1 BOLAND DRIVE PATH PROJECT Martin Le Jack Reilly Paul Rodriguez Allison Rotella Maria Wilson

2 INTRODUCTION TO PROJECT The purpose: to construct a multi-purpose path, which will connect two existing bike and pedestrian paths The scope: the area along the south side of Boland Drive between Riverside Drive and Portage Avenue, a location that runs parallel to Pinhook Lake The elements: a cantilevered bridge in areas of steep decline to the lake, a recreational overlook, and a shared path sidewalk along Boland Drive The end goal: to encourage biking and walking as alternative forms of transportation for motorists.

3 BIKE THE BEND Bicycle Friendly Community Status Top ranked in Indiana City Plan of 2006 includes a Bicycle Plan outlining how the City will address encouraging bicycling as a form of alternate transportation Bike South Bend Long-term 103-mile bike plan Beneficial for individuals and community at large Reduction in congestion and delays on roadways, lower emissions from gasoline-powered vehicles, reduction in maintenance costs for roadways, amplified interest in the recreational area

4 CITY S BIKE PLAN Mid-2013: 63.4 miles complete Multi-purpose Paths Striped Bike Lanes On-road Shared Routes Future Goals League of American Bicyclists 5 Es

5 DESIGN PHILOSOPHY Efficiency, Creativity, and Ethics Efficiency federal funds are limited, so design must be cost effective, and use local contractors Creativity thinking outside of the box for fresh ideas Ethics important to remain ethical at all times J.A.M.M.P. Engineering has a variety of experience in providing engineering services to both public and private clients We pride ourselves in the quality of our work and our ability to provide for our clients as a committed and well - qualified team of engineers

6 PROJECT TEAM City of South Bend Client J.A.A.M.P. Engineering Project Lead Eric Wolverton Technical Consultant Allison Rotella Project Manager Martin Le John Reilly Maria Wilson Paul Rodriguez Earth Exploration Bridge Design Field Surveying Regulatory Compliance

7 DESIGN ALTERNATIVES Several design characteristics considered: Location Material Structural System Path Use

8 LOCATION Path will follow the south side of Boland Drive on the North Side of Pinhook Lake Alternatives include: North Side of Boland Following Ribourde Drive

9 MATERIALS Reinforced concrete piles and decking Wood-Plastic Composite Wearing Surface and Railings Alternatives include: Steel Lumber

10 STRUCTURAL SYSTEM Combination of Piles into Lakebed and cantilevered supports from bank Outlook area will require more piles into lakebed Transitions from sidewalk on Boland to path on lake will require supports into bank with varying degrees of cantilever effect Geological properties of the area currently unknown Exact survey data also unknown

11 DESIGN CHALLENGES Stability of Bank AASHTO Requirements ADA Requirements Gabion Wall Traffic Maintenance

12 TYPICAL CROSS SECTION OF TWO WAY SHARED USE PATH

13 SAFETY RAILING REQUIREMENTS Ideal Shoulder Width: 3 5 Maximum Cross Slope: 6:1 Recommended Cross Slope: -typical = 1% -not to exceed = 2% Grade Requirements: -5% max for any distance -8.3% max for up to % max or up to % max for up to 10

14 SAFETY RAILING REQUIREMENTS

15 ROAD CROSSING REQUIREMENTS

16 EXAMPLE SIGNAGE

17 PROJECT SCHEDULE

18 SUMMARY Location: the south side of Boland Drive in the area between Riverside Drive and Portage Avenue Components: a bridge portion along Pinhook Lake, an overlook, and a sidewalk running parallel to Boland Drive Structure: a combination of cantilevered and piles Material: a concrete deck with wood paneling Use: a bike and pedestrian path, as well as a recreational center due to the overlook and benches

19 CONCLUSION We are confident that our design and construction of the Boland Drive Multi-Use Pathway between Portage Avenue and Riverside Drive will enhance the local area. The path, which will comply with regional standards and accommodate all bicycle and pedestrian users, will fit in nicely with the City s Comprehensive Plan. As such, J.A.M.M.P. would be honored to be an integral part of the Boland Drive Path Project.

Chapter 3 DESIGN SPECIFICATIONS

Chapter 3 DESIGN SPECIFICATIONS Brampton PathWays Planning and Design Guidelines 27 Chapter 3 DESIGN SPECIFICATIONS 3.1 CLASS 1 MULTI-USE PATH Off-road multi-use trails are the backbone of the Brampton PathWays Network. They are typically

More information

Saskatchewan Drive Roadway Rehabilitation and Shared-Use Path Widening

Saskatchewan Drive Roadway Rehabilitation and Shared-Use Path Widening Saskatchewan Drive Roadway Rehabilitation and Shared-Use Path Widening We are here today to present the draft plan for the Saskatchewan Drive Roadway Rehabilitation and Shared-Use Path Widening project

More information

Complete Streets Policy DAVID CRONIN, P.E., CITY ENGINEER

Complete Streets Policy DAVID CRONIN, P.E., CITY ENGINEER Complete Streets Policy DAVID CRONIN, P.E., CITY ENGINEER Complete Streets City Commission adopted a Complete Streets policy in 2012 Complete Streets are road networks that are designed for all users:

More information

C C C

C C C C-012-001 Thank you for your support for the creation of new public space and nonmotorized access between downtown and the waterfront through the Overlook Walk, the East-West Connections, and the Promenade.

More information

South Carolina Department of Transportation. Engineering Directive

South Carolina Department of Transportation. Engineering Directive South Carolina Department of Transportation Engineering Directive Directive Number: ED-22 Effective: December 16, 2009 Subject: References: Purpose: This Directive Applies to: Considerations for Bicycle

More information

Construction Specifications Manual

Construction Specifications Manual Isle of Wight County Pedestrian and Bicycle Master Plan Construction Specifications Manual Adopted August 20, 2009 Introduction The Isle of Wight County Pedestrian and Bicycle Facilities Master Plan was

More information

Community Bicycle Planning

Community Bicycle Planning Community Bicycle Planning City of Mentor s Bicycle Facility Plan Allen E. Pennington, P.E. Civil Engineer - Traffic Office of the Mentor City Engineer Why has Mentor participated in bicycle planning?

More information

Off-Road Facilities Part 1: Shared Use Path Design

Off-Road Facilities Part 1: Shared Use Path Design Off-Road Facilities Part 1: Shared Use Path Design Presentation by: Eric Mongelli, P.E. Tom Huber October 9, 2012 FOLLOW THE CONVERSATION ON TWITTER Toole Design Group is live tweeting this webinar @tooledesign

More information

Bicycle and Pedestrian Connectivity Study. Old Colony Planning Council

Bicycle and Pedestrian Connectivity Study. Old Colony Planning Council Bicycle and Pedestrian Connectivity Study Old Colony Planning Council Outline Why consider bike/peds in road designs? Why are measures needed? Connecting Land Use with Transportation Evaluation Tools:

More information

APPENDIX A: Complete Streets Checklist DRAFT NOVEMBER 2016

APPENDIX A: Complete Streets Checklist DRAFT NOVEMBER 2016 APPENDIX A: Complete Streets Checklist DRAFT NOVEMBER 2016 Complete Streets Checklist MetroPlan Orlando s Complete Streets Checklist is an internal planning tool for staff to further implementation of

More information

Gordon Proctor Director Policy on Accommodating Bicycle and Pedestrian Travel on ODOT Owned or Maintained Facilities

Gordon Proctor Director Policy on Accommodating Bicycle and Pedestrian Travel on ODOT Owned or Maintained Facilities Approved: Policy: 20-004(P) Responsible Office: Planning Gordon Proctor Director Policy on Accommodating Bicycle and Pedestrian Travel on ODOT Owned or Maintained Facilities I. POLICY STATEMENT: This policy

More information

Montclair s Complete Streets Experience

Montclair s Complete Streets Experience Presented by: Hon. Jerry Fried, Mayor Montclair Township About Montclair Six square miles Six commuter rail stations Four local bus routes (NJ Transit) Two private commuter bus routes Five business districts

More information

Intersection Improvement: Sturgeon Road, Silver Avenue and Murray Park Road Roundabout. Welcome. Public Information Session

Intersection Improvement: Sturgeon Road, Silver Avenue and Murray Park Road Roundabout. Welcome. Public Information Session Intersection Improvement: 1 Welcome WHY IS AN INTERSECTION IMPROVEMENT NEEDED? 2 Traffic volumes for Sturgeon Road, Silver Avenue and Murray Park Road exceed the capacity of the existing 4-way stop controlled

More information

Emergency Response Support Signage on Multi-Use Trails Plan

Emergency Response Support Signage on Multi-Use Trails Plan DRAFT ( ) Emergency Response Support Signage on Multi-Use Trails Plan Prepared for: SATS Multi-Use Trails Jurisdictions Committee Table of Contents Introduction... 3 Mileage Markers... 4 Rest Stop Identifiers...

More information

Atwood Avenue Fair Oaks Avenue Cottage Grove Road

Atwood Avenue Fair Oaks Avenue Cottage Grove Road Atwood Avenue Fair Oaks Avenue Cottage Grove Road Agenda Purpose Review project scope & goals Present design alternatives Gather feedback Answer Questions Format Open House Presentation Q&A Open House

More information

Washington St. Corridor Study

Washington St. Corridor Study FIGURE 7.17 Bridge Alternatives - Cross Sections 86 Discarded Alternative: Short-Term Bridge Repair Short-term repairs and west bridge span replacement were considered during analysis. Short-term repairs

More information

Hospital Link Project Project Update September 2017

Hospital Link Project Project Update September 2017 Hospital Link Project Project Update September 2017 General The project provides a link from Riverside Drive and the Transitway to the Hospital Link Road. Construction is well underway. Read on for important

More information

Perryville TOD and Greenway Plan

Perryville TOD and Greenway Plan Perryville TOD and Greenway Plan Greenway Glossary Pathway: A bicycle and pedestrian path separated from motorized vehicular traffic by an open space, barrier or curb. Multi-use paths may be within the

More information

MAG Town of Cave Creek Bike Study Task 6 Executive Summary and Regional Significance Report

MAG Town of Cave Creek Bike Study Task 6 Executive Summary and Regional Significance Report Page 1 MAG Town of Cave Creek Bike Study Task 6 Executive Summary and Regional Significance Report August 1, 2012 MAG Project #481 Page 2 Task 6 Executive Summary and Regional Significance Report Introduction

More information

5. RUNNINGWAY GUIDELINES

5. RUNNINGWAY GUIDELINES 5. RUNNINGWAY GUIDELINES These guidelines should be considered collectively when making runningway decisions. A runningway is the linear component of the transit system that forms the right-of-way reserved

More information

CITY OF BLOOMINGTON COMPLETE STREETS POLICY

CITY OF BLOOMINGTON COMPLETE STREETS POLICY CITY OF BLOOMINGTON COMPLETE STREETS POLICY POLICY OBJECTIVE: The City of Bloomington will enhance safety, mobility, accessibility and convenience for transportation network users of all ages and abilities,

More information

NM-POLICY 1: Improve service levels, participation, and options for non-motorized transportation modes throughout the County.

NM-POLICY 1: Improve service levels, participation, and options for non-motorized transportation modes throughout the County. Transportation PRINCE WILLIAM COUNTY 2008 COMPREHENSIVE PLAN NON-MOTORIZED PLAN CONTENTS Goals, Policies, and Action Strategies Table 4 (Bike Facility Classifications and Descriptions) Table 5 (Bike Facility

More information

NJDOT Complete Streets Checklist

NJDOT Complete Streets Checklist Background The New Jersey Department of Transportation s Complete Streets Policy promotes a comprehensive, integrated, connected multi-modal network by providing connections to bicycling and walking trip

More information

CITY OF ELKO BICYCLE AND PATHWAY PLAN

CITY OF ELKO BICYCLE AND PATHWAY PLAN CITY OF ELKO BICYCLE AND PATHWAY PLAN INTRODUCTION: The City of Elko is intended to provide the basic framework for the development of a functional bicycle and pathway system for the community with connections

More information

Item to be Addressed Checklist Consideration YES NO N/A Required Description Complete Streets Guidelines

Item to be Addressed Checklist Consideration YES NO N/A Required Description Complete Streets Guidelines Passaic County Complete Streets Checklist - Concept Development Project Name Item to be Addressed Checklist Consideration YES NO N/A Required Description Complete Streets Guidelines Existing Plans Have

More information

Arlington s Master Transportation Plan

Arlington s Master Transportation Plan Arlington s Master Transportation Plan The Master Transportation Plan (MTP) Adopted in eight parts Goals & Policies element and MTP Map adopted in 2007 Bicycle, Pedestrian and Demand and Systems Management

More information

Off-road Trails. Guidance

Off-road Trails. Guidance Off-road Trails Off-road trails are shared use paths located on an independent alignment that provide two-way travel for people walking, bicycling, and other non-motorized users. Trails specifically along

More information

The Transformation of Portland into a Two-Wheeled Mecca. Mia Birk, Principal, Alta Planning + Design

The Transformation of Portland into a Two-Wheeled Mecca. Mia Birk, Principal, Alta Planning + Design The Transformation of Portland into a Two-Wheeled Mecca Mia Birk, Principal, Alta Planning + Design Development of Portland s Bikeway Network 1990 Early 1990s Infrastructure Growing Public Support Growing

More information

Planning Guidance in the 2012 AASHTO Bike Guide

Planning Guidance in the 2012 AASHTO Bike Guide Planning Guidance in the 2012 AASHTO Bike Guide Presentation by: RJ Eldridge Peter Lagerwey August 22, 2012 WEBINAR 2: PLANNING GUIDANCE IN THE 2012 AASHTO BIKE GUIDE Today s Webinar Significant Updates

More information

COMPLETE STREETS DURING CONSTRUCTION

COMPLETE STREETS DURING CONSTRUCTION COMPLETE STREETS DURING CONSTRUCTION MAINTAINING ACCESSIBILITY FOR ALL Presented by Robbie Burgess, P.E., PTOE Associate Principal Construction Services Manager Howard Stein Hudson rburgess@hshassoc.com

More information

Appendix T CCMP TRAIL TRAFFIC & TRANSPORTATION DESIGN STANDARD

Appendix T CCMP TRAIL TRAFFIC & TRANSPORTATION DESIGN STANDARD Appendix T CCMP 3.3.4 TRAIL TRAFFIC & TRANSPORTATION DESIGN STANDARD 3.3.4 Trail Traffic and Transportation Design Multi-use trails have certain design standards, which vary depending on the agency that

More information

ECONOMY PEOPLE ENVIRONMENT

ECONOMY PEOPLE ENVIRONMENT Report Back on Local Transit Improvements May 29, 2013 ECONOMY PEOPLE ENVIRONMENT Intro Council Requested Report Back Topics Progress on Planning for Broadway Subway False Creek Bridges Local Transit Improvements

More information

DISTRIBUTION: Electronic Recipients List TRANSMITTAL LETTER NO. (17-01) MINNESOTA DEPARTMENT OF TRANSPORTATION. MANUAL: Road Design English Manual

DISTRIBUTION: Electronic Recipients List TRANSMITTAL LETTER NO. (17-01) MINNESOTA DEPARTMENT OF TRANSPORTATION. MANUAL: Road Design English Manual DISTRIBUTION: Electronic Recipients List MINNESOTA DEPARTMENT OF TRANSPORTATION DEVELOPED BY: Design Standards Unit ISSUED BY: Office of Project Management and Technical Support TRANSMITTAL LETTER NO.

More information

Balancing Operation & Safety for Motorized and Non-Motorized Traffic

Balancing Operation & Safety for Motorized and Non-Motorized Traffic Balancing Operation & Safety for Motorized and Non-Motorized Traffic Brian Willham, PE, PTOE Iowa Director - MOVITE June 30, 2014 Learning Objectives: When & Why should we measure the performance of complete

More information

Austell Road Access Management Plan Public Meeting February 17, 2009

Austell Road Access Management Plan Public Meeting February 17, 2009 Austell Road Access Management Plan Public Meeting February 17, 2009 Laraine Vance: Dan Cohen: Cobb DOT Project Manager Pond & Company Planning Director 1 Access Management What is Access Management? The

More information

Citywide Sidewalk and Crosswalk Programs

Citywide Sidewalk and Crosswalk Programs Citywide Sidewalk and Crosswalk Programs Council Meeting October 20, 2015 Presented by Rita Hu and Jamal Mahmoud Program Goals Implement the City s comprehensive plan. Provide pedestrian with safe walking

More information

On Road Bikeways Part 1: Bicycle Lane Design

On Road Bikeways Part 1: Bicycle Lane Design On Road Bikeways Part 1: Bicycle Lane Design Presentation by: Nick Jackson Bill Schultheiss, P.E. September 04, 2012 FOLLOW THE CONVERSATION ON TWITTER Toole Design Group is live tweeting this webinar

More information

Hospital Link Project Project Update November 2017

Hospital Link Project Project Update November 2017 Hospital Link Project Project Update November 2017 General The project provides a link from Riverside Drive and the Transitway to the Hospital Link Road. Construction is well underway. Read on for important

More information

Bicycle Facilities Planning

Bicycle Facilities Planning Bicycle Facilities Planning Overview Types of Cyclists Purpose for Riding Types of Facilities Bike Lanes Bicycle Boulevards Cycle Tracks Intersections Signals Signing and Marking Discussion Types of Bicyclists

More information

TRANSPORTATION TRAINING TOPICS. April 6, 2010

TRANSPORTATION TRAINING TOPICS. April 6, 2010 TRANSPORTATION TRAINING TOPICS April 6, 2010 Roles of Transportation Providers Context and Policy Makers Division of Transportation and Traffic Other City Operations Other Transportation Operators CMA

More information

Appendix 3 Roadway and Bike/Ped Design Standards

Appendix 3 Roadway and Bike/Ped Design Standards Appendix 3 Roadway and Bike/Ped Design Standards OTO Transportation Plan 2040 4/20/2017 Page A3-1 Adopted Standards The adopted OTO Design Standards and Major Thoroughfare Plan are contained herein.

More information

CONNECTING PEOPLE TO PLACES

CONNECTING PEOPLE TO PLACES CONNECTING PEOPLE TO PLACES 82 EAST BENCH MASTER PLAN 07 Introduction The East Bench transportation system is a collection of slow moving, treelined residential streets and major arteries that are the

More information

2014 Regional Bicycle and Pedestrian Study Evaluation Tools Leslie A. Meehan, AICP MPO Technical Coordinating Committee Meeting April 1, 2015

2014 Regional Bicycle and Pedestrian Study Evaluation Tools Leslie A. Meehan, AICP MPO Technical Coordinating Committee Meeting April 1, 2015 Mayor Mayor Kenneth Karl Dean, Wilber, Chairman 2014 Regional Bicycle and Pedestrian Study Evaluation Tools Leslie A. Meehan, AICP MPO Technical Coordinating Committee Meeting April 1, 2015 Evaluation

More information

Presentation Starts at 5:30 PM

Presentation Starts at 5:30 PM Presentation Starts at 5:30 PM Public Meeting #1 September 22, 2016 Purpose of Study Conceptual Complete Streets Study on South Carson Street 5 th Street to Roland Drive Approximately 2.5 miles Consider

More information

Appendix D: Planning Level Cost Calculator

Appendix D: Planning Level Cost Calculator Appendix D: Planning Level Cost Calculator Network Costs by Facility Type Facility Type Total Miles of Facility Total Number of Intersections Cost per feature or per mile Total Cost Bicycle Boulevard 52.14

More information

INDOT Complete Streets Guideline & Policy

INDOT Complete Streets Guideline & Policy INDOT Complete Streets Guideline & Policy INTRODUCTION The Complete Streets guidelines build upon multiple efforts and promote a multimodal transportation system that is integrated and sustains land use

More information

RESOLUTION NO ?? A RESOLUTION OF THE CITY OF NEPTUNE BEACH ADOPTING A COMPLETE STREETS POLICY

RESOLUTION NO ?? A RESOLUTION OF THE CITY OF NEPTUNE BEACH ADOPTING A COMPLETE STREETS POLICY RESOLUTION NO. 2018-?? A RESOLUTION OF THE CITY OF NEPTUNE BEACH ADOPTING A COMPLETE STREETS POLICY WHEREAS, safe, convenient, and accessible transportation for all users is a priority of the City of Neptune

More information

Driveway Design Criteria

Driveway Design Criteria Design Manual Chapter 5 - Roadway Design 5L - Access Management 5L-4 Driveway Design Criteria A. General For efficient and safe operations, access drives and minor public street intersections can be improved

More information

General Design Factors

General Design Factors Chapter 3: 3-1.0 Introduction General Design Factors Mn/DOT s goals include encouraging and accommodating safe bicycling. From a design perspective, these goals are achieved by first having an understanding

More information

Non-Motorized Transportation 7-1

Non-Motorized Transportation 7-1 Non-Motorized Transportation 7-1 Transportation facilities no longer mean just accommodating a vehicle powered by a combustion engine. Pedestrian and non-motorized facilities are important modes of travel

More information

Derby Street. Project Updates. Salem, Massachusetts

Derby Street. Project Updates. Salem, Massachusetts Derby Street Project Updates Salem, Massachusetts September 13, 2017 Project Limits Derby Street Project Objectives 1. Improve complete streets elements on Derby Street 2. Improve sidewalks on finger streets

More information

Bicyclist Signing Guidelines

Bicyclist Signing Guidelines Bicyclist Signing Guidelines April, 2009 1 Introduction This paper describes the Montana Department of Transportation s (MDT) current practices related to bicyclist safety and signing issues and presents

More information

CITY OF COCOA BEACH 2025 COMPREHENSIVE PLAN. Section VIII Mobility Element Goals, Objectives, and Policies

CITY OF COCOA BEACH 2025 COMPREHENSIVE PLAN. Section VIII Mobility Element Goals, Objectives, and Policies CITY OF COCOA BEACH 2025 COMPREHENSIVE PLAN Section VIII Mobility Element Goals, Objectives, and Policies Adopted August 6, 2015 by Ordinance No. 1591 VIII MOBILITY ELEMENT Table of Contents Page Number

More information

Who is Toole Design Group?

Who is Toole Design Group? 2018 AASHTO Bike Guide Status Update NCHRP 15 60 Amalia Leighton Cody, PE, AICP & Kenneth Loen, PE Washington APWA October 4, 2018 Who is Toole Design Group? TDG is a full service engineering, planning

More information

Roads and Vehicular Traffic Design Principles. Roads and Vehicular Traffic Recommendations

Roads and Vehicular Traffic Design Principles. Roads and Vehicular Traffic Recommendations CIRCULATION AND PARKING roads and vehicular traffic The Campus Master Plan updates the campus transportation network through a multi-modal approach that encourages walking and biking while improving vehicular

More information

Land Use Patterns. Traditional Modern

Land Use Patterns. Traditional Modern Street Types Pre WWII: tight street grid, straight connected streets, sidewalks and alleys, block size 400 or < Post WWII: curvilinear streets, cul-de-sacs, few sidewalks, large blocks at 600 or > and

More information

Multimodal Transportation Plan

Multimodal Transportation Plan Multimodal Transportation Plan The Multimodal Transportation Plan will accommodate MILLENIALS ARE DRIVING LESS. WE CANNOT BUILD OUR WAY all modes of transportation by keeping pedestrians, OUT OF CONGESTION.

More information

Case Study: Transportation Plan Environmental Impact Statement. National Park Service U.S. Department of the Interior

Case Study: Transportation Plan Environmental Impact Statement. National Park Service U.S. Department of the Interior National Park Service U.S. Department of the Interior Grand Teton National Park Wyoming Case Study: Transportation Plan Environmental Impact Statement November 2010 Brian T. Alward CRP 5540: Introduction

More information

Access Routes from US 101 to the Richmond San Rafael Bridge

Access Routes from US 101 to the Richmond San Rafael Bridge Access Routes from US 101 to the Richmond San Rafael Bridge TAM Board Meeting January 28, 2016 RSRB Project Elements Eastbound Third Lane: Sir Francis Drake Blvd. to Marine Street 10 ft Barrier Separated

More information

MEMORANDUM. Earl Haugen and UND Transportation and Traffic Coordination Committee

MEMORANDUM. Earl Haugen and UND Transportation and Traffic Coordination Committee SRF No. 7766 MEMORANDUM TO: FROM: Earl Haugen and UND Transportation and Traffic Coordination Committee Rick Lane, P.E. DATE: November 26, 2013 SUBJECT: UNIVERSITY AVE REVIEW Our review of the University

More information

City of Roseville Section 13 Design Standards. _Bikeways January 2016 SECTION 13 BIKEWAYS

City of Roseville Section 13 Design Standards. _Bikeways January 2016 SECTION 13 BIKEWAYS SECTION 13 BIKEWAYS 13-1 GENERAL The City of Roseville bikeway standards are designed to insure that transportation and recreational bikeways are constructed in a manner that would provide a safe and comfortable

More information

The Bike Buzz in Richland. November 2017 Carl Berkowitz

The Bike Buzz in Richland. November 2017 Carl Berkowitz The Bike Buzz in Richland November 2017 Carl Berkowitz Richland has been growing by leaps and bounds with lots of new homes and roads throughout the community. Recognizing all the growth in the Queensgate

More information

Tonight is for you. Learn everything you can. Share all your ideas.

Tonight is for you. Learn everything you can. Share all your ideas. Strathcona Neighbourhood Renewal Draft Concept Design Tonight is for you. Learn everything you can. Share all your ideas. What is Neighbourhood Renewal? Creating a design with you for your neighbourhood.

More information

Public Information Meeting #1. Pā ia Community Center 5:30 PM 8:00 PM

Public Information Meeting #1. Pā ia Community Center 5:30 PM 8:00 PM Public Information Meeting #1 Pā ia Community Center 5:30 PM 8:00 PM October 22, 2008 Overview of Tonight s Meeting Pā ia Mini Bypass Pā ia Relief Route Project Description and Study Area Context t Sensitive

More information

City of Wilsonville 5 th Street to Kinsman Road Extension Project

City of Wilsonville 5 th Street to Kinsman Road Extension Project City of Wilsonville 5 th Street to Kinsman Road Walking Tour & Neighborhood Workshop Summary Report Public Outreach Overview On July 18 th, 2017, the City of Wilsonville hosted a neighborhood walking tour

More information

Dr. M.L. King, Jr. Street North Complete Streets Resurfacing Opportunities HOUSING, LAND USE, AND TRANSPORTATION COMMITTEE MARCH 22, 2018

Dr. M.L. King, Jr. Street North Complete Streets Resurfacing Opportunities HOUSING, LAND USE, AND TRANSPORTATION COMMITTEE MARCH 22, 2018 Dr. M.L. King, Jr. Street North Complete Streets Resurfacing Opportunities HOUSING, LAND USE, AND TRANSPORTATION COMMITTEE MARCH 22, 2018 What s Happening The City plans to mill and resurface Dr. M.L.

More information

Overview. Illinois Bike Summit IDOT Complete Streets Policy Presentation. What is a Complete Street? And why build them? And why build them?

Overview. Illinois Bike Summit IDOT Complete Streets Policy Presentation. What is a Complete Street? And why build them? And why build them? Overview Illinois Bike Summit IDOT Complete Streets Policy Presentation Aren Kriks, P.E. District One Bicycle Coordinator and Bureau of Programming Project Engineer History of Complete Streets IDOT Policy

More information

St. Francis Drive through the City of Santa Fe Corridor Study

St. Francis Drive through the City of Santa Fe Corridor Study VII. ENGINEERING AND ENVIRONMENTAL EVALUATION TRAIL CONNECTIVITY In the southern portion of the Corridor there is a lack of a sidewalk, trail or bicycle facility within the right-ofway. However, the City

More information

ACTIVE TRANSPORTATION

ACTIVE TRANSPORTATION ACTIVE TRANSPORTATION Mobility 2040 Supported Goals Improve the availability of transportation options for people and goods. Support travel efficiency measures and system enhancements targeted at congestion

More information

DRAFT. System Components. Greenway Trails. Introduction. Trail Types. Zebulon Greenway Master Plan

DRAFT. System Components. Greenway Trails. Introduction. Trail Types. Zebulon Greenway Master Plan 5 System Components Wakefield Street Photo Simulation showing Sharrows Introduction The Master Plan identifies various system components that, together, create a comprehensive greenway system. These components

More information

Houma-Thibodaux Metropolitan Planning Organization STP<200K Funding Application APPLICATION

Houma-Thibodaux Metropolitan Planning Organization STP<200K Funding Application APPLICATION APPLICATION HOUMA-THIBODAUX METROPOLITAN PLANNING ORGANIZATION (HTMPO) FOR SURFACE TRANSPORTATION PROGRAM (STP

More information

What Is a Complete Street?

What Is a Complete Street? Session 5 Charleen Zimmer, AICP, Zan Associates May 5-7, 2010 What Is a Complete Street? May 2010 5-1 Not a Complete Street More of a Complete Street May 2010 5-2 Benefits of Complete Streets Safety for

More information

Complete Streets Funding Program Project Prioritization Plan

Complete Streets Funding Program Project Prioritization Plan Funding Program Project Prioritization Plan Location and Type Needs South Street Crosswalk Installation Stripe a new formalized crosswalk across South Street at the Anne T. Dunphy School pedestrian path

More information

CHAPTER 16 PEDESTRIAN FACILITIES DESIGN AND TECHNICAL CRITERIA TABLE OF CONTENTS

CHAPTER 16 PEDESTRIAN FACILITIES DESIGN AND TECHNICAL CRITERIA TABLE OF CONTENTS CHAPTER 16 PEDESTRIAN FACILITIES DESIGN AND TECHNICAL CRITERIA TABLE OF CONTENTS Section Title Page 16.1 General... 16-1 16.1.1 AASHTO Reference... 16-1 16.1.2 ADA Requirements... 16-1 16.2 Sidewalks...

More information

An Assessment of Potential Greenhouse Gas Emissions Reductions from Proposed On Street Bikeways

An Assessment of Potential Greenhouse Gas Emissions Reductions from Proposed On Street Bikeways An Assessment of Potential Greenhouse Gas Emissions Reductions from Proposed On Street Bikeways Through the Sustainable Bethlehem Initiative, the Town of Bethlehem has identified both the improvement of

More information

section 4 Existing Conditions, Issues, and Options

section 4 Existing Conditions, Issues, and Options section 4 Existing Conditions, Issues, and Options 4.0 Existing Conditions, Issues, and Options This section analyzes each segment of the corridor on a street to street basis. Each segment is discussed

More information

Hampton Roads Pedestrian and Bicycle Advisory Committee

Hampton Roads Pedestrian and Bicycle Advisory Committee Hampton Roads Pedestrian and Bicycle Advisory Committee HRTPO Transportation Technical Advisory Committee November 6, 2013 Carl E. Jackson III, AICP Transportation Planning Specialist Hampton Roads District

More information

Mid Rivers Mall Drive Multi-Use Path (Rte. N to MO 364)

Mid Rivers Mall Drive Multi-Use Path (Rte. N to MO 364) Mid Rivers Mall Drive Multi-Use Path (Rte. N to MO 364) Sponsor St Peters Project No. RB19-000022 Project Type Other TOTAL FUNDING Total County Sponsor Federal $1,177,251.00 $238,179.00 $59,546.00 $879,526.00

More information

Section 5: Bike and Pedestrian

Section 5: Bike and Pedestrian Section 5: Bike and Pedestrian Existing Conditions: One defining feature of Glynn County appreciated by both residents and visitors is the extensive sidewalk and bike path system. The City of Brunswick,

More information

Shared Use Path Design

Shared Use Path Design 12B-2 Design Manual Chapter 12 - Sidewalks and Bicycle Facilities 12B - Bicycle Facilities Shared Use Path Design A. Accessible Shared Use Path Design 1. General: Applicable portions from the following

More information

ADA & Public Rights of Way

ADA & Public Rights of Way ADA & Public Rights of Way Overview of Current and Up-coming Requirements FDOT Design Training Expo 2012 Orlando, FL Dean Perkins, RA - ADA Coordinator Florida Department of Transportation Office of Design,

More information

01. VICINITY OF GREENBRAE POC: EXISTING CONDITIONS

01. VICINITY OF GREENBRAE POC: EXISTING CONDITIONS 01. VICINITY OF GREENBRAE POC: EXISTING CONDITIONS Existing Bus Stop Existing US101 On-ramp Existing POC Old Redwood Highway Rich Street City ROW Environmental Study Limit Industrial Way NO DESIGNATED

More information

Prince George s County plans, policies, and projects

Prince George s County plans, policies, and projects Prince George s County plans, policies, and projects Over 250 projects for trails, bikeways, designated bike lanes and sidewalk construction Trail projects that improve access to Metro Sidewalk and trail

More information

Double the amount of bicycle ridership while at the same time reducing the number of bicycle crashes by one-third.

Double the amount of bicycle ridership while at the same time reducing the number of bicycle crashes by one-third. CHAPTER 6 Recommended Policies and Action Items To achieve the goals stated in Chapter 1 and guide implementation of the Bicycle Plan, policies and action items have been identified. They are presented

More information

Chapter 2: Standards for Access, Non-Motorized, and Transit

Chapter 2: Standards for Access, Non-Motorized, and Transit Standards for Access, Non-Motorized, and Transit Chapter 2: Standards for Access, Non-Motorized, and Transit The Washtenaw County Access Management Plan was developed based on the analysis of existing

More information

ACTIA Programs Annual Compliance Report Reporting Year Bicycle and Pedestrian Safety Table 1: Summary of Expenditures and Accomplishments

ACTIA Programs Annual Compliance Report Reporting Year Bicycle and Pedestrian Safety Table 1: Summary of Expenditures and Accomplishments Bicycle and Pedestrian Safety Table 1: Summary of Expenditures and Accomplishments Note: Definitions for each drop down menu appear as Comments (scroll over the column title or in the Review mode, choose

More information

Anne Arundel County BICYCLE, PEDESTRIAN, TRANSIT ASSESSMENT GUIDELINES

Anne Arundel County BICYCLE, PEDESTRIAN, TRANSIT ASSESSMENT GUIDELINES Anne Arundel County BICYCLE, PEDESTRIAN, TRANSIT ASSESSMENT GUIDELINES December 2018 TABLE OF CONTENTS I. Executive Summary 3 II. When Is A Bicycle Pedestrian Transit Assessment (BPTA) Required? 4 III.

More information

FM 1092/Murphy Road Access Management Study Pulic Meeting #1. Wednesday, August 31, :00 p.m. 8:00 p.m.

FM 1092/Murphy Road Access Management Study Pulic Meeting #1. Wednesday, August 31, :00 p.m. 8:00 p.m. FM 1092/Murphy Road Access Management Study Pulic Meeting #1 Wednesday, August 31, 2011 6:00 p.m. 8:00 p.m. Introductions Agency Partners H-GAC Missouri City TxDOT Introductions Consulting Team In Association

More information

Small Town & Rural Multimodal Networks

Small Town & Rural Multimodal Networks Small Town & Rural Multimodal Networks Fred Young, PLA Andrea Clinkscales, AICP, PMP Alta Planning + Design Funding Partners Project Team Existing Design Guidance AASHTO Flexibility Guide 2004 AASHTO Bike

More information

Chapter VISION, MISSION, AND GOALS AND OBJECTIVES. Vision. Mission. Goals and Objectives CONNECTING COMMUNITIES ACROSS THE ST.

Chapter VISION, MISSION, AND GOALS AND OBJECTIVES. Vision. Mission. Goals and Objectives CONNECTING COMMUNITIES ACROSS THE ST. VISION, MISSION, AND GOALS AND OBJECTIVES Chapter 3 The Plan s vision, mission, and goals and objectives were developed through a series of interactive exercises with the Citizens Advisory Committee (CAC)

More information

Connecting cyclists to work. Syracuse Metropolitan Transportation Council

Connecting cyclists to work. Syracuse Metropolitan Transportation Council Connecting cyclists to work Syracuse Metropolitan Transportation Council Overview Prepared at request: NYS Department of Transportation (NYSDOT) Project Achievements Target group Purpose Process Recommendations

More information

EXECUTIVE SUMMARY. Vision

EXECUTIVE SUMMARY. Vision Vision Walking and bicycling in Salt Lake City will be safe, convenient, comfortable, and viable transportation options that connect people to places, foster recreational and economic development opportunities,

More information

Eliminate on-street parking where it will allow for a dedicated bus only lane %

Eliminate on-street parking where it will allow for a dedicated bus only lane % Traffic Dashboard Priorities Survey Responses Introduction 1) Are you familiar with bus rapid transit (BRT)? a. No, BRT is new to me. 597 23.5% b. I ve heard of BRT, but I don t know much about it. 1,136

More information

Americans with Disabilities Act Transition Plan for Public Right-of-Way Improvements

Americans with Disabilities Act Transition Plan for Public Right-of-Way Improvements Americans with Disabilities Act Transition Plan for Public Right-of-Way Improvements Prepared by: Public Works Department Engineering Division October 2015 Table of Contents Section I Introduction.. 3

More information

Bikeway action plan. Bicycle Friendly Community Workshop March 5, 2007 Rochester, MN

Bikeway action plan. Bicycle Friendly Community Workshop March 5, 2007 Rochester, MN Bikeway action plan Summary The was held on March 5, 2007 at the Rochester Mayo Civic Center. The workshop was hosted by Rochester-Olmsted County Planning Department in collaboration with the League of

More information

City of Madison: 2017 Capital Budget Capital Improvement Plan

City of Madison: 2017 Capital Budget Capital Improvement Plan Capital Improvement Plan Project Summary Bikeways Program 779,000 751,000 630,000 670,000 703,000 703,000 Cannonball Path 210,000 - - 730,000 - - Cap City Trail 1,140,000-360,000 - - 910,000 Ice Age Junction

More information

Bicycle and Pedestrian Facilities Toolbox (Excerpt from Figure 3.1)

Bicycle and Pedestrian Facilities Toolbox (Excerpt from Figure 3.1) Appendix B Neighborhood Connections Summaries This Appendix is a supplement to the information presented in Chapter 3 Connect People. The Appendix includes a summary or profile for each of the proposed

More information

Chapter 5. Complete Streets and Walkable Communities.

Chapter 5. Complete Streets and Walkable Communities. Chapter 5. Complete Streets and Walkable Communities. 5.1 Description of Complete Streets. Cities throughout the world, and specifically the United States, are coming to embrace a new transportation and

More information

Summary of Feedback Received during Speak Up Broward s 22 Speakers Bureau Engagements from December 10, 2013 through April 2, 2014

Summary of Feedback Received during Speak Up Broward s 22 Speakers Bureau Engagements from December 10, 2013 through April 2, 2014 Summary of Feedback Received during Speak Up Broward s 22 Speakers Bureau Engagements from December 10, 2013 through April 2, 2014 Broward County Transit (BCT): Concerns for the safety of children particularly

More information

Vision: Traditional hamlet with an attractive business/pedestrian friendly main street connected to adjacent walkable neighborhoods

Vision: Traditional hamlet with an attractive business/pedestrian friendly main street connected to adjacent walkable neighborhoods N D. Focus Area II Vision: Traditional hamlet with an attractive business/pedestrian friendly main street connected to adjacent walkable neighborhoods Transit Road Focus Area II is located in the Hamlet

More information