Drilling Under Pressure: HDD Beneath an Active Airport

Size: px
Start display at page:

Download "Drilling Under Pressure: HDD Beneath an Active Airport"

Transcription

1 North American Society for Trenchless Technology (NASTT) NASTT s 2016 No-Dig Show Dallas, Texas March 20-24, 2016 MM-T2-01 Drilling Under Pressure: HDD Beneath an Active Airport Dylan Davidson, Staheli Trenchless Consultants, Lynwood, WA Laura Wetter, Staheli Trenchless Consultants, Lynnwood, WA James Campero, City of Camarillo, Camarillo, CA Bill Yates, Kennedy Jenks Consultants, Ventura, CA 1. Abstract The Camarillo Airport is a general aviation reliever airport with approximately 190,000 takeoffs and landings per year. As such, it is vital to keep airport disruptions to a minimum during construction projects. This led the City of Camarillo to consider trenchless options during a planned upgrade to the Camarillo Airport water system. The upgrade required the construction of approximately 1,900 feet of 16-inch water main pipeline beneath the airport without disturbance to the runway and parallel primary taxiway. The initial feasibility analysis compared horizontal directional drilling (HDD) with a combination of open-cut and auger boring for the water main construction. HDD was ultimately selected as the preferred method, leading to design challenges associated with a creative pullback layout requiring lofting above the County flood control channel just north of the airport. The active runway and taxiway also made drill navigation very challenging. A conventional wireline system could not be placed, a walkover system was considered to be too disruptive to airport operations, and rebar beneath the runway and taxiway was anticipated to cause magnetic interference. Ultimately, the drill was guided using a combination of wire coils near the entry and exit points and an AC beacon in the infield between the runway and taxiway. Continuous coordination with air traffic control was required during all phases of the installation which was successfully completed without major incident. This paper details the design and construction of the new waterline, focusing on lessons learned during drilling beneath the active airport. 2. Introduction The City of Camarillo needed to install a new water main; however, the proposed pipeline alignment crossed beneath an active airport. The Camarillo Airport is owned by Ventura County and is considered a general aviation reliever airport with approximately 190,000 takeoffs and landings per year. As such, it was vital to keep airport disruptions to a minimum during all phases of the construction process. That meant no surface construction was allowed to take place within the restricted area of the active runway and taxiway. This led the City of Camarillo to consider trenchless alternatives for upgrading the Camarillo Airport s water system. The upgrade required the construction of approximately 1,900 feet of 16-inch water main pipeline beneath the airport. Auger boring with a combination of open-cut construction was considered for the project; however, auger boring required dewatering and open-cut resulted in significant impacts to the airport. As such, horizontal directional drilling (HDD) was determined to be the preferred trenchless alternative for the project. It reduced the impacts to airport operations and did not necessitate dewatering. There were two challenging parts to the HDD design; pullback layout and drill navigation. Due to the County flood control channel just north of the airport, a creative pullback layout was required which included lofting the fused pipe above the channel during continuous pullback operations. In addition, due to the active runway and taxiway, tracking of the drill was challenging. A conventional wireline system could not be used, a walkover system was considered to be too disruptive to airport operations, and rebar beneath the runway and taxiway was anticipated to cause magnetic interference to any system. Ultimately the HDD Paper MM-T

2 was guided using a Paratrack-2 with a combination of wire coils near the entry and exit points and an AC beacon in the infield between the runway and taxiway. Ventura Directional Drilling Inc. (VDD) was awarded the contract for a bid price of approximately $550,000. VDD installed the HDD totaling approximately 1,685 feet of 16-inch HDPE pipe. In all, the project took six weeks to complete. 3. Geotechnical and Site Conditions To determine the soil and groundwater conditions at the project s site, two borings were drilled to depths greater than 70 feet. Both borings encountered approximately 10 feet of medium stiff to stiff clays underlain by interbedded layers of alluvial soils consisting of medium to very dense/stiff silts, clays, sand, and silty sands to the maximum depth explored (Earth Systems Southern California, 2012). Although the groundwater elevation could not be determined due to the drilling method performed (rotary wash method), historically high groundwater in the area was approximately 10 feet below the ground surface (Earth Systems Southern California, 2012). However, the moisture content of the samples in the upper 10 feet of clay was indicative of saturated soils; therefore, for purposes of design, the groundwater was assumed to be at the ground surface. 4. Feasibility Approach The primary focus of the design team was to ensure disruptions to the airport operations would be minimal. The more disruptions to the airport, the longer the construction would take. Therefore, a continuous open-cut option through the runway was eliminated from consideration. During the initial approach to the project, microtunneling, auger boring, pipe ramming, and HDD were evaluated to determine which trenchless methods were the most appropriate for the project. The project site is shown below in Figure 1. Figure 1: Project site showing critical crossings locations, boring locations, and total length Paper MM-T

3 Microtunneling was not considered a practical option for the project due to the long drive length and the costs of microtunneling; particularly the up front costs associated with mobilization. To minimize the risk of microtunneling, the 1,900 feet of new pipeline would either need to be split up into two separate drives of approximately 200 feet and 500 feet (see Figure 1) and combined with open-cut construction, or intermediate jacking stations would need to be used to increase the jacking capacity along the length of the pipeline. However, both of these options were deemed impractical as there were other feasible trenchless methods available at a much lower cost. Pipe ramming was determined to not be feasible. Similar to microtunneling, the 1,900 feet of new pipeline could be split up into two shorter pipe ram drives and combined with open-cut; however, this was considered particularly risky. In general, pipe rams are typically limited to drives less than 300 feet with a drive on the order of 500 feet considered exceptional. This project would require a 500-foot drive length which the design team determined would present an unnecessary amount of risk to the project and eliminated pipe ramming from consideration. Auger boring was determined to be a feasible option. Similar to microtunneling and pipe ramming, auger boring would involve splitting the 1,900 feet of pipeline into two shorter drives of 200 feet and 500 feet and combined with open-cut construction; thus yielding a viable alternative. Auger boring was a preferred alternative over microtunneling due to the lower costs of construction and mobilization. On the other hand, there were several drawbacks to auger boring. These drawbacks included several shafts needed for construction, substantial dewatering and a two-pass installation were required; all leading to an increased cost for auger boring. Although auger boring was the most practical pipe jacking approach for the project, it was not the chosen trenchless method. HDD was considered the least costly and most practical option for crossing the Camarillo Airport, as the technology excels where the other technologies had shortcomings. For example, HDD can be drilled to lengths upwards of 3,000 feet or more at the project s pipe diameter of 16-inches, eliminating the need for shafts. Additionally, this method reduces the disruptions to airport operations since there is significantly less work being performed near the taxiway and runway, particularly at the surface. Because auger boring and HDD were the most feasible trenchless methods, they were compared as shown below in Table 1. Based on the analysis, HDD was the most practical option for installation of the pipeline. Table 1: Comparison Table for Trenchless Method Selection. Green: most favorable; Yellow: neutral; Red: least favorable. Paper MM-T

4 5. HDD Design Once HDD was chosen as the preferred trenchless method, measures were taken to ensure drilling operations would not affect airport operations; risks were identified and work areas were established. Critical risks that needed to be mitigated included: soil settlement, heave of the runway, and hydrofracture. Soil settlement resulting from HDD operations is primarily caused by collapse of the annular space between the borehole and the product pipe. The risk of soil settlement increases in unstable soils, or where depth of cover is low. Fortunately for this project, the majority of the pipeline was anticipated to be within medium to very dense/stiff silts, clays, and sands, resulting in a stable borehole which greatly reduced the likelihood of settlement occurring. However, even if catastrophic borehole failure were to occur, a depth of cover of 40 to 50 feet was designed to protect the airports critical locations, the runway and taxiway, against settlement. Surface heave resulting from HDD can occur if excess drilling fluid is pumped after circulation is lost, if reaming is performed without sufficient depth of cover, or if reaming is performed too quickly. It was critical that surface heave did not occur at the airport s runway and taxiway. To mitigate these issues, the bore was designed to have significant depth of cover at the critical crossing locations, the entry pit was to be constantly monitored to ensure the drilling fluid was always in circulation, and the reaming rates were to be carefully monitored. Hydrofracture was also considered. Hydrofracture occurs when drilling fluid pressure exceeds the strength and confining stress of the soils surrounding the borehole. The excess pressure fractures the soil around the bore, allowing drilling fluid to escape. Although drilling fluid is non-toxic and is typically 97 to 99 percent water, it is still important to reduce the risk of hydrofracture. Drilling fluid is extremely slick and if a plane or car were to drive across it, there is a high potential risk of losing all steering control of the plane or car. To reduce this risk, hydrofracture calculations were performed and used to design the bore to ensure it achieved a sufficient depth at which point the drill crosses beneath the runway and taxiway. At the taxiway location, the bore was designed to be approximately 60 feet below the ground surface. At the runway location, the bore was designed to be approximately 65 feet below the ground surface. On the other hand, the soils within the immediate vicinity of the entry and exit locations were at an even higher risk for hydrofracture due to the low depth of cover. The HDD contractor was required to have adequate equipment and materials on site to immediately respond to and cleanup any inadvertent returns to the surface. The HDD contractor was contracted to install approximately 1,750 feet of 16-inch HDPE IPS DR-11 pipe. The HDD was designed to have an entry angle of 16 degrees to allow the bore to achieve greater depths before reaching the taxiway; the first critical crossing location of the Camarillo Airport. Conductor casing was not required on the project. During pullback operations, the string of product pipe was required to be loaded onto pipe rollers to fully support the pipeline as the product pipe was not allowed to be dragged across the ground. Additionally, a bridge was required to support the pipeline as it crossed the County flood control channel during pullback. One of the most challenging parts of the project was utilizing a drill tracking system that could adequately track the location of the drill bit while drilling across an active airport. The tracking system must be able to continuously monitor and record the drill s location at least once per drill pipe length. A walkover wireline system was considered too disruptive to airport operations as the wireline would need to be strung across the entire length of the HDD to allow continuous monitoring. The Camarillo Airport would not allow this because stringing the wireline across the taxiway and runway was a risk to airport operations. The final design specified the use of a Paratrack-2 system, with a combination of wire coils near the entry and exit points, and an AC beacon tracking system. A Paratrack-2 system is first established by setting up a grid around both the entry pit and exit pit work areas. With a Paratrack-2, a coil is setup around the perimeter of the pits and down the designed centerline of the bore. The wire coil is wrapped around wooden stakes to create a complete loop, a grid, which establishes a magnetic field and runs an AC current. The Paratrack-2, in conjunction with the AC beacon, reads the induced magnetic field created by the wire coil to locate itself for performing a land survey. The land survey established the known points of the magnetic field at both pit locations. Figure 2 shows the AC beacon and the magnetic field being established by the wire coil. Paper MM-T

5 Once the magnetic field is established at both pit locations, the Paratrack-2 is loaded into a non-magnetic drilling collar (the monel) and orientated into the orientation sub housing, which was then connected to the monel. A wireline was also strung from the back of the monel and through each drill pipe that was added to the drill string to allow the location of the bit to be tracked continuously. After each drill pipe was advanced, the steer hand took a survey shot of the bore, which gave the azimuth, inclination, and away distance of the bore. Prior to drilling, the drill bit, directly in front of the monel, was surveyed to ensure that it was oriented in the direction of the designed bore path. The rig was then be adjusted according to the surveyed data and the entry angle was established. The tracking data was monitored using two programs; Rivcross and AutoCAD. Rivcross is a software that integrates tracking and survey data from the Paratrack tooling to provide real time steering guidance. The steer hand then determined the location of the Paratrack using the azimuth, inclination, and away distances read by the Paratrack, as interpreted in xyz coordinates by the Rivcross software. The data was then plotted in relation to the design using AutoCAD. The steer hand then coordinated with the driller on the steering required to follow the HDD design path. Figure 2: AC beacon tracking system with the survey equipment in the background (left); Wire coil strung around the perimeter of the entry pit area to establish the magnetic field (right). One of the more challenging parts of the tracking system design, comes from the restrictions of the AC beacon. The AC beacon has a maximum range of approximately 300 feet radially, meaning it needs to be moved after every 600 feet of drilling. Once the drill passes the taxiway, the bit will be out of range from the AC beacon, meaning the driller will need to steer using true magnetic north of the Earth for orientation. The magnetic field was only established at the entry and exit pit locations, so the infield, the area between the taxiway and the runway, was not surveyed. The AC beacon, which was used to verify the bore path, needs to be moved to the infield along the centerline of the bore path, such that the Paratrack-2 navigation system could contact the tracking software to ensure an accurate bore path. Each day as the drill advanced closer to the exit pit, the AC beacon in the infield needed to be moved further down the bore path to ensure the bore was accurately drilled. 5. Construction Before anyone could work on the Camarillo Airport property, everyone, including the contractor, inspectors, and any subcontractors, were required to pass an airport driving training course that focused on how to drive on an active airport. Restrictions included no one being allowed to take a step onto the taxiway or runway without the approval from air traffic control. No one was allowed to walk within 100 feet of the runway without permission. If anyone were to step onto either the taxiway or the runway without consent, they were subject to immediate arrest. The Camarillo Airport took these regulations very seriously. Ventura Directional Drilling (VDD) employees were required to carry walkie-talkies at all times so they could be in constant contact with air traffic control since the airport was open during all hours of construction. The first week of the project consisted of fusing together the HDPE product pipe. The pipe was fused together at the north end of the airport in three separate sections; two 750 foot strings and a 300 foot string. VDD elected to locate their drilling equipment at the south end of the site. VDD drilled the project with a Ditch Witch JT100-Mach 1 HDD Paper MM-T

6 Rig. VDD hired InRock as their steering subcontractor to provide tracking of the drill. Figure 3 shows the HDD rig used on the project. While VDD was mobilizing their equipment, InRock began setting up their survey and tracking equipment. InRock began by surveying the coil grid using a theodolite and known markers. InRock surveyors repeated these steps at the exit side. The surveyors then needed to move to the infield to mark the centerline of the HDD bore path. To do this, VDD coordinated with air traffic control prior to crossing the taxiway. Next, InRock repeated the steps for establishing the coil at the exit side. InRock then installed the probe into the monel with the orientation sub and the wire line was attached and installed into the monel. Since the stakes had been surveyed and the wire line was attached to the monel, the wire coil was then wrapped around the wooden stakes that bordered the entry pit side and was connected to the AC beacon to establish the magnetic field. The magnetic field could be turned on and off as needed. Figure 3: Ditch Witch JT100-Mach 1 HDD Rig used by Ventura Directional Drilling, Inc. After all surveying was completed, the site was prepared for drilling. The first phase of drilling, the pilot bore, took eight days to complete. The bore was drilled a distance of approximately 1,685 feet from entry to exit. During the pilot bore, several issues manifested. One of those issues occurred on the first day of drilling. During drilling, the drill bit began sinking beyond the design path and continued to sink the further VDD was drilling. Originally, VDD chose to use a mud motor in anticipation of dense soil conditions; however, the down hole assembly (DHA), consisting of the monel, orientation sub, and mud motor, was causing over-excavation, resulting in sinking of the pilot bore. The HDD was designed to have a bore path tolerance of plus or minus 5 feet. Within six drill pipes, the bore had sunk 4.75 feet below the designed bore path. After leaving the site and coming back the next day, VDD was informed by the steer hand that if they continued to drill on the path they were on, they would exceed the design tolerances and would be approximately 40 feet deeper than designed. Because of this, VDD changed their tooling by removing the mud motor and changing their drill bit. They switched from a 6.5-inch mill tooth tri-cone drill bit to a 6.5-inch spade dirt bit because the soil encountered along the bore did not require a mud motor for excavation. Figure 4 shows the two bits used on the project. In addition, they changed the designed bend radius from 1000 feet to approximately 562 feet due to the steep bore path. The design team was consulted on these changes and was concerned about the depth of the new borepath. The geotechnical borings on the project terminated at a depth of 78 feet, but with the proposed drilling plan, the bore would be drilled to a depth of 75 feet. VDD was allowed to proceed but agreed to proceed at their own risk should they drill deeper than the designed maximum depth of 63 feet. Paper MM-T

7 Figure 4: First drill bit, 6.5-inch mill tooth tri-cone bit (left); Second drill bit, 6.5-inch spade dirt bit (right) Once the new drill bit reached the existing borehole where drilling was paused to switch drill bits and remove the mud motor, VDD began drilling its new bore path at the altered bending radius. The new drill bit s response to steering was greatly improved once the mud motor was removed. After drilling approximately 308 feet, the AC beacon was moved to the north side of the taxiway. VDD was previously drilling under the taxiway using true magnetic north for reference, with the guidance of InRock. Moving the AC beacon to the other side of the taxiway allowed the drill to be tracked via the InRock software, as the magnetic beacon used the wireline and the downhole signals to locate the drill bit. After moving the AC beacon, the steering hand adjusted the elevation of the bore as the beacon reading indicated that the bit was approximately 3 feet lower than calculated with true magnetic north. They continued drilling to move further from the taxiway and re-evaluated their location. The new drill bit was successful in regaining elevation. VDD continued drilling until they were approximately 560 feet out, at which point the InRock steering hand had to guide the bore off of only the azimuth and inclination readings. Since the steer hand was confident in performing the method, it was decided that they would continue to guide the bore via the azimuth and inclination until they reach the exit coil that was setup prior to the start of the pilot bore. In all, there were no other steering issues that occurred. In relation to the project s design, the completed pilot bore ended up being 3.1 feet to the left of the centerline and 4.5 feet short of the designed exit point (Figure 5). Another issue during the pilot bore resulted from the wireline being attached to the monel and being strung out through each drill pipe. Occasionally the wireline would cut out, resulting in the bore tracking being rendered useless. VDD would then trip back several drill pipes until the problem could be fixed. In some cases, VDD would need to trip back all the way to the monel to fix the issue. Since this issue continued to be a problem, VDD decided that after drill pipe #42 (~620 feet) they would add a built-in spider to the drill string. The spider acted as an area to store the wireline, such that if the wireline were to cut out again, VDD would only need to trip back to the location of the spider to regain connection. In addition, VDD switched their wirelines from zinc to copper wire in hopes it would also assist in reducing wire shortages. Paper MM-T

8 Figure 5: HDD designed exit point vs. actual drill bit exit point The biggest issue with the pilot bore was also one of the biggest risks the design team hoped to avoid. While drilling at 1,350 feet, the crew noticed a loss of circulation, as mud returns back at the entry pit were slim, if any at all. They believed the mud must have been going into a void or fissure of the existing soil because no inadvertent fluid returns, or frac-out, was found on the surface at the entry, exit, or infield locations. This made the crew slightly worrisome, so they monitored the surface for any fluid returns. Alas, after drilling 1,605 feet out, inadvertent fluid returns were found at the exit side, directly over the bore centerline, in very close proximity to the runway (Figure 6). The drilling mud covered an area measuring approximately 20 feet by 30, approximately 50 feet short of the designed exit point. Fortunately, the thickness of the runway was adequate to confine the drilling fluid pressures, keeping the drilling mud from escaping onto the runway or taxiway. After it was spotted, air traffic control was alerted. Air traffic control had to temporary stop all take-offs and landing for planes on the runway until they spill could be cleaned up and contained. VDD brought out vac trucks, while being escorted by Camarillo Airport personnel, to vacuum the inadvertent fluid returns. The cleanup caused a delay of approximately 30 minutes. Unfortunately, the location where the inadvertent fluids were surfacing from the ground could not be located. Figure 6: Inadvertent fluid returns area found right next to the airport s runway Paper MM-T

9 After the spill was contained and cleaned up, VDD decided that since they were only 50 feet from the exit point, they would drill the rest of the bore without mud. They believed that since the source of the surfacing drill fluid could not be located, drilling without mud would be the safest choice for not causing another frac-out. No problems occurred from drilling without mud for the remainder of the pilot bore. After the pilot bore was completed, VDD was ready to begin the reaming phase. VDD had hoped to push ream with a 24-inch barrel reamer and then simply swab the bore hole prior to pullback; however, the plan did not go smoothly. After push reaming for four days and advancing approximately 690 feet, VDD decided to use a different type of reamer due to very slow reaming times. They tripped the reamer back to the surface revealing that the reamer was packed with a mixture of clay, silt, and sand. They added an 18-inch fly cutter reamer to be placed in front of the 24-inch barrel reamer in hopes it would speed up the push reaming process. However, the new reaming plan failed after approximately 30 feet of reaming due to high torque. Since the previous attempts at push reaming failed, VDD decided to start over with a pull reaming process. VDD began with an 8-inch hole opener which took one day to complete. Next, they used a 12-inch terminator hole opener which took slightly over one day to complete. Once completed, VDD installed an 18-inch open type, threeblade reamer with carbon bits in front of the 12-inch terminator. The 18-inch pull ream took another day to complete. After completion, VDD then prepared for the final pull ream phase. They used the 12-inch terminator in front as the stabilizer and attached a 19/24-inch combo reamer behind it. The final pull reaming took a day and a half. Figure 7 shows the various reamers used on the project. Figure 7: Clockwise from upper left: 24-inch barrel reamer; 18-inch fly cutter reamer; 12-inch terminator hole opener; 18-inch open type, three-blade reamer; 19/24-inch combo reamer. Paper MM-T

10 After the reaming phase was completed, VDD prepared for pullback. They started by using the 19/24-inch combo reamer in front of a 22-inch diameter barrel reamer to swab pull the bore hole to prove it was ready for pullback. While this was happening, VDD also prepared the 1,800 feet of HDPE pipe for pullback by fusing the three sections together and setting it on rollers. The crew needed to be creative in ensuring the pipe could be supported during continious pullback operations. The County flood control channel, slightly north of the exit point, required the pipe to be continuously supported as it is lofted and pulled across the channel. The crew used pieces of wood and a back hoe to fully support the pipeline as it crossed the channel. Figure 8 shows the pipe being fully supported across the channel. Figure 8: 16-inch HDPE pipe being supported across the County flood control channel (left and right) For pullback, a 2-inch tremie pipe was strung throughout the 16-inch HDPE pipe and filled with water for buoyancy control to allow ballasting during installation. The 22-inch barrel reamer was attached in front of the swivel which connected to the 1,800 feet of HDPE pipe. In all, pullback was completed in one continious operation and took approximately six hours and thirty minutes to complete. 6. Lessons Learned Although the installation had some difficulties, VDD was able to successfully cross the active Camarillo Airport via HDD. Similar to other HDD projects, permits and coordination with public or private establishments are still required and inadvertent fluid returns are still a concern. In this case however, inadvertent fluid returns were seen as a higher risk because spilling onto an active runway is extremely dangerous due to the properties of the fluids. To improve upon this project, VDD should have had someone constantly monitoring for fluid returns on the exit side. The large spill area next to the runway would not have been able to get as large as it did if it was constantly being monitored during the entire pilot bore. In addition, a Paratrack-2 and AC beacon tracking system proved to be successful at tracking the HDD operation while crossing beneath an active airport without causing any major disruptions to airport operations. This project serves as an example for the Federal Aviation Administration (FAA) and other engineers as to how to directionally drill beneath an active airport. 7. References Bennett, D., and Ariaratnam, S. (2008) Horizontal Directional Drilling Good Practices Guidelines, North American Society for Trenchless Technology (NASTT), Third Edition, USA. Daily Inspection Reports and Photos, Camarillo Airport Project Earth Systems Southern California (2012) Geotechnical Engineering Report For Proposed Waterline Camarillo Airport Camarillo, California. Plans and Specifications, Camarillo Airport Project Staheli, K., Wetter, L. (2012), Trenchless Method Feasibility Camarillo Airport Water Improvement Project. Paper MM-T

OCEAN OUTFALL PRESENTS CHALLENGES TO HDD CONSTRUCTION

OCEAN OUTFALL PRESENTS CHALLENGES TO HDD CONSTRUCTION North American Society for Trenchless Technology (NASTT) No-Dig Show 2010 Chicago, Illinois May 2-7, 2010 Paper A-1-04 OCEAN OUTFALL PRESENTS CHALLENGES TO HDD CONSTRUCTION Laura Wetter, G.I.T. 1, Matt

More information

TULALIP TRIBE AND CITY OF EVERETT BRING REGIONAL WATER TO THE PACIFIC NORTHWEST WITH MASSIVE HDD PROJECT

TULALIP TRIBE AND CITY OF EVERETT BRING REGIONAL WATER TO THE PACIFIC NORTHWEST WITH MASSIVE HDD PROJECT North American Society for Trenchless Technology (NASTT) No-Dig Show 2012 Nashville, TN March 11-15, 2012 Paper D-1-04 TULALIP TRIBE AND CITY OF EVERETT BRING REGIONAL WATER TO THE PACIFIC NORTHWEST WITH

More information

DIRECTIONAL DRILLING

DIRECTIONAL DRILLING DIRECTIONAL DRILLING 1. General. Installation of pipelines through the levee embankment using directional drilling technology is prohibited. Installation of pipelines through a flood control project foundation

More information

INADVERTENT RETURN PLAN FOR HORIZONTAL DIRECTIONAL DRILLING (HDD)

INADVERTENT RETURN PLAN FOR HORIZONTAL DIRECTIONAL DRILLING (HDD) INADVERTENT RETURN PLAN FOR HORIZONTAL DIRECTIONAL DRILLING (HDD) FACILITY OPERATOR: NextEra Energy Resources, LLC 700 Universe Boulevard Juno Beach, FL 33408 For Horizontal Directional Drilling Contents

More information

Feasibility Study of HDD Strait of Belle Isle

Feasibility Study of HDD Strait of Belle Isle Muskrat Falls Project - CE-1 Rev. (Public) Page 1 of 108 Labrador Coast Newfoundland Island Coast Feasibility Study of HDD Strait of Belle Isle FOR THE FINAL REPORT December 10, 010 Report No: H6-RPT-CA01-01

More information

Chapter 5 HORIZONTAL DRILLING

Chapter 5 HORIZONTAL DRILLING Chapter 5 HORIZONTAL DRILLING Chapter 5 How much money am I about to put on the table for a horizontal well? Did I do sufficient planning? Keys to Successful Horizontal Wells Multi-disciplined teams working

More information

Attachment 6. HDD Feasibility Report

Attachment 6. HDD Feasibility Report May 2016 May 2016 May 2016 Page 1 of 21 The Pipeline Project TABLE OF CONTENTS 1 Introduction... 3 2 HDD Crossings... 3 3 Design Parameters... 3 4 Tributary to Simonette River Crossing... 4 4.1 Watercourse

More information

Bore-Gard Installation - 1,000 ft. Perry, Oklahoma

Bore-Gard Installation - 1,000 ft. Perry, Oklahoma Bore-Gard Installation - 1,000 ft. Perry, Oklahoma Distance of Installation: Maximum Pulling Force on Pipe: Reamer Diameter: Soil Conditions: 1,000 feet Approx. 7,500 pounds 8 inch Beaver Tail Wet Clay

More information

Construction Dewatering

Construction Dewatering Construction Dewatering Introduction The control of groundwater is one of the most common and complicated problems encountered on a construction site. Construction dewatering can become a costly issue

More information

DIRECTIONAL DRILLING SAFE WORK PRACTICE

DIRECTIONAL DRILLING SAFE WORK PRACTICE NORSEMAN SAFE WORK RACTICES DIRECTIONAL DRILLING SAFE WORK RACTICE UROSE The purpose of this practice is to promote compliance with both government and company guidelines regarding directional drilling

More information

Third time s a charm for installing gravity sewer in tough Georgia rock

Third time s a charm for installing gravity sewer in tough Georgia rock Third time s a charm for installing gravity sewer in tough Georgia rock Facing challenging ground conditions, DeKalb Pipeline succeeds using laser-guided boring system It took a contractor who was receptive

More information

TRANSCANADA KEYSTONE PIPELINE PROJECT EXECUTION PHASE HDD EXECUTION PLAN FOR WATER COURSE CROSSINGS. Shannon Creek

TRANSCANADA KEYSTONE PIPELINE PROJECT EXECUTION PHASE HDD EXECUTION PLAN FOR WATER COURSE CROSSINGS. Shannon Creek TRANSCANADA KEYSTONE PIPELINE PROJECT EXECUTION PHASE HDD EXECUTION PLAN FOR WATER COURSE CROSSINGS Shannon Creek Rev. 1 Owner: TransCanada Prime Contractor: Ledcor Pipeline Limited HDD Contractor: Dwayne

More information

RULES OF THE OIL AND GAS PROGRAM DIVISION OF WATER RESOURCES CHAPTER DRILLING WELLS TABLE OF CONTENTS

RULES OF THE OIL AND GAS PROGRAM DIVISION OF WATER RESOURCES CHAPTER DRILLING WELLS TABLE OF CONTENTS RULES OF THE OIL AND GAS PROGRAM DIVISION OF WATER RESOURCES CHAPTER 0400-52-06 DRILLING WELLS TABLE OF CONTENTS 0400-52-06-.01 Drilling Equipment 0400-52-06-.03 Casingheads 0400-52-06-.02 Blowout Prevention

More information

Talk about a bore! Driver Pipeline (USA) completes a mile (1.8 km) bore through rock in one continuous shot

Talk about a bore! Driver Pipeline (USA) completes a mile (1.8 km) bore through rock in one continuous shot Talk about a bore! Driver Pipeline (USA) completes a 1.13- mile (1.8 km) bore through rock in one continuous shot Affectionately known by officials with project owner Chesapeake Midstream Partners as FRAP

More information

Perched Box Caisson Overview. January 2014

Perched Box Caisson Overview. January 2014 Perched Box Caisson Overview January 2014 Why perched box caissons? Perched box caissons are used to construct the portion of the river piers that will support the steel arch spans Construction can occur

More information

North American sealing solutions Bridge Plug Ball Drop Frac Plug Caged Ball Frac Plug

North American sealing solutions Bridge Plug Ball Drop Frac Plug Caged Ball Frac Plug North American sealing solutions Bridge Plug Ball Drop Frac Plug Caged Ball Frac Plug The North American Sealing Solutions composite bridge plug, caged ball and ball drop (flow thru) frac plug provide

More information

WILD WELL CONTROL WARNING SIGNS OF KICKS

WILD WELL CONTROL WARNING SIGNS OF KICKS WARNING SIGNS OF KICKS Warning Signs of Kicks Learning Objectives You will learn the warning signs that indicate the well may be kicking: Warning signs of kicks False kick indicators You will also learn

More information

SGS MUSCOWPETUNG ABORIGINAL CONSTRUCTION MONITORING

SGS MUSCOWPETUNG ABORIGINAL CONSTRUCTION MONITORING SGS MUSCOWPETUNG ABORIGINAL CONSTRUCTION MONITORING WEEKLY REPORT SPREAD# 5 SEPTEMBER 24 TH TO SEPTEMBER 30 TH, 2018 Page 1 of 8 Field Observation Social and Cultural Features # of occurrences Traditional

More information

Appendix J: Q1-Highway 35 Route Construction Plan

Appendix J: Q1-Highway 35 Route Construction Plan PSC REF#:150055 Wisconsin CPCN Appendix J Appendix J: Q1-Highway 35 Route Construction Plan Public Service Commission of Wisconsin RECEIVED: 06/29/11, 8:51:24 AM Hampton Rochester La Crosse 345 kv Transmission

More information

Bridge Plugs, Ball Drop & Caged Ball Plugs For Zone Isolation

Bridge Plugs, Ball Drop & Caged Ball Plugs For Zone Isolation Bridge Plugs, Ball Drop & Caged Ball Plugs For Zone Isolation ADVANTAGE composite bridge plug, caged ball and ball drop (flow thru) frac plug provide a means to isolate multiple zones during high pressure

More information

PUSH PIER SYSTEMS STABILITY. SECURITY. INTEGRITY. Push Pier Systems PN #MBPPT

PUSH PIER SYSTEMS STABILITY. SECURITY. INTEGRITY. Push Pier Systems PN #MBPPT PUSH PIER SYSTEMS STABILITY. SECURITY. INTEGRITY. PN #MBPPT Push Pier Systems About Foundation Supportworks is a network of the most experienced and knowledgeable foundation repair and new construction

More information

The Time Has Come For Coiled Rod. Reprinted from Well Servicing magazine

The Time Has Come For Coiled Rod. Reprinted from Well Servicing magazine The Time Has Come For Coiled Rod Reprinted from Well Servicing magazine The development of flush-by well service units and stand-alone coiled rod injector head technology has helped grow the coiled rod

More information

Hydro-Mech Bridge Plug

Hydro-Mech Bridge Plug Manual No: 0620000303 Revision: F Approved By: Quality Engineer Date: 2014-9-9 Hydro-Mech Bridge Plug DESCRIPTION: Map Hydro-Mech Bridge Plug is hydraulically actuated and mechanically set. Compact, with

More information

W I L D W E L L C O N T R O L FLUIDS

W I L D W E L L C O N T R O L FLUIDS FLUIDS Fluids Learning Objectives You will learn about different fluids that can be used in well control. You will become familiar with the characteristics and limitations of fluids. You will learn general

More information

Float Equipment TYPE 925/926

Float Equipment TYPE 925/926 Type 925 Float Collar Plunger Valve Float Equipment For less demanding well conditions, such as shallower depths or lower pressures, Top- Co offers economical float equipment certified to API RP 10F category

More information

Type 967 Diamond Broaching Type 968 Sidewinder reamer shoe

Type 967 Diamond Broaching Type 968 Sidewinder reamer shoe Type 965 float collar Type 966 float shoe 1. GENERAL INFORMATION & RECOMMENDATIONS Type 967 Diamond Broaching Type 968 Sidewinder reamer shoe Type 969 Sidewinder reamer shoe Float Equipment Top-Co Float

More information

TECHNICAL MEMORANDUM 002 EMORANNO. 001

TECHNICAL MEMORANDUM 002 EMORANNO. 001 TECHNICAL MEMORANDUM 002 EMORANNO. 001 To: Jack Synder, P.E. EES Consulting From: Mort McMillen, P.E. Paul Larson, SE Date: October 13, 2010 Project: Cc: Taylor Bowen Subject: Technical Memorandum (TM)

More information

Perforating Options Currently Available in Horizontal Shale Oil and Gas Wells. Kerry Daly, Global BD Manager- DST TCP

Perforating Options Currently Available in Horizontal Shale Oil and Gas Wells. Kerry Daly, Global BD Manager- DST TCP MENAPS 2013 Perforating Options Currently Available in Horizontal Shale Oil and Gas Wells Kerry Daly, Global BD Manager- DST TCP MENAPS 13-17 WELL FLOW MANAGEMENT TM Scope/ Contents: MENAPS 13-17 Study

More information

Horizontal Directional Drilling and Impact Moling

Horizontal Directional Drilling and Impact Moling THE INSTITUTION OF GAS ENGINEERS Safety Recommendations Founded 1863 IGE/SR/26 Royal Charter 1929 Communication 1662 Patron Her Majesty The Queen Horizontal Directional Drilling and Impact Moling President:

More information

Appendix C - HDD Inadvertent Returns and Contingency Plan

Appendix C - HDD Inadvertent Returns and Contingency Plan Appendix C - HDD Inadvertent Returns and Contingency Plan HDD Inadvertent Returns and Contingency Plan PennEast Pipeline Project Issue and Revision Record Rev Date Originator Checker Approver Description

More information

Cook Inlet pipeline crossing is about making the best choices

Cook Inlet pipeline crossing is about making the best choices Cook Inlet pipeline crossing is about making the best choices By Larry Persily lpersily@kpb.us Aug. 26, 2015 (This update, provided by the Kenai Peninsula Borough mayor s office, is part of an ongoing

More information

REPORT GEO-TECHNICAL INVESTIGATION FOR THE PROPOSED BLOCK-7 SUB-STATION SY NO-225, NEAR RAYACHERLU VILLAGE

REPORT GEO-TECHNICAL INVESTIGATION FOR THE PROPOSED BLOCK-7 SUB-STATION SY NO-225, NEAR RAYACHERLU VILLAGE REPORT ON GEO-TECHNICAL INVESTIGATION FOR THE PROPOSED BLOCK-7 SUB-STATION SY NO-225, NEAR RAYACHERLU VILLAGE CLIENT: KARNATAKA SOLAR POWER DEVELOPMENT CORPORATION BANGALORE 0 GEO-TECHNICAL INVESTIGATION

More information

float equipment OPERATING MANUAL TYPE 505/506 Float Equipment 1. INFORMATION & RECOMMENDATIONS Float Equipment

float equipment OPERATING MANUAL TYPE 505/506 Float Equipment 1. INFORMATION & RECOMMENDATIONS Float Equipment Contents 1. GENERAL INFORMATION & RECOMMENDATIONS 1 2. INSTALLATION FLOAT EQUIPMENT 2 2.1 PRE-USE FIELD INSPECTION 2 2.2 POSITION FLOAT ON CASING STRING 3 3. RUNNING OF FLOAT EQUIPMENT 3 3.1 CIRCULATION

More information

REPORT GEO-TECHNICAL INVESTIGATION FOR THE PROPOSED BLOCK-1 SUB-STATION SY NO-44, NEAR KYATAGANACHERLU VILLAGE

REPORT GEO-TECHNICAL INVESTIGATION FOR THE PROPOSED BLOCK-1 SUB-STATION SY NO-44, NEAR KYATAGANACHERLU VILLAGE REPORT ON GEO-TECHNICAL INVESTIGATION FOR THE PROPOSED BLOCK-1 SUB-STATION SY NO-44, NEAR KYATAGANACHERLU VILLAGE CLIENT: KARNATAKA SOLAR POWER DEVELOPMENT CORPORATION BANGALORE 0 GEO-TECHNICAL INVESTIGATION

More information

Coal Bed Methane (CBM) Permeability Testing

Coal Bed Methane (CBM) Permeability Testing Coal Bed Methane (CBM) Permeability Testing WTN Network Meeting April 28-29, 2011 ExxonMobil Exploration / Well Testing Team CBM Flow Characteristics Flow mechanism Gas desorbs when pressure drops below

More information

SCORPION HIGH-QUALITY, FULLY COMPOSITE PLUGS

SCORPION HIGH-QUALITY, FULLY COMPOSITE PLUGS SCORPION HIGH-QUALITY, FULLY COMPOSITE PLUGS A DIFFERENT KIND OF ENERGY COMPANY Nine Energy Service isn t your typical oilfield services company. Our success stems from a culture driven by performance

More information

Rig Math. Page 1.

Rig Math. Page 1. Page 1 The Calculator and Main Keyboard Display Numerical 10-key pad used for entering numerical values Trigonometric Functions These keys will be used where wellbore angle is an issue These are the keys

More information

PROPOSED NEW SUB- CODE 1 RIG UP AND TEAR. Possibly Fits into Existing Code. 7/26/2018 Review PROPOSED NEW CODE EXISTING OPERATION

PROPOSED NEW SUB- CODE 1 RIG UP AND TEAR. Possibly Fits into Existing Code. 7/26/2018 Review PROPOSED NEW CODE EXISTING OPERATION NW NW 1 RIG UP AND TAR 1 no sub-code RIG UP AND TAR DOWN Start: Rig released from previous well, nd: Rig fully rigged up, acceptance tests successfully completed, and signed off. DOWN 1 1 Rig Under Tow

More information

FEDERAL ENERGY REGULATORY COMMISSION HDD MONITORING PROGRAM ROVER PIPELINE PROJECT PROJECT DOCKET: CP

FEDERAL ENERGY REGULATORY COMMISSION HDD MONITORING PROGRAM ROVER PIPELINE PROJECT PROJECT DOCKET: CP WEEKLY REPORT NO. 7: REPORT PERIOD: Nov. 5, 2017 Nov. 11, 2017 HDD MONITORING At the request of the Federal Energy Regulatory Commission (FERC), representatives of J.D. Hair & Associates, Inc. (JDH&A)

More information

Striking an underground pipeline or underground electric line can lead to serious injury or death. If you hit either, call (800) , even if

Striking an underground pipeline or underground electric line can lead to serious injury or death. If you hit either, call (800) , even if 1 Striking an underground pipeline or underground electric line can lead to serious injury or death. If you hit either, call (800) 477-5050, even if there is no apparent damage. Call 911 if gas is blowing

More information

Horizontal Directional Drill Contingency and Frac-Out Response Plan. Harpster-Lima Pipeline Project

Horizontal Directional Drill Contingency and Frac-Out Response Plan. Harpster-Lima Pipeline Project Horizontal Directional Drill Contingency and Frac-Out Response Plan Harpster-Lima Pipeline Project March 2016 Horizontal Directional Drill Contingency and Frac-Out Response Plan TABLE OF CONTENTS 1.0 INTRODUCTION...

More information

Along-string pressure, temperature measurements hold revolutionary promise for downhole management

Along-string pressure, temperature measurements hold revolutionary promise for downhole management Along-string pressure, temperature measurements hold revolutionary promise for downhole management IT S WIDELY KNOWN that the majority of stuck pipe incidents occur while pulling out of hole. If we can

More information

HDD Wire Guided Waterway Crossing ATON Plan. Augwick Creek (S-L28)

HDD Wire Guided Waterway Crossing ATON Plan. Augwick Creek (S-L28) HDD Wire Guided Waterway Crossing ATON Plan Augwick Creek (S-L28) Mariner East Phase 2 Pipeline Project Prepared for: Sunoco Pipeline, L.P. 535 Friztown Road Sinking Spring, PA 19608 Prepared by: Tetra

More information

GROUND IMPROVEMENT USING RAPID IMPACT COMPACTION

GROUND IMPROVEMENT USING RAPID IMPACT COMPACTION 13 th World Conference on Earthquake Engineering Vancouver, B.C., Canada August 1-, Paper No. 9 GROUND IMPROVEMENT USING RAPID IMPACT COMPACTION Henrik KRISTIANSEN 1, Michael DAVIES SUMMARY Geotechnical

More information

Stuart River Preliminary HDD Feasibility Assessment Report

Stuart River Preliminary HDD Feasibility Assessment Report Stuart River Preliminary HDD Feasibility Assessment Report 08C7138-PL-RPT-0006, Rev. 3 08-Jun-2010 Enbridge Northern Gateway Project WorleyParsons Canada Services Ltd. Calgary Division 400, 10201 Southport

More information

Step-Rate Formation Integrity Test Method for Geothermal Wells

Step-Rate Formation Integrity Test Method for Geothermal Wells GRC Transactions, Vol. 41, 2017 Step-Rate Formation Integrity Test Method for Geothermal Wells William M. Rickard, Ozgur Balamir and Ernesto Rivas Geothermal Resource Group, Inc. services@geothermalresourcegroup.com

More information

Lecture 8&9: Construction Dewatering

Lecture 8&9: Construction Dewatering Arab Academy for Science, Technology & Maritime Transport Colleague of Engineering & Technology Construction & Building Engineering CB 523 Methods and Equipment for Construction 1 Lecture 8&9: Construction

More information

SAFETY BULLETIN HOSE WHIPPING HOW TO AVOID INJURY BY A HOSE WHIPPING FROM RELEASE OF TRAPPED AIR AMERICAN CONCRETE PUMPING ASSOCIATION

SAFETY BULLETIN HOSE WHIPPING HOW TO AVOID INJURY BY A HOSE WHIPPING FROM RELEASE OF TRAPPED AIR AMERICAN CONCRETE PUMPING ASSOCIATION SAFETY BULLETIN HOSE WHIPPING HOW TO AVOID INJURY BY A HOSE WHIPPING FROM RELEASE OF TRAPPED AIR AMERICAN CONCRETE PUMPING ASSOCIATION WWW.CONCRETEPUMPERS.COM Copyright 2010 v1.01 ACPA All rights reserved

More information

1) INTRODUCTION 2) THE UNFAIR ADVANTAGE

1) INTRODUCTION 2) THE UNFAIR ADVANTAGE 1 1) INTRODUCTION 2) THE UNFAIR ADVANTAGE and Stingray earth anchors are driven tipping plate soil anchors for reaction of tensile loads. anchors have ultimate capacities up to 20 tons, and Stingray anchors

More information

Real Time Data Acquisition and Prediction Model Comparison using Maxi Directional Drills

Real Time Data Acquisition and Prediction Model Comparison using Maxi Directional Drills Real Time Data Acquisition and Prediction Model Comparison using Maxi Directional Drills by Kyle Verwey A thesis presented to the University of Waterloo in fulfillment of the thesis requirement for the

More information

Kiawah Island Utility Directionally Drills Water Main under Wetlands and Kiawah River

Kiawah Island Utility Directionally Drills Water Main under Wetlands and Kiawah River North American Society for Trenchless Technology (NASTT) NASTT s 2017 No-Dig Show Washington, D.C. April 9-12, 2017 TA-T2-01 Kiawah Island Utility Directionally Drills Water Main under Wetlands and Kiawah

More information

Excavations and Trenches

Excavations and Trenches Purpose Excavation and trenching are among the most hazardous work activities undertaken by the TNRD. This document outlines general requirements and specific safe work procedures to ensure the health

More information

An Introduction to Deep Foundations

An Introduction to Deep Foundations An Introduction to Deep Foundations J. Paul Guyer, P.E., R.A. Paul Guyer is a registered mechanical engineer, civil engineer, fire protection engineer and architect with over 35 years experience in the

More information

Safe Excavation & Safety Watch Guidelines

Safe Excavation & Safety Watch Guidelines Safe Excavation & Safety Watch Guidelines For your SAFETY Or call 1-800-940-3447 RELEASE OF NATURAL GAS In the event of any damage to a natural gas pipeline (regardless of whether it is steel, plastic

More information

CONE PENETRATION TESTS

CONE PENETRATION TESTS February 25, 2015 John Doe, P.E. Acme Engineering and Testing 1234 Test Avenue, Suite 204 Lake Wales, FL 33853 Re: Sample CPT Soundings Dear Mr. Doe, Direct Push Services, LLC (DPS) was retained by Acme

More information

New generation of solid expandable liners help give operators a jump on trouble zones

New generation of solid expandable liners help give operators a jump on trouble zones New generation of solid expandable liners help give operators a jump on trouble zones By Pat York, Weatherford SINCE SOLID EXPANDABLE technology has gained credibility as an effective contingency option,

More information

IWCF Equipment Sample Questions (Surface Stack)

IWCF Equipment Sample Questions (Surface Stack) IWCF Equipment Sample Questions (Surface Stack) 1. During a well control operation 4000 psi was shut in below the middle pipe rams. Ram type BOP data: Model: Cameron U type Rated Working Pressure: 15000

More information

PRO-ROD TM COILED ROD. Reduce Maintenance Increase Production Enhance Profit

PRO-ROD TM COILED ROD. Reduce Maintenance Increase Production Enhance Profit PRO-ROD TM COILED ROD Reduce Maintenance Increase Production Enhance Profit DOVER ARTIFICIAL LIFT Elevating the Potential of Artificial Lift Production. Dover Artificial Lift, part of Dover Energy, offers

More information

APPENDIX A 'F' MANITOBA HYDRO REQUIREMENTS

APPENDIX A 'F' MANITOBA HYDRO REQUIREMENTS The City of Winnipeg Appendix A 'F' Bid Opportunity No. 602-2018 Addendum 1 Page 1 of 1 Template Version: C420180312 - RW APPENDIX A 'F' GEOTECHNICAL MANITOBA HYDRO REPORTS GAS REQUIREMENTS Safe

More information

Blasting soft, plastic mineral inside a silo at a copper mine

Blasting soft, plastic mineral inside a silo at a copper mine Blasting soft, plastic mineral inside a silo at a copper mine Benjamin Cebrian ABSTRACT Metallurgical testing at Cobre Las Cruces prior to production at the mill was done with overburden gossan. Some of

More information

TECHNICAL BULLETIN PINPOINT CONDUIT COUPLING AND SPLICING RECOMMENDATIONS

TECHNICAL BULLETIN PINPOINT CONDUIT COUPLING AND SPLICING RECOMMENDATIONS TECHNICAL BULLETIN PINPOINT CONDUIT COUPLING AND SPLICING RECOMMENDATIONS CONTENTS: 1.0 General Information 2.0 Preparation and Splicing of PinPoint Wire 3.0 PinPoint Direct Bury Splice Kit Specifications

More information

TRENCH AND EXCAVATION COLLAPSE

TRENCH AND EXCAVATION COLLAPSE TRENCH AND EXCAVATION COLLAPSE A. GENERAL This guideline provides operational guidance at rescue incidents that involve the location, disentanglement and removal of victims from sub-surface trench and

More information

APPENDIX C VEGETATED EMERGENCY SPILLWAY. VERSION 1.0 March 1, 2011

APPENDIX C VEGETATED EMERGENCY SPILLWAY. VERSION 1.0 March 1, 2011 APPENDIX C VEGETATED EMERGENCY SPILLWAY VERSION 1.0 March 1, 2011 [NOTE: Could use a better photo more clearly showing the emergency spillway in the context of the dam.] SECTION C-1: DESCRIPTION OF PRACTICE

More information

Wapiti River Preliminary HDD Feasibility Assessment Report

Wapiti River Preliminary HDD Feasibility Assessment Report Wapiti River Preliminary HDD Feasibility Assessment Report 08C7138-PL-RPT-0014, Rev. 1 08-Jun-2010 Enbridge Northern Gateway Project WorleyParsons Canada Services Ltd. Calgary Division 400, 10201 Southport

More information

Memo. Lake Elev. (ft) Target Depth (ft) Azi. ( )

Memo. Lake Elev. (ft) Target Depth (ft) Azi. ( ) SRK Consulting (Canada) Inc. 2200 1066 West Hastings Street Vancouver, BC V6E 3X2 T: +1.604.681.4196 F: +1.604.687.5532 vancouver@srk.com www.srk.com Memo To: Will Brits, Wentzel Coetzer Client: Cabot

More information

Basic Mountain Flying

Basic Mountain Flying Advanced Manoeuvres Basic Mountain Flying This training introduces students to the principles of basic mountain flying and further develops their experience and understanding of operating near terrain

More information

OPERATING MANUAL DOUBLE ACTING DRILLING INTENSIFIER HYDRAULIC TYPE

OPERATING MANUAL DOUBLE ACTING DRILLING INTENSIFIER HYDRAULIC TYPE Page 1 of 8 OPERATING MANUAL DOUBLE ACTING DRILLING INTENSIFIER HYDRAULIC TYPE Size Series 6.50" 478 Reviewed And Approved By: Signature: Initials: Date: Page 2 of 8 Section OPERATING MANUAL DOUBLE ACTING

More information

1. The well has been shut in on a kick and the kill operation has not started.

1. The well has been shut in on a kick and the kill operation has not started. Well Control Methods Day 2 1. The well has been shut in on a kick and the kill operation has not started. Shut in drill pipe pressure Shut in casing pressure 500 psi 700 psi After stabilization, both pressures

More information

VII.H. Go-Around/Rejected Landing

VII.H. Go-Around/Rejected Landing VII.H. Go-Around/Rejected Landing References: FAA-H-8083-3; POH/AFM Objectives Key Elements Elements Schedule Equipment IP s Actions SP s Actions Completion Standards The student should develop knowledge

More information

Specialising in: Highly Accurate, Laser-Guided Microtunnels. Sydney Uni PHONE + 61 (2) WEBSITE

Specialising in: Highly Accurate, Laser-Guided Microtunnels. Sydney Uni PHONE + 61 (2) WEBSITE Specialising in: Highly Accurate, WEBSITE The designer (Warren Smith and Partners) had the challenge of getting the sewer from a new development within versity to an old oviform sewer traversing nearby.

More information

Installation and Operation Instruction Manual

Installation and Operation Instruction Manual Installation and Operation Instruction Manual Toggle Lok Anchor - Model #7442 Portable Concrete Anchorage Connector ANSI Z359.1 5,000 lbs / 22.24 kn FallTech, Inc 1306 Alameda Street Compton, CA 90221

More information

DESIGN CRITERIA DIVISION 4900 TRAFFIC SIGNALS

DESIGN CRITERIA DIVISION 4900 TRAFFIC SIGNALS DESIGN CRITERIA DIVISION 4900 TRAFFIC SIGNALS 4901 GENERAL: These criteria shall be adhered to for the design of all publiclyfinanced or privately-financed traffic signal systems to be installed in the

More information

Buoyancy Control Calculated Cost Allowance for 1 Year Study Cost Estimate

Buoyancy Control Calculated Cost Allowance for 1 Year Study Cost Estimate Prepared for Millennium Project Revision A 21 March 2005 by Greg Lamberson Record of Revisions Prepared Rev Date Description By A 21 Mar 05 Buoyancy Control Study Report FGL Checked By Client Accept Approved

More information

Debris Management Drilling Tools

Debris Management Drilling Tools Debris Management Drilling Tools Protecting BHA components during well construction Remove drilling debris from the wellbore before it creates expensive problems. Debris commonly causes downhole tool failure,

More information

GOM Diving Safety Work Group

GOM Diving Safety Work Group GOM Diving Safety Work Group COMMITTEE WORK GROUP Underwater Excavation with Hand Jetting July 14, 2015 DISCLAIMER This US GOM DSWG document is not meant to be all inclusive, and not every rule and regulation

More information

Vacuum Excavation in the vicinity of the Wellington Electricity Network

Vacuum Excavation in the vicinity of the Wellington Electricity Network Vacuum Excavation in the vicinity of the Network. Document no: ENG-116 Document Rev: 1 Issue Status: Final Issue Date: 14/05/2015 Page 1 of 9 Contents 1. PURPOSE... 3 2. POLICY... 3 3. SCOPE... 3 4. REFERENCES...

More information

RIH intermediate section casing in Bazian-1 exploration oil well

RIH intermediate section casing in Bazian-1 exploration oil well Energy and Sustainability V 559 RIH intermediate section casing in Bazian-1 exploration oil well A. K. Darwesh Petroleum Engineering Department, Engineering Faculty, Koya University, Kurdistan Abstract

More information

Cased-Hole Logging Environment

Cased-Hole Logging Environment Cased-Hole Logging Environment 2 Planning a Production Logging Job Planning is an important part of a production logging job. Frequently these jobs can only be done in safety during daylight. Thus, the

More information

IMPACT RING BIT SYSTEM Care & Maintenance Instructions

IMPACT RING BIT SYSTEM Care & Maintenance Instructions IMPACT RING BIT SYSTEM Care & Maintenance Instructions 646 Thompson Road Thompson, CT 06277 USA Phone: +1 (860) 923-9551 Fax: +1 (860) 923-2617 E-mail: numa@numahammers.com www.numahammers.com 2010 Numa

More information

22. Specialty Valves.

22. Specialty Valves. 22. Specialty Valves. a. Types of Specialty Valves. 1) Use of the following specialty valves is covered in this section: Altitude Valve, Pressure Reducing Valve, Pressure Relief Valve, Swing Check Valve,

More information

Civil Application Solutions

Civil Application Solutions Civil Application Solutions Features - Chiseled Cutting Edges - Increased Surface Area - Lateral Direction Guide Ribs Benefits - Faster Installation and Penetrates Harder Soils - Quicker Loading, Stronger

More information

Beavers are particularly adept at manipulating their

Beavers are particularly adept at manipulating their Beavers are particularly adept at manipulating their environment to suit their needs. They instinctively build dams to raise water levels and increase the area covered by water. Beaver ponds provide security

More information

Worked Questions and Answers

Worked Questions and Answers Worked Questions and Answers A Learning Document for prospective Candidates For the Rotary Drilling Well Control Test Programme Copyright, IWCF June 2000 Revision No.1, November 2000 IWCF 2000 page 1 of

More information

INSTALLATION PROCEDURE FOR OPGW FIBER OPTIC CABLES

INSTALLATION PROCEDURE FOR OPGW FIBER OPTIC CABLES Page 1 of 15 INSTALLATION PROCEDURE FOR OPGW FIBER OPTIC CABLES Page 2 of 15 1. PURPOSE 2. SCOPE 3. REFERENCES 4. GENERAL INDEX 5. PROCEDURES 5.1 Line survey 5.2 Transport, loading, unloading and storage

More information

AUTOMATED MONITORING EQUIPMENT FOR ACIP AND DD PILES

AUTOMATED MONITORING EQUIPMENT FOR ACIP AND DD PILES AUTOMATED MONITORING EQUIPMENT FOR ACIP AND DD PILES Presented by: W. Morgan NeSmith, P.E. Berkel & Company Contractors Inc. 770.941.5100 mnesmith@berkelapg.com ANNUAL KANSAS CITY SPECIALTY GEOTECHNICAL

More information

SPECIFICATION FOR CAISSON CONSTRUCTION

SPECIFICATION FOR CAISSON CONSTRUCTION SPECIFICATION FOR CAISSON CONSTRUCTION 1.0 METHOD OF EXCAVATION Caissons shall be hand-excavated, i.e. using of hand-held air tools. Full details of support measures and any dewatering and/or grouting

More information

Casing Design. Casing Design. By Dr. Khaled El-shreef

Casing Design. Casing Design. By Dr. Khaled El-shreef Casing Design By Dr. Khaled El-shreef 1 Casing Design CONTENTS Function of Casing Casing Types & Tools Strength Properties Casing Specification Casing Design 2 1 RUNNING AND CEMENTING CASING Reasons for

More information

COAL SEAM METHANE - EXPLORATION AND PRODUCTION

COAL SEAM METHANE - EXPLORATION AND PRODUCTION COAL SEAM METHANE - EXPLORATION AND PRODUCTION Dr Ian Gray, Principal Sigra Pty Ltd, 72 Donaldson Road, Rocklea, Queensland 4106 Australia. Tel +61 7 3216 6344, Fax +61 7 3216 6988, WWW: www.sigra.com.au

More information

CHAPTER 4: BEST MANAGEMENT PRACTICES FOR EROSION AND SEDIMENTATION CONTROL

CHAPTER 4: BEST MANAGEMENT PRACTICES FOR EROSION AND SEDIMENTATION CONTROL Figure 4.4m. Type III Floating Turbidity Barrier Source: American Boom and Barrier Corporation and Virginia Department of Transportation (DOT) Standard Sheets 71 4.4.6 Floating Turbidity Barrier Definition

More information

Deepwater Horizon Incident Internal Investigation

Deepwater Horizon Incident Internal Investigation Not all Information has been verified or corroborated. Subject to review based on additional information or analysis. Deepwater Horizon Incident Internal Investigation 1 Areas of Discussion Investigation

More information

FATAL AND SEVERE RISK PROGRAM

FATAL AND SEVERE RISK PROGRAM FATAL AND SEVERE RISK PROGRAM LEADER SESSION FALL FROM HEIGHTS Only do the task if it can be done safely FALL FROM HEIGHTS OUR COMMITMENT LIFE SAVING BEHAVIOUR: I WILL ALWAYS USE ADEQUATE PROTECTION WHERE

More information

SITE S7: EMBANKMENT FAILURE WEST OF MILLARVILLE

SITE S7: EMBANKMENT FAILURE WEST OF MILLARVILLE LANDSLIDE RISK ASSESSMENT SOUTHERN REGION SITE S7: EMBANKMENT FAILURE WEST OF MILLARVILLE LEGAL LOCATION: LSD 4-3-21-4 W5M and 1-4-21-4 W5M REFERENCE LOCATION ALONG HIGHWAY The slide area is located between

More information

Item 404 Driving Piling

Item 404 Driving Piling Item Driving Piling 1. DESCRIPTION Drive piling. 2. EQUIPMENT 2.1. Driving Equipment. Use power hammers for driving piling with specified bearing resistance. Use power hammers that comply with Table 1.

More information

CPCS renewal test factsheet

CPCS renewal test factsheet CPCS renewal test factsheet Introduction to the CPCS renewal test The industry-led CPCS Management Committee has determined that key safety-related knowledge must be checked on each category prior to the

More information

Blowout during Workover Operation A case study Narration by: Tarsem Singh & Arvind Jain, OISD

Blowout during Workover Operation A case study Narration by: Tarsem Singh & Arvind Jain, OISD 1. Introduction An incident of gas leakage from a well took place during workover operations. Subsequently, the gas caught fire on the fourth day in which twelve persons were injured. Two contract workers,

More information

ARTICLE. Overcome casing integrity issues in your plug-and-perf operations

ARTICLE. Overcome casing integrity issues in your plug-and-perf operations ARTICLE Overcome casing integrity issues in your plug-and-perf operations CONTENT A challenge to plug-and-perf success 3 Causes of casing restrictions 9 How extended-range frac plugs keep operations moving

More information

ACTIVITY 1: Buoyancy Problems. OBJECTIVE: Practice and Reinforce concepts related to Fluid Pressure, primarily Buoyancy

ACTIVITY 1: Buoyancy Problems. OBJECTIVE: Practice and Reinforce concepts related to Fluid Pressure, primarily Buoyancy LESSON PLAN: SNAP, CRACKLE, POP: Submarine Buoyancy, Compression, and Rotational Equilibrium DEVELOPED BY: Bill Sanford, Nansemond Suffolk Academy 2012 NAVAL HISTORICAL FOUNDATION TEACHER FELLOWSHIP ACTIVITY

More information

APPENDIX A1 - Drilling and completion work programme

APPENDIX A1 - Drilling and completion work programme APPENDIX A1 - Drilling and completion work programme Information about the well and drilling To the extent possible, the international system of units (SI) should be adhered to, and the drilling programme

More information

ITEM 400 STRUCTURAL EXCAVATION AND BACKFILL

ITEM 400 STRUCTURAL EXCAVATION AND BACKFILL AFTER MARCH 1, 2012 ITEM 400 STRUCTURAL EXCAVATION AND BACKFILL 400.1 Description. This item shall govern for all excavation required for the construction of all structures, except pipe or box sewers for

More information

This section applies to all open excavations made in the earth's surface. Excavations are defined to include trenches.

This section applies to all open excavations made in the earth's surface. Excavations are defined to include trenches. Appendix H Specific Excavation Requirements This section applies to all open excavations made in the earth's surface. Excavations are defined to include trenches. Surface encumbrances All surface encumbrances

More information