1 Presentation Starts at 5:30 PM Public Meeting #1 September 22, 2016

2 Purpose of Study Conceptual Complete Streets Study on South Carson Street 5 th Street to Roland Drive Approximately 2.5 miles Consider alternatives for the corridor Drop in volume and current conditions are vehicle dominated Engage the community and businesses 2

3 What is a Complete Street? Complete Streets are streets for everyone Improve safety for everyone Users of all ages & abilities Provide multimodal choices Pedestrians Bicyclists Motorists Transit riders 3

4 What is a Complete Street? Complete Streets make it easy to: Cross the street Walk to shops/work Bicycle to shops/work They make it safe for people to walk to and from transit stations Benefit vehicle traffic through treatments such as access efficiencies 4

5 Benefits of Complete Streets Safety improvements Economic growth Improved mode choice Public health Reduced congestion Improved air quality Aesthetic improvements 5

6 Project Need NDOT transferring South Carson Street to Carson City, and per agreement $5.1M for City to improve roadway Freeway extending from Fairview to US 50 Significantly less traffic on Carson Street No longer need 6 travel lanes 6

7 5 th Street PROJECT LIMITS Roland Street 7

8 What does a Complete Street look like? No standard design Each Complete Street is unique and responds to the community needs A Complete Street may include: Sidewalks Bike lanes Transit accommodation Access improvements Median islands Pedestrian crossing opportunities Reduction of through travel lanes Roundabouts Aesthetics (landscaping, street furniture) 8

9 Complete Streets Transformation Simulation by Steve Price, UrbanAdvantage E14th Corridor - San Leandro, CA Source: Community, Design + Architecture 9

10 Complete Streets Transformation Simulation by Steve Price, UrbanAdvantage E14th Corridor - San Leandro, CA Source: Community, Design + Architecture 10

11 Complete Streets Transformation Simulation by Steve Price, UrbanAdvantage E14th Corridor - San Leandro, CA Source: Community, Design + Architecture 11

12 Change is Gradual Steve Price, UrbanAdvantage 12

13 Change is Gradual Steve Price, UrbanAdvantage 13

14 Change is Gradual Steve Price, UrbanAdvantage 14

15 Changing Thoroughfare and Context Steve Price, UrbanAdvantage 15

16 Changing Thoroughfare and Context Steve Price, UrbanAdvantage 16

17 17 Steve Price, UrbanAdvantage

18 18 Steve Price, UrbanAdvantage

19 What is the day of the week? A. Monday B. Tuesday C. Wednesday D. Thursday E. Friday 88% 2% 0% 4% 6% 19

20 The capital of Nevada is: A. Las Vegas B. Reno C. Carson City D. Elko 100% 0% 0% Las Vegas Reno Carson City 0% Elko 20

21 In your opinion which mode should be the priority on South Carson Street? A. Walking B. Biking C. Automobile D. Transit E. No opinion 21% 75% 2% 2% 0% 21

22 What should be the vehicle priority along South Carson Street? A. Vehicle access to businesses B. Vehicle mobility along the roadway (faster travel times) 78% 22% 22 Vehicle access to businesses Vehicle mobility along the roadway (faster travel times)

23 Which roadway safety improvements would you most like to see on the corridor? A. Consolidated access points B. Intersection improvements (turn lanes, flashing yellow arrow) C. Median islands D. Roundabouts 14% 40% 18% 28% 23

24 How important is it that lighting be improved along the roadway? A. Low importance B. Medium importance C. High importance 63% 31% 6% Low importance Medium importance High importance 24

25 How important is upgrading the existing streetscape with landscaping, furniture, and other amenities? A. Low importance B. Medium importance C. High importance 22% 46% 32% Low importance Medium importance High importance 25

26 26 Walkability

27 Which best describes your general opinion about the walkability of South Carson Street? A. A very walkable street B. A walkable street that needs improvements in certain areas C. Walkable in isolated areas D. Not very walkable 4% 20% 30% 46% 27

28 How important is walkability along South Carson Street? A. Low importance B. Medium importance C. High importance 24% 40% 36% Low importance Medium importance High importance 28

29 Which of the following is most likely to get you to walk more? A. Wider sidewalks B. A vibrant street scene 52% C. An attractive streetscape with trees, benches, and other amenities 8% 20% 6% 14% D. Access to transit E. I do not walk 29

30 30 Bikeability

31 Which best describes your general opinion about the bikeability of South Carson Street? A. A very bikeable street B. A bikeable street that needs improvements in certain areas C. Bikeable in isolated areas D. Not very bikeable 2% 8% 22% 67% 31

32 How important is bikeability along South Carson Street? A. Low importance B. Medium importance C. High importance 59% 18% 22% Low importance Medium importance High importance 32

33 Which best describes your bike riding habits? A. Recreational or exercise B. Occasionally to run errands C. Regularly to work D. Occasionally to work E. Ride to school or other public places F. Ride to transit station G. I don t ride very much because it s dangerous H. I don t ride and wouldn t even if safe 48% 4% 6% 2% 4% 0% 20% 16% 33

34 Of the following, which is most likely to get you to ride more often? A. Bike paths separated from roadways 57% B. Buffered bike lanes C. Striped and signed bike lanes on streets D. Bike within in the vehicle travel lane 22% 8% 0% 12% E. Nothing would 34

35 Thank You Contact Information:

Multimodal Transportation Plan

Multimodal Transportation Plan Multimodal Transportation Plan The Multimodal Transportation Plan will accommodate MILLENIALS ARE DRIVING LESS. WE CANNOT BUILD OUR WAY all modes of transportation by keeping pedestrians, OUT OF CONGESTION.

More information

Vision: Traditional hamlet with an attractive business/pedestrian friendly main street connected to adjacent walkable neighborhoods

Vision: Traditional hamlet with an attractive business/pedestrian friendly main street connected to adjacent walkable neighborhoods N D. Focus Area II Vision: Traditional hamlet with an attractive business/pedestrian friendly main street connected to adjacent walkable neighborhoods Transit Road Focus Area II is located in the Hamlet

More information

Proposed. City of Grand Junction Complete Streets Policy. Exhibit 10

Proposed. City of Grand Junction Complete Streets Policy. Exhibit 10 Proposed City of Grand Junction Complete Streets Policy Exhibit 10 1 City of Grand Junction Complete Streets Policy Vision: The Complete Streets Vision is to develop a safe, efficient, and reliable travel

More information

Illustrated Principles of Good Planning

Illustrated Principles of Good Planning Illustrated Principles of Good Planning The Miami 21 Zoning Code incorporates time-tested planning principles into the zoning regulations of our City. These are principles that make for better neighborhoods,

More information

A CHANGING CITY. of Edmonton, it is essential that it reflects the long-term vision of the City.

A CHANGING CITY. of Edmonton, it is essential that it reflects the long-term vision of the City. A CHANGING CITY By the year 2040, Edmonton will be home to more than 1 million people. To accommodate growth and support a healthy and compact city, we need a new approach to development/redevelopment

More information

95 th Street Corridor Transportation Plan. Steering Committee Meeting #2

95 th Street Corridor Transportation Plan. Steering Committee Meeting #2 95 th Street Corridor Transportation Plan Steering Committee Meeting #2 February 18, 2015 PURPOSE OF THE MEETING Update Steering Committee Present Community/Stakeholder Survey Results Present Transportation

More information

Bicycle Facilities Planning

Bicycle Facilities Planning Bicycle Facilities Planning Overview Types of Cyclists Purpose for Riding Types of Facilities Bike Lanes Bicycle Boulevards Cycle Tracks Intersections Signals Signing and Marking Discussion Types of Bicyclists

More information

Richmond Connects Visioning Update

Richmond Connects Visioning Update Richmond Connects Visioning Update To date there have been four elements of the visioning process: Vision20 Night at Byrd Theatre on May 3rd Advisory Committee Meeting on May 12 th Public Visioning Workshop

More information

Public Workshop #2. September 14, 2016

Public Workshop #2. September 14, 2016 Public Workshop #2 September 14, 2016 Agenda Welcome Project Overview Where We Have Been Alternatives for State Street Land Use Street Design Next Steps 2 Project Overview Create a Vibrant State Street

More information

STEERING COMMITTEE MEETING June 17, Streetscape Overview Burlington Comprehensive Master Plan

STEERING COMMITTEE MEETING June 17, Streetscape Overview Burlington Comprehensive Master Plan STEERING COMMITTEE MEETING June 17, 2015 Streetscape Overview Burlington Comprehensive Master Plan 1 Introduction Slide This slide show was presented to the Burlington Steering Committee on June 17, 2015

More information

Omaha s Complete Streets Policy

Omaha s Complete Streets Policy Omaha s Complete Streets Policy (Adopted August 2015) VISION To create great places and enhance our quality of life, the City of Omaha will provide safe, accessible streets for all users. Complete Streets

More information

Memo. Ocean Avenue Corridor Design Project Public Workshop #2 Summary

Memo. Ocean Avenue Corridor Design Project Public Workshop #2 Summary Ocean Avenue Corridor Design Project Public Workshop #2 Summary The second public workshop for the Ocean Avenue Corridor Design Project was held on Wednesday, May 14, 2014 from, 6 to 8 pm at Lick Wilmerding

More information

CRESTON ROAD COMPLETE AND SUSTAINABLE STREETS CORRIDOR PLAN

CRESTON ROAD COMPLETE AND SUSTAINABLE STREETS CORRIDOR PLAN CRESTON ROAD COMPLETE AND SUSTAINABLE STREETS CORRIDOR PLAN Preferred Plan Community Presentation September 27, 2017 City of El Paso de Robles in partnership with: Local Government Commission, W-Trans,

More information

Active Transportation Facility Glossary

Active Transportation Facility Glossary Active Transportation Facility Glossary This document defines different active transportation facilities and suggests appropriate corridor types. Click on a facility type to jump to its definition. Bike

More information

Front and Myrtle Improvement Project

Front and Myrtle Improvement Project Front and Myrtle Improvement Project MAKING BOISE THE MOST LIVABLE CITY IN THE COUNTRY DOWNTOWN: Our unique and vibrant urban neighborhood GUIDING PRINCIPLES: Innovation Celebration Transportation Downtown

More information

CITY OF COCOA BEACH 2025 COMPREHENSIVE PLAN. Section VIII Mobility Element Goals, Objectives, and Policies

CITY OF COCOA BEACH 2025 COMPREHENSIVE PLAN. Section VIII Mobility Element Goals, Objectives, and Policies CITY OF COCOA BEACH 2025 COMPREHENSIVE PLAN Section VIII Mobility Element Goals, Objectives, and Policies Adopted August 6, 2015 by Ordinance No. 1591 VIII MOBILITY ELEMENT Table of Contents Page Number

More information

El Camino Real Specific Plan. TAC/CAC Meeting #2 Aug 1, 2018

El Camino Real Specific Plan. TAC/CAC Meeting #2 Aug 1, 2018 El Camino Real Specific Plan TAC/CAC Meeting #2 Aug 1, 2018 Land Use Alternatives Goals and Tradeoffs Parks & open space Housing Retail & services Civic spaces Parking Community gathering spaces 3 Alternatives

More information

Broadway Complete Streets Project

Broadway Complete Streets Project Broadway Complete Streets Project Megan Johnson, P.E. Associate Civil Engineer James Pangburn, P.E. Consultant Project Manager After the construction of the highway system, Broadway was cut off

More information

COMPLETE STREETS PLANNER S PORTFOLIO

COMPLETE STREETS PLANNER S PORTFOLIO COMPLETE STREETS PLANNER S PORTFOLIO ISSUE 3 APRIL 2016 PLANNER S PORTFOLIO COMPLETE STREETS 1 2 6 10 14 OVERVIEW MATURE NEIGHBORHOODS GROWING SUBURBS CENTRAL PLACES ACTIVITY CORRIDORS Planner s Portfolio

More information

Creating walkable, bikeable and transit-supportive communities in Halton

Creating walkable, bikeable and transit-supportive communities in Halton Creating walkable, bikeable and transit-supportive communities in Halton By presenting current research and best practices, the information in this paper is meant to support and broaden discussion on how

More information

Berkeley Strategic Transportation Plan A-76

Berkeley Strategic Transportation Plan A-76 Berkeley Strategic Transportation Plan A-76 Appendices 1. A Team Effort 2. Where We ve Been A-11 Berkeley Strategic Transportation Plan Alameda County Transportation Plan Alameda County will be served

More information

4 MOBILITY PLAN. Mobility Plan Objectives. Mobility Context. 1. Integrate with Local and Regional Transit Improvements

4 MOBILITY PLAN. Mobility Plan Objectives. Mobility Context. 1. Integrate with Local and Regional Transit Improvements Harbor Mixed Use CHAPTER Transit Corridor 4: Mobility Plan 4 MOBILITY PLAN Mobility Plan Objectives The Harbor Corridor Plan seeks to expand and improve the ways that people move along and through the

More information

Why invest in the 1 Street S.W. Corridor?

Why invest in the 1 Street S.W. Corridor? Why invest in the 1 Street S.W. Corridor? This project is an investment in the Beltline Community and Calgary s economy. It is anticipated that The City s investment along this corridor will help with

More information

City of Wilsonville 5 th Street to Kinsman Road Extension Project

City of Wilsonville 5 th Street to Kinsman Road Extension Project City of Wilsonville 5 th Street to Kinsman Road Walking Tour & Neighborhood Workshop Summary Report Public Outreach Overview On July 18 th, 2017, the City of Wilsonville hosted a neighborhood walking tour

More information

Planning Study SR 976. Project Advisory Team Meeting May 24, 2017

Planning Study SR 976. Project Advisory Team Meeting May 24, 2017 ` SR 976 BIRD ROAD/SW 40TH STREET FROM SR 821/HEFT TO SR 5/US-1 Miami-Dade County, Florida FPID No.: 434845-4-22-01 Planning Study Project Advisory Team Meeting May 24, 2017 1 Agenda Introductions Project

More information

Item to be Addressed Checklist Consideration YES NO N/A Required Description Complete Streets Guidelines

Item to be Addressed Checklist Consideration YES NO N/A Required Description Complete Streets Guidelines Passaic County Complete Streets Checklist - Concept Development Project Name Item to be Addressed Checklist Consideration YES NO N/A Required Description Complete Streets Guidelines Existing Plans Have

More information

APPENDIX A: Complete Streets Checklist DRAFT NOVEMBER 2016

APPENDIX A: Complete Streets Checklist DRAFT NOVEMBER 2016 APPENDIX A: Complete Streets Checklist DRAFT NOVEMBER 2016 Complete Streets Checklist MetroPlan Orlando s Complete Streets Checklist is an internal planning tool for staff to further implementation of

More information

Designing Complete Streets: What you need to know

Designing Complete Streets: What you need to know Designing Complete Streets: What you need to know Getting from this to this. Continuous sidewalk Buffer w/trees Bicycle lane Raised median Buildings close to the street Flexibility in design Design and

More information

PRINCE GEORGE S PLAZA METRO AREA PEDESTRIAN PLAN

PRINCE GEORGE S PLAZA METRO AREA PEDESTRIAN PLAN PRINCE GEORGE S PLAZA METRO AREA PEDESTRIAN PLAN May 28, 2008 Agenda Welcome and introductions Project overview and issue identification Planning context and strengths Design challenges and initial recommendations

More information

Executive Summary Route 30 Corridor Master Plan

Executive Summary Route 30 Corridor Master Plan Route Corridor Master Plan Project Overview The Route Corridor Master Plan is a coordinated multimodal transportation and land use plan for the entire stretch of Route through East Whiteland Township,

More information

Report. Typical Sections. City of Middleton, WI

Report. Typical Sections. City of Middleton, WI Report Typical Sections City of Middleton, WI December 2006 Report for City of Middleton, Wisconsin Typical Sections repared by: Traffic Associates LLC and STRAND ASSOCIATES, INC. 910 West Wingra Drive

More information

Living Streets Policy

Living Streets Policy Living Streets Policy Introduction Living streets balance the needs of motorists, bicyclists, pedestrians and transit riders in ways that promote safety and convenience, enhance community identity, create

More information

Bicycle Boulevards and Neighborhood Greenways

Bicycle Boulevards and Neighborhood Greenways Bicycle Boulevards and Neighborhood Greenways Traffic Safety is Improving for Everyone 90 80 70 60 50 40 30 20 10 0 PORTLAND: TOTAL TRAFFIC FATALITIES 1986-2008 1986 1987 1988 1989 1990 1991 1992 1993

More information

Exhibit 1 PLANNING COMMISSION AGENDA ITEM

Exhibit 1 PLANNING COMMISSION AGENDA ITEM Exhibit 1 PLANNING COMMISSION AGENDA ITEM Project Name: Grand Junction Circulation Plan Grand Junction Complete Streets Policy Applicant: City of Grand Junction Representative: David Thornton Address:

More information

Dr. M.L. King, Jr. Street North Complete Streets Resurfacing Opportunities HOUSING, LAND USE, AND TRANSPORTATION COMMITTEE MARCH 22, 2018

Dr. M.L. King, Jr. Street North Complete Streets Resurfacing Opportunities HOUSING, LAND USE, AND TRANSPORTATION COMMITTEE MARCH 22, 2018 Dr. M.L. King, Jr. Street North Complete Streets Resurfacing Opportunities HOUSING, LAND USE, AND TRANSPORTATION COMMITTEE MARCH 22, 2018 What s Happening The City plans to mill and resurface Dr. M.L.

More information

RESOLUTION NO ?? A RESOLUTION OF THE CITY OF NEPTUNE BEACH ADOPTING A COMPLETE STREETS POLICY

RESOLUTION NO ?? A RESOLUTION OF THE CITY OF NEPTUNE BEACH ADOPTING A COMPLETE STREETS POLICY RESOLUTION NO. 2018-?? A RESOLUTION OF THE CITY OF NEPTUNE BEACH ADOPTING A COMPLETE STREETS POLICY WHEREAS, safe, convenient, and accessible transportation for all users is a priority of the City of Neptune

More information

CITY OF BLOOMINGTON COMPLETE STREETS POLICY

CITY OF BLOOMINGTON COMPLETE STREETS POLICY CITY OF BLOOMINGTON COMPLETE STREETS POLICY POLICY OBJECTIVE: The City of Bloomington will enhance safety, mobility, accessibility and convenience for transportation network users of all ages and abilities,

More information

Table #6 VISION CHARACTERISTICS

Table #6 VISION CHARACTERISTICS Table #6 VISION White Flint is a place to live, work, play, shop, and walk with sufficient density to encourage quality redevelopment. Vibrant streets and consistent streetscapes are important. CHARACTERISTICS

More information

Moving Towards Complete Streets MMLOS Applications

Moving Towards Complete Streets MMLOS Applications Moving Towards Complete Streets MMLOS Applications Transportation Education Series May 18 th, 2012 It s not just for cars! Presentation Overview The Complete Streets Movement What is Multi-Modal Level

More information

Creating Complete Streets to Accommodate All Users

Creating Complete Streets to Accommodate All Users Creating Complete Streets to Accommodate All Users Peter Lagerwey, Toole Design Group plagerwey@tooledesign.com Brian Dougherty, Seattle DOT brian.dougherty@seattle.gov International Conference on Urban

More information

Eliminate on-street parking where it will allow for a dedicated bus only lane %

Eliminate on-street parking where it will allow for a dedicated bus only lane % Traffic Dashboard Priorities Survey Responses Introduction 1) Are you familiar with bus rapid transit (BRT)? a. No, BRT is new to me. 597 23.5% b. I ve heard of BRT, but I don t know much about it. 1,136

More information

Better Market Street Project Update. Urban Forestry Council September 17, 2014

Better Market Street Project Update. Urban Forestry Council September 17, 2014 Better Market Street Project Update Urban Forestry Council September 17, 2014 Project Area Limits Better Market Street Schedule Market Street City s busiest transit corridor Over 85 buses per hour 14 surface

More information

Agenda. Overview PRINCE GEORGE S PLAZA METRO AREA PEDESTRIAN PLAN

Agenda. Overview PRINCE GEORGE S PLAZA METRO AREA PEDESTRIAN PLAN PRINCE GEORGE S PLAZA METRO AREA PEDESTRIAN PLAN May 28, 2008 Agenda Welcome and introductions Project overview and issue identification Planning context and strengths Design challenges and initial recommendations

More information

7 Complete Streets & Roadway Aesthetics

7 Complete Streets & Roadway Aesthetics 7 Complete Streets & Roadway Aesthetics 7.1 OVERVIEW Our streets lay the foundation for how we interface with travel needs, physical exercise, social exchanges and access to goods and services. They are

More information

Columbia Pike Implementation Team (CPIT) Meeting

Columbia Pike Implementation Team (CPIT) Meeting Columbia Pike Implementation Team (CPIT) Meeting November 30, 2010 Agenda Introductions / Purpose of Meeting Review of project goals Multimodal project: 10% street design between the curbs Discussion Multimodal

More information

Town of Babylon Sustainable Complete Streets Policy

Town of Babylon Sustainable Complete Streets Policy Town of Babylon Sustainable Complete Streets Policy Steve Bellone, Supervisor Adopted July 14, 2010 1 Table of Contents Vision... 3 Policy Statement... 3 Definition... 3 Road Users... 4 Network... 4 Roads...

More information

Chapter 5. Complete Streets and Walkable Communities.

Chapter 5. Complete Streets and Walkable Communities. Chapter 5. Complete Streets and Walkable Communities. 5.1 Description of Complete Streets. Cities throughout the world, and specifically the United States, are coming to embrace a new transportation and

More information

Cycle Track Design Best Practices Cycle Track Sections

Cycle Track Design Best Practices Cycle Track Sections Design Best Practices Sections It is along street segments where the separation and protection methods of cycle tracks offer more comfort than conventional bicycle lanes, and are more attractive to a wide

More information

Safe Streets. City of Lake Forest Park. March 21, 2017

Safe Streets. City of Lake Forest Park. March 21, 2017 Safe Streets City of Lake Forest Park March 21, 2017 1 01 WELCOME 2 Agenda WELCOME WHAT IS THIS PROJECT? CONTEXT DRAFT CITYWIDE PROJECTS EXERCISE INTRODUCTION 3 02 WHAT IS THIS PROJECT? 4 WHAT IS THIS

More information

BETHEL ROAD AND SEDGWICK ROAD CORRIDOR STUDY

BETHEL ROAD AND SEDGWICK ROAD CORRIDOR STUDY DRAFT PLAN City Council Meeting August 14, 2017 STUDY AREA Sedgwick Corridor State Route 160, principal arterial with Class 3 access management designation, commuter and freight route, connection to SR

More information

5 Circulation & Parking

5 Circulation & Parking 5 Circulation & Parking Downtown Parking & Circulation Strategy. Downtown Wayne has a somewhat disconnected system of local public streets to connect downtown with the residential neighborhoods, and primary

More information

Ocean Park Boulevard Streetscape Improvement Project Alternatives & Trade Offs

Ocean Park Boulevard Streetscape Improvement Project Alternatives & Trade Offs City Council Study Session January 27, 2009 Ocean Park Boulevard Streetscape Improvement Project Alternatives & Trade Offs Scope of Work Purpose of Tonight s Meeting Review work to date and direct staff

More information

EXECUTIVE SUMMARY. Vision

EXECUTIVE SUMMARY. Vision Vision Walking and bicycling in Salt Lake City will be safe, convenient, comfortable, and viable transportation options that connect people to places, foster recreational and economic development opportunities,

More information

Thank you for attending

Thank you for attending Improving mobility safety comfort WELCOME Thank you for attending The purpose of this meeting is to: Learn about the project Prioritize potential walking and biking improvements on Snelling Ave Gather

More information

Environment and Public Works Committee Presentation

Environment and Public Works Committee Presentation Mixed Use Centers Complete Streets Guidelines Project Environment and Public Works Committee Presentation December 10, 2008 Project Objectives: Conduct an inter-departmental and agency process to study

More information

Lawrence Avenue Streetscape Concepts August 30, 2011

Lawrence Avenue Streetscape Concepts August 30, 2011 Lawrence Avenue Streetscape Concepts August 30, 2011 Neighborhood Context Phase II: River to Western Ave. Phase I: Western Ave. to Clark St. Key Map Lawrence Ave. Existing Streetscape Conditions East of

More information

C C C

C C C C-012-001 Thank you for your support for the creation of new public space and nonmotorized access between downtown and the waterfront through the Overlook Walk, the East-West Connections, and the Promenade.

More information

Community Task Force July 25, 2017

Community Task Force July 25, 2017 Community Task Force July 25, 2017 Welcome and Introductions Project Partners Regional Transportation District (RTD) Colorado Department of Transportation (CDOT) Denver Regional Council of Governments

More information

CITY OF SIGNAL HILL Cherry Avenue Signal Hill, CA

CITY OF SIGNAL HILL Cherry Avenue Signal Hill, CA CITY OF SIGNAL HILL 2175 Cherry Avenue Signal Hill, CA 90755-3799 AGENDA ITEM TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL FROM: STEVE MYRTER, P. E. DIRECTOR OF PUBLIC WORKS SUBJECT: SPRING STREET

More information

APPENDIX A. Outreach Summary

APPENDIX A. Outreach Summary APPENDIX A Outreach Summary COUNTYWIDE TRANSPORTATION PLAN Summary of Public Outreach and Engagement To gather an understanding of the transportation issues and priorities throughout the county, and inform

More information

INDOT Complete Streets Guideline & Policy

INDOT Complete Streets Guideline & Policy INDOT Complete Streets Guideline & Policy INTRODUCTION The Complete Streets guidelines build upon multiple efforts and promote a multimodal transportation system that is integrated and sustains land use

More information

EL CAMINO REAL BUS RAPID TRANSIT (BRT) PROJECT

EL CAMINO REAL BUS RAPID TRANSIT (BRT) PROJECT Agenda Item #4.2 EL CAMINO REAL BUS RAPID TRANSIT (BRT) PROJECT VTA BOARD WORKSHOP MAY 1, 2015 ABOUT THIS PRESENTATION CONTEXT Existing conditions and planning for growth WHAT IS THE PROJECT? Project alternatives

More information

PUBLIC REALM MASTER PLAN

PUBLIC REALM MASTER PLAN WESTSHORE BUSINESS DISTRICT PUBLIC REALM MASTER PLAN MASTER PLAN COMMITTEE MEETING MARCH 20, 2013 WESTSHORE BUSINESS DISTRCT PUBLIC REALM MASTER PLAN MACRO-SCALE CONCEPT: A PUBLIC REALM FRAMEWORK DEFINED

More information

Perryville TOD and Greenway Plan

Perryville TOD and Greenway Plan Perryville TOD and Greenway Plan Greenway Glossary Pathway: A bicycle and pedestrian path separated from motorized vehicular traffic by an open space, barrier or curb. Multi-use paths may be within the

More information

Prince George s County plans, policies, and projects

Prince George s County plans, policies, and projects Prince George s County plans, policies, and projects Over 250 projects for trails, bikeways, designated bike lanes and sidewalk construction Trail projects that improve access to Metro Sidewalk and trail

More information

Public Open House #2. THE CITY OF NORTH VANCOUVER CHESTERFIELD AVENUE CYCLING IMPROVEMENTS (4th - 13th STREET) JULY 2013

Public Open House #2. THE CITY OF NORTH VANCOUVER CHESTERFIELD AVENUE CYCLING IMPROVEMENTS (4th - 13th STREET) JULY 2013 CHESTERFIELD AVENUE CYCLING IMPROVEMENTS (4th - 13th Street) Public Open House #2 1 Chesterfield Avenue provides an important north/south connection between Lonsdale Quay and West 23rd Street Purpose of

More information

City of Fairfax, Virginia City Council Work Session

City of Fairfax, Virginia City Council Work Session City of Fairfax, Virginia City Council Work Session Agenda Item # 4b City Council Meeting 6/2/2015 TO: FROM: SUBJECT: ISSUE(S): SUMMARY: FISCAL IMPACT: RECOMMENDATION: ALTERNATIVE COURSE OF ACTION: RESPONSIBLE

More information

Physical Implications of Complete Streets Policies

Physical Implications of Complete Streets Policies Presentation Overview Physical Implications of Complete Norm Cox, ASLA, LLA Landscape Architect Ann Arbor, Michigan, 10:45 to Noon What Are Complete Streets? What Matters to Bicyclists and Pedestrians

More information

How To Encourage More Efficient Transportation in Brazilian Cities

How To Encourage More Efficient Transportation in Brazilian Cities How To Encourage More Efficient Transportation in Brazilian Cities Todd Litman Victoria Transport Policy Institute Presented Seminar on Discouraging The Use Of Cars São Paulo, Brazil 3 September 2013 Creating

More information

Terwillegar Drive Expressway Draft Concept Plan

Terwillegar Drive Expressway Draft Concept Plan Terwillegar Drive Expressway Draft Concept Plan Anthony Henday Drive to Whitemud Drive November 28 5:00-8:00 p.m. December 1 10:00 a.m. - 3:00 p.m. Let s Talk Today you can: Learn about the new direction

More information

Kennedy Plaza and Providence Downtown Transit Connector PUBLIC MEETING. Stakeholder Meeting #1 October 24, 2016

Kennedy Plaza and Providence Downtown Transit Connector PUBLIC MEETING. Stakeholder Meeting #1 October 24, 2016 Kennedy Plaza and Providence Downtown Transit Connector PUBLIC MEETING Stakeholder Meeting #1 October 24, 2016 May 2017 1 WHAT IS THE DTC? 1.5 mile corridor between Providence Station and the Hospital

More information

Las Tunas Downtown Revitalization City Council Study Session. December 1, :00 p.m. Live Oak Park Community Center

Las Tunas Downtown Revitalization City Council Study Session. December 1, :00 p.m. Live Oak Park Community Center Las Tunas Downtown Revitalization City Council Study Session December 1, 2015 7:00 p.m. Live Oak Park Community Center AGENDA 2 Provide downtown context. Confirm project goals. Analyze three design concepts.

More information

General Plan Circulation Element Update Scoping Meeting April 16, 2014 Santa Ana Senior Center, 424 W. 3rd Street, Santa Ana, CA 92701

General Plan Circulation Element Update Scoping Meeting April 16, 2014 Santa Ana Senior Center, 424 W. 3rd Street, Santa Ana, CA 92701 General Plan Circulation Element Update Scoping Meeting April 16, 2014 Santa Ana Senior Center, 424 W. 3rd Street, Santa Ana, CA 92701 Meeting Agenda 1. Purpose of Scoping Meeting 2. Project Overview 3.

More information

Chapter 2: Standards for Access, Non-Motorized, and Transit

Chapter 2: Standards for Access, Non-Motorized, and Transit Standards for Access, Non-Motorized, and Transit Chapter 2: Standards for Access, Non-Motorized, and Transit The Washtenaw County Access Management Plan was developed based on the analysis of existing

More information

OCALA/MARION TPO CITY OF BELLEVIEW CORRIDOR PLAN STUDY PRESENTATION TO THE BELLEVIEW CITY COMMISSION JANUARY 25, :00 PM

OCALA/MARION TPO CITY OF BELLEVIEW CORRIDOR PLAN STUDY PRESENTATION TO THE BELLEVIEW CITY COMMISSION JANUARY 25, :00 PM OCALA/MARION TPO CITY OF BELLEVIEW CORRIDOR PLAN STUDY PRESENTATION TO THE BELLEVIEW CITY COMMISSION JANUARY 25, 2016 6:00 PM STUDY AREA Ocala/Marion TPO US-441 Corridor Study 2 Ocala/Marion TPO US-441

More information

MAKE YOUR PLACE IN CHANNELSIDE

MAKE YOUR PLACE IN CHANNELSIDE MAKE YOUR PLACE IN CHANNELSIDE INTRODUCTION PROJECT LIMITS Channelside Drive from Cumberland Ave to Kennedy Boulevard EXISTING CONDITIONS EXISTING CONDITIONS CHANNELSIDE DRIVE FROM E. CUMBERLAND AVENUE

More information

FOLSOM-HOWARD STREETSCAPE OVERVIEW

FOLSOM-HOWARD STREETSCAPE OVERVIEW FOLSOM-HOWARD STREETSCAPE OVERVIEW SoMa residents should have the same kinds of amenities that other neighborhoods have. The Folsom- Howard Streetscape Project will make SoMa more livable by making it

More information

Paoli Road Improvement Feasibility Study

Paoli Road Improvement Feasibility Study Paoli Road Improvement Feasibility Study & Public Participation Project March 24, 2015 Prepared for: Tredyffrin Township Prepared by: McMahon Associates, Inc. with Town Planning Partnership, LLC Glackin

More information

City of Novi Non-Motorized Master Plan 2011 Executive Summary

City of Novi Non-Motorized Master Plan 2011 Executive Summary City of Novi Non-Motorized Master Plan 2011 Executive Summary Prepared by: February 28, 2011 Why Plan? Encouraging healthy, active lifestyles through pathway and sidewalk connectivity has been a focus

More information

Mission-Geneva Transportation Study Community Workshop 2 July 8, 2006

Mission-Geneva Transportation Study Community Workshop 2 July 8, 2006 Community Workshop 2 July 8, 2006 Small Group Workbook 1 Basic Improvements on Mission Street Streetscape. Pedestrian-scale lighting; landscaping; community art on utility boxes; more (possibly unique)

More information

Pennsylvania Avenue (CR 484) Design Alternatives Study

Pennsylvania Avenue (CR 484) Design Alternatives Study MEMORANDUM Pennsylvania Avenue (CR 484) Design Alternatives Study Prepared for: APRIL 2016 Prepared By TABLE OF CONTENTS Project Background... 2 Previous Concept... 2 Existing Conditions... 4 New Alternatives...

More information

complete streets design and construction standards public primer City of Edmonton

complete streets design and construction standards public primer City of Edmonton complete streets design and construction standards public primer City of Edmonton introduction Complete Streets are streets for everyone: people who walk, wheel, bike, take transit, or drive. They are

More information

Ocean Park Boulevard Green Street Project Alternatives & Trade Offs

Ocean Park Boulevard Green Street Project Alternatives & Trade Offs Planning Commission March 4, 2009 Ocean Park Boulevard Green Street Project Alternatives & Trade Offs Purpose of Tonight s Meeting Review concept plans and options Provide input on alternatives and trade-offs

More information

Roadways. Roadways III.

Roadways. Roadways III. Introduction 97 Roadway Design Principles 98 Safe Speeds 99 Optimizing of Street Space 00 Minimum Lane Widths in the City of Boston 02 Design Features that Reduce Operating Speeds 05 Travel Lanes Transit

More information

Giles Run Connector Road

Giles Run Connector Road Giles Run Connector Road Laurel Hill Adaptive Reuse Area to Laurel Crest Drive South County Federation Meeting June 14, 2016 History Connector road included in the Laurel Hill Comprehensive Plan amendment

More information

Figure 5-1 Complete Street Zones. Roadside. May include frontage, pedestrian throughway, furnishings and curbside areas.

Figure 5-1 Complete Street Zones. Roadside. May include frontage, pedestrian throughway, furnishings and curbside areas. Design Guidelines 5 The design guidelines presented in this section provide descriptions related to the form and function of the four Complete Streets zones: roadside, parking, roadways and lanes, median,

More information

Bristol Street Improvements Civic Center Dr. to Washington Ave. Washington Square Artesia Pilar Flower Park. Tuesday, September 27, 2016

Bristol Street Improvements Civic Center Dr. to Washington Ave. Washington Square Artesia Pilar Flower Park. Tuesday, September 27, 2016 Street Civic Center Dr. to Washington Ave. Special Joint Neighborhoods Meeting Washington Square Artesia Pilar Flower Park Tuesday, September 27, 2016 El Salvador Recreation Center 1 Previous Informational

More information

Road Diets: Reconfiguring Streets for Multi-Modal Travel

Road Diets: Reconfiguring Streets for Multi-Modal Travel Road Diets: Reconfiguring Streets for Multi-Modal Travel Tom Grant, P.E., PTOE What is a Road Diet? Reconfiguration of travel lanes to benefit all roadway users (i.e., Complete Street) Reclaiming the space

More information

Vision. Goals and Objectives. Walking

Vision. Goals and Objectives. Walking Vision Walking and biking is an accepted and valued part of everyday life in Portsmouth. People of all ages and abilities include walking and biking as part of their daily activities which helps to make

More information

ACTIVE TRANSPORTATION

ACTIVE TRANSPORTATION ACTIVE TRANSPORTATION Mobility 2040 Supported Goals Improve the availability of transportation options for people and goods. Support travel efficiency measures and system enhancements targeted at congestion

More information

SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY

SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY THIS PRINT COVERS CALENDAR ITEM NO. : 12 DIVISION: Sustainable Streets BRIEF DESCRIPTION: SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY Approving various bicycle improvements and traffic modifications

More information

2014 Wisconsin Tribal Transportation Conference. Matt Halada Transportation Planner NE Region

2014 Wisconsin Tribal Transportation Conference. Matt Halada Transportation Planner NE Region 2014 Wisconsin Tribal Transportation Conference Matt Halada Transportation Planner NE Region Implementing Wisconsin s Pedestrian and Bicycle Accommodations Law (Complete Streets) Tools and methods for

More information

El Paso County 2040 Major Transportation Corridors Plan

El Paso County 2040 Major Transportation Corridors Plan El Paso County 2040 Major Transportation Corridors Plan Connect-our-County Online Transportation User Survey Preliminary Results June 24, 2010 Years of Residence 2. How many years have you LIVED HERE?

More information

Multimodal Through Corridors and Placemaking Corridors

Multimodal Through Corridors and Placemaking Corridors 68 Multimodal Through Corridors and Placemaking Corridors Corridors have different functions in a region. Some corridors are used to get smoothly and rapidly through a region or to get quickly to major

More information

North Avenue Corridor Study

North Avenue Corridor Study North Avenue Corridor Study City Council October 6, 2014 Presentation Outline Project Initiation & Process Corridor Conditions & Issues Vision & Goals Concept Development - Development/Evaluation Implementation

More information

Monterey Road Complete Streets

Monterey Road Complete Streets Monterey Road Complete Streets Complete Street Objectives Improve livability and economic vitality Enhance pedestrian environment Accommodate bicyclists safely Reduce noise and air pollution Create attractive,

More information

Frequently Asked Questions

Frequently Asked Questions Frequently Asked Questions Business US 190 in Copperas Cove From Avenue D to Constitution Drive What is access management? A. Access Management is a growing effort by government agencies to improve how

More information

Balancing Operation & Safety for Motorized and Non-Motorized Traffic

Balancing Operation & Safety for Motorized and Non-Motorized Traffic Balancing Operation & Safety for Motorized and Non-Motorized Traffic Brian Willham, PE, PTOE Iowa Director - MOVITE June 30, 2014 Learning Objectives: When & Why should we measure the performance of complete

More information

Use this guide to learn more about walkability and how you can make your community safer to walk

Use this guide to learn more about walkability and how you can make your community safer to walk Walkability Guide Do You Enjoy Walking In Your Community? Use this guide to learn more about walkability and how you can make your community safer to walk 2 About This Guide Circulate San Diego believes

More information

TRANSPORTATION ASSESSMENT

TRANSPORTATION ASSESSMENT TRANSPORTATION ASSESSMENT Traffic Modeling The mobility findings analysis for Dallas was based on the methodology of the North Central Texas Council of Government s Regional travel demand model. This model

More information