CITY OF KINGSTON REPORT TO COUNCIL. Report No.:
|
|
- Bruno Jennings
- 5 years ago
- Views:
Transcription
1 CITY OF KINGSTON REPORT TO COUNCIL Report No.: TO: FROM: RESOURCE STAFF: Mayor and Members of Council Jim Keech, President and CEO, Utilities Kingston Mark Van Buren, Director of Engineering DATE OF MEETING: February 5, 2013 SUBJECT: Signing Authority To Enter Into A Cost-Sharing Agreement With The Ministry Of Transportation Ontario For The Installation Of A New Traffic Signal At The Intersection Of Perth Road And McAdoo s Lane EXECUTIVE SUMMARY: The Ministry of Transportation Ontario has plans to widen and rehabilitate Highway 401 from west of Montreal Street to the Cataraqui structure as early as this summer subject to funding with an estimated project duration of 5 years. There will be short and long-term ramp closures at the Montreal Street interchange to facilitate construction. The proposed detour route during these ramp closures will route traffic along McAdoo s Lane north of Highway 401, between Perth Road and Battersea Road. The City s latest traffic counts indicate that a traffic signal is already required under existing conditions at the intersection of Perth Road and McAdoo s Lane. As the Ministry of Transportation was prepared to pay for a temporary traffic signal at this intersection, they have instead offered to design and install a permanent traffic signal to municipal standards and enter into a cost-sharing agreement with the City. RECOMMENDATION: THAT the Mayor and Clerk be authorized to enter into a cost-sharing agreement with the Ministry of Transportation Ontario for the installation of a new traffic signal at the intersection of Perth Road and McAdoo s Lane, and that such agreement be in a form satisfactory to the Director of Legal Services. Council Meeting 5 February 5,
2 - Page 2 - AUTHORIZING SIGNATURES: Jim Keech, President and CEO, Utilities Kingston Gerard Hunt, Chief Administrative Officer CONSULTATION WITH THE FOLLOWING COMMISSIONERS: Cynthia Beach, Sustainability & Growth Lanie Hurdle, Community Services N/R N/R Denis Leger, Transportation, Properties & Emergency Services (N/R indicates consultation not required) Council Meeting 5 February 5,
3 - Page 3 - OPTIONS/DISCUSSION: The Ministry of Transportation Ontario has plans to widen and rehabilitate Highway 401 from west of Montreal Street to the Cataraqui River Bridge. As part of this work, the existing bridge at Montreal Street will be demolished and replaced. Subject to funding, the earliest possible date for the contractor to be on-site is June or July of this year with an estimated project duration of up to 5 years with the final paving being completed by July There will be short and longterm ramp closures at the Montreal Street interchange to facilitate construction for a period of up to 5 years. The worst-case scenario, is the simultaneous closure of all 4 of the interchange ramps, occurring for possibly a one-week period. At other times, the following 3 ramps could be simultaneously closed for up to a three-month period. 1) North/south Montreal Street to Eastbound 401 2) North/south Montreal Street to Westbound 401 3) Eastbound 401 to north/south Montreal Street The proposed detour route for the closure will route traffic along McAdoo s Lane north of Highway 401, between Perth Road and Battersea Road, and use the Division Street interchange at Highway 401 for access to and from the highway. The Ministry of Transportation Ontario hired the consulting firm McCormick Rankin to analyze the detour route to identify the requirement for temporary traffic signals to accommodate the detoured traffic at the following intersections: 1) Perth Road at McAdoo s Lane 2) Battersea Road at McAdoo s Lane Perth Road at McAdoo s Lane The City s traffic counts completed in July of 2012, indicate that a traffic signal is already required under existing conditions at the intersection of Perth Road and McAdoo s Lane. Although a new traffic signal is not currently scheduled for installation within the existing multi-year infrastructure plan, there were tentative plans to install a signal here as early as Since McCormick Rankin s report confirms the need for a traffic signal, even without the construction detour in place, it is recommended that a permanent traffic signal be installed at this intersection prior to the implementation of the detour route for the Highway 401 and Montreal Street interchange construction. As the Ministry of Transportation was prepared to pay for all costs associated with a temporary traffic signal at Perth Road and McAdoo s Lane, they have instead offered to design and install a permanent traffic signal and enter into a cost-sharing agreement with the City. The Ministry of Transportation would be responsible for the design, construction and inspection of the traffic signal and they have agreed to comply with City standards. The City would be responsible for the cost of the traffic signal less the amount that the Ministry of Transportation would have paid for a temporary traffic signal. Since the City typically budgets $220,000 for a permanent traffic signal and the Ministry of Transportation estimates the cost of a temporary traffic signal to be Council Meeting 5 February 5,
4 - Page 4 - $60,000, the cost to the City is expected to be approximately $160,000. This cost can be accommodated within the existing Engineering Department s Capital Budget. Battersea Road at McAdoo s Lane The City s traffic counts completed in July of 2010 (with a growth factor of 3%), indicate that a traffic signal is not required, and is not close to meeting the warrants for a traffic signal, under existing conditions at the intersection of Battersea Road and McAdoo s Lane. According to McCormick Rankin s report, this intersection would only meet the requirements for a traffic signal when the westbound off ramp is closed and if ALL of the detoured traffic uses the McAdoo Lane route. Since it is most likely that some of the traffic will choose other routes, it is not expected that a traffic signal will be required at this location. For this reason, both the Ministry of Transportation and McCormick Rankin do not recommend that a temporary or permanent traffic signal be installed at the intersection of Battersea Road at McAdoo s Lane in order to accommodate the detoured traffic. The Ministry of Transportation does however have plans to monitor this intersection and if there are traffic-related issues, there are funds within their budget to hire police to direct traffic as required. Potential for a Roundabout at Division Street & McAdoo s Lane The feasibility of installing a roundabout instead of a traffic signal at Division Street and McAdoo s Lane was also considered. A preliminary analysis of the site was completed by Ourston Roundabout Engineering and it was determined that a roundabout is most likely technically feasible at this intersection. Since a realignment of the north leg on Division Street could be required, it is likely that a roundabout would be considerably more expensive than a traffic signal. Further work would be required in order to complete a conceptual design and a cost estimate that would be used to determine if the operational and safety advantages of a roundabout are worth the additional capital cost. It is important to note that even if a roundabout is the preferred option at this location, the design and construction could take several years. Since a traffic signal is required by MTO at the intersection anyway for a period of up to 5 years, it could be a difficult adjustment for motorists if the signal was removed by MTO and then replaced with a roundabout several years later. It is also important to note that if MTO installs and then removes a temporary traffic signal at this location, there will be no opportunity for cost-sharing of a permanent future traffic signal. EXISTING POLICY/BY LAW: NOTICE PROVISIONS: Council Meeting 5 February 5,
5 - Page 5 - ACCESSIBILITY CONSIDERATIONS: FINANCIAL CONSIDERATIONS: Since the City typically budgets $220,000 for a permanent traffic signal and the Ministry of Transportation estimates the cost of a temporary traffic signal to be $60,000, the cost to the City is expected to be approximately $160,000. This cost can be accommodated within the existing Engineering Department s Capital Budget. More specifically, the Road Reconstruction program for 2012 has sufficient remaining funds following completion of all scheduled 2012 road reconstruction projects, to enable funding for this project. CONTACTS: Mark VanBuren, Director of Engineering ext Deanna Green, Manager, Traffic Division ext OTHER CITY OF KINGSTON STAFF CONSULTED: Hal Linscott, Director, Legal Services ext Peter Huigenbos, Director, Real Estate & Construction ext EXHIBITS ATTACHED: Not applicable. Council Meeting 5 February 5,
City of Kingston Report to Council Report Number
To: From: Resource Staff: Date of Meeting: April 17 2018 Subject: Executive Summary: City of Kingston Report to Council Report Number 18-119 Mayor and Members of Council Lanie Hurdle, Commissioner, Community
More informationCITY OF KINGSTON INFORMATION REPORT TO ENVIRONMENT, INFRASTRUCTURE & TRANSPORTATION POLICIES COMMITTEE Report No.: EITP
CITY OF KINGSTON INFORMATION REPORT TO ENVIRONMENT, INFRASTRUCTURE & TRANSPORTATION POLICIES COMMITTEE TO: FROM: RESOURCE STAFF: Chair and Members of Environment, Infrastructure & Transportation Policies
More informationCity of Kingston Information Report to Rural Advisory Committee Report Number RAC
To: From: Resource Staff: City of Kingston Information Report to Rural Advisory Committee Report Number RAC-18-004 Chair and Members of Rural Advisory Committee Jim Keech, President and CEO, Utilities
More informationCITY OF KINGSTON REPORT TO COUNCIL. Report No.:
CITY OF KINGSTON REPORT TO COUNCIL Report No.: 10-097 TO: FROM: RESOURCE STAFF: Mayor and Members of Council Jim Keech, President & CEO, Utilities Kingston Mark Van Buren, Director of Engineering DATE
More informationCity of Kingston Report to Council Report Number
To: From: Resource Staff: City of Kingston Report to Council Report Number 17-012 Mayor and Members of Council Date of Meeting: Subject: Executive Summary: Lanie Hurdle, Commissioner, Community Services
More informationCity of Kingston Report to Council Report Number
To: From: Resource Staff: Date of Meeting: June 16, 2015 Subject: City of Kingston Report to Council Report Number 15-291 Mayor and Members of Council Jim Keech, President and CEO, Utilities Kingston Mark
More informationDesign Criteria. Design Criteria
F Design Criteria Design Criteria Ministry of Transportation Ministère des Transports DESIGN CRITERIA Page: 1 of 13 WORK PROJECT NO. N/A GO Bloomington Station TYPE OF PROJECT LOCATION Bloomington Road
More informationMunicipal Class EA To Address Traffic Congestion On The Ontario Street Corridor (Grand Bend) Public Information Meeting June 4, 2018
Municipal Class EA To Address Traffic Congestion On The Ontario Street Corridor (Grand Bend) Public Information Meeting June 4, 2018 Background Agenda Traffic Study Update Class EA Alternatives Bridge
More informationPurpose: Financial Implications and Impact Statement: It is estimated that the cost to implement:
Various Modifications Lower Jarvis Street and Lake Shore Boulevard East; Lower Jarvis Street, east side, between Lake Shore Boulevard East and The Esplanade - 45-77 Lower Jarvis Street; and Lower Jarvis
More informationI-215 / NEWPORT ROAD INTERCHANGE PROJECT PRESS KIT
I-215 / NEWPORT ROAD INTERCHANGE PROJECT PRESS KIT March I-215 / NEWPORT ROAD INTERCHANGE PROJECT Fact Sheet Project Overview This project will reconstruct the existing interchange located on Interstate
More information8 PROPOSED ROUNDABOUT DUFFERIN STREET AND KING VAUGHAN ROAD INTERSECTION CITY OF VAUGHAN
8 PROPOSED ROUNDABOUT DUFFERIN STREET AND KING VAUGHAN ROAD INTERSECTION CITY OF VAUGHAN The Transportation Services Committee recommends the adoption of the recommendation contained in the following report
More informationBank Street Widening Class EA Study Leitrim Road to Rideau Road. Gloucester South Seniors Centre, 4550 Bank Street
AECOM 302 1150 Morrison Drive 613 820 8282 tel Ottawa, ON, Canada K2H 8S9 613 820 8338 fax www.aecom.com Minutes of Meeting Date of Meeting April 4, 2013 Start Time 6:30 p.m. Project Number 60246226 Project
More informationToronto and East York Community Council. Director, Transportation Services, Toronto and East York District
No Turn on Red Regulations STAFF REPORT ACTION REQUIRED Date: June 1, 2010 To: From: Toronto and East York Community Council Director, Transportation Services, Toronto and East York District Wards: Trinity
More informationIL Route 71 Construction Update
100 Parkers Mill Oswego, IL. 60543 (630) 554-3618 4.20.16 IL 71 TRAFFIC ADVISORY: Tentatively scheduled for April 21st A new traffic pattern from Paradise to Wolf Crossing on IL 71 will be in use. The
More informationPedestrian Crossing Guidelines 2016
Pedestrian Crossing Guidelines 2016 Engineering Services 1.0 Introduction and Background The City of Kingston s first Pedestrian Crossing Guidelines were approved by Council in 2008 in order to provide
More informationMEMORANDUM TERESA MCCLISH, COMMUNITY DEVELOPMENT DIRECTOR
MEMORANDUM TO: FROM: BY: CITY COUNCIL TERESA MCCLISH, COMMUNITY DEVELOPMENT DIRECTOR MATTHEW DOWNING, PLANNING MANAGER SUBJECT: CONSIDERATION OF TEMPORARY USE PERMIT CASE NO. 18-015; AUTHORIZING THE VILLAGE
More information2. Executing a legal agreement with respect to (1) above.
3. INSTALLATION OF TRAFFIC CONTROL SIGNALS AT HUNT CLUB AND PAUL ANKA TO ACCOMMODATE THE DEVELOPMENT OF A GAS BAR, CONVENIENCE STORE AND CAR WASH COMMITTEE RECOMMENDATIONS That Council approve the installation
More informationKalamazoo County Weekly Project Updates from the Cities of Portage, Kalamazoo and the Kalamazoo County Road Commission
FOR IMMEDIATE RELEASE Date: October 31, 2014 Kalamazoo County Weekly Project Updates from the Cities of Portage, Kalamazoo and the Kalamazoo County Road Commission Kalamazoo, MI- In a collaborative effort
More informationInterstate Route 77 / US Route 62 / State Route 687 (Fulton Road) Transportation Improvement Project. Prepared September 6, 2017
EODOT Project: ODOT Project: STA-IR 77-.50; PID 00290 Interstate Route 77 / US Route 62 / State Route 687 (Fulton Road) Transportation Improvement Project Summary of Public Comments Received and Responses
More informationPublic Works and Infrastructure Committee. General Manager, Transportation Services
STAFF REPORT ACTION REQUIRED Extending the Bay Street Bicycle Lanes Date: May 16, 2013 To: From: Public Works and Infrastructure Committee General Manager, Transportation Services Wards: Toronto Centre
More informationList of Display Boards
List of Display Boards Welcome Introduction Municipal Class Environmental Assessment (EA) Process Need and Justification for an Interchange Alternatives for Evaluation Vertical and Horizontal Alignments
More informationHIGHWAY 401 WIDENING SECOND LINE WEST STRUCTURE
HIGHWAY 401 WIDENING SECOND LINE WEST STRUCTURE Public Meeting November 16, 2011 OVERVIEW BACKGROUND DISCUSSION ITEMS TRAFFIC ANALYSIS CYCLIST / PEDESTRIAN CONNECTION BACKGROUND February 1982 Ministry
More information5. MODIFICATIONS AT JEANNE D ARC BOULEVARD/REGIONAL ROAD 174 INTERCHANGE INTERSECTION - PUBLIC HEARING COMMITTEE RECOMMENDATION
5. MODIFICATIONS AT JEANNE D ARC BOULEVARD/REGIONAL ROAD 174 INTERCHANGE INTERSECTION - PUBLIC HEARING COMMITTEE RECOMMENDATION Having held a public hearing, that Council approve the preliminary designs
More informationWELCOME. Purpose of the Open House. Update you on the project. Present a draft recommended plan. Receive your input
WELCOME Purpose of the Open House The Town of Smiths Falls has initiated the Beckwith Street Redevelopment Plan that includes the preparation of a streetscape functional design for the renewal of Beckwith
More informationScarlett Road Bridge & Road Improvements Lambton Park Community School - Gymnasium Tuesday November 28 th, 2017
Scarlett Road Bridge & Road Improvements Lambton Park Community School - Gymnasium Tuesday November 28 th, 2017 PROJECT LOCATION 2 SCARLETT ROAD BRIDGE Constructed in 1912, the bridge carries 4 active
More information4 COMMUNITY SAFETY ZONES WALTER SCOTT PUBLIC SCHOOL AND ROSELAWN PUBLIC SCHOOL TOWN OF RICHMOND HILL
4 COMMUNITY SAFETY ZONES WALTER SCOTT PUBLIC SCHOOL AND ROSELAWN PUBLIC SCHOOL TOWN OF RICHMOND HILL The Transportation Services Committee recommends the adoption of the recommendations contained in the
More informationIntersection Traffic Control Feasibility Study
Intersection Traffic Control Feasibility Study CSAH 9 at CSAH 60 (185th Avenue) Prepared For: Dakota County Transportation Department Western Service Center 14955 Galaxie Avenue, 3rd Floor Apple Valley,
More informationCITY CLERK. (City Council on October 2, 3 and 4, 2001, adopted this Clause, without amendment.)
CITY CLERK Clause embodied in Report No. 7 of the, as adopted by the Council of the City of Toronto at its meeting held on October 2, 3 and 4, 2001. 15 Draft By-laws- Installation of Speed Humps - Various
More informationTransportation Impacts: Toronto York Spadina Subway Extension
STAFF REPORT ACTION REQUIRED Transportation Impacts: Toronto York Spadina Subway Extension Date: June 6, 2011 To: From: Wards: Reference Number: North York Community Council Director, Transportation Services
More informationTraffic Calming Policy
City of Friendswood Traffic Calming Policy May 2012 Community Development Department Table of Contents Title Page Table of contents... 1 Background and History... 2 Purpose and Goals... 2 City Procedure
More informationCincinnati Dayton Rd Widening
Cincinnati Dayton Rd Widening Project Overview Widening of Cincinnati Dayton Rd to four lanes - providing a center turn lane and an additional northbound lane Realignment of Station Rd Widening of bridge
More informationCOUNTY ROAD 22 HORSESHOE VALLEY ROAD. Municipal Class Environmental Assessment. simcoe.ca
OCTOBER 2014 Municipal Class Environmental Assessment COUNTY ROAD 22 HORSESHOE VALLEY ROAD Project A Truck Climbing Lanes Project B Intersection Improvements simcoe.ca CORPORATE COMMUNICATIONS DEPARTMENT
More informationFY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Projects
ROUTE/ Project ID No. TIP No. Electrical Load Center Replacement - North 04324 04324 This project will provide for the betterment of the existing highway lighting facilities located along Routes 3, 17
More informationWEST AND SOUTH WEST RING ROAD DOWNSTREAM TRAFFIC IMPACTS
Page 1 of 9 EXECUTIVE SUMMARY Alberta Transportation ( AT ) is preparing to construct the final sections of the Calgary Ring Road. This includes the South West Ring Road ( SWRR ) (from Lott Creek Blvd
More informationMETHODOLOGY. Signalized Intersection Average Control Delay (sec/veh)
Chapter 5 Traffic Analysis 5.1 SUMMARY US /West 6 th Street assumes a unique role in the Lawrence Douglas County transportation system. This principal arterial street currently conveys commuter traffic
More informationMemorandum Office of the City Clerk
Memorandum Office of the City Clerk To: John Thorson, Acting Interim City Manager Subject: American Heart Association Heart Walk Date: March 8, 2017 Attached is an application, letter and route map from
More informationPUBLIC INFORMATION MEETING
PUBLIC INFORMATION MEETING Bridge Rehabilitation Project Project Identification Number 5134.45 NY Route 5 Buffalo Skyway I-190 North Ramp, Pearl Street Ramp Wednesday, April 18, 2018 4:00 p.m. to 7:00
More informationBicycle Traffic Control Signal - St. Clair Avenue West and Poplar Plains Road
PW17.11 REPORT FOR ACTION Bicycle Traffic Control Signal - St. Clair Avenue West and Poplar Plains Road Date: November 4, 2016 To: Public Works and Infrastructure Committee From: Acting General Manager,
More informationCITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF NOVEMBER 15, 2016
CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF NOVEMBER 15, 2016 Item 6, Report No. 38, of the Committee of the Whole, which was adopted without amendment by the Council of the City of Vaughan
More informationCITY OF KINGSTON REPORT TO COUNCIL. Report No.:
CITY OF KINGSTON REPORT TO COUNCIL Report No.: 10-132 TO: FROM: RESOURCE STAFF: Mayor and Council Stephen Dickey, Deputy Treasurer Lana Foulds, Financial Planning Coordinator DATE OF MEETING: 2010-04-20
More informationJoshua Jester, E.I., Florida Department of Transportation, District One
MEMORANDUM To: From: Joshua Jester, E.I., Florida Department of Transportation, District One Michael Garau, P.E., Kimley-Horn and Associates, Inc. Date: October 5, 2018 Subject: at Gulfstream Avenue Intersection
More informationWeymouth - Abington Route 18 Widening and Reconstruction Project File No
Weymouth - Abington Route 18 Widening and Reconstruction Project File No. 601630 PROJECT LOCATION Project Limit Previously Completed Signalized Intersections (Typical) Route 18 Widening Bridge No. W-32-013
More informationHaving held a public hearing, that Council approve:
3. MODIFICATIONS TO MERIVALE ROAD FROM FALLOWFIELD ROAD TO OLD HIGHWAY 16 TO ACCOMMODATE THE GROWTH WITHIN THE SOUTH MERIVALE BUSINESS PARK - PUBLIC HEARING COMMITTEE RECOMMENDATIONS Having held a public
More information2015 MAJOR TRANSPORTATION CONSTRUCTION PROJECTS UPDATE
2015 MAJOR TRANSPORTATION CONSTRUCTION PROJECTS UPDATE 2015 MAJOR TRANSPORTATION CONSTRUCTION PROJECTS HOLD HARD ROAD & SAWMILL ROAD INTERSECTION HARD ROAD WIDENING RIVERSIDE DRIVE REALIGNMENT I-270/US
More informationPreliminary Engineering Study
Preliminary Engineering Study Open House # 2 June 6, 2018 PREPARED FOR: PREPARED BY: Agenda Background and status of preliminary engineering study County Road 26 design summary County Road 63 design summary
More information4 DISRUPTION MANAGEMENT PLAN HIGHWAY 7 RAPIDWAY CONSTRUCTION BETWEEN BAYVIEW AVENUE AND WARDEN AVENUE TOWNS OF MARKHAM AND RICHMOND HILL
4 DISRUPTION MANAGEMENT PLAN HIGHWAY 7 RAPIDWAY CONSTRUCTION BETWEEN BAYVIEW AVENUE AND WARDEN AVENUE TOWNS OF MARKHAM AND RICHMOND HILL The Transportation Services Committee recommends the adoption of
More informationTRAFFIC IMPACT STUDY COMPREHENSIVE UPDATE TOWN OF THOMPSON S STATION, TENNESSEE PREPARED FOR: THE TOWN OF THOMPSON S STATION
TRAFFIC IMPACT STUDY COMPREHENSIVE UPDATE TOWN OF THOMPSON S STATION, TENNESSEE PREPARED FOR: THE TOWN OF THOMPSON S STATION Transportation Consultants, LLC 1101 17 TH AVENUE SOUTH NASHVILLE, TN 37212
More informationCouncil Meeting Number Addeds Tuesday, June 16, 2015
ouncil Meeting Number 2015-17 Addeds Tuesday, Page 1 of 3 The ommittee Of The Whole losed Meeting The consent of ouncil is requested for the addition the following item: f) Litigation or potential litigation,
More informationRebuilding Highway 7 Town Centre Boulevard to Sciberras Road
Rebuilding Highway 7 Town Centre Boulevard to Sciberras Road Project Status Update Presentation to City of Markham Development Services Committee October 22, 2013 Presentation Outline Background Status
More informationEmergency Detour Route Guideline and Best Practices
000 EDR 000 EDR Guideline and Best Practices 000 EDR 000 EDR Introduction Ontario s Highways carry over 8 million drivers and 9 million registered vehicles. Thousands of businesses rely on highways to
More informationCRESTON ROAD COMPLETE AND SUSTAINABLE STREETS CORRIDOR PLAN
CRESTON ROAD COMPLETE AND SUSTAINABLE STREETS CORRIDOR PLAN Preferred Plan Community Presentation September 27, 2017 City of El Paso de Robles in partnership with: Local Government Commission, W-Trans,
More informationTable 1: Recommended Interim Improvement and Long Term Improvement/ROW Preservation Proposed Improvements. Recommended Interim Improvement
Rebecca W. Arnold, President Sara M. Baker, Vice President John S. Franden, Commissioner Carol A. McKee, Commissioner Mitchell Jaurena, Commissioner June 19, 2012 Planning & Programming Department TO:
More informationCITY OF HAMILTON PLANNING AND ECONOMIC DEVELOPMENT DEPARTMENT Transportation Planning and Parking Division
CITY OF HAMILTON PLANNING AND ECONOMIC DEVELOPMENT DEPARTMENT Transportation Planning and Parking Division TO: Chair and Members Public Works Committee COMMITTEE DATE: June 18, 2018 SUBJECT/REPORT NO:
More information2. NORTEL CARLING CAMPUS EXPANSION - PROPOSED MODIFICATIONS TO MOODIE DRIVE (REGIONAL ROAD 59) AND HIGHWAY 417 INTERCHANGE
2. NORTEL CARLING CAMPUS EXPANSION - PROPOSED MODIFICATIONS TO MOODIE DRIVE (REGIONAL ROAD 59) AND HIGHWAY 417 INTERCHANGE COMMITTEE RECOMMENDATIONS AS AMENDED That Council approve: 1. The endorsement
More informationImportant Lane Closures for Jan , 2012
Jan. 19, 2011 CONTACT: Marcia McAllister T: 703-572-0506 C: 571-730-9117 marcia.mcallister@dullesmetro.com Important Lane Closures for Jan. 22-28, 2012 Bridge Construction along Median of Route 7 Continues,
More informationCOMMITTEE RECOMMENDATIONS. That Council approve:
4. MODIFICATIONS TO INNES ROAD (REGIONAL ROAD 30) AND TENTH LINE ROAD (REGIONAL ROAD 47) TO ACCOMMODATE THE DEVELOPMENT OF THE TRINITY COMMONS SHOPPING CENTRE COMMITTEE RECOMMENDATIONS That Council approve:
More informationImproving Cyclist Safety at the Dundas Street West and Sterling Road Intersection
STAFF REPORT ACTION REQUIRED Improving Cyclist Safety at the Dundas Street West and Sterling Road Intersection Date: August 17, 2012 To: From: Wards: Reference Number: Public Works and Infrastructure Committee
More informationFDOT Treasure Coast Traffic Report
July 6, 2018 Barbara Kelleher, 954 777 4090 Barbara.Kelleher@dot.state.fl.us FDOT Treasure Coast Traffic Report July 6 through July 13, 2018 TREASURE COAST Construction and maintenance related lane closures
More informationAPPENDIX F: TECHNICAL NOTE 22 (VICARAGE ROAD JUNCTION)
APPENDIX F: TECHNICAL NOTE 22 (VICARAGE ROAD JUNCTION) West Midlands Interchange Transport Assessment DCO Submission WEST MIDLANDS INTERCHANGE SUBJECT: Technical Note 22 Review of Vicarage Road Junction
More informationHighway 49, Highway 351 and Highway 91 Improvements Feasibility Study Craighead County
Highway 49, Highway 351 and Highway 91 Improvements Feasibility Study Craighead County Executive Summary March 2015 Highway 49, Highway 351 and Highway 91 Improvements Feasibility Study Craighead County
More informationSouthwest Bus Rapid Transit (SW BRT) Functional Planning Study - Executive Summary January 19 LPT ATTACHMENT 2.
Southwest Bus Rapid Transit (SW BRT) Functional Planning Study - Executive Summary 2011 January 19 1 of 19 Introduction This executive summary presents the results of the Southwest Bus Rapid Transit (SW
More informationDowney Road. Transportation Improvement Study
Downey Road Transportation Improvement Study Workshop 2 Participant Handbook Workshop 1 May 18 and 19, 2016 Workshop 2 June 23 and 28, 2016 Prepared By: City of Guelph Paradigm Transportation Solutions
More informationReview of Considerations and Requirements for Automated Enforcement
Review of Considerations and Requirements for Automated Enforcement Summary: The purpose of this report is to provide information related to expanding the use of automated enforcement in the City of Toronto,
More informationCITY OF WOODINVILLE ONGOING CAPITAL IMPROVEMENT PROJECT UPDATES
CITY OF WOODINVILLE ONGOING CAPITAL IMPROVEMENT PROJECT UPDATES PROJECT LOCATION MAP (1) DEYOUNG PARK IMPROVEMENTS Project Description - DeYoung Park Improvements include treehouse deck, play area, new
More information3 FRAMEWORK FOR IMPLEMENTATION OF LAKE-TO-LAKE CYCLING ROUTE
3 FRAMEWORK FOR IMPLEMENTATION OF LAKE-TO-LAKE CYCLING ROUTE The Planning and Economic Development Committee recommends the adoption of the recommendations contained in the following report dated December
More informationChapter 4 Traffic Analysis
Chapter 4 Traffic Analysis PURPOSE The traffic analysis component of the K-68 Corridor Management Plan incorporates information on the existing transportation network, such as traffic volumes and intersection
More informationCounty of Fairfax, Virginia. Department of Transportation
Fairfax County Parkway History 2 Planning began 50 years ago 1960s Washington s Regional Transportation Plan Recommends improved north/south travel Construct Capital Beltway and outer beltway Outer beltway
More informationQUEEN ELIZABETH WAY / MARTINDALE ROAD BRIDGE DEMOLITION DETOUR ANALYSIS
QUEEN ELIZABETH WAY / MARTINDALE ROAD BRIDGE DEMOLITION DETOUR ANALYSIS Fabio Saccon, P.Eng Area Traffic Manager Bernard James Engineer in Training Martin Sneep Senior Project Manager Lance Dutchak Traffic
More informationWelcome. Thank you for your interest in the Lewis & Clark Viaduct Concept Study
Welcome Thank you for your interest in the Lewis & Clark Viaduct Concept Study Please use the arrows in the upper left hand corner to navigate through the presentation. Use the envelope icon to ask a question
More informationHighway 111 Corridor Study
Highway 111 Corridor Study June, 2009 LINCOLN CO. HWY 111 CORRIDOR STUDY Draft Study Tea, South Dakota Prepared for City of Tea Sioux Falls Metropolitan Planning Organization Prepared by HDR Engineering,
More information4. ENVIRONMENTAL IMPACT ANALYSIS 9. TRANSPORTATION AND TRAFFIC
4. ENVIRONMENTAL IMPACT ANALYSIS 9. TRANSPORTATION AND TRAFFIC 4.9.1 INTRODUCTION The following section addresses the Proposed Project s impact on transportation and traffic based on the Traffic Study
More informationInspector MUST Sign and Date Each Inspection
Work Area: Applicant: Mercer County Department of Transportation - Highways Division Application and Permit for Road Work in Mercer County, New Jersey NO. East Windsor Ewing Hamilton Hopewell Lawrence
More informationUPDATES 11/14/2018: 10/25/2018: CLOSED 10/22/2018: 10/12/2018: 10/05/2018: 09/27/2018:
Veterans Boulevard (formerly Boundary Road) This two-year construction project will widen and pave all of Veterans Boulevard. In 2017, the first portion of the road from Highway 16A to 44 Avenue was completed.
More informationTransportation Master Plan Advisory Task Force
Transportation Master Plan Advisory Task Force Network Alternatives & Phasing Strategy February 2016 BACKGROUND Table of Contents BACKGROUND Purpose & Introduction 2 Linking the TMP to Key Council Approved
More informationCITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF NOVEMBER 21, 2017
CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF NOVEMBER 21, 2017 Item 9, Report No. 39, of the Committee of the Whole, which was adopted without amendment by the Council of the City of Vaughan
More informationLee County Department of Transportation 1500 Monroe Street Fort Myers, FL (239) (239) Fax
Lee County Department of Transportation 1500 Monroe Street Fort Myers, FL 33901 (239) 533-8580 (239) 485-8520 Fax ROAD WATCH UPDATE October 12 October 18, 2017 Gunnery Road and 8th Street SW Intersection
More information133 rd Street and 132 nd /Hemlock Street 132 nd Street and Foster Street MINI ROUNDABOUTS. Overland Park, Kansas
133 rd Street and 132 nd /Hemlock Street 132 nd Street and Foster Street MINI ROUNDABOUTS Overland Park, Kansas September 1, 2017 TABLE OF CONTENTS 1. INTRODUCTION... 1 2. LITERATURE REVIEW... 1 3. CONCEPT
More informationAttached for your reference please find project updates on ongoing VDOT construction projects in Southampton County.
SOUTHAMPTON COUNTY BOARD OF SUPERVISORS Regular Session i July 25, 2016 6. HIGHWAY MATTERS A. PLAN PROJECT UPDATES Attached for your reference please find project updates on ongoing VDOT construction projects
More informationWelcome to the Open House
Leslie Street Between 19 th Avenue and Stouffville Road Addendum to Class Environmental Assessment Study Welcome to the Open House Please sign in at the front desk. March 28, 2017 Richmond Green Sports
More informationWork Session. Agenda Item # 4. Meeting Date September 8, Daryl Braithwaite Public Works Director. Prepared By. Suzanne R. Ludlow City Manager
Agenda Item # 4 Work Session Meeting Date September 8, 2015 Prepared By Approved By Daryl Braithwaite Public Works Director Suzanne R. Ludlow City Manager Discussion Item Background Temporary Neighborhood
More informationMay 10, 2013 Meredith Cruz, (561) Palm Beach County Traffic Report May 10 through May 17, 2013
May 10, 2013 Meredith Cruz, (561) 641-6440 mcruz@corradino.com Palm Beach County Traffic Report May 10 through May 17, 2013 Palm Beach County Palm Beach County traffic will be affected this week by ongoing
More informationCTH M HIGHWAY PROJECT CTH Q to STH 113
CTH M HIGHWAY PROJECT CTH Q to STH 113 PUBLIC INFORMATIONAL MEETING #3 Wednesday, May 25, 2005 Town of Westport Administration Building 5387 Mary Lake Road 6:00 p.m. to 8:00 p.m. PUBLIC INFORMATIONAL MEETING
More informationEXHIBIT R1. Neighborhood Cul-de-Sac Implementation
Neighborhood Cul-de-Sac Implementation The traffic study conducted for the Talaria project analyzed the amount of project traffic expected to use local, residential streets immediately north of the project
More informationAPPENDIX G: INTERSECTION NEEDS AT OKEECHOBEE BOULEVARD
APPENDIX G: INTERSECTION NEEDS AT OKEECHOBEE BOULEVARD INTERSECTION NEEDS AT SR 7 and OKEECHOBEE BOULEVARD SR 7 Extension Project Development and Environment (PD&E) Study From Okeechobee Boulevard (SR
More information5 REQUEST FOR GRADE-SEPARATED PEDESTRIAN UNDERPASS CROSSINGS OF LESLIE STREET AND ST. JOHN S SIDEROAD TOWN OF AURORA
5 REQUEST FOR GRADE-SEPARATED PEDESTRIAN UNDERPASS CROSSINGS OF LESLIE STREET AND ST. JOHN S SIDEROAD TOWN OF AURORA The Transportation Services Committee recommends the adoption of the recommendations
More informationMOUNTAIN HOUSE SPECIFIC PLAN I 9.1 INTRODUCTION ASSUMPTIONS TRANSPORTATION FACILITIES TRANSPORTATION IMPROVEMENTS PHASING 9.
CHAPTER NINE: TRANSPORTATION AND CIRCULATION 9.1 INTRODUCTION 9.1 9.2 ASSUMPTIONS 9.1 9.3 TRANSPORTATION FACILITIES 9.1 9.4 TRANSPORTATION IMPROVEMENTS PHASING 9.3 LIST OF FIGURES LIST OF TABLES Figure
More informationFDOT Treasure Coast Traffic Report
July 13, 2018 Barbara Kelleher, 954 777 4090 Barbara.Kelleher@dot.state.fl.us FDOT Treasure Coast Traffic Report July 13 through July 20, 2018 TREASURE COAST Construction and maintenance related lane closures
More informationCity of Kingston Report to Arts Recreation & Community Policies Committee Report Number ARCP
To: From: Resource Staff: City of Kingston Report to Arts Recreation & Community Policies Committee Report Number ARCP 18-001 Chair and Members of the Arts Recreation & Community Policies Committee Date
More informationInfrastructure, Transportation and Safety Sub-committee MINUTES
The Corporation of the City of Stratford Infrastructure, Transportation and Safety Sub-committee MINUTES Date: Time: Location: Sub-committee Present: Staff Present: Also present: 4:30 P.M. Council Chamber,
More informationbrampton.ca rlowgt LITV Committee of the Council of The Corporation of the City of Brampton Date: January 11,2011 COMMITTEE OF COUNCIL
...BRAMPTON1'' C_JS brampton.ca rlowgt LITV Committee of the Council of The Corporation of the City of Brampton Date: January 11,2011 COMMITTEE OF COUNCIL File: G25 Economic Development ATE: *»**& fl,*ol.l.
More informationa) receiving of legal advice subject to solicitor client privilege and labour relations regarding contract negotiations
Regional Municipality of Waterloo Planning and Works Committee Agenda Tuesday, April 4, 2017 9:30 a.m. (Following Closed Session) Regional Council Chamber 150 Frederick Street, Kitchener Media Release:
More informationSummary: Mercer County Princeton Avenue & Spruce Street Study January 2009
Summary: Several recent studies have assessed potential development and redevelopment opportunities in the Mercer Crossing area of Trenton, Ewing, and Lawrence. This Princeton Avenue and Spruce Street
More informationCITY OF WEST KELOWNA COUNCIL POLICY MANUAL
CITY OF WEST KELOWNA COUNCIL POLICY MANUAL Page 1 of 7 DEPARTMENT: Engineering Services SUBJECT: Traffic Calming Policy (Revised June 6, 2017) Policy Statement: The provision of traffic calming measures
More informationUniversity Hill Transportation Study Technical Memorandum Alternatives Modeling and Analysis May 2007
Technical Memorandum May 2007 Syracuse Metropolitan Transportation Council Edwards and Kelcey with Wallace Roberts and Todd Alta Planning and Design CONTENTS SECTION ONE- INTRODUCTION...1 SECTION TWO-
More informationWHEREAS, the New Jersey Department of Transportation' s Complete Streets
WHEREAS, the State Department of Transportation adopted a Complete Streets Policy ( Policy No. 703), effective December 3, 2009, for all projects funded through the Department' s Capital Program and strongly
More information2017 Temporary traffic control guidelines for pedestrians. v.2
2017 Temporary traffic control guidelines for pedestrians v.2 Temporary Traffic Control Guidelines for Pedestrians (2017) The safety and mobility of pedestrians, cyclists and motorists must be considered
More informationCITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF OCTOBER 30, 2012
CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF OCTOBER 30, 2012 Item 31, Report No. 39, of the Committee of the Whole, which was adopted without amendment by the Council of the City of Vaughan
More informationSt. John's Sideroad and Leslie Street Trail System Underpasses
Office of the Clerk John D. Leach Director of Customer and Legislative ServicesfTown Clerk 905-727-3123 ext. 4771 ileach@aurora.ca Town of Aurora 1 00 John West Way, Box 1 000 Aurora, ON L4G 6J1 August
More informationCity of Palo Alto (ID # 7812) City Council Staff Report
City of Palo Alto (ID # 7812) City Council Staff Report Report Type: Consent Calendar Meeting Date: 3/20/2017 Summary Title: 101 Auxiliary Project Parcels Relinquishments Acceptance and Release of Parcels
More informationAmericans with Disabilities Act Transition Plan for Public Right-of-Way Improvements
Americans with Disabilities Act Transition Plan for Public Right-of-Way Improvements Prepared by: Public Works Department Engineering Division October 2015 Table of Contents Section I Introduction.. 3
More information