1 I-105 ExpressLanes Project Public Scoping Meetings March 2018

2 Introduction to Scoping This process is your opportunity to give us your thoughts on: The purpose and need for the proposed improvements The proposed alternatives The environmental issues that concern your community The local projects that may be proposed in the study area The community participation approach 2

3 Public Scoping Meetings Public Scoping Meeting #1 Wednesday, March 21, :00 8:00pm Lennox Park Community Room Condon Av, Lennox, CA Public Scoping Meeting #2 Thursday, March 22, :00 8:00pm Watts Labor Community Action Committee Phoenix Hall S Central Av, Los Angeles, CA Live Webcast You can also join via live webcast on Thursday, March 22 at The live webcast presentation starts at 6:30pm Public Scoping Meeting #3 Saturday, March 24, :30 11:30am Paramount Community Center Paramount Bl, Paramount, CA

4 Agenda I-10 and I-110 ExpressLanes Background Project Overview, Purpose, and Need Proposed Alternatives Tolling Requirements Environmental Process and Timeline Public Outreach Scoping Comments Stay Informed Comment Period 4

5 ExpressLanes Background Initiated as a one-year congestion reduction demonstration project. o I-110 opened in November 2012 o I-10 opened in February 2013 The project s success led the Metro Board to approve continuation of the operation of the ExpressLanes in The California Legislature allowed tolling in perpetuity in

6 Current Business Rules All vehicles (except buses, motorcycles, & emergency response) required to have a FasTrak transponder. Dynamically priced. Single Occupant Vehicles (SOV) Pay Toll at all times. I-10 - HOV 3+ Toll-free peak hours; HOV 2 off-peak. I HOV 2+ Toll-free at all times. $40 to open account, $1 per month account maintenance fee. Low-income Assistance Plan; maintenance fee is waived 6

7 How ExpressLanes Work 7

8 Project Map 8

9 Project Need I-105 experiences heavy demand during peak commute hours that exceeds the freeway s capacity. Between 200,000 to 250,000 daily vehicles on an average weekday. HOV lane is degraded (speeds are less than 45 miles per hour during peak periods). o It can take 43 minutes to drive the HOV lane during the PM peak compared to 15 minutes with no congestion Peak period speeds average 25 miles per hour or less in the General Purpose lanes. o It can take as long as 50 minutes to drive the corridor during the PM peak compared to 15 minutes with no congestion 9

10 Project Purpose Enhance traffic flow; Improve trip reliability and travel times; and, Sustain and manage mobility within the corridor. 10

11 Project Description The I-105 ExpressLanes Project is studying the possible implementation of ExpressLanes on the I-105 between the I-405and I-605, a distance of 15.7 miles. o In addition, the Project will also study the I-105 west of the I- 405 to Sepulveda Bl and east of the I-605 to Studebaker Rd to identify potential signage locations and access points into the ExpressLanes. 11

12 Proposed Alternatives Alternative 1: Alternative 2: Alternative 3: Alternative 4: Existing Conditions (No Build) Convert High-Occupancy Vehicle(HOV) lane to one (1) ExpressLane Convert HOV lane to one ExpressLane and add a second ExpressLane (nonstandard lane widths) Convert HOV lane to one ExpressLane and add a second ExpressLane (standard lane widths) 12

13 Alternative 1 Existing Conditions (No Build) Graphic illustrates current conditions with no changes No additional travel lanes or ramp improvements would be installed as part of this alternative *Note: Auxiliary Lane is only in certain locations on I

14 Alternative 2 Convert HOV to One (1) ExpressLane (Standard Lane Width) Convert existing HOV to one (1) ExpressLane in each direction with standard (12 ft) lane width Property acquisition is not anticipated *Note: Auxiliary Lane is only in certain locations on I

15 Alternative 3 Two (2) ExpressLanes (Non-standard Lane Widths) Convert existing HOV lane to one ExpressLane and add a second ExpressLane in each direction Non-standard lane and shoulder widths o Lane could be reduced from 12 ft to 11 ft Property acquisition is not anticipated at this time but will be assessed as part of this effort 15 *Note: Auxiliary Lane is only in certain locations on I-105.

16 Alternative 4 Two (2) ExpressLanes (Standard Lane Widths) Convert existing HOV lane to one ExpressLane and add a second ExpressLane in each direction Standard lane (12 ft) and shoulder widths Property acquisition is anticipated *Note: Auxiliary Lane is only in certain locations on I

17 Tolling Requirements Concept of Operations (ConOps) o Define operational policies, toll collection systems, and facility design Traffic and Revenue (T&R) Study o o Will consider congestion, capacity, and potential time savings Estimate toll rates and potential toll revenue for this corridor Apply for Tolling Authority o Metro and Caltrans will need to apply for tolling authority through the California Transportation Commission (CTC) in order to implement ExpressLanes on the I

18 Environmental Document & Studies Project Approval/Environmental Document (PA/ED) o o o o Project Report Environmental Impact Report (EIR), pursuant to California Environmental Quality Act (CEQA) Environmental Assessment (EA), pursuant to National Environmental Policy Act (NEPA) Caltrans is the CEQA/NEPA Lead Agency for EIR/EA 18

19 Environmental Considerations Air Quality Aesthetics Biological Resources Community Impact Study Cultural Resources Cumulative Analysis Environmental Justice Hazards and Hazardous Materials Hydrology/ Water Quality Noise Right-of-way (ROW) Transportation/Traffic Utilities/ Service Systems 19

20 Key Milestones: Environmental Process WE ARE HERE 20

21 Scoping Comments Written comments due by Monday, April 16, 2018 Law requires all scoping comments to be provided in writing Comment submittal options Comment Card: Submit at the Public Scoping Meetings Web Comment Form: Mail: Ronald Kosinski, Deputy District Director California Department of Transportation Division of Environmental Planning 100 S. Main Street MS 16A Los Angeles, CA

22 Outreach Plan for Scoping Meetings Direct mail to addresses within 750 feet of the study area Stakeholder database, elected officials, and agencies E-Blast Print and digital newspaper ads Social media advertising Project website Extended outreach to city offices, libraries, and community centers City and Elected Official Briefings 22

23 Opportunities for Public Involvement Ongoing Outreach Project Update Community Meetings City and Elected Official Briefings Event Booths / Pop-up Information Tables Outreach to businesses and local communities Public Hearings Release of Draft EIR/EA 23

24 Stay Connected Philbert Wong Project Manager, Metro One Gateway Plaza, MS Los Angeles, CA metro.net/105expresslanes 24

25 Comment Ground Rules Verbal comments will not be considered as formal comments. Please submit your comment in writing for it to be included in the scoping record. Submit a speaker card to staff collecting cards after the presentation if you d like to speak. 25

26 Thank You!

101 Corridor Managed Lanes

101 Corridor Managed Lanes 101 Corridor Managed Lanes TA BOD Meeting May 5, 2016 Agenda Item 11a Presentation Outline 101 Corridor Profile System Deficiencies Background Managed Lanes Proposed Purpose and Need Alternatives Under

More information

Washington DC Section of ITE Project Briefing

Washington DC Section of ITE Project Briefing Washington DC Section of ITE Project Briefing November 5, 2015 Renée Hamilton, VDOT, Deputy District Administrator I-66 Outside the Beltway Improvement Area Project Location Virginia 2 Purpose and Need

More information

I-395 Express Lanes Northern Extension Project Public Hearings

I-395 Express Lanes Northern Extension Project Public Hearings I-395 Express Lanes Northern Extension Project Public Hearings Susan Shaw, PE, Megaprojects Director Virginia Department of Transportation Amanda Baxter, Special Projects Manager Virginia Department of

More information

I-395 Express Lanes Northern Extension Project Crystal City Civic Association September 21, 2016

I-395 Express Lanes Northern Extension Project Crystal City Civic Association September 21, 2016 I-395 Express Lanes Northern Extension Project Crystal City Civic Association September 21, 2016 Mike Snare, PE, Project Manager Virginia Department of Transportation GEC Michelle Holland, Megaprojects

More information

405 Express Lanes General Information & Frequently Asked Questions

405 Express Lanes General Information & Frequently Asked Questions The questions and answers below provide current information on the project to improve Interstate 405 (I-405) in Orange County from State Route 73 to Interstate 605. Why are improvements needed on I-405?

More information

I-635 LBJ EAST PROJECT

I-635 LBJ EAST PROJECT 635 I-635 LBJ EAST PROJECT Transportation and Trinity River Project Committee 9 June 2014 TxDOT Dallas District Dallas County, Texas CSJ: 2374-01-137, 2374-02-053 Agenda I-635 LBJ East Project Overview

More information

I-395 Express Lanes Northern Extension Project Fairlington Citizens Association September 12, 2016

I-395 Express Lanes Northern Extension Project Fairlington Citizens Association September 12, 2016 I-395 Express Lanes Northern Extension Project Fairlington Citizens Association September 12, 2016 Susan Shaw, PE, Megaprojects Director, Virginia Department of Transportation Amanda Baxter, Special Projects

More information

Transportation Corridor Agencies t..

Transportation Corridor Agencies t.. Proposed State Route 241/91 Tolled Express Lanes Connector Draft Supplemental Environmental Impact Report/ Environmental Impact Statement Public Hearing November 29, 2016 Transportation Corridor Agencies

More information

Tolling Study. July 23, 2009

Tolling Study. July 23, 2009 Eastside Corridor Tolling Study Interagency Working Group July 23, 2009 1 Welcome Craig Stone Director of WSDOT Toll Division 2 Agenda Introductions/Roles & Responsibilities Meeting Goals Express Toll

More information

395 Express Lanes Extension

395 Express Lanes Extension 395 Express Lanes Extension January 2016 Building a network of Express Lanes Project overview Add capacity on I-395 with addition of a third HOV lane and active traffic management Generate guaranteed transit

More information

IH 85 EXPRESS LANES ATLANTA, GA USDOT Congestion Reduction Demonstration Program Grant ($110M)

IH 85 EXPRESS LANES ATLANTA, GA USDOT Congestion Reduction Demonstration Program Grant ($110M) IH 85 EXPRESS LANES ATLANTA, GA USDOT Congestion Reduction Demonstration Program Grant ($110M) HOV to HOT: 15 miles Convert from 2+ HOV to managed (3+ free) Project includes Express Lane component, new

More information

Presented by: Aziz Elattar Deputy District Director Planning, Public Transportation and Local Assistance October 4, 2013

Presented by: Aziz Elattar Deputy District Director Planning, Public Transportation and Local Assistance October 4, 2013 Presented by: Aziz Elattar Deputy District Director Planning, Public Transportation and Local Assistance October 4, 2013 2 Project Study Report Project Development Support (PSR-PDS) 1. Purpose: Gain approval

More information

Transform 66 Project February 4, 2016 Partnering Conference Michigan Department of Transportation American Council of Engineering Companies

Transform 66 Project February 4, 2016 Partnering Conference Michigan Department of Transportation American Council of Engineering Companies Transform 66 Project February 4, 2016 Partnering Conference Michigan Department of Transportation American Council of Engineering Companies Susan Shaw, PE, CCM, DBIA Megaprojects Director Northern Virginia

More information

General Plan Circulation Element Update Scoping Meeting April 16, 2014 Santa Ana Senior Center, 424 W. 3rd Street, Santa Ana, CA 92701

General Plan Circulation Element Update Scoping Meeting April 16, 2014 Santa Ana Senior Center, 424 W. 3rd Street, Santa Ana, CA 92701 General Plan Circulation Element Update Scoping Meeting April 16, 2014 Santa Ana Senior Center, 424 W. 3rd Street, Santa Ana, CA 92701 Meeting Agenda 1. Purpose of Scoping Meeting 2. Project Overview 3.

More information

DULLES AREA TRANSPORTATION ASSOCIATION (DATA) February 18, Susan Shaw, P.E., VDOT, Megaprojects Director

DULLES AREA TRANSPORTATION ASSOCIATION (DATA) February 18, Susan Shaw, P.E., VDOT, Megaprojects Director DULLES AREA TRANSPORTATION ASSOCIATION (DATA) February 18, 2015 Susan Shaw, P.E., VDOT, Megaprojects Director I-66 Corridor Conditions Steady population growth Employment growth in activity centers Congestion

More information

I-66 Corridor Improvements Route 15 to I-495. November 2014

I-66 Corridor Improvements Route 15 to I-495. November 2014 I-66 Corridor Improvements Route 15 to I-495 November 2014 I-66 Corridor: Haymarket to the Beltway = Park and Ride Lots 2 Purpose and Need Improve multimodal mobility along the I-66 corridor by providing

More information

I-395 Express Lanes Northern Extension Project Arlington County Board October 18, 2016

I-395 Express Lanes Northern Extension Project Arlington County Board October 18, 2016 I-395 Express Lanes Northern Extension Project Arlington County Board October 18, 2016 Susan Shaw, PE, Megaprojects Director Virginia Department of Transportation Amanda Baxter, Special Projects Manager

More information

Public Hearing Tarrant County. October 11 th, 2012

Public Hearing Tarrant County. October 11 th, 2012 Public Hearing Tarrant County October 11 th, 2012 Public Hearing Agenda Welcome and Project Overview Ms. Maribel P. Chavez, P.E. District Engineer Texas Department of Transportation Fort Worth District

More information

Overview of 64 Express Lanes. Secretary of Transportation Aubrey Layne April 12, 2017

Overview of 64 Express Lanes. Secretary of Transportation Aubrey Layne April 12, 2017 Overview of 64 Express Lanes Secretary of Transportation Aubrey Layne April 12, 2017 2 More Choices for Motorists Coming December 2017 Purpose and Use Our purpose is two-fold: Reduce congestion by making

More information

Managed Lanes. Steve Schilke, P.E. Major Projects Unit Head District 1. Illinois Traffic Engineering and Safety Conference October 2016

Managed Lanes. Steve Schilke, P.E. Major Projects Unit Head District 1. Illinois Traffic Engineering and Safety Conference October 2016 Managed Lanes Steve Schilke, P.E. Major Projects Unit Head District 1 Illinois Traffic Engineering and Safety Conference October 2016 Agenda Managed Lanes Projects I-55 (Stevenson Expressway) Express Toll

More information

COUNTYWIDE EXPRESSLANES STRATEGIC PLAN FINAL REPORT

COUNTYWIDE EXPRESSLANES STRATEGIC PLAN FINAL REPORT March 1, 2017 COUNTYWIDE EXPRESSLANES STRATEGIC PLAN FINAL REPORT Approved by Metro Board of Directors on January 26, 2017 Prepared for: Prepared by: One Gateway Plaza Los Angeles, CA 90012 444 South Flower

More information

Project Mobility - Route 3 South Express Toll Lanes. Industry Day Overview

Project Mobility - Route 3 South Express Toll Lanes. Industry Day Overview Project Mobility - Route 3 South Express Toll Lanes Industry Day Overview October 15, 2014 Today s Agenda Project Mobility Overview Design Alternatives and Construction Estimates Existing Traffic Congestion/Project

More information

Alternatives Public Workshop

Alternatives Public Workshop US 1 Express Lanes Project Development & Environment (PD&E) Study Alternatives Public Workshop August 2013 1 Today s Agenda Project Background and Overview Tier 1 Alternatives Development Tier 2 Decision-Making

More information

Northwest Corridor Project (I-75/I-575) Agenda. Brief Project History. Stakeholder Briefing January 27, Brief Project history

Northwest Corridor Project (I-75/I-575) Agenda. Brief Project History. Stakeholder Briefing January 27, Brief Project history Northwest Corridor Project (I-75/I-575) Stakeholder Briefing January 27, 2010 GDOT Project No. CSNHS-0008-00(256) GDOT P.I. No. 0008256 (Formerly Project Nos. NH-75-3(232), NHS-0001-00(00) and NH-575-1(28)

More information

Memorandum. Fund Allocation Fund Programming Policy/Legislation Plan/Study Capital Project Oversight/Delivery Budget/Finance Contract/Agreement Other:

Memorandum. Fund Allocation Fund Programming Policy/Legislation Plan/Study Capital Project Oversight/Delivery Budget/Finance Contract/Agreement Other: Memorandum Date: November 20, 2017 To: Transportation Authority Board From: Eric Cordoba Deputy Director Capital Projects Subject: 12/5/17 Board Meeting: San Francisco Freeway Corridor Management Study

More information

I-95 Express Lanes Fredericksburg Extension (Fred Ex) Public Hearing. September 25, 2017

I-95 Express Lanes Fredericksburg Extension (Fred Ex) Public Hearing. September 25, 2017 I-95 Express Lanes Fredericksburg Extension (Fred Ex) Public Hearing September 25, 2017 Purpose of Tonight s Meeting Provide information and gain public input: Draft Environmental Assessment (EA) Design

More information

7.0 FREEWAYS CONGESTION HOT SPOT PROBLEM & IMPROVEMENT PROJECT ANALYSIS & DEFINITION

7.0 FREEWAYS CONGESTION HOT SPOT PROBLEM & IMPROVEMENT PROJECT ANALYSIS & DEFINITION 7.0 FREEWAYS CONGESTION HOT SPOT PROBLEM & IMPROVEMENT PROJECT ANALYSIS & DEFINITION 7.1 INTRODUCTION & METHODOLOGY FEASIBILITY REPORT Congestion hot spot problem locations have been assessed using the

More information

Public Information Meeting

Public Information Meeting Richmond Highway (U.S. Route 1) Corridor Improvements Public Information Meeting Tuesday, April 18, 2017 Mount Vernon High School 8515 Old Mt. Vernon Road, Alexandria, VA 22309 Amanda Baxter, VDOT, Special

More information

Wilshire Boulevard Bus Rapid Transit Project

Wilshire Boulevard Bus Rapid Transit Project Los Angeles County Metropolitan Transportation Authority Wilshire Boulevard Bus Rapid Transit Project COMMUNITY MEETINGS November 2008 Agenda Introduction Proposed Project Overview Participating Agencies

More information

Technology and the Changing Face of Tollways

Technology and the Changing Face of Tollways Technology and the Changing Face of Tollways Harris County Toll Road Authority Lisa Castañeda, PE, Assistant Director ITS Texas 2009 November 12, 2009 Topics Growth and Evolution of Tollways in Houston

More information

Detailed Description of Work

Detailed Description of Work Trail Items I-580 Eastbound Shoulder Running Lane and Bi-Directional Bike Lane Project Bay Area Toll Authority Task Order Contract with HNTB Corporation Effective May 12, 2014 Description of Work: Implement

More information

US 1 Express Lanes Public Kick-Off Meeting

US 1 Express Lanes Public Kick-Off Meeting US 1 Express Lanes Project Development & Environment (PD&E) Study Public Kick-Off Meeting September 7 & 8, 2011 Miami Dade County, Florida 1 Presentation Agenda Introduction to MDX Background to PD&E studies

More information

CITY OF SIGNAL HILL Cherry Avenue Signal Hill, CA

CITY OF SIGNAL HILL Cherry Avenue Signal Hill, CA CITY OF SIGNAL HILL 2175 Cherry Avenue Signal Hill, CA 90755-3799 AGENDA ITEM TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL FROM: STEVE MYRTER, P. E. DIRECTOR OF PUBLIC WORKS SUBJECT: SPRING STREET

More information

Interstate 66 Tier 1 Environmental Impact Statement (EIS)

Interstate 66 Tier 1 Environmental Impact Statement (EIS) WELCOME Welcome to the second Citizen Information Meeting for the Tier 1 Environmental Impact Statement (EIS). As an integral part in the environmental study process, the study team is seeking your comments

More information

The I-85 Express Lanes Project NASCIO Recognition Award Nomination

The I-85 Express Lanes Project NASCIO Recognition Award Nomination The I-85 Express Lanes Project 2012 NASCIO Recognition Award Nomination Submitting Agency: State Road and Tollway Authority Nomination Category: Information Communications Technology Contact: Malika Reed

More information

APPENDIX S REVISED PAGES OF THE SUPPLEMENTAL TRAFFIC IMPACT ANALYSIS

APPENDIX S REVISED PAGES OF THE SUPPLEMENTAL TRAFFIC IMPACT ANALYSIS APPENDIX S REVISED PAGES OF THE SUPPLEMENTAL TRAFFIC IMPACT ANALYSIS The capacity of the toll plaza was estimated based on data from numerous studies as well as traffic counts conducted at the toll plaza

More information

Key objectives of the survey were to gain a better understanding of:

Key objectives of the survey were to gain a better understanding of: 3 COMMUNITY INPUT Community input is an essential part of corridor studies. For the SR 87 corridor study, VTA staff conducted an extensive online survey of people living and commuting along the corridor.

More information

What are Managed Lanes?

What are Managed Lanes? Express Lanes What are Managed Lanes? Highway facilities or a set of lanes where operational strategies are proactively implemented and managed in response to changing conditions. http://ops.fhwa.dot.gov/freewaymgmt/managedlanesvideo/index.htm

More information

Transform I-66. Chief Engineer Garrett W. Moore, P.E. July 12, 2018

Transform I-66. Chief Engineer Garrett W. Moore, P.E. July 12, 2018 Transform I-66 Chief Engineer Garrett W. Moore, P.E. July 12, 2018 Transform 66: Program Goals Improve multimodal mobility by providing diverse travel choices in a cost-effective manner Enhance transportation

More information

Public Comment Meeting Geary BRT Project Draft Environmental Impact Statement/Report

Public Comment Meeting Geary BRT Project Draft Environmental Impact Statement/Report Public Comment Meeting Geary BRT Project Draft Environmental Impact Statement/Report Open House and Opportunity to Provide Comments Public comments can be submitted to the court reporter stationed in the

More information

1.221J/11.527J/ESD.201J TRANSPORTATION SYSTEMS FALL 2003 FINAL EXAMINATION. 1. Open-book and open-notes, calculators are fine -- no laptops.

1.221J/11.527J/ESD.201J TRANSPORTATION SYSTEMS FALL 2003 FINAL EXAMINATION. 1. Open-book and open-notes, calculators are fine -- no laptops. 1.221J/11.527J/ESD.201J TRANSPORTATION SYSTEMS FALL 2003 FINAL EXAMINATION Instructions: PROFESSOR JOSEPH M. SUSSMAN (LECTURER) 1. Open-book and open-notes, calculators are fine -- no laptops. 2. The exam

More information

DRAFT. The HOV/HOT Alternative: Working Paper #3

DRAFT. The HOV/HOT Alternative: Working Paper #3 Portland Area Mainline Needs Assessment DRAFT The HOV/HOT Alternative: Working Paper #3 The feasibility of an HOV/HOT lane on the Maine Turnpike HNTB Corporation Original: April 2018 Revised: June 2018

More information

ACTION: SELECT PREFERRED LIGHT RAIL ALIGNMENT FOR PHASE 2 OF THE EXPOSITION CORRIDOR TRANSIT PROJECT

ACTION: SELECT PREFERRED LIGHT RAIL ALIGNMENT FOR PHASE 2 OF THE EXPOSITION CORRIDOR TRANSIT PROJECT 6.h DATE: APRIL 2, 2009 TO: FROM: BOARD OF DIRECTORS RICHARD D. THORPE CHIEF EXECUTIVE OFFICER ACTION: SELECT PREFERRED LIGHT RAIL ALIGNMENT FOR PHASE 2 OF THE EXPOSITION CORRIDOR TRANSIT PROJECT RECOMMENDATION

More information

US 101 Express Lanes Project Open House WELCOME! Want to learn more?

US 101 Express Lanes Project Open House WELCOME! Want to learn more? Silicon Valley Express Lanes US Project Environmental Phase US Express Lanes Project Open House WELCOME! Want to learn more? VTA staff members are ready to answer your questions! Here is how: 1. Watch

More information

I-95/Temple Avenue Improvements Project Colonial Heights, VA

I-95/Temple Avenue Improvements Project Colonial Heights, VA I-95/Temple Avenue Improvements Project Colonial Heights, VA Pardon Our Dust Informational Meeting February 3, 2016 Harold Dyson, P.E. Construction Manager, Richmond District Tom Heil, P.E. Allan Myers

More information

I-105 Corridor Sustainability Study (CSS)

I-105 Corridor Sustainability Study (CSS) I-105 Corridor Sustainability Study (CSS) Metro Streets and Freeways Subcommittee March 21, 2019 Gary Hamrick Cambridge Systematics, Inc. I-105 CSS Project History & Background Funded by Caltrans Sustainable

More information

Managed Lanes: A Popular and Effective Urban Solution. Ed Regan Presented by Susan Buse

Managed Lanes: A Popular and Effective Urban Solution. Ed Regan Presented by Susan Buse Managed Lanes: A Popular and Effective Urban Solution Ed Regan Presented by Susan Buse Overview of Managed Lanes First ML: SR 91 Orange County, CA 1996 Today About 23 Operating Projects in 9 States Basic

More information

July 10, :00-11:30 a.m.

July 10, :00-11:30 a.m. July 10, 2012 10:00-11:30 a.m. 1. Welcome and Self Introductions 2. Briefing on 10 & 110 Metro ExpressLanes Stephanie Wiggins, Executive Officer, ExpressLanes Demo Project, Metro Metro ExpressLanes is

More information

3.0 PROJECT DESCRIPTION

3.0 PROJECT DESCRIPTION The following section of the Draft EIR contains a description of the proposed Elk Grove Boulevard/SR 99 Interchange Modification project, consistent with the requirements of CEQA Guidelines Section 15124.

More information

Managed Lanes in California:

Managed Lanes in California: Managed Lanes in California: Where We ve Been Where We re Going Joe Rouse Managed Lanes Manager California Department of Transportation Managed Lanes Defined Lanes that are proactively managed in response

More information

Commuter Connections Regional TDM Marketing Group Meeting

Commuter Connections Regional TDM Marketing Group Meeting Item #6 Commuter Connections Regional TDM Marketing Group Meeting September 19, 2017 Michelle T. Holland, Megaprojects Communications Manager Virginia Department of Transportation Program Area Map 2 Program

More information

Project Budget and Schedule Status

Project Budget and Schedule Status Item 8 Program Management Project Budget and Schedule Status Transit Project Delivery Finance, Budget & Audit Committee February 20, 2013 Project Schedules Project 2012 2013 2014 2015 2016 2017 2018 2019

More information

The Future of All Electronic Tolling Brian Patno Raytheon ITS Texas October 26, 2012

The Future of All Electronic Tolling Brian Patno Raytheon ITS Texas October 26, 2012 The Future of All Electronic Tolling Brian Patno Raytheon ITS Texas October 26, 2012 Copyright 2012 Raytheon Company. All rights reserved. Customer Success Is Our Mission is a registered trademark of Raytheon

More information

The Bay Bridge Corridor Congestion Study

The Bay Bridge Corridor Congestion Study Bay Bridge Corridor Congestion Study Tony Bruzzone, Arup TJPA Board Nov 1, 2010 Funded by AC Transit/Federal Transit Administration (FTA) Contracted with the Transbay Joint Powers Authority (TJPA) Stakeholders:

More information

City of Fairfax, Virginia City Council Work Session

City of Fairfax, Virginia City Council Work Session City of Fairfax, Virginia City Council Work Session Agenda Item # 4c City Council Meeting 6/2/2015 TO: FROM: SUBJECT: Honorable Mayor and Members of City Council Robert Sisson, City Manager Discussion

More information

EL CAMINO REAL BUS RAPID TRANSIT (BRT) PROJECT

EL CAMINO REAL BUS RAPID TRANSIT (BRT) PROJECT Agenda Item #4.2 EL CAMINO REAL BUS RAPID TRANSIT (BRT) PROJECT VTA BOARD WORKSHOP MAY 1, 2015 ABOUT THIS PRESENTATION CONTEXT Existing conditions and planning for growth WHAT IS THE PROJECT? Project alternatives

More information

COMMUNITY PARTICIPATION CHAPTER 8

COMMUNITY PARTICIPATION CHAPTER 8 COMMUNITY PARTICIPATION CHAPTER 8 8.1 ROLE OF THE CITY S BICYCLE ADVISORY COMMISION 8.2 BICYCLE TRANSPORTATION PLAN STAKEHOLDERS 8.2.1 Stakeholders 8.2.2 Stakeholders Letters of Recommendations 8.3 CITY

More information

Municipal Class EA To Address Traffic Congestion On The Ontario Street Corridor (Grand Bend) Public Information Meeting June 4, 2018

Municipal Class EA To Address Traffic Congestion On The Ontario Street Corridor (Grand Bend) Public Information Meeting June 4, 2018 Municipal Class EA To Address Traffic Congestion On The Ontario Street Corridor (Grand Bend) Public Information Meeting June 4, 2018 Background Agenda Traffic Study Update Class EA Alternatives Bridge

More information

Toll Rate Public Hearing

Toll Rate Public Hearing Toll Rate Public Hearing I-77 Express Toll Rate Hearing September 13, 2018 AGENDA AND HOUSEKEEPING Speaker Signup Bathrooms/Exits Facebook Live Introductions Thanks and Recognition 6:30-6:35 6:35-6:55

More information

Managed Lanes Fundamentals and Opportunities. September 12, 2013

Managed Lanes Fundamentals and Opportunities. September 12, 2013 Managed Lanes Fundamentals and Opportunities September 12, 2013 What are managed lanes? What are managed lanes? Specialized lanes rather than general purpose Synonym for high occupancy toll (HOT) lanes

More information

City of Palo Alto (ID # 7812) City Council Staff Report

City of Palo Alto (ID # 7812) City Council Staff Report City of Palo Alto (ID # 7812) City Council Staff Report Report Type: Consent Calendar Meeting Date: 3/20/2017 Summary Title: 101 Auxiliary Project Parcels Relinquishments Acceptance and Release of Parcels

More information

Los Angeles Congestion Reduction Demonstration (LA CRD) ExpressLanes Program National Evaluation:

Los Angeles Congestion Reduction Demonstration (LA CRD) ExpressLanes Program National Evaluation: Los Angeles Congestion Reduction Demonstration (LA CRD) ExpressLanes Program National Evaluation: Technical Memorandum on Congestion, Tolling, Transit, and Equity Results www.its.dot.gov/index.htm Final

More information

Interstate 66 Tier 1 Environmental Impact Statement. Cooperating and Participating Agencies Meeting March 19, 2012

Interstate 66 Tier 1 Environmental Impact Statement. Cooperating and Participating Agencies Meeting March 19, 2012 Interstate 66 Tier 1 Environmental Impact Statement Cooperating and Participating Agencies Meeting March 19, 2012 Chris Collins Virginia Department of Transportation, Environmental Division Meeting Agenda

More information

Transportation and Air Quality Committee GEL Project Briefing and Update

Transportation and Air Quality Committee GEL Project Briefing and Update Transportation and Air Quality Committee GEL Project Briefing and Update Mr. Darryl D. Van Meter, P.E. State Innovative Delivery Engineer June 11, 2015 Georgia Express Lane Projects 2 Program Benefits

More information

EXECUTIVE SUMMARY... vii 1 STUDY OVERVIEW Study Scope Study Area Study Objectives

EXECUTIVE SUMMARY... vii 1 STUDY OVERVIEW Study Scope Study Area Study Objectives Contents EXECUTIVE SUMMARY... vii 1 STUDY OVERVIEW... 1-1 1.1 Study Scope... 1-1 1.2 Study Area... 1-1 1.3 Study Objectives... 1-3 2 EXISTING CONDITIONS... 2-1 2.1 Existing Freeway Conditions... 2-4 2.1.1

More information

Institute for Real Estate Management Chapter (IREM) 77 VDOT Northern Virginia Megaprojects September 13, 2017

Institute for Real Estate Management Chapter (IREM) 77 VDOT Northern Virginia Megaprojects September 13, 2017 Institute for Real Estate Management Chapter (IREM) 77 VDOT Northern Virginia Megaprojects September 13, 2017 Susan Shaw, P.E., Megaprojects Director Virginia Department of Transportation Northern Virginia

More information

Transit Choices December 8, 2016

Transit Choices December 8, 2016 Transit Choices December 8, 2016 Agenda 1. Network Redesign Status 2. Public Hearings & Bus Stops 3. Public Education Plan 4. Capital Projects Update 1 st Draft Winter Outreach October 2015 February 2016

More information

It s Been 15 Years Already?!

It s Been 15 Years Already?! It s Been 15 Years Already?! What We ve Learned from 12 Operational Facilities 14 Parsons Brinckerhoff, 2012. THEY WORK! May 24, 2012 Parsons Brinckerhoff, 2012. 2 David Ungemah ungemah@pbworld.com May

More information

ROUTES 55 / 42 / 676 BUS RAPID TRANSIT LOCALLY PREFERRED ALTERNATIVE

ROUTES 55 / 42 / 676 BUS RAPID TRANSIT LOCALLY PREFERRED ALTERNATIVE ROUTES 55 / 42 / 676 BUS RAPID TRANSIT LOCALLY PREFERRED ALTERNATIVE April, 2012 1 INTRODUCTION The need for transit service improvements in the Routes 42/55/676 corridor was identified during the Southern

More information

Santa Clara I-280 CORRIDOR STUDY

Santa Clara I-280 CORRIDOR STUDY Santa Clara I-280 CORRIDOR STUDY OCTOBER 2017 PREPARED BY: 1.1 Background The I-280 Corridor Study within Santa Clara County is a high-level highway planning study led by the Santa Clara VTA, in partnership

More information

FM #: ETDM #: 11241

FM #: ETDM #: 11241 SR 826/Palmetto Expressway PD&E Study From SR 93/I 75 to the Golden Glades Interchange FM #: 418423 1 22 01 ETDM #: 11241 Agency/ Kick Off Meeting October 27, 2011 2 Location Map From SR 93/I 75 to Golden

More information

Freeway Improvement Project

Freeway Improvement Project CapCity Corridor History and Milestones CapCity Partners CapCity Origin and Destination analysis Origins and Destinations Destinations based on Origins North of I-80 8% O & D data prepared by SACOG Origins

More information

An Easier Commute. Learn how to use I-77 Express to save you time.

An Easier Commute. Learn how to use I-77 Express to save you time. An Easier Commute Learn how to use I-77 Express to save you time PUBLIC-PRIVATE PARTNERSHIP I-77 Express is the first-ever toll lane public-private partnership with NCDOT I-77 Mobility Partners is financing,

More information

Dulles Area Transportation Association. October 11, Susan Shaw, P.E., Megaprojects Director Virginia Department of Transportation

Dulles Area Transportation Association. October 11, Susan Shaw, P.E., Megaprojects Director Virginia Department of Transportation Dulles Area Transportation Association October 11, 2017 Susan Shaw, P.E., Megaprojects Director Virginia Department of Transportation Transform 66: Outside the Beltway 2 Project Overview Multimodal improvements

More information

VDOT I-66 Inside the Beltway Eastbound Widening Environmental Assessment. Staff Recommendations

VDOT I-66 Inside the Beltway Eastbound Widening Environmental Assessment. Staff Recommendations VDOT I-66 Inside the Beltway Eastbound Widening Environmental Assessment Staff Recommendations Department of Environmental Services Transportation January 28, 2017 Timeline of Transform66 June 2012: I-66

More information

The I-680 Southbound Express Lane

The I-680 Southbound Express Lane The I-680 Southbound Express Lane ALAMEDA County Transportation Commission FY2014-15 Annual Report SUNOL SMART CARPOOL LANE JOINT POWERS AUTHORITY Table of Contents Message from the Chair...3 I-680 Southbound

More information

Priced Managed Lanes in America. October 2013

Priced Managed Lanes in America. October 2013 Priced Managed Lanes in America October 2013 1 Priced Managed Lanes What are they? Where are they? Why do them? When to do them? Common issues Lessons learned What are Priced Managed Lanes? The subset

More information

Regional Transportation Needs Within Southeastern Wisconsin

Regional Transportation Needs Within Southeastern Wisconsin Regional Transportation Needs Within Southeastern Wisconsin #118274 May 24, 2006 1 Introduction The Southeastern Wisconsin Regional Planning Commission (SEWRPC) is the official areawide planning agency

More information

122 Avenue: 107 Street to Fort Road

122 Avenue: 107 Street to Fort Road : 107 Street to Fort Road November 24, 2015 4:30 8:00 p.m. Meeting Purpose Summarize project work completed to date Share results of public input from Phase 1 Share the draft concept plan and proposed

More information

North Coast Corridor:

North Coast Corridor: North Coast Corridor: Connecting People, Transportation & Environment Legislative Hearing: 11.8.10 1 North Coast Corridor Region s Lifeline A Regional Strategy Mobility, Economy & Environment North Coast

More information

MnPASS System Today and the Future

MnPASS System Today and the Future MnPASS System Today and the Future April 2010 By Nick Thompson Minnesota Department of Transportation Topics Minnesota s Current and Future MnPASS High Occupancy Toll Systems Overview of the MnPASS System

More information

August 12, The Honorable Edmund G. Brown Jr. Governor, State of California State Capitol Sacramento, CA Dear Governor Brown:

August 12, The Honorable Edmund G. Brown Jr. Governor, State of California State Capitol Sacramento, CA Dear Governor Brown: August 12, 2014 The Honorable Edmund G. Brown Jr. Governor, State of California State Capitol Sacramento, CA 95814 Dear Governor Brown: The (VTA) supports AB 1720 (Bloom) and respectfully requests that

More information

IMPACTS TO TRANSIT FROM LOS ANGELES CONGESTION REDUCTION DEMONSTRATION. Word Count: 3,386 (body) + 2,000 (8 tables) + 1,500 (6 figures) = 6,886 words

IMPACTS TO TRANSIT FROM LOS ANGELES CONGESTION REDUCTION DEMONSTRATION. Word Count: 3,386 (body) + 2,000 (8 tables) + 1,500 (6 figures) = 6,886 words IMPACTS TO TRANSIT FROM LOS ANGELES CONGESTION REDUCTION DEMONSTRATION TRB PAPER -0 Brian Pessaro, AICP Senior Research Associate Center for Urban Transportation Research (CUTR) University of South Florida

More information

1.0 INTRODUCTION 1.1 PURPOSE OF THIS REPORT

1.0 INTRODUCTION 1.1 PURPOSE OF THIS REPORT 1.0 INTRODUCTION This chapter provides an overview of the purpose, authorization and focus of this Recirculated Draft Environmental Impact Report (EIR), an identification of the Lead Agency, an outline

More information

Active Traffic Management and Part-Time Shoulder Use in Montgomery County, PA

Active Traffic Management and Part-Time Shoulder Use in Montgomery County, PA Active Traffic Management and Part-Time Shoulder Use in Montgomery County, PA PENN STATE TESC SESSION 8B MOVING PENNDOT AND PTC FORWARD DECEMBER 8, 2017 Agenda Define Active Traffic Management and describe

More information

4 Level of Service Results: HOV and Express Lanes

4 Level of Service Results: HOV and Express Lanes 4 Level of Service Results: HOV and Express Lanes Considering the importance of managed lanes (such as HOV and express lanes) in improving the overall performance of a corridor, Alameda CTC started monitoring

More information

Capital Beltway HOT Lanes - Frequently Asked Questions

Capital Beltway HOT Lanes - Frequently Asked Questions Capital Beltway HOT Lanes - Frequently Asked Questions December 20, 2007 1. What is the cost of the project? The fixed-price design-build cost is approximately $1.4 billion. 2. Why have the project costs

More information

PURPOSE AND NEED SUMMARY 54% Corridor Need 1. Corridor Need 2. Corridor Need 3. Corridor Need 4. Corridor Need 5

PURPOSE AND NEED SUMMARY 54% Corridor Need 1. Corridor Need 2. Corridor Need 3. Corridor Need 4. Corridor Need 5 SUMMARY PURPOSE AND NEED Chapel Hill Transit ridership has increased Buses operate every 4 minutes and have standing room only Exceeding seated capacity by 12% Corridor Need 1 by more than 20 percent between

More information

TABLE TRAFFIC ANALYSIS SCENARIOS

TABLE TRAFFIC ANALYSIS SCENARIOS 4.11 TRANSPORTATION The potential traffic impacts of the proposed project are evaluated in the Buena Park Beach/Orangethorpe Mixed Use Project Traffic Analysis (Traffic Analysis) by Austin-Foust Associates

More information

DEVELOPING A POLICY TO PLAN AND OPERATE MANAGED LANES IN NORTH CENTRAL TEXAS: LBJ IN DALLAS COUNTY AND AIRPORT FREEWAY IN TARRANT COUNTY

DEVELOPING A POLICY TO PLAN AND OPERATE MANAGED LANES IN NORTH CENTRAL TEXAS: LBJ IN DALLAS COUNTY AND AIRPORT FREEWAY IN TARRANT COUNTY DEVELOPING A POLICY TO PLAN AND OPERATE MANAGED LANES IN NORTH CENTRAL TEXAS: LBJ IN DALLAS COUNTY AND AIRPORT FREEWAY IN TARRANT COUNTY Regional Transportation Council May 11, 2006 Transportation Department

More information

Enhancing Return on Investment for MnPASS Express Lanes

Enhancing Return on Investment for MnPASS Express Lanes Enhancing Return on Investment for MnPASS Express Lanes Minnesota s Transportation Conference February 28, 2018 mnpass.org Agenda MnPASS Express Lane Background MnPASS System Update Enhancing Return on

More information

Transit Operations in the I-95 Express Lanes

Transit Operations in the I-95 Express Lanes Transit Operations in the I-95 Express Lanes TRB 15 th International Conference on Managed Lanes Miami, Florida Presented by Diane Quigley FDOT Transit Planning Administrator May 5, 2016 FDOT Governance

More information

Public Hearing October 21, 2014 University of North Florida Adam W. Herbert University Center Alumni Drive Jacksonville, FL 32224

Public Hearing October 21, 2014 University of North Florida Adam W. Herbert University Center Alumni Drive Jacksonville, FL 32224 - Project Development & Environment Study from SR 9B to SR 202 (JTB Blvd.) Duval County, Florida Financial Project ID: 209301-3-22-01 Public Hearing October 21, 2014 University of North Florida Adam W.

More information

NOTICE OF AVAILABILITY/NOTICE OF COMMENT PERIOD OF A DRAFT EIR/EIS/EIS FOR PUBLIC REVIEW AND HEARINGS

NOTICE OF AVAILABILITY/NOTICE OF COMMENT PERIOD OF A DRAFT EIR/EIS/EIS FOR PUBLIC REVIEW AND HEARINGS Tahoe Transportation District 128 Market Street, Suite 3F Stateline, NV 89449 Phone: (775) 589-5500 www.tahoetransportation.org Federal Highway Administration 650 Capitol Mall, Suite 4-100 Sacramento,

More information

Charlotte Region Fast Lanes Study Phase III

Charlotte Region Fast Lanes Study Phase III Charlotte Region Fast Lanes Study Phase III Stakeholder Workshop #3 December 13, 2012 Fast Lanes Study, Phases I and II Performed between 2007 and 2009 Evaluated all types of managed lanes (HOV, HOT, truck-only

More information

Austin Avenue Bridges Project. Public Meeting Summary

Austin Avenue Bridges Project. Public Meeting Summary Austin Avenue Bridges Project Public Meeting Summary June 29, 2016 Red Table Safety and Connectivity Notes: 1. Would like to see forensic report evaluations 2. What is the lifespan? 3. Extend safety considerations

More information

Today s Agenda. Welcome & Introductions. I-526 Lowcountry Corridor Update. Table Discussions. Next Steps / Conclusion

Today s Agenda. Welcome & Introductions. I-526 Lowcountry Corridor Update. Table Discussions. Next Steps / Conclusion SCDOT Turns 100! SCDOT Turns 100! Today s Agenda Welcome & Introductions I-526 Lowcountry Corridor Update Table Discussions Next Steps / Conclusion Project Limits I-526 Lowcountry Corridor Project Description

More information

SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY

SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY THIS PRINT COVERS CALENDAR ITEM NO. : 11 DIVISION: Sustainable Streets BRIEF DESCRIPTION: SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY Approving traffic modifications on Twin Peaks Boulevard between Christmas

More information

Diamond Springs Parkway Project

Diamond Springs Parkway Project Diamond Springs Parkway Project Public Information Meeting, Monday, March 18, 2013 330 Fair Lane, Building A, Placerville County Board of Supervisors Meeting Room, 6:30 8:00 p.m. PRESENTED BY: County of

More information

INTRODUCTION. The focus of this study is to reduce congestion and improve mobility for all modes of transportation. Figure ES-1 Study Corridor Map

INTRODUCTION. The focus of this study is to reduce congestion and improve mobility for all modes of transportation. Figure ES-1 Study Corridor Map INTRODUCTION The I-280 Corridor Study is a highway planning study led by Santa Clara VTA, in partnership with the City of Cupertino and in coordination with other stakeholders in the study area. The study

More information