1 Improving Bicycle/Pedestrian Access at Select Rail Stations Wheaton Station, Montgomery County This document is part of a Transportation Planning Board project focused on identifying and documenting specific, high-impact bicycle and pedestrian investments that could improve access to and from rail stations around the Washington, D.C. region. This station profile summarizes the observations and findings for Wheaton Station in Montgomery County. For more background information on this initiative, see Page 11. Station Description Wheaton Station is a Washington Metropolitan Area Transit Authority (WMATA) Red Line station located in Montgomery County, Maryland. In 2013, WMATA reported an average of 4,094 eekday boardings at Wheaton, hich is significantly loer than the system average of 7,975. The station is bounded by Georgia Avenue to the southeast, Veirs Mill Road to the southest, and Reedie Drive to the north. There is a significant amount of multifamily housing to the north and east of the station, as ell as thriving retail nodes, including the Westfield Wheaton Mall to the station s est and north. The Wheaton CBD and (2012) calls for major redevelopment throughout the station area, facilitating increased density of residential, commercial/retail and office land uses. Redevelopment has already taken place on the east side of Georgia Avenue at the station, and on properties north of the station near Arcola Road, ith other redevelopments in the application process. Plan Revi Existing local and regional plans and studies ere revied to identify recommendations that ould improve pedestrian and/or bicycle access to the station. These recommendations ere compiled in a central database that includes a variety of attributes for each record, including location, modes served, type of improvement, estimated cost, etc. Pedestrian related improvements ere included if they ere located ithin one mile of the station; bicycling improvements if ithin three miles. Plans and studies revied for the Wheaton station included: Wheaton CBD and (2012) Countyide Bikays Functional Master Plan (2005) WMATA Bicycle and Pedestrian Program Station Needs (2011) 1 Corner of Reedie Drive and Georgia Avenue near Wheaton Station Field Work The Wheaton station as selected for field ork in consultation ith local planners in Montgomery County. The field evaluation focused on the folloing themes: a) pedestrian-oriented needs ithin one mile of the station, b) pedestrian and bicycle access needs that ould serve the higher density residential neighborhoods southeast and north of the station, and c) pedestrian and bicycle access improvements serving employment destinations such as the nearby public schools and adjacent shopping mall. Toole Design Group (TDG) used aerial photography and the U.S. Census OnTheMap tool to confirm hich field ork focus areas contained higher density housing and employment and generally limited field investigation to areas ithin to miles of the station. The field ork as conducted by Toole Design Group staff in October 2014.

2 Key Themes Related to Station Access Building upon the recommendations identified in the plan revi process, the TDG field ork team identified n, specific bicycle and pedestrian facility investments that could improve access to the Wheaton Metro Station. The field ork recommendations are shon on Page 5 and in the table at the end of this document. Key themes from the field ork include the folloing needs: A. Improved pedestrian accommodations in the area immediately surrounding the Metro Station site, hich is bounded by large state highays: Georgia Avenue, Viers Mill Road and University Boulevard The TDG field team identified a number of pedestrian access improvements in the immediate station area, including filling in gaps in the netork at the Viers Mill/Georgia Y and a suggested mid-block crossing of Georgia Avenue to serve n, high density residential community to the east. Potential midblock crossing location on Georgia Avenue B. High quality linkages to the multi-family residential areas south and east of the station South and east of the station, there is a need for higher quality bicycle and pedestrian linkages at the end of cul de sacs. Passagays linking to cul de sacs or a cul de sac to a park trail should be 6-10 feet ide, ADA accessible here feasible, and feature lighting and ayfinding signage for pedestrians and bicyclists. Landscaping, stormater treatments and erosion prevention infrastructure may also be needed to ensure the durability of capital improvements made in these types of locations. on Bucknell Drive lacks direct bicycle access C. High quality linkages and arterial crossings to existing and future development north of the station There is a need for improved station access for pedestrians and bicyclists traveling to/from redevelopment areas north and east of the station, as ell as crossing improvements on University Boulevard. The field ork team recommended bicycle and pedestrian improvements along Elkin Street and a climbing lane along Grandvi Avenue, rather than shared lane markings ( sharros ) as recommended in the CBD and. Existing curb to curb idths support the recommended climbing lane. Additionally, TDG recommended that all short connecting streets in the 2 Pedestrians using unstriped midblock crossing on University Boulevard

3 station area, such as Price Avenue, and any n small streets built as a part of redevelopment should have bike lanes, climbing lanes or shared lane markings depending on their idth and other design characteristics. Although existing County plans recommend sharros for Viers Mill Road and parts of Georgia Avenue, traffic volumes and speeds indicate that sharros may not be appropriate or provide adequate comfort for bicyclists traveling in these areas. D. Formal and upgraded linkages to the ring road around the shopping mall from the neighborhoods south and est of the mall Crossalk ithout ADA on Mall Ring Road The TDG field team identified multiple bicycle and pedestrian access improvements near and on the Wheaton Mall Ring Road, including curb ramp upgrades, parking lot crossing accommodations, stair runnels (i.e. rolling trays for bicycle heels), and reconstruction of aging pathays. Additionally, and trail improvements are recommended to link multi-family residential properties along University Boulevard est of the Mall to the Mall and Metro Station, and to link Nport Mill Middle School and Einstein High School to the ton center and Metro. Informal bicycle/pedestrian connection to Windham Lane from Faulkner Place to Mall Ring Road in disrepair Faded crossalk at Mall Entrance and Veirs Mill Road 3

4 Widen Bike Lane Maps of Plan Revi and Field Work Recommendations Esri, HERE, DeLorme, MapmyIndia, OpenStreetMap contributors, and the GIS user community MWCOG Wheaton Miles Plan revi recommendations Further study needed Repair/Resurface Climbing Lane Climbing Lane Install n Widen Widen Existing Repair/Resurface ÉM Metro Station Spot Improvements Intersection Trail/ Sidalk Wayfinding Linear Improvements Bike Parking On Street Bike Facility Bus Stop Improvement Trail/ Other Improvement Sidalk Wayfinding Lighting Other Improvement Esri, HERE, DeLorme, MapmyIndia, OpenStreetMap contributors, and the GIS user community MWCOG Wheaton Miles Field ork recommendations 4

5 n Install urther alk F sid needed study Sha rro Sh ar ro ne de Wi Sha Co ns tru ct Ne all n Inst alk sid Intersection Trail/ Sidalk Wayfinding Spot Improvements ro g tin Metro Station Sh ar xis rro M É c t Ne tn e sid ct N alk all Inst n lk a side den Wi uc alk side Con stru n Wide rro Sha Co ns tr Bike Lan Sh ar ane rro L bing Sha ln tal alk s n I de si Clim R / air ep ce rfa su e R Constru tn Lane uc n Install lk sida Climbing Co ns tr ro ro Shar Sh ar ro Repair/Resurface Bike Parking Bus Stop Improvement Other Improvement Linear Improvements On Street Bike Facility Trail/ Sidalk Wayfinding Lighting Other Improvement Esri, HERE, DeLorme, MapmyIndia, OpenStreetMap contributors, and the GIS user community MWCOG Wheaton Miles All area recommendations 5

6 Plan Revi and Field Work Recommendations STREET LOCATION IMPROVEMENT CATEGORY N Connection N Connection N Connection N Connection Amherst Ave University Blvd East Ave Upton Dr McComas Ave/ Douglas Ave Mall Ring Rd Blueridge Ave Valleyvi Dr/Mall Ring Rd Beteen Georgia Ave - Blueridge Ave, & Elkin St Beteen Georgia Ave - Blueridge Ave, & Elkin St East of Amherst Ave - north of Readie Dr Connection beteen Peregoy Dr & Wheaton Mall From Windham Ln to Arcola Ave From Amherst Ave & Sector Plan Boundary From Upton Dr to Mall Ring Rd From Hillsdale Dr & East Dr From Peregoy Dr & Amherst Dr From Faulkner Place to Reedie Dr entrance From Galt Ave to Amherst Ave From Hillsdale Dr to LB-3 IMPROVEMENT DESCRIPTION SOURCE Pedestrian/ADA Wheaton CBD and Pedestrian/ADA Wheaton CBD and Pedestrian/ADA Wheaton CBD and Pedestrian/ADA Wheaton CBD and Bicycle N Bike Lane Wheaton CBD and Bicycle Trail/ Wheaton CBD and Bicycle N Wheaton CBD and Bicycle N Wheaton CBD and Bicycle N Wheaton CBD and Bicycle N Wheaton CBD and Bicycle N Wheaton CBD and Bicycle N Wheaton CBD and Mall Ring Rd From LB-3 to SR-25 Bicycle N Wheaton CBD and Prichard Rd/Horde St Kensington Blvd Kensington Blvd Elkin St From Amherst Ave to Windham Ln From Upton Dr to Fenimore Rd/SR-21 From Veirs Mill Rd to Fenimore Rd/ SR-21 From Amherst Ave to Sector Plan Boundary Bicycle N Wheaton CBD and Bicycle N Wheaton CBD and Bicycle N Wheaton CBD and Bicycle N Wheaton CBD and 6

7 Plan Revi and Field Work Recommendations (continued) STREET LOCATION IMPROVEMENT CATEGORY Horde St From Prichard Rd/ Bicycle Carmody Dr to Wheaton Forest Park Boundary Blueridge Ave From Amherst Bicycle Ave to Sector Plan Boundary Georgia Ave From Windham Ln & Reedie Dr IMPROVEMENT DESCRIPTION Trail/ Trail/ SOURCE Wheaton CBD and Wheaton CBD and Bicycle N Wheaton CBD and Fenimore Rd From Galt Ave to Grandvi Ave Bicycle N Wheaton CBD and Grandvi Ave From Reedie Dr to Dason Ave Bicycle N Wheaton CBD and Galt Ave From Fenimore Rd to Dason Ave Bicycle N Wheaton CBD and Torrance Ct From Douglas Ave to Mall Ring Rd Bicycle N Wheaton CBD and Mall Ring Rd From Torrance Ct to Reedie Dr entrance Bicycle N Wheaton CBD and Reedie Dr From Mall Ring Rd to Amherst Ave Bicycle N Wheaton CBD and Windham Lane From Amherst Ave to Horde St Bicycle N Wheaton CBD and Veirs Mill Rd From Georgia Ave to Kensington Blvd Bicycle N Wheaton CBD and Windham Lane Upton Dr Plyers Mill Rd From Amherst Ave to the Sligo Creek Trail From Nport Mill Middle School to Upton Dr From Beach Dr to Georgia Ave Bicycle N Wheaton CBD and Bicycle 7 Trail/ Wheaton CBD and Bicycle N Countyide Bikays Functional Master Plan

8 Plan Revi and Field Work Recommendations (continued) STREET LOCATION IMPROVEMENT CATEGORY University Blvd From Sligo Creek Bicycle Parkay to Veirs Mill Rd Ernalls Ave Hickerson Dr Beteen Veirs Mill Rd and Grandvi Ave Grandvi Ave to Elkin St IMPROVEMENT DESCRIPTION Trail/ SOURCE Countyide Bikays Functional Master Plan Pedestrian/ADA Wheaton CBD and Pedestrian/ADA Wheaton CBD and From Hickerson Dr to University Blvd Pedestrian/ADA Wheaton CBD and Georgia Ave Veirs Mill to Slip Lane Pedestrian/ADA TCSP Fieldork Veirs Mill Rd Georgia Ave to Slip Lane Pedestrian/ADA Construct n TCSP Fieldork Bucknell Dr North dead end to Bucknell Terrace Bicycle Widen existing trail/ path TCSP Fieldork Windham Dr dead end to other dead end Combination Repair/resurface trail/path TCSP Fieldork Carmody Dr Alberti Dr to Horde St Bicycle N TCSP Fieldork Alberti Dr Inood Ave to Horde St Bicycle N TCSP Fieldork Elkin St Price Ave to Amherst Ave Bicycle N TCSP Fieldork N Street Leesborough Circle to Elkin to Blueridge Combination / More study needed for bike facility TCSP Fieldork Goat path beteen Melvin Grove Ct and Littleford Ln McComas Ave to Mall Ring Road Combination Trail/ TCSP Fieldork Existing path Faulkner Ct to Mall Ring Road Pedestrian/ADA Repair/resurface Trail/ TCSP Fieldork 8

9 Plan Revi and Field Work Recommendations (continued) STREET LOCATION IMPROVEMENT CATEGORY Valley Vi Dr University to Mall Combination Ring Road IMPROVEMENT DESCRIPTION Trail/ SOURCE TCSP Fieldork University Bl Nport Mill to Veirs Mill Combination Widen TCSP Fieldork Grandvi Ave Kensington to Reedie Bicycle N Climbing lane TCSP Fieldork Georgia Ave Reedie Dr to Veirs Mill Rd Pedestrian/ADA Widen TCSP Fieldork Fern Rd Reedie Dr to University Ave Bicycle N Climbing lane TCSP Fieldork Veirs Mill Rd at Reedie Dr Pedestrian/ADA Improved Crossalk WMATA Veirs Mill Rd at North bus entrance Pedestrian/ADA Repair curb ramp TCSP Fieldork Veirs Mill Rd at North bus entrance Pedestrian/ADA Combination TCSP Fieldork Georgia Ave halfay beteen Pritchard and Reedie Pedestrian/ADA N crossing location TCSP Fieldork Veirs Mill Rd Georgia Ave Pedestrian/ADA Improved crossalk TCSP Fieldork Reedie Dr Georgia Ave Pedestrian/ADA Combination TCSP Fieldork Reedie Dr Georgia Ave Pedestrian/ADA Address barrier or obstruction TCSP Fieldork Reedie Dr at Veirs Mill Rd Pedestrian/ADA Combination TCSP Fieldork Bucknell Dr Just north of Windham Dr Pedestrian/ADA Improved Crossalk TCSP Fieldork 9

10 Plan Revi and Field Work Recommendations (continued) STREET LOCATION IMPROVEMENT CATEGORY Bucknell Dr North and south Bicycle dead ends Bucknell Dr North and south dead ends Bicycle IMPROVEMENT DESCRIPTION Dead end connection Dead end connection Glenhaven Dr at Windham Dr Bicycle Dead end connection Jamaica Dr at Windham Dr Bicycle Dead end connection Windham Dr at east dead end by elementary school Bicycle Dead end connection Windham Dr At Francis Bicycle Dead end connection Windham Dr at Huntley Ave Bicycle Dead end connection University Bl at Elkin St Pedestrian/ADA N crossing location Torrance Dr at Mall Ring Road Bicycle Reconstruct stair for runnel SOURCE TCSP Fieldork TCSP Fieldork TCSP Fieldork TCSP Fieldork TCSP Fieldork TCSP Fieldork TCSP Fieldork TCSP Fieldork TCSP Fieldork Torrance Dr at Mall Ring Road Pedestrian/ADA N curb TCSP Fieldork Mall Ring Rd at Target entrance Pedestrian/ADA N crossalk TCSP Fieldork Georgia Ave at Veirs Mill Rd Pedestrian/ADA N crossalk TCSP Fieldork Georgia Ave at Veirs Mill Rd Pedestrian/ADA N crossalk TCSP Fieldork 10

11 Project Background The purpose of the Improving Bicycle/Pedestrian Access at Select Stations analysis is to identify and document specific, high-impact investments that ill improve multimodal access to and from rail stations around the Washington, D.C. region. This project as funded by a grant from the Federal Highay Administration s Transportation, Community and System Preservation (TCSP) Grant Program. Tenty-five selected stations ere identified among the region s Metro, VRE and MARC stations using to criteria: A) stations ith excess rail capacity (more people could take advantage of existing transit service at this location) and B) stations ith concentrations of employment and/or transit-dependent populations nearby. All of the selected stations are adopted Metropolitan Washington Council of Governments (MWCOG) Activity Centers. Existing local and regional plans for these stations (e.g. sector plans, station area plans, comprehensive plans, etc.) ere revied and pedestrian and bicycle facility recommendations ere complied into a central database. Additional field ork as conducted at a subset of the selected stations. Wheaton TPB Project Selected Stations Pentagon City, Arlington County Virginia Square, Arlington County Eisenhoer Avenue, City of Alexandria King Street, City of Alexandria Anacostia, District of Columbia Capitol Heights, District of Columbia Congress Heights, District of Columbia Friendship Heights, District of Columbia Minnesota Avenue, District of Columbia Mt. Vernon Square/7th St Convention Cntr, DC Rhode Island Avenue, District of Columbia Waterfront SEU, District of Columbia Dunn Loring/Merrifield Avenue, Fairfax County Franconia/Springfield, Fairfax County McLean, Fairfax County Silver Spring, Montgomery County Tinbrook, Montgomery County Wheaton, Montgomery County White Flint, Montgomery County Branch Ave, Prince George's County Largo Ton Center, Prince George's County N Carrollton, Prince George's County Prince George's Plaza, Prince George's County West Hyattsville, Prince George's County Woodbridge, Prince William County 11

Appendix 3 Transportation Analyses For more information, call the Transportation Division at Wheaton CBD and Vicinity Sector Plan

Appendix 3 Transportation Analyses For more information, call the Transportation Division at Wheaton CBD and Vicinity Sector Plan Appendix 3 Transportation Analyses For more information, call the Transportation Division at 301-495-4525 montgomery county planning board maryland-national capital park and planning commission Contents

More information

ITEM 7 Action April 19, 2017 Approval of Regional Bike to Work Day 2017 Proclamation. None

ITEM 7 Action April 19, 2017 Approval of Regional Bike to Work Day 2017 Proclamation. None ITEM 7 Action April 19, 2017 Approval of Regional Bike to Work Day 2017 Proclamation Staff Recommendation: Approve the Bike to Work Day 2017 Proclamation. Issues: Background: None In an effort to increase

More information

ADA Transition Plan. City of Gainesville FY19-FY28. Date: November 5, Prepared by: City Of Gainesville Department of Mobility

ADA Transition Plan. City of Gainesville FY19-FY28. Date: November 5, Prepared by: City Of Gainesville Department of Mobility ADA Transition Plan FY19-FY28 Date: November 5, 2018 Prepared by: City Of Gainesville Department of Mobility 1.0 INTRODUCTION 1.1 BACKGROUND The federal statute known as the Americans with Disabilities

More information

Agenda. Overview PRINCE GEORGE S PLAZA METRO AREA PEDESTRIAN PLAN

Agenda. Overview PRINCE GEORGE S PLAZA METRO AREA PEDESTRIAN PLAN PRINCE GEORGE S PLAZA METRO AREA PEDESTRIAN PLAN May 28, 2008 Agenda Welcome and introductions Project overview and issue identification Planning context and strengths Design challenges and initial recommendations

More information

APPENDIX E BIKEWAY PRIORITIZATION METHODOLOGY

APPENDIX E BIKEWAY PRIORITIZATION METHODOLOGY APPENDIX E BIKEWAY PRIORITIZATION METHODOLOGY INTRODUCTION The network of bikeways recommended in the Bicycle Master Plan is extensive and is likely to be only partially completed during the 25-year life

More information

MONTGOMERY COUNTY COUNCIL MEMORANDUM

MONTGOMERY COUNTY COUNCIL MEMORANDUM MONTGOMERY COUNTY COUNCIL R O C K V I L L E, M A R Y L A N D HANS RIEMER COUNCILMEMBER AT-LARGE MEMORANDUM To: T&E Committee From: Councilmember Hans Riemer Date: March 1, 2016 Re: Funding a Protected

More information

Preliminary Transportation Analysis

Preliminary Transportation Analysis Preliminary Transportation Analysis Goals of a Robust, Multimodal Transportation Network Safe Accessible/Connected Efficient Comfortable Context-Sensitive Motor Vehicle: Continue to analyze the data to

More information

SPRINGFIELD REVITALIZATION REPORT

SPRINGFIELD REVITALIZATION REPORT SPRINGFIELD REVITALIZATION REPORT August 2015 Homewood Suites Springfield Town Center Promenade 2 SPRINGFIELD OVERVIEW This report covers recent development activity in the Springfield Commercial Revitalization

More information

PRINCE GEORGE S PLAZA METRO AREA PEDESTRIAN PLAN

PRINCE GEORGE S PLAZA METRO AREA PEDESTRIAN PLAN PRINCE GEORGE S PLAZA METRO AREA PEDESTRIAN PLAN May 28, 2008 Agenda Welcome and introductions Project overview and issue identification Planning context and strengths Design challenges and initial recommendations

More information

7/23/2017 VIA . Michael Hanebutt City of Sacramento Community Development Department 300 Richards Boulevard, 3 rd Floor Sacramento, CA 95811

7/23/2017 VIA  . Michael Hanebutt City of Sacramento Community Development Department 300 Richards Boulevard, 3 rd Floor Sacramento, CA 95811 7/23/2017 VIA EMAIL Michael Hanebutt City of Sacramento Community Development Department 300 Richards Boulevard, 3 rd Floor Sacramento, CA 95811 RE: 65 th Street Apartments (DR17-220) Dear Mr. Hanebutt:

More information

Proposed Transportation Network

Proposed Transportation Network Proposed Transportation Network Goals and Vision This Plan includes goals, policies, and strategies that can be used to shape public and private transportation initiatives for the next decade. Throughout

More information

This page intentionally left blank.

This page intentionally left blank. This page intentionally left blank. COMMUNITY Coweta Community Overview Coweta Coweta, a residential community located in Wagoner County, is a suburb of Tulsa situated southeast of the metropolitan area

More information

Geo-coding of the 2012 WMATA Rail Survey. Travel Forecasting Subcommittee January 25, 2012 Clara Reschovsky

Geo-coding of the 2012 WMATA Rail Survey. Travel Forecasting Subcommittee January 25, 2012 Clara Reschovsky Geo-coding of the 2012 WMATA Rail Survey Travel Forecasting Subcommittee January 25, 2012 Clara Reschovsky 1 2012 WMATA Rail Survey Period of study: April 13 May 25, 2012 Forms distributed to 40% of riders

More information

If a person walks within this focus area, these are examples of the places he or she could walk to or from:

If a person walks within this focus area, these are examples of the places he or she could walk to or from: Portland Hillsdale Hillsdale Portland The Hillsdale focus area is located in the City of Portland. It is situated approximately three miles from the City of Portland s downtown, 5.5 miles from the City

More information

Chapter 9: Pedestrians and Bicyclists

Chapter 9: Pedestrians and Bicyclists Chapter 9: Pedestrians and Bicyclists Walking and bicycling are essential modes of transportation. These modes allow people to travel without contributing to congestion and air pollution, to access other

More information

Presentation Comments and Questions

Presentation Comments and Questions Presentation Comments and Questions The community had a number of questions regarding the master plan process and operational issues in and around the MARC rail station areas. The bullet points below are

More information

Table #6 VISION CHARACTERISTICS

Table #6 VISION CHARACTERISTICS Table #6 VISION White Flint is a place to live, work, play, shop, and walk with sufficient density to encourage quality redevelopment. Vibrant streets and consistent streetscapes are important. CHARACTERISTICS

More information

Bus Livability Grant: The Bus Stop Amenity Survey and Love Your Bus Stop Outreach Campaign

Bus Livability Grant: The Bus Stop Amenity Survey and Love Your Bus Stop Outreach Campaign Washington Metropolitan Area Transit Authority Bus Livability Grant: The Amenity Survey and Love Your Outreach Campaign Riders Advisory Council February 12, 2014 1 Background WMATA received a $1.875 million

More information

HYATTSVILLE TRANSPORTATION PLAN. City Council Update March 19, 2018

HYATTSVILLE TRANSPORTATION PLAN. City Council Update March 19, 2018 HYATTSVILLE TRANSPORTATION PLAN City Council Update March 19, 2018 AGENDA PROJECT GOALS DATA COLLECTION WHAT WE LEARNED NEXT STEPS PROJECT GOALS Identify bicycle and pedestrian needs of the city Evaluate

More information

COWETA HIGH SCHOOL AND EAST HIGHWAY 51

COWETA HIGH SCHOOL AND EAST HIGHWAY 51 COWETA HIGH SCHOOL AND EAST HIGHWAY 51 Lack of sidewalks along Ben Lumpkin Rd. Lack of crosswalks and ramps at intersection. Hwy 51 is wide to cross as a pedestrian. No ADA compliance or connection to

More information

ABOUT THE PROJECT. DOWNTOWN WEST Transportation Planning Study. Pennsylvania Ave. NW: H Street NW: Farragut. K St. NW. North. I St.

ABOUT THE PROJECT. DOWNTOWN WEST Transportation Planning Study. Pennsylvania Ave. NW: H Street NW: Farragut. K St. NW. North. I St. ABOUT THE PROJECT Downtown West seeks to improve east-west travel for pedestrians and cyclists on Pennsylvania Avenue NW and persons using public transit along H and I Streets NW. K St. NW North I St.

More information

Color your stress away

Color your stress away Color your stress away Learn about the Bicycle Master Plan s comfortable, low-stress bicycling network in Montgomery County. Unwind as you color the bicycling scenes. Check out montgomeryplanning.org/bikeplan

More information

FY Transportation Capital Improvement Plan Update Arlington Committee for Transportation Choices

FY Transportation Capital Improvement Plan Update Arlington Committee for Transportation Choices FY 2017-2026 Transportation Capital Improvement Plan Update Arlington Committee for Transportation Choices November 1, 2017 Forecasted Growth Arlington continues to grow with a shift towards multi-family

More information

SAFE ROUTES TO SCHOOL

SAFE ROUTES TO SCHOOL SAFE ROUTES TO SCHOOL Edgewood Elementary School Existing Conditions and ACTION PLAN > Oak Creek - Franklin Joint School District Table of Contents CONTEXT Enrollment Boundaries Enrollment

More information

Chapter 13 ORANGE COVE

Chapter 13 ORANGE COVE Chapter 13 ORANGE COVE This chapter describes the current status and future plans for biking and walking in the City of Orange Cove. RELATIONSHIP TO CITY PLANS AND POLICIES The Orange Cove General Plan

More information

NM-POLICY 1: Improve service levels, participation, and options for non-motorized transportation modes throughout the County.

NM-POLICY 1: Improve service levels, participation, and options for non-motorized transportation modes throughout the County. Transportation PRINCE WILLIAM COUNTY 2008 COMPREHENSIVE PLAN NON-MOTORIZED PLAN CONTENTS Goals, Policies, and Action Strategies Table 4 (Bike Facility Classifications and Descriptions) Table 5 (Bike Facility

More information

September The State of Bicycling in Montgomery County

September The State of Bicycling in Montgomery County September 2015 The State of Bicycling in Montgomery County The State of Bicycling in Montgomery County Abstract: This report documents the state of bicycling in Montgomery County as of September 2015.

More information

Countywide Transit Corridors Functional Master Plan

Countywide Transit Corridors Functional Master Plan Countywide Transit Corridors Functional Master Plan Makeover Montgomery II May 10, 2014 Master Plan Status Begun: August 2011 Planning Board Approved Draft Plan: July 2013 Council Approved Final Plan:

More information

MONTGOMERY COUNTY PLANNING DEPARTMENT THE MARYLAND-NATIONAL CAPITAL PARK AND PLANNING COMMISSION

MONTGOMERY COUNTY PLANNING DEPARTMENT THE MARYLAND-NATIONAL CAPITAL PARK AND PLANNING COMMISSION MONTGOMERY COUNTY PLANNING DEPARTMENT THE MARYLAND-NATIONAL CAPITAL PARK AND PLANNING COMMISSION MCPB Item No. 4 Date: 09-10-15 Scope of Work for the Bicycle Master Plan David Anspacher, Planner/Coordinator,

More information

Non-Motorized Transportation 7-1

Non-Motorized Transportation 7-1 Non-Motorized Transportation 7-1 Transportation facilities no longer mean just accommodating a vehicle powered by a combustion engine. Pedestrian and non-motorized facilities are important modes of travel

More information

5/7/2013 VIA . RE: University Village Safeway Expansion (P13-019)

5/7/2013 VIA  . RE: University Village Safeway Expansion (P13-019) 5/7/2013 VIA EMAIL David Hung, Associate Planner Community Development Department, Current Planning Division City of Sacramento 300 Richards Boulevard, 3 rd Floor Sacramento, CA 95811 RE: University Village

More information

Comments EXECUTIVE SUMMARY

Comments EXECUTIVE SUMMARY Comments 1. Under any Alternatives, MCDOT should provide better at-grade pedestrian crossing of Georgia Avenue and Forest Glen Road, including improved crosswalks with wider medians and adequate signal

More information

Watertown Complete Streets Prioritization Plan. Public Meeting #1 December 14, 2017

Watertown Complete Streets Prioritization Plan. Public Meeting #1 December 14, 2017 Watertown Complete Streets Prioritization Plan Public Meeting #1 December 14, 2017 Goals for Public Meeting Overview of MassDOT Complete Streets Funding Program Educate the community on Complete Streets

More information

Tigard Tigard Transit Center

Tigard Tigard Transit Center Tigard Tigard Transit Center Tigard Transit Center Tigard The Tigard Transit Center focus area is located in the City of Tigard. It is situated in the City of Tigard s downtown and is 4.5 miles from the

More information

Prince George s County plans, policies, and projects

Prince George s County plans, policies, and projects Prince George s County plans, policies, and projects Over 250 projects for trails, bikeways, designated bike lanes and sidewalk construction Trail projects that improve access to Metro Sidewalk and trail

More information

FM 1092/Murphy Road Access Management Study Pulic Meeting #1. Wednesday, August 31, :00 p.m. 8:00 p.m.

FM 1092/Murphy Road Access Management Study Pulic Meeting #1. Wednesday, August 31, :00 p.m. 8:00 p.m. FM 1092/Murphy Road Access Management Study Pulic Meeting #1 Wednesday, August 31, 2011 6:00 p.m. 8:00 p.m. Introductions Agency Partners H-GAC Missouri City TxDOT Introductions Consulting Team In Association

More information

CHAPTER 7 OF THE COMPREHENSIVE PLAN TRANSPORTATION Mobility for all Modes

CHAPTER 7 OF THE COMPREHENSIVE PLAN TRANSPORTATION Mobility for all Modes CHAPTER 7 OF THE COMPREHENSIVE PLAN TRANSPORTATION 2030 Adopted xxx, xx, xxxx Mobility for all Modes Chapter 7, Page 0, Draft version 48 Context and Vision Why Automobiles Alone are not the Answer Because

More information

Development of Arlington County s Marked Crosswalk Guidelines. Jon Lawler, P.E. Design Engineer Arlington County, VA

Development of Arlington County s Marked Crosswalk Guidelines. Jon Lawler, P.E. Design Engineer Arlington County, VA Development of Arlington County s Marked Crosswalk Guidelines Jon Lawler, P.E. Design Engineer Arlington County, VA April 13, 2015 Transportation System Users Residents Estimated 215,000 in 2014 Lowest

More information

City of Gainesville Transportation/Roadway Needs PROJECT SUMMARY

City of Gainesville Transportation/Roadway Needs PROJECT SUMMARY A1 Roadway Resurfacing $23,846,000 TYPE: Preservation of existing system Roadway resurfacing A2 Signal Replacement $6,000,000 TYPE: Preservation of existing system Replace traffic signals. B1 W 6th St

More information

CITY OF COCOA BEACH 2025 COMPREHENSIVE PLAN. Section VIII Mobility Element Goals, Objectives, and Policies

CITY OF COCOA BEACH 2025 COMPREHENSIVE PLAN. Section VIII Mobility Element Goals, Objectives, and Policies CITY OF COCOA BEACH 2025 COMPREHENSIVE PLAN Section VIII Mobility Element Goals, Objectives, and Policies Adopted August 6, 2015 by Ordinance No. 1591 VIII MOBILITY ELEMENT Table of Contents Page Number

More information

CHAPTER 1: INTRODUCTION

CHAPTER 1: INTRODUCTION CHAPTER 1: INTRODUCTION 7 8 UNION STATION GEORGETOWN: ALTERNATIVES ANALYSIS for PREMIUM TRANSIT SERVICE Premium transit is high-quality transit that offers improved reliability and speed, and includes

More information

City of Charlottesville Bicycle and Pedestrian Master Plan Update

City of Charlottesville Bicycle and Pedestrian Master Plan Update City of Charlottesville Bicycle and Pedestrian Master Plan Update September 17, 2014 I. Welcome and meeting overview II. Project status update III. Network overview IV. Break-out groups Pedestrian Network

More information

12/4/2016 VIA . RE: Grocery Outlet Del Paso (DR16-328)

12/4/2016 VIA  . RE: Grocery Outlet Del Paso (DR16-328) 12/4/2016 VIA EMAIL Ethan Meltzer, Assistant Planner City of Sacramento Community Development Department 300 Richards Blvd, 3 rd Floor Sacramento, CA 95811 RE: Grocery Outlet Del Paso (DR16-328) Dear Mr.

More information

San Bernardino County Non-Motorized Transportation Plan - Chapter 5

San Bernardino County Non-Motorized Transportation Plan - Chapter 5 City of Yucaipa Population 51,476 City Overview Yucaipa is located in the eastern portion of the San Bernardino Valley area, at the foot of the San Bernardino Mountains, between the Cities of Redlands

More information

Presentation of Staff Draft March 18, 2013 COUNTYWIDE TRANSIT CORRIDORS FUNCTIONAL MASTER PLAN

Presentation of Staff Draft March 18, 2013 COUNTYWIDE TRANSIT CORRIDORS FUNCTIONAL MASTER PLAN Presentation of Staff Draft March 18, 2013 COUNTYWIDE TRANSIT CORRIDORS FUNCTIONAL MASTER PLAN Public Outreach Fall 2011: Two community meetings/open houses Fall 2012: Three community meetings/open houses

More information

3/20/2015 VIA . Teresa Haenggi, Associate Planner Community Development Department 300 Richards Blvd. Sacramento, CA 95811

3/20/2015 VIA  . Teresa Haenggi, Associate Planner Community Development Department 300 Richards Blvd. Sacramento, CA 95811 3/20/2015 VIA EMAIL Teresa Haenggi, Associate Planner Community Development Department 300 Richards Blvd. Sacramento, CA 95811 RE: Ice Blocks (P14-062) Dear Ms. Haenggi: WALKSacramento has reviewed the

More information

Hennepin County Bicycle and Pedestrian Planning

Hennepin County Bicycle and Pedestrian Planning Hennepin County Bicycle and Pedestrian Planning 1 Value of bicycle and sidewalk systems Safety Livability Mobility Health Personal Finances Economic Sustainability Clean Air Recreation Parking and congestion

More information

San Jose Transportation Policy

San Jose Transportation Policy San Jose Transportation Policy Protected Intersections in LOS Policies to Support Smart Growth Presented by: Manuel Pineda City of San Jose Department of Transportation Bay Area Map San Francisco Oakland

More information

City of Hyattsville. Citywide Traffic Study and Transportation Plan. Sabra, Wang & Associates. February, 2010

City of Hyattsville. Citywide Traffic Study and Transportation Plan. Sabra, Wang & Associates. February, 2010 City of Hyattsville Citywide Traffic Study and Transportation Plan February, 2010 Outline Existing Conditions Recommendations Future Conditions Traffic Growth Development Capacity and Level of Service

More information

11/3/2017 VIA . RE: River Oaks Phase 2 (P17-051)

11/3/2017 VIA  . RE: River Oaks Phase 2 (P17-051) 11/3/2017 VIA EMAIL Ethan Meltzer, Assistant Planner City of Sacramento Community Development Department 300 Richards Blvd., 3 rd Floor Sacramento, CA 98811 RE: River Oaks Phase 2 (P17-051) Dear Mr. Meltzer:

More information

This page intentionally left blank.

This page intentionally left blank. This page intentionally left blank. COMMUNITY Glenpool Community Overview Glenpool Glenpool is a city of nearly 12,000 residents located in Tulsa County southwest of Tulsa and Jenks. The city is growing

More information

Proposed White Flint Separated Bike Lane Network September 2015

Proposed White Flint Separated Bike Lane Network September 2015 Proposed White Flint Separated Bike Lane Network September 2015 Abstract This report includes a proposed separated bike lane network for the White Flint Sector Plan area. Separated bike lanes create a

More information

RZC Appendix 8A Marymoor Subarea Street Requirements

RZC Appendix 8A Marymoor Subarea Street Requirements RZC Appendix 8A Marymoor Subarea Street Requirements For additional design details for Marymoor Subarea infrastructure, refer to the 2017 Marymoor Subarea Infrastructure Planning Report. STREET REQUIREMENTS

More information

Abstract. Source of Copies The Maryland-National Capital Park and Planning Commission 8787 Georgia Avenue Silver Spring, MD 20910

Abstract. Source of Copies The Maryland-National Capital Park and Planning Commission 8787 Georgia Avenue Silver Spring, MD 20910 1 Abstract This document contains an examination of and recommendations for transit, bicycle, and pedestrian infrastructure that will help create complete transportation options. With the approval and

More information

/ ARLINGTON COUNTY, VIRGINIA

/ ARLINGTON COUNTY, VIRGINIA / ARLINGTON COUNTY, VIRGINIA County Board Agenda Item Meeting of September 24, 2016 DATE: August 11, 2016 SUBJECT: Amendment of the Master Transportation Plan (MTP) Streets Element to include new local

More information

Roosevelt Estates Neighborhood Improvements

Roosevelt Estates Neighborhood Improvements Roosevelt Estates Neighborhood Improvements Transportation Alternatives Application May 5 th, 2016 Qualifying Activities Construction of on-road and off-road trail facilities for pedestrians, bicyclists,

More information

8/1/2018 VIA . Darcy Goulart City of Rancho Cordova Planning Department 2729 Prospect Park Drive Rancho Cordova, CA 95670

8/1/2018 VIA  . Darcy Goulart City of Rancho Cordova Planning Department 2729 Prospect Park Drive Rancho Cordova, CA 95670 8/1/2018 VIA EMAIL Darcy Goulart City of Rancho Cordova Planning Department 2729 Prospect Park Drive Rancho Cordova, CA 95670 RE: Towne Place Suites by Marriott Hotel (DD9806) Dear Ms. Goulart: WALKSacramento

More information

RESOLUTION NO ?? A RESOLUTION OF THE CITY OF NEPTUNE BEACH ADOPTING A COMPLETE STREETS POLICY

RESOLUTION NO ?? A RESOLUTION OF THE CITY OF NEPTUNE BEACH ADOPTING A COMPLETE STREETS POLICY RESOLUTION NO. 2018-?? A RESOLUTION OF THE CITY OF NEPTUNE BEACH ADOPTING A COMPLETE STREETS POLICY WHEREAS, safe, convenient, and accessible transportation for all users is a priority of the City of Neptune

More information

9/21/2016 VIA . RE: The Knot (DR16-270)

9/21/2016 VIA  . RE: The Knot (DR16-270) 9/21/2016 VIA EMAIL Garrett Norman, Assistant Planner City of Sacramento Community Development Department 300 Richards Boulevard, 3 rd Floor Sacramento, CA 95811 RE: The Knot (DR16-270) Dear Mr. Norman:

More information

ACTIVE TRANSPORTATION

ACTIVE TRANSPORTATION ACTIVE TRANSPORTATION Mobility 2040 Supported Goals Improve the availability of transportation options for people and goods. Support travel efficiency measures and system enhancements targeted at congestion

More information

The Nexus between Transportation Demand Your sub title Management (TDM), Transit Station Access, and Internal Station Circulation

The Nexus between Transportation Demand Your sub title Management (TDM), Transit Station Access, and Internal Station Circulation YOUR LINKING TITLE THE LINKS The Nexus between Transportation Demand Your sub title Management (TDM), Transit Station Access, and Internal Station Circulation Presentation Makeover Montgomery Location

More information

City of San Bernardino

City of San Bernardino City of San Bernardino Population 204,800 City Overview The City of San Bernardino is the largest City and the county seat of San Bernardino County, California. The City encompasses approximately 81 square

More information

Safe Streets. City of Lake Forest Park. March 21, 2017

Safe Streets. City of Lake Forest Park. March 21, 2017 Safe Streets City of Lake Forest Park March 21, 2017 1 01 WELCOME 2 Agenda WELCOME WHAT IS THIS PROJECT? CONTEXT DRAFT CITYWIDE PROJECTS EXERCISE INTRODUCTION 3 02 WHAT IS THIS PROJECT? 4 WHAT IS THIS

More information

Merrick and Memorial Neighborhood Study 5/14/2014 Public Meeting

Merrick and Memorial Neighborhood Study 5/14/2014 Public Meeting Merrick and Memorial Neighborhood Study 5/14/2014 Public Meeting Study Area April 9 Public Meeting Comments Summary Pedestrian Safety - A Walking Neighborhood Pedestrian traffic is very difficult A need

More information

5/31/2016 VIA . Arwen Wacht City of Sacramento Community Development Department 300 Richards Blvd., 3 rd Floor Sacramento, CA 95811

5/31/2016 VIA  . Arwen Wacht City of Sacramento Community Development Department 300 Richards Blvd., 3 rd Floor Sacramento, CA 95811 5/31/2016 VIA EMAIL Arwen Wacht City of Sacramento Community Development Department 300 Richards Blvd., 3 rd Floor Sacramento, CA 95811 RE: El Pollo Loco (P16-028) Dear Ms. Wacht: WALKSacramento has reviewed

More information

8/31/2016 VIA . RE: Freeport Arco Fuel Station (P16-039)

8/31/2016 VIA  . RE: Freeport Arco Fuel Station (P16-039) 8/31/2016 VIA EMAIL Garrett Norman, Assistant Planner City of Sacramento Community Development Department 300 Richards Boulevard, 3 rd Floor Sacramento, CA 95811 RE: Freeport Arco Fuel Station (P16-039)

More information

APPENDIX D: SACRAMENTO URBAN AREA TRANSPORTATION PRIORITIES

APPENDIX D: SACRAMENTO URBAN AREA TRANSPORTATION PRIORITIES 1 County County County County 2 Yolo Arterial Roadway Collector Roadway Urban Residential Street Rural Residential Roadway I-80 / U.S. 50 Bus/Carpool Lanes in both directions Richards Blvd PM Yol 80 0.237

More information

10/30/2012 VIA

10/30/2012 VIA 10/30/2012 VIA EMAIL David Hung, Associate Planner Community Development Department, Current Planning Division City of Sacramento 300 Richards Blvd., 3 rd Floor Sacramento, CA 95811 RE: The Cannery On-Site

More information

Meeting Schedule 7:00-7:15 Open House 7:15-7:45 Existing Conditions/Short-Term Improvements Study Presentation 7:45-8:00 Q&A Session 8:00-8:10

Meeting Schedule 7:00-7:15 Open House 7:15-7:45 Existing Conditions/Short-Term Improvements Study Presentation 7:45-8:00 Q&A Session 8:00-8:10 Meeting Schedule 7:00-7:15 Open House 7:15-7:45 Existing Conditions/Short-Term Improvements Study Presentation 7:45-8:00 Q&A Session 8:00-8:10 Long-Term Study Presentation 8:10-8:40 Table Discussions 8:40-9:00

More information

PenPlace SPRC #6. September 27, DRAFT

PenPlace SPRC #6. September 27, DRAFT PenPlace SPRC #6 1 Agenda Site and Project Overview Multiple Transportation Options Traffic Analysis Neighborhood Analysis Street Network Street Sections/Sidewalk Width Pedestrian/Bicycle Circulation Secure

More information

WELCOME. Thank you for joining us at the Second Public Workshop for the Carlsbad Pedestrian Master Plan. We look forward to receiving your feedback.

WELCOME. Thank you for joining us at the Second Public Workshop for the Carlsbad Pedestrian Master Plan. We look forward to receiving your feedback. City of Carlsbad Pedestrian Master Plan: WELCOME WELCOME Please Sign In Provide Input at Flip Charts Review Boards Presentation of Draft Plan Thank you for joining us at the Second Public Workshop for

More information

SR-203 Sidewalks and Town-Wide Mobility Improvements. Town Council Presentation September 7, 2016

SR-203 Sidewalks and Town-Wide Mobility Improvements. Town Council Presentation September 7, 2016 SR-203 Sidewalks and Town-Wide Mobility Improvements Town Council Presentation September 7, 2016 SR-203 Sidewalks and Town- Wide Mobility Improvements SR-203 Sidewalks and Appurtenances Town-Wide Mobility

More information

Appendix P (Version 2) Bikeway Projects in Currently Approved Plans. Planned Improvements from Sector & Area Plans that have been added to the MTP

Appendix P (Version 2) Bikeway Projects in Currently Approved Plans. Planned Improvements from Sector & Area Plans that have been added to the MTP Appendix P (Version 2) Bikeway Projects in Currently Approved Plans Key: Removals Scope Changes Question Keep this in plan? = Included on map O = Not Included on map Planned Improvements from Sector &

More information

Bus Rapid Transit Plans

Bus Rapid Transit Plans Twin Cities Region Bus Rapid Transit Plans ULI Minnesota Workshop Connecting Bus Rapid Transit to the Community December 15, 2009 John Levin Director of Service Development Metro Transit Metropolitan Area

More information

11/28/2016 VIA

11/28/2016 VIA 11/28/2016 VIA EMAIL Ethan Meltzer, Assistant Planner City of Sacramento Community Development Department 300 Richards Blvd., 3 rd Floor Sacramento, Ca 95811 RE: Natomas Corporate Center Commercial Building

More information

ARLINGTON COUNTY, VIRGINIA

ARLINGTON COUNTY, VIRGINIA ARLINGTON COUNTY, VIRGINIA County Board Agenda Item Meeting of October 15, 2016 DATE: October 7, 2016 SUBJECT: Adoption of amendments to the Master Transportation Plan (MTP) to create a new Pedestrian

More information

San Bernardino County Non-Motorized Transportation Plan - Chapter 5

San Bernardino County Non-Motorized Transportation Plan - Chapter 5 City of Upland Population 76,106 City Overview The City of Upland was incorporated on May 15, 1906, after previously being named North Ontario. The City was originally established as an irrigation colony

More information

Chapter 6 Transportation Plan

Chapter 6 Transportation Plan Chapter 6 Transportation Plan Transportation Plan Introduction Chapter 6 Transportation Plan Transportation Plan Introduction This chapter describes the components of Arvada s transportation system, comprised

More information

Fitting Light Rail through Well-established Communities

Fitting Light Rail through Well-established Communities Fitting Light Rail through Well-established Communities San Francisco 2008 Michael D. Madden Chief, Project Development, Maryland Transit Administration Project Setting Located inside the Capital Beltway

More information

CHAPTER IV Transportation

CHAPTER IV Transportation IV. TRANSPORTATION Transportation serves as an integral component of the overall revitalization efforts for Marlboro Pike. The transportation system in this area is intended to complement the area in support

More information

Planned Improvements from Sector & Area Plans that have been added to the MTP

Planned Improvements from Sector & Area Plans that have been added to the MTP Appendix P Bikeway Projects in Currently Approved Plans Planned Improvements from Sector & Area Plans that have been added to the MTP Airport Viaduct Trail Connection to National Airport Implement a pedestrian/bicycle

More information

7 NE 145TH STREET STATION TOD POTENTIAL

7 NE 145TH STREET STATION TOD POTENTIAL 7 NE 145TH STREET STATION TOD POTENTIAL Key Findings The 145th Street Station area has limited TOD potential, primarily because of its location in an area that is currently zoned predominantly single-family

More information

RE: Park Plaza Walgreens (P12-016)

RE: Park Plaza Walgreens (P12-016) 12/5/2014 VIA EMAIL David Hung, Associate Planner City of Sacramento Community Development Department 300 Richards Blvd., 3rd Floor Sacramento, CA 95811 RE: Park Plaza Walgreens (P12-016) Dear Mr. Hung:

More information

MONTGOMERY COUNTY PLANNING DEPARTMENT THE MARYLAND-NATIONAL CAPITAL PARK AND PLANNING COMMISSION

MONTGOMERY COUNTY PLANNING DEPARTMENT THE MARYLAND-NATIONAL CAPITAL PARK AND PLANNING COMMISSION MONTGOMERY COUNTY PLANNING DEPARTMENT THE MARYLAND-NATIONAL CAPITAL PARK AND PLANNING COMMISSION MCPB Item No. 5 Date: 12/3/15 Draft White Flint Separated Bike Lanes Network David Anspacher, Functional

More information

McLEAN CITIZENS ASSOCIATION

McLEAN CITIZENS ASSOCIATION McLEAN CITIZENS ASSOCIATION RESOLUTION DULLES RAIL SUPPLEMENTAL EIS With ATTACHMENT A - PEDESTRIAN AND BICYCLE ACCESS ISSUES DULLES CORRIDOR RAIL STATIONS IN TYSONS CORNER (Charts - 7 pages) Approved by

More information

WELCOME! Please complete a comment sheet as we value your feedback. 4 pm to 8 pm. September 15, Hosted by: AECOM on behalf of City of Calgary

WELCOME! Please complete a comment sheet as we value your feedback. 4 pm to 8 pm. September 15, Hosted by: AECOM on behalf of City of Calgary WELCOME! Thank you for attending our open house. There will be no formal presentation today so please take the time to read the boards. If you have any questions, please do not hesitate to approach one

More information

CITY OF PITTSBURGH. City of Pittsburgh Active Transportation Profile REGIONAL ACTIVE TRANSPORTATION PLAN FOR SOUTHWESTERN PENNSYLVANIA

CITY OF PITTSBURGH. City of Pittsburgh Active Transportation Profile REGIONAL ACTIVE TRANSPORTATION PLAN FOR SOUTHWESTERN PENNSYLVANIA REGIONAL ACTIVE TRANSPORTATION PLAN FOR SOUTHWESTERN PENNSYLVANIA 1 2 ACTIVE TRANSPORTATION AT A GLANCE Trails & Bike Routes 270 miles 28 miles 41 miles 24 miles 3 F A C I L I T I E S Facility Metrics

More information

ACTION TRANSMITTAL No

ACTION TRANSMITTAL No Transportation Advisory Board of the Metropolitan Council of the Twin Cities DATE: August 25, 2016 TO: FROM: ACTION TRANSMITTAL No. 2016-47 Technical Advisory Committee TAC Funding and Programming Committee

More information

N. Frederick Street to N. Manchester Street

N. Frederick Street to N. Manchester Street November 20, 2014 N. Frederick Street to N. Manchester Street Goals and Summary, November 2007 Map, December 2007 Bicycle Element, July 2008 Pedestrian Element, July 2008 Demand and System Management,

More information

This page intentionally left blank.

This page intentionally left blank. This page intentionally left blank. Community Plan Skiatook Community Overview Skiatook Skiatook is a growing city located approximately 14 miles north of downtown Tulsa with its main street, W.C. Rogers

More information

Clackamas County Comprehensive Plan

Clackamas County Comprehensive Plan ROADWAYS The County s road system permits the movement of goods and people between communities and regions, using any of a variety of modes of travel. Roads provide access to virtually all property. They

More information

MCA Member Meeting: Tysons Update. Fairfax County Department of Transportation November 13, 2017

MCA Member Meeting: Tysons Update. Fairfax County Department of Transportation November 13, 2017 MCA Member Meeting: Tysons Update Fairfax County Department of Transportation November 13, 2017 Presentation Overview Balancing Land Use and Transportation How Are We Doing? Studies and Projects Neighborhood

More information

Project Description Form 8EE

Project Description Form 8EE Project Description Form 8EE Basic Project Information Submitting Jurisdiction/Agency: Town of Dumfries Project Title: Route 1 (Fraley Blvd) Widening: Brady's Hill Road to Dumfries Road Project Location:

More information

Solana Beach Comprehensive Active Transportation Strategy (CATS)

Solana Beach Comprehensive Active Transportation Strategy (CATS) Solana Beach Comprehensive Active Transportation Strategy (CATS) 3.0 Goals & Policies The Solana Beach CATS goals and objectives outlined below were largely drawn from the Solana Beach Circulation Element

More information

FI-2 I-66 Between Route 29, Lee Highway and Route 15, James Madison Highway

FI-2 I-66 Between Route 29, Lee Highway and Route 15, James Madison Highway TRANSPORTATION PLAN INTENT Transportation is the key to the economic and social development of Prince William County and especially to the I 66/Route 29 Sector Plan area. This includes transportation for

More information

VIRGINIA RAILWAY EXPRESS

VIRGINIA RAILWAY EXPRESS PREPARING FOR THE NEXT QUARTER-CENTURY Arlington County Board Work Session June 28, 2017 1 TODAY S PRESENTATION VRE Overview VRE in Arlington County VRE System 2040 Plan Future Vision for Crystal City

More information

Pedestrian Transportation Plan

Pedestrian Transportation Plan Pedestrian Transportation Plan for Madison, Wisconsin ADOPTED PLAN September 1997 September, 1997 I am excited to introduce the Pedestrian Transportation Plan for Madison, Wisconsin. Unanimously adopted

More information

ACTION TRANSMITTAL No

ACTION TRANSMITTAL No Transportation Advisory Board of the Metropolitan Council of the Twin Cities ACTION TRANSMITTAL No. 2016-15 DATE: January 14, 2016 TO: TAC Planning Committee PREPARED BY: Steven Elmer (651) 602-1756 SUBJECT:

More information

Chapter 7. Transportation. Transportation Road Network Plan Transit Cyclists Pedestrians Multi-Use and Equestrian Trails

Chapter 7. Transportation. Transportation Road Network Plan Transit Cyclists Pedestrians Multi-Use and Equestrian Trails Chapter 7 Transportation Transportation Road Network Plan Transit Cyclists Pedestrians Multi-Use and Equestrian Trails 7.1 TRANSPORTATION BACKGROUND The District of Maple Ridge faces a number of unique

More information

6/14/2013 VIA . Evan Compton, Associate Planner Community Development Department City of Sacramento 300 Richards Blvd Sacramento, CA 95814

6/14/2013 VIA  . Evan Compton, Associate Planner Community Development Department City of Sacramento 300 Richards Blvd Sacramento, CA 95814 6/14/2013 VIA EMAIL Evan Compton, Associate Planner Community Development Department City of Sacramento 300 Richards Blvd RE: Sacramento Natural Foods Co-Op (P13-025) Dear Mr. Compton: WALKSacramento appreciates

More information