1 connections 2040 the waco metropolitan transportation plan amendment 2 developed by the waco metropolitan planning organization in cooperation with the following agencies: Adopted December 14, 2017
2 amendment 2: december, 2017 purpose and need for amendment On October 26, 2017, the Texas Transportation Commission awarded funding to 2 project applications submitted by the City of Waco under the Transportation Alternatives Set-Aside Program (TASA). This amendment specifically identifies these projects and updates the project limits, scope of work, cost and funding sources to ensure consistency with Commission actions and project programming within the Transportation Improvement Program. revenue forecasts Federal law requires projects identified within the Metropolitan Transportation Plan to be constrained by a reasonable projection of funds which governments within McLennan County anticipate receiving during the planning period. Project costs beyond the anticipated revenues are unfunded and cannot be identified as a recommended priority within the MTP. This section outlines significant changes anticipated to transportation revenues through 2040 as a result of Legislative action that have taken place since adoption of the MTP in January, The projects identified within this amendment received a formal commitment for funding by the Texas Transportation Commission through Minute Order approved on October 26, highways and bridges table A2-1 approved state highway revenues in millions: 2019 through 2025 Funding Category Total Funds Cat 9 Trans Alternatives $3.7 New MTP Mobility Total $3.7 table A2-2 approved state highway revenues in millions: mtp planning horizon: 2015 through 2040 Funding Category Total Funds Cat 9 Trans Alternatives $3.7 New MTP Mobility Total $3.7 strategy 6: improve regional livability additional short term priorities (2019 to 2025) New Priority 2 Project ID: BP-001 Facility: Current: Scope of Work: Elm Ave Brazos River to Forrest St / Garrison St 2 lane urban arterial Construct continuous sidewalks, bike lanes and streetscape improvements Purpose and Need: Provide bicycle and pedestrian connection between Downtown Waco and East Waco Funding Commitment through Transportation Commission Minute Order * Engineering $0.3** Right of Way $0.0 Construction $3.1 Total $3.4 **Phase complete or underway New Priority 3 Project ID: BP-002 Facility: Current: Scope of Work: South 11 th Street / South 12 th Street Garden Dr to Columbus Ave 2 lane urban arterial Construct continuous sidewalks and bike lanes Purpose and Need: Provide bicycle and pedestrian connection between Downtown Waco, South Waco and southern portion of Baylor University campus Funding Commitment through Transportation Commission Minute Order * Engineering $0.05** Right of Way $0.0 Construction $0.4 Total $0.45 **Phase complete or underway connections 2040: the waco metropolitan transportation plan Page 117
3 New Priority 4 Project ID: BP-003 Facility: Current: Scope of Work: Gurley Ln South 10 th Street to South 27 th Street 2 lane urban collector Construct continuous sidewalks Purpose and Need: Provide pedestrian connection between Kennedy Circle Homes (Waco Housing Authority) and South Waco Elementary School Funding Commitment through Transportation Commission Minute Order * Engineering $0.05** Right of Way $0.0 Construction $0.2 Total $0.25 **Phase complete or underway long term priorities (2026 to 2040) Reassigned to Priority 5 Project ID: BRW-3 NOTE: No changes to extent, scope of work or costs. Facility: Brazos Riverwalk Scope of Work: Brazos Park East to Riverbend Park 1) Construct multi-purpose bicycle and pedestrian trail adjacent to the Brazos / Bosque Rivers 2) Construct bicycle and pedestrian bridge across Brazos River either adjacent to or attached to the M L King Drive bridge Purpose and Need: Extend bicycle and pedestrian access via riverwalk to several recreational facilities and McLennan Community College USDOT Transportation Alternatives Program (TAP) * Engineering $0.4 Right of Way $0.5 Construction $7.0 Total $7.9 Reassigned to Priority 6 Project ID: R-001 NOTE: No changes to extent, scope of work or costs. Service: Interregional Passenger Rail Oklahoma to Mexico Scope of Work: 1) Construct passenger rail station adjacent to Intermodal Transfer Station for Waco Transit 2) Implement passenger rail services with stop in Downtown Waco (see note below) Purpose and Need: Provide connections to Dallas / Fort Worth, Austin, San Antonio and beyond as additional method to address interregional mobility demand Notes: TxDOT / USDOT passenger rail development funds, farebox revenue TxDOT study underway to determine feasibility of different service options, speeds, and stop locations. This project does not identify specifics with regards to these and other factors such as proposed alignments or grade separation as they are unknown as of publication of this plan. The project is a placeholder; however, indicating MPO support for the eventual recommendations of the TxDOT study provided any proposed service stops in Downtown Waco. The costs identified below are only for the construction of the Downtown Waco station. * Engineering $0.4 Right of Way $0.5 Construction $4.0 Total $4.9 table A2-3 additional total costs* for strategy 6 Mode Short-Term Long-Term Total Highways $0 $0.0 $0.0 Bicycle $0 $1.2 $1.2 Pedestrian $0 $2.5 $2.5 Total All Modes $0 $3.7 $3.7 Total MTP Strategy 6 $466.9 $3.7 $3.7 summary of recommendations In October, 2017, the Texas Transportation Commission awarded funding for several bicycle & pedestrian projects within the City of Waco as part of the Transportation Alternatives Set-Aside Program (TASA). As a result of this funding commitment, this amendment adds these projects to the Metropolitan Transportation Plan as funded recommendations within Strategy 6: Improve Regional Livability. connections 2040: the waco metropolitan transportation plan Page 118
4 table A2-4 total additional costs* of plan recommendations by strategy Strategy 1 Highway Mobility Short- Term Long-Term Total Percent of Amendment $0.0 $0.0 $ % 2 - Maintenance $0.0 $0.0 $ % 3 Access to Opportunity $0.0 $0.0 $ % 4 - Safety $0.0 $0.0 $ % 5 - Efficiency $0.0 $0.0 $ % 6 Livability $3.7 $0.0 $ % Total Plan $3.7 $0.0 $ % table A2-6 total costs* of plan recommendations by strategy after amendment Strategy 1 Highway Mobility Short- Term Long-Term Total Percent of Plan $466.9 $188.4 $ % 2 - Maintenance $324.6 $677.8 $1, % 3 Access to Opportunity $134.7 $187.0 $ % 4 - Safety $29.4 $61.2 $ % 5 - Efficiency $12.2 $3.0 $ % 6 Livability $19.7 $31.4 $ % Total Plan $987.5 $1,148.8 $2, % table A2-5 total additional costs* of plan recommendations by transportation mode Mode Short- Term Long-Term Total Percent of Amendment Highway $0.0 $0.0 $ % Public Transportation $0.0 $0.0 $ % Bicycle $1.2 $0.0 $ % Pedestrian $2.5 $0.0 $ % Passenger Rail $0.0 $0.0 $ % Total Plan $3.7 $0.0 $ % connections 2040: the waco metropolitan transportation plan Page 119
5 China Spring!( Chalk Bluff!( current priorities new additions waco metropolitan area 1 priority ranking 1637 China Spring Rd Bosqueville!( Lacy- Lakeview 35 Craven Ave Airbase Rd!( B77 F Miles november, 2017 map A2.1 Amendment 2 strategy 6: improve regional livability project recommendations!( 6 North River Crossing 185 Speegleville!( Speegleville Rd N Hwy Old Lorena Rd *Main lanes only. Bicycles permitted on frontage roads.!( 6 Lake Waco Chapel Rd Panther Way Ritchie Rd Santa Fe Dr Woodway Hewitt Dr Lake Shore Dr H ill crest Tx Central Pkwy Lake Air Dr Park Lake Dr MacArthur Dr Dr New Rd N Valley Mills Dr 1695 Hewitt Sanger Ave Steinbeck Bend Dr N 19th St 1637 Imperial Dr 2063 N 25th St Bosque Blvd Franklin Ave Bagby Ave N18th St Lake Shore Dr M L King Jr Dr S Valley Mills Dr Memorial Dr 340 New Rd iver Braz os R N 4th St WACO Washington Ave Herring Ave S 17th St E Waco Dr 35 S Loop 340 Gholson Rd 2 6 Elm St 3 4 Beverly Hills 77 1 Robinson Robinson Dr 35 LaSalle Ave!( 6 S Loop Dr 340 Bellmead Dr B77 Bellmead S Univ Parks Dr Orchard Ln 434 S Univ Parks Dr E Loop S 3rd St Rd 434!( 6 E Hwy 6 connections 2040 the waco metropolitan transportation plan 1860 Disclaimer: This product is for informational purposes and may not have been prepared for or be suitable for legal, engineering, or surveying purposes. It does not represent an on-the-ground survey and represents only the approximate relative location of property boundaries, if applicable Moonlight Dr
6
7
8
section 8: recommendations
section 8: recommendations The Waco MPO has identified the following strategies in order to make progress towards the guiding principles identified in Section 3. Each of these strategies is constrained
More informationsection 8: recommendations
section 8: recommendations The Waco MPO has identified the following strategies in order to make progress towards the guiding principles identified in Section 3. Each of these strategies is constrained
More informationThe Transportation Improvement Program
Waco Metropolitan Planning Organization The Transportation Improvement Program Waco Urbanized Area For Fiscal Years 2015 Through 2018 Proposed Amendment 4 FY 2016 PHASE: E COUNTY: McLennan LIMITS FROM:
More informationsection 6: needs and gap analysis
section 6: needs and gap analysis 6.1 highways and bridges With more than 93% of the region s commuters using automobiles (US Census Bureau, 2008-2012), the highway mode is by far the current mode of choice
More informationCorpus Christi Metropolitan Transportation Plan Fiscal Year Introduction:
Introduction: The Safe, Accountable, Flexible, Efficient Transportation Equity Act: A Legacy for Users (SAFETEA-LU) has continued the efforts started through the Intermodal Surface Transportation Efficiency
More informationAttachment One. Integration of Performance Measures Into the Bryan/College Station MPO FY 2019 FY 2022 Transportation Improvement Program
Attachment One Integration of Performance Measures Into the Bryan/College Station MPO FY 2019 FY 2022 Transportation Improvement Program Introduction Begun as part of the Moving Ahead for Progress in the
More informationBicycle and Pedestrian Plans and Improvements
Bicycle and Pedestrian Plans and Improvements Presented to the City Council By Randle Harwood, Planning and Development, and Richard Zavala, Parks and Community Services September 24, 2013 Purpose Review
More informationBasalt Creek Transportation Refinement Plan Recommendations
Basalt Creek Transportation Refinement Plan Recommendations Introduction The Basalt Creek transportation planning effort analyzed future transportation conditions and evaluated alternative strategies for
More informationBICYCLE PROGRAM IMPLEMENTATION UPDATE. Transportation and Trinity River Project Council Committee June 13, 2016
BICYCLE PROGRAM IMPLEMENTATION UPDATE Transportation and Trinity River Project Council Committee Purpose 01 Provide background and a status update on onstreet bicycle facility planning and implementation
More informationBroward Boulevard Gateway Implementation Project, Downtown Walkability Analysis, & Joint Development Initiative (JDI)
Broward Boulevard Gateway Implementation Project, Downtown Walkability Analysis, & Joint Development Initiative (JDI) City of Fort Lauderdale ~ Commission Conference July 10, 2012 Page 1 of 15 A Multi-Agency
More informationAPPENDIX D: Southwest Volusia Regional Transportation Study. Evaluation Criteria FINAL
D: PROJECT PRIORITIZATION Prioritization of the improvements proposed in the Multimodal Improvement Plan is required in order to determine which projects should be funded first, where the transportation
More informationWaco Downtown Transportation Study
Waco Downtown Transportation Study Technical Memorandum 1 Prepared for: City of Waco Public Open House Michael Townes Vice President, Transit Market Leader CDM Smith April 10, 2014 Agenda Introduction
More informationTulsa Metropolitan Area LONG RANGE TRANSPORTATION PLAN
Tulsa Metropolitan Area LONG RANGE TRANSPORTATION PLAN Indian Nations Council of Governments August 2005 CONTACTING INCOG In developing the Destination 2030 Long Range Transportation Plan, INCOG s Transportation
More informationProposed Project I 35 from Denton to Cooke County Line
Proposed Project I 35 from Denton to Cooke County Line The existing I 35 facility is four lanes from I 35E/I 35W to Farm to Market Road (FM) 3002. The purpose of the proposed project is to increase capacity
More informationMulti Modal Transit Access Plan KIPDA ID # 239. Project Type: STUDY
Multi Modal Transit Access Plan KIPDA ID # 239 Project Type: STUDY Description: In conjunction with the results from Project Gobility and the Transit LOS Analysis, TARC seeks to examine the possibilities
More informationPEDESTRIAN ACTION PLAN
CITY OF SANTA MONICA PEDESTRIAN ACTION PLAN DRAFT OCTOBER 2015 City Council, February 23, 2016 Beth Rolandson, AICP Principal Transportation Planner Mobility Division, Planning and Community Development
More informationNon-Motorized Transportation 7-1
Non-Motorized Transportation 7-1 Transportation facilities no longer mean just accommodating a vehicle powered by a combustion engine. Pedestrian and non-motorized facilities are important modes of travel
More informationBicycle and Pedestrian Chapter TPP Update Overview. TAB September 20, 2017
Bicycle and Pedestrian Chapter TPP Update Overview TAB September 20, 2017 Bicycling & Walking in the Twin Cities Where are we now? The Bike-Pedestrian system Current trends New developments Where are we
More informationBest Southwest Transportation Committee. North Central Texas Council of Governments Transportation Department
Best Southwest Transportation Committee North Central Texas Council of Governments Transportation Department The The Regional Regional Veloweb Veloweb Review Review NCTCOG Bicycle and Pedestrian Program
More informationACTIVE TRANSPORTATION
ACTIVE TRANSPORTATION Mobility 2040 Supported Goals Improve the availability of transportation options for people and goods. Support travel efficiency measures and system enhancements targeted at congestion
More informationADOT Statewide Bicycle and Pedestrian Program Summary of Phase IV Activities APPENDIX B PEDESTRIAN DEMAND INDEX
ADOT Statewide Bicycle and Pedestrian Program Summary of Activities APPENDIX B PEDESTRIAN DEMAND INDEX May 24, 2009 Pedestrian Demand Index for State Highway Facilities Revised: May 29, 2007 Introduction
More informationRail Station Fact Sheet DFW Airport North Station* (*station under construction with anticipated start of service in late 2018)
Rail Station Fact Sheet DFW Airport North Station* (*station under construction with anticipated start of service in late 018) Station Overview DFW Airport North Station will be located on DFW nternational
More informationBASS PRO DRIVE TO: WEST OF FARM-TO-MARKET ROAD (FM)
NOTICE OF PUBLIC MEETING INTERSTATE HIGHWAY 30 (Rockwall) FROM: BASS PRO DRIVE TO: WEST OF FARM-TO-MARKET ROAD (FM) 2642 CSJs: 0009-11-238; 0009-12-215; 0009-12-908 Dallas County and Rockwall County, Texas
More informationWe believe the following comments and suggestions can help the department meet those goals.
The Honorable Secretary Anthony Foxx The Secretary of Transportation United States Department of Transportation 1200 New Jersey Avenue, SE Washington, DC 20590 August 30, 2013 Dear Secretary Foxx, Thank
More informationAppendix C 3. Bicycle / Pedestrian Planning
Appendix C 3. Bicycle / Pedestrian Planning BICYCLE/PEDESTRIAN PLANNING 2005 Master Plan GOAL: Provide for safe and convenient bicycle and pedestrian circulation throughout the City. Develop a city-wide
More information4. ENVIRONMENTAL IMPACT ANALYSIS 9. TRANSPORTATION AND TRAFFIC
4. ENVIRONMENTAL IMPACT ANALYSIS 9. TRANSPORTATION AND TRAFFIC 4.9.1 INTRODUCTION The following section addresses the Proposed Project s impact on transportation and traffic based on the Traffic Study
More informationPedestrian Improvements Kemp Blvd Wichita Falls (Midwestern Pkwy to Southwest Pkwy)
EXHIBIT A TRANSPORTATION ALTERNATIVES PROGRAM (TAP) PROJECTS SELECTED FOR FUNDING SMALL URBAN AREAS (POPULATION 5,001 200,000) Nominating Entity TAP Project Name Federal Funds Bryan South College Phase
More informationPortland International Airport Bicycle and Pedestrian Plan (October 2003) Staff Acknowledgements
Portland International Airport Bicycle and Pedestrian Plan (October 2003) Staff Acknowledgements Scott King, Senior Aviation Planner Jason Gately, Senior Aviation Planner Preston Beck, Associate Planner
More informationOTO BIKE/PED PLAN REPORT
OTO BIKE/PED PLAN REPORT 6/30/2012 Implementation in FY2012 This report outlines the bike/ped accomplishments related to the OTO Bike/Ped Plan. Activities occurring during the 2012 Fiscal Year, July 1,
More informationSR-203 Sidewalks and Town-Wide Mobility Improvements. Town Council Presentation September 7, 2016
SR-203 Sidewalks and Town-Wide Mobility Improvements Town Council Presentation September 7, 2016 SR-203 Sidewalks and Town- Wide Mobility Improvements SR-203 Sidewalks and Appurtenances Town-Wide Mobility
More informationDRAFT BUENA VISTA 2020 TRANSPORTATION PLAN
DRAFT BUENA VISTA 2020 TRANSPORTATION PLAN DEVELOPED BY THE TRANSPORTATION PLANNING DIVISION OF THE VIRGINIA DEPARTMENT OF TRANSPORTATION IN COOPERATION WITH THE U.S. DEPARTMENT OF TRANSPORTATION, FEDERAL
More informationBuilding Great Neighbourhoods BONNIE DOON
Building Great Neighbourhoods BONNIE DOON We Are Here Today To Explain the Neighbourhood Renewal Process Show you the Westwood Preliminary Design Ask for local knowledge Highlight the Local Improvement
More informationChapter 5 Future Transportation
Chapter 5 Future Transportation The Future Land Use Plan identifies the desired land use designations. The land uses desired for Crozet depend, in large part, on the success of the transportation system,
More informationNEW BRAUNFELS SEGUIN AREA REGIONAL TRANSPORTATION DRAFT PLAN NEW BRAUNFELS CITY COUNCIL MEETING
NEW BRAUNFELS SEGUIN AREA REGIONAL TRANSPORTATION DRAFT PLAN NEW BRAUNFELS CITY COUNCIL MEETING February 13, 2012 This regional transportation plan will: 1. Review existing plans for the cities and counties,
More informationVDOT BICYCLE & PEDESTRIAN IMPLEMENTATION GUIDE FOR LOCALITY INVOLVEMENT April 2017
VDOT BICYCLE & PEDESTRIAN IMPLEMENTATION GUIDE FOR LOCALITY INVOLVEMENT April 2017 1 TABLE OF CONTENTS Topic Page(s) About this Guide 3 Encouraging development of bicycle and pedestrian plans by localities
More informationCity of Gainesville Transportation/Roadway Needs PROJECT SUMMARY
A1 Roadway Resurfacing $23,846,000 TYPE: Preservation of existing system Roadway resurfacing A2 Signal Replacement $6,000,000 TYPE: Preservation of existing system Replace traffic signals. B1 W 6th St
More informationCommerce Street Complete Street Project from Good Latimer Expressway to Exposition Avenue
Commerce Street Complete Street Project from Good Latimer Expressway to Exposition Avenue T A N Y A B R O O K S A S S I S T A N T D I R E C T O R M O B I L I T Y P L A N N I N G M O B I L I T Y A N D S
More informationTRANSPORTATION & MOBILITY
TRANSPORTATION & MOBILITY ROADWAY SYSTEM There are approximately 40 miles of roadways in Manitou Springs. For planning purposes, roadways are typically assigned a functional classification which defines
More informationPrince George s County plans, policies, and projects
Prince George s County plans, policies, and projects Over 250 projects for trails, bikeways, designated bike lanes and sidewalk construction Trail projects that improve access to Metro Sidewalk and trail
More informationDISTRICT BICYCLE PROGRAM
DISTRICT BICYCLE PROGRAM TxDOT Fort Worth District Public Hearing Bicycle Use on the State Highway System Public Hearing Agenda 1 2 3 4 5 6 Introduction Susan Howard TxDOT Public Involvement Specialist
More informationFMATS Transportation Improvement Program Non-Motorized Project Nomination Form
Project nominations are accepted from the public and are scored based on the adopted Project Scoring Criteria. These criteria assign weight based on the project s impact on the following: 1. Health and
More informationWestgate/Belvedere Homes Community Redevelopment Agency. Belvedere Heights. Streetlights & Sidewalks Improvements Project.
Westgate/Belvedere Homes Community Redevelopment Agency Belvedere Heights Streetlights & Sidewalks Improvements Project Phase II TPA 2018 Transportation Alternatives Program (TAP) BTPAC Presentation Thursday,
More informationCity of Hamilton s Transportation Master Plan (TMP) Public Consultation 3 December 2015
City of Hamilton s Transportation Master Plan (TMP) Public Consultation 3 December 2015 McPhail Transportation Planning Services Ltd. AGENDA 6:00 7:00 pm Viewing Boards / Q & A with the Team 7:00 7:50
More informationCongress Avenue. Palm Beach MPO Subcommittee Meetings December 2017
1 Congress Avenue Palm Beach MPO Subcommittee Meetings December 2017 2 Agenda Study Purpose Study Process Multimodal Alternatives Development Next Steps *ACTION ITEM: CONFIRM ALTERNATIVES TO MOVE INTO
More informationCITY OF BLOOMINGTON COMPLETE STREETS POLICY
CITY OF BLOOMINGTON COMPLETE STREETS POLICY POLICY OBJECTIVE: The City of Bloomington will enhance safety, mobility, accessibility and convenience for transportation network users of all ages and abilities,
More informationEXISTING PRIORITIES FUNDED FOR CONSTRUCTION LRTP
EXISTING PRIORITIES FUNDED FOR CONSTRUCTION Limits Description Status 1 415489 3 H1865 US HWY 301 FROM SR 674 TO BALM RD Widen 2 lanes to 6 lanes divided County / Construction Programmed 2016 2 405492
More informationKEARNY MESA COMMUNITY PLAN UPDATE
KEARNY MESA COMMUNITY PLAN UPDATE January 18, 2018 SUBCOMMITTEE MEETING Mobility Concepts and Urban Design Presentation Outline Mobility Concepts: Multimodal Planning Toolbox Presentation and Activities
More informationThird Street Bridge & Corridor Project
Third Street Bridge & Corridor Project Preparation for the FY2018 budget to commence October 1, 2017, includes funding to address a project that has been considered since 1994. The Third Street bridge
More informationNEED FOR ADDITIONAL FUNDING
Measure B BACKGROUND 2013: Vision for a supplement to Measure A that prioritizes local roads & regional capital projects Plan developed by Professional Advisory Group Consensus recently built on RT O&M
More informationTRANSPORTATION TRAINING TOPICS. April 6, 2010
TRANSPORTATION TRAINING TOPICS April 6, 2010 Roles of Transportation Providers Context and Policy Makers Division of Transportation and Traffic Other City Operations Other Transportation Operators CMA
More informationBICYCLE PUBLIC HEARING INTRODUCTION. Kathy Kleinschmidt, P.E. Bicycle and Pedestrian Coordinator Dallas District
BICYCLE PUBLIC HEARING INTRODUCTION Kathy Kleinschmidt, P.E. Bicycle and Pedestrian Coordinator Dallas District Purpose of Public Hearing Texas State Law (Title 43, Subchapter D, 25.55 (b)) affords each
More informationExhibit 1 PLANNING COMMISSION AGENDA ITEM
Exhibit 1 PLANNING COMMISSION AGENDA ITEM Project Name: Grand Junction Circulation Plan Grand Junction Complete Streets Policy Applicant: City of Grand Junction Representative: David Thornton Address:
More informationWest Dimond Blvd Upgrade Jodhpur Street to Sand Lake Road
West Dimond Blvd Jodhpur St to Sand Lake CSS Transportation Project Summary Municipality of Anchorage Project # 05 005 Project Manager: John Smith, P.E. (MOA PM&E) Project Administrator: Julie Makela,
More informationMEASURE B AND MEASURE BB Annual Program Compliance Report Reporting Fiscal Year AGENCY CONTACT INFORMATION
MEASURE B AND MEASURE BB Annual Program Compliance Report Reporting Fiscal Year 2016-2017 AGENCY CONTACT INFORMATION Agency Name: City of Livermore Date: 12/4/2017 Primary Point of Contact Name: Debbie
More informationShenango Valley MPO. State Transportation Commission 2015 Twelve Year Program Development
State Transportation Commission 2015 Twelve Year Program Development Regional results of the survey and public feedback from August thru November 2013 Shenango Valley MPO Version 01-2014 Mobility Concerns
More informationWELCOME TO OPEN HOUSE # 1 June 14, 2017
Langstaff Road Weston Road to Highway 7 Class Environmental Assessment Study WELCOME TO OPEN HOUSE # 1 June 14, 2017 Please sign in and join our mailing list Purpose of Open House #1 & Study Area York
More informationSan Jose Transportation Policy
San Jose Transportation Policy Protected Intersections in LOS Policies to Support Smart Growth Presented by: Manuel Pineda City of San Jose Department of Transportation Bay Area Map San Francisco Oakland
More informationComplete Streets Policies in Charlotte
Complete Streets Policies in Charlotte Complete Streets Peer Exchange Baton Rouge, LA January 19, 2016 Norm Steinman, AICP Charlotte DOT Changing what we do to change what will happen 1. Inventory of Conditions
More informationRail Station Fact Sheet Buckner Station
Rail Station Fact Sheet Buckner Station Station Overview Buckner Station is located at the intersection of Buckner Boulevard and Elam Road in Dallas. The station opened in 2010 and currently serves as
More informationEnvironment and Public Works Committee Presentation
Mixed Use Centers Complete Streets Guidelines Project Environment and Public Works Committee Presentation December 10, 2008 Project Objectives: Conduct an inter-departmental and agency process to study
More informationHennepin County Bicycle and Pedestrian Planning
Hennepin County Bicycle and Pedestrian Planning 1 Value of bicycle and sidewalk systems Safety Livability Mobility Health Personal Finances Economic Sustainability Clean Air Recreation Parking and congestion
More informationSTATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM FY
STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM FY 008-0 Austin District NOVEMBER 007 Quarterly Revisions CAMPO Capital Area Metropolitan Planning Organization October 5, 007 Mr. Robert Daigh, P.E. District
More informationPriority 1: Ala Wai Pedestrian and Bicycle Safety and Mobility Project
Priority 1: Ala Wai Pedestrian and Bicycle Safety and Mobility Project The full application can be found here: http://www.oahumpo.org/wp-content/uploads/2015/05/alawai_application.pdf Description The Ala
More informationCity of Bartow Comprehensive Plan. Transportation Element
City of Bartow 2030 Comprehensive Plan Amended through January 7, 2013 TRANSPORTATION ELEMENT GOAL: IT SHALL BE A GOAL OF THE CITY OF BARTOW TO PROVIDE A SAFE AND EFFICIENT MULTI-MODAL TRANSPORTATION SYSTEM
More information2.0 Existing Conditions
20 2.0 Existing Conditions 2.1 Land Use, Future Growth Patterns, Physical Barriers Geographic Overview Sutter County s land use pattern is characterized by extensive agricultural areas, significant natural
More informationTransportation. Our Parker community. will develop and sustain. a safe, convenient and. efficient transportation. system incorporating
VISION Our Parker community will develop and sustain a safe, convenient and efficient transportation system incorporating and integrating various modes of travel including automobiles, public transportation,
More informationBuilding Great Neighbourhoods QUEEN ALEXANDRA
Building Great Neighbourhoods QUEEN ALEXANDRA We are here today to Explain how the City is investing in improving your neighbourhood and how your neighbourhood will be improved to meet current City standards.
More informationI-35 Corridor Segment Committee NW Loop 410 San Antonio, Texas. February 11, :00 AM to Noon
I-35 Corridor Segment Committee 4 3500 NW Loop 410 San Antonio, Texas February 11, 2010 9:00 AM to Noon Welcome Nancy Parker Facilitator Committee Work Session Nancy Parker Facilitator Discussion of Proposed
More informationFlorida Department of Transportation District Four. I-95 at 6 th Avenue Interchange Improvements FDOT PM - Fernando Morales, PE
1 Florida Department of Transportation District Four I-95 at 6 th Avenue Interchange Improvements FDOT PM - Fernando Morales, PE Presentation Outline Overview of Planning and Programming I-95 Interchange
More informationGoal 3: Foster an environment of partnerships and collaboration to connect our communities and regions to one another.
Non-Motorized Transportation Plan (NMTP) Draft Vision, Goal and,, Tri-County Regional Planning Commission (TCRPC) Purpose The purpose of the Tri-County Regional Planning Commission (TCRPC) Non-Motorized
More informationActive Transportation Infrastructure Investment A Business Case
Active Transportation Infrastructure Investment A Business Case In 2016, the Real Estate Foundation awarded the Capital Regional District a $50,000 grant for Shifting Gears: Land Use Change through Active
More informationAAMPO MOBILITY PROJECT DISCUSSION. July/August 2015
AAMPO MOBILITY PROJECT DISCUSSION July/August 2015 Proposition 1 FY 16 & 17 $1.74 billion transferred to State Highway Fund in FY 2015 $147.3 million let in SAT district in FY 2015 US 90, IH 10, IH 410
More informationTransportation Master Plan Advisory Task Force
Transportation Master Plan Advisory Task Force Network Alternatives & Phasing Strategy February 2016 BACKGROUND Table of Contents BACKGROUND Purpose & Introduction 2 Linking the TMP to Key Council Approved
More informationCity of Atlanta-MARTA Sales Tax Referendum Draft Project List. Atlanta City Council Work Session May 19, 2016
1 City of Atlanta-MARTA Sales Tax Referendum Draft Project List Atlanta City Council Work Session May 19, 2016 2 SB 369 - MARTA Sales tax for up to 0.50% is allowed in the City of Atlanta for MARTA Purpose
More informationLynchburg District Update
Lynchburg District Update Virginia Statewide Bicycle and Pedestrian Advisory Committee Spring Meeting May 16 th, 2017 David Cook Transportation Planner, VDOT Lynchburg District Table of Contents Active
More informationFY 2016 TRANSPORTATION ALTERNATIVES PROGRAM PROJECT SELECTION
AGENDA ITEM #8: FY 2016 TRANSPORTATION ALTERNATIVES PROGRAM PROJECT SELECTION The Transportation Alternatives Program (TAP) created by MAP-21 requires that 50% of the program funds received by the state
More informationTransportation, Parking & Roads
Transportation, Parking & Roads Design Carolina North as a walkable community Design the transportation system and development patterns (i.e., urban design elements such as density, building design, mix
More informationSustainable Transportation Planning in the Portland Region
Sustainable Transportation Planning in the Portland Region Jennifer Dill, Ph.D. Associate Professor School of Urban Studies & Planning jdill@pdx.edu http://web.pdx.edu/~jdill/ Outline Elements of a sustainable
More informationBICYCLE FACILITIES INVENTORY: SUMMARY REPORT
BICYCLE FACILITIES INVENTORY: SUMMARY REPORT Southern New Jersey September 2008 2002 D Lincoln Drive West Marlton, NJ 08053 (856) 596-8228 www.driveless.com BICYCLE FACILITIES INVENTORY SUMMARY REPORT
More informationArlington s Master Transportation Plan
Arlington s Master Transportation Plan The Master Transportation Plan (MTP) Adopted in eight parts Goals & Policies element and MTP Map adopted in 2007 Bicycle, Pedestrian and Demand and Systems Management
More informationSANTA CLARA COUNTYWIDE BICYCLE PLAN August 2008
SANTA CLARA COUNTYWIDE BICYCLE PLAN August 2008 To assist VTA and Member Agencies in the planning, development and programming of bicycle improvements in Santa Clara County. Vision Statement To establish,
More informationDES MOINES AREA MPO. Presentation to Iowa Commercial Real Estate Association. April 6, 2017
DES MOINES AREA MPO Presentation to Iowa Commercial Real Estate Association April 6, 2017 Presentation Outline MPO Overview Trends We re Watching Plans, Projects, Initiatives, Regional Transportation Priorities
More information2016 MOBILITY BOND PROGRAM
February 22, 2017 2016 MOBILITY BOND PROGRAM $720 million bond proposition for transportation and mobility improvements including planning, designing, engineering, constructing, reconstructing, renovating
More information5. RUNNINGWAY GUIDELINES
5. RUNNINGWAY GUIDELINES These guidelines should be considered collectively when making runningway decisions. A runningway is the linear component of the transit system that forms the right-of-way reserved
More informationBikeway Plan for the Roanoke Valley Area MPO Update ACKWOWLEDGEMENTS
ACKWOWLEDGEMENTS This report was prepared by the Roanoke Valley-Alleghany Regional Commission (RVARC), which is the lead staff agency for the Roanoke Valley Area Metropolitan Planning Organization (MPO)
More informationWEST AND SOUTH WEST RING ROAD DOWNSTREAM TRAFFIC IMPACTS
Page 1 of 9 EXECUTIVE SUMMARY Alberta Transportation ( AT ) is preparing to construct the final sections of the Calgary Ring Road. This includes the South West Ring Road ( SWRR ) (from Lott Creek Blvd
More informationEXECUTIVE SUMMARY... vii 1 STUDY OVERVIEW Study Scope Study Area Study Objectives
Contents EXECUTIVE SUMMARY... vii 1 STUDY OVERVIEW... 1-1 1.1 Study Scope... 1-1 1.2 Study Area... 1-1 1.3 Study Objectives... 1-3 2 EXISTING CONDITIONS... 2-1 2.1 Existing Freeway Conditions... 2-4 2.1.1
More informationTRASBURG RANSPORTATION
TRASBURG RANSPORTATION LAN DEVELOPED BY THE TRANSPORTATION PLANNING DIVISION OF THE VIRGINIA DEPARTMENT OF TRANSPORTATION IN COOPERATION WITH THE U.S. DEPARTMENT OF TRANSPORTATION, FEDERAL HIGHWAY ADMINISTRATION
More informationSTREET AND HIGHWAY PLAN
STREET AND HIGHWAY PLAN Introduction The street and highway system in the Winston-Salem Urban Area consists of thousands of miles of traffic carrying facilities, ranging from short local residential streets
More informationCirculation in Elk Grove includes: Motor vehicles, including cars and trucks
Circulation, as it is used in this General Plan, refers to the many ways people and goods move from place to place in Elk Grove and the region. Circulation in Elk Grove includes: Motor vehicles, including
More informationChapter 14 PARLIER RELATIONSHIP TO CITY PLANS AND POLICIES. Recommendations to Improve Pedestrian Safety in the City of Parlier (2014)
Chapter 14 PARLIER This chapter describes the current status and future plans for biking and walking in the City of Parlier. RELATIONSHIP TO CITY PLANS AND POLICIES The Parlier General Plan is the primary
More informationCONNECTING PEOPLE TO PLACES
CONNECTING PEOPLE TO PLACES 82 EAST BENCH MASTER PLAN 07 Introduction The East Bench transportation system is a collection of slow moving, treelined residential streets and major arteries that are the
More informationTxDOT Bicycle Tourism Trails Study Update. April 2017 BAC Meeting April 10, 2017
AGENDA ITEM 6 TxDOT Bicycle Tourism Trails Study Update April 2017 BAC Meeting April 10, 2017 Agenda Approval of interim products o Present study vision statement, goals, and study objectives o Present
More informationAPPENDIX G: INTERSECTION NEEDS AT OKEECHOBEE BOULEVARD
APPENDIX G: INTERSECTION NEEDS AT OKEECHOBEE BOULEVARD INTERSECTION NEEDS AT SR 7 and OKEECHOBEE BOULEVARD SR 7 Extension Project Development and Environment (PD&E) Study From Okeechobee Boulevard (SR
More informationChapter 7. Transportation. Transportation Road Network Plan Transit Cyclists Pedestrians Multi-Use and Equestrian Trails
Chapter 7 Transportation Transportation Road Network Plan Transit Cyclists Pedestrians Multi-Use and Equestrian Trails 7.1 TRANSPORTATION BACKGROUND The District of Maple Ridge faces a number of unique
More informationBicycle Pedestrian Master Plan Pre Bid Meeting Portsmouth, NH August 15, 2013
Bicycle Pedestrian Master Plan Pre Bid Meeting Portsmouth, NH August 15, 2013 2005 Master Plan GOAL: Provide for safe and convenient bicycle and pedestrian circulation throughout the City. Develop a city
More informationComplete Streets Process and Case Study: Taft / McMillian Two-Way Street Conversion Cincinnati, Ohio. Traffic Engineering Workshop June 4, 2014
Complete Streets Process and Case Study: Taft / McMillian Two-Way Street Conversion Cincinnati, Ohio Traffic Engineering Workshop June 4, 2014 Complete Streets Streets that enable safe access for users
More informationMEETING Agenda. Introductions. Project Overview. Key Study Components. Alternative Station Concepts. Preferred Station Concept. Next Steps.
City GARLAND Council ROADVISION Briefing STUDY VISION STUDY Dallas, TX April 8, 2010 1 1 MEETING Agenda Introductions Project Overview Key Study Components Alternative Station Concepts Preferred Station
More informationVIII. Project Prioritization & Implementation
Transportation Plan 2030 July 2006 VIII. Project Prioritization & Implementation Public Transit Service Investigation into the development of a demand responsive service route system through a process
More informationBIKE & PEDESTRIAN IMPLEMENTATION GUIDE FOR LOCALITY INVOLVEMENT. November 2006
BIKE & PEDESTRIAN IMPLEMENTATION GUIDE FOR LOCALITY INVOLVEMENT November 2006 1 of 9 TABLE OF CONTENTS Topic Page(s) Encouraging development of Bike and pedestrian plans by localities 3 5 Involving localities
More information