Ptarmigan Resources Ltd. Ptarmigan Resources Project Conceptual Engineering Study

Size: px
Start display at page:

Download "Ptarmigan Resources Ltd. Ptarmigan Resources Project Conceptual Engineering Study"

Transcription

1 Ptarmigan Resources Ltd. Ptarmigan Resources Project Conceptual Engineering Study August 2004

2 Conceptual Engineering Study Final Report Table of Contents TABLE OF CONTENTS 1.0 Executive Summary Introduction Scope of Study Design Basis MetaOcean Data Wind Waves Temperatures Currents Seafloor Conditions Ice Data Facilities Description/Requirements General Oil Processing System Introduction Liquid and Gas Separation Gas Processing System Water Injection System Chemical Injection Systems Utilities & Other Systems Concept Options FPSO Description and Concept Mooring/Export Systems CALM Buoy SALM Buoy Soft Yoke Tower FPSO New Build Versus Lease Typical FPSO Operating Scenarios Subsea Wells Drilling Typical Operating Cost Lease FPSO Project Schedule Jack-Up Bottom Founded Caisson General Production, Storage and Offloading Drilling Seasonal Vs. Year-Round Production Typical Operating Cost New Build Bottom Founded Caisson Project Schedule... 33

3 Conceptual Engineering Study Final Report Table of Contents 8.0 Conclusion Appendix... 35

4 Conceptual Engineering Study Final Report Page 1 of Executive Summary Ptarmigan Resources Offshore Newfoundland project is located near the West Coast of the province, 25km offshore in 40 meters of water. While the region can be deemed a hostile environment, the conditions are not nearly as severe as the better known Grand Banks area off the East coast, where the Hibernia, Terra Nova and White Rose projects are located. Firstly, there are no icebergs, secondly, the winter icepack covers the region for only one month per year and in some years, there is no icepack. Thirdly, the seastate conditions are less severe than the open Atlantic of the Grand Banks area. Three potential development options were evaluated for a 300 million barrel recoverable reserve case: FPSO Jack-Up Bottom Founded Caisson However, other more costly new build development options, including gravity base structures and subsea tiebacks to onshore processing facilities may still be applicable to larger reserve cases. The FPSO with its production and storage facilities located on one vessel provides many advantages. However, with relatively shallow water, compared to the Grand Banks, an external mooring/export system is required. Two cases were evaluated, seasonal versus year-round production. The second option, a combination Jack-Up drilling and production platform was evaluated as it is a proven concept for shallow water East Coast Canada. However, for a field of 300 million barrels recoverable with 20 wells producing a total of 160,000 barrels per day, a converted drilling Jack-Up is not a viable alternative. It is estimated that the Topsides process facilities required to support a field producing 160,000 barrels per day would weigh in the range of 12,500 tonnes. Secondly, the footprint of such a Topsides package would be significant and the concept would be further challenged with 20 producers and 8 well injection wells. The last option, a Bottom Founded Caisson, is capable of year-round operations but will be the most costly of the options and will require a longer start-up schedule. Typical all-inclusive costs for each concept are as follows: FPSO USD $878,700 per day Caisson USD $1,019,400 per day

5 Conceptual Engineering Study Final Report Page 2 of 35 Secondly, schedule requirements for each of the above are: FPSO 24 months Caisson 48 months It should be noted, that the budget allocated for this conceptual engineering study did not permit an in-depth analysis of the many engineering issues associated with seasonal versus year-round production, subsea versus land-type trees, flow assurance issues, and the like.

6 Conceptual Engineering Study Final Report Page 3 of Introduction Ptarmigan Resources is the license holder of an offshore block located West of the Port au Port Peninsula on the West coast of the Province of Newfoundland and Labrador. The prospects are located approximately 25 kilometers offshore, in 40 meters water depth. Fully risked prospect potential has been estimated at over 600 million barrels of recoverable oil, from up to four prospective zones. In keeping with conservatism, this study is based on development options for recoverable reserves of half that size, or 300 million barrels. While the study focuses on an oil case, there is a strong possibility of significant gas. In May 2004, Pan Maritime Energy Services Inc. were retained to conduct a conceptual engineering study of production options. Figure 1 Map of Region

7 Conceptual Engineering Study Final Report Page 4 of Scope of Study The scope of this Conceptual Engineering Study is as follows: a) Identify and evaluate various production options b) For each options, identify the advantages/disadvantages c) Seasonal versus year-round production d) Mooring/Export systems e) Identify facilities requirements f) Subsea versus dry completions g) Review metaocean data h) Identify project schedule for each option i) Provide ± 25% cost estimate for each option

8 Conceptual Engineering Study Final Report Page 5 of Design Basis The Ptarmigan Project is located 25km offshore, West Coast Newfoundland, in 40m of water. The following are the design parameters, assumed for this study. Item No. Description Assumption 1 Field Location Co-ordinates Latitude: N48 55 Longitude: W Water depth 40m 3 Distance Offshore 25km 4 Average planned well depth 3500m 5 No. of wells, two of six prospects, producers million barrels 4 gas injection 4 water injection 6 Well productivity 5,000 to 15,000 bopd 7 Estimated daily oil production 160,000 bopd 8 Total daily fluids production 200,000 bpd 9 Reserves estimate 300 million barrels oil 200 bcf gas 10 Estimated field size 40 to 75 Sq. km 11 GOR 300m 3 /m 3 12 Water Production 15% water cut 13 Water Properties CL 170,000 mg/l 14 FWHP 750 psi SWHP 1900 psi 15 System Design Life 20/25 yr.

9 Conceptual Engineering Study Final Report Page 6 of MetaOcean Data Metaocean data for this study has been gathered and compiled from the following sources: Geological Survey of Canada (Seabed Conditions) Environment Canada (Sea Ice Conditions, Wind, Waves) Fisheries and Oceans Canada (Currents, Temperatures) 5.1 Wind Wind is a significant factor in the planning of any offshore development, in particular for floating production platforms. Table 1.0 is a summary of annual wind statistics for the Port au Port Region as recorded by Environment Canada. Month Mean Speed (Knots) Table 1.0 PORT AU PORT REGION NEWFOUNDLAND & LABRADOR ANNUAL WIND STATISTICS GULF PORT AU PORT Max Speed (Knots) Direction % of the Time W SW N NW NE E SE S Jan Feb Mar Apr May June July Aug Sept Oct Nov Dec

10 Conceptual Engineering Study Final Report Page 7 of 35 The predominant wind direction for the study area is West to Southwest at a mean speed of 10 to 18 knots and maximum of 51 knots. Generally, West to Southwest winds prevail 25 to 50% of the time. 5.2 Waves While offshore Port au Port can be deemed a hostile environment, the weather is not as harsh as you would find on the Grand Banks. Table 2.0 is a summary of wave data. The mean wave height is 0.5 to 2.2 meters, maximum wave height is 10.5 meters. Table 2.0 PORT AU PORT REGION NEWFOUNDLAND & LABRADOR ANNUAL WAVE STATISTICS GULF PORT AU PORT Month Mean (m) Max (m) January February March April May June July August September October November December Temperatures Temperatures in this region can vary from -15 C in winter to 28 C during summer. Seawater temperatures are typically -1 C during winter to +9 C during summer. 5.4 Currents Current data for the area is not abundant. Information from the Government of Canada, Department of Fisheries and Oceans database, indicates currents in this area to be relatively low, in the 0.5 to 1.0 knot range, predominantly from the North.

11 Conceptual Engineering Study Final Report Page 8 of Seafloor Conditions Like current data, seafloor data for the region is not abundant. The Geological Survey of Canada classifies the seafloor conditions as comprised of reworked sand and gravel of glacial origin. Any development planned for this area will require geotechnical sampling. 5.6 Ice Data While ice is a significant factor for any offshore Newfoundland development, the West coast of Newfoundland is generally iceberg free. The predominant ice feature in the region is winter pack ice. In January the Northern ice pack migrates down the Strait of Belle Isle. By February, it extends into the Gulf of St. Lawrence. However, the Port au Port Region remains ice free. It is not until March that the Port au Port area will see the ice pack. By April the area is again ice free. From a development point of view, the ice challenge is not as severe as previously thought. Essentially, the area planned for development is ice free 11 months per year and it is possible, some years, the area will be ice free. With respect to ice thickness, C- CORE, renowned St. John s Ice Engineering Consultants, estimate ice thickness ranging from 0.5 to 1.0m. Environment Canada Ice data for West Coast Newfoundland over a thirty year period ( ) are summarized in following figures:

12 Conceptual Engineering Study Final Report Page 9 of 35 Figure 2 January Pack Ice Figure 3 February Pack Ice

13 Conceptual Engineering Study Final Report Page 10 of 35 Figure 4 March Pack Ice Figure 5 April Pack Ice

14 Conceptual Engineering Study Final Report Page 11 of 35 Figure 6 May Pack Ice

15 Conceptual Engineering Study Final Report Page 12 of Facilities Description/Requirements 6.1 General This section provides a general overview of the topsides process and utility systems required in accordance with the Design Basis as set down in Section 4.0. To stay within the budget of this study, specific topsides layouts for various options i.e. FPSO, Jack-Up or Bottom Founded Caisson have not been generated. However, typical topsides layouts for an FPSO are enclosed in Appendix 1. The main purpose of the topsides facilities is to safely process the crude oil, to produce stabilized and dehydrated oil for storage and transport. A three stage separation process is used to separate the crude oil from its associated gas and water. The stable crude oil is stored, depending on the concept, on board the platform or remote for offloading to shuttle tankers. The associated gas is treated for use as fuel gas and lift gas. Any remaining gas can be disposed of by re-injection into the field. Produced water that has been separated from the crude oil will be re-injected unless reservoir planning dictates otherwise. 6.2 Oil Processing System Introduction The basic purpose of the oil processing system is to stabilize and prepare the crude oil for tanker transport by removing impurities and reducing the vapor pressure. Produced water, separated in the system is for now assumed to be re-injected. However, technical, cost or reservoir consideration during the detailed engineering phase may for example, dictate treating the water for overboard disposal Liquid and Gas Separation The separation train will comprise three stabilization stages, high pressure (HP), medium pressure (MP) and low pressure (LP) separation followed by crude oil dehydration. The live crude when it arrives on the platform is directed to a HP production manifold and onto a two phase HP separator. Liquids from the HP separator are typically routed to the MP separator via intermediate heating. Gas from the HP separator is routed to a LP Gas Compressor. Crude from the HP separator is depressurized, heated and routed to a three phase MP separator. Here, produced water and gas is separated from the crude.

16 Conceptual Engineering Study Final Report Page 13 of 35 During the final stage of LP separation, crude oil stability (vapor pressure) is achieved by removing light volatile components. Produced water from the proposed field is expected to contain chlorides in the range of 170,000 mg/l, therefore highly corrosive. This factor will have to be considered during material selection for tubing strings and down hole equipment versus down hole chemical injection of corrosion inhibitors. Secondly, it is assumed and recommended that produced water be re-injected, if reservoir engineering permits rather then treating and disposing overboard which can be very costly Gas Processing System A gas processing system is required to upgrade produced gas to conditions where it can be used for gas lift, fuel gas and re-injection. Typically, a gas processing system consists of: Flash Gas Compression LP Gas Compression Gas Dehydration Lift and Injection Gas Compression The Flash Gas Compression system enables pressurization of the low pressure and intermediate pressure gases from the LP and MP separators, respectively, to the inlet pressure of the Gas Re-injection Compression System. The LP Gas Compression System compresses the HP Separator and flash gas from the Flash Gas Compressor to a pressure level where it can be used as HP fuel gas, with further compression for gas lift/re-injection. A gas dehydration system will be required to prevent hydrate formation in the gas lift and gas re-injection lines. In addition, a gas lift/gas re-injection system is required to pressurize the dry gas from the gas dehydration pressure to the pressure required for gas lift and re-injection into the well. 6.3 Water Injection System It is anticipated that the topsides water injection system will be required to handle approximately 30,000 to 50,000 barrels per day of produced water with allowance for future increases. The purpose of the water injection system is to treat and condition produced water and possibly to condition seawater for injection into the reservoir for pressure maintenance.

17 Conceptual Engineering Study Final Report Page 14 of Chemical Injection Systems Due to the anticipated corrosive nature of formation water and the potential for paraffin, downhole chemical injection will be required. Secondly, if it is deemed more feasible, to produce the field on a seasonal basis, flow assurance issues will require that chemical injection and fluid inhibition be carefully considered. 6.5 Utilities & Other Systems Other systems which will be part of the overall topsides requirements include, but due to the nature of this study scope, will not be described in detail: Flare System Fuel Gas System Heating System (Crude Oil Conditioning) Cooling System Seawater System (Injection & Cooling) Nitrogen System (Blanket & Purge Gas) Diesel System (Back-up Power Generation) Freshwater System Firewater System Aviation Fuel System

18 Conceptual Engineering Study Final Report Page 15 of Concept Options Initially, the following concepts were identified as potential development options, these included: Gravity Base Structure (GBS) Subsea Tie-back to Onshore Processing Facility FPSO Jack-Up Bottom Founded Caisson Following a discussion of the above, Ptarmigan and Pan Maritime agreed to eliminate the GBS and Subsea Tie-back options from the scope of this study. This is not to say that these are not options for development. In larger case reserves, as estimated by Ptarmigan they most certainly would be. For conservatism, it was decided to investigate lower cost options, with lease scenarios, under a smaller reserve case to test economic viability. The main reason for eliminating the GBS is that at 150,000 to 300,000 barrels of oil recoverable, the project would be challenged to support the cost of a GBS. Similarly, the Subsea Tie-back to Onshore Facilities was eliminated but for different reasons. From a flow assurance point of view, the wells may require frequent intervention due to high wax content and with anticipated low flowing wellhead pressures, boosting will be required to deliver the fluids to an onshore facility. Once processed onshore, there is no market or transportation infrastructure to ship the product to market. A pre-requisite for this study was that only proven technology in similar environments would be considered with the smaller reserves case. From this starting point, the FPSO and Jack-Up concepts have been proven in the Atlantic Canadian offshore, namely the Terra Nova FPSO, White Rose FPSO (under construction) and the COPAN Jack-Up Production Platform. With respect to a Bottom Founded Caisson, the Gulf Molikpaq, previously built for the Canadian Beaufort Sea as a mobile drilling unit is now part of the Sakhalin Island Offshore Development Project, a similar but more hostile environment. 7.1 FPSO Description and Concept The FPSO is a proven concept for harsh environments and Newfoundland in particular. One FPSO is currently in operation on the Grand Banks for Petro Canada (Figure 6) and a second FPSO is in the final construction stage at Marystown, Newfoundland for Husky Energy.

19 Conceptual Engineering Study Final Report Page 16 of 35 Figure 7 - Terra Nova FPSO Some of the advantages of an FPSO are, the topsides process facilities and storage are located on the same platform. Secondly, being a mobile platform, the facility can be moved if required during severe ice conditions and re-deployed at a future date. The Grand Banks operating environment is more severe than the offshore Port au Port region of Western Newfoundland. The Grand Banks is more exposed to the open North Atlantic, therefore, seastates, wind and ice conditions are more severe. In addition, there is the presence of icebergs. The Grand Banks does have one advantage over the offshore Port au Port location and that is water depth. The Grand Banks with typically m. water depths is more favourable for internal turret FPSO mooring systems. At 40m water depth, neither the Terra Nova nor White Rose FPSO with internal turret arrangement will work. The vessel draft combined with the bending radius requirements for flexible risers would rule out this type of FPSO mooring configuration for the West Coast, 40 meter water depths. The FPSO is however, still an excellent concept for West Coast Newfoundland but will require an external, bow mounted turret, mooring or yoke arrangement. Initially, a bow mounted turret with spread mooring arrangement (Figure 8) was considered but upon evaluation of metaocean data, in particular winds, the spread moored FPSO concept was ruled out due to the variable direction of winds in the study area.

20 Conceptual Engineering Study Final Report Page 17 of 35 Figure 8 Spread Moored FPSO Mooring/Export Systems While it is quite possible that we can achieve year-round production, we must plan for the possibility of a disconnect. In such an event, the FPSO sails safely away but the loading and mooring system will be left behind. In our review of suitable FPSO mooring systems, we evaluated the CALM BUOY SALM BUOY SOFT YOKE TOWER CALM Buoy The CALM Buoy (Catenary Anchor Leg Mooring System, Figure 9) is a proven loading/offloading mooring concept. A CALM Buoy was used to moor and load the FSO Nordic Apollo supporting the Panuke Cohasset Project for Pan Canadian in Nova Scotia. This field while on production, produced 40,000 bopd. The CALM buoy is typically used in more benign environments and compared with other mooring/loading systems is relatively inexpensive. There are several manufacturers of the CALM buoy, including SBM IMODCO and Bluewater Offshore Production Systems. A new CALM buoy is typically in the US $5 million range but frequently used CALM buoys can be found for US $ million. It should be noted however, that the CALM buoy does have seastate limitations, typically 3.5 to 4.0 meters significant wave height. Secondly, in the event of a disconnect, the CALM buoy could become sacrificial.

21 Conceptual Engineering Study Final Report Page 18 of 35 Figure 9 CALM Buoy / FSO SALM Buoy The SALM buoy (Single Anchor Leg Mooring, Figure 10 and Figure 11) is a proven concept for hostile environments. At Sakhalin Island, a SALM Buoy/FSO combination is being used to support production from the Bottom Founded Caisson platform, Molikpaq. The Sakhalin environment is much more severe than West Coast Newfoundland. At Sakhalin, during the Winter months, the SALM buoy is ballasted and layed down on the seafloor, while the FSO sails away. Once the pack ice recedes, the FSO returns, the SALM Buoy is retrieved and hooked-up. Figure 10 SALM Buoy / FSO

22 Conceptual Engineering Study Final Report Page 19 of 35 Figure 11 SALM Buoy In our evaluation of ice data for the region, two facts are noteworthy, a) the ice pack is generally not more than 1.0m in thickness, typically 0.5m (Source: C-CORE) and b) the pack ice is present for only 1 month per year. The SALM has an advantage over the CALM Buoy. Should the FPSO have to disconnect and leave the site, the SALM can be ballasted and laid on the seafloor where it is protected from pack ice. Once the ice threat disappears, the SALM can be de-ballasted, refloated and reconnected to the FPSO. While it is possible that the SALM could be designed to withstand a typical west coast ice pack, this is outside the present study scope and is speculation at this time. Therefore, at this time, we make the assumption that a SALM system would result in 2 months downtime per year. Typical cost for a SALM Buoy would be in the US $14 15 million range Soft Yoke Tower The Soft Yoke Tower mooring system (Figure 12) is similarly a proven concept and there are several companies, including SBM and Bluewater capable of engineering and constructing such a system. The tubular Soft Yoke Tower is pile driven to the seafloor, to resist environmental forces and to provide a solid base to which one can moor and load an FPSO or FSO.

23 Conceptual Engineering Study Final Report Page 20 of 35 Soft Yoke Towers are currently being used on the following projects: Selat Lalang, Indonesia Adanga/Akam/Ebughu, Nigeria Bozhong, China Bohai, China Suizhong, China Shell EA, Nigeria Figure 12 Soft Yoke In consultation with SBM IMODCO, suppliers of the above noted Soft Yoke Towers, we are confident that a similar Soft Yoke Tower with an ice deflection shield can be designed to withstand the ice pack and metaocean conditions of West Coast Newfoundland. The Soft Yoke Tower mooring system offers many technical advantages: a) Year-round mooring/loading operation b) Can be designed to resist ice pack c) Permit use of steel risers versus flexible risers from seafloor to swivel loading system Typical cost for a Soft Yoke Tower mooring system will be in the US $25 30 million range.

24 Conceptual Engineering Study Final Report Page 21 of FPSO New Build Versus Lease An FPSO can be deployed in two ways: Operator owned and operated (or managed under contract) Leased (Bareboat or with Management contract) There are dozens of FPSO s in service around the world. Therefore, Ptarmigan, depending on timing can elect for a new-build, used vessel or lease a vessel. A new-build while providing the advantages of tailoring the vessel and systems to fit the field will be a costly scenario. Typical new build costs, for a 160,000 bopd FPSO with 900,000 barrels of storage can run up to US $450 million. Depending on timing, Ptarmigan may find a vessel of opportunity i.e. a used FPSO which could be modified to suit the project. This will depend largely on market conditions at the time and one s knowledge of the FPSO market. However, the FPSO lease option is one which we would recommend. Under this scenario, the owner can establish fixed capex/opex costs related to the operation of the FPSO and the contractor can bring the FPSO operations experience that Ptarmigan may not have. FPSO lease costs can be quite variable. There are several FPSO contractors who can lease and also operate an FPSO, including: SBM Bluewater Modec Vanguard Floating Production SBM, Bluewater and Modec are the world s largest and leading suppliers of FPSO s for purchase or lease. Consequently, they serve the higher end market and will be the most expensive. A typical bareboat lease cost for a 160,000 bopd FPSO with 900,000 barrels of storage will be in US $175,000/day range. Operating (contractor) costs will be in the US $25,000 $30,000/day range. Depending on field size, project economics, one should not rule out smaller FPSO contractors such as Vanguard Floating Production. Vanguard specializes in smaller projects and typically deploy, used tanker conversions. Vanguard could probably offer an FPSO solution in the US $100,000 $125,000/day range or less depending on the unit.

25 Conceptual Engineering Study Final Report Page 22 of Typical FPSO Operating Scenarios In summary, these are the typical FPSO operating scenarios envisioned for offshore Port au Port, West Coast Newfoundland: a) FPSO with CALM Buoy b) FPSO with SALM Buoy c) FPSO with Soft Yoke FPSO with CALM Buoy The FPSO with a CALM Buoy mooring system will be the least expensive FPSO solution but will have operating and other limitations. The CALM Buoy is firstly, seastate limited, typically you cannot discharge cargo in seastates greater than meters. This means, based on the environmental data for the area, you may experience downtime, any month of the year. Secondly, it would not be feasible to design the CALM Buoy mooring system to resist pack ice. Therefore, in the event of a disconnect, the CALM Buoy mooring system may be in jeopardy. Having stated the above, in spite of limitations, the FPSO CALM Buoy configuration should not be ruled out and should be the subject of further study during a Front End Engineering phase. The upside of a CALM mooring system is that there are hundreds in service around the world and used CALM Buoys are cheap and readily available. Further ice studies may show that with ice management/ice breaking, one may be able to remain on station with a CALM Buoy. FPSO with SALM Buoy The SALM Buoy offers operational advantages over the CALM Buoy. As a proven mooring/loading system in hostile, ice environments, the FPSO/SALM Buoy combination should permit the FPSO to operate at least 11 months per year, possibly 12 depending on pack ice conditions. As noted previously, at Sakhalin where the ice conditions are more severe, the SALM Buoy is laid on the seafloor during the Winter season. This feature is a plus. If it is deemed not feasible for technical or economic reasons to design a SALM capable of permitting the FPSO to operate year-round, offshore Port au Port then it is possible to ballast down the SALM, lay it on the seafloor, thereby protecting the mooring system for future re-connect. FPSO with Soft Yoke Tower A Soft Yoke Tower Mooring System, specifically designed to resist the ice and metaocean forces will permit year-round mooring/loading of an FPSO or FSO. This feature offers a significant advantage over the CALM or SALM Buoy. As the Soft Yoke Tower is a rigid structure, pile driven into the seafloor, we believe, with an ice shield

26 Conceptual Engineering Study Final Report Page 23 of 35 around the structure, it can provide a year-round mooring/export system for an FPSO or FSO. Year-round operations versus seasonal is preferred. From a seasonal perspective, even if the downtime is 1 or 2 months, there are many logistics and costs issues to deal with, such as: Lost revenue due to lost production Lost revenue during demob and remob. Crewing considerations. Flow assurance issues when wells have been shut-in for 2 months. Effects of lost production and interruption of supply to your customers Subsea Wells If an FPSO is chosen as the production concept, subsea completed wells will be required. With twenty (20) producers and eight (8) injectors planned, manifolding on the seafloor will be the preferred option, so as to limit the number of lines coming into the FPSO. Two lines are suggested for producers as there should be provision for pigging, and one each for gas injection and water injection Drilling As there is no provision for drilling on a typical FPSO, a mobile drilling unit will be required to drill and complete the subsea wells Typical Operating Cost Lease FPSO Assuming that both the FPSO and Bottom Founded Caisson are technically acceptable, the selection of an optimum solution depends also on economics, an option which will provide the greatest return with the least amount of risk. While a case can probably be made for using less expensive equipment and accepting seasonal production which would be the case for say an FPSO hull which is not ice strengthened, moored via a CALM or SALM Buoy, there is a greater element of risk presented to the project. Any time you connect or disconnect an FPSO, CALM or SALM Buoy, you introduce risk into the equation. Risk can never be fully eliminated but can be managed by sound engineering and operating practices. An FPSO moored via a Soft Yoke can be engineered for year-round operation. In this case, the risk is mitigated by sound engineering. However, under emergency conditions the FPSO can be released by a quick connect/disconnect (QC/DC) feature. For the purpose of this study, we have assumed year-round operation, based on a leased FPSO.

27 Conceptual Engineering Study Final Report Page 24 of 35 Table 3.0 is a summary of typical operating costs for a leased FPSO. Table Typical Operating Costs Leased FPSO (For 28 Well Scenario) Item Description Cost per Day (USD) 1 FPSO (Bareboat) 175, ,000 bopd, 900,000 bbl storage 2 FPSO (Opex) 30,000 3 Shorebase Support 30 persons, $2,250,000 office, $300,000 Warehousing, forklifts, craneage, $750,000 Marine Base, third party, $2,000,000 Overheads, 35% (personnel, travel, vehicles, etc), 1,600,000 Misc. (insurance, etc), $2,000,000 Total, $7,500, = 20,550/day 20,550 4 Logistics Support Helicopter, $4,000, = $10,100/day Supply Boats, 2 x $40,000 = $80,000/day (with lubes & fuel) Ice Management, 1 boat, 3 mo., $45,000 x 90 days 365 = $11,100 Weather forecasting, ice watch, $250, = 700 Total = $101,800 5 Drilling, 28 $25,000,000 ea. + 20% contingency = $840,000,000, amort. 10 yr., 10% = $11,100,000/mo x = $365,000/day 6 Completions 28 wellheads, $125,000 x 28 = $3,500, SS Trees, 4 Manifolds, jumpers, hoses, flowlines, $30,000,000 Flexible risers/umbilicals/offloading hoses, $30,000,000 Running tools, spares, $5,000,000 Total, $68,500,000, 10 yr., 10% = $905,100/mo x = $29,750/day 7 Subsea Installation 4 Manifolds, umbilicals, risers, flowlines, jumpers, 45 days Pile drive & install Soft Yoke Mooring Sys, 21 days 101, ,000 29,750 9,050

28 Conceptual Engineering Study Final Report Page 25 of 35 1 Offshore installation/contruction vessel, 1 workboat Mob/demob, $1,000,000 Dayrate, $300,000, both vessels $300,000 x 66 = 19,800,000 + $1,000,000 = $20,800,000 $20,800,000 amort. 10 yr., 10% = $274,900/mo x = 9,050/day 8. Soft Yoke Mooring System, 30,000,000, 10 yr., 10% = $396,500/mo x = $13,000/day 9 Engineering & Project management, 50,000,000, 10 yr., 10% = $660,700 x = $21, Maintenance & Repair 7.5% of Capital Cost of Assets FPSO, $450 million; Soft Yoke $30 million, Subsea $69 million 549,000,000 x 7.5% = 41,175, = $112,800/day 13,000 21, ,800 Total $878, Project Schedule If an FPSO solution is chosen for this project, the overall schedule from project sanction to first oil can be affected by many issues such as regulatory, engineering and construction time. Putting the regulatory time frame aside, the FPSO schedule will depend largely on whether a new build or used FPSO is deployed. Typically, a new build FPSO will add 12 to 18 months to a project schedule assuming you can secure a construction slot in a shipyard without great difficulty.

29 Conceptual Engineering Study Final Report Page 26 of 35 The following schedule (Figure 13) is typical for a FPSO conversion. Figure 13 - FPSO Conversion Project Sanction FEED Engineering Detailed Engineering Procure Long Lead Items FPSO Conversion Commissioning (FPSO) Procure Mooring / Export Sys. Install Mooring Sys. Drill Wells & Complete First Oil Months Jack-Up A Jack-Up drilling rig modified to serve as a production facility is a proven East Coast Canada offshore production concept. The Lasmo Panuke Cohasset project (Figure 14), offshore Nova Scotia over a 6 year period, produced 49 million barrels of oil at an average rate of 40,000 barrels per day. The overall production concept consisted of the following elements: Modified Rowan Gorilla III Jack-Up drill rig with production facilities. CALM Buoy with moored FSO tanker. First oil was achieved June 3, 1992, 18 months following project sanction. However, for a 300 million barrel field, with 20 producers and 8 injectors, a converted drilling Jack-Up is not deemed feasible solution. Firstly, at a production rate of 160,000 bopd, the Topsides process facilities with water and gas re-injection is estimated to weigh 12,500 tonnes. Secondly, the variable deckload capacity of a typical drilling Jack-Up would be challenged to accommodate such a large process facility while at the same time maintaining a drilling package. Last but not least, 28 wells would prove to be a challenge for a Jack-Up while trying to maintain the disconnect option.

30 Conceptual Engineering Study Final Report Page 27 of 35 Figure 14 Jack-Up Drilling & Production Platform 7.3 Bottom Founded Caisson General A third option for the shallow water Port au Port region is a Bottom Founded Caisson which is essentially a Gravity Base System. When one speaks of a Gravity Base System or GBS it is generally implied that the structure is constructed of concrete, for example the Hibernia GBS. However, over the past decade, engineering and construction advances have produced a new generation of GBS structures, less bulky and more cost effective than the early North Sea GBS and Hibernia GBS structures. An example of this new generation of GBS structures is the Aker Kvaerner PA-B Gravity Base Structure for the Sakhalin Phase II development in 30 meters of water, but the cost is still relatively high, in the US $900 million to $950 million range. Therefore, probably not feasible for this project. The Bottom Founded Caisson in its most simplistic form can also take the form of a barge. In Canada, the concept was first pioneered in the early 80 s by Gulf Canada and Dome Petroleum in the shallow waters (20-25m) of the Canadian Beaufort Sea. There, Gulf Canada deployed a mobile arctic caisson, octagonal in shape, namely the Molikpaq. Dome on the other hand deployed a bottom strengthened barge, the SSDC (Single Steel Drilling Caisson), which when ballasted sat on a submerged purpose built sand/gravel berm.

31 Conceptual Engineering Study Final Report Page 28 of 35 A Bottom Founded Caisson generally constructed of steel can take on virtually any shape. The guiding principle is that its ultimate, ballasted in-place mass is sufficient to withstand ice and metaocean forces. In examining a Bottom Founded Caisson as an option, we studied the previously Gulf owned and built Molikpaq, now operating in the Russian archipelago of Sakhalin under new owners. The Molikpaq (Figure 15 & 16) is of steel construction and purpose built to withstand an ice-pack, hostile arctic environment. As a bottom founded structure, weight restrictions are typically not a problem and with ample footprint or deck space, drilling and production facilities can be accommodated. While there is no reason why oil storage capacity cannot be designed into the structure, the Molikpaq does not have internal storage, as it was initially designed as a drilling unit only, and therefore, oil storage was not required. As it is outside the scope of this study, we will assume that sand ballast is required to keep the Bottom Founded Caisson stable under ice-pack forces and that for now no internal oil storage is available.

32 Conceptual Engineering Study Final Report Page 29 of 35 Figure 15 Bottom Founded Caisson Molikpaq Figure 16 Cross section of Molikpaq

33 Conceptual Engineering Study Final Report Page 30 of Production, Storage and Offloading Whether oil storage can or cannot be accommodated in a Molikpaq type Bottom Founded Caisson, a remote external export/loading system is still required. Such a loading system can be the SALM or Soft Yoke Tower. If internal oil storage is available in a Bottom Founded Caisson, the Export/Loading Buoy will serve as mooring/loading terminal for a shuttle tanker. If no storage is available within the Caisson, the Buoy will serve as a mooring/loading system for a permanently moored FSO with loading of a shuttle tanker via the stern of the FSO. Either the SALM Buoy or Soft Yoke Mooring/Export system discussed previously are options for the Bottom Founded Caisson concept. The SALM is more limiting but less costly. The Soft Yoke, while more costly, will ensure the yearround capability of loading/offloading Drilling An advantageous feature of a purpose built Bottom Founded Caisson is the ability to incorporate drilling facilities. By locating drilling and production on a common platform, there are obvious cost savings associated with crewing, logistics support and the sharing of common facilities such as power generation, utilities and the like. In addition, a purpose built Caisson with drilling facilities will provide an opportunity to design in sufficient slots plus spares for the drilling of the necessary development and injection wells. This is a significant advantage over the Jack-Up where wells slots can be limited Seasonal Vs. Year-Round Production A Bottom Founded Caisson is capable of year-round operations in an ice infested hostile environment. These systems are now well proven in the Canadian Arctic and offshore Sakhalin. However, logistics and loading/export systems such as the Soft Yoke Tower will require careful planning and engineering to ensure that they are not the weak links in a year-round system Typical Operating Cost New Build Bottom Founded Caisson If a Bottom Founded Caisson was chosen as the preferred production option, it is unlikely that a used Caisson such as the Molikpaq would be available. For shallow to middepth water production worldwide, the most popular concept is a Jack-Up or some form of steel jacket. Bottom Founded Caissons have been popular mainly in hostile Arctic environments and as such not many units have been built. A Molikpaq type Caisson could be built at Bull Arm Newfoundland where the Hibernia GBS was built. Alternatively, it could be built in Asia as was the case for Molikpaq.

34 Conceptual Engineering Study Final Report Page 31 of 35 Table 5.0 Typical Operating Cost New Build Bottom Founded Caisson 1. Molikpaq type Caisson New build cost USD $675 million, incl. Installation, transportation from Bull Arm, Commissioning. Amort. 10 yr., 10% = $298,000/day 2. OPEX $30, Shorebase Support $20, persons, $2,250,000 office, $300,000 Warehousing, forklifts, craneage, $750,000 Marine Base, third party, $2,000,000 Overheads, 35% (personnel, travel, vehicles, etc), 1,600,000 Misc. (insurance, etc), $2,000,000 Total, $7,500, = 20,550/day 4. Logistics Support $101,800 Helicopter, $4,000, = $10,100/day Supply Boats, 2 x $40,000 = $80,000/day (with lubes & fuel) Ice Management, 1 boat, 3 mo., $45,000 x 90 days 365 = $11,100 Weather forecasting, ice watch, $250, = 700 Total = $101, Drilling, million ea. + 20% contingency, $840 million, 10yr., 10% = $365,000/day 6. Completions 28 wellheads, $125,000 ea. x 28 = $3,500,000 7 Trees (Land type) + access., $300,000 x 28 = $8,400,000 Total $11,900,000, 10 yr., 10% = $5,200/day 7. Soft Yoke Tower, $30 million $30 million, 10 yr., 10% = $13,000/day (USD) Cost Per Day $298,000 $365,000 $5,200 $13,000

35 Conceptual Engineering Study Final Report Page 32 of Subsea Flowlines (2) from Caisson to Soft Yoke Tower, Loading Hose FSO/Shuttle tanker & spare, $4.5 million, 10%, 10 yr. = $59,461/Mth. X = $1,950/day 9. Installation of Soft Yoke Tower, Flowlines MOB/Demob conversion vessel with pile driver, $1.0 million Install Soft Yoke Tower, 21 days Install flowlines tower, 5 days 1 construction vessel, 1 workboat Dayrate, $300,000 bath vessels $300,000 x 26 days = $7,800,000 $7,800,000, 10%, 10 yr. = $103,065/Mth. $103,065/Mth. X = $3,400/day 10. Engineering & Project Management $75 million, 10%, 10 yr. = $991,000/Mth. $991,000/Mth x = $32, Maintenance & Repair 7.5% of capital cost of assets $675 million + 12 million + 30 million million = million x = $54.1 million $54.1 million 365 = $148,000/day $1,950/day $3,400 $32,500 $148,000 Total $1,019,400

36 Conceptual Engineering Study Final Report Page 33 of Project Schedule If a Bottom Founded Caisson is chosen, the overall project schedule from engineering through to construction and commissioning will be 48 months. Figure 17 New Build Bottom Founded Caisson Project Sanction FEED Engineering (6 Mth) Detailed Engineering (18 Mth) Procure Long Lead Items (12 Mth) Construct & Outfit Caisson (24 Mth) Tow-out & Install (3 Mth) Procure Soft Yoke Tower (12 Mth) Install Tower & Flowlines Procure & Modify FSO Install FSO Drill Wells & Complete First Oil Months

37 Conceptual Engineering Study Final Report Page 34 of Conclusion During the course of this Study, we examined several potential options for offshore development and looked at current and past East Coast Canada Offshore projects such as Hibernia, Terra Nova, White Rose, Panuke Cohasset and international projects such as Sakhalin Island. Early in the Study, we eliminated further investigation of the GBS for cost reasons and the Subsea Tie-back for technical challenges in flow assurance. In keeping with the guideline of examining only proven technology, we investigated the FPSO, Jack-Up and Bottom Founded Caisson. The Jack-Up was subsequently deemed not feasible for a 300 million barrel recoverable reserves case producing at 160,000 bopd. A typical converted Jack-Up could not accommodate the estimated 12,500 tonnes of Topsides required to support 160,000 bopd and the platform would be challenged to accommodate 28 wells. It is the Conclusion of this Study that the FPSO or Bottom Founded Caisson represents the best alternatives for Ptarmigan s Offshore West Coast acreage. There are pros and cons for each option with the merits of each clearly identified in the Study. The FPSO represents a smaller investment, shorter overall project schedule but slightly more risk in terms of achieving year-round production. The Bottom Founded Caisson on the other hand presents less production risk, but is more costly and has a much longer project implementation schedule. In closing, we feel both options are viable alternatives and in making a final selection, you would need to conduct an in-depth risk analysis and more detailed costing. You may well find that the FPSO s year-round ability to maintain full production is a manageable risk in which case its cheaper cost and reduced project schedule will give it an edge over the Bottom Founded Caisson.

38 Conceptual Engineering Study Final Report Page 35 of Appendix

Minimal Structures for Marginal Nova Scotia Developments

Minimal Structures for Marginal Nova Scotia Developments Minimal Structures for Marginal Nova Scotia Developments May 12, 2009 Cameron Dunn Martec is a member of the Lloyd s Register Group 1 2 Minimal Structures Project NSDOE working to make the Nova Scotia

More information

RIGID RISERS FOR TANKER FPSOs

RIGID RISERS FOR TANKER FPSOs RIGID RISERS FOR TANKER FPSOs Stephen A. Hatton 2H Offshore Engineering Ltd. SUMMARY Recent development work on the subject of dynamic rigid (steel pipe) risers demonstrates that their scope of application

More information

From the Wellhead to the Tanker Offshore Production Systems. 28/03/2014 Instituto Superior Técnico

From the Wellhead to the Tanker Offshore Production Systems. 28/03/2014 Instituto Superior Técnico From the Wellhead to the Tanker Offshore Production Systems Index Offshore Installations Subsea Systems Field overview Christmas Trees Manifolds Templates Mid-Water Arches Topsides FPSOs The Oil Production

More information

LNG TANDEM OFFLOADING A KEY ENABLING TECHNOLOGY TO MAKE LNG PRODUCTION OFFSHORE HAPPEN

LNG TANDEM OFFLOADING A KEY ENABLING TECHNOLOGY TO MAKE LNG PRODUCTION OFFSHORE HAPPEN LNG TANDEM OFFLOADING A KEY ENABLING TECHNOLOGY TO MAKE LNG PRODUCTION OFFSHORE HAPPEN Fabrice Dumortier 1, Jean-Pierre Queau 1, Jean-Robert Fournier 2 1. SBM Offshore 2. SBM Offshore Keywords: 1. LNG;

More information

Learn more at

Learn more at Bottom Weighted Riser A Novel Design for Re-location and Disconnection Frank Lim and John McGrail 2H Offshore Engineering Ltd. Woking, Surrey, United Kingdom ABSTRACT Flexible pipe risers have limitations

More information

RPSEA UDW Forum June 22 & 23, Secure Energy for America

RPSEA UDW Forum June 22 & 23, Secure Energy for America RPSEA UDW Forum June 22 & 23, 2010 Secure Energy for America PROJECT TEAM RPSEA Operator Advisory Committee Anadarko Chevron Shell ConocoPhillips Subcontractors IntecSea NOV CTES General Marine Contractors

More information

Low Cost Flexible Production System for Remote Ultra-Deepwater Gulf of Mexico Field Development

Low Cost Flexible Production System for Remote Ultra-Deepwater Gulf of Mexico Field Development Low Cost Flexible Production System for Remote Ultra-Deepwater Gulf of Mexico Field Development 10121-4404-03 Jelena Vidic-Perunovic, Doris, Inc. Lars Ødeskaug, Sevan Marine ASA RPSEA Ultra-Deepwater Technology

More information

Caltec. The world leader in Surface Jet Pump (SJP) and compact separation systems for upstream oil and gas production enhancement

Caltec.   The world leader in Surface Jet Pump (SJP) and compact separation systems for upstream oil and gas production enhancement Caltec brings simple passive technology that enables oil and gas operators to harness the kinetic energy of the production process to enhance their production, extending economic field life and reducing

More information

Development of Self-Installing Deepwater Spar. Ashit Jadav February 2017

Development of Self-Installing Deepwater Spar. Ashit Jadav February 2017 Development of Self-Installing Deepwater Spar Ashit Jadav February 2017 Contents Introduction & Background ACE Spar breakdown Installation Sequence Main particulars, Hull design and Weight control Stability

More information

Deepwater Floating Production Systems An Overview

Deepwater Floating Production Systems An Overview Deepwater Floating Production Systems An Overview Introduction In addition to the mono hull, three floating structure designs Tension leg Platform (TLP), Semisubmersible (Semi), and Truss Spar have been

More information

Numerical modelling of disconnectable turret mooring systems

Numerical modelling of disconnectable turret mooring systems Numerical modelling of disconnectable turret mooring systems A. Duggal, S. Ryu & O. De Andrade Research & Development Department, SOFEC Inc., USA. Abstract Floating, Production, Storage, and Offloading

More information

Offshore Oil and Gas Platforms for Deep Waters

Offshore Oil and Gas Platforms for Deep Waters Offshore Oil and Gas Platforms for Deep Waters Atilla Incecik Department of Naval Architecture, Ocean and Marine Engineering University of Strathclyde, Glasgow, UK (atilla.incecik@strath.ac.uk) Summary

More information

FIXED VERSUS DISCONNECTABLE TURRET SYSTEM FOR F(P)SO S FOR GULF OF MEXICO

FIXED VERSUS DISCONNECTABLE TURRET SYSTEM FOR F(P)SO S FOR GULF OF MEXICO FIXED VERSUS DISCONNECTABLE TURRET SYSTEM FOR F(P)SO S FOR GULF OF MEXICO London T. England Jr. FMC SOFEC Floating Systems, USA ABSTRACT With the anticipated development of a large number of deepwater

More information

Fundamentals Of Petroleum Engineering PRODUCTION

Fundamentals Of Petroleum Engineering PRODUCTION Fundamentals Of Petroleum Engineering PRODUCTION Mohd Fauzi Hamid Wan Rosli Wan Sulaiman Department of Petroleum Engineering Faculty of Petroleum & Renewable Engineering Universiti Technologi Malaysia

More information

TARPON A Minimal Facilities Platform

TARPON A Minimal Facilities Platform TARPON A Minimal Facilities Platform Contents Introduction TARPON Description TARPON Features TARPON Benefits TARPON Proofs TARPON Typical Installation Options Design Codes & Certification Novel Application

More information

Re-usable Riser and Flowline System for Deep Water Application. C. DIEUMEGARD SUBSEA ASIA - 11 th June 2008

Re-usable Riser and Flowline System for Deep Water Application. C. DIEUMEGARD SUBSEA ASIA - 11 th June 2008 Re-usable Riser and Flowline System for Deep Water Application C. DIEUMEGARD SUBSEA ASIA - 11 th June 2008 Table of Contents Flexible Pipe Technology Deep Water Challenges for Riser, Flowline and Umbilical

More information

A NEW DEEPWATER TANKER LOADING SYSTEM FOR WEST AFRICA

A NEW DEEPWATER TANKER LOADING SYSTEM FOR WEST AFRICA A NEW DEEPWATER TANKER LOADING SYSTEM FOR WEST AFRICA Arun S. Duggal, FMC SOFEC Floating Systems, USA Charles O. Etheridge, FMC SOFEC Floating Systems, USA James Mattinson, FMC SOFEC Floating Systems,

More information

EXPRESSION OF INTEREST

EXPRESSION OF INTEREST EXPRESSION OF INTEREST Contractor: WorleyParsons Canada Services Ltd. Project: Hebron Topsides Project Package: SC-64 GBS Caisson Field Welding Services Category: XXXXX-XXXXX Closing Date: 19 June 2013

More information

Construction. MCP-01: Construction to Decommissioning

Construction. MCP-01: Construction to Decommissioning MCP-01: Construction to Decommissioning Construction MCP-01 sat in 94m of water 173km, or roughly 108 miles, off the coast of Aberdeen, in Block 14/9 of the North Sea. Although MCP is usually regarded

More information

Charlottetown Marine Terminal Pipeline Decommissioning Project Description

Charlottetown Marine Terminal Pipeline Decommissioning Project Description Charlottetown Marine Terminal Pipeline Decommissioning Project Description 69 Marr Road Unit B Rothesay NB, E2E 3J9 Tel (506) 848-1920 Fax (506) 848-1929 Charlottetown Marine Terminal Pipeline Decommissioning

More information

Risers for Deepwater FPSO s

Risers for Deepwater FPSO s Risers for Deepwater FPSO s John Bob-Manuel Senior Engineer 2H Offshore Engineering Ltd. March 2013 Agenda 2H overview Challenges of Deepwater Operations Freestanding Riser Overview Riser Configurations

More information

The Impact of Composites on Future Deepwater Riser Configurations

The Impact of Composites on Future Deepwater Riser Configurations The Impact of Composites on Future Deepwater Riser Configurations Thomas Brown 2H Offshore Engineering Ltd NH GRAND HOTEL KRASNAPOLSKY AMSTERDAM 3-5 APRIL 2017 Deepwater Riser Technology Today s deepwater

More information

Global SURF (Subsea Umbilicals, Risers and Flowlines) Market: 2018 World Market Review and Forecast to 2023

Global SURF (Subsea Umbilicals, Risers and Flowlines) Market: 2018 World Market Review and Forecast to 2023 Global SURF (Subsea Umbilicals, Risers and Flowlines) Market: 2018 World Market Review and Forecast to 2023 By Water Depth Shallow Water and Deep Water By Type- Umbilical, Riser and Flowlines By Umbilical

More information

APPENDIX D. Assessment of Ship Impact Frequencies

APPENDIX D. Assessment of Ship Impact Frequencies APPENDIX D Assessment of Ship Impact Frequencies WHITE ROSE DEVELOPMENT APPLICATION APPENDIX D ASSESSMENT OF SHIP IMPACT FREQUENCIES SUBMITTED BY: HUSKY OIL OPERATIONS LIMITED AS OPERATOR SUITE 801, SCOTIA

More information

The SDS Skip. Subsea Deployment Systems Ltd.

The SDS Skip. Subsea Deployment Systems Ltd. The SDS Skip SUBSEA SKIP An alternative to enhance the recovery of structures, spool pieces, mattresses etc. during decommissioning work Can be used to transport complex structures or spool pieces to field

More information

1.0 PURPOSE AND NEED

1.0 PURPOSE AND NEED 1.0 PURPOSE AND NEED 1.0 PURPOSE OF AND NEED FOR THE PROPOSED ACTION 1.1 INTRODUCTION The National Environmental Policy Act (NEPA) of 1969, as amended (42 United States Code Section 4321 et seq.); the

More information

FPSO MOORING CONFIGURATION BASED ON MALAYSIA S ENVIRONMENTAL CRITERIA

FPSO MOORING CONFIGURATION BASED ON MALAYSIA S ENVIRONMENTAL CRITERIA FPSO MOORING CONFIGURATION BASED ON MALAYSIA S ENVIRONMENTAL CRITERIA Mazlan Muslim and Md Salim Kamil Marine and Design Technology Section, University Kuala Lumpur MIMET, Lumut, Perak, Malaysia E-Mail

More information

GAS TANKER COMMITTEE #4

GAS TANKER COMMITTEE #4 GAS TANKER COMMITTEE #4 FSRU-Critical link in Global LNG Supply chain Singapore 12 th October 2017 Lian-Gee CHUA, DNV GL 12 October 2017 1 SAFER, SMARTER, GREENER ABOUT DNV GL - The leading classification

More information

PRO-ROD TM COILED ROD. Reduce Maintenance Increase Production Enhance Profit

PRO-ROD TM COILED ROD. Reduce Maintenance Increase Production Enhance Profit PRO-ROD TM COILED ROD Reduce Maintenance Increase Production Enhance Profit DOVER ARTIFICIAL LIFT Elevating the Potential of Artificial Lift Production. Dover Artificial Lift, part of Dover Energy, offers

More information

RAMSTM. 360 Riser and Anchor-Chain Integrity Monitoring for FPSOs

RAMSTM. 360 Riser and Anchor-Chain Integrity Monitoring for FPSOs RAMS 360 Riser and Anchor-Chain Integrity Monitoring for FPSOs Introduction to RAMS Tritech s RAMS is a 360 anchor-chain and riser integrity monitoring system for Floating Production Storage and Offloading

More information

GUIDELINES FOR SURVEY OF OIL FLOATING STORAGE VESSELS FIXED AT ANCHORAGE

GUIDELINES FOR SURVEY OF OIL FLOATING STORAGE VESSELS FIXED AT ANCHORAGE GUIDANCE NOTES GD03-2017 CHINA CLASSIFICATION SOCIETY GUIDELINES FOR SURVEY OF OIL FLOATING STORAGE VESSELS FIXED AT ANCHORAGE 2017 Effective from 1 March 2017 BEIJING Chapter 1 GENERAL 1.1 Application

More information

WIND TURBINE SHUTTLE HUISMAN PRODUCT BROCHURE

WIND TURBINE SHUTTLE HUISMAN PRODUCT BROCHURE WIND TURBINE SHUTTLE HUISMAN PRODUCT BROCHURE WIND TURBINE HUTTLE TABLE OF CONTENTS 01 DESCRIPTION 03 1.1 Vessel General 03 1. Purpose of the Vessel 0 1.3 High Workability 0 1. Installation Scenarios 05

More information

SHELL ALASKA. December Use this area for cover image (height 6.5cm, width 8cm) Shell Exploration & Production Co.

SHELL ALASKA. December Use this area for cover image (height 6.5cm, width 8cm) Shell Exploration & Production Co. SHELL ALASKA December 2014 Use this area for cover image (height 6.5cm, width 8cm) Shell Exploration & Production Co. 1 DEFINITIONS AND CAUTIONARY NOTE The companies in which Royal Dutch Shell plc directly

More information

Shell Beaufort and Chukchi Sea Program Update

Shell Beaufort and Chukchi Sea Program Update Shell Beaufort and Chukchi Sea Program Update Pete Slaiby Vice President, Shell Alaska January, 2011 1 Beaufort Sea Leaseholders 2 Chukchi Sea Leaseholders 3 Alaska OCS - Benefits To Alaska and the Nation

More information

Internal riser inspections on FPSO storage & production facilities

Internal riser inspections on FPSO storage & production facilities Internal riser inspections on FPSO storage & production facilities by Jurgen F P Elbertse A Hak Industrial Services bv, Rhenen, Netherlands Contents of this Paper: Introduction Preparations Testing Mobilization

More information

Protectingpipelinesfor

Protectingpipelinesfor 24 Protectingpipelinesfor Michael Paulin, Damien Humby and Joseph Cocker, INTECSEA Canada, and Glenn Lanan, INTECSEA Inc., describe the process of trenching for the protection of pipelines in ice environments.

More information

SUPPLY OPERATIONS IN ICE CONDITIONS

SUPPLY OPERATIONS IN ICE CONDITIONS OKHOTSK SEA & SEA ICE, MOMBETSU, JAPAN, 24-28.2.2002 SUPPLY OPERATIONS IN ICE CONDITIONS Kimmo Juurmaa, Göran Wilkman Kvaerner Masa-Yards Arctic Technology SUPPLY OPERATIONS IN ICE CONDITIONS Kimmo Juurmaa,

More information

Fully Submersible Heavy Lift Vessel

Fully Submersible Heavy Lift Vessel Fully Submersible Heavy Lift Vessel Arnbjorn Joensen Aberdeen Maritime Branch (28th January 2015) PRESENTATION Introduction to the Subsea Deployment Vessel Installation method Tank test video Potential

More information

INSTRUCTIONS FOR THE USE OF LONG LENGTH AND SPLICED HOSES

INSTRUCTIONS FOR THE USE OF LONG LENGTH AND SPLICED HOSES ContiTech Rubber Industrial Kft. Hose Technical Department HANDLING Page: 1/6 Date: 31.07.2008 Invalidate the document TKO AS1 rev.3 INSTRUCTIONS FOR THE USE OF LONG LENGTH AND SPLICED HOSES Prepared by:

More information

Field Development & Construction

Field Development & Construction Field Development & Construction Michael Cowie Technical Director Ecosse Subsea Systems Ltd Ambient Lifting: A Real Alternative to Heavy Lift Vessels 4 th February 2016, AECC, Michael Cowie Presentation

More information

An Ocean of Possibility

An Ocean of Possibility An Ocean of Possibility SPM Offloading Buoy CALM Buoy Orwell Offshore s Catenary Anchor Leg Mooring (CALM) Buoy offers a reliable state-of-the-art solution for loading and offloading crude oil, refined

More information

Fully Submersible Heavy Lift Vessel

Fully Submersible Heavy Lift Vessel Fully Submersible Heavy Lift Vessel Arnbjorn Joensen Oil and Gas Authority (OGA) (15th February 2016) CONTENT Leadon structures demobilisation Competitiveness (case studies) Decommissioning options Installation

More information

Challenges in Ship Design to Maintain Thrusters inside Ship

Challenges in Ship Design to Maintain Thrusters inside Ship DYNAMIC POSITIONING CONFERENCE October 9-10, 2012 Thrusters Challenges in Ship Design to Maintain Thrusters inside Ship Tom Nylund and Timo Rintala Beacon Finland 1 DP Conference - Challenges in Ship Design

More information

Permanent buoyancy systems. matrix composites & engineering

Permanent buoyancy systems. matrix composites & engineering Permanent buoyancy systems matrix composites & engineering Contents Permanent buoyancy systems 3 Materials qualification testing 4 Distributed buoyancy clamping system 5 Buoyancy building block system

More information

Memo. Shelley Cohen. From: Bill Dickson CC: Date: February 5, 2015 Re: Editorial Oil & Gas News

Memo. Shelley Cohen. From: Bill Dickson CC: Date: February 5, 2015 Re: Editorial Oil & Gas News Memo To: Shelley Cohen From: Bill Dickson CC: Date: February 5, 2015 Re: Editorial Oil & Gas News Tag Line: Bauer Compressors, Inc. Delivers a Custom Solution Copy: Bauer has manufactured and provided

More information

A Single-Point Mooring System for Direct Pumpout of Hopper Dredges

A Single-Point Mooring System for Direct Pumpout of Hopper Dredges ..-0. -..- DRP-3-08 November 1992 Dredging Technical Research Notes A Single-Point Mooring System for Direct Pumpout of Hopper Dredges Purpose This technical note describes a direct pumpout (DPO) system

More information

MATING OF THE MOLIKPAQ DRILLING RIG

MATING OF THE MOLIKPAQ DRILLING RIG ARGONAUTICS Marine Engineering Page 1 MATING OF THE MOLIKPAQ DRILLING RIG Frank van Hoorn, ARGONAUTICS Marine Engineering Sausalito, Ca, USA In-Tae Kim, Daewoo Heavy Industries Ltd. Okpo Yard, Korea Introduction

More information

The Benefits Of Composite Materials In Deepwater Riser Applications. 26 th March 2015 Hassan Saleh Senior Engineer 2H Offshore Engineering Ltd

The Benefits Of Composite Materials In Deepwater Riser Applications. 26 th March 2015 Hassan Saleh Senior Engineer 2H Offshore Engineering Ltd The Benefits Of Composite Materials In Deepwater Riser Applications 26 th March 2015 Hassan Saleh Senior Engineer 2H Offshore Engineering Ltd Composite Benefits and Challenges Composite Materials offer

More information

Rates and Charges Operative from 1st January 2019

Rates and Charges Operative from 1st January 2019 Rates and Charges Operative from 1 st January 2019 P a g e 1 Port of Cromarty Firth Rates and Charges Operative from 1 st January 2019 All enquiries regarding Rates and Charges to:- Port of Cromarty Firth

More information

PRESTIGE OIL RECOVERY FROM THE SUNKEN PART OF THE WRECK Massimo Fontolan, Sonsub Ltd., Robin Galletti, SATE srl. Introduction

PRESTIGE OIL RECOVERY FROM THE SUNKEN PART OF THE WRECK Massimo Fontolan, Sonsub Ltd., Robin Galletti, SATE srl. Introduction PRESTIGE OIL RECOVERY FROM THE SUNKEN PART OF THE WRECK Massimo Fontolan, Sonsub Ltd., Robin Galletti, SATE srl. Introduction This lecture deals with the equipment developed and the experience gained during

More information

The Time Has Come For Coiled Rod. Reprinted from Well Servicing magazine

The Time Has Come For Coiled Rod. Reprinted from Well Servicing magazine The Time Has Come For Coiled Rod Reprinted from Well Servicing magazine The development of flush-by well service units and stand-alone coiled rod injector head technology has helped grow the coiled rod

More information

Règlement pour la navigation pour la zone arctique. Alexey DUDAL Marine Division Bureau VERITAS

Règlement pour la navigation pour la zone arctique. Alexey DUDAL Marine Division Bureau VERITAS Règlement pour la navigation pour la zone arctique Alexey DUDAL Marine Division Bureau VERITAS 1 Contents 1. Introduction 2. BV Rules and Guidelines for Ice-Going Vessels 3. Direct Calculation Tool 4.

More information

Cook Inlet pipeline crossing is about making the best choices

Cook Inlet pipeline crossing is about making the best choices Cook Inlet pipeline crossing is about making the best choices By Larry Persily lpersily@kpb.us Aug. 26, 2015 (This update, provided by the Kenai Peninsula Borough mayor s office, is part of an ongoing

More information

FPSO Riser Solutions for Harsh environments

FPSO Riser Solutions for Harsh environments FPSO Riser Solutions for Harsh environments Hanh Ha and Hugh Howells AOG Perth, March 2015 Overview Design challenges Flexibles Configurations and response Mild Environment Riser Harsh Environment Riser

More information

Innovative and Robust Design. With Full Extension of Offshore Engineering and Design Experiences.

Innovative and Robust Design. With Full Extension of Offshore Engineering and Design Experiences. Innovative and Robust Design by VL Offshore With Full Extension of Offshore Engineering and Design Experiences www.vloffshore.com Y Wind Semi Designed by VL Offshore The Y Wind Semi platform (foundation)

More information

(12) Patent Application Publication (10) Pub. No.: US 2008/ A1

(12) Patent Application Publication (10) Pub. No.: US 2008/ A1 (19) United States US 2008.0096448A1 (12) Patent Application Publication (10) Pub. No.: US 2008/0096448 A1 LOkken et al. (43) Pub. Date: (54) COMBINED RISER, OFFLOADING AND MOORING SYSTEM (76) Inventors:

More information

Wind Energy 101 for Southeastern Policy Makers Overview of Wind Energy Development and Potential in the US

Wind Energy 101 for Southeastern Policy Makers Overview of Wind Energy Development and Potential in the US Wind Energy 101 for Southeastern Policy Makers Overview of Wind Energy Development and Potential in the US Jim Doane, Senior Engineer March 2012, Charlotte, North Carolina, USA Agenda Introduction to PMSS

More information

EM Global Initiatives in diving, Balder Life Extension Project & Decommissioning Opportunities

EM Global Initiatives in diving, Balder Life Extension Project & Decommissioning Opportunities March 3 rd, 2016 EM Global Initiatives in diving, Balder Life Extension Project & Decommissioning Opportunities This presentation includes forward-looking statements. Actual future conditions (including

More information

Learn more at

Learn more at IBP1833_06 COST EFFICIENT ARTIFICIAL BUOYANT SEABED DRILLING SOLUTION Dan Moutrey 1, Frank Lim 2 Copyright 2006, Instituto Brasileiro de Petróleo e Gás - IBP This Technical Paper was prepared for presentation

More information

Feasibility of Steel Lazy Wave Risers in the North Sea

Feasibility of Steel Lazy Wave Risers in the North Sea NH GRAND HOTEL KRASNAPOLSKY AMSTERDAM 3-5 APRIL 2017 Feasibility of Steel Lazy Wave Risers in the North Sea Rohit Shankaran 2H Offshore Engineering Ltd. Agenda Risers in deepwater North Sea Are steel catenary

More information

Vapor Recovery from Condensate Storage Tanks Using Gas Ejector Technology Palash K. Saha 1 and Mahbubur Rahman 2

Vapor Recovery from Condensate Storage Tanks Using Gas Ejector Technology Palash K. Saha 1 and Mahbubur Rahman 2 37 Journal of Chemical Engineering, IEB Vapor Recovery from Condensate Storage Tanks Using Gas Ejector Technology Palash K. Saha 1 and Mahbubur Rahman 2 Abstract 1 Bibyana Gas Field 2 Department of Petroleum

More information

Simplicity in VRU by using a Beam Gas Compressor

Simplicity in VRU by using a Beam Gas Compressor Simplicity in VRU by using a Beam Gas Compressor By Charlie D. McCoy and Mark Lancaster Abstract: Vapor Recovery Units are often expensive, complicated to operate and unable to deal with High H2S and liquids.

More information

INNOVATIVE MOORING SYSTEMS

INNOVATIVE MOORING SYSTEMS INNOVATIVE MOORING SYSTEMS VESSEL AUTOMOORING MODULES QUAY AUTOMOORING INSTALLATIONS DOCKLOCK brings mooring to a next level PAGE 2 FOR OVER A CENTURY THE WORLD S LEADING EXPERT IN MOORING, BERTHING AND

More information

Pile Gripper Systems

Pile Gripper Systems Pile Gripper Systems Accurate positioning and restraint of offshore construction piles + + Accurate handling of piles up to 8.0m in diameter + + Pile positioning and adjustment within large envelopes +

More information

Completion Workover Riser System. Enabling efficient operations by reducing interface complexities and minimizes operational risk

Completion Workover Riser System. Enabling efficient operations by reducing interface complexities and minimizes operational risk Completion Workover Riser System Enabling efficient operations by reducing interface complexities and minimizes operational risk Well integrity with fatigue management were key drivers for our system design

More information

A Novel Platform for Drilling in Harsh High-Latitude Environments.

A Novel Platform for Drilling in Harsh High-Latitude Environments. AADE-7-NTCE-73 A Novel Platform for Drilling in Harsh High-Latitude Environments. Brian Roberts, Technip; Chunqun Ji, Technip; Jim O Sullivan, Technip and Terje Eilertsen, Technip. Copyright 27, AADE This

More information

EXAMINER S REPORT AND RECOMMENDATION STATEMENT OF THE CASE

EXAMINER S REPORT AND RECOMMENDATION STATEMENT OF THE CASE OIL AND GAS DO0KET NO. 01-0249550 THE APPLICATION OF REGENCY FS LP UNDER RULE 36 AND RULE 46 TO DISPOSE OF OIL AND WASTE CONTAINING HYDROGEN SULFIDE GAS INTO ITS TILDEN GPI WELL NO. 1, TILDEN, S. (WILCOX

More information

(12) United States Patent (10) Patent No.: US 6,456,197 B1

(12) United States Patent (10) Patent No.: US 6,456,197 B1 USOO6456197B1 (12) United States Patent (10) Patent No.: Lauritsen et al. (45) Date of Patent: Sep. 24, 2002 (54) OIL-IN-WATER DETECTOR BUOY (56) References Cited ARRANGEMENT U.S. PATENT DOCUMENTS (75)

More information

ACCESS the BLUE ECONOMY ALL OCEANS Engineering Ltd

ACCESS the BLUE ECONOMY ALL OCEANS Engineering Ltd Subsea Expo 2018 ROV Conference 07.02.2018 ACCESS the BLUE ECONOMY The BLUE ECONOMY - DEFINITION The Blue Economy is a book by Gunter Pauli publish in 2010 based on the idea that he developed in 2004 In

More information

BRINGING A NEW DIMENSION TO PIPELINE PIGGING. By: David Aitken, Aubin Group, UK

BRINGING A NEW DIMENSION TO PIPELINE PIGGING. By: David Aitken, Aubin Group, UK BRINGING A NEW DIMENSION TO PIPELINE PIGGING By: David Aitken, Aubin Group, UK The importance of keeping pipework clear of restrictions and debris to allow maximum flow conditions cannot be emphasised

More information

GAS LIFT IN NEW FIELDS

GAS LIFT IN NEW FIELDS GAS LIFT IN NEW FIELDS GAS LIFT in NEW FIELDS NEW DESIGN FOR WELLS AND COMPRESSORS RESERVOIR AND PRODUCTION SIMULATION MATCHING REQUIRED PRODUCTION NODAL ANALYSIS SIMULATION USED TO SELECT INJECTION DEPTH

More information

Offshore Pipeline Installation SEABED INTERVENTION THE GAME-CHANGING EFFECT DISRUPTION TO HEAVY LIFTING HOW DO YOU MAKE THE SEABED?

Offshore Pipeline Installation SEABED INTERVENTION THE GAME-CHANGING EFFECT DISRUPTION TO HEAVY LIFTING HOW DO YOU MAKE THE SEABED? OSI 2016 VOLUME 9 ISSUE 1 OSI VOL. 9 ISSUE 1 2016 i n d u s t r y DECOMMISSIONING THE GAME-CHANGING EFFECT DISRUPTION TO HEAVY LIFTING OFFSHORE-INDUSTRY.EU SEABED INTERVENTION HOW DO YOU MAKE THE SEABED?

More information

APPENDIX D Oil Loading Pipeline - Options

APPENDIX D Oil Loading Pipeline - Options MAUREEN DECOMMISSIONING PROGRAMME APPENDIX D CONTENTS D.1 Summary of Decommissioning Options Considered 3 D.1.1 D.1.2 D.1.3 Option 1 - Float the Pipeline and Tow it to Shore for Disposal 3 Option 2 Recover

More information

Offshore Wind Vessels. Steven Kopits Douglas-Westwood LLC

Offshore Wind Vessels. Steven Kopits Douglas-Westwood LLC Offshore Wind Vessels Steven Kopits Douglas-Westwood LLC Offshore Wind: Removing Market Barriers DOE Webinar July 25, 2012 1 www.dw-1.com Our business History and Office Locations Established 1990 Aberdeen,

More information

PASSENGER SHIPS Guidelines for preparation of Hull Structural Surveys

PASSENGER SHIPS Guidelines for preparation of Hull Structural Surveys (Feb 2010) PASSENGER SHIPS Guidelines for preparation of Hull Structural Surveys Contents 1 Introduction 2 Preparations for Survey 2.1 General 2.2 Conditions for survey 2.3 Access to structures 2.4 Survey

More information

Protection for Vessels Engaged in Servicing Submarine Cables

Protection for Vessels Engaged in Servicing Submarine Cables Protection for Vessels Engaged in Servicing Submarine Cables Proposed Amendments to COLREGS Brief to Navigation Safety Advisory Council November 28, 2012 Tampa, FL Dr. Ronald J. Rapp TE SubCom and Representing

More information

Helicopter Underwater Emergency Breathing Apparatus (HUEBA) Implementation Plan

Helicopter Underwater Emergency Breathing Apparatus (HUEBA) Implementation Plan CANADIAN ASSOCIATION OF PETROLEUM PRODUCERS Helicopter Underwater Emergency Breathing Apparatus (HUEBA) Implementation Plan 211 Evaluation of HUEBA Training HUEBA training will be evaluated by the CAPP

More information

Pipeline Flooding, Dewatering and Venting Dr Aidan O'Donoghue, Pipeline Research Limited, Glasgow, Scotland

Pipeline Flooding, Dewatering and Venting Dr Aidan O'Donoghue, Pipeline Research Limited, Glasgow, Scotland Pipeline Flooding, Dewatering and Venting Dr Aidan O'Donoghue, Pipeline Research Limited, Glasgow, Scotland Abstract Flooding, cleaning, gauging, dewatering and venting of offshore oil and gas pipelines

More information

Spread Moored or Turret Moored FPSO s for Deepwater Field Developments

Spread Moored or Turret Moored FPSO s for Deepwater Field Developments Spread Moored or Turret Moored FPSO s for Deepwater Field Developments G. Boyd Howell, FMC Technologies Floating Systems, USA Arun S. Duggal, FMC Technologies Floating Systems, USA Caspar Heyl, FMC Technologies

More information

Polar Research Vessel Operational Requirements and Summary of Technical Studies

Polar Research Vessel Operational Requirements and Summary of Technical Studies Polar Research Vessel Operational Requirements and Summary of Technical Studies Presentation to UNOLS by Jim St John Science and Technology Corporation - Polar Technology Office Why a New Antarctic Research

More information

Update on Canadian Research Vessels Ship Procurement Projects

Update on Canadian Research Vessels Ship Procurement Projects Update on Canadian Research Vessels Ship Procurement Projects 28 th International Research Ship Operators Meeting (IRSO) La Jolla, California October 2012 Jennifer Vollrath 1 Outline National Ship Building

More information

AUSTRALIA ARGENTINA CANADA EGYPT NORTH SEA U.S. CENTRAL U.S. GULF. SEMS HAZARD ANALYSIS TRAINING September 29, 2011

AUSTRALIA ARGENTINA CANADA EGYPT NORTH SEA U.S. CENTRAL U.S. GULF. SEMS HAZARD ANALYSIS TRAINING September 29, 2011 AUSTRALIA ARGENTINA CANADA EGYPT NORTH SEA U.S. CENTRAL U.S. GULF SEMS HAZARD ANALYSIS TRAINING September 29, 2011 Purpose The purpose of this meeting is to provide guidelines for determination of hazard

More information

Adapting and Developing Hands Free Mooring for Navigation Locks Speaker: Benoit Nolet

Adapting and Developing Hands Free Mooring for Navigation Locks Speaker: Benoit Nolet Adapting and Developing Hands Free Mooring for Navigation Locks Speaker: Benoit Nolet The Great Lakes St. Lawrence Seaway System A gateway to the heartland of North America 3,700 km (2,300 m) marine highway

More information

Hurricane IVAN Lessons Learned Energy Loss Adjusters Perspective. Bryan C. Johnson

Hurricane IVAN Lessons Learned Energy Loss Adjusters Perspective. Bryan C. Johnson Hurricane IVAN Lessons Learned Energy Loss Adjusters Perspective Bryan C. Johnson I. Lessons Learned - Adjustment Process II. Lessons Learned - The Storm Lessons Learned - Adjustment Process Issues Regarding

More information

Western Canadian Spill Services Ltd. Field Testing Exercise Report

Western Canadian Spill Services Ltd. Field Testing Exercise Report Western Canadian Spill Services Ltd. Field Testing Exercise Report Wednesday, July 15, 2009 Clearwater River, Rocky Mountain House, AB Background Western Canadian Spill Services Ltd. (WCSS) held a field

More information

N2 Membrane+ Nitrogen Production Systems for Offshore. Where you are. Where you need to be. We are here too.

N2 Membrane+ Nitrogen Production Systems for Offshore. Where you are. Where you need to be. We are here too. N2 Membrane+ Nitrogen Production Systems for Offshore Where you are. Where you need to be. We are here too. www.airliquide.com OVERVIEW AIR LIQUIDE OIL AND GAS SERVICES is dedicated to the supply of products

More information

Platelets & Plasma The Management of Unplanned Flow

Platelets & Plasma The Management of Unplanned Flow Platelets & Plasma The Management of Unplanned Flow Who are Brinker? Managing Unplanned Flo Range of innovative products & specialist services to enable operators to effectively manage unplanned flow events

More information

SPE Forum: Source Control for Wells in Shallow Water. Lars Herbst, Gulf of Mexico Regional Director

SPE Forum: Source Control for Wells in Shallow Water. Lars Herbst, Gulf of Mexico Regional Director SPE Forum: Source Control for Wells in Shallow Water Lars Herbst, Gulf of Mexico Regional Director Agenda Introduction and Background Historical Well Control Events Scope of Discussion Scenario Driven

More information

The TURTLE Concept Contents:

The TURTLE Concept Contents: The TURTLE Concept Contents: General Assumptions The Turtle In Brief Why Developing the Turtle Turtle Lay Outs A Field Presentation The Delta TURTLE Concept General assumptions It must be possible to develop

More information

R. Randall Center for Dredging Studies Texas A&M University

R. Randall Center for Dredging Studies Texas A&M University R. Randall Center for Dredging Studies Texas A&M University i Glory (Caisson) holes for subsea installations Pipeline trenches Deep ocean mining LNG ports & ship channels Summary WEDA 33 & TAMU 44 2 WEDA

More information

Top Tensioned Riser Challenges and Solutions for Dry Tree Facilities in Asia Pacific

Top Tensioned Riser Challenges and Solutions for Dry Tree Facilities in Asia Pacific June 2011 Top Tensioned Riser Challenges and Solutions for Dry Tree Facilities in Asia Pacific Daniel Brooker, MCS Kenny Presentation Agenda 1. Objectives 2. Top Tensioned Riser (TTR) Selection Drivers

More information

NOBLE REV 02 FPSO MOORING SYSTEM INTEGRITY STUDY

NOBLE REV 02 FPSO MOORING SYSTEM INTEGRITY STUDY DENTON INTEGRITY STUDY APPENDIX C INCIDENT REPORTS Incident One FPSO Questionnaire Failure of gripper used to rotate turret Several months after installation This FPSO has an internal partially rotating

More information

VESSEL DESIGNS HUISMAN PRODUCT BROCHURE

VESSEL DESIGNS HUISMAN PRODUCT BROCHURE VESSEL DESIGNS HUISMAN PRODUCT BROCHURE VESSEL ESIGNS TABLE OF CONTENTS 01 GENERAL 03 1.1 Introduction 03 1.2 Development 03 02 DRILL SHIPS 06 2.1 HuisDrill 12000 06 03 MOBILE OFFSHORE DRILLING UNITS 07

More information

$ Millions. The PC Semi: A Low Motion Semisubmersible Capable of a Wet or Dry Tree Configuration. Semi Hull CAPEX Differentials. Topsides.

$ Millions. The PC Semi: A Low Motion Semisubmersible Capable of a Wet or Dry Tree Configuration. Semi Hull CAPEX Differentials. Topsides. The : A Low Motion Semisubmersible Capable of a Wet or Dry Tree Configuration In our ever changing and uncertain market conditions, it is extremely important to ensure capital investments are successful

More information

USE OF ISOLATION STOPPLES FOR VALVE REPLACEMENT ON TRANS ALASKA PIPELINE

USE OF ISOLATION STOPPLES FOR VALVE REPLACEMENT ON TRANS ALASKA PIPELINE 2000 international Pipeline Conference Volume 1 ASME 2000 IPC2000-114 USE OF ISOLATION STOPPLES FOR VALVE REPLACEMENT ON TRANS ALASKA PIPELINE Glen W. Pomeroy, P.E., Engineering Manager, Alyeska Pipeline

More information

ROV Development ROV Function. ROV Crew Navigation IRATECH SUB SYSTEMS 2010

ROV Development ROV Function. ROV Crew Navigation IRATECH SUB SYSTEMS 2010 IR AT EC H SU B SY ST EM S 20 10 Remotely Operated Vehicle ROV INTRODUCTORY 2008 2008 1 KEY POINTS ROV Introductory ROV Development ROV Function Types of ROV ROV Crew Navigation ROV Components 2 ROV Development

More information

New Innovative Anchor Solution for Deepwater Mooring Gravity Intalled Anchors Reduce Time and Costs of Marine Operations Jon Tore Lieng CTO

New Innovative Anchor Solution for Deepwater Mooring Gravity Intalled Anchors Reduce Time and Costs of Marine Operations Jon Tore Lieng CTO New Innovative Anchor Solution for Deepwater Mooring Gravity Intalled Anchors Reduce Time and Costs of Marine Operations Jon Tore Lieng CTO Wokshop on Deepwater Subsea TieBack Damai Puri Resort & Spa,

More information

Time-domain Nonlinear Coupled Analyses Covering Typical Mooring and Riser Configurations for FPSOs

Time-domain Nonlinear Coupled Analyses Covering Typical Mooring and Riser Configurations for FPSOs PAU, FRANCE 5-7 APRIL 2016 Time-domain Nonlinear Coupled Analyses Covering Typical Mooring and Riser Configurations for FPSOs Author: Fan Joe Zhang Presenter: Styrk Finne DNV GL - Software Contents Typical

More information

Geo-Vibro Corer

Geo-Vibro Corer High Frequency Vibro Coring System Operational Features Proven performance & high quality cores 30 kn impulse at 30 Hz for fast penetration Reliable, lightweight & cost effective Modular construction (cores

More information

Operations and Requirements A Practical Approach to Managing DP Operations

Operations and Requirements A Practical Approach to Managing DP Operations Operations and Requirements A Practical Approach to Managing DP Operations Suman Muddusetti Shell International Exploration and Production, Inc. Doug Phillips Global Maritime, Inc. October 17-18, 2006

More information