FRONT RANGE CROSSINGS TRAFFIC IMPACT STUDY
|
|
- Arlene Watson
- 5 years ago
- Views:
Transcription
1 FRONT RANGE CROSSINGS TRAFFIC IMPACT STUDY Prepared for: City of Thornton And Colorado Department of Transportation Prepared by: 11 Blake Street, Suite 2 Denver, Colorado 822 Contact: Brian Bern, PE, PTOE (33) 72 2 On Behalf of: SWVP Noddle 228 S. 7 th Street, Suite 2 Omaha, NE 81 July 27, 218
2
3 F RONT RANGE CROSSINGS Table of Contents Background Information... 1 General Existing Traffic Conditions... 7 Roadway Network... 7 Traffic Volumes... 8 Intersection and Roadway Capacity Analysis... 9 Development Site Characteristic Site Access Trip Generation Trip Generation Comparison: Trip Distribution Trip Distribution with 12 nd Avenue Connected to Trip Distribution without 12 nd Avenue connected to Traffic Assignments and Off Site Traffic Analysis Roadway Improvements Roadway Improvements... 3 Future 223 Background Traffic Future 238 Background Traffic Traffic Analysis... 2 Background Traffic... 2 Total Traffic... 2 Level of Service Analysis Traffic Analysis with 12 nd Ave Connected to... 4 Background Traffic... 4 Total Traffic... 4 Level of Service Analysis Traffic Analysis without 12 nd Ave Connected to Background Traffic Total Traffic Level of Service Analysis Findings and Recommendations Conclusion i
4 Appendices: F RONT RANGE CROSSINGS A. Existing 218 Traffic Counts B. 218 Level of Service Output Existing Traffic C. ITE Internal Capture Output D. 223 Background Traffic Analysis Output E. 223 Total Traffic Analysis Output F. 238 Background Traffic Analysis Output G. 238 Total Traffic with 12 nd Ave Connection to Analysis Output H. 238 Total Traffic without 12 nd Ave Connection to Analysis Output I. Traffic Signal Warrant Calculations List of Figures Figure 1 Vicinity Map... 4 Figure 2 Existing Roadway Characteristics... Figure 3 Existing Intersection Geometry... Figure Weekday Exist Traffic... 1 Figure 218 Saturday Exist Traffic... 1 Figure Site Plan Figure Trip Distribution Figure Trip Percentages Figure Weekday Site Traffic... 2 Figure Saturday Site Traffic... 2 Figure Trip Distribution Figure Trip Percentages with 12 nd Ave Connected to Figure Weekday Site Traffic with 12 nd Ave Connected to Figure Saturday Site Traffic with 12 nd Ave Connected to... 3 Figure Trip Percentages without 12 nd Ave Connected to Figure Weekday Site Traffic without 12 nd Ave Connected to Figure Saturday Site Traffic without 12 nd Ave Connected to Figure Intersection Spacing Figure Intersection Geometry... 4 Figure Weekday Background Traffic... 4 Figure Saturday Background Traffic Figure Intersection Spacing Figure Intersection Geometry Figure Weekday Background Traffic... Figure Saturday Background Traffic... 1 Figure Weekday Total Traffic... 2 Figure PM Total Traffic... 3 Figure Weekday Total Traffic with 12 nd Ave Connected to Figure Saturday Total Traffic with 12 nd Ave Connected to... 8 Figure Weekday Total Traffic without 12 nd Ave Connected to Figure Saturday Total Traffic without 12 nd Ave connected to... 9 ii
5 F RONT RANGE CROSSINGS List of Tables Table 1 Signalized Intersection Level of Service Criteria... 9 Table 2 Unsignalized Intersection Level of Service Criteria... 1 Table 3 Roadway Level of Service Thresholds by Functional Classification... 1 Table Existing Traffic Level of Service Table 218 Existing Traffic Progression Summary Table ITE Land Use Codes Table 7 Trip Generation Table 8 Full Build out Trip Generation by TAZ Table 9 Trip Generation: Front Range Crossings vs Transportation Master Plan... 2 Table Trip Generation of Adjacent Properties Table Trip Generation of Adjacent Properties Table Background Traffic Level of Service... 2 Table Background Traffic Progression Summary... Table Total Traffic Level of Service... Table Total Traffic Progression Analysis... 1 Table Background Traffic Level of Service... Table Background Traffic Progression Summary... 7 Table Total Traffic Level of Service w/ 12 nd Ave Connected to Table Total Traffic Progression Summary w/ 12 nd Ave Connected to Table Total Traffic Level of Service w/o 12 nd Ave Connected to Table Total Traffic Progression Summary w/o 12 nd Ave Connected to iii
6 Background Information F RONT RANGE CROSSINGS The Front Range Crossings development is located within two undeveloped parcels of land partly in the City of Thornton and partly in unincorporated Adams County, Colorado that is going through the annexation process. A brief description of each parcel is listed below. The Northeast Parcel is almost 128 acres located south of 14 th Ave, west of SH 7, north of 1 th Ave., and east of reet. The Northwest Parcel is proposed as a mixed use development with 1,, square feet of office, 12, square feet of retail, and 42 dwelling units of apartments. The Southwest Parcel is a little over 8 acres located south of 1 th Ave, west of Washington Street, north of E 47, and east of I 2. The Southwest Parcel is proposed as entirely office with 1,14, square feet. Development of the project is anticipated to be phased. The portion northwest of State Highway 7 and 12 nd Avenue is expected to develop first with build out of this portion expected to occur by 223. The rest of the development is anticipated to have a slower absorption rate and reach full build out by 238. Subsequent traffic studies will be needed in the future if portions of the project are built out in phases to determine necessary improvements by phase. The purpose of this Traffic Impact Study (TIS) is to assess the effects that the development traffic may have on the City of Thornton s transportation network and to support the entitlement process. See Figure 1 for the location of the proposed development and the nearby existing and future land uses. Figure illustrates the proposed site plan. A brief description of the adjacent roadway characteristics is presented below. General roadway segment laneage, intersection spacing, and locations of existing traffic signals can be seen in Figure 2. Specific intersection lane geometry can be seen in Figure 3. Intersection turn lane storage lengths are included in the level of service analysis tables later in this TIS. 1 th Avenue Currently a minor arterial roadway consisting of one 11 lane in each direction with no raised median, no curb and gutter, no bike lanes, and no sidewalks. The roadway has a posted speed limit of 4 MPH west of reet and 4 MPH east of reet. The City of Thornton Transportation Plan 29 lists the street as a four lane major arterial roadway with two lanes in each direction at full buildout. 12 nd Avenue West of reet A collector roadway consisting of two 12 lanes in each direction, with a raised median, curb and gutter, bike lanes, sidewalks, and a posted speed limit of 3 MPH. 14 th Avenue A collector roadway consisting of two 12 lanes in each direction with a raised median, curb and gutter, no bike lanes, a sidewalk on the north side, and a posted speed limit of 3 MPH. 1
7 F RONT RANGE CROSSINGS The segment between the Home Depot and Daveco Liquors is built in an interim condition with one 12 lane in each direction, no raised median, curb and gutter, no bike lanes, a sidewalk on the north side, and a posted speed limit of 3 MPH. reet Currently a major arterial roadway with laneage, medians, curb and gutter, and sidewalks that vary by segment, no bike lanes, and a posted speed limit that varies from 4 MPH to 4 MPH. The City of Thornton Transportation Plan 29 lists the street as a six lane major arterial roadway with three lanes in each direction at full buildout. The segment south of 1 th Avenue has one 12 lane in each direction with no raised median, no curb and gutter, no bike lanes, no sidewalk and a posted speed limit of 4 mph. The segment between 1 th Avenue and 12 nd Avenue consists of three 12 lanes southbound, two 12 lanes northbound (asphalt built for three 12 lanes in the future), with a raised median, curb and gutter, no bike lanes, a sidewalk on the west side, and a posted speed limit of 4 MPH. The segment between 12 nd Avenue and 13 rd Avenue consists of three 12 lanes southbound, two 12 lanes northbound, with a raised median, curb and gutter, no bike lanes, a sidewalk on the west side, and a posted speed limit of 4 MPH. The segment between 13 rd Avenue and 14 th Avenue consists of three 12 lanes southbound, two 12 lanes northbound (asphalt built for three 12 lanes in the future) with a raised median, curb and gutter, no bike lanes, a sidewalk on the west side, and a posted speed limit of 4 MPH. The segment between 14 th Avenue and State Highway 7 consists of three 12 lanes in each direction with a raised median, curb and gutter, no bike lanes, a sidewalk, and a posted speed limit of 4 MPH. State Highway 7 A major arterial roadway with laneage, medians, curb and gutter, bike lanes, sidewalks that vary by segment and a posted speed limit that varies from 4 MPH to MPH. The City of Thornton Transportation Plan 29 lists the street as a six lane major regional arterial roadway with three lanes in each direction at full buildout. The segment east of York Street consists of two 12 lanes in each direction with a raised median, curb and gutter, bike lanes, sidewalks, and a posted speed limit of MPH. The segment between York Street and 1 th Avenue consists of two 12 lanes eastbound, one 12 lane westbound with no raised median, no curb and gutter, no bike lanes, no sidewalks, and a posted speed limit of MPH. The segment between 1 th Avenue and 14 th Avenue consists of one 12 lane in each direction with no raised median, no curb and gutter, no bike lanes, no sidewalks, and a posted speed limit of MPH. The segment between 14 th Avenue and reet consists of two 12 through lanes and a continuous accel/decel lane in each direction with a raised median, curb and gutter, no bike lanes, a sidewalk on the west side, and a posted speed limit of MPH. The segment between reet and I 2 consists of two 12 through lanes and a continuous accel/decel lane in each direction with a raised median, curb and gutter, no bike lanes, a sidewalk on the west/south side, and a posted speed limit of MPH. 2
8 F RONT RANGE CROSSINGS York Street North & South of State Highway 7 Currently a minor arterial roadway consisting of one 12 lane in each direction with no raised median, curb and gutter on the east side, a bike lane on the east side, a sidewalk on the east side, and a posted speed limit of 4 MPH. The City of Thornton Transportation Plan 29 lists the street as a six lane major arterial roadway with three lanes in each direction at full buildout. Road D North of 14 th Avenue A private road consisting of one 12 wide travel lane in each direction with curb and gutter and a sidewalk on the east side. The roadway does not have a raised median or bike lanes. The speed limit is not posted, but can be assumed to be similar to a local road with a speed limit of 2 MPH. The City of Thornton Transportation Plan 29 has the Northeast Parcel planned as commercial and the Southwest Parcel planned as a business park. The Front Range Crossings project will develop the Southwest Parcel with office uses in conformance with the Transportation Plan. The Northeast Parcel with a mix of retail, office and multi family results in a reduction in traffic compared to the Transportation Plan. Additional discussion on existing and proposed trip generation are included later in this report. Further roadway network details are found in the existing traffic conditions section and the development site characteristics section later in this traffic impact study. 3
9 Broomfield County Weld County 18th Ave Broomfield Broomfield County Adams County Northglenn Weld County Adams County 2 North Creek Farms Current/Future: Residential South Larkridge Current: Retail Future: Retail and Apartments SOUTHWEST PARCEL North Larkridge Current/Future: Retail Washingotn St Future NW Office Current: Residential Future: Office UV 7 NORTHEAST PARCEL Future East Residential Current/Future: Residential Current/Future: Residential Future South Residential Current: Residential/Agriculture Future: Residential Morrison Property Development Current/Future: Residential 1th Ave Cundall Farms Development Current/Future: Residential Future Employment Center Current: Residential and Agriculture Future: Office and Industrial Thornton UV E47 YORK ST Thornton 3, Feet FRONT RANGE CROSSINGS TRAFFIC IMPACT STUDY Figure 1 VICINITY MAP FILE: G:\gis_projects\Front_Range_Crossings\active\apps\Front_Range_Crossings_Vicinity_Map.mxd, 7//218, chris_martin
10 18th Ave N. Larkridge 4 I-2 14th Ave Colorado State Hwy # 7 12nd Ave 2 York St 1th Ave LEGEND # OF THROUGH LANES SIGNALIZED INTERSECTION NORTH FRONT RANGE CROSSINGS TRAFFIC IMPACT STUDY Figure 2 EXISTING ROADWAY CHARACTERISTICS
11 18th Ave N. Larkridge I-2 D-Street 14th Ave Colorado State Hwy # 7 12nd Ave York St 1th Ave NORTH FRONT RANGE CROSSINGS TRAFFIC IMPACT STUDY Figure EXISTING INTERSECTION GEOMETRY
12 General Existing Traffic Conditions F RONT RANGE CROSSINGS Roadway Network The existing roadway network evaluated in this TIS is bounded on the north and east by State Highway 7 and York street, on the west by, and on the south by 1 th Ave. A diagram of the existing roadway network with travel lanes and intersection configurations are shown on Figure 2 Existing Roadway Characteristics and Figure 3 Existing Intersection Geometry. A description of the existing roadways are described below: 1 th Avenue Currently a minor arterial roadway consisting of one 11 lane in each direction with no raised median, no curb and gutter, no bike lanes, and no sidewalks. The roadway has a posted speed limit of 4 MPH west of reet and 4 MPH east of reet. The City of Thornton Transportation Plan 29 lists the street as a four lane major arterial roadway with two lanes in each direction at full buildout. 12 nd Avenue West of reet A collector roadway consisting of two 12 lanes in each direction, with a raised median, curb and gutter, bike lanes, sidewalks, and a posted speed limit of 3 MPH. 14 th Avenue A collector roadway consisting of two 12 lanes in each direction with a raised median, curb and gutter, no bike lanes, a sidewalk on the north side, and a posted speed limit of 3 MPH. The segment between the Home Depot and Daveco Liquors is built in an interim condition with one 12 lane in each direction, no raised median, curb and gutter, no bike lanes, a sidewalk on the north side, and a posted speed limit of 3 MPH. reet Currently a major arterial roadway with laneage, medians, curb and gutter, and sidewalks that vary by segment, no bike lanes, and a posted speed limit that varies from 4 MPH to 4 MPH. The City of Thornton Transportation Plan 29 lists the street as a six lane major arterial roadway with three lanes in each direction at full buildout. The segment south of 1 th Avenue has one 12 lane in each direction with no raised median, no curb and gutter, no bike lanes, no sidewalk and a posted speed limit of 4 mph. The segment between 1 th Avenue and 12 nd Avenue consists of three 12 lanes southbound, two 12 lanes northbound (asphalt built for three 12 lanes in the future), with a raised median, curb and gutter, no bike lanes, a sidewalk on the west side, and a posted speed limit of 4 MPH. The segment between 12 nd Avenue and 13 rd Avenue consists of three 12 lanes southbound, two 12 lanes northbound, with a raised median, curb and gutter, no bike lanes, a sidewalk on the west side, and a posted speed limit of 4 MPH. The segment between 13 rd Avenue and 14 th Avenue consists of three 12 lanes southbound, two 12 lanes northbound (asphalt built for three 12 lanes in the future) with a raised median, curb and gutter, no bike lanes, a sidewalk on the west side, and a posted speed limit of 4 MPH. The segment between 14 th Avenue and State Highway 7 consists of three 12 lanes in each direction with a raised median, curb and gutter, no bike lanes, a sidewalk, and a posted speed limit of 4 MPH. 7
13 F RONT RANGE CROSSINGS State Highway 7 A major arterial roadway with laneage, medians, curb and gutter, bike lanes, sidewalks that vary by segment and a posted speed limit that varies from 4 MPH to MPH. The City of Thornton Transportation Plan 29 lists the street as a six lane major regional arterial roadway with three lanes in each direction at full buildout. The segment east of York Street consists of two 12 lanes in each direction with a raised median, curb and gutter, bike lanes, sidewalks, and a posted speed limit of MPH. The segment between York Street and 1 th Avenue consists of two 12 lanes eastbound, one 12 lane westbound with no raised median, no curb and gutter, no bike lanes, no sidewalks, and a posted speed limit of MPH. The segment between 1 th Avenue and 14 th Avenue consists of one 12 lane in each direction with no raised median, no curb and gutter, no bike lanes, no sidewalks, and a posted speed limit of MPH. The segment between 14 th Avenue and reet consists of two 12 through lanes and a continuous accel/decel lane in each direction with a raised median, curb and gutter, no bike lanes, a sidewalk on the west side, and a posted speed limit of MPH. The segment between reet and I 2 consists of two 12 through lanes and a continuous accel/decel lane in each direction with a raised median, curb and gutter, no bike lanes, a sidewalk on the west/south side, and a posted speed limit of MPH. York Street North & South of State Highway 7 A minor arterial roadway consisting of one 12 lane in each direction with no raised median, curb and gutter on the east side, a bike lane on the east side, a sidewalk on the east side, and a posted speed limit of 4 MPH. The City of Thornton Transportation Plan 29 lists the street as a six lane major arterial roadway with three lanes in each direction at full buildout. Road D North of 14 th Avenue A private road consisting of one 12 wide travel lane in each direction with curb and gutter and a sidewalk on the east side. The roadway does not have a raised median or bike lanes. The speed limit is not posted, but can be assumed to be like a local road with a speed limit of 2 MPH. Traffic Volumes Turning movement traffic counts were collected at the nine key intersections listed below during the AM and PM peak hours on Thursday, May 17, 218. Saturday peak hour traffic counts were collected on Saturday, May 19, hour traffic counts were conducted in 1 minute increments on Thursday, May 17, 218. Figure 4 shows both AM and PM peak hour turning movements and Figure shows the Saturday peak hour turning movements at the nine study area intersections in the vicinity of the site. Appendix A contains the raw traffic count data. The AM peak hour generally occurs between 7 and 8 AM. The PM peak hour generally occurs between and PM. The Saturday peak hour generally occurs between noon and 1 PM. 1. State Highway 7 & York Street 2. State Highway 7 & 1 th Avenue 3. State Highway 7 & 14 th Avenue 4. State Highway 7 & reet. reet & 1 th Avenue. reet & 12 nd Avenue 8
14 F RONT RANGE CROSSINGS 7. reet & 14 th Avenue 8. reet & North Larkridge Private Road th Avenue & D Street (Daveco Liquor) The Average Daily Traffic (ADT) was counted in 1 minute increments on Thursday, May 17, 218 at ten key locations in the vicinity of the project area as listed below. Figure 4 and Figure show the existing turning movement volumes and the existing ADT. 1. State Highway 7 west of 18 th Avenue 2. State Highway 7 east of reet 3. State Highway 7 east of York Street 4. reet south of 1 th Avenue. reet north of 12 nd Avenue. reet south of State Highway 7 7. York Street south of State Highway th Avenue east of I th Avenue east of reet th Avenue west of D Street (Daveco Liquors) Intersection and Roadway Capacity Analysis To determine how efficiently and effectively the perimeter street system accommodates the existing traffic volumes, the key intersections in the vicinity of the proposed development were analyzed using Synchro 1 software. The results are shown as Levels of Service (LOS). LOS is a qualitative measure used to describe the condition of traffic flow and delay, ranging from excellent conditions at LOS A to very poor conditions at LOS F. Per the City of Thornton Transportation Plan 29 adopted on September 8, 29, the City of Thornton requires a minimum of LOS D for intersection operations. Table 1 provides a description of conditions for each level of service at a signalized intersection. Table 1 Signalized Intersection Level of Service Criteria Level of Service Average Stopped Delay* Description A <1 Very low delay. Most vehicles do not stop. B >1 to 2 Generally good progression. Slight delays. C >2 to 3 Increased number of stopped vehicles D >3 to Noticeable congestion. E > to 8 High delays and frequent cycle failures. F >8 Forced flow. Extensive queuing. *Seconds per vehicle. Source: HCM Highway Capacity Manual th Edition (Transportation Research Board, 21) For unsignalized (side street stop controlled) intersections, Synchro 1 software was used again. The software applies the Transportation Research Board s 21 Highway Capacity Manual th Edition methodology for unsignalized intersections to determine average control delay per vehicle (measured in seconds) for each stop controlled movement. The method incorporates delay associated with deceleration, acceleration, stopping, and moving up in the queue. For side street stop controlled intersections, delay is represented as the average delay per vehicle for the worst 9
15 F RONT RANGE CROSSINGS approach, not the overall intersection. Table 2 summarizes the relationship between delay and level of service. Table 2 Unsignalized Intersection Level of Service Criteria Level of Service Average Total Delay (seconds per vehicle) Description A < 1 Little or no conflicting traffic for minor street approach. B >1 to 1 Minor street begins to notice absence of available gaps. C >1 to 2 Minor street begins experiencing delay for available gaps. D >2 to 3 Minor street starts to experience queuing. E >3 to Extensive minor street queuing due to insufficient gaps. F > Insufficient gaps to allow minor street traffic to cross safely through the major street traffic stream. Source: HCM Highway Capacity Manual th Edition (Transportation Research Board, 21) The City of Thornton Transportation Plan 29, lists volume thresholds for different roadway classifications based on number of lanes. Table 3 summarizes ADT volume and level of service. Table 3 Roadway Level of Service Thresholds by Functional Classification Level of Service A B C D E Major Reginal Arterial Lanes 3,7 48,2,9 4,8 72, Major Arterial Lanes 27, 3,2 42,7 48, 4, 4 Lanes 18,4 24,1 28,4 32,4 3, Minor Arterial 4 Lanes 1,3 21,4 2,3 28,8 32, Collector 2 Lanes,1 8, 9, 1,8 12, Source: City of Thornton Transportation Plan 29 Roadway progression is an additional metric to analyze roadway corridors. As a guideline, efficiency below.12 is considered poor, efficiency from.13 to.24 is fair, and efficiency from.2 to.3 is good progression. Great progression is anything over.3. CDOT typically requires a 3 percent efficiency or better. As can be seen in table 9, preferential progression is given to the dominate direction along State Highway 7 under the existing AM and PM traffic signal timing plans. The reet corridor is not coordinated at this time so progression cannot be determined. Table 4 presents the existing intersection levels of service. The existing traffic signal timing plans are used for the signalized intersections on reet and on State Highway 7. Table presents the progression analysis. Appendix B contains the analysis output, signal timings, and timespace diagrams. As presented, most of the intersections currently operate well and meet established performance standards (LOS D or better). Additional discussion is included after the table. 1
16 F RONT RANGE CROSSINGS Table Existing Traffic Level of Service Intersection Control 218 Existing 218 Existing 218 Existing Storage Length 1 Weekday AM Weekday PM Saturday LOS Queue LOS Queue LOS Queue SH 7 & York St Signalized B B B EB Left SH 7 ex. 21 B 8 A 13 A 7 EB Thru SH 7 B 18 B 178 B 178 EB Right SH 7 ex. 21 B 39 B 3 B 34 WB Left SH 7 ex. 48 A 87 A 43 A 1 WB Thru SH 7 B 19 B 11 A 12 WB Right SH 7 ex. 2 A A 12 A NB Left York ex. 11 D 142 E 1 D 12 NB Thru York C 19 D 38 C 2 NB Right York ex. 21 C 3 D D 42 SB Left York ex. 18 C 21 D 4 C 17 SB Thru/Rt York C 9 D 112 C 4 SH 7 & 1 th Full Movement Ave Stop Controlled 2 A E D EB Thru/Rt SH 7 A A A WB Left SH 7 ex. 2 A 2 B 2 B 2 WB Thru SH 7 A A A NB Left 1 th ex. A E 2 D 2 NB Right 1 th NA Drop Lane A A A SH 7 & 14 th Ave Signalized B B B EB Left 14 th ex. 2 C 9 D 31 C 31 EB Thru 14 th D 31 D 94 C 7 EB Right 14 th ex. 3 D D 38 D 44 WB Left 14 th ex. 14 D D 32 D 1 WB Thru/RT 14 th F 11 E 94 E 98 NB LT SH 7 ex. 48 A 1 A 38 A 7 NB Thru SH 7 A 148 A 17 A 13 NB RT SH 7 ex. 18 A A 4 A SB LT SH 7 ex. 2 A A 2 A 18 SB Thru SH 7 A 28 A 7 B 4 SB RT SH 7 ex. 23 A A A Washington St & SH 7 Signalized B B C EB Thru SH 7 A 11 B 29 B 19 EB Right SH 7 NA Drop Lane A 24 B 43 C WB Left SH 7 ex. 23 D 3 D 3 D 48 WB Thru SH 7 A 2 A 9 A
17 Intersection Control F RONT RANGE CROSSINGS Storage Length Existing Weekday AM 218 Existing Weekday PM 218 Existing Saturday LOS Queue LOS Queue LOS Queue NB Left Washington NA Drop Lane C 97 D 232 D 273 NB Right Washington NA Drop Lane C 17 D 2 C 33 Washington St. & N. Signalized B C C Larkridge EB Left N. Larkridge ex. 38 C 3 C 74 C 113 EB Thru N. Larkridge C 2 C 41 C 4 EB Right N. Larkridge ex. 38 C C C WB Left N. Larkridge ex. 13 C 1 C 24 D 32 WB Thru N. Larkridge C 2 C 3 C 7 WB Right N. Larkridge ex. 2 C 8 C 24 D NB Left Washington ex. 19 C 11 C 18 D 27 NB Thru Washington A 1 B 44 B 74 NB Right Washington ex. 1 A B B SB Left Washington ex. 19 C 4 C 8 D 89 SB Thru Washington A 13 A 3 B 2 SB Right Washington ex. 2 A A B 3 Washington St & 14 th Signalized C C C Ave EB Left 14 th ex. 17 C 14 C 44 C 72 EB Thru 14 th C 8 C 28 C 4 EB Right 14 th ex. 1 C C C WB Left 14 th ex. 1 C 2 C 38 C 4 WB Thru 14 th C 7 C 19 C 37 WB Right 14 th ex. 1 C C C NB Left Washington ex. 19 C C 19 C 2 NB Thru Washington A 12 A 2 A 3 NB Right Washington ex. 1 A A 8 B 22 SB Left Washington ex. 2 D 9 D 1 D 1 SB Thru Washington A 12 A 3 B 47 SB Right Washington ex. 1 A B 1 B 17 Washington St & 12 nd Signalized A A B EB Left 12 nd ex. 2 C C 24 C 3 EB Right 12 nd ex. 2 C 13 C 33 D 43 NB Left Washington ex. 19 C 8 C 2 C 43 NB Thru Washington A 8 A 17 A 24 SB Thru Washington A 11 A 2 A 37 SB Right Washington ex. 1 A A 14 A 1 12
18 F RONT RANGE CROSSINGS Intersection Control 218 Existing 218 Existing 218 Existing Storage Length 1 Weekday AM Weekday PM Saturday LOS Queue LOS Queue LOS Queue Washington St & 1 th Signalized C C C EB Left 1 th ex. 28 D 3 D 4 D 8 EB Thru\RT 1 th A 128 A 192 C 78 WB left 1 th ex. 13 D 19 D 23 D 24 WB Thru\RT 1 th A 14 A 1 A 98 NB Left Washington ex. 2 C 9 D 22 D 3 NB Thru\RT Washington A 32 A 3 A 77 SB Left Washington ex. 2 D 19 D 4 D 7 SB Thru Washington A 2 A 2 A 89 SB Right Washington ex. 21 A A 3 A th Ave & Full Movement D St Stop Controlled 2 A B B EB Left 14 th ex. 18 A A 28 A EB Thru 14 th WB Thru 14 th WB Right 14 th NA Drop Lane SB Left D Street ex. 7 A 11 B 139 B 11 SB Right D Street NA Drop Lane ex. = existing storage length 2. Overall level of service for unsignalized intersections is based on the worst movement LOS. Roadway Segment Functional Classification LOS SH 7 west of 4 Lane Major Arterial B SH 7 east of 4 Lane Major Arterial A SH 7 east of York St 4 Lane Major Arterial B south of SH 7 Lane Major Arterial A north of 12 nd Ave 4 Lane Major Arterial A south of 1 th Ave 2 Lane Minor Arterial A 1 th Ave east of I 2 2 Lane Minor Arterial B 1 th Ave east of 2 Lane Minor Arterial A 14 th Ave west of D Street 2 Lane Collector A York St south of SH 7 2 Lane Minor Arterial B 218 Existing Traffic Operational Results Roadway Level of Service The existing ADT on State Highway 7, reet, 1 th Avenue, and 14 th Avenue can be seen on Figure 4 and Figure. Based on the Roadway Level of Service Thresholds by Functional Classification in Table 3, these volumes indicate a Roadway LOS of A to B. 13
19 F RONT RANGE CROSSINGS Intersection Level of Service Based on the Intersection Level of Service analysis most of the intersections in the study area are anticipated to operate at a LOS of D or better which meets or exceed the City s established performance standards. The two exceptions are the minor street stop controlled intersection of State Highway 7 and 1 th Avenue and the westbound right turn movement at the signalized intersection of State Highway 7 and 14 th Avenue which are discussed below. State Highway 7 and 1th Avenue State Highway 7 is a single lane in each direction at this location with relatively high traffic volumes which results in limited gaps for the left turn from 1th Avenue to State Highway 7. For this reason, it appears very few drivers make this left turn movement ( in the AM peak hour, 8 in the PM peak hour and 4 in the Saturday peak hour). The vehicles that choose to make this left turn experience LOS E during the PM peak hour and LOS D during the Saturday peak hour, but the queue generally does not exceed one car at a time. With very little traffic turning left, a traffic signal is not warranted at this location. State Highway 7 and 1th Avenue Westbound Right Turn Based on the current traffic signal timing plan, there does not appear to be sufficient green time for the westbound approach. If the green time were to be increased 3 seconds during the AM peak hour, the westbound right turn performance would improve from LOS F to a more acceptable LOS E. Although delay is experienced by motorist making this maneuver, the queue ends before the next intersection at Downing Street. Progression Analysis The existing traffic signals along State Highway 7 are actuated/coordinated with an AM cycle length of 9 seconds, a PM cycle length of 11 seconds, and a Saturday cycle length of 9 seconds. The reet corridor is not coordinated at this time, so progression cannot be determined. Table summarizes the progression by time period. The time space diagrams are included with the signal timing sheets in Appendix B. Table 218 Existing Traffic Progression Summary AM Pk. Hr. PM Pk. Hr. Sat Pk Hr. SH 7 EB Efficiency.3.3. WB Efficiency NB Efficiency N/A N/A N/A SB Efficiency N/A N/A N/A As seen in Table, CDOT provides preferential timing under the existing traffic signal timing plans for the westbound direction of State Highway 7 during the AM peak hour and the eastbound direction during the PM peak hour. 14
20 24/1 9/4 2/4 4/8 /1 9/73 8/ 7/31 /87 8/9 /12 /31 /172 11/32 7/18 1/49 8/182 7/8 12/23 1/21 9/1 72/94 1/24 11/37 34,7 17/88 11/28 18th Ave 21/ 14/34 32/2 48/41 21/94 4/44 7/18 11/ 17/8 19/9 13/47 4/4 1/19 3/49 32/4 3/88 98/229 11/48 11,2 N. Larkridge 17,7 8/ 12/83 18/19 11/ I-2 2,4 14th Ave, 12nd Ave 44/128 12/27 1/2 29/9 2/14 /74 Colorado State Hwy # 7 York St, 4, 21, 1th Ave 8/43 8/2 3/2 23/ 19/189 7/4 /11 14/14 8/12 3/8 98/193 /11 4,8 3/73 2/ /8 13/249 9/8 192/134 13/22 48/3 31/41 1/7 79/3 218/141 7,7 LEGEND 9/27 AM/PM PEAK HOUR TRAFFIC 28/82 482/78 147/27 13/13 3/4 1/11 NORTH 22, AVERAGE ANNUAL DAILY TRAFFIC FRONT RANGE CROSSINGS TRAFFIC IMPACT STUDY Figure WEEKDAY EXISTING TRAFFIC
21 ,7 18th Ave ,2 17,7 N. Larkridge I-2 2,4 14th Ave Colorado State Hwy # 7, York St 12nd Ave 1 14, 4, 21, 1th Ave , ,7 LEGEND PEAK HOUR TRAFFIC NORTH 22, AVERAGE ANNUAL DAILY TRAFFIC FRONT RANGE CROSSINGS TRAFFIC IMPACT STUDY Figure 218 SATURDAY EXISTING TRAFFIC
22 Development Site Characteristic F RONT RANGE CROSSINGS Site Access Internal to the site, the proposed development will have parking lots dispersed throughout that can be accessed via the internal roadway system. Sidewalks will be constructed on site with connections from the buildings to the internal and external roadway systems for pedestrian and ADA access. The project will have roadway connections to State Highway 7, reet, 1 th Avenue and 14 th Avenue as outlined below and seen on the site plan, Figure. Intersection spacing is shown on Figure 22 and geometric layout of the intersections is shown on Figure 23. Connections to State Highway 7 13 rd Avenue will be right in/right out located approximately 7 south of 14 th Avenue. 12 nd Avenue will be a full movement signalized intersection located approximately 74 south of 14 th Avenue. 11 st Avenue will be right in/right out located approximately south of 12 nd Avenue aligned with an existing driveway. Connections to reet 12 nd Avenue eastern leg of the existing signalized intersection. The intersection is constructed with curb returns and turn lanes for the eastern leg. This TIS analyzes the road network with and without site traffic connected to the eastern leg of the intersection of reet and 12 nd Avenue. 11 st Avenue will be a ¾ access with southbound left, northbound right and westbound right located approximately 44 north of 1 th Avenue. X Street will be a ¾ access with northbound left, southbound right and eastbound right located approximately 4 south of 1 th Avenue. 18 th Parkway will be a full movement signalized intersection located approximately 7 south of X Street. Connections to 1 th Avenue A Street will be right in/right out located approximately 73 east of reet. B Street will be a full movement signalized intersection located approximately east of A Street C Street will be right in/right out located approximately 9 east of B Street. Y Street will be right in/right out located approximately west of reet. Grant Street southern leg of the full movement signalized intersection proposed with the Larkridge Development located approximately 78 west of Y Street. Connections to 14 th Avenue B Street will be right in/right out located approximately 43 west of D Street (Daveco Liquors). D Street southern leg of the existing unsignalized intersection. The intersection and turn lanes are constructed with curb returns and turn lanes for the southern leg. 17
23 F RONT RANGE CROSSINGS Trip Generation The vehicle trips associated with Front Range Crossings development are calculated using the ITE Trip Generation Manual, Tenth Edition. This methodology consists of choosing an independent variable for the land use for a particular time of day. The independent variable correlates to the variation in trip ends and is related to the land use. The value of the independent variable is either multiplied by a weighted average or used in a regression equation to calculate the trips generated by the land use. The ITE Trip Generation Manual provides guidance on when to use the weighted average versus the regression equation. In most cases, the regression equations are recommended when there are adequate study data points. Table shows the ITE land use codes used in the analysis. Since the specific type of retail and restaurants are not defined at this point, the shopping center land use code was assumed for these uses. Table ITE Land Use Codes Independent Land Use Variable ITE Code Retail/Rest. Square Feet 82 Office Square Feet 71 Apartments Dwelling Units 22 Because the Northeast Parcel is a mixed use development, some of the associated trips will be captured internally. Using the ITE Online Traffic Impact Study Software, the AM peak hour trips were reduced by roughly 12 percent, the PM peak hour trips were reduced approximately 14 percent, the Saturday peak hour trips were reduced almost 22%, and Daily trips were reduced by a little over 1 percent to account for internal capture within the Northeast Parcel. No reductions were taken for the Southwest Parcel given the single land use type and more isolated location. The internal capture output from the ITE Online Traffic Impact Study Software is included in Appendix C. Table 7 shows the trip generation for the build out of the development. Table 7 Trip Generation AM Peak PM Peak Saturday Daily Land Use In Out In Out In Out In Out Northeast Parcel Apartments (42 DU) ,499 1,499 Office (1, KSQFT) ,97 4,97 Retail/Restaurant (12 KSQFT) ,18 3,18 NE Parcel Subtotal 1,9 3 1, ,992 9,992 Internal Capture* ,13 1,13 NE Parcel Total , ,479 8,479 Southwest Parcel Office (1,14 KSQFT) ,18,18 SW Parcel Subtotal ,18,18 Grand Total , ,497 13,497 *Internal capture volumes per the ITE Online Traffic Impact Software. See Appendix C. 18
24 F RONT RANGE CROSSINGS Due to the size and number of access points with the Northeast Parcel, the site was divided into three traffic analysis zones (TAZ s). TAZ A is north of 12 nd Avenue, TAZ B is south of 12 nd Avenue and east of B Street, TAZ C is south of 12 nd Avenue and west of B Street. The entire Southwest Parcel is identified as TAZ D. The trips associated with each TAZ are based on the anticipated land uses as shown in Table 8 below. The location of each TAZ can be seen on the site plan, Figure. Table 8 Full Build-out Trip Generation by TAZ AM Peak PM Peak Saturday Daily Land Use In Out In Out In Out In Out TAZ A (N. of 12nd) Office (3 KSQFT) ,7 1,83 Retail/Restaurant (12 KSQFT) ,88 2,78 TAZ A Subtotal ,4 4,441 TAZ B (SE of 12 nd & B Street) Office (29 KSQFT) , 2,439 TAZ B Subtotal , 2,439 TAZ C (SW of 12 nd & B Street) Apartments (42 DU) ,87 Office (111 KSQFT) TAZ C Subtotal ,284 1,99 TAZ D (Southwest Parcel) Office (1,14 KSQFT) ,18,18 TAZ D Subtotal ,18,18 Grand Total 1, , ,497 13,497 Trip Generation Comparison: The City of Thornton Transportation Plan 29, identifies the planned land use for the Northeast Parcel as commercial and the planned land use for the Southwest Parcel as business park. The Front Range Crossings development will be constructing office within the Southwest Parcel which is in general conformance with the Transportation Plan. The Northeast Parcel will have a mix of apartments, office, and retail. Table 9 presents a comparison between the proposed Front Range Crossings development and the commercial land use identified in the Transportation Plan. Since the specific type of commercial is not defined, the shopping center ITE land use code 82 was assumed to compare site trips to the proposed project. The commercial land use presented in the table is based on the Northeast Parcel area of 128 acres and a floor to area ratio (FAR) of.2. As seen in the table, the proposed mixed use development results in a reduction in anticipated vehicle trips during the PM peak hour, Saturday peak hour and the Daily traffic. There is an increase in vehicle trips during the AM peak hour, but this also coincides with the lowest levels of traffic on the adjacent roadways. 19
25 F RONT RANGE CROSSINGS Table 9 Trip Generation: Front Range Crossings vs Transportation Master Plan Front Range Crossings Commercial Delta AM Peak Hour In Out Total 1, PM Peak Hour In 47 1,4 1,78 Out 1,14 1,83 43 Total 1,1 3,237 1,21 Saturday Peak Hr In 92 2,13 1,471 Out 2 1,997 1,377 Total 1,313 4,1 2,847 Daily In 8,479 1,494 7,1 Out 8,479 1,494 7,1 Total 1,98 3,989 14, Trip Distribution The portion of the site north of 12 nd Avenue is anticipated to be constructed by the year 223. This area will be a mix of office and retail as discussed previously. Most of the trips are anticipated to come from major arterials and highways with smaller percentages coming from adjacent areas. Vehicles using E 47 east of the project area are assumed to use the York Street Interchange while vehicles using E 47 west of the project area are assumed to use the Sheridan Interchange and come in on 1 th Avenue. One percent of the trips are assumed to go to/from the North Creek Farms neighborhood east of the State Highway 7 & 14 th Avenue intersection. Within the site, vehicles are assumed to use the internal road network to gain access to the external road network based on the most direct route. Figure 7 shows the expected external distribution of travel for the site generated trips and Figure 8 illustrates the anticipated percent of site traffic for each movement at the intersections included within the study. Figure 9 shows the weekday peak hour site traffic volumes at each intersection and Figure 1 shows the Saturday peak hour site traffic volumes at each intersection. Both Figure 9 and Figure 1 show the site generated average daily traffic volumes (ADT). 238 Trip Distribution with 12 nd Avenue Connected to The full site is anticipated to be built out by the year 238. With office being the largest component of the overall site, much of the site traffic is anticipated to come from major arterials and highways with smaller percentages coming from adjacent areas. Vehicles using E 47 east of the project area are assumed to use the York Street Interchange while vehicles using E 47 west of the project area are assumed to use Sheridan Interchange and come in on 1 th Avenue. One item to note is that while roughly 2 percent of the trips are anticipated to use I 2 south of the project area, a portion of TAZ C s trips and all of TAZ D s trips using I 2 south are anticipated to use Washington to go 2
26 F RONT RANGE CROSSINGS south to 144 th Avenue rather than traveling an extra 2 miles by using the I 2 & SH 7 Interchange. Another item to note is that drivers from TAZ s B, C, and D trying to use State Highway 7 west of I 2 are assumed to use 1 th Avenue and Huron Street to avoid the heavily congested I 2 & SH 7 Interchange. It is assumed 1% of the site traffic will come from/to the North Creek Farms neighborhood located east of the State Highway 7 and 14 th Avenue intersection and 1% of the site traffic will come from/to the future East Residential development located east of the State Highway 7 and 12 nd intersection and east of the State Highway 7 and 1 th Avenue intersection. Within the site, vehicles are assumed to use the internal road network to gain access to the external road network based on the most direct route. Anticipated site traffic at 12 nd & Road B is included for reference purposes. As will be discussed later in this study, the internal roads can be sized by looking at the highest volume links as they connect to the external road network. Figure 11 shows the expected external distribution of travel for the site generated trips and Figure 12 illustrates the anticipated percent of site traffic for each movement at the intersections included within the study. Figure 13 shows the weekday peak hour site traffic volumes at each intersection and Figure 14 shows the Saturday peak hour site traffic volumes at each intersection. Both Figure 13 and Figure 14 show the site generated average daily traffic volumes (ADT). 238 Trip Distribution without 12 nd Avenue connected to 12 nd Avenue between reet and B Street is outside the limits of the Front Range Crossings property. To determine how the surrounding roadway network would perform if this segment of roadway were to be built by others and deferred until the adjacent property is developed, an additional 238 analysis is included later in this traffic report and an additional site distribution is included in this section. The external distribution is the same with and without this segment of 12 nd Avenue as seen in Figure 11. Internal to the site, the trips within the Northeast Parcel have been reassigned to gain access to the external road network without the 12 nd Avenue & reet connection. Figure 1 shows the anticipated percent of site traffic for each movement at the intersections included within the study. Figure 1 shows the weekday peak hour site traffic volumes at each intersection and Figure 17 shows the Saturday peak hour site traffic volumes at each intersection. Both Figure 1 and Figure 17 show the site generated average daily traffic volumes (ADT). 21
27 7 V U 1 T WASHINGTON ST -S TAZ A 13RD AVE BUL L CANAL E AV T 1S 1 B - ST H T 1 E AV Y - ST A - ST GRANT ST E AV TAZ B TAZ C 11ST AVE E AV D 2N 1 Northeast Parcel 12ND AVE 1TH AVE D 3R 1 D 14TH AVE E AV C - ST 2 H 4T Southwest Parcel X - ST TAZ D 18TH PKWY Legend Northeast Parcel Southwest Parcel Short Term Development by 223 V U Long Term Development by 238 E47 FRONT RANGE CROSSINGS TRAFFIC IMPACT STUDY FILE: G:\gis_projects\Front_Range_Crossings\active\apps\Front_Range_Crossings.mxd, 7/12/218, spencer_percival 1,8 Feet Figure SITE PLAN
28 1% 18th Ave 1% Colorado State Hwy #7 I-2 1% 2% 14th Ave D- St 12nd Ave B-Street TAZ A 12nd Ave 13rd Ave York St Grant Street 1% 1% 1th Ave LEGEND 14% % TAZ A 223 DISTRIBUTION 1% FRONT RANGE CROSSINGS TRAFFIC IMPACT STUDY Figure SHORT TERM ANALYSIS TRIP DISTRIBUTION
29 LEGEND % PERCENT OF SITE TRAFFIC 9.3% 4.8% % 8.2% 3.9% %.4%.1% th Ave 3.3% % 9. % %.8%.4% %.1% % % 1 I-2 Grant Street N. Larkridge 4 14th Ave 1th Ave B-Street 3 2 D-Street 12nd Ave 13rd Ave 21 Colorado State Hwy # 7 York St 2 % % % 4.4% 2.7% % 1.3% 1.3%.2%.2%.8% %.3% %.1% 4.1% %.3% % 9.1%.2% 8.4% % 1.4% 1.3% %.1% 2.3% 1.2%.2%.1% % % 9% 3%.% NORTH %.3% % 1.4% %.4% 11 %.1% 2.7%.7% 7.2%.2%.% 4.4% % % % % 17 1.% % 3.7% 4.4% 4% % 2.% 4.8% % % % % 18 7.% %.3% %.1% % % % % % 7.3% % 19 %.7% % % % % % % % % 7.1% 3.% 2 % 1 % % % 4% 3.2%.1% 3.9% 21.2% FRONT RANGE CROSSINGS TRAFFIC IMPACT STUDY Figure SHORT TERM ANALYSIS PERCENT OF GENERATED TRIPS PER MOVEMENT
30 LEGEND I-2 9 Grant Street 1,2 4, N. Larkridge 1,4 9/12 AM/PM PEAK HOUR TRAFFIC B-Street th Ave AVERAGE ANNUAL DAILY TRAFFIC 18th Ave 1 3,7 1, th Ave D-Street 12nd Ave 13rd Ave 3,2 21 Colorado State Hwy #7 York St 1, / /28 / / / 2/1 17/14 / / / / / /29 2/43 1/97 18/113 / / / / 42/27 / / /3 / 4/4 / 22/137 83/9 / /43 7/8 / 2/1 1/ / 3 4 / 111/92 / 28/171 17/12 / / / / / / / / 1/97 / / 4/3 / /29 / 111/92 / /3 1,3 1,4 NORTH / 4/24 2/11 37/31 / / 11 / 7/4 9/ / 2/43 / / /3 / / / / 17 / / / / 89/74 / 33/28 / / / / / 18 / / /3 89/74 / / / / / / 33/28 / 19 / / / / / / / 14/8 14/8 / / / 2 / /4 / / / /4 17/14 7/ 2/1 21 1/97 FRONT RANGE CROSSINGS TRAFFIC IMPACT STUDY Figure SHORT TERM ANALYSIS WEEKDAY SITE TRAFFIC
31 LEGEND 12 AM/PM PEAK HOUR TRAFFIC 4 1,2 AVERAGE ANNUAL DAILY TRAFFIC ,1 18th Ave I-2 9 Grant Street 19 N. Larkridge 1, th Ave 1,4 B-Street th Ave 3,7 D-Street 12nd Ave 8 13rd Ave 21 3,2 Colorado State Hwy # 7 York St 1, ,3 1,4 NORTH FRONT RANGE CROSSINGS TRAFFIC IMPACT STUDY Figure SHORT TERM ANALYSIS SATURDAY SITE TRAFFIC
32 1%/1%/ 1%/1% %/%/ %/% %/%/%/% %/%/%/% I-2 Colorado State Hwy #7 1%/1%/ 1%/1% 1%/1%/ 1%/1% 2%/2%/1%/% Grant St 14th Ave 12nd Ave See Note 11st Ave TAZ C A-St B-Street B-St D-St TAZ A 13rd Ave TAZ B C-St 11st Ave.% /.%/. %/.%.%/.%/.%/.% York St 1%/1%/ 1%/1% Y-St X-St 18th Parkway 1th Ave LEGEND 14%/14%/ 24%/34% %/%/%/% TAZ A/TAZ B/TAZ C/TAZ D 238 DISTRIBUTION PROPOSED 1th AVE REALIGNMENT BY %/14%/ 14%/14% PROPOSED WASHINGTON ST EXTENSION & 18th REALIGNMENT BY 238 EXISTING 18th AVE FRONT RANGE CROSSINGS TRAFFIC IMPACT STUDY Note: This Traffic Study analyzes 238 scenarios with and without 12nd Ave constructed between and B-Street Figure TRIP DISTRIBUTION
33 LEGEND % PERCENT OF SITE TRAFFIC % 4.2% 2.1% % 1.2% 1.2% % 9.% 1.% %.2%.1% 18th Ave 4.3% 4.% % % 12.% %.%.% %.2% 1.4% % 1 I-2 Grant St 14 Y-St 19 N. Larkridge th Ave st Ave 1 B-Street nd Ave C-St A-St X-St 12 D-St 1th Ave 13rd Ave 21 11st Ave Colorado State Hwy # 7 22 York St 2 % % % 3.% 1.4% % 1.4%.% 1.%.2% 3.8% 4.8% %.3% %.1% 1.7% 3 4.1%.4%.1% % 3.8%.2% 8.9% %.9%.%.1%.2%..% 1.% %.1%.1% % 3.7% 1.%.3% 13 18th Pkwy NORTH.8% % % % % % 7 % %.1%.2% 2.8% % %.7% 2.4% 8.1% 1.4%.% 3.% 7.% 9 3.9%.2% %.3% 3.% %.9% % 9.1% 1.9% 1.1% 11.% % 1.3% % 3.%.1% 1.1% 11 %.%.9% 3.1% 4.9%.% 3.3% 8.4% 1.% % %.% 4.%.% 11.%.7% % 2.1%.9% % % % % 2.4%.% 14 %.9%.% 4.2% % 4.4%.3%.3% % 1 3.9% %.% % 1.% 1.3% % % 1 1.% 1.1%.8% % % 2.3% % % % % 17 % % % % 8.4% % 1.1% 2.2% % % % % % %.3% %.1%.3% % % % % 3.3% % % 19 % 8.3% % % % % % % % 11..3% 3.% 2 % 3.% % % % 1.% 1.8% 2.1% 3.2% 21 1.% 7.1%.4% 2.% 22 4.% FRONT RANGE CROSSINGS TRAFFIC IMPACT STUDY Figure PERCENT OF GENERATED TRIPS PER MOVEMENT WITH 12nd BETWEEN WASHINGTON ST & B-STREET
34 LEGEND I-2 3, Grant Street 14 Y-St X-St 1,2,3 19 N. Larkridge th Ave 18th Ave 1 B-Street D-Street nd Ave 11st Ave 1 C-St A-St , 9/12 AM/PM PEAK HOUR TRAFFIC 3,9 18th Parkway AVERAGE ANNUAL DAILY TRAFFIC, 2, 13rd Ave 21 4,8 22 4,1 11st Ave Colorado State Hwy # 7 2 1th Ave York St 3,8 4/31 113/33 / / / 4/92 118/34 / 2/1 12/ / / /3 17/14 31/221 2/1 19/11 / 3/123 4/17 21/127 / 1/7 11/77 42/287 / 1 2 / 8/2 4/4 18/23 17/14 / 24/148 2/ /3 / 12/11 219/9 /42 1/ 39/23 / / 4/27 / 7/2 2/2 1// 3/14 / 12/ /2 2/ 29/21 / 1/9 / 1/99 17/4 NORTH 4,,1 17/14 2/43 4/17 / / 9/7 7 / 9/42 /4 / 37/31 / 37/7 38/11 / 8 2/4 14/38 1/17 2/8 2/128 11/47 9/141 8/ /9 78/24 / 17/8 143/8 17/237 49/1 1 /4 23/213 23/8 133/2 /29 / 193/121 2/ 11 34/32 131/183 2/13 / 14/17 88/97 14/88 12/ / /228 8/17 24/12 12/73 28/17 7/29 9/ /92 21/39 71/14 / 18/4 89/17 / / / 14 / 39/1 129/2 2/1 / 18/117 14/211 38/7 / 1 1/13 / 18/18 / 39/2 19/121 / / 1 39/41 43/29 111/23 / 34/7 21/1 / / / / 17 8/9 / 18/87 82/3 8/222 / 33/28 241/ / / / / 18 8/2 / 1/7 1/9 7/272 / / / / / / 19 / 7/279 / 27/93 4 / / / / 2/3 13/8 / / / 2 / 2/9 / / / 2/43 18/42 7/ 14/ /221 33/18 4/8 / /11 FRONT RANGE CROSSINGS TRAFFIC IMPACT STUDY Figure WEEKDAY SITE TRAFFIC WITH 12ND AVE BETWEEN WASHINGTON ST & B-STREET
Traffic Impact Analysis Chatham County Grocery Chatham County, NC
Chatham County Grocery Chatham County, NC TABLE OF CONTENTS 1. INTRODUCTION... 1 1.1. Location and Study Area... 1 1.2. Proposed Land Use and Access... 2 1.3. Adjacent Land Uses... 2 1.4. Existing ways...
More informationTRAFFIC ASSESSMENT River Edge Colorado
TRAFFIC ASSESSMENT River Edge Colorado Submitted by: Fehr & Peers 621 17th Street, Ste. 231 Denver, CO 8293 (33) 296-43 December, 21 App. M-2 Traffic Assessment River Edge Colorado December 21 TABLE OF
More informationTraffic Impact Study WestBranch Residential Development Davidson, NC March 2016
Traffic Impact Study WestBranch Residential Development Davidson, NC March 216 TRAFFIC IMPACT STUDY FOR THE WestBranch Residential Development LOCATED IN DAVIDSON, NC Prepared For: Lennar Carolinas, LLC
More informationTraffic Impact Analysis Walton Acres at Riverwood Athletic Club Clayton, NC
Traffic Impact Analysis Walton Acres at Riverwood Athletic Club Clayton, NC 1. TABLE OF CONTENTS INTRODUCTION...1 1.1. Site Location and Study Area...1 1.2. Proposed Land Use and Site Access...2 1.3.
More information5858 N COLLEGE, LLC N College Avenue Traffic Impact Study
5858 N COLLEGE, LLC nue Traffic Impact Study August 22, 2016 Contents Traffic Impact Study Page Preparer Qualifications... 1 Introduction... 2 Existing Roadway Conditions... 5 Existing Traffic Conditions...
More informationTransportation Impact Study for Abington Terrace
Transportation Impact Study for Abington Terrace Abington Township, Montgomery County, PA Sandy A. Koza, P.E., PTOE PA PE License Number PE059911 Prepared by McMahon Associates, Inc. 425 Commerce Drive,
More informationMeadowlake Ranch Traffic Impact Analysis (LSC #184600) August 27, 2018
LSC TRANSPORTATION CONSULTANTS, INC. 545 East Pikes Peak Avenue, Suite 210 Colorado Springs, CO 80903 (719) 633-2868 FAX (719) 633-5430 E-mail: lsc@lsctrans.com Website: http://www.lsctrans.com Traffic
More informationList of Attachments. Location Map... Site Plan... City of Lake Elsinore Circulation Element... City of Lake Elsinore Roadway Cross-Sections...
List of Attachments Exhibits Location Map... Site Plan... City of Lake Elsinore Circulation Element... City of Lake Elsinore Roadway Cross-Sections... Existing Lane Geometry and Traffic Controls... Existing
More informationTraffic Impact Study Little Egypt Road Development Denver, North Carolina June 2017
Traffic Impact Study Little Egypt Road Development Denver, North arolina June 2017 N. Little Egypt Road DQ\ QDQFLQJ VDOHV RU RWKHU SHUIRUPDQFH EDVHG FULWHULD Proposed Site Driveways Site Driveway 1 TRAFFI
More informationTHIS PAGE LEFT BLANK INTENTIONALLY
GA SR 25 Spur at Canal Road Transportation Impact Analysis PREPARED FOR GLYNN COUNTY, GEORGIA 1725 Reynolds Street, Suite 300 Brunswick, Georgia 31520 PREPARED BY 217 Arrowhead Boulevard Suite 26 Jonesboro,
More informationChapter 4 Traffic Analysis
Chapter 4 Traffic Analysis PURPOSE The traffic analysis component of the K-68 Corridor Management Plan incorporates information on the existing transportation network, such as traffic volumes and intersection
More informationTraffic Circulation Study for Neighborhood Southwest of Mockingbird Lane and Airline Road, Highland Park, Texas
ARIZONA TEXAS NEW MEXICO OKLAHOMA February 13, 2015 Mr. Meran Dadgostar P.E., R.S. Town of Highland Park 4700 Drexel Dr. Highland Park, Texas 75205 Re: Traffic Circulation Study for Neighborhood Southwest
More informationWalmart (Store # ) 60 th Street North and Marion Road Sioux Falls, South Dakota
Walmart (Store #4865-00) 60 th Street North and Marion Road Sioux Falls, South Dakota Prepared for: Wal-Mart Stores, Inc. Bentonville, Arkansas Prepared by: Kimley-Horn and Associates, Inc. ã2013 Kimley-Horn
More informationHenderson Avenue Mixed-Use Development
Zoning Case: Z145-3 Traffic Impact Analysis Henderson Avenue Mixed-Use Development Dallas, TX October 26 th, 216 Kimley-Horn and Associates, Inc. Dallas, Texas Project #644827 Registered Firm F-928 Traffic
More informationEXECUTIVE SUMMARY. Page 1 of 6
EXECUTIVE SUMMARY The purpose of this report is to identify conformance with the original traffic impact study for the proposed retail development on Lot 5 of Riverdale Retail Filing No. 1 located on the
More informationWaterford Lakes Small Area Study
Waterford Lakes Small Area Study Existing Traffic Conditions PREPARED FOR: ORANGE COUNTY PUBLIC WORKS DEPARTMENT TRAFFIC ENGINEERING DIVISION ORLANDO, FLORIDA PREPARED WITH: INWOOD CONSULTING ENGINEERS
More informationTRANSPORTATION ANALYSIS REPORT US Route 6 Huron, Erie County, Ohio
TRANSPORTATION ANALYSIS REPORT US Route 6 Huron, Erie County, Ohio December 12, 2012 Prepared for: The City of Huron 417 Main Huron, OH 44839 Providing Practical Experience Technical Excellence and Client
More informationDonahue Drive Corridor Traffic Operational Evaluation
Donahue Drive Corridor Traffic Operational Evaluation PREPARED FOR: THE CITY OF AUBURN PREPARED BY: JANUARY 2007 Donahue Drive Corridor Study--Auburn, Alabama TABLE OF CONTENTS Introduction... 1 Background
More informationShockoe Bottom Preliminary Traffic and Parking Analysis
Shockoe Bottom Preliminary Traffic and Parking Analysis Richmond, Virginia August 14, 2013 Prepared For City of Richmond Department of Public Works Prepared By 1001 Boulders Pkwy Suite 300, Richmond, VA
More informationTRAFFIC IMPACT STUDY. Creekside Thornton, Colorado. For. August 2015 November 2015 Revised: August Prepared for:
TRAFFIC IMPACT STUDY For Creekside Thornton, Colorado August 215 November 215 Revised: August 216 Prepared for: Jansen Strawn Consulting Engineers 45 West 2 nd Avenue Denver, Colorado 8223 Prepared by:
More informationEvaluation of M-99 (Broad Street) Road Diet and Intersection Operational Investigation
Evaluation of M-99 (Broad Street) Road Diet and Intersection Operational Investigation City of Hillsdale, Hillsdale County, Michigan June 16, 2016 Final Report Prepared for City of Hillsdale 97 North Broad
More informationTRAFFIC IMPACT STUDY And A TRAFFIC SIGNAL WARRANT ANALYSIS FOR A SENIOR LIVING AND APARTMENT DEVELOPMENT
TRAFFIC IMPACT STUDY And A TRAFFIC SIGNAL WARRANT ANALYSIS FOR A SENIOR LIVING AND APARTMENT DEVELOPMENT DEERFIELD TOWNSHIP, WARREN COUNTY, OHIO Nantucket Circle and Montgomery Road () Prepared for: ODLE
More informationDUNBOW ROAD FUNCTIONAL PLANNING
DUNBOW ROAD FUNCTIONAL PLANNING Final Report August 3, 216 #31, 316 5th Avenue NE Calgary, AB T2A 6K4 Phone: 43.273.91 Fax: 43.273.344 wattconsultinggroup.com Dunbow Road Functional Planning Final Report
More informationSubject: Solberg Avenue / I-229 Grade Separation: Traffic Analysis
MEMORANDUM Transportation Bill Troe, AICP Jason Carbee, AICP 12120 Shamrock Plaza Suite 300 Omaha, NE 68154 (402) 334-8181 (402) 334-1984 (Fax) To: Project File Date: Subject: Solberg Avenue / I-229 Grade
More informationPINESTONE TRAFFIC IMPACT STUDY Travelers Rest, South Carolina
PINESTONE TRAFFIC IMPACT STUDY Travelers Rest, South Carolina Prepared for Longbranch Development Prepared by January 13, 219 ii Table of Contents Subject Page Signature Page... i Table of Contents...
More information6060 North Central Expressway Mixed-Use Site Dallas, Texas
Volume 1 Traffic Impact Analysis 6060 North Central Expressway Mixed-Use Site Dallas, Texas April 30, 2018 Kimley-Horn and Associates, Inc. Dallas, Texas Project #063238300 Registered Firm F-928 Traffic
More informationTraffic Impact Statement
Traffic Impact Statement Mixed Use Development, US 41 and Old Trail Drive aka Tide-Starbucks 4900 9 th Street North General Development Site Plan (GDSP) Collier County, FL 10/6/2015 Prepared for: Prepared
More informationGlenn Avenue Corridor Traffic Operational Evaluation
Glenn Avenue Corridor Traffic Operational Evaluation PREPARED FOR: THE CITY OF AUBURN PREPARED BY: DECEMBER 2007 Glenn Avenue Corridor Study--Auburn, Alabama TABLE OF CONTENTS Introduction... 1 Background
More informationEAST AND SOUTH STREET CITY OF ANAHEIM, CALIFORNIA
T R A F F I C I M P A C T A N A LY S I S EAST AND SOUTH STREET CITY OF ANAHEIM, CALIFORNIA April 217 T R A F F I C I M P A C T A N A LY S I S EAST AND SOUTH STREET CITY OF ANAHEIM, CALIFORNIA Submitted
More informationHighway 111 Corridor Study
Highway 111 Corridor Study June, 2009 LINCOLN CO. HWY 111 CORRIDOR STUDY Draft Study Tea, South Dakota Prepared for City of Tea Sioux Falls Metropolitan Planning Organization Prepared by HDR Engineering,
More informationProject Report. South Kirkwood Road Traffic Study. Meadows Place, TX October 9, 2015
Meadows Place, TX October 9, 2015 Contents 1 Introduction... 1 2 Data Collection... 1 3 Existing Roadway Network... 2 4 Traffic Volume Development... 2 5 Warrant Analysis... 3 6 Traffic Control Alternative
More informationTRAFFIC IMPACT STUDY COMPREHENSIVE UPDATE TOWN OF THOMPSON S STATION, TENNESSEE PREPARED FOR: THE TOWN OF THOMPSON S STATION
TRAFFIC IMPACT STUDY COMPREHENSIVE UPDATE TOWN OF THOMPSON S STATION, TENNESSEE PREPARED FOR: THE TOWN OF THOMPSON S STATION Transportation Consultants, LLC 1101 17 TH AVENUE SOUTH NASHVILLE, TN 37212
More informationALLEY 24 TRAFFIC STUDY
ALLEY 24 TRAFFIC STUDY in City of Frostburg, Maryland January 2013 3566 Teays Valley Road Hurricane, WV Office: (304) 397-5508 www.denniscorporation.com Alley 24 Traffic Study January 2013 Frostburg, Maryland
More information1609 E. FRANKLIN STREET HOTEL TRAFFIC IMPACT STUDY EXECUTIVE SUMMARY
1609 E. FRANKLIN STREET HOTEL TRAFFIC IMPACT STUDY EXECUTIVE SUMMARY Prepared for: The Town of Chapel Hill Public Works Department Traffic Engineering Division Prepared by: HNTB North Carolina, PC 343
More informationMarina Loft (DRC 51-R-12)
Marina Loft (DRC 51-R-12) traffic study prepared for: Cymbal Development OCtober 2012 Traf Tech October 1, 2012 Mr. Asi Cymbal - President Cymbal Development 3470 North Miami Avenue Upper Suite Miami,
More informationTraffic Impact Study. Roderick Place Columbia Pike Thompson s Station, TN. Transportation Group, LLC Traffic Engineering and Planning
F i s c h b a c h Transportation Group, LLC Traffic Engineering and Planning Traffic Impact Study Roderick Place Columbia Pike Thompson s Station, TN Prepared March 2016 Ms. Gillian L. Fischbach, P.E.,
More informationTroutbeck Farm Development
Troutbeck Farm Development Willistown Township, Chester County PA For Submission To: Willistown Township Last Revised: October, 4 TPD# INLM.A. 5 E. High Street Suite 65 Pottstown, PA 9464 6.36.3 TPD@TrafficPD.com
More informationFINAL Albertville Business Park AUAR Update Traffic Study
FINAL Albertville Business Park AUAR Update Traffic Study Prepared for City of Albertville, MN July 20, 2017 SRF No. 10060.00 Table of Contents Introduction... 1 Existing Conditions... 1 Data Collection...
More informationDraft Report. Traffic Impact Study. Superstore, Wal-Mart, and Kent Development. Yarmouth, Nova Scotia. Prepared for
oad & Traffic Management Road & Traffic Management R Atlantic Traffic Engineering Specialists Draft Report Traffic Impact Study Superstore, Wal-Mart, and Kent Development Yarmouth, Nova Scotia Prepared
More informationTRAFFIC STUDY GUIDELINES Clarksville Street Department
TRAFFIC STUDY GUIDELINES Clarksville Street Department 9/1/2009 Introduction Traffic studies are used to help the city determine potential impacts to the operation of the surrounding roadway network. Two
More informationTRAFFIC IMPACT STUDY CRITERIA
Chapter 6 - TRAFFIC IMPACT STUDY CRITERIA 6.1 GENERAL PROVISIONS 6.1.1. Purpose: The purpose of this document is to outline a standard format for preparing a traffic impact study in the City of Steamboat
More informationAppendix C. NORTH METRO STATION AREA TRAFFIC IMPACT STATEMENT 88th Avenue Station
Appendix C NORTH METRO STATION AREA TRAFFIC IMPACT STATEMENT 88th Avenue Station Prepared for: Regional Transportation Department and URS Corporation as part of the North Metro EIS David Evans and Associates,
More informationKing Soopers #116 Thornton, Colorado
Traffic Impact Study King Soopers #116 Thornton, Colorado Prepared for: Galloway & Company, Inc. 1.0 EXECUTIVE SUMMARY King Soopers #116, a grocery marketplace anchored commercial development, is proposed
More informationVolume 1 Traffic Impact Analysis. Texas Odyssey TIA Dallas, Texas. Kimley-Horn and Associates, Inc. Dallas, Texas. May 23, 2018
Volume 1 Traffic Impact Analysis Texas Odyssey TIA Dallas, Texas May 23, 2018 Kimley-Horn and Associates, Inc. Dallas, Texas Project #064529800 Registered Firm F-928 Traffic Impact Analysis Texas Odyssey
More informationBistro 6. City of Barrie. Traffic Impact Study for Pratt Hansen Group Inc. Type of Document: Final Report. Project Number: JDE 1748
City of Barrie Traffic Impact Study for Pratt Hansen Group Inc. Type of Document: Final Report Project Number: JDE 1748 Date Submitted: June 12 th, 2017 06/12/17 John Northcote, P.Eng. Professional License
More informationMEETING FACILITY 2901 GIBFORD DRIVE CITY OF OTTAWA TRANSPORTATION BRIEF. Prepared for: Holiday Inn Express 2881 Gibford Drive Ottawa, ON K1V 2L9
MEETING FACILITY 2901 GIBFORD DRIVE CITY OF OTTAWA TRANSPORTATION BRIEF Prepared for: Holiday Inn Express 2881 Gibford Drive Ottawa, ON K1V 2L9 December 18, 2012 112-566 Brief_1.doc D. J. Halpenny & Associates
More informationFigure 1: Vicinity Map of the Study Area
ARIZONA TEXAS NEW MEXICO OKLAHOMA May 5, 2016 Mr. Anthony Beach, P.E. BSP Engineers 4800 Lakewood Drive, Suite 4 Waco, Texas 76710 Re: Intersection and Access Analysis along Business 190 in Copperas Cove
More informationList of Exhibits...ii
One Brickell Traffic Study TABLE OF CONTENTS List of Exhibits...ii EXECUTIVE SUMMARY...1 1. INTRODUCTION...2 1.1 Study Area...2 1.2 Study Objective...5 2. EXISTING TRAFFIC CONDITIONS...6 2.1 Data Collection...6
More informationREDEVELOPMENT TRAFFIC IMPACT STUDY
REDEVELOPMENT TRAFFIC IMPACT STUDY For Wendy s Parker, Colorado January 215 Prepared for: Sterling Design Associates, LLC 29 W. Littleton Boulevard #3 Littleton, Colorado 812 Prepared by: 1233 Airport
More informationINDUSTRIAL BUILDING 3009 HAWTHORNE ROAD CITY OF OTTAWA TRANSPORTATION OVERVIEW REVISED. Prepared for: Canada Inc.
INDUSTRIAL BUILDING 3009 HAWTHORNE ROAD CITY OF OTTAWA TRANSPORTATION OVERVIEW REVISED Prepared for: 7849648 Canada Inc. Octiober 1, 2015 114-598 Overview_2.doc D. J. Halpenny & Associates Ltd. Consulting
More informationRoad Conversion Study Plumas Street
Plumas Street Phase I Submitted to The Regional Transportation Commission of Washoe County Submitted by Zong Tian, Ph.D., P.E. Saeedeh Farivar Haiyuan Li, Ph.D. Center for Advanced Transportation Education
More informationTRAFFIC IMPACT ANALYSIS
TRAFFIC IMPACT ANALYSIS FOR THE CHAMPAIGN UNIT#4 SCHOOL DISTRICT PROPOSED HIGH SCHOOL (SPALDING PARK SITE) IN THE CITY OF CHAMPAIGN Final Report Champaign Urbana Urbanized Area Transportation Study 6/24/2014
More informationOTTAWA TRAIN YARDS PHASE 3 DEVELOPMENT CITY OF OTTAWA TRANSPORTATION IMPACT STUDY. Prepared for:
OTTAWA TRAIN YARDS PHASE 3 DEVELOPMENT CITY OF OTTAWA TRANSPORTATION IMPACT STUDY Prepared for: The Ottawa Train Yards Inc. 223 Colonnade Road South, Suite 212 Nepean, Ontario K2E 7K3 January 17, 2012
More informationFINAL DESIGN TRAFFIC TECHNICAL MEMORANDUM
FINAL DESIGN TRAFFIC TECHNICAL MEMORANDUM July 2014 FINAL (SR 43) Project Development and Environment Study From State Road 60 (Adamo Drive) to I-4 (SR 400) Hillsborough County, Florida Work Program Item
More informationOFFICE/RETAIL DEVELOPMENT 1625 BANK STREET OTTAWA, ONTARIO TRANSPORTATION BRIEF. Prepared for: Canada Inc.
OFFICE/RETAIL DEVELOPMENT 1625 BANK STREET OTTAWA, ONTARIO TRANSPORTATION BRIEF Prepared for: 9402209 Canada Inc. December 15, 2015 115-625 Report_2.doc D. J. Halpenny & Associates Ltd. Consulting Transportation
More informationIntersection of Massachusetts Avenue and Maple Street in Lexington Signalized Intersection and Roundabout Comparison
Intersection of Massachusetts Avenue and Maple Street in Lexington Signalized Intersection and Roundabout Comparison Michael Wallwork, Roundabout Expert, Orange Park, Florida Tom Bertulis (MS, PE, PTOE),
More informationCapital Region Council of Governments
March 23, 2018 Capital Region Council of Governments PROJECT CONCEPT REPORT Realignment of Swamp and Northfield Road s approaches to Route 44 (Boston Turnpike) Town of Coventry SUMMARY: The Town of Coventry
More informationTechnical Memorandum TRAFFIC IMPACT STUDY. RIDLEY ROAD CONVENIENCE STORE Southampton County, VA. Prepared for: Mr. David Williams.
Technical Memorandum TRFFIC IMPCT STUDY RIDLEY ROD CONVENIENCE STORE Southampton County, V Prepared for: Mr. David Williams By: Charles Smith, P.E., PTOE EPR Charlottesville, V July 2014 1 TBLE OF CONTENTS
More informationExisting Conditions. Date: April 16 th, Dan Holderness; Coralville City Engineer Scott Larson; Coralville Assistant City Engineer
Date: April 16 th, 2015 To: From: Re: Dan Holderness; Coralville City Engineer Scott Larson; Coralville Assistant City Engineer Darian Nagle-Gamm, Traffic Engineering Planner Highway 6 (2 nd Street) /
More informationTRANSPORTATION IMPACT STUDY PROPOSED RIVERFRONT 47 MIXED USE DEVELOPMENT
November 2016 TRANSPORTATION IMPACT STUDY PROPOSED RIVERFRONT 47 MIXED USE DEVELOPMENT & Aspinwall Borough, Sharpsburg Borough & O Hara Township, Allegheny County, Pennsylvania Prepared for: Riverfront
More informationQueensgate Drive Corridor Traffic Study
January 2015 Prepared for: City of Richland Prepared by: J-U-B ENGINEERS, Inc. 2810 W. Clearwater Avenue, Suite 201 Kennewick, Washington 99336 Table of Contents Introduction and Background... 1 Existing
More informationNO BUILD TRAFFIC OPERATIONS
3. 23 NO BUILD TRAFFIC OPERATIONS This section addresses the operations of the transportation system and details how it would be expected to function under year 23 No Build conditions with the projected
More informationTraffic Impact Study. Westlake Elementary School Westlake, Ohio. TMS Engineers, Inc. June 5, 2017
TMS Engineers, Inc. Traffic Impact Study Westlake Elementary School Westlake, Ohio June 5, 2017 Prepared for: Westlake City Schools - Board of Education 27200 Hilliard Boulevard Westlake, OH 44145 TRAFFIC
More informationTABLE TRAFFIC ANALYSIS SCENARIOS
4.11 TRANSPORTATION The potential traffic impacts of the proposed project are evaluated in the Buena Park Beach/Orangethorpe Mixed Use Project Traffic Analysis (Traffic Analysis) by Austin-Foust Associates
More informationTraffic Study North Shore School District 112
Traffic Study North Shore School District 112 Proposed Expansion of Northwood Junior High School Prepared By: May 1, 2015 1. Introduction Kenig, Lindgren, O Hara, Aboona, Inc. (KLOA, Inc.) has been retained
More informationQUICKIE C STORE AND GAS BAR 1780 HERON ROAD OTTAWA, ONTARIO TRANSPORTATION BRIEF. Prepared for:
QUICKIE C STORE AND GAS BAR 1780 HERON ROAD OTTAWA, ONTARIO TRANSPORTATION BRIEF Prepared for: Quickie Convenience Stores Larny Holdings Ltd. c/o PBC Group April 15, 2015 115-615 Report_1.doc D. J. Halpenny
More informationT$- RIB Endineering, ac
T$- RIB Endineering, ac..' Transportation Endineerimg Solutions Transportation Impact Study Vineyard-Goldelm Fort Collins, Colorado February 2016 Vineyard-Goldelm Transportation Impact Study Fort Collins,
More informationNEW YORK CENTRAL PARK SUBDIVISION BLAIS STREET/ST-PIERRE STREET EMBRUN, ONTARIO TRAFFIC IMPACT STUDY. Prepared for:
NEW YORK CENTRAL PARK SUBDIVISION BLAIS STREET/ST-PIERRE STREET EMBRUN, ONTARIO TRAFFIC IMPACT STUDY Prepared for: Solidex Holdings Limited & Investissement Maurice Lemieux Investments Attn: Mr. Anthony
More informationM-58 HIGHWAY ACCESS MANAGEMENT STUDY Mullen Road to Bel-Ray Boulevard. Prepared for CITY OF BELTON. May 2016
M-58 HIGHWAY ACCESS MANAGEMENT STUDY Prepared for CITY OF BELTON By May 2016 Introduction Missouri State Highway 58 (M-58 Highway) is a major commercial corridor in the City of Belton. As development has
More informationMEMORANDUM. Matt Folden, AICP, MNCPPC Rebecca Torma, MCDOT. Nancy Randall, AICP, PTP Barbara Mosier, P.E., PTOE Kevin Berger
To: From: Matt Folden, AICP, MNCPPC Rebecca Torma, MCDOT Nancy Randall, AICP, PTP Barbara Mosier, P.E., PTOE Kevin Berger 1110 Bonifant Street Suite 210, Silver Spring, MD 20910 301-448-1333 WellsandAssociates.com
More informationTABLE OF CONTENTS TABLE OF CONTENTS... I APPENDICES... III LIST OF EXHIBITS... V LIST OF TABLES... VII LIST OF ABBREVIATED TERMS...
TABLE OF CONTENTS TABLE OF CONTENTS... I APPENDICES... III LIST OF EXHIBITS... V LIST OF TABLES... VII LIST OF ABBREVIATED TERMS... IX 1 INTRODUCTION... 1 1.1 Project Overview... 1 1.2 Analysis Scenarios...
More informationLIBERTY TREE ACADEMY TRAFFIC IMPACT STUDY
LIBERTY TREE ACADEMY TRAFFIC IMPACT STUDY Prepared for: Liberty Tree Academy Prepared by: 161 Blake Street, Suite 2 Denver, Colorado 822 Contact: David Kline, PE, PTOE (33)-572-2 On Behalf of: Liberty
More informationFORM A PASCO COUNTY ACCESS CONNECTION PERMIT APPLICATION
FORM 901.3.A PASCO COUNTY ACCESS CONNECTION PERMIT APPLICATION The following information is required from all applicants directly or indirectly accessing any collector or arterial road or as otherwise
More informationCarMax Auto Superstore/ Reconditioning Center #6002 Murrieta, California
CarMax Auto Superstore/ Reconditioning Center #6002 Murrieta, California TUSTIN 17782 17th Street Suite 200 Tustin, CA 92780-1947 714.665.4500 Fax: 714.665.4501 LOS ANGELES 145 S. Spring Street Suite 120
More informationDRAFT. Corridor study. Honeysuckle Road. October Prepared for the City of Dothan, AL. Prepared by Gresham, Smith and Partners
DRAFT Corridor study Honeysuckle Road October 2017 Prepared for the City of Dothan, AL Prepared by TABLE OF CONTENTS SECTION I... 1 STUDY SUMMARY... 1 INTRODUCTION... 1 CONCLUSIONS... 5 SECTION II... 7
More informationTraffic Impact Study for Rolling Ridge Redevelopment
Traffic Impact Study for Rolling Ridge Redevelopment Webster Groves, Missouri October 19, 2018 Prepared For: Gershman Commercial Real Estate 150 North Meramec Avenue Suite 500 St. Louis, Missouri 63105
More informationjoint access drive. will be
Date: To: From: Subject: June 22, 2015 Bradley Reiner, PE Bowman Consulting David R. Kline, PE, PTOE, Incline Associates Thornton Self-Storage Traffic Analysis (DRAFT) - Thornton, Colorado INTRODUCTION
More informationTruck Climbing Lane Traffic Justification Report
ROUTE 7 (HARRY BYRD HIGHWAY) WESTBOUND FROM WEST MARKET STREET TO ROUTE 9 (CHARLES TOWN PIKE) Truck Climbing Lane Traffic Justification Report Project No. 6007-053-133, P 101 Ι UPC No. 58599 Prepared by:
More informationClay Street Realignment Project Traffic Study
Final Clay Street Realignment Project Traffic Study November 24, 2009 Prepared for: City of Placerville RS07-2466 2990 Lava Ridge Court, Suite 200 Roseville, CA 95661 (916) 773-1900 Fax (916) 773-2015
More informationGateway Transportation Study
Gateway Transportation Study Amherst, Massachusetts SUBMITTED TO University of Massachusetts Amherst Town of Amherst SUBMITTED BY Vanasse Hangen Brustlin, Inc. Watertown, Massachusetts March 213 Back of
More informationSTILLWATER AVENUE CORRIDOR STUDY Old Town, Maine
Draft Study STILLWATER AVENUE CORRIDOR STUDY Old Town, Maine SUBMITTED TO: BANGOR AREA COMPREHENSIVE TRANSPORTATION SYSTEM SUBMITTED BY: I MAY 23, 2017 DRAFT STILLWATER AVENUE STUDY FINAL REPORT Table
More informationMEMORANDUM. Charlotte Fleetwood, Transportation Planner
MEMORANDUM Date: Updated August 22, 2017 To: Organization: Charlotte Fleetwood, Transportation Planner Boston Transportation Department From: Jason DeGray, P.E., PTOE, Regional Director of Engineering
More information1609 E. FRANKLIN STREET HOTEL
1609 E. FRANKLIN STREET HOTEL TRAFFIC IMPACT STUDY Prepared for: The Town of Chapel Hill Public Works Department Traffic Engineering Division Prepared by: HNTB North Carolina, PC 343 East Six Forks Road
More informationINDUSTRIAL BUILDING 1660 COMSTOCK ROAD CITY OF OTTAWA TRANSPORTATION OVERVIEW. Prepared for:
INDUSTRIAL BUILDING 1660 COMSTOCK ROAD CITY OF OTTAWA TRANSPORTATION OVERVIEW Prepared for: Simluc Contractors Limited 2550 Blackwell Street, Ottawa K1B 5R1 October 18, 2013 113-584 Overview_1.doc D. J.
More informationTRAFFIC IMPACT ANALYSIS
TRAFFIC IMPACT ANALYSIS DRAFT 4401 BARCLAY DOWNS DRIVE Barclay Downs Drive Bet. Carnegie Boulevard & Bulfinch Road Charlotte, North Carolina REZONING PETITION #TBD for ZOM Carolinas June 2016 629-001 (C-2165)
More informationIntersection Traffic Control Feasibility Study
Intersection Traffic Control Feasibility Study CSAH 9 at CSAH 60 (185th Avenue) Prepared For: Dakota County Transportation Department Western Service Center 14955 Galaxie Avenue, 3rd Floor Apple Valley,
More informationTRAFFIC IMPACT REPORT CASTLE PINES APARTMENTS CASTLE PINES, COLORADO
TRAFFIC IMPACT REPORT CASTLE PINES APARTMENTS CASTLE PINES, COLORADO APRIL 12, 218 REV. JULY 16, 218 Prepared for: Davis Development 43 Corporate Center Dr Suite 21 Stockbridge, GA 3281 Prepared by: 112
More informationThe current document is revised based on the comments received on:
General Overview 1 Introduction Over the last several years, the Waterford Lakes area has experienced increased congestion due to a substantial increase in residential and commercial development. The current
More informationAbrams Associates. Transportation Impact Analysis. City of Rocklin. Prepared for: David Mohlenbrok City of Rocklin 4081 Alvis Court Rocklin, CA 95677
Transportation Impact Analysis Sierra College Boulevard Commercial Project City of Rocklin Prepared for: David Mohlenbrok City of Rocklin 081 Alvis Court Rocklin, CA 95677 Prepared by: 1875 Olympic Boulevard,
More informationDIMARCO CANANDAIGUA PROPERTIES HOUSING PROJECT CANANDAIGUA, ONTARIO COUNTY, NEW YORK
TRAFFIC IMPACT STUDY FOR THE DIMARCO CANANDAIGUA PROPERTIES HOUSING PROJECT CANANDAIGUA, ONTARIO COUNTY, NEW YORK MARCH 14, 2017 PREPARED FOR: 1950 Brighton Henrietta Town Line Rd Rochester, NY 14623 PREPARED
More informationTable of Contents FIGURES TABLES APPENDICES. Traffic Impact Study Hudson Street Parking Garage MC Project No.: A Table of Contents
Traffic Impact Study Hudson Street Parking Garage MC Project No.: 151714A Table of Contents Table of Contents I. INTRODUCTION... 2 II. EXISTING CONDITIONS... 5 III. 215 EXISTING TRAFFIC CONDITIONS... 6
More information4.0 TRANSPORTATION SYSTEMS
Transportation Systems 4.0 TRANSPORTATION SYSTEMS This chapter examines the impacts of the Central Corridor Extension on existing roadways and traffic operations and discusses the transit service, operations,
More informationFigure 1: East West Connector Alignment Alternatives Concept Drawing
Page 2 of 9 Figure 1: East West Connector Alignment Alternatives Concept Drawing The Montebello Drive extension will run north south and connect Wilsonville Road to the Boones Ferry Road to Brown Road
More informationD.13 Transportation and Traffic
This section addresses transportation and traffic issues and impacts related to the Proposed Project. Section D.13.1 provides a description of the affected environment for the Proposed Project. Applicable
More informationMEMORANDUM. DATE March 1, 2012 TO Town of Milton Mark Abbott, Seth Asante, and Efi Pagitsas Boston Region MPO Staff
MEMORANDUM DATE March 1, 212 TO Town of Milton FROM RE Mark Abbott, Seth Asante, and Efi Pagitsas Boston Region MPO Staff FFY 211 Safety and Operations Analyses at Selected Boston Region MPO Intersections:
More informationAPPENDIXB. Traffic Operations Technical Memorandum
APPENDIXB Traffic Operations Technical Memorandum Environmental Assessment - Lincoln County, SD 85 th Street: Sundowner Avenue to Louise Avenue November 2017 MEMORANDUM Transportation Jim Kollbaum, PE
More informationMagnolia Place. Traffic Impact Analysis. Prepared for: City of San Mateo. Prepared by: Hexagon Transportation Consultants, Inc.
Magnolia Place Traffic Impact Analysis Prepared for: City of San Mateo Prepared by: Hexagon Transportation Consultants, Inc. Updated January 4, 2010 Table of Contents 1. Introduction...1 2. Existing Conditions...6
More informationAtlanta Braves Stadium and Mixed- Use Development
Transportation Analysis Atlanta Braves Stadium and Mixed- Use Development DRI #2381 Cobb County, Georgia Prepared for: BRED Co., LLC Prepared by: Kimley-Horn and Associates, Inc. 817 West Peachtree Street
More informationHILTON GARDEN INN HOTEL HOTEL EXPANSION 2400 ALERT ROAD, OTTAWA TRANSPORTATION BRIEF. Prepared for:
HILTON GARDEN INN HOTEL HOTEL EXPANSION 2400 ALERT ROAD, OTTAWA TRANSPORTATION BRIEF Prepared for: Bona Building & Management Co. Ltd. Place Vanier, 333 North River Road Vanier, Ontario K1L 8B9 October
More information4. ENVIRONMENTAL IMPACT ANALYSIS 9. TRANSPORTATION AND TRAFFIC
4. ENVIRONMENTAL IMPACT ANALYSIS 9. TRANSPORTATION AND TRAFFIC 4.9.1 INTRODUCTION The following section addresses the Proposed Project s impact on transportation and traffic based on the Traffic Study
More information