CONCEPT STUDY. Kasold Drive Improvements (6th Street to Bob Billings Parkway) Lawrence, Kansas PREPARED FOR

Size: px
Start display at page:

Download "CONCEPT STUDY. Kasold Drive Improvements (6th Street to Bob Billings Parkway) Lawrence, Kansas PREPARED FOR"

Transcription

1 CONCEPT STUDY Kasold Drive Improvements (6th Street to Bob Billings Parkway) Lawrence, Kansas PREPARED FOR City of Lawrence, Kansas Public Works Department July 2015 PREPARED BY: CFS Lawrence 2121 Moodie Road Lawrence, Kansas Topeka Lawrence Wichita Kansas City Branson Springfield Jefferson City

2 TABLE OF CONTENTS STAKEHOLDER TEAM CONSULTANT TEAM EXECUTIVE SUMMARY SECTION 1. INTRODUCTION Project Approach Goals and Objectives SECTION 2. PROJECT INFORMATION Project Area Existing Conditions Existing Utilities Design Criteria Related Studies and Work Product SECTION 3. ALTERNATIVES OVERVIEW, EVALUATION & SUMMARY Complete Streets Option Typical Street Reconstruction Option Intersections Kasold & 8th Pavement and Subgrade Waterline Replacement and Extension of Shared Use Path Utility Relocation Phasing, Traffic Control, Landscaping and Street Lighting Cost Estimates Community Outreach Conclusions SECTION 4. REFERENCES APPENDIX A - PRELIMINARY CONCEPT PLANS APPENDIX B - COST ESTIMATES APPENDIX C - EVALUATION OF OPTIONS LIST OF TABLES Peak Hour Traffic Volumes Traffic Travel and Delay Times LIST OF FIGURES Principles of Smart Transportation Smart Transportation Planning Ideal Site Vicinity Map and Study Area Page 1

3 Stakeholder Team City of Lawrence, KS Jeremy Farmer, Mayor Leslie Soden, Vice-Mayor Mike Amyx, City Commissioner Stuart Boley, City Commissioner Matthew Herbert, City Commissioner Charles Soules, PE, Public Works Director David Cronin, PE, City Engineer Steve Lashley, PE, Pavement Engineer David Woosley, PE, Traffic Engineer Mike Lawless, PE, Asst. Director of Utilities Captain Chris King, IAAI-CFI, Lawrence Fire Medical Department Crystal Miles, Horticulturalist Jeanne Pees, Sunset Hills Neighborhood Association Carolyn Crawford, Sunset Hills Neighborhood Association Ron May, Director of Administrative Services, USD 497 Wayne Zachary, Manager, First Student (Busses) Adjacent/Affected Residents Adjacent/Affected Commercial Business Owners Consultant Team CFS Engineers Lance Scott, PE, Principal-in-Charge Aaron Gaspers, PE, Project Manager Katherin Steinbacher, PE, Public Involvement Bill Stafford, PE, Geotechnical Engineer Tom Ingram, PE, Traffic Engineer Andrew Robertson, Traffic Engineer Mike Adams, PLS, Survey Grob Engineering Dean Grob, PE FTE, Inc. Kevin Vogt, LA Latimer, Sommers & Associates Dave Everhart, PE, LEED-AP Page 2

4 EXECUTIVE SUMMARY This concept study utilizes the Principles of Smart Transportation to evaluate the impacts of complete reconstruction of Kasold Drive from 6th Street to Bob Billings Parkway with: the Complete Streets Option - including lane reconfiguration, from four to two lanes, along Kasold from 14th Street to 8th Street, with construction of a roundabout at intersection of Harvard and Kasold, and the Typical Street Reconstruction Option - maintaining the four-lane section along Kasold with installation of a traffic signal at intersection of Harvard and Kasold. Both alignment options include a median with center left turn lanes when necessary, designated bike lanes on both sides, a sidewalk on the east side and a shared use path on the west side. Construction of a 20 wide pavement section in each direction or construction of a mountable median would be implemented to ensure emergency access as well as to enable ease of access for postal, garbage/recycling and street cleaning services. Various concepts for improving the intersection of 8th & Kasold were evaluated, including maintaining stop signs, constructing roundabout, installing traffic signal, installing pedestrian signal, and eliminating left turn movements. Costs and feasibility for replacement of the water distribution system along Kasold Drive and the extension of the shared use path along Kasold Drive north to Peterson Road were also evaluated. The options selected for study were chosen in an attempt to incorporate the City s 2012 Complete Streets Policy ( streets that are planned, designed and operated to enable efficient and safe access for all users--pedestrians, bicyclists, motorists and transit riders of all ages and abilities) as well as to evaluate the recent transition many similar communities have made in instituting calmer, safer, and more livable streets. A budget of approximately $5M was identified for all phases of this project (not including the proposed waterline replacement). Additional Federal-Aid funding sources were identified in the amount of $400,000 to offset the costs associated with design and construction of a round-a-bout at the intersection of Kasold Drive and Harvard Road. This study finds that Kasold Drive, between Bob Billings Parkway and 6 th Street, is a critical link in the City s transportation infrastructure and that the existing pavement has exceeded its current service life and requires full replacement. All options evaluated increase the level of service of the existing roadway and intersections. All options decrease vehicle travel time for the project corridor. The Complete Streets Option appears to present the most benefits and the least disadvantages while providing the most cost savings, allowing potential inclusion of the extension of the shared use path north along Kasold Drive to Peterson Road. Replacement of the water distribution system as part of this project is recommended. Page 3

5 SECTION 1. INTRODUCTION PROJECT APPROACH In March 2015 the City of Lawrence engaged CFS Engineers to prepare a concept study for improvements to Kasold Drive from 6 th Street to Bob Billings Parkway (BBP). Throughout the process the Stakeholder Team and the Consultant Team served to implement the Principles of Smart Transportation as listed in the graphic to the right. This process provides the foundation for balancing competing interests and needs against various options for improvement and employs significant public involvement, including the following qualities and characteristics: An open, honest and transparent decision-making process conducted through constructive two-way communication between the project team and the public. Early opportunities for stakeholders to share values, understand the study area, develop potential solutions and raise issues and concerns to be considered by the project team. Proactively inform and encourage the participation of stakeholders. Build widespread community understanding of opportunities, constraints, findings and decisions. Implement a process driving ownership, validity and commitment to the development of solutions. Principles of Smart Transportation The context of the Kasold Drive Concept Study is described through the various components of the Smart Transportation Planning Ideal as outlined in the graphic to the left. Each component s relevance to the project was considered in the analysis of each alternative. Smart Transportation Planning Ideal Page 4

6 GOALS AND OBJECTIVES The purpose of this study was to evaluate the following: 1. Impacts of complete reconstruction of the roadway with: The Complete Streets Option: Lane reconfiguration, from four to two lanes, along Kasold from 14th Street to 8th Street, with construction of a roundabout at intersection of Harvard and Kasold The Typical Street Reconstruction Option: A four-lane section along Kasold with installation of a traffic signal at intersection of Harvard and Kasold 2. A sustainable sub-grade and pavement section that will minimize construction costs while providing for the longest service life for the new roadway. 3. Costs and feasibility for: Various concepts for improving the intersection of 8th & Kasold, including maintaining stop signs, constructing roundabout, installing traffic signal, installing pedestrian signal, eliminating left turn movements Replacement of the water distribution system along Kasold Drive Extension of the shared use path along Kasold Drive north to Peterson Road Each typical section being evaluated included a median with center left turn lanes when necessary, designated bike lanes on both sides, a sidewalk on the east side and a shared use path on the west side. Reconstruction of the intersection of Kasold Drive and Bob Billings Parkway was also included in both options while neither option included replacement of the intersection of Kasold Drive and 6th Street. The options selected for study were chosen in an attempt to incorporate the City s 2012 Complete Streets Policy ( streets that are planned, designed and operated to enable efficient and safe access for all users--pedestrians, bicyclists, motorists and transit riders of all ages and abilities) as well as to evaluate the recent transition many similar communities have made in instituting calmer, safer, and more livable streets (refer to related studies in References section). A budget of approximately $5M was identified for all phases of this project (not including the proposed waterline replacement which would be funded through the City s Utilities Department). Additional Federal-Aid funding sources were identified in the amount of $400,000 to offset the costs associated with design and construction of a round-a-bout at the intersection of Kasold Drive and Harvard Road. Page 5

7 SECTION 2. PROJECT INFORMATION Site Vicinity Map and Study Area PROJECT AREA The project area includes an approximately mile long stretch of Kasold Drive located between Bob Billings Parkway on the south end and 6th Street on the north end. Kasold Drive is one of the most used north-south arterials in Lawrence, second only to Iowa Street. The surrounding vicinity is an established residential area with commercial and office areas along 6 th Street and along 15 th / Bob Billings Parkway (BBP). The area surrounding this segment of Kasold between 6 th and BBP has been fully developed for over twenty-five years. Kasold Drive south of the Bob Billings Parkway has been recently reconstructed all the way to the 31st Street curve incorporating a four-lane road section with a shared use path. EXISTIING CONDITIONS Existing Kasold Drive Page 6

8 Existing Kasold Drive is a four-lane roadway with curb and gutter and a raised grass median that was originally constructed in The northbound and southbound sides are set at different crown elevations with individual cross slopes. The associated geo-technical report identifies the pavement as un-reinforced concrete with an asphalt overlay and no known sub-grade treatment. The existing pavement has significant cracking and rutting and has been milled, overlaid and patched multiple times and has failed in many locations. The existing stormwater collection and conveyance system includes inlets along the eastern and western sides of the roadway as well as within the median, necessitated by the differing crown elevations and individual cross slopes of the northbound and southbound sides of the roadway. The locations of existing inlets and stormwater piping are represented graphically on the plan sheets located in the appendices. The associated geotechnical report identifies site soils as mainly consisting of fat clays with little or no evidence of rock. The current traffic counts along the project site are as shown below. Kasold Drive - 14,735 vehicles per day (VPD) Harvard Road - 3,035 VPD Intersection of Kasold and Harvard - 17,902 VPD Between the City of Lawrence and the University of Kansas, the area appears to be well-served by public transportation; several City and University busses were observed during traffic counting sessions. The western side of Kasold has continuous sidewalks extending all the way from 6 th Street to Bob Billings Parkway to accommodate pedestrians and there are no existing bicycle lanes along Kasold. EXISTING UTILITIES For the purpose of this concept study existing utilities were investigated using field observation and utility maps obtained from the City of Lawrence and local utility companies. Field locates were not made and more detailed information will be obtained during the full topographic survey of the project prior to the commencement of design. From the information collected the following utilities were observed: Page 7

9 Westar Overhead power - Overhead power lines can be seen along the west side of Kasold Drive. City of Lawrence Water - 8 cast iron waterline (circa 1960 s) along Kasold under southbound driving lane from 6th St. to Yale, 12 cast iron waterline (circa 1960 s) along Kasold under the median south of Yale City of Lawrence Sanitary Sewer - Sanitary lines outside of the existing right-of-way on the north end of the corridor, crossing Kasold just south of 6th St. Black Hills Energy AT&T WOW Cable Fiber Optic Existing Utilities, Kasold Drive The locations of these utilities are represented graphically on the preliminary plan sheets located in the appendices. These locations are provided for informational purposes only and have been obtained directly from maps and information provided by the respective utility company. DESIGN CRITERIA The following design criteria was used for completion of this study: City of Lawrence, Kansas Design Criteria, Standard Technical Specifications and Standard Detail Sheets, 2015 City of Lawrence, Kansas Complete Streets Policy, 2012 City of Lawrence, Kansas, Lawrence-Douglas County Metropolitan Planning Organization, Kansas Transportation 2040, 2013 (T2040) Kansas Department of Transportation Standard Specifications for Road and Bridge Construction, 2007 T2040 traffic predictions utilized a 59% increase over current traffic levels or, in other words, a growth rate of 1.56% increase in traffic every year. It was determined that this appeared to be unrealistic for a fully developed arterial street; therefore City staff and the Consultant team agreed upon a growth rate of approximately 0.5% per year to establish projected traffic volumes. These projections are believed to provide conservative estimates that will serve to incorporate any alterations to traffic due to the construction of the final portion of the South Lawrence Trafficway as well as the construction of the new interchange for the western extension of Bob Billings Parkway. RELATED STUDIES AND WORK PRODUCT The following related studies and surveys were used for the completion of this study: Traffic Impact Study, Kasold Drive Improvements, 6 th Street to 15 th Street/Bob Billings Parkway, 2015, CFS Engineers, Lawrence, KS Geotechnical Investigation and Study, Kasold Drive Improvements, 6 th Street to 15 th Street/Bob Billings Parkway, 2015, CFS Engineers, Lawrence, KS Page 8

10 Topographical Survey, Kasold Drive (6 th Street to 15 th Street/Bob Billings Parkway), completed 2015, CFS Engineers, Lawrence, KS The website found at the following URL has been designed and is being managed in order to offer information about this project and its progress and to facilitate public input. This is the first ever project-specific website utilized by the City of Lawrence Public Works Department. This website serves as a format for the public to voice opinions, comments and questions and will be managed throughout the project life-cycle to provide real time updates of progress and construction/traffic control information. Website, Kasold Drive Improvements, 6 th Street to 15 th Street/Bob Billings Parkway kasolddrive.com Page 9

11 SECTION 3. ALTERNATIVES OVERVIEW, EVALUATION & SUMMARY Various alternatives were considered for this project, including: The options selected for study were chosen in an attempt to incorporate the City s 2012 Complete Streets Policy ( streets that are planned, designed and operated to enable efficient and safe access for all users--pedestrians, bicyclists, motorists and transit riders of all ages and abilities). The current and projected annual daily traffic and peak hour traffic volumes for this project corridor fall within the range of volumes in which similar communities have successfully instituted transitions to calmer, safer, and more livable streets by constructing lane reconfiguration and geometric intersection improvement projects. Utilizing the above information, two alternatives were considered for the length of the new roadway. They include: The Complete Streets Option: Lane reconfiguration, from four to two lanes, along Kasold from 14th Street to 8th Street, with construction of a roundabout at intersection of Harvard and Kasold The Typical Street Reconstruction Option: A four-lane section along Kasold with installation of a traffic signal at intersection of Harvard and Kasold Both options include a median with center left turn lanes when necessary, designated bike lanes on both sides, a sidewalk on the east side and a shared use path on the west side. THE COMPLETE STREETS OPTION Lane Reconfiguration A two-lane section was proposed for Kasold Drive between the intersections of 14 th Street and 8 th Street. The areas south of 14 th Street and north of 8 th Street would remain four lanes, similar to the existing street. The section would consist of two 12 feet wide lanes and the inclusion of an 8 feet wide center median which would easily allow for designated left turn lanes when necessary without any need for lane shifting, constructing pavement within the median only when necessary for turn lanes. The section would be crowned at the median, therefore eliminating the need for inlets at the median and reducing the amount of storm sewer required. In discussions with Fire Medical staff, two options were identified that would help to ensure emergency access: 1) maintaining a minimum of 20 of pavement from toe of curb to toe of curb in each direction, 2) the construction of mountable median curb. The raised median could also be completely eliminated and a full length center turn lane constructed - this option would entail higher pavement costs and would provide a lower level of safety by removing pedestrian refuge areas and allowing adjacent property owners to make left turns into driveways. The Complete Streets Option allows for the use of five feet wide bike lanes (these are usually only four feet wide), providing more room and increasing safety for bicycle traffic from vehicle traffic and obstacles such as curb inlets. The narrower nature of this proposed roadway allows for minimization of the need to acquire additional rights-of-way and/or easements resulting in probable cost savings. This narrower section also greatly reduces the need for relocation of existing utilities, minimizing disruption to surrounding residents and providing additional cost savings. An improvement in traffic flow and a general reduction in vehicle speed were identified while no significant increases in delay for the project corridor were identified with this option. Page 10

12 Several published studies and papers outline the benefits of conversion of a four- lane, undivided roadway to a three- lane roadway with a center left turn lane and present examples of locations where successful conversions have taken place. These studies found that this lane-reconfiguration resulted in better traffic flow, no significant increase in delay and a significant decrease in vehicle collisions. The lane-reconfigurations resulted in a general reduction of congestion and vehicle speed, and improvement of safety. Several studies document examples where successful conversions have taken place on roadways with Average Daily Traffic (ADT) ranges of 10,000 to 25,000 vehicles (see References Section). These studies also illustrated an increase in bicyclist and pedestrian safety as the three- lane facilities provided refuge allowing crossing bicyclists and pedestrians to focus on one lane of traffic at a time. In addition to those provided in the aforementioned studies, the following locations provide examples a little closer to home. Haskell Avenue, from 23rd to 31st: This roadway is striped as a two-lane road with a center turn lane and has similar traffic volumes to the studied section of Kasold. 9th Street, from Emery to Mississippi: This roadway was recently re-striped from a four-lane roadway to a two-lane road with a center left turn lane and bike lanes and has similar traffic volumes to the studied section of Kasold. Haskell Avenue, south of 23rd 9th Street, east of Emery Each of these converted roadways function well and exhibit the positive benefits identified in the studies discussed above. The existing traffic signals along 9th Street actually decrease the flow of traffic along this stretch - indicating that Kasold Drive would function at an even more efficient level than 9th Street. Round-a-bout at Kasold and Harvard In the proposed Complete Streets Option improvements, the existing intersection at Kasold and Harvard would be reconstructed as a roundabout. This option would increase the level-of-service (LOS) ratings for all directions of the intersection to LOS A (the best). On the southeastern quadrant of the roundabout, an additional northbound right-turn lane would be added to improve the turning movements around the sharp corner. The center of the roundabout would be shifted north to provide increased clearance for the existing residential driveway on the southwest quadrant (the existing driveway location is approximately 25' south of Harvard's south curb-line). Even with the reduction in lanes from four to two, traffic modeling actually showed improved capacity over the existing stop-controlled intersection at Harvard Road, with the ability of the roundabout to keep traffic in constant motion without having to stop. While the skewed nature of the intersecting streets creates a Page 11

13 challenge to the geometric layout of a round-a-bout, the layout presented balances both the realignment of the intersection and the need for additional rights-of-way acquisition. Round-a-bouts also have zero operating costs compared to traffic signals which require regular maintenance and attention along with equipment upgrades. Preliminary plan sheets for the construction of a round-a-bout at this intersection can be found in Appendix A. A study conducted by Persaud, Retting, Garder and Lord evaluated the changes in motor vehicle crashes following conversion of 23 intersections from stop sign and traffic signal control to modern roundabouts. The study found highly significant reductions in both vehicle collisions (40% reduction) and injury crashes (80% reduction). The reasons provided for the increased safety level at roundabouts are as follows: Roundabouts have fewer conflict points in comparison to conventional intersections. They completely eliminate right angle crashes and left turn head on crashes. Roundabouts with single- lane approaches have fewer potential conflicts between vehicles and pedestrians due to short crossing distances thereby producing greater safety benefits than roundabouts with multi-lane approaches. Since the approach speeds and circulating speeds in roundabouts are low they give drivers more time to react to potential conflicts, thus helping to improve the safety performance of roundabouts. Due to low relative speeds, crash severity can be reduced compared to some traditionally controlled intersections. Pedestrians must concentrate on only one direction of traffic at a time, at each approach, as they traverse roundabouts, when compared to un -signalized intersections. Conflict points between vehicles and pedestrians are generally not affected by the presence of a roundabout. $400,000 in Federal-Aid Highway Safety Improvement Program Funds has been identified as an additional funding source for construction of a round-a-bout at this intersection, providing the most cost effective solution by far. If these funds are utilized it would be necessary to prepare and submit a separate set of plans to the Kansas Department of Transportation (KDOT) for review and approval. This would entail minimal additional costs to the design phase of the project. Preliminary plan sheets for the Complete Streets Option can be found in Appendix A. Traffic count tables and diagrams can be found in the related Traffic Study. The cost estimate for the Complete Streets Option is significantly less than for the Typical Street Reconstruction Option, mainly due to the inclusion of lesser pavement quantities in this design and the exclusion of costly traffic signal equipment. TYPICAL STREET RECONSTRUCTION OPTION Four-Lane Section The proposed option for the four-lane section would reduce the existing lane widths to 11 feet and reduce the existing median width to 7 feet. This would allow for the addition of five foot bike lanes in both directions while maintaining the same total width of street as currently exists. The roadway would be crowned at the median, therefore eliminating the need for inlets at the median and reducing the amount of storm sewer required. No increase in delay was identified for this option. traffic with faster motorists passing slower drivers. This configuration would be less conducive to calming Acquisition of temporary construction easements would Page 12

14 be necessary to construct this option, and it is probable that additional easements and/or rights-of-way would need to be obtained. Traffic Signal at Kasold and Harvard For the proposed Typical Street Reconstruction Option improvements, the intersection of Kasold and Harvard would be fully signalized with new north and southbound left-turn lanes constructed in the center median. Signalizing this intersection would increase the level-of-service (LOS) ratings for all directions of the intersection to LOS A (the best). The north and southbound left-turns would be permitted and protected. The east and west legs would remain single lanes due to right-of-way restrictions with the established homes fronting Harvard Road. The delays, level-of-service ratings and queue lengths for vehicles stopped at intersections would improve th over the existing conditions while a coordinated signal system with the existing signalized intersections at 6 Street and at Bob Billings Parkway would accommodate motorists by cutting down on stops at intersections. The Typical Street Reconstruction Option provides the highest construction cost due mainly to the increased pavement quantities and traffic signal equipment costs. Preliminary plan sheets for the Typical Street Reconstruction Option can be found in Appendix B. count tables and diagrams can be found in the related Traffic Study. Traffic INTERSECTIONS The associated traffic study finds that the intersections at Kasold Drive and Bob Billings Parkway and Kasold Drive and 6 th Street function well as currently configured and no geometric improvements are recommended. This project proposes to fully reconstruct the intersection of Kasold and Bob Billings Parkway which provides an excellent opportunity to complete the proposed waterline crossing at the same time. This project will tie in to the existing section at the south curb return of the intersection of 6th St. and Kasold; the proposed waterline crossing would be bored under 6th St. All other intersections, with the exception of Kasold Drive and 8 th Street (which is discussed below) will incorporate designated left turn lanes with both options. As discussed above, no significant increase in delays were identified with either option. KASOLD AND 8TH STREET The associated traffic study identified that the intersection of Kasold & 8th warrants improvements to achieve an increase in level of service The accident history of this intersection is also an extremely sensitive topic that engenders high emotions in surrounding residents. Various alternatives for improvement were considered, including: maintaining the existing three-way stop construction of a round-a-bout removal of stop signs installation of a traffic signal installation of a pedestrian crossing signal elimination of left-turn movements Three-Way Stop at Kasold and 8 th Street If the intersection of 8 th & Kasold were to remain a three-way stop configuration, as modeled with Option 2 in the associated Traffic Study, the addition of a southbound left-turn lane to the median is recommended to Page 13

15 help facilitate the relatively high number of movements (129 vehicles per hour (VPH) during the AM peak hour and 90 VPH during the PM peak). A right turn lane is not practical due to right-of-way constrictions and the location of the existing house and driveway on the southeast corner. Round-a-bout at Kasold and 8 th Street This option, modeled with Option 1 in the associated Traffic Study, would reconstruct the existing intersection as a roundabout. This option would increase the level-of-service (LOS) ratings for all directions of the intersection and improve the values for all approaches over the existing three-way stop conditions. Construction of this option would require significant acquisition of additional rights-of-way. Signalization at Kasold and 8 th Street Signalizing this intersection would increase the level-of-service (LOS) ratings for all directions and improve the values for all approaches over the existing three-way stop conditions. This option could also incorporate pedestrian crossing signals for walkers and schoolchildren going to and from Sunset Hill Elementary School, located further east on 8 th /9 th Street. If the existing three-way stop-control intersection were modified to remove the northbound and southbound stops and add only a pedestrian crossing signal the values for delays and LOS for the remaining stop-controlled westbound approach would suffer considerably. The westbound approach LOS would drop by one rating point for both the AM and PM peak hour conditions, and the corresponding delays would nearly double over the existing conditions. Elimination of left turn movements at Kasold and 8 th Street If the proposed median along Kasold were carried through this intersection, left turning movements could be eliminated for the south bound traffic on Kasold as well as the west bound traffic on 8th Street. While this option was not modeled, it would be anticipated that this would most likely increase LOS ratings for the intersection. TRAVEL TIME ANALYSIS The associated traffic study calculated the travel times for vehicles along Kasold Drive between 6th Street and Bob Billings Parkway. The following table summarizes the travel times for both northbound and southbound passenger vehicles. Tr avel Times along Kasold Dr ive between 6th Str eet and Bob Billings Par kway Pre-Development (minutes) NB - SB - Total Complete Streets Option (minutes) NB - SB - Total Typical Street Stop Signs at 8th (minutes) NB - SB - Total Typical Street Signal at 8th (minutes) NB - SB - Total AM Peak - Current PM Peak - Current AM Peak PM Peak Page 14

16 As this table illustrates, all options studied exhibit decreased travel times as compared to existing conditions. PAVEMENT AND SUBGRADE In order to improve the sustainability of the roadway section the associated geotechnical report identified the following design alternatives for consideration for both the pavement and the sub-grade preparation: City standard concrete pavement Structurally equivalent thickness of pervious pavement City standard fly ash treated sub-grade Structurally equivalent thickness of recycled crushed pavement sub-base Subgrade and Pavement Recommendations It is possible that the inclusion of pervious pavement would help to reduce stormwater runoff and therefore minimize sizes of inlets and stormwater piping. While this could result in minor cost savings and environmental benefit, we would not recommend the use of pervious pavement for this project. The costs of maintenance requirements associated with ensuring optimum performance of the pavement would far outweigh the possible initial savings while the soils present on site are not ideal for the pervious pavement option. No need for underdrain was identified as the field investigation found little or no evidence of rock or ground water. The City of Lawrence standard KCMMB concrete section is recommended for this project along with a sub-grade preparation recycling the existing pavement into crushed aggregate base. This allows for a significant cost savings over fly ash treated sub-grade and adds environmental benefit by re-using the existing roadway rather than wasting and landfilling it. WATERLINE REPLACEMENT AND EXTENSION OF SHARED USE PATH The following two items have also been investigated for inclusion into this project: Replacement of the water distribution system along Kasold Drive Extension of the shared use path along Kasold Drive north to Peterson Road Waterline Replacement Replacement of the existing water distribution system has been identified as a priority by the City of Lawrence Utilities Department. It has been proposed that this utility work be included in the scope of the Kasold Improvements project. A new 12 watermain would be installed at a probable location behind the proposed eastern curb. All cross street lines would be up-sized, if needed, to 8" within Kasold right-of-way and reduced to connect to existing main sizes. Existing services and hydrants would be adjusted to connect to the new watermain. 6th Street would be crossed (bored) to connect to the existing 12" main that runs east-west on the north side of 6 th St. Bob Billings would be crossed to connect to the existing 12" main that runs east-west on the south side of Bob Billings. This work would be funded by the City Utilities Department, separate from the other project costs. Page 15

17 Inclusion of the waterline replacement work with the Kasold improvements project would offer the following benefits: prevent the removal and replacement of new pavement which would occur if the waterline were replaced after the Kasold project were complete minimize ongoing disruption to adjacent property owners as the road project will be fully reconstructing the intersection of Kasold and Bob Billings Parkway it provides an excellent opportunity to complete this waterline crossing at the same time The preliminary plan sheets found in the appendices illustrate the proposed location of the new water main. Extension of Shared Use Path In order to extend pedestrian traffic to the north of this corridor the option of extending the shared use path along Kasold north to Peterson Road for a little over a mile was identified. Inclusion of this option in this project would entail relatively minor amounts of additional survey and design time and could be accomplished if the monies remain available in the budget after the completion of the previously discussed road improvements. It is most likely that this option would be able to be included in this project only if the Complete Streets Option were selected due to estimated construction costs. UTILITY RELOCATION The necessity for relocation of existing utilities appears to be minimal for the options and alternates investigated (with the exception of the waterline replacement project discussed above). Impacts to sanitary sewer would be minimal with only the adjustment of existing manholes anticipated. Some moderate work to the existing sanitary system may be required if the round-a-bout option is constructed at 8 th & Kasold. PHASING, TRAFFIC CONTROL, LANDSCAPING AND STREET LIGHTING No matter which alternates or options are eventually selected, this project will entail challenges in operation and phasing during construction. A detailed phasing plan and a traffic control plan will be produced during the design phase that will ensure that access to residences, businesses and properties would be maintained at all times. Design plans will also include landscaping, irrigation and street lighting plans. COST ESTIMATES Preliminary costs were developed for each option. The cost estimates can be found in Appendix B. Costs were estimated for both options as well as for the separate alternates for 8th Street and for the waterline replacement and the extension of the shared use path north to Peterson. For each estimate, unit prices are based on 2015 values. The costs shown on the estimates represent an estimate of probable costs prepared in good faith and with reasonable care. CFS Engineers has no control over the costs of construction labor, materials or equipment, nor over bidding and negotiating methods and does not make any commitment or assume any duty to assure that final costs will not vary from this estimate. Cost estimates are for construction costs only and do not include the costs of engineering design, right-of-way acquisition, utility relocation, construction inspection or administration. COMMUNITY OUTREACH MEETINGS Public Outreach Meeting A public outreach meeting was held on Wednesday, May 27, 2015 from 7:00PM until 9:00PM at Christ Community Church located at 1100 Kasold Drive. Members of City staff and the Consultant team began by presenting the project goals, and the studied options. Preliminary plan sheets and a video were presented Page 16

18 and attendees were given time to review the presentation materials and have informal discussions with project team members. Several attendees asked questions and made comments regarding issues including, but not limited to, the associated traffic study, roundabouts, traffic flow along Kasold, bike lanes and shared use paths, street lighting and the accident history at 8th & Kasold. The project s website was unveiled at kasolddrive.com - the City s first ever project specific website for a Public Works project. Comment cards were also available for attendees to fill out. WOW 6 news was in attendance and interviewed several attendees. Public input that has been received as of the date of publication of this study has been compiled and summarized. Commercial Business Owner Meeting A meeting with affected commercial business owners was held on Tuesday, July 7, 2015 from 2:00PM to 3:00PM at University National Bank located at 1400 Kasold Drive. Members of City staff and the Consultant team began by presenting the project goals, and the studied options. Preliminary plan sheets and a video were presented and attendees were given time to review the presentation materials and have informal discussions with project team members. Several attendees asked questions and made comments regarding issues including, but not limited to, access during construction, project schedule, the associated traffic study, traffic flow and previous construction projects along Kasold Drive. Presentations to additional community organizations are also anticipated. This study will be presented to the Lawrence City Commission on a future agenda with additional opportunity for public comment. CONCLUSIONS Kasold Drive, between Bob Billings Parkway and 6 th Street is a critical link in the City s transportation infrastructure. The existing pavement has exceeded its current service life and requires full replacement. All options evaluated increase the level of service of the existing roadway and intersections. Neither option negatively affects travel or delay times within the corridor. The Complete Streets Option appears to present the most benefits and the least disadvantages while providing the most cost savings, allowing potential inclusion of the extension of the shared use path north along Kasold Drive to Peterson Road. Replacement of the water distribution system as part of this project is recommended. Page 17

19 SECTION 4. REFERENCES New Jersey Department of Transportation & Pennsylvania Department of Transportation. Smart Transportation Guidebook. March City of Lawrence, Kansas Design Criteria, Standard Technical Specifications and Standard Detail Sheets, 2015 City of Lawrence, Kansas Complete Streets Policy, 2012 City of Lawrence, Kansas, Lawrence-Douglas County Metropolitan Planning Organization, Kansas Transportation 2040, 2013 (T2040) Kansas Department of Transportation Standard Specifications for Road and Bridge Construction, 2007 CFS Engineers, Traffic Impact Study, Kasold Drive Improvements, 6 th Street to 15 th Street/Bob Billings Parkway, 2015 CFS Engineers, Geotechnical Investigation and Study, Kasold Drive Improvements, 6 th Street to 15 th Street/Bob Billings Parkway, 2015 Knapp, K.K., Welch, T.M. and Witmer, J.A., Converting Four Lane Undivided Roadways to a Three-Lane Cross Section: Factors to Consider, ITE Annual Meeting,1999. Knapp, Chandler, et al. for the Federal Highway Administration, Road Diet Informational Guide, 2014 Kansas City Missouri Public Works Department, Road Diet Analysis, 2015 Russell & Mandavilli for Kansas State University, Analysis of a Road Diet Conversion and Alternative Traffic Controls, 2003 AARP and the Walkable and Livable Communities Institute, Road Diets - A Livability Fact Sheet, 2014 Burden, D. and Lagerwey, P., Road Diets: Fixing the Big Roads, Walkable Communities, Inc., March Walkable Streets (August 2003), Economic Merits of Road Diets and Traffic Calming Safe Routes to School National Center (November 2013), Safe Routes to School Online Guide crossing_distances_for_pedestrians.cfm#diet Page 18

20 APPENDIX A Preliminary Conceptual Plans

21 Complete Streets Typical 56' Back to Back STA TO STA STA TO STA LANE (NOT TO SCALE) Typical Street Reconstruction Typical 69' Back to Back STA TO STA STA TO STA LANE (NOT TO SCALE) Kasold Drive Improvements Lawrence, KS Street, Storm & Waterline Improvements EXISTING KASOLD DRIVE 4 LANE (NOT TO SCALE) 2

22 APPENDIX B Preliminary Estimates of Probable Construction Costs

23 ENGINEER'S OPINION OF PROBABLE CONSTRUCTION COST Kasold Drive, Bob Billings to 6th Street Lawrence, Kansas Typical Street Reconstruction Option ITEM DESCRIPTION UNIT Total UNIT PRICE Total Street, Storm & Waterline 1 Site Preparation L.S. 1 $50, $50, Unclassified Excavation C.Y. 15,000 $5.00 $75, Compaction of Earthwork C.Y. 15,000 $3.00 $45, " Concrete S.Y. 38,975 $60.00 $2,338, Flyash S.Y. 44,043 $4.50 $198, Curb & Gutter L.F. 14,359 $14.00 $201, ' Sidewalk L.F. 4,575 $18.50 $84, ' Shared Use Sidewalk L.F. 5,600 $26.50 $148, Ramps EA. 54 $1, $59, " RCP L.F. 1,095 $50.00 $54, " RCP L.F. 1,006 $55.00 $55, " RCP L.F. 252 $65.00 $16, " RCP L.F. 35 $80.00 $2, Curb Inlets EA. 19 $3, $60, Junction Box w/ Type II R & C EA. 8 $3, $30, Connect Proposed Inlets to Ex Pipe EA. 5 $ $4, " Nominal Dia. Rip-Rap S.Y. 100 $30.00 $3, Flowable Fill C.Y. 675 $69.00 $46, Remove Existing Inlets EA. 34 $1, $40, Remove Existing Storm Pipe L.F. 2,483 $15.00 $37, Remove Ex. Curb & Gutter L.F. 17,000 $6.75 $114, Remove Ex. Sidewalk L.F. 7,500 $6.75 $50, Remove Ex. Full Depth Pavement S.Y. 50,000 $9.00 $450, Remove Ex. Access Ramp EA. 39 $ $10, Adjust Ex. MH Rim EA. 5 $ $2, R/W & Easement Acquisition L.S. 1 $100, $100, Pavement Markings & Signage L.S. 1 $90, $90, Landscaping L.S. 1 $100, $100, Street Lighting L.S. 1 $150, $150, Repair & Maintenance of E.C. L.S. 1 $67, $67, Traffic Control L.S. 1 $125, $125, Construction Staking L.S. 1 $40, $40, Seed, Fertilize & Mulch L.S. 1 $25, $25, STREET & STORM TOTAL $4,877,996.10

24 ENGINEER'S OPINION OF PROBABLE CONSTRUCTION COST Kasold Drive, Bob Billings to 6th Street Lawrence, Kansas Complete Streets Option ITEM DESCRIPTION UNIT Total UNIT PRICE Total Street, Storm & Waterline 1 Site Preparation L.S. 1 $50, $50, Unclassified Excavation C.Y. 10,000 $5.00 $50, Compaction of Earthwork C.Y. 10,000 $3.00 $30, " Concrete S.Y. 31,525 $60.00 $1,891, Flyash S.Y. 39,450 $4.50 $177, Curb & Gutter L.F. 16,682 $14.00 $233, ' Sidewalk L.F. 4,575 $18.50 $84, ' Shared Use Sidewalk L.F. 5,600 $26.50 $148, Ramps EA. 62 $1, $68, " RCP L.F. 1,005 $50.00 $50, " RCP L.F. 996 $55.00 $54, " RCP L.F. 232 $65.00 $15, " RCP L.F. 35 $80.00 $2, Curb Inlets EA. 19 $3, $60, Junction Box w/ Type II R & C EA. 3 $3, $11, Connect Proposed Inlets to Ex Pipe EA. 5 $ $4, " Nominal Dia. Rip-Rap S.Y. 100 $30.00 $3, Flowable Fill C.Y. 475 $69.00 $32, Remove Existing Inlets EA. 34 $1, $40, Remove Existing Storm Pipe L.F. 2,483 $15.00 $37, Remove Ex. Curb & Gutter L.F. 17,000 $6.75 $114, Remove Ex. Sidewalk L.F. 7,500 $6.75 $50, Remove Ex. Full Depth Pavement S.Y. 50,000 $9.00 $450, Remove Ex. Access Ramp EA. 39 $ $10, Adjust Ex. MH Rim EA. 5 $ $2, R/W & Easement Acquisition L.S. 1 $100, $100, Pavement Markings & Signage L.S. 1 $90, $90, Landscaping L.S. 1 $100, $100, Street Lighting L.S. 1 $150, $150, Repair & Maintenance of E.C. L.S. 1 $67, $67, Traffic Control L.S. 1 $125, $125, Construction Staking L.S. 1 $40, $40, Seed, Fertilize & Mulch L.S. 1 $25, $25, STREET & STORM TOTAL $4,372,775.50

25 APPENDIX C Evaluation of Alternates Chart

26

Complete Streets Policy DAVID CRONIN, P.E., CITY ENGINEER

Complete Streets Policy DAVID CRONIN, P.E., CITY ENGINEER Complete Streets Policy DAVID CRONIN, P.E., CITY ENGINEER Complete Streets City Commission adopted a Complete Streets policy in 2012 Complete Streets are road networks that are designed for all users:

More information

Street / Bob Billings Parkway Lawrence, Kansas CFS Project No

Street / Bob Billings Parkway Lawrence, Kansas CFS Project No Drive Improvements 6 th Street to 15 th Street / Bob Billings Parkway Lawrence, Kansas 6644 CFS Project No. 15-56 Traffic Impact Study July 15, 15 Prepared for: City of Lawrence Public Works Department

More information

M-58 HIGHWAY ACCESS MANAGEMENT STUDY Mullen Road to Bel-Ray Boulevard. Prepared for CITY OF BELTON. May 2016

M-58 HIGHWAY ACCESS MANAGEMENT STUDY Mullen Road to Bel-Ray Boulevard. Prepared for CITY OF BELTON. May 2016 M-58 HIGHWAY ACCESS MANAGEMENT STUDY Prepared for CITY OF BELTON By May 2016 Introduction Missouri State Highway 58 (M-58 Highway) is a major commercial corridor in the City of Belton. As development has

More information

BETHEL ROAD AND SEDGWICK ROAD CORRIDOR STUDY

BETHEL ROAD AND SEDGWICK ROAD CORRIDOR STUDY DRAFT PLAN City Council Meeting August 14, 2017 STUDY AREA Sedgwick Corridor State Route 160, principal arterial with Class 3 access management designation, commuter and freight route, connection to SR

More information

4. ENVIRONMENTAL IMPACT ANALYSIS 9. TRANSPORTATION AND TRAFFIC

4. ENVIRONMENTAL IMPACT ANALYSIS 9. TRANSPORTATION AND TRAFFIC 4. ENVIRONMENTAL IMPACT ANALYSIS 9. TRANSPORTATION AND TRAFFIC 4.9.1 INTRODUCTION The following section addresses the Proposed Project s impact on transportation and traffic based on the Traffic Study

More information

TOWN OF MORAGA MORAGA WAY AND CAMINO PABLO/CANYON ROAD IMPROVEMENTS Town Council Meeting March 13, 2019

TOWN OF MORAGA MORAGA WAY AND CAMINO PABLO/CANYON ROAD IMPROVEMENTS Town Council Meeting March 13, 2019 TOWN OF MORAGA MORAGA WAY AND CAMINO PABLO/CANYON ROAD IMPROVEMENTS Town Council Meeting March 13, 2019 1 Edric Kwan, Public Works Director Josh Peterman, Principal, Fehr and Peers Shawn Knapp, Senior

More information

Atwood Avenue Fair Oaks Avenue Cottage Grove Road

Atwood Avenue Fair Oaks Avenue Cottage Grove Road Atwood Avenue Fair Oaks Avenue Cottage Grove Road Agenda Purpose Review project scope & goals Present design alternatives Gather feedback Answer Questions Format Open House Presentation Q&A Open House

More information

East Downtown Tax Increment Reinvestment Zone (TIRZ) No. 15 Infrastructure Assessment Study

East Downtown Tax Increment Reinvestment Zone (TIRZ) No. 15 Infrastructure Assessment Study East Downtown Tax Increment Reinvestment Zone (TIRZ) No. 15 Infrastructure Assessment Study Houston, TX Technical Memorandum April 15 th, 2009 Prepare by: 2950 North Loop West, Ste. 900 Houston, TX 77092

More information

Tonight is for you. Learn everything you can. Share all your ideas.

Tonight is for you. Learn everything you can. Share all your ideas. Strathcona Neighbourhood Renewal Draft Concept Design Tonight is for you. Learn everything you can. Share all your ideas. What is Neighbourhood Renewal? Creating a design with you for your neighbourhood.

More information

Lee s Summit Road Improvement Study Public Open House June 7, 2007 Summary of Comment Card Responses

Lee s Summit Road Improvement Study Public Open House June 7, 2007 Summary of Comment Card Responses Lee s Summit Road Improvement Study Public Open House June 7, 2007 Summary of Comment Card Responses Introduction At the Lee s Summit Road Improvement Study Public Open House held Thursday, June 7, 2007

More information

Comments EXECUTIVE SUMMARY

Comments EXECUTIVE SUMMARY Comments 1. Under any Alternatives, MCDOT should provide better at-grade pedestrian crossing of Georgia Avenue and Forest Glen Road, including improved crosswalks with wider medians and adequate signal

More information

DRAFT. Corridor study. Honeysuckle Road. October Prepared for the City of Dothan, AL. Prepared by Gresham, Smith and Partners

DRAFT. Corridor study. Honeysuckle Road. October Prepared for the City of Dothan, AL. Prepared by Gresham, Smith and Partners DRAFT Corridor study Honeysuckle Road October 2017 Prepared for the City of Dothan, AL Prepared by TABLE OF CONTENTS SECTION I... 1 STUDY SUMMARY... 1 INTRODUCTION... 1 CONCLUSIONS... 5 SECTION II... 7

More information

Item No. 14 Town of Atherton

Item No. 14 Town of Atherton Item No. 14 Town of Atherton CITY COUNCIL STAFF REPORT CONSENT AGENDA TO: THROUGH: FROM: HONORABLE MAYOR AND CITY COUNCIL GEORGE RODERICKS, CITY MANAGER MICHAEL KASHIWAGI, COMMUNITY SERVICES DIRECTOR MARTY

More information

Project Goal and Description. Why Broadway? Broadway SFMTA.COM/BROADWAY. The goal of the Broadway Safety Improvement

Project Goal and Description. Why Broadway? Broadway SFMTA.COM/BROADWAY. The goal of the Broadway Safety Improvement PROJECT OVERVIEW Project Goal and Description The goal of the Broadway Safety Improvement d St Van Ness Ave Project is to improve safety and comfort for all who Franklin St Hyde St Octavia St Gough St

More information

Chapter 2: Standards for Access, Non-Motorized, and Transit

Chapter 2: Standards for Access, Non-Motorized, and Transit Standards for Access, Non-Motorized, and Transit Chapter 2: Standards for Access, Non-Motorized, and Transit The Washtenaw County Access Management Plan was developed based on the analysis of existing

More information

Final Sidewalk Feasibility Study

Final Sidewalk Feasibility Study Garfield Drive From Anastasia Drive to Elizabeth Place City of South Daytona July 23, 2009 Final Sidewalk Feasibility Study Prepared for: Prepared by: Final Sidewalk Feasibility Study Garfield Drive 2

More information

TRANSPORTATION COMMISSION East 19 th St, Harper to O Connell Thursday, March 29, :00 PM City Commission Room, City Hall, 6 E.

TRANSPORTATION COMMISSION East 19 th St, Harper to O Connell Thursday, March 29, :00 PM City Commission Room, City Hall, 6 E. TRANSPORTATION COMMISSION East 19 th St, Harper to O Connell Thursday, March 29, 2018 6:00 PM City Commission Room, City Hall, 6 E. 6th Street AGENDA Public comment related to the meeting topic will be

More information

Welcome! San Jose Avenue Open House August 25, 2015

Welcome! San Jose Avenue Open House August 25, 2015 Welcome! San Jose Avenue Open House August 25, 2015 Vision Zero The City and County of San Francisco adopted Vision Zero San Francisco Vision Zero High Injury Network as a policy in 2014, committing an

More information

City of Madison, East Johnson Street North Baldwin Street to First Street Local Street Dane County

City of Madison, East Johnson Street North Baldwin Street to First Street Local Street Dane County City of Madison, East Johnson Street North Baldwin Street to First Street Local Street Dane County Public Involvement Meeting Thursday, April 28, 2016 6 to 8 P.M. Lapham Elementary School 1045 E. Dayton

More information

Multi-Modal Traffic Analysis. Parisi and Associates

Multi-Modal Traffic Analysis. Parisi and Associates Mill Valley to Corte Madera Bicycle and Pedestrian Corridor Study Appendix D: Multi-Modal Traffic Analysis Prepared by Parisi and Associates August 2009 Appendix D - Multi-Modal Traffic Analysis Table

More information

Cycle Track Design Best Practices Cycle Track Sections

Cycle Track Design Best Practices Cycle Track Sections Design Best Practices Sections It is along street segments where the separation and protection methods of cycle tracks offer more comfort than conventional bicycle lanes, and are more attractive to a wide

More information

EXECUTIVE SUMMARY. Vision

EXECUTIVE SUMMARY. Vision Vision Walking and bicycling in Salt Lake City will be safe, convenient, comfortable, and viable transportation options that connect people to places, foster recreational and economic development opportunities,

More information

Chapter 4 Traffic Analysis

Chapter 4 Traffic Analysis Chapter 4 Traffic Analysis PURPOSE The traffic analysis component of the K-68 Corridor Management Plan incorporates information on the existing transportation network, such as traffic volumes and intersection

More information

STANLEY STREET December 19, 2017

STANLEY STREET December 19, 2017 STANLEY STREET December 19, 2017 Welcome Mike Wiza, Mayor Scott Beduhn, Director of Public Works Agenda 1. Introduction 2. Existing Roadway Conditions 3. Current Alternative Improvements 4. Summary of

More information

SECTION 5: PEER CITY REVIEW

SECTION 5: PEER CITY REVIEW SECTION 5: PEER CITY REVIEW 5.1 Introduction It is evident that the City of Lincoln continually strives to improve its operations and practices. To that end, a list of peer cities was developed to compare

More information

Bay to Bay Boulevard Complete Streets Project

Bay to Bay Boulevard Complete Streets Project Bay to Bay Boulevard Complete Streets Project Dale Mabry Highway to Bayshore Boulevard February 08, 2018 Photo Source: Tampa Bay Times Alessandra Da Pra Meeting Format Introduction Resurfacing Information

More information

Chapter 5. Complete Streets and Walkable Communities.

Chapter 5. Complete Streets and Walkable Communities. Chapter 5. Complete Streets and Walkable Communities. 5.1 Description of Complete Streets. Cities throughout the world, and specifically the United States, are coming to embrace a new transportation and

More information

Dr. M.L. King, Jr. Street North Complete Streets Resurfacing Opportunities HOUSING, LAND USE, AND TRANSPORTATION COMMITTEE MARCH 22, 2018

Dr. M.L. King, Jr. Street North Complete Streets Resurfacing Opportunities HOUSING, LAND USE, AND TRANSPORTATION COMMITTEE MARCH 22, 2018 Dr. M.L. King, Jr. Street North Complete Streets Resurfacing Opportunities HOUSING, LAND USE, AND TRANSPORTATION COMMITTEE MARCH 22, 2018 What s Happening The City plans to mill and resurface Dr. M.L.

More information

4APNOIPF Vh, YII PTC CITY COUNCIL AGENDA REPORT. Honorable Mayor and City Council Members. 8K TH 63 River Crossing Bridge Replacement Project

4APNOIPF Vh, YII PTC CITY COUNCIL AGENDA REPORT. Honorable Mayor and City Council Members. 8K TH 63 River Crossing Bridge Replacement Project City of RE 4APNOIPF Vh, X` W\ YII PTC ING, CITY COUNCIL AGENDA REPORT Council Meeting Date: September 26, 2016 To: From: Agenda Item: Honorable Mayor and City Council Members Ron Rosenthal, Engineering

More information

Los Altos Hills Town Council - June 18, 2015 Palo Alto City Council June 22, AGENDA ITEM #2.B Presentation

Los Altos Hills Town Council - June 18, 2015 Palo Alto City Council June 22, AGENDA ITEM #2.B Presentation Los Altos Hills Town Council - June 18, 2015 Palo Alto City Council June 22, 2015 AGENDA ITEM #2.B Presentation Previous Presentations Los Altos Hills Town Council in May 2014 and February 2015 Palo Alto

More information

Access requests to County streets and roadways are processed through one of the following methods:

Access requests to County streets and roadways are processed through one of the following methods: 13.1 GENERAL APPLICATION PROCESS Access requests to County streets and roadways are processed through one of the following methods: A. Planned Developments may set general locations for access points.

More information

Building Great Neighbourhoods BELLEVUE AND VIRGINIA PARK

Building Great Neighbourhoods BELLEVUE AND VIRGINIA PARK Building Great Neighbourhoods BELLEVUE AND VIRGINIA PARK This is Meeting 2 Unfortunately, some residents in Bellevue and Virginia Park received the wrong information for this public open house (Meeting

More information

City of Madison, East Johnson Street North Baldwin Street to First Street Local Street Dane County

City of Madison, East Johnson Street North Baldwin Street to First Street Local Street Dane County City of Madison, East Johnson Street North Baldwin Street to First Street Local Street Dane County Public Involvement Meeting Thursday, November 10, 2016 5:30 to 7 P.M. Festival Foods 810 E. Washington

More information

Municipal Class EA To Address Traffic Congestion On The Ontario Street Corridor (Grand Bend) Public Information Meeting June 4, 2018

Municipal Class EA To Address Traffic Congestion On The Ontario Street Corridor (Grand Bend) Public Information Meeting June 4, 2018 Municipal Class EA To Address Traffic Congestion On The Ontario Street Corridor (Grand Bend) Public Information Meeting June 4, 2018 Background Agenda Traffic Study Update Class EA Alternatives Bridge

More information

Evaluation of M-99 (Broad Street) Road Diet and Intersection Operational Investigation

Evaluation of M-99 (Broad Street) Road Diet and Intersection Operational Investigation Evaluation of M-99 (Broad Street) Road Diet and Intersection Operational Investigation City of Hillsdale, Hillsdale County, Michigan June 16, 2016 Final Report Prepared for City of Hillsdale 97 North Broad

More information

Access Location, Spacing, Turn Lanes, and Medians

Access Location, Spacing, Turn Lanes, and Medians Design Manual Chapter 5 - Roadway Design 5L - Access Management 5L-3 Access Location, Spacing, Turn Lanes, and Medians This section addresses access location, spacing, turn lane and median needs, including

More information

Complete Streets Process and Case Study: Taft / McMillian Two-Way Street Conversion Cincinnati, Ohio. Traffic Engineering Workshop June 4, 2014

Complete Streets Process and Case Study: Taft / McMillian Two-Way Street Conversion Cincinnati, Ohio. Traffic Engineering Workshop June 4, 2014 Complete Streets Process and Case Study: Taft / McMillian Two-Way Street Conversion Cincinnati, Ohio Traffic Engineering Workshop June 4, 2014 Complete Streets Streets that enable safe access for users

More information

TRANSPORTATION ANALYSIS REPORT US Route 6 Huron, Erie County, Ohio

TRANSPORTATION ANALYSIS REPORT US Route 6 Huron, Erie County, Ohio TRANSPORTATION ANALYSIS REPORT US Route 6 Huron, Erie County, Ohio December 12, 2012 Prepared for: The City of Huron 417 Main Huron, OH 44839 Providing Practical Experience Technical Excellence and Client

More information

CITY OF WEST LAKE HILLS. Forest View Neighborhood Traffic Calming Study

CITY OF WEST LAKE HILLS. Forest View Neighborhood Traffic Calming Study CITY OF WEST LAKE HILLS 901 South Mopac Expressway Building V, Suite 220 Austin, Texas 78746 Texas P.E. Firm Registration No. F-929 Klotz Associates Final Report Submittal: March 20, 2015 Revised Final

More information

Intersection Traffic Control Feasibility Study

Intersection Traffic Control Feasibility Study Intersection Traffic Control Feasibility Study CSAH 9 at CSAH 60 (185th Avenue) Prepared For: Dakota County Transportation Department Western Service Center 14955 Galaxie Avenue, 3rd Floor Apple Valley,

More information

Readington Road (C.R. 637) Construction

Readington Road (C.R. 637) Construction Public Information Meeting Thursday, August 2, 2012 Readington Road (C.R. 637) Construction from Dreahook Road to Harlan School Road Branchburg Township, Somerset County Readington Township, Hunterdon

More information

Public Information Meeting. Orange Camp Road. Dr. Martin Luther King Jr. Beltway to I-4. Presented by: Volusia County August 2, 2018

Public Information Meeting. Orange Camp Road. Dr. Martin Luther King Jr. Beltway to I-4. Presented by: Volusia County August 2, 2018 Public Information Meeting Orange Camp Road Dr. Martin Luther King Jr. Beltway to I-4 Presented by: Volusia County August 2, 2018 1 Project Goals To improve the operations and safety for Orange Camp Road

More information

City of Wilsonville 5 th Street to Kinsman Road Extension Project

City of Wilsonville 5 th Street to Kinsman Road Extension Project City of Wilsonville 5 th Street to Kinsman Road Walking Tour & Neighborhood Workshop Summary Report Public Outreach Overview On July 18 th, 2017, the City of Wilsonville hosted a neighborhood walking tour

More information

Water Street Promenade. Engineering and Design Services. Public Information Meeting No. 2. Education / Infrastructure / Innovation. Maplewood Avenue &

Water Street Promenade. Engineering and Design Services. Public Information Meeting No. 2. Education / Infrastructure / Innovation. Maplewood Avenue & Public Information Meeting No. 2 Water Street Promenade Maplewood Avenue & Engineering and Design Services Adjacent Areas July 16,2014Portsmouth, NH May 10, 2016 Education / Infrastructure / Innovation

More information

Southbend to Prima Vista. October 30, Floresta Corridor Master Plan

Southbend to Prima Vista. October 30, Floresta Corridor Master Plan Application of a Complete Street initiative and how it might function operationally 8 8 Southbend to Prima Vista October 30, 2017 Presentation Agenda 2 Perspective and History Traffic projections, Levels

More information

CSAH 101 Preliminary Design

CSAH 101 Preliminary Design CSAH 101 Preliminary Design Public Open House No. 2 January 29, 2013 CSAH 62 to Hutchins Drive Welcome / Introductions Hennepin County Craig Twinem, Transportation Maury Hooper, Transportation Nick Peterson,

More information

EUCLID AVENUE PARKING STUDY CITY OF SYRACUSE, ONONDAGA COUNTY, NEW YORK

EUCLID AVENUE PARKING STUDY CITY OF SYRACUSE, ONONDAGA COUNTY, NEW YORK EUCLID AVENUE PARKING STUDY CITY OF SYRACUSE, ONONDAGA COUNTY, NEW YORK CITY OF SYRACUSE DEPARTMENT OF PUBLIC WORKS 1200 CANAL STREET EXTENSION SYRACUSE, NEW YORK 13210 DRAFT REPORT DATE: November 13,

More information

WELCOME Public Information Centre

WELCOME Public Information Centre WELCOME Public Information Centre Fernforest Drive Brampton Soccer Centre Community Room #2 Tuesday January 19, 2016 6:30 p.m.to 9:00 p.m. Please sign in Neighbourhood Traffic Calming Guide Background

More information

Public Information Centre

Public Information Centre WELCOME Public Information Centre Father Tobin Road Lougheed Middle School - Library Wednesday November 7, 2012 7:00 p.m.to 9:00 p.m. Please sign in Neighbourhood Traffic Calming Guide Background The City

More information

Poor pavement condition Substandard Intersections. / Substandard bike/pedestrian/transit accommodations. Driveway access Environmental concerns

Poor pavement condition Substandard Intersections. / Substandard bike/pedestrian/transit accommodations. Driveway access Environmental concerns Public Informational Meeting University Avenue (Allen Boulevard Segoe Road) March 23, 2011 City of Madison City of Middleton Village of Shorewood Hills Dane County Existing Roadway Conditions Poor pavement

More information

INNOVATIVE INTERSECTION DESIGN

INNOVATIVE INTERSECTION DESIGN INNOVATIVE INTERSECTION DESIGN J. Eddie Valtier, P.E. ELP TP&D Director Introduction Why Do We Need To Start Looking For Innovative Intersection Designs? Congestion is worsening and traffic volumes and

More information

Information on display. Inside this handout. Triangle Area revisions. Project need displays. Preferred alternative on aerial maps

Information on display. Inside this handout. Triangle Area revisions. Project need displays. Preferred alternative on aerial maps Public information meeting #4 4 to 7 p.m., September 30, 2009 Hales Corners Welcome Thank you for attending this public information meeting for the WIS 100 Corridor Study. Your interest and comments are

More information

PROPOSED BICYCLE AND PEDESTRIAN FACILITY Vicinity of Route 123/I-495 Interchange Tysons, Fairfax County, Virginia

PROPOSED BICYCLE AND PEDESTRIAN FACILITY Vicinity of Route 123/I-495 Interchange Tysons, Fairfax County, Virginia PROPOSED BICYCLE AND PEDESTRIAN FACILITY Vicinity of Route 123/I-495 Interchange Tysons, Fairfax County, Virginia PRELIMINARY ENGINEERING REPORT Prepared for: Prepared by: July 2017 Table of Contents 1

More information

JONESBORO HIGHWAY 63 HIGHWAY 18 CONNECTOR STUDY

JONESBORO HIGHWAY 63 HIGHWAY 18 CONNECTOR STUDY JONESBORO HIGHWAY 63 HIGHWAY 18 CONNECTOR STUDY Craighead County May 2007 JONESBORO HIGHWAY 63 HIGHWAY 18 CONNECTOR STUDY Craighead County May 2007 Prepared by Planning and Research Division Arkansas State

More information

TOWN OF PORTLAND, CONNECTICUT COMPLETE STREETS POLICY

TOWN OF PORTLAND, CONNECTICUT COMPLETE STREETS POLICY TOWN OF PORTLAND, CONNECTICUT COMPLETE STREETS POLICY I. VISION, GOALS & PRINCIPLES VISION To improve the streets of Portland making them safer and more accessible for all users including pedestrians,

More information

2014/2015 BIKE ROUTE PLAN 83 AVENUE PROTECTED BIKE LANE

2014/2015 BIKE ROUTE PLAN 83 AVENUE PROTECTED BIKE LANE About the Project 2014/2015 BIKE ROUTE PLAN The City of Edmonton is planning a major bike route on the south side of Edmonton. This bike route is one part of a plan to provide citizens with transportation

More information

Brooklyn Boulevard (County Road 152) Reconstruction Project Phase I. OPEN HOUSE June 20, 2017

Brooklyn Boulevard (County Road 152) Reconstruction Project Phase I. OPEN HOUSE June 20, 2017 Brooklyn Boulevard (County Road 152) Reconstruction Project Phase I OPEN HOUSE June 20, 2017 Brooklyn Boulevard (County Road 152) Phase I Project Partners Project Lead Other Project Partners include Brooklyn

More information

Giles Run Connector Road

Giles Run Connector Road Giles Run Connector Road Laurel Hill Adaptive Reuse Area to Laurel Crest Drive South County Federation Meeting June 14, 2016 History Connector road included in the Laurel Hill Comprehensive Plan amendment

More information

Application of a Complete Street

Application of a Complete Street Application of a Complete Street Southbend to Prima Vista Update May 14, 2018 Meeting Agenda Perspective and History Public input received Typical sections being considered Presentation of the 2-lane master

More information

Lincoln Avenue Road Diet Trial

Lincoln Avenue Road Diet Trial Lincoln Avenue Road Diet Trial Data Collection Report June 1, 2015 Department of Transportation Table of Contents I. Introduction...... 3 II. Data Collection Methodology & Results...... 5 A. Traffic Volume

More information

ENHANCED PARKWAY STUDY: PHASE 2 CONTINUOUS FLOW INTERSECTIONS. Final Report

ENHANCED PARKWAY STUDY: PHASE 2 CONTINUOUS FLOW INTERSECTIONS. Final Report Preparedby: ENHANCED PARKWAY STUDY: PHASE 2 CONTINUOUS FLOW INTERSECTIONS Final Report Prepared for Maricopa County Department of Transportation Prepared by TABLE OF CONTENTS Page EXECUTIVE SUMMARY ES-1

More information

WELCOME. Stakeholder Involvement Group Meeting #2 Round Lake Public Works October 24, 2018

WELCOME. Stakeholder Involvement Group Meeting #2 Round Lake Public Works October 24, 2018 WELCOME Stakeholder Involvement Group Meeting #2 Round Lake Public Works October 24, 2018 MEETING AGENDA 1. Welcome and Introductions 2. Study Progress Update 3. Problem Statement 4. Technical Analysis

More information

Boston Post Road Design Feasibility Study

Boston Post Road Design Feasibility Study Boston Post Road Design Feasibility Study Prepared for the City of Rye Final Report July 18, 2007 Prepared by: Buckhurst Fish & Jacquemart (BFJ) 115 Fifth Avenue New York, NY 10003 www.bfjplanning.com

More information

Summary: Mercer County Princeton Avenue & Spruce Street Study January 2009

Summary: Mercer County Princeton Avenue & Spruce Street Study January 2009 Summary: Several recent studies have assessed potential development and redevelopment opportunities in the Mercer Crossing area of Trenton, Ewing, and Lawrence. This Princeton Avenue and Spruce Street

More information

AGENDA REPORT. Issue: Discussion of potential improvements on Barnwell Road at Niblick Drive

AGENDA REPORT. Issue: Discussion of potential improvements on Barnwell Road at Niblick Drive AGENDA REPORT To: From: By: Honorable Mayor and City Council Members Warren Hutmacher, City Manager Tom Black, Public Works Director Date: March 23, 2016 Agenda: March 28, 2016 WORK SESSION AGENDA: Barnwell

More information

Blair/Williamson Intersection Expressed Needs

Blair/Williamson Intersection Expressed Needs Blair/Williamson Intersection Expressed Needs NORTH Blair Street is a barrier for pedestrians and bicycles Relocate Capitol City Trail crossing from Blair Street and John Nolen Drive intersection to Williamson

More information

Lincoln Highway Streetscape Plan Concept Plan

Lincoln Highway Streetscape Plan Concept Plan Lincoln Highway Streetscape Plan Concept Plan November 14, 2014 Introduction This report provides a summary of conceptual transportation, land use, and design recommendations in the Lincoln Highway Streetscape

More information

Downey Road. Transportation Improvement Study

Downey Road. Transportation Improvement Study Downey Road Transportation Improvement Study Workshop 2 Participant Handbook Workshop 1 May 18 and 19, 2016 Workshop 2 June 23 and 28, 2016 Prepared By: City of Guelph Paradigm Transportation Solutions

More information

31st Street Corridor Study Iowa Street to County Route 1057

31st Street Corridor Study Iowa Street to County Route 1057 Iowa Street to County Route 1057 January 28, 2003 Prepared for: City of Lawrence, Kansas Douglas County, Kansas Prepared by: TranSystems Corporation 2400 Pershing Road, Suite 400 Kansas City, MO 64108

More information

Toronto and East York Community Council. Director, Transportation Services, Toronto and East York District

Toronto and East York Community Council. Director, Transportation Services, Toronto and East York District No Turn on Red Regulations STAFF REPORT ACTION REQUIRED Date: June 1, 2010 To: From: Toronto and East York Community Council Director, Transportation Services, Toronto and East York District Wards: Trinity

More information

Fleur Drive Reconstruction

Fleur Drive Reconstruction Fleur Drive Reconstruction October 29, 2018 1 Agenda: Fleur Drive Reconstruction Project Scope & Cost Overview Fleur Drive Cross Section Elements - Travel Lane Widths - Sidewalk Widths - Parkway Widths

More information

Legislative Update Williamsburg Residency

Legislative Update Williamsburg Residency Hampton Roads District Legislative Update Williamsburg Residency Jim Brewer, Resident Administrator 757-253-5140 Projects Under Way Warwick Boulevard Project http://www.warwickboulevard.org/ Contractors:

More information

Prepared By: Town of Waxhaw Traffic Calming Policy

Prepared By: Town of Waxhaw Traffic Calming Policy Policy For Resolutions for Town Meetings Prepared By: Town Manager Michael McLaurin Director Greg Mahar CPD Waxhaw N.C. Community Planning &Development Administrative Department Department: Date Approved

More information

Active Transportation Facility Glossary

Active Transportation Facility Glossary Active Transportation Facility Glossary This document defines different active transportation facilities and suggests appropriate corridor types. Click on a facility type to jump to its definition. Bike

More information

25th Avenue Road Diet Project A One Year Evaluation. Transportation Fund for Clean Air Project #05R07

25th Avenue Road Diet Project A One Year Evaluation. Transportation Fund for Clean Air Project #05R07 25th Avenue Road Diet Project A One Year Evaluation Transportation Fund for Clean Air Project #05R07 Submitted by: The San Francisco Municipal Transportation Agency Dan Provence May 22, 2009 EXECUTIVE

More information

University Hill Transportation Study Technical Memorandum Alternatives Modeling and Analysis May 2007

University Hill Transportation Study Technical Memorandum Alternatives Modeling and Analysis May 2007 Technical Memorandum May 2007 Syracuse Metropolitan Transportation Council Edwards and Kelcey with Wallace Roberts and Todd Alta Planning and Design CONTENTS SECTION ONE- INTRODUCTION...1 SECTION TWO-

More information

133 rd Street and 132 nd /Hemlock Street 132 nd Street and Foster Street MINI ROUNDABOUTS. Overland Park, Kansas

133 rd Street and 132 nd /Hemlock Street 132 nd Street and Foster Street MINI ROUNDABOUTS. Overland Park, Kansas 133 rd Street and 132 nd /Hemlock Street 132 nd Street and Foster Street MINI ROUNDABOUTS Overland Park, Kansas September 1, 2017 TABLE OF CONTENTS 1. INTRODUCTION... 1 2. LITERATURE REVIEW... 1 3. CONCEPT

More information

5. RUNNINGWAY GUIDELINES

5. RUNNINGWAY GUIDELINES 5. RUNNINGWAY GUIDELINES These guidelines should be considered collectively when making runningway decisions. A runningway is the linear component of the transit system that forms the right-of-way reserved

More information

TRAFFIC CALMING GUIDE FOR TORONTO CITY OF TORONTO TRANSPORTATION SERVICES DIVISION

TRAFFIC CALMING GUIDE FOR TORONTO CITY OF TORONTO TRANSPORTATION SERVICES DIVISION TRAFFIC CALMING GUIDE FOR TORONTO CITY OF TORONTO TRANSPORTATION SERVICES DIVISION CITY OF TORONTO TRANSPORTATION SERVICES DIVISION 2016 TRAFFIC CALMING GUIDE FOR TORONTO TABLE OF CONTENTS Introduction

More information

TRAFFIC IMPACT ANALYSIS

TRAFFIC IMPACT ANALYSIS TRAFFIC IMPACT ANALYSIS FOR THE CHAMPAIGN UNIT#4 SCHOOL DISTRICT PROPOSED HIGH SCHOOL (SPALDING PARK SITE) IN THE CITY OF CHAMPAIGN Final Report Champaign Urbana Urbanized Area Transportation Study 6/24/2014

More information

Improving Cyclist Safety at the Dundas Street West and Sterling Road Intersection

Improving Cyclist Safety at the Dundas Street West and Sterling Road Intersection STAFF REPORT ACTION REQUIRED Improving Cyclist Safety at the Dundas Street West and Sterling Road Intersection Date: August 17, 2012 To: From: Wards: Reference Number: Public Works and Infrastructure Committee

More information

Broad Street Bicycle Boulevard Design Guidelines

Broad Street Bicycle Boulevard Design Guidelines Broad Street Bicycle Boulevard Design Guidelines Building from the strategies introduced in the 2013 Bicycle Transportation Plan and community input received thus far, City Transportation Staff have identified

More information

5.0 Roadway System Plan

5.0 Roadway System Plan Southwest Boise Transportation Study Page 16 5.0 Roadway System Plan The Roadway System Plan outlines roadway improvements in the Initial Study Area. It forecasts future deficiencies on the arterial system,

More information

Chapter 3 DESIGN SPECIFICATIONS

Chapter 3 DESIGN SPECIFICATIONS Brampton PathWays Planning and Design Guidelines 27 Chapter 3 DESIGN SPECIFICATIONS 3.1 CLASS 1 MULTI-USE PATH Off-road multi-use trails are the backbone of the Brampton PathWays Network. They are typically

More information

PROJECT NO. 093 MA 199 H C. FEDERAL NO. xxxx WIKIEUP-WICKENBURG-PHOENIX HIGHWAY TEGNER STREET, ALTERNATIVE 10 PROJECT IMPROVEMENT

PROJECT NO. 093 MA 199 H C. FEDERAL NO. xxxx WIKIEUP-WICKENBURG-PHOENIX HIGHWAY TEGNER STREET, ALTERNATIVE 10 PROJECT IMPROVEMENT PROJECT NO. 093 MA 199 H 5807 01C FEDERAL NO. xxxx WIKIEUP-WICKENBURG-PHOENI HIGHWAY TEGNER STREET, ALTERNATIVE 10 PROJECT IMPROVEMENT (INTERSECTION IMPROVEMENT) US 93/US 60 FINAL PROJECT ASSESSMENT April

More information

MEMORANDUM INTRODUCTION AREA DESCRIPTION. DATE: December 8, 2017

MEMORANDUM INTRODUCTION AREA DESCRIPTION. DATE: December 8, 2017 7719 SOUTH MAIN STREET MIDVALE, UT 84047 P 801.307.3400 MEMORANDUM DATE: December 8, 2017 TO: FROM: SUBJECT: PROJECT NUMBER: 344-7517-003 PROJECT NAME: Keith Ludwig, P.E. Midvale City Lesley Burns, Midvale

More information

APPENDIX G: INTERSECTION NEEDS AT OKEECHOBEE BOULEVARD

APPENDIX G: INTERSECTION NEEDS AT OKEECHOBEE BOULEVARD APPENDIX G: INTERSECTION NEEDS AT OKEECHOBEE BOULEVARD INTERSECTION NEEDS AT SR 7 and OKEECHOBEE BOULEVARD SR 7 Extension Project Development and Environment (PD&E) Study From Okeechobee Boulevard (SR

More information

Albany Shaker Road Corridor Study Public Meeting # 2

Albany Shaker Road Corridor Study Public Meeting # 2 Albany Shaker Road Corridor Study Public Meeting # 2 Scope / Meeting Purpose This project is a CDTC Linkage Study. The Linkage Program is designed to implement the adopted planning and investment principles

More information

8 PROPOSED ROUNDABOUT DUFFERIN STREET AND KING VAUGHAN ROAD INTERSECTION CITY OF VAUGHAN

8 PROPOSED ROUNDABOUT DUFFERIN STREET AND KING VAUGHAN ROAD INTERSECTION CITY OF VAUGHAN 8 PROPOSED ROUNDABOUT DUFFERIN STREET AND KING VAUGHAN ROAD INTERSECTION CITY OF VAUGHAN The Transportation Services Committee recommends the adoption of the recommendation contained in the following report

More information

New Measure A Expenditure Categories DEFINITIONS OF ELIGIBLE EXPENDITURES Adopted March 8, 2007

New Measure A Expenditure Categories DEFINITIONS OF ELIGIBLE EXPENDITURES Adopted March 8, 2007 New Measure A Expenditure Categories DEFINITIONS OF ELIGIBLE EXPENDITURES Adopted March 8, 2007 City Street and County Road Maintenance Program The preservation and keeping of public street and road rights-of-way

More information

Washington St. Corridor Study

Washington St. Corridor Study FIGURE 7.17 Bridge Alternatives - Cross Sections 86 Discarded Alternative: Short-Term Bridge Repair Short-term repairs and west bridge span replacement were considered during analysis. Short-term repairs

More information

Project Report. South Kirkwood Road Traffic Study. Meadows Place, TX October 9, 2015

Project Report. South Kirkwood Road Traffic Study. Meadows Place, TX October 9, 2015 Meadows Place, TX October 9, 2015 Contents 1 Introduction... 1 2 Data Collection... 1 3 Existing Roadway Network... 2 4 Traffic Volume Development... 2 5 Warrant Analysis... 3 6 Traffic Control Alternative

More information

Welcome to the Open House

Welcome to the Open House Leslie Street Between 19 th Avenue and Stouffville Road Addendum to Class Environmental Assessment Study Welcome to the Open House Please sign in at the front desk. March 28, 2017 Richmond Green Sports

More information

2014/2015 BIKE ROUTE PLAN 83 AVENUE PROTECTED BIKE LANE

2014/2015 BIKE ROUTE PLAN 83 AVENUE PROTECTED BIKE LANE About the Project The City of Edmonton is planning a major bike route on the southside of Edmonton. The Strathcona Bike Route will connect the communities of Strathcona, Garneau and the University area,

More information

DEPARTMENT OF ENVIRONMENTAL SERVICES. North Harrison Street (Lee Highway to Little Falls Road) Comparative Analysis. Prepared for:

DEPARTMENT OF ENVIRONMENTAL SERVICES. North Harrison Street (Lee Highway to Little Falls Road) Comparative Analysis. Prepared for: DEPARTMENT OF ENVIRONMENTAL SERVICES North Harrison Street (Lee Highway to Little Falls Road) Comparative Analysis Prepared for: Arlington County Department of Environmental Services 2100 Clarendon Boulevard,

More information

Main-McVay Transit Study: Phase 2 Options Definition and High Level Constraints Evaluation

Main-McVay Transit Study: Phase 2 Options Definition and High Level Constraints Evaluation Main-McVay Transit Study: Phase 2 Options Definition and High Level Constraints Evaluation APRIL 2016 A collaborative study between: For Additional Information or to Comment If you would like additional

More information

Paoli Road Improvement Feasibility Study

Paoli Road Improvement Feasibility Study Paoli Road Improvement Feasibility Study & Public Participation Project March 24, 2015 Prepared for: Tredyffrin Township Prepared by: McMahon Associates, Inc. with Town Planning Partnership, LLC Glackin

More information

Designing Complete Streets: What you need to know

Designing Complete Streets: What you need to know Designing Complete Streets: What you need to know Getting from this to this. Continuous sidewalk Buffer w/trees Bicycle lane Raised median Buildings close to the street Flexibility in design Design and

More information

RZC Appendix 8A Marymoor Subarea Street Requirements

RZC Appendix 8A Marymoor Subarea Street Requirements RZC Appendix 8A Marymoor Subarea Street Requirements For additional design details for Marymoor Subarea infrastructure, refer to the 2017 Marymoor Subarea Infrastructure Planning Report. STREET REQUIREMENTS

More information

Access Management in the Vicinity of Intersections

Access Management in the Vicinity of Intersections Access Management in the Vicinity of Intersections FHWA-SA-10-002 Technical Summary Photo: Ralph Bentley (used with permission) 0 Access Management is: The design, implementation and management of entry

More information