CEE 2720 Carnegie TOD Recommendations Traffic Group 4/26/12
|
|
- Belinda Rich
- 5 years ago
- Views:
Transcription
1 CEE 2720 Carnegie TOD Recommendations Traffic Group 4/26/12
2 Outline Data Collection Analysis of Current and Future Conditions Recommendations
3 Data Collection We collected turning movement count data at six intersections: Mansfield and Walnut (unsignalized) Mansfield and Broadway Mansfield and Campbell s Run Busway and Campbell s Run Mansfield, Jefferson, and Main Main Street and Third Street We used Synchro to analyze levels of service at each
4
5 Methodology Base: To determine future base volumes, we grew the existing traffic by 1% (linearly) for 10 years to get 2022 volumes. - Performed Highway Capacity Manual (HCM) capacity analysis at each intersection.
6
7 Methodology Trip Distribution: reduced trips generated by each land use by 5% to account for transit use. Then determined distribution of entering and exiting traffic for the TAZ using existing proportions. Distributed the trips for each new land use through the network using these proportions.
8
9
10
11
12
13
14 Methodology Combined: To determine projections for the combined condition, we added the trips generated by new land use to 2022 base volumes. Performed HCM capacity analysis at each intersection.
15
16 Level of Service Analysis
17 Mansfield and Walnut Existing Future Base Future Combined Northbound C C C Southbound B C D Eastbound A A B Westbound A A A HCM LOS A A A Average Delay
18 Mansfield and Broadway Existing Future Base Future Combined Northbound E E F Southbound D D D Eastbound A B B Westbound A A B HCM LOS B B C Average Delay
19 Mansfield and Campbell s Run Existing Future Base Future Combined Northbound D D D Southbound D D D Eastbound D D D Westbound C C E HCM LOS D D D Average Delay
20 Campbell s Run and Busway (actuation only on Busway) Existing Future Base Future Combined Northbound A A A Southbound A A A Eastbound E E E Westbound E E E HCM LOS A A A Average Delay
21 Mansfield, Jefferson, and West Main Existing Future Base Future Combined Northbound E E E Northwest E E E Eastbound A A C Westbound A A B HCM LOS B B C Average Delay
22 Main and Third Existing Future Base Future Combined Northbound E E E Eastbound A B B Westbound A A B HCM LOS B B C Average Delay
23
24
25
26 Recommendations
27 Road Diet We analyzed a road diet scenario using Synchro The Level-of-Service will not degrade below D for any intersection in the study area with mitigation measures Thus, we concur with Trans Associates recommendation for a road diet from Cubbage Street to Jefferson Street We also recommend extending the road diet from Jefferson Street to the intersection of Chestnut Street (where Mansfield becomes one-way)
28 Road Diet Cross Section (TA) Courtesy Trans Associates
29 Road Diet Pros No significant degradation of vehicle level of service Increases pedestrian and bicycle connectivity Installs missing sidewalk between intersections Signal equipment and pedestrian ramp upgrades at each intersection Allows for streetscape type beautification
30 Road Diet Cons Not a low cost solution Potential for controversy with commuters Scope of project may require the project be to completed in phases
31 Traffic Optimize signal timings and splits Update all signal heads to LED bulbs (currently only installed at Jefferson Street) 30 Percent Brighter (FHWA) More Energy Efficient Last Longer Courtesy FHWA
32 Pedestrians Install missing sidewalk connections Jefferson looking towards Mansfield Mansfield looking towards Jefferson Between Mansfield and Jefferson
33 Pedestrians We recommend that all curb ramps be upgraded in accordance with ADA standards (including truncated domes) Remove Install
34 Pedestrians We recommend repainting crosswalks for a consistent scheme of diagonal or perpendicular markings Or Remove Install Install
35 Pedestrians All Pedestrian signals should be retrofitted with countdown timers Remove Remove Install
36 Pedestrians A sidewalk should connect the crossing at Jefferson to the opening where pedestrians cross the railroad or crosswalk should be removed
37 Pedestrians Install signing at railroad crossing at busway Also, install rubber surfacing at crossing Reduces maintenance (FHWA) Reduces change in level (FHWA) Upgrade Install Courtesy NYDOT Install Courtesy FHWA
38 Transit At present, the Carnegie station is performing well below capacity, at LOS A even with future growth ACTA provides shuttle services between the station and job sites, but currently has low ridership We recommend public outreach to improve ridership and take advantage of the excess ridership capacity
39 Parking Previous recommendations: 366-space parking structure in place of the park-and-ride lot With the bus station operating well under capacity, we recommend studying the possibility of an additional level in the parking garage With the road diet, we hope to encourage pedestrian activity and reduce the increase in parking demand
40 References ftp://ftp.dot.state.pa.us/planning/pcti/2010-data/ /carnegie%20road%20diet%20report% pdf %20Pedestrian%20Treatments%20at%20Crossings%20ERCC.pdf
41 Questions? James Smith Douglas Smith Lindsay Meyers Chelsey Ackerman Nicole Bonomo Alaina Elias Joshua Cumberland Matthew Gilfillan Patrick Ryan Daniel Kennevan Ruth Muthoga Gregory Turko David Valko Zachary Visgarda Corey Woloschi Bradley Yagla
STH 57 & STH 100 Intersection Village of Brown Deer Milwaukee County November 2015
STH 57 & STH 100 Intersection Village of Brown Deer Milwaukee County November 2015 Introduction How we got to here WIS 57 Bridge over WIS 100 in need of replacement Local support favors At-Grade Intersection
More informationFigure 1: East West Connector Alignment Alternatives Concept Drawing
Page 2 of 9 Figure 1: East West Connector Alignment Alternatives Concept Drawing The Montebello Drive extension will run north south and connect Wilsonville Road to the Boones Ferry Road to Brown Road
More informationTRAFFIC IMPACT ANALYSIS
TRAFFIC IMPACT ANALYSIS FOR THE CHAMPAIGN UNIT#4 SCHOOL DISTRICT PROPOSED HIGH SCHOOL (SPALDING PARK SITE) IN THE CITY OF CHAMPAIGN Final Report Champaign Urbana Urbanized Area Transportation Study 6/24/2014
More informationAppendix C. NORTH METRO STATION AREA TRAFFIC IMPACT STATEMENT 88th Avenue Station
Appendix C NORTH METRO STATION AREA TRAFFIC IMPACT STATEMENT 88th Avenue Station Prepared for: Regional Transportation Department and URS Corporation as part of the North Metro EIS David Evans and Associates,
More informationTraffic Impact Study for Rolling Ridge Redevelopment
Traffic Impact Study for Rolling Ridge Redevelopment Webster Groves, Missouri October 19, 2018 Prepared For: Gershman Commercial Real Estate 150 North Meramec Avenue Suite 500 St. Louis, Missouri 63105
More informationTRAFFIC ASSESSMENT River Edge Colorado
TRAFFIC ASSESSMENT River Edge Colorado Submitted by: Fehr & Peers 621 17th Street, Ste. 231 Denver, CO 8293 (33) 296-43 December, 21 App. M-2 Traffic Assessment River Edge Colorado December 21 TABLE OF
More informationTraffic Impact Study WestBranch Residential Development Davidson, NC March 2016
Traffic Impact Study WestBranch Residential Development Davidson, NC March 216 TRAFFIC IMPACT STUDY FOR THE WestBranch Residential Development LOCATED IN DAVIDSON, NC Prepared For: Lennar Carolinas, LLC
More informationHarrah s Station Square Casino
Transportation Analysis Harrah s Station Square Casino Pittsburgh, Pennsylvania Submitted To: City of Pittsburgh and Pennsylvania Gaming Control Board Prepared By: DKS Associates GAI Consultants December
More informationALLEY 24 TRAFFIC STUDY
ALLEY 24 TRAFFIC STUDY in City of Frostburg, Maryland January 2013 3566 Teays Valley Road Hurricane, WV Office: (304) 397-5508 www.denniscorporation.com Alley 24 Traffic Study January 2013 Frostburg, Maryland
More informationCITY OF OAKLAND. 27th Street Bikeway Feasibility and Design. Final Report (v3) March 23, Kimley-Horn and Associates, Inc.
CITY OF OAKLAND 27th Street Bikeway Feasibility and Design Final Report (v3) March 23, 2007 PREPARED BY: Kimley-Horn and Associates, Inc. Table of Contents 1. Introduction 3 2. 27 th Street/Bay Place Corridor
More informationGrant Avenue Streetscape
REPORT TYPE GOES HERE Grant Avenue Streetscape PREPARED FOR City of Manassas 9027 Center Street Manassas, VA 20110 PREPARED BY 8300 Boone Boulevard Suite 700 Vienna, Virginia 22182 571.389.8121 July 31,
More informationDate: September 7, Project #: Re: Spaulding Youth Center Northfield, NH Property. Traffic Impact Study
To: Ms. Susan C. Ryan Spaulding Youth Center 72 Spaulding Road Northfield, NH 03276 Date: September 7, 2017 Project #: 52455.00 From: Robin Bousa Director of Transportation Systems Re: Spaulding Youth
More informationTransportation Setting
Transportation Setting Operational Analysis Study Area and Periods The study area consists of the following intersections: 1. Serramonte Boulevard/I-28 Southbound Ramps 2. Serramonte Boulevard/I-28 rthbound
More information133 rd Street and 132 nd /Hemlock Street 132 nd Street and Foster Street MINI ROUNDABOUTS. Overland Park, Kansas
133 rd Street and 132 nd /Hemlock Street 132 nd Street and Foster Street MINI ROUNDABOUTS Overland Park, Kansas September 1, 2017 TABLE OF CONTENTS 1. INTRODUCTION... 1 2. LITERATURE REVIEW... 1 3. CONCEPT
More informationTRANSPORTATION ANALYSIS REPORT US Route 6 Huron, Erie County, Ohio
TRANSPORTATION ANALYSIS REPORT US Route 6 Huron, Erie County, Ohio December 12, 2012 Prepared for: The City of Huron 417 Main Huron, OH 44839 Providing Practical Experience Technical Excellence and Client
More informationCanarsie Tunnel Repairs: Planning Ahead for the Crisis
Canarsie Tunnel Repairs: Planning Ahead for the Crisis Beginning in April 2019, the Canarsie Tunnel between Brooklyn and Manhattan will close for 15 months, affecting over 400,000 daily riders of the L
More informationEvaluation of M-99 (Broad Street) Road Diet and Intersection Operational Investigation
Evaluation of M-99 (Broad Street) Road Diet and Intersection Operational Investigation City of Hillsdale, Hillsdale County, Michigan June 16, 2016 Final Report Prepared for City of Hillsdale 97 North Broad
More informationHuntington Station Metro Zone / North Kings Highway Concept Plan
Summary Narrative of Huntington Station Metro Zone / North Kings Highway Concept Plan Located in Fairfax County, Virginia prepared for A.J. Dwoskin & Associates, Inc.. 9302 Lee Highway, Suite 300 Fairfax,
More informationTransportation Impact Study for Abington Terrace
Transportation Impact Study for Abington Terrace Abington Township, Montgomery County, PA Sandy A. Koza, P.E., PTOE PA PE License Number PE059911 Prepared by McMahon Associates, Inc. 425 Commerce Drive,
More informationTypical Cross Section: DOWNTOWN (Observer Highway - 8th Street)
Typical Cross Section: DOWNTOWN (Observer Highway - 8th Street) DRAFT SEPTEMBER 23, 14 1 Washington Street Typical Block Downtown Typical Block: DOWNTOWN (Observer Highway - 8th Street) New crosswalks
More information4. ENVIRONMENTAL IMPACT ANALYSIS 9. TRANSPORTATION AND TRAFFIC
4. ENVIRONMENTAL IMPACT ANALYSIS 9. TRANSPORTATION AND TRAFFIC 4.9.1 INTRODUCTION The following section addresses the Proposed Project s impact on transportation and traffic based on the Traffic Study
More informationDate: April 4, Project #: Re: A Street/Binford Street Traffic/Intersection Assessment
To: Peter Cavanaugh General Electric From: David Bohn, PE Ryan White, PE Date: April 4, 217 Project #: 13421. Re: / Traffic/Intersection Assessment Consistent with the Cooperation Agreement between the
More informationTraffic Circulation Study for Neighborhood Southwest of Mockingbird Lane and Airline Road, Highland Park, Texas
ARIZONA TEXAS NEW MEXICO OKLAHOMA February 13, 2015 Mr. Meran Dadgostar P.E., R.S. Town of Highland Park 4700 Drexel Dr. Highland Park, Texas 75205 Re: Traffic Circulation Study for Neighborhood Southwest
More informationTRAFFIC IMPACT STUDY And A TRAFFIC SIGNAL WARRANT ANALYSIS FOR A SENIOR LIVING AND APARTMENT DEVELOPMENT
TRAFFIC IMPACT STUDY And A TRAFFIC SIGNAL WARRANT ANALYSIS FOR A SENIOR LIVING AND APARTMENT DEVELOPMENT DEERFIELD TOWNSHIP, WARREN COUNTY, OHIO Nantucket Circle and Montgomery Road () Prepared for: ODLE
More informationSan Pablo High Treatment applied incrementally at each N + ++
Transit Improvements T1 Further study options for creation or designation of segregated transit lanes along San Pablo, including options for restrictions during a limited number of peak travel hours and
More informationD.13 Transportation and Traffic
This section addresses transportation and traffic issues and impacts related to the Proposed Project. Section D.13.1 provides a description of the affected environment for the Proposed Project. Applicable
More informationProject Report. South Kirkwood Road Traffic Study. Meadows Place, TX October 9, 2015
Meadows Place, TX October 9, 2015 Contents 1 Introduction... 1 2 Data Collection... 1 3 Existing Roadway Network... 2 4 Traffic Volume Development... 2 5 Warrant Analysis... 3 6 Traffic Control Alternative
More informationMichael A. Werthmann, PE, PTOE Principal
9575 West Higgins Road, Suite 400 Rosemont, Illinois 60018 p: 847-518-9990 f: 847-518-9987 MEMORANDUM TO: FROM: Brian Lorenc GHB-630, LLC Michael A. Werthmann, E, TOE rincipal Luay R. Aboona, E rincipal
More informationChicago Safe Routes to School Safe Routes to High School (SRTS/SRTHS)
Chicago Safe Routes to School Safe Routes to High School (SRTS/SRTHS) Marshall Community High School and Faraday Elementary School Recommended Improvements Agenda Goals Related Programs Project Location/Area
More information4.0 TRANSPORTATION SYSTEMS
Transportation Systems 4.0 TRANSPORTATION SYSTEMS This chapter examines the impacts of the Central Corridor Extension on existing roadways and traffic operations and discusses the transit service, operations,
More informationGateway Transportation Study
Gateway Transportation Study Amherst, Massachusetts SUBMITTED TO University of Massachusetts Amherst Town of Amherst SUBMITTED BY Vanasse Hangen Brustlin, Inc. Watertown, Massachusetts March 213 Back of
More informationConversion of One-Way Couplet Streets to Two-Way
Conversion of One-Way Couplet Streets to Two-Way May 5, 2016 Oklahoma Traffic Engineers Association 2016 Spring Meeting, Tulsa, OK Kevin St. Jacques, P.E., PTOE, PTP Freese and Nichols Overview Initial
More informationTRANSPORTATION IMPACT STUDY PROPOSED RIVERFRONT 47 MIXED USE DEVELOPMENT
November 2016 TRANSPORTATION IMPACT STUDY PROPOSED RIVERFRONT 47 MIXED USE DEVELOPMENT & Aspinwall Borough, Sharpsburg Borough & O Hara Township, Allegheny County, Pennsylvania Prepared for: Riverfront
More informationTAKOMA METRO STATION
TKOM METRO STTION Traffic nalysis Technical Memorandum Station Planning in Support of Joint evelopment Job No. 13-FQ165-LN-2 November 213 WSHINGTON METROPOLITN RE TRNSIT UTHORITY (WMT) Takoma Metro Station
More informationFoothill Expressway Improvements Between El Monte and San Antonio
Foothill Expressway Improvements Between El Monte and San Antonio June 29, 2017 - Los Altos Community Meeting Introduction Project Background Agenda Visit Stations: Provide Input and Ask Questions Reconvene:
More informationAppendix B. Environmental Resource Technical Memorandum. Assessment on Travel Pattern and Access Impacts
Appendix B Environmental Resource Technical Memorandum Assessment on Travel Pattern and Access Impacts TECHNICAL MEMORANDUM ENVIRONMENTAL RE-EVALUATION FOR UNION STATION TO OAK CLIFF DALLAS STREETCAR To:
More informationBay to Bay Boulevard Complete Streets Project
Bay to Bay Boulevard Complete Streets Project Dale Mabry Highway to Bayshore Boulevard February 08, 2018 Photo Source: Tampa Bay Times Alessandra Da Pra Meeting Format Introduction Resurfacing Information
More informationMETHODOLOGY. Signalized Intersection Average Control Delay (sec/veh)
Chapter 5 Traffic Analysis 5.1 SUMMARY US /West 6 th Street assumes a unique role in the Lawrence Douglas County transportation system. This principal arterial street currently conveys commuter traffic
More informationDeer Street Parking Garage & Deer Street Associates Development
Traffic Impact and Access Study Deer Street Parking Garage & Deer Street Associates Development Portsmouth, New Hampshire Submitted to: City of Portsmouth, New Hampshire 1 Junkins Avenue Portsmouth, New
More informationClay Street Realignment Project Traffic Study
Final Clay Street Realignment Project Traffic Study November 24, 2009 Prepared for: City of Placerville RS07-2466 2990 Lava Ridge Court, Suite 200 Roseville, CA 95661 (916) 773-1900 Fax (916) 773-2015
More informationAbrams Associates. Transportation Impact Analysis. City of Rocklin. Prepared for: David Mohlenbrok City of Rocklin 4081 Alvis Court Rocklin, CA 95677
Transportation Impact Analysis Sierra College Boulevard Commercial Project City of Rocklin Prepared for: David Mohlenbrok City of Rocklin 081 Alvis Court Rocklin, CA 95677 Prepared by: 1875 Olympic Boulevard,
More informationcanopy Ithaca The Commons by Hilton
Traffic Impact Study f or t h e p r o p o s e d canopy Ithaca The Commons by Hilton C i t y o f I t h a c a T o m p k i n s C o u n t y, N ew Y ork January 215 Project No. 347 Prepared For: 3 3 7 E l m
More informationBLOSSOM AT PICKENS SIGNALIZED INTERSECTION IMPROVEMENT STUDY
BLOSSOM AT PICKENS SIGNALIZED INTERSECTION IMPROVEMENT STUDY Class Project Report for ECIV 542 Traffic Engineering Submitted by Omor Sharif Muchun Song Narges Kaveshgar Quyen Pham Chih-Yao Lin Submission
More informationMagnolia Place. Traffic Impact Analysis. Prepared for: City of San Mateo. Prepared by: Hexagon Transportation Consultants, Inc.
Magnolia Place Traffic Impact Analysis Prepared for: City of San Mateo Prepared by: Hexagon Transportation Consultants, Inc. Updated January 4, 2010 Table of Contents 1. Introduction...1 2. Existing Conditions...6
More informationEast 12 th Street Bikeway Feasibility Study
Final Report East 12 th Street Bikeway Feasibility Study Prepared for: City of Oakland Public Works Agency Submitted by: 180 Grand Avenue, Suite 250 Oakland, CA 94612 Phone: (510) 839-1742; Fax: (510)
More informationOTTAWA TRAIN YARDS PHASE 3 DEVELOPMENT CITY OF OTTAWA TRANSPORTATION IMPACT STUDY. Prepared for:
OTTAWA TRAIN YARDS PHASE 3 DEVELOPMENT CITY OF OTTAWA TRANSPORTATION IMPACT STUDY Prepared for: The Ottawa Train Yards Inc. 223 Colonnade Road South, Suite 212 Nepean, Ontario K2E 7K3 January 17, 2012
More informationNEW YORK CENTRAL PARK SUBDIVISION BLAIS STREET/ST-PIERRE STREET EMBRUN, ONTARIO TRAFFIC IMPACT STUDY. Prepared for:
NEW YORK CENTRAL PARK SUBDIVISION BLAIS STREET/ST-PIERRE STREET EMBRUN, ONTARIO TRAFFIC IMPACT STUDY Prepared for: Solidex Holdings Limited & Investissement Maurice Lemieux Investments Attn: Mr. Anthony
More informationBalancing Operation & Safety for Motorized and Non-Motorized Traffic
Balancing Operation & Safety for Motorized and Non-Motorized Traffic Brian Willham, PE, PTOE Iowa Director - MOVITE June 30, 2014 Learning Objectives: When & Why should we measure the performance of complete
More informationList of Exhibits...ii
One Brickell Traffic Study TABLE OF CONTENTS List of Exhibits...ii EXECUTIVE SUMMARY...1 1. INTRODUCTION...2 1.1 Study Area...2 1.2 Study Objective...5 2. EXISTING TRAFFIC CONDITIONS...6 2.1 Data Collection...6
More informationTRAFFIC IMPACT STUDY CRITERIA
Chapter 6 - TRAFFIC IMPACT STUDY CRITERIA 6.1 GENERAL PROVISIONS 6.1.1. Purpose: The purpose of this document is to outline a standard format for preparing a traffic impact study in the City of Steamboat
More information1609 E. FRANKLIN STREET HOTEL TRAFFIC IMPACT STUDY EXECUTIVE SUMMARY
1609 E. FRANKLIN STREET HOTEL TRAFFIC IMPACT STUDY EXECUTIVE SUMMARY Prepared for: The Town of Chapel Hill Public Works Department Traffic Engineering Division Prepared by: HNTB North Carolina, PC 343
More informationMultnomah County Courthouse Relocation. Transportation Alternatives Analysis Technical Memorandum: FINAL
Multnomah County Courthouse Relocation Portland, Oregon Transportation Alternatives Analysis Technical Memorandum: FIL Prepared for Multnomah County Facilities and Property Management Division 41 N Dixon
More informationNorth Shore Transportation Improvement Strategy
North Shore Transportation Improvement Strategy Preliminary, Near-term Recommendation 2016 April Transportation Improvement Strategy (TIS) Comprehensive and Analytical A multi-modal transportation strategy
More informationTraffic Impact Study. Westlake Elementary School Westlake, Ohio. TMS Engineers, Inc. June 5, 2017
TMS Engineers, Inc. Traffic Impact Study Westlake Elementary School Westlake, Ohio June 5, 2017 Prepared for: Westlake City Schools - Board of Education 27200 Hilliard Boulevard Westlake, OH 44145 TRAFFIC
More informationCalifornia Department of Transportation, District 4. Sloat Boulevard Project Skyline Blvd. to 19 th Ave. Community Update January 13, 2016
California Department of Transportation, District 4 Sloat Boulevard Project Skyline Blvd. to 19 th Ave. Community Update January 13, 2016 Agenda Welcome and introductions Project overview, history and
More informationMEETING FACILITY 2901 GIBFORD DRIVE CITY OF OTTAWA TRANSPORTATION BRIEF. Prepared for: Holiday Inn Express 2881 Gibford Drive Ottawa, ON K1V 2L9
MEETING FACILITY 2901 GIBFORD DRIVE CITY OF OTTAWA TRANSPORTATION BRIEF Prepared for: Holiday Inn Express 2881 Gibford Drive Ottawa, ON K1V 2L9 December 18, 2012 112-566 Brief_1.doc D. J. Halpenny & Associates
More informationAppendix B: Forecasting and Traffic Operations Analysis Framework Document
Existing Conditions Report - Appendix Appendix B: Forecasting and Traffic Operations Analysis Framework Document This document defines the methodology and assumptions that will be used in the traffic forecasting
More informationDraft North Industrial Area-Wide Traffic Plan
Summary of North Industrial and Hudson Bay Industrial Recommended Improvements Table 1. Summary of s Item Location 1 2 3 4 5 6 7 8 9 10 11 12 Millar Ave north of 51st St Super 8 Motel back lane 400 Block
More informationPreliminary Transportation Analysis
Preliminary Transportation Analysis Goals of a Robust, Multimodal Transportation Network Safe Accessible/Connected Efficient Comfortable Context-Sensitive Motor Vehicle: Continue to analyze the data to
More informationDRAFT Davidson Elementary School Expansion Transportation Impact Analysis
DRAFT Davidson Elementary School Expansion Transportation Impact Analysis Prepared for: Town of Davidson 216 S. Main Street Davidson, NC 28036 Prepared by: Stantec Consulting Services Inc. 2127 Ayrsley
More informationTraffic Impact Analysis Chatham County Grocery Chatham County, NC
Chatham County Grocery Chatham County, NC TABLE OF CONTENTS 1. INTRODUCTION... 1 1.1. Location and Study Area... 1 1.2. Proposed Land Use and Access... 2 1.3. Adjacent Land Uses... 2 1.4. Existing ways...
More informationRoad Conversion Study Plumas Street
Plumas Street Phase I Submitted to The Regional Transportation Commission of Washoe County Submitted by Zong Tian, Ph.D., P.E. Saeedeh Farivar Haiyuan Li, Ph.D. Center for Advanced Transportation Education
More informationPRELIMINARY DRAFT WADDLE ROAD / I-99 INTERCHANGE PROJECT ALTERNATIVE ANALYSIS FINAL TRAFFIC SUMMARY REPORT
PRELIMINARY DRAFT WADDLE ROAD / I-99 INTERCHANGE PROJECT ALTERNATIVE ANALYSIS FINAL TRAFFIC SUMMARY REPORT Prepared by: In Association with: November 2013 EXECUTIVE SUMMARY Patton Township, in partnership
More information4.13 TRANSPORTATION AND TRAFFIC
4.13 This chapter describes the regulatory framework and existing conditions in the vicinity of the Project site related to transportation and traffic, and the potential impacts of the proposed Project
More informationCOMMUNITY MEETING AGENDA
COMMUNITY MEETING AGENDA Welcome and Introductions SAFE Presentation Project Presentation Priorities Feedback Next Steps Q&A Santa Cruz Avenue Corridor Study 1 Santa Cruz Avenue Corridor Study Community
More informationJoe Rocca P.Eng., Traffic and Asset Management Supervisor. Review for Proposed Kingsway Sports and Entertainment Complex, City of Greater Sudbury
LETTER REPORT TO: Joe Rocca P.Eng., Traffic and Asset Management Supervisor FROM: Brett Sears and Ubaid Ali, WSP SUBJECT: Review for Proposed Kingsway Sports and Entertainment Complex, City of Greater
More informationHOLIDAY INN HOTEL 235 KING EDWARD AVENUE CITY OF OTTAWA TRANSPORTATION BRIEF. Prepared for:
HOLIDAY INN HOTEL 235 KING EDWARD AVENUE CITY OF OTTAWA TRANSPORTATION BRIEF Prepared for: Momentum Planning & Communications 1165 Greenlawn Crescent Ottawa, ON K1L 6C2 June 29, 2015 115-618 Brief_1.doc
More informationINDUSTRIAL BUILDING 1660 COMSTOCK ROAD CITY OF OTTAWA TRANSPORTATION OVERVIEW. Prepared for:
INDUSTRIAL BUILDING 1660 COMSTOCK ROAD CITY OF OTTAWA TRANSPORTATION OVERVIEW Prepared for: Simluc Contractors Limited 2550 Blackwell Street, Ottawa K1B 5R1 October 18, 2013 113-584 Overview_1.doc D. J.
More informationCity of Hyattsville. Citywide Traffic Study and Transportation Plan. Sabra, Wang & Associates. February, 2010
City of Hyattsville Citywide Traffic Study and Transportation Plan February, 2010 Outline Existing Conditions Recommendations Future Conditions Traffic Growth Development Capacity and Level of Service
More informationShockoe Bottom Preliminary Traffic and Parking Analysis
Shockoe Bottom Preliminary Traffic and Parking Analysis Richmond, Virginia August 14, 2013 Prepared For City of Richmond Department of Public Works Prepared By 1001 Boulders Pkwy Suite 300, Richmond, VA
More informationCOMMERCIAL DEVELOPMENT 2015 ROBERTSON ROAD OTTAWA, ONTARIO TRANSPORTATION BRIEF. Prepared for:
COMMERCIAL DEVELOPMENT 2015 ROBERTSON ROAD OTTAWA, ONTARIO TRANSPORTATION BRIEF Prepared for: First Bay Properties Inc. 311 Richmond Road, Suite 203 Ottawa, ON K1Z 6X3 August 8, 2017 117-663 Brief_1.doc
More informationPolk Streetscape Project
What is this project? The Polk Streetscape Project is an effort to improve safety for everyone traveling on Polk Street between Union and McAllister streets. Also included in this project are paving, sewer
More informationClay Street Bridge Replacement Project
Clay Street Bridge Replacement Project Frequently Asked Questions (FAQs) The project is located in downtown Placerville on Clay Street between US Highway 50 and Main Street and Cedar Ravine Road. The proposed
More information5858 N COLLEGE, LLC N College Avenue Traffic Impact Study
5858 N COLLEGE, LLC nue Traffic Impact Study August 22, 2016 Contents Traffic Impact Study Page Preparer Qualifications... 1 Introduction... 2 Existing Roadway Conditions... 5 Existing Traffic Conditions...
More informationTRAFFIC IMPACT ANALYSIS OF PROPOSED CHESTNUT HILL COLLEGE MASTER PLAN DEVELOPMENT
TRAFFIC IMPACT ANALYSIS OF PROPOSED CHESTNUT HILL COLLEGE MASTER PLAN DEVELOPMENT Prepared by Orth-Rodgers & Associates, Inc. December 14, 2009 Updated November 9, 2010 230 South Broad Street Philadelphia
More informationPINESTONE TRAFFIC IMPACT STUDY Travelers Rest, South Carolina
PINESTONE TRAFFIC IMPACT STUDY Travelers Rest, South Carolina Prepared for Longbranch Development Prepared by January 13, 219 ii Table of Contents Subject Page Signature Page... i Table of Contents...
More informationBicycle Traffic Control Signal - St. Clair Avenue West and Poplar Plains Road
PW17.11 REPORT FOR ACTION Bicycle Traffic Control Signal - St. Clair Avenue West and Poplar Plains Road Date: November 4, 2016 To: Public Works and Infrastructure Committee From: Acting General Manager,
More informationFreeway ramp intersection study
Freeway ramp intersection study Supporting Vision Zero: Zero traffic deaths in San Francisco by 2024 Study Goals: Primary Improve Safety Improve Accessibility Secondary Provide Efficient Circulation Accommodate
More informationParking Lot P6C Transportation Impact Assessment
Transportation Carleton University Parking Lot P6C Transportation Impact Assessment Prepared by: AECOM 302 1150 Morrison Drive 613 820 8282 tel Ottawa, ON, Canada K2H 8S9 613 820 8338 fax www.aecom.com
More informationDUNBOW ROAD FUNCTIONAL PLANNING
DUNBOW ROAD FUNCTIONAL PLANNING Final Report August 3, 216 #31, 316 5th Avenue NE Calgary, AB T2A 6K4 Phone: 43.273.91 Fax: 43.273.344 wattconsultinggroup.com Dunbow Road Functional Planning Final Report
More informationTraffic Signal Redesign 50% Design Report
Traffic Signal Redesign 50% Design Report Joseph Davis, Jace Elkins, Jordan Weyrauch and Zach Crimmins CENE 486 Capstone J3Z Engineering March 10 th, 2016 Table of Contents 1.0 Project Description...1
More informationChapter 4: Transportation Systems
4.1 INTRODUCTION This chapter evaluates the transportation benefits and impacts of the Preferred Alternative on the existing transportation system (No Action Alternative). Table 4 1 summarizes the transportation
More informationAddendum to Mitigated Negative Declaration
Addendum Date: Case No.: 2014.1499E Project Title: (MDSP) - Mission Valencia Green Gateway Streetscape Project Original: 2008.1075, MDSP Mitigated Negative Declaration Project Sponsor: Charlie Ream, San
More informationSan Jose Transportation Policy
San Jose Transportation Policy Protected Intersections in LOS Policies to Support Smart Growth Presented by: Manuel Pineda City of San Jose Department of Transportation Bay Area Map San Francisco Oakland
More informationTABLE OF CONTENTS TABLE OF CONTENTS... I APPENDICES... III LIST OF EXHIBITS... V LIST OF TABLES... VII LIST OF ABBREVIATED TERMS...
TABLE OF CONTENTS TABLE OF CONTENTS... I APPENDICES... III LIST OF EXHIBITS... V LIST OF TABLES... VII LIST OF ABBREVIATED TERMS... IX 1 INTRODUCTION... 1 1.1 Project Overview... 1 1.2 Analysis Scenarios...
More informationHILTON GARDEN INN HOTEL HOTEL EXPANSION 2400 ALERT ROAD, OTTAWA TRANSPORTATION BRIEF. Prepared for:
HILTON GARDEN INN HOTEL HOTEL EXPANSION 2400 ALERT ROAD, OTTAWA TRANSPORTATION BRIEF Prepared for: Bona Building & Management Co. Ltd. Place Vanier, 333 North River Road Vanier, Ontario K1L 8B9 October
More informationLow Level Road Improvements Traffic Analysis. Report
Low Level Road Improvements Traffic Analysis Report June, 22 Table of Contents. INTRODUCTION.... LOW LEVEL ROAD PROJECT....2 STUDY AREA....2. West-End Corridor Improvements... 2.2.2 East-End Corridor Improvements...
More information3.9 - Transportation and Traffic
Transportation and Traffic 3.9 - Transportation and Traffic This section describes the potential transportation and traffic effects of project implementation on the project site and its surrounding area.
More informationHighway 111 Corridor Study
Highway 111 Corridor Study June, 2009 LINCOLN CO. HWY 111 CORRIDOR STUDY Draft Study Tea, South Dakota Prepared for City of Tea Sioux Falls Metropolitan Planning Organization Prepared by HDR Engineering,
More informationDEPARTMENT OF ENVIRONMENTAL SERVICES. North Harrison Street (Lee Highway to Little Falls Road) Comparative Analysis. Prepared for:
DEPARTMENT OF ENVIRONMENTAL SERVICES North Harrison Street (Lee Highway to Little Falls Road) Comparative Analysis Prepared for: Arlington County Department of Environmental Services 2100 Clarendon Boulevard,
More informationChapter 4 Traffic Analysis
Chapter 4 Traffic Analysis PURPOSE The traffic analysis component of the K-68 Corridor Management Plan incorporates information on the existing transportation network, such as traffic volumes and intersection
More informationCorporation of the Town of Oakville. December 16, 2013
Corporation of the Town of Oakville Transportation Impact Analysis and Parking Study for Proposed Secondary School, Oakville Draft Final Report Submitted by: HDR Corporation 100 York Boulevard, Suite 300
More informationDescription: Widen I-64 to 6 lanes from I-265 to the KY 53 interchange in Shelby County.
I-64 KIPDA ID # 350 Project Type: ROADWAY CAPACITY Description: Widen I-64 to 6 lanes from I-265 to the KY 53 interchange in Shelby County. Purpose: Project will improve capacity and address safety concerns.
More informationMASER ASSOCIATES. Engineers Planners Surveyors TRAFFIC IMPACT ANALYSIS FOR PROPOSED RESIDENTIAL MULTI-FAMILY SEA GULL VILLAGE TOWNSHIP OF COLTS NECK
000 MASER ASSOCIATES Engineers Planners Surveyors TRAFFIC IMPACT ANALYSIS FOR PROPOSED RESIDENTIAL MULTI-FAMILY DEVELOPMENT SEA GULL VILLAGE TOWNSHIP OF COLTS NECK MONMOUTH COUNTY Prepared By: Richard
More informationSouth End Transportation Study. Public Meeting. January 31, 2019 Welcome. Public Meeting. January 10, 2018 WELCOME
Public Meeting January 31, 2019 Welcome Public Meeting January 10, 2018 WELCOME What You Will Hear Tonight All ideas presented are options currently under consideration Study Team found no single solution
More informationMultimodal Analysis in the 2010 Highway Capacity Manual
Multimodal Analysis in the 2010 Highway Capacity Manual It s not just cars anymore! Jamie Parks, AICP HCAT Conference May 9-10, 2011 Multimodal LOS in the 2010 HCM History and background Overview of methods
More informationNorth Park Mid-City Bikeways Project: Traffic and Safety Impact Assessment
FINAL REPORT North Park Mid-City Bikeways Project: University Bikeway Traffic and Safety Impact Assessment April 23, 2018 Lead Agency: San Diego Association of Governments (SANDAG) 401 B Street, Suite
More informationTraffic Impact Study Little Egypt Road Development Denver, North Carolina June 2017
Traffic Impact Study Little Egypt Road Development Denver, North arolina June 2017 N. Little Egypt Road DQ\ QDQFLQJ VDOHV RU RWKHU SHUIRUPDQFH EDVHG FULWHULD Proposed Site Driveways Site Driveway 1 TRAFFI
More informationOFFICE/RETAIL DEVELOPMENT 1625 BANK STREET OTTAWA, ONTARIO TRANSPORTATION BRIEF. Prepared for: Canada Inc.
OFFICE/RETAIL DEVELOPMENT 1625 BANK STREET OTTAWA, ONTARIO TRANSPORTATION BRIEF Prepared for: 9402209 Canada Inc. December 15, 2015 115-625 Report_2.doc D. J. Halpenny & Associates Ltd. Consulting Transportation
More informationExisting Conditions. Date: April 16 th, Dan Holderness; Coralville City Engineer Scott Larson; Coralville Assistant City Engineer
Date: April 16 th, 2015 To: From: Re: Dan Holderness; Coralville City Engineer Scott Larson; Coralville Assistant City Engineer Darian Nagle-Gamm, Traffic Engineering Planner Highway 6 (2 nd Street) /
More information