DREDGING AND DISPOSAL REPORT for the PORT OF BROOKINGS PORT OF BROOKINGS HARBOR, OREGON

Size: px
Start display at page:

Download "DREDGING AND DISPOSAL REPORT for the PORT OF BROOKINGS PORT OF BROOKINGS HARBOR, OREGON"

Transcription

1 DREDGING AND DISPOSAL REPORT for the PORT OF BROOKINGS PORT OF BROOKINGS HARBOR, OREGON Attn: Mr. Ted Fitzgerald, Port Director PO Box 848 Brookings, OR By Jack Akin, EMC, Engineers/Scientists, LLC 2/15/13 TABLE OF CONTENTS 1.0 INTRODUCTION POST-TSUNAMI DREDGE AND DISPOSAL DREDGING MAJOR DREDGING EQUIPMENT LIST SEDIMENT DISPOSAL PROJECT DESIGN DESCRIPTION OF WORK PROCEDURE DREDGE OPERATION FIELD MEASUREMNT CHECKS ENVIRONMENTAL PROTECTION HORIZONTAL/VERTICAL CONTROL OF DREDGING EQUIPMENT SEDIMENT DISPOSAL LOCATION MONITORING ENVIRONMENTAL PROTECTION REQUEST TO DECANT DREDGE AREAS PROTECTION AGAINST TURBIDITY-RELATED POLLUTANTS WORKING HOURS POSITIONING & PROGRESS SURVEYS DREDGE NAVIGATION VESSEL TRAFFIC AND SECURITY PROTECTION OF PORT FACILITIES... 9 ATTACHED DRAWINGS FIGURE 1 NOTES, PAGE 3; FIGURE 1, PAGE 2; DETAIL B1, PAGE 21; DETAIL H1, PAGE 37; FIGURE 1.6, PAGE 13; FLUID CALCULATIONS FOR 14 INCH, SDR 17 HDPE PIPE SYSTEM, PAGES 4 AND 5 OF 5; PORT OF BROOKINGS POST DREDGING VOLUMES, SHEET 1 OF 1

2 1.0 INTRODUCTION This 2/15/13 Dredge Report is submitted by EMC - Engineers/Scientists, LLC (PE), on behalf of the Port of Brookings, Harbor, Oregon. The PE was contracted by the Port of Brookings (Port) to propose for permits, and to provide engineering, labor, materials and equipment to conduct post-tsunami dredging and disposal of about 31,000 yds 3 of sediment within the North and South Basins (Basin 1 and Basin 2), and within the Ice House/Fueling Dock Inlet, Port of Brookings Harbor, Oregon. This work was conducted under a Joint Permit (Permit # /3) to remove accumulated sediments. In addition to the plan view of the proposed dredging areas shown in the Dredge & Disposal Plan (DDP), cross-sectional views (prisms) have been constructed at key locations, which have been provided to the USACE, and are available to particular regulatory reviewers of this report upon request (Jack Akin, Engineer of Record, Work Phone: , Ext. 1. If Jack is not at his desk, calls are auto-transferred to Akin s cell phone. address is emc@emcengineersscientists.com). 2.0 POST-TSUNAMI DREDGE AND DISPOSAL 2.1 DREDGING A permit to dredge the Port basins was received from the USACE on March 6 th, 2012 (Permit # /3). However, since the in-water work window at this harbor has been from November 15 th to February 15 th, the Port would have been unable to dredge until November 15 th, The Port therefore petitioned for an earlier date to begin, and eventually was informed in late August that a start-date to begin September 1 st was approved by the Program Review Group (PRG). The Port proceeded after annual boating events on September 6 th, and completed by October 10 th, the dredging of about 27,000 yds 3 via FEMA/OEM and Oregon State matching funding, and about 4000 yds 3 via Oregon State Marine Board funding, of port harbor basin sediments that had been shifted by the 3/11/11 tsunami. The dredging was accomplished by hydraulic suction dredge with cutter head as described below. The Port employed equipment for this project as described within the Section below entitled Major Dredging Equipment List for Plan. 1

3 2.2 MAJOR DREDGING EQUIPMENT LIST 1) Dredge - 12x12 DSC Shark 2) Tug boat with A- Frame 3) 2 Connex boxes of tools and supplies 4) Work skiff 5) Misc. equipment anchors, cables, etc. 6) C-15 Caterpillar 650 hp engine, driving a 36 impeller booster 7) A total of about 10,500 feet of 14 SDR 17 HDPE pipe 8) HDPE pipe welder with 10, 12 and 14 dies. 9) Specialized HDPE floats, buoys and lighting 10) Silent monitor 3.0 SEDIMENT DISPOSAL The sediment, after removal by a hydraulic dredge (see photo below), was pumped through direct piping from the hydraulic dredge through the booster to the Chetco ODMDS. According to the above-referenced EPA EIS, the average depth of this disposal area is feet. The dumping site is about a mile off-shore in and is called the Chetco ODMDS (see attached drawing FIGURE 1 Notes, Page 3), and is described, for example, in the EPA document entitled Chetco Ocean Dredged Material Disposal Site Designation, Draft Environmental Impact Statement, (1999). The four corners of the 1800 X 1800 sediment disposal area are located via four geographic points in that EIS. A pipeline (14 diameter, plastic, welded, see footnote) was constructed, laid out and towed to location, and anchored to the ocean floor as shown on attached drawing FIGURE 1, Page 2. 12x12 DSC Shark, with Work Skiff Alongside The pipe outlet was mounted to a platform (see photo on next page) and equipped with location monitoring. Dredged sediment was thence pumped directly from the hydraulic suction dredge to the disposal location. 2

4 4.0 PROJECT DESIGN 4.1 DESCRIPTION OF WORK - The sediments were transported via hydraulic dredge from the harbor, through a designed piping and pumping system, and disposed in the Chetco ODMDS. The Port completed the dredging of post-tsunami moved sediments on October 10 th, Anchored Platform Supporting Silent Monitor 4.2 PROCEDURE - The Port completed the dredging of about 27,000 yds 3 via FEMA/OEM and Oregon State matching funding, and about 4000 yds 3 via Oregon State Marine Board funding, of port harbor basin sediments that had been shifted by the 3/11/11 tsunami, via a 12x12 DSC Shark hydraulic suction dredge, equipped with a cutter head. A rock guard was welded to the cutter head to limit rock size to 8 diameter. The dredge operated in the harbor only, and pumped sediment-slurries ranging from about 10% - 40% solids, through a maximum of 3500 feet, to a C-15 engine driven, 36 impeller mounted booster pump. The booster pump drove the slurry thence a maximum of about 7000 to the sediment disposal area, described in Section 3.0. All piping was 14 SDR 17 HDPE. The harbor piping was submerged during operations. Piping from the dredge was laid underwater (when containing slurry), until reaching land, and thence upland to the booster pump. Piping from the booster pump outlet was not attached to floats to a point out to sea just beyond the nose of the adjacent jetty, in order remain beneath breaking waves, after which the pipe was floated to the anchored platform supporting the silent monitor. The floating pipe was kept aloft by in-house designed and built floats, constructed of older HDPE pipe that had been determined by the PE to be less safe for pressures required for this dredging project. 25 lengths of 14 SDR 17 and 12 SDR 17 of this piping were cut and caps welded thereon. The sealed floats were then strapped to the piping to be floated, spaced as directed by the PE (see attached drawing DETAIL B1, Page 35). The decision to float the pipe from a point beyond the surf to the disposal site was made at the PE s recommendation, in order to avoid collisions with vessels moving at higher speeds during accidentally surfacing of pipe sections which were not visible out at sea. 3

5 A floating pipeline, lit by flashing solar lights and buoys (see attached drawing DETAIL H1, Page 37), helped to prevent such collisions. Additionally, since some of the pipe was not new, and because the Port did not have knowledge of the quality of old welds, pipe breaks were more easily detected and repaired. All pipeline out to sea was stayed from drift via anchoring. All piping in the harbor was fully visible, when floating, to the dredge operator deckman, as well to the workers on the work skiff and tender vessel, at all times. Therefore piping in the harbor was sunk via maintaining adequate sediment in the piping. No pipe anchoring was used within the harbor. On several occasions during the project the piping in the harbor surfaced accidentally. However, with personnel and vessels available, the slow-moving vessels in the harbor were piloted away from the floating pipeline. 4.3 DREDGE OPERATION - First, pipe lengths were welded (and flange-bolted at convenient pipe segment joints) into 1000 and 2000 lengths, and staged either on land nearby or along the east bank of the Chetco River. All pipe welding was performed by Port employees, after adequate certifying training for each welder was completed. The pipe fuse-welding unit utilized was leased from the company performing the training. The welded lengths were then flange-bolted together at sea as needed. The leased dredge and assistance vessels were at the same time lowered into the harbor by the boat lift located at the south end of Basin 2 (South Basin). Pipe lengths were then flange-bolted to the dredge pipe outlet, and to the inlet and outlet of the booster pump (see attached drawing FIGURE 1.6, Page 13). The dredge operated by utilization of a cutter, a C-15 engine-driven centrifugal pump (the cutter head is also powered by an estimated hp from the engine), and a combination of winches, anchors, and spuds. The cutterhead broke the material free from the bottom, and pulled it to the suction zone in solution for pumping. This slurry was then pumped by means of a centrifugal pump through a pipeline towards the disposal location. The dredge swings from side to side using winches pulling on anchors while pivoting on spuds, one at a time as it swings from side to side, and is piloted by the skiff and/or workboat. With the combination of swing anchors and winches, and by alternating spuds in staggering positions, the dredge walked forward into the banks of post-tsunami shifted material. The swing anchors, located off to the sides of the work zones, are marked by buoys. Dredging began in the west side of the South Basin (Docks C K), thence to the east side (Docks P & Q), thence to the Ice House Inlet, thence to the east side of the North Basin (Docks A H), and completed the project at the Sports Transient Dock near the northwest corner of the North Basin. 4

6 4.4 FIELD MEASUREMENTS CHECKS Pipe and Pumping System Fluid calculations were submitted within drawing notes (see attached drawings entitled FLUID CALCULATIONS FOR 14 INCH, SDR 17 HDPE PIPE SYSTEM, Pages 4 of 5 and 5 of 5) 1 with the Dredge and Disposal Plan. Therein design power requirements were calculated using Hazen-Williams pipe friction, confirmed by Darcy-Weisbach. The friction factor in Darcy Weisbach was calculated via Swamee-Jain exponentials, and tested using Colebrooke-White. The most conservative of the two was used in the total dynamic head calculations for power determinations. A spreadsheet was constructed for various pipe lengths, pipe diameters and dimensional ratios, and efficiency factors, also included within the design drawings. Additionally, other dependant characteristics, including buoyancies, spans and production rates, were presented. These fluid calculations within the drawing notes corroborated closely with field observations. For example, the PE observed the 650 hp C RPM enginedriven-booster pump, while running at 1500 rpm, drove the fluid in the id HDPE pipe at feet/second (measured via Greyline Doppler flow-meter) through 6000 feet of pipe, with an inlet pressure of psi and outlet pressure of psi. At 1500 rpm, fluid laws indicated that the booster pump was operating at or under 50% capacity Turbidity measurements were taken by the PE each day. During the first two days turbidity was measured once each hour during dredging. When measurements provided the PE with adequate sense of predictability, two sample events, randomly selected, were conducted each day for the ten days, and then one per day, randomly selected, was conducted for the remaining project period. Depths of samples collected ranged from two feet beneath the water surface to within one foot from basin floor, feet from the cutter head. At no time did turbidity measurement readings exceed 15 NTUs, and 90% read between 5 and 10 NTUs. An Omega Portable turbidity unit was used for the project, calibrated by the PE each day (range NTUs). 4.5 ENVIRONMENTAL PROTECTION The pipeline was inspected initially by the PE, and subsequently, at the least, daily when dredging was taking place Only sound pipeline was used. The PE reviewed the pipe and application. Net maximum pressure on the piping material is internal, created by flow requirements, and is greatest at maximum hydrostatic conditions (at water surface). 1 These and all calculations shown in this Report are for the use of the PE referred to in this Report, are specific to this project, and any use by outside persons are at their own risk. The Port and the PE does not support or protect or guarantee the use of any of the design details or parameters for any use outside of this particular project. 5

7 As mentioned above, highest pressures in the system were noted at the pressure gage located just after the booster pump to be about 95 psi. 17 SDR HDPE pipe is ASTM-rated at 160 PSI. Since some of the pipe in this system was used, the PE calculated the SDR pressure rating based on the thinnest wall of piping that was pressurized in the project, which was inch wall of a 14 OD HDPE pipe is ASTM rated as an SDR 22 pipe at 120 psi (approximated by 2(1250)/(SDR- 1)). The selected pipe was rated as a function of the hydrostatic strength of the material, the pipe dimensional ratio, and environmental and temperature factors. Affected employees had undergone pipe handling and welding training, as provided by the pipe supplier (3-4 classroom plus 4-hour hands-on training session, to certify employees to set up and weld medium diameter (4 20 ) HDPE pipe via butt fusion. Welded pipe bending radii did not exceed that recommended (usually about 25 pipe diameters). All calculations available upon request The pipeline was positioned, weighted and marked for safe navigation NAME AND TELEPHONE NUMBERS OF REPRESENTATIVES ON- SITE PE (Jack Akin, , Ext. 1) was on site during operations SCHEDULE Dredging prep and mobilization began on September 6 th, Pumping rates required that minimum in-water work period required 25 days, barring unforeseen problems (breakdowns, encountering of unseen debris, garbage, etc. during hydraulic dredging). Dredging flowrates averaged 200 (about 50% capacity of on-site equipment) cubic yards per hour, 10 hours a day, with 10 40% solids pumped, with about 40% debris-clearing loss of efficiency In-water work was completed by October 9 th, SLURRING OF MATERIALS - All dredged materials were pumped utilizing the hydraulic suction dredge QUANTITY OF MATERIAL DREDGED - Approx. 31,000 cubic yards were removed and disposed DREDGE DESIGN DEPTHS - Project depths are as per plans and specs, and are in NAVD. Completed depths were measured by the PE after the dredging was completed, and are presented within the attached, contoured drawing entitled PORT OF BROOKINGS POST DREDGING VOLUMES, SHEET 1 OF CONTROLS FOR DREDGE SITE (Implemented when necessary in the judgment of the PE and dredge operator: otherwise see applicable sections below) Dredge positioning on the Port project was done utilizing DGPS for Dredge positioning, a gyro compass for Dredge direction, a pressure transducer for cutter depth, all linked together in a computer with dredge positioning software. 6

8 The corner point coordinates for the project were entered into the system, and the dredge was positioned accordingly. Horizontal positioning was verified by visual observations, comparing the plans with the dredge location in reference to structures, land, and/or stakes and docks. Ladder depth was verified visually with a ladder scale. Vertical control utilized an auto tide gauge and/or visual tide boards PIPELINE - 14 inch diameter SDR 17 HDPE pipe was used. Only pipeline in sound condition was used, inspected and approved per section by the PE LIMITS & CONTROLS FOR DISPOSAL SITE: Per the USACE-issued Permit # / Detailed drawings and specifications of the centrifugal pump & piping system are attached Dredged quantities were calculated by multiplying the estimated and measured pump rates by the dredge pump time, and recorded on the dredge logs, confirmed by on-site post-dredging depth measurements, conducted and adjusted by MLLW readings by the PE Pipeline Layout diagram was adjacent to cut and parallel cut, from the dredge, and on the side of the channel along jetty. 5.0 HORIZONTAL AND VERTICAL CONTROL OF DREDGING EQUIPMENT When necessary in the judgment of the PE and dredge operator, controls were implemented as described in Section At minimum horizontal positioning was accomplished by using line of sight positioning from the numerous visual reference points in the harbor. This was feasible because all planned dredging occurred within the harbor, where reference landmarks (i.e. boat slips, floating and permanent docks) were readily available. Vertical positioning was accomplished via a ladder gauge on the dredge. This gauge was regularly checked with the tide gauge near the Port fueling station. 6.0 SEDIMENT DISPOSAL LOCATION MONITORING Silent monitoring was provided by an anchored platform vessel that anchored the pipe end (see photo on Page 3 of this Report). 7

9 7.0 ENVIRONMENTAL PROTECTION See Section REQUEST TO DECANT Direct piping of dredged sediment from the dredge to the Chetco ODMDS eliminated the need to decant, so this request was removed from the DDP. 9.0 DREDGE AREAS Description Table The following table presents the specific sub-areas within the basins and dock more generally named Basin 1, or North Basin ; Basin 2, or South Basin ; and the Ice House/Fuel dock Inlet. The volumes listed below were calculated from post-dredging depths as measured by the PE, shown on attached drawing entitled PORT OF BROOKINGS POST DREDGING VOLUMES, SHEET 1 OF 1. Area Map Name Estimated Volume Removed (yds. 3 ) Docks A - H Area Ice House/Fuel Dock Area Docks C-Q Areas 3 & PROTECTION AGAINST TURBIDITY-RELATED POLLUTANTS It was proposed that turbidity curtains not be utilized for this project. It was within the DDP noted that all licensed and very experienced operators who have proposed this project, including Dutra Group, Nehalem Dredging and Camenzind Dredging, submitted their proposals assuming, from their knowledge and experience, that hydraulic dredging to direct piping to disposal site does not produce enough turbidity to justify the traffic impedance and expense created by turbidity curtain use. However, conditions within the Permit required that a turbidity curtain be employed. Therefore, a turbidity curtain system was on-site throughout the entire project, and turbidity was measured as described in Section of this report. At no time did turbidity measurement readings exceed 15 NTUs, and 90% read between 5 and 10 NTUs WORKING HOURS Working hours for the duration of the project were 12 hours per day. 8

10 12.0 POSITIONING & PROGRESS SURVEYS When necessary in the judgment of the PE and dredge operator, controls were implemented as described in Section At minimum the Port utilized a survey rod and/or sonar depth finder system to measure and confirm that basin floor design depths had been obtained, but not exceeded. Used in conjunction with the US Coast Guard posted vertical reference marker, frequent measurements and recordings were used to assist. The marker is a tide gauge, or a tide board with markings in tenths of feet, posted near the Port basin entry from the Chetco River. Depth readings were recorded on existing contoured maps of the basin floors. The maps were updated as a result of depth measurements taken after the dredging of each area was completed. Some of these have been referenced and attached to this Report DREDGE NAVIGATION See above Sections and VESSEL TRAFFIC AND SECURITY The Port is a working facility and was able to coordinate with Port management on how to both avoid interference with vessel traffic and complete the project within the permitted time constraints. The Port notified the Coast Guard of activities as required to comply with Coast Guard and Port regulations guiding operations near the Chetco River PROTECTION OF PORT FACILITIES The facilities were returned to the identical condition at project completion as they are found to be at project outset. Sincerely, Jack Akin, MS, PE Environmental Management Consultants, Engineers/Scientists, LLC (on behalf of Port of Brookings Harbor, Oregon) 13 e:\emc\dataemc\pob\basins Dredge\FEMA Budget\Sediment\Regulation & Guidance\Correspondences\Benny Dean\post-tsunami DREDGING REPORT.pdf 9

SECTION PRESSURE TESTING OF PIPING

SECTION PRESSURE TESTING OF PIPING SECTION 15044 PRESSURE TESTING OF PIPING PART 1 - GENERAL 1.01 DESCRIPTION A. Scope of Work: This section specifies the leakage and pressure testing of piping. B. Testing Records: PART 2 - PRODUCTS 2.01

More information

EFFECTS ON CUTTER SUCTION DREDGE PRODUCTION WHILE DREDGING SIMULATED DEBRIS IN THE LABORATORY

EFFECTS ON CUTTER SUCTION DREDGE PRODUCTION WHILE DREDGING SIMULATED DEBRIS IN THE LABORATORY EFFECTS ON CUTTER SUCTION DREDGE PRODUCTION WHILE DREDGING SIMULATED DEBRIS IN THE LABORATORY R. Randall 1, M. Warwick 2, J. Henriksen 3, D. Young 4, and A. Manikantan 5 ABSTRACT The cutter suction dredge

More information

Nome Harbor Page 2 of 12

Nome Harbor Page 2 of 12 Nome Harbor Nome Harbor Page 2 of 12 Condition of Improvements 30 December 2015 Nome Harbor, Alaska (CWIS No. 010422, 012270, 072742, 087755) Authorization (1) Rivers and Harbors Act, 8 August 1917 (House

More information

Rules Practice Exam 11

Rules Practice Exam 11 1 BOTH INTERNATIONAL & INLAND While underway in fog, you hear a vessel sound one prolonged blast followed by two short blasts on the whistle. What does this signal indicate? A. A vessel towing B. A vessel

More information

R. Randall Center for Dredging Studies Texas A&M University

R. Randall Center for Dredging Studies Texas A&M University R. Randall Center for Dredging Studies Texas A&M University i Glory (Caisson) holes for subsea installations Pipeline trenches Deep ocean mining LNG ports & ship channels Summary WEDA 33 & TAMU 44 2 WEDA

More information

Ninilchik Harbor Page 2 of 11

Ninilchik Harbor Page 2 of 11 Ninilchik Harbor Ninilchik Harbor Page 2 of 11 Condition of Improvements 31 December 2017 Ninilchik Harbor, Alaska (CWIS No. 012640, 087345) Authorization Rivers and Harbors Act, 3 July 1958 (P.L. 85-500

More information

Juneau Douglas Harbor

Juneau Douglas Harbor Juneau Douglas Harbor Douglas Harbor Page 2 of 8 Condition of Improvements 31 December 2015 Douglas Harbor, Alaska (CWIS No. 072789, 180942) Authorization Rivers and Harbors Act, 3 July 1958 (House Doc.

More information

Condition of Improvements 30 December 2014 Wrangell Harbors, Alaska (CWIS No , )

Condition of Improvements 30 December 2014 Wrangell Harbors, Alaska (CWIS No , ) Wrangell Harbors Condition of Improvements 30 December 2014 Wrangell Harbors, Alaska (CWIS No. 010435, 021500) Authorization (1) Rivers and Harbors Act, 22 September 1922 (House Doc. 161, 67th Congress,

More information

Charlottetown Marine Terminal Pipeline Decommissioning Project Description

Charlottetown Marine Terminal Pipeline Decommissioning Project Description Charlottetown Marine Terminal Pipeline Decommissioning Project Description 69 Marr Road Unit B Rothesay NB, E2E 3J9 Tel (506) 848-1920 Fax (506) 848-1929 Charlottetown Marine Terminal Pipeline Decommissioning

More information

1-32 NOME HARBOR, ALASKA (CWIS NOS , 87755, 12270, & 10422) Condition of Improvement 30 September 2012

1-32 NOME HARBOR, ALASKA (CWIS NOS , 87755, 12270, & 10422) Condition of Improvement 30 September 2012 NOME HARBOR 1-32 NOME HARBOR, ALASKA (CWIS NOS. 72742, 87755, 12270, & 10422) Condition of Improvement 30 September 2012 AUTHORIZATION: (1) Rivers and Harbors Act, 8 August 1917 (House Doc. 1932, 64th

More information

TECHNICAL MEMORANDUM 002 EMORANNO. 001

TECHNICAL MEMORANDUM 002 EMORANNO. 001 TECHNICAL MEMORANDUM 002 EMORANNO. 001 To: Jack Synder, P.E. EES Consulting From: Mort McMillen, P.E. Paul Larson, SE Date: October 13, 2010 Project: Cc: Taylor Bowen Subject: Technical Memorandum (TM)

More information

Ocean Structures and Material Prof. Dr. Srinivasan Chandrasekaran Department of Ocean Engineering Indian Institute of Technology, Madras

Ocean Structures and Material Prof. Dr. Srinivasan Chandrasekaran Department of Ocean Engineering Indian Institute of Technology, Madras Ocean Structures and Material Prof. Dr. Srinivasan Chandrasekaran Department of Ocean Engineering Indian Institute of Technology, Madras Module - 2 Lecture - 5 Dredging II In the fifth lecture we discussed

More information

Admiralty Inlet Pilot Tidal Project FERC No Appendix C. Derelict Gear Monitoring Plan

Admiralty Inlet Pilot Tidal Project FERC No Appendix C. Derelict Gear Monitoring Plan Appendix C Derelict Gear Monitoring Plan ADMIRALTY INLET PILOT TIDAL PROJECT FERC PROJECT NO. 12690 DERELICT GEAR MONITORING PLAN (submitted with the Final Application for a New Pilot Project License)

More information

Hydrographic Surveying Methods, Applications and Uses

Hydrographic Surveying Methods, Applications and Uses Definition: Hydrographic Surveying Methods, Applications and Uses It is the branch of surveying which deals with any body of still or running water such as a lake, harbor, stream or river. Hydrographic

More information

Dredging Keeping Our Underwater Highways Open

Dredging Keeping Our Underwater Highways Open Dredging Keeping Our Underwater Highways Open Sedimentation Material that falls to the bottom of a liquid is called sediment. If enough sediment deposits to build a shallow spot on the river or ocean bottom,

More information

AUTOMATIC DREDGING PROFILE AND CONTOUR CONTROL

AUTOMATIC DREDGING PROFILE AND CONTOUR CONTROL AUTOMATIC DREDGING PROFILE AND CONTOUR CONTROL Jay Wise 1 ABSTRACT Phillips and Jordan, a leading excavating and disaster recovery contractor, was faced with the challenge to manage a civil contract involving

More information

1-32 NOME HARBOR, ALASKA (CWIS NOS , 87755, & 10422) Condition of Improvement 30 September 2009

1-32 NOME HARBOR, ALASKA (CWIS NOS , 87755, & 10422) Condition of Improvement 30 September 2009 NOME HARBOR 1-32 NOME HARBOR, ALASKA (CWIS NOS. 72742, 87755, & 10422) Condition of Improvement 30 September 2009 AUTHORIZATION: (1) Rivers and Harbors Act, 8 August 1917 (House Doc. 1932, 64th Congress,

More information

Rules Practice Exam 14

Rules Practice Exam 14 1 BOTH INTERNATIONAL & INLAND Additional light signals are provided in the Annexes to the Rules for vessels. A. engaged in fishing B. not under command C. engaged in towing D. under sail 2 BOTH INTERNATIONAL

More information

REVISED SILT CURTAIN DEPLOYMENT PLAN

REVISED SILT CURTAIN DEPLOYMENT PLAN Contract No.: HY/2009/11 Central Wanchai Bypass, North Point Reclamation REVISED SILT CURTAIN DEPLOYMENT PLAN Name Prepared by: China Harbour Engineering Co., Ltd. China Road and Bridge Corporation Joint

More information

Special projects are mainly capital equipment purchases and improvements to the inlet. Most improvements are cost shared with FDEP and FIND.

Special projects are mainly capital equipment purchases and improvements to the inlet. Most improvements are cost shared with FDEP and FIND. Background In 1957 the Florida Legislature created the Hillsboro Inlet District. This is a special independent district that can levy taxes to finance the maintenance and improvements to the Inlet. The

More information

{ } Jack Holland Page 1 of DOC

{ } Jack Holland Page 1 of DOC Background In 1957 the Florida Legislature created the Hillsboro Inlet District. This is a special independent district that can levy taxes to finance the maintenance and improvements to the Inlet. The

More information

Reliance Industries, LLC Operating instructions for the / Bolt-on D-Ring Anchorage. Model # 3071

Reliance Industries, LLC Operating instructions for the / Bolt-on D-Ring Anchorage. Model # 3071 Reliance Industries, LLC Operating instructions for the 3071-1 / 3071-2 Bolt-on D-Ring Anchorage Model # 3071 Reliance Industries, LLC PO Box 140008 Denver, CO 80214 Ph. (800) 488-5751 Ph. (303) 424-8650

More information

S/Y MORSKI ZEKAN TECHNICAL INFORMATION

S/Y MORSKI ZEKAN TECHNICAL INFORMATION S/Y MORSKI ZEKAN TECHNICAL INFORMATION Cabins: 3 Toilets: 1 Max. Persons: 8 (6+2) LOA: 11,35 m Beam: 3,80 m Draft: 1,95 m Engine: Volvo 28HP Water tanks: 360 L Fuel tank: 150 L Anchor windlass Speed and

More information

LAKOS Waterworks. PWC Series Sand Separators. Installation & Operation Manual LS-829 (10/12)

LAKOS Waterworks. PWC Series Sand Separators. Installation & Operation Manual LS-829 (10/12) LAKOS Waterworks PWC Series Sand Separators Installation & Operation Manual LS-829 (10/12) Table of Contents Separator Operation... 3 Individual Model Details.... 4 Flow vs. Pressure Loss Chart 4 Installation

More information

Cordova Harbor Page 2 of 9

Cordova Harbor Page 2 of 9 Cordova Harbor Cordova Harbor Page 2 of 9 Condition of Improvements 30 December 2017 Cordova Harbor, Alaska (CWIS No. 087136, 087186, 087711) Authorization Rivers and Harbors Act, 30 August 1935 (R & H

More information

Juneau Aurora Harbor

Juneau Aurora Harbor Juneau Aurora Harbor Aurora Harbor Page 2 of 6 Condition of Improvements 31 December 2017 Aurora Harbor Juneau, Alaska (CWIS No. 020960) Authorization Rivers and Harbors Act, 3 July 1958 (House Doc. 286,

More information

Angela Lane, Lowe Environmental Impact / Karen Akuhata (WDC) The Wairoa wastewater treatment system requires a replacement consent by May 2019.

Angela Lane, Lowe Environmental Impact / Karen Akuhata (WDC) The Wairoa wastewater treatment system requires a replacement consent by May 2019. MEMORANDUM Job No.10292 To: From: Jamie Cox, Wairoa District Council Angela Lane, Lowe Environmental Impact / Karen Akuhata (WDC) Date: 11 September 2017 Subject: Task A2I2 Current Outfall Pipe Description

More information

Title/Description: Fuel Cell Fill Procedure

Title/Description: Fuel Cell Fill Procedure Fuel Cell Procedure Document No.: Author: Kurt Stiffel Title/Description: Approved by: Revision: 1-00 Effective Date: 1.0 Reference Documents All released OOI documents in Alfresco 3161-20000 Fuel Cell

More information

MOREHEAD CITY HARBOR, NC. Dredged Material Management Plan (DMMP)

MOREHEAD CITY HARBOR, NC. Dredged Material Management Plan (DMMP) MOREHEAD CITY HARBOR, NC Dredged Material Management Plan (DMMP) Public Meeting/Info Session 15 January 2014 US Army Corps of Engineers Morehead City Harbor DMMP Presentation Topics Morehead City Harbor

More information

Float Equipment TYPE 925/926

Float Equipment TYPE 925/926 Type 925 Float Collar Plunger Valve Float Equipment For less demanding well conditions, such as shallower depths or lower pressures, Top- Co offers economical float equipment certified to API RP 10F category

More information

DRAFT. October 17, 2014 File No Mr. Brendhan Zubricki Town Administrator Essex Town Hall 30 Martin Street Essex, MA.

DRAFT. October 17, 2014 File No Mr. Brendhan Zubricki Town Administrator Essex Town Hall 30 Martin Street Essex, MA. GZA GeoEnvironmental, Inc. Engineers and Scientists October 17, 2014 File No. 18.0171857.00 Mr. Brendhan Zubricki Town Administrator Essex Town Hall 30 Martin Street Essex, MA. 01929 DRAFT Re: Essex River

More information

2 Boating Rules and Regulations... 73

2 Boating Rules and Regulations... 73 Contents at a Glance Chapter 1 Boat Design and Construction Chapter 2 Boating Rules and Regulations Chapter 3 Navigation Rules (ColRegs) Chapter 4 Boat Operating and Seamanship Chapter 5 Piloting and Navigation

More information

You must stop your. pass with caution on the port side of vessel "B" The vessel moving upstream against the current

You must stop your. pass with caution on the port side of vessel B The vessel moving upstream against the current BK NUM ANS QUESTION ANSWER A ANSWER B ANSWER C ANSWER D ILLUST 1 1 C 1 2 B INLAND ONLY You are navigating in a narrow channel and must remain in the channel for safe operation. Another vessel is crossing

More information

CHAPTER 4: BEST MANAGEMENT PRACTICES FOR EROSION AND SEDIMENTATION CONTROL

CHAPTER 4: BEST MANAGEMENT PRACTICES FOR EROSION AND SEDIMENTATION CONTROL Figure 4.4m. Type III Floating Turbidity Barrier Source: American Boom and Barrier Corporation and Virginia Department of Transportation (DOT) Standard Sheets 71 4.4.6 Floating Turbidity Barrier Definition

More information

Item 404 Driving Piling

Item 404 Driving Piling Item Driving Piling 1. DESCRIPTION Drive piling. 2. EQUIPMENT 2.1. Driving Equipment. Use power hammers for driving piling with specified bearing resistance. Use power hammers that comply with Table 1.

More information

CLEANING, INSPECTION, AND TESTING OF SEWERS

CLEANING, INSPECTION, AND TESTING OF SEWERS CLEANING, INSPECTION, AND TESTING OF SEWERS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Cleaning, Inspecting, and Testing Sanitary Sewers B. Cleaning, Inspecting, and Testing Storm Sewers C. Cleaning and

More information

UMass Boston Waterfront at a glance

UMass Boston Waterfront at a glance UMass Boston Waterfront at a glance Fox Point Pavilion Over the years, the Fox Point Landing has been a rest area, an outdoor classroom and a general meeting place for students, staff and faculty of the

More information

Delaware River Vessel Reporting System Mariners Advisory Committee For

Delaware River Vessel Reporting System Mariners Advisory Committee For Delaware River Vessel Reporting System Mariners Advisory Committee For the Bay and River Delaware The Mariner's Advisory Committee is comprised of Master Mariners, River Pilots, and concerns itself with

More information

REFER TO AQUATHERM TECHNICAL BULLETIN A-AQTTB FOR ADDITIONAL INFORMATION AND SAFETY PRECAUTIONS

REFER TO AQUATHERM TECHNICAL BULLETIN A-AQTTB FOR ADDITIONAL INFORMATION AND SAFETY PRECAUTIONS Aquatherm Standard Pressure Testing Procedure Aquatherm offers an extensive warranty to protect against damages caused by failure from manufacturer s defect. Aquatherm requires that all installations be

More information

1-44. SITKA HARBOR, ALASKA (Western Channel, Crescent Bay Basin, Channel Rock Breakwaters) (CWIS NOS , 16840, 10322, 55030, 13787)

1-44. SITKA HARBOR, ALASKA (Western Channel, Crescent Bay Basin, Channel Rock Breakwaters) (CWIS NOS , 16840, 10322, 55030, 13787) SITKA 1-44 SITKA HARBOR, ALASKA (Western Channel, Crescent Bay Basin, Channel Rock Breakwaters) (CWIS NOS. 72845, 16840, 10322, 55030, 13787) Condition of Improvement 30 September 2011 AUTHORIZATION:

More information

Towing Officers' Assessment Record: Western Rivers

Towing Officers' Assessment Record: Western Rivers Towing Officers' Assessment Record: Western Rivers NAME: LICENSE NO.: Task No. Considered Proficient Common Element Task or Duty DE's Initials Date A. Vessel Familiarization A.1. X Locate and demonstrate

More information

Shoalwater Bay Shorline Erosion Dredging

Shoalwater Bay Shorline Erosion Dredging Shoalwater Bay Shorline Erosion Dredging ROSS ISLAND SAND & GRAVEL CO. Saving the Tokeland Penninsula Willapa Bay & Tokeland Penninsula Southwestern Washington Coast Shoalwater Bay Historic View Settlements

More information

Description of Underwater Noise Attenuation System Design Unit 2. New NY Bridge Project

Description of Underwater Noise Attenuation System Design Unit 2. New NY Bridge Project New NY Bridge Project Description of Underwater Noise Attenuation System (NAS) Design Unit 2 Description of Underwater Noise Attenuation System Design Unit 2 for the New NY Bridge Project Revision 1 May

More information

Plot the Path. Mary Anne Otten. lesson three

Plot the Path. Mary Anne Otten. lesson three Plot the Path Mary Anne Otten lesson three Subject/Grade: Grade 2, Math, Social Studies, Science Duration: one class period Materials needed: Per class: Day the Great Lakes Drained Away by Charles Ferguson

More information

VERTICAL BLADDER TANK

VERTICAL BLADDER TANK Balanced Pressure Proportioning System Reliable Foam System Requiring Only Water Power Perfect For Tight Spaces UL Listed, ASME, National Board Registered Bladder-UL162 Approved, High Tensile Pressure

More information

22. Specialty Valves.

22. Specialty Valves. 22. Specialty Valves. a. Types of Specialty Valves. 1) Use of the following specialty valves is covered in this section: Altitude Valve, Pressure Reducing Valve, Pressure Relief Valve, Swing Check Valve,

More information

ROV Development ROV Function. ROV Crew Navigation IRATECH SUB SYSTEMS 2010

ROV Development ROV Function. ROV Crew Navigation IRATECH SUB SYSTEMS 2010 IR AT EC H SU B SY ST EM S 20 10 Remotely Operated Vehicle ROV INTRODUCTORY 2008 2008 1 KEY POINTS ROV Introductory ROV Development ROV Function Types of ROV ROV Crew Navigation ROV Components 2 ROV Development

More information

National Maritime Center

National Maritime Center National Maritime Center Providing Credentials to Mariners U.S.C.G. Merchant Marine Exam (Sample Examination) Page 1 of 22 U.S.C.G. Merchant Marine Exam: Illustrations: 10 Choose the best answer to the

More information

Rules Practice Exam 7

Rules Practice Exam 7 1 INTERNATIONAL ONLY The light which may be used with a vessel's whistle is to be. A. used when the whistle is broken B. used prior to sounding the whistle C. used only at night D. a white light 2 INTERNATIONAL

More information

Good Mooring to You! Jensen Beach Mooring Field. Kathy Fitzpatrick, P.E. Coastal Engineer, Martin County

Good Mooring to You! Jensen Beach Mooring Field. Kathy Fitzpatrick, P.E. Coastal Engineer, Martin County Good Mooring to You! Kathy Fitzpatrick, P.E. Coastal Engineer, Martin County Penny Cutt Regional Manager, Coastal Systems International Mooring Field Advantages Provide a safe and secure anchorage at a

More information

EPA R6 Dive Team Operations Report. San Jacinto Waste Pits Channelview, TX December 9-10, 2015

EPA R6 Dive Team Operations Report. San Jacinto Waste Pits Channelview, TX December 9-10, 2015 EPA R6 Dive Team Operations Report San Jacinto Waste Pits Channelview, TX December 9-10, 2015 BACKGROUND The San Jacinto River Waste Pit Site history has been documented in several documents prepared for,

More information

U. S. Coast Guard Sector Boston Merrimack River Approach and Entrance, MA. Waterways Management Survey

U. S. Coast Guard Sector Boston Merrimack River Approach and Entrance, MA. Waterways Management Survey U. S. Coast Guard Sector Boston Merrimack River Approach and Entrance, MA. Waterways Management Survey The Waterways Analysis and Management Survey (WAMS) process is an essential component of both the

More information

R E V I S E D D A T E 0 4 /

R E V I S E D D A T E 0 4 / R E V I S E D D A T E 0 4 / 2 0 0 9 Guidelines Growing Oysters with the OysterGro System (OGS) Congratulations, you have just invested in one of the most efficient oyster growing system there is, the OysterGro.

More information

A real time vessel air gap monitoring system

A real time vessel air gap monitoring system Journal of Physics: Conference Series A real time vessel air gap monitoring system To cite this article: D McStay and K Thabeth 2009 J. Phys.: Conf. Ser. 178 012038 View the article online for updates

More information

PE 2708 CTS & IPS GAS PIPE

PE 2708 CTS & IPS GAS PIPE Specifications: Resin Chevron Phillips TR418Q PE 2708 Resin formulation listed in PPI TR4 Hydrostatic Design Basis: 1250 psi @ 73 F, 800 psi @ 140 F Cell Classification per ASTM D3350 = 234373E or 234375E

More information

1-22. KETCHIKAN, ALASKA (Thomas and Bar Point Basins) (CWIS NOS & 87071) Condition of Improvement 30 September 2007

1-22. KETCHIKAN, ALASKA (Thomas and Bar Point Basins) (CWIS NOS & 87071) Condition of Improvement 30 September 2007 KETCHIKAN HARBOR 1-22 KETCHIKAN, ALASKA (Thomas and Bar Point Basins) (CWIS NOS. 00631 & 87071) Condition of Improvement 30 September 2007 AUTHORIZATION: (1) Rivers and Harbors Act, 3 July 1930 (House

More information

GM Series Dual-Block Multi-Function Gas Control Valves

GM Series Dual-Block Multi-Function Gas Control Valves Installation Sheets Manual 121 Gas Combustion Combination Controls and Systems Section G Technical Bulletin GM Issue Date 0297 GM Series Dual-Block Multi-Function Gas Control Valves Figure 1: GM Series

More information

Leak testing of Valves. Standards for acceptable Rates of Valve Leakage

Leak testing of Valves. Standards for acceptable Rates of Valve Leakage Leak testing of Valves Standards for acceptable Rates of Valve Leakage American Petroleum Institute (API) The API standard 598: Valve Inspection and Testing, covers the testing and inspection requirements

More information

HARBOR INFRASTRUCTURE INVENTORIES Oak Orchard Harbor, New York

HARBOR INFRASTRUCTURE INVENTORIES Oak Orchard Harbor, New York HARBOR INFRASTRUCTURE INVENTORIES Oak Orchard Harbor, New York Harbor Location: Oak Orchard Harbor is located on the southern shore of Lake Ontario at the mouth of Oak Orchard Creek in the village of Point

More information

Enclosure (5) to NVIC 03-16

Enclosure (5) to NVIC 03-16 TOWING OFFICER ASSESSMENT RECORD LIMITED LOCAL AREA LOCAL LIMITED AREA (LLA) TOAR INSTRUCTIONS FOR USE The following Towing Officer Assessment Record (TOAR) is intended as a model for endorsements as Limited

More information

GUIDELINES FOR SURVEY OF OIL FLOATING STORAGE VESSELS FIXED AT ANCHORAGE

GUIDELINES FOR SURVEY OF OIL FLOATING STORAGE VESSELS FIXED AT ANCHORAGE GUIDANCE NOTES GD03-2017 CHINA CLASSIFICATION SOCIETY GUIDELINES FOR SURVEY OF OIL FLOATING STORAGE VESSELS FIXED AT ANCHORAGE 2017 Effective from 1 March 2017 BEIJING Chapter 1 GENERAL 1.1 Application

More information

Cover Page for Lab Report Group Portion. Pump Performance

Cover Page for Lab Report Group Portion. Pump Performance Cover Page for Lab Report Group Portion Pump Performance Prepared by Professor J. M. Cimbala, Penn State University Latest revision: 02 March 2012 Name 1: Name 2: Name 3: [Name 4: ] Date: Section number:

More information

Rules Practice Exam 5

Rules Practice Exam 5 1 BOTH INTERNATIONAL & INLAND Vessel "A" (towing) and vessel "B" are meeting as shown. In this situation, which statement is TRUE? Diagram 12 A. Both vessels should alter course to starboard and pass port

More information

Cook Inlet pipeline crossing is about making the best choices

Cook Inlet pipeline crossing is about making the best choices Cook Inlet pipeline crossing is about making the best choices By Larry Persily lpersily@kpb.us Aug. 26, 2015 (This update, provided by the Kenai Peninsula Borough mayor s office, is part of an ongoing

More information

IAPMO GUIDE CRITERIA FOR BALL VALVES IAPMO IGC PURPOSE

IAPMO GUIDE CRITERIA FOR BALL VALVES IAPMO IGC PURPOSE INTERNATIONAL ASSOCIATION OF PLUMBING AND MECHANICAL OFFICIALS IAPMO GUIDE CRITERIA FOR BALL VALVES IAPMO IGC 157-20067 1 PURPOSE 1.1 The purpose of this standard is to establish an acceptable standard

More information

PERKFILTER. Inspection and Maintenance Guide

PERKFILTER. Inspection and Maintenance Guide PERKFILTER Inspection and Maintenance Guide PerkFilter Media Filtration System Description The PerkFilter is a stormwater treatment device used to remove pollutants from urban runoff. Impervious surfaces

More information

APPENDIX M DREDGED MATERIAL MANAGEMENT PLAN (DMMP) FINAL INTEGRATED FEASIBILITY REPORT AND ENVIRONMENTAL ASSESSMENT

APPENDIX M DREDGED MATERIAL MANAGEMENT PLAN (DMMP) FINAL INTEGRATED FEASIBILITY REPORT AND ENVIRONMENTAL ASSESSMENT APPENDIX M DREDGED MATERIAL MANAGEMENT PLAN (DMMP) Brazos Island Harbor, Texas Channel Improvement Study FINAL INTEGRATED FEASIBILITY REPORT AND ENVIRONMENTAL ASSESSMENT This page is intentionally left

More information

NOTES ON WATER HAMMER. 55

NOTES ON WATER HAMMER. 55 NOTES ON WATER HAMMER. 55 NOTES ON WATER HAMMER. By A. B. Robison. When the flow conditions of a liquid in a pipe line are varied by the opening or closing of a valve or the equivalent, a change in the

More information

3.9 Marine Transportation

3.9 Marine Transportation 3.9 Marine Transportation 3. Affected Environment and Environmental Analysis 3.9 Marine Transportation 3.9.1 Introduction This section describes existing marine vessel transportation within the Port, the

More information

VRS Assembly & Operating Instructions

VRS Assembly & Operating Instructions VRS Assembly & Operating Instructions Models VRS-18 Pn #270003 VRS-24 Pn #270006 VRS-30 Pn #270010 Not for use on pressure vessels equipped with Automatic exhaust valve (680 controls) EMPIRE ABRASIVE EQUIPMENT

More information

Doors in watertight bulkheads of cargo ships and passenger ships

Doors in watertight bulkheads of cargo ships and passenger ships (June 2002) (Rev.1 Oct 2018) Doors in watertight bulkheads of cargo ships and passenger ships Application This unified interpretation pertains to doors 1 located in way of the internal watertight subdivision

More information

References: Manual Chapt. 9 ISO 9001 par.7 ISO par. 4 ISM Code par. 7; 8

References: Manual Chapt. 9 ISO 9001 par.7 ISO par. 4 ISM Code par. 7; 8 SQEMS OPERATING PROCEDURE OP-SAF-03 1 of 5 References: Manual Chapt. 9 ISO 9001 par.7 ISO 14001 par. 4 ISM Code par. 7; 8 1. SCOPE This Procedure establishes criteria for the control and management of

More information

OIL IN NAVIGABLE WATERS REGULATIONS [L.N. 101 of 1968.] under sections 5 and 7. [22nd April, 1968] [Comrnencernent.]

OIL IN NAVIGABLE WATERS REGULATIONS [L.N. 101 of 1968.] under sections 5 and 7. [22nd April, 1968] [Comrnencernent.] OIL IN NAVIGABLE WATERS REGULATIONS [L.N. 101 of 1968.] under sections 5 and 7 [Comrnencernent.] [22nd April, 1968] 1. Short title and interpretation (1) These Regulations may be cited as the Oil in Navigable

More information

Anchoring Is Important

Anchoring Is Important BCC Sailing Classes - Third Theory Anchoring Anchoring Is Important 1 The Anchor is your last resort. Anchoring Keep off a lee shore. Needs to be shaped (type of anchor) to bury in the type of bottom for

More information

OIL SUPPLY SYSTEMS ABOVE 45kW OUTPUT 4.1 Oil Supply

OIL SUPPLY SYSTEMS ABOVE 45kW OUTPUT 4.1 Oil Supply OIL SUPPLY SYSTEMS ABOVE 45kW OUTPUT 4.1 Oil Supply 4.1.1 General The primary function of a system for handling fuel oil is to transfer oil from the storage tank to the oil burner at specified conditions

More information

Wexford Harbour. Yachting Guide. Navigation

Wexford Harbour. Yachting Guide. Navigation Wexford Harbour Yachting Guide Navigation This document supersedes all previous editions. Approvals: Yacht Club Committee April, 2015 Wexford Board of Directors April, 2015 # Date Section Revision 1 6.5.2015

More information

Chart Features Maritime maps and Admiralty charts have these features:

Chart Features Maritime maps and Admiralty charts have these features: Introduction to Charts A chart or map of the area is an important safety item to carry on board. It allows the Master to obtain knowledge of the area to be travelled, and indicates the navigable channels

More information

Plot the Path into the Harbor

Plot the Path into the Harbor Plot the Path into the Harbor By Mary Anne Otten, Rudyard Area Schools and Joan Chadde, Michigan Technological University Subject/Grade: Grade 3 6, Math, Social Studies, Science Duration: 35 minutes Lesson

More information

TECHNICAL DATA Q= C. Table 1 - Specifications

TECHNICAL DATA Q= C. Table 1 - Specifications September 25, 2013 Pressure Regulation 537a 1. Description The Model B-3 Pilot Operated Pressure Control Valve is a factory assembled unit. The unit consists of a Model J-2 Halar coated Flow Control Valve,

More information

Inflatable Packer Single & Double. Single & Double Packer Dimension. Wireline Packer. Water Testing Packer (WTP) Packer

Inflatable Packer Single & Double. Single & Double Packer Dimension. Wireline Packer. Water Testing Packer (WTP) Packer Inflatable Packer Single & Double Single & Double Packer Dimension Wireline Packer Water Testing Packer (WTP) Packer Packer Working Pressure & Depth Chart Packer Water Hand Pump Packer Air Driven Pump

More information

DIVERLESS SUBSEA HOT TAPPING OF PRODUCTION PIPELINES

DIVERLESS SUBSEA HOT TAPPING OF PRODUCTION PIPELINES DIVERLESS SUBSEA HOT TAPPING OF PRODUCTION PIPELINES Dale Calkins Senior Project Engineer, TD Williamson Inc Biography Dale Calkins joined TD Williamson Inc in November of 1999 after working as a consulting

More information

Code of Federal Regulations

Code of Federal Regulations Page 1 of 6 Code of Federal Regulations Title 33 - Navigation and Navigable Waters Volume: 2 Date: 2010-07-01 Original Date: 2010-07-01 Title: Section 165.1325 - Regulated Navigation Areas; Bars Along

More information

The content of this resource has been generously provided by the AGC Houston, the Associated General Contractors of America.

The content of this resource has been generously provided by the AGC Houston, the Associated General Contractors of America. Construction & Utilities Division Planning Tools The content of this resource has been generously provided by the AGC Houston, the Associated General Contractors of America. Guidelines for Creation of

More information

Float Operated Level Controllers

Float Operated Level Controllers CONTENTS Float Operated Level Controllers IM0015 Nov. 2014 PAGE Introduction 1 Scope 1 Description 1 Specification 1 Control Installation 2 INTRODUCTION Side Mount Back Mount Prior to installing, the instructions

More information

INADVERTENT RETURN PLAN FOR HORIZONTAL DIRECTIONAL DRILLING (HDD)

INADVERTENT RETURN PLAN FOR HORIZONTAL DIRECTIONAL DRILLING (HDD) INADVERTENT RETURN PLAN FOR HORIZONTAL DIRECTIONAL DRILLING (HDD) FACILITY OPERATOR: NextEra Energy Resources, LLC 700 Universe Boulevard Juno Beach, FL 33408 For Horizontal Directional Drilling Contents

More information

Learn more at

Learn more at Full scale model tests of a steel catenary riser C. Bridge 1, H. Howells 1, N. Toy 2, G. Parke 2, R. Woods 2 1 2H Offshore Engineering Ltd, Woking, Surrey, UK 2 School of Engineering, University of Surrey,

More information

Standard Operating and Maintenance Instructions for Pumping System Model PS-150

Standard Operating and Maintenance Instructions for Pumping System Model PS-150 Standard Operating and Maintenance Instructions for Pumping System Model PS-150 High Pressure Equipment Company, LLC 2955 West 17th Street, Suite 6 PO Box 8248 Erie, PA 16505 USA 814-838-2028 (phone) 814-838-6075

More information

Towing Officers' Assessment Record: Near Coastal/Oceans

Towing Officers' Assessment Record: Near Coastal/Oceans Towing Officers' Assessment Record: Near Coastal/Oceans NAME: LICENSE NO.: Task No. Considered Proficient Common Element Task or Duty DE's Initials Date A. Vessel Familiarization A.1. X Locate and demonstrate

More information

Provisions for Moorings

Provisions for Moorings Provisions for Moorings Tasman Resource Management Plan Summary Guide No. 11 Current: July 2013 1. Introduction Structures and occupation of the coastal marine area (CMA) are managed to control the location

More information

Preventing Damage to Harbour Facilities and. Ship Handling in Harbours PART 2 INDEX

Preventing Damage to Harbour Facilities and. Ship Handling in Harbours PART 2 INDEX Preventing Damage to Harbour Facilities and Ship Handling in Harbours PART 2 INDEX 1 Vessel handling is based on the basic knowledge that a vessel floats in the water and returns to its original position

More information

GUIDANCE NOTICE. Unpowered Barges. Definition. General. Risk assessment. Application. Safety Management. Compliance

GUIDANCE NOTICE. Unpowered Barges. Definition. General. Risk assessment. Application. Safety Management. Compliance GUIDANCE NOTICE Unpowered Barges Definition Unpowered Barge - a vessel that is not propelled by mechanical means and is navigated by a powered vessel that moves it by pushing or towing. General This notice

More information

CLARIFICATION PAPER DREDGED MATERIAL VOLUME ESTIMATES

CLARIFICATION PAPER DREDGED MATERIAL VOLUME ESTIMATES CLARIFICATION PAPER DREDGED MATERIAL VOLUME ESTIMATES Prepared by Hiram Arden (Corps of Engineers), David Fox (Corps of Engineers) and Ted Benson (DNR) for the PSDDA agencies. INTRODUCTION In a PSDDA sediment

More information

Guide for Evaluating Your Hose Assembly Supplier

Guide for Evaluating Your Hose Assembly Supplier Guide for Evaluating Your Hose Assembly Supplier Supplier Evaluation Checklist, and How to Clearly Define Application Requirements Safe, reliable hose assemblies require appropriate specification work

More information

Order no. 939 of 27 November 1992 on the protection of submarine cables and submarine pipelines (the Cable Order)

Order no. 939 of 27 November 1992 on the protection of submarine cables and submarine pipelines (the Cable Order) Order no. 939 of 27 November 1992 on the protection of submarine cables and submarine pipelines (the Cable Order) Pursuant to Section 5(4) and Section 6(3) of the Act on Safety of Navigation, cf. Consolidated

More information

"FALL PROTECTION IN CONSTRUCTION ENVIRONMENTS"

FALL PROTECTION IN CONSTRUCTION ENVIRONMENTS MAJOR PROGRAM POINTS "FALL PROTECTION IN CONSTRUCTION ENVIRONMENTS" Part of the "CONSTRUCTION SAFETY KIT" Series Quality Safety and Health Products, for Today...and Tomorrow OUTLINE OF MAJOR PROGRAM POINTS

More information

BUTTERFLY VALVES Series 800

BUTTERFLY VALVES Series 800 BUTTERFLY VALVES Series 800 WARNING Before proceeding read ALL instructions and become familiar with the equipment and associated drawings. Follow ALL applicable safety regulations and codes for pressurized

More information

NATURAL GAS MAINTENANCE. Part 192 Subpart "M"

NATURAL GAS MAINTENANCE. Part 192 Subpart M NATURAL GAS MAINTENANCE Part 192 Subpart "M" CONTACT INFORMATION Pamela West Pipeline Safety Specialist U.S. Department of Transportation PHMSA Inspector Training and Qualifications Main: (405) 686-2310

More information

CLASS D - SENSITIVE LEAK TEST GAS AND BUBBLE METHOD. 1.1 To provide definitive requirements for PNEUMATIC pressure testing of piping systems.

CLASS D - SENSITIVE LEAK TEST GAS AND BUBBLE METHOD. 1.1 To provide definitive requirements for PNEUMATIC pressure testing of piping systems. Page 1 of 7 CLASS D - SENSITIVE LEAK TEST GAS AND BUBBLE METHOD 1. SCOPE 1.1 To provide definitive requirements for PNEUMATIC pressure testing of piping systems. 1.2 The piping system as used herein is

More information

Protectingpipelinesfor

Protectingpipelinesfor 24 Protectingpipelinesfor Michael Paulin, Damien Humby and Joseph Cocker, INTECSEA Canada, and Glenn Lanan, INTECSEA Inc., describe the process of trenching for the protection of pipelines in ice environments.

More information

HORIZONTAL BLADDER TANK

HORIZONTAL BLADDER TANK Balanced Pressure Proportioning System Reliable Foam System Requiring Only Water Power Perfect For Low Ceilings UL Listed, ASME, National Board Registered Bladder-UL162 Approved, High Tensile Pressure

More information