1 BRT for Berkeley A Proposal for Consideration CITY OF BERKELEY STAFF PROPOSAL FOR A LOCALLY PREFERRED ALTERNATIVE OF THE EAST BAY BUS RAPID TRANSIT PROJECT SEPTEMBER 8, 2009

2

3 Table of Contents Executive Summary... ES-1 ES-1 About This Report... ES-2 ES-2 Project Overview... ES-2 ES-3 Proposed Locally Preferred Alternative... ES-3 ES-3.1 Telegraph South of Dwight... ES-3 ES-3.2 Telegraph North of Dwight... ES-4 ES-3.3 Telegraph to Shattuck (Bancroft and Durant)... ES-4 ES-3.4 Shattuck... ES-4 ES-4 Summary Analysis of Benefits and Impacts... ES-5 ES-5 Summary of Proposed Mitigations and Improvements to the Project... ES-6 ES-5.1 Mitigations Proposed by AC Transit... ES-6 ES-5.2 Improvements Proposed by Berkeley Staff... ES-6 Chapter 1. Introduction to Bus Rapid Transit and the East Bay BRT Project Bus Rapid Transit (BRT) BRT and Dedicated Lanes Benefits of Dedicated Lanes Other Benefits of BRT The East Bay Bus Rapid Transit Project Project Rationale Existing Demand for Transit Existing Land Use Patterns Population and Traffic Growth in the Corridor Future Demand for Transit Project History Project Details Features of the AC Transit East Bay BRT project Service Plan: Combined Service Details of the Service Plan Vehicles BRT and Rapid Bus What is Rapid Bus? Sidebar: Could Rapid Bus Be Improved Instead of Building BRT? Chapter 2. Proposed Locally Preferred Alternative How to Read the LPA Telegraph South of Dwight: Median Transitway Recommended Design Alignment, Transit Right-of-Way, and Stops Transit Service Traffic and Circulation Parking and Loading Bicycles Pedestrians Streetscape Economic and Community Other Alternatives Considered Summary of Issues Remaining for Resolution Telegraph North of Dwight: Northbound Mixed-Flow Lane, Southbound Transit/Delivery Lane Recommended Design Alignment, Transit Right-of-Way, and Stops Transit Service i

4 Traffic and Circulation Parking and Loading Bicycles Pedestrians Streetscape Economic and Community Other Alternatives Considered Summary of Issues Remaining for Resolution Telegraph to Shattuck: Side-Running Transitways on Bancroft and Durant Recommended Design Alignment, Transit Right-of-Way, and Stops Transit Service Traffic and Circulation Parking and Loading Bicycles Pedestrians Streetscape Economic and Community Other Alternatives Considered Summary of Issues Remaining for Resolution Shattuck: No Dedicated Lane ( No-Build ) Recommended Design Alignment Stops Other Alternatives Considered Summary of Issues Remaining for Resolution Chapter 3. Frequently Asked Questions About the East Bay BRT Project Who Rides the Bus in the Corridor, and Where Are They Going? Would BRT Duplicate BART? Would It Be Worth It to Dedicate Lanes to Buses? How Would BRT Affect Safety (including Emergency Vehicle Access)? What Would Be the Land Use and Economic Impacts of BRT? How Would BRT Affect Spillover Parking in Neighborhoods? Would the East Bay BRT Project Be Cost-Effective? How Effective Have Other BRT Projects Been? Travel Time Reliability Ridership Chapter 4. Impacts and Strategies to Address Impacts Summary of LPA Impacts and Mitigations Traffic and Parking Impacts, and Mitigations Proposed by AC Transit Traffic Impacts AC Transit Traffic Mitigations Parking Impacts AC Transit Parking Mitigations Additional Mitigation Strategies Proposed by Berkeley Staff for Further Analysis Chapter 5. Next Steps Future Process Appendices: BRT Resources... A-1 APX-1 EBBRT Resources... A-1 City of Berkeley EBBRT webpage... A-1 AC Transit EBBRT webpages... A-1 ACT for Me website... A-2 APX-2 Berkeley Planning Resources... A-2 ii

5 Downtown Area Plan... A-2 Draft Southside Plan... A-2 Climate Action Plan... A-2 UC Berkeley Long Range Development Plan... A-2 APX-3 General BRT Resources... A-2 Federal Transit Administration (FTA) BRT webpages... A-2 Federal Transit Administration: Characteristics of Bus Rapid Transit for Decision-Making... A-2 California Department of Transportation (Caltrans) BRT webpages... A-2 American Public Transportation Association (APTA) BRT webpages... A-2 BRT Information Clearinghouse... A-2 National BRT Institute... A-2 Buses with High Level of Service... A-2 United States General Accounting Office (GAO)... A-2 Bus Rapid Transit Shows Promise report... A-2 Transit Cooperative Research Program (TCRP) Report 90: Bus Rapid Transit, Volume 1: Case Studies in Bus Rapid Transit and Volume 2: Implementation Guidelines... A-3 Transit Cooperative Research Program (TCRP) Report 118: Bus Rapid Transit Practitioner's Guide... A-3 Victoria Transport Policy Institute BRT webpage... A-3 Wikipedia BRT webpage... A-3 APX-4 Examples of Dedicated Bus Lanes... A-3 Table of Figures Figure ES-1 Proposed Locally Preferred Alternative: Summary of Benefits and Impacts... 5 Figure 1-1 Problems with Bus Service, and Proposed BRT Solutions Figure 1-2 & Figure 1-3 Median Transitways: Los Angeles Orange Line and Cleveland Health Line Figure 1-4 Side-Running Lane and Bulb-Out Stop: Boston Silver Line Figure 1-5 BRT Stop with Level Boarding: Eugene (Oregon) Emx Figure 1-6 East Bay Bus Rapid Transit: Conceptual Alignments (AC Transit DEIS/R) Figure 1-7 Top Five Projected Ridership Increases Among Proposed Bay Area BRT Corridors (2035) Figure 1-8 Proposed Locally Preferred Alternative (Including Local Stops Proposed for Removal) Figure 1-9 Elements of Local, Rapid, Enhanced Rapid, and BRT Service Figure 2-1 Major Issues Considered by City Staff Figure 2-2 Telegraph from Woolsey to Ashby Figure 2-3 Telegraph from Ashby to Ward Figure 2-4 Telegraph from Ward to Dwight Figure 2-5 Dual Threat to Pedestrians at Unsignalized Intersections Figure 2-6 Telegraph North of Dwight Figure 2-7 Durant from Ellsworthto Telegraph Figure 2-8 Durant from Shattuck to Ellsworth Figure 2-9 Bancroft from Telegraph to Ellsworth Figure 2-10 Bancroft from Ellsworth to Shattuck Figure 2-11 Shattuck from Durant to Center Figure 2-12 Shattuck from Allston to Addison iii

6 Figure 2-13 Cross-Sections of All Shattuck Alternatives Figure 3-1 Origins and Destinations for Route 1R Trips with One or Both Ends in Berkeley Figure 3-2 FTA Cost-Effectiveness Ratings for East Bay BRT and Peer Projects Figure 3-3 Examples of BRT Travel Time Savings Figure 3-4 Examples of BRT Ridership Increases Figure 3-5 Percentages of BRT Riders Shifting from Driving Figure 4-1 AM Peak Hour Intersection Levels of Service Figure 4-2 PM Peak Hour Intersection Levels of Service Figure 4-3 PM Peak Hour Traffic Volumes on Telegraph, With and Without BRT Figure 4-4 Existing Parking Supply and Occupancy By Segment Figure 5-1 Major Steps Remaining Before Construction Could Begin iv

Item Description: Presentation and Discussion: Berkeley Rapid Transit Locally Preferred Alternative

Item Description: Presentation and Discussion: Berkeley Rapid Transit Locally Preferred Alternative Office of the City Manager Meeting Date: April 29, 2010 Item Number: 1 Item Description: Presentation and Discussion: Berkeley Rapid Transit Locally Preferred Alternative Staff report, resolution, and

More information

Item B1 November 19, 2009

Item B1 November 19, 2009 November 19, 2009 Planning and Development Department Land Use Planning Division DATE: November 19, 2009 STAFF REPORT TO: FROM: SUBJECT: Members of the Transportation Commission Elizabeth Greene Senior

More information

Presentation of Staff Draft March 18, 2013 COUNTYWIDE TRANSIT CORRIDORS FUNCTIONAL MASTER PLAN

Presentation of Staff Draft March 18, 2013 COUNTYWIDE TRANSIT CORRIDORS FUNCTIONAL MASTER PLAN Presentation of Staff Draft March 18, 2013 COUNTYWIDE TRANSIT CORRIDORS FUNCTIONAL MASTER PLAN Public Outreach Fall 2011: Two community meetings/open houses Fall 2012: Three community meetings/open houses

More information

Community Task Force July 25, 2017

Community Task Force July 25, 2017 Community Task Force July 25, 2017 Welcome and Introductions Project Partners Regional Transportation District (RTD) Colorado Department of Transportation (CDOT) Denver Regional Council of Governments

More information

Bus Rapid Transit Plans

Bus Rapid Transit Plans Twin Cities Region Bus Rapid Transit Plans ULI Minnesota Workshop Connecting Bus Rapid Transit to the Community December 15, 2009 John Levin Director of Service Development Metro Transit Metropolitan Area

More information

Metropolitan Council Transportation Committee

Metropolitan Council Transportation Committee Nicollet-Central Transit Alternatives Metropolitan Council Transportation Committee August 2013 Project Purpose (approved by Policy Advisory Committee 10/25/2012) The purpose is to improve transit connectivity,

More information

PURPOSE AND NEED SUMMARY 54% Corridor Need 1. Corridor Need 2. Corridor Need 3. Corridor Need 4. Corridor Need 5

PURPOSE AND NEED SUMMARY 54% Corridor Need 1. Corridor Need 2. Corridor Need 3. Corridor Need 4. Corridor Need 5 SUMMARY PURPOSE AND NEED Chapel Hill Transit ridership has increased Buses operate every 4 minutes and have standing room only Exceeding seated capacity by 12% Corridor Need 1 by more than 20 percent between

More information

Van Ness Avenue BRT Overview and Scoping Process. Geary BRT CAC January 8, 2009

Van Ness Avenue BRT Overview and Scoping Process. Geary BRT CAC January 8, 2009 Van Ness Avenue BRT Overview and Scoping Process Geary BRT CAC January 8, 2009 VAN NESS AVENUE S ROLE Identified in Prop K for BRT treatment Muni 47 and 49; 19 operates on Polk 20,000 daily riders on Van

More information

SFMTA SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY

SFMTA SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY SFMTA SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY VAN NESS BUS RAPID TRANSIT PROJECT UPDATE PRESENTATION TO SFMTA BOARD OF DIRECTORS RELEASE OF DRAFT ENVIRONMENTAL IMPACT STATEMENT / REPORT 10 18 2011

More information

EL CAMINO REAL BUS RAPID TRANSIT (BRT) PROJECT

EL CAMINO REAL BUS RAPID TRANSIT (BRT) PROJECT Agenda Item #4.2 EL CAMINO REAL BUS RAPID TRANSIT (BRT) PROJECT VTA BOARD WORKSHOP MAY 1, 2015 ABOUT THIS PRESENTATION CONTEXT Existing conditions and planning for growth WHAT IS THE PROJECT? Project alternatives

More information

Eliminate on-street parking where it will allow for a dedicated bus only lane %

Eliminate on-street parking where it will allow for a dedicated bus only lane % Traffic Dashboard Priorities Survey Responses Introduction 1) Are you familiar with bus rapid transit (BRT)? a. No, BRT is new to me. 597 23.5% b. I ve heard of BRT, but I don t know much about it. 1,136

More information

Highway Transitway Corridor Study

Highway Transitway Corridor Study Highway Transitway Corridor Study CTS Research Conference May 21, 2014 1 2030 Transportation Policy Plan Transitway modes on highways: Highway bus rapid transit (BRT), plan identified 6 total Highway BRT

More information

Roadways. Roadways III.

Roadways. Roadways III. Introduction 97 Roadway Design Principles 98 Safe Speeds 99 Optimizing of Street Space 00 Minimum Lane Widths in the City of Boston 02 Design Features that Reduce Operating Speeds 05 Travel Lanes Transit

More information

EXECUTIVE SUMMARY... vii 1 STUDY OVERVIEW Study Scope Study Area Study Objectives

EXECUTIVE SUMMARY... vii 1 STUDY OVERVIEW Study Scope Study Area Study Objectives Contents EXECUTIVE SUMMARY... vii 1 STUDY OVERVIEW... 1-1 1.1 Study Scope... 1-1 1.2 Study Area... 1-1 1.3 Study Objectives... 1-3 2 EXISTING CONDITIONS... 2-1 2.1 Existing Freeway Conditions... 2-4 2.1.1

More information

Scottsdale Road/Rural Road Alternatives Analysis (AA) Study. Arizona ITE/IMSA Spring Conference March 7, 2012

Scottsdale Road/Rural Road Alternatives Analysis (AA) Study. Arizona ITE/IMSA Spring Conference March 7, 2012 Scottsdale Road/Rural Road Alternatives Analysis (AA) Study Arizona ITE/IMSA Spring Conference March 7, 2012 Study Location and Duration Primary Study Corridor (major focus of effort) Rural Road and Scottsdale

More information

In station areas, new pedestrian links can increase network connectivity and provide direct access to stations.

In station areas, new pedestrian links can increase network connectivity and provide direct access to stations. The Last Mile Planning for Pedestrians Planning around stations will put pedestrians first. Making walking to stations safe and easy is important; walking will be a part of every rapid transit Accessible

More information

Purpose and Need. Chapter Introduction. 2.2 Project Purpose and Need Project Purpose Project Need

Purpose and Need. Chapter Introduction. 2.2 Project Purpose and Need Project Purpose Project Need Chapter 2 Purpose and Need 2.1 Introduction The El Camino Real Bus Rapid Transit (BRT) Project (Project) would make transit and other transportation improvements along a 17.6-mile segment of the El Camino

More information

Wilshire Boulevard Bus Rapid Transit Project

Wilshire Boulevard Bus Rapid Transit Project Los Angeles County Metropolitan Transportation Authority Wilshire Boulevard Bus Rapid Transit Project COMMUNITY MEETINGS November 2008 Agenda Introduction Proposed Project Overview Participating Agencies

More information

Telegraph Avenue Complete Streets DRAFT Recommendations. Oakland Public Works Department September 11 and 13, 2014 Open Houses

Telegraph Avenue Complete Streets DRAFT Recommendations. Oakland Public Works Department September 11 and 13, 2014 Open Houses Telegraph Avenue Complete Streets DRAFT Recommendations Oakland Public Works Department September 11 and 13, 2014 Open Houses Presentation Overview What are complete streets? What problem are we trying

More information

Seattle Transit Master Plan

Seattle Transit Master Plan Seattle Transit Master Plan Seattle City Council Transportation Committee Briefing July 26, 2011 Seattle Department of Transportation In Association with: URS Corporation SVR DKS Associates The Underhill

More information

El Camino Real Bus Rapid Transit Conceptual Engineering. Los Altos Council Workshop January 24, 2012

El Camino Real Bus Rapid Transit Conceptual Engineering. Los Altos Council Workshop January 24, 2012 El Camino Real Bus Rapid Transit Conceptual Engineering Los Altos Council Workshop January 24, 2012 Agenda Introduction Growth in the El Camino Real Corridor Benefits of BRT El Camino Real BRT Decision

More information

Sacramento Grid 2.0. The Downtown Transportation Study

Sacramento Grid 2.0. The Downtown Transportation Study Sacramento Grid 2.0 The Downtown Transportation Study April 20, 2016 The Grid 4.25 square miles Street grid defined at birth of City Lettered and numbered streets spaced every 400 ft East-west alleys halfway

More information

Bus Rapid Transit on Silicon Valley s El Camino Real: Working Together to Create a Grand Boulevard Steven Fisher

Bus Rapid Transit on Silicon Valley s El Camino Real: Working Together to Create a Grand Boulevard Steven Fisher Bus Rapid Transit on Silicon Valley s El Camino Real: Working Together to Create a Grand Boulevard Steven Fisher Senior Transportation Planner Santa Clara Valley Transportation Authority San Jose, CA How

More information

Public Comment Meeting Geary BRT Project Draft Environmental Impact Statement/Report

Public Comment Meeting Geary BRT Project Draft Environmental Impact Statement/Report Public Comment Meeting Geary BRT Project Draft Environmental Impact Statement/Report Open House and Opportunity to Provide Comments Public comments can be submitted to the court reporter stationed in the

More information

Chapter 3 BUS IMPROVEMENT CONCEPTS

Chapter 3 BUS IMPROVEMENT CONCEPTS Chapter 3 BUS IMPROVEMENT CONCEPTS The purpose of this chapter is to describe potential bus improvement strategies and potential impacts or implications associated with BRT implementation within the existing

More information

Evan Johnson, Tindale Oliver & Associates. Alan Danaher, P.E., PTOE, AICP, PTP

Evan Johnson, Tindale Oliver & Associates. Alan Danaher, P.E., PTOE, AICP, PTP To: Copies: From: Evan Johnson, Tindale Oliver & Associates Matt Muller, RTS Jesus Gomez, RTS Alan Danaher, P.E., PTOE, AICP, PTP Date: January 14, 2014 Subject: Ridership Projections Gainesville Streetcar

More information

Frequently Asked Questions (FAQ)

Frequently Asked Questions (FAQ) Frequently Asked s (FAQ) Study Process... 2 Rapid Transit Service and Operations... 5 Public Consultation... 8 Business Impacts... 8 Design and Property Impacts... 9 Construction Impacts...12 Traffic,

More information

ALTERNATIVES ANALYSIS EXECUTIVE SUMMARY

ALTERNATIVES ANALYSIS EXECUTIVE SUMMARY West Valley Connector Corridor ALTERNATIVES ANALYSIS EXECUTIVE SUMMARY FINAL September 2014 Ontario International Airport Ontario Mills Rancho Cucamonga Metrolink Station Kaiser Permanente PARSONS EXECUTIVE

More information

San Pablo High Treatment applied incrementally at each N + ++

San Pablo High Treatment applied incrementally at each N + ++ Transit Improvements T1 Further study options for creation or designation of segregated transit lanes along San Pablo, including options for restrictions during a limited number of peak travel hours and

More information

Main-McVay Transit Study: Phase 2 Options Definition and High Level Constraints Evaluation

Main-McVay Transit Study: Phase 2 Options Definition and High Level Constraints Evaluation Main-McVay Transit Study: Phase 2 Options Definition and High Level Constraints Evaluation APRIL 2016 A collaborative study between: For Additional Information or to Comment If you would like additional

More information

Scope of the Transit Priority Project

Scope of the Transit Priority Project Transit Planning Committee #1 March 19, 2015 Scope of the Transit Priority Project Review of the 2010 plan Analysis of Transit Priority Measures Preliminary plans for rapid transit Recommendations for

More information

Afeasibility study to evaluate bus rapid transit service in the East-West Corridor connecting major employment and activity centers between downtown

Afeasibility study to evaluate bus rapid transit service in the East-West Corridor connecting major employment and activity centers between downtown East-West Bus Rapid Transit Feasibility Study Update and Recommended Locally Preferred Alternative (LPA) Summary City of Wauwatosa, Transportation Affairs Committee June 2016 Afeasibility study to evaluate

More information

4. ENVIRONMENTAL IMPACT ANALYSIS 9. TRANSPORTATION AND TRAFFIC

4. ENVIRONMENTAL IMPACT ANALYSIS 9. TRANSPORTATION AND TRAFFIC 4. ENVIRONMENTAL IMPACT ANALYSIS 9. TRANSPORTATION AND TRAFFIC 4.9.1 INTRODUCTION The following section addresses the Proposed Project s impact on transportation and traffic based on the Traffic Study

More information

Providence Downtown Transit Connector STAKEHOLDER MEETING #2. Stakeholder Meeting #1 October 24, 2016

Providence Downtown Transit Connector STAKEHOLDER MEETING #2. Stakeholder Meeting #1 October 24, 2016 Providence Downtown Transit Connector STAKEHOLDER MEETING #2 Stakeholder Meeting #1 October 24, 2016 February 2017 1 AGENDA 1 DTC Goals and Expectations 2 Street Design Concepts 3 Potential Benefits and

More information

TELEGRAPH AVENUE COMPLETE STREETS PLAN DRAFT FINAL PLAN

TELEGRAPH AVENUE COMPLETE STREETS PLAN DRAFT FINAL PLAN TELEGRAPH AVENUE COMPLETE STREETS PLAN DRAFT FINAL PLAN SEPTEMBER 2014 TABLE OF CONTENTS Executive Summary...1 Project Purpose and Need...5 Analysis of Street Design Options...11 Recommended Project...17

More information

1. Operate along freeways, either in regular traffic lanes, in high-occupancy vehicle (HOV) lanes, or along the shoulders.

1. Operate along freeways, either in regular traffic lanes, in high-occupancy vehicle (HOV) lanes, or along the shoulders. Most decisions about whether or not to use transit involve time and cost, and most transit services are slower than travel by private vehicle. However, when transit is faster or nearly as fast as travel

More information

Berkeley Strategic Transportation Plan A-76

Berkeley Strategic Transportation Plan A-76 Berkeley Strategic Transportation Plan A-76 Appendices 1. A Team Effort 2. Where We ve Been A-11 Berkeley Strategic Transportation Plan Alameda County Transportation Plan Alameda County will be served

More information

Bellevue Transportation: Challenges, Opportunities and Priorities Bellevue Downtown Association September 20, 2018

Bellevue Transportation: Challenges, Opportunities and Priorities Bellevue Downtown Association September 20, 2018 Bellevue Transportation: Challenges, Opportunities and Priorities Bellevue Downtown Association September 20, 2018 Dave Berg Transportation Director City of Bellevue Traffic, traffic and more traffic!

More information

Bus Rapid Transit ALTERNATIVES ANALYSIS. Open House

Bus Rapid Transit ALTERNATIVES ANALYSIS. Open House Bus Rapid Transit ALTERNATIVES ANALYSIS Open House June 23, 2015 Open House Meeting Agenda Agenda Introductions What is BRT? Project Goals Study Tasks Next steps Discussion PVTA Bus Rapid Transit Study

More information

Durham Region Long Term Transit Strategy

Durham Region Long Term Transit Strategy Durham Region Long Term Transit Strategy An adaptive, safe, reliable, frequent, accessible and desirable transit system that shapes and connects Durham Region and beyond in an economically and environmentally

More information

Van Ness Avenue Bus Rapid Transit (BRT) San Francisco Environment Commission Policy Committee

Van Ness Avenue Bus Rapid Transit (BRT) San Francisco Environment Commission Policy Committee Van Ness Avenue Bus Rapid Transit (BRT) San Francisco Environment Commission Policy Committee 04.30.12 Van Ness Avenue BRT Project Background Key north-south link in San Francisco s Rapid Transit network

More information

Los Altos Hills Town Council - June 18, 2015 Palo Alto City Council June 22, AGENDA ITEM #2.B Presentation

Los Altos Hills Town Council - June 18, 2015 Palo Alto City Council June 22, AGENDA ITEM #2.B Presentation Los Altos Hills Town Council - June 18, 2015 Palo Alto City Council June 22, 2015 AGENDA ITEM #2.B Presentation Previous Presentations Los Altos Hills Town Council in May 2014 and February 2015 Palo Alto

More information

Arterial Transitway Corridors Study. Ave

Arterial Transitway Corridors Study. Ave Arterial Transitway Corridors Study Ave January 2012 Arterial Transitway Corridors Study Overview Corridor Features and Demographics 11 study corridors, 95 route miles 86,000 daily rides and half of existing

More information

A Federal Perspective on Congestion Pricing. Wayne Berman Federal Highway Administration July 8, 2010

A Federal Perspective on Congestion Pricing. Wayne Berman Federal Highway Administration July 8, 2010 A Federal Perspective on Congestion Pricing Wayne Berman Federal Highway Administration July 8, 2010 Overview Background on Congestion Pricing Benefits and Experiences of Pricing Case Study Miami I-95

More information

THE ALAMEDA CONCEPT DESIGN COMMUNITY MEETING 3. A Plan for The Beautiful Way JANUARY 28, 2010

THE ALAMEDA CONCEPT DESIGN COMMUNITY MEETING 3. A Plan for The Beautiful Way JANUARY 28, 2010 CONCEPT DESIGN COMMUNITY MEETING 3 JANUARY 28, 2010 AGENDA INTRODUCTION COMMUNITY INPUT ROADWAY STUDIES STREETSCAPE DESIGN STATIONS DISCUSSION SUMMARY AND DISCUSSION NEXT STEPS CLOSE INTRODUCTION SCHEDULE

More information

Appendix A-1: Purpose and Need Statement

Appendix A-1: Purpose and Need Statement Appendix A-1: Purpose and Need Statement PURPOSE AND NEED STATEMENT Western & Ashland Corridors Bus Rapid Transit (BRT) Project Prepared for Chicago Transit Authority 567 West Lake Street Chicago, IL 60661

More information

A Selection Approach for BRT Parking Lots Nicolls Road Corridor Parking Study

A Selection Approach for BRT Parking Lots Nicolls Road Corridor Parking Study A Selection Approach for BRT Parking Lots Nicolls Road Corridor Parking Study Chirantan Kansara, P.E. Engineering Construction Design Planning 2018 ITE Northeastern District Annual Meeting Lake George,

More information

CITY OF HAMILTON PLANNING AND ECONOMIC DEVELOPMENT DEPARTMENT Transportation Planning and Parking Division

CITY OF HAMILTON PLANNING AND ECONOMIC DEVELOPMENT DEPARTMENT Transportation Planning and Parking Division CITY OF HAMILTON PLANNING AND ECONOMIC DEVELOPMENT DEPARTMENT Transportation Planning and Parking Division TO: Chair and Members Public Works Committee COMMITTEE DATE: June 18, 2018 SUBJECT/REPORT NO:

More information

ROUTES 55 / 42 / 676 BUS RAPID TRANSIT LOCALLY PREFERRED ALTERNATIVE

ROUTES 55 / 42 / 676 BUS RAPID TRANSIT LOCALLY PREFERRED ALTERNATIVE ROUTES 55 / 42 / 676 BUS RAPID TRANSIT LOCALLY PREFERRED ALTERNATIVE April, 2012 1 INTRODUCTION The need for transit service improvements in the Routes 42/55/676 corridor was identified during the Southern

More information

Re: DBA Comments Regarding Impact of BRT Dedicated Lanes in Downtown Berkeley

Re: DBA Comments Regarding Impact of BRT Dedicated Lanes in Downtown Berkeley January 28, 2010 City of Berkeley Planning Commission Jordan Harrison, Secretary Land Use Planning Division 2120 Milvia Street, 2nd Floor Berkeley, CA 94704 Dear Planning Commission: Re: DBA Comments Regarding

More information

Speaker: Brian Dranzik, Fiscal & Policy Administrator Milwaukee County

Speaker: Brian Dranzik, Fiscal & Policy Administrator Milwaukee County Milwaukee County Speaker: Brian Dranzik, Fiscal & Policy Administrator Milwaukee County Department of Transportation and Public Works Project coordinated by Milwaukee County Transit System and Southeastern

More information

Station Plan: Penn & 43rd Avenue

Station Plan: Penn & 43rd Avenue Station Plan: Penn & 43rd Avenue This station will serve the northern portion of the Penn Avenue corridor, including the commercial node at 44th Avenue. Ridership and roadway geometry support station siting

More information

Appendix A-2: Screen 1 Alternatives Report

Appendix A-2: Screen 1 Alternatives Report Appendix A-2: Screen 1 Alternatives Report SCREEN 1 ALTERNATIVES REPORT Western & Ashland Corridors Bus Rapid Transit (BRT) Project Prepared for Chicago Transit Authority 567 West Lake Street Chicago,

More information

Topics To Be Covered. Summarize Tier 2 Council Direction Discuss Mill and Ash Alternatives Next Steps

Topics To Be Covered. Summarize Tier 2 Council Direction Discuss Mill and Ash Alternatives Next Steps Topics To Be Covered Summarize Tier 2 Council Direction Discuss Mill and Ash Alternatives Next Steps Tier 2 Council Direction Dismiss Bus Rapid Transit along the Union Pacific Railroad Dismiss Bus Rapid

More information

The Who and What: Bus Rapid Transit Riders and Systems in the U.S.

The Who and What: Bus Rapid Transit Riders and Systems in the U.S. The Who and What: Bus Rapid Transit Riders and Systems in the U.S. Cheryl Thole December 12, 2013 Webinar Center for Urban Transportation Research University of South Florida Pre presentation How familiar

More information

How familiar are you with BRT?

How familiar are you with BRT? The Who and What: Bus Rapid Transit Riders and Systems in the U.S. Cheryl Thole December 12, 2013 Webinar Center for Urban Transportation Research University of South Florida Pre presentation How familiar

More information

WHAT IS BRT? Jack M. Gonsalves, PE, Parsons Brinckerhoff, Inc. February 22, 2012

WHAT IS BRT? Jack M. Gonsalves, PE, Parsons Brinckerhoff, Inc. February 22, 2012 WHAT IS BRT? Jack M. Gonsalves, PE, Parsons Brinckerhoff, Inc. February 22, 2012 What is Bus Rapid Transit (BRT)? A flexible, high performance rapid transit mode that combines a variety of physical, operating,

More information

Bicycle Boulevard Network

Bicycle Boulevard Network Bicycle Boulevard Network Each of the bicycle boulevards is named after the street that it entirely, or in large part, travels along. At times, you ll find that the bicycle boulevard jogs from one street

More information

MOBILITY WORKSHOP. Joint City Council and Transportation Commission May 5, 2014

MOBILITY WORKSHOP. Joint City Council and Transportation Commission May 5, 2014 MOBILITY WORKSHOP Joint City Council and Transportation Commission May 5, 2014 Review of General Plan M-1 Develop world-class transit system M-3 Maintain/enhance pedestrian-oriented City M-4 Create comprehensive

More information

TABLE OF CONTENTS. Executive Summary

TABLE OF CONTENTS. Executive Summary Executive Summary Background... ES-1 Pedestrian Network... ES-2 Bikeway Network... ES-2 Collision History... ES-2 Public Input... ES-4 Conclusions and Recommendations... ES-4 1. Introduction and Setting

More information

Pocatello Regional Transit Master Transit Plan Draft Recommendations

Pocatello Regional Transit Master Transit Plan Draft Recommendations Pocatello Regional Transit Master Transit Plan Draft Recommendations Presentation Outline 1. 2. 3. 4. What is the Master Transit Plan? An overview of the study Where Are We Today? Key take-aways from existing

More information

Community Task Force October 5, 2017

Community Task Force October 5, 2017 Community Task Force October 5, 2017 Welcome and Introductions Project Partners Regional Transportation District (RTD) Colorado Department of Transportation (CDOT) Denver Regional Council of Governments

More information

Memorandum. Fund Allocation Fund Programming Policy/Legislation Plan/Study Capital Project Oversight/Delivery Budget/Finance Contract/Agreement Other:

Memorandum. Fund Allocation Fund Programming Policy/Legislation Plan/Study Capital Project Oversight/Delivery Budget/Finance Contract/Agreement Other: Memorandum Date: November 20, 2017 To: Transportation Authority Board From: Eric Cordoba Deputy Director Capital Projects Subject: 12/5/17 Board Meeting: San Francisco Freeway Corridor Management Study

More information

ALTERNATIVES SCREENING REPORT

ALTERNATIVES SCREENING REPORT VAN NESS AVENUE BUS RAPID TRANSIT (BRT) ALTERNATIVES SCREENING REPORT Revised Draft, 3/28/08 San Francisco County Transportation Authority 1 Introduction The San Francisco County Transportation Authority

More information

Community Task Force March 14, 2018

Community Task Force March 14, 2018 Community Task Force March 14, 2018 Welcome and Introductions Project Partners Regional Transportation District (RTD) City of Aurora Colorado Department of Transportation (CDOT) Denver Regional Council

More information

EL CAMINO REAL BUS RAPID TRANSIT PROJECT

EL CAMINO REAL BUS RAPID TRANSIT PROJECT EL CAMINO REAL BUS RAPID TRANSIT PROJECT Would upgrade the current 522 Rapid Bus to BRT status by making changes to El Camino Real and The Alameda that make transit FAST, FREQUENT AND RELIABLE and make

More information

Southwest Bus Rapid Transit (SW BRT) Functional Planning Study - Executive Summary January 19 LPT ATTACHMENT 2.

Southwest Bus Rapid Transit (SW BRT) Functional Planning Study - Executive Summary January 19 LPT ATTACHMENT 2. Southwest Bus Rapid Transit (SW BRT) Functional Planning Study - Executive Summary 2011 January 19 1 of 19 Introduction This executive summary presents the results of the Southwest Bus Rapid Transit (SW

More information

North Hollywood to Pasadena BRT Corridor Technical Study. Eco-Rapid Transit/Orange Line Development Authority March 8, 2017

North Hollywood to Pasadena BRT Corridor Technical Study. Eco-Rapid Transit/Orange Line Development Authority March 8, 2017 North Hollywood to Pasadena BRT Corridor Technical Study Eco-Rapid Transit/Orange Line Development Authority March 8, 2017 Agenda 1. Background 2. Corridor Review 3. Key Challenge 4. Preliminary BRT Alignments

More information

Grant Applications Due by July 31, 2015: Alameda Countywide Transportation Commission Call for Projects

Grant Applications Due by July 31, 2015: Alameda Countywide Transportation Commission Call for Projects Office of the City Manager ACTION CALENDAR July 14, 2015 To: From: Honorable Mayor and Members of the City Council Christine Daniel, City Manager Submitted by: Andrew Clough, Director, Public Works Subject:

More information

Creating the Future Bruce B Downs Blvd

Creating the Future Bruce B Downs Blvd Creating the Future Bruce B Downs Blvd How things look today May not be how things look in the future. Bruce B Downs PD&E Study 2003 Construction programmed 2009, Palm Springs to Pebble Creek Tampa Rail

More information

VOLUME 5 Technology and Option Evaluation

VOLUME 5 Technology and Option Evaluation VICTORIA REGIONAL RAPID TRANSIT Victoria / West Shore Link VOLUME 5 Technology and Option Evaluation August 2011 Prepared for BC Transit by SNC-Lavalin Inc McElhanney Consulting Services Ltd Errata 1.

More information

Welcome. If you have any questions or comments on the project, please contact:

Welcome. If you have any questions or comments on the project, please contact: Welcome This drop-in public open house is intended to provide information about the Bay Street bike lanes project. This project proposes a dedicated cycling facility along Bay Street between Aberdeen Avenue

More information

Outreach Approach RENEW SF served as the primary liaison with the North Beach community; the Chinatown. Executive Summary

Outreach Approach RENEW SF served as the primary liaison with the North Beach community; the Chinatown. Executive Summary Executive Summary Executive Summary The Columbus Avenue Neighborhood Transportation Study s objective is to identify changes to transportation infrastructure and policies that could enhance the livability

More information

State Road 54/56 Tampa Bay s Northern Loop. The Managed Lane Solution Linking I-75 to the Suncoast Parkway

State Road 54/56 Tampa Bay s Northern Loop. The Managed Lane Solution Linking I-75 to the Suncoast Parkway State Road 54/56 Tampa Bay s Northern Loop The Managed Lane Solution Linking I-75 to the Suncoast Parkway SUNCOAST PARKWAY Both I 75 and the Suncoast Parkway are planning, or in the process of constructing,

More information

Title. Metropolitan Council Transportation Committee December 12, Brad Larson Metro District MnDOT

Title. Metropolitan Council Transportation Committee December 12, Brad Larson Metro District MnDOT Title Metropolitan Council Transportation Committee December 12, 2016 Evaluating the potential for Bus Rapid Transit and MnPASS Express Lanes in the southwest Metro Brad Larson Metro District MnDOT Background

More information

Tulsa Metropolitan Area LONG RANGE TRANSPORTATION PLAN

Tulsa Metropolitan Area LONG RANGE TRANSPORTATION PLAN Tulsa Metropolitan Area LONG RANGE TRANSPORTATION PLAN Indian Nations Council of Governments August 2005 CONTACTING INCOG In developing the Destination 2030 Long Range Transportation Plan, INCOG s Transportation

More information

3.0 PROJECT DESCRIPTION

3.0 PROJECT DESCRIPTION The following section of the Draft EIR contains a description of the proposed Elk Grove Boulevard/SR 99 Interchange Modification project, consistent with the requirements of CEQA Guidelines Section 15124.

More information

Geary Corridor Bus Rapid Transit SFMTA Citizens Advisory Committee

Geary Corridor Bus Rapid Transit SFMTA Citizens Advisory Committee Geary Corridor Bus Rapid Transit SFMTA Citizens Advisory Committee Project Update SAN FRANCISCO COUNTY TRANSPORTATION AUTHORITY SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY August 6, 2015 Project Overview

More information

A District Council of the Urban Land Institute

A District Council of the Urban Land Institute A District Council of the Urban Land Institute Thank you to our sponsors! A District Council of the Urban Land Institute Thank you to our Community Partners! A District Council of the Urban Land Institute

More information

Giles Run Connector Road

Giles Run Connector Road Giles Run Connector Road Laurel Hill Adaptive Reuse Area to Laurel Crest Drive South County Federation Meeting June 14, 2016 History Connector road included in the Laurel Hill Comprehensive Plan amendment

More information

Better Market Street. Engineering, Maintenance & Safety Committee (EMSC) February 28, 2018

Better Market Street. Engineering, Maintenance & Safety Committee (EMSC) February 28, 2018 Better Market Street Engineering, Maintenance & Safety Committee (EMSC) February 28, 2018 1 Market Street Market Street - San Francisco by rulenumberone2 2 Market Street is the... City s busiest pedestrian

More information

RapidRide Roosevelt Seat Sea t t le t le Depa De r pa t r men men t of Sept T an r sp an or sp t or a t t a ion

RapidRide Roosevelt Seat Sea t t le t le Depa De r pa t r men men t of Sept T an r sp an or sp t or a t t a ion RapidRide Roosevelt Seattle Bicycle Advisory Board 1 Our mission, vision, and core values Mission: deliver a high-quality transportation system for Seattle Vision: connected people, places, and products

More information

Appendix B. Environmental Resource Technical Memorandum. Assessment on Travel Pattern and Access Impacts

Appendix B. Environmental Resource Technical Memorandum. Assessment on Travel Pattern and Access Impacts Appendix B Environmental Resource Technical Memorandum Assessment on Travel Pattern and Access Impacts TECHNICAL MEMORANDUM ENVIRONMENTAL RE-EVALUATION FOR UNION STATION TO OAK CLIFF DALLAS STREETCAR To:

More information

Measuring the Distribution and Costs of Congestion. Tim Lomax Texas Transportation Institute

Measuring the Distribution and Costs of Congestion. Tim Lomax Texas Transportation Institute Measuring the Distribution and Costs of Congestion Tim Lomax Texas Transportation Institute http://mobility.tamu.edu The Congestion Measurement Story Travel time, variations, compare to goals WHAT? WHY?

More information

Interim Transit Ridership Forecast Results Technical Memorandum

Interim Transit Ridership Forecast Results Technical Memorandum Interim Transit Ridership 401 South Jackson Street Seattle, WA 98104-2826 September 2012 Table of Contents 1 INTRODUCTION... 1-1 1.1 Project Background... 1-1 2 RIDERSHIP FORECASTS... 2-1 2.1 System Ridership

More information

Southside Pilot Proposal

Southside Pilot Proposal To improve bicycle access and mobility to UC Berkeley, Downtown Berkeley, and the Southside area, a pilot project could include a two-way parking-protected cycle track. Turn pockets and island bus stops

More information

University Hill Transportation Study Technical Memorandum Alternatives Modeling and Analysis May 2007

University Hill Transportation Study Technical Memorandum Alternatives Modeling and Analysis May 2007 Technical Memorandum May 2007 Syracuse Metropolitan Transportation Council Edwards and Kelcey with Wallace Roberts and Todd Alta Planning and Design CONTENTS SECTION ONE- INTRODUCTION...1 SECTION TWO-

More information

Town of Bethlehem. Planning Assessment. Bethlehem Town Board

Town of Bethlehem. Planning Assessment. Bethlehem Town Board Town of Bethlehem US 9W Corridor Transportation Planning Assessment Presented e to: Bethlehem Town Board June 2009 Overview Study Background Route 9W Corridor Conditions and Improvements Selkirk Bypass

More information

North Coast Corridor:

North Coast Corridor: North Coast Corridor: Connecting People, Transportation & Environment Legislative Hearing: 11.8.10 1 North Coast Corridor Region s Lifeline A Regional Strategy Mobility, Economy & Environment North Coast

More information

Technical Working Group November 15, 2017

Technical Working Group November 15, 2017 Technical Working Group November 15, 2017 Welcome and Introductions Project Partners Regional Transportation District (RTD) Colorado Department of Transportation (CDOT) Denver Regional Council of Governments

More information

CITY OF COCOA BEACH 2025 COMPREHENSIVE PLAN. Section VIII Mobility Element Goals, Objectives, and Policies

CITY OF COCOA BEACH 2025 COMPREHENSIVE PLAN. Section VIII Mobility Element Goals, Objectives, and Policies CITY OF COCOA BEACH 2025 COMPREHENSIVE PLAN Section VIII Mobility Element Goals, Objectives, and Policies Adopted August 6, 2015 by Ordinance No. 1591 VIII MOBILITY ELEMENT Table of Contents Page Number

More information

Greater Cleveland Regional Transit Authority

Greater Cleveland Regional Transit Authority Greater Cleveland Regional Transit Authority Transit Priority Corridor Initiatives West 25 th Street /East 105 th /East 93 rd Streets June 20, 2017 Presented to: Planning & Development Committee Greater

More information

Calgary Transit Route 302 Southeast BRT Year One Review June

Calgary Transit Route 302 Southeast BRT Year One Review June Calgary Transit Route 302 Southeast BRT Year One Review 2011 June Calgary Transit Route 302 Southeast BRT: Year One Review 2011 April Table of Contents 1.0 Executive Summary... 1 2.0 Introduction... 3

More information

NY 5 BRT Conceptual Design Study: Study Advisory Committee Meeting 1. with Creighton Manning Engineering, LLP Logitrans Herb Levinson

NY 5 BRT Conceptual Design Study: Study Advisory Committee Meeting 1. with Creighton Manning Engineering, LLP Logitrans Herb Levinson NY 5 BRT Conceptual Design Study: Study Advisory Committee Meeting 1 with Creighton Manning Engineering, LLP Logitrans Herb Levinson September 22, 2003 Overview Introduction to the consultant team Goals

More information

MAYFIELD ROAD CORRIDOR MULTIMODAL TRANSPORTATION PLAN. Public Workshop

MAYFIELD ROAD CORRIDOR MULTIMODAL TRANSPORTATION PLAN. Public Workshop MAYFIELD ROAD CORRIDOR MULTIMODAL TRANSPORTATION PLAN Public Workshop 06.06.18 AGENDA Project Process & Schedule Document Review Summary Project Goals Initial Findings Concept Development Next Steps PROJECT

More information

South King County High-Capacity Transit Corridor Study

South King County High-Capacity Transit Corridor Study HIGH-CAPACITY TRANSIT CORRIDOR STUDY South King County Corridor South King County High-Capacity Transit Corridor Study Corridor Report August 2014 South King County High Capacity Transit Corridor Report

More information

Community Task Force November 15, 2017

Community Task Force November 15, 2017 Community Task Force November 15, 2017 Welcome and Introductions Project Partners Regional Transportation District (RTD) Colorado Department of Transportation (CDOT) Denver Regional Council of Governments

More information

FINAL REPORT DECEMBER 2011

FINAL REPORT DECEMBER 2011 FINAL REPORT DECEMBER 2011 AKNOWLEDGEMENTS SFMTA Staff Erin Miller, Project Manager Timothy Papandreou Jerry Robbins Pamela Stone Mike Sallaberry Chris Dimeling Emily Drennen Suzanne Chen-Harding San

More information

Baseline Road Rapid Transit: Bayshore Station to Prince of Wales Drive

Baseline Road Rapid Transit: Bayshore Station to Prince of Wales Drive Baseline Road Rapid Transit: Bayshore Station to Prince of Wales Drive Planning and Environmental Assessment Study Consultation Group Meetings May 2014 Presentation Agenda Study Overview Study Progress

More information

Service Development 1600 Franklin Street, Oakland CA 94612

Service Development 1600 Franklin Street, Oakland CA 94612 Service Development 1600 Franklin Street, Oakland CA 94612 January 11, 2018 Jeff Bond Community Development Director 1000 San Pablo Avenue Albany, CA 94706 Dear Mr. Bond, AC Transit is requesting that

More information