planner NE Region 2014 Wisconsin Tribal Transportation Conference Matt Halada Transportation Planner NE Region Implementing Wisconsin s Pedestrian and Bicycle Accommodations Law (Complete Streets) Tools and methods for

More information

Chapter 5 Future Transportation

Chapter 5 Future Transportation Chapter 5 Future Transportation The Future Land Use Plan identifies the desired land use designations. The land uses desired for Crozet depend, in large part, on the success of the transportation system,

More information

ADA Transition Plan. City of Gainesville FY19-FY28. Date: November 5, Prepared by: City Of Gainesville Department of Mobility

ADA Transition Plan. City of Gainesville FY19-FY28. Date: November 5, Prepared by: City Of Gainesville Department of Mobility ADA Transition Plan FY19-FY28 Date: November 5, 2018 Prepared by: City Of Gainesville Department of Mobility 1.0 INTRODUCTION 1.1 BACKGROUND The federal statute known as the Americans with Disabilities

More information

Citywide Sidewalk and Crosswalk Programs

Citywide Sidewalk and Crosswalk Programs Citywide Sidewalk and Crosswalk Programs Council Meeting October 20, 2015 Presented by Rita Hu and Jamal Mahmoud Program Goals Implement the City s comprehensive plan. Provide pedestrian with safe walking

More information

Article 3.0 circulation plan

Article 3.0 circulation plan Article 3.0 circulation plan Article 3.0 describes the existing circulation in the vicinity of the Plan Area, and illustrates the configuration of the surrounding roadway network. The proposed access and

More information

Final Sidewalk Feasibility Study

Final Sidewalk Feasibility Study Garfield Drive From Anastasia Drive to Elizabeth Place City of South Daytona July 23, 2009 Final Sidewalk Feasibility Study Prepared for: Prepared by: Final Sidewalk Feasibility Study Garfield Drive 2

More information

/ ARLINGTON COUNTY, VIRGINIA

/ ARLINGTON COUNTY, VIRGINIA / ARLINGTON COUNTY, VIRGINIA County Board Agenda Item Meeting of September 24, 2016 DATE: August 11, 2016 SUBJECT: Amendment of the Master Transportation Plan (MTP) Streets Element to include new local

More information

Minor Amendments to the Street and Traffic By-law 2849 and Skateboards in Protected Bike Lanes

Minor Amendments to the Street and Traffic By-law 2849 and Skateboards in Protected Bike Lanes ADMINISTRATIVE REPORT Report Date: October 31, 2017 Contact: Lon LaClaire Contact No.: 604.873.7336 RTS No.: 12241 VanRIMS No.: 08-2000-20 Meeting Date: November 15, 2017 TO: FROM: SUBJECT: Standing Committee

More information

Active Transportation Facility Glossary

Active Transportation Facility Glossary Active Transportation Facility Glossary This document defines different active transportation facilities and suggests appropriate corridor types. Click on a facility type to jump to its definition. Bike

More information

CONNECTIVITY PLAN. Adopted December 5, 2017 City of Virginia Beach

CONNECTIVITY PLAN. Adopted December 5, 2017 City of Virginia Beach CONNECTIVITY PLAN Adopted December 5, 2017 City of Virginia Beach CONTENTS 1.0 Background & Purpose... 2 2.0 Existing Inventory & Analysis... 3 ViBe District Existing Walking Conditions... 4 3.0 ViBe District

More information

MAG Town of Cave Creek Bike Study Task 6 Executive Summary and Regional Significance Report

MAG Town of Cave Creek Bike Study Task 6 Executive Summary and Regional Significance Report Page 1 MAG Town of Cave Creek Bike Study Task 6 Executive Summary and Regional Significance Report August 1, 2012 MAG Project #481 Page 2 Task 6 Executive Summary and Regional Significance Report Introduction

More information

Bicycle and Pedestrian Connectivity Study. Old Colony Planning Council

Bicycle and Pedestrian Connectivity Study. Old Colony Planning Council Bicycle and Pedestrian Connectivity Study Old Colony Planning Council Outline Why consider bike/peds in road designs? Why are measures needed? Connecting Land Use with Transportation Evaluation Tools:

More information

DRAFT. Table of Contents. Background

DRAFT. Table of Contents. Background Douglas County Table of Contents Existing Infrastructure 86 Funding 89 Policy and Program Recommendations 90 Infrastructure Recommendations 92 Conclusion 95 Background Home to 4,500 residents and Baker

More information

G AT E WAY PLAN. Community BRIEFING KIT GATEWAY BIKE

G AT E WAY PLAN. Community BRIEFING KIT GATEWAY BIKE G AT E WAY PLAN GATEWAY BIKE Community BRIEFING KIT PLAN August 2016 TABLE OF CONTENTS INTRODUCTION... 1 THE BENEFITS OF A BIKEABLE COMMUNITY... 2 ECONOMY...2 SAFETY...3 HEALTH...3 HOUSEHOLD SPENDING...3

More information

Cycle Track Design Best Practices Cycle Track Sections

Cycle Track Design Best Practices Cycle Track Sections Design Best Practices Sections It is along street segments where the separation and protection methods of cycle tracks offer more comfort than conventional bicycle lanes, and are more attractive to a wide

More information

Exhibit 1 PLANNING COMMISSION AGENDA ITEM

Exhibit 1 PLANNING COMMISSION AGENDA ITEM Exhibit 1 PLANNING COMMISSION AGENDA ITEM Project Name: Grand Junction Circulation Plan Grand Junction Complete Streets Policy Applicant: City of Grand Junction Representative: David Thornton Address:

More information

Bikeway action plan. Bicycle Friendly Community Workshop March 5, 2007 Rochester, MN

Bikeway action plan. Bicycle Friendly Community Workshop March 5, 2007 Rochester, MN Bikeway action plan Summary The was held on March 5, 2007 at the Rochester Mayo Civic Center. The workshop was hosted by Rochester-Olmsted County Planning Department in collaboration with the League of

More information

This page intentionally left blank.

This page intentionally left blank. This page intentionally left blank. COMMUNITY Coweta Community Overview Coweta Coweta, a residential community located in Wagoner County, is a suburb of Tulsa situated southeast of the metropolitan area

More information

City of Saline. Complete Streets Ordinance

City of Saline. Complete Streets Ordinance City of Saline Complete Streets Ordinance September 13 and 20, 2010 CARLISLE/WORTMAN ASSOCIATES What Are Complete Streets? Complete streets are designed to serve everyonemotorists as well as pedestrians

More information

Active Transportation Infrastructure Investment A Business Case

Active Transportation Infrastructure Investment A Business Case Active Transportation Infrastructure Investment A Business Case In 2016, the Real Estate Foundation awarded the Capital Regional District a $50,000 grant for Shifting Gears: Land Use Change through Active

More information

GIS Based Non-Motorized Transportation Planning APA Ohio Statewide Planning Conference. GIS Assisted Non-Motorized Transportation Planning

GIS Based Non-Motorized Transportation Planning APA Ohio Statewide Planning Conference. GIS Assisted Non-Motorized Transportation Planning The Purpose of GIS Assisted Network GIS Assisted Non-Motorized Transportation 2011 APA Ohio Statewide Conference Friday, 10:45 AM to Noon Focus on near-term projects wwwgreenwaycollabcom The purpose of

More information

Proposed. City of Grand Junction Complete Streets Policy. Exhibit 10

Proposed. City of Grand Junction Complete Streets Policy. Exhibit 10 Proposed City of Grand Junction Complete Streets Policy Exhibit 10 1 City of Grand Junction Complete Streets Policy Vision: The Complete Streets Vision is to develop a safe, efficient, and reliable travel

More information

Ottawa Beach Road Study

Ottawa Beach Road Study Ottawa Beach Road Study Prepared For: Park Township September 30, 2014 Project No. G140303 OTTAWA BEACH ROAD STUDY PREPARED FOR: PARK TOWNSHIP SEPTEMBER 30, 2014 PROJECT NO. G140303 TABLE OF CONTENTS 1.0

More information

Commerce Street Complete Street Project from Good Latimer Expressway to Exposition Avenue

Commerce Street Complete Street Project from Good Latimer Expressway to Exposition Avenue Commerce Street Complete Street Project from Good Latimer Expressway to Exposition Avenue T A N Y A B R O O K S A S S I S T A N T D I R E C T O R M O B I L I T Y P L A N N I N G M O B I L I T Y A N D S

More information

Improvements Infrastructure Gap Assessment and Improvements Street Striping

Improvements Infrastructure Gap Assessment and Improvements Street Striping Infrastructure Project Proposal The federal-aid Safe Routes to School program funds infrastructure/engineering projects that fall into two categories: Design (available only to School Development Authority

More information

2.0 Existing Conditions

2.0 Existing Conditions 20 2.0 Existing Conditions 2.1 Land Use, Future Growth Patterns, Physical Barriers Geographic Overview Sutter County s land use pattern is characterized by extensive agricultural areas, significant natural

More information

PROPOSAL: Review of Alaska DOT&PF project 68471, Glacier Highway reconstruction and pedestrian improvements from

PROPOSAL: Review of Alaska DOT&PF project 68471, Glacier Highway reconstruction and pedestrian improvements from PROPOSAL: Review of Alaska DOT&PF project 68471, Glacier Highway reconstruction and pedestrian improvements from Fritz Cove Rd to Seaview Ave, for consistency with locally adopted plans and ordinances.

More information

RESOLUTION NO ?? A RESOLUTION OF THE CITY OF NEPTUNE BEACH ADOPTING A COMPLETE STREETS POLICY

RESOLUTION NO ?? A RESOLUTION OF THE CITY OF NEPTUNE BEACH ADOPTING A COMPLETE STREETS POLICY RESOLUTION NO. 2018-?? A RESOLUTION OF THE CITY OF NEPTUNE BEACH ADOPTING A COMPLETE STREETS POLICY WHEREAS, safe, convenient, and accessible transportation for all users is a priority of the City of Neptune

More information

Summary of School Observations and Education and Encouragement Initiatives

Summary of School Observations and Education and Encouragement Initiatives Rye Shared Committee Summary of School Observations and Education and Encouragement Initiatives Presented to the Rye City Council & The Rye City School District Board of Education April 9 th, 2011 1 Why

More information

July 5, Arthur R. Ware, Jr. Elementary School 2017 Safe Routes to School Walkabout Report

July 5, Arthur R. Ware, Jr. Elementary School 2017 Safe Routes to School Walkabout Report July 5, 2017 Arthur R. Ware, Jr. Elementary School 2017 Safe Routes to School Walkabout Report 1 Walkabout Report Introduction On April 28, 2017, City, School, and SAWMPO staff met to conduct a Safe Routes

More information

City of Birmingham Draft Multi-modal Transportation Plan

City of Birmingham Draft Multi-modal Transportation Plan City of Birmingham Draft Multi-modal Transportation Plan City Commission Public Hearing Monday, November 25, 2013 7:30 pm Norman Cox, PLA, ASLA The Greenway Collaborative, Inc. Ann Arbor, Michigan The

More information

WELCOME. Thank you for joining us at the Second Public Workshop for the Carlsbad Pedestrian Master Plan. We look forward to receiving your feedback.

WELCOME. Thank you for joining us at the Second Public Workshop for the Carlsbad Pedestrian Master Plan. We look forward to receiving your feedback. City of Carlsbad Pedestrian Master Plan: WELCOME WELCOME Please Sign In Provide Input at Flip Charts Review Boards Presentation of Draft Plan Thank you for joining us at the Second Public Workshop for

More information

Plant City Walk-Bike Plan

Plant City Walk-Bike Plan Plant City Walk-Bike Plan Plant City Commute Mode Share 2.2% 1.4% 2.9% Drove alone 10.2% Carpooled Public transportation (0.1%) Walked Used a Bike (0.4%) 82.9% Taxicab, motorcycle, or other means Worked

More information

City of Madison, East Johnson Street North Baldwin Street to First Street Local Street Dane County

City of Madison, East Johnson Street North Baldwin Street to First Street Local Street Dane County City of Madison, East Johnson Street North Baldwin Street to First Street Local Street Dane County Public Involvement Meeting Thursday, April 28, 2016 6 to 8 P.M. Lapham Elementary School 1045 E. Dayton

More information

Safe Streets. City of Lake Forest Park. March 21, 2017

Safe Streets. City of Lake Forest Park. March 21, 2017 Safe Streets City of Lake Forest Park March 21, 2017 1 01 WELCOME 2 Agenda WELCOME WHAT IS THIS PROJECT? CONTEXT DRAFT CITYWIDE PROJECTS EXERCISE INTRODUCTION 3 02 WHAT IS THIS PROJECT? 4 WHAT IS THIS

More information

CITY OF SIGNAL HILL Cherry Avenue Signal Hill, CA

CITY OF SIGNAL HILL Cherry Avenue Signal Hill, CA CITY OF SIGNAL HILL 2175 Cherry Avenue Signal Hill, CA 90755-3799 AGENDA ITEM TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL FROM: STEVE MYRTER, P. E. DIRECTOR OF PUBLIC WORKS SUBJECT: SPRING STREET

More information

FOCUS AREA 1 - Alberta Avenue Pocket Park 3 (121 Ave and 92 St)

FOCUS AREA 1 - Alberta Avenue Pocket Park 3 (121 Ave and 92 St) FOCUS AREA 1 - Alberta Avenue Pocket Park 3 (121 Ave and 92 St) New benches Plant evergreen trees Widen existing sidewalk from 1.5m to 1.8m Marked crosswalk 1.8m wide sidewalk Add pedestrian oriented lights

More information

Environment and Public Works Committee Presentation

Environment and Public Works Committee Presentation Mixed Use Centers Complete Streets Guidelines Project Environment and Public Works Committee Presentation December 10, 2008 Project Objectives: Conduct an inter-departmental and agency process to study

More information

CITY OF ELKO BICYCLE AND PATHWAY PLAN

CITY OF ELKO BICYCLE AND PATHWAY PLAN CITY OF ELKO BICYCLE AND PATHWAY PLAN INTRODUCTION: The City of Elko is intended to provide the basic framework for the development of a functional bicycle and pathway system for the community with connections

More information

RZC Appendix 8A Marymoor Subarea Street Requirements

RZC Appendix 8A Marymoor Subarea Street Requirements RZC Appendix 8A Marymoor Subarea Street Requirements For additional design details for Marymoor Subarea infrastructure, refer to the 2017 Marymoor Subarea Infrastructure Planning Report. STREET REQUIREMENTS

More information

AGENDA ITEM SUMMARY SPECIAL AGENDA ITEM NO. _1A_

AGENDA ITEM SUMMARY SPECIAL AGENDA ITEM NO. _1A_ AGENDA ITEM SUMMARY AGENCY: City Council MEETING DATE: June 25, 2012 DEPARTMENT: Community Dev PREPARED BY: T Spade DEPT. DIR. APPROVAL: MJ CITY MGR. APPROVAL: LR PRESENTED BY: T Spade TITLE: RECEIVE REPORT

More information

Chapter 14 PARLIER RELATIONSHIP TO CITY PLANS AND POLICIES. Recommendations to Improve Pedestrian Safety in the City of Parlier (2014)

Chapter 14 PARLIER RELATIONSHIP TO CITY PLANS AND POLICIES. Recommendations to Improve Pedestrian Safety in the City of Parlier (2014) Chapter 14 PARLIER This chapter describes the current status and future plans for biking and walking in the City of Parlier. RELATIONSHIP TO CITY PLANS AND POLICIES The Parlier General Plan is the primary

More information

Gordon Proctor Director Policy on Accommodating Bicycle and Pedestrian Travel on ODOT Owned or Maintained Facilities

Gordon Proctor Director Policy on Accommodating Bicycle and Pedestrian Travel on ODOT Owned or Maintained Facilities Approved: Policy: 20-004(P) Responsible Office: Planning Gordon Proctor Director Policy on Accommodating Bicycle and Pedestrian Travel on ODOT Owned or Maintained Facilities I. POLICY STATEMENT: This policy

More information

What Is a Complete Street?

What Is a Complete Street? Session 5 Charleen Zimmer, AICP, Zan Associates May 5-7, 2010 What Is a Complete Street? May 2010 5-1 Not a Complete Street More of a Complete Street May 2010 5-2 Benefits of Complete Streets Safety for

More information

Solana Beach Comprehensive Active Transportation Strategy (CATS)

Solana Beach Comprehensive Active Transportation Strategy (CATS) Solana Beach Comprehensive Active Transportation Strategy (CATS) 3.0 Goals & Policies The Solana Beach CATS goals and objectives outlined below were largely drawn from the Solana Beach Circulation Element

More information

Safe Routes to School Action Plan Aberdeen, Idaho

Safe Routes to School Action Plan Aberdeen, Idaho Background Aberdeen, Idaho is a largely agricultural community of nearly 2,000 people and is located in the southeast portion of the state on the western edge of American Falls Reservoir. The community

More information

Bicycle Master Plan Goals, Strategies, and Policies

Bicycle Master Plan Goals, Strategies, and Policies Bicycle Master Plan Goals, Strategies, and Policies Mobilizing 5 This chapter outlines the overarching goals, action statements, and action items Long Beach will take in order to achieve its vision of

More information

5/7/2013 VIA . RE: University Village Safeway Expansion (P13-019)

5/7/2013 VIA  . RE: University Village Safeway Expansion (P13-019) 5/7/2013 VIA EMAIL David Hung, Associate Planner Community Development Department, Current Planning Division City of Sacramento 300 Richards Boulevard, 3 rd Floor Sacramento, CA 95811 RE: University Village

More information

Minutes of the regular meeting of the City of Birmingham Multi-Modal Transportation Board held June 19, 2014.

Minutes of the regular meeting of the City of Birmingham Multi-Modal Transportation Board held June 19, 2014. CITY OF BIRMINGHAM START-UP MEETING OF THE MULTI-MODAL TRANSPORTATION BOARD THURSDAY, JUNE 19, 2014 City Commission Room 151 Martin Street, Birmingham, Michigan Minutes of the regular meeting of the City

More information

WHEREAS delivery trucks also pass through the Narrows, into the northern parking lot, to loading docks in the back of the building.

WHEREAS delivery trucks also pass through the Narrows, into the northern parking lot, to loading docks in the back of the building. CEDAR-ISLES-DEAN NEIGHBORHOOD ASSOCIATION ( CIDNA ) RESOLUTION OPPOSING A DRUG STORE DRIVE THRU, AND COMMENDING DORAN COMPANIES FOR PROPOSING MITIGATING AMENITIES INCLUDING NEW LANDSCAPING AND A DEDICATED

More information

TRANSPORTATION & MOBILITY

TRANSPORTATION & MOBILITY TRANSPORTATION & MOBILITY ROADWAY SYSTEM There are approximately 40 miles of roadways in Manitou Springs. For planning purposes, roadways are typically assigned a functional classification which defines

More information

Hennepin County Bicycle and Pedestrian Planning

Hennepin County Bicycle and Pedestrian Planning Hennepin County Bicycle and Pedestrian Planning 1 Value of bicycle and sidewalk systems Safety Livability Mobility Health Personal Finances Economic Sustainability Clean Air Recreation Parking and congestion

More information

HARRISON STREET/OAKLAND AVENUE COMMUNITY TRANSPORTATION PLAN

HARRISON STREET/OAKLAND AVENUE COMMUNITY TRANSPORTATION PLAN HARRISON STREET/OAKLAND AVENUE Community Workshop #4: Draft Plan Review December 3, 2009 D E S I G N, C O M M U N I T Y & E N V I R O N M E N T INTRODUCTIONS Key Project Staff: Alisa Shen, Project Manager,

More information