1 Sensor Platform Project Marine Trials Bidders Conference Fundy Ocean Research Center for Energy fundyforce.ca 1
2 Project Team FORCE OceanWorks International Preliminary Design, Operational Procedures Murray Scotney, OceanMoor Technical Svcs Operational Procedures Mike Wilson, PICC Cable Engineering 2
3 Agenda The Project (15 min) Scope, progress, preliminary design, cable The Site (15 min) CLA, seabed topography, currents, data The Trials (15 min) RFP requirements, recovery, redeployment Q and A - (1hr) 3
4 Objectives: 1. To enhance confidence that we understand the site and the effects of turbines on the environment. 2. Develop Canadian expertise in tidal site characterization 3. Develop the infrastructure, equipment and techniques to reliably: A. Characterize and monitor high flow sites B. Assess the interaction of turbines on its surroundings 4
5 Infrastructure: A recoverable platform - A cabled node - Removable instrument bay - Serviced by moored surface vessel 2 to 3 times a year 5
6 Project Plan: Today Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Phase 1: Definition Phase 2: Preliminary Design and Trials Phase 3: Design/Build Marine Trials Phase 4: Integration Data Cable Install Phase 5: Install
7 Status: Preliminary Design Phase 2 Risk Studies: Operations Assessed highest risk Stability Data Cable Float Release Mechanism 7
8 Next Steps: Operational Trials Marine Trials: Retire risks associated with operations to the greatest extent possible Demonstrate: Mooring Recovery ROV demonstration? 8
9 Next Steps: Cable Deployment Install Data Cable: also serve as deployment test cable for medium voltage cables 9
10 FORCE Crown Lease Area One of the most powerful in the world 7000 MW in Minas Passage 2500 MW estimated safely extractable straight flowing currents, speeds over 5 m/s pushing 14 billion tonnes of water on avg. 10
11 FORCE Test Area 11
12 12
13 Berth Site ADCP Data Collection 14
14 Site D ADCP Data September 2011 Current Direction Spring Tide Ebb Ebb Neap Tide Operations Window 15
15 Slack Water at FORCE Courtesy of Dr. Richard Karsten and Dr. Joel Culina Acadia Tidal Energy Institute 16
16 Site D ADCP Data September 2011 Current Direction Spring Neap Spring Neap 17
17 18
18 Relevant Information Environmental Assessment Report including all appendices and 2010 addendum ADCP Data Sets and Summary Reports 400kHz and 600kHz high F sampling Sonar Surveys 2m and.4m multibeam.025m side scan Meteorological Report Seabed photos and video 19
19 Marine Services RFP: Conduct sea trials to verify deployment concepts. Components: Part 1: Engineering Study Part 2: Sheltered Harbour Trial Part 3: Minas Passage Trial
20 Part 1: Engineering Study A detailed mooring plan backed up with an engineering analysis Identify deck equipment and mooring arrangement Describe the process to control the mooring lines and position the vessel ( geometry described in App 3) The engineering study will validate assumptions in anchor size Installation and recovery plan for the moorings FORCE will validate the analysis conducted via 3 rd party engineering consultant 21
21 Part 2: Sheltered Harbour Trials Test Float Recovery Device Refine recovery/deployment procedures Evaluate deck layout Validate positioning of the vessel on mooring Training Conduct near home port (mutually agreed location) Assets should test actual equipment to be used (mooring may be scaled back) Data cable to be simulated with 1.25 wire rope and DMA 22
22 Part 3: Minas Passage Trials Trial will be conducted at neap tides.for safety mooring should be able to hold through 10 knts. Recovery will be done around slack water. Assess performance of float release in high flow. Float submergence is critical factor. Validate mooring plan and test positioning control in high flow Evaluate marine asset performance Validate recovery/deployment procedures in high flow Training Data cable to be simulated with wire rope and DMA 23
23 RFP Schedule 10 Apr: Bidders Conference 26 April: RFP submission deadline 06 May: Begin shortlisted candidates presentations 10 May: Notification of successful contractor 31 May: Contract Award Summer: Sheltered Harbour + Minas Passage Trials Contract to be awarded in phases based on performance and results on each phase. 24
24 Safety and Risk Management Contractors Safety System will be provided to FORCE for review 15 days after initial contract award Inspection of certifications and vessel surveys will be conducted prior to Part 2 and Part 3 FORCE will develop node recovery procedures Contractor will develop transit plan and mooring procedure Joint risk review process Part 2 and Part 3 Risk management plan developed for each phase 25
25 The Sensor Platform -The FORCE Science Node will be replaced by a Sea Trial Node Base for the marine trials. -The two nodes are physically the same 4.1 m Physical Specifications Summary 4.5 m x 4.1 m x 1.0 m Weight in air 10 tonnes Weight in water 8.7 tonnes 4.5 m 26 1 m
26 Tension Control - Recovery must be accomplished with this cable attached. - Tension force on this cable is not to exceed 4500 Kg. - For the trials a wire rope will be used to simulate the data cable. 27
27 Node Recovery Procedure - When ready for recovery, the Node will release a float that pulls a 60m messenger line to the surface. - The messenger line is attached to the main lift line that is attached to the main lift point of the Node. - It is left to the contractor decide how best to safely retrieve the buoy and lift line and to recover the node to the ship deck for servicing. 28
28 Float Release Mechanism - The lift line for the Node is contained within the Node itself in the Float Release Assembly. Main lift points 29
29 Float Release Mechanism - The Float Release Assembly contains the lift line, float, and release mechanisms. Acoustic Release Lift Line and drum Float Main Lift Points Solenoid Release 30
30 Stage 1: Initial Positioning and Lift Line Recovery - When ready for recovery, the float can be released from a shore station signal or if that fails, by an acoustic release activated from the vessel. - The Watch Area diagram is overlaid here for reference. 31
31 Stage 2: Recovering the Node - The vessel must be able to be repositioned in order to not exceed the maximum allowable tension force on the cable. Lift line lead angle will be key indicator. - Cable tensions max : 4500kg ideally b/t kgs. 32
32 Stage 3: Node on Deck - Once on board, proper cable tension must be maintained. Ideally redeployed in same tidal cycle. However, trials will validate ability to maintain tension over multiple tidal cycles. Tension monitor will be applied. - Node will also be secured. 33
33 Servicing the Sensor Platform - NOT REQUIRED FOR SEA TRIALS - The Instrument Node is replaced with abandonment pod and will require a crane in order to lift them in and out. A crane will be required to swap out the instrument pods. 34
34 Redeployment - The recovered lift line can be used to launch the serviced Node once it is ready and an acoustic release is attached. - Deployment requires the proper SDC tension to be maintained. - The vessel will have to be repositioned as the Node is deployed in order to maintain the proper tension. 35
35 Redeployment - Any deck tie downs removed prior to luffing overboard. - Vessel to reposition as node deployed to seabed - All procedures and personnel to adhere to marine and safety best practices. 36
MEASUREMENT OF LONG-TERM AMBIENT NOISE AND TIDAL TURBINE LEVELS IN THE BAY OF FUNDY
MEASUREMENT OF LONG-TERM AMBIENT NOISE AND TIDAL TURBINE LEVELS IN THE BAY OF FUNDY 11 th European Conference on Underwater Acoustics, 3 July 2012 Bruce Martin 1, Andrew Gerber 2, Christopher Whitt 1,
More informationOcean Observatories Initiative (OOI) Moorings: New Capabilities for Seagoing Science
Ocean Observatories Initiative Ocean Observatories Initiative (OOI) Moorings: New Capabilities for Seagoing Science presented by Ed Dever and Walt Waldorf November 20, 2014 OOI Science Themes Coastal and
More informationChapter 9: Sea operations
Chapter 9: Sea operations ANTARES takes advice from IFREMER for the sea operations, which concern the installation and recovery of the different components of the detector : Junction Box, Strings, Interconnecting
More informationRAMSTM. 360 Riser and Anchor-Chain Integrity Monitoring for FPSOs
RAMS 360 Riser and Anchor-Chain Integrity Monitoring for FPSOs Introduction to RAMS Tritech s RAMS is a 360 anchor-chain and riser integrity monitoring system for Floating Production Storage and Offloading
More informationBACKGROUND TO STUDY CASE
BACKGROUND TO STUDY CASE German Aerospace Center (DLR) is using Andøya Rocket Range for a sounding rocket campaign. On 27th October 2005 a 300 kg payload (SHEFEX) was launched Due do a technical problems
More informationDelivery and Deployment of the U.S. Navy s Submarine Rescue System
Delivery and Deployment of the U.S. Navy s Submarine Rescue System Andrew DeSpirito Advanced Undersea Systems Program Office (PMS394) Naval Sea Systems Command Agenda Submarine Rescue Diving and Recompression
More informationLocation: Barkley Canyon Date: September 9, 2013 Constraints: none
Page 1 of 11 DIVE PLAN R1650 Location: Barkley Canyon Date: September 9, 2013 Constraints: none Objectives Deploy POD 1 autonomous CTD Survey POD 3 for sediment enrichment sites; deposit cages; collect
More informationLESSONS LEARNED. Marine Operations Minas Passage
LESSONS LEARNED Marine Operations Minas Passage Contents How to Use This Report Introduction Acronyms and Abbreviations Types of Vessels Dive Operations Equipment Challenges Environmental limitations Fundy
More informationPolar Research Vessel Operational Requirements and Summary of Technical Studies
Polar Research Vessel Operational Requirements and Summary of Technical Studies Presentation to UNOLS by Jim St John Science and Technology Corporation - Polar Technology Office Why a New Antarctic Research
More informationLearn more at
STRIDE JIP Phase III SUT Talk 15th November 2 Offshore VIV monitoring (vortex induced vibration) Catenary riser interaction with deepwater seabeds 3 Full Scale Riser Monitoring To get real measurements
More informationSeaSmart. Jonathan Evans
SeaSmart A new approach for rapid, on-site resource assessment at potential tidal stream energy array sites using MAS Marine Solutions for the Deep Data World Jonathan Evans Presentation Outline Marine
More informationModelling and Assessment of Marine Renewable Energy Resources. Andrew Cornett Canadian Hydraulics Centre National Research Council Canada May 2008
Modelling and Assessment of Marine Renewable Energy Resources Andrew Cornett Canadian Hydraulics Centre National Research Council Canada May 2008 Background Pan-Canadian resource inventory in 2005/06 Canada
More informationMulti-Purpose Workboats and Vessels. Marine Engineering and Construction. Salvage and Wreck Removal. Marine Consultancy Services
Multi-Purpose Workboats and Vessels Marine Engineering and Construction Salvage and Wreck Removal Marine Consultancy Services Marine Expertise and Support We are a progressive company with more than 50
More informationSea Views SEACAMS. month s edition. In this. Business aboard the RV Prince Madog What do seals do underwater? All aboard the RV Prince Madog
February 2013 SEACAMS Sea Views In this month s edition Business aboard the RV Prince Madog What do seals do underwater? All aboard the RV Prince Madog 0845 519 9029 www.seacams.ac.uk ebost: email: info@seacams.ac.uk
More informationOcean Observatories Initiative Cabled Array Observatory Extension Cables/Connectors
Ocean Observatories Initiative Cabled Array Observatory Extension Cables/Connectors Mike Harrington mikeh@apl.washington.edu Infrastructure Cable Laying Problem: Get to the interesting stuff. Laying interconnection
More informationStevpris installation
chaser Stevpris deployment for MODUs Introduction Typical methods for deployment and retrieval of Stevpris anchors with an anchor handling vessel (AHV) are described, focusing on the use of chasers for
More informationTRIAXYS Acoustic Doppler Current Profiler Comparison Study
TRIAXYS Acoustic Doppler Current Profiler Comparison Study By Randolph Kashino, Axys Technologies Inc. Tony Ethier, Axys Technologies Inc. Reo Phillips, Axys Technologies Inc. February 2 Figure 1. Nortek
More informationAppendix 5: Currents in Minas Basin. (Oceans Ltd. 2009)
Appendix 5: Currents in Minas Basin (Oceans Ltd. 29) Current in Minas Basin May 1, 28 March 29, 29 Submitted To: Minas Basin Pulp and Power P.O. Box 41 53 Prince Street Hansport, NS, BP 1P by 22, Purdy
More informationRV Southern Surveyor program
2011 RV Southern Surveyor program voyageplan SS2011_c01 Tsunami Detection Buoy Maintenance for Australian Tsunami Warning System (ATWS) Itinerary Mobilise 0700 Sydney, Tuesday 5 April 2011 Depart Sydney
More informationMooring Modifications for the Reduction of Losses to Vandalism
Mooring Modifications for the Reduction of Losses to Vandalism H. Paul Freitag Chris Meinig Andrew J. Shepherd Pacific Marine Environmental Laboratory Seattle, Washington, USA Linda D. Stratton JISAO/University
More informationIsis Deployment. TMS and Live Boating. Inmartech08. Dave Turner Operations Co-ordinator.
Isis Deployment TMS and Live Boating Inmartech08 Dave Turner Operations Co-ordinator TMS Operations Why Why do do we we have have aa TMS? TMS? ItIt was was deemed deemed an an essential essential part
More informationRR10106 Cruise Plan ITOP Mooring Recovery and PhilSea10 Seaglider Operation (R/V Revelle November 6-26, 2010)
RR10106 Cruise Plan ITOP Mooring Recovery and PhilSea10 Seaglider Operation (R/V Revelle November 6-26, 2010) Chief Scientist: Ren-Chieh Lien, Applied Physics Lab, University of Washington Co-Chief Scientist:
More informationHYDROGRAPHIC AND SITE SURVEY REPORT
HYDROGRAPHIC AND SITE SURVEY REPORT Proposed Pen Site at Dounie, Sound of Jura Prepared for: Kames Fish Farming Ltd Kilmelford Argyll PA34 4XA Tel: +44 (0)1631 720699 TransTech Limited www.transtechltd.com
More informationUS Navy Wave Energy Test Site. Kaneohe, HI
US Navy Wave Energy Test Site Kaneohe, HI Presented by: Luis A. Vega Ph.D., HNEI, University of Hawaii September 24, 2014 MHK Testing in Hawaii (excluding OTEC) What do you do to support/facilitate testing?
More informationUsing AUVs in Under-Ice Scientific Missions
Using AUVs in Under-Ice Scientific Missions James Ferguson, International Submarine Engineering Ltd. Presented at Arctic Change 08 11 Decenber 2008- Quebec City, Canada 1/16 ISE s s Experience in Arctic
More informationRVSS Appendix A Overview
RVSS Appendix A Overview Presented at RVTEC 2008 by Rich Findley rfindley@rsmas.miami.edu Definitions WINCH OWNER: The party or their representative who is normally responsible for the operation, inspection,
More informationOcean Observatories Initiative. Coastal & Global Scale Nodes. Hydrogen Safety. OOI Surface Mooring Hydrogen Safety Review
Ocean Observatories Initiative Coastal & Global Scale Nodes Hydrogen Safety CP01 Mooring Timeline: 21 November 2013: CP01CNSM was deployed and transitioned to shore controlled operations. 17 Feb. 2014:
More informationAppendix 11-B Anchor Handling Systems, Set Up and Handling
Revision History Revision Date Section Changes Number 1 Sept 1 Permanent Chaser Pendant (PCP) Drawing updated 2018 2 Pennant Buoy System Drawing updated 3 Working Wire/Chaser Termination on Drawing updated
More informationRISK ASSESSMENT -HEATS-
Honda RYA Youth RIB Championship 2018 RISK ASSESSMENT -HEATS- Issued by Royal Yachting Association October 2017 Page 1 of 12 Risk Assessment Event Summary Event Honda RYA Youth RIB Championship Organising
More informationCathodic Protection Retrofit Options Comparison of Current Distribution
Cathodic Protection Retrofit Options Comparison of Current Distribution 1.0 Introduction There are three basic methods available for the deployment of anode systems when considering an offshore cathodic
More informationThis guidance is based on the Risk Assessment approved by the Management Committee under the Club s Health & Safety Policy.
Guidance on Safe Use of Dalgety Bay Sailing Club Raft This guidance is based on the Risk Assessment approved by the Management Committee under the Club s Health & Safety Policy. Where any items referred
More informationUTEC Survey Pipeline Inspection Using Low Logistic AUV June 2016
SUCCESS YOU CAN MEASURE UTEC Survey Pipeline Inspection Using Low Logistic AUV June 2016 Chris Erni Product Line Manager E T H I C S P E R F O R M A N C E E X C E L L E N C E P E O P L E GLOBAL FOOTPRINT
More informationREVISED SILT CURTAIN DEPLOYMENT PLAN
Contract No.: HY/2009/11 Central Wanchai Bypass, North Point Reclamation REVISED SILT CURTAIN DEPLOYMENT PLAN Name Prepared by: China Harbour Engineering Co., Ltd. China Road and Bridge Corporation Joint
More informationDear Captain, Anchor lowering procedure all berths. Page 3: Mooring procedure Parker Point 2 and 4. Page 4: Mooring procedure Parker Point 3 and 5.
Dear Captain, Safety of all personnel involved in the mooring of ships is a priority for our company. To assist us in a safe and incident free mooring operation please review the following mooring procedures
More informationSaab Seaeye Cougar XT Compact
The Seaeye Cougar-XT Compact is a highly flexible and extremely powerful electric ROV with working depths of 300 metres. This system comes with almost all of the specifications of the very reliable Couger-XT
More informationManaging Dynamic Positioning (DP) Operations
Managing Dynamic Positioning (DP) Operations Captain Andy Goldsmith, IMCA Technical Adviser IOSH Offshore Conference Tools for the trade 19 October 2017 1 2 IMCA OPERATIONAL STRUCTURE BOARD CEO SECRETARIAT
More informationLarge-scale Field Test
Vaskinn 1 Large-scale Field Test Kjetil Arne Vaskinn kav@trh.statkraftgroner.no Statkraft Grøner AS SUMMARY The objective the controlled failure of large-scale embankment is to monitor and record the failure
More informationIMCA Competence Assessment Portfolio June 2013
IMCA Competence Portfolio June 2013 Name: Start Date in Current Self- Checklist Entry Level Criteria Acceptance Criteria Attained Certification 500 GRT or more: Valid certificate of competency or certificate
More informationSummary of Architecture Parallel Session. G. Hallewell/CPP Marseille P. Piattelli/ LNS Catania
Summary of Architecture Parallel Session G. Hallewell/CPP Marseille P. Piattelli/ LNS Catania Parallel Session A1.2: Architecture: First session mainly devoted to undersea connectivity Chair: G. HALLEWELL,
More informationFully Submersible Heavy Lift Vessel
Fully Submersible Heavy Lift Vessel Arnbjorn Joensen Aberdeen Maritime Branch (28th January 2015) PRESENTATION Introduction to the Subsea Deployment Vessel Installation method Tank test video Potential
More informationOffshore Wind Energy Stringent quality assurance and quality control. Coastal and Freshwater Fast responding and flexible organisation
Services Oceanographic and Positioning Equipment Rental Meteorological and Oceanographic Surveys Data Analysis and Characterisation Marine Energy Resource Assessment Real-Time Monitoring Founded in 2010,
More informationIMCA Competence Assessment Portfolio June 2013
IMCA Competence Portfolio June 2013 Name: Start Date in Current Self- Checklist Entry Level Criteria Acceptance Criteria Attained Certification 500 GRT or more: Valid certificate of competency or certificate
More informationA FINAL REPORT BY PARTRAC LIMITED: MAY 2006
A FINAL REPORT BY PARTRAC LIMITED: MAY 26 Measurement of Suspended Sediment Concentration & Tidal Current During Dredging Operations and Post-Dredge at the Offshore Disposal Area, Poole, Dorset QUALITY
More information11 Anchor Handling & MOU Moving 11-2
Contents 11 Anchor Handling & MOU Moving 11-2 11.1 Introduction... 11-2 11.1.1 Definitions and Abbreviations... 11-2 11.2 Jointly Agreed Procedures and Responsibilities... 11-3 11.2.1 Operating Company...
More informationNSF's Ocean Observatories Initiative: Building Research Infrastructure for the Pacific Northwest and the Broader Community
Agenda Item B.3.b Supplemental OOI PowerPoint April 2013 Ocean Observatories Initiative NSF's Ocean Observatories Initiative: Building Research Infrastructure for the Pacific Northwest and the Broader
More informationThe Next Generation Easy-to-Deploy (ETD) Tsunami Assessment Buoy
The Next Generation Easy-to-Deploy (ETD) Tsunami Assessment Buoy R.A. Lawson and D. Graham Science Applications International Corporation 4025 Hancock Street San Diego, CA 92110 USA S. Stalin, C. Meinig,
More informationNorway s solution: Hywind- world s first full scale floating turbine Dr. Nenad Keseric Asset Manager/Specialist Statoil ASA MPR RE Operations
Norway s solution: Hywind- world s first full scale floating turbine Dr. Nenad Keseric Asset Manager/Specialist Statoil ASA MPR RE Operations Strategy and Support Leveraging Statoil s offshore oil and
More informationTARPON A Minimal Facilities Platform
TARPON A Minimal Facilities Platform Contents Introduction TARPON Description TARPON Features TARPON Benefits TARPON Proofs TARPON Typical Installation Options Design Codes & Certification Novel Application
More informationAasta Hansteen. Operational Experiences. FFU Seminar 28 th January Tom-Erik Henriksen
Aasta Hansteen Operational Experiences FFU Seminar 28 th January 2016 Tom-Erik Henriksen Agenda Introduction to Aasta Hansteen Main Challenges & Risks Operational Experiences - 2015 Campaigns 2 seabed-to-surface
More informationR E V I S E D D A T E 0 4 /
R E V I S E D D A T E 0 4 / 2 0 0 9 Guidelines Growing Oysters with the OysterGro System (OGS) Congratulations, you have just invested in one of the most efficient oyster growing system there is, the OysterGro.
More informationInnovative and Robust Design. With Full Extension of Offshore Engineering and Design Experiences.
Innovative and Robust Design by VL Offshore With Full Extension of Offshore Engineering and Design Experiences www.vloffshore.com Y Wind Semi Designed by VL Offshore The Y Wind Semi platform (foundation)
More informationORE Open Research Exeter
ORE Open Research Exeter TITLE Performance assessment of a novel active mooring system for load reduction in marine energy converters AUTHORS Luxmoore, J; Grey, S; Newsam, D; et al. DEPOSITED IN ORE 21
More informationNWEI. Fred.Olsen. Columbia Power
U.S. Marine Corps Base Hawaii, Kaneohe 30m, 60m, 80m berths in place, grid-connected First device deployed, second Jan 2016, third Sep 2016 HNEI role Funded by DOE, US Navy, ONR, State of Hawaii Acoustic,
More informationMEASUREMENT COMMUNICATION INSIGHT
Temperature & Depth MEASUREMENT COMMUNICATION INSIGHT CONTENTS Introduction to Aquatec Measuring Temperature and Depth 2 3 Aquatec s Temperature and Depth Loggers AQUAlogger 520 AQUAlogger 530 AQUAlogger
More informationROV Development ROV Function. ROV Crew Navigation IRATECH SUB SYSTEMS 2010
IR AT EC H SU B SY ST EM S 20 10 Remotely Operated Vehicle ROV INTRODUCTORY 2008 2008 1 KEY POINTS ROV Introductory ROV Development ROV Function Types of ROV ROV Crew Navigation ROV Components 2 ROV Development
More informationPORT TALBOT BULK TERMINAL MOORING OPERATIONS MANUAL
PORT TALBOT BULK TERMINAL MOORING OPERATIONS MANUAL ABP Marine Operations & Tata Burdening Departments 2017 RESPONSIBILLITIES Tata Steel UK (TSUK) is the operator of the Port Talbot Harbour Bulk Terminal.
More information(a) Calculate the speed of the sphere as it passes through the lowest point of its path.
1991 Q33 A sphere of mass 3 kg on the end of a wire is released from rest and swings through a vertical distance of 0.4 m. (Neglect air friction.) (a) Calculate the speed of the sphere as it passes through
More informationUpdate on Canadian Research Vessels Ship Procurement Projects
Update on Canadian Research Vessels Ship Procurement Projects 28 th International Research Ship Operators Meeting (IRSO) La Jolla, California October 2012 Jennifer Vollrath 1 Outline National Ship Building
More informationCruise Plan for QPE (R/V Revelle Sept/ 12-16, 2009)
Cruise Plan for QPE (R/V Revelle Sept/ 12-16, 2009) Objectives In this cruise we will recover six subsurface ADCP/TC moorings (Lien), five restrained ADCP (Centurioni), and perform shipboard ADCP, Revelle
More informationWave Hub Update All Energy 21/22 May Stuart Herbert Commercial Director
Wave Hub Update All Energy 21/22 May 2014 Stuart Herbert Commercial Director Deployment Site EMEC, Orkney NaREC/EMEC Refined Prototype Testing Market penetration NaREC, Northumberland Market entry with
More information1 Module A (uniform topography) survey lines Module B (topographic wake) survey lines Module C (submesoscale soup) survey lines...
..................................................................................... point Sal Coastal circulation Experiment (SCoNE) / SP1723 CRUISE PLAN ANDRÉ PALÓCZY R/V Robert Gordon Sproul, September/10
More informationPreventing Damage to Harbour Facilities and. Ship Handling in Harbours PART 2 INDEX
Preventing Damage to Harbour Facilities and Ship Handling in Harbours PART 2 INDEX 1 Vessel handling is based on the basic knowledge that a vessel floats in the water and returns to its original position
More informationGeo-Vibro Corer
High Frequency Vibro Coring System Operational Features Proven performance & high quality cores 30 kn impulse at 30 Hz for fast penetration Reliable, lightweight & cost effective Modular construction (cores
More informationKetchikan Harbors Thomas Basin and Bar Point Harbor
Ketchikan Harbors Thomas Basin and Bar Point Harbor Condition of Improvements 30 December 2014 Thomas Basin & Bar Point Harbors Ketchikan, Alaska (CWIS No. 000631 & 087071) Authorization (1) Rivers and
More informationCB-40 Data Buoy Quick Start Guide
CB-40 Data Buoy Quick Start Guide The NexSens CB-40 Data Buoy offers a compact and affordable platform for deploying water quality sondes and other instruments that integrate power and data logging. The
More informationProducts and Services HR3D, AUV3D
Products and Services HR3D, AUV3D Multi-streamer Short Offset High Resolution 3D Seismic Acquisition Peter Sack Tor Haugland Sound Oceanics, LLC Houston, Texas USA 15 March 2012 Background Petromar V West
More informationUSCG Development Proposal: Heavy Oil Tracking Tactics, Techniques and Procedures Presented to: Ms. Brenda M. Burke (RDC)
USCG Development Proposal: Heavy Oil Tracking Tactics, Techniques and Procedures Presented to: Ms. Brenda M. Burke (RDC) BAA Number: HSCG32-07-R-R00013 Title of Proposal: Heavy Oil Tracking Tactics, Techniques
More informationSuction anchor foundations for tension and taut leg floaters in deep waters. Tension Leg Platform. Taut Leg Platform. upper chain. risers.
Case history: Soil investigation for offshore suction anchors anchor foundations for tension and taut leg floaters in deep waters Alternative anchors for floating structures pile Over last 5 - years anchoring
More informationvoyageplan SS Itinerary Principal Investigator(s) RV Southern Surveyor program
2008 RV Southern Surveyor program voyageplan SS04-2008 RESEARCH CHARTER Deep-Ocean Tsunami Detection Buoy (DART) Scheduled Maintenance Replacement for the Australian Tsunami Warning System (ATWS) Itinerary
More informationFocus on Operational Efficiency and Crew Safety - Introducing Advanced ROV Technology in Marine Towed Streamer Seismic
Focus on Operational Efficiency and Crew Safety - Introducing Advanced ROV Technology in Marine Towed Streamer Seismic R. Tonnessen* (Petroleum Geo-Services) & T. Skadberg (Petroleum Geo- Services) SUMMARY
More informationThe Wave Glider: A Mobile Buoy Concept for Ocean Science. 009 Liquid Robotics Inc.
The Wave Glider: A Mobile Buoy Concept for Ocean Science 009 Liquid Robotics Inc. J. Manley & T. Richardson: Liquid Robotics Inc. DBCP XXV Paris September 28, 2009 1 Wave Glider Overview Unique Two Part
More informationOriginal URI Scanfish MKII
Scanfish MKII URI s Scanfish MKII Sensors include CTD, Fluorometer, Dissolved Oxygen and Seabird Fast Temperature and Conductivity Sensors logging at 400 Hz and sending 50 Hz data via 9600 Baud uplink
More informationNoise Experiment #2. Marine Physical Laboratory Scripps Institution of Oceanography La Jolla, CA February 22 February 2010
Noise Experiment #2 Marine Physical Laboratory Scripps Institution of Oceanography La Jolla, CA 92093-0701 16 February 22 February 2010 1. Objective The objective of the noise experiment is to observe
More informationBreak in the Bahamas. Cutters Head to the Caribbean to Wire Saw Sunken Pier. A 25-foot by 25-foot steel pier section had sunk into the water.
Break in the Bahamas Cutters Head to the Caribbean to Wire Saw Sunken Pier A 25-foot by 25-foot steel pier section had sunk into the water. CONCRETE CASES Divers were used to inspect the damaged structure
More informationCargo and hull damage while at anchor in heavy weather
October 2017 Cargo and hull damage while at anchor in heavy weather A small general cargo vessel loaded steel cargo at several different ports. At the first port the vessel loaded steel plates and at the
More information[***] = both land and marine [***] = Marine only [***] = Land only + ([***] = Shallow Water) if needed
Stand-By conditions: [***] = both land and marine (Terms may require capitalisation or substitution subject to terminology used in the relevant contract) The below Stand-By conditions list is non-exhaustive
More informationACCESS the BLUE ECONOMY ALL OCEANS Engineering Ltd
Subsea Expo 2018 ROV Conference 07.02.2018 ACCESS the BLUE ECONOMY The BLUE ECONOMY - DEFINITION The Blue Economy is a book by Gunter Pauli publish in 2010 based on the idea that he developed in 2004 In
More informationANY OTHER BUSINESS. Guidelines for passenger ship tender operator. Submitted by Cruise Lines International Association (CLIA) SUMMARY
E SUB-COMMITTEE ON STANDARDS OF TRAINING AND WATCHKEEPING 42nd session Agenda item 3 STW 42/13/2 25 October 2010 Original: ENGLISH ANY OTHER BUSINESS Guidelines for passenger ship tender operator Submitted
More informationMSC Guidelines for the Review of Oil Spill Response Vessels (OSRV), Lightship and Stability
R. J. LECHNER, CDR, Chief, Tank Vessel and Offshore Division Purpose This Plan Review Guidance (PRG) explains the requirements for seeking plan approval for stability plans and calculations from the Marine
More informationA Wind Profiling Platform for Offshore Wind Measurements and Assessment. Presenter: Mark Blaseckie AXYS Technologies Inc.
A Wind Profiling Platform for Offshore Wind Measurements and Assessment Presenter: Mark Blaseckie AXYS Technologies Inc. Any Sensor, Any Telemetry, Any Environment Founded in 1974 Part of the AXYS Group
More informationWelcome! Did You Know...? Aquatic Centre Dock Rebuild. Key Objectives
1 Welcome! Aquatic Centre Dock Rebuild The City of Vancouver is improving the dock at the Vancouver Aquatic Centre, which is nearing the end of its service life and is in need of replacement. This creates
More informationApplication for Consent to Conduct Marine Scientific Research. F Internal Waves in Straits (IWISE) Institution Contact Information Director
1. General Information 1.1 Reference ID: Application for Consent to Conduct Marine Scientific Research Application number: Project name: F2010-111 Internal Waves in Straits (IWISE) 1.2 Sponsoring institution(s):
More informationThe topics I will briefly cover, are; Stack Configurations Wellhead Connector Considerations Control Systems Tensioning Systems will be discussed by
Thank you Greg. 1 The topics I will briefly cover, are; Stack Configurations Wellhead Connector Considerations Control Systems Tensioning Systems will be discussed by Mr. Muhammad Sadiq, however in short,
More informationTides. Tides: longest waves. or seas. or ripples
Tides or ripples or seas Tides: longest waves Tides Definition: The rise and fall of sea level due to the gravitational forces of the Moon and Sun and the rotation of the Earth. Why tides are important?
More informationAstrolabe Reef Access Plan Stakeholder Presentation
Astrolabe Reef Access Plan Stakeholder Presentation *Rena s bow thruster approx 18m Agenda Overview Access Plan Introduction State of the Reef & Wreck Site What to Expect Timetable & Activity Questions
More informationHigh Frequency Acoustical Propagation and Scattering in Coastal Waters
High Frequency Acoustical Propagation and Scattering in Coastal Waters David M. Farmer Graduate School of Oceanography (educational) University of Rhode Island Narragansett, RI 02882 phone: (401) 874-6222
More informationUnderstanding the Dynamics of Shallow-Water Oceanographic Moorings
Understanding the Dynamics of Shallow-Water Oceanographic Moorings Mark A. Grosenbaugh Department of Applied Ocean Physics & Engineering Woods Hole Oceanographic Institution Woods Hole, MA 02543 phone:
More informationFINAL REPORT DERELICT FISHING GEAR IDENTIFICATION AND REMOVAL PROJECT PORT SUSAN
1900 W. NICKERSON, STE. 207 SEATTLE, WASHINGTON 98119-1650, U.S.A. TELEPHONE: (206) 285-3480 TELEFAX: (206) 283-8263 E-Mail : jjune@nrccorp.com (corporate) FINAL REPORT DERELICT FISHING GEAR IDENTIFICATION
More informationApplication of Value Engineering The Crosstown Project
Application of Value Engineering The Crosstown Project Presented To: CSVA Conference, Toronto November 15, 2011 Presented by: Rick Thompson, Chief Project Manager SRT/Yards Agenda 1. Eglinton Scarborough
More informationQuicker and Safer Deployment of Deepwater MODU Moorings.
Quicker and Safer Deployment of Deepwater MODU Moorings www.offspringinternational.com Deepwater MODU Mooring Deepwater exploration increasing further offshore Deeper moorings over 7,000ft Larger MODUs
More informationTRACK RECORD SEP. 2018
TRACK RECORD SEP. 2018 TABLE OF CONTENTS 1 INTRODUCTION... 3 2 MOTION COMPENSATED GANGWAY... 5 2.1 In operation at Walney Extension... 6 2.2 In operation at Borkum Riffgrund II... 7 3 MOTION COMPENSATED
More informationSOP GEN-007X Crane and Winch Operations
Page 1 of 7 SOP GEN-007X 1.0 Introduction 2.0 Responsibility 3.0 References 4.0 Training and Qualifications 5.0 Operational Inspections 6.0 Maintenance and Load Tests 7.0 Cranes 8.0 Winches 9.0 Mobile
More informationPoint LaBarbe/McGulpin Point Response April 2 May 8, 2018 Regional Response Team 3 Meeting November, 2018
Point LaBarbe/McGulpin Point Response April 2 May 8, 2018 Regional Response Team 3 Meeting November, 2018 TJ Mangoni District Response Advisory Team Supervisor Ninth Coast Guard District 216-214-4285 Summary
More informationDIVE PLAN Leg 1 Dive 11 Recover Wally 1
DIVE PLAN Leg 1 Dive 11 Recover Wally 1 Page 1 of 6 Location: Barkley Canyon Date: 9 May, 2014 14:00 Constraints: Weather, Sufficient deck space ROV Dive # OE 114 Objectives Prepare Wally I cable for recovery
More informationOFFSHORE SURVEY IN DEVELOPMENT PROJECTS. Ian Douglas Head, Offshore Surveys, Shell Projects & Technology Europe
OFFSHORE SURVEY IN DEVELOPMENT PROJECTS Ian Douglas Head, Offshore Surveys, Shell Projects & Technology Europe THE PROJECT: GOLDENEYE GOLDENEYE FACTS ST. FERGUS GOLDENEYE PLATFORM Gas Condensate Field
More informationUNDERWATER SERVICES COMPANY PROFILE
UNDERWATER SERVICES COMPANY PROFILE irov Underwater Services is an Italian Independent H i g h l y S p e c i a l i z e d C o m p a n y p r o v i d i n g underwater technology and ROV assistance to Salvage
More informationCONSTRUCTION OF LNG RECEIVING TERMINAL ON THE SAINT LAWRENCE TIDAL CURRENT CONDITIONS IN THE LEVIS AREA
RABASKA PROJECT CONSTRUCTION OF LNG RECEIVING TERMINAL ON THE SAINT LAWRENCE TIDAL CURRENT CONDITIONS IN THE LEVIS AREA FINAL REPORT MARCH 2006 N/Réf. : 24237.360 3075, ch. des Quatre-Bourgeois Sainte-Foy
More informationSPHL-R. A part of the James Fisher Hyperbaric Rescue Service. (Self Propelled Hyperbaric Lifeboat Recovery) Subsea UK Expo 2016
SPHL-R (Self Propelled Hyperbaric Lifeboat Recovery) A part of the James Fisher Hyperbaric Rescue Service Who is JFD? JFD A part of the James Fisher & Sons plc Group 160 yr old Marine Services Company
More informationNT09-21 Cruise Report SURUGA-BAY Cable Laying Experiment / VBCS Function Test
NT09-21 Cruise Report SURUGA-BAY Cable Laying Experiment / VBCS Function Test December 2009 Table of Contents 1. Overview 2. Schedule 3. Dive Summary 4. Concluding Remarks 1. Overview A unique development
More informationUNIT Coastal Navigation 1 (Intermediate 1)
National Unit Specification: general information NUMBER DC63 10 COURSE SUMMARY This unit is designed to enable candidates to understand the basic elements of coastal navigation and to plan a coastal passage
More information