1 Lawrence Avenue Streetscape Concepts August 30, 2011

2 Neighborhood Context

3 Phase II: River to Western Ave. Phase I: Western Ave. to Clark St. Key Map Lawrence Ave.

4 Existing Streetscape Conditions East of Western Ave.

5 Lawrence Avenue Existing Cross Section Western Ave. to Ashland Ave.

6 Lane reduction: 4-lane to 3-lane Conversion Wider sidewalks Designated bike lane Benefits all modes of transportation AASHTO Design guidelines no longer recommend urban four-lane roadways without medians and turning pockets. Why Lawrence Ave? Narrow sidewalks on both sides of the street High bicycle use that exceeds state recommendations for installation of a dedicated bike lane Strong public transit use via the CTA Brown Line, Metra North Line, and 6 bus routes on or intersecting Lawrence. Economic strength of Lincoln Square / Lincoln Ave Corridor Mid-scale commercial and institutional land uses Road Diet / Complete Streets Basics

7 Lawrence Avenue Proposed Cross Section East of Western Ave.

8 Wider Sidewalks for Cafes Improved Lighting Over 150 New Street Trees Community Identifiers Site Furniture Permeable Pavers Streetscape Improvements East of Western Ave.

9 Kiosk Gateway with Identifier Streetscape Elements: River to Damen

10 Pedestrian Refuge Islands oshorter crosswalk distance with 11 New pedestrian refuge areas created at center turn lane crosswalks. Bump outs Stamped Asphalt Crosswalks Storm Water Bumpouts Streetscape Improvements Pedestrian Improvements East of Western Ave.

11 N Key Plan Bump-outs Into Lawrence Side Street Bump-outs * Still to be determined which bump outs are planters or are hardscape Pedestrian Refuge Islands Streetscape Elements: East of Western Bump-Out Key Plan

12 Mid-Block Sidewalk Planters o41 planters located near catch basins to allow for infiltration planter design. oproposed between Western Ave. and Clark St. where sidewalk widths allow. o Maintenance Agreement will be required prior to construction Streetscape Improvements Mid-Block Planters

13 New Designated Bike Lane oadding 1 mile of designated bike lane (in each direction). ocompleting the 5 mile link from the Kennedy/Blue Line to east of Sheridan Rd (Elston to Central Park shared) and to Lakefront. Streetscape Improvements Designated Bike Lanes East of Western Ave.

14 Existing Streetscape Conditions East of Western Ave.

15 Proposed Streetscape Conditions East of Western Ave.

16 Impact of the Road Diet on the Lawrence Corridor Increased motorist delay while traveling the Lawrence Corridor Depending on the time of day, travel times between Ashland Ave. and Western Ave. may increase by 3-9 mins. Current travel times for westbound evening rush hour: Western Ave. to Kedzie Ave. - 5:65 Ashland Ave. to Western Ave. 3:52 Increased motorist delay in turning off/onto Lawrence Ave and crossing Lawrence Ave. Queue Lengths will increase at traffic signals, with the heaviest at PM westbound rush hour. During peak hours, traffic will backup through side streets. Increased potential of cut-through traffic by cars and delivery vans. Traffic calming elements (speed humps) exist on numerous side streets. Corridor Impacts

17 Streetscape Changes to Mitigate Negative Impacts of the Road Diet Traffic signal timings will be adjusted to provide greater efficiency for through-traffic on Lawrence Ave. All signals 85 seconds Ped crossings between ft/second A center turn lane is being provided so that turning cars do not interrupt the flow through traffic and to facilitate cars turning onto Lawrence. Corridor Impacts

18 Streetscape Changes to Mitigate Negative Impacts of the Road Diet Pedestrian refuge islands will increase safety for pedestrians crossing at non-signalized intersections Bump-Outs on side streets will reduce cut-through traffic onto side streets Corridor Impacts

19 Key Plan N Existing Traffic calming element (Speed Bump) Streetscape Elements: Western to Ashland Traffic Calm Key Plan

20 Streetscape Changes to Mitigate Negative Impacts of the Road Diet Buses are still able to pull over at stops in order to allow through-traffic to pass The major intersections of Western Ave., Damen Ave., and Ashland Ave will maintain 4-lane cross sections Corridor Impacts

21 Traffic flow expected to remain about the same by: Making right turn bays into rightthru lanes (8 parking stalls lost). Increased length of left turn storage bays. Addition of left turn signals. Pavement marking changes only; no curb line adjustments. Major Intersection- Ashland Ave.

22 Traffic flow expected to remain about the same by: Making right turn bays into shared rightthrough lanes (11 parking stalls lost). Increased length of left turn storage bays on Lawrence by 90 ft. Addition of left turn signals for eastbound and westbound traffic on Lawrence. Adjustment to traffic signal timing to allow for longer greens on Lawrence. Enlargement of Intersection at Damen Ave.

23 Traffic flow expected to remain the same by: Making right turn bays into shared rightthrough lanes (11 parking stalls lost). Increased length of left turn storage bays on Western by 200 ft on the south leg and 20 ft on the north leg. Major Intersection- Western Ave.

24 Claremont Plaza - Area Context

25

26 Concept A

27

28

29 Phase II: River to Western Ave. Phase I: Western Ave. to Clark St. Key Map Lawrence Ave.

30 Existing Streetscape Conditions West of Western Ave.

31 Lawrence Avenue Existing Cross Section West of Western Ave.

32 Lawrence Avenue Proposed Cross Section West of Western Ave.

33 Wider Sidewalks for Cafes Improved Lighting Over 100 New Street Trees Community Identifiers Site Furniture Permeable Pavers Streetscape Improvements East of Western Ave.

34 ADA Compliant Crosswalks Stamped Asphalt Crosswalk o Shorter pedestrian crossing distances o Larger buffer zone for pedestrians Streetscape Improvements Pedestrian Improvements

35 Bump-outs o Shorter pedestrian crossing distances o Larger buffer zone for pedestrians o Area for plantings Streetscape Elements: Bump-outs

36 Storm Water Bump-outs o Collect storm water runoff onative Grass plantings provide multi season interest Streetscape Elements: Storm Water Bump-outs

37 Key Plan N Bump-outs Into Lawrence Side Street Bump-outs Still to be determined which bump outs are planters or are hardscape Streetscape Elements: Bump-out Key Plan

38 Kiosk Gateway with Identifier Streetscape Elements: River to Damen

39 Existing Streetscape Conditions West of Western Ave.

40 Proposed Streetscape Conditions West of Western Ave.

41 Lawrence Avenue Streetscape Concepts THANK YOU

Complete Streets Chicago: Data Driven Design. Luann Hamilton Deputy Commissioner

Complete Streets Chicago: Data Driven Design. Luann Hamilton Deputy Commissioner Complete Streets Chicago: Data Driven Design Luann Hamilton Deputy Commissioner AGENDA Chicago s goals Complete Streets & Sustainable Infrastructure Guides Data-Driven Planning Setting goals Scoping/research

More information

Clybourn Ave. Protected Bike Lane Study Halsted St. to Division St.

Clybourn Ave. Protected Bike Lane Study Halsted St. to Division St. Clybourn Ave. Protected Bike Lane Study Halsted St. to Division St. Nathan Roseberry, Senior Engineer Pam Broviak, Project Manager July 24, 2014 Agenda Project Goals Existing Roadway Conditions Traffic

More information

Balancing Operation & Safety for Motorized and Non-Motorized Traffic

Balancing Operation & Safety for Motorized and Non-Motorized Traffic Balancing Operation & Safety for Motorized and Non-Motorized Traffic Brian Willham, PE, PTOE Iowa Director - MOVITE June 30, 2014 Learning Objectives: When & Why should we measure the performance of complete

More information

SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY

SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY THIS PRINT COVERS CALENDAR ITEM NO. : 10.2 DIVISION: Sustainable Streets BRIEF DESCRIPTION: SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY Adopting Conceptual Proposal for Streetscape Improvements to Broadway,

More information

Traffic Improvements for the Transit Oriented Development District (TODD) Meriden Public Library March 11, 2014

Traffic Improvements for the Transit Oriented Development District (TODD) Meriden Public Library March 11, 2014 Traffic Improvements for the Transit Oriented Development District (TODD) Meriden Public Library March 11, 2014 Project Overview Coordinate roadway improvements with other major projects HUB Flood Control

More information

Community Meeting February 27, 2007 Dorchester Avenue Transportation & Streetscape Improvements Action Plan February 27, 2007

Community Meeting February 27, 2007 Dorchester Avenue Transportation & Streetscape Improvements Action Plan February 27, 2007 Community Meeting Tonight s Agenda 6:00 Introductions South Boston/Dot Ave Improvement Study Background 6:15 Consultant Introductions Review of Scope and Schedule Review of Proposed Corridor Wide Guidelines

More information

MARTIN LUTHER KING JR. WAY

MARTIN LUTHER KING JR. WAY OCTOBER 2011 40 Vision and Goals The Martin Luther King, Jr. Way Illustrative Master Plan that follows has been developed through a process of community involvement. It expresses a long term vision for

More information

Chicago Safe Routes to School Safe Routes to High School (SRTS/SRTHS)

Chicago Safe Routes to School Safe Routes to High School (SRTS/SRTHS) Chicago Safe Routes to School Safe Routes to High School (SRTS/SRTHS) Marshall Community High School and Faraday Elementary School Recommended Improvements Agenda Goals Related Programs Project Location/Area

More information

Off-road Trails. Guidance

Off-road Trails. Guidance Off-road Trails Off-road trails are shared use paths located on an independent alignment that provide two-way travel for people walking, bicycling, and other non-motorized users. Trails specifically along

More information

122 Avenue: 107 Street to Fort Road

122 Avenue: 107 Street to Fort Road : 107 Street to Fort Road November 24, 2015 4:30 8:00 p.m. Meeting Purpose Summarize project work completed to date Share results of public input from Phase 1 Share the draft concept plan and proposed

More information

CURBSIDE ACTIVITY DESIGN

CURBSIDE ACTIVITY DESIGN 5 CURBSIDE ACTIVITY DESIGN This chapter provides design guidance for separated bike lanes adjacent to curbside activities including parking, loading and bus stops. Typical configurations are presented

More information

Mission-Geneva Transportation Study Community Workshop 2 July 8, 2006

Mission-Geneva Transportation Study Community Workshop 2 July 8, 2006 Community Workshop 2 July 8, 2006 Small Group Workbook 1 Basic Improvements on Mission Street Streetscape. Pedestrian-scale lighting; landscaping; community art on utility boxes; more (possibly unique)

More information

APPENDIX A: Complete Streets Checklist DRAFT NOVEMBER 2016

APPENDIX A: Complete Streets Checklist DRAFT NOVEMBER 2016 APPENDIX A: Complete Streets Checklist DRAFT NOVEMBER 2016 Complete Streets Checklist MetroPlan Orlando s Complete Streets Checklist is an internal planning tool for staff to further implementation of

More information

Omaha s Complete Streets Policy

Omaha s Complete Streets Policy Omaha s Complete Streets Policy (Adopted August 2015) VISION To create great places and enhance our quality of life, the City of Omaha will provide safe, accessible streets for all users. Complete Streets

More information

Commerce Street Complete Street Project from Good Latimer Expressway to Exposition Avenue

Commerce Street Complete Street Project from Good Latimer Expressway to Exposition Avenue Commerce Street Complete Street Project from Good Latimer Expressway to Exposition Avenue T A N Y A B R O O K S A S S I S T A N T D I R E C T O R M O B I L I T Y P L A N N I N G M O B I L I T Y A N D S

More information

San Jose Transportation Policy

San Jose Transportation Policy San Jose Transportation Policy Protected Intersections in LOS Policies to Support Smart Growth Presented by: Manuel Pineda City of San Jose Department of Transportation Bay Area Map San Francisco Oakland

More information

PUBLIC REALM MASTER PLAN

PUBLIC REALM MASTER PLAN WESTSHORE BUSINESS DISTRICT PUBLIC REALM MASTER PLAN MASTER PLAN COMMITTEE MEETING MARCH 20, 2013 WESTSHORE BUSINESS DISTRCT PUBLIC REALM MASTER PLAN MACRO-SCALE CONCEPT: A PUBLIC REALM FRAMEWORK DEFINED

More information

THE ALAMEDA CONCEPT DESIGN COMMUNITY MEETING 3. A Plan for The Beautiful Way JANUARY 28, 2010

THE ALAMEDA CONCEPT DESIGN COMMUNITY MEETING 3. A Plan for The Beautiful Way JANUARY 28, 2010 CONCEPT DESIGN COMMUNITY MEETING 3 JANUARY 28, 2010 AGENDA INTRODUCTION COMMUNITY INPUT ROADWAY STUDIES STREETSCAPE DESIGN STATIONS DISCUSSION SUMMARY AND DISCUSSION NEXT STEPS CLOSE INTRODUCTION SCHEDULE

More information

Road Diets FDOT Process

Road Diets FDOT Process Florida Department of TRANSPORTATION Road Diets FDOT Process Humberto Castillero, PE, PTOE Roadway Design Office Purpose of Guide Develop a statewide lane elimination review process Balance state & local

More information

Geary Bus Rapid Transit Project

Geary Bus Rapid Transit Project Geary Bus Rapid Transit Project Outreach Update SAN FRANCISCO COUNTY TRANSPORTATION AUTHORITY SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY April 28, 2016 Project Activities Since January Meeting Continued

More information

Ocean Park Boulevard Streetscape Improvement Project Alternatives & Trade Offs

Ocean Park Boulevard Streetscape Improvement Project Alternatives & Trade Offs City Council Study Session January 27, 2009 Ocean Park Boulevard Streetscape Improvement Project Alternatives & Trade Offs Scope of Work Purpose of Tonight s Meeting Review work to date and direct staff

More information

City of Seattle Edward B. Murray, Mayor

City of Seattle Edward B. Murray, Mayor City of Seattle Edward B. Murray, Mayor Department of Transportation Scott Kubly, Director Eastlake Community Council 117 E Louisa St. #1 Seattle, WA 98102-3278 January 28, 2016 RE: Roosevelt to Downtown

More information

Monroe Street Reconstruction

Monroe Street Reconstruction Total participants: 45+ Monroe Street Reconstruction Cross Section Workshop Notes September 29, 2016, Wingra School Workshop Orientation, Technical and Functional Considerations: The workshop began with

More information

FOCUS AREA 1 - Alberta Avenue Pocket Park 3 (121 Ave and 92 St)

FOCUS AREA 1 - Alberta Avenue Pocket Park 3 (121 Ave and 92 St) FOCUS AREA 1 - Alberta Avenue Pocket Park 3 (121 Ave and 92 St) New benches Plant evergreen trees Widen existing sidewalk from 1.5m to 1.8m Marked crosswalk 1.8m wide sidewalk Add pedestrian oriented lights

More information

Report. Typical Sections. City of Middleton, WI

Report. Typical Sections. City of Middleton, WI Report Typical Sections City of Middleton, WI December 2006 Report for City of Middleton, Wisconsin Typical Sections repared by: Traffic Associates LLC and STRAND ASSOCIATES, INC. 910 West Wingra Drive

More information

95 th Street Corridor Transportation Plan. Steering Committee Meeting

95 th Street Corridor Transportation Plan. Steering Committee Meeting 95 th Street Corridor Transportation Plan Steering Committee Meeting August 11, 2014 PROJECT OBJECTIVES Develop a Transportation and Economic Plan for the 95 th Street Corridor Improve public transit efficiency

More information

Ocean Park Boulevard Green Street Project Alternatives & Trade Offs

Ocean Park Boulevard Green Street Project Alternatives & Trade Offs Planning Commission March 4, 2009 Ocean Park Boulevard Green Street Project Alternatives & Trade Offs Purpose of Tonight s Meeting Review concept plans and options Provide input on alternatives and trade-offs

More information

Long Island Rail Road Expansion Project Floral Park to Hicksville

Long Island Rail Road Expansion Project Floral Park to Hicksville Long Island Rail Road Expansion Project Floral Park to Hicksville Final Environmental Impact Statement Appendix 1-D Complete Streets Policy Checklist April 2017 0902ML PIN: Project Location: 18A-4 Floral

More information

Item to be Addressed Checklist Consideration YES NO N/A Required Description Complete Streets Guidelines

Item to be Addressed Checklist Consideration YES NO N/A Required Description Complete Streets Guidelines Passaic County Complete Streets Checklist - Concept Development Project Name Item to be Addressed Checklist Consideration YES NO N/A Required Description Complete Streets Guidelines Existing Plans Have

More information

Henderson Ave. Complete Streets Project

Henderson Ave. Complete Streets Project Henderson Ave. Complete Streets Project Meeting Purpose To finalize conceptual components of project prior to proceeding with preliminary engineering www.dallascompletestreets.wordpress.com MeetingAgenda

More information

Streetscape: Core Shopping District

Streetscape: Core Shopping District Streetscape: Core Shopping District DRAFT DRAFT DRAFT May 00 Core Shopping District: Phase Blue Island s Core Shopping District is located along Western Avenue, between Grove and Union Streets. Streetscape

More information

Complete Street Analysis of a Road Diet: Orange Grove Boulevard, Pasadena, CA

Complete Street Analysis of a Road Diet: Orange Grove Boulevard, Pasadena, CA Complete Street Analysis of a Road Diet: Orange Grove Boulevard, Pasadena, CA Aaron Elias, Bill Cisco Abstract As part of evaluating the feasibility of a road diet on Orange Grove Boulevard in Pasadena,

More information

Broad Street Bicycle Boulevard Design Guidelines

Broad Street Bicycle Boulevard Design Guidelines Broad Street Bicycle Boulevard Design Guidelines Building from the strategies introduced in the 2013 Bicycle Transportation Plan and community input received thus far, City Transportation Staff have identified

More information

Neighborhood Pedestrian Safety and Traffic Calming Study

Neighborhood Pedestrian Safety and Traffic Calming Study Neighborhood Pedestrian Safety and Traffic Calming Study for the area bounded by Foster Avenue, Bedford Avenue, Farragut Road and Ocean Avenue Flatbush, Brooklyn, New York prepared by Michael King, miking@trafficcalmer.com

More information

5. RUNNINGWAY GUIDELINES

5. RUNNINGWAY GUIDELINES 5. RUNNINGWAY GUIDELINES These guidelines should be considered collectively when making runningway decisions. A runningway is the linear component of the transit system that forms the right-of-way reserved

More information

UPTOWN REGIONAL BIKE CORRIDORS PROJECT SAN DIEGO ASSOCIATION OF GOVERNMENTS

UPTOWN REGIONAL BIKE CORRIDORS PROJECT SAN DIEGO ASSOCIATION OF GOVERNMENTS UPTOWN REGIONAL BIKE CORRIDORS PROJECT SAN DIEGO ASSOCIATION OF GOVERNMENTS SUMMARY REPORT: COMMUNITY UPDATE MEETING February 6, 2014 6 8:30 p.m. Roosevelt Middle School Library 3366 Park Blvd, San Diego

More information

Community Task Force November 15, 2017

Community Task Force November 15, 2017 Community Task Force November 15, 2017 Welcome and Introductions Project Partners Regional Transportation District (RTD) Colorado Department of Transportation (CDOT) Denver Regional Council of Governments

More information

Joshua Saak, P.E., PTOE Traffic Design Engineer Ada County Highway District May 23, 2013

Joshua Saak, P.E., PTOE Traffic Design Engineer Ada County Highway District May 23, 2013 Joshua Saak, P.E., PTOE Traffic Design Engineer Ada County Highway District May 23, 2013 Creating Great Streets Through Road Diets and Conversions The Charlotte Experience Topics to Discuss Charlotte s

More information

City of Wausau Wausau Center Urban Design and Transportation Master Plan. Design Workshop // October 18, 2018

City of Wausau Wausau Center Urban Design and Transportation Master Plan. Design Workshop // October 18, 2018 City of Wausau Wausau Center Urban Design and Transportation Master Plan Design Workshop // October 18, 2018 Design Workshops // October 15-18 Workshop Study Evaluate circulation and parking patterns around

More information

About the study. North Milwaukee Ave. Key goals of this study are to: Achieve Vision Zero* by. Harmonize the space and improve walkability

About the study. North Milwaukee Ave. Key goals of this study are to: Achieve Vision Zero* by. Harmonize the space and improve walkability About the study Key goals of this study are to: North Milwaukee Avenue is a local and regional street for multiple modes of transportation. It is officially zoned and functions as a pedestrian street southeast

More information

Overview. Illinois Bike Summit IDOT Complete Streets Policy Presentation. What is a Complete Street? And why build them? And why build them?

Overview. Illinois Bike Summit IDOT Complete Streets Policy Presentation. What is a Complete Street? And why build them? And why build them? Overview Illinois Bike Summit IDOT Complete Streets Policy Presentation Aren Kriks, P.E. District One Bicycle Coordinator and Bureau of Programming Project Engineer History of Complete Streets IDOT Policy

More information

Downtown Naples Mobility and Connectivity Study. Naples City Council Presentation January 2017

Downtown Naples Mobility and Connectivity Study. Naples City Council Presentation January 2017 Downtown Naples Mobility and Connectivity Study Naples City Council Presentation January 2017 Agenda 1. Introduction 2. Scope Review 3. Project Schedule 4. Existing Conditions 5. Public Charrette 6. Mobility

More information

Dr. M.L. King, Jr. Street North Complete Streets Resurfacing Opportunities HOUSING, LAND USE, AND TRANSPORTATION COMMITTEE MARCH 22, 2018

Dr. M.L. King, Jr. Street North Complete Streets Resurfacing Opportunities HOUSING, LAND USE, AND TRANSPORTATION COMMITTEE MARCH 22, 2018 Dr. M.L. King, Jr. Street North Complete Streets Resurfacing Opportunities HOUSING, LAND USE, AND TRANSPORTATION COMMITTEE MARCH 22, 2018 What s Happening The City plans to mill and resurface Dr. M.L.

More information

Designing Complete Streets: What you need to know

Designing Complete Streets: What you need to know Designing Complete Streets: What you need to know Getting from this to this. Continuous sidewalk Buffer w/trees Bicycle lane Raised median Buildings close to the street Flexibility in design Design and

More information

95 th Street Corridor Transportation Plan. Steering Committee Meeting #2

95 th Street Corridor Transportation Plan. Steering Committee Meeting #2 95 th Street Corridor Transportation Plan Steering Committee Meeting #2 February 18, 2015 PURPOSE OF THE MEETING Update Steering Committee Present Community/Stakeholder Survey Results Present Transportation

More information

US 278 Corridor Concept Presentation. Avondale Estates Intersection Improvement/Roundabout and Road Diet Feasibility Study March 19, 2015

US 278 Corridor Concept Presentation. Avondale Estates Intersection Improvement/Roundabout and Road Diet Feasibility Study March 19, 2015 US 278 Corridor Concept Presentation Avondale Estates Intersection Improvement/Roundabout and Road Diet Feasibility Study March 19, 2015 Thanks to our Partners Atlanta Regional Commission Georgia Department

More information

COWETA HIGH SCHOOL AND EAST HIGHWAY 51

COWETA HIGH SCHOOL AND EAST HIGHWAY 51 COWETA HIGH SCHOOL AND EAST HIGHWAY 51 Lack of sidewalks along Ben Lumpkin Rd. Lack of crosswalks and ramps at intersection. Hwy 51 is wide to cross as a pedestrian. No ADA compliance or connection to

More information

Geary Corridor Bus Rapid Transit

Geary Corridor Bus Rapid Transit Geary Corridor Bus Rapid Transit Near-term Improvements Update SAN FRANCISCO COUNTY TRANSPORTATION AUTHORITY SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY Phasing Packages Phase 1 Near-term: Delivers project

More information

Agenda. Overview PRINCE GEORGE S PLAZA METRO AREA PEDESTRIAN PLAN

Agenda. Overview PRINCE GEORGE S PLAZA METRO AREA PEDESTRIAN PLAN PRINCE GEORGE S PLAZA METRO AREA PEDESTRIAN PLAN May 28, 2008 Agenda Welcome and introductions Project overview and issue identification Planning context and strengths Design challenges and initial recommendations

More information

Saskatchewan Drive Roadway Rehabilitation and Shared-Use Path Widening

Saskatchewan Drive Roadway Rehabilitation and Shared-Use Path Widening Saskatchewan Drive Roadway Rehabilitation and Shared-Use Path Widening We are here today to present the draft plan for the Saskatchewan Drive Roadway Rehabilitation and Shared-Use Path Widening project

More information

Station 1: Street & Sidewalk Upgrades

Station 1: Street & Sidewalk Upgrades Station 1: Street & Sidewalk Upgrades Existing no left turn; Potential left turn arrow, see Circulation Study boards for more information Thru-lane guidance Improved lead-in green bike lane 17TH ST CASTRO

More information

Fleur Drive Reconstruction

Fleur Drive Reconstruction Fleur Drive Reconstruction October 29, 2018 1 Agenda: Fleur Drive Reconstruction Project Scope & Cost Overview Fleur Drive Cross Section Elements - Travel Lane Widths - Sidewalk Widths - Parkway Widths

More information

STREETSCAPE CONCEPT PLAN

STREETSCAPE CONCEPT PLAN 03 STREETSCAPE CONCEPT PLAN Zone 1 This zone includes the gateway into both the downtown and the Village at Harlem. The gateway features are shown closer to the Harlem intersection to make them more prominent.

More information

STEERING COMMITTEE MEETING June 17, Streetscape Overview Burlington Comprehensive Master Plan

STEERING COMMITTEE MEETING June 17, Streetscape Overview Burlington Comprehensive Master Plan STEERING COMMITTEE MEETING June 17, 2015 Streetscape Overview Burlington Comprehensive Master Plan 1 Introduction Slide This slide show was presented to the Burlington Steering Committee on June 17, 2015

More information

COMPLETE STREETS PLANNER S PORTFOLIO

COMPLETE STREETS PLANNER S PORTFOLIO COMPLETE STREETS PLANNER S PORTFOLIO ISSUE 3 APRIL 2016 PLANNER S PORTFOLIO COMPLETE STREETS 1 2 6 10 14 OVERVIEW MATURE NEIGHBORHOODS GROWING SUBURBS CENTRAL PLACES ACTIVITY CORRIDORS Planner s Portfolio

More information

REGIONAL BICYCLE AND PEDESTRIAN DESIGN GUIDELINES

REGIONAL BICYCLE AND PEDESTRIAN DESIGN GUIDELINES REGIONAL BICYCLE AND PEDESTRIAN DESIGN GUIDELINES November 16, 2011 Deb Humphreys North Central Texas Council of Governments Bicycle and Pedestrian Advisory Committee Snapshot of the Guide 1. Introduction

More information

Southview Blvd & 3 rd Avenue Improvement Project. Public Open House December 4, to 7pm

Southview Blvd & 3 rd Avenue Improvement Project. Public Open House December 4, to 7pm Southview Blvd & 3 rd Avenue Improvement Project Public Open House December 4, 2014 5 to 7pm Southview Blvd & 3 rd Avenue Public Information Meeting Agenda Presentation 5:30 to 6:15 pm Purpose of Project

More information

INDOT Complete Streets Guideline & Policy

INDOT Complete Streets Guideline & Policy INDOT Complete Streets Guideline & Policy INTRODUCTION The Complete Streets guidelines build upon multiple efforts and promote a multimodal transportation system that is integrated and sustains land use

More information

Queensboro Bridge Bus Priority Study: Summary of Recommendations. Presentation to Manhattan Community Board 8 May 4, 2011

Queensboro Bridge Bus Priority Study: Summary of Recommendations. Presentation to Manhattan Community Board 8 May 4, 2011 : Summary of Recommendations Presentation to Manhattan Community Board 8 May 4, 2011 1 Overview Study Goal: Identify cost-effective ways to improve bus speed and reliability for local and express buses

More information

Complete Streets Policy DAVID CRONIN, P.E., CITY ENGINEER

Complete Streets Policy DAVID CRONIN, P.E., CITY ENGINEER Complete Streets Policy DAVID CRONIN, P.E., CITY ENGINEER Complete Streets City Commission adopted a Complete Streets policy in 2012 Complete Streets are road networks that are designed for all users:

More information

Joe Routt Boulevard. Access Design Options

Joe Routt Boulevard. Access Design Options Access Design Options Impacted area highlighted in yellow. Access Design Option 1 This option would involve closing Joe Routt between Gene Stallings Blvd. and Houston St. to car and bus traffic, creating

More information

RIVERSIDE DRIVE: 21st to 41st

RIVERSIDE DRIVE: 21st to 41st RIVERSIDE DRIVE: 21st to 41st Traffic Calming, Parking Lane, and Bike Lane Traffic Calming Options Traffic Calming Design Alternatives and Recommendations by Road Section Parking Lane & Bike Lane Guidance

More information

Wood and Cortland Neighborhood Greenways

Wood and Cortland Neighborhood Greenways Wednesday, May 25 th, 2016 Wood and Cortland Neighborhood Greenways Alderman Hopkins 2 nd Ward Alderman Waguespack 32 nd Ward Mike Amsden, AICP Assistant Director of Transportation Planning David Smith,

More information

City of Madison, East Johnson Street North Baldwin Street to First Street Local Street Dane County

City of Madison, East Johnson Street North Baldwin Street to First Street Local Street Dane County City of Madison, East Johnson Street North Baldwin Street to First Street Local Street Dane County Public Involvement Meeting Thursday, November 10, 2016 5:30 to 7 P.M. Festival Foods 810 E. Washington

More information

Appendix A-2: Screen 1 Alternatives Report

Appendix A-2: Screen 1 Alternatives Report Appendix A-2: Screen 1 Alternatives Report SCREEN 1 ALTERNATIVES REPORT Western & Ashland Corridors Bus Rapid Transit (BRT) Project Prepared for Chicago Transit Authority 567 West Lake Street Chicago,

More information

NJDOT Complete Streets Checklist

NJDOT Complete Streets Checklist Background The New Jersey Department of Transportation s Complete Streets Policy promotes a comprehensive, integrated, connected multi-modal network by providing connections to bicycling and walking trip

More information

FOLSOM-HOWARD STREETSCAPE OVERVIEW

FOLSOM-HOWARD STREETSCAPE OVERVIEW FOLSOM-HOWARD STREETSCAPE OVERVIEW SoMa residents should have the same kinds of amenities that other neighborhoods have. The Folsom- Howard Streetscape Project will make SoMa more livable by making it

More information

Designing for Pedestrian Safety in Washington, DC

Designing for Pedestrian Safety in Washington, DC Designing for Pedestrian Safety in Washington, DC February 25, 2014 George Branyan Pedestrian Program Coordinator District Department of Transportation DC Journey to work mode split: 2012 Means of Transportation

More information

Downtown BRT Corridor Alternatives Review: 1 st, 2 nd, 3 rd and 4 th Avenue. Bus Rapid and Conventional Transit Planning and Design Services

Downtown BRT Corridor Alternatives Review: 1 st, 2 nd, 3 rd and 4 th Avenue. Bus Rapid and Conventional Transit Planning and Design Services Downtown BRT Corridor Alternatives Review: 1 st, 2 nd, 3 rd and 4 th Avenue Bus Rapid and Conventional Transit Planning and Design Services City of Saskatoon February 2018 Project Team HDR Corporation

More information

Figure 4-10: Pedestrian Improvements Types of Potential Station Area Improvements - Place-Making Improvements

Figure 4-10: Pedestrian Improvements Types of Potential Station Area Improvements - Place-Making Improvements INCORPORATE FEATURE PAVIN IN CROSSWALK AND INTERSECTION FIELDS Identifies high-priority pedestrian areas and create a station identity through colorful and interesting patterns ADD CURB EXTENSIONS Extending

More information

PRINCE GEORGE S PLAZA METRO AREA PEDESTRIAN PLAN

PRINCE GEORGE S PLAZA METRO AREA PEDESTRIAN PLAN PRINCE GEORGE S PLAZA METRO AREA PEDESTRIAN PLAN May 28, 2008 Agenda Welcome and introductions Project overview and issue identification Planning context and strengths Design challenges and initial recommendations

More information

Citizen Advisory Group Meeting #8 May 5, Welcome. Today s meeting will focus on: Land Use & Transportation CHARLOTTEPLANNING.

Citizen Advisory Group Meeting #8 May 5, Welcome. Today s meeting will focus on: Land Use & Transportation CHARLOTTEPLANNING. Citizen Advisory Group Meeting #8 May 5, 2010 Welcome. Today s meeting will focus on: Land Use & Transportation CHARLOTTEPLANNING.ORG Meeting Agenda Handouts: o Meeting Agenda o Summary of East Seventh

More information

WELCOME. Purpose of the Open House. Update you on the project. Present a draft recommended plan. Receive your input

WELCOME. Purpose of the Open House. Update you on the project. Present a draft recommended plan. Receive your input WELCOME Purpose of the Open House The Town of Smiths Falls has initiated the Beckwith Street Redevelopment Plan that includes the preparation of a streetscape functional design for the renewal of Beckwith

More information

Brooklyn Boulevard (County Road 152) Reconstruction Project Phase I. OPEN HOUSE June 20, 2017

Brooklyn Boulevard (County Road 152) Reconstruction Project Phase I. OPEN HOUSE June 20, 2017 Brooklyn Boulevard (County Road 152) Reconstruction Project Phase I OPEN HOUSE June 20, 2017 Brooklyn Boulevard (County Road 152) Phase I Project Partners Project Lead Other Project Partners include Brooklyn

More information

NEWMARKET UPHAM S CORNER

NEWMARKET UPHAM S CORNER SOUTH STATION Planning Initiative NEWMARKET UPHAM S CORNER COLUMBIA ROAD (P) FOUR CORNERS/GENEVA Working Advisory Group (WAG) Meeting #5 TALBOT AVENUE MORTON STREET BLUE HILL AVE/CUMMINS HWY (P) RIVER

More information

Public Works Committee Meeting Richard E. Mastrangelo Council Chamber November 20, 2017

Public Works Committee Meeting Richard E. Mastrangelo Council Chamber November 20, 2017 Public Works Committee Meeting Richard E. Mastrangelo Council Chamber November 20, 2017 Purpose of Meeting Why are we here? Project Recap/Updates Project Limits/Segments Road Diet Concept Lessons Learned

More information

CITY OF OTTAWA ROADWAY MODIFICATION APPROVAL UNDER DELEGATED AUTHORITY

CITY OF OTTAWA ROADWAY MODIFICATION APPROVAL UNDER DELEGATED AUTHORITY RMA-2015-ATM-038 CITY OF OTTAWA ROADWAY MODIFICATION APPROVAL UNDER DELEGATED AUTHORITY DATE: April 22, 2015 SUBJECT Approval of Roadway Modifications Recommended through an Area Traffic Management Study

More information

Bay to Bay Boulevard Complete Streets Project

Bay to Bay Boulevard Complete Streets Project Bay to Bay Boulevard Complete Streets Project Dale Mabry Highway to Bayshore Boulevard February 08, 2018 Photo Source: Tampa Bay Times Alessandra Da Pra Meeting Format Introduction Resurfacing Information

More information

CONNECTIVITY PLAN. Adopted December 5, 2017 City of Virginia Beach

CONNECTIVITY PLAN. Adopted December 5, 2017 City of Virginia Beach CONNECTIVITY PLAN Adopted December 5, 2017 City of Virginia Beach CONTENTS 1.0 Background & Purpose... 2 2.0 Existing Inventory & Analysis... 3 ViBe District Existing Walking Conditions... 4 3.0 ViBe District

More information

Lincoln Highway Streetscape Plan Concept Plan

Lincoln Highway Streetscape Plan Concept Plan Lincoln Highway Streetscape Plan Concept Plan November 14, 2014 Introduction This report provides a summary of conceptual transportation, land use, and design recommendations in the Lincoln Highway Streetscape

More information

Transportation Planning Division

Transportation Planning Division Transportation Planning Division Presentation Outline Study Tasks Recap of Previous Meetings Data Collected Focus Areas within Study Limits Design Principles Tool Box Recommended Concepts Schedule Moving

More information

A Guide to Great Streets: The Basics. September 25, 2009

A Guide to Great Streets: The Basics. September 25, 2009 A Guide to Great Streets: The Basics September 25, 2009 Streets are more than connectors, they are the city 2 Streets are the glue that hold a city together 3 Streets are the means in which a city is perceived

More information

C C C

C C C C-012-001 Thank you for your support for the creation of new public space and nonmotorized access between downtown and the waterfront through the Overlook Walk, the East-West Connections, and the Promenade.

More information

El Camino Real Specific Plan. TAC/CAC Meeting #2 Aug 1, 2018

El Camino Real Specific Plan. TAC/CAC Meeting #2 Aug 1, 2018 El Camino Real Specific Plan TAC/CAC Meeting #2 Aug 1, 2018 Land Use Alternatives Goals and Tradeoffs Parks & open space Housing Retail & services Civic spaces Parking Community gathering spaces 3 Alternatives

More information

Advancing Transportation Choices in Des Moines. MPO Environmental Roundtable January 9, 2018

Advancing Transportation Choices in Des Moines. MPO Environmental Roundtable January 9, 2018 Advancing Transportation Choices in Des Moines MPO Environmental Roundtable January 9, 2018 Presented by Jennifer McCoy, PE, PTOE City Traffic Engineer Agenda Des Moines Area Transportation Planning Connect

More information

Princeton Avenue and Spruce Street Transportation and Site Access Enhancements Project

Princeton Avenue and Spruce Street Transportation and Site Access Enhancements Project Princeton Avenue and Spruce Street Transportation and Site Access Enhancements Project Mercer County Planning Division AECOM Transportation (formerly DMJM Harris) January 29, 2009 Agenda Project Status

More information

HARRISON STREET/OAKLAND AVENUE COMMUNITY TRANSPORTATION PLAN

HARRISON STREET/OAKLAND AVENUE COMMUNITY TRANSPORTATION PLAN HARRISON STREET/OAKLAND AVENUE Community Workshop #4: Draft Plan Review December 3, 2009 D E S I G N, C O M M U N I T Y & E N V I R O N M E N T INTRODUCTIONS Key Project Staff: Alisa Shen, Project Manager,

More information

Fulton Market Streetscape

Fulton Market Streetscape Fulton Market Streetscape Ogden Avenue to Halsted Street Public Meeting Recommended Improvements December 10th, 2014 Meeting Purpose and Goals Present Existing Conditions Community Input and Charrette

More information

Front and Myrtle Improvement Project

Front and Myrtle Improvement Project Front and Myrtle Improvement Project MAKING BOISE THE MOST LIVABLE CITY IN THE COUNTRY DOWNTOWN: Our unique and vibrant urban neighborhood GUIDING PRINCIPLES: Innovation Celebration Transportation Downtown

More information

Project Goal and Description. Why Broadway? Broadway SFMTA.COM/BROADWAY. The goal of the Broadway Safety Improvement

Project Goal and Description. Why Broadway? Broadway SFMTA.COM/BROADWAY. The goal of the Broadway Safety Improvement PROJECT OVERVIEW Project Goal and Description The goal of the Broadway Safety Improvement d St Van Ness Ave Project is to improve safety and comfort for all who Franklin St Hyde St Octavia St Gough St

More information

I-290 Phase I Study Area OAK PARK AVE AUSTIN BLVD. Reconstruction Area (9 miles) Oak Park RIDGELAND AVE CENTRAL AVE HARLEM AVE. Cicero.

I-290 Phase I Study Area OAK PARK AVE AUSTIN BLVD. Reconstruction Area (9 miles) Oak Park RIDGELAND AVE CENTRAL AVE HARLEM AVE. Cicero. RIDGELAND AVE OAK PARK AVE AUSTIN BLVD UP-RR BRC-RR ASHLAND AVE Study Area Map I-290 Phase I Study Area 294 UP RR Metra UP-W Illinois Prairie Path 38 Berkeley WOLF RD Hillside MANNHEIM RD Bellwood 290

More information

HIGHBURY AVENUE/HAMILTON ROAD INTERSECTION IMPROVEMENTS PUBLIC INFORMATION CENTRE 1 MAY 14, 2015

HIGHBURY AVENUE/HAMILTON ROAD INTERSECTION IMPROVEMENTS PUBLIC INFORMATION CENTRE 1 MAY 14, 2015 HIGHBURY AVENUE/HAMILTON ROAD INTERSECTION IMPROVEMENTS Municipal Class Environmental Assessment PUBLIC INFORMATION CENTRE 1 MAY 14, 2015 ACCESSIBILITY Under the Accessibility Standards 2015 for Customer

More information

Las Tunas Downtown Revitalization City Council Study Session. December 1, :00 p.m. Live Oak Park Community Center

Las Tunas Downtown Revitalization City Council Study Session. December 1, :00 p.m. Live Oak Park Community Center Las Tunas Downtown Revitalization City Council Study Session December 1, 2015 7:00 p.m. Live Oak Park Community Center AGENDA 2 Provide downtown context. Confirm project goals. Analyze three design concepts.

More information

2.0 LANE WIDTHS GUIDELINE

2.0 LANE WIDTHS GUIDELINE 2.0 LANE WIDTHS GUIDELINE Road Engineering Design Guidelines Version 2.0.1 May 2018 City of Toronto, Transportation Services City of Toronto Page 0 Background In early 2014, Transportation Services initiated

More information

Figure 1: Vicinity Map of the Study Area

Figure 1: Vicinity Map of the Study Area ARIZONA TEXAS NEW MEXICO OKLAHOMA May 5, 2016 Mr. Anthony Beach, P.E. BSP Engineers 4800 Lakewood Drive, Suite 4 Waco, Texas 76710 Re: Intersection and Access Analysis along Business 190 in Copperas Cove

More information

Walk Friendly Communities Engineering Strategies. Carl Sundstrom Walk Friendly Communities Workshop Grandview, MO June 2015

Walk Friendly Communities Engineering Strategies. Carl Sundstrom Walk Friendly Communities Workshop Grandview, MO June 2015 Walk Friendly Communities Carl Sundstrom Walk Friendly Communities Workshop Grandview, MO June 2015 Module Overview Topics Background and purpose Sidewalks Crossings Traffic calming www.pedbikeimages.org

More information

Columbia Pike Implementation Team (CPIT) Meeting

Columbia Pike Implementation Team (CPIT) Meeting Columbia Pike Implementation Team (CPIT) Meeting November 30, 2010 Agenda Introductions / Purpose of Meeting Review of project goals Multimodal project: 10% street design between the curbs Discussion Multimodal

More information

Tonight is for you. Learn everything you can. Share all your ideas.

Tonight is for you. Learn everything you can. Share all your ideas. Strathcona Neighbourhood Renewal Draft Concept Design Tonight is for you. Learn everything you can. Share all your ideas. What is Neighbourhood Renewal? Creating a design with you for your neighbourhood.

More information

Design Guidelines. Overview. Design Vision for Yellow Brick Road

Design Guidelines. Overview. Design Vision for Yellow Brick Road Design Guidelines Overview This section presents the design vision for the Yellow Brick Road network. The Yellow Brick Road is envisioned to be an interconnected network of safe and secure roadways where

More information

RZC Appendix 8A Marymoor Subarea Street Requirements

RZC Appendix 8A Marymoor Subarea Street Requirements RZC Appendix 8A Marymoor Subarea Street Requirements For additional design details for Marymoor Subarea infrastructure, refer to the 2017 Marymoor Subarea Infrastructure Planning Report. STREET REQUIREMENTS

More information