OTC Floatover Deck Installation for Spars J. V. Maher, I. Prislin, J. C. Chao, J. E. Halkyard, L. D. Finn, CSO Aker Engineering, Inc.

Size: px
Start display at page:

Download "OTC Floatover Deck Installation for Spars J. V. Maher, I. Prislin, J. C. Chao, J. E. Halkyard, L. D. Finn, CSO Aker Engineering, Inc."

Transcription

1 OTC Floatover Deck Installation for Spars J. V. Maher, I. Prislin, J. C. Chao, J. E. Halkyard, L. D. Finn, CSO Aker Engineering, Inc. Copyright 2001, Offshore Technology Conference This paper was prepared for presentation at the 2001 Offshore Technology Conference held in Houston, Texas, 30 April 3 May This paper was selected for presentation by the OTC Program Committee following review of information contained in an abstract submitted by the author(s). Contents of the paper, as presented, have not been reviewed by the Offshore Technology Conference and are subject to correction by the author(s). The material, as presented, does not necessarily reflect any position of the Offshore Technology Conference or its officers. Electronic reproduction, distribution, or storage of any part of this paper for commercial purposes without the written consent of the Offshore Technology Conference is prohibited. Permission to reproduce in print is restricted to an abstract of not more than 300 words; illustrations may not be copied. The abstract must contain conspicuous acknowledgment of where and by whom the paper was presented. Abstract The spar floating production system offers an attractive alternative for drilling, producing and storing oil in deep water depths. Of the spars installed to date, conventional derrick barge methods have been used to install the top deck in multiple lifts and to perform hook up and commissioning operations offshore. Development and engineering have been carried out in developing economical alternatives to install top decks. One such scheme is the float-over deck installation onto a pre-installed spar hull with the deck supported by two barges. Using this method, the top deck will be hooked up and commissioned onshore and installed in one piece to reduce offshore operation time and to avoid the use of a large, expensive derrick barge. The development of such a floatover method is presented in the present paper. Introduction Several spar-based drilling and production platforms have been installed in the deep water of the Gulf of Mexico (GOM) [1,2,3]; a number of other spars are currently being fabricated and designed for the GOM and other deep water regions (Fig 1). The deep draft, intrinsic stability, and low motions of the spar make it an attractive option in many deep water regions throughout the world. All the spars that have been installed to date have utilized dynamically positioned large crane vessels to install the top decks in single or multiple lifts followed by hook up and commissioning at the deepwater site. Day rates of such crane vessels with large lift capacity are high and these vessels are not available at all offshore locations. Furthermore, hook up and commissioning of deck facilities offshore are inherently expensive. CSO Aker Engineering, Inc. (AEI) has been conducting research and engineering in developing alternative methods to install top decks onto a spar hull without using a large expansive crane vessel. One of the methods developed is a self- floating deck and has been described in an early presentation [4]. In this method, all the required drilling and/or production facilities are installed on a barge and hooked up and commissioned inshore; the barge is then towed to the spar site to mate with the pre-installed spar hull (Fig 2). The second method being developed is the float-over deck in which the integrated deck is supported by two small-waterplane-area pontoon barges for mating with the spar hull (Fig 3). The advantage of this method is its reduced motions and higher operable seastates. This method was also presented in an early paper [5]. An alternate float-over deck method is to use, instead of two small-water-plane-area pontoon barges, two ships or barges to support the deck. Again, the top deck is fabricated in one piece with all facilities hooked up and commissioned onshore. The top deck is transported by two support barges to the spar site and positioned over the spar for mating with the spar hull. AEI has carried out theoretical studies and model tests for all the above schemes. In the present paper, the second floatover deck method using two ships or barges will be discussed. Specifically, this paper will discuss the seakeeping characteristics of the barges, the proposed mating operations, model tests and comparison of predictions with model test results. While the procedures have been developed for using either two ships or two barges. We will use "barges" in the following discussion. The float-over method is not new to the offshore industry. The method has been used successfully for mating decks in calm waters (e.g., GBS structures in Norway and Canada), and to a limited extent in open waters (e.g., fixed structures in Australia, Middle East, and West Africa) [6,7]. Floatover Deck Installation Procedures To provide a basis for the following discussion, the entire float-over procedure is given in this section. The base case procedure is assumed to start from the time the top deck fabrication and commissioning are complete (and is ready to be transported to the site) to the final mating operation of the deck with the spar hull. Analysis and design results for the base case procedure will be discussed in the following sections. While the float-over technology was developed for

2 2 J.V. MAHER, I. PRISLIN, J.C. CHAO, J.E. HALKYARD, L.D. FINN OTC use in a wide range of application conditions (e.g., Offshore West Africa, Offshore Brazil, and GOM), a GOM installation site is assumed in the following discussion. In addition, the deck is assumed to be loaded onto the support barges at the Aker Gulf Marine (AGM) yard. outside of Corpus Christi. Pre-Install Spar Hull: Upon completion of the spar hull and prior to towing the top deck to the site, the spar hull must be installed at the site and be prepared to receive the top deck (Fig 4). First, the mooring system is installed at the site, then the spar hull is towed to the location, upended, and connected to the pre-installed mooring system. Fixed ballast is then placed, followed by controlled flooding of several selected tanks to bring the spar hull to the desired freeboard. The spar will be at a shallow freeboard to allow the deck to be floated over. To ballast the spar hull, temporary pumps with power supplies will be placed on top of the spar hull or on a surface support vessel. The pumps will be connected to manifolds with control valves to direct the water to the appropriate tanks. Load Deck onto Support Barges: After the deck fabrication, hook-up and commissioning are complete, the deck is ready to be loaded onto the barges. One scheme to load the deck onto the support barges would be to skid the deck directly onto the two barges at the quayside (Fig 5). Next, the top deck is fastened to the barges, the barges are deballasted to the correct towing draft and is ready to be towed to the spar site. Tow Deck/Barges to Installation Site: Fig 6 shows that the deck and support barges are being towed out of the AGM yard and through the ship channel. Fig 7 illustrates the offshore tow of the deck. It is assumed that the final installation site is not far from the AGM yard and the deck can be towed safely in the catamaran configuration. If the final installation site is far from the deck loading yard a temporary mating site could be established at a deep water site not far from the deck loading yard. The deck can be mated at this temporary site and then the spar with its installed deck can be vertically towed to the final installation site. A temporary mating site not far from the loading yard will make the catamaran tow a shorter operation. This will reduce the tow risk as the weather window can be more accurately predicted for a short tow. Maneuver and Position Deck over Spar Hull: When the tow arrives in the field, the support vessel will hip up to one of the barges and together with the tow tugs will maneuver the deck towards the spar hull. As the deck approaches the spar, mooring lines will be connected between the spar hull and the barges to assist with maneuvering of the barges on each side of the spar hull. Fig 8 illustrates such a maneuvering and approach operation. Final positioning of the deck over the spar hull can be made with the assistance of soft lines connecting the spar hull to the barges and a fendering system between the spar hull and the barges. Fig 9 illustrates the positioning and docking of the deck/barge over the spar hull. For the majority of conventional float-over deck installations performed to date for fixed platforms, two basic schemes have been used to position and secure the deck barges. One scheme is to have a clearance between the deck barge and jacket fendering and have a system of mooring lines between the barge and jacket to hold the barge in position. The other approach is to have minimal clearance between the deck and jacket so the barge cannot move laterally. For the spar deck float-over using two barges, the minimal clearance approach is considered to be the most suitable as the barge position can be controlled at all phases of the mating operation. Mate Deck with Spar Hull: Two critical phases of the mating operation in a seaway are: (1) initial contact between the spar hull and the deck, and (2) separation of the deck from the barges. It is during these phases that wave induced motions can induce large loads to the structure. The float-over operation will be controlled from the surface support vessel. After alignment is made between the spar hull and the top deck, mating operation can commence. Mating operation includes lifting of the spar and at the same time ballasting the barge and eventually transfer the deck from the barges to the spar hull. An air system has been described by Chao, et al [5] to provide buoyancy and lift to the spar hull. Deballast the spar and ballast the barge by a large pump system can also be used depending upon the amount of ballast needs to be moved and the available weather window for the mating operation. A mechanical or hydraulic system that will allow a quick separation of the deck from the barges can be incorporated into the deck supports on the barges. After the barges are separated from the deck, they will be safely towed out from underneath the deck. Fig 10 shows four sketches illustrating the mating operation to transfer the deck from the support barges to the spar hull. To ensure and maintain alignment between the deck and the spar hull during the mating operation, the deck will be fitted with stabbing cones that will go down into the hull support columns. Alignment pins inserted into the stabbing cones will ensure that the deck remains properly aligned before and during the weight transfer. Conventional passive elastomeric shock cells, used on most deck float-overs onto jackets, will be incorporated into the stabbing guide system to accommodate any possible impact loads at the start of load transfer. Fig 11 shows one such possible mating units. Floatover System/Components Analysis and Design AEI has conducted an extensive R&D program including analysis tool development and model tests for floatover operations and equipment designs. Technology development, and analyses and designs of major floatover deck components/systems are discussed in this section. Model tests will be discussed in the next section. Technology/Software Development: AEI has modified ABAQUS and MLTSIM to simulate floatover operations. MLTSIM [8] is a time-domain hydrodynamics computer

3 OTC FLOATOVER DECK INSTALLATION FOR SPARS 3 program capable of computing motions and loads on multiple floating bodies. ABAQUS is used to model the structures of the floating bodies. The connections between any given two bodies (e.g., between a spar and a deck) are simulated as nonlinear springs. Hydrodynamic inputs to the program are specified by a set of user-defined coefficients for added mass, linear damping, and quadratic viscous drag. Added mass, potential damping, slow varying drift forces, and diffraction forces are computed using programs such as WAMIT, HYDRO3, or similar. Simulating reactions between deck and spar (or barges) using stiff connectors result in a stiff system of differential equations. This requires a special solver to obtain solutions for these differential equations. Top Deck Design: One design issue for the floatover operation is to determine the deck structure required to withstand the loads induced by the floatover operation. Several structure designs have been carried out for floatover decks to determine the increase in structure weight. The structure weight for floatover decks are compared with conventional decks. Floatover decks showed a modest increase around 10% in steel weight. The required additional strengthening involves mostly increased wall thickness of the diagonal bracings. The reasons for this modest increase are: (1) the original structure is designed for an inplace operational load (higher) and 100 year event, (2) the floatover condition (while with a different support configuration) is designed for a lower dry installation weight and a lower design environment (installation seastate), (3) the design stress levels for installation operation (short duration) can be higher. Deck Support Loads on Barges during Transport: Deck supports on the barges need to be designed to withstand the transportation loads. Sea fastening could be required when the dynamic loads become large. A number of analyses and designs have been made to determine the loads induced during transport of the dock to the mating site. Fig 12 shows one support arrangement on the barges used in the analysis. Fig 13 shows the predicted load time history at the most heavily loaded support. This calculation was made for a seastate of 16 ft and for a deck weight of 25,000 st, with a dimension of 230 ft by 210 ft supported by two barges of ft x 55.8 ft x 52 ft each. This analysis assumes four supports on each barge. It can be seen that the static load on each support is 6,300 kips; the maximum dynamic load is 3,800 kips indicating that the supports are always under compression. These support loads will be reduced when more supports are used. Floatover Operation: Four-body model (two barges, spar and the deck) was used to simulate the floatover operation. Fig 14 shows the support arrangement for one of the mating simulation; the deck is initially supported on four supports on each barge and the deck weight is eventually loaded onto the spar hull with eight supports. Fig 15 shows the simulation of the entire mating operation from the point when the spar is started below the deck (~ 5 ft), come into contact with deck and finally the deck separates from the barges. It can be seen that the wave induced motion of the spar is very small at the beginning (when the spar is at a deep draft, i.e., low freeboard) while the motions of the deck/barge are relatively large. At the point of spar making contact with the deck; some motions are being imparted to the spar. Afterwards, the deck/barge and the spar move essentially as a single body when ballasting of the barges and deballasting of the spar hull continues. When the top of the spar reaches to around 25 ft from the waterline the deck starts to separate from the barges; finally the deck is completely separated from the barges when the spar is at about 28 ft. It can be seen that the motions of the barges become large after the deck weight is removed and these barges need to be removed from the site quickly. This simulation was made for a seastate of 6.6 ft. The deck and barge dimensions used in the simulation are as discussed above. These results are used to determine the loads for designing the contact pads between the deck and the spar hull supports and between the deck and barge supports. These results are also used to define the seastates that mating operation can be performed. Tables 1 and 2 present additional results from the simulation. Table 1 gives the spar and deck relative motions during mating and Table 2 presents the maximum dynamic loads at the spar support at the time of making contact and the loads at the deck supports at the time when the barges separate from the deck. It can be seen that the loads at the barge supports are larger as the barge motions are higher. These dynamic loads are, however, not large; elastomeric pads (or shock cells) can be designed easily to withstand these loads. The loads will be reduced if the number of supports are increased (e.g., eight). Model Test AEI has conducted a number of model test programs for various floatover concepts including the self-floating deck [9], the small-water-plane-area pontoon barges [10] and the flatbottom barges [11]. In the present paper, only the model test with flat-bottom barges are discussed and are used to compare with theoretical calculations discussed in the above section. The model tests were performed at the Offshore Model Basis in Escondido, California. Model Scale was 1: The objectives of the model test program are: (1) to validate and calibrate analytical tools used for the analysis of large deck catamaran towing and floatover with a spar platform, (2) to provide data needed for design of equipment required for these operations, and (3) to assist with evaluation of the various phases of transportation and mating operations. Fig 16 is a photo of the model test showing the deck and support barges over the spar hull. The deck modeled is 35,000 st with a dimension of 270 ft by 250 ft. The barges modeled are 485 ft x 105 ft x 30 ft each. The barge weight is 7,000 st each. Two spacer structures are employed on top of the barges to support the deck to provide the required height for floatover. The spar modeled is 158 ft in diameter. Measurements included motions of the various bodies and loads at various contact points. Tests included

4 4 J.V. MAHER, I. PRISLIN, J.C. CHAO, J.E. HALKYARD, L.D. FINN OTC seakeeping tests, catamaran tow tests, floatover and mating tests in various wave and current conditions. Comparison of Predictions and Model Test Results Fig 17 shows part of a load measurement made during one of the mating tests. The load time histories are comparable to those discussed above. The test was made for a 6.6 ft quartering seas. Fig 18 compares the predicted and measured load time histories. It can be seen that the predictions match well with the measured values, both in amplitudes and periods. The average (static) simulated loads differ slightly from the measured loads because of slightly different initial conditions set in the numerical model. This, however, does not significantly change the results for the dynamic part of the load. Table 3 presents additional comparison between measured and predicted loads. Fig 19 shows a comparison of measured and predicted load spectra. The location of the main spectral peaks and magnitudes of the spectral peaks agree reasonably well between measured and predicted loads. Economics This study demonstrates the technical feasibility of using barges for float-over deck installation. Costs to modify existing barges for floatover operation were found to be lower than employ a large crane vessel. The exact savings depending upon the location of the installation site (WA, GOM, or Brazil) and deck weight. The economics of the float-over method will become even more attractive when multiple use of the barges becomes possible. Our analysis of the spar projects in the GOM, Brazil and West Africa certainly support this potential. References 1. R. D. Vardeman, S. Richardson and C. R. McCandless, Neptune project: overview and project management, Offshore Technology Conference, Houston (1997). 2. M. De Luca, Seventy US gulf deepwater fields awaiting development; 26 in production, Offshore, (September, 1998). 3. G. Taylor, Genesis spar assembled, positioned offshore, Offshore, (November, 1998). 4. P. N. Stanton, J. L. LeJune, J. C. Chao, and H. G. Kumpis, Deep water drill spar, Offshore West Africa '99 Conference and Exhibition, Abidjan, Cote D'Ivoire, (March, 1999). 5. J. C.. Chao, J. E. Halkyard, J. A. Hinrichs, B. N. Johnson, M. R. Zeringer, H. M. Thompson, G. N. Beitch, Floatover Decks for the Spar Floating Production System, Deep and Ultra-Deep Water Offshore Technology Conference, (March, 1999). 6. J. P. Labbe, V. Allegre, J. Volker and F. Agdern, Ekpe gas compression project-float over deck installation, Offshore Technology Conference, Houston (May 1998). 7. J. H. Sigrist, P. Athomas and J. C. Naudin, Experience in float over integrated deck - flexibility of the concept, Offshore Technology Conference, Houston (May, 1998). 8 Y. S. Hong, J. R. Pauling, A procedure for the computation of wave- and motion-induced forces on three-dimensional bodies at zero forward speed, A report to the American Bureau of Shipping (1979). 9 Universal Spar, Self-Floating Deck Model Test, Deep Oil Technology, Inc. (December, 1997). 10 Float on Deck Model Test, Deep Oil Technology, Inc. (September, 1996). 11 Float Over Model Test, Aker Maritime, Inc., (November, 2000). Hs (ft) TABLE 1 SPAR / DECK RELATIVE MOTIONS Max Vertical Max Spar Support Motion of Deck Col Contact Pt (ft) Motion (ft) Max Relative Motion (ft) The max motions are based on 30 min duration TABLE 2 MAXIMUM DYNAMIC LOADS DURING DECK TRANSFER Hs (ft) Spar Initiates Contact (kips) Barge Separates from Deck (kips) ,084 3,000 TABLE 3 COMPARISON OF MEASURED AND PREDICTED FORCES Mean (kips) Min (kips) Max (kips) RMS (kips) Tp (sec) Td (sec) Spar Portside Barge Measured Predicted Measured Predicted 15,780 11,420 27,690 29,310 18,330 13,420 29,570 32,300 12,890 9,166 25,600 27,

5 OTC FLOATOVER DECK INSTALLATION FOR SPARS 5 Fig 1 Classic Spar Fig 2 Truss Spar 40' MWL 36' 46' 50' SPAR Fig 3 Self-Floating Deck Fig 4 Small-Water-Plane Pontoon Barges PRE-INSTALL MOORING SYSTEM AT SITE TOW SPAR HULL TO SITE UPEND SPAR HULL CONNECT MOORING SYSTEM TO SPAR HULL HOOK UP AIR SUPPLY AND BALLAST SUPPLY INSTALL FIXED BALLAST PRESSURE UP SKIRT TANK ADJUST BALLAST TO OBTAIN START BALLASTING CORRECT FREEBOARD Fig 5 Pre-Install Spar Hull at Site

6 6 J.V. MAHER, I. PRISLIN, J.C. CHAO, J.E. HALKYARD, L.D. FINN Fig 6 Skid Deck onto Support Barges Fig 8 Deck./Barge Offshore Tow Fig 10 Maneuver Deck/Barge over Spar Hull Fig 7 Tow Deck/Barge out of AGM Yard Fig 9 Deck/Barge Approaches Spar Hull Fig 12 Mating Unit (Shock Cell) OTC 12971

7 OTC FLOATOVER DECK INSTALLATION FOR SPARS 7 FLOAT DECK OVER BALLASTED SPAR HULL DEBALLAST THE SPAR 3 FEET SHOCK CELL COMPRESSED - 10% OF LOAD TRANSFERRED) 5' 12' 9' 34' 22' UPPER 24' UPPER 29' 30' 10' FREEBOARD LOWER 20' FREEBOARD LOWER LC SPAR CL LC SPAR CL (a) Deck/Barge Floatover Spar & Aligned (b) Contact between Spar and Deck Made DEBALLAST THE SPAR RAPIDLY TO TRANSFER REMAINING 10% OF LOAD AND LOWER SUPPORTS TO CLEAR S BY 5 FEET DEBALLAST THE SPAR TO THE OPERATING FREEBOARD OF 35 FEET - LOAD TRANSFER COMPLETE PULL AWAY FROM SPAR PULL AWAY FROM SPAR 24' UPPER LOWER UPPER LOWER LC SPAR CL LC CL (c) Deck Separated from Barges (d) Tow Barges from Site Fig 11 Deck Mating Operation MLTSIM Model for Catamaran Tow Configuration 1 0E+00-1E+06-2E+06-3E+06 1 force y -4E+06-5E+06-6E+06-7E time (s) Fig 13 Deck Supports on Barges Fig 14 Predicted Support Load Time History

8 8 J.V. MAHER, I. PRISLIN, J.C. CHAO, J.E. HALKYARD, L.D. FINN OTC ABASIM Model for Mating Operation Configuration 1 40 Spar & Deck/Barge Mating Spar & Deck Displacement (ft) Time (sec) Fig 15 Spar & Barges Supports Fig 16 Mating Operation Simulation Float Over: Dynamic Deck Mating With the Spar Piggyback Configuration (Model Test; Hs=6.6 ft, Tp=7 sec; quartering sea) Deck Load Distribution 100% 90% 80% 70% 60% 50% 40% 30% 20% 10% Portside barge Starboard barge Spar 0% time (sec) Fig 17 Model Test Fig 18 Measurements During Mating Test 50% Numerical Simulation: Hs=6.6 ft Tp=7 s (GOM) Vertical Load (% of Deck Weight) 45% 40% 35% 30% 25% 20% 15% 10% 5% Spar Portside barge Starboard barge 0% time (s) 50% Model Test: Hs=6.6 ft; Tp=7 s (GOM) Dynamic1 - after mating Vertical Load (% of Deck Weight) 45% 40% 35% 30% 25% 20% 15% 10% 5% Spar Portside barge Starboard barge 0% time (s) Fig 19 Predicted & Measured Load Time History During Mating Test

9 OTC FLOATOVER DECK INSTALLATION FOR SPARS 9 s par Spectrum (sim ulation) PSB Spectrum (simulated) 3.50E E+11 PSD (unit2) ^2/sec 3.00E E E E E E E+ 00 PSD (unit2) ^2/sec 2.50E E E E E E Period (s) Period (s) Ports ide barge Spectrum Spar Spe ctrum (Mode l test) (measured) 3.50E E+11 PSD (unit2) ^2/sec 3.00E E E E E E E+ 00 PSD (unit2) ^2/sec 2.50E E E E E E Period (s) Period (s) Fig 20 Comparison of Predicted & Measured Force Spectra

10 本文献由 学霸图书馆 - 文献云下载 收集自网络, 仅供学习交流使用 学霸图书馆 ( 是一个 整合众多图书馆数据库资源, 提供一站式文献检索和下载服务 的 24 小时在线不限 IP 图书馆 图书馆致力于便利 促进学习与科研, 提供最强文献下载服务 图书馆导航 : 图书馆首页文献云下载图书馆入口外文数据库大全疑难文献辅助工具

Development of Self-Installing Deepwater Spar. Ashit Jadav February 2017

Development of Self-Installing Deepwater Spar. Ashit Jadav February 2017 Development of Self-Installing Deepwater Spar Ashit Jadav February 2017 Contents Introduction & Background ACE Spar breakdown Installation Sequence Main particulars, Hull design and Weight control Stability

More information

Dynamic Small Animal Lung Imaging Via a Postacquisition Respiratory Gating Technique using Micro-Cone Beam Computed Tomography 1

Dynamic Small Animal Lung Imaging Via a Postacquisition Respiratory Gating Technique using Micro-Cone Beam Computed Tomography 1 Original Investigations Dynamic Small Animal Lung Imaging Via a Postacquisition Respiratory Gating Technique using Micro-Cone Beam Computed Tomography 1 Jicun Hu, PhD, Steve T. Haworth, PhD, Robert C.

More information

To link to this article:

To link to this article: This article was downloaded by: [Tufts University] On: 03 December 2014, At: 12:19 Publisher: Routledge Informa Ltd Registered in England and Wales Registered Number: 1072954 Registered office: Mortimer

More information

Searching efficient plans for emergency rescue through simulation: the case of a metro fire

Searching efficient plans for emergency rescue through simulation: the case of a metro fire Cogn Tech Work (2004) 6: 117 126 DOI 10.1007/s10111-004-0150-6 ORIGINAL ARTICLE Nikos Zarboutis Æ Nicolas Marmaras Searching efficient plans for emergency rescue through simulation: the case of a metro

More information

Repeatability of Kinematic, Kinetic, and Electromyographic Data in Normal Adult Gait

Repeatability of Kinematic, Kinetic, and Electromyographic Data in Normal Adult Gait Journal of Orthopaedic Research 7:849-860 Raven Press, Ltd., New York 0 1989 Orthopaedic Research Society Repeatability of Kinematic, Kinetic, and Electromyographic Data in Normal Adult Gait M. P. Kadaba,

More information

Bioequivalence (BE) is defined as the absence of a

Bioequivalence (BE) is defined as the absence of a Operating Characteristics of a Partial-block Randomized Crossover Bioequivalence Study for Dutasteride, a Drug with a Long Half-life: Investigation through Simulation and Comparison with Final Results

More information

Floatover Installation Method

Floatover Installation Method Floatover Installation Method Basic Floatover Manoeuvre Barge Positioning In-between Jacket Top Structure Float through Section (front view) Floatover Support Frame Floatover Section Topsides Control Tug

More information

HISTORIQUE ET EVOLUTION DES PLATES-FORMES AVEC TETES DE PUITS EN SURFACE (SPAR? ) LES TENDANCES POUR LE FUTUR

HISTORIQUE ET EVOLUTION DES PLATES-FORMES AVEC TETES DE PUITS EN SURFACE (SPAR? ) LES TENDANCES POUR LE FUTUR ATMA 2006 HISTORIQUE ET EVOLUTION DES PLATES-FORMES AVEC TETES DE PUITS EN SURFACE (SPAR? ) LES TENDANCES POUR LE FUTUR Partie 1 Pierre-Armand THOMAS TECHNIP Division Offshore - Paris (France) Diapositives

More information

Deepwater Floating Production Systems An Overview

Deepwater Floating Production Systems An Overview Deepwater Floating Production Systems An Overview Introduction In addition to the mono hull, three floating structure designs Tension leg Platform (TLP), Semisubmersible (Semi), and Truss Spar have been

More information

Innovative and Robust Design. With Full Extension of Offshore Engineering and Design Experiences.

Innovative and Robust Design. With Full Extension of Offshore Engineering and Design Experiences. Innovative and Robust Design by VL Offshore With Full Extension of Offshore Engineering and Design Experiences www.vloffshore.com Y Wind Semi Designed by VL Offshore The Y Wind Semi platform (foundation)

More information

Floatover Installation Method

Floatover Installation Method Floatover Installation Method Basic Floatover Manoeuvre Barge Positioning In-between Jacket Top Structure Float through Section (front view) Floatover Support Frame Floatover Section Topsides Control Tug

More information

Offshore Oil and Gas Platforms for Deep Waters

Offshore Oil and Gas Platforms for Deep Waters Offshore Oil and Gas Platforms for Deep Waters Atilla Incecik Department of Naval Architecture, Ocean and Marine Engineering University of Strathclyde, Glasgow, UK (atilla.incecik@strath.ac.uk) Summary

More information

Minimal Structures for Marginal Nova Scotia Developments

Minimal Structures for Marginal Nova Scotia Developments Minimal Structures for Marginal Nova Scotia Developments May 12, 2009 Cameron Dunn Martec is a member of the Lloyd s Register Group 1 2 Minimal Structures Project NSDOE working to make the Nova Scotia

More information

RIGID RISERS FOR TANKER FPSOs

RIGID RISERS FOR TANKER FPSOs RIGID RISERS FOR TANKER FPSOs Stephen A. Hatton 2H Offshore Engineering Ltd. SUMMARY Recent development work on the subject of dynamic rigid (steel pipe) risers demonstrates that their scope of application

More information

LOAD AND RESPONSE OFA SWATH SHIP IN WA VES

LOAD AND RESPONSE OFA SWATH SHIP IN WA VES EDWARD T. RELLY, YUNG S. SHN, PH.D. & ERNST H. KOTTE A PREDCTON OF STRUCTURAL LOAD AND RESPONSE OFA SWATH SHP N WA VES THE AUTHORS Edward T. Reilly is an assistant vice president at the American Bureau

More information

A Novel Platform for Drilling in Harsh High-Latitude Environments.

A Novel Platform for Drilling in Harsh High-Latitude Environments. AADE-7-NTCE-73 A Novel Platform for Drilling in Harsh High-Latitude Environments. Brian Roberts, Technip; Chunqun Ji, Technip; Jim O Sullivan, Technip and Terje Eilertsen, Technip. Copyright 27, AADE This

More information

WIND TURBINE SHUTTLE HUISMAN PRODUCT BROCHURE

WIND TURBINE SHUTTLE HUISMAN PRODUCT BROCHURE WIND TURBINE SHUTTLE HUISMAN PRODUCT BROCHURE WIND TURBINE HUTTLE TABLE OF CONTENTS 01 DESCRIPTION 03 1.1 Vessel General 03 1. Purpose of the Vessel 0 1.3 High Workability 0 1. Installation Scenarios 05

More information

STRIDE PROJECT Steel Risers in Deepwater Environments Achievements

STRIDE PROJECT Steel Risers in Deepwater Environments Achievements STRIDE PROJECT Steel Risers in Deepwater Environments Achievements 1999-21 Neil Willis Principal Engineer 2H Offshore Engineering 6 th Annual Deepwater Technologies and Developments Conference 21 The presentation

More information

Alternative Installation Methods for. Offshore Wind Substations

Alternative Installation Methods for. Offshore Wind Substations Department of Mechanical and Aerospace Engineering Alternative Installation Methods for Offshore Wind Substations Author: Justo Aguiar Quintana Supervisor: Mr Cameron Johnstone A thesis submitted in partial

More information

TLP Minimum tendon tension design and tendon down-stroke investigation

TLP Minimum tendon tension design and tendon down-stroke investigation Published by International Association of Ocean Engineers Journal of Offshore Engineering and Technology Available online at www.iaoejoet.org TLP Minimum tendon tension design and tendon down-stroke investigation

More information

Edit this text for your title

Edit this text for your title Edit this text for your title MEK 4450 Marine Operations Edit this text for your sub-title Presenter name, location, date etc. Kværner ASA / DNV, Fall 2013 Lesson 2/3 Lift phases Load out Transportation

More information

OTC Kikeh Development: Spar Topside Floatover Installation D. Edelson, M. Luo, and J. Halkyard, Technip; D. Smiley, Murphy Sabah Oil Co., Ltd.

OTC Kikeh Development: Spar Topside Floatover Installation D. Edelson, M. Luo, and J. Halkyard, Technip; D. Smiley, Murphy Sabah Oil Co., Ltd. OTC 19639 Kikeh Development: Spar Topside Floatover Installation D. Edelson, M. Luo, and J. Halkyard, Technip; D. Smiley, Murphy Sabah Oil Co., Ltd. Copyright 2008, Offshore Technology Conference This

More information

Numerical modelling of disconnectable turret mooring systems

Numerical modelling of disconnectable turret mooring systems Numerical modelling of disconnectable turret mooring systems A. Duggal, S. Ryu & O. De Andrade Research & Development Department, SOFEC Inc., USA. Abstract Floating, Production, Storage, and Offloading

More information

Pile Gripper Systems

Pile Gripper Systems Pile Gripper Systems Accurate positioning and restraint of offshore construction piles + + Accurate handling of piles up to 8.0m in diameter + + Pile positioning and adjustment within large envelopes +

More information

Trine Risøy, Bergen,

Trine Risøy, Bergen, part of Aker The Installation of Subsea Structures without Offshore Crane Vessel Trine Risøy, Bergen, 04.06.2008 2008 Aker Solutions AKER MARINE CONTRACTORS (AMC) 35 years experience worldwide: Subsea

More information

Fully Submersible Heavy Lift Vessel

Fully Submersible Heavy Lift Vessel Fully Submersible Heavy Lift Vessel Arnbjorn Joensen Oil and Gas Authority (OGA) (15th February 2016) CONTENT Leadon structures demobilisation Competitiveness (case studies) Decommissioning options Installation

More information

FAST SUPPLY INTERVENTION and CREW TRANSFER VESSEL M P 6 2 5

FAST SUPPLY INTERVENTION and CREW TRANSFER VESSEL M P 6 2 5 FAST SUPPLY INTERVENTION and CREW TRANSFER VESSEL M P 6 2 5 MAIN PARTICULARS LENGTH OVER ALL 60.68 m LENGTH WATER LINE 59.35 m BREADTH MAX 20.80 m DRAUGHT MAX 3.10 m DEPTH 6.70 m MAX SPEED 37.0 knots @

More information

EXPERIMENTAL INVESTIGATIONS OF BARGE FLOATER WITH MOONPOOL FOR 5 MW WIND TURBINE

EXPERIMENTAL INVESTIGATIONS OF BARGE FLOATER WITH MOONPOOL FOR 5 MW WIND TURBINE EXPERIMENTAL INVESTIGATIONS OF BARGE FLOATER WITH MOONPOOL FOR 5 MW WIND TURBINE 1 MR. G.VIJAYA KUMAR, 2 DR. R. PANNEER SELVAM 1 M.S. Research Scholar, Department of Ocean Engineering, IIT Madras, Chennai,

More information

Application of CFD for Improved Vertical Column Induced Gas Flotation (IGF) System Development

Application of CFD for Improved Vertical Column Induced Gas Flotation (IGF) System Development Application of CFD for Improved Vertical Column Induced Gas Flotation (IGF) System Development Chang-Ming Lee and Ted Frankiewicz NATCO Group, Inc., 2950 North Loop West, Suite 750, Houston, TX 77092 Prepared

More information

ITTC - Recommended Procedures and Guidelines

ITTC - Recommended Procedures and Guidelines 7.5 Page 1 of 5 Table of Contents 1. PURPOSE OF PROCEDURE... 2 2. DESCRIPTION OF PROCEDURE... 2 4. DOCUMENTATION... 4 5. REFERENCES... 4 3. PARAMETERS... 4 Updated by Approved Manoeuvring Committee of

More information

The Benefits Of Composite Materials In Deepwater Riser Applications. 26 th March 2015 Hassan Saleh Senior Engineer 2H Offshore Engineering Ltd

The Benefits Of Composite Materials In Deepwater Riser Applications. 26 th March 2015 Hassan Saleh Senior Engineer 2H Offshore Engineering Ltd The Benefits Of Composite Materials In Deepwater Riser Applications 26 th March 2015 Hassan Saleh Senior Engineer 2H Offshore Engineering Ltd Composite Benefits and Challenges Composite Materials offer

More information

Quantitative estimation of bubble size in PFBC. P. Cai, M. Schiavetti, G. De Michele, G.C. Grazzinia, M. Micciob>*

Quantitative estimation of bubble size in PFBC. P. Cai, M. Schiavetti, G. De Michele, G.C. Grazzinia, M. Micciob>* ELSEVIER Powder Technology 80 (1994) 99-109 POWOER TECHNOLOGY Quantitative estimation of bubble size in PFC P. Cai, M. Schiavetti, G. e Michele, G.C. Grazzinia, M. Micciob>* ENEL Xpsi. (Italian Electricity

More information

Proceedings of the ASME th International Conference on Ocean, Offshore and Arctic Engineering OMAE2011

Proceedings of the ASME th International Conference on Ocean, Offshore and Arctic Engineering OMAE2011 Proceedings of the ASME 2011 30th International Conference on Ocean, Offshore and Arctic Engineering OMAE2011 June 19-24, 2011, Rotterdam, The Netherlands Proceedings of the ASME 2011 30th International

More information

Dynamic Positioning: Method for Disaster Prevention and Risk Management

Dynamic Positioning: Method for Disaster Prevention and Risk Management Available online at www.sciencedirect.com ScienceDirect Procedia Earth and Planetary Science 11 ( 2015 ) 216 223 Global Challenges, Policy Framework & Sustainable Development for Mining of Mineral and

More information

MATING OF THE MOLIKPAQ DRILLING RIG

MATING OF THE MOLIKPAQ DRILLING RIG ARGONAUTICS Marine Engineering Page 1 MATING OF THE MOLIKPAQ DRILLING RIG Frank van Hoorn, ARGONAUTICS Marine Engineering Sausalito, Ca, USA In-Tae Kim, Daewoo Heavy Industries Ltd. Okpo Yard, Korea Introduction

More information

U S F O S B u o y a n c y And Hydrodynamic M a s s

U S F O S B u o y a n c y And Hydrodynamic M a s s 1 U S F O S B u o y a n c y And Hydrodynamic M a s s 2 CONTENTS: 1 INTRODUCTION... 3 2 ACCURACY LEVELS... 3 2.1 LEVEL-0... 3 2.2 LEVEL-1... 3 2.3 PANEL MODEL... 3 3 EX 1. SINGLE PIPE. NON FLOODED... 4

More information

SOFTWARE. Sesam user course. 02 May 2016 HydroD Input. Ungraded SAFER, SMARTER, GREENER DNV GL 2016

SOFTWARE. Sesam user course. 02 May 2016 HydroD Input. Ungraded SAFER, SMARTER, GREENER DNV GL 2016 SOFTWARE Sesam user course DNV GL 1 SAFER, SMARTER, GREENER About the presenter Name: Torgeir Kirkhorn Vada Position: Product Manager for floating structures Background: PhD in Applied mathematics/hydrodynamics

More information

LNG TANDEM OFFLOADING A KEY ENABLING TECHNOLOGY TO MAKE LNG PRODUCTION OFFSHORE HAPPEN

LNG TANDEM OFFLOADING A KEY ENABLING TECHNOLOGY TO MAKE LNG PRODUCTION OFFSHORE HAPPEN LNG TANDEM OFFLOADING A KEY ENABLING TECHNOLOGY TO MAKE LNG PRODUCTION OFFSHORE HAPPEN Fabrice Dumortier 1, Jean-Pierre Queau 1, Jean-Robert Fournier 2 1. SBM Offshore 2. SBM Offshore Keywords: 1. LNG;

More information

Learn more at

Learn more at Full scale model tests of a steel catenary riser C. Bridge 1, H. Howells 1, N. Toy 2, G. Parke 2, R. Woods 2 1 2H Offshore Engineering Ltd, Woking, Surrey, UK 2 School of Engineering, University of Surrey,

More information

TARPON A Minimal Facilities Platform

TARPON A Minimal Facilities Platform TARPON A Minimal Facilities Platform Contents Introduction TARPON Description TARPON Features TARPON Benefits TARPON Proofs TARPON Typical Installation Options Design Codes & Certification Novel Application

More information

Modelling of Extreme Waves Related to Stability Research

Modelling of Extreme Waves Related to Stability Research Modelling of Extreme Waves Related to Stability Research Janou Hennig 1 and Frans van Walree 1 1. Maritime Research Institute Netherlands,(MARIN), Wageningen, the Netherlands Abstract: The paper deals

More information

$ Millions. The PC Semi: A Low Motion Semisubmersible Capable of a Wet or Dry Tree Configuration. Semi Hull CAPEX Differentials. Topsides.

$ Millions. The PC Semi: A Low Motion Semisubmersible Capable of a Wet or Dry Tree Configuration. Semi Hull CAPEX Differentials. Topsides. The : A Low Motion Semisubmersible Capable of a Wet or Dry Tree Configuration In our ever changing and uncertain market conditions, it is extremely important to ensure capital investments are successful

More information

ITTC Recommended Procedures Testing and Extrapolation Methods Loads and Responses, Seakeeping Experiments on Rarely Occurring Events

ITTC Recommended Procedures Testing and Extrapolation Methods Loads and Responses, Seakeeping Experiments on Rarely Occurring Events Loads and Responses, Seakeeping Page 1 of 5 CONTENTS 1. PURPOSE OF PROCEDURE 2. STANDARDS FOR EXPERIMENTS ON RARELY OCCURRING EVENTS 2.1 Previous Recommendations of ITTC 2.2 Model Design and Construction

More information

STATION KEEPING EXTENSIVE MODEL TESTING OF A DRY-TREE SPREAD-MOORED BARGE IN BRAZILLIAN WATERS

STATION KEEPING EXTENSIVE MODEL TESTING OF A DRY-TREE SPREAD-MOORED BARGE IN BRAZILLIAN WATERS STATION KEEPING EXTENSIVE MODEL TESTING OF A DRY-TREE SPREAD-MOORED BARGE IN BRAZILLIAN WATERS Arjan Voogt (MARIN) and Mamoun Naciri (SBM) Deep Offshore Technology XIV (DOT-2002) ABSTRACT This paper describes

More information

Advanced Applications in Naval Architecture Beyond the Prescriptions in Class Society Rules

Advanced Applications in Naval Architecture Beyond the Prescriptions in Class Society Rules Advanced Applications in Naval Architecture Beyond the Prescriptions in Class Society Rules CAE Naval 2013, 13/06/2013 Sergio Mello Norman Neumann Advanced Applications in Naval Architecture Introduction

More information

EXPERIMENTAL STUDY ON THE HYDRODYNAMIC BEHAVIORS OF TWO CONCENTRIC CYLINDERS

EXPERIMENTAL STUDY ON THE HYDRODYNAMIC BEHAVIORS OF TWO CONCENTRIC CYLINDERS EXPERIMENTAL STUDY ON THE HYDRODYNAMIC BEHAVIORS OF TWO CONCENTRIC CYLINDERS *Jeong-Rok Kim 1), Hyeok-Jun Koh ), Won-Sun Ruy 3) and Il-Hyoung Cho ) 1), 3), ) Department of Ocean System Engineering, Jeju

More information

INCLINOMETER DEVICE FOR SHIP STABILITY EVALUATION

INCLINOMETER DEVICE FOR SHIP STABILITY EVALUATION Proceedings of COBEM 2009 Copyright 2009 by ABCM 20th International Congress of Mechanical Engineering November 15-20, 2009, Gramado, RS, Brazil INCLINOMETER DEVICE FOR SHIP STABILITY EVALUATION Helena

More information

Study of Passing Ship Effects along a Bank by Delft3D-FLOW and XBeach1

Study of Passing Ship Effects along a Bank by Delft3D-FLOW and XBeach1 Study of Passing Ship Effects along a Bank by Delft3D-FLOW and XBeach1 Minggui Zhou 1, Dano Roelvink 2,4, Henk Verheij 3,4 and Han Ligteringen 2,3 1 School of Naval Architecture, Ocean and Civil Engineering,

More information

Hydrodynamic Analysis of a Heavy Lift Vessel during Offshore Installation Operations

Hydrodynamic Analysis of a Heavy Lift Vessel during Offshore Installation Operations Presentation for Defense of Master Thesis Hydrodynamic Analysis of a Heavy Lift Vessel during Offshore Installation Operations Speaker: Bin Wang Supervisor: Prof. Robert Bronsart 23 rd Feb, 2015 Nantes

More information

Low Cost Flexible Production System for Remote Ultra-Deepwater Gulf of Mexico Field Development

Low Cost Flexible Production System for Remote Ultra-Deepwater Gulf of Mexico Field Development Low Cost Flexible Production System for Remote Ultra-Deepwater Gulf of Mexico Field Development 10121-4404-03 Jelena Vidic-Perunovic, Doris, Inc. Lars Ødeskaug, Sevan Marine ASA RPSEA Ultra-Deepwater Technology

More information

Design of Offshore Structures Prof. S. Nallayarasu Department of Ocean Engineering Indian Institute of Technology, Madras

Design of Offshore Structures Prof. S. Nallayarasu Department of Ocean Engineering Indian Institute of Technology, Madras (Refer Slide Time: 00:32) Design of Offshore Structures Prof. S. Nallayarasu Department of Ocean Engineering Indian Institute of Technology, Madras Module - 2 Lecture - 1 Concepts of Fixed Offshore Platform

More information

A Study on Roll Damping of Bilge Keels for New Non-Ballast Ship with Rounder Cross Section

A Study on Roll Damping of Bilge Keels for New Non-Ballast Ship with Rounder Cross Section International Ship Stability Workshop 2013 1 A Study on Roll Damping of Bilge Keels for New Non-Ballast Ship with Rounder Cross Section Tatsuya Miyake and Yoshiho Ikeda Department of Marine System Engineering,

More information

SAMPLE MAT Proceedings of the 10th International Conference on Stability of Ships

SAMPLE MAT Proceedings of the 10th International Conference on Stability of Ships and Ocean Vehicles 1 Application of Dynamic V-Lines to Naval Vessels Matthew Heywood, BMT Defence Services Ltd, mheywood@bm tdsl.co.uk David Smith, UK Ministry of Defence, DESSESea-ShipStab1@mod.uk ABSTRACT

More information

Learn more at

Learn more at IBP1833_06 COST EFFICIENT ARTIFICIAL BUOYANT SEABED DRILLING SOLUTION Dan Moutrey 1, Frank Lim 2 Copyright 2006, Instituto Brasileiro de Petróleo e Gás - IBP This Technical Paper was prepared for presentation

More information

Wind Turbine Shuttle. Ferdinand van Heerd

Wind Turbine Shuttle. Ferdinand van Heerd Wind Turbine Shuttle Ferdinand van Heerd Contents Introduction Concept Resistance Seakeeping Vessel motion compensation system Hoisting motion compensation system Landing the wind turbine Workability Efficiency

More information

DP Ice Model Test of Arctic Drillship

DP Ice Model Test of Arctic Drillship Author s Name Name of the Paper Session DYNAMIC POSITIONING CONFERENCE October 11-12, 211 ICE TESTING SESSION DP Ice Model Test of Arctic Drillship Torbjørn Hals Kongsberg Maritime, Kongsberg, Norway Fredrik

More information

The SDS Skip. Subsea Deployment Systems Ltd.

The SDS Skip. Subsea Deployment Systems Ltd. The SDS Skip SUBSEA SKIP An alternative to enhance the recovery of structures, spool pieces, mattresses etc. during decommissioning work Can be used to transport complex structures or spool pieces to field

More information

Offshore Stabilization Pontoon for a heavy lift vessel Concept design & workability

Offshore Stabilization Pontoon for a heavy lift vessel Concept design & workability Offshore Stabilization Pontoon for a heavy lift vessel A.M. ten Klooster Delft University of Technology OFFSHORE STABILIZATION PONTOON FOR A HEAVY LIFT VESSEL CONCEPT DESIGN & WORKABILITY by A.M. ten Klooster

More information

Dynamic Positioning Control Augmentation for Jack-up Vessels

Dynamic Positioning Control Augmentation for Jack-up Vessels DYNAMIC POSITIONING CONFERENCE October 9-10, 2012 Design and Control Session Dynamic Positioning Control Augmentation for Jack-up Vessels By Bradley Deghuee L-3 Communications 1 Introduction Specialized

More information

DAMAGE STABILITY TESTS OF MODELS REPRESENTING RO-RC) FERRIES PERFORMED AT DMI

DAMAGE STABILITY TESTS OF MODELS REPRESENTING RO-RC) FERRIES PERFORMED AT DMI TECHNISCHE UNIVERSITET laboratoriurn vow Scheepshydromechareba slechlef Meketweg 2, 2628 CD. Delft Tel.: 015-788873 - Fax 015-781838 DAMAGE STABILITY TESTS OF MODELS REPRESENTING RO-RC) FERRIES PERFORMED

More information

Design Challenges & Solutions for Large Diameter Export Risers

Design Challenges & Solutions for Large Diameter Export Risers Design Challenges & Solutions for Large Diameter Export Risers Elizabeth Tellier, Hugh Howells & Mark Cerkovnik 2H Offshore Engineering AOG 2011 Agenda WA export riser design challenges Development options

More information

OVERVIEW. Capabilities & Services

OVERVIEW. Capabilities & Services +1.713.467.0505 Sales@boamarine.com www.boamarine.com OVERVIEW Capabilities & Services BOA MARINE SERVICES provides engineering, construction and contracting services related to fi xed and fl oating offshore

More information

INTRODUCING THE PILLAR BOAT! U.S. Patent No. 9,623,935 ABSTRACT

INTRODUCING THE PILLAR BOAT! U.S. Patent No. 9,623,935 ABSTRACT INTRODUCING THE PILLAR BOAT! U.S. Patent No. 9,623,935 ABSTRACT The need to conduct motion sensitive operations at sea is increasing in the fields of space launch and recovery, oil exploration, aquaculture,

More information

Suction anchor foundations for tension and taut leg floaters in deep waters. Tension Leg Platform. Taut Leg Platform. upper chain. risers.

Suction anchor foundations for tension and taut leg floaters in deep waters. Tension Leg Platform. Taut Leg Platform. upper chain. risers. Case history: Soil investigation for offshore suction anchors anchor foundations for tension and taut leg floaters in deep waters Alternative anchors for floating structures pile Over last 5 - years anchoring

More information

Computer Simulation Helps Improve Vertical Column Induced Gas Flotation (IGF) System

Computer Simulation Helps Improve Vertical Column Induced Gas Flotation (IGF) System JOURNAL ARTICLES BY FLUENT SOFTWARE USERS JA187 Computer Simulation Helps Improve Vertical Column Induced Gas Flotation (IGF) System Computer simulation has helped NATCO engineers make dramatic improvements

More information

Fully Submersible Heavy Lift Vessel

Fully Submersible Heavy Lift Vessel Fully Submersible Heavy Lift Vessel Arnbjorn Joensen Aberdeen Maritime Branch (28th January 2015) PRESENTATION Introduction to the Subsea Deployment Vessel Installation method Tank test video Potential

More information

Low Cost Flexible Production System for Remote Ultra-Deepwater Gulf of Mexico (GOM) Field Development, Phase 2

Low Cost Flexible Production System for Remote Ultra-Deepwater Gulf of Mexico (GOM) Field Development, Phase 2 Low Cost Flexible Production System for Remote Ultra-Deepwater Gulf of Mexico (GOM) Field Development, Phase 2 10121-4404-03 Jelena Vidic-Perunovic Doris, Inc. 1 Best of RPSEA 10 Years of Research - Ultra-Deepwater

More information

Corrugated Hose Loop Calculations

Corrugated Hose Loop Calculations Corrugated Hose Loop Calculations The loop installation is one of the most common application for metal hoses. It allows the flexible hose assembly to work properly. Care must always be exercised to ensure

More information

The WindFloat Project. Hamburg, September 2016

The WindFloat Project. Hamburg, September 2016 The WindFloat Project Hamburg, September 2016 WindFloat Atlantic: a step change in turning floating wind commercial Technical Performance Competitive LCOE Bankability 2 WindFloat Atlantic: overall description

More information

Experience and Future Potential of the Oblique Icebreaker

Experience and Future Potential of the Oblique Icebreaker SHIP Design & Engineering CONSULTING & Project Development ICE MODEL & Full Scale Testing OFFSHORE Development Experience and Future Potential of the Oblique Icebreaker Mika Hovilainen Project Manager

More information

WESTRIDGE MARINE TERMINAL VANCOUVER, BC PASSING SHIP ANALYSIS

WESTRIDGE MARINE TERMINAL VANCOUVER, BC PASSING SHIP ANALYSIS WESTRIDGE MARINE TERMINAL VANCOUVER, BC PASSING SHIP ANALYSIS Prepared for: Prepared by: WESTRIDGE MARINE TERMINAL VANCOUVER, BC PASSING SHIP ANALYSIS M&N Project No. 7773 01 Revision Description Issued

More information

Aasta Hansteen. Operational Experiences. FFU Seminar 28 th January Tom-Erik Henriksen

Aasta Hansteen. Operational Experiences. FFU Seminar 28 th January Tom-Erik Henriksen Aasta Hansteen Operational Experiences FFU Seminar 28 th January 2016 Tom-Erik Henriksen Agenda Introduction to Aasta Hansteen Main Challenges & Risks Operational Experiences - 2015 Campaigns 2 seabed-to-surface

More information

SOFTWARE. Sesam user course. 12 May 2016 HydroD Hydrostatics & Stability. Ungraded SAFER, SMARTER, GREENER DNV GL 2016

SOFTWARE. Sesam user course. 12 May 2016 HydroD Hydrostatics & Stability. Ungraded SAFER, SMARTER, GREENER DNV GL 2016 SOFTWARE Sesam user course DNV GL 1 SAFER, SMARTER, GREENER Scope of presentation Describe features & commands for performing a hydrostatic analysis, and their concepts Analysis setup Code-checking Reporting

More information

Operations. On The Use of Safety Moorings in DP Operations

Operations. On The Use of Safety Moorings in DP Operations Return to Session Directory DYNAMIC POSITIONING CONFERENCE October 7-8, 28 Operations On The Use of Safety Moorings in DP Operations Nils Albert Jenssen Kongsberg Maritime, (Kongsberg Norway) Abstract

More information

Proceedings of the International Conference on Emerging Trends in Engineering and Management (ICETEM14) 30-31,December, 2014, Ernakulam, India

Proceedings of the International Conference on Emerging Trends in Engineering and Management (ICETEM14) 30-31,December, 2014, Ernakulam, India INTERNATIONAL JOURNAL OF DESIGN AND MANUFACTURING TECHNOLOGY (IJDMT) Proceedings of the International Conference on Emerging Trends in Engineering and Management (ICETEM14) ISSN 0976 6995 (Print) ISSN

More information

RELIABILITY ASSESSMENT, STATIC AND DYNAMIC RESPONSE OF TRANSMISSION LINE TOWER: A COMPARATIVE STUDY

RELIABILITY ASSESSMENT, STATIC AND DYNAMIC RESPONSE OF TRANSMISSION LINE TOWER: A COMPARATIVE STUDY RELIABILITY ASSESSMENT, STATIC AND DYNAMIC RESPONSE OF TRANSMISSION LINE TOWER: A COMPARATIVE STUDY Yusuf Mansur Hashim M. Tech (Structural Engineering) Student, Sharda University, Greater Noida, (India)

More information

1. Outline of the newly developed control technologies

1. Outline of the newly developed control technologies This paper describes a vertical lifting control and level luffing control design for newly developed, fully hydraulicdriven floating cranes. Unlike lattice boom crawler cranes for land use, the floating

More information

CRITERIA OF BOW-DIVING PHENOMENA FOR PLANING CRAFT

CRITERIA OF BOW-DIVING PHENOMENA FOR PLANING CRAFT 531 CRITERIA OF BOW-DIVING PHENOMENA FOR PLANING CRAFT Toru KATAYAMA, Graduate School of Engineering, Osaka Prefecture University (Japan) Kentarou TAMURA, Universal Shipbuilding Corporation (Japan) Yoshiho

More information

Top Tensioned Riser Challenges and Solutions for Dry Tree Facilities in Asia Pacific

Top Tensioned Riser Challenges and Solutions for Dry Tree Facilities in Asia Pacific June 2011 Top Tensioned Riser Challenges and Solutions for Dry Tree Facilities in Asia Pacific Daniel Brooker, MCS Kenny Presentation Agenda 1. Objectives 2. Top Tensioned Riser (TTR) Selection Drivers

More information

Dynamic analyses of tankers moored at berth

Dynamic analyses of tankers moored at berth Dynamic analyses of tankers moored at berth Marin byggteknikkdagen 18.4.2018 Martin Thuve Hovden Department of Marine Tecnology, Multiconsult Tromsø Department of Marine Tecnology, Tromsø 27 marine & coastal

More information

INTERNATIONAL JOURNAL OF CIVIL AND STRUCTURAL ENGINEERING Volume 1, No 4, 2010

INTERNATIONAL JOURNAL OF CIVIL AND STRUCTURAL ENGINEERING Volume 1, No 4, 2010 Effect of geometric dimensions on the transmission coefficient of floating breakwaters Mohammad Hosein Tadayon, Khosro Bargi 2, Hesam Sharifian, S. Reza Hoseini - Ph.D student, Department of Civil Engineering,

More information

COUPLED DYNAMIC ANALYSIS OF MOORING LINES FOR DEEP WATER FLOATING SYSTEMS

COUPLED DYNAMIC ANALYSIS OF MOORING LINES FOR DEEP WATER FLOATING SYSTEMS Proceedings of International Conference in Ocean Engineering, ICOE Proceedings 2009 of ICOE 2009 Coupled Dynamic Analysis IIT Madras, of Chennai, Mooring India. Lines for Deep Water Floating Systems 1-5

More information

Learn more at

Learn more at STRIDE JIP Phase III SUT Talk 15th November 2 Offshore VIV monitoring (vortex induced vibration) Catenary riser interaction with deepwater seabeds 3 Full Scale Riser Monitoring To get real measurements

More information

Pipeline Flooding, Dewatering and Venting Dr Aidan O'Donoghue, Pipeline Research Limited, Glasgow, Scotland

Pipeline Flooding, Dewatering and Venting Dr Aidan O'Donoghue, Pipeline Research Limited, Glasgow, Scotland Pipeline Flooding, Dewatering and Venting Dr Aidan O'Donoghue, Pipeline Research Limited, Glasgow, Scotland Abstract Flooding, cleaning, gauging, dewatering and venting of offshore oil and gas pipelines

More information

MINIMUM DECK HEIGHT OF A SEMI-SUBMERSIBLE PLATFORM ACCORDING TO BLACK SEA ENVIRONMENT

MINIMUM DECK HEIGHT OF A SEMI-SUBMERSIBLE PLATFORM ACCORDING TO BLACK SEA ENVIRONMENT MINIMUM DECK HEIGHT OF A SEMI-SUBMERSIBLE PLATFORM ACCORDING TO BLACK SEA ENVIRONMENT Ionuț-Cristian SCURTU Principal instructor, Navy Academy Mircea cel Batran Constanta, Romania Abstract-The fast evolution

More information

The Impact of Composites on Future Deepwater Riser Configurations

The Impact of Composites on Future Deepwater Riser Configurations The Impact of Composites on Future Deepwater Riser Configurations Thomas Brown 2H Offshore Engineering Ltd NH GRAND HOTEL KRASNAPOLSKY AMSTERDAM 3-5 APRIL 2017 Deepwater Riser Technology Today s deepwater

More information

A new possibility for crossing: The Submerged Floating Tube Bridge

A new possibility for crossing: The Submerged Floating Tube Bridge A new possibility for crossing: The Submerged Floating Tube Bridge Statens vegvesen study for the SFTB in Bjørnafjord 01.11.2018 What is a Submerged Floating Tube Bridge? Bridge SFTB Tunnel Tunnel Geometry

More information

Development of a New Deep-Water Riser System. Daniel Karunakaran Subsea 7

Development of a New Deep-Water Riser System. Daniel Karunakaran Subsea 7 Development of a New Deep-Water Riser System Daniel Karunakaran Subsea 7 Introduction Grouped SLOR TM is an open bundle riser solution developed by Subsea 7 and 2H Offshore Array of close standing SLOR

More information

Port Infrastructure to Support Floating Offshore Wind West Coast USA

Port Infrastructure to Support Floating Offshore Wind West Coast USA Port Infrastructure to Support Floating Offshore Wind West Coast USA Focus on California Figure: Principle Power Aaron Porter, P.E., & Shane Phillips, P.E. Mott MacDonald Seattle, WA BOEM Project Manager:

More information

A STUDY OF THE LOSSES AND INTERACTIONS BETWEEN ONE OR MORE BOW THRUSTERS AND A CATAMARAN HULL

A STUDY OF THE LOSSES AND INTERACTIONS BETWEEN ONE OR MORE BOW THRUSTERS AND A CATAMARAN HULL A STUDY OF THE LOSSES AND INTERACTIONS BETWEEN ONE OR MORE BOW THRUSTERS AND A CATAMARAN HULL L Boddy and T Clarke, Austal Ships, Australia SUMMARY CFD analysis has been conducted on a 100m catamaran hull

More information

Offshore engineering science

Offshore engineering science Offshore engineering science In this research stream theoretical models advanced geotechnical models and new numerical techniques were used in applied offshore engineering topics such as loading, design

More information

DETRMINATION OF A PLUNGER TYPE WAVE MAKER CHARACTERISTICE IN A TOWING TANK

DETRMINATION OF A PLUNGER TYPE WAVE MAKER CHARACTERISTICE IN A TOWING TANK The 9 th International Conference on Coasts, Ports and Marine Structures (ICOPMAS 2010) 29 Nov.-1 Dec. 2010 (Tehran) DETRMINATION OF A PLUNGER TYPE WAVE MAKER CHARACTERISTICE IN A TOWING TANK sayed mohammad

More information

Learn more at

Learn more at Bottom Weighted Riser A Novel Design for Re-location and Disconnection Frank Lim and John McGrail 2H Offshore Engineering Ltd. Woking, Surrey, United Kingdom ABSTRACT Flexible pipe risers have limitations

More information

ISOLATION OF NON-HYDROSTATIC REGIONS WITHIN A BASIN

ISOLATION OF NON-HYDROSTATIC REGIONS WITHIN A BASIN ISOLATION OF NON-HYDROSTATIC REGIONS WITHIN A BASIN Bridget M. Wadzuk 1 (Member, ASCE) and Ben R. Hodges 2 (Member, ASCE) ABSTRACT Modeling of dynamic pressure appears necessary to achieve a more robust

More information

Computational Analysis of Oil Spill in Shallow Water due to Wave and Tidal Motion Madhu Agrawal Durai Dakshinamoorthy

Computational Analysis of Oil Spill in Shallow Water due to Wave and Tidal Motion Madhu Agrawal Durai Dakshinamoorthy Computational Analysis of Oil Spill in Shallow Water due to Wave and Tidal Motion Madhu Agrawal Durai Dakshinamoorthy 1 OUTLINE Overview of Oil Spill & its Impact Technical Challenges for Modeling Review

More information

BWS ONLINE FORECASTING BERTH OPERATING SAFETY. Matthew R. O Halloran, Daphne Choong

BWS ONLINE FORECASTING BERTH OPERATING SAFETY. Matthew R. O Halloran, Daphne Choong BWS ONLINE FORECASTING BERTH OPERATING SAFETY Matthew R. O Halloran, Daphne Choong OMC International Pty Ltd, 2/2 Walmer St, Abbotsford, Vic 3067, Australia matthew@omc-international.com.au daphne@omc-international.com.au

More information

Comparison of Motion Sickness Incidence (MSI) of three Crew Transfer Vessels with different hull forms. Héloïse Vignal

Comparison of Motion Sickness Incidence (MSI) of three Crew Transfer Vessels with different hull forms. Héloïse Vignal Comparison of Motion Sickness Incidence (MSI) of three Crew Transfer Vessels with different hull forms Héloïse Vignal University Supervisors : Prof. Zbigniew Sekulski, ZUT Prof. Florin Pacuraru, UGAL Industrial

More information

Tutorial. BOSfluids. Relief valve

Tutorial. BOSfluids. Relief valve Tutorial Relief valve The Relief valve tutorial describes the theory and modeling process of a pressure relief valve or safety valve. It covers the algorithm BOSfluids uses to model the valve and a worked

More information

2.016: Hydrodynamics

2.016: Hydrodynamics 2.016: Hydrodynamics Alexandra H. Techet Dept. of Mechanical Engineering Lecture 1 What is Hydrodynamics? Hydrodynamics v. Aerodynamics Water is almost 1000 times denser than air! Marine Hydrodynamics

More information

LOADS ON TIE-DOWN SYSTEMS FOR FLOATING DRILLING RIGS DURING HURRICANE CONDITIONS. A Thesis YOON HYEOK BAE

LOADS ON TIE-DOWN SYSTEMS FOR FLOATING DRILLING RIGS DURING HURRICANE CONDITIONS. A Thesis YOON HYEOK BAE LOADS ON TIE-DOWN SYSTEMS FOR FLOATING DRILLING RIGS DURING HURRICANE CONDITIONS A Thesis by YOON HYEOK BAE Submitted to the Office of Graduate Studies of Texas A&M University in partial fulfillment of

More information