D.13 Transportation and Traffic

Size: px
Start display at page:

Download "D.13 Transportation and Traffic"

Transcription

1 This section addresses transportation and traffic issues and impacts related to the Proposed Project. Section D.13.1 provides a description of the affected environment for the Proposed Project. Applicable transportation and traffic regulations are described in Section D Significance criteria and analyses of the Proposed Project impacts and proposed mitigation are presented in Sections D The analysis of project alternatives, including the no project alternative, are included below as Sections D.13.4 through D The purpose of this Traffic Impact Analysis (TIA) is to identify and analyze the impacts to the traffic if the proposed Liberty XXIII Renewable Energy Power Plant is developed. The objectives of this study are to: Review the current traffic conditions; Project and analyze future traffic conditions, with and without the project; Compare the with/without traffic situations; Identify traffic impacts that are created by the project; and Propose mitigation for any impacts. D.13.1 Environmental Setting The project site is located along the south side of Westward Avenue, east of the intersection with South Hathaway Street, in the City of Banning, County of Riverside, California. The site is just south of the Banning Municipal Airport and Interstate 10 (I-10). I-10 is under the jurisdiction of the California Department of Transportation (Caltrans). The site is located on 20.3 acres across three parcels. The Assessor s Parcel Numbers are , , and The project site spans partially across all three parcels (all of 034, ½ of 035, all of 038-lot 16 and ½ of 038-lot 15). Tractor-trailer trucks will access the site from the north side along Westward Avenue and a private paved road will be constructed from the current end of pavement on Westward Avenue to the site. Existing Roadway Facilities There are four main roadways within the project study area. East Lincoln Street. East Lincoln Street is currently a two-lane roadway which extends east to west through study area. Within the study area, it intersects with South Hargrave Street and South Hathaway Street. Adjacent land uses along East Lincoln Street between Hargrave Street and Hathaway Street include residential and several existing churches. Also, the Banning Municipal Airport s runway runs north of East Lincoln Street as it approaches South Hathaway Street. The roadway is designated as a major highway in the City of Banning Circulation Element. South Hargrave Street. South Hargrave Street is currently a two-lane roadway which extends north to south through the study area. Within the study area, the roadway has an interchange with the I-10, providing access to both east and west. Adjacent land uses along South Hargrave Street include commercial convenience just north of the interchange, and between Lincoln and the I-10 interchange, there is residential to the west and industrial to the east. The roadway is designated as a secondary highway in the City of Banning Circulation Element. South Hathaway Street. South Hathaway Street is currently a two-lane roadway which extends north to south through the study area. Within the study area, the roadway intersects East Lincoln Street and Westward Avenue. Adjacent land uses along South Hathaway Street include residential to the west and industrial to the Draft EIR D.13-1 June 2008

2 east. The roadway is planned to be a secondary highway at buildout according to the City of Banning Circulation Element. Westward Avenue. Westward Avenue is currently a two-lane roadway which extends east to west through the study area. Within the study area, the roadway intersects South Hathaway Street and also borders the north side of the project site and provides access into the Liberty XXIII Biofuels Power, LLC (Liberty Energy) facility. The City has plans to extend the roadway east to Cottonwood Road where there are plans to build an additional interchange with the I-10 freeway. The added interchange at Cottonwood will help alleviate congestion at the Hargrave interchange. Existing Bus Transit Facilities Pass Transit provides bus service within the study. There is one bus route which operates within the study area. Route 6 Southern provides service from the Kmart Garden Center on Sunlakes Boulevard within the city limits to Sunset Avenue and West Ramsey Street. Service is provided on one-hour headways on weekdays from 6:00 AM to 7:00 PM. Bicycle/Pedestrian Network There are no existing bicycle facilities located within the project study area. There are no sidewalks along the project frontage, but there are intermittent sidewalks along other roadways within the study area. Traffic Data Collection and Intersection Operations Traffic counts at three existing intersections were collected in November and December These counts are summarized in Figure D As shown in Table D , all intersections operate at LOS C or better during the peak hours, except for the interchanges with the I-10 Eastbound at Hargrave Street. The LOS threshold currently applied by the City of Banning is LOS C, except where LOS D is allowed at interchanges with I-10. Table D Intersection Levels of Service - Existing Conditions Intersection Control AM Peak Hour PM Peak Hour Delay LOS Delay LOS S. Hathaway Street/ Unsignalized 2.6 A 2.3 A Westward Avenue S. Hargrave Street/ E. Unsignalized 8.5 A 8.6 A Lincoln Street S. Hargrave Street/ I-10 Unsignalized >50 F 18.2 C Eastbound Ramps S. Hargrave Street/ I-10 Westbound Ramps Unsignalized 16.1 C 16.3 C Notes: Average delay reported in seconds per vehicle. For side-street stop controlled intersection worst case movement delay reported. HCM 2000 methodology employed. LOS= Level of Service Source: Fehr & Peers, The Existing Roadway Segment LOS is shown in Table D Table D Roadway Segment Daily Level of Service- Existing Conditions Roadway Segment Classification (Number of Existing LOS C Capacity Lanes) ADT LOS C or Better South Hargrave Street north of East Secondary Highway (2) 24,000 15,140 Yes Lincoln Street East Lincoln Street Major Highway (2) 30,400 1,520 Yes South Hathaway Street Collector (2) 12, Yes Westward Avenue Collector (2) 12, Yes Notes: ADT = Average Daily Traffic June 2008 D.13-2 Draft EIR

3 PREPARED BY Aspen Environmental Group Source: Fehr & Peers, 2008 Figure D.13-1 Existing Traffic Counts June 2008 D.13-3 Draft EIR

4 D.13.2 Applicable Regulations, Plans, and Standards D Local City of Banning The local regulations that apply in the City of Banning include the policies outlined in the City of Banning General Plan as well as requirements listed in the Riverside County Transportation Department Traffic Impact Analysis Preparation Guide. Intersection Analysis The Riverside County Transportation Department (RCTD) requires the use of the Transportation Research Board Highway Capacity Manual (HCM), 2000 update. Unsignalized intersections are required to be analyzed using Chapter 17 of the Highway Capacity Manual. Analysis Scenarios The RCTD requires that all traffic impact analysis include the following scenarios: Existing Traffic, Project Completion, Cumulative, and Project Phasing (if the project is proposed to be built in phases). Relevant Policies in the Circulation Element of the City of Banning s General Plan include: Policy 6: The City shall maintain peak hour Level of Service C or better on all local intersections, except those on Ramsey Street and at I-10 interchanges, where Level of Service D or better shall be maintained. Policy 7: New development proposals shall pay their fair share for the improvement of street within and surrounding their project on which they have an impact, including roadways, bridges, grade separations, and traffic signals. Policy 11: Sidewalks or other pedestrian walkways shall be required on all streets within all new subdivisions. Policy 18: The city shall review its transit service to major regional attractions, and intra-city recreational locations in future planning efforts, based on need. Policy 19: Bus pullouts shall be designed into all new projects on arterial roadways, to allow buses to leave the flow of traffic and reduce congestion. Policy 21: Update the Airport Master Plan every five years to meet the needs of the general aviation, business, and tourist segments of the community. Policy 25: The City shall develop and implement plans for a coordinated and connected bicycle lane network in the community that allows for safe use of bicycles on City streets. Policy 27: The City shall provide for a comprehensive, interconnected recreational trails system suitable for bicycles, equestrians, and/or pedestrians. D.13.3 Environmental Impacts and Mitigation Measures for the Proposed Project This section explains how impacts are assessed including the presentation of the significance criteria in Section D on which impact determinations are based, and Section D lists all impacts identified for the Proposed Project. June 2008 D.13-4 Draft EIR

5 Analysis Scenarios The analysis considers both near term and cumulative traffic impacts. The near-term analysis reflects the existing conditions, as recorded in recent traffic counts, the immediate impact of project trips, and the addition of traffic from projects directly adjacent to the project site. The cumulative analysis includes traffic from approved and proposed development projects within the study area, as well as ambient growth in traffic volumes on study area roadways, as defined by the City of Banning General Plan. Five scenarios are therefore considered: Existing, Project Opening Year (2013), Project Opening Year Plus Project (2013), Cumulative (Post 2030), and Cumulative (Post 2030) Plus Project. Analysis Methodology The analysis considers both intersections and roadway segments. Signalized Intersections Signalized intersection operations are evaluated using methodologies listed in the 2000 Highway Capacity Manual (HCM) (Transportation Research Board).These methods assess average control delays and then assign a corresponding letter grade that represents the overall condition of the intersection. These grades range from Level of Service (LOS) A (minimal delay) to LOS F (excessive congestion). Descriptions of the LOS grades for signalized intersections are provided in Table D Table D Signalized Intersection Criteria Level of Service Description A Operations with very low delay occurring with favorable progression and/or short cycle length. B Operations with low delay occurring with good progression and/or short cycle lengths. C Operations with average delay occurring with fair progression and/or longer cycle lengths. Individual cycle failures begin to appear. D Operations with longer delays due to a combination of unfavorable progression, long cycle lengths, or high V/C ratios. Many vehicles stop and individual cycle failures are noticeable. E Operations with high delay values indicating poor progression, long cycle lengths, and high V/C ratios. Individual cycle failures are frequent occurrences. This is considered to be the limit of acceptable delay. F Operations with delays unacceptable to most drivers occurring due to over saturation, poor progression, and/or very long cycle lengths. Source: Highway Capacity Manual (Transportation Research Board, 2000) Average Control Delay Per Vehicle (Seconds) 10.0 > 10.0 to 20.0 > 20.0 to 35.0 > 35.0 to 55.0 > 55.0 to 80.0 Levels of service are calculated using Synchro 6.0 software, which implements 2000 HCM methodologies. Synchro allows the input of signal timing and coordination data to more accurately reflect actual conditions. Delay and the resulting LOS is based on total intersection operations. Individual movements through the intersection will have varying levels of delay due to unique conditions affecting each movement. > 80.0 Draft EIR D.13-5 June 2008

6 Unsignalized Intersections Unsignalized intersection levels of service are analyzed using Synchro software, which implements the 2000 HCM methodologies. Please note that delay is calculated for movements that operate under traffic control. Therefore, the delay value at side-street stop-controlled reflects only the delay accruing for vehicles that are stopping at the stop sign. The LOS ranges for unsignalized intersections are shown in Table D Table D Unsignalized Intersection Criteria Level of Service Description Average Control Delay Per Vehicle (Seconds) A Little or no delays 10.0 B Short traffic delays > 10.0 to 15.0 C Average traffic delays > 15.0 to 25.0 D Long traffic delays > 25.0 to 35.0 E Very long traffic delays > 35.0 to 50.0 F Extreme traffic delays with intersection capacity exceeded > 50.0 Source: Highway Capacity Manual (Transportation Research Board, 2000) Roadway Segment Capacities Staff applied the Roadway Segment LOS capacities in Table D.13-5 to determine whether the roadway segments would meet the city of Banning s daily trip thresholds, as set forth in their General Plan. Table D Roadway Segment LOS Criteria Roadway Type Number of Lanes LOS C LOS D LOS E Collector 2 12,800 14,400 16,000 Secondary 4 24,000 27,000 30,000 Major 4 30,400 34,200 38,000 Source: City of Banning General Plan Update Traffic Study 2004 Project Trip Generation The project trip generation was developed by reviewing trip generation sources and then estimating project trip generation based on these assumptions. At the request of the City of Banning, a standardized Institute of Transportation Engineers (ITE) trip generation was applied. While staff had proposed to use trip generation derived directly from the characteristics of the site, the City requested the ITE data be applied instead. The ITE trip generation category most similar to the Proposed Project in operation was Light Industrial (Land Use 110). Table D.13-6 provides the ITE trip generation estimates for Light Industrial uses. It was determined that the use of ITE data, instead of project specific data provided by Liberty Energy, would result in a conservative estimate of the project trips for the following reasons: Unlike most light industrial facilities, this project would operate 24 hours a day meaning that traffic would be distributed through all hours of the day at the Liberty Energy facility. The trip generation is based on the square footage of the entire facility (approximately 86,600 square feet). The City requested that trip generation estimates are calculated using square footage of the facility, which provides a more accurate estimate of trip generation in comparison to total acreage of the site. Using square footage also produces the highest number of peak hour trips, which will conservatively estimate the potential impacts of the site. Instead of work areas or offices that might be found at a typical light industrial facility, much of this square footage would be power facilities. The actual work or office areas of this facility would be limited. As this approach would likely overestimate the likely trips generated by the project, it provides a conservative representation of the trips generated by the project. For example, it was determined that the project may only June 2008 D.13-6 Draft EIR

7 generate 30 AM and PM Peak Hour trips, assuming 24-hour schedule of operations. This estimate of peak hour trips is much less than what was estimated using ITE rates, as shown in Table As shown in Table D.13-6., the project is anticipated to generate 80 AM Peak Hour trips, 85 PM Peak Hour trips, and 604 daily trips. Of the 604 daily trips, 40 are expected to be made by the 20 employees working at the facility. Table D Trip Generation Estimates ITE Trip Rates Trips Code AM Peak Hour PM Peak Hour Land Use Used Size/EMP AM PM Daily In Out Total In Out Total Daily Light Industrial KSF Notes: KSF= 1,000 sq. ft. Trip Distribution Project trips were distributed based on the following assumptions: Biomass and biosolids would be delivered to the facility via the I-10 freeway, exiting Hargrave Street, traveling southbound to East Lincoln Street, and turn east on Lincoln Street, and then travel eastbound to Hathaway Street. The trucks would then turn southbound on Hathaway Street to Westward Avenue where they would turn east and follow Westward Avenue to the project entrance. Trucks leaving the facility would follow this route in reverse to I-10. The most likely biomass sources would be from Los Angeles, Riverside, and San Bernardino Counties, according to information provided by the project applicant. Therefore, vehicles accessing the vehicles carry biomass would be accessing the site mainly from the west. Approximately 10 employees working at the site would commute from Beaumont/Banning, and 5 would commute from Riverside, most of whom are likely to travel eastbound on the I-10 to access the facility. Five employees are expected to commute from the Coachella Valley, for a total of 20 employees. The project trip distribution is shown on Figure D Trip Assignment Project trips were assigned using the distribution shown in Figure D The most direct access to the site from I-10 would occur from Hargrave Street at the existing interchange. D Criteria for Determining Significance The following significance criteria were employed to determine if the project caused significant traffic impacts, based on the results of the traffic study. These criteria reflect input from the City of Banning General Plan as well as the application of standard traffic engineering guidelines. The project, including project driveways, will disrupt traffic operations. Traffic impacts were assessed using both quantitative (Level of Service (LOS)) and qualitative criteria. A disruption of traffic operations is defined as any of the following a. If the addition of project traffic causes the LOS to degrade at a signalized intersection from LOS C or better to D, E, or F at a signalized intersections. b. If the addition of project traffic causes an increase in traffic volumes at a signalized intersection already operating at LOS D, E, or F. c. If the addition of project traffic causes an unsignalized intersection to degrade to LOS D, E or F and one of more traffic signal warrants (as defined by the Manual of Uniform Traffic Control Devices (MUTCD)) are met. Draft EIR D.13-7 June 2008

8 PREPARED BY Aspen Environmental Group Source: Fehr & Peers, 2008 Figure D.13-2 Project Trip Distribution June 2008 D.13-8 Draft EIR

9 PREPARED BY Aspen Environmental Group Source: Fehr & Peers, 2008 Figure D.13-3 Project Trips with Existing Roadways June 2008 D.13-9 Draft EIR

10 d. If the project contributes traffic to an unsignalized intersection operating at LOS F and one or more traffic signal warrants (as defined by the Manual of Uniform Traffic Control Devices (MUTCD)) are met. e. If the project contributes traffic to a roadway segment LOS to degrade from LOS C or better to LOS D or F. f. If the project contributes traffic to a roadway segment operating at LOS D, E or F prior to the addition of project traffic. g. A project interferes with, conflicts with or precludes other planned improvements such as roadway extensions/ expansions, planned trail facilities, proposed creek restoration projects, etc. h. A project conflicts with or creates inconsistencies with adopted traffic plans, guidelines, policies or standards. i. The construction of a project creates a temporary but prolonged impact due to lane closures, need for temporary signals, emergency vehicles access, traffic hazards to bike, pedestrians, damage to roadbed, truck traffic on roadways not designated as truck routes, etc. Transit Impacts were considered significant if: a. A project or project related mitigation disrupts existing transit services or facilities. This includes disruptions caused by proposed-project driveways on transit streets and impacts to transit stops/shelters; and impacts to transit operations from traffic improvements proposed or resulting from a project. b. A project interferes with planned transit services or facilities. c. A project conflicts with or creates inconsistencies with adopted transit system plans, guidelines, policies or standards. d. The project created demand for public transit services above the capacity which is provided, or planned. Bicycle impacts were considered significant if: a. A project disrupts existing bicycle services. b. A project interferes with planned bicycle facilities. This includes failure to dedicate right-of-way for planned on- and off-street bicycle facilities included in an adopted Bicycle Master Plan or to contribute toward construction of planned bicycle facilities along the project s frontages. c. A project conflicts with or creates inconsistencies with adopted bicycle system plans, guidelines, policies or standards. Pedestrian impacts were considered if: a. A project disrupts existing pedestrian facilities. This can include adding new vehicular, bicycle or pedestrian traffic to an area experiencing pedestrian safety concerns such as an adjacent crosswalk or school, particularly if the added traffic reduces the number of acceptable pedestrian gaps at unsignalized crossings or cause queues to spillback towards pedestrian crossings. b. A project interferes with planned pedestrian facilities. In existing and/or planned urbanized areas, main streets or pedestrian districts, this can include impacts to the quality of the walking environment. c. A project conflicts or creates inconsistencies with adopted pedestrian system plans, guidelines, policies or standards. Project site plans and proposed site improvements, including mitigation, were reviewed for consistency with local design standards, parking codes, and other adopted guidelines. Project impacts were considered significant if: a. Project designs for on-site circulation, access and parking fail to meet industry standard design guidelines. b. A project fails to provide a sufficient quantity of on-site parking for vehicles. This analysis will consider both the anticipated parking demand and the parking, as required by the City of Banning Municipal Code. c. A project fails to provide accessible and safe pedestrian connections between buildings. d. A project fails to provide adequate accessibility for service and delivery trucks on-site including access to truck loading areas. e. A project violates access management standards (e.g. driveway spacing, signal spacing, sight distance, etc.) in a way that causes an adverse effect on the environment or reduction in public safety. June 2008 D Draft EIR

11 D Impact Analysis This section documents the project impacts during the Opening year Scenario. The Opening Year scenario reflects conditions in 2013, which is anticipated to be the likely Buildout. Impact T-1: The project, including project driveways, would disrupt existing traffic operations (Class II) Traffic volumes for the Opening Year scenario were estimated by applying a 2% background growth percentage to the existing traffic counts at the existing study intersections. In addition, project traffic from three projects scheduled to be built within the study area were added since those projects are likely to be present when the Proposed Project opens. By adding traffic from these projects in the Opening Year, the projections represent a conservative view of Opening Year conditions. These volumes are shown in Figure D The Opening Year Project Trips added to existing condition volumes are shown on Figure D Daily Volumes were estimated by assuming that the PM Peak Hour volumes were estimated to be 10% of the daily volumes. Tables D.13-7 provides the delay and LOS at the time of project completion. As shown in this table, several of the study intersections would operate at LOS F prior to and after the addition of project traffic. Table D.13-8 provides the roadway segment LOS for the No Project and With Project condition. Table D Intersection Levels of Service - Year 2013 Conditions Year 2013 No Project Year 2013 Plus Project Intersection Control AM Peak PM Peak AM Peak PM Peak Delay LOS Delay LOS Delay LOS Delay LOS S. Hathaway Street/ Unsignalized 9.5 A 9.2 A 9.5 A 9.6 A Westward Avenue S. Hargrave Street/ E. Unsignalized 13.3 B 12.6 B 15.2 C 13.8 B Lincoln Street S. Hargrave Street/ I-10 Unsignalized >50 F >50 F >50 F >50 F Eastbound Ramps S. Hargrave Street/ I-10 Westbound Ramps Unsignalized 37.7 E >50 F 43.1 E >50 F Notes: Average delay reported in seconds per vehicle. For side-street stop controlled intersection worst case movement delay reported. HCM 2000 methodology employed. LOS= Level of Service Source: Fehr & Peers, Table D Roadway Segment Daily Level of Service - Year 2013 Conditions Roadway Segment Classification (Number of Lanes) LOS C Opening Year No Project Opening Year With Project Capacity LOS C or LOS C or ADT ADT Better Better 24,000 20,550 Yes 21,150 Yes South Hargrave Street north of East Lincoln Street Secondary Highway (2) East Lincoln Street Major Highway (2) 30,400 10,170 Yes 10,770 Yes South Hathaway Street Collector (2) 12,800 7,210 Yes 7,810 Yes Westward Avenue Collector (2) 12, Yes 820 Yes Notes: ADT = Average Daily Traffic Source: City of Banning General Plan Update Traffic Study, Draft EIR D June 2008

12 PREPARED BY Aspen Environmental Group Source: Fehr & Peers, 2008 Figure D.13-4 Project Opening Year - No Project Trips June 2008 D Draft EIR

13 PREPARED BY Aspen Environmental Group Source: Fehr & Peers, 2008 Figure D.13-5 Project Opening Year With Project Trips June 2008 D Draft EIR

14 Based on the significance criteria above, impacts were evaluated related to signalized intersections, unsignalized intersections, roadway segments, planned roadway improvements, transportation policies, and construction traffic impacts. Additional information regarding each area is presented below. Signalized Intersections: All four of the study area intersections currently operate as unsignalized intersections. Therefore, no impacts to signalized intersections would occur (No Impact). Unsignalized Intersections: With the addition of project trips, two of the four study intersections would operate at LOS F and would meet peak hour traffic signal warrants as defined by the MUTCD and a significant traffic impact would occur. Based on the previously defined significance criteria, the impacted intersections would be the I-10 Westbound Ramps/Hargrave Street and the I-10 Eastbound Ramps/Hargrave Street. Mitigation Measure T-1a (Install Traffic Signals) would require the installation of two traffic signals at the I-10 Eastbound Ramps/Hargrave Street and the I-10 Westbound Ramps/Hargrave Street intersections. Both of the intersections will operate at LOS F in the near-term.the signalization of these intersections was addressed in the City of Banning General Plan but may not occur prior to the development of the project site. With the implementation of this mitigation measure, the project impacts would be reduced to a less than significant level (Class II). Roadway Segments: Even with the addition of project trips, the roadway segment LOS would remain at LOS C or better. Therefore, the impacts related to roadway segments would be less than significant and no mitigation would be required (Class III). Planned Roadway Improvements: The City of Banning s General Plan anticipates several significant roadway improvements within the City. However, none of these proposed improvements would occur on the project site or be affected by the development of the project. Therefore it can be concluded that the project impacts related to planned roadway improvements would be less than significant and no mitigation would be required (Class III). Transportation Policies: The City of Banning s General Plan contains numerous policies related to transportation facilities. Specific policies include the requirement to maintain LOS C on a majority of the City roadways and policies designed to encourage alternative transportation modes. Therefore, it can be concluded that the development of the project would not conflict with the City s policies related to transportation. For example, the project would implement several improvements at impacted roadways to maintain the required LOS. Any conflicts would be less than significant (Class III). Construction Traffic: Construction traffic would include haul trucks required for any import/export of fill material, construction equipment traveling to and from the site, and the influx of construction workers. This evaluation of construction traffic impacts considers not only the likely traffic as well as the context area involved including the adjacent uses. Based on the following considerations, it was determined that a construction related impact would occur, resulting in a significant traffic impact: Construction of the site would involve the import of construction equipment including bulldozers, concrete mixers, and other related items. Construction will also require the daily importation of construction materials such as concrete and other construction materials in addition to workers traveling to and from the site on a daily basis. These materials would have to be transported to the site, stored on the site, and removed from the June 2008 D Draft EIR

15 site following the completion of construction. Construction equipment, materials, and workers would travel to the site along the same roadways and intersections studied above. As noted previously, several of these intersections are projected to operate at a deficient LOS. Therefore, construction vehicles may experience delay as they travel to the site while contributing to the delay experienced by other vehicles. Consequently, construction activities could result in significant traffic impacts (Class II). Mitigating this construction related impact would require the preparation of a Construction Traffic Mitigation Plan, as outlined in Mitigation Measure T-1b (Prepare Construction Traffic Management Plan) below. Mitigation Measures for Impact T-1 T-1a T-1b Install Traffic Signals. The project would be responsible for the installation of traffic signals at the I-10 Eastbound/South Hargrave Street and I-10 Westbound/South Hargrave Street intersections. The project would be responsible for the design and construction of these two traffic signals. These traffic signals would be installed prior to the project commencing operations. Prepare Construction Traffic Management Plan. The project would be responsible for developing a construction traffic management plan to address potential traffic impacts related to the project. This plan would be provided to the City Banning for its review and approval prior to the commencement of construction activities. Specific measures included in this construction traffic management plan would include haul and equipment delivery routes, any limitations on peak hour travel during construction, and other items as applicable. Impact T-2: The project would disrupt transit service or conflict with transit policies (Class III) The Proposed Project would have the potential to disrupt existing or planned transit service, conflict with plans and policies associated with transit, or increase the demand for transit service above capacity. Construction and operational transport routes associated with the Proposed Project would not conflict with existing transit in the study area provided by Pass Transit. There is no planned transit service which would extend across the site and would therefore be affected by the development of the site. Additionally, the only roadway improvements associated with the site related to the signalization of several unsignalized intersections, which can only improve transit operations at these locations. The City s General Plan incorporates several policy statements related to transit. However, these policy statements are directed at project sites such as residential subdivisions where transit service could be utilized. As this site is not conducive to transit (as a majority of the trips would be associated with the delivery of materials to the site using trucks), there is little need to incorporate transit facilities into the site. Since the use of the site is not conducive to transit, the demand for transit service would be minimal. Consequently, any impacts associated with the disruption of transit or conflicts with transit policies would be less than significant (Class III). Impact T-3: The project would disrupt bicycle facilities or conflict with bicycle policies (Class III) There are no existing or proposed bicycle facilities within the project site or in its vicinity that would be affected by the development of the site. The City s General Plan incorporates several policy statements related to bicycling. These statements relate to the provision of bicycle facilities on roadways instead of facilities within projects. Additionally, the project is not likely to generate bicycling trips or be accessed by persons using bicycles. Any impacts associated with the disruption of bicycle use or conflicts with bicycle use policies would be less than significant (Class III). Draft EIR D June 2008

16 Impact T-4: The project would disrupt pedestrian facilities or conflict with pedestrian policies (Class III) There are no existing or planned future pedestrian facilities adjacent to the project site which would be affected by the development of the Proposed Project. There are no conflicts with the policy statements in the General Plan related to pedestrians. For example, this project is not a subdivision where pedestrian walkways or sidewalks would need to be provided. It is anticipated that, given the usage of the site, pedestrian travel within the site would be limited and no external pedestrian access would be provided. Consequently, any impacts associated with pedestrians or conflicts with pedestrian policies would be less than significant (Class III). Impact T-5: Project site plans and proposed site improvements, including mitigation, are consistent with local design standards, parking codes, and other adopted guidelines (Class II) The review of the project site plan considered on-site circulation and site access, parking adequacy, pedestrian connectivity, delivery vehicle access, and access management standards. On-Site Circulation and Site Access: The project would have a single driveway on Westward Street. All of the project vehicles would take access at this location. From this driveway, vehicles would travel through the site via an internal roadway. This internal roadway would connect the various buildings including the administration building (where a majority of workers will park) and the biomass and biosolids facilities, which would be accessed by the trucks traveling to the site. Given the number of vehicles accessing the site during both the peak hour and daily basis, a single driveway and internal roadway would provide sufficient access. Based on these considerations, any impact would be less than significant and no mitigation is required (Class II). Parking Adequacy: The City of Banning Municipal Code contains no parking requirement for a facility similar to the Proposed Project. Therefore, the Municipal Code can not be utilized to assess the parking adequacy. Parking adequacy can be assessed by comparing the number of employees against the parking spaces provided on-site. The maximum number of employees at the site would be 20 with 24-hour operations on the site. With 24-hour operation, it is anticipated that no more than 2/3 of the employees would be found on the site at any time. Since 15 parking spaces are provided, the parking provided would be adequate and the impact would be less than significant (Class III). Therefore, no mitigation would be required. Internal Pedestrian Connectivity: A majority of the pedestrian travel would occur between the parking area and the administration building. There could be intermittent pedestrian travel between the administration building and the other facilities on the site using the internal roadway provided. Due to the limited pedestrian use on-site and the capacity of the internal roadway, the internal pedestrian connectivity would be adequate and any impacts would be less than significant (Class III). No mitigation would be required. Delivery Vehicle Access: A variety of delivery vehicles would take access to the site on a daily basis. The majority of these vehicles would be delivering biomass and biosolid fuel material to be consumed at the facility. The remaining delivery vehicles would carry chemical supplies and miscellaneous equipment used at the facility. Regional delivery vehicle access would be provided through roadways like I-10 with access to the site itself provided by Westward Street. From the driveway on Westward Street, delivery vehicles would take access to the areas of the site through the internal roadway provided. As the project is located close to I-10, the need for vehicles to use surface streets would be limited. As described above in Impact T-1, operational delivery access would be significant, but with the implementation of Mitigation Measure T-1a (Install Traffic Signals), any impacts would be reduced to be less than significant (Class II). June 2008 D Draft EIR

17 Access Management Standards: In addition to the items considered above, the analysis also evaluated how the project would comply with applicable access management standards, which relates to traffic signal and driveway spacing. As the project would not involve the installation of traffic signals at any project driveways, standards related to signal spacing would not apply. Additionally, the project would take access from Westward Street in a section located away from adjacent uses. The proposed driveway would therefore be located away from others, which would limit conflicts with adjacent driveways. Based on these considerations, the project would be in compliance with applicable access management standards and any impacts would be less than significant (Class III). No mitigation would therefore be required. D.13.4 Alternative 1 The Charles Street Truck Route Alternative would provide a different route for trucks delivering biofuel and removing ash. Along this Alternative, instead of turning east on Westward Avenue, trucks would continue on Hathaway Street to Charles Street, where they would turn east and follow Charles Street to the Liberty Energy facility. All other components of construction and operation of the Liberty Energy facility would remain the same as described for the Proposed Project. D Alternative 1 Environmental Setting As the Charles Street Truck Route Alternative would have similar truck travel routes as the Proposed Project, and no other components of construction or operation of the Liberty Energy facility would change as compared to the Proposed Project, the environmental settings for traffic would be identical to that described previously. D Alternative 1 - Environmental Impacts and Mitigation Measures Impact T-1: The project, including project driveways, would disrupt existing traffic operations (Class II) Traffic impacts associated with Alternative 1 would be the same as those identified for the Proposed Project. In particular, the significant traffic impacts identified at the I-10 Eastbound Ramps/Hathaway Street and I-10 Westbound Ramps/Hathaway Street would remain as this alternative does not change the regional access route for vehicles or the reduce the need to use I-10 to provide regional connectivity. Mitigation Measure T-1a (Install Traffic Signals) would still be required. Additionally, construction traffic impacts would also remain significant as this alternative does not change the level or intensity of construction. Therefore, Mitigation Measure T-1b (Prepare Construction Traffic Management Plan) would also still be required. Implementation of these mitigation measures would reduce impacts to be less than significant (Class II). Impact T-2: The project would disrupt transit service or conflict with transit policies (Class III) Transit impacts associated with Alternative 1 would be the same as identified for the Proposed Project. Construction and operational transport routes associated with the Proposed Project would not conflict with existing or planned transit in the study area provided by Pass Transit. Additionally, roadway improvements associated with the site related to the signalization of several unsignalized intersections would only improve transit operations at these locations. As the site is not conducive to transit, there is little need to incorporate transit facilities into the site, so the demand for transit service would be minimal. Consequently, any impacts associated with the disruption of transit or conflicts with transit policies would be less than significant (Class III). Draft EIR D June 2008

18 Impact T-3: The project would disrupt bicycle facilities or conflict with bicycle policies (Class III) As there are no existing or proposed bicycle facilities within the project site or in its vicinity, bicycle impacts associated with Alternative 1 would be the same as described for the Proposed Project. The City s General Plan incorporates several policy statements related to the provision of bicycle facilities on roadways instead of facilities within projects and so would not be applicable to the alternative. Additionally, the project is not likely to generate bicycling trips or be accessed by persons using bicycles. Any impacts associated with the disruption of bicycle use or conflicts with bicycle use policies would be less than significant (Class III). Impact T-4: The project would disrupt pedestrian facilities or conflict with pedestrian policies (Class III) Pedestrian impacts associated with Alternative 1 would be identical to those identified for the Proposed Project. There are no existing or planned future pedestrian facilities adjacent to the project site which would be affected by the development of Alternative 1. There are no conflicts with the policy statements in the General Plan related to pedestrians. It is anticipated that, given the usage of the site, pedestrian travel within the site would be limited and no external pedestrian access would be provided. Consequently, any impacts associated with pedestrians or conflicts with pedestrian policies would be less than significant (Class III). Impact T-5: Project site plans and proposed site improvements, including mitigation, are consistent with local design standards, parking codes, and other adopted guidelines (Class II) Consistency with local design standards, parking codes, and other guidelines would be the same for Alternative 1 as described for the Proposed Project. Given the number of vehicles accessing the site during both the peak hour and daily basis, on-site circulation and access would be adequate. As the maximum number of employees at the site would be 20 with 24-hour operations on the site and no more than 2/3 of the employees would be found on the site at any time, the 15 parking spaces provided would be adequate. Due to the limited pedestrian use on-site and the capacity of the internal roadway, the internal pedestrian connectivity would be sufficient for Alternative 1. Alternative 1 would also be in compliance with applicable access management standards. As described above in Impact T-1, operational delivery access would be significant, but with the implementation of Mitigation Measure T-1a (Install Traffic Signals), any impacts would be reduced to be less than significant (Class II). D.13.5 Alternative 2 Under this alternative, operational truck traffic would be restricted to occur only outside of peak traffic hours. Construction of the Alternative 2 would be the same as described for the Proposed Project. With the exception of the times that operational truck traffic would be restricted, operation and maintenance of Alternative 2 would be the same as the Proposed Project. D Alternative 2 Environmental Setting As the Avoid Peak Hours Traffic Alternative would have identical truck travel routes as the Proposed Project, and no other components of construction or operation of the Liberty Energy facility would change as compared to the Proposed Project, the environmental settings for traffic would be identical to that described previously. The only change would be a reduction of peak hour traffic with the restrictions on truck operations. Even with the reduction in truck operations, some peak hour trips would occur on the project site as employees would June 2008 D Draft EIR

19 still travel to and from the site during these same peak hours. Therefore, peak hour traffic would be reduced but not eliminated. D Alternative 2 - Environmental Impacts and Mitigation Measures Impact T-1: The project, including project driveways, would disrupt existing traffic operations (Class II) Traffic impacts associated with Alternative 2 would be similar to those identified in Section D In particular, the significant traffic impacts identified at the I-10 Eastbound Ramps/Hathaway Street and I-10 Westbound Ramps/Hathaway Street would remain as the project trips would be reduced but not eliminated. With the residual employee trips, the intersections would remain at LOS F and still meet one or more of the traffic signal warrants. Mitigation Measure T-1a (Install Traffic Signals) would still be required. Additionally, construction traffic impacts would also remain significant as this alternative does not change the level or intensity of construction. Therefore, Mitigation Measure T-1b (Prepare Construction Traffic Management Plan) would also still be required. Implementation of these mitigation measures would reduce impacts to be less than significant (Class II). Impact T-2: The project would disrupt transit service or conflict with transit policies (Class III) Transit impacts associated with Alternative 2 would be the same as identified for the Proposed Project. Construction and operational transport routes associated with the Proposed Project would not conflict with existing or planned transit in the study area provided by Pass Transit. Additionally, roadway improvements associated with the site related to the signalization of several unsignalized intersections would only improve transit operations at these locations. As the site is not conducive to transit, there is little need to incorporate transit facilities into the site, so the demand for transit service would be minimal. Consequently, any impacts associated with the disruption of transit or conflicts with transit policies would be less than significant (Class III). Impact T-3: The project would disrupt bicycle facilities or conflict with bicycle policies (Class III) As there are no existing or proposed bicycle facilities within the project site or in its vicinity, bicycle impacts associated with Alternative 2 would be the same as described for the Proposed Project. The City s General Plan incorporates several policy statements related to the provision of bicycle facilities on roadways instead of facilities within projects and so would not be applicable to the alternative. Additionally, the project is not likely to generate bicycling trips or be accessed by persons using bicycles. Any impacts associated with the disruption of bicycle use or conflicts with bicycle use policies would be less than significant (Class III). Impact T-4: The project would disrupt pedestrian facilities or conflict with pedestrian policies (Class III) Pedestrian impacts associated with Alternative 2 would be identical to those identified for the Proposed Project. There are no existing or planned future pedestrian facilities adjacent to the project site which would be affected by the development of Alternative 2. There are no conflicts with the policy statements in the General Plan related to pedestrians. It is anticipated that, given the usage of the site, pedestrian travel within the site would be limited and no external pedestrian access would be provided. Consequently, any impacts associated with pedestrians or conflicts with pedestrian policies would be less than significant (Class III). Draft EIR D June 2008

20 Impact T-5: Project site plans and proposed site improvements, including mitigation, are consistent with local design standards, parking codes, and other adopted guidelines (Class II) Consistency with local design standards, parking codes, and other guidelines would be the same for Alternative 2 as described for the Proposed Project. Given the number of vehicles accessing the site during both the peak hour and daily basis, on-site circulation and access would be adequate. As the maximum number of employees at the site would be 20 with 24-hour operations on the site and no more than 2/3 of the employees would be found on the site at any time, the 15 parking spaces provided would be adequate. Due to the limited pedestrian use on-site and the capacity of the internal roadway, the internal pedestrian connectivity would be sufficient for Alternative 2. Alternative 2 would also be in compliance with applicable access management standards. As described above in Impact T-1, operational delivery access would be significant, but with the implementation of Mitigation Measure T-1a (Install Traffic Signals), any impacts would be reduced to be less than significant (Class II). D.13.6 No Project Alternative Under the No Project Alternative, traffic associated with the development of the site would not occur. As the site is currently vacant, the site would generate no trips. Additionally, there would be no construction related traffic. Given these considerations, Impact T-1 would no longer occur and Mitigation Measures T- 1a (Install Traffic Signals) and T-1b (Prepare Construction Traffic Management Plan) would no longer be required. D.13.7 Mitigation Monitoring, Compliance, and Reporting Table Table D.13-9 on the following page presents the mitigation monitoring recommendations for Transportation and Traffic. June 2008 D Draft EIR

Magnolia Place. Traffic Impact Analysis. Prepared for: City of San Mateo. Prepared by: Hexagon Transportation Consultants, Inc.

Magnolia Place. Traffic Impact Analysis. Prepared for: City of San Mateo. Prepared by: Hexagon Transportation Consultants, Inc. Magnolia Place Traffic Impact Analysis Prepared for: City of San Mateo Prepared by: Hexagon Transportation Consultants, Inc. Updated January 4, 2010 Table of Contents 1. Introduction...1 2. Existing Conditions...6

More information

3.9 - Transportation and Traffic

3.9 - Transportation and Traffic Transportation and Traffic 3.9 - Transportation and Traffic This section describes the potential transportation and traffic effects of project implementation on the project site and its surrounding area.

More information

TRAFFIC IMPACT ANALYSIS

TRAFFIC IMPACT ANALYSIS TRAFFIC IMPACT ANALYSIS FOR THE CHAMPAIGN UNIT#4 SCHOOL DISTRICT PROPOSED HIGH SCHOOL (SPALDING PARK SITE) IN THE CITY OF CHAMPAIGN Final Report Champaign Urbana Urbanized Area Transportation Study 6/24/2014

More information

TABLE OF CONTENTS TABLE OF CONTENTS... I APPENDICES... III LIST OF EXHIBITS... V LIST OF TABLES... VII LIST OF ABBREVIATED TERMS...

TABLE OF CONTENTS TABLE OF CONTENTS... I APPENDICES... III LIST OF EXHIBITS... V LIST OF TABLES... VII LIST OF ABBREVIATED TERMS... TABLE OF CONTENTS TABLE OF CONTENTS... I APPENDICES... III LIST OF EXHIBITS... V LIST OF TABLES... VII LIST OF ABBREVIATED TERMS... IX 1 INTRODUCTION... 1 1.1 Project Overview... 1 1.2 Analysis Scenarios...

More information

TRAFFIC ASSESSMENT River Edge Colorado

TRAFFIC ASSESSMENT River Edge Colorado TRAFFIC ASSESSMENT River Edge Colorado Submitted by: Fehr & Peers 621 17th Street, Ste. 231 Denver, CO 8293 (33) 296-43 December, 21 App. M-2 Traffic Assessment River Edge Colorado December 21 TABLE OF

More information

Abrams Associates. Transportation Impact Analysis. City of Rocklin. Prepared for: David Mohlenbrok City of Rocklin 4081 Alvis Court Rocklin, CA 95677

Abrams Associates. Transportation Impact Analysis. City of Rocklin. Prepared for: David Mohlenbrok City of Rocklin 4081 Alvis Court Rocklin, CA 95677 Transportation Impact Analysis Sierra College Boulevard Commercial Project City of Rocklin Prepared for: David Mohlenbrok City of Rocklin 081 Alvis Court Rocklin, CA 95677 Prepared by: 1875 Olympic Boulevard,

More information

TRAFFIC IMPACT STUDY CANYON HILLS PROJECT LOS ANGELES, CALIFORNIA INTRODUCTION This traffic analysis has been conducted to identify and evaluate the potential traffic impacts of the proposed Canyon Hills

More information

Traffic Impact Analysis Walton Acres at Riverwood Athletic Club Clayton, NC

Traffic Impact Analysis Walton Acres at Riverwood Athletic Club Clayton, NC Traffic Impact Analysis Walton Acres at Riverwood Athletic Club Clayton, NC 1. TABLE OF CONTENTS INTRODUCTION...1 1.1. Site Location and Study Area...1 1.2. Proposed Land Use and Site Access...2 1.3.

More information

CarMax Auto Superstore/ Reconditioning Center #6002 Murrieta, California

CarMax Auto Superstore/ Reconditioning Center #6002 Murrieta, California CarMax Auto Superstore/ Reconditioning Center #6002 Murrieta, California TUSTIN 17782 17th Street Suite 200 Tustin, CA 92780-1947 714.665.4500 Fax: 714.665.4501 LOS ANGELES 145 S. Spring Street Suite 120

More information

MEMORANDUM. To: 1.0 PURPOSE

MEMORANDUM. To: 1.0 PURPOSE MEMORANDUM To: Scott Holland, Elements Architecture From: Brian Grover, Dudek Date: July 16, 2014 1.0 PURPOSE In response to the November 4, 2013 request (RE: Incomplete Application Southern California

More information

4.11 TRANSPORTATION 4.11 TRANSPORTATION Environmental Setting Intersection, Roadway, and Freeway Evaluation Methodology

4.11 TRANSPORTATION 4.11 TRANSPORTATION Environmental Setting Intersection, Roadway, and Freeway Evaluation Methodology 4.11 TRANSPORTATION This section describes the road transportation system in the vicinity of the proposed Project and the potential impacts to this system from the proposed Project. The analysis in this

More information

Figure 1: East West Connector Alignment Alternatives Concept Drawing

Figure 1: East West Connector Alignment Alternatives Concept Drawing Page 2 of 9 Figure 1: East West Connector Alignment Alternatives Concept Drawing The Montebello Drive extension will run north south and connect Wilsonville Road to the Boones Ferry Road to Brown Road

More information

1609 E. FRANKLIN STREET HOTEL TRAFFIC IMPACT STUDY EXECUTIVE SUMMARY

1609 E. FRANKLIN STREET HOTEL TRAFFIC IMPACT STUDY EXECUTIVE SUMMARY 1609 E. FRANKLIN STREET HOTEL TRAFFIC IMPACT STUDY EXECUTIVE SUMMARY Prepared for: The Town of Chapel Hill Public Works Department Traffic Engineering Division Prepared by: HNTB North Carolina, PC 343

More information

4.0 TRAFFIC IMPACT STUDIES

4.0 TRAFFIC IMPACT STUDIES SECTION 4 4.0 TRAFFIC IMPACT STUDIES 4.1 TRAFFIC IMPACT STUDY REQUIREMENTS The City has established Traffic Impact Study (TIS) requirements for the purpose of ensuring that both the quantitative and qualitative

More information

THIS PAGE LEFT BLANK INTENTIONALLY

THIS PAGE LEFT BLANK INTENTIONALLY GA SR 25 Spur at Canal Road Transportation Impact Analysis PREPARED FOR GLYNN COUNTY, GEORGIA 1725 Reynolds Street, Suite 300 Brunswick, Georgia 31520 PREPARED BY 217 Arrowhead Boulevard Suite 26 Jonesboro,

More information

4. ENVIRONMENTAL IMPACT ANALYSIS 9. TRANSPORTATION AND TRAFFIC

4. ENVIRONMENTAL IMPACT ANALYSIS 9. TRANSPORTATION AND TRAFFIC 4. ENVIRONMENTAL IMPACT ANALYSIS 9. TRANSPORTATION AND TRAFFIC 4.9.1 INTRODUCTION The following section addresses the Proposed Project s impact on transportation and traffic based on the Traffic Study

More information

TABLE TRAFFIC ANALYSIS SCENARIOS

TABLE TRAFFIC ANALYSIS SCENARIOS 4.11 TRANSPORTATION The potential traffic impacts of the proposed project are evaluated in the Buena Park Beach/Orangethorpe Mixed Use Project Traffic Analysis (Traffic Analysis) by Austin-Foust Associates

More information

Project Report. South Kirkwood Road Traffic Study. Meadows Place, TX October 9, 2015

Project Report. South Kirkwood Road Traffic Study. Meadows Place, TX October 9, 2015 Meadows Place, TX October 9, 2015 Contents 1 Introduction... 1 2 Data Collection... 1 3 Existing Roadway Network... 2 4 Traffic Volume Development... 2 5 Warrant Analysis... 3 6 Traffic Control Alternative

More information

Traffic Impact Study. Westlake Elementary School Westlake, Ohio. TMS Engineers, Inc. June 5, 2017

Traffic Impact Study. Westlake Elementary School Westlake, Ohio. TMS Engineers, Inc. June 5, 2017 TMS Engineers, Inc. Traffic Impact Study Westlake Elementary School Westlake, Ohio June 5, 2017 Prepared for: Westlake City Schools - Board of Education 27200 Hilliard Boulevard Westlake, OH 44145 TRAFFIC

More information

Traffic Circulation Study for Neighborhood Southwest of Mockingbird Lane and Airline Road, Highland Park, Texas

Traffic Circulation Study for Neighborhood Southwest of Mockingbird Lane and Airline Road, Highland Park, Texas ARIZONA TEXAS NEW MEXICO OKLAHOMA February 13, 2015 Mr. Meran Dadgostar P.E., R.S. Town of Highland Park 4700 Drexel Dr. Highland Park, Texas 75205 Re: Traffic Circulation Study for Neighborhood Southwest

More information

TRANSPORTATION ANALYSIS REPORT US Route 6 Huron, Erie County, Ohio

TRANSPORTATION ANALYSIS REPORT US Route 6 Huron, Erie County, Ohio TRANSPORTATION ANALYSIS REPORT US Route 6 Huron, Erie County, Ohio December 12, 2012 Prepared for: The City of Huron 417 Main Huron, OH 44839 Providing Practical Experience Technical Excellence and Client

More information

Transportation Impact Study for Abington Terrace

Transportation Impact Study for Abington Terrace Transportation Impact Study for Abington Terrace Abington Township, Montgomery County, PA Sandy A. Koza, P.E., PTOE PA PE License Number PE059911 Prepared by McMahon Associates, Inc. 425 Commerce Drive,

More information

4.10 TRAFFIC AND CIRCULATION

4.10 TRAFFIC AND CIRCULATION 4.10 TRAFFIC AND CIRCULATION The following section is based on a traffic and circulation study prepared by Fehr & Peers, Inc. (November 2003; refer to Appendix F for technical calculations). The effects

More information

TRAFFIC IMPACT STUDY COMPREHENSIVE UPDATE TOWN OF THOMPSON S STATION, TENNESSEE PREPARED FOR: THE TOWN OF THOMPSON S STATION

TRAFFIC IMPACT STUDY COMPREHENSIVE UPDATE TOWN OF THOMPSON S STATION, TENNESSEE PREPARED FOR: THE TOWN OF THOMPSON S STATION TRAFFIC IMPACT STUDY COMPREHENSIVE UPDATE TOWN OF THOMPSON S STATION, TENNESSEE PREPARED FOR: THE TOWN OF THOMPSON S STATION Transportation Consultants, LLC 1101 17 TH AVENUE SOUTH NASHVILLE, TN 37212

More information

TRAFFIC IMPACT STUDY And A TRAFFIC SIGNAL WARRANT ANALYSIS FOR A SENIOR LIVING AND APARTMENT DEVELOPMENT

TRAFFIC IMPACT STUDY And A TRAFFIC SIGNAL WARRANT ANALYSIS FOR A SENIOR LIVING AND APARTMENT DEVELOPMENT TRAFFIC IMPACT STUDY And A TRAFFIC SIGNAL WARRANT ANALYSIS FOR A SENIOR LIVING AND APARTMENT DEVELOPMENT DEERFIELD TOWNSHIP, WARREN COUNTY, OHIO Nantucket Circle and Montgomery Road () Prepared for: ODLE

More information

List of Attachments. Location Map... Site Plan... City of Lake Elsinore Circulation Element... City of Lake Elsinore Roadway Cross-Sections...

List of Attachments. Location Map... Site Plan... City of Lake Elsinore Circulation Element... City of Lake Elsinore Roadway Cross-Sections... List of Attachments Exhibits Location Map... Site Plan... City of Lake Elsinore Circulation Element... City of Lake Elsinore Roadway Cross-Sections... Existing Lane Geometry and Traffic Controls... Existing

More information

TRAFFIC STUDY GUIDELINES Clarksville Street Department

TRAFFIC STUDY GUIDELINES Clarksville Street Department TRAFFIC STUDY GUIDELINES Clarksville Street Department 9/1/2009 Introduction Traffic studies are used to help the city determine potential impacts to the operation of the surrounding roadway network. Two

More information

4.13 TRANSPORTATION AND TRAFFIC

4.13 TRANSPORTATION AND TRAFFIC 4.13 This chapter describes the regulatory framework and existing conditions in the vicinity of the Project site related to transportation and traffic, and the potential impacts of the proposed Project

More information

Traffic Impact Study WestBranch Residential Development Davidson, NC March 2016

Traffic Impact Study WestBranch Residential Development Davidson, NC March 2016 Traffic Impact Study WestBranch Residential Development Davidson, NC March 216 TRAFFIC IMPACT STUDY FOR THE WestBranch Residential Development LOCATED IN DAVIDSON, NC Prepared For: Lennar Carolinas, LLC

More information

Mission Street Medical Office Development

Mission Street Medical Office Development reet Medical Office Development Traffic Impact Analysis Prepared for: Palo Alto Medical Foundation February 23, 2012 Hexagon Office: 7888 Wren Avenue, Suite B121 Gilroy, CA 95020 Hexagon Job Number: 11RD11

More information

Bridge Street Corridor Study Report

Bridge Street Corridor Study Report Bridge Street Corridor Study Report Prepared for: Prepared by: BRIDGE STREET CORRIDOR STUDY REPORT PREPARED FOR: CITY OF ARROYO GRANDE COMMUNITY DEVELOPMENT DEPARTMENT 300 EAST BRANCH STREET ARROYO GRANDE,

More information

5.16 TRAFFIC AND CIRCULATION

5.16 TRAFFIC AND CIRCULATION 5.16 TRAFFIC AND CIRCULATION This section is based upon the Tierra Robles Traffic Impact Study (May 2015) and Supplemental Traffic Impact Analysis (August 2017) prepared by Omni-Means Engineering Solutions,

More information

Technical Memorandum TRAFFIC IMPACT STUDY. RIDLEY ROAD CONVENIENCE STORE Southampton County, VA. Prepared for: Mr. David Williams.

Technical Memorandum TRAFFIC IMPACT STUDY. RIDLEY ROAD CONVENIENCE STORE Southampton County, VA. Prepared for: Mr. David Williams. Technical Memorandum TRFFIC IMPCT STUDY RIDLEY ROD CONVENIENCE STORE Southampton County, V Prepared for: Mr. David Williams By: Charles Smith, P.E., PTOE EPR Charlottesville, V July 2014 1 TBLE OF CONTENTS

More information

3.0 PROJECT DESCRIPTION

3.0 PROJECT DESCRIPTION The following section of the Draft EIR contains a description of the proposed Elk Grove Boulevard/SR 99 Interchange Modification project, consistent with the requirements of CEQA Guidelines Section 15124.

More information

Traffic Impact Analysis Chatham County Grocery Chatham County, NC

Traffic Impact Analysis Chatham County Grocery Chatham County, NC Chatham County Grocery Chatham County, NC TABLE OF CONTENTS 1. INTRODUCTION... 1 1.1. Location and Study Area... 1 1.2. Proposed Land Use and Access... 2 1.3. Adjacent Land Uses... 2 1.4. Existing ways...

More information

5858 N COLLEGE, LLC N College Avenue Traffic Impact Study

5858 N COLLEGE, LLC N College Avenue Traffic Impact Study 5858 N COLLEGE, LLC nue Traffic Impact Study August 22, 2016 Contents Traffic Impact Study Page Preparer Qualifications... 1 Introduction... 2 Existing Roadway Conditions... 5 Existing Traffic Conditions...

More information

Clay Street Realignment Project Traffic Study

Clay Street Realignment Project Traffic Study Final Clay Street Realignment Project Traffic Study November 24, 2009 Prepared for: City of Placerville RS07-2466 2990 Lava Ridge Court, Suite 200 Roseville, CA 95661 (916) 773-1900 Fax (916) 773-2015

More information

TRAFFIC IMPACT STUDY CRITERIA

TRAFFIC IMPACT STUDY CRITERIA Chapter 6 - TRAFFIC IMPACT STUDY CRITERIA 6.1 GENERAL PROVISIONS 6.1.1. Purpose: The purpose of this document is to outline a standard format for preparing a traffic impact study in the City of Steamboat

More information

City of Homewood Transportation Plan

City of Homewood Transportation Plan City of Homewood Transportation Plan Prepared for: City of Homewood, Alabama Prepared by: Skipper Consulting, Inc. May 2007 TABLE OF CONTENTS INTRODUCTION... 1 BACKGROUND INFORMATION... 1 EXISTING TRANSPORTATION

More information

6.14 Traffic and Circulation

6.14 Traffic and Circulation 6.14 Traffic and Circulation 6.14.1 Introduction The analysis in this section summarizes the findings and recommendations presented in the "Marywood Development Traffic Impact Study, City of Orange, California"

More information

4.12 TRANSPORTATION Executive Summary. Setting

4.12 TRANSPORTATION Executive Summary. Setting 4.12 TRANSPORTATION 4.12.1 Executive Summary This section is based on the Multimodal Transportation Impact Study (TIS; 2016) prepared by Omni-Means, Ltd. to evaluate projected transportation impact conditions

More information

METHODOLOGY. Signalized Intersection Average Control Delay (sec/veh)

METHODOLOGY. Signalized Intersection Average Control Delay (sec/veh) Chapter 5 Traffic Analysis 5.1 SUMMARY US /West 6 th Street assumes a unique role in the Lawrence Douglas County transportation system. This principal arterial street currently conveys commuter traffic

More information

Traffic Analysis and Design Report. NW Bethany Boulevard. NW Bronson Road to NW West Union Road. Washington County, Oregon

Traffic Analysis and Design Report. NW Bethany Boulevard. NW Bronson Road to NW West Union Road. Washington County, Oregon Traffic Analysis and Design Report NW Bethany Boulevard NW Bronson Road to NW West Union Road Washington County, Oregon May 2011 Table of Contents Table of Contents Section 1 Executive Summary... 2 Section

More information

Waterford Lakes Small Area Study

Waterford Lakes Small Area Study Waterford Lakes Small Area Study Existing Traffic Conditions PREPARED FOR: ORANGE COUNTY PUBLIC WORKS DEPARTMENT TRAFFIC ENGINEERING DIVISION ORLANDO, FLORIDA PREPARED WITH: INWOOD CONSULTING ENGINEERS

More information

Chapter 4 Traffic Analysis

Chapter 4 Traffic Analysis Chapter 4 Traffic Analysis PURPOSE The traffic analysis component of the K-68 Corridor Management Plan incorporates information on the existing transportation network, such as traffic volumes and intersection

More information

Chapter 16: Traffic and Parking A. INTRODUCTION

Chapter 16: Traffic and Parking A. INTRODUCTION Chapter 6: Traffic and Parking A. ITRODUCTIO This chapter examines the potential traffic and parking impacts of the proposed Fresh Kills Park roads. The analysis of transit and pedestrians is presented

More information

Lyons Avenue/Dockweiler Road Extension Project Draft Environmental Impact Report. Appendix I Traffic Impact Study

Lyons Avenue/Dockweiler Road Extension Project Draft Environmental Impact Report. Appendix I Traffic Impact Study Lyons Avenue/Dockweiler Road Extension Project Draft Environmental Impact Report Appendix I Traffic Impact Study Street 0 80-1947 500.4501 RITA ld Court 0 91355-1096 400.7401 LA n Avenue 0 590-3745 300-9301

More information

CHAPTER 3. Transportation and Circulation

CHAPTER 3. Transportation and Circulation CHAPTER 3 Transportation and Circulation 3.0 TRANSPORTATION AND CIRCULATION This chapter evaluates traffic circulation, transit, parking, pedestrian, bicycle, and rail operational conditions in the Project

More information

Highway 111 Corridor Study

Highway 111 Corridor Study Highway 111 Corridor Study June, 2009 LINCOLN CO. HWY 111 CORRIDOR STUDY Draft Study Tea, South Dakota Prepared for City of Tea Sioux Falls Metropolitan Planning Organization Prepared by HDR Engineering,

More information

Los Coyotes Country Club Development Plan Traffic Impact Analysis

Los Coyotes Country Club Development Plan Traffic Impact Analysis Los Coyotes Country Club Development Plan Traffic Impact Analysis Prepared For: Phil Martin Associates 2073007450 Los Coyotes Country Club Development Plan Traffic Impact Analysis June 19, 2014 Prepared

More information

Prescott Plaza TRAFFIC IMPACT ANALYSIS TOWN OF YUCCA VALLEY

Prescott Plaza TRAFFIC IMPACT ANALYSIS TOWN OF YUCCA VALLEY Prescott Plaza TRAFFIC IMPACT ANALYSIS TOWN OF YUCCA VALLEY PREPARED BY: Aric Evatt, PTP aevatt@urbanxroads.com (949) 660-1994 x204 Charlene So, PE cso@urbanxroads.com (949) 660-1994 x222 OCTOBER 18, 2018

More information

Henderson Avenue Mixed-Use Development

Henderson Avenue Mixed-Use Development Zoning Case: Z145-3 Traffic Impact Analysis Henderson Avenue Mixed-Use Development Dallas, TX October 26 th, 216 Kimley-Horn and Associates, Inc. Dallas, Texas Project #644827 Registered Firm F-928 Traffic

More information

Cricket Valley Energy Project Dover, NY Updated Traffic Impact Study

Cricket Valley Energy Project Dover, NY Updated Traffic Impact Study Updated Traffic Impact Study Community Resources 6.3A Traffic and Transportation Amended This amended Traffic Study incorporates comments from NYSDOT, provided after their review of the original Traffic

More information

TRAFFIC IMPACT STUDY. Creekside Thornton, Colorado. For. August 2015 November 2015 Revised: August Prepared for:

TRAFFIC IMPACT STUDY. Creekside Thornton, Colorado. For. August 2015 November 2015 Revised: August Prepared for: TRAFFIC IMPACT STUDY For Creekside Thornton, Colorado August 215 November 215 Revised: August 216 Prepared for: Jansen Strawn Consulting Engineers 45 West 2 nd Avenue Denver, Colorado 8223 Prepared by:

More information

SECTION 1 - TRAFFIC PLANNING

SECTION 1 - TRAFFIC PLANNING SECTION 1 - TRAFFIC PLANNING 1.1 TRAFFIC OPERATIONS 1.1.1 Roadway Functional Classification The Multnomah County Comprehensive Framework Plan s Policy 34: Trafficways and the Functional Classification

More information

HENDERSON DEVELOPMENT 213, 217, 221, 221 ½, 223 HENDERSON AVENUE and 65 TEMPLETON STREET OTTAWA, ONTARIO TRANSPORTATION OVERVIEW.

HENDERSON DEVELOPMENT 213, 217, 221, 221 ½, 223 HENDERSON AVENUE and 65 TEMPLETON STREET OTTAWA, ONTARIO TRANSPORTATION OVERVIEW. HENDERSON DEVELOPMENT 213, 217, 221, 221 ½, 223 HENDERSON AVENUE and 65 TEMPLETON STREET OTTAWA, ONTARIO TRANSPORTATION OVERVIEW Prepared for: 2294170 Ontario Inc. February 2, 2017 117-652 Report_1.doc

More information

EAST AND SOUTH STREET CITY OF ANAHEIM, CALIFORNIA

EAST AND SOUTH STREET CITY OF ANAHEIM, CALIFORNIA T R A F F I C I M P A C T A N A LY S I S EAST AND SOUTH STREET CITY OF ANAHEIM, CALIFORNIA April 217 T R A F F I C I M P A C T A N A LY S I S EAST AND SOUTH STREET CITY OF ANAHEIM, CALIFORNIA Submitted

More information

5.3 TRAFFIC, CIRCULATION AND PARKING

5.3 TRAFFIC, CIRCULATION AND PARKING 5.3 TRAFFIC, CIRCULATION AND PARKING This section is based upon the Downtown Lancaster Specific Plan Traffic Impact Analysis (April 2, 2008) and the Downtown Lancaster Specific Plan Parking Analysis (May

More information

3.13 TRANSPORTATION AND TRAFFIC

3.13 TRANSPORTATION AND TRAFFIC 3.13 TRANSPORTATION AND TRAFFIC INTRODUCTION This section of the Draft EIR describes the transportation and traffic based on the Transportation Impact Analysis (TIA) prepared by Overland Traffic Consultants,

More information

Walton Acres at Riverwood Athletic Club Clayton, North Carolina

Walton Acres at Riverwood Athletic Club Clayton, North Carolina 9. CONCLUSIONS This Traffic Impact Analysis Update was conducted to determine the potential traffic impacts of the proposed Walton Acres at Riverwood Athletic Club residential development, located east

More information

Traffic Impact Memorandum. May 22, 2018

Traffic Impact Memorandum. May 22, 2018 BISHOP PROFESSIONAL DEVELOPMENT BUILDING Proposed Land-use Change & Parking Modification 3601 SW 31st Street Topeka, Kansas 66614 CFS Project No. 185077 Traffic Impact Memorandum May 22, 2018 Prepared

More information

Walmart (Store # ) 60 th Street North and Marion Road Sioux Falls, South Dakota

Walmart (Store # ) 60 th Street North and Marion Road Sioux Falls, South Dakota Walmart (Store #4865-00) 60 th Street North and Marion Road Sioux Falls, South Dakota Prepared for: Wal-Mart Stores, Inc. Bentonville, Arkansas Prepared by: Kimley-Horn and Associates, Inc. ã2013 Kimley-Horn

More information

INDUSTRIAL BUILDING 3009 HAWTHORNE ROAD CITY OF OTTAWA TRANSPORTATION OVERVIEW REVISED. Prepared for: Canada Inc.

INDUSTRIAL BUILDING 3009 HAWTHORNE ROAD CITY OF OTTAWA TRANSPORTATION OVERVIEW REVISED. Prepared for: Canada Inc. INDUSTRIAL BUILDING 3009 HAWTHORNE ROAD CITY OF OTTAWA TRANSPORTATION OVERVIEW REVISED Prepared for: 7849648 Canada Inc. Octiober 1, 2015 114-598 Overview_2.doc D. J. Halpenny & Associates Ltd. Consulting

More information

ALLEY 24 TRAFFIC STUDY

ALLEY 24 TRAFFIC STUDY ALLEY 24 TRAFFIC STUDY in City of Frostburg, Maryland January 2013 3566 Teays Valley Road Hurricane, WV Office: (304) 397-5508 www.denniscorporation.com Alley 24 Traffic Study January 2013 Frostburg, Maryland

More information

Planning Committee STAFF REPORT March 7, 2018 Page 2 of 4 The following MTSOs are being used across the five subregions: Intersection Level of Service

Planning Committee STAFF REPORT March 7, 2018 Page 2 of 4 The following MTSOs are being used across the five subregions: Intersection Level of Service Planning Committee STAFF REPORT Meeting Date: March 7, 2018 Subject Summary of Issues Recommendations Financial Implications Options Attachments Changes from Committee Review Draft 2017 Multimodal Transportation

More information

VIVA RETIREMENT COMMUNITIES OAKVILLE TRAFFIC IMPACT STUDY

VIVA RETIREMENT COMMUNITIES OAKVILLE TRAFFIC IMPACT STUDY VIVA RETIREMENT COMMUNITIES OAKVILLE TRAFFIC IMPACT STUDY VIVA RETIREMENT COMMUNITIES OAKVILLE TRAFFIC IMPACT STUDY DECEMBER 2012 READ, VOORHEES & ASSOCIATES TORONTO, ONTARIO Read, Voorhees & Associates

More information

Recommended Roadway Plan Section 2 - Land Development and Roadway Access

Recommended Roadway Plan Section 2 - Land Development and Roadway Access Recommended Roadway Plan Section 2 - Land Development and Roadway Access SECTION 2 Land Development and Roadway Access 2.1 Land Use and Access Management The Federal Highway Administration (FHWA) defines

More information

Troutbeck Farm Development

Troutbeck Farm Development Troutbeck Farm Development Willistown Township, Chester County PA For Submission To: Willistown Township Last Revised: October, 4 TPD# INLM.A. 5 E. High Street Suite 65 Pottstown, PA 9464 6.36.3 TPD@TrafficPD.com

More information

Route 7 Corridor Study

Route 7 Corridor Study Route 7 Corridor Study Executive Summary Study Area The following report analyzes a segment of the Virginia State Route 7 corridor. The corridor study area, spanning over 5 miles in length, is a multi

More information

City of Wayzata Comprehensive Plan 2030 Transportation Chapter: Appendix A

City of Wayzata Comprehensive Plan 2030 Transportation Chapter: Appendix A A1. Functional Classification Table A-1 illustrates the Metropolitan Council s detailed criteria established for the functional classification of roadways within the Twin Cities Metropolitan Area. Table

More information

Table of Contents FIGURES TABLES APPENDICES. Traffic Impact Study Hudson Street Parking Garage MC Project No.: A Table of Contents

Table of Contents FIGURES TABLES APPENDICES. Traffic Impact Study Hudson Street Parking Garage MC Project No.: A Table of Contents Traffic Impact Study Hudson Street Parking Garage MC Project No.: 151714A Table of Contents Table of Contents I. INTRODUCTION... 2 II. EXISTING CONDITIONS... 5 III. 215 EXISTING TRAFFIC CONDITIONS... 6

More information

Clackamas County Comprehensive Plan

Clackamas County Comprehensive Plan ROADWAYS The County s road system permits the movement of goods and people between communities and regions, using any of a variety of modes of travel. Roads provide access to virtually all property. They

More information

Existing Conditions. Date: April 16 th, Dan Holderness; Coralville City Engineer Scott Larson; Coralville Assistant City Engineer

Existing Conditions. Date: April 16 th, Dan Holderness; Coralville City Engineer Scott Larson; Coralville Assistant City Engineer Date: April 16 th, 2015 To: From: Re: Dan Holderness; Coralville City Engineer Scott Larson; Coralville Assistant City Engineer Darian Nagle-Gamm, Traffic Engineering Planner Highway 6 (2 nd Street) /

More information

3.9 Recreational Trails and Natural Areas

3.9 Recreational Trails and Natural Areas 3.9 Recreational Trails and Natural Areas 3.9.1 Introduction Parks and other recreational facilities such as trails, bicycle routes, and open space are important community resources. This section discusses

More information

9 Leeming Drive Redevelopment Ottawa, ON Transportation Brief. Prepared By: Stantec Consulting Ltd.

9 Leeming Drive Redevelopment Ottawa, ON Transportation Brief. Prepared By: Stantec Consulting Ltd. 9 Leeming Drive Redevelopment Ottawa, ON Transportation Brief Prepared By: Stantec Consulting Ltd. TIA GUIDELINES CHECKLIST Report Context Municipal Address Comment: Section 1.1 Location relative to major

More information

REDEVELOPMENT TRAFFIC IMPACT STUDY

REDEVELOPMENT TRAFFIC IMPACT STUDY REDEVELOPMENT TRAFFIC IMPACT STUDY For Wendy s Parker, Colorado January 215 Prepared for: Sterling Design Associates, LLC 29 W. Littleton Boulevard #3 Littleton, Colorado 812 Prepared by: 1233 Airport

More information

Traffic Impact Analysis

Traffic Impact Analysis Traffic Impact Analysis TRAFFIC IMPACT ANALYSIS FOR A PROPOSED NEIGHBORHOOD SHOPPING CENTER Civic Center Way and Cross Creek Road City of Malibu Prepared for: Goldman Firth Rossi Architects Prepared by:

More information

V. ENVIRONMENTAL IMPACT ANALYSIS K. TRANSPORTATION AND CIRCULATION

V. ENVIRONMENTAL IMPACT ANALYSIS K. TRANSPORTATION AND CIRCULATION V. ENVIRONMENTAL IMPACT ANALYSIS K. TRANSPORTATION AND CIRCULATION ENVIRONMENTAL SETTING The following section is based on the Draft Traffic Circulation Study for the Malibu La Paz Project (Traffic Study),

More information

3.16 TRANSPORTATION, CIRCULATION, AND PARKING Regulatory Setting Environmental Setting ROADWAY SYSTEM

3.16 TRANSPORTATION, CIRCULATION, AND PARKING Regulatory Setting Environmental Setting ROADWAY SYSTEM 3.16 TRANSPORTATION, CIRCULATION, AND PARKING This section assesses the potential for implementation of the Orchard Park Redevelopment component of the 2018 LRDP to result in impacts related to transportation,

More information

Michael A. Werthmann, PE, PTOE Principal

Michael A. Werthmann, PE, PTOE Principal 9575 West Higgins Road, Suite 400 Rosemont, Illinois 60018 p: 847-518-9990 f: 847-518-9987 MEMORANDUM TO: FROM: Brian Lorenc GHB-630, LLC Michael A. Werthmann, E, TOE rincipal Luay R. Aboona, E rincipal

More information

MEDICAL/OFFICE BUILDING 1637 BANK STREET OTTAWA, ONTARIO TRANSPORTATION OVERVIEW. Prepared for:

MEDICAL/OFFICE BUILDING 1637 BANK STREET OTTAWA, ONTARIO TRANSPORTATION OVERVIEW. Prepared for: MEDICAL/OFFICE BUILDING 1637 BANK STREET OTTAWA, ONTARIO TRANSPORTATION OVERVIEW Prepared for: 2434984 Ontario Inc. 13-5510 Canotek Road Ottawa, Ontario K1J 9J5 June 4, 2015 115-613 Report_2.doc D. J.

More information

DUNBOW ROAD FUNCTIONAL PLANNING

DUNBOW ROAD FUNCTIONAL PLANNING DUNBOW ROAD FUNCTIONAL PLANNING Final Report August 3, 216 #31, 316 5th Avenue NE Calgary, AB T2A 6K4 Phone: 43.273.91 Fax: 43.273.344 wattconsultinggroup.com Dunbow Road Functional Planning Final Report

More information

GOAL 2A: ESTABLISH AND MAINTAIN A SAFE, CONVENIENT, AND EFFICIENT MULTI-MODAL TRANSPORTATION SYSTEM TO MOVE PEOPLE AND GOODS THROUGHOUT THE CITY.

GOAL 2A: ESTABLISH AND MAINTAIN A SAFE, CONVENIENT, AND EFFICIENT MULTI-MODAL TRANSPORTATION SYSTEM TO MOVE PEOPLE AND GOODS THROUGHOUT THE CITY. 2. TRANSPORTATION ELEMENT The purpose of this element is to assist in establishing an adequate transportation system within the City and to plan for future motorized and non-motorized traffic circulation

More information

6060 North Central Expressway Mixed-Use Site Dallas, Texas

6060 North Central Expressway Mixed-Use Site Dallas, Texas Volume 1 Traffic Impact Analysis 6060 North Central Expressway Mixed-Use Site Dallas, Texas April 30, 2018 Kimley-Horn and Associates, Inc. Dallas, Texas Project #063238300 Registered Firm F-928 Traffic

More information

Complete Street Analysis of a Road Diet: Orange Grove Boulevard, Pasadena, CA

Complete Street Analysis of a Road Diet: Orange Grove Boulevard, Pasadena, CA Complete Street Analysis of a Road Diet: Orange Grove Boulevard, Pasadena, CA Aaron Elias, Bill Cisco Abstract As part of evaluating the feasibility of a road diet on Orange Grove Boulevard in Pasadena,

More information

Section 3.14 Transportation and Traffic

Section 3.14 Transportation and Traffic Section 3.14 Transportation and Traffic 3.14.1 Introduction The analysis contained in this section is based on the results of the TIA prepared by Fehr and Peers, dated March 2017, and included in Appendix

More information

TRAFFIC IMPACT ANALYSIS OF PROPOSED CHESTNUT HILL COLLEGE MASTER PLAN DEVELOPMENT

TRAFFIC IMPACT ANALYSIS OF PROPOSED CHESTNUT HILL COLLEGE MASTER PLAN DEVELOPMENT TRAFFIC IMPACT ANALYSIS OF PROPOSED CHESTNUT HILL COLLEGE MASTER PLAN DEVELOPMENT Prepared by Orth-Rodgers & Associates, Inc. December 14, 2009 Updated November 9, 2010 230 South Broad Street Philadelphia

More information

5. RUNNINGWAY GUIDELINES

5. RUNNINGWAY GUIDELINES 5. RUNNINGWAY GUIDELINES These guidelines should be considered collectively when making runningway decisions. A runningway is the linear component of the transit system that forms the right-of-way reserved

More information

PRELIMINARY DRAFT WADDLE ROAD / I-99 INTERCHANGE PROJECT ALTERNATIVE ANALYSIS FINAL TRAFFIC SUMMARY REPORT

PRELIMINARY DRAFT WADDLE ROAD / I-99 INTERCHANGE PROJECT ALTERNATIVE ANALYSIS FINAL TRAFFIC SUMMARY REPORT PRELIMINARY DRAFT WADDLE ROAD / I-99 INTERCHANGE PROJECT ALTERNATIVE ANALYSIS FINAL TRAFFIC SUMMARY REPORT Prepared by: In Association with: November 2013 EXECUTIVE SUMMARY Patton Township, in partnership

More information

Bistro 6. City of Barrie. Traffic Impact Study for Pratt Hansen Group Inc. Type of Document: Final Report. Project Number: JDE 1748

Bistro 6. City of Barrie. Traffic Impact Study for Pratt Hansen Group Inc. Type of Document: Final Report. Project Number: JDE 1748 City of Barrie Traffic Impact Study for Pratt Hansen Group Inc. Type of Document: Final Report Project Number: JDE 1748 Date Submitted: June 12 th, 2017 06/12/17 John Northcote, P.Eng. Professional License

More information

Draft Report. Traffic Impact Study. Superstore, Wal-Mart, and Kent Development. Yarmouth, Nova Scotia. Prepared for

Draft Report. Traffic Impact Study. Superstore, Wal-Mart, and Kent Development. Yarmouth, Nova Scotia. Prepared for oad & Traffic Management Road & Traffic Management R Atlantic Traffic Engineering Specialists Draft Report Traffic Impact Study Superstore, Wal-Mart, and Kent Development Yarmouth, Nova Scotia Prepared

More information

REVIEW OF LOCAL TRAFFIC FLOW / LONG RANGE PLANNING SOLUTIONS STUDY

REVIEW OF LOCAL TRAFFIC FLOW / LONG RANGE PLANNING SOLUTIONS STUDY ITEM Town of Atherton TRANSPORTATION COMMITTEE STAFF REPORT TO: FROM: MEMBERS OF THE COMMITTEE ROBERT OVADIA, PUBLIC WORKS DIRECTOR DATE: FEBRUARY 12, 2019 SUBJECT: REVIEW OF LOCAL TRAFFIC FLOW / LONG

More information

SELECTED ROADWAY CAPACITY ANALYSIS

SELECTED ROADWAY CAPACITY ANALYSIS CHAPTERFOUR SELECTED ROADWAY CAPACITY ANALYSIS 4.1 SELECTED ROADWAY CAPACITY ANALYSIS Introduction Capacity analysis was performed on six selected roadways within the Dearborn County study area using the

More information

APPENDIXB. Traffic Operations Technical Memorandum

APPENDIXB. Traffic Operations Technical Memorandum APPENDIXB Traffic Operations Technical Memorandum Environmental Assessment - Lincoln County, SD 85 th Street: Sundowner Avenue to Louise Avenue November 2017 MEMORANDUM Transportation Jim Kollbaum, PE

More information

Appendix B: Forecasting and Traffic Operations Analysis Framework Document

Appendix B: Forecasting and Traffic Operations Analysis Framework Document Existing Conditions Report - Appendix Appendix B: Forecasting and Traffic Operations Analysis Framework Document This document defines the methodology and assumptions that will be used in the traffic forecasting

More information

122 Avenue: 107 Street to Fort Road

122 Avenue: 107 Street to Fort Road : 107 Street to Fort Road November 24, 2015 4:30 8:00 p.m. Meeting Purpose Summarize project work completed to date Share results of public input from Phase 1 Share the draft concept plan and proposed

More information

CITY OF SASKATOON COUNCIL POLICY

CITY OF SASKATOON COUNCIL POLICY ORIGIN/AUTHORITY Clause 1, Report No. 1-1980 and Clause 4, Report No. 22-1990 of the Works and Utilities Committee; Clause 6, Report No. 17-2004 of the Planning and Operations Committee; and Clause D5,

More information

Glenn Avenue Corridor Traffic Operational Evaluation

Glenn Avenue Corridor Traffic Operational Evaluation Glenn Avenue Corridor Traffic Operational Evaluation PREPARED FOR: THE CITY OF AUBURN PREPARED BY: DECEMBER 2007 Glenn Avenue Corridor Study--Auburn, Alabama TABLE OF CONTENTS Introduction... 1 Background

More information

APPENDIX H TRAFFIC REPORT

APPENDIX H TRAFFIC REPORT APPENDIX H TRAFFIC REPORT Keith Higgins Traffic En ginee r WEST END SAND CITY TRAFFIC IMPACT ANALYSIS DRAFT REPORT SAND CITY, CALIFORNIA Prepared for DBO Development No. 3 Monterey, CA Prepared by Keith

More information

EXECUTIVE SUMMARY. Page 1 of 6

EXECUTIVE SUMMARY. Page 1 of 6 EXECUTIVE SUMMARY The purpose of this report is to identify conformance with the original traffic impact study for the proposed retail development on Lot 5 of Riverdale Retail Filing No. 1 located on the

More information