Warsaw, Missouri Van Buren Street Preliminary Engineering Report

Size: px
Start display at page:

Download "Warsaw, Missouri Van Buren Street Preliminary Engineering Report"

Transcription

1 Warsaw, Missouri Van Buren Street Preliminary Engineering Report Prepared for: The City of Warsaw 181 Harrison Street Warsaw, MO (660) Prepared by Charles LePage, P.E. CFS Engineers 119 W. Pacific Street Branson, MO 65611

2 TABLE OF CONTENTS VAN BUREN STREET I. EXECUTIVE SUMMARY II. III. IV. EXISTING CONDITIONS..3 DESIGN CHALLENGES...7 Koskiusko to Osage Osage to Jackson Jackson to Jefferson....8 Jefferson to Washington....9 Washington to Main Main to Harrison DESIGN CONSIDERATIONS Proposed Improvements Parking Bike Accommodations Environmental Street Lighting Easements and Right of Way Koskiusko Street Improvements North Elementary School V. RECOMMENDATIONS AND CONCEPTUAL DESIGN.15 Koskiusko to Osage Osage to Jackson Jackson to Jefferson Jefferson to Washington Main to Harrison APPENDICES VAN BUREN STREET EXHIBITS I III SCHOOL TRANSIT CENTER EXHIBITS SCHOOL WEST PARKING AND KOSKIUSKO EXHIBIT 1

3 INTRODUCTION VAN BUREN STREET Over the past 19 years, the city of Warsaw, Missouri has taken proactive steps to make community-wide improvements to their infrastructure. This started with a series of planning processes that looked comprehensively at sewer and water, transportation, community recreation and tourism. The goal of the City was to overcome deficiencies in the infrastructure, develop a more livable community and create an environment that would attract businesses and tourists. The catalyst for creating a livable community derived from a series of strategies and planning documents that were continually updated to reflect successes and short falls. These studies and planning documents outlined community needs and recommended improvements with priorities and cost estimates for budgeting. The City aggressively sought out funding for these much needed improvements with great success. The City has made significant upgrades to its existing utility network and recreational facilities as well as some improvements to the transportation system. The City is now focusing on its attention on addressing the transportation network to better accommodates the citizens of Warsaw along with the increasing number of visitors to the area. In addition, the City desires to improve accessibility to all modes of transportation throughout the community that will encourage the attraction of new residents and businesses. This new direction by the City was initiated with the adoption of the community s new Comprehensive Plan titled, Building on Success to Capitalize on the Future. This Comprehensive Plan includes a section entitled Warsaw Livable Community Transportation Improvement Plan (TIP). The TIP is a very thorough plan on how to improve the community s transportation system that provides great connectivity throughout the City, and capitalizes on the exceptional waterfront trails system that currently exists. The goal of the transportation improvements plan is to create a network of multi-modal streets and pathways that link to the trail system to create a unique transportation system for all who live, visit or conduct business in Warsaw. These highly visible projects will make a statement that Warsaw is a progressive city that is willing to invest in improving the quality of life for all who live, work or visit our community. These improvements will provide everyone with great flexibility, safety and comfort to enjoy the many unique and abundant outdoor beauty and experience opportunities that Warsaw has to offer. For future planning and funding the City of Warsaw has commissioned CFS, Engineers to study the Van Buren corridor between Koskiusko Street and Harrison Street. For the City s proposed CDBG funding application, the project area will be defined as from Kiokiusko Street to Jackson Street. Currently CFS is also preparing a Preliminary Engineering Report for the City that addresses transportation issues and needs along the entire Jackson Street Corridor. The two studies will assist the city in developing a comprehensive approach to providing multi-modal transportation improvements for the two vitally important routes. Improvements along these two corridors with multi-modal capabilities will encourage redevelopment as outlined in the city comprehensive plan entitled Building on Success to Capitalize on the Future. Additionally, the improved streets will provide muti-modal routes that access parks, commercial and residential areas and community services and amenities. 2

4 EXECUTIVE SUMMARY The Van Buren Preliminary Engineering Report (PER) project limits extend from Harrison Street in the downtown, Northward to Koskiusko Street and the North Elementary School property. The purpose of the (PER) is to evaluate the condition of the existing infrastructure, identify conflicts, issues and limitations for motorists, pedestrians and cyclists, discuss critical needs and determine improvements that will promote multi-modal transportation choices as well as health and safety for citizens of the community. The existing conditions along several blocks of Van Buren are unsafe for pedestrians as can be seen in the adjacent photo where students and parents are seen walking in the roadway. VAN BUREN STREET The PER addresses needed improvements such as ADA compliant sidewalks, potential for bike lanes, improved storm drainage, streetscapes, lighting, parking and traffic flow and pavement marking and signage. This study also looks at the North Elementary School and provides recommendations for a transit facility that will improve traffic safety and conflict resolutions between students and buses from multiple schools with multiple arrival and departure times. The school site is a central location within the community and streets connecting to the school (such as Van Buren) see a large volume of pedestrian and bicycle use. Because of its strategic location, the overall concept of a transit facility at the school can also provide additional opportunities for community when the school is not using the facility. These uses could include: a community transit facility, parking for users of the multi-modal transportation network and community event parking. The PER discusses the environmental permitting process and probable issues that will need to be addressed for agency approval, depending upon which funding source is utilized. The report provides conceptual design with cost estimates for engineering and surveys, utility adjustments, easements and construction related expenses for various alternatives and includes recommendations for proposed improvements. The ultimate rational for this project is to continue promoting Warsaw s goal of developing safe, reliable, and economical transportation choices to by investing in walk-able neighborhoods. Improvements to Van Buren Street were mentioned in the 2015 Warsaw Livable Streets Transportation Improvements Plan. The benefits of which are to provide connectivity from the downtown waterfront trail system to the heart of the community. Van Buren was identified as one of the key streets to be improved as it provides an important route between downtown and North Elementary School. 3

5 Existing Conditions VAN BUREN STREET Van Buren Street in Downtown Warsaw, MO. Vicinity Map General Van Buren Street s boundaries extend about 1,785 feet, from Kosciusko Street and North Elementary School at the north end to Harrison Street and the Warsaw Community Building at the south end. From Kosciusko south to Jefferson, the area is residential, changing to a mostly commercial area from Jefferson to the Community Building. Portions of Van Buren Street have received major improvements as part of several downtown renovation projects. Traffic Van Buren Street is currently a Community Connector between the North Elementary School and the Warsaw downtown, Community Building and waterfront. At about the midway point along this section of roadway, Van Buren crosses Jackson Street which is one of the primary arterials through the City. Vehicular traffic along Van Buren north of downtown is light through most of the day with heavier numbers occurring during the morning and evening start and end of the school day. The North Elementary School serves as a transit center for dropping off and picking up students from three of the area schools, including the elementary school. As a result there are large numbers of buses, passenger cars and pedestrians converging at this location. Confusion and traffic conflicts are common. A large percentage of this traffic travels along Van Buren Street. 4

6 Roadway Sections The right of way width for Van Buren Street is 66 feet. The existing roadway is an approximately 24 foot wide asphalt pavement. The pavement is in fair to poor condition and mostly in need of an asphalt overlay. Sidewalks exist along portions of Van Buren, but are generally in poor condition. Beginning about 200 feet southwest of Jefferson Street and extending to Koskiusko Street, Van Buren has variable width, turf shoulders and open ditches with sidewalks at the back of the ditches. From 200 feet southwest of Jefferson to Washington Street, Van Buren has no shoulders or ditches but includes on-street parking with a sidewalk beyond the parking area. Between Washington Street and Main Street, Van Buren has been upgraded to include ADA compliant sidewalks, corner bump-outs with on-street parking, landscaping and ornamental street lighting. The area between Main Street and Harrison Street has a sidewalk along the west side of the street only with diagonal on-street parking on both sides and ornamental lighting at the corners. Sidewalks The current sidewalk is mostly a 4 foot wide section north of Washington Street and is located between 10 and 15 feet from the edge of the existing pavement, near the existing right of way line. The majority of this sidewalk is in very poor condition, presents trip hazards, has gaps and is non-continuous. To the right is an example of a sidewalk that shows evidence of upheaval from tree roots. Between Jackson Street and Koskiusko a sidewalk exists on the west side of the roadway only. This is likely due to some of the physical challenges and obstacles in this area. From Kosciusko to Osage the roadway grade is very steep with the existing sidewalk incorporating concrete steps and retaining walls to help meet the roadway grade and a concrete sidewalk bridge to help pass over the Town Branch Creek box culvert at Osage. From Osage Street southward, about 110 of sidewalk was reconstructed along the west side of the roadway as part of city-wide waterline replacement project. About 60 of this sidewalk was constructed adjacent to the edge of roadway, due to drainage issues at the southwest corner of the intersection. This segment of sidewalk is 6 feet wide, meets ADA compliance and can be used in-place with a future sidewalk project. The remaining 50 feet of sidewalk that was constructed with this project is offset from the roadway to align with the older sidewalk to the south and is in excellent condition. From Jackson St. to Washington St. there are currently sidewalks on both sides of Van Buren, but sections are missing. 5

7 At Jackson Street there are sidewalk extensions in three of the four corners of the intersection that connect with the 4 feet wide sidewalks currently running east and west on Jackson Street. At Jefferson there are sidewalk connections with the cross street in the NE and SW quadrants of the intersection. At Washington Street there are sidewalk connection with the cross street in all four quadrants. The sidewalks between Washington and Main Street were reconstructed in recent years and upgraded to be ADA compliant with a 10 sidewalk on the west side and a 6 sidewalk on the east side (Benton County Courthouse) and both are in excellent condition. ADA compliant sidewalks also extend to the west along the south side of Washington Street and to the east adjacent to the courthouse. Stamped concrete pavers and landscape beds create island bump outs at the corners to provide protected buffers for parked vehicles. From Main Street to Harrison Street, the sidewalk is currently located on the west side of the roadway only. The sidewalk on the west side is 4 feet wide adjacent to a barrier curb at the front and a building at the back. Complete street improvements were recently constructed with the Harrison Street project that included ADA compliant sidewalk upgrades to the southwest and southeast quadrants of the Van Buren intersection across from the entrance to the Community Building. On-street diagonal parking exists on both sides of the street in this area. Buildings on either side of the street appear to have zero setback from the right-of-way line. Storm Water The storm water and drainage system along Van Buren is currently handled using roadside shallow swales, ditches and culverts. These culverts are located underneath some of the entrances and under the roadways at intersections. The storm water runoff beginning at Koskiusko Street travels overland, southwesterly toward Osage Street. Most of this runoff flows into the Town Branch Creek at the northwest corner of Osage Street, however a portion of the storm water flows across the street and into the southwest corner of the intersection. At the intersection of Osage and Van Buren there is a large 5 foot by 10 foot box culvert that carries drainage from the Town Branch Creek under the intersection from the NW quadrant to the SE quadrant. The property owner at the southwest corner of this intersection has complained that 6

8 there is a considerable amount of storm water that backs up into their property during heavy rainfall events. At Jackson Street, there are culverts with head-walls that carry storm water east to west on both the north and south sides of Jackson, as well as carry the water from the south to the east and west. In the SE quadrant of this intersection there is a sizable ditch with retaining walls on both sides to the east. At the Jefferson Street intersection, culverts with head-walls carry storm water from south to north across Jefferson on the west side of the road, as well as east to west on the south side of Jefferson. At the Washington Street intersection, the storm water from the roadway is handled by grate inlets located adjacent to the roadway, in the NE and NW quadrants of the intersection. Small pipe culverts outlet the water into shallow ditches that drain northward to Jefferson Street. The storm water from Washington to Main Street is captured by inlets installed during the reconstruction projects for this stretch of roadway. From Main to Harrison Street, the storm water flows southward and into drainage structures constructed with the Harrison Street project. Driveways/Entrances Between Kosciusko and Washington there are many residential, and several commercial entrances and driveways. These driveways consist of a variety of material including aggregate, asphalt, and concrete. As discussed earlier, some of these driveways have pipe culverts under them, some of them do not. The profile grade of nearly all of these driveways are flat to very gentle. Parking Parking is currently allowed on the street throughout the corridor, however, limited shoulder space is not conducive to parking for much of the area north of Jefferson Street. From Harrison Street to midway between Washington and Jefferson, there is designated on-street parking. Utilities Utilities along the Van Buren Street corridor include water, sanitary sewer, natural gas, telephone, and overhead power. The waterlines in this area are in good condition and should not require much adjustment. Other utilities such as power poles may require minor adjustments to stay out of the proposed sidewalks. Bike Lanes Currently, bike lanes do not exist along this roadway. There is adequate room for adding bike lanes along the Van Buren Street for about half of the corridor. Street Lighting Street lighting exists along Van Buren in several locations. Between Koskiusko and Osage, there are three lights located on power poles along the west side of the roadway. There are no street lights between Osage and Jackson Street. A light attached to a power pole exists at the southwest corner of the Jackson Street intersection. No lights exist along the remainder of the block from Jackson to Jefferson. The next light pole is at the southwest corner of the Jefferson Street intersection. No lighting exists along the remainder of the block southward to Washington. The 7

9 block of Van Buren from Washington Street to Main Street contains three ornamental lights on each side of the street, as well as a light on the southeast and southwest corners of Main Street. There are no lights again, until Harrison Street. 8

10 Design Challenges VAN BUREN STREET Kosciusko Street to Osage Street This stretch of Van Buren has many design challenges, the first being the steep grade of the roadway. This steep grade and the current offset of the sidewalk from the roadway on the west side contributed to concrete stairs being constructed along the sidewalk instead of sidewalk ramps. These existing stairs along with large segments of retaining walls will have to be removed and the area adjacent will require regrading with new retaining walls constructed. Along with the grade of the road, along the side of the road there are steep grades up to the private properties in some places. A major problem in this stretch of the corridor is the large box culvert at the NW corner of Osage and Van Buren. This culvert carries the drainage of Town Branch Creek diagonally underneath the intersection and outlets on the SE corner. The existing roadway side-slope drops very steeply from the edge of the pavement down to the existing elevated sidewalk and continues to fall away under the sidewalk down to the channel bellow. In order to rebuild the sidewalk in this area, some form of retaining wall will be required, as well as an extension of the inlet/upstream end of the box culvert. Handrails should also be considered. Clearing of some trees at this location will be required to do the construction. The power pole at this location will probably not require relocation. Another design challenge will be constructing a sidewalk around raised sanitary sewer manholes on the east side of Van Buren. There are also overhead utility poles that will have to be designed around or relocated. At the SE corner of Kosciusko and Van Buren, and at the NE corner of Osage and Van Buren there are old concrete street markers that will need to be undisturbed or removed and reset, as they are likely set at the property corners. These street markers are located at nearly all intersections. The challenges with the roadway grade, steep side slopes, utility and property conflicts present many physical limitations to adding bike lanes along this block of Van Buren. 9

11 Osage Street to Jackson Street This section of Van Buren includes the challenge of constructing a sidwalk around or over the box culvert at the Town Branch Creek. At the SW corner of Osage and Van Buren in order to construct a sidewalk, some form of retaining wall, as well as possibly extension of the outlet end of the box culvert will be required. While steep at the north end towards Osage, the roadway to the south is mostly very flat with no ditches or drainage structures, except at Jackson Street, where there is a cross road pipe with head-walls under Van Buren Street. At Jackson Street new sidewalks will require connections to sidewalks that link to the east and west and will require extension of existing pipe culverts. Overhead utility poles will need to be relocated or sidewalks will need to be designed around the poles. Jackson Street complete street improvements are planned for future reconstruction, including bike lanes and sidewalks. This will be addressed later in this report and needs to be taken into account during the design of Van Buren in this area. At the NE corner of Jackson and Van Buren there is an old street marker that will need to be undisturbed or removed and reset, as it is likely set at the property corner. There is adequate room to widen the roadway to add 5 bicycle lanes along most of this block of Van Buren, except for the area near the Osage Street intersection. Jackson Street to Jefferson Street From Jackson to Jefferson Street, ditches are located along both sides of the roadway for most of this section. Culverts carry storm water underneath private entrances. Culverts with head-walls carry storm water under Van Buren, draining from west to east at Jackson. Jackson has been planned for future improvements as stated previously, and that design will need to be incorporated into this intersection design. At the southeast corner of the Jackson intersection, There is a large ditch that runs to the east with a retaining wall which will need to be taken into account when designing this intersection. Along the west side of Van Buren, towards the south end of this stretch, there are several small retaining walls at the property line, as well as concrete steps on private property in some locations that will need to be taken into account when designing this section of Van Buren. There is a culvert with a headwall that carries water from south to the north under Jefferson street on the west side of Van Buren as well as a sidewalk connection to the west that includes some concrete steps 10

12 approximately 75 feet west of the intersection that would likely need to be reconstructed as a sidewalk ramp. Overhead utility poles along the corridor will need to be designed around or relocated and old street name markers at intersections will need to be undisturbed or removed and replaced at the likely property corners. There is adequate room to widen the roadway to add 5 bicycle lanes along this block of Van Buren, Jefferson Street to Washington Street There are ditches along both sides of the road on the north half of this stretch of roadway. At the south side of Jefferson Street, a pipe culvert carries storm water under Van Buren draining from west to east with head-walls on both ends of the pipe. Large ditches running east and west along the south side of Jefferson Street will also require culvert extensions in order to design and construct a new sidewalks along Van Buren. Along the west side of the roadway, there are retaining walls at the property line supporting the raised grade of the private property, with concrete steps leading into some of the properties. These walls will likely need to be removed and new walls will need to be constructed. Small block walls, or concrete walls integral to the sidewalks would be the preferred options. Entrances with culverts under them line the west side of the roadway. Grate inlets at the edge of the street about halfway between Jefferson and Washington will need to be relocated and replaced in order to accommodate curbs and sidewalks. Along the east side of Van Buren towards Washington, there is currently on street angled parking with sidewalk at the back on the property line. This sidewalk is raised from the road grade, and the grade difference is rather large at the southernmost end, with steps to return to road/parking grade at Washington. Retaining walls may be needed at the property line in this area, and a fence at the property line will also need to be relocated, or replaced. Grate inlets again on the north side of Washington will need to be relocated and replaced to accommodate sidewalks and curbs through this section. The south side of the Washington and Van Buren intersection was reconstructed recently, so no further design is necessary. Old street name markers at the SE corner of Jefferson and the NW corner of Washington will need to be undisturbed or removed and reset as they are likely at the property corners. 11

13 There is adequate room to widen the roadway to add 5 bicycle lanes for about half of this block of Van Buren, Approaching the Washington Street intersection, on-street parking limits the ability to add bike lanes. Washington Street to Main Street This block of Van Buren Street was recently reconstructed with sidewalks, curb ramps, onstreet parking, street lighting and landscaping so no further design or construction is necessary. Design considerations for Van Buren within the downtown business area should be consistent with the nature and appearance of this block. Main Street to Harrison Street The intersection of Main Street and Van Buren was reconstructed with downtown Main Street renovations, so no further design is necessary. South of Main, sidewalks run along the west side, but not the east side. The sidewalk along the west side is in good condition, but is only about 4 feet in width. There is angled parking along both sides of Van Buren in this area. In order to build a sidewalk along the east side of Van Buren, this angled parking will likely need to be changed to parallel parking. The sidewalk on the west side could be reconstructed to 6 feet wide and still allow diagonal parking. Another concern is an elevated entrance into the building on the east that currently has wooden steps. These steps will need to be replaced and a curb bump out will need to be constructed to accommodate this entrance. South of the building, there is a concrete retaining wall which may be able to be used in place, but some inspection will need to be done to determine whether or not is should be replaced. At the south end, the Harrison Street intersection was recently reconstructed, and includes sidewalk connections, so the sidewalks along Van Buren will need to be designed to tie into these connections. 12

14 Design Considerations VAN BUREN STREET Proposed Improvements In order to accommodate upgraded sidewalks, and better control the storm water runoff, curb and gutter should be constructed along Van Buren. A 28 foot cross section with 2 12 foot lanes and 2 foot curb and gutter would allow for reconstruction of the sidewalk and allow room for separation from the roadway and grading within the right of way. A rollback, low-profile curb and gutter is recommended where the roadway side slopes fall away steeply. In addition to curb and gutter roadway improvements, a mill and asphalt overlay would be beneficial to Van Buren Street. The existing terrain, as well as some large drainage structures will require that the sidewalk be designed at the back of the curb adjacent to the roadway in some locations. The new sidewalk would be 5 foot wide for most of the corridor, along both sides of the road. In some locations, where the sidewalk would be at the back of curb, it would need to be 6 feet wide. At the Town Branch Creek crossing, the existing box culvert may need to be extended, however sidewalk construction may be possible with a block retaining wall. A combination of both box culvert extension and retaining wall may be the best solution. A wider sidewalk could be constructed along one side of the roadway to accommodate bikes for most of the block from Kosiusko to Osage. With the addition of curb and gutter to Van Buren, an enclosed storm sewer system will be required. This storm sewer system would collect the runoff and divert it to existing ditches along the side roads, as well as to the Town Branch Creek. Near the Washington Street intersection, storm water is currently being captured in existing inlets with culverts that flow into open ditches along the shoulder. Ideally some portions of the existing storm culvert pipes could be used as part of a larger system to capture and divert the storm water. For the purposes of this report, new inlet structures and piping will be assumed to be required throughout the corridor. It is also possible for portions of Van Buren to be upgraded with new sidewalks without the addition of curb and gutter. The segments of roadway between Osage and Jefferson could be constructed without curb and gutter. In this region, the ditches could be modified by adding 13

15 storm pipes and filling in the ditches to create shallow swales. The storm water runoff from the roadway would collect in area inlets located at low spots within the swales. Connecting to the existing sidewalks running east and west on the side roads will also present a challenge in some areas. The design will include a length of sidewalk to the east and west at each intersection. In addition to the sidewalk connection at the side roads, the storm culverts would be extended to accommodate these transitions. Parking On-street parking should be maintained where it exists currently. The parking between Washington Street and Main Street should remain unchanged. The north side of the Washington Street intersection should include curb bump outs to match the south side of the intersection and to protect on street parking, as well as provide safer and more defined pedestrian crossings. The addition of curb bump outs in this area will also allow for landscaping and better storm water collection. Some of the areas where diagonal parking exists should be reconfigured as parallel parking to allow for improved sidewalks. One area in particular is the east side of Van Buren, between Main Street and Harrison. This area currently has diagonal parking with insufficient room to add sidewalks. A solution for this issue would be to reconfigure the parking as parallel parking, which would allow for a 6 foot sidewalk adjacent to the building. The sidewalk would need to jog around the doorway into the side of the building and new stairs would need to be constructed something similar to the rendering shown. Parking at this location would reduce from 9 spaces to 6 spaces. Bike Accommodations In addition to the pedestrian upgrades along Van Buren, enhancements for bike transportation should be investigated. About 850 feet of bike lanes could be added to Van Buren between Washington Street and Osage, up to where on-street parking near Washington Street exists Ditches are very shallow in this area and would not require a significant amount of earthwork to widen and add bike lanes. This would likely eliminate the use of curb and gutters in this segment of Van Buren. North of Jackson Street, the roadway side slopes drop off and would require earthen fill that would encroach on adjacent properties, requiring easements or would necessitate retaining walls at the back of the sidewalks in order to widen for bike lanes. At the Town Branch Creek crossing 14

16 and going up the hill toward Koskiusko, the issues with adding bike lanes are very problematic and costly and would require substantial grading on private properties as well as impact to sanitary sewers and other utilities. From Washington Street to Harrison Street there is inadequate room to add bike lanes. With these design concerns, impacts and associated costs, dedicated bike lanes would be not be recommended for this roadway. The low vehicular traffic volume on Van Buren for most of the day is conducive to a shared roadway, using sharrow type pavement markings and signage to denote Van Buren as a Share the Road facility. With the improved sidewalks, younger bicyclists would have a safer alternative to riding in the street. Environmental The environmental concerns of a Van Buren street project are minimal. Section 106 clearance will be required and likely 404 permits for work done in the Town Branch Creek, which will be impacted only minimally. Possibly an extension of the existing box culvert or a large block retaining wall along the existing bank to help prevent erosion. Impacts to Public Lands such as the school playground may warrant the need for Section 4f clearance. Other environmental concerns will most likely be covered by a Storm Water Pollution Protection Plan (SWPPP). The NEPA process will need to be adhered to if federal funds are utilized for improvements to the corridor. Street Lighting Street lighting is present at some locations along the corridor. In addition to other improvements, including pedestrian/street lighting should be considered along Van Buren Street. As mentioned above, Van Buren is a major pedestrian thoroughfare connecting the school to the community center and harbor. The addition of lighting on both sides of the street would provide additional safety for pedestrians and vehicle traffic. The street lighting fixtures should be similar to those already installed in the downtown area and should be spaced at no more than 140 feet apart. This spacing would typically place lights near the intersections and midway between blocks. Easements and Right of Way This project can be designed to be completely constructed within the existing right of way for Van Buren and the side roads. Temporary construction easements will be required along the corridor to reconstruct private sidewalks, remove existing structures, build storm sewers and regrade slopes. Right of way or permanent easement will be needed at the NW corner of the Van Buren and Osage intersection. A large volume of earthen fill will be needed to bring the slopes up to a reasonable grade for the sidewalk, as well as bank bank stabilization and box culvert extension. Additional right of way for future maintenance of the box culvert or retaining walls along the creek bank is warranted. Kosciusko Street Improvements Also included in this project will be the closure of Kosciusko Street to through, motorized vehicular traffic between Stagecoach and Seminary Street. There is one house located along this portion of Koskiusko, with driveway access about 130 east of Seminary Street. Access would continue to be provided to this house, but beyond this property eastward, Kosciusko would be 15

17 converted in to a bike/pedestrian pathway, restricting access to other vehicles. There are several ways to accomplish this, including construction of curbs creating a neck-down at each end, or installing bollards at each end which would create the same effect as a neck-down in a more cost efficient manner. Bollards would need to be placed at spacing that would be narrow enough to restrict motorized vehicles from passing through, probably 6 feet. Street lighting should also be considered along this new pedestrian/bicycle route. Special signing would added as well to let users know that this is a new addition to the existing Warsaw bike and pedestrian trail system. North Elementary School The final aspect to the Van Buren Street Preliminary Engineering Report focuses on improvement needs at the North Elementary School. These improvements include upgrades to parking and the addition of a school bus transit center (bus pick up and drop off). There are two parking areas that are considered. The first is the grassy lot immediately southeast of the school. This area would be used for a new parking lot for parents dropping off and picking up students that ride the buses to the other schools in the district. This lot would separate these vehicles from the pedestrian traffic entering the school from the east side. Adjacent to this lot would be a new transit center with one-way bus traffic in and out of the dropoff and pick up area. Shelters could be provided at the drop-off zone. Sidewalks would connect between the transit center, the new parking lot and the school. The existing drop-off area could be modified and utilized for drop-off and pick up of special needs students and possibly for other uses. The parking area would have access to Niangua and Kosciusko streets, and would be the main location for parents to wait while they drop off or pick up their children. The transit center would have a one-way (southbound) roadway between Niangua and Koskiusko. The transit center could be connected to Kosciusko, Niangua, and Commercial streets in a number of different configurations. Construction of this new parking area and transit center would require relocation of the existing school playground. Land to the north of the school could be utilized for a new playground and for parking for school employees. The relocation of the playground would also include the closure of part of Niangua on the north side of the school to provide a safe crossing for children to and from the playground. This closing could be permanent or temporary with gates during school hours. Southwest of the school, there is currently a gravel parking area with driveway connections to Kosciusko and Stagecoach that is used for dropping off and picking up children by parents. This parking lot could be paved to provide better delineation for parking, as well as be converted to a one way in and out to reduce conflicts and improve traffic flow. A curb with a 6 foot sidewalk could be constructed adjacent to the edge of pavement for students being dropped off. Parents could use this area to drop off and pick up their children as well as the new parking area discussed earlier. 16

18 Recommendations and Conceptual Design VAN BUREN STREET Van Buren Street should be upgraded to include as much infrastructure improvement as can be afforded by the City of Warsaw and ideally optimize the amount of funding that can be acquired for the corridor. The project limits should encompass the boundaries between Koskiusko Street and Washington Street and the block from Main Street to Harrison Street. Minimum improvements should consist of constructing a new 5 sidewalk on both sides of the roadway for the entire route. Recommended improvements would consist of a wider sidewalk (8 to 10 ) on one side that could be used as a multi-use path, the construction of curb and guttering with an enclosed storm sewer system, street lighting, and landscaped islands at the corners of Washington Street. At all intersections sidewalks and curb ramps should be constructed that parallel the cross streets in the area between the Van Buren sidewalks and the edge of the roadway. Pavement markings should be applied for crosswalks and street lighting should also be included. Exhibits I - V in the Appendix show aerial displays of the Conceptual Designs for Van Buren and the Elementary School. The recommended improvements are discussed on a block-by-block basis as follows: Koskiusko to Osage This block of Van Buren will require significant grading and embankment in order to construct a sidewalk on each side. The 5 sidewalk beginning at Koskiusko would be located a minimum of 5 behind the back of curb to provide a buffer from the roadway. Heading down the hill, the sidewalk would be constructed closer to the edge of the street and likely at the back of curb due to the challenges with steep side-slopes and potential impact to utilities. Where the sidewalk is constructed at the back of the curb it would need to be 6 feet wide. The existing sidewalks and stairs, including a fair amount of the private sidewalks leading back to the houses will need to be demolished and reconstructed along this block. Existing retaining walls will need to be removed and replaced or have the slopes regraded back toward the houses. Retaining walls would be required to avoid damage to mature trees. At the Osage Street intersection, the existing 5 x 10 concrete box culvert will likely need to be extended both upstream and downstream in order to accommodate sidewalks in this area. At the upstream end of this culvert, a retaining wall at the back of the sidewalk or bank slope protection along the channel wall would be recommended to protect the embankment from erosion and collapse. Crosswalks would be added at all street crossings as well as signage. 17

19 East side of Van Buren near southeast corner of Osage Street Osage to Jackson Street The block between Osage and Jackson Street should include curb and guttering with a minimum 5 buffer separating the sidewalk from the back of the curb. This area has relatively gentle sideslopes from about 100 south of Osage Street to the intersection of Jackson and is conducive to providing the grass buffer with sidewalks located near the right-of-way line. Impacts to existing utilities are minimal and storm drainage improvements would be easy to accommodate. West side of Van Buren facing southward toward Jackson Street 18

20 Jackson to Jefferson Street The block between Jackson Street and Jefferson Street includes a drainage ditch along both sides of the street through much of the block. These ditches will allow for minimal grading to install curb and guttering and an enclosed drainage system. A minimum 5 buffer separating the sidewalk from the back of the curb is easy to accommodate and should be provided. This area has relatively gentle side-slopes although a few properties would likely require small retaining walls or grading outside of the right-of-way limits. Sidewalks should be located near the right-of-way line as much as possible, however there are some locations where the sidewalks may need to move closer to the back of curb to avoid power poles and other utilities. The other option is to have the poles relocated closer to the roadway and continue the straight route of the sidewalk. West side of Van Buren facing southward toward Jefferson Street Tree stumps along the east side will require removal and mailboxes may require relocation behind the curbing. Jefferson to Washington Street The block between Jefferson and Washington Street includes a drainage ditch along both sides of the street for the north half of the block, with an enclosed storm drainage system through the south half. Curb and gutter and a new enclosed storm drainage should be constructed along the entire block. The east side of the street has a vacant lot covering about half the block and has gentle sideslopes. Along the west side of the street, existing retaining walls should be able to remain in place. A minimum 5 buffer separating the sidewalk from the back of the curb is easy to 19

21 accommodate and should be provided where possible. Sidewalks should be located near the right-of-way line as much as possible, however there are some locations where the sidewalks may need to move closer to the back of curb where on-street parking exists. The areas near Washington Street should continue to include on-street parking, however the diagonal parking on the east side should be converted to parallel parking. Island bump-outs should be constructed to match what was previously constructed along the block to the south. Street lighting should be located near intersections at all four corners and at mid-block. Landscaping should be added to all islands. Southeast corner of Van Buren at Washington Street 20

22 Main Street to Harrison This block of Van Buren should include constructing 6 wide sidewalks adjacent to the buildings on either side with a barrier curb at the edge of the pavement. Diagonal parking on the east side of Van Buren should be converted to parallel parking. The sidewalk should jog around the side doorway into the building and new stairs with handrails should need to be constructed. Street lights should be added at mid-block. No storm drainage inlets or piping should be needed. The estimated cost to construct Van Buren Street improvements from Koskiusko Street to Harrison Street is $819,705. The the total cost estimate, including right of way costs, utility adjustments, engineering and construction administration and inspection is $1,041,843. The addition of street lighting is a major cost item for this project. Eliminating street lighting would drop the overall cost estimate to $815,270. The estimated cost to construct improvements from Koskiusko Street to Jackson Street is $380,542. The the total cost estimate, including right of way costs, utility adjustments, engineering and construction administration and inspection is $498,066. Extending new sidewalks, with minimal additional improvements southward to Jefferson Street would increase the cost estimate to just under $580,000. This would not include curb and gutters, storm drainage or lighting for this additional block. This would be recommended scope of improvements for the City s proposed USDA funding application. Curb and gutters, enclosed storm sewers and street lighting could be added later when additional funding is available or some elements could be constructed by City forces. The estimated cost to construct improvements from Koskiusko Street to Jefferson Street is $560,350. The the total cost estimate, including right of way costs, utility adjustments, engineering and construction administration and inspection is $729,150. Kosciusko Street Improvements Kosciusko should be converted into a bike and pedestrian pathway between the lone house on the block and Stagecoach Avenue. Raised islands should be constructed to restrict and prevent motorized vehicles from passing through this section of the block. Street lighting should also be considered along this new pedestrian/bicycle route for enhanced safety. Special signing should also be added alert and deter motorists and to inform bike and pedestrians of the purpose of the route. Refer to Exhibit V in the Appendix for a conceptual layout of the proposed Koskiuko street improvements. 21

23 Street lighting is the most significant cost for this improvement. The estimated cost to revise the existing roadway to accommodate bikes and pedestrians (if done in conjunction with the Van Buren or school projects) would be about $70,000. If constructed as a separate project the mobilization costs would increase the estimate to $80,000 to $85,000. These costs include engineering and construction administration. North Elementary School East Side The North Elementary School improvements should include upgrades to the existing parking and the addition of a school bus transit center (bus pick up and drop off). The grass lot immediately southeast of the school should be graded and a new parking lot should be constructed to allow parents to drop off and pick up students that ride the buses to the other schools in the district. This lot should be designed and constructed to provide as much parking as possible. The lot would separate parent and student vehicles from the pedestrian traffic entering the school from the east side. Adjacent to this lot to the east a new transit center should be constructed. This center should function to allow one-way bus traffic in and out of the drop-off and pick up area. Shelters could be provided at the drop-off zone. Sidewalks should be constructed to connect the transit center to the new parking lot and the school. The existing drop-off area could be modified and utilized for drop-off and pick up of special needs students and possibly for other uses. The new parking area would have access to Niangua and Kosciusko streets, and be the main location for parents to wait while they drop off or pick up their children. The transit center would have a one-way (southbound) roadway between Niangua and Koskiusko. The transit center could be connected to Kosciusko, Niagua, and Commercial streets in a number of different configurations. Construction of this new parking area and transit center would require relocation of the existing school playground. Land to the north of the school could be utilized for a new playground and for parking for school employees. The relocation of the playground should also include the closure of part of Niangua Street on the north side of the school to provide a safe crossing for children to and from the playground. Refer to Exhibit IV in the Appendix for a conceptual layout of the proposed improvements. The estimated cost to construct these improvements including engineering and construction administration is $565,322. North Elementary School East Side Southwest of the school, the existing gravel parking area should be reconstructed and reconfigured to provide a more efficient method of dropping off and picking up students. This parking lot could be paved to provide better delineation for parking, as well as be converted to a one way in and out to reduce conflicts and improve traffic flow. A curb with a 6 foot sidewalk should be constructed adjacent to the edge of pavement for students being dropped off. Refer to Exhibit V in the Appendix for a conceptual layout of the proposed improvements. The estimated cost to revise and pave the existing parking lot (if done in conjunction with the Van Buren or school projects) would be about $120,086. If constructed as a separate project the 22

24 mobilization costs would increase the estimate by about another $10,000 to $15,000. These costs include engineering and construction administration. 23

Complete Streets. Designing Streets for Everyone. Sarnia

Complete Streets. Designing Streets for Everyone. Sarnia Complete Streets Designing Streets for Everyone Sarnia Complete Streets ~ Sarnia ~ 2018 Introduction Our City is made up of a network of streets that we use to go for a walk, cycle to work, drive to the

More information

Non-Motorized Transportation 7-1

Non-Motorized Transportation 7-1 Non-Motorized Transportation 7-1 Transportation facilities no longer mean just accommodating a vehicle powered by a combustion engine. Pedestrian and non-motorized facilities are important modes of travel

More information

RZC Appendix 8A Marymoor Subarea Street Requirements

RZC Appendix 8A Marymoor Subarea Street Requirements RZC Appendix 8A Marymoor Subarea Street Requirements For additional design details for Marymoor Subarea infrastructure, refer to the 2017 Marymoor Subarea Infrastructure Planning Report. STREET REQUIREMENTS

More information

Warsaw, Missouri Main Street Complete Streets Preliminary Engineering Report

Warsaw, Missouri Main Street Complete Streets Preliminary Engineering Report Warsaw, Missouri Main Street Complete Streets Preliminary Engineering Report Prepared for: The City of Warsaw 181 Harrison Street Warsaw, MO 65355 (660) 438-5522 Prepared by Charles LePage, P.E. CFS Engineers

More information

Broad Street Bicycle Boulevard Design Guidelines

Broad Street Bicycle Boulevard Design Guidelines Broad Street Bicycle Boulevard Design Guidelines Building from the strategies introduced in the 2013 Bicycle Transportation Plan and community input received thus far, City Transportation Staff have identified

More information

Brooklyn Boulevard (County Road 152) Reconstruction Project Phase I. OPEN HOUSE June 20, 2017

Brooklyn Boulevard (County Road 152) Reconstruction Project Phase I. OPEN HOUSE June 20, 2017 Brooklyn Boulevard (County Road 152) Reconstruction Project Phase I OPEN HOUSE June 20, 2017 Brooklyn Boulevard (County Road 152) Phase I Project Partners Project Lead Other Project Partners include Brooklyn

More information

CHAPTER 16 PEDESTRIAN FACILITIES DESIGN AND TECHNICAL CRITERIA TABLE OF CONTENTS

CHAPTER 16 PEDESTRIAN FACILITIES DESIGN AND TECHNICAL CRITERIA TABLE OF CONTENTS CHAPTER 16 PEDESTRIAN FACILITIES DESIGN AND TECHNICAL CRITERIA TABLE OF CONTENTS Section Title Page 16.1 General... 16-1 16.1.1 AASHTO Reference... 16-1 16.1.2 ADA Requirements... 16-1 16.2 Sidewalks...

More information

Final Sidewalk Feasibility Study

Final Sidewalk Feasibility Study Garfield Drive From Anastasia Drive to Elizabeth Place City of South Daytona July 23, 2009 Final Sidewalk Feasibility Study Prepared for: Prepared by: Final Sidewalk Feasibility Study Garfield Drive 2

More information

St. Francis Drive through the City of Santa Fe Corridor Study

St. Francis Drive through the City of Santa Fe Corridor Study VII. ENGINEERING AND ENVIRONMENTAL EVALUATION TRAIL CONNECTIVITY In the southern portion of the Corridor there is a lack of a sidewalk, trail or bicycle facility within the right-ofway. However, the City

More information

Building Great Neighbourhoods BELLEVUE AND VIRGINIA PARK

Building Great Neighbourhoods BELLEVUE AND VIRGINIA PARK Building Great Neighbourhoods BELLEVUE AND VIRGINIA PARK This is Meeting 2 Unfortunately, some residents in Bellevue and Virginia Park received the wrong information for this public open house (Meeting

More information

MAG Town of Cave Creek Bike Study Task 6 Executive Summary and Regional Significance Report

MAG Town of Cave Creek Bike Study Task 6 Executive Summary and Regional Significance Report Page 1 MAG Town of Cave Creek Bike Study Task 6 Executive Summary and Regional Significance Report August 1, 2012 MAG Project #481 Page 2 Task 6 Executive Summary and Regional Significance Report Introduction

More information

CONNECTIVITY PLAN. Adopted December 5, 2017 City of Virginia Beach

CONNECTIVITY PLAN. Adopted December 5, 2017 City of Virginia Beach CONNECTIVITY PLAN Adopted December 5, 2017 City of Virginia Beach CONTENTS 1.0 Background & Purpose... 2 2.0 Existing Inventory & Analysis... 3 ViBe District Existing Walking Conditions... 4 3.0 ViBe District

More information

Duwamish Way-finding and CTR Report

Duwamish Way-finding and CTR Report V. North Tukwila When the North Tukwila Manufacturing and Industrial Center was designated in 1992 as part of the region s land use and transportation plan, the plan called for the area to set a light-rail

More information

TRANSPORTATION COMMISSION Agenda Staff Report

TRANSPORTATION COMMISSION Agenda Staff Report TRANSPORTATION COMMISSION Agenda Staff Report Agenda Item No. 5.a DATE: JULY 31, 2014 TO: FROM: SUBJECT: TRANSPORTATION COMMISSION COMMUNITY DEVELOPMENT DEPARTMENT - PLANNING DRAFT OLYMPIC CORRIDOR PREFERRED

More information

Omaha s Complete Streets Policy

Omaha s Complete Streets Policy Omaha s Complete Streets Policy (Adopted August 2015) VISION To create great places and enhance our quality of life, the City of Omaha will provide safe, accessible streets for all users. Complete Streets

More information

Safe Routes to School Action Plan Aberdeen, Idaho

Safe Routes to School Action Plan Aberdeen, Idaho Background Aberdeen, Idaho is a largely agricultural community of nearly 2,000 people and is located in the southeast portion of the state on the western edge of American Falls Reservoir. The community

More information

Corpus Christi Metropolitan Transportation Plan Fiscal Year Introduction:

Corpus Christi Metropolitan Transportation Plan Fiscal Year Introduction: Introduction: The Safe, Accountable, Flexible, Efficient Transportation Equity Act: A Legacy for Users (SAFETEA-LU) has continued the efforts started through the Intermodal Surface Transportation Efficiency

More information

Poor pavement condition Substandard Intersections. / Substandard bike/pedestrian/transit accommodations. Driveway access Environmental concerns

Poor pavement condition Substandard Intersections. / Substandard bike/pedestrian/transit accommodations. Driveway access Environmental concerns Public Informational Meeting University Avenue (Allen Boulevard Segoe Road) March 23, 2011 City of Madison City of Middleton Village of Shorewood Hills Dane County Existing Roadway Conditions Poor pavement

More information

Item No. 14 Town of Atherton

Item No. 14 Town of Atherton Item No. 14 Town of Atherton CITY COUNCIL STAFF REPORT CONSENT AGENDA TO: THROUGH: FROM: HONORABLE MAYOR AND CITY COUNCIL GEORGE RODERICKS, CITY MANAGER MICHAEL KASHIWAGI, COMMUNITY SERVICES DIRECTOR MARTY

More information

Active Transportation Facility Glossary

Active Transportation Facility Glossary Active Transportation Facility Glossary This document defines different active transportation facilities and suggests appropriate corridor types. Click on a facility type to jump to its definition. Bike

More information

Bluffdale/ UDOT South High-T Intersection Project Type Operations

Bluffdale/ UDOT South High-T Intersection Project Type Operations Bluffdale/ UDOT 14600 South High-T Intersection Project Type Operations 14600 South and Redwood Road $ 600,000 $ 550,000 This project is to install a new High-T intersection at Redwood Road and 14600 South

More information

WHEREAS delivery trucks also pass through the Narrows, into the northern parking lot, to loading docks in the back of the building.

WHEREAS delivery trucks also pass through the Narrows, into the northern parking lot, to loading docks in the back of the building. CEDAR-ISLES-DEAN NEIGHBORHOOD ASSOCIATION ( CIDNA ) RESOLUTION OPPOSING A DRUG STORE DRIVE THRU, AND COMMENDING DORAN COMPANIES FOR PROPOSING MITIGATING AMENITIES INCLUDING NEW LANDSCAPING AND A DEDICATED

More information

5 CIRCULATION AND STREET DESIGN

5 CIRCULATION AND STREET DESIGN 5 CIRCULATION AND STREET DESIGN This chapter describes circulation and streetscape improvements proposed for the Northwest Chico Specific Plan Area. It includes detailed design specifications for existing

More information

Appendix T CCMP TRAIL TRAFFIC & TRANSPORTATION DESIGN STANDARD

Appendix T CCMP TRAIL TRAFFIC & TRANSPORTATION DESIGN STANDARD Appendix T CCMP 3.3.4 TRAIL TRAFFIC & TRANSPORTATION DESIGN STANDARD 3.3.4 Trail Traffic and Transportation Design Multi-use trails have certain design standards, which vary depending on the agency that

More information

Chapter 3 DESIGN SPECIFICATIONS

Chapter 3 DESIGN SPECIFICATIONS Brampton PathWays Planning and Design Guidelines 27 Chapter 3 DESIGN SPECIFICATIONS 3.1 CLASS 1 MULTI-USE PATH Off-road multi-use trails are the backbone of the Brampton PathWays Network. They are typically

More information

Chapter 5 Future Transportation

Chapter 5 Future Transportation Chapter 5 Future Transportation The Future Land Use Plan identifies the desired land use designations. The land uses desired for Crozet depend, in large part, on the success of the transportation system,

More information

DRAFT. Scholls Ferry Road Conceptual Design Plan Technical Memorandum Multi-Modal Examples. Multnomah County 1600 SE 190th Avenue Portland, OR 97233

DRAFT. Scholls Ferry Road Conceptual Design Plan Technical Memorandum Multi-Modal Examples. Multnomah County 1600 SE 190th Avenue Portland, OR 97233 Technical Memorandum Multi-Modal Examples Prepared for 1600 SE 190th Avenue Portland, OR 97233 December 2008 CITATION This project is partially funded by a grant from the Transportation and Growth Management

More information

FOCUS AREA 1 - Alberta Avenue Pocket Park 3 (121 Ave and 92 St)

FOCUS AREA 1 - Alberta Avenue Pocket Park 3 (121 Ave and 92 St) FOCUS AREA 1 - Alberta Avenue Pocket Park 3 (121 Ave and 92 St) New benches Plant evergreen trees Widen existing sidewalk from 1.5m to 1.8m Marked crosswalk 1.8m wide sidewalk Add pedestrian oriented lights

More information

APPENDIX A: Complete Streets Checklist DRAFT NOVEMBER 2016

APPENDIX A: Complete Streets Checklist DRAFT NOVEMBER 2016 APPENDIX A: Complete Streets Checklist DRAFT NOVEMBER 2016 Complete Streets Checklist MetroPlan Orlando s Complete Streets Checklist is an internal planning tool for staff to further implementation of

More information

Off-road Trails. Guidance

Off-road Trails. Guidance Off-road Trails Off-road trails are shared use paths located on an independent alignment that provide two-way travel for people walking, bicycling, and other non-motorized users. Trails specifically along

More information

01. VICINITY OF GREENBRAE POC: EXISTING CONDITIONS

01. VICINITY OF GREENBRAE POC: EXISTING CONDITIONS 01. VICINITY OF GREENBRAE POC: EXISTING CONDITIONS Existing Bus Stop Existing US101 On-ramp Existing POC Old Redwood Highway Rich Street City ROW Environmental Study Limit Industrial Way NO DESIGNATED

More information

ACTIVE TRANSPORTATION

ACTIVE TRANSPORTATION ACTIVE TRANSPORTATION Mobility 2040 Supported Goals Improve the availability of transportation options for people and goods. Support travel efficiency measures and system enhancements targeted at congestion

More information

Readington Road (C.R. 637) Construction

Readington Road (C.R. 637) Construction Public Information Meeting Thursday, August 2, 2012 Readington Road (C.R. 637) Construction from Dreahook Road to Harlan School Road Branchburg Township, Somerset County Readington Township, Hunterdon

More information

City of Margate, Florida. Neighborhood Traffic Management Manual

City of Margate, Florida. Neighborhood Traffic Management Manual City of Margate, Florida Neighborhood Traffic Management Manual Table of Contents Page No. I. INTRODUCTION... 1 II. TRAFFIC CALMING REQUEST AND PROCESSING PROCEDURES... 2 1. COMPLETE AND SUBMIT PROJECT

More information

DRAFT. System Components. Greenway Trails. Introduction. Trail Types. Zebulon Greenway Master Plan

DRAFT. System Components. Greenway Trails. Introduction. Trail Types. Zebulon Greenway Master Plan 5 System Components Wakefield Street Photo Simulation showing Sharrows Introduction The Master Plan identifies various system components that, together, create a comprehensive greenway system. These components

More information

Bikeway action plan. Bicycle Friendly Community Workshop March 5, 2007 Rochester, MN

Bikeway action plan. Bicycle Friendly Community Workshop March 5, 2007 Rochester, MN Bikeway action plan Summary The was held on March 5, 2007 at the Rochester Mayo Civic Center. The workshop was hosted by Rochester-Olmsted County Planning Department in collaboration with the League of

More information

West Dimond Blvd Upgrade Jodhpur Street to Sand Lake Road

West Dimond Blvd Upgrade Jodhpur Street to Sand Lake Road West Dimond Blvd Jodhpur St to Sand Lake CSS Transportation Project Summary Municipality of Anchorage Project # 05 005 Project Manager: John Smith, P.E. (MOA PM&E) Project Administrator: Julie Makela,

More information

Bicycle and Pedestrian Facilities Toolbox (Excerpt from Figure 3.1)

Bicycle and Pedestrian Facilities Toolbox (Excerpt from Figure 3.1) Appendix B Neighborhood Connections Summaries This Appendix is a supplement to the information presented in Chapter 3 Connect People. The Appendix includes a summary or profile for each of the proposed

More information

Figure 4-10: Pedestrian Improvements Types of Potential Station Area Improvements - Place-Making Improvements

Figure 4-10: Pedestrian Improvements Types of Potential Station Area Improvements - Place-Making Improvements INCORPORATE FEATURE PAVIN IN CROSSWALK AND INTERSECTION FIELDS Identifies high-priority pedestrian areas and create a station identity through colorful and interesting patterns ADD CURB EXTENSIONS Extending

More information

CITY MANUALS AND STANDARDS REVIEW

CITY MANUALS AND STANDARDS REVIEW GEORGETOWN SIDEWALK MASTER PLAN CITY MANUALS AND STANDARDS REVIEW RESOURCES AND STANDARDS As part of the Master Plan process, a review and evaluation of current City documents and policies relevant to

More information

Chapter 3: Multi-Modal Circulation and Streetscapes

Chapter 3: Multi-Modal Circulation and Streetscapes CHAPTER 3: MULTI-MODAL CIRCULATION AND STREETSCAPES Chapter 3: Multi-Modal Circulation and Streetscapes Overview Streetscape improvements have already been completed for Depot Street between Main Avenue

More information

STEERING COMMITTEE MEETING June 17, Streetscape Overview Burlington Comprehensive Master Plan

STEERING COMMITTEE MEETING June 17, Streetscape Overview Burlington Comprehensive Master Plan STEERING COMMITTEE MEETING June 17, 2015 Streetscape Overview Burlington Comprehensive Master Plan 1 Introduction Slide This slide show was presented to the Burlington Steering Committee on June 17, 2015

More information

CITY OF COCOA BEACH 2025 COMPREHENSIVE PLAN. Section VIII Mobility Element Goals, Objectives, and Policies

CITY OF COCOA BEACH 2025 COMPREHENSIVE PLAN. Section VIII Mobility Element Goals, Objectives, and Policies CITY OF COCOA BEACH 2025 COMPREHENSIVE PLAN Section VIII Mobility Element Goals, Objectives, and Policies Adopted August 6, 2015 by Ordinance No. 1591 VIII MOBILITY ELEMENT Table of Contents Page Number

More information

Construction Specifications Manual

Construction Specifications Manual Isle of Wight County Pedestrian and Bicycle Master Plan Construction Specifications Manual Adopted August 20, 2009 Introduction The Isle of Wight County Pedestrian and Bicycle Facilities Master Plan was

More information

Solana Beach Comprehensive Active Transportation Strategy (CATS)

Solana Beach Comprehensive Active Transportation Strategy (CATS) Solana Beach Comprehensive Active Transportation Strategy (CATS) 3.0 Goals & Policies The Solana Beach CATS goals and objectives outlined below were largely drawn from the Solana Beach Circulation Element

More information

See Figure 38, Existing Nonmotorized Connections.

See Figure 38, Existing Nonmotorized Connections. Nonmotorized Connections Existing Nonmotorized Connections Pedestrian, vehicle and bike traffic access and movements are confined primarily to Penny Drive on campus. Due to the steep slope along the length

More information

o n - m o t o r i z e d transportation is an overlooked element that can greatly enhance the overall quality of life for the community s residents.

o n - m o t o r i z e d transportation is an overlooked element that can greatly enhance the overall quality of life for the community s residents. N o n - m o t o r i z e d transportation is an overlooked element that can greatly enhance the overall quality of life for the community s residents. 84 Transportation CHAPTER 11 INTRODUCTION Transportation

More information

Complete Streets Policy DAVID CRONIN, P.E., CITY ENGINEER

Complete Streets Policy DAVID CRONIN, P.E., CITY ENGINEER Complete Streets Policy DAVID CRONIN, P.E., CITY ENGINEER Complete Streets City Commission adopted a Complete Streets policy in 2012 Complete Streets are road networks that are designed for all users:

More information

Houma-Thibodaux Metropolitan Planning Organization STP<200K Funding Application APPLICATION

Houma-Thibodaux Metropolitan Planning Organization STP<200K Funding Application APPLICATION APPLICATION HOUMA-THIBODAUX METROPOLITAN PLANNING ORGANIZATION (HTMPO) FOR SURFACE TRANSPORTATION PROGRAM (STP

More information

NM-POLICY 1: Improve service levels, participation, and options for non-motorized transportation modes throughout the County.

NM-POLICY 1: Improve service levels, participation, and options for non-motorized transportation modes throughout the County. Transportation PRINCE WILLIAM COUNTY 2008 COMPREHENSIVE PLAN NON-MOTORIZED PLAN CONTENTS Goals, Policies, and Action Strategies Table 4 (Bike Facility Classifications and Descriptions) Table 5 (Bike Facility

More information

City of Gainesville Transportation/Roadway Needs PROJECT SUMMARY

City of Gainesville Transportation/Roadway Needs PROJECT SUMMARY A1 Roadway Resurfacing $23,846,000 TYPE: Preservation of existing system Roadway resurfacing A2 Signal Replacement $6,000,000 TYPE: Preservation of existing system Replace traffic signals. B1 W 6th St

More information

Executive Summary Route 30 Corridor Master Plan

Executive Summary Route 30 Corridor Master Plan Route Corridor Master Plan Project Overview The Route Corridor Master Plan is a coordinated multimodal transportation and land use plan for the entire stretch of Route through East Whiteland Township,

More information

Building Great Neighbourhoods QUEEN ALEXANDRA

Building Great Neighbourhoods QUEEN ALEXANDRA Building Great Neighbourhoods QUEEN ALEXANDRA We are here today to Explain how the City is investing in improving your neighbourhood and how your neighbourhood will be improved to meet current City standards.

More information

East Burke Transportation, Safety and Capacity Improvements

East Burke Transportation, Safety and Capacity Improvements East Burke Transportation, Safety and Capacity Improvements The purpose of this project is to increase mobility and improve safety for pedestrians, cyclists, and motor vehicles along VT Route 114 in the

More information

Appendix 3 Roadway and Bike/Ped Design Standards

Appendix 3 Roadway and Bike/Ped Design Standards Appendix 3 Roadway and Bike/Ped Design Standards OTO Transportation Plan 2040 4/20/2017 Page A3-1 Adopted Standards The adopted OTO Design Standards and Major Thoroughfare Plan are contained herein.

More information

Americans with Disabilities Act Transition Plan for Public Right-of-Way Improvements

Americans with Disabilities Act Transition Plan for Public Right-of-Way Improvements Americans with Disabilities Act Transition Plan for Public Right-of-Way Improvements Prepared by: Public Works Department Engineering Division October 2015 Table of Contents Section I Introduction.. 3

More information

City of Davis East Covell Corridor Plan

City of Davis East Covell Corridor Plan Community Open House #2 January 22, 2014 6:00 8:00 p.m. Veterans Memorial Center, Club Room City of Davis Introduction The (ECCP) is a taking a comprehensive look at the existing transportation systems

More information

Driveway Design Criteria

Driveway Design Criteria Design Manual Chapter 5 - Roadway Design 5L - Access Management 5L-4 Driveway Design Criteria A. General For efficient and safe operations, access drives and minor public street intersections can be improved

More information

ADA Transition Plan. City of Gainesville FY19-FY28. Date: November 5, Prepared by: City Of Gainesville Department of Mobility

ADA Transition Plan. City of Gainesville FY19-FY28. Date: November 5, Prepared by: City Of Gainesville Department of Mobility ADA Transition Plan FY19-FY28 Date: November 5, 2018 Prepared by: City Of Gainesville Department of Mobility 1.0 INTRODUCTION 1.1 BACKGROUND The federal statute known as the Americans with Disabilities

More information

APPENDIX 2 LAKESHORE ROAD TRANSPORTATION REVIEW STUDY EXECUTIVE SUMMARY

APPENDIX 2 LAKESHORE ROAD TRANSPORTATION REVIEW STUDY EXECUTIVE SUMMARY APPENDIX 2 LAKESHORE ROAD TRANSPORTATION REVIEW STUDY EXECUTIVE SUMMARY Appendix 2 City of Mississauga Lakeshore Road FINAL REPORT Transportation Review Study December 2010 EXECUTIVE SUMMARY Study Purpose

More information

COWETA HIGH SCHOOL AND EAST HIGHWAY 51

COWETA HIGH SCHOOL AND EAST HIGHWAY 51 COWETA HIGH SCHOOL AND EAST HIGHWAY 51 Lack of sidewalks along Ben Lumpkin Rd. Lack of crosswalks and ramps at intersection. Hwy 51 is wide to cross as a pedestrian. No ADA compliance or connection to

More information

Orange Center Elementary School

Orange Center Elementary School Drag and drop pic and stretch/crop to the limits of the blue rectangle (delete this text box) Orange Center Elementary School Drag and drop pic and stretch/crop to the limits of the blue rectangle (delete

More information

C C C

C C C C-012-001 Thank you for your support for the creation of new public space and nonmotorized access between downtown and the waterfront through the Overlook Walk, the East-West Connections, and the Promenade.

More information

Henderson Ave. Complete Streets Project

Henderson Ave. Complete Streets Project Henderson Ave. Complete Streets Project Meeting Purpose To finalize conceptual components of project prior to proceeding with preliminary engineering www.dallascompletestreets.wordpress.com MeetingAgenda

More information

DRAFT. A fifth objective, other considerations, has been added to capture considerations not captured by the four primary objectives.

DRAFT. A fifth objective, other considerations, has been added to capture considerations not captured by the four primary objectives. TECHNICAL MEMORANDUM Albany - Washington Avenue Traffic Calming Evaluation Matrix of Conceptual Alternatives Date: May 17, 2017 Project #: 17356 To: Aleida Andrino-Chavez From: Laurence Lewis, Sara Muse,

More information

What Is a Complete Street?

What Is a Complete Street? Session 5 Charleen Zimmer, AICP, Zan Associates May 5-7, 2010 What Is a Complete Street? May 2010 5-1 Not a Complete Street More of a Complete Street May 2010 5-2 Benefits of Complete Streets Safety for

More information

Roadway Classification Design Standards and Policies. Pueblo, Colorado November, 2004

Roadway Classification Design Standards and Policies. Pueblo, Colorado November, 2004 Roadway Classification Design Standards and Policies Pueblo, Colorado November, 2004 Table of Contents Page Chapter 1. General Provisions 1.1 Jurisdiction 3 1.2 Purpose and Intent 3 1.3 Modification 3

More information

Multi-Modal Traffic Analysis. Parisi and Associates

Multi-Modal Traffic Analysis. Parisi and Associates Mill Valley to Corte Madera Bicycle and Pedestrian Corridor Study Appendix D: Multi-Modal Traffic Analysis Prepared by Parisi and Associates August 2009 Appendix D - Multi-Modal Traffic Analysis Table

More information

AGENDA REPORT. Issue: Discussion of potential improvements on Barnwell Road at Niblick Drive

AGENDA REPORT. Issue: Discussion of potential improvements on Barnwell Road at Niblick Drive AGENDA REPORT To: From: By: Honorable Mayor and City Council Members Warren Hutmacher, City Manager Tom Black, Public Works Director Date: March 23, 2016 Agenda: March 28, 2016 WORK SESSION AGENDA: Barnwell

More information

Alberta Infrastructure HIGHWAY GEOMETRIC DESIGN GUIDE AUGUST 1999

Alberta Infrastructure HIGHWAY GEOMETRIC DESIGN GUIDE AUGUST 1999 Alberta Infrastructure HIGHWAY GEOMETRIC DESIGN GUIDE AUGUST 1999,1'(; A ACCELERATION Data on acceleration from stop D-29 Effects of grade D-35 Intersections D-97, D-99 Lanes D-97, F-5, F-7, F-15, F-21,

More information

ENGINEERING AND PUBLIC WORKS. Transportation Improvements: Santa s Village Road (MR15) Public Meeting

ENGINEERING AND PUBLIC WORKS. Transportation Improvements: Santa s Village Road (MR15) Public Meeting ENGINEERING AND PUBLIC WORKS Transportation Improvements: Santa s Village Road (MR15) Public Meeting March 22, 2018 Agenda Welcome and Introductions Fred Jahn: Commissioner of Engineering and Public Works

More information

Fulton Market Streetscape

Fulton Market Streetscape Fulton Market Streetscape Ogden Avenue to Halsted Street Public Meeting Recommended Improvements December 10th, 2014 Meeting Purpose and Goals Present Existing Conditions Community Input and Charrette

More information

Appendix C. TRAFFIC CALMING PROGRAM TOOLBOX

Appendix C. TRAFFIC CALMING PROGRAM TOOLBOX Appendix C. TRAFFIC CALMING PROGRAM TOOLBOX PHASE I...2 Do Not Enter Sign...3 One-Way Sign...4 Turn Prohibition...5 Pavement Markings...6 Speed Monitoring Trailer...7 Neighborhood Speed Watch...8 Police

More information

City of Novi Non-Motorized Master Plan 2011 Executive Summary

City of Novi Non-Motorized Master Plan 2011 Executive Summary City of Novi Non-Motorized Master Plan 2011 Executive Summary Prepared by: February 28, 2011 Why Plan? Encouraging healthy, active lifestyles through pathway and sidewalk connectivity has been a focus

More information

Third Street Bridge & Corridor Project

Third Street Bridge & Corridor Project Third Street Bridge & Corridor Project Preparation for the FY2018 budget to commence October 1, 2017, includes funding to address a project that has been considered since 1994. The Third Street bridge

More information

Building Great Neighbourhoods BONNIE DOON

Building Great Neighbourhoods BONNIE DOON Building Great Neighbourhoods BONNIE DOON We Are Here Today To Explain the Neighbourhood Renewal Process Show you the Westwood Preliminary Design Ask for local knowledge Highlight the Local Improvement

More information

Chapter 2: Standards for Access, Non-Motorized, and Transit

Chapter 2: Standards for Access, Non-Motorized, and Transit Standards for Access, Non-Motorized, and Transit Chapter 2: Standards for Access, Non-Motorized, and Transit The Washtenaw County Access Management Plan was developed based on the analysis of existing

More information

EXECUTIVE SUMMARY. Vision

EXECUTIVE SUMMARY. Vision Vision Walking and bicycling in Salt Lake City will be safe, convenient, comfortable, and viable transportation options that connect people to places, foster recreational and economic development opportunities,

More information

Building Great Neighbourhoods LANSDOWNE

Building Great Neighbourhoods LANSDOWNE Building Great Neighbourhoods LANSDOWNE We are here today to Explain how the City is investing in improving your neighbourhood and how your neighbourhood will be improved to meet current City standards.

More information

This Chapter sets forth the minimum design, technical criteria and specifications to be used in the preparation of all roadway plans.

This Chapter sets forth the minimum design, technical criteria and specifications to be used in the preparation of all roadway plans. 4.1 GENERAL This Chapter sets forth the minimum design, technical criteria and specifications to be used in the preparation of all roadway plans. These Roadway Standards are for new construction and modification

More information

David Hung, Associate Planner City of Sacramento Community Development Department 300 Richards Boulevard, 3 rd Floor Sacramento, CA

David Hung, Associate Planner City of Sacramento Community Development Department 300 Richards Boulevard, 3 rd Floor Sacramento, CA June 13, 2016 VIA EMAIL David Hung, Associate Planner City of Sacramento Community Development Department 300 Richards Boulevard, 3 rd Floor Sacramento, CA 959811 RE: Fire Station 14 (DR16-128) Dear Mr.

More information

TRAFFIC CALMING GUIDE FOR TORONTO CITY OF TORONTO TRANSPORTATION SERVICES DIVISION

TRAFFIC CALMING GUIDE FOR TORONTO CITY OF TORONTO TRANSPORTATION SERVICES DIVISION TRAFFIC CALMING GUIDE FOR TORONTO CITY OF TORONTO TRANSPORTATION SERVICES DIVISION CITY OF TORONTO TRANSPORTATION SERVICES DIVISION 2016 TRAFFIC CALMING GUIDE FOR TORONTO TABLE OF CONTENTS Introduction

More information

5. RUNNINGWAY GUIDELINES

5. RUNNINGWAY GUIDELINES 5. RUNNINGWAY GUIDELINES These guidelines should be considered collectively when making runningway decisions. A runningway is the linear component of the transit system that forms the right-of-way reserved

More information

CURBSIDE ACTIVITY DESIGN

CURBSIDE ACTIVITY DESIGN 5 CURBSIDE ACTIVITY DESIGN This chapter provides design guidance for separated bike lanes adjacent to curbside activities including parking, loading and bus stops. Typical configurations are presented

More information

Tonight is for you. Learn everything you can. Share all your ideas.

Tonight is for you. Learn everything you can. Share all your ideas. Strathcona Neighbourhood Renewal Draft Concept Design Tonight is for you. Learn everything you can. Share all your ideas. What is Neighbourhood Renewal? Creating a design with you for your neighbourhood.

More information

A. Arlington County Master Transportation Plan Pedestrian Element B. Arlington County Horizontal Standards H-3.1 Driveway Entrances

A. Arlington County Master Transportation Plan Pedestrian Element B. Arlington County Horizontal Standards H-3.1 Driveway Entrances GENERAL 1. Description This standard identifies minimum requirements that shall be met for all accessible ramps in the design and construction of elements for Arlington County Horizontal Design Standards.

More information

TO: Board Members Vancouver Park Board FROM: General Manager Parks and Recreation SUBJECT: Seaside Greenway Improvements

TO: Board Members Vancouver Park Board FROM: General Manager Parks and Recreation SUBJECT: Seaside Greenway Improvements Date: October 1, 2013 TO: Board Members Vancouver Park Board FROM: General Manager Parks and Recreation SUBJECT: Seaside Greenway Improvements RECOMMENDATION A. THAT the Board approve the new bike paths

More information

Item to be Addressed Checklist Consideration YES NO N/A Required Description Complete Streets Guidelines

Item to be Addressed Checklist Consideration YES NO N/A Required Description Complete Streets Guidelines Passaic County Complete Streets Checklist - Concept Development Project Name Item to be Addressed Checklist Consideration YES NO N/A Required Description Complete Streets Guidelines Existing Plans Have

More information

CONNECTING PEOPLE TO PLACES

CONNECTING PEOPLE TO PLACES CONNECTING PEOPLE TO PLACES 82 EAST BENCH MASTER PLAN 07 Introduction The East Bench transportation system is a collection of slow moving, treelined residential streets and major arteries that are the

More information

DRAFT - CITY OF MEDFORD TRANSPORTATION SYSTEM PLAN Roadway Cross-Sections

DRAFT - CITY OF MEDFORD TRANSPORTATION SYSTEM PLAN Roadway Cross-Sections Roadway Cross-Sections Medford s roadway cross-section standards apply to new and reconstructed roads. The crosssections take into consideration roadway function and operational characteristics, including

More information

Long Island Rail Road Expansion Project Floral Park to Hicksville

Long Island Rail Road Expansion Project Floral Park to Hicksville Long Island Rail Road Expansion Project Floral Park to Hicksville Final Environmental Impact Statement Appendix 1-D Complete Streets Policy Checklist April 2017 0902ML PIN: Project Location: 18A-4 Floral

More information

5 Circulation & Parking

5 Circulation & Parking 5 Circulation & Parking Downtown Parking & Circulation Strategy. Downtown Wayne has a somewhat disconnected system of local public streets to connect downtown with the residential neighborhoods, and primary

More information

NJDOT Complete Streets Checklist

NJDOT Complete Streets Checklist Background The New Jersey Department of Transportation s Complete Streets Policy promotes a comprehensive, integrated, connected multi-modal network by providing connections to bicycling and walking trip

More information

Outreach Approach RENEW SF served as the primary liaison with the North Beach community; the Chinatown. Executive Summary

Outreach Approach RENEW SF served as the primary liaison with the North Beach community; the Chinatown. Executive Summary Executive Summary Executive Summary The Columbus Avenue Neighborhood Transportation Study s objective is to identify changes to transportation infrastructure and policies that could enhance the livability

More information

PEDESTRIAN ACTION PLAN

PEDESTRIAN ACTION PLAN ATTACHMENT 2 CITY OF SANTA MONICA PEDESTRIAN ACTION PLAN CITY OF SANTA MONICA PEDESTRIAN ACTION PLAN This page intentionally left blank EXECUTIVE SUMMARY CHAPTER 1 EXECUTIVE SUMMARY Setting the Stage

More information

ADA TRANSITION PLAN 2013

ADA TRANSITION PLAN 2013 ADA TRANSITION PLAN 2013 TABLE OF CONTENTS Contents Introduction 1 Purpose 2 Identified Obstacles to the Public Right of Way 3 Criteria for Determining Impediments at Village Facilities 4 Removing Barriers

More information

CITY OF KASSON TRANSPORTATION ALTERNATIVES KASSON SAFE ROUTES TO SCHOOL

CITY OF KASSON TRANSPORTATION ALTERNATIVES KASSON SAFE ROUTES TO SCHOOL ve ha 8t G B A Mantorville Ave N 240th Ave 16th St NE 11th Ave NE K-M HIGH SCHOOL SUNRISE TRAIL TO MANTORVILLE MNTH 57 SUNSET TRAIL TO MANTORVILLE NE PARK 16TH ST NE TRAIL K-M ELEMENTARY SCHOOL K-M MIDDLE

More information

City of Madison, East Johnson Street North Baldwin Street to First Street Local Street Dane County

City of Madison, East Johnson Street North Baldwin Street to First Street Local Street Dane County City of Madison, East Johnson Street North Baldwin Street to First Street Local Street Dane County Public Involvement Meeting Thursday, November 10, 2016 5:30 to 7 P.M. Festival Foods 810 E. Washington

More information

section 4 Existing Conditions, Issues, and Options

section 4 Existing Conditions, Issues, and Options section 4 Existing Conditions, Issues, and Options 4.0 Existing Conditions, Issues, and Options This section analyzes each segment of the corridor on a street to street basis. Each segment is discussed

More information

Exhibit 1 PLANNING COMMISSION AGENDA ITEM

Exhibit 1 PLANNING COMMISSION AGENDA ITEM Exhibit 1 PLANNING COMMISSION AGENDA ITEM Project Name: Grand Junction Circulation Plan Grand Junction Complete Streets Policy Applicant: City of Grand Junction Representative: David Thornton Address:

More information