Detailed Provisions for

Size: px
Start display at page:

Download "Detailed Provisions for"

Transcription

1 Accession No: Detailed Provisions for SCADA SYSTEM INSTALLS AND UPGRADES, Project ID No VOLUME III - CENTRAL SECTION Project Schedule (unless amended): Bid Documents Available: Tuesday, July 24, 2012 Deadline for Questions: 1:30 PM, Tuesday, August 14, 2012 Bid Open: 1:30 PM, Tuesday, September 6, 2012 SET No.:

2 SPECIFICATIONS INDEX Master Format 2004 Description Comments Summary of Project Construction Sequence Control of Work Measurement and Payment Contract Considerations Project Meetings Site Safety Plan Construction Progress Schedule Submittals Reference Forms Installation and Erection Data Special Provisions Applicable Codes Contractor Quality Control Plan Testing Laboratory Services Temporary Facilities Delivery, Storage and Handling Material and Equipment Field Engineering Restoration of Improvements Cutting and Patching Cleaning Equipment Startup and Verification Sequence Equipment Factory Acceptance Testing Equipment Commissioning Equipment Startup System Functional Testing Process Performance Testing Process Operational Testing Contract Closeout Substantial Completion Equipment Operating and Maintenance Information Warranties and Bonds Record Documents Spare Parts and Maintenance Materials Training Commissioning Not Used Selective Electrical Demolition Cast-in-Place Concrete Not Used Unit Masonry Not Used Glazed Concrete Unit Masonry Not Used Metal Fabrications Not Used i

3 Master Format 2004 Description Comments Applied Fireproofing Not Used Penetration Firestopping Joint Sealants Not Used Hollow Metal Doors and Frames Not Used Metal Doors Not Used Door Hardware Not Used Glazing Not Used Acoustical Ceilings Not Used Painting Not Used Interior Painting Not Used High Performance Coatings Not Used Clean Agent Fire Suppression Plumbing Not Used Testing Adjusting and Balancing for HVAC Not Used HVAC Insulation Not Used Refrigerant Piping Not Used HVAC Ducts and Casings Not Used Self-Contained Air-Conditioners Not Used Split System Air-Conditioners Not Used Integrated Automation Instrumentation and Terminal Devices for Facility Equipment Low-Voltage Electrical Power Conductors and Cables Manufactured Wiring Assemblies Grounding and Bonding for Electrical Systems Hangers and Supports for Electrical Systems Raceways and Boxes for Electrical Systems Underground Duct Raceways for Electric Systems Not Used Excavation Backfill Not Used Identification for Electrical Systems Testing Not Used Electrical Power Monitoring Control Not Used Dry Type Transformers Not Used Panelboards Not Used Electrical Cabinets and Enclosures Not Used Wiring Devices Static Uninterruptible Power Supplies Uninterruptible Power Supplies Not Used Interior Lighting Not Used Grounding and Bonding for Communication Systems Hangers and Supports for Communication Systems Not Used Conduits and Backboxes for Communication Systems Not Used Cable Trays for Communication Systems ii

4 Master Format 2004 Description Comments Identification for Communication Systems Communications Services Cabling Video Surveillance System Not Used Site Preparation Not Used Earthwork Not Used Level Process Measuring Not Used Electric Actuators Not Used Programmable Logic Controllers Process Control Hardware/Software Allowance Continuous Emissions Monitoring Systems (CEMS) Not Used iii

5 THIS PAGE LEFT BLANK INTENTIONALLY iv

6 SECTION SUMMARY OF PROJECT PART 1 - GENERAL 1.01 SECTION INCLUDES A. Project Work covered by all Contract Documents B. Part 1 Electrical and Instrumentation & Controls C. Part 2 Heating, Ventilating & Air Conditioning (HVAC), Plumbing, Fire Suppression, and Mechanical D. Part 3 Not Used E. Contract Milestones and other General Provisions 1.02 RELATED DOCUMENTS A. Drawings and general provisions of the Contract Documents, and Division 1 Specification Sections including Specification Section Special Provisions, apply to this section PROJECT WORK COVERED BY ALL CONTRACT DOCUMENTS A. Work of the Project includes construction of Redundant SCADA Ethernet Network and the conversion of legacy Allen-Bradley PLC-3 system to Allen-Bradley ControlLogix PLC systems. The Work shall be performed for the CITY in accordance with the Contract Documents. The Work includes, but is not limited to, demolition, removal, replacement, installation of new equipment and/or modifications to existing equipment to the following areas and processes: North Pump Station New Grit Building Primary Sludge Pumping (E-Bldg) Return Activated Sludge (RAS) Building Secondary Sampling Building Secondary Effluent Disinfection Building Disinfection Chemical Storage Building Secondary Thickening Dewatering Server Room Dewatering Electrical Room Central Maintenance Facility Server Room Compressor Building Primary Skimmings Building SUMMARY OF PROJECT JULY 2012

7 Final Effluent Disinfection Building The Redundant SCADA Ethernet network requires a fiber optic backbone consisting of one 24- fiber cable. The fiber cable will make a loop or ring around the treatment facility. At each location where an Ethernet device or devices need to be connected to the network a Fiber Patch Panel and either a Field Network Cabinet (14 places) or a Server Switch Cabinet (2 places) must be installed. The Field Network Cabinets and/or Server Switch Cabinets require 120 Vac power. At each location a number of Ethernet devices will need to be connected to either Ring A, or Ring B, or both Ring A and Ring B. The network drawings show all devices connected to the Ethernet networks. The CONTRACTOR will route fiber through existing underground tunnels wherever possible using cable tray (preferred) or conduit. If the fiber ring is collapsed, meaning the to and from cable is run in the same cable tray the first fiber cable will be on one side of cable tray and the second fiber cable will be on the other side of the cable tray. If using conduits each fiber cable will be run in a separate conduit. Ring A fibers will be in one conduit and Ring B fiber cables will be in a separate conduit. If fiber path is to be routed outside conduits will be used. B. In the 1980 s a number of Allen-Bradley PLC-3s were installed to control the Treatment Plant. Over time most of these units have been replaced, upgraded and or modified in one way or another. This project will replace the remaining PLC-3s with Allen-Bradley ControlLogix or CompactLogix PLCs and any remaining Allen-Bradley 1771 IO will be replaced with ControlLogix PLC. The following list identifies what areas require new ControlLogix PLCs and/or CompactLogix PLCs: North Pump Station AOS-1 Panel Existing PLC-3 to be removed; a ControlLogix PLC has already been installed. North Pump Station Panel 1-1 Existing 1711 I/O to be removed and replaced Primary Sludge Pumping Panel 1-3 Existing 1771 I/O to be removed and replaced Primary Thickened Skimmings Panel Existing PLC-5 and 1771 I/O to be removed and replaced. Compressor Building AOS-2 and Panel 2-2 Existing PLC-3 and 1771 I/O to be removed and replaced. RAS Building Panel 0 and Panel 0-1 Existing PLC-3 and 1771 I/O to be removed and replaced. RAS Building Panel 2-1 Existing 1771 I/O to be removed and replaced. Gravity Thickening Existing PLC-3 and 1771 I/O to be removed. A new ControlLogix PLC has already been added. Dewatering Building AOS 4, Panel 4-1, and Panel 4-2 Existing PLC-5 and 1771 I/O to be removed and replaced ELECTRICAL INSTRUMENTATION & CONTROLS BIDDING PART 1 A. The work of to be performed under Bidding Part 1 of this section shall include all necessary SUMMARY OF PROJECT JULY 2012

8 demolition, the furnishing of all materials, equipment and tools; and performing all necessary labor and supervision, for the complete construction of the Electrical and Instrumentation Work and all other work appurtenant thereto except for work to be performed under separate Bidding Parts of this sections. The work to be performed under Bidding Part 1 of this section shall consist of the work delineated in the following Divisions of the Specifications: 1. Division 1 - General Requirements (as applicable). 2. Division 2 Selective Electrical Demolition (as applicable). 3. Division 7 Penetration Firestopping (as applicable). 4. Division 25 - Integrated Automation (as applicable). 5. Division 26 - Electrical (as applicable). 6. Division 27 - Communications (as applicable). 7. Division 40 Process Integration (as applicable). B. Work shall be performed according to contract Specifications, contract Drawings, and any supplemental installation drawings provided by the CITY. The major items of work to be performed und Part 1 shall include, but is not limited to, the following: 1. Furnish and install all equipment and perform all labor for the work outlined in specifications and shown on E Drawings, including: a. Fiber Optic Backbone b. Fiber Optic Patch Panels c. Network Field Cabinets d. New PLC Enclosures e. New PLC Backpanels f. Modifications to existing PLC Enclosures 2. Provide all conduit, cable tray, fiber optic cable, power wiring, instrumentation wiring, and control wiring to all new equipment, including power to heating and ventilation equipment. 3. Provide all conduit, fittings, supports, and pull boxes. 4. Provide anchors, sleeves, hangers, supports, inserts, seals, and other accessories required for completion of Part 1 work. SUMMARY OF PROJECT JULY 2012

9 5. Provide and install all wire and cables unless otherwise specified. 6. Provide and install all electrical control panels and perform modifications to existing control panels as outlined in E Drawings. 7. Provide all grounding as specified in Section 26 specifications. 8. Installation of firestop material for wall or floor penetrations into Electrical Rooms. 9. Perform all tests, commissioning, cleaning, and adjusting required for the successful completion of work outlined in Part Disconnection and demolition of all electrical and controls equipment, including wiring and conduit, associated with existing equipment to be abandoned or relocated as part of Part 1 work. 11. Perform overall project coordination among the Contractors for all divisions of work. 12. Removal and replacement of water based fire suppression system with new chemical fire suppression system. C. NORTH PUMP STATION 1. For the redundant Ethernet Network the CONTRACTOR will provide and install Fiber Patch Panel M2-10-N01 and Field Network Cabinet M2-10-S01 in the MCC Room. The fiber optic rings will come from Final Effluent Disinfection and continue on to Grit. Refer to drawings for fiber connection details. 2. The existing CompactLogix PLCs that control each of the 12 Raw Sewage Pumps must be connected to one of the Ethernet Network by the CONTRACTOR. In addition to each PLC there is an existing GE Multlilin for each pump, these Multilins must communicate to the CompactLogixs, to facilitate this communication path a Serial-to-Ethernet device must be installed refer to the network diagrams for details. CONTRACTOR will coordinate with ENGINEER the switchover of Ethernet devices from the existing network to the new redundant networks. 3. There are a number of GE Feeder Relays and GE Transformer Relays that the CONTRACTOR will connect to one of the networks via CONTRACTOR provided Serial-to-Ethernet gateways. Refer to the network diagrams for details. 4. CONTRACTOR will provide and install Redundant ControlLogix PLC Panel M2-10- C01. Both processor racks will be connected to both Ethernet Ring A and Ring B. The redundant ControlNet network must be extended to Panel 1-1 and AOS The Non-redundant ControlLogix PLC in AOS-1 will be converted to remote I/O racks by removing the processor and upgrading the ControlNet modules to redundant ControlNet modules. The I/O will be controlled by the redundant ControlLogix PLC in Panel M2-10- C01. CONTRACTOR to provide new redundant ControlNet modules and ControlNet SUMMARY OF PROJECT JULY 2012

10 cabling to AOS-1. CONTRACTOR will coordinate these activities with ENGINEER. 6. The existing AOS-1 panel has PLC-3, 1771 I/O, and ControlLogix PLC and ControlLogix I/O installed in it. There is no active I/O monitored or controlled by the 1771 I/O. At the end of the project CONTRACTOR will remove the PLC-3 and 1771 I/O. The ControlLogix racks will remain in place. View showing left side of AOS-1, 1171 I/O rack to be removed shown within yellow rectangle. SUMMARY OF PROJECT JULY 2012

11 PLC-3 Equipment adjacent to AOS-1 to be removed at end of project shown within yellow rectangle. 7. CONTRACTOR will provide and install I/O panel M2-10-R01 adjacent to existing Panel 1-1. CONTRACTOR to provide housekeeping pad for panel M2-10-R01 to match existing housekeeping pad of Panel 1-1. I/O modules in Panel M2-10-R01 shall be provided with pigtails of wires to connect to existing field I/O terminals in Panel 1-1. Once all existing I/O has been replaced with new ControlLogix I/O CONTRACTOR will remove the existing 1771 I/O racks with Panel 1-1. SUMMARY OF PROJECT JULY 2012

12 Inside view of Panel 1-1, 1771 I/O racks to be removed shown within yellow rectangle. 8. CONTRACTOR to provide new Ethernet cabling from new Field Network Cabinet M2-10-S01 to the following existing devices: Bar Screen 1 Bar Screen 2 Bar Screen 3 Bar Screen 4 East Odor Control Pumps Monitoring Raw Sewage Pumps 1 thru 12 CompactLogix PLCs Raw Sewage Pumps 1 thru 12 Multilins requires Serial-to-Ethernet devices Raw Sewage Pumps 4 & 10, 6 & 11/, 7 & 12 VFDs Two Tie Switch Feeder Protective Relays (GE 750) requires Serial-to-Ethernet devices Six Transformer Protective Relays requires Serial-to-Ethernet devices CONTRACTOR responsible for all cabling including serial cabling to Multilins, Feeder Protection Relays, and Transformer Protection Relays. CONTRACTOR to coordinate the switchover from the existing PLC network to the new Ethernet networks with ENGINEER. 9. CONTRACTOR to provide new Ethernet cabling from new Field Network Cabinet M2- SUMMARY OF PROJECT JULY 2012

13 10-S01 to the new redundant PLC Panel M2-10-C01 and to the North Pump Station Control Room. 10. CONTRACTOR to provide three new I/O points from Non-Potable Water System. New I/O points will be wired to field terminals in Panel 1-1, see I/O listing. CONTRACTOR to research existing wiring and determine if interposing relays are required. Provide interposing relays if required. 11. CONTRACTOR to provide two new I/O points from Seal Water System. New I/O points will be wired to field terminals in Panel 1-1, see I/O listing. CONTRACTOR to research existing wiring and determine if interposing relays are required. Provide interposing relays if required. 12. CONTRACTOR to provide fiber optic cabling between Field Network Cabinet M2-10- S01 to Septage Receiving PLC transceiver and Barrier Dam PLC transceiver both transceivers are located in the old Administration Building Network Room. D. FINAL EFFLUENT DISINFECTION 1. For the redundant Ethernet Network the CONTRACTOR will provide and install Fiber Patch Panel M2-40-N01 and Field Network Cabinet M2-40-S01 in the MCC Room. The fiber optic rings will come from Primary Skimmings Building and continue on to North Pump Station. Refer to drawings for fiber connection details. 2. CONTRACTOR to provide new Ethernet cabling from new Field Network Cabinet M2-40-S01 to the Final Effluent Disinfection PLC (M2-C51). CONTRACTOR to provide cabling to both Ring A and Ring B. CONTRACTOR to provide one additional Allen- Bradley ControlLogix Ethernet module to be installed in PLC rack. All work to be coordinated with ENGINEER. E. NEW GRIT BUILDING 1. For the redundant Ethernet Network the CONTRACTOR will provide and install Fiber Patch Panel M2-14-N01 and Field Network Cabinet M2-14-S01 in the Electrical Room. The fiber optic rings will come from North Pump Station and continue on to Primary Sludge Pumping. Refer to drawings for fiber connection details. 2. CONTRACTOR to provide new Ethernet cabling for both rings from new Field Network Cabinet M2-14-S01 to the following existing redundant ControlLogix PLCs: Main Grit PLC Grit Washers 1 and 2 PLC Grit Washers 3 and 4 PLC Grit Washers 5 and 6 PLC All work to be coordinated with ENGINEER. SUMMARY OF PROJECT JULY 2012

14 F. PRIMARY SKIMMINGS BUILDING 1. For the redundant Ethernet Network the CONTRACTOR will provide and install Fiber Patch Panel M2-23-N01 and Field Network Cabinet M2-23-S01 in the Electrical Room. The fiber optic rings will come from Compressor Building and continue on to Final Effluent Disinfection. Refer to drawings for fiber connection details. 2. CONTRACTOR to provide new Ethernet cabling for both rings from new Field Network Cabinet M2-23-S01 to the following existing ControlLogix PLCs: Primary Skimmings PLC West Odor Control PLC (Ring A only) CONTRACTOR to provide one additional Allen-Bradley ControlLogix Ethernet module to be installed in Primary Skimmings PLC rack. All work to be coordinated with ENGINEER. G. PRIMARY SLUDGE PUMPING BUILDING (E-BUILDING) 1. For the redundant Ethernet Network the CONTRACTOR will provide and install Fiber Patch Panel M2-21-N01 and Field Network Cabinet M2-21-S01on the first mezzanine level near existing Panel 1-3. The fiber optic rings will come from Grit Building and continue on to RAS Building. Refer to drawings for fiber connection details. 2. Each of the eight Primary Flocculation/Settling Tanks Collector Flights is monitored by individual Siemens PLCs. The collector flights motor starters are monitored and controlled by 1771 I/O in Panel 1-3. The PLC-5 in the Primary Thickened Skimmings Control Panel has hardwired inputs that monitor the Siemens PLCs. The Siemens PLCs will be replaced by CompactLogix PLCs and associated 1771 outputs in Panel 1-3 will be replaced by CompactLogix outputs at each tank. The 1771 inputs in the Primary Thickened Skimmings Panel are already monitored by the existing Siemens PLCs and will be disconnected in the field. SUMMARY OF PROJECT JULY 2012

15 Inside view of existing Siemens PLC Panel (Typical of 8). Siemens PLC in center 3. The CONTRACTOR is to provide Ethernet Ring A connections to each new Flocculation/Settling Tank CompactLogix PLC. Due to distance limitation of copper SUMMARY OF PROJECT JULY 2012

16 Ethernet cabling Ring A will need to be extended via fiber optic cabling and media converters. CONTRACTOR to provide all conduit, fiber cables, and media converters. 4. CONTRACTOR is to remove all pilot devices on the left door of the Primary Thickened Skimmings Control Panel. CONTRACTOR to provide and install one 12-guage stainless steel plate to cover pilot device holes in left door. View showing left door of Primary Thickened Skimmings Control Panel 5. The existing Primary Thickened Skimmings Panel houses both a PLC-5 and ControlLogix PLC. The PLC-5 primarily monitors the existing Siemens PLCs and a few extra I/O points. The CONTRACTOR will remove this PLC-5 from the panel and the CONTRACTOR will move any I/O that is not monitored or controlled by the new CompactLogix PLCs at each Flocculation/Settling Tank to the ControlLogix PLC, Contactor to provide one digital input module and one digital output module for the ControlLogix PLC. CONTRACTOR to remove all DeviceNet equipment within the Primary Thickened Skimmings Panel. SUMMARY OF PROJECT JULY 2012

17 Inside view of Primary Thickened Skimmings Panel equipment to be removed is shown within yellow rectangles. Existing ControlLogix PLC is shown in upper right. SUMMARY OF PROJECT JULY 2012

18 6. CONTRACTOR is to remove the following conduits that start at the Primary Thickened Skimmings Control Panel: DeviceNet cabling conduit Control Wiring Conduit 1 to Primary Flocculation/Settling Tanks 1-4 drive combination motor start disconnects Control Wiring Conduit 2 to Primary Flocculation/Settling Tanks 5-8 drive combination motor start disconnects 7. The CONTRACTOR is to provide Ethernet Ring A and Ring B cabling from Field Network Cabinet M2-21-S01 to the ControlLogix PLC in the Primary Thickened Skimmings Control Panel M2-21-C01. The CONTRACTOR is to provide one new ControlLogix Ethernet module to be installed in PLC rack. CONTRACTOR will coordinate these activities with ENGINEER. 8. The CONTRACTOR is to connect the existing Primary Odor Control PLC and Water Heater PLC to Ethernet Ring B. Existing Ethernet cabling maybe re-routed if possible. CONTRACTOR will coordinate these activities with ENGINEER. Inside view of existing Panel 1-3, PLC-5 racks to be removed shown in yellow rectangle 9. CONTRACTOR is to remove the two existing 1771 I/O racks in Panel 1-3. In the space vacated by the 1771 I/O racks the CONTRACTOR will install one 17-slot ControlLogix Remote I/O rack, all remaining active I/O in this panel to be wired to new ControlLogix SUMMARY OF PROJECT JULY 2012

19 modules. This remote I/O rack will be controlled by the ControlLogix PLC located in the Primary Thickened Skimmings Control Panel M2-21-C01 upstairs. CONTRACTOR is to provide all necessary redundant ControlNet cabling and devices. 10. CONTRACTOR to add a fluorescent light in front of new Field Network Cabinet M2-21- S01 and CONTRACTOR is to move existing fluorescent light in front of Panel 1-3 so that the light is out of the way when doors of Panel 1-3 are opened. H. COMPRESSOR BUILDING 1. For the redundant Ethernet Network the CONTRACTOR will provide and install Fiber Patch Panel M2-30-N01 near Blower 1 Control Panel on ground floor and Field Network Cabinet M2-30-S01 in the Compressor Control Room on second floor. The fiber optic rings will come from Central Maintenance Facility and continue on to Primary Skimmings Building. The Compressor Control Room is very crowded so the CONTRACTOR will temporarily place the Field Network Cabinet M2-30-S01 near the door to the control room. Once the existing panel AOS-2 is removed the Network Equipment Enclosure will be moved to the space vacated by the removal of AOS To make room for new PLC Panel M2-30-C01 the CONTRACTOR coordinate with MSD s IT group the moving of existing network switch rack to the South wall of the control room. MSD IT will do the actual work of moving the existing network switch. Once the existing panel AOS-2 is removed the existing network switch rack will be moved to the space vacated by the removal of AOS-2. SUMMARY OF PROJECT JULY 2012

20 View of existing network switch rack in Compressor Control Room. 3. CONTRACTOR will provide and install PLC Panel M2-30-C01 adjacent to existing SUMMARY OF PROJECT JULY 2012

21 Panel 2-2. CONTRACTOR to provide housekeeping pad for panel M2-30-C01 to match existing housekeeping pad of Panel 2-2. I/O modules in Panel M2-30-C01 shall be provided with pigtails of wires to connect to existing field I/O terminals in Panel 2-2. Once all existing I/O has been replaced with new ControlLogix I/O CONTRACTOR will remove the existing 1771 I/O racks within Panel 2-2. CONTRACTOR to remove existing ControlLogix rack in Panel 2-2. Inside view of left two doors of Panel 2-2, 1771 I/O racks to be removed are shown in yellow rectangles. SUMMARY OF PROJECT JULY 2012

22 Inside view of rightmost door of Panel 2-2, 1171 I/O racks and ControlLogix rack to be removed are shown in yellow rectangle. 4. CONTRACTOR to provide new Ethernet cabling for both rings from new Field Network SUMMARY OF PROJECT JULY 2012

23 Cabinet M2-30-S01 to redundant ControlLogix PLC in panel M2-30-C01. I. 5. CONTRACTOR will extend redundant ControlNet network from panel M2-30-C01 to panel M2-30-R01 located on first floor mezzanine of RAS Building using fiber optic repeaters and cables. 6. At end of project CONTRACTOR will remove existing panel AOS-2 and move the new Field Network Cabinet M2-30-S01 and existing network switch rack to the space vacated by AOS-2. All existing ControlLogix equipment within AOS-2 to be removed and returned to CITY. RETURN ACTIVATED SLUDGE (RAS) BUILDING 1. For the redundant Ethernet Network the CONTRACTOR will provide and install Fiber Patch Panel M2-99-N01 and Field Network Cabinet M2-99-S01in the RAS Control Room on second floor. The fiber optic rings will come from Primary Sludge Pump Building and continue on to Secondary Sampling. Refer to drawings for fiber connection details. 2. CONTRACTOR will remove and replace the existing 1771 I/O racks in panel COS with ControlLogix racks on backpanel M2-99-R01, CONTRACTOR to provide backpanel M299-R01. I/O modules on backpanel M2-99-R01 shall be provided with pigtails of wires to connect to existing field I/O terminals in Panel 0-1. Once all existing I/O has been replaced with new ControlLogix I/O CONTRACTOR will remove the existing 1771 I/O racks within Panel 0-1. SUMMARY OF PROJECT JULY 2012

24 Inside view of rightmost door of existing COS panel. Entire backpanel to be removed and replaced with backpanel M2-99-R01. SUMMARY OF PROJECT JULY 2012

25 Inside view of Panel 0-1, 1771 I/O racks to be removed are shown in yellow rectangle. 3. The CONTRACTOR will remove the remainder of the PLC-3 equipment in existing panel COS at the end of the project. SUMMARY OF PROJECT JULY 2012

26 Inside view of leftmost two doors of panel COS, all PLC-3 equipment shown above will be removed at end of project. 4. The CONTRACTOR will provide Ethernet Ring A and Ring B connections to Secondary PLC MLC-AD CONTRACTOR to provide all cabling and an additional ControlLogix Ethernet module to be installed in PLC rack. This work is to be coordinated with ENGINEER. 5. The CONTRACTOR will provide Ethernet Ring A connection to Non-Potable Water Strainer PLC in tunnel below RAS Building. This work is to be coordinated with ENGINEER. 6. CONTRACTOR to remove existing abandoned UPS located to the left of existing Panel 2-1. Water lines to the left of existing Panel 2-1 to be re-routed to make room for new panel M2-30-R01. SUMMARY OF PROJECT JULY 2012

27 UPS Water Lines View of abandoned UPS and Water Lines next to Panel CONTRACTOR will provide and install I/O panel M2-30-R01 adjacent to existing Panel 2-1. CONTRACTOR to provide housekeeping pad for panel M2-30-R01 to match existing housekeeping pad of Panel 2-1. I/O modules in Panel M2-30-R01 shall be provided with pigtails of wires to connect to existing field I/O terminals in Panel 2-1. Once all existing I/O has been replaced with new ControlLogix I/O CONTRACTOR will remove the existing 1771 I/O racks within Panel 2-1. SUMMARY OF PROJECT JULY 2012

28 View of inside left door of existing Panel 2-1 showing 1771 I/O rack in yellow rectangle to be removed. SUMMARY OF PROJECT JULY 2012

29 View of inside middle door of existing Panel 2-1 showing 1771 I/O racks in yellow rectangles to be removed. SUMMARY OF PROJECT JULY 2012

30 View of inside right door of existing Panel 2-1 showing 1771 I/O racks in yellow rectangle to be removed. SUMMARY OF PROJECT JULY 2012

31 J. SECONDARY SAMPLING 1. For the redundant Ethernet Network the CONTRACTOR will provide and install Fiber Patch Panel M2-30-N02 and Field Network Cabinet M2-30-S02in the tunnel under Secondary Sampling. The fiber optic rings will come from RAS Building and continue on to Secondary Effluent Disinfection. The fiber route from Secondary Sampling to Secondary Effluent Disinfection will primarily be outside in conduit along Secondary Effluent Channel. Refer to drawings for connection details. 2. The CONTRACTOR will provide Ethernet Ring A and Ring B connections to existing Secondary Sampling PLC M2-AC1. CONTRACTOR to provide all cabling and an additional ControlLogix Ethernet module to be installed in PLC rack. This work is to be coordinated with ENGINEER. K. SECONDARY EFFLUENT DISINFECTION 1. For the redundant Ethernet Network the CONTRACTOR will provide and install Fiber Patch Panel M2-30-N03 and Field Network Cabinet M2-30-S03. in the MCC Room. The fiber optic rings will come from Secondary Sampling and continue on to Disinfection Chemical Storage. The fiber route from Secondary Effluent Disinfection to Disinfection Chemical Storage will start outside along Secondary Tanks and then move into the tunnel system. Refer to drawings for connection details. 2. For Field Network Cabinet M2-30-S03 to fit the existing Network Enclosure must be moved approximately one foot to the South. 3. The CONTRACTOR will provide Ethernet Ring A and Ring B connections to existing Secondary Sampling PLC M2-C22. CONTRACTOR to provide all cabling and an additional ControlLogix Ethernet module to be installed in PLC rack. This work is to be coordinated with ENGINEER. L. DISINFECTION CHEMICAL STORAGE BUILDING 1. For the redundant Ethernet Network the CONTRACTOR will provide and install Fiber Patch Panel M2-40-N02 and Field Network Cabinet M2-40-S02 in the MCC Room. The fiber optic rings will come from Secondary Effluent Disinfection and continue on to Secondary Thickening through Fiber Patch Panel M2-40-N03 located in Disinfection Chemical Storage. Refer to drawings for connections details. 2. The CONTRACTOR will provide Ethernet Ring A and Ring B connections to existing Disinfection Chemical Storage PLC M2-C31. CONTRACTOR to provide all cabling and an additional ControlLogix Ethernet module to be installed in PLC rack. This work is to be coordinated with ENGINEER. 3. The CONTRACTOR will provide a second Fiber Patch Panel M2-40-S03 in the MCC Room at this time the fiber cables from Secondary Thickening to Dewatering will be patched through at this Fiber Patch Panel. In the future if the Ethernet network is SUMMARY OF PROJECT JULY 2012

32 upgraded to 10-Gigabyte there will be a need for a fiber repeater because the distance between Secondary Thickening and Dewatering is greater than 984 feet (300 meters). M. SECONDARY THICKENING 1. For the redundant Ethernet Network the CONTRACTOR will provide and install Fiber Patch Panel M2-60-N01 and Field Network Cabinet M2-60-S01 in the MCC Room. The fiber optic rings will come from Disinfection Chemical Storage and continue on to Dewatering through fiber patch panel M2-40-N03 located in Disinfection Chemical Storage. Refer to drawings for connection details. 2. The CONTRACTOR will provide Ethernet Ring A and Ring B connections to existing Secondary PLC STCP PLC 3. CONTRACTOR to provide all cabling and an additional ControlLogix Ethernet module to be installed in PLC rack. This work is to be coordinated with ENGINEER. 3. CONTRACTOR to provide new Ethernet cabling from one ring from new Field Network Cabinet M2-60-S01 to the following existing devices: Secondary Polymer Blender 1 Secondary Polymer Blender 2 Secondary Thickening Centrifuge 1 Sec. Thick. Centrifuge 1 Power Quality Meter (requires Serial to Ethernet Converter) Secondary Thickening Centrifuge 2 Sec. Thick. Centrifuge 2 Power Quality Meter (requires Serial to Ethernet Converter) Secondary Thickening Centrifuge 3 Sec. Thick. Centrifuge 3 Power Quality Meter (requires Serial to Ethernet Converter) Secondary Thickening Centrifuge 4 Sec. Thick. Centrifuge 4 Power Quality Meter (requires Serial to Ethernet Converter) CONTRACTOR is to provide all cabling, serial-to-ethernet converters and other devices to connect the above devices to new SCADA Ethernet network. CONTRACTOR is to replace existing GE-Quickpanel at Polymer Blender 1 and 2 with similar Allen-Bradley Panelview. At each Centrifuge there is also a Panelview, the CONTRACTOR is to provide all cabling and connectors to allow the Panelview to communicate serially to the Centrifuge PLC. CONTRACTOR is to provide all devices, cabling and connections. All work to be coordinated with ENGINEER. 4. CONTRACTOR to remove abandoned AOS-3A enclosure in Secondary Thickening Control Room. SUMMARY OF PROJECT JULY 2012

33 View of abandoned AOS-3A in Secondary Thickening Control Room 5. The existing Remote I/O Panel (CIO-3-0) in Primary Thickening Tunnel contains two remote I/O ControlLogix racks which are controlled by Secondary PLC STCP PLC 3. SUMMARY OF PROJECT JULY 2012

34 Each remote I/O is powered by a single power supply, CONTRACTOR is to provide and install a new stainless steel enclosure with two sets of redundant ControlLogix Power Supplies (4 total power supplies). This enclosure is to be mounted on the back of the existing CIO-3-0 panel and the redundant power supplies are to be wired/ cabled to the existing remote I/O racks. 6. CONTRACTOR to re-route the Sludge Flow signal from the existing flow meter to panel CIO-3-0. Currently the signal goes to Panel 3-1 but signal needs to go to CIO At the end of the project CONTRACTOR is to remove existing panels AOS-3 and Panel 3-1 in the Primary Thickening Electrical Room. All conduits to be removed to their source. All work to be coordinated with ENGINEER. 8. CONTRACTOR to remove abandoned 1771 I/O racks in Panel 3-6 located in MCC Room of Secondary Thickening Building. N. DEWATERING SERVER ROOM 1. For the redundant Ethernet Network the CONTRACTOR will provide and install Fiber Patch Panel M2-72-N01 and Server Switch Cabinet M2-72-S01 in the MCC Room. The fiber optic rings will come from Secondary Thickening and continue on to Dewatering Electrical Room. 2. CONTRACTOR to provide and install 12-strand armored fiber cable between this Server Switch Cabinet and Server Switch Cabinet to be installed in Central Maintenance Facility. CONTRACTOR to provide and install Fiber patch panels in each switch cabinet (M2-72S01 and M2-97-SO1). This fiber cable is used to synch the ifix servers. 3. The CONTRACTOR will provide Ethernet Ring A and Ring B connections to four existing ifix servers. O. DEWATERING ELECTRICAL ROOM 1. For the redundant Ethernet Network the CONTRACTOR will provide and install Fiber Patch Panel M2-72-N02 and Field Network Cabinet M2-72-S02 in the MCC Room. The fiber optic rings will come from Dewatering Server Room and continue on to Central Maintenance Facility Server Room. Refer to drawings for connection details. 2. CONTRACTOR to provide new Ethernet cabling for one ring from new Field Network Cabinet M to the following existing devices: Dewatering Polymer Blender 1 Dewatering Polymer Blender 2 Dewatering Polymer Blender 3 Dewatering Polymer Blender 4 Dewatering Polymer Blender 5 Dewatering Polymer Blender 6 Dewatering Polymer Blender 7 Dewatering Centrifuge 1 SUMMARY OF PROJECT JULY 2012

35 Dewatering Centrifuge 1 Power Quality Meter (requires Serial to Ethernet Converter) Dewatering Centrifuge 2 Dewatering Centrifuge 2 Power Quality Meter (requires Serial to Ethernet Converter) Dewatering Centrifuge 3 Dewatering Centrifuge 3 Power Quality Meter (requires Serial to Ethernet Converter) Dewatering Centrifuge 4 Dewatering Centrifuge 4 Power Quality Meter (requires Serial to Ethernet Converter) Dewatering Centrifuge 5 Dewatering Centrifuge 5 Power Quality Meter (requires Serial to Ethernet Converter) Dewatering Centrifuge 6 Dewatering Centrifuge 6 Power Quality Meter (requires Serial to Ethernet Converter) Schwing Pump 1 Schwing Pump 2 Schwing Pump 3 Schwing Pump 4 Schwing Pump 5 Schwing Pump 6 CONTRACTOR is to provide all cabling, serial-to-ethernet converters and other devices to connect the above devices to new SCADA Ethernet network. At each Centrifuge there is also a Panelview, the CONTRACTOR is to provide all cabling and connectors to allow the Panelview to communicate serially to the Centrifuge PLC. CONTRACTOR is to provide all devices, cabling and connections. All work to be coordinated with ENGINEER. 3. CONTRACTOR to provide new Ethernet cabling for both rings from new Field Network Cabinet M2-72-S02 to the following existing redundant ControlLogix PLCs: Incinerator PLC 5-1 Incinerator PLC 5-2 Incinerator PLC 5-3 Incinerator PLC 5-4 CONTRACTOR is to provide two ControlLogix Ethernet modules per redundant ControlLogix listed above, modules to be installed by ENGINEER. All work is to be coordinated with ENGINEER. 4. CONTRACTOR is to provide and install two Ethernet switches (allowance item) like units in Field Network Cabinet to be installed in existing rack in CEMS Room on same floor as Dewatering Electrical Room. These switches are to be connected to switches in Field Network Cabinet using CONTRACTOR provided and installed fiber optic cabling. CONTRACTOR is to provide new Ethernet cabling from these two new switches to each of the following PLCs: ICEMS-1 (non-redundant) ICEMS-2 (non-redundant) ICEMS-3 (non-redundant) Incinerator PLC 5 (Redundant) SUMMARY OF PROJECT JULY 2012

36 CONTRACTOR is to provide one ControlLogix Ethernet module per non-redundant ControlLogix and two ControlLogix Ethernet modules per redundant ControlLogix PLC list above, modules to be installed by ENGINEER. All work is to be coordinated with ENGINEER. 5. CONTRACTOR is to provide an Ethernet connection to one of the rings from the new Field Network Cabinet M2-72-S02 to the Sludge Receiving PLC. Due to the distance this connection will need to be a fiber optic connection. CONTRACTOR is to provide all cabling, media converters, and other devices. 6. CONTRACTOR will provide and install redundant ControlLogix PLC panel M2-72-C01 adjacent to existing Panel 4-1. CONTRACTOR to provide housekeeping pad for panel M2-72-C01 to match existing housekeeping pad of Panel 4-1. I/O modules in Panel M272-C01 shall be provided with pigtails of wires to connect to existing field I/O terminals in Panel 4-1. Once all existing I/O has been replaced with new ControlLogix I/O CONTRACTOR will remove the existing 1771 I/O racks within Panel 4-1. Both processor racks located in M2-72-C01 will be connected to both Ethernet Ring A and Ring B. The redundant ControlNet network must be extended to new panel M2-72-R02 and existing panel AOS-4 (M2-72-R01). SUMMARY OF PROJECT JULY 2012

37 View of existing Panel 4-1 showing 1771 I/O racks to be removed within yellow rectangles. 7. CONTRACTOR to provide and install backpanel M2-72-R01, backpanel to be installed in leftmost bay of existing AOS-4 enclosure. I/O modules on backpanel M2-72-R01 shall be SUMMARY OF PROJECT JULY 2012

38 provided with pigtails of wires to connect to existing field I/O terminals in AOS-4. Once all existing I/O has been replaced with new ControlLogix I/O CONTRACTOR will remove the existing 1771 I/O racks within AOS-4. CONTRACTOR to provide and install redundant ControlNet cabling to panel M2-72-R01 from M2-72-C01. Redundant ControlNet to continue to panel M2-72-Ro2 in Polymer Unloading area. View of middle door of existing AOS-4 panel showing 1771 I/O racks to be removed within yellow rectangle. SUMMARY OF PROJECT JULY 2012

39 Inside view of left door of existing AOS-4 panel showing space where backpanel M2-72-R01 will be placed. SUMMARY OF PROJECT JULY 2012

40 8. CONTRACTOR will provide and install remote I/O panel M2-72-R02 adjacent to existing Panel 4-2. I/O modules in Panel M2-72-R02 shall be provided with pigtails of wires to connect to existing field I/O terminals in Panel 4-2. Once all existing I/O has been replaced with new ControlLogix I/O CONTRACTOR will remove the existing 1771 I/O racks within Panel 4-2. CONTRACTOR to provide and install redundant ControlNet cabling to panel M2-72-R02 from backpanel M2-72-R01. SUMMARY OF PROJECT JULY 2012

41 View of existing Panel 4-2 showing 1771 I/O racks to be removed within yellow rectangles. SUMMARY OF PROJECT JULY 2012

42 P. CENTRAL MAINTENANCE FACILITY SERVER ROOM 1. For the redundant Ethernet Network the CONTRACTOR will provide and install Fiber Patch Panel M2-97-N01 and Server Switch Cabinet M2-97-S01 in the Server Room (Room 252). The fiber optic rings will come from Dewatering Electrical Room and continue on to Compressor Building. Refer to drawings for connection details. 2. CONTRACTOR to provide and install 12-strand armored fiber cable between Server Switch Cabinet M2-97-S01 and Server Switch Cabinet M2-71-S01 to be installed in Dewatering. CONTRACTOR to provide and install Fiber patch panels in each switch cabinet. This fiber cable is used to synch the ifix servers. 3. The CONTRACTOR will provide Ethernet Ring A and Ring B connections to four existing ifix servers. 4. CONTRACTOR is to provide two Ethernet switches (allowance item) like units in Server Switch Cabinet to be installed in existing rack in Electrical Room on same floor as Server Room. These switches are to be connected to switches in Server Switch Cabinet using existing copper wiring in building. 5. CONTRACTOR to remove existing water-based fire protection system in the Central Maintenance Facility Server Room and replace with a FM-200 fire protection system. Q. DRAWINGS For each PLC Enclosure, Field Network Cabinet, and Server Switch Cabinet to be provided the CONTRACTOR is to submit dimensioned shop drawings showing front panel layout, back panel layout, and a Bill-of-Material. 2. For each PLC Enclosure and Field Network Cabinet to be provided the CONTRACTOR is to submit electrical schematics showing all terminations of panel mounted equipment and field I/O. A preliminary I/O list is provided. CONTRACTOR to verify all I/O points. HVAC, PLUMBING, MECHANICAL, AND FIRE SUPPRESSION BIDDING PART 2 A. The work to be performed under Bidding Part 2 of this section shall include all necessary demolition, the furnishing of all materials, equipment and tools; and performing all necessary labor and supervision, for the complete construction of the HVAC, Plumbing, and Mechanical Work and all other work appurtenant thereto except for work to be furnished and installed under Bidding Part 1 and Bidding Part 2 of this section. The work to be performed under Bidding Part 2 of this section shall consist of the work delineated in the following Divisions of the Specifications: 1. Division 1 - General Requirements (as applicable). 2. Division 21 - Fire Suppression (as applicable). B. Work shall be performed according to contract Specifications, contract Drawings, and any supplemental installation drawings provided by the CITY. The major items of work to be SUMMARY OF PROJECT JULY 2012

43 performed under Part 3 shall include, but is not limited to, the following: Removal of water based fire suppression equipment in server room in Central Maintenance Facility. 2. Furnish and install and make operational new chemical fire suppression system in server room in Central Maintenance Facility. New fire suppression system must interact with existing building fire protection and alarming system. 3. Perform all testing, adjusting, and cleaning for systems installed under Part 3. BUILDING TRADES CONSTRUCTION BIDDING PART 3 NOT USED 1.07 REFERENCE SPECIFICATIONS/GENERAL A. To the extent the technical specifications in the Contract Documents reference the State of Ohio, Department of Transportation, Construction and Material Specifications (the "ODOT Specifications"), the Work shall be performed in accordance with the requirements of the applicable ODOT Specifications, unless the applicable ODOT Specifications are modified by the City of Cincinnati, Supplement to the State of Ohio, Department of Transportation, Construction and Material Specifications (the "City Supplement"). If the ODOT Specifications are modified by the City Supplement, the Work shall be performed in accordance with the City Supplement. Finally, to the extent that either the ODOT Specifications or the City Supplement is inconsistent with the Contract Documents, the Work shall be performed in accordance with the Contract Documents SEQUENCE OF WORK A. The CONTRACTOR shall schedule the Work to conform to the general construction sequencing requirements described in Section CONTRACTOR S USE OF SITE A. The CONTRACTOR shall locate field offices, store materials and equipment and confine his construction activities to areas so indicated on the Drawings or as directed by the CITY. The CONTRACTOR shall also comply with all applicable Special Right-of-Way provisions in Section CONSTRUCTION PROCEDURE A. It shall be the CONTRACTOR's responsibility during the construction of the Project to work equipment around poles, trees, or other obstructions which permit the passage of the bucket and boom but prevent passage of other portions of the equipment and, if necessary, to excavate from both sides of the poles, trees, or other obstruction, and to remove materials by hand labor, tunneling, or by other means, all at the CONTRACTOR s own expense. SUMMARY OF PROJECT JULY 2012

44 1.11 REQUESTS FOR SUPPLEMENTARY INFORMATION A. It shall be the responsibility of the CONTRACTOR to make timely requests of the CITY for any additional information not already in the CONTRACTOR s possession and which should be furnished by the CITY under the terms of the Contract Documents, and which will be required in the planning and execution of the work. Such requests may be submitted from time to time as the need approaches, but each shall be filed in ample time to permit appropriate action to be taken by all parties involved so as to avoid delay. B. Each request shall be in writing, and list the various items and the latest day by which each will be required by the CONTRACTOR. The first list shall be submitted within two (2) weeks after contract award and shall be as complete as possible at that time. The CONTRACTOR shall, if required, furnish promptly any assistance and information the CITY may require in responding to these requests of the CONTRACTOR. The CONTRACTOR shall be fully responsible for any delay in work, or to the work of others, arising from failure to comply with the provisions of this section PERMITS A. The CONTRACTOR shall be responsible to obtain and incur the cost of all required permits unless otherwise noted, including but not limited to Plumbing, Electrical, and any permit required for local governments. B. Although the CITY may obtain and incur the cost of a permit, the CONTRACTOR shall comply with provisions of all permits and make any necessary submittals. C. All CONTRACTORS and Subcontractors of any tier, shall comply with all applicable standards, orders, regulations and permits, including but not limited to the Clean Water Act of 1970 (42 U.S.C. 1857, et seq.), the Federal Water Pollution Control Act (33 U.S.C. 1251, et seq.) as amended, Permits to Install, and NPDES 401 and 404 Permit requirements. PART 2 - PRODUCTS NOT USED PART 3 - EXECUTION NOT USED END OF SECTION SUMMARY OF PROJECT JULY 2012

45 THIS PAGE LEFT BLANK INTENTIONALLY SUMMARY OF PROJECT JULY 2012

46 SECTION CONSTRUCTION SEQUENCE PART 1 - GENERAL 1.01 SECTION INCLUDES A. Site Conditions. B. Construction Constraints. C. Suggested Construction Sequence D. Active Projects: 1. Mill Creek Grit Project 2. Mill Creek Secondary Project 3. Mill Creek Digester Removal Project 4. Mill Creek Blower Upgrade Project 1.02 RELATED SECTIONS NOT USED 1.03 SITE CONDITIONS A. At the discretion of the CITY, the CITY will videotape the construction limits along the proposed alignment or work areas as detailed on the plans, within the Right-of-Way or easements, as well as potentially impacted properties adjacent to the work zone. The videotape will document preconstruction (existing) and/or post construction conditions. The CONTRACTOR shall make himself available at the project site during the videotaping, when requested by the CITY. B. CONTRACTOR shall coordinate with the Plant Operating Personnel, as designated by the CITY, to accomplish a logical order to maintain the process flow through the plant and to allow construction to be completed within the time allowed by Contract Documents. Coordinate the activities with the other contractors, if any, to allow orderly and timely completion of all the Work. C. CONTRACTOR shall schedule construction activities so as to keep any treatment facilities in operation at all times unless otherwise approved by the CITY. 1. CONTRACTOR shall furnish and operate any temporary equipment required to maintain the wastewater flows around construction operations so the system will not be out of service. This includes pumping as required to maintain flow. 2. All temporary pumping, piping or miscellaneous equipment as shown on the Drawings or as required by the CONTRACTOR shall be furnished, maintained and subsequently CONSTRUCTION SEQUENCE JULY 2012

47 removed by the CONTRACTOR. D. All proposed construction sequences, and all system shutdowns and equipment tie-ins shall be scheduled well in advance and shall occur only after being approved by ENGINEER. E. When access through construction areas must be disrupted, CONTRACTOR shall provide alternate acceptable access for the plant operators or other contractors. F. CONTRACTOR shall coordinate all activities in the interface or common areas with other contractors and the plant operators. Submit to the CITY a description and schedule as to how the common areas will be utilized, recognizing the required coordination with other contractors and the plant operators. G. Various interconnections within the plant will depend on the closure of various valves and gates. Many of these valves and gates are old and may not seal properly. CONTRACTOR shall coordinate with the plant operation personnel prior to attempting any such closure and provide any corrective measure of temporary facilities necessary to attain the shut-off needed to perform the work at no additional cost to the CITY and without interrupting the plant operation. H. Various interconnections within the plant may require temporary partial power shutdown. Make every effort necessary to minimize the shutdown time and coordinate with the plant operating personnel and/or utility authorities prior to attempting any such power shutdown. Furthermore, provide any corrective measure or temporary facilities necessary to perform the work at no additional cost to the CITY and without interrupting the plant operation. I. When the Work requires an existing facility to be taken out of operation, temporarily or permanently, notify the CITY in writing and plant operators at least one (1) week in advance. J. The CONTRACTOR may be allowed to use, if available, non-potable plant water after express approval from the CITY at no charge. The CITY reserves the right to restrict access or charge for plant water service if CONTRACTOR abuses his right of use, including water wastage or excessive use. K. During Start-Up Testing, make available the manpower, equipment and manufacturer's representatives required to make any necessary adjustments and training CONSTRUCTION CONSTRAINTS A. The following is a list of constraints to consider in developing the overall plan of construction. This list is not intended to release the CONTRACTOR from the responsibility to coordinate the Work in any manner which will ensure Project completion within the time allowed. 1. The scope of work for the CONTRACTOR includes modifications to an operating WWTP. 2. Due to ongoing plant operation and limited staffing, multiple shutdowns for any process shall not occur on consecutive days or the same day without prior approval from the OWNER. 3. Any outages necessary to facilitate the cut-in of new equipment must be coordinated with CONSTRUCTION SEQUENCE JULY 2012

Section GAS CHLORINATION SYSTEM

Section GAS CHLORINATION SYSTEM PART 1 GENERAL 1.01 SUMMARY Section 11260 This Section includes the furnishing and subsequent installation, complete and in place, of a functioning gas chlorination disinfection system for water as shown

More information

Bulletin Swimming pool, hot tub and spa installations Rules , , , , , and

Bulletin Swimming pool, hot tub and spa installations Rules , , , , , and Bulletin 68-7-11 Swimming pool, hot tub and spa installations Rules 68-000, 68-056, 68-058, 68-064, 68-068, 68-302 and 68-404 Scope (1) Swimming pools - general (2) Grounding & bonding (a) Bonding for

More information

SyncroFlo Municipal University and Hydraulic Institute, Pump Systems Optimization

SyncroFlo Municipal University and Hydraulic Institute, Pump Systems Optimization SyncroFlo Municipal University and Hydraulic Institute, Pump Systems Optimization COURSE SYLLABUS September 16 th 18 th, 2013 9/16/13 Day One Hydraulic Institute Workshop (8:30am) PUMP SYSTEMS OPTIMIZATION:

More information

GAS FUEL VALVE FORM AGV5 OM 8-03

GAS FUEL VALVE FORM AGV5 OM 8-03 ALTRONIC AGV5 OPERATING MANUAL GAS FUEL VALVE FORM AGV5 OM 8-03 WARNING: DEVIATION FROM THESE INSTALLATION INSTRUCTIONS MAY LEAD TO IMPROPER ENGINE OPERATION WHICH COULD CAUSE PERSONAL INJURY TO OPERATORS

More information

Check with local zoning official for property line distance requirements.

Check with local zoning official for property line distance requirements. RESIDENTIAL POOL PLAN SUBMITTAL GUIDELINES The following guidelines are intended to assist municipal residents with the permit acquisition process with regard to pools, spas and hot tubs for single family

More information

PRICED BID -PACKAGE II Page 1 of 19 Vendor Seal and Signature. Set 103. Set 23 pulse transmitter and Non return valve for 1.5" ethanol line.

PRICED BID -PACKAGE II Page 1 of 19 Vendor Seal and Signature. Set 103. Set 23 pulse transmitter and Non return valve for 1.5 ethanol line. 1 2 3 Supply of flowmeters 3" line: Supply of Positive displacement type flowmeters, Strainer with DPG, air eliminator, with pulse transmitter for 3" line Erection of Positive displacement type flowmeters,

More information

Piped Air SCBA Refilling System Standard

Piped Air SCBA Refilling System Standard WALT WHITE Fire Chief 5770 Freeport Blvd., Suite 200 Sacramento, CA 95822-3516 Ph: (916) 808-1300 Fax: (916) 808-1629 www.sacfire.org Piped Air SCBA Refilling System Standard SCOPE: This specification

More information

SWIMMING POOL & SPA DOCUMENT SUBMITTAL LIST

SWIMMING POOL & SPA DOCUMENT SUBMITTAL LIST SWIMMING POOL & SPA DOCUMENT SUBMITTAL LIST Completed Application for Construction or Use (Permit application). Application must include authorized signature from the property owner if it is not owner

More information

Swimming Pool Requirements

Swimming Pool Requirements Swimming Pool Requirements 8040 S. 6th Street Oak Creek, WI 53154 (414) 766-7000 www.oakcreekwi.org Revised: August 8. 2017 PERMITS A permit from the Inspection Department is required prior to putting

More information

DESIGN CRITERIA DIVISION 4900 TRAFFIC SIGNALS

DESIGN CRITERIA DIVISION 4900 TRAFFIC SIGNALS DESIGN CRITERIA DIVISION 4900 TRAFFIC SIGNALS 4901 GENERAL: These criteria shall be adhered to for the design of all publiclyfinanced or privately-financed traffic signal systems to be installed in the

More information

Type 1 - Nitrogen Generation System. Designed for: Dry or Pre-Action Fire Protection Systems (FPS) with a total capacity up to 750 gallons

Type 1 - Nitrogen Generation System. Designed for: Dry or Pre-Action Fire Protection Systems (FPS) with a total capacity up to 750 gallons Type 1 - Nitrogen Generation System Designed for: Dry or Pre-Action Fire Protection Systems (FPS) with a total capacity up to 750 gallons 1.0 Nitrogen Generation Corrosion Inhibiting System 1.1 The Fire

More information

TECHNICAL DATA. TRIMPAC Model B-5 & B-5B

TECHNICAL DATA. TRIMPAC Model B-5 & B-5B September 16, 2013 Trimpac 250a 1. DESCRIPTION DEsCRIPTIoN is a factory assembled trim package for a ed an electric/pneumatic release module in a metal enclosure. The standard trim normally required on

More information

$ Plan Review Fee when Permit Application is submitted HOT TUBS AND SPAS BUILDING PERMIT APPLICATION. COST: $80.

$ Plan Review Fee when Permit Application is submitted HOT TUBS AND SPAS BUILDING PERMIT APPLICATION. COST: $80. Community Development 1050 W Romeo Rd, Romeoville, IL 60446-1530 (815) 886-7200 Fax #: (815) 886-2724 Email: buildinginspections@romeoville.org HOT TUBS AND SPAS BUILDING PERMIT APPLICATION Application

More information

City of Crystal Lake Community Development Department

City of Crystal Lake Community Development Department City of Crystal Lake Community Development Department 100 W. Woodstock Street Crystal Lake, IL 60014 www.crystallake.org Phone (815) 356-3605 Fax (815) 479-1647 building@crystallake.org ABOVE GROUND SWIMMING

More information

TECHNICAL DATA. Trimpac 251a. Spetember 16, 2013

TECHNICAL DATA. Trimpac 251a. Spetember 16, 2013 Spetember 16, 2013 Trimpac 251a 1. DEsCrIpTION DESCRIPTION TRIMPAC Model B-6 and B-6B is a factory assembled trim package for a double interlocked preaction system with an electric/pneu-lectric release

More information

SWIMMING POOL REQUIREMENTS

SWIMMING POOL REQUIREMENTS PERMITS A permit from the Inspection Department is required prior to putting up a permanent pool. A permit is required for permanent pools, such as the following: SWIMMING POOL REQUIREMENTS The pool is

More information

E2.14 Control of Hazardous Energy. Effective Date: 03/01/2018

E2.14 Control of Hazardous Energy. Effective Date: 03/01/2018 University Policy Volume E2: Environment, Health, Safety and Security E2.14 Control of Hazardous Energy Responsible Office: Facilities Management Responsible Officer: Safety Officer POLICY STATEMENT All

More information

DEH Instructions. Three-Phase, Platform-Mounted Distribution Transformers

DEH Instructions. Three-Phase, Platform-Mounted Distribution Transformers g DEH 40050 Instructions Three-Phase, Platform-Mounted Distribution Transformers Introduction The equipment covered by these instructions should be operated and serviced only by competent technicians familiar

More information

The purpose of this brochure is to explain to owners and contractors the City of Burnaby s requirements for private swimming pools.

The purpose of this brochure is to explain to owners and contractors the City of Burnaby s requirements for private swimming pools. Building Information BURNABY PLANNING & BUILDING DEPARTMENT Swimming Pools The purpose of this brochure is to explain to owners and contractors the City of Burnaby s requirements for private swimming pools.

More information

Energy Control. Suite 2A, 55 Frid Street Hamilton, ON L8P 4M3 office: cell:

Energy Control. Suite 2A, 55 Frid Street Hamilton, ON L8P 4M3 office: cell: Energy Control Suite 2A, 55 Frid Street Hamilton, ON L8P 4M3 office: 905.577.0303 cell: 905.977.0210 consultant@staffaid.ca www.staffaid.com Safety, Energy Control, Power Lockout & Function Test Procedures

More information

Page 1 of 1 04/19/13 SBR

Page 1 of 1 04/19/13 SBR Office of Roadway Engineering - Plan Insert Sheets Number Title Date Number Title Date Number Title Date 201015 Extension of Anchor Bolts 07/20/12 207000 Bikeway Pavement Marking Details 01/18/13 202010

More information

Cycling Device Training Manual

Cycling Device Training Manual NRG POWER, INC. Industrial Electrical Contractors NRG POWER, INC. Phone: 714.424.6484 Industrial Electrical Contractors Fax: 714.424.6477 3011 South Shannon Street email: nrgpower@yahoo.com Santa Ana,

More information

South-Tek Systems - Nitrogen Generation Corrosion Inhibiting System. Designed for: Dry or Preaction Fire Protection Systems (FPS)

South-Tek Systems - Nitrogen Generation Corrosion Inhibiting System. Designed for: Dry or Preaction Fire Protection Systems (FPS) South-Tek Systems - Nitrogen Generation Corrosion Inhibiting System Designed for: Dry or Preaction Fire Protection Systems (FPS) 1.0 Description of Work 1.1 The Fire Sprinkler Contractor shall provide

More information

TECHNICAL DATA. Trimpac 244a. September 16, 2013

TECHNICAL DATA. Trimpac 244a. September 16, 2013 September 16, 2013 Trimpac 244a 1. DEsCrIpTION DESCRIPTION TRIMPAC Model B-1 and B-1B is a factory-assembled trim package with an electric release module in a metal enclosure. The standard trim normally

More information

RPS900W Redundant Power Supply. Installation Guide.

RPS900W Redundant Power Supply. Installation Guide. RPS900W Redundant Power Supply Installation Guide www.edge-core.com Installation Guide RPS900W Redundant Power Supply Single DC Output Port with Dual Output Voltages RPS900W E10013-CS-R01 1500000081A

More information

LOCKOUT/TAGOUT PROGRAM

LOCKOUT/TAGOUT PROGRAM Santa Clarita Community College District LOCKOUT/TAGOUT PROGRAM Revised March 2018 TABLE OF CONTENTS PURPOSE... 3 COMPLIANCE...4 DEFINITIONS...5 SECTION I - ENERGY CONTROL PROCEDURES... 7 SECTION II -

More information

MOYNO FLUID DETECTION CONTROL SERVICE MANUAL. Section: ACCESSORIES. Page: 1 of 8 Date: May 1, 1998 GENERAL

MOYNO FLUID DETECTION CONTROL SERVICE MANUAL. Section: ACCESSORIES. Page: 1 of 8 Date: May 1, 1998 GENERAL MOYNO Section: ACCESSORIES Page: 1 of 8 Date: May 1, 1998 SERVICE MANUAL FLUID DETECTION CONTROL GENERAL The Moyno Fluid Detection Control prevents unnecessary loss of production time or repair costs to

More information

City of Lockport Above Ground Pool Regulations

City of Lockport Above Ground Pool Regulations Location: City of Lockport Above Ground Pool Regulations Pool to be at least 6 feet from both rear and side lot lines, but not in any easements. If located on a corner lot, pool must be located behind

More information

TECHNICAL DATA. Trimpac 257a. September 16, 2013

TECHNICAL DATA. Trimpac 257a. September 16, 2013 September 16, 2013 Trimpac 257a 1. DESCrIpTION DESCRIPTION The Viking Double SUREFIRE SIngle Interlock Preaction TRIMPAC Model D-2 and D-2B used with either a Model E or F Deluge Valve (A.1), a Viking

More information

TECHNICAL DATA. Trimpac 256a. October 31, 2013

TECHNICAL DATA. Trimpac 256a. October 31, 2013 October 31, 2013 Trimpac 256a 1. DESCRIPTION The Viking SUREFIRE SIngle Interlock Preaction TRIMPAC Model D-1 and D- 1B used with either a Model E or F Deluge Valve (A.1), a Viking Easy Riser check valve

More information

TANK MANAGER FOR TWO TANKS OPERATING MANUAL. 10/31/11 C-More T6C L color touch panel

TANK MANAGER FOR TWO TANKS OPERATING MANUAL. 10/31/11 C-More T6C L color touch panel TANK MANAGER FOR TWO TANKS OPERATING MANUAL 10/31/11 C-More T6C L color touch panel 1 TABLE OF CONTENTS GENERAL...3 INSTALLATION...4 STONE TEST PROCEDURE...7 OPERATIONAL SUMMARY...7 AUTO CARBONATION...10

More information

THE CANDU 9 DISTRffiUTED CONTROL SYSTEM DESIGN PROCESS

THE CANDU 9 DISTRffiUTED CONTROL SYSTEM DESIGN PROCESS THE CANDU 9 DISTRffiUTED CONTROL SYSTEM DESIGN PROCESS J.E. HARBER, M.K. KATTAN Atomic Energy of Canada Limited 2251 Speakman Drive, Mississauga, Ont., L5K 1B2 CA9900006 and M.J. MACBETH Institute for

More information

Florida Building Code 6 th Edition (2017) Residential. Broward County Edition Loose-leaf Supplement

Florida Building Code 6 th Edition (2017) Residential. Broward County Edition Loose-leaf Supplement Board of Rules and Appeals FBC 6 th Edition (2017)- Residential - Supplement No. 1 January 1, 2018 Florida Building Code 6 th Edition (2017) Residential File removed pages for reference. Broward County

More information

UltraLo 1800 Alpha Particle Counter

UltraLo 1800 Alpha Particle Counter XIA LLC UltraLo 1800 Alpha Particle Counter Site Requirements & Planning Version: 0.4 Friday, February 15, 2013 Table of Contents I. Site Preparation Tasks... 3 A. Instrument Overview... 3 B. Installation

More information

MaxSB - Low Voltage Switchboard

MaxSB - Low Voltage Switchboard BU 3101 Low Voltage Systems, March 2009 Low Voltage Systems MaxSB - Low Voltage Switchboard May 5, 2009 Slide 1 MaxSB Product Overview Description Value Rated Main bus current 1600A, 2000A, 3000A, 3200A,

More information

(1) Minimum Required. At least one entrance of sufficient area shall be provided to

(1) Minimum Required. At least one entrance of sufficient area shall be provided to (B) Clear Spaces. Working space required by this section shall not be used for storage. When normally enclosed live parts are exposed for inspection or servicing, the working space, if in a passageway

More information

Section GATE VALVES

Section GATE VALVES Section 02521 PART 1 GENERAL 1.01 SUMMARY This Section includes the furnishing and installation of gate valves for isolation and dead-end service as shown on Plans and as specified herein. 1.02 MEASUREMENT

More information

ACV-10 Automatic Control Valve

ACV-10 Automatic Control Valve ACV-10 Automatic Control Valve Installation, Operation & Maintenance General: The Archer Instruments ACV-10 is a precision automatic feed rate control valve for use in vacuum systems feeding Chlorine,

More information

UBEC 1AT. AUTO TANK Fill System Installation, Operation, & Setup Instructions

UBEC 1AT. AUTO TANK Fill System Installation, Operation, & Setup Instructions Document Number: XE-ATA5PM-R1A UBEC 1AT AUTO TANK Fill System 08899155 Installation, Operation, & Setup Instructions Rev170906-EB-FRC PHYSICAL: 1302 WEST BEARDSLEY AVE ELKHART, IN 46514 WWW.ELKHARTBRASS.COM

More information

Type 3 - PSA Nitrogen Generation System

Type 3 - PSA Nitrogen Generation System Type 3 - PSA Nitrogen Generation System Designed for: Dry or Pre-Action Fire Protection Systems (FPS) with a total capacity from 6,000 to 18,000 gallons 1.0 Nitrogen Generation Corrosion Inhibiting System

More information

RESIDENTIAL SWIMMING POOLS AND SPAS A GUIDE FOR HOMEOWNERS

RESIDENTIAL SWIMMING POOLS AND SPAS A GUIDE FOR HOMEOWNERS RESIDENTIAL SWIMMING POOLS AND SPAS A GUIDE FOR HOMEOWNERS City of Redding 777 Cypress Avenue Redding CA 96001 Telephone: (530) 225-4013 FAX: (530) 225-4360 A Swimming Pool is any body of water 18 inches

More information

PART 1 GENERAL..2 Components of the gas chlorination system include, but are not limited to the following:

PART 1 GENERAL..2 Components of the gas chlorination system include, but are not limited to the following: PART 1 GENERAL 1.1 DESCRIPTION.1 This section includes the supply, delivery and installation, testing and placement into operation of a gas chlorination system, and appurtenances as specified herein and

More information

LAKE ARROWHEAD COMMUNITY SERVICES DISTRICT STANDARD OPERATING PROCEDURES FACILITY SAFETY The following procedures are to be used by all District employees when working in the District facilities or with

More information

Flamco Airfix D-E. Installation and operating instructions. 1999, Flamco eps

Flamco Airfix D-E. Installation and operating instructions. 1999, Flamco eps Airfix D-E 6442.eps GB Installation and operating instructions 1999, Exclusion of liability All operation and maintenance related technical information, data and instructions contained in these installation

More information

Whitehall Township Swimming Pool, Spa and Hot Tub Code Guide

Whitehall Township Swimming Pool, Spa and Hot Tub Code Guide Whitehall Township Swimming Pool, Spa and Hot Tub Code Guide THIS IS A GUIDE ONLY! YOU MUST COMPLY WITH ALL APPLICABLE PROVISIONS OF THE ADOPTED EDITION OF THE INTERNATIONAL RESIDENTIAL CODE (IRC). FOR

More information

Cable Pressurization Buffering

Cable Pressurization Buffering Cable Pressurization Buffering What This Practice Is About Introduction This practice describes the various buffering practices that are used to protect the integrity of the pressurized cable network during

More information

Installation, Operation and Maintenance Instructions for Electronically Controlled Pressurisation Units

Installation, Operation and Maintenance Instructions for Electronically Controlled Pressurisation Units Installation, Operation and Maintenance Instructions for Electronically Controlled Pressurisation Units Models: EPS Single Pump EPT Twin Pump EPS-HP EPT-HP Single Pump High Pressure Twin Pump High Pressure

More information

Swimming Pool Installation

Swimming Pool Installation Swimming Pool Installation The following information is provided to assist in the planning and installation of swimming pools and hot tubs within the City of Vandalia, OH. Zoning, Fence and Electric Permits

More information

Accu-Tab PowerBase 3012AT by Axiall Corporation

Accu-Tab PowerBase 3012AT by Axiall Corporation Accu-Tab PowerBase 3012AT by Axiall Corporation Installation and Operating Instructions DANGER: DO NOT MIX CHEMICALS! The PowerBase 3012AT chlorinator system is designed for use with Axiall Corp. approved

More information

SPECIFICATIONS ATTENTION

SPECIFICATIONS ATTENTION VPS 504 S06 Installation Manual - P/N 80122 - Ed. 01/09 VPS 504 S06 and S05 Valve Proving System Installation Instructions VPS 1 6 Gases Natural gas, air and other inert gases. NOT suitable for butane

More information

INSTRUCTION MANUAL Pressure Relief Device LPT

INSTRUCTION MANUAL Pressure Relief Device LPT INSTRUCTION MANUAL Pressure Relief Device LPT 5COV475800 LPT REV00 CONTENT: 1 SAFETY 1.1 Safety instructions 2 1.2 Specified applications 2 1.3 Safety notes on the equipment operation 2 2 PRESSURE RELIEF

More information

IEP SENSOR BRACKET CHECKOUT AND VERIFICATION. This is a non-hazardous test.

IEP SENSOR BRACKET CHECKOUT AND VERIFICATION. This is a non-hazardous test. Page 1 of 20 NEXT GENERATION GAS SYSTEM (NGGS ) IEP SENSOR BRACKET CHECKOUT AND VERIFICATION PROCEDURE 870-PROC-623 Revision A Goddard Space Flight Center Greenbelt, Maryland 20771 FEBRUARY 13, 2002 This

More information

WATER MADE EASY MARINE ENERGY MUNICIPAL INDUSTRIAL

WATER MADE EASY MARINE ENERGY MUNICIPAL INDUSTRIAL Capital Controls Series 71V3000 The Series 71V3000 electrically-heated vaporizer automatically vaporizes and superheats liquid chlorine, sulfur dioxide or ammonia at a rate controlled by the gas feed system.

More information

OEM Manual MODEL 2305 ECONOMICAL DIGITAL SINGLE CYLINDER SCALE

OEM Manual MODEL 2305 ECONOMICAL DIGITAL SINGLE CYLINDER SCALE OEM Manual MODEL 2305 ECONOMICAL DIGITAL SINGLE CYLINDER SCALE 1 These instructions generally describe the installation, operation, and maintenance of subject equipment. The manufacturer reserves the right

More information

Autocalibration Systems For In Situ Oxygen Analyzers

Autocalibration Systems For In Situ Oxygen Analyzers Product Data Sheet PDS 106-340AC SPS 4000, IMPS 4000, and MPS 3000 January, 1999 Autocalibration Systems For In Situ Oxygen Analyzers Cost-effective autocalibration systems for installations ranging from

More information

MANUAL GAS MANIFOLDS

MANUAL GAS MANIFOLDS MANUAL GAS MANIFOLDS Phoenix Pipeline Products Limited. Unit 8, McKenzie Industrial Park, Tel No.: 44 (0) 161 428 7200 Bird Hall Lane, Fax No.: 44 (0) 161 428 7010 Stockport, Email: info@p3-phoenix.com

More information

Nottingham Township 909 Sugar Run Road Eighty Four PA (724) Fax (724)

Nottingham Township 909 Sugar Run Road Eighty Four PA (724) Fax (724) Nottingham Township 909 Sugar Run Road Eighty Four PA 15330 (724) 348-5622 Fax (724) 348-8822 Swimming Pool Application Requirements SWIMMING POOL Any structure intended for swimming or recreational bathing

More information

Field Certification Certificate of Compliance

Field Certification Certificate of Compliance 1 Field Certification Certificate of Compliance Certificate: 2460594 Master Contract: 244849 Project: 2460594 Date Issued: 2011-12-23 Issued to: Sirio Sistemi Elettronici SpA Via Fleming 16 59100 Prato

More information

Accu-Tab Systems 1000 Series by Axiall Corporation

Accu-Tab Systems 1000 Series by Axiall Corporation Accu-Tab Systems 1000 Series by Axiall Corporation Installation and Operating Instructions Model 1050 DANGER: DO NOT MIX CHEMICALS! The Accu-Tab chlorinator is designed for use with Axiall approved tablets

More information

ADDENDUM NO. 3 TO THE BIDDING DOCUMENTS FOR UNIVERSITY OF ILLINOIS COLLEGE OF MEDICINE PEORIA INTERIOR RENOVATIONS

ADDENDUM NO. 3 TO THE BIDDING DOCUMENTS FOR UNIVERSITY OF ILLINOIS COLLEGE OF MEDICINE PEORIA INTERIOR RENOVATIONS ADDENDUM NO. 3 TO THE BIDDING DOCUMENTS FOR UNIVERSITY OF ILLINOIS COLLEGE OF MEDICINE PEORIA INTERIOR RENOVATIONS DATE: October 10 TH 2016 TO ALL BIDDERS BIDDING ON THE ABOVE PROJECT: All Bidders submitting

More information

Copeland Discus with CoreSense Diagnostics January 2011

Copeland Discus with CoreSense Diagnostics January 2011 Copeland Discus with CoreSense Diagnostics January 2011 Slide 1 1/27/2011 5:48 PM Discus with CoreSense Diagnostics Case Studies Supermarket In Columbus, Ohio Saves $4,500 With Discus with CoreSense Diagnostics

More information

2-1- Shipping Receiving Lifting Location on Site Installation Stages 6

2-1- Shipping Receiving Lifting Location on Site Installation Stages 6 NEUTRAL GROUNDING RESISTORS INSTALLATION, OPERATION & MAINTENANCE MANUAL Contents 1- SAFETY INSTRUCTIONS... 3 1-1- Compliance with Instructions in this Manual. 3 1-2- Guidance Notes Installation.... 3

More information

MODELS (2 foot Version) (4 foot Version)

MODELS (2 foot Version) (4 foot Version) INSTALLATION AND MAINTENANCE MANUAL DUROSITE LED LINEAR FIXTURE Document No: 9100-127-2571-99 Rev A April, 2016 MODELS (2 foot Version) (4 foot Version) ALL LAE ALL LBE These instructions contain important

More information

Permit and Inspection Requirements for Swimming Pools

Permit and Inspection Requirements for Swimming Pools Permit and Inspection Requirements for Swimming Pools Building Inspection Office (817) 503.1030 City of Colleyville 100 Main Street Colleyville, TX 76034 Inspection Request Line (817) 503.1172 Building

More information

SECTION DOMESTIC WATER PIPING

SECTION DOMESTIC WATER PIPING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions Specification Sections, apply to this Section. B. Related Sections

More information

Field Instruction. Protect Horizon Power employees and contractors from a potential hazard.

Field Instruction. Protect Horizon Power employees and contractors from a potential hazard. 2.15 Temporary Safety Barriers and/or Warning Signs Purpose This instruction sets out the minimum requirements for the installation and erection of temporary safety barriers and/or warning signs to: Protect

More information

Installation, operating and maintenance Instructions for Seemag bypass level indicator

Installation, operating and maintenance Instructions for Seemag bypass level indicator Issue: S Date: 05-09-14 Type G35 General information The Seetru bypass magnetic level indicator, abbreviate SEEMAG, serves to show the filling level of fluids in tanks, basins, tubes etc. The Seemag operates

More information

TECHNICAL DATA. Q = C v P S

TECHNICAL DATA. Q = C v P S January 6, 2012 Preaction 331a 1. Description Viking supervised Double-Interlocked Electric/Pneumatic Release Preaction Systems utilize the Viking G-3000P Valve. The small profile, lightweight, pilot-operated

More information

General Requirements of the NEC Advanced Course. Building Officials and Inspectors Educational Association

General Requirements of the NEC Advanced Course. Building Officials and Inspectors Educational Association General Requirements of the NEC Advanced Course Building Officials and Inspectors Educational Association General Requirements -NEC Course Outcome Explain general requirements found in Article 110 of the

More information

Residential Swimming pools

Residential Swimming pools City of Republic Community Development Department Residential Swimming pools REVISION DATE: JANUARY 2017 Swimming Pool Safety Definitions: Barrier Requirements: A) Application All swimming pools over 24

More information

FINDLAY TOWNSHIP BUILDING INSPECTION DEPT

FINDLAY TOWNSHIP BUILDING INSPECTION DEPT Page 1 of 7 FINDLAY TOWNSHIP BUILDING INSPECTION DEPT. RESIDENTIAL SWIMMING POOLS Permit application submittal requirements (As per the 2009 International Residential Code) NOTE: A building permit is required

More information

OPERATING PROCEDURES

OPERATING PROCEDURES OPERATING PROCEDURES 1.0 Purpose This element identifies Petsec s Operating Procedures for its Safety and Environmental Management System (SEMS) Program; it applies to all Petsec operations. Petsec is

More information

SWIMMING POOL BUILDING PERMIT REQUIREMENTS FOR THE UNINCORPORATED TERRITORY OF DOUGLAS COUNTY, KANSAS

SWIMMING POOL BUILDING PERMIT REQUIREMENTS FOR THE UNINCORPORATED TERRITORY OF DOUGLAS COUNTY, KANSAS SWIMMING POOL BUILDING PERMIT REQUIREMENTS FOR THE UNINCORPORATED TERRITORY OF DOUGLAS COUNTY, KANSAS ALL CONSTRUCTION SHALL BE BUILT IN ACCORDANCE WITH STANDARDS SET FORTH IN THE 2012 International Code

More information

SPECIFICATIONS - DETAILED PROVISIONS Section Butterfly Valves C O N T E N T S

SPECIFICATIONS - DETAILED PROVISIONS Section Butterfly Valves C O N T E N T S SPECIFICATIONS - DETAILED PROVISIONS Section 15103 - Butterfly Valves C O N T E N T S PART 1 - GENERAL... 1 1.01 REQUIREMENT... 1 1.02 VALVE MANUFACTURER... 1 1.03 GUARANTEE... 1 PART 2 - PRODUCT... 1

More information

Specialists in HTM Medical Gas Pipeline Equipment AVSU/Module Operating and Maintenance Instructions

Specialists in HTM Medical Gas Pipeline Equipment AVSU/Module Operating and Maintenance Instructions The Area Value Service Units and Module format (AVSU) provide a local gas isolation facility for use during normal installation and maintenance or in the event of an emergency. They are built in accordance

More information

AMITY TWP POOL REQUIREMENTS

AMITY TWP POOL REQUIREMENTS AMITY TWP POOL REQUIREMENTS Construction In-ground, Above-ground and Storable pools and Spas shall be designed and constructed in conformance with International Swimming Pool & Spa Code (ISPSC) Location

More information

Two-port seat valves

Two-port seat valves 4 345 Two-port seat valves with flange, PN16 VVF45... Two-port seat valves with flange, PN16 Spheroidal cast iron GGG-40 DN50...150 mm k vs 19...300 m 3 /h Stroke 20 or 40 mm Can be equipped with actuators

More information

HYDROVEX TTT Membrane Flow Regulator

HYDROVEX TTT Membrane Flow Regulator HYDROVEX TTT Membrane Flow Regulator INSTALLATION, OPERATION AND MAINTENANCE MANUAL PROJECT EQUIPMENT LOCATION EQUIPMENT DESCRIPTION HYDROVEX TTT REFERENCE N OF THE SUPPLIER MODEL N SERIAL N DATE OF FABRICATION

More information

NIV EAU MATIC ST User Manual Made in Canada

NIV EAU MATIC ST User Manual Made in Canada NIV EAU MATIC ST User Manual Made in Canada www.niveaumatic.com info@niveaumatic.com -2- Table of contents Introduction Section 1 Page 4 Installation Section 2 Pages 5 to 10 2.1 Control box 2.2 Sensor

More information

TITLE 16 STREETS AND SIDEWALKS, ETC 1 CHAPTER 1 EXCAVATIONS AND CUTS 2

TITLE 16 STREETS AND SIDEWALKS, ETC 1 CHAPTER 1 EXCAVATIONS AND CUTS 2 6- CHAPTER. EXCAVATIONS AND CUTS. 2. MISCELLANEOUS. TITLE 6 STREETS AND SIDEWALKS, ETC CHAPTER EXCAVATIONS AND CUTS 2 SECTION 6-0. Manner of excavating--barricades and lights--temporary sidewalks. 6-02.

More information

DuPage County Environmental, Safety, Health & Property Loss Control Program Hazardous Energy Control (Lockout/Tagout)

DuPage County Environmental, Safety, Health & Property Loss Control Program Hazardous Energy Control (Lockout/Tagout) Purpose: To provide the minimum requirements for the lockout or tagout of energy isolating devices whenever work is performed or servicing is done on County of DuPage machinery, equipment, vehicles and

More information

CONTROL TECHNOLOGY INC Middlebrook Pike, Knoxville, TN Phone FAX

CONTROL TECHNOLOGY INC Middlebrook Pike, Knoxville, TN Phone FAX CONTROL TECHNOLOGY INC. 5734 Middlebrook Pike, Knoxville, TN 3792 Phone 865.584.0440 www.controltechnology.com FAX 865.584.5720 CE Declaration of Conformity August 5, 205 Manufacturer: Control Technology

More information

TECHNICAL DATA. Q = C v P S

TECHNICAL DATA. Q = C v P S Page 1 of 13 1. DESCRIPTION The Viking 6 Model G-6000 Dry Valve Riser Assembly consists of a small profile, light weight, pilot operated valve that is used to separate the water supply from the dry sprinkler

More information

New Hampshire Public Utilities Commission CFR 49 Part 192 Regulations. MINIMUM Pipeline Safety Regulations

New Hampshire Public Utilities Commission CFR 49 Part 192 Regulations. MINIMUM Pipeline Safety Regulations New Hampshire Public Utilities Commission CFR 49 Part 192 Regulations MINIMUM Pipeline Safety Regulations Application for Jurisdictional LPG Operators 1 Pipeline Safety Regulations 49 CFR Part 192 (NOTE:

More information

Swimming Pools, Hot Tubs and Spas

Swimming Pools, Hot Tubs and Spas OLATHE FIRE DEPARTMENT BUILDING CODES 1225 S. Hamilton Circle Olathe, KS 66061 / Main: (913) 971-7900 / Fax: (913) 971-9812 Swimming Pools, Hot Tubs and Spas Definitions: Swimming Pool- Any structure intended

More information

SECTION CLIMBING WALLS. PART 1 GENERAL 1.1 SUMMARY A. This section includes the following:

SECTION CLIMBING WALLS. PART 1 GENERAL 1.1 SUMMARY A. This section includes the following: SECTION 131200 - CLIMBING WALLS PART 1 GENERAL 1.1 SUMMARY A. This section includes the following: 1. GFRC Rock Realistic Climbing Wall System B. Related Sections 1. Division 04 Unit Masonry 2. Division

More information

TECHNICAL DATA 3 MODEL G-3000 DRY VALVE RISER ASSEMBLY

TECHNICAL DATA 3 MODEL G-3000 DRY VALVE RISER ASSEMBLY Page 1 of 13 1. DESCRIPTION The Viking 3 Model G-3000 Dry Valve Riser Assembly is equipped with a small profile, light weight, pilot operated valve that is used to separate the water supply from the dry

More information

Significant Change to Dairy Heat Treatment Equipment and Systems

Significant Change to Dairy Heat Treatment Equipment and Systems Significant to Dairy Heat Treatment September 2008 Page 1 Significant to Dairy Heat Treatment Equipment and Systems September 2008 1 Background Requirements for the assessment of dairy heat treatment equipment

More information

BUBBLER CONTROL SYSTEM

BUBBLER CONTROL SYSTEM BUBBLER CONTROL SYSTEM Description: The HDBCS is a fully automatic bubbler system, which does liquid level measurements in water and wastewater applications. It is a dual air compressor system with, air

More information

TECHNICAL DATA. Q = C v P S

TECHNICAL DATA. Q = C v P S January 6, 2012 Preaction 333a 1. Description Viking supervised Surefire Preaction Systems Utilize the Viking G-3000P Valve. The small profile, lightweight, pilot-operated Viking G-3000P Valve comes complete

More information

ELECTRICAL (COMPREHENSIVE) SAFETY PROGRAM REGULATORY STANDARD: OSHA - 29 CFR CFR , ,

ELECTRICAL (COMPREHENSIVE) SAFETY PROGRAM REGULATORY STANDARD: OSHA - 29 CFR CFR , , ELECTRICAL (COMPREHENSIVE) SAFETY PROGRAM REGULATORY STANDARD: OSHA - 29 CFR 1910.331 335-29 CFR 1926.302, 1926.416, 1926.417 BASIS: The National Safety Council estimates that there are at least 300 deaths

More information

TECHNICAL DATA. Q= Cv S

TECHNICAL DATA. Q= Cv S Page 1 of 13 1. DESCRIPTION The Viking 4 inch Model G-4000 Dry Valve Riser Assembly consists of a small profile, light weight, pilot operated valve that is used to separate the water supply from the dry

More information

MANUAL DIRECT PURGE OPTION. UNION Instruments GmbH CWD2005 PLUS. General information, safety standards and regulations for direct purge option

MANUAL DIRECT PURGE OPTION. UNION Instruments GmbH CWD2005 PLUS. General information, safety standards and regulations for direct purge option MANUAL DIRECT PURGE OPTION UNION Instruments GmbH CWD2005 PLUS General information, safety standards and regulations for direct purge option Version: V1.00 Stand: 24.03.2010 Union Instruments GmbH Zeppelinstr.

More information

TECHNICAL DATA Q = C. v P S. 2 Model G-2000 Dry valve. Page 1 of 13

TECHNICAL DATA Q = C. v P S. 2 Model G-2000 Dry valve. Page 1 of 13 Page 1 of 13 1. Description The Viking 2 Model G-2000 Dry Valve Riser Assembly consists of a small profile, light weight, pilot operated valve that is used to separate the water supply from the dry sprinkler

More information

3800 SERIES END SUCTION PUMP REPAIR PARTS INDEX. Model Model 3804

3800 SERIES END SUCTION PUMP REPAIR PARTS INDEX. Model Model 3804 Model 3801 Model 3804 3800 SERIES END SUCTION PUMP REPAIR PARTS INDEX NOTE! To the installer: Please make sure you provide this manual to the owner of the equip ment or to the responsible party who maintains

More information

SWIMMING POOL, SPA, & HOT TUB GUIDELINES

SWIMMING POOL, SPA, & HOT TUB GUIDELINES SWIMMING POOL, SPA, & HOT TUB GUIDELINES A. Adopted construction codes and installation requirements 1. 2015 edition of the International Residential Code and Appendix Q, 2. 2014 edition of the National

More information

Accu-Tab Systems 2000 P Series by Axiall Corporation

Accu-Tab Systems 2000 P Series by Axiall Corporation Accu-Tab Systems 2000 P Series by Axiall Corporation Installation and Operating Instructions Models 2075 P 2150 P For NSF/ANSI-Standard 61 NSF STANDARD 61 applications use NSF/ANSI Standard 60 listed Axiall

More information

TECHNICAL DATA. Q = C v P S

TECHNICAL DATA. Q = C v P S Preaction 346a 1. Description The 6 Model G-6000P Electric Release Preaction System Riser Assembly can be used as a Single Interlock Preaction System with Electric Release, or as a Double Interlock Preaction

More information

AMTEC SUPPORT GRIPS STANDARD, HEAVY DUTY & CONDUIT GRIPS

AMTEC SUPPORT GRIPS STANDARD, HEAVY DUTY & CONDUIT GRIPS AMTEC SUPPORT GRIPS STANDARD, HEAVY DUTY & CONDUIT GRIPS DESIGNED TO HOLD THE WEIGHT FOR ELECTRICAL CABLE AS IT HANGS IN VERTICAL, SLOPING OR HORIZONTAL POSITIONS. EASILY INSTALLED AND REMOVED USING NO

More information

MUELLER. A Wall Type. Indicator Post. Reliable Connections. General Information 2. Technical Data/ Dimensions 3. Installation 4-5.

MUELLER. A Wall Type. Indicator Post. Reliable Connections. General Information 2. Technical Data/ Dimensions 3. Installation 4-5. Installation Instructions manual MUELLER table of contents PAGE A-20814 Wall Type General Information 2 Technical Data/ Dimensions Installation 4-5 Maintenance 6 Parts 7 Indicator Post! WARNING: 1. Read

More information