SH&E Work Method Statement Concrete Cutting & Drilling Fast Cut Qld Pty Ltd, 91 Basalt St, GEEBUNG QLD 4031 ph ABN:
|
|
- Esther Pope
- 5 years ago
- Views:
Transcription
1 SH&E Work Method Statement Concrete Cutting & Drilling Fast Cut Qld Pty Ltd, 91 Basalt St, GEEBUNG QLD 4031 ph ABN: OHS-FRM-100 Rev 11 (07/18) Page 1 SH&EWMS No.: F-C-QLD-05 Revision Date: July 2018 Revision Due: July 2019 Work Activity: Core Drilling Brief Description of Work Activity: Core Drilling as required Personnel responsible for monitoring this activity: Rob East PH: (07) Codes of Practice/Standards Consulted: Work Health and Safety Act 2011, Work Health and Safety Reg 2011, How to Manage Work Health and Safety s Code of Practice 2011, Hazardous Manual Tasks Code of Practice 2011, Managing Noise and Preventing Hearing Loss at Work Code of Practice 2011, Plant Code of Practice 2005, Hazardous Chemicals Code of Practice 2003, Managing the of Falls at Workplaces Code of Practice 2011,Managing the Work Environment and Facilities Code of Practice 2011, Code of Practice stated in Control Measures. Equipment, refer to the operator manual. Plant, PPE and Equipment required for this activity: Core Drill and Stand. Safety glasses, Hard hat, Hi Vis, steel capped boots, Long sleeves, hearing protection, dust masks. Details of Maintenance Checks Required for this activity: Plant Assessment, Daily Pre-start Checklist, daily servicing by operator, scheduled servicing by mechanic. Electrical tool tested and tagged. Project / Site: Client: Materials Used: MSDS Required: No High Construction Work: Working on or adjacent to a road, Work that is carried out on or near energised electrical installations or services, the movement of powered mobile plant. Personnel Qualifications Required for this activity: General safety induction, competency based assessment. Review and corrective actions: To be reviewed daily by personnel responsible for monitoring this activity, to be reviewed weekly with formal audit. Hazard report to be completed to address corrective action required. Minor: Complete incident form. Major: Complete incident form with an investigation. Specific training required for this activity: Site specific Induction, SH&EWMS moving plant, SH&EWMS Hazardous Substances. 05 Core Drilling Version 11 Created July 2018 Review Date July 2019 Page 1 of 9
2 PART 1: Fast Cut Pty Ltd - Job Safety & Environmental Analysis/Safe Work Method Statement Analysis by: Fast Cut Qld Pty Ltd ABN: Issue No. Eleven Copy No. 11 Revision date : July 2019 Document No. JSA-Fast Cut 005 Doc. Controller Approved: Draft 11 TASK: Using a Core Drill & Stand JSA-Fast Cut 05 Description of any Relevant Interfaces with Other Trades & Other Activities: Please reference PC s daily pre-start meeting. PART 2: JSEA/SWMS PROCEDURES 1. The JSEA/SWMS must be specific to the site environment and the particular work-crew, equipment and materials. It must identify plant and equipment to be used, hazardous materials, qualifications/licences of personnel, permits and authorisations required. 2. The JSEA/SWMS must comply with the Principal Contractors Safe Work Instructions, General Safety Instructions Booklet and environmental control plans. It must also comply with and specify relevant codes of Practice, legislation and contract requirements. 3. The workers and supervisors involved in carrying out the work activity must be consulted in identifying the safety and environmental hazards and determining the work methods. 4. Any significant changes to the work process or sequence or to the type of plant or materials used is to trigger a review of this JSEA/SWMS. The need to review/amend the JSEA/SWMS is to be assessed in the event of a LTI/MTI, Near Miss, Environmental Breach, or notice served by a regulatory authority. 5. Changes are not to be made to the Work Methods, Plant or Materials prescribed in this JSEA/SWMS without first consulting with the work team. Changes are to be documented, reviewed and approved. All workers are to be inducted into the changes and a record maintained. PART 3: CHECKLIST & SIGN OFF CHECKLIST - In preparing and reviewing this JSEA/SWMS, the following considerations have been taken into account: Tick if Applicable. Manufacturers/Suppliers Recommendations Experience/competency/licensing of workers/operators/supervisors Previous (similar work) injuries/incidents Hazardous material safeguards Engineering/Client approvals Safety Alerts Site Safety Plan Environmental Management Plan Workcover Codes/Guides Plant/Equipment Suitability Revision 8 Date:20/10/2015 Prepared: Tayla Roberts Reviewed: Rob East Approved: 20/10/2015 Description of Changes: Reviewed and signed off Revision 9 Date:05/07/2016 Prepared: Tayla Roberts Reviewed: Rob East Approved: 05/07/2016 Description of Changes: Reviewed and signed off Signed: Signed: 05 Core Drilling Version 11 Created July 2018 Review Date July 2019 Page 2 of 9
3 Revision 10 Revision 11 Date:05/07/2017 Prepared: Tayla Roberts Reviewed: Rob East Approved: 05/07/2017 Signed: Description of Changes: Reviewed and signed off Date:02/07/2018 Prepared: Tayla Roberts Reviewed: Rob East Approved: 02/07/2018 Signed: Description of Changes: Reviewed and signed off PART 4: SAFETY AND ENVIRONMENTAL ANALYSIS & DETERMINATION OF WORK METHODS Project / Site: Client: Principal Contractors Safe Work Method Instructions to be complied with: ALL Requirements of Principal Contractors Safety Instructions Booklet to be complied with: ALL Codes/Standards to be complied with: How to Manage Work Health and Safety s Code of Practice 2011, Managing Noise and Preventing Hearing Loss at Work Code of Practice 2011, Plant Code of Practice 2005, Hazardous Manual Tasks Code of Practice 2011, Hazardous Chemicals Code of Practice 2003 Legislation to be complied with: WH&S Act of 2011, WH&S Regulation of 2011 Permits/Licences/Approvals required: Competent plant operator, Truck driver, Hot work Permit (if required) PART 4A: SET UP FOR DRILLING 1. Contact Site Person before entry to work area 2. Drill for Locksen 3. Mount Drill Rig 4. Attach Drill and Barrel 5. Ensure Area Clear of Hazards Summary of Assessed Hazards Please complete Working at Height Yes Exposure to hazardous material Yes Human factors Yes Hot work Yes Confined space entry No Release of stored energy Yes Excavation & collapse No Heat stress Yes Manual handling Yes Slip, trips and falls Yes Underground service Yes Moving Vehicles Yes Working with plant Yes Use of tools Yes Environmental considerations Yes Moving Plant Yes Live power sources Yes 05 Core Drilling Version 11 Created July 2018 Review Date July 2019 Page 3 of 9
4 Task Description Hazards Likelihood x Step 1 Pre Start Checks Control Measures Daily Plan AC x 1 1 Pre Start Check Tool Box Meeting Vehicle on Site AC x 2 2 All vehicles to be tested and approved for use on site. Fitness for Work P x 2 2 Attend work in a fit state free from influence of illicit drugs and alcohol. In right frame of mind Report all prescription medication to supervisor Cuts, abrasions P x S 2 Correct PPE long sleeves hi-vis shirts, long trousers, safety glasses, hearing protection, dust mask if required. Responsible Person Likelihood x New U x 3 3 Supervisor Supervisor U x 3 3 U x 3 3 U x MI 3 Step 2 Load / unload stores/ equipment Manual handling P x S 2 Ensure loads are lifted / carried using the appropriate methods Cuts P x S 2 Correct PPE to be worn long sleeves hi vis shirt, long pants, steel cap boots, safety glasses and hard hat. Live power sources and electrocution or electric shock. P x 1 1 Suspend all leads and power supply to prevent electric shock by water on ground. Ensure that pre assessments have been undertaken by the contractor if original plans have not been consulted by a qualified engineer. If no consultation has taken place, works are not to be undertaken by Fast Cut employee. No drilling to be completed until Permit to Work is approved. Water Use P x 1 1 Is adequate water supply to core drill to avoided equipment damage. within 25m from cut area or use water tank from company vehicle have it located near work area Supervisor/ All U x MI 3 All U x MI 3 U x MI 3 U x M Core Drilling Version 11 Created July 2018 Review Date July 2019 Page 4 of 9
5 Task Description Hazards Likelihood x Step 3 Drilling Flying Objects including drill chucks and damaged barrels. Falling Objects including core through suspended slabs. Control Measures L x MA 1 Barricade work area. Spotter required when coring through suspended slabs. Ensure drill bits are correct and secured and inspect barrel condition prior to drilling. Check key and spanners have been removed prior to starting, Spotter required. Excess Noise Hearing Loss AC x MA 1 Wear Australian Standard Optime 5 Earmuffs protection. Require others to wear ear muffs, ear plugs or vacate area. Barricades and signage Dust Particles/Slurry splashing eyes Dust/mist breathing L x MA 1 All personnel in area to wear eye protection and dust masks. Excessive dust requires mono goggles or Face shield. Sweep up dust as soon as practical and dispose of in waste bin. Dampen down if require. Plenty of water or coolant is used and that the coolant/water is suppressing dust at the point of generation (airborne dust is a health hazard) Environmental risk Slurry L x MA 1 Dam storm water and pick up with wetvac or CCS EPU. Slurry taken off site to approved dumping site. Skin Irritation P x S 2 Use correct PPE, long sleeves, trousers, gloves Cutting of services L x CA 1 Make sure client has located all services, especially electricity and has signed work form for service locations before cutting Fumes P x MA 2 Use Generator in well ventilated area or use mains power. Supply extra ventilation (extractor fans/blower fans). Run extra power leads to remove generator from area, max 25m. Contact office if any doubt about ventilation. Responsible Person Likelihood x 05 Core Drilling Version 11 Created July 2018 Review Date July 2019 Page 5 of 9 New R x MI 3 U x MI 3 U x MI 3 U x MI R x MI 3 U x MO 3 R x MI 3
6 Task Description Hazards Likelihood x Step 4 Drilling Walls Step 5 Drilling Floors Step 6 Site Specific Hazards & Controls Control Measures Fall injury L x MA 1 Scaffold to be erected by qualified competent person, certification from registered training organization required. Received training in working at heights if over 2m Rescue procedure required if over 2m Falling object injury L x MA 1 Barricades & warning signs to be in position prior to cutting Personnel not to walk / work under cutting area, wear hard hat if working near All staff to keep a look out, spotter required. Site approved PPE as per JSEA Falling Object injury L x MA 1 Barricades & warning signs to be in position prior to cutting Personnel not to walk / work under cutting area, wear hard hat if working near All staff to keep a look out, spotter required. Site approved PPE as per JSEA Responsible Person Likelihood x New Supervisor U x MI 3 All Staff All Staff R x MI 3 R x MI 3 Slips, trips P x S 2 Clean site area as required Supervisor R x MI 3 Equipment damage L x S 2 Ensure equipment is correctly secured Driver R X MI 3 prior to leaving Step 7 Exiting Site Manual Handling, clean up P x S 2 Ensure area is safe and free of debris Driver R X MI 3 The qualitative risk analysis matrix has been taken from AS/NZS 4360:1999 Management Standard. This matrix is used to arrive at the Level of score throughout the risk analysis and is presented here for reference. 05 Core Drilling Version 11 Created July 2018 Review Date July 2019 Page 6 of 9
7 PART 5: SUPERVISORS SIGN-OFF I understand and will comply with the requirements of this JSEA/SWMS. I will monitor the implementation of this JSEA/SWMS, and take action in the event of any noncompliance. I will consult with the work crew and amend this JSEA/SWMS as necessary in the event of any changes to the work method, equipment, sequence, materials or the like and in the event of any safety or environmental breaches, incidents or near misses. Supervisor 1: Name: Rob East Signature: Date: Supervisor 2 As applicable Name: Signature: Date: PART 6: JSEA/SWMS RECORD OF CONSULTATION AND INDUCTION INTO WORK METHODS I, the worker have been consulted, acknowledge and understand the requirements of this JSEA/SWMS. I have the opportunity at monthly Toolbox meetings to provide feedback on the development and review of this document. NOTE: DO NOT SIGN THIS RECORD IF YOU DO NOT UNDERSTAND THE SAFE WORK METHODS PRESCRIBED ASK THE SUPERVISOR TO EXPLAIN Ref # Last Name First Name Job Description (Trade Classification) Employed By JSEA/ SWMS Rev# Signature Date of Induction Induction Verified by: 05 Core Drilling Version 11 Created July 2018 Review Date July 2019 Page 7 of 9
8 INSTRUCTIONS - RISK ASSESSMENT BY HAZARD SWMS PREPARATION Select appropriate person(s) to develop the SWMS. Person preparing SWMS is to complete all pages. Column A Identify Activity Steps (consult all parties involved). Column B Identify hazards associated with each Activity Step. Column C Use Assessment Table to determine consequences and likelihood of occurrence. Insert the Alpha abbreviation into SWMS under Column C Sub-columns L & C. Column D - Use Matrix to determine Class of. Insert the numeric rating under R. Column E - Determine appropriate control measures to eliminate the risk or reduce it to as low as practicable. Column F - Allocate responsibility for implementing required control under Who By. Column G - Reassess the risk of each control and insert the Alpha and Numeric rating chart following the controls Column H - Use Matrix to determine Class of. Insert the numeric rating under R. Assess items in the Part B Evaluation/Review Checklist to ensure relevant to the SWMS and amend if necessary. Train all persons involved in activities covered by SWMS using specific training meeting or toolbox talk and have them sign the last page of SWMS to confirm training complete. Submit SWMS to relevant Site Management Team member. Relevant Site Management Team members evaluate SWMS using Part B - Evaluation/Review Checklist. Nominated person completes SWMS Evaluation/Review Checklist and amended SWMS when necessary and forwards a copy to Project Safety Supervisor. Communicate all SWMS amendments via toolbox talks to all persons involved in SWMS activities. NB. Use the following tables to determine the risk class for each activity step. RISK CLASS OR RATING (R) High 1 Medium 2 Low 3 RISK ASSESSMENT TABLE Likelihood (L) (C) Almost Certain Expected To Occur In Most Catastrophic Permanent Disability/Death (AC) Circumstances (CA) Likely Major Extensive Injuries/ Serious LTI (L) Probably Occur In Most Circumstances (MA) Possible Significant Disabling/Short-Term LTI (P) Probably Occur At Some Time (S) Unlikely Moderate Medical Treatment (U) Could Occur At Some Time (MO) Rare (R) May Occur In Exceptional Circumstances Minor (MI) First Aid Treatment Multiply by Likelihood to determine Rating. RISK MATRIX (C) Likelihood (L) Catastrophic (CA) Major (MA) Significant (S) Moderate (MO) Minor (MI) Almost certain (AC) Likely (L) Possible (P) Unlikely (U) Rare (R) Hierarchy of Control Elimination. Modify the process method or material to eliminate the hazard completely Substitution. Redesign/Engineering Isolate Administration PPE. Replace the material, substance or process with a less hazardous one Controls Redesign or modify the plant or process to reduce or eliminate the risk Separate the hazard from the person by safeguarding or by space or time. Adjust the exposure time or conditions or process by training, procedure, signs etc Use appropriately designed and properly fitted equipment where other controls are not practicable or are accepted Monitoring as per WH&S Reg Core Drilling Version 11 Created July 2018 Review Date July 2019 Page 8 of 9
9 PART 7: JSEA/SWMS SUMMARY REPORT JSEA/SWMS CHECKLIST ITEM CHECKLIST CRITERIA COMPLIES Yes or No 01 Does the JSEA/SWMS set out step-by-step all of the activities? Y/N 02 Does the JSEA/SWMS describe how each activity will be carried out? Y/N 03 Does the JSEA/SWMS consider the environment within which the activities are to be undertaken including interfaces with other trades? Y/N 04 Does the JSEA/SWMS identify safety, health and environmental hazards that will/may arise at each stage of the work? Y/N 05 Does the JSEA/SWMS clearly document control measures to be put in place for each hazard that is identified? Y/N 06 Does the JSEA/SWMS describe all plant and equipment that will be used? Y/N 07 Does the JSEA/SWMS identify relevant Standards and Codes of Practice that must be complied with? Y/N 08 Does the JSEA/SWMS identify any pre-start and in process certifications/authorisations/permits? Y/N 09 Does the JSEA/SWMS specify licensing and qualifications required for personnel (including specific qualifications for specific roles/tasks)? Y/N 10 Does the JSEA/SWMS specify training and/or trialling required to enable the work to be done safely? Y/N Reviewed By: Rob East Signature: Date: 2 nd July 2018 Signed by the Management Representative of Fast Cut QLD Pty Ltd PRINCIPAL CONTRACTORS COMMENTS: JSEA/SWMS has been reviewed with no comments JSEA/SWMS has been reviewed with issues raised with Fast Cut Qld: Summary of details of issues/comments/rectifications required: Reviewed by Principal Contractor: Signature: Date: 05 Core Drilling Version 11 Created July 2018 Review Date July 2019 Page 9 of 9
SH&E Work Method Statement Concrete Cutting & Drilling Fast Cut Qld Pty Ltd, 91 Basalt, GEEBUNG PH M ABN
SH&E Work Method Statement Concrete Cutting & Drilling Fast Cut Qld Pty Ltd, 91 Basalt, GEEBUNG PH 07 3265 6537 M 0411 756 719 ABN 45 081 359 613 OHS-FRM-100 Rev 11 (07/18) Page 1 SH&EWMS No.: F-C-QLD-30
More informationSH&EWMS No.: F-C-QLD-10 Revision Date: July 2018 Revision Due: July 2019
OHS-FRM-103 Rev11 (07/18) SH&E Work Method Statement Concrete Cutting & Drilling Fast Cut Qld Pty Ltd, 91 Basalt, GEEBUNG ABN 45 081 359 613 Phone: 07 3889 8827 Mobile: 0411 756 719 Page 1 SH&EWMS No.:
More informationSH&EWMS No.: F-C-QLD-14 Revision Date: July 2018 Revision Due: July 2019
SH&E Work Method Statement Concrete Cutting & Drilling Fast Cut Qld Pty Ltd, 91 Basalt, GEEBUNG ABN 45 081 359 613 Phone: 07 3265 6537 Mobile: 0411 756 719 OHS-FRM-100 Rev 11 (07/19) Page 1 SH&EWMS No.:
More informationSH&E Work Method Statement Concrete Cutting & Drilling Fast Cut Qld Pty Ltd, 91 Basalt St, GEEBUNG QLD 4031 ph ABN:
SH&E Work Method Statement Concrete Cutting & Drilling Fast Cut Qld Pty Ltd, 91 Basalt St, GEEBUNG QLD 4031 ph 07 3265 6537 ABN: 45 081 359 613 OHS-FRM-100 Rev 6 (07/14) Page 1 SH&EWMS No.: F-C-QLD-01
More informationSH&EWMS No: F-C-QLD-23 Revision Date: July 2018 Revision Due: July Brief Description of Work Activity: Use Petrol Hand Saw / Ring Saw
SH&E Work Method Statement Concrete Cutting & Drilling Fast Cut Qld Pty Ltd, 91 Basalt St, GEEBUNG 4034 ABN 45 081 359 613 Phone: 07 3265 6537 Mobile: 0411 756 719 OHS-FRM-100 Rev 11 (07/18) Page 1 SH&EWMS
More informationSH&EWMS No.: FC-QLD-017 Revision Date: July 2017 Revision Due: July 2018
SH&E Work Method Statement Concrete Cutting & Drilling Fast Cut Qld Pty Ltd, 91 Basalt St, GEEBUNG 4034 ABN 45 081 359 613 Phone: 07 3265 6537 Mobile: 0411 756 719 OHS-FRM-100 Rev 10 (07/17) Page 1 SH&EWMS
More informationWORK METHOD STATEMENT STRUCTURAL STEEL
ORGANISATION DETAILS Organisation Name: Gedoun Constructions Pty Ltd Contact Name: Joe Gedoun ACN/ABN: 52 284 873 581 Contact Position: Director Address: PO Box 1138, Townsville QLD 4810 Contact Phone
More informationJOB SAFETY ANALYSIS. How to use the Risk Assessment Charts. Likelihood A (Almost Certain) B (Likely) C (Possible)
Page 1 of 6 How to use the Assessment Charts 1. Determine the Likelihood on the Qualitative Assessment Process Chart (pick a letter applicable to the task). 2. Determine the Consequence on the Qualitative
More informationWORK METHOD STATEMENT CARPET LAYING
ORGANISATION DETAILS Organisation Name: Gedoun Constructions Pty Ltd Contact Name: Joe Gedoun ACN/ABN: 52 284 873 581 Contact Position: Director Address: PO Box 1138, Townsville QLD 4810 Contact Phone
More informationWORK METHOD STATEMENT TERMITE PROTECTION
ORGANISATION DETAILS Organisation Name: Gedoun Constructions Pty Ltd Contact Name: Joe Gedoun ACN/ABN: 52 284 873 581 Contact Position: Director Address: PO Box 1138, Townsville QLD 4810 Contact Phone
More informationSAFE WORK METHOD STATEMENT Part B
SAFE WORK METHOD STATEMENT Part B SWMS No.: 01 WORK ACTIVITY DESCRIPTION: Door Installation All FORESEEABLE OHS & ENVIRONMENTAL HAZARDS & RISKS ASSOSSIATED WITH THE WORKS MUST BE ASSESSED & ALLOCATED CONTROLS
More informationHow severely could the risk hurt someone? Low/Insignificant First aid
Safe Work Method Statement No: WMS-0 Task: Line Marking This WMS is submitted to: Project name and site address: Contact: Preparation of WMS by: Robert Raams Company: Enwon (Australia) Pty Ltd Authorised
More informationSAFE WORK METHOD STATEMENT SWMS No Version
SAFE WORK METHOD STATEMENT SWMS No Version Company Name: Hunter Readymixed Concrete Pty Ltd 00 004 Location: Thornton Cessnock Tea Gardens Gateshead ABN: 6 076 08 695 SWMS Developed By: Duane Harrison
More informationHow severely could the risk hurt someone?
Safe Work Method Statement No: WMS-08 Task: Install Drainage This WMS is submitted to: Project name and site address: Contact: Preparation of WMS by: Robert Raams Company: Enwon (Australia) Pty Ltd Authorised
More informationThe Sample Company Pty Ltd
Job Safety and Environmental Analysis (JSEA) / Safe Work Method Statement (SWMS) Part 1: Project and Task Identification Process Initiators of SWMSs are responsible for consulting the Project Supervisor,
More informationSAFE WORK METHOD STATEMENT
SAFE WORK METHOD STATEMENT EXCAVATION OR TRENCHING Prepared for Client: Rural Construction & Maintenance Pty Ltd Project No: 1 Site: 660 Great Ocean Road, Bellbrae Date Prepared: 29/07/2015 1. RESPONSIBILITIES
More informationContractor OHS Induction. AOHS-05-GUI September 2016
Contractor OHS Induction AOHS-05-GUI-002 8 September 2016 1 About AQWEST AQWEST is a Government Trading Enterprise responsible for supplying drinking water to Bunbury. Formed in 1906 as the Bunbury Water
More informationSafe Work Method Statement
TE CONTROLLED COPY OF TIS DOCUMENT IS ON TE COMPUTER NETWORK PRINTED COPIES ARE ONLY CURRENT FOR TE DATE AT TE BOTTOM OF TE PAGE. Title Working at eight SWMS No. 16 Authorized and email Signed by the (Managing
More informationSafe Work Method Statement
Title Skid Steer Operation (Bobcat) SWMS No. 14 Authorized and email Signed by the (Managing Director / CEO / Partner / Proprietor) on Date 01/08 /2016 Safe Work Procedure for the Work:- Yes No Employees
More informationWORK METHOD STATEMENT ALUMINIUM WINDOWS AND DOORS
ORGANISATION DETAILS Organisation Name: Gedoun Constructions Pty Ltd Contact Name: Joe Gedoun ACN/ABN: 52 284 873 581 Contact Position: Director Address: PO Box 1138, Townsville QLD 4810 Contact Phone
More informationHow severely could the risk hurt someone? Low/Insignificant First aid
Safe Work Method Statement No: WMS-02 Task: Concreting, Formwork and Steel Fixing This WMS is submitted to: Project name and site address: Contact: Preparation of WMS by: Robert Raams Company: Enwon (Australia)
More informationSafe Work Method Statement LRB TREE SERVICES 6 Behland St, Kearneys Spring QLD, 4350 ABN
JOB NO: PROJECT: DATE: 1/1/2018 SWMS NO: SWMS 001.1 PREPARED BY: LUKE BLINCO REVISED BY: ACTIVITY: TREE REMOVAL & PRUNING SIGNED BY: REVISION DATE: MINIMUM PERSONAL PROTECTIVE EQUIPMENT (PPE) REQUIREMENTS
More informationWH&S Act 2011 & Regulations 2011, Environmental Protection Act and Regulations
Workplace Address: Page 1 of PART 1: TASK DETAILS Client: JOB/TASK: Using Water blaster PART 2: RESOURCES Relevant Legislation/Codes Practice: Training Required: Equipment Used: Materials Used: Substances
More informationWORK METHOD STATEMENT ELECTRICAL
ORGANISATION DETAILS Organisation Name: Gedoun Constructions Pty Ltd Contact Name: Joe Gedoun ACN/ABN: 52 284 873 581 Contact Position: Director Address: PO Box 1138, Townsville QLD 4810 Contact Phone
More informationSWMS No 012 Samark North Qld Pty Ltd ABN : Electrical Contractors License C37121 Page 2 of 6
Samark North Qld Pty Ltd SWMS SWMS No 0 Samark North Qld Pty Ltd ABN : 99 08 98 87 Electrical Contractors License C37 Page of 6 Safe Work Method Statement Title: SWMS:0 INSTALLING LIGHT POLES Work Method
More informationJOB SAFETY ENVIRONMENT ANALYSIS (JSEA) Working With In Situ Testing Rigs
Personnel Involved Manager Project Operators Assistant Notes re Operator/Off-Sider Training Allan McConnell In situ testing is a niche business with very few rigs in Australia. There are no specific training
More informationWHS OHS HAZARD REGISTER (SITE AND OFFICE OPERATIONS)
WHS 017 - WHS 017 Hazard Register - Version 5.0 April 20 Doc No: WHS 017 Effective Date: 04/04/20 1 WORKING WITH EARTHMOVING PLANT/ TRUCKS/SITE VEHICLES COLLISIONS OTHER PLANT EQUIPMENT SITE VEHICLES PERSONNELL
More informationSAFE WORK METHOD STATEMENT
SAFE WORK METHOD STATEMENT AUGER / POST HOLE DIGGER Prepared for Client: Rural Construction & Maintenance Pty Ltd Project No: 1 Site: 660 Great Ocean Road, Bellbrae Date Prepared: 29/07/2015 1. RESPONSIBILITIES
More informationSWMS No 001 Samark North Qld Pty Ltd ABN : Electrical Contractors License C37121 Page 2 of 5
Samark North Qld Pty Ltd SWMS Manual SWMS No 00 Samark North Qld Pty Ltd ABN : 99 082 98 87 Electrical Contractors License C372 Page 2 of Safe Work Method Statement Title: SWMS:00 USING PORTABLE LADDERS
More informationSAFE WORK METHOD STATEMENT Part 1
SAFE WORK METHOD STATEMENT Part 1 Company Details: Aztech Integrated Systems Pty Ltd ABN: 50 142 740 172 Director : Aaron Caruana +61 418 178 719 7/227A Brisbane Road, Labrador, QLD, 4215. Project Details:
More informationSection J. How to develop safety elements for project safety management system. How to develop safety elements for project SMS
Section J How to develop safety elements for project safety management system 1. Once the project management has developed or adopted a safety policy, it needs to develop safety elements to meet the objectives
More informationSAFE WORK METHOD STATEMENT WORKING IN CONFINED SPACE HSE NET NAT SWMS APAND00030
SAFE WORK METHOD STATEMENT WORKING IN CONFINED SPACE HSE NET NAT SWMS APAND00030 HIGH RISK APT AM Holdings Pty. Ltd. [ABN] 95124754383 Principal Contractor (PC) APA Group Level 19, HSBC Building 580 George
More informationSafe Work Method Statement
Company Name: Safe Work Method Statement Site Address: Other Details: Contractor: Activity/Trade: Electrician Date: TASKS List the tasks required to perform the activity in sequence carried out. Entry
More informationSpecific Safety Legislation/Codes of Practice/Australian Standards applicable to this JSA (Tick those applicable).
OCCUPATIONAL HEALTH & SAFETY MANUAL Section OHS-005, Job Safety Analysis SCORESBY, VIC 3179 GEELONG, VIC 3218 MALAGA, WA 6090 DUDLEY PARK, SA 5008 MANSFIELD, QLD 4122 NORTH ROCKS, NSW, 2641 ACT 2609 LAVINGTON,
More informationSWMS No 009 Samark North Qld Pty Ltd ABN : Electrical Contractors License C37121 Page 2 of 4
Samark North Qld Pty Ltd SWMS Manual SWMS No 009 Samark North Qld Pty Ltd ABN : 99 082 98 87 Electrical Contractors License C72 Page 2 of Safe Work Method Statement Title: SWMS:009 Confined Space Work
More informationTemporary load-bearing support for structural alterations or repairs
CRITICAL NOTE This document only becomes a Safe Work Method Statement where the High Risk Construction Work section of this document is completed Company: ABN: Contact Person: Ph: Project/Site: Principal
More informationSafety Guidelines for Live Entertainment and Events I Part 2. Hazard Identification and Risk Management 1
Safety Guidelines for Live Entertainment and Events Part 2. Hazard Identification and Risk Management Contents Disclaimer... 1 1. Principles of Risk Management... 2 2. The Risk Management Process... 2
More informationSAFE WORK METHOD STATEMENT (SWMS) All Trades Abseiling ABN: Ph:
PCBU: ALL TRADES ABSEILING ABN: 42 137 576 035 PO Box 774 NEWPORT NSW 2106 LIC: 123517C P: 0412 227 578 Principal Contractor (PC): Date SWMS provided to PC: Work activity: Workplace location: High risk
More informationTHE CONTROLLED COPY OF THIS DOCUMENT IS ON THE COMPUTER NETWORK PRINTED COPIES ARE ONLY CURRENT FOR THE DATE AT THE BOTTOM OF THE PAGE.
TE CONTROLLED COPY OF TIS DOCUMENT IS ON TE COMPUTER NETWORK PRINTED COPIES ARE ONLY CURRENT FOR TE DATE AT TE BOTTOM OF TE PAGE. Title Using Angle Grinders SWMS No. 8 Authorized and email Signed by the
More informationHow severely could the risk hurt someone? Low/Insignificant First aid
Safe Work Method Statement No: WMS-0 Task: Operate Diesel Road Saw This WMS is submitted to: Project name and site address: Contact: Preparation of WMS by: Robert Raams Company: Enwon (Australia) Pty Ltd
More informationSAFE WORK METHOD STATEMENT
SAFE WORK METHOD STATEMENT WATER PUMP - PETROL Prepared for Client: Rural Construction & Maintenance Pty Ltd Project No: 1 Site: 660 Great Ocean Road, Bellbrae Date Prepared: 29/07/2015 1. RESPONSIBILITIES
More informationSAFE WORK METHOD STATEMENT CARPENTER
HOST EMPLOYER DECLARATION I declare the worker/s named on this work authority have been provided with a site specific safety induction that complies with the requirements of the Workplace Health & Safety
More informationWork Activity (e.g. Road Work): Work Location:.
Working with Cranes Work Activity (e.g. Road Work): Work Location:. GENERAL INFORMATION Hinchinbrook Shire Council Lannercost Street Ingham Qld, 4850 ABN 46 291 971 168 Ph: 47764610 All personnel conducting
More informationFLYING OBJECTS MANUAL HANDLING EXCESSIVE NOISE
JOB NO: PROJECT: DATE: SWMS NO: SWMS 002 PREPARED BY: Ian Hartley REVISED BY: Nick Bragg & Cameron McNeil ACTIVITY: STUMP REMOVAL SUPERVISED BY: REVISION DATE: April 2016 MINIMUM PERSONAL PROTECTIVE EQUIPMENT
More informationSafe Work Method Statement
TE CONTROLLED COPY OF TIS DOCUMENT IS ON TE COMPUTER NETWORK PRINTED COPIES ARE ONLY CURRENT FOR TE DATE AT TE BOTTOM OF TE PAGE. Title Dogging of Crane General Loading and Unloading SWMS No. 20 Authorized
More informationSAFE WORK METHOD STATEMENT Part 1. Company Details. Company Name: Contact Name, Position and Phone number: Address: Project details.
SAFE WORK METHOD STATEMENT Part 1 Company Details Company Name: ABN: Contact Name, Position and Phone number: Address: Project details Project: Area: Job Address: Job Description: Activity: Installation
More informationWheeler Cranes 6 McIntyre Rd Tomago NSW 2324
Wheeler Cranes 6 McIntyre Rd Tomago NSW 2324 ABN: 34 088 229 190 This SWMS has been developed and authorised by: Name Albie Wheeler Position Managing Director Date 1/7/12 Signature Phone 0249649991 Mobile
More informationAccident/Incident Reporting and Investigation Procedures
Accident/Incident Reporting and Investigation Procedures Policy reference Workplace Health and Safety Policy Procedure reference Workplace Health and Safety Risk Assessment Procedures Procedure It is imperative
More informationSafe Work Method Statement (SWMS)
Safe Work Method Statement (SWMS) Organisation Details : Organisation Name Northern Plumbing Contact ABN 17 15 41 4 Position Director Address 47 Thomas Street Edgeworth 85 Phone Number 0411 10 4 Project
More informationAppendix 4C - Sample SWMS Trenching
Appendix 4C - Sample SWMS Trenching SAFE WORK METHOD STATEMENT SWMS Reference : Insert document number : Version A Date : Workplace / Project : Company Address: Work Activity / Job / Task or Process :
More informationWORK METHOD STATEMENT RENDERING
ORGANISATION DETAILS Organisation Name: Gedoun Constructions Pty Ltd Contact Name: Joe Gedoun ACN/ABN: 52 284 873 581 Contact Position: Director Address: PO Box 1138, Townsville QLD 4810 Contact Phone
More informationAccident /Incident/Injury Report & Investigation Form
Accident /Incident/Injury Report & Investigation Form Incident Details: Location/s of Incident: Address of Incident: Person Involved Details: Person Involved: Witness Name (If Applicable): Time of Incident
More informationWINDMILL (pre-start) HAZARD INSPECTION CHECKLIST
Windmill Hazard Inspection Checklist WINDMILL (pre-start) HAZARD INSPECTION CHECKLIST Authorised by: LOCATION OF INSPECTION...... Inspected By (1)........... (2)..... PRINT PRINT Signature (1):. (2)....
More informationSafe work method statements
Information about Safe work method statements How to prepare and use a safe work method statement (SWMS) for high risk construction work (HRCW) and who needs to prepare one. October 2018 Key concepts Hazard
More informationSAFE WORK METHOD STATEMENT (SWMS)
SAF WORK MTHOD STATMNT (SWMS) Organisation Name: ABN: Address: Project: Activity: SWMS prepared by: Name Signature Date Area: Client: This makes mandatory: Organisation Details Contact Name: Contact Position:
More informationJob Safety and Environmental Analysis (JSEA)/Safe Work Method Statement (SWMS)
Job Safety and Environmental Analysis (JSEA)/Safe Work Method Statement (SWMS) Part 1: Project and Task Identification Process: Initiators of JSEAs are responsible for consulting the Project Supervisor,
More informationSAFE WORK METHOD STATEMENT Part 1 CONCRETE SAWING
SAFE WORK METHOD STATEMENT Part 1 CONCRETE SAWING Personal Protective Equipment Foot Hearing High Visibility Head Eye Face Hand Protective Clothing Breathing Normal Requirements: Safety footwear, hearing
More informationTelco Antennas SWMS Working At Height Above 2m
Telco Antennas SWMS Working At Height Above 2m A SWMS shall be developed for a task where the risk has been assessed as Medium or Higher Division: Date: SWMS No: (e.g. Installation, Engineering Workshop)
More informationB S Glass Ltd Safety procedures- outsourced Workplaces
B S Glass Ltd Jan 17 B S Glass Ltd Safety procedures- outsourced Workplaces Index - - - - - - - - Page No On Site safety - - - - - - - - - - - - - - - - - - - Content 3. 1.00 Health and Safety Mission
More informationSWMS documented by: Feb Bo Ceprnja Date Feb Feb Feb 2018
Contractor Company Details: BUILDSAFE SAFE WORK METHOD STATEMENT 0002 (Void Platform Stairs) Part 1 (To be used in conjunction with SWMS 0001 General Site Activities & SWMS 0002 Void Platform) Additional
More informationProcedure: Work health and safety hazard management
Procedure: Work health and safety hazard management Purpose This procedure describes how the Australian National University (ANU) manages Work Health Safety hazards for the health, safety, rehabilitation
More informationSAFE WORK METHOD STATEMENTS
Recips 11/56 Norcal Road Nunawading Vic. 11 ABN: 48 04 075 70 Contact Person: Dean Spicer Contact Number: 9878 9006 SAFE WORK METHOD STATEMENTS for Format 1 Various Service Clients for Service work and
More informationSAFE WORK METHOD STATEMENT (SWMS) GENERAL GARDENING with Blowers, Hedge Trimmers, Whipper Snippers, Pruners, Spray Units
Job Description/Task/: General Gardening such as using Blowers, Hedge Trimmers, Whipper Snippers, Pruners, Spray Units Name and Phone Number of Person Completing SWMS: Name and Phone Number of the Person
More informationOur commitment to safety
2 Our commitment to safety At South East Water, we have an absolute commitment to achieving and maintaining a safe and healthy workplace for our people, including our contractors and stakeholders which
More informationSAFE WORK METHOD STATEMENT
SAFE WORK METHOD STATEMENT LOADING AND UNLOADING VEHICLES Prepared for Client: Rural Construction & Maintenance Pty Ltd Project No: 1 Site: 660 Great Ocean Road, Bellbrae Date Prepared: 29/07/2015 1. RESPONSIBILITIES
More informationHAZARD MANAGEMENT PROCEDURE
TABLE OF CONTENTS 1. OBJECTIVE... 2 2. SCOPE... 2 3. DEFINITIONS... 2 4. RESPONSIBILITIES... 2 5. HAZARD IDENTIFICATION... 3 5.1 HAZARD AND RISK IDENTIFICATION TOOLS AND METHODS... 3 5.1.1 Take 5 Risk
More informationPLANNED LIGHTING MAINTENANCE LTD METHOD STATEMENT & RISK ASSESSMENT REPLACEMENT OF LAMPS OR REPAIRS TO HIGH LEVEL LIGHT UNITS
PLANNED LIGHTING MAINTENANCE LTD METHOD STATEMENT & RISK ASSESSMENT REPLACEMENT OF LAMPS OR REPAIRS TO HIGH LEVEL LIGHT UNITS Project: (insert Client) Replacement/ Repair of high level light units/ high
More informationCONTRACTOR WHS HAZARD STANDARD HAZARDOUS CHEMICALS EXTERNAL USE ONLY
CONTRACTOR WHS HAZARD STANDARD HAZARDOUS CHEMICALS EXTERNAL USE ONLY Principles in the Optus Contractor WHS management process CONTRACTOR MANAGEMENT STAGES PRINCIPLES THIS STANDARD REQUISITION Requisition
More informationSWMS No 007 Samark North Qld Pty Ltd ABN : Electrical Contractors License C37121 Page 2 of 6
Samark North Qld Pty Ltd SWMS Manual SWMS No 007 Samark North Qld Pty Ltd ABN : 99 082 958 487 Electrical Contractors License C37121 Page 2 of 6 Safe Work Method Statement Title: SWMS:007 WORKING ON ENERGISED
More informationWork Health and Safety Risk Management Procedures
Work Health and Safety Risk Management Procedures Table of Contents 1. Governing Policy 2. Purpose 3. Scope 4. Definitions 5. Responsibilities 6. Risk Management Process 6.1. Process summary 6.2. Hazard
More informationCONSTRUCTION HEALTH AND SAFETY MANAGEMENT SYSTEM BASELINE HIRA
RECOMMENDED ADDITIONAL CONTROLS TASK / ACTIVITY/ EQUIPMENT/ FACILITY HAZARDS UNWANTED EVENT MINIMUM CONTROLS REQUIRED RISK NO. LIKELI-HOOD CONSE-QUENCE RISK VALUE Project Risk Assessment Page 1 of 16 All
More informationHS329 Risk Management Procedure
HS329 Risk Management Procedure Work Health and Safety Act 2011 Policy hierarchy link Work Health and Safety Regulation 2011 Work Health and Safety Policy Code of Practice How to Manage Work Health and
More informationConfined Spaces. This procedure applies to all workers of the Diocese of Maitland Newcastle (DoMN).
Purpose To provide guidance in controlling the risks associated with confined spaces including identifying confined spaces, working in a confined space and issuing confined space entry permits. Scope This
More informationHazard & Risk Management
Hazard & Risk Management Introduction The Church recognises WHS hazards and risks must be appropriate managed to ensure, so far as reasonably practicable, the health and safety of all workers at Church
More informationWheeler Cranes 6 McIntyre Rd Tomago NSW 2324
Wheeler Cranes 6 McIntyre Rd Tomago NSW 2324 ABN: 34 088 229 190 This SWMS has been developed and authorised by: Name Steve Smallman Position Safety & Systems Manager Date 21/6/13 Phone 0249649991 Signature
More informationHazard Management Making your workplace safer
Hazard Management Making your workplace safer A Guide to Hazard Identification, Risk Assessment, Control and Reviewing 1 What is a hazard? A hazard is something which has the potential to harm the health,
More informationSAFE WORK METHOD STATEMENT
SWMS No. 09 SEED COECTION Barung andcare Assoc Inc 38A Coral St, Maleny Qld, 4552 Tel: 07 5494 3151 Email: info@barunglandcare.org.au ABN: 48 562 796 065 VERSION CONTRO Original version Date of this version
More informationHealth & Safety Policy & Plan. Rightway Roofing.
Health & Safety Policy & Plan. Rightway Roofing. Valid: 02/2012-02/2013 Contents ( 1 ) Policy Statement. ( 2 ) Hazard Identification. ( 3 ) Hazard Management. ( 4 ) Induction & Training. ( 5 ) Monitoring
More informationTo comply with the OHS Act, the responsible manager must carry out and document the following:
Owner: Manager Health, Wellbeing and Safety Last Update: 10 January 2018 Contents 1. Purpose... 1 2. Minimum Compliance Requirements... 1 3. Definitions... 2 4. Legislative requirements under the OHS Act
More informationUniversity of Vermont Department of Physical Plant Personal Protective Equipment Program
University of Vermont Department of Physical Plant Personal Protective Equipment Program REVISED AND DISTRIBUTED BY: THE UNIVERSITY OF VERMONT DEPARTMENT OF PHYSICAL PLANT TRAINING AND COMPLIANCE OFFICE
More informationConducting An Effective. Welcome!
Conducting An Effective An introduction to the Five Step Process of Job Hazard Analysis JHA-JSA-SWMS-AHA Introductions Welcome! What do you know about Job Hazard Analysis (JHA s)? Does OSHA require JHA
More informationSAFETY MANAGEMENT SYSTEM
Equipment Location: Hazard Hired From All Master Hire Stores Entanglement Can anyone s hair, clothing, gloves, necktie, jewellery, cleaning brushes, rags or other materials become entangled with moving
More informationOccupational Health Safety and Welfare. Our Policy
Occupational Health Safety and Welfare Our Policy OCUPATIONAL HEALTH AND SAFETY POLICY Management of QI Electrical Services is committed to ensuring, as far as responsibly practicable, that all employees
More informationPre-control risk estimate. Likelihood Risk
Activity Consequence s mitigation measures Site Access & Egress Slips, trips & falls al injury by falling. Sprains & broken bones. Site operatives 3 4 12 Ensure access to site is kept clear of plant &
More informationInstructions for the Use of the Excel Spreadsheet. There are Three tabs at the bottom of this worksheet. Instructions tab is the one you are reading
Instructions for the Use of the Excel Spreadsheet There are Three tabs at the bottom of this worksheet Instructions tab is the one you are reading H&S Plan Tab The Plan Tab is the front cover pages of
More informationPART 4: IMPLEMENTATION & OP
TITLE PART 4: IMPLEMENTATION & OPERATION Prepared by: 4.2 Personal Protective Equipment (PPE) Learning Objectives To define what is Personal Protective Equipment (PPE). To describe the management & legal
More informationWHS PROCEDURE P Confined Spaces. Approved by: Ruth Hampton Review Date: 6 th December 2015
5 WHS PROCEDURE P21-01 Page 1 of 7 Issue: 2 1. Intent The Salvation Army Australia Eastern Territory (TSA-AUE) is committed to the provision of a safe, healthy and injury free environment for all persons
More information1. SHEWMS DETAILS. Project No. Valid From
Name of Project Name / Description of Work Activity being undertaken Location at which Activity is being undertaken Name of SHEWMS Owner (Contractor) SHEWMS Owner Business Address Name of person who prepared
More informationSAFE WORK METHOD STATEMENT 0005 (Hang-On Platform) Part 1 (To be used in conjunction with SWMS 0001 General Site Activities)
Contractor Company Details: BUILDSAFE SAFE WORK METHOD STATEMENT 0005 (Hang-On Platform) Part 1 (To be used in conjunction with SWMS 0001 General Site Activities) Additional Information (if required):
More informationSite-Specific Safety Plan
Site-Specific Safety Plan All the documents you need can be accessed through the menu below. Click on the icon to go to the section that applies to you. Once in the section you can easily click the back
More informationEVENT SAFETY RISK ASSESSMENT - (SMALL TO MEDIUM SIZED COMMUNITY EVENTS) 1
EVENT SAFETY RISK ASSESSMENT (SMALL TO MEDIUM SIZED COMMUNITY EVENTS) EVENT SAFETY MANAGEMENT INFORMATION SHEET September 2010 #3 RISK ASSESSMENT IT S A MUST The success of your event is measured in many
More informationCONTRACTOR SAFETY INDUCTION HANDBOOK
CONTRACTOR SAFETY INDUCTION HANDBOOK As a valued contractor for Total Group we would ask that you read and carefully consider the details included in this document. Total Group carry out work for a number
More information1. Silica Identifying and managing crystalline silica dust exposure
1. Silica Identifying and managing crystalline silica dust exposure This information guide provides brief guidance on the legislative requirements for identifying and managing respirable crystalline silica
More informationPRO Lifting Operations
MS&L Procedure PRO-4.5-0001-1-06 Lifting Operations Document Owner: Bill Kruesi HSSE Manager - Asset Mgmt. Owen Quake ANZ Engineering Authority Approved By: Bill Kruesi HSSE Manager - Asset Mgmt. Control
More informationMETHODOLOGY RISK TABLES TABLE 1 - QUALITATIVE MEASURES OF CONSEQUENCE OR IMPACT TABLE 2 - QUALITATIVE MEASURES OF LIKELIHOOD
METHODOLOGY This Assessment has been performed as outlined in Australian Standard AS/NZS ISO 31000:2009 with reference to tables 1, 2 and 3 below, for the use of leased land for the purposes of performing
More informationUniversity College Dublin Machinery/Equipment Risk Assessment Template
1. General Information Name of Person(s) carrying out assessment and their position Principal Investigator / Supervisor / Head of School or Unit (Person responsible for ensuring safety) Date of assessment
More informationSafety is a priority at Vault Pipelines.
Safety is a priority at Vault Pipelines. At Vault Pipelines we believe that every incident is preventable and that every task can be completed safely and efficiently. We will achieve this through our cultural
More informationQUEENSLAND UNIVERSITY OF TECHNOLOGY
QUEENSLAND UNIVERSITY OF TECHNOLOGY SITE SPECIFIC SAFETY MANAGEMENT PLAN FOR SAMFORD HOUSE SAMFORD ECOLOGICAL RESEARCH FACILITY SAMFORD VALLEY 2007 Dylan Randall SN: 06305466 dylan.randall@student.qut.edu.au
More informationSOP. Working in Confined Spaces
Purpose This procedure outlines the requirements for the management of entry into confined spaces in all work areas with the intention of minimising risks to health and safety from any potential hazards
More informationPLANT RISK ASSESSMENT REPORT
PLANT RISK ASSESSMENT REPORT SECTION 1: PLANT IDENTIFICATION Report Number: 407/752 Assessment Date: 5 th May 2015 Company: Wacker Neuson Plant Type: Telescopic Light Balloon Make: Wacker Neuson Model:
More information