APPENDIX A ACTIVITY HAZARD ANALYSIS FORMS

Size: px
Start display at page:

Download "APPENDIX A ACTIVITY HAZARD ANALYSIS FORMS"

Transcription

1 HydroGeoLogic, Inc. Site Safety & Health Plan Fritzsche Army Airfield Fire Drill Area Former Fort Ord, California APPENDIX A ACTIVITY HAZARD ANALYSIS FORMS U.S. Army Corps of Engineers Appendix A.doc HydroGeoLogic, Inc. 8/2/04

2 HydroGeoLogic, Inc. Site Safety & Health Plan Fritzsche Army Airfield Fire Drill Area Former Fort Ord, California This appendix is reserved for activity hazard analysis forms which set forth the tasks, hazards and control measures to provide safe work practices for operations at the project site. NOTE: EACH ACTIVITY MUST BE REANALYZED FOR EACH DELIVERY ORDER Groundwater Sampling Mobilization Drilling Soil Sampling Well Installation Decontamination of Equipment Disposition of Investigation Derived Waste Demobilization Excavation and Trenching Installation of Groundwater Extraction Treatment Systems Groundwater Extraction Treatment System O&M U.S. Army Corps of Engineers Appendix A.doc HydroGeoLogic, Inc. 8/2/04

3 ACTIVITY: Groundwater Sampling Reviewed By: Mary Ann Heaney PRINCIPAL STEPS POTENTIAL SAFETY / HEALTH HAZARDS RECOMMENDED CONTROLS Staging equipment Slip, trip, and fall hazards Heavy lifting Falling objects Flying debris, dirt, dust, etc. Pinch points Fire Contact with moving equipment/vehicles Bees, spiders and snakes Cut hazards Chemical exposure Determine best access route before transporting equipment. Good housekeeping, keep work area picked up and clean as feasible. Continually inspect the work area for slip, trip and fall hazards. Look before you step, insure safe and secure footing. Use proper lifting techniques. Lifts greater than 60 pounds require assistance or mechanical equipment; size up the lift. Stay alert and clear of materials suspended overhead. Wear hard hat and steel toes boots. Use safety glasses/goggles. Ensure that eye wash is in good working order. Keep hands, fingers, and feet clear of moving/suspended materials and equipment. Beware of contact points. Stay alert at all times. Fire extinguishers shall be suitably placed, distinctly marked, readily accessible, and maintained in a fully charged and operable condition. All flammable liquids will be transported in UL/FM approved containers and sources of ignition will be prohibited. Work area will be barricaded/demarcated. Equipment will be laid out in a area free of traffic flow. Inspect work area carefully and avoid placing hands and feet into concealed areas. Wear adequate hand protection. Use care when handling glassware. Initial real time air monitoring will take place. Proper use of PPE. Label all containers as to contents and disposes of properly.

4 ACTIVITY: Groundwater Sampling Reviewed By: Mary Ann Heaney PRINCIPAL STEPS POTENTIAL SAFETY / HEALTH HAZARDS RECOMMENDED CONTROLS Staging equipment (continued) Sample collection Chemical exposure (continued) Noise Electrical shock Bees spiders and snakes Cross-contamination and contact with potentially contaminated materials Cut hazards Chemical exposure Strains/sprains Spills/residual materials Obtain Material Safety Data Sheets for solvents, etc. that are being used. Sound levels above 85 dba mandates hearing protection. All electrical circuits will be de-energized and locked out. Inspect work areas carefully and avoid placing hands and feet into concealed areas. Sampling technicians will wear proper protective clothing and equipment to safeguard against potential contamination. Only essential personnel will be in the work area. Initial real-time air monitoring will take place before and during sampling activities. All personnel will follow good hygiene practices. Proper decontamination procedures will be followed. All liquids and materials used for decontamination will be contained and disposed of in accordance with Federal, State and Local regulations. Use care when handling glassware. Wear adequate hand protection. Label all containers as to contents. Proper use of PPE. Use the proper tool for the job being performed. Get assistance if needed. Avoid twisting/turning while pulling tools, grates, manway covers, etc. Absorbent materials and containers will be kept available where leaks or spills may occur.

5 ACTIVITY: Groundwater Sampling Reviewed By: Mary Ann Heaney PRINCIPAL STEPS POTENTIAL SAFETY / HEALTH HAZARDS RECOMMENDED CONTROLS Sample collection (continued) Lighting Unattended worker Adequate lighting will be provided to insure a safe work environment. Buddy System Visual contact will be maintained with the sampling technician during sampling activities. Equipment decontamination Chemical exposure Maintain MSDS for all chemicals such as methanol or hexane and follow protection procedures. Moving and shipping collected samples Heavy lifting Pinch points Cut hazards Chemical exposure Use proper lifting techniques. Lifts of greater than 60 pounds require assistance or mechanical equipment; size up the lift. Keep hands, fingers, and feet clear of moving/suspended materials and equipment. Beware of contact points. Stay alert at all times Wear adequate hand protection. Use care when handling glassware. Label all containers as to contents and associated hazards. Equipment To Be Used Inspection Requirements Training Requirements Hand tools PPE Sampling equipment Pre-post maintenance Visual prior to use Tailgate Safety Meeting Site specific orientation Hazardous waste operations Hazard communication

6 ACTIVITY: Mobilization Reviewed By: Mary Ann Heaney Installation of office and support structures Slip, trip and fall hazards Heavy lifting Falling objects Flying debris, dirt, dust, etc., Noise Pinch points Fire Vehicle traffic Determine best access route before transporting equipment. Good Housekeeping, keep work area picked up and clean as feasible. Continually inspect the work area for slip, trip and fall hazards. Look before you step, ensure safe and secure footing. Use proper lifting techniques. Lifts greater than 60 lbs. Require assistance or mechanical equipment; size-up the lift. Hardhat, stay alert and clear of materials suspended overhead, steel-toed boots. Use safety glasses/goggles. Ensure that the eye wash station is in good working order. Hearing protection is mandatory above 85 dba. Keep hands and feet clear of moving/suspended materials and equipment. Stay alert at all times. Beware of contact points. Fire extinguishers shall be suitably placed, distinctly marked, readily accessible and maintained in a fully charged and operable condition. Fire lanes providing access to all areas shall be established and maintained free of obstruction (the minimum space between one-story non-fire-resistant buildings shall be 20 feet). Initial survey of the suitability and effectiveness of fire prevention and protection measures and facilities at each installation shall be made by competent persons. Fuel will be transported and stored in approved containers. Pay attention at all times. Wear high visibility clothing. Make sure that operators of vehicles know that you are near their equipment.

7 ACTIVITY: Mobilization Reviewed By: Mary Ann Heaney Installation of office support structures (continued) Vehicle traffic (continued) A spotter will aid in the backing of all vehicles with poor rear visibility. Work area will be barricaded/demarcated. Contact with utilities Cut hazards Biological hazards Hazardous plants (poison oak, sumac, ivy), insects, snakes, etc. Flood potentials Toilets Heat Stress High winds Hazard communication Above and underground utilities shall be located. A qualified person shall install required utilities in compliance with national, state, and local codes. Wear adequate hand protection. Inspect work area carefully and avoid placing hands or feet into concealed areas. Be alert for bees, spiders, ticks and snakes. Remove vegetation, identify hazardous plants, insects, etc. Check meteorology/climatology of the area. Look for any history of flooding. Chemical toilets provided in accordance with the SSHP. Refer to the appropriate section of the SSHP. Mobile/portable facilities shall be anchored to withstand high winds. Label all containers as to contents (fuel cans, etc.). Obtain Material Safety Data Sheets for materials brought on site. Mobilization of trailers Contact with potentially contaminated materials Strains and sprains Driving over soft ground No exclusion zone activities are associated with this task. Use the proper tool for the job being performed. Make initial visual check. Level ground and spread gravel if needed. Apply gravel if needed to prevent mud or standing water. Loader (if used for spreading of grading) must meet all safety requirements.

8 ACTIVITY: Mobilization Reviewed By: Mary Ann Heaney Mobilization of trailers (continued) Level/Blocking trailer, driving stakes (stabilization) anchoring Setting steps in place Electric shock Ventilation Use caution when jacking and placing blocks or cribbing. If ground is soft, add stone to secure footing. Steps must be OSHA-approved (with proper handrails, mid-rail, steps, with a platform in front of the door. Refer to USACE Section 21.E 02, 05, 07, 08). Lighting for work and means of egress; electrical hookup to trailers to be made by qualified electrician, GFCIs required on all circuits. Trailer ventilation shall not bring in exhaust from vehicles, etc. EQUIPMENT TO BE USED INSPECTION REQUIREMENTS TRAINING REQUIREMENTS Hand tools PPE Heavy Equipment Vendor trucks Pre/post maintenance Visual prior to use Tailgate Safety Meeting Site specific orientation Hazard communication

9 ACTIVITY: Drilling Reviewed By: Mary Ann Heaney Drilling/boring Slip, trip, and fall hazards Strains and sprains, heavy lifting Falling objects Flying debris, dirt, dust, etc. Noise Pinch points Good housekeeping, keep work area picked up and as clean as feasible. Continually inspect the work area for slip, trip and fall hazards. Use proper lifting techniques, lifts greater than 60 pounds require assistance or mechanical equipment; size up the lift. Hardhat, stay alert and clear of materials suspended overhead, steel-toed boots. Use safety glasses/goggles. Ensure that the eye wash station is in good working order. Noise levels above 85 dba mandates hearing protection. Keep feet and hands clear of moving/suspended materials and equipment. Beware of contact points. Stay alert at all times. Contact with overhead power lines Minimum overhead clearance shall be in accordance with Table 3.4. Fire Underground utilities Open excavations Cuts Traffic Driving over soft ground Contact with poison oak The drill rig or boring rig will be equipped with at least one dry chemical fire extinguisher having a minimum UL rating of 1A5BC. All underground utilities will be located prior to excavating. HydroGeoLogic, Inc. Corporate HSP Procedure 6. 4 Barricading for Work Site Protection will be adhered to at all times. Wear adequate hand protection. Work area will be barricaded off. Personnel will wear high visibility vests for high visibility. Make initial visual check. Apply gravel if needed to prevent mud or standing water. Level ground with loader and spread gravel is necessary. Conduct visual inspection prior to work.

10 ACTIVITY: Drilling Reviewed By: Mary Ann Heaney Drilling/boring (continued) Contact with poison oak (continued) Contact with contaminated materials Contact with drilling equipment Wear PPE. Decon with soap if needed. Personnel will wear appropriate PPE for the operation. This may include chemical resistant gloves, boot covers, splash suit. Before any machinery or mechanized equipment is placed into service, it shall be inspected and tested by a competent mechanic and certified to be in safe operating condition. Equipment shall be inspected before being placed into service and at the beginning of each shift. Preventive maintenance procedures recommended by the manufacturer shall be followed. A lockout-tagout procedure shall be used for equipment found to be faulty or undergoing maintenance. Only qualified personnel shall operate machinery and mechanized equipment. Machinery or equipment requiring an operator shall not be permitted to run unattended. Machinery or equipment will not be operated in a manner that will endanger persons or property nor will the safe operating speeds or loads be exceeded. All machinery or equipment will be shut down and positive means taken to prevent its operation while repairs or manual lubrications are being done. All repairs on machinery or equipment will be made at a location that provides protection from traffic for repairpersons. Maintain eye contact with drill operator when entering zone of operation. Establish work zone around drill rig. All mobile equipment shall be equipped with a back-up alarm.

11 ACTIVITY: Drilling Reviewed By: Mary Ann Heaney EQUIPMENT TO BE USED INSPECTION REQUIREMENTS TRAINING REQUIREMENTS Hand tools Pipe Heavy equipment Pre-post maintenance Visual prior to use Client required form Tailgate safety meetings Site specific orientation Hazardous waste operations

12 ACTIVITY: Soil Sampling Reviewed By: Mary Ann Heaney Staging equipment Slip, trip, and fall hazards Heavy lifting Falling objects Flying debris, dirt, dust, etc. Pinch points Fire Contact with moving equipment/vehicles Bees, spiders and snakes Cuts Determine best access route before transporting equipment. Good housekeeping, keep work area picked up and clean as feasible. Continually inspect the work area for slip, trip and fall hazards. Look before you step, insure safe and secure footing. Use proper lifting techniques. Lifts greater than 60 pounds require assistance or mechanical equipment; size up the lift. Stay alert and clear of materials suspended overhead. Wear hardhat and steel toes boots. Use safety glasses/goggles. Ensure that the eye wash station is in good working order. Noise Sound levels above 85 dba mandates hearing protection. Keep hands, fingers, and feet clear of moving/suspended materials and equipment. Beware of contact points. Stay alert at all times. Fire extinguishers shall be suitably placed, distinctly marked, readily accessible, and maintained in a fully charged and operable condition. All flammable liquids will be transported in UL/FM approved containers and sources of ignition will be prohibited. Work areas will be barricaded/demarcated. Equipment will be laid out in an area free of traffic flow. Wear high visibility clothing. Inspect work area carefully and avoid placing hands and feet into concealed areas. Wear adequate hand protection. Use care when handling glassware.

13 ACTIVITY: Soil Sampling Reviewed By: Mary Ann Heaney Staging equipment (continued) Sample collection Chemical exposure Noise Electrical shock Bees, spiders and snakes Cross-contamination and contact with potentially contaminated materials Cut hazards Chemical exposure Strains/sprains Initial real time air monitoring will take place. Label all containers as to contents and disposes of properly. Obtain Material Safety Data Sheets for solvents, etc. that are being used. Proper use of PPE. Sound levels above 85 dba mandates hearing protection. All non-essential electrical circuits will be de-energized and locked out. Inspect work areas carefully and avoid placing hands and feet into concealed areas. Sampling technicians will wear appropriate PPE in accordance with the SSHP. Only essential personnel will be in the work area. Initial real-time air monitoring will take place before and during sampling activities. All personnel will follow good hygiene practices. Proper decontamination procedures will be followed. All liquids and materials used for decontamination will be contained and disposed of in accordance with Federal, State and Local regulations. Use care when handling glassware. Wear adequate hand protection. Label all containers as to contents. Use the proper tool for the job being performed. Get assistance if needed. Avoid twisting/turning while pulling tools, grates, manway covers, etc.

14 ACTIVITY: Soil Sampling Reviewed By: Mary Ann Heaney Sample collection (continued) Spills/residual materials Lighting Unattended worker Absorbent materials and containers will be kept available where leaks or spills may occur. Adequate lighting will be provided to insure a safe work environment. Buddy System Visual contact will be maintained with the sampling technician during sampling activities. Equipment decontamination Chemical exposure Maintain MSDS for all chemicals such as methanol or hexane and follow protection procedures. Moving and shipping collected samples Heavy lifting Pinch points Cut hazards Chemical exposure Use proper lifting techniques. Lifts of greater than 60 pounds require assistance or mechanical equipment; size up the lift. Keep hands, fingers, and feet clear of moving/suspended materials and equipment. Beware of contact points. Stay alert at all times. Wear adequate hand protection. Use care when handling glassware. Label all containers as to contents and associated hazards. EQUIPMENT TO BE USED INSPECTION REQUIREMENTS TRAINING REQUIREMENTS Hand tools PPE Sampling equipment Pre-post maintenance Visual prior to use Tailgate Safety Meeting Site specific orientation Hazardous waste operations Hazard communication

15 ACTIVITY: Well Installation Analyzed By: Mike Lawson Staging equipment Slip, trip, and fall hazards Heavy lifting Falling objects Flying debris, dirt, dust, etc. Pinch points Fire Contact with moving equipment/vehicles Bees, spiders and snakes Determine best access route before transporting equipment. Good housekeeping, keep work area picked up and clean as feasible. Continually inspect the work area for slip, trip and fall hazards. Look before you step, insure safe and secure footing. Use proper lifting techniques. Lifts greater than 60 pounds require assistance or mechanical equipment; size up the lift. Stay alert and clear of materials suspended overhead. Wear hardhat and steel toes boots. Use safety glasses/goggles. Ensure that the eye wash station is in good working order. Noise Sound levels above 85 dba mandates hearing protection. Keep hands, fingers, and feet clear of moving/suspended materials and equipment. Beware of contact points. Stay alert at all times. Fire extinguishers shall be suitably placed, distinctly marked, readily accessible, and maintained in a fully charged and operable condition. All flammable liquids will be transported in UL/FM approved containers and sources of ignition will be prohibited. Work areas will be barricaded/demarcated. Equipment will be laid out in an area free of traffic flow. Wear high visibility clothing. Inspect work area carefully and avoid placing hands and feet into concealed areas.

16 ACTIVITY: Well Installation Analyzed By: Mike Lawson Staging equipment (continued) Well installation Cuts Chemical exposure Open excavations Noise Drilling equipment operations Wear adequate hand protection. Use care when handling glassware. Initial real time air monitoring will take place. Label all containers as to contents and disposes of properly. Obtain Material Safety Data Sheets for solvents, etc. that are being used. HydroGeoLogic Inc Health and Safety Program Procedure 6.4 Barricading for Work Site Protection will be adhered to at all times. Noise levels above 85 dba mandates hearing protection. Refer to Activity Hazard Analysis for Drilling. EQUIPMENT TO BE USED INSPECTION REQUIREMENTS TRAINING REQUIREMENTS Hand tools Pipe Heavy equipment Pre-post maintenance Visual prior to use Client required form Tailgate safety meetings Site specific orientation Hazardous waste operations Hazard communication

17 ACTIVITY HAZARD ACTIVITY: Decontamination of Equipment Reviewed by: Mary Ann Heaney Movement to DECON area Noise Contact with heavy equipment Contact with potentially contaminated materials Noise levels above 85 dba mandates hearing protection. A lockout-tagout procedure shall be used for equipment found to be faulty or undergoing maintenance. Only designated personnel shall operate machinery and mechanized equipment. Getting off or on any equipment while it is in motion is prohibited. Machinery or equipment requiring an operator shall not be permitted to run unattended. Machinery or equipment will not be operated in a manner that will endanger persons or property nor will the safe operating speeds or loads be exceeded. All machinery or equipment will be shut down and positive means taken to prevent its operation while decontamination is being done. Bulldozer and scraper blades, end-loader buckets, and similar equipment will be either fully lowered or blocked when being repaired or when not in use. All mobile equipment shall be equipped with a back-up alarm. Real time air monitoring will take place. Proper personal protective clothing and equipment will be utilized. Good housekeeping will be stressed to safe guard against cross contamination of surrounding areas and eliminate safety hazards. All site personnel will practice good personal hygiene. The work area will be demarcated. All unnecessary personnel will be kept out of the work area and in an upwind location. Refer to SSHSP for chemical hazard discussion. Wear proper PPE.

18 ACTIVITY HAZARD ACTIVITY: Decontamination of Equipment Reviewed by: Mary Ann Heaney Movement to DECON area Pressure Washing Strains and sprains, heavy lifting Cut hazards/cuts Eye Injuries Burns Good housekeeping, keep work area picked up and as clean as feasible. Continually inspect the work area for slip, trip and fall hazards. Use proper lifting techniques, lifts greater than 60 pounds require assistance or mechanical equipment; size up the lift. Keep feet and hands clear of moving/suspended materials and equipment. Beware of contact points. Stay alert at all times. Wear adequate hand protection. Work area will be barricaded off to prevent entry by unauthorized individuals. Leg and metatarsal guards shall be worn. All connections shall be inspected prior to use of pressure equipment. Verification of the proper pressure shall be made prior to use of the equipment. LO/TO shall be used is work on the system must be performed. Safety glasses or goggles AND a face shield shall be worn. Rain suits or suits of equivalent material shall be worn to prevent direct contact with hot water. Decontamination or washing of PPE while on a person is prohibited. EQUIPMENT TO BE USED INSPECTION REQUIREMENTS TRAINING REQUIRMENTS Hand tools PPE Heavy equipment Dump Trucks Pre-post maintenance Visual prior to use Client required form Tailgate Safety Meeting Site specific orientation Hazardous waste operation

19 ACTIVITY: Disposition of Investigation Derived Waste Analyzed By: Mike Lawson Staging equipment Slip, trip, and fall hazards Heavy lifting Falling objects Flying debris, dirt, dust, etc. Pinch points Fire Contact with moving equipment/vehicles Bees, spiders and snakes Cuts Determine best access route before transporting equipment Good housekeeping, keep work area picked up and clean as feasible. Continually inspect the work area for slip, trip and fall hazards. Look before you step, insure safe and secure footing. Use proper lifting techniques. Lifts greater than 60 pounds require assistance or mechanical equipment; size up the lift. Stay alert and clear of materials suspended overhead. Wear hardhat and steel toes boots. Use safety glasses/goggles. Ensure that the eye wash station is in good working order. Noise Sound levels above 85 dba mandates hearing protection. Keep hands, fingers, and feet clear of moving/suspended materials and equipment. Beware of contact points. Stay alert at all times. Fire extinguishers shall be suitably placed, distinctly marked, readily accessible, and maintained in a fully charged and operable condition. All flammable liquids will be transported in UL/FM approved containers and sources of ignition will be prohibited. Work areas will be barricaded/demarcated. Equipment will be laid out in an area free of traffic flow. Inspect work area carefully and avoid placing hands and feet into concealed areas. Wear adequate hand protection. Use care when handling glassware.

20 ACTIVITY: Disposition of Investigation Derived Waste Analyzed By: Mike Lawson Staging equipment (continued) Sample collection Chemical exposure Hazard communication Noise Electrical shock Bees, spiders and snakes Cross-contamination and contact with potentially contaminated materials Cuts Chemical Exposure Strains/sprains Initial real time air monitoring will take place. Wear appropriate PPE. Label all containers as to contents and disposes of properly. Obtain Material Safety Data Sheets for solvents, etc. that are being used. Sound levels above 85 dba mandates hearing protection. All non-essential electrical circuits will be de-energized and locked out. Inspect work areas carefully and avoid placing hands and feet into concealed areas. Sampling technicians will wear appropriate PPE in accordance with the SSHP. Only essential personnel will be in the work area. Initial real-time air monitoring will take place before and during sampling activities All personnel will follow good hygiene practices. Proper decontamination procedures will be followed. All liquids and materials used for decontamination will be contained and disposed of in accordance with Federal, State and Local regulations. Use care when handling glassware. Wear adequate hand protection. Label all containers as to contents. Wear PPE. Use the proper tool for the job being performed. Get assistance if needed.

21 ACTIVITY: Disposition of Investigation Derived Waste Analyzed By: Mike Lawson Sample collection (continued) Strains/sprains (continued) Spills/residual materials Lighting Unattended worker Avoid twisting/turning while pulling tools, grates, manway covers, etc. Absorbent materials and containers will be kept available where leaks or spills may occur. Adequate lighting will be provided to insure a safe work environment. Buddy System Visual contact will be maintained with the sampling technician during sampling activities. Equipment decontamination Chemical exposure Maintain MSDS for all chemicals such as methanol or hexane and follow protection procedures. Moving and shipping collected samples Heavy lifting Pinch points Cut hazards Hazard communication Use proper lifting techniques. Lifts of greater than 60 pounds require assistance or mechanical equipment; size up the lift. Keep hands, fingers, and feet clear of moving/suspended materials and equipment. Beware of contact points. Stay alert at all times. Wear adequate hand protection. Use care when handling glassware. Label all containers as to contents and associated hazards. EQUIPMENT TO BE USED INSPECTION REQUIREMENTS TRAINING REQUIREMENTS Hand tools PPE Sampling equipment Pre-post maintenance Visual prior to use Tailgate Safety Meeting Site specific orientation Hazardous waste operations Hazard communication

22 Activity: Demobilization Reviewed by: Mary Ann Heaney Removal of office and support structures Heavy lifting Noise Falling Objects Flying debris, dirt, dust etc. Pinch points Fire Vehicle traffic Contact with utilities Slip, trip, and fall hazards Cut hazards Use proper lifting techniques. Lifts greater than 60 pounds require assistance or mechanical equipment; size up the lift. Hearing protection is mandatory above 85 dba. Hardhat, stay alert and clear of materials suspended overhead, Steel toed boots required. Safety glasses/eye wash. Keep hands and feet clear of moving/suspended materials and equipment. Stay alert at all times. Beware of contact points. Fire extinguishers shall be suitably placed, distinctly marked, readily accessible, and maintained in a fully charged and operable condition. Pay attention at all times. Wear high visibility vest. Make sure that operators of vehicles know that you are near their equipment. A spotter will aid in the backing of all vehicles with poor rear visibility. Above and underground utilities shall be located. A qualified person shall install required utilities in compliance with national state, and local codes. Determine best access route before transporting equipment. Good housekeeping, keep work area picked up and clean as feasible. Continually inspect the work area for slip, trip, and fall hazards. Look before you step, ensure safe and secure footing. Wear adequate hand protection.

23 Activity: Demobilization Reviewed by: Mary Ann Heaney Biological hazards Inspect work area carefully and avoid placing hands or feet into concealed areas. Be alert for bees, spiders, ticks, and snakes. Removal of office and support structures (Continued) Demobilization of trailers Contact with poison oak. Toilets (sanitary) Heat stress Fuel Contact with moving equipment/vehicles Contact with potentially contaminated materials Strains and sprains Unattended worker Driving over soft ground Removing/Blocking trailer, stakes and anchoring Conduct visual inspection prior to work. Wear PPE. Decon with soap if needed. Chemical toilets provided in accordance with this SSHP. Refer to Section 4.0 of the SSHP Fuel will be transported and stored in approved containers. Work area will be barricaded/demarcated. No Exclusion Zone activities are associated with this task. Use the proper tool for the job being performed. Get assistance if needed. Avoid twisting/tuning while pulling on tools, materials, etc. Buddy System visual contact will be maintained between personnel performing site activities. Make initial visual check. Level ground with loader and spread gravel. Apply gravel if needed to prevent mud or standing water. Loader (if used for spreading or grading) must meet all safety requirements. Use caution when jacking and removing blocks or cribbing. If ground is soft, add stone to secure footing.

24 Activity: Demobilization Reviewed by: Mary Ann Heaney EQUIPMENT TO BE USED INSPECTION REQUIREMENTS TRAINING REQUIREMENTS Hand tools PPE Heavy equipment Vendor trucks Pre-post maintenance Visual prior to use Tailgate Safety Meeting Site specific orientation Hazard communication

25 ACTIVITY: Excavation and Trenching Reviewed By: Mary Ann Heaney Excavation Underground utilities Open excavations Noise Contact with heavy equipment All underground utilities will be located prior to excavating. HydroGeoLogic Inc Corporate HSP procedure 6.2 Excavation and Trenching Procedures will be adhered to at all times. Noise levels above 85 dba mandates hearing protection. Before any machinery or mechanized equipment is placed into service, it shall be inspected and tested by a competent mechanic and certified to be in safe operating condition. Equipment shall be inspected before being placed into service and at the beginning of each shift. Preventive maintenance procedures recommended by the manufacturer shall be followed. A lockout-tagout procedure shall be used for equipment found to be faulty or undergoing maintenance. Machinery and mechanized equipment shall be operated only by designated personnel. Getting off or on any equipment while it is in motion is prohibited. Machinery or equipment requiring an operator shall not be permitted to run unattended. Machinery or equipment will not be operated in a manner that will endanger persons or property nor will the safe operating speeds or loads be exceeded. All machinery or equipment will be shut down and positive means taken to prevent its operation while repairs or manual lubrications are being done. All repairs on machinery or equipment will be made at a location which provides protection from traffic for repairpersons. Bulldozer and scraper blades, end-loader buckets, and similar equipment will be either fully lowered or blocked when being repaired or when not in use and whenever the operator leaves the machine.

26 ACTIVITY: Excavation and Trenching Reviewed By: Mary Ann Heaney Excavation (continued) Contact with heavy equipment (continued) All mobile equipment shall be equipped with a back-up alarm. Maintain eye contact with the operator at all times. Use spotter if necessary. Establish a work zone around equipment that protects personnel from swing radius. Contact with overhead power lines See overhead clearances in SSHP Table 3-5. Fire Slip, trip, and fall hazards Pinch points Strains and sprains, heavy lifting Cut hazards Traffic Each bulldozer, backhoe, or other similar equipment will be equipped with at least one dry chemical fire extinguisher having a minimum UL rating of 1A5BC. Good housekeeping, keep work area picked up and as clean as feasible. Continually inspect the work area for slip, trip and fall hazards. Keep feet and hands clear of moving/suspended materials and equipment. Beware of contact points. Stay alert at all times. Use proper lifting techniques, lifts greater than 60 pounds require assistance or mechanical equipment; size up the lift. Wear adequate hand protection. Work area will be barricaded off. EQUIPMENT TO BE USED INSPECTION REQUIREMENTS TRAINING REQUIREMENTS Hand tools PPE Heavy equipment Pre-post maintenance Visual prior to use Client required form Tailgate Safety Meetings Site specific orientation Hazardous waste operations

27 ACTIVITY: Installation of Groundwater Extraction Treatment Systems Developed by: Mary Ann Heaney PRINCIPAL STEPS POTENTIAL SAFETY/HEALTH HAZARDS RECOMMENDED CONTROLS Installation of piping system Heavy Lifting Falling Objects Flying debris, dirt, dust, etc. Slip trip and fall hazards Cuts Heat Stress Contact with poison oak. Contact with heavy equipment Use proper lifting techniques. Lifts greater than 60 lbs require assistance or mechanical equipment. Size up the lift. Hardhat, stay alert and clear of materials suspended overhead, steel toed boots. Safety Glasses/eyewash. Determine bust access route before transporting equipment. Good housekeeping, keep work area picked up and clean as feasible. Continually inspect the work area for slip, trip and fall hazards. Wear adequate hand protection. Wear loose fitting, light colored clothing. Drink adequate water. Inspect work area visually. Wear PPE. Decon with soap if necessary. Before any machinery of mechanized equipment is placed into service, it shall be inspected and tested by a competent operator/mechanic and certified to be in safe operating condition. Only designated personnel shall operate machinery and mechanized equipment. Getting off or on any equipment while it is in motion is prohibited. Machinery of equipment requiring an operator shall not be permitted to run unattended. All mobile equipment shall be equipped with backup alarms.

28 ACTIVITY: Installation of Groundwater Extraction Treatment Systems Developed by: Mary Ann Heaney PRINCIPAL STEPS POTENTIAL SAFETY/HEALTH HAZARDS RECOMMENDED CONTROLS Installation of piping system (continued) Installation of electrical units and pumps Driving over soft ground Failure of ropes, chains, slings, cables Ropes, slings, chains and hooks, elevated loads Use of welding torches Contact with electrical current. Failure of ropes, chains, slings, cables Heavy Lifting Make initial visual check. Ensure another vehicle available for assistance. Daily inspections of all lift equipment shall be performed. Rigging equipment shall not be loaded in excess of its recommended safe working load. Work or travel under elevated loads shall not be permitted. Taglines shall be used to control the loads being handled by hoisting equipment. Obtain a Hot Work Permit. Store and use compressed gases properly. Install radiation shields when welding in close proximity to other individuals. Ensure tat a fire extinguisher is in the immediate area. Follow Lockout/Tagout/Tryout Procedures when testing or starting equipment. Daily inspections of all lift equipment shall be performed. Rigging equipment shall not be loaded in excess of its recommended safe working load. Work or travel under elevated loads shall not be permitted. Use proper lifting techniques. Lifts greater than 60 lbs require assistance or mechanical equipment. Size up the lift.

29 ACTIVITY: Installation of Groundwater Extraction Treatment Systems Developed by: Mary Ann Heaney EQUIPMENT TO BE USED INSPECTION REQUIREMENTS TRAINING REQUIREMENTS Heavy equipment Hand tools Welding/cutting equipment When equipment brought on site and before placed into operation Tailgate safety meeting each morning and as needed through the day Equipment operators must have proper authorization for the equipment they are using. Electricians must be certified to perform the work they are assigned.

30 ACTIVITY: Groundwater Extraction Treatment System O&M Analyzed By: Mary Ann Heaney PRINCIPAL STEPS POTENTIAL SAFETY/HEALTH HAZARDS RECOMMENDED CONTROLS Routine system operation and general maintenance Maintenance requiring system shutdown Heavy Lifting Falling Objects Flying debris, dirt, dust, etc. Slip trip and fall hazards Cut hazards Heat Stress Unexpected system activation Exposure to hazardous materials Use proper lifting techniques. Lifts greater than 60 lbs require assistance or mechanical equipment. Size up the lift. Hardhat, stay alert and clear of materials suspended overhead, steel toed boots. Safety Glasses/eyewash. Determine bust access route before transporting equipment. Good housekeeping, keep work area picked up and clean as feasible. Continually inspect the work area for slip, trip and fall hazards. Wear adequate hand protection. Wear loose fitting, light colored clothing. Drink adequate water. Implement Lock Out/Tag Out procedures in accordance with HydroGeoLogic, Inc. Corporate HSP Policy 6.3. Before any machinery of mechanized equipment is placed into service, it shall be inspected and tested by a competent operator/mechanic and certified to be in safe operating condition Machinery and mechanized equipment shall be operated only by designated personnel. Getting off or on any equipment while it is in motion is prohibited. Machinery of equipment requiring an operator shall not be permitted to run unattended. Initial monitoring of air in the breathing zone shall be performed before disconnecting any piping or appurtenances. Direct measurement of vapor concentrations within system equipment shall be performed immediately upon opening or disconnecting any system equipment. Proper use of PPE.

31 ACTIVITY: Groundwater Extraction Treatment System O&M Analyzed By: Mary Ann Heaney PRINCIPAL STEPS POTENTIAL SAFETY/HEALTH HAZARDS RECOMMENDED CONTROLS Maintenance requiring system shutdown (continued) Driving over soft ground Contact with poison oak. Electric shock Make initial visual check. Level ground with loader and spread gravel is necessary. Apply gravel if needed to prevent mud or standing water. Conduct visual inspection prior to work. Wear PPE. Decon with soap if needed. Lighting for work and means of egress; electrical hookup to trailers to be made by qualified electrician, GFCIs required on all circuits. EQUIPMENT TO BE USED INSPECTION REQUIREMENTS TRAINING REQUIREMENTS Heavy equipment Hand tools Welding/cutting equipment When equipment brought on site and before placed into operation Tailgate safety meeting each morning and as needed through the day OSHA 40 hour Hazardous Waste Training and 8 Hour Refresher as needed Equipment operators must have proper authorization for the equipment they are using.

Activity Hazard Analysis. Final Review: Dr. R. Von Burg

Activity Hazard Analysis. Final Review: Dr. R. Von Burg Appendix C Activity Hazard Analysis Mobilization/ Demobilization Physical injury from heavy equipment; heavy lifting, pinch points; slip, trip, and fall hazards Brush Clearing Cuts, slashes, dismemberment.

More information

Basewide Site Safety and Health Plan Former Fort Ord, California

Basewide Site Safety and Health Plan Former Fort Ord, California Appendix C Activity Hazard Analyses Revision 8 Basewide Site Safety and Health Plan Former Fort Ord, California LIST OF ACTIVITY HAZARD ANALYSIS (AHAs) Number Description 1 Underground Storage Tank Removal

More information

Job Hazard Analysis. JHA No. FBP-JHA Revision No. Draft General or Job-Specific Description of Work

Job Hazard Analysis. JHA No. FBP-JHA Revision No. Draft General or Job-Specific Description of Work JHA No. FBP-JHA-14-0014 Revision No. Draft General or Job-Specific Description of Work Clean X230 Outlet Basin Site Location PORTS Activity or Area Name Not listed Facility or Project [Unspecified] Specific

More information

CONTRACTOR SAFETY RULES

CONTRACTOR SAFETY RULES CONTRACTOR SAFETY RULES CONTRACTOR SAFETY RULES AND REGULATIONS This manual sets forth policy with regards to contractor safety. Each Quinn facility consists of one or several diverse operations under

More information

Job Hazard Analysis. University of Washington Seattle Campus Facilities Services Campus Engineering & Operations Seattle, WA 98195

Job Hazard Analysis. University of Washington Seattle Campus Facilities Services Campus Engineering & Operations Seattle, WA 98195 Job Hazard Analysis University of Washington Seattle Campus Facilities Services Campus Engineering & Operations Seattle, WA 98195 Working Job Title: Utility Worker 2 (CEO) JHA Completed by Date: The Job

More information

Risk Management Resources

Risk Management Resources Risk Management Resources Machine Guarding Name: Notes: Electrical Systems: Fire Prevention Are circuit breakers accessible to personnel, protected from physical damage, and located away from ignitable

More information

CONSTRUCTION HEALTH AND SAFETY MANAGEMENT SYSTEM BASELINE HIRA

CONSTRUCTION HEALTH AND SAFETY MANAGEMENT SYSTEM BASELINE HIRA RECOMMENDED ADDITIONAL CONTROLS TASK / ACTIVITY/ EQUIPMENT/ FACILITY HAZARDS UNWANTED EVENT MINIMUM CONTROLS REQUIRED RISK NO. LIKELI-HOOD CONSE-QUENCE RISK VALUE Project Risk Assessment Page 1 of 16 All

More information

SAFETY POLICY AND PROCEDURE MANUAL QUESTIONNAIRE

SAFETY POLICY AND PROCEDURE MANUAL QUESTIONNAIRE The following questionnaire is designed to aid us in the creation of your policy and procedure manual. Please place a checkmark in the boxes that correspond to the sections that you would like to be included

More information

WORKPLACE SAFETY INSPECTIONS TABLE OF CONTENTS INTRODUCTION...2 OBJECTIVE...2 REFERENCES...2 PREREQUISITES...2 PRECAUTIONS...2 CHECKLISTS...

WORKPLACE SAFETY INSPECTIONS TABLE OF CONTENTS INTRODUCTION...2 OBJECTIVE...2 REFERENCES...2 PREREQUISITES...2 PRECAUTIONS...2 CHECKLISTS... REVISION 0 PAGE 1 OF 8 TABLE OF CONTENTS SECTION PAGE INTRODUCTION...2 OBJECTIVE...2 REFERENCES...2 PREREQUISITES...2 PRECAUTIONS...2 CHECKLISTS...2 PROCEDURE...3 Responsibilities...3 Work Area Safety

More information

Lockout/Tagout - Energy Control Program

Lockout/Tagout - Energy Control Program Lockout/Tagout - Energy Control Program Lockout and Tagging of ELECTRICAL Circuits This portion of the K.R. Miller Contractors, Inc. safety program has been created to maintain a written copy of procedures

More information

Safe Work Method Statement LRB TREE SERVICES 6 Behland St, Kearneys Spring QLD, 4350 ABN

Safe Work Method Statement LRB TREE SERVICES 6 Behland St, Kearneys Spring QLD, 4350 ABN JOB NO: PROJECT: DATE: 1/1/2018 SWMS NO: SWMS 001.1 PREPARED BY: LUKE BLINCO REVISED BY: ACTIVITY: TREE REMOVAL & PRUNING SIGNED BY: REVISION DATE: MINIMUM PERSONAL PROTECTIVE EQUIPMENT (PPE) REQUIREMENTS

More information

7 Hazard assessment 8 Worker participation 9 Hazard elimination and control

7 Hazard assessment 8 Worker participation 9 Hazard elimination and control This document is a guideline only. Employers have a responsibility of assessing all applicable occupational health and safety legislation, for the tasks they are performing. Businesses in this industry

More information

Operation of Embrey Excavator Shears Safe Work Procedure PTES_HSE_SWP_039. Name Date Signature. Author Jarred Hearle 27/11/2015

Operation of Embrey Excavator Shears Safe Work Procedure PTES_HSE_SWP_039. Name Date Signature. Author Jarred Hearle 27/11/2015 Operation of Embrey Excavator Shears Safe Work Procedure PTES_HSE_SWP_039 Name Date Signature Author Jarred Hearle 27/11/2015 Reviewed FMG Site Team 27/11/2015 ---------- Approved Geoff Selfe 27/11/2015

More information

Staffing Services Client Evaluation Form

Staffing Services Client Evaluation Form Staffing Services Client Evaluation Form Client Name: Location: Contact(s): Completed By: A Safety Performance Experience Modification Factor? OSHA 300 Logs Available? # Of Injuries/Illnesses? Types of

More information

EMA, Inc. SITE SAFETY PLAN

EMA, Inc. SITE SAFETY PLAN EMA, Inc. SITE SAFETY PLAN A. SITE DESCRIPTION JOB NAME: JOB NUMBER: DATE: PLAN REVISION NUMBER: SITE ADDRESS: Additional Site / Project Information: B. SCOPE OF WORK 1. 2. 3. 4. 5. 6. C. ONSITE ORGANIZATION

More information

Self Inspection Checklist

Self Inspection Checklist Self Inspection Checklist Name: Date: Job Name: Title: Time: Job Number: Instructions: Review each lettered subpart under each section that you are responsible for completing. If you have inspected all

More information

PERSONAL PROTECTIVE EQUIPMENT

PERSONAL PROTECTIVE EQUIPMENT 13.0 The purpose of this program is to ensure that, where applicable, the appropriate and necessary personal protective equipment (PPE) is selected and provided to employees to protect from illness or

More information

Operations: HSE. Health and Industrial Hygiene. Laboratory Safe Work Practice

Operations: HSE. Health and Industrial Hygiene. Laboratory Safe Work Practice Operations: HSE Health and Industrial Hygiene Laboratory Safe Work Practice Page 2 of 8 AMENDMENT RECORD Amendment Date Revision Number Revision Number 08/11/2016 4 Authority: Health Manager Custodian:

More information

ELECTRICAL (COMPREHENSIVE) SAFETY PROGRAM REGULATORY STANDARD: OSHA - 29 CFR CFR , ,

ELECTRICAL (COMPREHENSIVE) SAFETY PROGRAM REGULATORY STANDARD: OSHA - 29 CFR CFR , , ELECTRICAL (COMPREHENSIVE) SAFETY PROGRAM REGULATORY STANDARD: OSHA - 29 CFR 1910.331 335-29 CFR 1926.302, 1926.416, 1926.417 BASIS: The National Safety Council estimates that there are at least 300 deaths

More information

1b. Slipping; tripping; getting knocked into by pedestrians.

1b. Slipping; tripping; getting knocked into by pedestrians. MAINTAINING AND REPAIRING HYDRAULIC AND TRACTION PASSENGER AND FREIGHT ELEVATORS AND HANDICAP EQUIPMENT Activity Hazard Identification Required Precautions 1. Walking to and from work site. 1a. Back ache;

More information

Omega Safety Training, Inc Hwy 6 North, Ste. 207 Houston, Texas Ph:

Omega Safety Training, Inc Hwy 6 North, Ste. 207 Houston, Texas Ph: Omega Safety Training, Inc. 4654 Hwy 6 North, Ste. 207 Houston, Texas 77084 Ph: 281-979-4849 Email: Chad@omegasafetytraining.com Training Syllabus: P.E.C. 24 Hour Core Compliance SafeLand USA & SafeGulf

More information

U.S. CONCRETE, INC. SAFETY POLICY and PROCEDURE MANUAL

U.S. CONCRETE, INC. SAFETY POLICY and PROCEDURE MANUAL SAFE -14 Page 1 of 8 U.S. CONCRETE, INC. SAFETY POLICY and PROCEDURE MANUAL FUNCTION Safety TOPIC Hotwork Permit Program OBJECTIVE(S): GENERAL POLICY: To provide a work atmosphere that is conducive to

More information

Industry Code: Alberta Small Employer OHS Legislated Requirements

Industry Code: Alberta Small Employer OHS Legislated Requirements This document is a guideline only. Employers have a responsibility of assessing all applicable occupational health and safety legislation, for the tasks they are performing. Services in this industry can

More information

Hazard Identification and Risk Assessment Form. Risk Assessment

Hazard Identification and Risk Assessment Form. Risk Assessment Identification and Assessment Form Assessment Tool & Machine Work General Various injuries (including potential fatalities) All staff complete safety induction programme at the start of the module. instructed

More information

Lockout/Tagout Safety Policy

Lockout/Tagout Safety Policy University of North Carolina Wilmington Environmental Health & Safety Workplace Safety Lockout/Tagout Safety Policy GENERAL The UNCW Environmental Health & Safety Department (EH&S) is authorized by UNCW

More information

EMPLOYEE SAFETY ORIENTATION - PHYSICAL PLANT, RESIDENCE

EMPLOYEE SAFETY ORIENTATION - PHYSICAL PLANT, RESIDENCE Name Department Initial Orientation Date Supervisor Review Instructions: Check off each section once you have read and discussed it with your Supervisor. EMPLOYEE SAFETY ORIENTATION - PHYSICAL PLANT, RESIDENCE

More information

Site Safety Inspection Checklist

Site Safety Inspection Checklist Site Safety Inspection Checklist Assess your project s safety program based using criteria from AECOM s SH&E Management System. Location: Business Group: Business Unit: Prepared by (name/title): Project:

More information

University of Vermont Department of Physical Plant Personal Protective Equipment Program

University of Vermont Department of Physical Plant Personal Protective Equipment Program University of Vermont Department of Physical Plant Personal Protective Equipment Program REVISED AND DISTRIBUTED BY: THE UNIVERSITY OF VERMONT DEPARTMENT OF PHYSICAL PLANT TRAINING AND COMPLIANCE OFFICE

More information

Identify, evaluate and assess workplace improvements to reduce hazards. Provide personal protective equipment based on hazard assessment

Identify, evaluate and assess workplace improvements to reduce hazards. Provide personal protective equipment based on hazard assessment PAGE 1 OF 7 1.0 INTRODUCTION The purpose of this program is to help employees work safely in their environments by identifying and assessing workplace hazards, eliminating or reducing the hazards where

More information

CENTRAL PLANT HEATING/CHILLED WATER OPERATOR Ref. Code: C-WO-4

CENTRAL PLANT HEATING/CHILLED WATER OPERATOR Ref. Code: C-WO-4 CENTRAL PLANT HEATING/CHILLED WATER OPERATOR Ref. Code: C-WO-4 OPERATING OF AUXILIARY EQUIPMENT Activity Hazard Identification Required Precautions 1. Inspecting boilers. 1a. Slipping on oily or wet floor.

More information

The purpose of this document is to establish the procedures for accident prevention and investigation at (Insert Company Name) jobsites.

The purpose of this document is to establish the procedures for accident prevention and investigation at (Insert Company Name) jobsites. CORPORATE SAFETY MANUAL ENVIRONMENTAL, HEALTH AND SAFETY STANDARDS TITLE: Document Number: * Issue Date: Revision Date: * 1 Purpose The purpose of this document is to establish the procedures for accident

More information

BOILER MECHANIC//SR. BOILER MECHANIC

BOILER MECHANIC//SR. BOILER MECHANIC WORKING IN STEAM MANHOLES Activity Hazard Identification Required Precautions 1. Driving to and from work site. 1. Motor vehicle accident; striking pedestrians, bicyclists, or individuals using rollerblades.

More information

Compliance Requirements

Compliance Requirements Compliance Requirements The compliance requirements for OSHA s Personal Protective Equipment regulations are very straightforward, and logical. GENERAL REQUIREMENTS (29 CFR 1910.132) The general OSHA Personal

More information

CONFINED SPACE PROGRAM

CONFINED SPACE PROGRAM CONFINED SPACE PROGRAM A confined space, as defined in 29 CFR 1910.146: Is large enough and so configured that an employee can bodily enter and perform assigned work AND Has limited or restricted means

More information

Safety Powder Spray Systems

Safety Powder Spray Systems Instruction Sheet P/N 107 952C Safety Powder Spray Systems 1. Introduction This section contains general safety instructions for using your Nordson equipment. Task- and equipment-specific warnings are

More information

Personal commitments you can live and work by:

Personal commitments you can live and work by: Personal commitments you can live and work by: I anticipate possible dangers in any given operation and make every effort to analyze and avoid them before starting work, including immediately communicating

More information

OFFICE OF STATE HUMAN RESOURCES

OFFICE OF STATE HUMAN RESOURCES OFFICE OF STATE HUMAN RESOURCES NUMBER: PPE-1 TOTAL PAGES: 8 SUBJECT: Personal Protective Equipment Program Effective Date: Revision Date: Revision #: RELATED LEGISLATION: The purpose of this program is

More information

PALM BEACH STATE COLLEGE PERSONAL PROTECTIVE EQUIPMENT (PPE) JOB HAZARD ASSESSMENT

PALM BEACH STATE COLLEGE PERSONAL PROTECTIVE EQUIPMENT (PPE) JOB HAZARD ASSESSMENT PALM BEACH STATE COLLEGE PERSONAL PROTECTIVE EQUIPMENT (PPE) JOB HAZARD ASSESSMENT Department: Facilities Campus: All Task: Replace a Light Ballast Job Title(s) Performing Task: Electrician, Maintenance

More information

Minimum Safety Requirements for Contractors Working on Railway Property

Minimum Safety Requirements for Contractors Working on Railway Property Minimum Safety Requirements for Contractors Working on Railway Property Effective_ April 1, 2007 Introduction Canadian Pacific is committed to provide a Safe and Healthy working environment for all Railway

More information

Personal Protective Equipment 29 CFR 1926

Personal Protective Equipment 29 CFR 1926 Personal Protective Equipment 29 CFR 1926 OSHA- PPE http://www.osha.gov/publications/osha31 51.html NIOSH s Protective Clothing Web Page http://www.cdc.gov/niosh/npptl/topics/prot clothing/ 1926.95 PPE

More information

Collision Repair Shop Inspection Checklist

Collision Repair Shop Inspection Checklist Collision Repair Shop Inspection Checklist Note: This is a sample inspection chesklist only, and may mot include all appropriate inspection items. The Occupational Health and Safety Regulation specifies

More information

CUSTODIAL Safety Inspection Checklist

CUSTODIAL Safety Inspection Checklist CUSTODIAL Safety Inspection Checklist Priority 1 Any condition which is life-threatening, or may cause injury, or permanent disability Priority 2 Any condition which may cause serious, but non-disabling

More information

Compressed Gases and Cryogens

Compressed Gases and Cryogens Compressed Gases and Cryogens University of Tennessee Safety Guide HM-011 Document Contact: EHS Date effective: January 1, 2009 Revision Date: October 1, 2015 Purpose This guideline adheres to the Occupational

More information

Orchard Farm Fire Protection District Standard Operating Procedure

Orchard Farm Fire Protection District Standard Operating Procedure Orchard Farm Fire Protection District Standard Operating Procedure Division: 200 Emergency Operations Section: 202 Fire & Rescue Subject: Supersedes: N/A Approved By: Page: 1 of 6 Date Last Reviewed: N/A

More information

LAKE ARROWHEAD COMMUNITY SERVICES DISTRICT STANDARD OPERATING PROCEDURES FACILITY SAFETY The following procedures are to be used by all District employees when working in the District facilities or with

More information

PALM BEACH STATE COLLEGE PERSONAL PROTECTIVE EQUIPMENT (PPE) JOB HAZARD ASSESSMENT

PALM BEACH STATE COLLEGE PERSONAL PROTECTIVE EQUIPMENT (PPE) JOB HAZARD ASSESSMENT 1. De-energize circuit serving the outlet following LOTO procedure (see pages 3 5). PALM BEACH STATE COLLEGE PERSONAL PROTECTIVE EQUIPMENT (PPE) JOB HAZARD ASSESSMENT Department: Facilities Campus: All

More information

OSHA Federal Standards October 1, 2016 September 30, 2017

OSHA Federal Standards October 1, 2016 September 30, 2017 OSHA Federal Standards October 1, 2016 September 30, 2017 29 CFR 1926 SUBPARTS 29 CFR 1926. C M L L E M M E X M MOST FREQUENTLY CITED SERIOUS VIOLATIONS IN CONSTRUCTION 2017.501(b)(13) FALL PROTECTION

More information

A Health & Safety Risk Management Tool that you can use today. Scott Norman, CIH, CSP Health & Safety Program Manager Bay West LLC

A Health & Safety Risk Management Tool that you can use today. Scott Norman, CIH, CSP Health & Safety Program Manager Bay West LLC A Health & Safety Risk Management Tool that you can use today Scott Norman, CIH, CSP Health & Safety Program Manager Bay West LLC I m a safety geek What are the hazards of your work environment? Who is

More information

LO/TO LOCKOUT/TAGOUT PROGRAM

LO/TO LOCKOUT/TAGOUT PROGRAM LO/TO LOCKOUT/TAGOUT PROGRAM April 2017 CONTENTS Section 1: Introduction...1 Section 2: Purpose... 1 Section 3: Application... 1 Section 4: Definitions... 2 Section 5: Roles and Responsibilities... 4 Section

More information

Job Hazard/Safety Analysis For the Electrician

Job Hazard/Safety Analysis For the Electrician Job Hazard/Safety Analysis For the Electrician 1 INTRODUCTION Job Hazard/Safety Analysis for the Electrician is a partial list of known task performed by the professional electrician. We have placed known

More information

QUEENSLAND UNIVERSITY OF TECHNOLOGY

QUEENSLAND UNIVERSITY OF TECHNOLOGY QUEENSLAND UNIVERSITY OF TECHNOLOGY SITE SPECIFIC SAFETY MANAGEMENT PLAN FOR SAMFORD HOUSE SAMFORD ECOLOGICAL RESEARCH FACILITY SAMFORD VALLEY 2007 Dylan Randall SN: 06305466 dylan.randall@student.qut.edu.au

More information

Doc No: WELDHOT Midland Engineering Co., Inc. Initial Issue Date 12/14/15 Safety Management System

Doc No: WELDHOT Midland Engineering Co., Inc. Initial Issue Date 12/14/15 Safety Management System Revision Preparation: Safety Mgr Authority: President Issuing Dept: Safety Page: Page 1 of 7 PURPOSE To provide guidelines for the safe operation of welding, cutting and hot work of equipment, and to itemize

More information

Temporary load-bearing support for structural alterations or repairs

Temporary load-bearing support for structural alterations or repairs CRITICAL NOTE This document only becomes a Safe Work Method Statement where the High Risk Construction Work section of this document is completed Company: ABN: Contact Person: Ph: Project/Site: Principal

More information

Removing Frozen Clips

Removing Frozen Clips Removing Frozen Clips Warning You cannot undertake this activity in the rail corridor unless you have completed a pre work brief and work site protection plan. Reference should also be made to the Protocol

More information

techconnect CARPENTRY Objectives Unit 2 Workplace Safety TechConnect - STUDENT WORKBOOK 2-1 Workplace Safety - Unit 2

techconnect CARPENTRY Objectives Unit 2 Workplace Safety TechConnect - STUDENT WORKBOOK 2-1 Workplace Safety - Unit 2 Unit 2 Workplace Safety techconnect One of the keys to working in any industry is the safety and health of the workers. The carpentry industry can be a dangerous industry in which to work if you do not

More information

Safe Work Method Statement

Safe Work Method Statement Company Name: Safe Work Method Statement Site Address: Other Details: Contractor: Activity/Trade: Electrician Date: TASKS List the tasks required to perform the activity in sequence carried out. Entry

More information

Pannier Corporation Health and Safety Handbook Marking System Group Aerial Lifts Original Date: Section: Revision date: Page: 12/5/ of 11

Pannier Corporation Health and Safety Handbook Marking System Group Aerial Lifts Original Date: Section: Revision date: Page: 12/5/ of 11 12/5/2013 37 1 of 11 1.0 Overview Aerial lifts are commonly used in construction, inspection, athletic events and repair services to lift Pannier employees to an elevated work position. Proper operation

More information

SAFE WORK METHOD STATEMENT

SAFE WORK METHOD STATEMENT SAFE WORK METHOD STATEMENT WATER PUMP - PETROL Prepared for Client: Rural Construction & Maintenance Pty Ltd Project No: 1 Site: 660 Great Ocean Road, Bellbrae Date Prepared: 29/07/2015 1. RESPONSIBILITIES

More information

ISD #535 Rochester Public Schools

ISD #535 Rochester Public Schools ISD #535 Rochester Public Schools Health & Safety Office Maintenance Service Building 10 9½ St SE Rochester, MN 55904 507-328-4507 Management Plan for Machine Guarding Modification Date Document Modification

More information

Health & Safety Policy and Procedures Manual SECTION 6 ELECTRICAL SAFETY / CONTROL OF HAZARDOUS ENERGY

Health & Safety Policy and Procedures Manual SECTION 6 ELECTRICAL SAFETY / CONTROL OF HAZARDOUS ENERGY SECTION 6 ELECTRICAL SAFETY / CONTROL OF HAZARDOUS ENERGY 1. CONTROL OF HAZARDOUS ENERGY POLICY AND PROCEDURES A. OSHA References: 29 CFR 1910.147, 29 CFR 1910.332, 29 CFR 1910.333, 29 CFR 1926.417 B.

More information

In an emergency the safety of all personnel and the public is of priority.

In an emergency the safety of all personnel and the public is of priority. P272 : Emergency Planning & Response This DOCUMENT and any linked FORMS have been created to provide specific requirements under the Amalgamated Operating System. For additional information and guidance,

More information

Instructions: Use this format to prepare the security plans for ACP contracts. EVERY point has to be covered; if they do not apply, write N/A.

Instructions: Use this format to prepare the security plans for ACP contracts. EVERY point has to be covered; if they do not apply, write N/A. APPENDIX F - RISK CONTROL PLAN FORMAT FOR CONTRACTORS OF THE PANAMA CANAL Instructions: Use this format to prepare the security plans for ACP contracts. EVERY point has to be covered; if they do not apply,

More information

Product Information Report Lockout/Tagout Hazardous Energy Control

Product Information Report Lockout/Tagout Hazardous Energy Control Overview A properly implemented (LOTO) program is designed to protect workers involved in the maintenance and servicing of equipment from the dangerous effects of hazardous energy caused by the unexpected

More information

How severely could the risk hurt someone? Low/Insignificant First aid

How severely could the risk hurt someone? Low/Insignificant First aid Safe Work Method Statement No: WMS-0 Task: Operate Diesel Road Saw This WMS is submitted to: Project name and site address: Contact: Preparation of WMS by: Robert Raams Company: Enwon (Australia) Pty Ltd

More information

Lockout / Tagout Safety Program

Lockout / Tagout Safety Program Lockout / Tagout Safety Program Prepared by: The Ohio State University Environmental Health and Safety Occupational Safety & Industrial Hygiene 1314 Kinnear Road Columbus, OH 43212-1168 614-292-1284 Phone

More information

Proper use of the JOB SAFETY ANALYSIS (JSA) FORM

Proper use of the JOB SAFETY ANALYSIS (JSA) FORM Safety Review & Tool Box Talk Company: Supervisor: Topic: Proper use of the JOB SAFETY ANALYSIS (JSA) FORM Participants Please Fill in this form and fax to (905) 847-1275 or scan and e-mail to tessa@camacc.com

More information

Work At Heights Toolkit. for Supervisors

Work At Heights Toolkit. for Supervisors Work At Heights Toolkit for Supervisors For Supervisors How to use this toolkit? The toolkit aims to provide information for supervisor to communicate one topic a day to workers. Pictures are for illustration

More information

WHS OHS HAZARD REGISTER (SITE AND OFFICE OPERATIONS)

WHS OHS HAZARD REGISTER (SITE AND OFFICE OPERATIONS) WHS 017 - WHS 017 Hazard Register - Version 5.0 April 20 Doc No: WHS 017 Effective Date: 04/04/20 1 WORKING WITH EARTHMOVING PLANT/ TRUCKS/SITE VEHICLES COLLISIONS OTHER PLANT EQUIPMENT SITE VEHICLES PERSONNELL

More information

Required Personal Protective Equipment (PPE) Checklist

Required Personal Protective Equipment (PPE) Checklist Required Personal Protective Equipment (PPE) Checklist When hazards are present, PPE is a necessity. PPE is clothing that is designed to protect the worker's body against occupational and safety hazards.

More information

Western Sydney University Safety Inspection Checklist - Laboratory Environments

Western Sydney University Safety Inspection Checklist - Laboratory Environments Western Sydney University Safety Inspection Checklist - Laboratory Environments Useful Hint: To maximise the benefits that can be gained from a workplace inspection activity read the Western Sydney University

More information

Contractor Hazard Identification and Control Guide

Contractor Hazard Identification and Control Guide Exposure to Asbestos Containing Materials (ACM) Accidental disturbance or removal of ACM. Asbestos Containing Materials are to be removed outside school hours. No DET employees, students or visitors are

More information

PERSONAL PROTECTIVE EQUIPMENT PROGRAM INTERNAL AND EXTERNAL PAGE: 1 DEPARTMENT: ALL OF: 5

PERSONAL PROTECTIVE EQUIPMENT PROGRAM INTERNAL AND EXTERNAL PAGE: 1 DEPARTMENT: ALL OF: 5 INTERNAL AND EXTERNAL PAGE: 1 1.0 OBJECTIVE The Federal Occupational Safety and Health Administration (OSHA) requirements for personal protective equipment (PPE) are presented in 29 CFR 1910.132 General

More information

DEPARTMENT OF THEATRE AND DANCE CALIFORNIA STATE UNIVERSITY, FULLERTON

DEPARTMENT OF THEATRE AND DANCE CALIFORNIA STATE UNIVERSITY, FULLERTON DEPARTMENT OF THEATRE AND DANCE CALIFORNIA STATE UNIVERSITY, FULLERTON SCENIC LAB SAFETY PROCEDURES (CPAC 154) 1. POLICY The Department Scenic Lab is a facility, which supports courses in scenic design

More information

A Health and Safety Tip Sheet for School Maintenance Staff. Did you know? Step 1. Identify job hazards. Step 2. Work towards solutions

A Health and Safety Tip Sheet for School Maintenance Staff. Did you know? Step 1. Identify job hazards. Step 2. Work towards solutions INSPECTION Health and CHECKLIST Safety Committees MAINTAINING SAFETY: A Health and Safety Tip Sheet for School Maintenance Staff 1 Maintenance and facilities staff members keep schools operational, safe,

More information

11/2/2017. Course Objectives. Overview

11/2/2017. Course Objectives. Overview Course Objectives The objective of this CBT module is to insure that personnel receive basic training in electrical safety. Every employee's work involves electricity. This may vary from typical electrical

More information

Laboratory Safety Review Checklist One Shields Ave Davis, CA Phone: (530) Fax: (530)

Laboratory Safety Review Checklist One Shields Ave Davis, CA Phone: (530) Fax: (530) http://safetyservices.ucdavis.edu Laboratory Safety Review Checklist One Shields Ave Davis, CA 95616 Phone: (530)752-1493 Fax: (530)752-4527 E-mail: researchsafety@ucdavis.edu U C Davis Environmental Health

More information

Electrical Safety Work Practices

Electrical Safety Work Practices Work Practices I. SCOPE This program covers any SOUTHWESTERN COMMUNITY COLLEGE employee that may work or be exposed to exposed electrical systems: To assure that employees are not exposed to potentially

More information

ANSI A Work Zone Safety for Highway Construction. Scott Schneider, CIH and Travis Parsons Laborers Health and Safety Fund of North America

ANSI A Work Zone Safety for Highway Construction. Scott Schneider, CIH and Travis Parsons Laborers Health and Safety Fund of North America ANSI A10.47-2009 Work Zone Safety for Highway Construction Scott Schneider, CIH and Travis Parsons Laborers Health and Safety Fund of North America Agenda Introductions History Overview of the Standard

More information

2. The purpose of this program is to achieve the following objectives:

2. The purpose of this program is to achieve the following objectives: Section 16A. Lockout and Tagout Program 1. In the course of their duties, personnel at the TFREC may need to secure controls, switches, and equipment in order to prevent injury caused by the sudden, unexpected

More information

Lockout / Tag out Program

Lockout / Tag out Program Lockout / Tag out Program Presented by DOSHTI www.doshti.com You will learn Purpose of Lockout- Tag out Requirements for LOTO Types of Hazardous Energy Procedures for LOTO The OSHA Standard for the Control

More information

LEVEL 2 CERTIFICATE OF COMPETENCE IN THE SAFE USE AND OPERATION OF MOBILE ELEVATED WORK PLATFORMS

LEVEL 2 CERTIFICATE OF COMPETENCE IN THE SAFE USE AND OPERATION OF MOBILE ELEVATED WORK PLATFORMS NPTC Registered Charity No. 1096429 NATIONAL AGRICULTURAL CENTRE STONELEIGH PARK, WARWICKSHIRE CV8 2LG Tel: 024 7669 6553 Fax: 024 7669 6128 Email: information@nptc.org.uk LEVEL 2 CERTIFICATE OF COMPETENCE

More information

University College Dublin Machinery/Equipment Risk Assessment Template

University College Dublin Machinery/Equipment Risk Assessment Template 1. General Information Name of Person(s) carrying out assessment and their position Principal Investigator / Supervisor / Head of School or Unit (Person responsible for ensuring safety) Date of assessment

More information

PERSONAL PROTECTIVE EQUIPMENT SAFETY PROGRAM

PERSONAL PROTECTIVE EQUIPMENT SAFETY PROGRAM PERSONAL PROTECTIVE EQUIPMENT SAFETY PROGRAM REGULATORY STANDARD: 29 CFR 1910.132-138. BASIS: This safety program establishes the requirements to ensure protective equipment is provided, where required,

More information

CITY AND COUNTY OF DENVER CR&CF RISK UNIT Job Hazard Analysis

CITY AND COUNTY OF DENVER CR&CF RISK UNIT Job Hazard Analysis CITY AND COUNTY OF DENVER CR&CF RISK UNIT 65.4.1 Job Hazard Analysis 1.0 Introduction The Job Hazard Analysis (JHA) shall be used to describe task specific hazards and to identify control measures that

More information

HAZARDOUS WASTE OPERATIONS AND EMERGENCY RESPONSE PLAN Kenyon College

HAZARDOUS WASTE OPERATIONS AND EMERGENCY RESPONSE PLAN Kenyon College HAZARDOUS WASTE OPERATIONS AND EMERGENCY RESPONSE PLAN Kenyon College PURPOSE The purpose of this Emergency Response Plan is to plan for and execute an organized response to hazardous waste spills or releases

More information

Personal Protective Equipment. Individual Unit Function: Safety Procedure No.: SOP-0147 Page: 1 of 9

Personal Protective Equipment. Individual Unit Function: Safety Procedure No.: SOP-0147 Page: 1 of 9 Procedure No.: SOP-0147 Page: 1 of 9 1. PURPOSE This procedure describes the minimum requirements concerning personal protective equipment for personnel who are exposed to areas or tasks where hazards

More information

Work Activity (e.g. Road Work): Work Location:.

Work Activity (e.g. Road Work): Work Location:. Working with Cranes Work Activity (e.g. Road Work): Work Location:. GENERAL INFORMATION Hinchinbrook Shire Council Lannercost Street Ingham Qld, 4850 ABN 46 291 971 168 Ph: 47764610 All personnel conducting

More information

FLYING OBJECTS MANUAL HANDLING EXCESSIVE NOISE

FLYING OBJECTS MANUAL HANDLING EXCESSIVE NOISE JOB NO: PROJECT: DATE: SWMS NO: SWMS 002 PREPARED BY: Ian Hartley REVISED BY: Nick Bragg & Cameron McNeil ACTIVITY: STUMP REMOVAL SUPERVISED BY: REVISION DATE: April 2016 MINIMUM PERSONAL PROTECTIVE EQUIPMENT

More information

Health and Safety Program Inspections

Health and Safety Program Inspections POLICY: It is CPP s policy to maintain a program of safety inspections. The objective of this program is to control and mitigate hazards in the workplace and worksite. All CPP s facilities and worksites

More information

Session Topics. Industrial Hygiene from an OSHA Perspective. Health Hazards in Shops. Labeling Example 1/27/2014. Shop Safety: Health & Ventilation

Session Topics. Industrial Hygiene from an OSHA Perspective. Health Hazards in Shops. Labeling Example 1/27/2014. Shop Safety: Health & Ventilation Session Topics Shop Safety: Health & Ventilation UW Extension Webinar January 28, 2014 Mary Bauer CIH, CSP Compliance Assistance Specialist Eau Claire, WI 54701 715-832-9019 1. Organization walk paths,

More information

Elements of a Lockout/Tagout Program OSHA

Elements of a Lockout/Tagout Program OSHA September 15, 2015 Elements of a Lockout/Tagout Program OSHA 1910.147 Dayna Noble Industrial Safety Consultant Specialist Ohio BWC 567-204-8917 Dayna.noble@bwc.state.oh.us Top 10 most frequently cited

More information

INDUSTRIAL - SOLVENT PARTS CLEANER

INDUSTRIAL - SOLVENT PARTS CLEANER INDUSTRIAL - SOLVENT PARTS CLEANER OPERATION & INSTRUCTION MANUAL I. Introduction A. Manufacturer s Statement CM400 This manual will provide you with important information about the Solvent Parts Cleaners

More information

Lockout Tagout Program

Lockout Tagout Program Lockout Tagout Program RIM of the World Unified School District 27315 North Bay Road Blue Jay, CA 92352 (909) 336-4100 July 2016 Safety and Risk Management Department RIM of the World Unified School District

More information

Responsibilities / Accountability

Responsibilities / Accountability Responsibilities / Accountability What we will cover Brief history of OPP safety program OPP s commitment to safety Safety responsibilities Accountability for safety Employee expectations History of Safety

More information

How severely could the risk hurt someone?

How severely could the risk hurt someone? Safe Work Method Statement No: WMS-08 Task: Install Drainage This WMS is submitted to: Project name and site address: Contact: Preparation of WMS by: Robert Raams Company: Enwon (Australia) Pty Ltd Authorised

More information

Appendix C Health and Safety Guidelines for investigators

Appendix C Health and Safety Guidelines for investigators 38 Appendix C Health and Safety Guidelines for investigators Introduction Investigations must be conducted in a safe manner. This document provides an overview of the health and safety guidelines investigators

More information

ARKANSAS TECH UNIVERSITY FACILITIES MANAGEMENT HEALTH AND SAFETY MANUAL (LOCKOUT/TAGOUT) 30.0

ARKANSAS TECH UNIVERSITY FACILITIES MANAGEMENT HEALTH AND SAFETY MANUAL (LOCKOUT/TAGOUT) 30.0 () 30.0 The purpose of the Energy Control Policy (Lockout/Tagout) is to ensure that before any employee performs any servicing and/or maintenance on machinery or equipment, where the unexpected energizing,

More information

Personal Protective Equipment

Personal Protective Equipment Northland Community & Technical College June 1, 2017 Personal Protective Equipment Safety Officer Cory Feller Chemical Hygiene Officer Kristel Kizer Telephone: 218-683-8633 1 Personal Protective Equipment

More information

CONSTRUCTION SAFETY PROGRAM FOR. Golder Acoustics Inc.

CONSTRUCTION SAFETY PROGRAM FOR. Golder Acoustics Inc. CONSTRUCTION SAFETY PROGRAM FOR Golder Acoustics Inc. TABLE OF CONTENTS Topic... Page Safety and Health Policy... 2 Safety and Health Objectives... 3 Job Site Inspections... 4 Contractor Safety Administrator...

More information

PART 4: IMPLEMENTATION & OP

PART 4: IMPLEMENTATION & OP TITLE PART 4: IMPLEMENTATION & OPERATION Prepared by: 4.2 Personal Protective Equipment (PPE) Learning Objectives To define what is Personal Protective Equipment (PPE). To describe the management & legal

More information