1 Sensor Platform Project Marine Trials Bidders Conference Fundy Ocean Research Center for Energy fundyforce.ca 1

2 Project Team FORCE OceanWorks International Preliminary Design, Operational Procedures Murray Scotney, OceanMoor Technical Svcs Operational Procedures Mike Wilson, PICC Cable Engineering 2

3 Agenda The Project (15 min) Scope, progress, preliminary design, cable The Site (15 min) CLA, seabed topography, currents, data The Trials (15 min) RFP requirements, recovery, redeployment Q and A - (1hr) 3

4 Objectives: 1. To enhance confidence that we understand the site and the effects of turbines on the environment. 2. Develop Canadian expertise in tidal site characterization 3. Develop the infrastructure, equipment and techniques to reliably: A. Characterize and monitor high flow sites B. Assess the interaction of turbines on its surroundings 4

5 Infrastructure: A recoverable platform - A cabled node - Removable instrument bay - Serviced by moored surface vessel 2 to 3 times a year 5

6 Project Plan: Today Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Phase 1: Definition Phase 2: Preliminary Design and Trials Phase 3: Design/Build Marine Trials Phase 4: Integration Data Cable Install Phase 5: Install

7 Status: Preliminary Design Phase 2 Risk Studies: Operations Assessed highest risk Stability Data Cable Float Release Mechanism 7

8 Next Steps: Operational Trials Marine Trials: Retire risks associated with operations to the greatest extent possible Demonstrate: Mooring Recovery ROV demonstration? 8

9 Next Steps: Cable Deployment Install Data Cable: also serve as deployment test cable for medium voltage cables 9

10 FORCE Crown Lease Area One of the most powerful in the world 7000 MW in Minas Passage 2500 MW estimated safely extractable straight flowing currents, speeds over 5 m/s pushing 14 billion tonnes of water on avg. 10

11 FORCE Test Area 11

12 12

13 Berth Site ADCP Data Collection 14

14 Site D ADCP Data September 2011 Current Direction Spring Tide Ebb Ebb Neap Tide Operations Window 15

15 Slack Water at FORCE Courtesy of Dr. Richard Karsten and Dr. Joel Culina Acadia Tidal Energy Institute 16

16 Site D ADCP Data September 2011 Current Direction Spring Neap Spring Neap 17

17 18

18 Relevant Information Environmental Assessment Report including all appendices and 2010 addendum ADCP Data Sets and Summary Reports 400kHz and 600kHz high F sampling Sonar Surveys 2m and.4m multibeam.025m side scan Meteorological Report Seabed photos and video 19

19 Marine Services RFP: Conduct sea trials to verify deployment concepts. Components: Part 1: Engineering Study Part 2: Sheltered Harbour Trial Part 3: Minas Passage Trial

20 Part 1: Engineering Study A detailed mooring plan backed up with an engineering analysis Identify deck equipment and mooring arrangement Describe the process to control the mooring lines and position the vessel ( geometry described in App 3) The engineering study will validate assumptions in anchor size Installation and recovery plan for the moorings FORCE will validate the analysis conducted via 3 rd party engineering consultant 21

21 Part 2: Sheltered Harbour Trials Test Float Recovery Device Refine recovery/deployment procedures Evaluate deck layout Validate positioning of the vessel on mooring Training Conduct near home port (mutually agreed location) Assets should test actual equipment to be used (mooring may be scaled back) Data cable to be simulated with 1.25 wire rope and DMA 22

22 Part 3: Minas Passage Trials Trial will be conducted at neap tides.for safety mooring should be able to hold through 10 knts. Recovery will be done around slack water. Assess performance of float release in high flow. Float submergence is critical factor. Validate mooring plan and test positioning control in high flow Evaluate marine asset performance Validate recovery/deployment procedures in high flow Training Data cable to be simulated with wire rope and DMA 23

23 RFP Schedule 10 Apr: Bidders Conference 26 April: RFP submission deadline 06 May: Begin shortlisted candidates presentations 10 May: Notification of successful contractor 31 May: Contract Award Summer: Sheltered Harbour + Minas Passage Trials Contract to be awarded in phases based on performance and results on each phase. 24

24 Safety and Risk Management Contractors Safety System will be provided to FORCE for review 15 days after initial contract award Inspection of certifications and vessel surveys will be conducted prior to Part 2 and Part 3 FORCE will develop node recovery procedures Contractor will develop transit plan and mooring procedure Joint risk review process Part 2 and Part 3 Risk management plan developed for each phase 25

25 The Sensor Platform -The FORCE Science Node will be replaced by a Sea Trial Node Base for the marine trials. -The two nodes are physically the same 4.1 m Physical Specifications Summary 4.5 m x 4.1 m x 1.0 m Weight in air 10 tonnes Weight in water 8.7 tonnes 4.5 m 26 1 m

26 Tension Control - Recovery must be accomplished with this cable attached. - Tension force on this cable is not to exceed 4500 Kg. - For the trials a wire rope will be used to simulate the data cable. 27

27 Node Recovery Procedure - When ready for recovery, the Node will release a float that pulls a 60m messenger line to the surface. - The messenger line is attached to the main lift line that is attached to the main lift point of the Node. - It is left to the contractor decide how best to safely retrieve the buoy and lift line and to recover the node to the ship deck for servicing. 28

28 Float Release Mechanism - The lift line for the Node is contained within the Node itself in the Float Release Assembly. Main lift points 29

29 Float Release Mechanism - The Float Release Assembly contains the lift line, float, and release mechanisms. Acoustic Release Lift Line and drum Float Main Lift Points Solenoid Release 30

30 Stage 1: Initial Positioning and Lift Line Recovery - When ready for recovery, the float can be released from a shore station signal or if that fails, by an acoustic release activated from the vessel. - The Watch Area diagram is overlaid here for reference. 31

31 Stage 2: Recovering the Node - The vessel must be able to be repositioned in order to not exceed the maximum allowable tension force on the cable. Lift line lead angle will be key indicator. - Cable tensions max : 4500kg ideally b/t kgs. 32

32 Stage 3: Node on Deck - Once on board, proper cable tension must be maintained. Ideally redeployed in same tidal cycle. However, trials will validate ability to maintain tension over multiple tidal cycles. Tension monitor will be applied. - Node will also be secured. 33

33 Servicing the Sensor Platform - NOT REQUIRED FOR SEA TRIALS - The Instrument Node is replaced with abandonment pod and will require a crane in order to lift them in and out. A crane will be required to swap out the instrument pods. 34

34 Redeployment - The recovered lift line can be used to launch the serviced Node once it is ready and an acoustic release is attached. - Deployment requires the proper SDC tension to be maintained. - The vessel will have to be repositioned as the Node is deployed in order to maintain the proper tension. 35

35 Redeployment - Any deck tie downs removed prior to luffing overboard. - Vessel to reposition as node deployed to seabed - All procedures and personnel to adhere to marine and safety best practices. 36

MEASUREMENT OF LONG-TERM AMBIENT NOISE AND TIDAL TURBINE LEVELS IN THE BAY OF FUNDY

MEASUREMENT OF LONG-TERM AMBIENT NOISE AND TIDAL TURBINE LEVELS IN THE BAY OF FUNDY MEASUREMENT OF LONG-TERM AMBIENT NOISE AND TIDAL TURBINE LEVELS IN THE BAY OF FUNDY 11 th European Conference on Underwater Acoustics, 3 July 2012 Bruce Martin 1, Andrew Gerber 2, Christopher Whitt 1,

More information

Ocean Observatories Initiative (OOI) Moorings: New Capabilities for Seagoing Science

Ocean Observatories Initiative (OOI) Moorings: New Capabilities for Seagoing Science Ocean Observatories Initiative Ocean Observatories Initiative (OOI) Moorings: New Capabilities for Seagoing Science presented by Ed Dever and Walt Waldorf November 20, 2014 OOI Science Themes Coastal and

More information

Chapter 9: Sea operations

Chapter 9: Sea operations Chapter 9: Sea operations ANTARES takes advice from IFREMER for the sea operations, which concern the installation and recovery of the different components of the detector : Junction Box, Strings, Interconnecting

More information

RAMSTM. 360 Riser and Anchor-Chain Integrity Monitoring for FPSOs

RAMSTM. 360 Riser and Anchor-Chain Integrity Monitoring for FPSOs RAMS 360 Riser and Anchor-Chain Integrity Monitoring for FPSOs Introduction to RAMS Tritech s RAMS is a 360 anchor-chain and riser integrity monitoring system for Floating Production Storage and Offloading

More information

BACKGROUND TO STUDY CASE

BACKGROUND TO STUDY CASE BACKGROUND TO STUDY CASE German Aerospace Center (DLR) is using Andøya Rocket Range for a sounding rocket campaign. On 27th October 2005 a 300 kg payload (SHEFEX) was launched Due do a technical problems

More information

Delivery and Deployment of the U.S. Navy s Submarine Rescue System

Delivery and Deployment of the U.S. Navy s Submarine Rescue System Delivery and Deployment of the U.S. Navy s Submarine Rescue System Andrew DeSpirito Advanced Undersea Systems Program Office (PMS394) Naval Sea Systems Command Agenda Submarine Rescue Diving and Recompression

More information

Location: Barkley Canyon Date: September 9, 2013 Constraints: none

Location: Barkley Canyon Date: September 9, 2013 Constraints: none Page 1 of 11 DIVE PLAN R1650 Location: Barkley Canyon Date: September 9, 2013 Constraints: none Objectives Deploy POD 1 autonomous CTD Survey POD 3 for sediment enrichment sites; deposit cages; collect

More information

LESSONS LEARNED. Marine Operations Minas Passage

LESSONS LEARNED. Marine Operations Minas Passage LESSONS LEARNED Marine Operations Minas Passage Contents How to Use This Report Introduction Acronyms and Abbreviations Types of Vessels Dive Operations Equipment Challenges Environmental limitations Fundy

More information

Polar Research Vessel Operational Requirements and Summary of Technical Studies

Polar Research Vessel Operational Requirements and Summary of Technical Studies Polar Research Vessel Operational Requirements and Summary of Technical Studies Presentation to UNOLS by Jim St John Science and Technology Corporation - Polar Technology Office Why a New Antarctic Research

More information

Learn more at

Learn more at STRIDE JIP Phase III SUT Talk 15th November 2 Offshore VIV monitoring (vortex induced vibration) Catenary riser interaction with deepwater seabeds 3 Full Scale Riser Monitoring To get real measurements

More information

SeaSmart. Jonathan Evans

SeaSmart. Jonathan Evans SeaSmart A new approach for rapid, on-site resource assessment at potential tidal stream energy array sites using MAS Marine Solutions for the Deep Data World Jonathan Evans Presentation Outline Marine

More information

Modelling and Assessment of Marine Renewable Energy Resources. Andrew Cornett Canadian Hydraulics Centre National Research Council Canada May 2008

Modelling and Assessment of Marine Renewable Energy Resources. Andrew Cornett Canadian Hydraulics Centre National Research Council Canada May 2008 Modelling and Assessment of Marine Renewable Energy Resources Andrew Cornett Canadian Hydraulics Centre National Research Council Canada May 2008 Background Pan-Canadian resource inventory in 2005/06 Canada

More information

Multi-Purpose Workboats and Vessels. Marine Engineering and Construction. Salvage and Wreck Removal. Marine Consultancy Services

Multi-Purpose Workboats and Vessels. Marine Engineering and Construction. Salvage and Wreck Removal. Marine Consultancy Services Multi-Purpose Workboats and Vessels Marine Engineering and Construction Salvage and Wreck Removal Marine Consultancy Services Marine Expertise and Support We are a progressive company with more than 50

More information

Sea Views SEACAMS. month s edition. In this. Business aboard the RV Prince Madog What do seals do underwater? All aboard the RV Prince Madog

Sea Views SEACAMS. month s edition. In this. Business aboard the RV Prince Madog What do seals do underwater? All aboard the RV Prince Madog February 2013 SEACAMS Sea Views In this month s edition Business aboard the RV Prince Madog What do seals do underwater? All aboard the RV Prince Madog 0845 519 9029 www.seacams.ac.uk ebost: email: info@seacams.ac.uk

More information

Ocean Observatories Initiative Cabled Array Observatory Extension Cables/Connectors

Ocean Observatories Initiative Cabled Array Observatory Extension Cables/Connectors Ocean Observatories Initiative Cabled Array Observatory Extension Cables/Connectors Mike Harrington mikeh@apl.washington.edu Infrastructure Cable Laying Problem: Get to the interesting stuff. Laying interconnection

More information

Stevpris installation

Stevpris installation chaser Stevpris deployment for MODUs Introduction Typical methods for deployment and retrieval of Stevpris anchors with an anchor handling vessel (AHV) are described, focusing on the use of chasers for

More information

TRIAXYS Acoustic Doppler Current Profiler Comparison Study

TRIAXYS Acoustic Doppler Current Profiler Comparison Study TRIAXYS Acoustic Doppler Current Profiler Comparison Study By Randolph Kashino, Axys Technologies Inc. Tony Ethier, Axys Technologies Inc. Reo Phillips, Axys Technologies Inc. February 2 Figure 1. Nortek

More information

Appendix 5: Currents in Minas Basin. (Oceans Ltd. 2009)

Appendix 5: Currents in Minas Basin. (Oceans Ltd. 2009) Appendix 5: Currents in Minas Basin (Oceans Ltd. 29) Current in Minas Basin May 1, 28 March 29, 29 Submitted To: Minas Basin Pulp and Power P.O. Box 41 53 Prince Street Hansport, NS, BP 1P by 22, Purdy

More information

RV Southern Surveyor program

RV Southern Surveyor program 2011 RV Southern Surveyor program voyageplan SS2011_c01 Tsunami Detection Buoy Maintenance for Australian Tsunami Warning System (ATWS) Itinerary Mobilise 0700 Sydney, Tuesday 5 April 2011 Depart Sydney

More information

Mooring Modifications for the Reduction of Losses to Vandalism

Mooring Modifications for the Reduction of Losses to Vandalism Mooring Modifications for the Reduction of Losses to Vandalism H. Paul Freitag Chris Meinig Andrew J. Shepherd Pacific Marine Environmental Laboratory Seattle, Washington, USA Linda D. Stratton JISAO/University

More information

Isis Deployment. TMS and Live Boating. Inmartech08. Dave Turner Operations Co-ordinator.

Isis Deployment. TMS and Live Boating. Inmartech08. Dave Turner Operations Co-ordinator. Isis Deployment TMS and Live Boating Inmartech08 Dave Turner Operations Co-ordinator TMS Operations Why Why do do we we have have aa TMS? TMS? ItIt was was deemed deemed an an essential essential part

More information

RR10106 Cruise Plan ITOP Mooring Recovery and PhilSea10 Seaglider Operation (R/V Revelle November 6-26, 2010)

RR10106 Cruise Plan ITOP Mooring Recovery and PhilSea10 Seaglider Operation (R/V Revelle November 6-26, 2010) RR10106 Cruise Plan ITOP Mooring Recovery and PhilSea10 Seaglider Operation (R/V Revelle November 6-26, 2010) Chief Scientist: Ren-Chieh Lien, Applied Physics Lab, University of Washington Co-Chief Scientist:

More information

HYDROGRAPHIC AND SITE SURVEY REPORT

HYDROGRAPHIC AND SITE SURVEY REPORT HYDROGRAPHIC AND SITE SURVEY REPORT Proposed Pen Site at Dounie, Sound of Jura Prepared for: Kames Fish Farming Ltd Kilmelford Argyll PA34 4XA Tel: +44 (0)1631 720699 TransTech Limited www.transtechltd.com

More information

US Navy Wave Energy Test Site. Kaneohe, HI

US Navy Wave Energy Test Site. Kaneohe, HI US Navy Wave Energy Test Site Kaneohe, HI Presented by: Luis A. Vega Ph.D., HNEI, University of Hawaii September 24, 2014 MHK Testing in Hawaii (excluding OTEC) What do you do to support/facilitate testing?

More information

Using AUVs in Under-Ice Scientific Missions

Using AUVs in Under-Ice Scientific Missions Using AUVs in Under-Ice Scientific Missions James Ferguson, International Submarine Engineering Ltd. Presented at Arctic Change 08 11 Decenber 2008- Quebec City, Canada 1/16 ISE s s Experience in Arctic

More information

RVSS Appendix A Overview

RVSS Appendix A Overview RVSS Appendix A Overview Presented at RVTEC 2008 by Rich Findley rfindley@rsmas.miami.edu Definitions WINCH OWNER: The party or their representative who is normally responsible for the operation, inspection,

More information

Ocean Observatories Initiative. Coastal & Global Scale Nodes. Hydrogen Safety. OOI Surface Mooring Hydrogen Safety Review

Ocean Observatories Initiative. Coastal & Global Scale Nodes. Hydrogen Safety. OOI Surface Mooring Hydrogen Safety Review Ocean Observatories Initiative Coastal & Global Scale Nodes Hydrogen Safety CP01 Mooring Timeline: 21 November 2013: CP01CNSM was deployed and transitioned to shore controlled operations. 17 Feb. 2014:

More information

Appendix 11-B Anchor Handling Systems, Set Up and Handling

Appendix 11-B Anchor Handling Systems, Set Up and Handling Revision History Revision Date Section Changes Number 1 Sept 1 Permanent Chaser Pendant (PCP) Drawing updated 2018 2 Pennant Buoy System Drawing updated 3 Working Wire/Chaser Termination on Drawing updated

More information

RISK ASSESSMENT -HEATS-

RISK ASSESSMENT -HEATS- Honda RYA Youth RIB Championship 2018 RISK ASSESSMENT -HEATS- Issued by Royal Yachting Association October 2017 Page 1 of 12 Risk Assessment Event Summary Event Honda RYA Youth RIB Championship Organising

More information

Cathodic Protection Retrofit Options Comparison of Current Distribution

Cathodic Protection Retrofit Options Comparison of Current Distribution Cathodic Protection Retrofit Options Comparison of Current Distribution 1.0 Introduction There are three basic methods available for the deployment of anode systems when considering an offshore cathodic

More information

This guidance is based on the Risk Assessment approved by the Management Committee under the Club s Health & Safety Policy.

This guidance is based on the Risk Assessment approved by the Management Committee under the Club s Health & Safety Policy. Guidance on Safe Use of Dalgety Bay Sailing Club Raft This guidance is based on the Risk Assessment approved by the Management Committee under the Club s Health & Safety Policy. Where any items referred

More information

UTEC Survey Pipeline Inspection Using Low Logistic AUV June 2016

UTEC Survey Pipeline Inspection Using Low Logistic AUV June 2016 SUCCESS YOU CAN MEASURE UTEC Survey Pipeline Inspection Using Low Logistic AUV June 2016 Chris Erni Product Line Manager E T H I C S P E R F O R M A N C E E X C E L L E N C E P E O P L E GLOBAL FOOTPRINT

More information

REVISED SILT CURTAIN DEPLOYMENT PLAN

REVISED SILT CURTAIN DEPLOYMENT PLAN Contract No.: HY/2009/11 Central Wanchai Bypass, North Point Reclamation REVISED SILT CURTAIN DEPLOYMENT PLAN Name Prepared by: China Harbour Engineering Co., Ltd. China Road and Bridge Corporation Joint

More information

Dear Captain, Anchor lowering procedure all berths. Page 3: Mooring procedure Parker Point 2 and 4. Page 4: Mooring procedure Parker Point 3 and 5.

Dear Captain, Anchor lowering procedure all berths. Page 3: Mooring procedure Parker Point 2 and 4. Page 4: Mooring procedure Parker Point 3 and 5. Dear Captain, Safety of all personnel involved in the mooring of ships is a priority for our company. To assist us in a safe and incident free mooring operation please review the following mooring procedures

More information

Saab Seaeye Cougar XT Compact

Saab Seaeye Cougar XT Compact The Seaeye Cougar-XT Compact is a highly flexible and extremely powerful electric ROV with working depths of 300 metres. This system comes with almost all of the specifications of the very reliable Couger-XT

More information

Managing Dynamic Positioning (DP) Operations

Managing Dynamic Positioning (DP) Operations Managing Dynamic Positioning (DP) Operations Captain Andy Goldsmith, IMCA Technical Adviser IOSH Offshore Conference Tools for the trade 19 October 2017 1 2 IMCA OPERATIONAL STRUCTURE BOARD CEO SECRETARIAT

More information

Large-scale Field Test

Large-scale Field Test Vaskinn 1 Large-scale Field Test Kjetil Arne Vaskinn kav@trh.statkraftgroner.no Statkraft Grøner AS SUMMARY The objective the controlled failure of large-scale embankment is to monitor and record the failure

More information

IMCA Competence Assessment Portfolio June 2013

IMCA Competence Assessment Portfolio June 2013 IMCA Competence Portfolio June 2013 Name: Start Date in Current Self- Checklist Entry Level Criteria Acceptance Criteria Attained Certification 500 GRT or more: Valid certificate of competency or certificate

More information

Summary of Architecture Parallel Session. G. Hallewell/CPP Marseille P. Piattelli/ LNS Catania

Summary of Architecture Parallel Session. G. Hallewell/CPP Marseille P. Piattelli/ LNS Catania Summary of Architecture Parallel Session G. Hallewell/CPP Marseille P. Piattelli/ LNS Catania Parallel Session A1.2: Architecture: First session mainly devoted to undersea connectivity Chair: G. HALLEWELL,

More information

Fully Submersible Heavy Lift Vessel

Fully Submersible Heavy Lift Vessel Fully Submersible Heavy Lift Vessel Arnbjorn Joensen Aberdeen Maritime Branch (28th January 2015) PRESENTATION Introduction to the Subsea Deployment Vessel Installation method Tank test video Potential

More information

Offshore Wind Energy Stringent quality assurance and quality control. Coastal and Freshwater Fast responding and flexible organisation

Offshore Wind Energy Stringent quality assurance and quality control. Coastal and Freshwater Fast responding and flexible organisation Services Oceanographic and Positioning Equipment Rental Meteorological and Oceanographic Surveys Data Analysis and Characterisation Marine Energy Resource Assessment Real-Time Monitoring Founded in 2010,

More information

IMCA Competence Assessment Portfolio June 2013

IMCA Competence Assessment Portfolio June 2013 IMCA Competence Portfolio June 2013 Name: Start Date in Current Self- Checklist Entry Level Criteria Acceptance Criteria Attained Certification 500 GRT or more: Valid certificate of competency or certificate

More information

A FINAL REPORT BY PARTRAC LIMITED: MAY 2006

A FINAL REPORT BY PARTRAC LIMITED: MAY 2006 A FINAL REPORT BY PARTRAC LIMITED: MAY 26 Measurement of Suspended Sediment Concentration & Tidal Current During Dredging Operations and Post-Dredge at the Offshore Disposal Area, Poole, Dorset QUALITY

More information

11 Anchor Handling & MOU Moving 11-2

11 Anchor Handling & MOU Moving 11-2 Contents 11 Anchor Handling & MOU Moving 11-2 11.1 Introduction... 11-2 11.1.1 Definitions and Abbreviations... 11-2 11.2 Jointly Agreed Procedures and Responsibilities... 11-3 11.2.1 Operating Company...

More information

NSF's Ocean Observatories Initiative: Building Research Infrastructure for the Pacific Northwest and the Broader Community

NSF's Ocean Observatories Initiative: Building Research Infrastructure for the Pacific Northwest and the Broader Community Agenda Item B.3.b Supplemental OOI PowerPoint April 2013 Ocean Observatories Initiative NSF's Ocean Observatories Initiative: Building Research Infrastructure for the Pacific Northwest and the Broader

More information

The Next Generation Easy-to-Deploy (ETD) Tsunami Assessment Buoy

The Next Generation Easy-to-Deploy (ETD) Tsunami Assessment Buoy The Next Generation Easy-to-Deploy (ETD) Tsunami Assessment Buoy R.A. Lawson and D. Graham Science Applications International Corporation 4025 Hancock Street San Diego, CA 92110 USA S. Stalin, C. Meinig,

More information

Norway s solution: Hywind- world s first full scale floating turbine Dr. Nenad Keseric Asset Manager/Specialist Statoil ASA MPR RE Operations

Norway s solution: Hywind- world s first full scale floating turbine Dr. Nenad Keseric Asset Manager/Specialist Statoil ASA MPR RE Operations Norway s solution: Hywind- world s first full scale floating turbine Dr. Nenad Keseric Asset Manager/Specialist Statoil ASA MPR RE Operations Strategy and Support Leveraging Statoil s offshore oil and

More information

TARPON A Minimal Facilities Platform

TARPON A Minimal Facilities Platform TARPON A Minimal Facilities Platform Contents Introduction TARPON Description TARPON Features TARPON Benefits TARPON Proofs TARPON Typical Installation Options Design Codes & Certification Novel Application

More information

Aasta Hansteen. Operational Experiences. FFU Seminar 28 th January Tom-Erik Henriksen

Aasta Hansteen. Operational Experiences. FFU Seminar 28 th January Tom-Erik Henriksen Aasta Hansteen Operational Experiences FFU Seminar 28 th January 2016 Tom-Erik Henriksen Agenda Introduction to Aasta Hansteen Main Challenges & Risks Operational Experiences - 2015 Campaigns 2 seabed-to-surface

More information

R E V I S E D D A T E 0 4 /

R E V I S E D D A T E 0 4 / R E V I S E D D A T E 0 4 / 2 0 0 9 Guidelines Growing Oysters with the OysterGro System (OGS) Congratulations, you have just invested in one of the most efficient oyster growing system there is, the OysterGro.

More information

Innovative and Robust Design. With Full Extension of Offshore Engineering and Design Experiences.

Innovative and Robust Design. With Full Extension of Offshore Engineering and Design Experiences. Innovative and Robust Design by VL Offshore With Full Extension of Offshore Engineering and Design Experiences www.vloffshore.com Y Wind Semi Designed by VL Offshore The Y Wind Semi platform (foundation)

More information

ORE Open Research Exeter

ORE Open Research Exeter ORE Open Research Exeter TITLE Performance assessment of a novel active mooring system for load reduction in marine energy converters AUTHORS Luxmoore, J; Grey, S; Newsam, D; et al. DEPOSITED IN ORE 21

More information

NWEI. Fred.Olsen. Columbia Power

NWEI. Fred.Olsen. Columbia Power U.S. Marine Corps Base Hawaii, Kaneohe 30m, 60m, 80m berths in place, grid-connected First device deployed, second Jan 2016, third Sep 2016 HNEI role Funded by DOE, US Navy, ONR, State of Hawaii Acoustic,

More information

MEASUREMENT COMMUNICATION INSIGHT

MEASUREMENT COMMUNICATION INSIGHT Temperature & Depth MEASUREMENT COMMUNICATION INSIGHT CONTENTS Introduction to Aquatec Measuring Temperature and Depth 2 3 Aquatec s Temperature and Depth Loggers AQUAlogger 520 AQUAlogger 530 AQUAlogger

More information

ROV Development ROV Function. ROV Crew Navigation IRATECH SUB SYSTEMS 2010

ROV Development ROV Function. ROV Crew Navigation IRATECH SUB SYSTEMS 2010 IR AT EC H SU B SY ST EM S 20 10 Remotely Operated Vehicle ROV INTRODUCTORY 2008 2008 1 KEY POINTS ROV Introductory ROV Development ROV Function Types of ROV ROV Crew Navigation ROV Components 2 ROV Development

More information

PORT TALBOT BULK TERMINAL MOORING OPERATIONS MANUAL

PORT TALBOT BULK TERMINAL MOORING OPERATIONS MANUAL PORT TALBOT BULK TERMINAL MOORING OPERATIONS MANUAL ABP Marine Operations & Tata Burdening Departments 2017 RESPONSIBILLITIES Tata Steel UK (TSUK) is the operator of the Port Talbot Harbour Bulk Terminal.

More information

(a) Calculate the speed of the sphere as it passes through the lowest point of its path.

(a) Calculate the speed of the sphere as it passes through the lowest point of its path. 1991 Q33 A sphere of mass 3 kg on the end of a wire is released from rest and swings through a vertical distance of 0.4 m. (Neglect air friction.) (a) Calculate the speed of the sphere as it passes through

More information

Update on Canadian Research Vessels Ship Procurement Projects

Update on Canadian Research Vessels Ship Procurement Projects Update on Canadian Research Vessels Ship Procurement Projects 28 th International Research Ship Operators Meeting (IRSO) La Jolla, California October 2012 Jennifer Vollrath 1 Outline National Ship Building

More information

Cruise Plan for QPE (R/V Revelle Sept/ 12-16, 2009)

Cruise Plan for QPE (R/V Revelle Sept/ 12-16, 2009) Cruise Plan for QPE (R/V Revelle Sept/ 12-16, 2009) Objectives In this cruise we will recover six subsurface ADCP/TC moorings (Lien), five restrained ADCP (Centurioni), and perform shipboard ADCP, Revelle

More information

Wave Hub Update All Energy 21/22 May Stuart Herbert Commercial Director

Wave Hub Update All Energy 21/22 May Stuart Herbert Commercial Director Wave Hub Update All Energy 21/22 May 2014 Stuart Herbert Commercial Director Deployment Site EMEC, Orkney NaREC/EMEC Refined Prototype Testing Market penetration NaREC, Northumberland Market entry with

More information

1 Module A (uniform topography) survey lines Module B (topographic wake) survey lines Module C (submesoscale soup) survey lines...

1 Module A (uniform topography) survey lines Module B (topographic wake) survey lines Module C (submesoscale soup) survey lines... ..................................................................................... point Sal Coastal circulation Experiment (SCoNE) / SP1723 CRUISE PLAN ANDRÉ PALÓCZY R/V Robert Gordon Sproul, September/10

More information

Preventing Damage to Harbour Facilities and. Ship Handling in Harbours PART 2 INDEX

Preventing Damage to Harbour Facilities and. Ship Handling in Harbours PART 2 INDEX Preventing Damage to Harbour Facilities and Ship Handling in Harbours PART 2 INDEX 1 Vessel handling is based on the basic knowledge that a vessel floats in the water and returns to its original position

More information

Geo-Vibro Corer

Geo-Vibro Corer High Frequency Vibro Coring System Operational Features Proven performance & high quality cores 30 kn impulse at 30 Hz for fast penetration Reliable, lightweight & cost effective Modular construction (cores

More information

Ketchikan Harbors Thomas Basin and Bar Point Harbor

Ketchikan Harbors Thomas Basin and Bar Point Harbor Ketchikan Harbors Thomas Basin and Bar Point Harbor Condition of Improvements 30 December 2014 Thomas Basin & Bar Point Harbors Ketchikan, Alaska (CWIS No. 000631 & 087071) Authorization (1) Rivers and

More information

CB-40 Data Buoy Quick Start Guide

CB-40 Data Buoy Quick Start Guide CB-40 Data Buoy Quick Start Guide The NexSens CB-40 Data Buoy offers a compact and affordable platform for deploying water quality sondes and other instruments that integrate power and data logging. The

More information

Products and Services HR3D, AUV3D

Products and Services HR3D, AUV3D Products and Services HR3D, AUV3D Multi-streamer Short Offset High Resolution 3D Seismic Acquisition Peter Sack Tor Haugland Sound Oceanics, LLC Houston, Texas USA 15 March 2012 Background Petromar V West

More information

USCG Development Proposal: Heavy Oil Tracking Tactics, Techniques and Procedures Presented to: Ms. Brenda M. Burke (RDC)

USCG Development Proposal: Heavy Oil Tracking Tactics, Techniques and Procedures Presented to: Ms. Brenda M. Burke (RDC) USCG Development Proposal: Heavy Oil Tracking Tactics, Techniques and Procedures Presented to: Ms. Brenda M. Burke (RDC) BAA Number: HSCG32-07-R-R00013 Title of Proposal: Heavy Oil Tracking Tactics, Techniques

More information

Suction anchor foundations for tension and taut leg floaters in deep waters. Tension Leg Platform. Taut Leg Platform. upper chain. risers.

Suction anchor foundations for tension and taut leg floaters in deep waters. Tension Leg Platform. Taut Leg Platform. upper chain. risers. Case history: Soil investigation for offshore suction anchors anchor foundations for tension and taut leg floaters in deep waters Alternative anchors for floating structures pile Over last 5 - years anchoring

More information

voyageplan SS Itinerary Principal Investigator(s) RV Southern Surveyor program

voyageplan SS Itinerary Principal Investigator(s) RV Southern Surveyor program 2008 RV Southern Surveyor program voyageplan SS04-2008 RESEARCH CHARTER Deep-Ocean Tsunami Detection Buoy (DART) Scheduled Maintenance Replacement for the Australian Tsunami Warning System (ATWS) Itinerary

More information

Focus on Operational Efficiency and Crew Safety - Introducing Advanced ROV Technology in Marine Towed Streamer Seismic

Focus on Operational Efficiency and Crew Safety - Introducing Advanced ROV Technology in Marine Towed Streamer Seismic Focus on Operational Efficiency and Crew Safety - Introducing Advanced ROV Technology in Marine Towed Streamer Seismic R. Tonnessen* (Petroleum Geo-Services) & T. Skadberg (Petroleum Geo- Services) SUMMARY

More information

The Wave Glider: A Mobile Buoy Concept for Ocean Science. 009 Liquid Robotics Inc.

The Wave Glider: A Mobile Buoy Concept for Ocean Science. 009 Liquid Robotics Inc. The Wave Glider: A Mobile Buoy Concept for Ocean Science 009 Liquid Robotics Inc. J. Manley & T. Richardson: Liquid Robotics Inc. DBCP XXV Paris September 28, 2009 1 Wave Glider Overview Unique Two Part

More information

Original URI Scanfish MKII

Original URI Scanfish MKII Scanfish MKII URI s Scanfish MKII Sensors include CTD, Fluorometer, Dissolved Oxygen and Seabird Fast Temperature and Conductivity Sensors logging at 400 Hz and sending 50 Hz data via 9600 Baud uplink

More information

Noise Experiment #2. Marine Physical Laboratory Scripps Institution of Oceanography La Jolla, CA February 22 February 2010

Noise Experiment #2. Marine Physical Laboratory Scripps Institution of Oceanography La Jolla, CA February 22 February 2010 Noise Experiment #2 Marine Physical Laboratory Scripps Institution of Oceanography La Jolla, CA 92093-0701 16 February 22 February 2010 1. Objective The objective of the noise experiment is to observe

More information

Break in the Bahamas. Cutters Head to the Caribbean to Wire Saw Sunken Pier. A 25-foot by 25-foot steel pier section had sunk into the water.

Break in the Bahamas. Cutters Head to the Caribbean to Wire Saw Sunken Pier. A 25-foot by 25-foot steel pier section had sunk into the water. Break in the Bahamas Cutters Head to the Caribbean to Wire Saw Sunken Pier A 25-foot by 25-foot steel pier section had sunk into the water. CONCRETE CASES Divers were used to inspect the damaged structure

More information

Cargo and hull damage while at anchor in heavy weather

Cargo and hull damage while at anchor in heavy weather October 2017 Cargo and hull damage while at anchor in heavy weather A small general cargo vessel loaded steel cargo at several different ports. At the first port the vessel loaded steel plates and at the

More information

[***] = both land and marine [***] = Marine only [***] = Land only + ([***] = Shallow Water) if needed

[***] = both land and marine [***] = Marine only [***] = Land only + ([***] = Shallow Water) if needed Stand-By conditions: [***] = both land and marine (Terms may require capitalisation or substitution subject to terminology used in the relevant contract) The below Stand-By conditions list is non-exhaustive

More information

ACCESS the BLUE ECONOMY ALL OCEANS Engineering Ltd

ACCESS the BLUE ECONOMY ALL OCEANS Engineering Ltd Subsea Expo 2018 ROV Conference 07.02.2018 ACCESS the BLUE ECONOMY The BLUE ECONOMY - DEFINITION The Blue Economy is a book by Gunter Pauli publish in 2010 based on the idea that he developed in 2004 In

More information

ANY OTHER BUSINESS. Guidelines for passenger ship tender operator. Submitted by Cruise Lines International Association (CLIA) SUMMARY

ANY OTHER BUSINESS. Guidelines for passenger ship tender operator. Submitted by Cruise Lines International Association (CLIA) SUMMARY E SUB-COMMITTEE ON STANDARDS OF TRAINING AND WATCHKEEPING 42nd session Agenda item 3 STW 42/13/2 25 October 2010 Original: ENGLISH ANY OTHER BUSINESS Guidelines for passenger ship tender operator Submitted

More information

MSC Guidelines for the Review of Oil Spill Response Vessels (OSRV), Lightship and Stability

MSC Guidelines for the Review of Oil Spill Response Vessels (OSRV), Lightship and Stability R. J. LECHNER, CDR, Chief, Tank Vessel and Offshore Division Purpose This Plan Review Guidance (PRG) explains the requirements for seeking plan approval for stability plans and calculations from the Marine

More information

A Wind Profiling Platform for Offshore Wind Measurements and Assessment. Presenter: Mark Blaseckie AXYS Technologies Inc.

A Wind Profiling Platform for Offshore Wind Measurements and Assessment. Presenter: Mark Blaseckie AXYS Technologies Inc. A Wind Profiling Platform for Offshore Wind Measurements and Assessment Presenter: Mark Blaseckie AXYS Technologies Inc. Any Sensor, Any Telemetry, Any Environment Founded in 1974 Part of the AXYS Group

More information

Welcome! Did You Know...? Aquatic Centre Dock Rebuild. Key Objectives

Welcome! Did You Know...? Aquatic Centre Dock Rebuild. Key Objectives 1 Welcome! Aquatic Centre Dock Rebuild The City of Vancouver is improving the dock at the Vancouver Aquatic Centre, which is nearing the end of its service life and is in need of replacement. This creates

More information

Application for Consent to Conduct Marine Scientific Research. F Internal Waves in Straits (IWISE) Institution Contact Information Director

Application for Consent to Conduct Marine Scientific Research. F Internal Waves in Straits (IWISE) Institution Contact Information Director 1. General Information 1.1 Reference ID: Application for Consent to Conduct Marine Scientific Research Application number: Project name: F2010-111 Internal Waves in Straits (IWISE) 1.2 Sponsoring institution(s):

More information

The topics I will briefly cover, are; Stack Configurations Wellhead Connector Considerations Control Systems Tensioning Systems will be discussed by

The topics I will briefly cover, are; Stack Configurations Wellhead Connector Considerations Control Systems Tensioning Systems will be discussed by Thank you Greg. 1 The topics I will briefly cover, are; Stack Configurations Wellhead Connector Considerations Control Systems Tensioning Systems will be discussed by Mr. Muhammad Sadiq, however in short,

More information

Tides. Tides: longest waves. or seas. or ripples

Tides. Tides: longest waves. or seas. or ripples Tides or ripples or seas Tides: longest waves Tides Definition: The rise and fall of sea level due to the gravitational forces of the Moon and Sun and the rotation of the Earth. Why tides are important?

More information

Astrolabe Reef Access Plan Stakeholder Presentation

Astrolabe Reef Access Plan Stakeholder Presentation Astrolabe Reef Access Plan Stakeholder Presentation *Rena s bow thruster approx 18m Agenda Overview Access Plan Introduction State of the Reef & Wreck Site What to Expect Timetable & Activity Questions

More information

High Frequency Acoustical Propagation and Scattering in Coastal Waters

High Frequency Acoustical Propagation and Scattering in Coastal Waters High Frequency Acoustical Propagation and Scattering in Coastal Waters David M. Farmer Graduate School of Oceanography (educational) University of Rhode Island Narragansett, RI 02882 phone: (401) 874-6222

More information

Understanding the Dynamics of Shallow-Water Oceanographic Moorings

Understanding the Dynamics of Shallow-Water Oceanographic Moorings Understanding the Dynamics of Shallow-Water Oceanographic Moorings Mark A. Grosenbaugh Department of Applied Ocean Physics & Engineering Woods Hole Oceanographic Institution Woods Hole, MA 02543 phone:

More information

FINAL REPORT DERELICT FISHING GEAR IDENTIFICATION AND REMOVAL PROJECT PORT SUSAN

FINAL REPORT DERELICT FISHING GEAR IDENTIFICATION AND REMOVAL PROJECT PORT SUSAN 1900 W. NICKERSON, STE. 207 SEATTLE, WASHINGTON 98119-1650, U.S.A. TELEPHONE: (206) 285-3480 TELEFAX: (206) 283-8263 E-Mail : jjune@nrccorp.com (corporate) FINAL REPORT DERELICT FISHING GEAR IDENTIFICATION

More information

Application of Value Engineering The Crosstown Project

Application of Value Engineering The Crosstown Project Application of Value Engineering The Crosstown Project Presented To: CSVA Conference, Toronto November 15, 2011 Presented by: Rick Thompson, Chief Project Manager SRT/Yards Agenda 1. Eglinton Scarborough

More information

Quicker and Safer Deployment of Deepwater MODU Moorings.

Quicker and Safer Deployment of Deepwater MODU Moorings. Quicker and Safer Deployment of Deepwater MODU Moorings www.offspringinternational.com Deepwater MODU Mooring Deepwater exploration increasing further offshore Deeper moorings over 7,000ft Larger MODUs

More information

TRACK RECORD SEP. 2018

TRACK RECORD SEP. 2018 TRACK RECORD SEP. 2018 TABLE OF CONTENTS 1 INTRODUCTION... 3 2 MOTION COMPENSATED GANGWAY... 5 2.1 In operation at Walney Extension... 6 2.2 In operation at Borkum Riffgrund II... 7 3 MOTION COMPENSATED

More information

SOP GEN-007X Crane and Winch Operations

SOP GEN-007X Crane and Winch Operations Page 1 of 7 SOP GEN-007X 1.0 Introduction 2.0 Responsibility 3.0 References 4.0 Training and Qualifications 5.0 Operational Inspections 6.0 Maintenance and Load Tests 7.0 Cranes 8.0 Winches 9.0 Mobile

More information

Point LaBarbe/McGulpin Point Response April 2 May 8, 2018 Regional Response Team 3 Meeting November, 2018

Point LaBarbe/McGulpin Point Response April 2 May 8, 2018 Regional Response Team 3 Meeting November, 2018 Point LaBarbe/McGulpin Point Response April 2 May 8, 2018 Regional Response Team 3 Meeting November, 2018 TJ Mangoni District Response Advisory Team Supervisor Ninth Coast Guard District 216-214-4285 Summary

More information

DIVE PLAN Leg 1 Dive 11 Recover Wally 1

DIVE PLAN Leg 1 Dive 11 Recover Wally 1 DIVE PLAN Leg 1 Dive 11 Recover Wally 1 Page 1 of 6 Location: Barkley Canyon Date: 9 May, 2014 14:00 Constraints: Weather, Sufficient deck space ROV Dive # OE 114 Objectives Prepare Wally I cable for recovery

More information

OFFSHORE SURVEY IN DEVELOPMENT PROJECTS. Ian Douglas Head, Offshore Surveys, Shell Projects & Technology Europe

OFFSHORE SURVEY IN DEVELOPMENT PROJECTS. Ian Douglas Head, Offshore Surveys, Shell Projects & Technology Europe OFFSHORE SURVEY IN DEVELOPMENT PROJECTS Ian Douglas Head, Offshore Surveys, Shell Projects & Technology Europe THE PROJECT: GOLDENEYE GOLDENEYE FACTS ST. FERGUS GOLDENEYE PLATFORM Gas Condensate Field

More information

UNDERWATER SERVICES COMPANY PROFILE

UNDERWATER SERVICES COMPANY PROFILE UNDERWATER SERVICES COMPANY PROFILE irov Underwater Services is an Italian Independent H i g h l y S p e c i a l i z e d C o m p a n y p r o v i d i n g underwater technology and ROV assistance to Salvage

More information

CONSTRUCTION OF LNG RECEIVING TERMINAL ON THE SAINT LAWRENCE TIDAL CURRENT CONDITIONS IN THE LEVIS AREA

CONSTRUCTION OF LNG RECEIVING TERMINAL ON THE SAINT LAWRENCE TIDAL CURRENT CONDITIONS IN THE LEVIS AREA RABASKA PROJECT CONSTRUCTION OF LNG RECEIVING TERMINAL ON THE SAINT LAWRENCE TIDAL CURRENT CONDITIONS IN THE LEVIS AREA FINAL REPORT MARCH 2006 N/Réf. : 24237.360 3075, ch. des Quatre-Bourgeois Sainte-Foy

More information

SPHL-R. A part of the James Fisher Hyperbaric Rescue Service. (Self Propelled Hyperbaric Lifeboat Recovery) Subsea UK Expo 2016

SPHL-R. A part of the James Fisher Hyperbaric Rescue Service. (Self Propelled Hyperbaric Lifeboat Recovery) Subsea UK Expo 2016 SPHL-R (Self Propelled Hyperbaric Lifeboat Recovery) A part of the James Fisher Hyperbaric Rescue Service Who is JFD? JFD A part of the James Fisher & Sons plc Group 160 yr old Marine Services Company

More information

NT09-21 Cruise Report SURUGA-BAY Cable Laying Experiment / VBCS Function Test

NT09-21 Cruise Report SURUGA-BAY Cable Laying Experiment / VBCS Function Test NT09-21 Cruise Report SURUGA-BAY Cable Laying Experiment / VBCS Function Test December 2009 Table of Contents 1. Overview 2. Schedule 3. Dive Summary 4. Concluding Remarks 1. Overview A unique development

More information

UNIT Coastal Navigation 1 (Intermediate 1)

UNIT Coastal Navigation 1 (Intermediate 1) National Unit Specification: general information NUMBER DC63 10 COURSE SUMMARY This unit is designed to enable candidates to understand the basic elements of coastal navigation and to plan a coastal passage

More information