1 Implementing Complete Streets in Ottawa October 1, 2015

2 The Essentials Complete Streets Implementation Framework will become part of the routine delivery of City transportation projects Approach uses every transportation project as a catalyst for improvements Integrates new approaches including Multi-modal Level of Service 2

3 Background Completed in 2013, Ottawa s Transportation Master Plan included the following actions related to Complete Streets Adopt a complete streets policy for road design, operation and maintenance; Update road design guidelines, standards, and processes to reflect complete streets principles; Use Multi-Modal Levels of Service (MMLOS) to assess road designs and allocate right of way. 3

4 Ottawa s Definition of Complete Streets Complete Streets incorporate the physical elements that allow a street to offer safety, comfort and mobility for all users of the street regardless of their age, ability, or mode of transportation. A Complete Streets approach uses every transportation project as a catalyst for improvements within the scope of that project to enable safe and comfortable access for all users. 4

5 Complete Streets Approach Integrates into the City of Ottawa s routine processes, guidelines and standards for transportation projects Strive first to accommodate the basic needs of all users Strive second to further improve conditions wherever possible within the scope of a transportation project, and with a balanced consideration of relevant plans and policies 5

6 Challenge The City of Ottawa delivers many different types of transportation projects Various branches are responsible for delivering different projects during various phases of the project development 6

7 Solution Goals are identified at project initiation to foster multi-modal and context-sensitive solutions Complete Street elements will align with the scope of transportation projects and Municipal Class Environmental Assessment (MCEA) requirements Key constraints are recognized early in the process, including right-of-way ownership, major utility conflicts, and long-term maintainability Projects will anticipate opportunities to incrementally achieve Complete Streets and networks over time, and in future phases of projects Each project must be budgeted appropriately for implementation of the Complete Street approach 7

8 Supporting Tools Current tools: Master Plans, Planning & Design Guidelines, Accessibility Guidelines for Ontarians with Disabilities, and Construction, Operation & Maintenance Manuals Tools Under Development: Road Design Guidelines project Multi-Modal Level of Service: a new approach to be incorporated into the Transportation Impact Assessment guidelines 8

9 Multi-Modal Level of Service A Custom Approach MMLOS to be used for both City-lead and developer lead projects Substantially simpler than HCM approach Builds on other approaches including PETSI MMLOS Guidelines developed to provide details on the methodology for each mode & provide targets, TIA Guidelines to provide details on how the methodologies are to be applied MMLOS approach is Draft subject to Council approval Oct 7,

10 MMLOS Ranges MODE ELEMENT LEVEL OF SERVICE A B C D E F Pedestrians (PLOS) Bicycles (BLOS) Trucks (PLOS) Transit (TLOS) Segments High level of comfort Low level of comfort Intersections Short delay, high level of comfort, low risk Long delay, low level of comfort, high risk Segments High level of comfort Low level of comfort Intersections Low level of risk / stress High level of risk / stress Segments Unimpeded movement Impeded movement Intersections Unimpeded movement / short delay Impeded movement / long delay Segments High level of reliability Low level of reliability Intersections Short delay Long delay Vehicles (LOS) Intersections Low lane utilization High lane utilization 10

11 PEDESTRIAN LEVEL OF SERVICE OTTAWA COMPLETE STREETS Pedestrian Level of Service (PLOS) Primary intent of the tool is to evaluate pedestrian comfort, safety and convenience 11

12 PLOS Data Requirements SEGMENTS SIGNALIZED INTERSECTIONS» Operating speed» Sidewalk width» Boulevard width» Motor vehicle volume (AADT / lane)» Presence of on-street parking Exposure to Traffic» Street width (number of through lanes to be crossed with or without a median) and presence of refuge island for crossing pedestrians» Right & left turn conflicts based on phasing (permitted, protected/permitted, protected, prohibited) and pedestrian-only phases (leading pedestrian interval)» Right turn on Red (RTOR) restrictions» Corner radius and type (smart right turn channel, right turn channel with receiving lane)» Crosswalk treatment (transverse marking, zebra stripe markings, textured/coloured crosswalks, raised crosswalks) Delay» Cycle length» Pedestrian green time (walk time) 12

13 PLOS Methodology Example for Segments Sidewalk Width (m) Boulevard Width (m) Motor Vehicle Traffic Volume (AADT / lane) Presence of Onstreet Parking Segment PLOS Operating Speed (km/h) 30 >30 or 50 >50 or 60 > N/A A A A B > 2 > 3000 Yes A B B N/A No A B C D 3000 N/A A A A B 2.0 or more 0.5 to 2 > 3000 Yes A B C N/A No A D D E 3000 NA A B C D 0 > 3000 Yes B B D N/A No D D E F 3000 N/A A A A B > 2 > 3000 Yes A B C N/A No A C D E 3000 N/A A B B D to 2 > 3000 Yes A C C N/A No B D E E 3000 N/A A B C D 0 > 3000 Yes B C D N/A No D E F F 3000 N/A C C C C > 2 Yes C C D N/A > 3000 No C E E E N/A C C C D 0.5 to 2 Yes C C D N/A > 3000 No D E E E 0 N/A F 2 F 2 F 2 F 2 < 1.5 N/A F 3 F 3 F 3 F 3 0 N/A 3000 N/A C 4 F F F > 3000 N/A F F F F 13

14 PLOS Methodology Intersections 5.1 Crossing Distance & Conditions Total travel lanes crossed 5.2 Signal Phasing & Timing Features Left turn conflict ("Left_turns") Points Permissive Protected/permissive Protected No left turn/prohibited Right turn conflict ("Right_turns") Points Permissive or yield control Protected/permissive Protected No right turn Right turns on red ("RTOR") Points Island Refuge Points No right turns 0 No -4 RTOR allowed 0 Yes 0 RTOR prohibited at certain time(s) 3 RTOR prohibited Corner Radius Leading ped interval? ("LPI") Points Corner radius Greater than 25m > 15m to 25m > 10m to 15m > 5m to 10m No median With Median (>2.4m) Points No 0-9 Yes Crosswalk Treatment Crosswalk treatment ("Crosswalk") Points > 3m to 5m Less than/equal to 3m -3 Standard transverse markings -7 No right turn 0 Textured/coloured pavement -4 Right turn channel with receiving -3 Zebra stripe hi-vis markings -4 Right turn "smart channel" 2 Raised crosswalk 0 Exhibit 1 PETSI Evaluation Table Pedestrian Exposure to Traffic LOS Points threshold LOS 90 A 75 B 60 C 45 D 30 E <30 F Exhibit 2 Pedestrian Delay Evaluation Table Average Pedestrian Crossing Delay Component Delay = < 10 s per intersection leg LOS A 10 to 20 sec LOS B >20 to 30 sec LOS C >30 to 40 sec LOS D >40 to 60 sec LOS E > 60 sec LOS F 14

15 PLOS Methodology - Segments Sidewalks 1.8m + Streets with low volume ( 3000 AADT) or low operating speeds ( 30 km/hr) Sidewalks m adjacent to roads with high operating speeds (typically <50 or 60) and higher volumes Sidewalks 1.5m with boulevards No sidewalk or substandard width Sidewalk adjacent to high volume, high speed roadways without any boulevard 15

16 PLOS Methodology - Signals Segments 4 lanes to be crossed assuming no major penalties 4-6 lanes to be crossed assuming no major penalties Delay <10s per intersection leg >20 to 30s 6 to 10+ lanes to be crossed depending on penalties >60s Penalties: large corner radii, unfavourable signal phasing, etc. 16

17 BICYCLE LEVEL OF SERVICE OTTAWA COMPLETE STREETS Bicycle Level of Service (BLOS) Primary intent of the tool is to evaluate the level of traffic stress (or degree of comfort) experienced by a cyclist Methodology is based on the Mineta Transportation Institute report, but adapted to City of Ottawa LOS A-F 17

18 BLOS Data Requirements SEGMENTS SIGNALIZED INTERSECTIONS Mixed Traffic (No cycling facility) Pocket bike lanes» Street width (total number of lanes in both directions)» Operating speed Bike Lanes» Street width (number of through lanes per direction)» Bike lane width (including marked buffer and paved gutter width)» Parking lane width (where bike lane is adjacent to parking lane)» Operating speed» Qualitative assessment of commercial deliveries for commercial areas Physically Separated Bikeway» Right turn lane characteristics (number of right turn lanes, length of turn lane, turning speed)» Operating speed» Left turn accommodation (presence of bike box, number of left turn lanes, number of lanes crossed) Mixed Traffic (No cycling facility)» Right turn lane characteristics (number of right turn lanes, length of turn lane, turning speed)» Operating speed» Left turn accommodation (presence of bike box, number of left turn lanes, number of lanes crossed)» No additional information needed Unsignalized Crossings» Presence of median refuge suitable for bicycle storage ( 1.8m wide)» Width of street being crossed (number of lanes in both directions)» Speed limit of street being crossed 18

19 BLOS Methodology Segments Physically separated bikeway Wide bike lanes on 2-lane roads with low operating speed ( km/h depending on parking lanes) Mixed traffic on 2-lane low speed residential streets Narrow bike lanes on roads with >2 lanes and higher speeds (60 km/h) Frequent bike lane blockage due to commercial activity Mixed traffic on high speed roads ( 60km/h) High stress unsignalized crossings (4+ lane roads with higher speeds) 19

20 BLOS Methodology Signals Left turn bike boxes provided for left turns No right-turn lanes or right-turn lanes to the left of cycling infrastructure 0-1 lane crossed to make a left turn at moderate speeds Short, low speed right-turn lane where cycling facilities are provided 2 or more lanes crossed to make a left turn with speeds 50 km/h Long / dual right-turn lanes 20

21 TRUCK LEVEL OF SERVICE OTTAWA COMPLETE STREETS Truck Level of Service (TkLOS) Primary intent of the tool is to complement motor vehicle LOS by considering the physical space available for trucks to negotiate corners quickly and easily, and to operate safely within travelled lanes 21

22 TkLOS Data Requirements SEGMENTS SIGNALIZED INTERSECTIONS» Street width (number of through lanes per direction)» Curb lane width (m)» Effective radius» Number of receiving lanes on departing leg of intersection 22

23 TkLOS Methodology Segments Curb lane width 3.5m+ Two travel lanes Curb lane width 3.3m with two travel lanes One travel lane width 3.5m One travel lane width <3m Signalized Intersections Effective radius >15m with more than one receiving lane Effective radius >15m with one receiving lane Effective radius <10m with one receiving lane 23

24 TRANSIT LEVEL OF SERVICE OTTAWA COMPLETE STREETS Transit Level of Service (TLOS) Primary intent of the tool is to evaluate the relative attractiveness of transit based on transit travel time and the transit priority afforded to transit vehicles 24

25 TLOS Data Requirements SEGMENTS SIGNALIZED INTERSECTIONS» Level/exposure to congestion delay, friction, and incidents (qualitative assessment)» Average Signal Delay» Average transit travel speed» Posted speed limit» Number of driveways along corridor and approximate crossing volume 25

26 TLOS Methodology - Segments Notes: Bus lane Mixed Traffic Facility Type Segregated ROW Level/exposure to congestion delay, friction and incidents Incident Congestion Friction Potential No No No N/A A No/limited parking/driveway friction No Low Low C f 60 B Frequent parking/driveway friction No Medium Medium C f > 60 C Limited parking/driveway friction Yes Low Medium Vt/Vp 0.8 D Moderate parking/driveway friction Yes Medium Medium Vt/Vp 0.6 E Frequent parking/driveway friction Yes High High Vt/Vp < 0.4 F Cf, Conflict Factor = = (Number of driveways x crossing volume) / 1 km Vt/Vp is the ratio of average transit travel speed to posted speed limit Quantitative Measurement LOS 26

27 TLOS Methodology Segments Segregated ROW Signalized Intersections Grade separated crossing (Delay = 0s) Bus lane with frequent parking / driveway friction (C f > 60) Mid-level TSP (Delay 20 sec) Mixed traffic w/ high friction Ratio of average transit travel speed to posted speed limit < 0.4 No TSP & long cycle length (Delay >40s) 27

28 AUTO LOS OTTAWA COMPLETE STREETS Auto LOS Methodology remains consistent with what is currently provided in the TIA 28

29 Targets & Tradeoffs 29

30 Ultimate objective of developing a MMLOS program is to enable designers, City staff and the public to evaluate and understand transportation choices Towards this end, modal level of service targets have been developed Targets must cover a wide range of conditions (i.e. varying built form and context) and therefore should be considered to provide broad guidance rather than absolute cut-offs Targets are likely to shift over time as they are better calibrated to reflect outcomes and initiatives 30

31 Targets Official Plan Designation / Land Use Central Area / Mixed Use Pedestrian Bicycle Transit Truck Automobile PLOS BLOS TLOS TrLOS MVLOS Centres High High High Low Low Transit Station Areas High High High Low Low School Areas High High Medium Low Low Traditional Main Streets High Medium Medium Low Low Arterial Main Streets Medium Medium Medium Medium Medium General Urban / Village Areas Medium Medium Medium Low Low Rapid Transit Corridors Medium Medium High Low Low Transit Priority Corridors Medium Medium Medium Low Low Crosstown Bike Routes N.A. High N.A. N.A. N.A. Bike Spine Routes N.A. Medium N.A. N.A. N.A. Truck Routes N.A. N.A. N.A. High N.A. 1 Values represent minimum targets to be exceeded wherever possible without negatively impacting other modes. 2 Not Applicable (N.A.) General Rural Areas Low Low N.A. Medium Medium 31

32 Summary Small changes to processes should yield big dividends for Complete Streets Adopting MMLOS will support decision making process around trade-offs Approaches do not replace need for good planning and design 32

City of Ottawa s Complete Streets Approach to Transportation Projects

City of Ottawa s Complete Streets Approach to Transportation Projects City of Ottawa s Complete Streets Approach to Transportation Projects Presentation to Stakeholders Date: May 5, 2015 Presentation Overview Purpose of the study Proposed definition of Complete Streets for

More information

Alta Planning + Design

Alta Planning + Design Alta Planning + Design Gavin Davidson, MCIP, RPP Principal, Senior Planner Vancouver Kate Whitfield, P.Eng., MCIP, RPP Senior Associate Engineer/Planner Ottawa Ottawa, Ontario, Canada Ottawa Toronto Syracuse

More information

1223 Michael Street, Suite 100, Ottawa, Ontario, K1J 7T2 P: l F: l

1223 Michael Street, Suite 100, Ottawa, Ontario, K1J 7T2 P: l F: l 1223 Michael Street, Suite 100, Ottawa, Ontario, K1J 7T2 P: +1 613.738.4160 l F: +1 613.739.7105 l www.parsons.com City of Ottawa 2017 TIA Guidelines Date July 3, 2018 TIA Screening Form Project 116 York

More information

10.0 CURB EXTENSIONS GUIDELINE

10.0 CURB EXTENSIONS GUIDELINE 10.0 CURB EXTENSIONS GUIDELINE Road Engineering Design Guidelines Version 1.0 March 2017 City of Toronto, Transportation Services City of Toronto Page 0 Background In early 2014, Transportation Services

More information

2.0 LANE WIDTHS GUIDELINE

2.0 LANE WIDTHS GUIDELINE 2.0 LANE WIDTHS GUIDELINE Road Engineering Design Guidelines Version 2.0.1 May 2018 City of Toronto, Transportation Services City of Toronto Page 0 Background In early 2014, Transportation Services initiated

More information

Bicycle and Pedestrian Connectivity Study. Old Colony Planning Council

Bicycle and Pedestrian Connectivity Study. Old Colony Planning Council Bicycle and Pedestrian Connectivity Study Old Colony Planning Council Outline Why consider bike/peds in road designs? Why are measures needed? Connecting Land Use with Transportation Evaluation Tools:

More information

Active Transportation Facility Glossary

Active Transportation Facility Glossary Active Transportation Facility Glossary This document defines different active transportation facilities and suggests appropriate corridor types. Click on a facility type to jump to its definition. Bike

More information

Bicycle Facilities Planning

Bicycle Facilities Planning Bicycle Facilities Planning Overview Types of Cyclists Purpose for Riding Types of Facilities Bike Lanes Bicycle Boulevards Cycle Tracks Intersections Signals Signing and Marking Discussion Types of Bicyclists

More information

APPENDIX A: Complete Streets Checklist DRAFT NOVEMBER 2016

APPENDIX A: Complete Streets Checklist DRAFT NOVEMBER 2016 APPENDIX A: Complete Streets Checklist DRAFT NOVEMBER 2016 Complete Streets Checklist MetroPlan Orlando s Complete Streets Checklist is an internal planning tool for staff to further implementation of

More information

Classification Criteria

Classification Criteria SCHEDULE D TO RECOMMENDED OFFICIAL PLAN AMENDMENT NO. 40 SCHEDULE C-4 Road Criteria Criteria Traffic Service Objective Land Service/Access Typical Daily Traffic Volume Flow characteristics Travel Speed

More information

El Camino Real Specific Plan. TAC/CAC Meeting #2 Aug 1, 2018

El Camino Real Specific Plan. TAC/CAC Meeting #2 Aug 1, 2018 El Camino Real Specific Plan TAC/CAC Meeting #2 Aug 1, 2018 Land Use Alternatives Goals and Tradeoffs Parks & open space Housing Retail & services Civic spaces Parking Community gathering spaces 3 Alternatives

More information

Appendix 3 Roadway and Bike/Ped Design Standards

Appendix 3 Roadway and Bike/Ped Design Standards Appendix 3 Roadway and Bike/Ped Design Standards OTO Transportation Plan 2040 4/20/2017 Page A3-1 Adopted Standards The adopted OTO Design Standards and Major Thoroughfare Plan are contained herein.

More information

9/25/2018. Multi-Modal Level of Service (MMLOS) Bianca Popescu, Transportation Planner

9/25/2018. Multi-Modal Level of Service (MMLOS) Bianca Popescu, Transportation Planner Multi-Modal Level of Service (MMLOS) Bianca Popescu, Transportation Planner 1 What is MMLOS? Is this a nice place to walk? Is this a nice place to bike? Is transit convenient? Bottom line - Are there options

More information

AMATS Complete Streets Policy

AMATS Complete Streets Policy AMATS Complete Streets Policy Table of Contents: Section 1. Definition of Complete Streets Section 2. Principles of Complete Streets Section 3. Complete Streets Policy Section 4. Consistency Section 5.

More information

Moving Cambridge. City of Cambridge Transportation Master Plan Public Consultation Centre. March 7, :00 8:00 PM.

Moving Cambridge. City of Cambridge Transportation Master Plan Public Consultation Centre. March 7, :00 8:00 PM. City of Cambridge Transportation Master Plan Public Consultation Centre March 7, 2018 5:00 8:00 PM Region of Waterloo City of Cambridge Transportation Master Plan Public Consultation Centre March 7, 2018

More information

BLUE SEA VILLAGE MER BLEUE 2159 MER BLEUE ROAD OTTAWA, ONTARIO TRANSPORTATION IMPACT ASSESSMENT. Prepared for: Ontario Limited.

BLUE SEA VILLAGE MER BLEUE 2159 MER BLEUE ROAD OTTAWA, ONTARIO TRANSPORTATION IMPACT ASSESSMENT. Prepared for: Ontario Limited. BLUE SEA VILLAGE MER BLEUE 2159 MER BLEUE ROAD OTTAWA, ONTARIO TRANSPORTATION IMPACT ASSESSMENT Prepared for: 2534189 Ontario Limited April 6, 2018 117-668 TIA Report_2.doc D. J. Halpenny & Associates

More information

Cycle Track Design Best Practices Cycle Track Sections

Cycle Track Design Best Practices Cycle Track Sections Design Best Practices Sections It is along street segments where the separation and protection methods of cycle tracks offer more comfort than conventional bicycle lanes, and are more attractive to a wide

More information

APPENDIX 2 LAKESHORE ROAD TRANSPORTATION REVIEW STUDY EXECUTIVE SUMMARY

APPENDIX 2 LAKESHORE ROAD TRANSPORTATION REVIEW STUDY EXECUTIVE SUMMARY APPENDIX 2 LAKESHORE ROAD TRANSPORTATION REVIEW STUDY EXECUTIVE SUMMARY Appendix 2 City of Mississauga Lakeshore Road FINAL REPORT Transportation Review Study December 2010 EXECUTIVE SUMMARY Study Purpose

More information

Access Management in the Vicinity of Intersections

Access Management in the Vicinity of Intersections Access Management in the Vicinity of Intersections FHWA-SA-10-002 Technical Summary Photo: Ralph Bentley (used with permission) 0 Access Management is: The design, implementation and management of entry

More information

Document 2 - City of Ottawa Pedestrian Crossover (PXO) Program

Document 2 - City of Ottawa Pedestrian Crossover (PXO) Program 40 Document 2 - City of Ottawa Pedestrian Crossover (PXO) Program OVERVIEW The City of Ottawa Pedestrian Crossover (PXO) Program provides the basis for PXO implementation in Ottawa. The program s processes

More information

Complete Streets: Planning, Policy & Performance

Complete Streets: Planning, Policy & Performance Complete Streets: Planning, Policy & Performance Tell Us About Your CS Experiences Successes Hardships Funding Politics Safety Not every street needs to be complete, but every mode needs a complete network.

More information

Long Island Rail Road Expansion Project Floral Park to Hicksville

Long Island Rail Road Expansion Project Floral Park to Hicksville Long Island Rail Road Expansion Project Floral Park to Hicksville Final Environmental Impact Statement Appendix 1-D Complete Streets Policy Checklist April 2017 0902ML PIN: Project Location: 18A-4 Floral

More information

Agenda. Overview PRINCE GEORGE S PLAZA METRO AREA PEDESTRIAN PLAN

Agenda. Overview PRINCE GEORGE S PLAZA METRO AREA PEDESTRIAN PLAN PRINCE GEORGE S PLAZA METRO AREA PEDESTRIAN PLAN May 28, 2008 Agenda Welcome and introductions Project overview and issue identification Planning context and strengths Design challenges and initial recommendations

More information

Off-road Trails. Guidance

Off-road Trails. Guidance Off-road Trails Off-road trails are shared use paths located on an independent alignment that provide two-way travel for people walking, bicycling, and other non-motorized users. Trails specifically along

More information

PRINCE GEORGE S PLAZA METRO AREA PEDESTRIAN PLAN

PRINCE GEORGE S PLAZA METRO AREA PEDESTRIAN PLAN PRINCE GEORGE S PLAZA METRO AREA PEDESTRIAN PLAN May 28, 2008 Agenda Welcome and introductions Project overview and issue identification Planning context and strengths Design challenges and initial recommendations

More information

SECTION 1 - TRAFFIC PLANNING

SECTION 1 - TRAFFIC PLANNING SECTION 1 - TRAFFIC PLANNING 1.1 TRAFFIC OPERATIONS 1.1.1 Roadway Functional Classification The Multnomah County Comprehensive Framework Plan s Policy 34: Trafficways and the Functional Classification

More information

What Is a Complete Street?

What Is a Complete Street? Session 5 Charleen Zimmer, AICP, Zan Associates May 5-7, 2010 What Is a Complete Street? May 2010 5-1 Not a Complete Street More of a Complete Street May 2010 5-2 Benefits of Complete Streets Safety for

More information

Moving Towards Complete Streets MMLOS Applications

Moving Towards Complete Streets MMLOS Applications Moving Towards Complete Streets MMLOS Applications Transportation Education Series May 18 th, 2012 It s not just for cars! Presentation Overview The Complete Streets Movement What is Multi-Modal Level

More information

Broad Street Bicycle Boulevard Design Guidelines

Broad Street Bicycle Boulevard Design Guidelines Broad Street Bicycle Boulevard Design Guidelines Building from the strategies introduced in the 2013 Bicycle Transportation Plan and community input received thus far, City Transportation Staff have identified

More information

Downey Road. Transportation Improvement Study

Downey Road. Transportation Improvement Study Downey Road Transportation Improvement Study Workshop 2 Participant Handbook Workshop 1 May 18 and 19, 2016 Workshop 2 June 23 and 28, 2016 Prepared By: City of Guelph Paradigm Transportation Solutions

More information

Environment and Public Works Committee Presentation

Environment and Public Works Committee Presentation Mixed Use Centers Complete Streets Guidelines Project Environment and Public Works Committee Presentation December 10, 2008 Project Objectives: Conduct an inter-departmental and agency process to study

More information

Dr. M.L. King, Jr. Street North Complete Streets Resurfacing Opportunities HOUSING, LAND USE, AND TRANSPORTATION COMMITTEE MARCH 22, 2018

Dr. M.L. King, Jr. Street North Complete Streets Resurfacing Opportunities HOUSING, LAND USE, AND TRANSPORTATION COMMITTEE MARCH 22, 2018 Dr. M.L. King, Jr. Street North Complete Streets Resurfacing Opportunities HOUSING, LAND USE, AND TRANSPORTATION COMMITTEE MARCH 22, 2018 What s Happening The City plans to mill and resurface Dr. M.L.

More information

Elmvale Acres Shopping Centre Redevelopment

Elmvale Acres Shopping Centre Redevelopment May 2017 Elmvale Acres Shopping Centre Redevelopment Community Transportation Study / Transportation Impact Study GoogleEarth 2015 Prepared for: Prepared by: Elmvale Acres Shopping Centre Redevelopment

More information

TOWN OF PORTLAND, CONNECTICUT COMPLETE STREETS POLICY

TOWN OF PORTLAND, CONNECTICUT COMPLETE STREETS POLICY TOWN OF PORTLAND, CONNECTICUT COMPLETE STREETS POLICY I. VISION, GOALS & PRINCIPLES VISION To improve the streets of Portland making them safer and more accessible for all users including pedestrians,

More information

Cycling and risk. Cycle facilities and risk management

Cycling and risk. Cycle facilities and risk management Cycling and risk Cycle facilities and risk management Failure to recognize possibilities is the most dangerous and common mistake one can make. Mae Jemison, astronaut 6/11/2010 York Regional Council Cycling

More information

Omaha s Complete Streets Policy

Omaha s Complete Streets Policy Omaha s Complete Streets Policy (Adopted August 2015) VISION To create great places and enhance our quality of life, the City of Omaha will provide safe, accessible streets for all users. Complete Streets

More information

Welcome. If you have any questions or comments on the project, please contact:

Welcome. If you have any questions or comments on the project, please contact: Welcome This drop-in public open house is intended to provide information about the Bay Street bike lanes project. This project proposes a dedicated cycling facility along Bay Street between Aberdeen Avenue

More information

Exhibit 1 PLANNING COMMISSION AGENDA ITEM

Exhibit 1 PLANNING COMMISSION AGENDA ITEM Exhibit 1 PLANNING COMMISSION AGENDA ITEM Project Name: Grand Junction Circulation Plan Grand Junction Complete Streets Policy Applicant: City of Grand Junction Representative: David Thornton Address:

More information

Zlatko Krstulich, P.Eng. City of O9awa

Zlatko Krstulich, P.Eng. City of O9awa Zlatko Krstulich, P.Eng. City of O9awa 1. Introduction to the Ontario Traffic Manual Series 2. What is OTM Book 18: Bicycle Facilities? 3. Study / Committee Team Members 4. Brief overview of the content

More information

Circulation in Elk Grove includes: Motor vehicles, including cars and trucks

Circulation in Elk Grove includes: Motor vehicles, including cars and trucks Circulation, as it is used in this General Plan, refers to the many ways people and goods move from place to place in Elk Grove and the region. Circulation in Elk Grove includes: Motor vehicles, including

More information

Young Researchers Seminar 2011

Young Researchers Seminar 2011 Young Researchers Seminar 2011 Young Researchers Seminar 2011 DTU, Denmark, 8 10 June, 2011 DTU, Denmark, June 8-10, 2011 Methods for assessing the pedestrian level of service: International experience

More information

IBI Group November 5, 2012

IBI Group November 5, 2012 IBI Group Agenda Session 1 3:00 PM Welcome / Sign in 3:10 PM Presentation 3:30 PM Questions? 3:35 PM World Café Discussion 4:45 PM Report on top 3 ideas 4:50 PM Next Steps 5:00 PM Adjourn 2 Agenda Session

More information

Complete Street Analysis of a Road Diet: Orange Grove Boulevard, Pasadena, CA

Complete Street Analysis of a Road Diet: Orange Grove Boulevard, Pasadena, CA Complete Street Analysis of a Road Diet: Orange Grove Boulevard, Pasadena, CA Aaron Elias, Bill Cisco Abstract As part of evaluating the feasibility of a road diet on Orange Grove Boulevard in Pasadena,

More information

Cyclists and Bikeways: What s your match? A guide to bikeway options for a variety of cyclists

Cyclists and Bikeways: What s your match? A guide to bikeway options for a variety of cyclists Cyclists and Bikeways: What s your match? guide to bikeway options for a variety of cyclists The workshop and this resource were made possible by funding from the Province of Ontario via the Ministry of

More information

DRAFT - CITY OF MEDFORD TRANSPORTATION SYSTEM PLAN Roadway Cross-Sections

DRAFT - CITY OF MEDFORD TRANSPORTATION SYSTEM PLAN Roadway Cross-Sections Roadway Cross-Sections Medford s roadway cross-section standards apply to new and reconstructed roads. The crosssections take into consideration roadway function and operational characteristics, including

More information

Simulation Analysis of Intersection Treatments for Cycle Tracks

Simulation Analysis of Intersection Treatments for Cycle Tracks Abstract Simulation Analysis of Intersection Treatments for Cycle Tracks The increased use of cycle tracks also known as protected bike lanes has led to investigations of how to accommodate them at intersections.

More information

Goodlettsville Bicycle and Pedestrian Plan Executive Summary

Goodlettsville Bicycle and Pedestrian Plan Executive Summary Goodlettsville Bicycle and Pedestrian Plan July 2010 In Cooperation with the Nashville Area Metropolitan Planning Executive Organization Summary Introduction Progressive and forward thinking communities

More information

MAG Town of Cave Creek Bike Study Task 6 Executive Summary and Regional Significance Report

MAG Town of Cave Creek Bike Study Task 6 Executive Summary and Regional Significance Report Page 1 MAG Town of Cave Creek Bike Study Task 6 Executive Summary and Regional Significance Report August 1, 2012 MAG Project #481 Page 2 Task 6 Executive Summary and Regional Significance Report Introduction

More information

REGIONAL BICYCLE AND PEDESTRIAN DESIGN GUIDELINES

REGIONAL BICYCLE AND PEDESTRIAN DESIGN GUIDELINES REGIONAL BICYCLE AND PEDESTRIAN DESIGN GUIDELINES November 16, 2011 Deb Humphreys North Central Texas Council of Governments Bicycle and Pedestrian Advisory Committee Snapshot of the Guide 1. Introduction

More information

Proposed. City of Grand Junction Complete Streets Policy. Exhibit 10

Proposed. City of Grand Junction Complete Streets Policy. Exhibit 10 Proposed City of Grand Junction Complete Streets Policy Exhibit 10 1 City of Grand Junction Complete Streets Policy Vision: The Complete Streets Vision is to develop a safe, efficient, and reliable travel

More information

In station areas, new pedestrian links can increase network connectivity and provide direct access to stations.

In station areas, new pedestrian links can increase network connectivity and provide direct access to stations. The Last Mile Planning for Pedestrians Planning around stations will put pedestrians first. Making walking to stations safe and easy is important; walking will be a part of every rapid transit Accessible

More information

CITY OF OTTAWA ROADWAY MODIFICATION APPROVAL UNDER DELEGATED AUTHORITY

CITY OF OTTAWA ROADWAY MODIFICATION APPROVAL UNDER DELEGATED AUTHORITY RMA-2015-ATM-038 CITY OF OTTAWA ROADWAY MODIFICATION APPROVAL UNDER DELEGATED AUTHORITY DATE: April 22, 2015 SUBJECT Approval of Roadway Modifications Recommended through an Area Traffic Management Study

More information

5. RUNNINGWAY GUIDELINES

5. RUNNINGWAY GUIDELINES 5. RUNNINGWAY GUIDELINES These guidelines should be considered collectively when making runningway decisions. A runningway is the linear component of the transit system that forms the right-of-way reserved

More information

NJDOT Complete Streets Checklist

NJDOT Complete Streets Checklist Background The New Jersey Department of Transportation s Complete Streets Policy promotes a comprehensive, integrated, connected multi-modal network by providing connections to bicycling and walking trip

More information

Chapter 3 DESIGN SPECIFICATIONS

Chapter 3 DESIGN SPECIFICATIONS Brampton PathWays Planning and Design Guidelines 27 Chapter 3 DESIGN SPECIFICATIONS 3.1 CLASS 1 MULTI-USE PATH Off-road multi-use trails are the backbone of the Brampton PathWays Network. They are typically

More information

BICYCLE LEVEL OF SERVICE for URBAN STREETS. Prepared by Ben Matters and Mike Cechvala. 4/16/14 Page 1

BICYCLE LEVEL OF SERVICE for URBAN STREETS. Prepared by Ben Matters and Mike Cechvala. 4/16/14 Page 1 BICYCLE LEVEL OF SERVICE for URBAN STREETS Prepared by Ben Matters and Mike Cechvala 4/16/14 Page 1 Introduction The methodology used for the Bicycle (BLOS) analysis is from the Highway Capacity Manual

More information

TRAFFIC CALMING GUIDE FOR TORONTO CITY OF TORONTO TRANSPORTATION SERVICES DIVISION

TRAFFIC CALMING GUIDE FOR TORONTO CITY OF TORONTO TRANSPORTATION SERVICES DIVISION TRAFFIC CALMING GUIDE FOR TORONTO CITY OF TORONTO TRANSPORTATION SERVICES DIVISION CITY OF TORONTO TRANSPORTATION SERVICES DIVISION 2016 TRAFFIC CALMING GUIDE FOR TORONTO TABLE OF CONTENTS Introduction

More information

Multimodal Analysis in the 2010 Highway Capacity Manual

Multimodal Analysis in the 2010 Highway Capacity Manual Multimodal Analysis in the 2010 Highway Capacity Manual It s not just cars anymore! Jamie Parks, AICP HCAT Conference May 9-10, 2011 Multimodal LOS in the 2010 HCM History and background Overview of methods

More information

Transportation Planning Division

Transportation Planning Division Transportation Planning Division Presentation Outline Study Tasks Recap of Previous Meetings Data Collected Focus Areas within Study Limits Design Principles Tool Box Recommended Concepts Schedule Moving

More information

Who is Toole Design Group?

Who is Toole Design Group? 2018 AASHTO Bike Guide Status Update NCHRP 15 60 Amalia Leighton Cody, PE, AICP & Kenneth Loen, PE Washington APWA October 4, 2018 Who is Toole Design Group? TDG is a full service engineering, planning

More information

CURBSIDE ACTIVITY DESIGN

CURBSIDE ACTIVITY DESIGN 5 CURBSIDE ACTIVITY DESIGN This chapter provides design guidance for separated bike lanes adjacent to curbside activities including parking, loading and bus stops. Typical configurations are presented

More information

Recommended Roadway Plan Section 2 - Land Development and Roadway Access

Recommended Roadway Plan Section 2 - Land Development and Roadway Access Recommended Roadway Plan Section 2 - Land Development and Roadway Access SECTION 2 Land Development and Roadway Access 2.1 Land Use and Access Management The Federal Highway Administration (FHWA) defines

More information

TRAFFIC IMPACT ANALYSIS

TRAFFIC IMPACT ANALYSIS TRAFFIC IMPACT ANALYSIS FOR THE CHAMPAIGN UNIT#4 SCHOOL DISTRICT PROPOSED HIGH SCHOOL (SPALDING PARK SITE) IN THE CITY OF CHAMPAIGN Final Report Champaign Urbana Urbanized Area Transportation Study 6/24/2014

More information

Report. Typical Sections. City of Middleton, WI

Report. Typical Sections. City of Middleton, WI Report Typical Sections City of Middleton, WI December 2006 Report for City of Middleton, Wisconsin Typical Sections repared by: Traffic Associates LLC and STRAND ASSOCIATES, INC. 910 West Wingra Drive

More information

485 Ancaster Avenue. Transportation Impact Assessment. Engineering. Planning. Landscape Architecture

485 Ancaster Avenue. Transportation Impact Assessment. Engineering. Planning. Landscape Architecture Engineering Land / Site Development Municipal Infrastructure Environmental / Water Resources Traffic / Transportation Structural Recreational 485 Ancaster Avenue Transportation Impact Assessment Planning

More information

Complete Streets: Policy Framework Complete Streets: Implementation Plans A more Complete Street: Laurier Bike Lane Pilot Project

Complete Streets: Policy Framework Complete Streets: Implementation Plans A more Complete Street: Laurier Bike Lane Pilot Project Complete Streets Initiatives City of Ottawa Complete Streets: Policy Framework Complete Streets: Implementation Plans A more Complete Street: Laurier Bike Lane Pilot Project Zlatko.Krstulic@Ottawa.ca May

More information

5/31/2016 VIA . Arwen Wacht City of Sacramento Community Development Department 300 Richards Blvd., 3 rd Floor Sacramento, CA 95811

5/31/2016 VIA  . Arwen Wacht City of Sacramento Community Development Department 300 Richards Blvd., 3 rd Floor Sacramento, CA 95811 5/31/2016 VIA EMAIL Arwen Wacht City of Sacramento Community Development Department 300 Richards Blvd., 3 rd Floor Sacramento, CA 95811 RE: El Pollo Loco (P16-028) Dear Ms. Wacht: WALKSacramento has reviewed

More information

COMPLETE STREETS CHECKLIST City of Philadelphia The City of Philadelphia's Complete Streets policies are designed ensure that city streets are safe, comfortable and convenient for people of all ages and

More information

Complete Streets Policy DAVID CRONIN, P.E., CITY ENGINEER

Complete Streets Policy DAVID CRONIN, P.E., CITY ENGINEER Complete Streets Policy DAVID CRONIN, P.E., CITY ENGINEER Complete Streets City Commission adopted a Complete Streets policy in 2012 Complete Streets are road networks that are designed for all users:

More information

INDOT Complete Streets Guideline & Policy

INDOT Complete Streets Guideline & Policy INDOT Complete Streets Guideline & Policy INTRODUCTION The Complete Streets guidelines build upon multiple efforts and promote a multimodal transportation system that is integrated and sustains land use

More information

Transportation Master Plan Advisory Task Force

Transportation Master Plan Advisory Task Force Transportation Master Plan Advisory Task Force Network Alternatives & Phasing Strategy February 2016 BACKGROUND Table of Contents BACKGROUND Purpose & Introduction 2 Linking the TMP to Key Council Approved

More information

West Dimond Blvd Upgrade Jodhpur Street to Sand Lake Road

West Dimond Blvd Upgrade Jodhpur Street to Sand Lake Road West Dimond Blvd Jodhpur St to Sand Lake CSS Transportation Project Summary Municipality of Anchorage Project # 05 005 Project Manager: John Smith, P.E. (MOA PM&E) Project Administrator: Julie Makela,

More information

Road Diets FDOT Process

Road Diets FDOT Process Florida Department of TRANSPORTATION Road Diets FDOT Process Humberto Castillero, PE, PTOE Roadway Design Office Purpose of Guide Develop a statewide lane elimination review process Balance state & local

More information

INDEX. Geometric Design Guide for Canadian Roads INDEX

INDEX. Geometric Design Guide for Canadian Roads INDEX Acceleration lane, see Lanes, Acceleration Access, 8.1 Access Management and Functional Classification 8.2 Access Management by Design Classification 8.3 Access Configuration 8.4 Building Set-Back Guidelines

More information

Improving Cyclist Safety at the Dundas Street West and Sterling Road Intersection

Improving Cyclist Safety at the Dundas Street West and Sterling Road Intersection STAFF REPORT ACTION REQUIRED Improving Cyclist Safety at the Dundas Street West and Sterling Road Intersection Date: August 17, 2012 To: From: Wards: Reference Number: Public Works and Infrastructure Committee

More information

Bellevue Transportation: Challenges, Opportunities and Priorities Bellevue Downtown Association September 20, 2018

Bellevue Transportation: Challenges, Opportunities and Priorities Bellevue Downtown Association September 20, 2018 Bellevue Transportation: Challenges, Opportunities and Priorities Bellevue Downtown Association September 20, 2018 Dave Berg Transportation Director City of Bellevue Traffic, traffic and more traffic!

More information

Balancing Operation & Safety for Motorized and Non-Motorized Traffic

Balancing Operation & Safety for Motorized and Non-Motorized Traffic Balancing Operation & Safety for Motorized and Non-Motorized Traffic Brian Willham, PE, PTOE Iowa Director - MOVITE June 30, 2014 Learning Objectives: When & Why should we measure the performance of complete

More information

5/7/2013 VIA . RE: University Village Safeway Expansion (P13-019)

5/7/2013 VIA  . RE: University Village Safeway Expansion (P13-019) 5/7/2013 VIA EMAIL David Hung, Associate Planner Community Development Department, Current Planning Division City of Sacramento 300 Richards Boulevard, 3 rd Floor Sacramento, CA 95811 RE: University Village

More information

CITY OF HAMILTON PLANNING AND ECONOMIC DEVELOPMENT DEPARTMENT Transportation Planning and Parking Division

CITY OF HAMILTON PLANNING AND ECONOMIC DEVELOPMENT DEPARTMENT Transportation Planning and Parking Division CITY OF HAMILTON PLANNING AND ECONOMIC DEVELOPMENT DEPARTMENT Transportation Planning and Parking Division TO: Chair and Members Public Works Committee COMMITTEE DATE: June 18, 2018 SUBJECT/REPORT NO:

More information

EXECUTIVE SUMMARY. Vision

EXECUTIVE SUMMARY. Vision Vision Walking and bicycling in Salt Lake City will be safe, convenient, comfortable, and viable transportation options that connect people to places, foster recreational and economic development opportunities,

More information

North Avenue Corridor Study

North Avenue Corridor Study North Avenue Corridor Study Advisory Committee Meeting #6 July 1, 2014 Agenda Concept Revisions based on Advisory Committee feedback Review of New Concept Scoring & Costs Concept Discussion/Questions Voting:

More information

Bike Planning: A New Day

Bike Planning: A New Day Bike Planning: A New Day Josh Sikich, AICP, LEED AP Chicago Office Director Alta Planning + Design 312-265-0628 joshuasikich@altaplanning.com cities of all sizes are changing Illinois Bike Summit October

More information

Coquitlam Cross-town Bike Route Improving Bicycle Facilities in a Mature Suburban Environment

Coquitlam Cross-town Bike Route Improving Bicycle Facilities in a Mature Suburban Environment Coquitlam Cross-town Bike Route Improving Bicycle Facilities in a Mature Suburban Environment Sarah Rocchi, Vice-President, Projects, Opus International Consultants (Main Presenter) Catherine Mohoruk,

More information

CONTEXT SENSITIVE STREETS STANDARDS COMMITTEE

CONTEXT SENSITIVE STREETS STANDARDS COMMITTEE CONTEXT SENSITIVE STREETS STANDARDS COMMITTEE February 23, 2015 Prepared by: Denise Chaplick, AICP City Jacksonville Bicycle and Pedestrian Coordinator Source: NCDOT Complete Streets Planning and Design

More information

Bellevue Downtown Association Downtown Bike Series

Bellevue Downtown Association Downtown Bike Series Bellevue Downtown Association Downtown Bike Series Meeting 2 Franz Loewenherz Andreas Piller Kyle Potuzak Chris Long October 26, 2017 Today s Agenda: 1) Meeting Purpose 2) 9/28 Meeting Recap 3) Candidate

More information

Chapter 2: Standards for Access, Non-Motorized, and Transit

Chapter 2: Standards for Access, Non-Motorized, and Transit Standards for Access, Non-Motorized, and Transit Chapter 2: Standards for Access, Non-Motorized, and Transit The Washtenaw County Access Management Plan was developed based on the analysis of existing

More information

TULSA CITY COUNCIL CAPITAL IMPROVEMENT PROGRAM TASK FORCE MEETING JANUARY

TULSA CITY COUNCIL CAPITAL IMPROVEMENT PROGRAM TASK FORCE MEETING JANUARY CITY OF TULSA BICYCLE & PEDESTRIAN INFRASTRUCTURE TULSA CITY COUNCIL CAPITAL IMPROVEMENT PROGRAM TASK FORCE MEETING JANUARY 31, 2013 CITY OF TULSA ENGINEERING SERVICES DEPARTMENT CITY OF TULSA ADA TRANSITION

More information

Physical Implications of Complete Streets Policies

Physical Implications of Complete Streets Policies Presentation Overview Physical Implications of Complete Norm Cox, ASLA, LLA Landscape Architect Ann Arbor, Michigan, 10:45 to Noon What Are Complete Streets? What Matters to Bicyclists and Pedestrians

More information

Pedestrian Crossing Guidelines 2016

Pedestrian Crossing Guidelines 2016 Pedestrian Crossing Guidelines 2016 Engineering Services 1.0 Introduction and Background The City of Kingston s first Pedestrian Crossing Guidelines were approved by Council in 2008 in order to provide

More information

6/22/2018 VIA . Darcy Goulart, Planning Manager City of Rancho Cordova Planning Department 2729 Prospect Park Drive Rancho Cordova, CA 95670

6/22/2018 VIA  . Darcy Goulart, Planning Manager City of Rancho Cordova Planning Department 2729 Prospect Park Drive Rancho Cordova, CA 95670 6/22/2018 VIA EMAIL Darcy Goulart, Planning Manager City of Rancho Cordova Planning Department 2729 Prospect Park Drive Rancho Cordova, CA 95670 RE: Quick Quack Car Wash (DD9801) Dear Ms. Goulart: WALKSacramento

More information

Making Great Urban Streets Confessions of a Highway Engineer. Timothy R. Neuman.. P.E. Chief Highway Engineer CH2M HILL

Making Great Urban Streets Confessions of a Highway Engineer. Timothy R. Neuman.. P.E. Chief Highway Engineer CH2M HILL Making Great Urban Streets Confessions of a Highway Engineer Timothy R. Neuman.. P.E. Chief Highway Engineer CH2M HILL Isn t this a Great Street? Characteristics of a Great Street It is a transportation

More information

Waterford Lakes Small Area Study

Waterford Lakes Small Area Study Waterford Lakes Small Area Study Existing Traffic Conditions PREPARED FOR: ORANGE COUNTY PUBLIC WORKS DEPARTMENT TRAFFIC ENGINEERING DIVISION ORLANDO, FLORIDA PREPARED WITH: INWOOD CONSULTING ENGINEERS

More information

Appendix T CCMP TRAIL TRAFFIC & TRANSPORTATION DESIGN STANDARD

Appendix T CCMP TRAIL TRAFFIC & TRANSPORTATION DESIGN STANDARD Appendix T CCMP 3.3.4 TRAIL TRAFFIC & TRANSPORTATION DESIGN STANDARD 3.3.4 Trail Traffic and Transportation Design Multi-use trails have certain design standards, which vary depending on the agency that

More information

NM-POLICY 1: Improve service levels, participation, and options for non-motorized transportation modes throughout the County.

NM-POLICY 1: Improve service levels, participation, and options for non-motorized transportation modes throughout the County. Transportation PRINCE WILLIAM COUNTY 2008 COMPREHENSIVE PLAN NON-MOTORIZED PLAN CONTENTS Goals, Policies, and Action Strategies Table 4 (Bike Facility Classifications and Descriptions) Table 5 (Bike Facility

More information

Hennepin County Pedestrian Plan Public Comment Report

Hennepin County Pedestrian Plan Public Comment Report Hennepin County Pedestrian Plan Public Comment Report On May 31, 2013, the draft Hennepin County Pedestrian Plan was released for a 45-day public comment period ending July 15, 2013. The county received

More information

TABLE OF CONTENTS TABLE OF CONTENTS... I APPENDICES... III LIST OF EXHIBITS... V LIST OF TABLES... VII LIST OF ABBREVIATED TERMS...

TABLE OF CONTENTS TABLE OF CONTENTS... I APPENDICES... III LIST OF EXHIBITS... V LIST OF TABLES... VII LIST OF ABBREVIATED TERMS... TABLE OF CONTENTS TABLE OF CONTENTS... I APPENDICES... III LIST OF EXHIBITS... V LIST OF TABLES... VII LIST OF ABBREVIATED TERMS... IX 1 INTRODUCTION... 1 1.1 Project Overview... 1 1.2 Analysis Scenarios...

More information

Complete Streets for Louisiana

Complete Streets for Louisiana Complete Streets for Louisiana Louisiana Transportation Conference 2011 Ellen W. Soll, AICP Planner Burk-Kleinpeter, Inc esoll@bkiusa.com 504.486.5901 x143 What is a Complete Street? What are Complete

More information

Creating Complete Streets to Accommodate All Users

Creating Complete Streets to Accommodate All Users Creating Complete Streets to Accommodate All Users Peter Lagerwey, Toole Design Group plagerwey@tooledesign.com Brian Dougherty, Seattle DOT brian.dougherty@seattle.gov International Conference on Urban

More information

Defining Purpose and Need

Defining Purpose and Need Advanced Design Flexibility Pilot Workshop Session 4 Jack Broz, PE, HR Green May 5-6, 2010 Defining Purpose and Need In your agency s project development process, when do design engineers typically get

More information

9.1 FUNCTIONAL HIGHWAY SYSTEMS IN URBANIZED AREAS Principal Arterial Interstate Principal Arterial Non-Interstate

9.1 FUNCTIONAL HIGHWAY SYSTEMS IN URBANIZED AREAS Principal Arterial Interstate Principal Arterial Non-Interstate Greater Bozeman Area Transportation Plan (2007 Update) Chapter 9: Recommended Major Street Network & Roadway Typical Sections 9.1 FUNCTIONAL HIGHWAY SYSTEMS IN URBANIZED AREAS The discussion in this Chapter

More information