1 9575 West Higgins Road, Suite 400 Rosemont, Illinois p: f: MEMORANDUM TO: FROM: David B. Nelson DRW Holdings, LLC Michael A. Werthmann, E, TOE rincipal Luay R. Aboona, E rincipal DATE: February 22, Revised April 30, 2012 SUBJECT: Traffic Impact Study ark Drive/Water Street Mixed-Use Development Chicago, Illinois This memorandum summarizes the methodologies, results, and findings of a traffic impact study conducted by Kenig, Lindgren, O Hara, Aboona, Inc. (KLOA, Inc.) for a proposed mixed-use development to be located in Chicago, Illinois. The site, which currently contains a surface parking lot, is located on the north side of Water Street bounded by ark Drive and New Street. As proposed, the development is to consist of approximately 400 apartments, a 400-room full-service hotel and a 243-space parking garage. Access to the parking garage is proposed on Lower Water Street with a drop-off/pick-up circle/lane proposed on both ark Drive (hotel) and Upper Water Street (apartments). It should be noted that a similar mixed-use development has been previously approved for the subject site. The purpose of this study was to examine background traffic conditions, assess the impact that the proposed development will have on traffic conditions in the area, and determine if any street or access improvements are necessary to accommodate traffic generated by the development. The sections of this report present the following. Existing conditions A description of the proposed development Directional distribution of the development generated traffic Vehicle trip generation for the proposed development Future traffic conditions including access to the site Traffic analyses for the weekday morning, weekday evening and Saturday midday peak hours Recommendations with respect to adequacy of the site access system and adjacent street network KLOA, Inc. Transportation and arking lanning Consultants
2 Existing Conditions Existing transportation conditions in the vicinity of the site were documented based on a field visits conducted by KLOA, Inc. in order to obtain a database for projecting future conditions. The following provides a description of the geographical location of the site, physical characteristics of the area street system including lane usage and traffic control devices, an inventory of the alternative modes of transportation serving the area and existing peak hour vehicle, pedestrian and bicycle volumes. Site Location The site, which currently contains a public parking lot, is bounded by a vacant parcel on the north, New Street on the east, Water Street on the south, and ark Drive on the west. Land uses in the immediate area consist primarily of residential, office, hotel, and retail land uses. The Sheraton Chicago Hotel and Towers is located south of the site. Figure 1 shows and aerial photo of the site. Area Streets The principal streets in the site vicinity that provide access to the site are described in the following paragraphs and shown in Figures 2 and 3. Illinois Street is a major one-way eastbound arterial street that forms a one-way pair with Grand Avenue. The Illinois-Grand pair provides direct access to/from Lake Shore Drive via the Illinois Street, Grand Avenue, and Lake Shore Drive interchange. Between Columbus Drive and McClurg Court, Illinois Street has three moving lanes with parking generally prohibited on both sides of the street. West of Columbus Drive, Illinois Street generally provides two moving lanes with parking prohibited on both sides of the street. Traffic signals are located at most intersections along Illinois Street including the intersections of Columbus Drive, McClurg Court and eshtigo Court. Columbus Drive is a major arterial street. In the vicinity of the site, Columbus Drive provides a six-lane cross section with parking prohibited on both sides of the street. Separate left-turn lanes are provided at most intersections, including its signalized intersections with Wacker Drive, Upper Water Street and Illinois Street. ark Drive is a north-south, local street that extends from Illinois Street south to Upper Water Street. It provides one lane in each direction with parking permitted on the east side of the street. A taxi stand is provided along the west side of the street. ark Drive is under stop sign control at its intersections with both Illinois Street and Upper Water Street. New Street is a north-south, local street that extends from Illinois Street to just south of Lower Water Street. Between Illinois Street and Lower Water Street, New Street provides one lane in each direction with parking permitted on the west side of the street. The portion of New Street south of Lower Water Street is a one-way northbound street with parking prohibited on both sides of the street. New Street is under stop sign control at its intersection with Illinois Street and under all-way stop sign control at its intersection with Lower Water Street. 2
3 Site Location Figure 1 3
4 Area Street System Figure 2 4
5 AMC ILLINOIS NBC TOWER COLUMBUS DR ARK DR SITE NEW CITY VIEW CONDOS TS NORTH WATER ER WATER LOWER WATER SHERATON LEGEND - TRAFFIC SIGNAL - O SIGN - TRAVEL LANE - BIKE LANE - ARKING ERMITTED - ARKING ROHIBITED - BUS O - BUS O WITH SHELTER TS - TAXI AND ROJECT: TITLE: ROJECT NO: ARK DRIVE/WATER REET MIXED-USE DEVELOMENT CHICAGO, ILLINOIS EXIING REET CONDITIONS FIGURE NO: 3
6 Lower Water Street is an east-west, local street. It provides one lane in each direction with parking generally prohibited on both sides of the street west of New Street and permitted on the south side of the street east of New Street. The Lower Water Street/New Street intersection is under all-way stop sign control. Upper Water Street is an east-west, local street that extends from Cityfront laza Drive to just east of ark Drive. It provides one lane in each direction with parking generally prohibited on both sides of the street. Its intersection with Columbus Drive is under traffic signal control. Alternative Modes of Transportation Accessibility to and from the area is enhanced by the various alternative modes of transportation serving the area as summarized below. ublic Transportation. The area is served by the CTA Red (Howard/Dan Ryan) rapid transit line which extends from the Howard Street station located on the City s northern border to the 95 th /Dan Ryan station located along the Dan Ryan Expressway at 95 th Street. A local stop is provided at State Street and Grand Avenue (Grand Avenue Station) which is located approximately ½ mile from the site. In addition, the following bus routes serve the immediate area and all have stops adjacent to the site. Route Number 2 - Hyde ark Express generally runs along Lake Shore Drive, State Street and Michigan Avenue between Hyde ark and the River North and Streeterville neighborhoods. Service is provided Monday through Friday during the morning and evening peak periods. Route Number 29 - State generally runs along State Street between the Red Line s 95 th /Dan Ryan station and the Illinois/Grand corridor. Service is provided seven days a week and on holidays. Route Number 65 - Grand generally runs along Grand Avenue between Navy ier and Nordic Avenue (7000 West Grand Avenue). Service is provided seven days a week and on holidays. Route Number 66 - Chicago generally runs along Chicago Avenue between Navy ier and Austin Avenue (6000 West Chicago Street). Service is provided seven days a week and on Holidays. Route Number Ogilvie/Wacker Express generally runs along Wacker Drive and the Illinois/Grand corridor between the Ogilvie Metra Station and Navy ier. Service is provided Monday through Friday during the morning and evening peak periods. Route Number Union/Wacker Express generally runs along Wacker Drive and the Illinois/Grand corridor between the Union Station and Navy ier. Service is provided Monday through Friday during the morning and evening peak periods. 6
7 Route Number Navy ier runs along Wacker Drive, Illinois Street, Grand Avenue and Madison Street between Navy ier and Ogilvie and Union Stations. Service is provided seven days a week and on Holidays. Lastly, numerous additional bus routes run along Michigan Avenue and Wacker Drive with bus stops located within walking distance of the project. Bicycle Routes. The following streets within the vicinity of the site have been recommended as bike routes by the Chicago Department of Transportation (CDOT). Both Illinois Street and Grand Avenue between Navy ier/lakeside Trail and Wells Street with bike lanes provided along both streets. McClurg Court between Illinois Street and Ohio Street. Ohio Street between McClurg Court and the pedestrian underpass under Lake Shore Drive. Lastly, the Lakefront Trail is located approximately one third of a mile from the site and extends along Lake Michigan for 18 miles between Hollywood Avenue on the north and 71st Street on the south. The Grand Avenue and Illinois Street bike lanes provide direct access between the site and the Lake Front Trail. It should be noted that CDOT is planning to grade separate the Lake Front Trail over the Chicago River and Lower Lake Shore Drive. The Navy ier Flyover is proposed to run along the eastern edge of Lake Shore Drive extending from just south of the river to just north of Jane Addams Memorial ark. According to the CDOT, construction could begin in edestrian Facilities. All of the streets within the immediate area have sidewalks on both sides of the street. In addition, the Chicago Riverwalk is located approximately a quarter mile from the site and the Lakefront Trail is located one-third of a mile from the site. Lastly, crosswalks and pedestrian traffic signals are generally provided at all of the intersections within the immediate area, with countdown pedestrian traffic signals provided at the intersections of Illinois Street/Columbus Drive and Illinois Street/McClurg Court. Census data (see Appendix) and surveys conducted by the Illinois-Grand Transportation Management Association (TMA) have shown that only approximately 33 percent of the residents within the southern portion of Streeterville drive a car to work. The majority of the residents within the area use the alternative modes of transportation to commute to/from work. Therefore, the proximity of Streeterville within the downtown area and the alternative modes of transportation serving the area has resulted in a significant reduction in the traffic generated by area residential developments, particularly during the critical weekday morning and evening commuter peak periods. 7
8 Existing Traffic Volumes In order to determine current traffic conditions in the vicinity of the site, KLOA, Inc. conducted peak period vehicle, pedestrian and bicycle counts at the following intersections. Illinois Street with Columbus Drive Illinois Street with ark Drive Illinois Street with New Street Upper Water Street with Columbus Drive Upper Water Street with ark Drive Lower Water Street with New Street The traffic counts were conducted on Tuesday, June 14, 2011 during the weekday morning (7:00 A.M. to 9:00 A.M.) and evening (4:00.M. to 6:00.M.) peak periods and on Saturday, June 18, 2011 during the midday (Noon to 2:00.M.) peak period. Based on the results of the traffic counts, the weekday morning peak hour of traffic occurs from 7:45 A.M. to 8:45 A.M., the weekday evening peak hour of traffic occurs from 5:00.M. to 6:00.M., and the Saturday midday peak hour occurs from 12:30.M. to 1:30.M. Figure 4 illustrates the existing peak hour traffic volumes and Figure 5 illustrates the existing pedestrian and bicycle volumes. Traffic Characteristics of the roposed Development In order to properly evaluate future traffic conditions in the surrounding area, it was necessary to determine the traffic characteristics of the proposed development including the directional distribution and volumes of traffic that it will generate. roposed Development lan As proposed, the mixed use development is to consist of approximately 400 apartments, 400 hotel rooms and a 243-space parking garage. Access to the parking garage is proposed on Lower Water Street with a drop-off/pick-up circle/lane proposed on both ark Drive (hotel) and Upper Water Street (apartments). Loading for the hotel and for the apartments is proposed on Lower Water Street. Directional Distribution of Site Traffic The directions from which the development-generated traffic will approach and depart the site were estimated based on the existing travel patterns as determined from the traffic counts and previous studies conducted in the area. Figure 6 illustrates the directional distribution for the development. 8
9 703 (677) [463] 167 (184) [245] AMC 119 (172) [58] 559 (1029) [653] 239 (435) [137] NBC TOWER 70 (40) [51] 64 (46) [57] 26 (41) [28] 45 (109) [32] 853 (1019) [480] NORTH WATER 19 (53) [69] 729 (830) [282] COLUMBUS DR 97 (58) [12] 213 (191) [110] 856 (955) [303] 904 (1370) 22 (20) [32] 38 (44) [9] [972] 35 (34) [36] 41 (33) [30] 51 (77) [35] 22 (36) [47] 1 (1) [2] ER WATER 70 (87) [26] 70 (39) [50] ARK DR 32 (30) [101] 30 (27) [50] SHERATON 868 (1349) [1050] SITE 96 (85) [62] 68 (51) [23] 36 (41) [30] NEW 49 (28) [27] 18 (31) [20] 42 (95) [30] 21 (36) [25] ILLINOIS CITY VIEW CONDOS LOWER WATER 12 (23) [13] 13 (16) [25] 22 (18) [35] 122 (43) [38] 15 (16) [15] 65 (27) [41] LEGEND 42 (68) [41] 00 (00) [00] - TRAFFIC SIGNAL - WEEKDAY MORNING EAK HOUR - WEEKDAY EVENING EAK HOUR - SATURDAY MIDDAY EAK HOUR 98 (94) [85] ROJECT: TITLE: ROJECT NO: ARK DRIVE/WATER REET MIXED-USE DEVELOMENT CHICAGO, ILLINOIS EXIING EAK HOUR TRAFFIC VOLUMES FIGURE NO: 4
10 14 (24) [6] AMC 164 (555) [960] 14 (60) [24] 188 (493) [213] 248 (479) [693] 175 (456) [707] 9 (21) [5] 6 (8) [10] 17 (23) [14] 120 (524) [759] 8 (18) [8] 24 (68) [21] 14 (24) [23] 15 (23) [12] 158 (528) [714] 6 (17) [8] ILLINOIS 24 (81) [12] NBC TOWER COLUMBUS DR 29 (36) [60] ARK DR 0 (3) [4] 1 (4) [2] NEW CITY VIEW CONDOS 18 (23) [7] SITE 1 (1) [0] NORTH WATER 3 (8) [5] 68 (118) [455] 173 (426) [169] 254 (425) [603] 166 (264) [277] 4 (5) [4] ER WATER 2 (10) [7] 16 (40) [57] 11 (27) [19] 35 (32) [33] 32 (49) [51] 11 (2) [6] 8 (18) [62] SHERATON 3 (1) [0] LEGEND 00 - TRAFFIC SIGNAL - EDERIAN VOLUMES 00 - BICYCLE VOLUMES 00 - WEEKDAY MORNING EAK HOUR (00) - WEEKDAY EVENING EAK HOUR [00] - SATURDAY MIDDAY EAK HOUR ROJECT: TITLE: ROJECT NO: ARK DRIVE/WATER REET MIXED-USE DEVELOMENT CHICAGO, ILLINOIS EXIING EDERIAN AND BICYCLE VOLUMES FIGURE NO: 5
11 ARK DR 40% (40%) 35% (25%) AMC 30% (20%) 35% (35%) ILLINOIS NBC TOWER COLUMBUS DR NEW CITY VIEW CONDOS SITE NORTH WATER ER WATER 30% (20%) 30% (20%) SHERATON LEGEND - TRAFFIC SIGNAL 00 (00) - - ROJECT: TITLE: ROJECT NO: ARK DRIVE/WATER REET MIXED-USE DEVELOMENT CHICAGO, ILLINOIS EIMATED DIRECTIONAL DIRIBUTION FIGURE NO: 6
12 Site Traffic Generation The peak hour vehicle traffic that will be generated by the development was estimated as follows. The Apartment (Land-Use Code 220) trip rates provided in the Institute of Transportation Engineers (ITE) Trip Generation Manual, 8 th Edition. However, rates provided in the Trip Generation Manual are based on suburban data where the primary mode of transportation is the automobile. Therefore, given the location of the development within a dense, urban area and its proximity to alternative modes of transportation, the rates provided in the Trip Generation Manual were reduced by 67 percent. The hotel trip generation surveys conducted in the River North and Streeterville neighborhoods by the arsons Transportation Group for the City of Chicago. (Copies of the rates are provided in the Appendix.) These rates take into account alternative modes of transportation for travel to and from the development and interactivity between mixed-use developments. Table 1 shows the estimated peak hour traffic to be generated by the proposed development. Table 1 ROJECTED SITE-GENERATED TRAFFIC VOLUMES Weekday Morning eak Hour Weekday Evening eak Hour Saturday Midday eak Hour Land Use In Out In Out In Out Apartments (400 units) Hotel (400 rooms) Total Notes: The apartment trip estimates were based on the Apartment (Land-Use Code 220) rates provided in the ITE Trip Generation Manual, 8 th Edition and reduced by 67 percent to account for other modes of transportation. The hotel trip estimates were based trip generation surveys conducted in the River North and Streeterville neighborhoods by the arsons Transportation Group for the City of Chicago. It should be noted that the site contains a surface parking lot that is currently generating traffic. Therefore, the traffic projected to be generated by the proposed development will not be all new traffic to the area as it will be replacing the existing parking lot. However, to provide a worst case analysis, the total development-generated trips were not reduced to account for the traffic generated by the existing public parking lot. rojected Traffic Volumes The estimated peak hour traffic volumes that will be generated by the proposed development were assigned to the street system in accordance with the previously described directional distribution. Figure 7 illustrates the development generated traffic volumes. 12
13 1 (3) [3] 29 (40) [26] AMC 30 (37) [26] 1 (2) [1] 22 (25) [15] 2 (6) [4] 7 (23) [14] 54 (60) [42] 37 (36) [22] 25 (25) [15] 19 (34) [21] 22 (12) [12] ILLINOIS NBC TOWER COLUMBUS DR 30 (47) [26] ARK 52 (49) [36] DR 28 (32) [18] 28 (36) [20] 22 (12) [12] 19 (16) [14] SITE 19 (34) [21] 2 (8) [6] CITY VIEW CONDOS NORTH WATER 2 (5) [4] 2 (6) [4] 19 (22) [16] 22 (24) [15] 18 (19) [12] 28 (36) [20] 2 (11) [6] ER WATER 18 (17) [13] 3 (10) [7] 8 (4) [4] 18 (17) [13] 9 (4) [4] 12 (7) [7] NEW LOWER WATER 19 (16) [14] SHERATON 2 (8) [6] LEGEND - TRAFFIC SIGNAL 00 - WEEKDAY MORNING EAK HOUR (00) - WEEKDAY EVENING EAK HOUR [00] - SATURDAY MIDDAY EAK HOUR ROJECT: TITLE: ROJECT NO: ARK DRIVE/WATER REET MIXED-USE DEVELOMENT CHICAGO, ILLINOIS SITE-GENERATED EAK HOUR VOLUMES FIGURE NO: 7
14 In addition to the development-generated traffic, the study also included the traffic that will be generated by the following developments proposed in the area. The proposed apartment development to be located directly north of the subject site. The proposed apartment development to be located on the east side of eshtigo Court between Grand Avenue and Illinois Street. The second residential tower proposed for the arkview West development to be located on the west side of eshtigo Court between Grand Avenue and Illinois Street. The proposed Northwestern Memorial Hospital arking Garage to be located between Ontario Street and Ohio Street just east of the site. The proposed apartment development to be located on the east side of McClurg Court between Grand Avenue and Ohio Street. Further, to account for other growth in the area, the existing volumes were increased by ten percent. Figure 8 shows the total peak hour volumes which includes the existing traffic volumes, the development-generated traffic volumes and other growth projected in the area. Traffic Analysis Traffic analyses were performed for the intersections within the study area to determine the operation of the existing street system, evaluate the impact of the proposed development, and determine the ability of the existing street system to accommodate projected traffic demands. Analyses were performed for the existing and the projected traffic volumes. The traffic analyses were performed using Synchro 7 computer software, which is based on the methodologies outlined in the Transportation Research Board s Highway Capacity Manual (HCM), The ability of an intersection to accommodate traffic flow is expressed in terms of level of service, which is assigned a letter grade from A to F based on the average control delay experienced by vehicles passing through the intersection. Control delay is that portion of the total delay attributed to the traffic signal or stop sign control operation and includes initial deceleration delay, queue move-up time, stopped delay, and final acceleration delay. Level of Service A is the highest grade (best traffic flow and least delay), Level of Service E represents saturated or at-capacity conditions, and Level of Service F is the lowest grade (oversaturated conditions, extensive delays). For two-way stop controlled (TWSC) intersections, levels of service are only calculated for the approaches controlled by a stop sign (not for the intersection as a whole). The Highway Capacity Manual definitions for levels of service and the corresponding control delay for signalized intersections and unsignalized intersections are shown in the Appendix. The results of the capacity analysis are summarized in Table 2 for the existing traffic volumes and Table 3 for the projected traffic volumes. 14
15 131 (189) [64] 1084 (1640) AMC 1077 (1624) [1302] ILLINOIS 819 (796) [554] 238 (291) [336] NBC TOWER SHERATON CITY VIEW CONDOS 65 (27) [41] 42 (68) [41] ROJECT: TITLE: ROJECT NO: FIGURE NO: 8 98 (94) [58] 14 (26) [15] 15 (18) [28] 17 (18) [17] 22 (42) [28] 46 (105) [33] 24 (20) [39] 135 (48) [42] 107 (64) [13] 974 (1095) [377] 73 (47) [44] 24 (40) [28] 70 (51) [63] 29 (45) [31] 50 (120) [35] 42 (47) [10] 78 (60) [55] 79 (107) [60] 32 (56) [60] 39 (31) [54] 111 (97) [71] 77 (44) [56] 983 (1170) [570] 23 (63) [80] 135 (89) [95] 3 (12) [8] 18 (17) [13] 19 (16) [14] 2 (8) [6] 38 (45) [33] 52 (49) [36] 28 (32) [18] 28 (36) [20] 22 (12) [12] 19 (34) [21] 75 (56) [25] 264 (481) [152] 859 (963) [350] 246 (235) [150] 703 (1226) [811] NORTH WATER 87 (74) [143] 60 (57) [45] [1205] 103 (112) [92] ER WATER SITE LOWER WATER LEGEND 00 (00) [00] - TRAFFIC SIGNAL - WEEKDAY MORNING EAK HOUR - WEEKDAY EVENING EAK HOUR - SATURDAY MIDDAY EAK HOUR ARK DRIVE/WATER REET MIXED-USE DEVELOMENT CHICAGO, ILLINOIS 101 (123) [50] 61 (52) [60] NEW COLUMBUS DR ARK DR 94 (90) [46] TOTAL EAK HOUR VOLUMES
16 Table 2 CAACITY ANALYSIS RESULTS EXIING TRAFFIC CONDITIONS Weekday A.M. eak Hour Weekday.M. eak Hour Saturday Midday eak Hour Intersection LOS Delay LOS Delay LOS Delay Illinois Street and Columbus Drive B 18.2 D 53.1 B 18.1 Illinois Street and ark Drive B 12.0 C 20.8 E 38.7 Illinois Street and New Street B 12.8 C 21.8 C 24.2 Upper Water Street and Columbus Drive B 13.9 B 12.6 B 11.5 Upper Water Street and ark Drive A 9.2 A 9.0 A 9.0 Lower Water Street and New Street A 7.8 A 7.8 A 7.4 LOS - Level of Service Delay - Measured in Seconds Table 3 CAACITY ANALYSIS RESULTS ROJECTED TRAFFIC CONDITIONS Weekday A.M. eak Hour Weekday.M. eak Hour Saturday Midday eak Hour Intersection LOS Delay LOS Delay LOS Delay Illinois Street and Columbus Drive C 23.0 E 78.1 C 21.0 Illinois Street and ark Drive B 14.2 D 30.8 F 80.7 Illinois Street and New Street B 14.4 D 27.4 D 29.9 Upper Water Street and Columbus Drive B 16.6 B 14.7 B 12.8 Upper Water Street and ark Drive A 9.8 A 9.8 A 9.4 Lower Water Street and New Street A 8.1 A 8.1 A 7.6 ark Drive and Outbound Access Drive A 9.3 A 9.3 A 9.6 Lower Water Street and Access Drive 1 B 10.1 A 9.6 A 9.2 LOS - Level of Service Delay - Measured in Seconds 1 To provide a worst case analysis, it was assumed all of the parking garage traffic uses one access drive on Lower Water Street. 16
17 Evaluation of the Street Operations The results of the capacity analyses show that all of the intersections in the study area are generally operating at an acceptable level of service under existing conditions. With the addition of the development traffic and the traffic from other proposed developments in the area indicated earlier as well as the assumed growth in background traffic, all of the intersections are generally projected to continue to operate at an acceptable level of service. The capacity analyses indicated that some queuing and delays are currently experienced on some approaches as well as certain individual movements, particularly on the north-south streets. However, field observation and the capacity analyses indicate that the queuing and delays are typically not excessive. The following outlines several of the factors that are contributing to the less than desirable operation on some approaches under existing conditions. 1. The north-south streets receive a limited amount of green time per signal cycle. This is because Grand Avenue and Illinois Street form a major one-way pair that provide access to/from the regional freeway system. As such, the signal timings at many of the intersections in the study area have been set to facilitate the east-west traffic movement. 2. The close spacing of the east-west streets within the area limits the available stacking (storage) distance between the intersections on the north-south streets. As a result, the queuing that occurs on the north-south streets, which is compounded by the limited green time, occasionally extends beyond mid-block access drives and downstream intersections, which contribute to the congestion and delay experienced during the peak periods at some of the intersection approaches on these streets. 3. Due to the high concentration of pedestrian movements in the area, particularly on weekends, the vehicle capacity of the intersections is limited. Turning vehicles yielding to pedestrian traffic in the crosswalks reduces the capacity of the intersections. It should be noted that the pedestrian and bicycle activity along the Lower Lake Shore Drive corridor will be significantly reduced with the proposed grade separation of the lakefront path over the Chicago River and Lower Lake Shore Drive. It should be noted that, during the weekday evening peak period, the Illinois Street/Columbus Drive intersection is operating on the threshold between a Level of Service D and E and will operate at a Level of Service E assuming the total projected traffic volumes. This is due to the poor operation of Illinois Street which has a very high volume of through and right-turn movements during the evening peak period. Currently, both of the Columbus Drive approaches are operating at a good level of service. In order to enhance the operation of the Illinois Street approach and its intersection with Columbus Drive, it is recommended that the City should consider adjusting the signal timings at this intersection. 17
18 Further, the stop sign controlled approach of ark Drive at its intersection with Illinois Street is currently and projected to continue to operate at a poor level of service during the Saturday midday peak period. This is primarily due to the high volume of pedestrians traversing along Illinois Street and crossing ark Drive as well as the significant growth projected in the area. The traffic on ark Drive can and will be able to turn onto Illinois Street. However, during the Saturday peak period, this approach may experience some additional delay and queuing. Transportation Sustainability Recommendations The following summarizes measures to be implemented by the development and/or recommendations to further minimize the impact of the development, foster alternative modes of transportation other than the automobile, and to enhance pedestrian/bicycle safety. Bike racks are proposed to be provided within the development. One to two parking spaces within the parking garage should be reserved for car-sharing vehicles. CDOT and the developer should consider implementing the following pedestrian safety improvements. The Columbus Drive/Upper Water Street traffic signal should be upgraded with countdown pedestrian signals for Upper Water Street pedestrians. The existing crosswalks at the New Street/Lower Water Street and Upper Water Street/ark Drive intersections are mostly faded and should be restriped with international style crosswalks. Site Access Access to the parking garage is to be provided via three access drives located on Lower Water Street. The easternmost access drive will provide inbound only access to the lower level parking (145 spaces). This access drive will provide one inbound lane. The middle access drive will be located adjacent to the easternmost access drive and will provide inbound and outbound access to the upper level parking (98 spaces). This access drive will provide one inbound lane and one outbound lane with the outbound lane under stop sign control. The westernmost access drive will provide outbound access to the lower level parking (145 spaces). This access drive will provide one outbound lane that will be under stop sign control. 18
19 The hotel drop-off/pick-up circle is proposed to be provided along the south end of the site with access provided via two access drives on ark Drive. Access to the one-way northbound drop-off/pick-up court will be provided via one inbound (south) access drive and one outbound (north) access drive. As proposed, the drop-off/pick-up circle will provide two northbound lanes and curb side stacking for approximately eight to ten vehicles. The vehicle stacking will be sufficient to accommodate the hotel peak demand if the operation, particularly the valet service, is run efficiently. During larger functions at the hotel, a sufficient number of valets should be provided to accommodate the additional drop-off/pick-up demand. The apartment drop-off/pick-up lane is proposed to be provided along the northeast end of the site via a drop-off/pick-up lane on Upper Water Street that will provide spacing for approximately three vehicles. Access to the hotel loading docks and to the apartment loading docks will be provided on the north side of Lower Water Street just west of New Street. It should be noted that all loading, including parcel deliveries, will be made via the loading docks. Lower Water Street is wide enough to accommodate the truck turning movements into and out of the loading docks. Exhibits demonstrating the truck movements to/from the loading docks are provided in the Appendix. It is recommended that consideration be given to restricting truck deliveries to the hotel to and from Lower Water Street. roposed Valet Operation As proposed, the hotel valet service will park the majority of the vehicles in the upper level of the parking garage to be provided within the development. The travel routes that the valet service will use, as assumed in the traffic study, to travel between the hotel drop-off/pick-up area and the parking garage are as follows. To the arking Garage: ark Avenue to Illinois Street to New Street to Lower Water Street to the parking garage. From the arking Garage: Lower Water Street to St. Clair Street to Illinois Street to ark Avenue to the hotel drop-off/pick-up area. The impact of the valet operation will be minimized due to the following. The routes to/from the parking garage will occur along lower volume local streets except for a short stretch along Illinois Street. Further, the routes require only right-turn movements at the various intersections. The hotel is proposing to provide a valet station in the garage that will allow patrons to pick up their vehicle directly from the parking garage. 19
20 ark Drive Taxi Stand A designated (signed) taxi stand is currently provided on the west side of ark Drive that extends from approximately 100 feet north of the Upper Water Street northern curb to approximately 300 feet north of the Upper Water Street northern curb. The inbound access drive to the hotel drop-off/pick-up circle is proposed to be located approximately 90 to 100 feet north of the Upper Water Street northern curb. It can be seen that the front of the designated (signed) taxi stand is located at the inbound access drive. As such, the existing designated taxi stand will be able to serve the proposed hotel as well as the Sheraton Hotel. In order to accommodate additional taxis, it is recommended that the designated taxi stand be extended to 100 feet south of the Illinois Street southern curb. This will extend the taxi stand from approximately 200 to 300 feet. Further, the extension of the taxi stand will not result in the loss of on-street parking as the western curb lane of ark Drive is currently signed for no parking between Illinois Street and the designated taxi stand. It should be noted that taxis often stack along ark Drive outside of the designated area between Upper Water Street and the southern portion of the taxis stand. It is recommended that taxis stack within the expanded designated area such that both Sheraton Hotel and the proposed hotel can utilize the taxis efficiently. Conclusion Based on the preceding analyses and recommendations, the following conclusions have been made. Accessibility to and from the area is enhanced by the various alternative modes of transportation serving the area as summarized below. The area is served by the CTA Red (Howard/Dan Ryan) rapid transit line which has a local stop ½ mile from the site. In addition, five bus routes serve the immediate area and all have stops that are two to three blocks from the site. Lastly, on-street bike lanes are provided along Grand Avenue and Illinois Street providing access to the Lake Front Trail as well as other bicycle streets. The amount of new traffic generated by the proposed development will be reduced due to (1) the proximity of development within the downtown area and the alternative modes of transportation serving the area and (2) the fact that the development is replacing an existing surface parking lot. The development-generated traffic can be accommodated efficiently without significant impact to the external street system. All of the intersections within the study limits are generally projected to operate at acceptable levels of service with the addition of the development generated traffic. 20
21 CDOT and the developer should consider installing the following pedestrian safety improvements: (1) upgrade the Columbus Drive/Upper Water Street traffic signal to provide countdown pedestrian signals for Upper Water Street and (2) restripe the intersections of New Street/Lower Water Street and ark Drive/Upper Water Street with international style crosswalks. The access system will be adequate to serve the traffic that will be generated by the proposed development. The results of the capacity analyses show that the access drives will provide orderly and efficient access with minimal impact on the street system Nelson ark Drive/Water Street Mixed-Use Development in Chicago February Revised April maw lra 21
22 Appendix
23 LEVEL OF CRITERIA SIGNALIZED INTERSECTIONS Delay per Vehicle Level of Service Interpretation (seconds) A B C D E Very short delay, with extremely favorable progression. Most vehicles arrive during the green phase and do not stop at all. Good progression, with more vehicles stopping than for Level of Service A, causing higher levels of average delay. Light congestion, with individual cycle failures beginning to appear. Number of vehicles stopping is significant at this level though many still pass through the intersection without stopping. Congestion is more noticeable, with longer delays resulting from combination of unfavorable progression, long cycle lengths, or high V/C ratios. Many vehicles stop and the proportion of vehicles not stopping declines. High delays result from poor progression, high cycle lengths and high V/C ratios >10 and 20.0 >20 and 35 >35 and 55 >55 and 80 F Unacceptable delay occurring, with oversaturation. >80.0 LEVEL OF CRITERIA UNSIGNALIZED INTERSECTIONS Level of Service Average Total Delay (SEC/VEH) A 10 B C D E >10 and 15 >15 and 25 >25 and 35 >35 and 50 Source: Highway Capacity Manual, F >50
24 Census Track Legend: Boundaries State '10 County Features Major Road Street Stream/Waterbody Your Selections Your Selections Items in grey text are not visible at this zoom level 1 of 1 04/04/2012
25 EXIING 58 LOADING DOCK RS/F AFF T EL: +8 ROOM EU 0.00 RESID. TRASH GENERAL & LANDSCAE ORAGE SF LOADING +14-4" ATS ROOM LOADING DOCK S 3.00 WB-50 Tractor Width Trailer Width Tractor Track Trailer Track feet : 8.00 Lock to Lock Time : 8.50 Steering Angle : 8.00 Articulating Angle :8.50 :6.0 : 17.7 : YARD SELF CONTAINED COMACTOR W/ 2 YARD CHARGE BOX (25-0" x 8-0") TO TO 1 2 IN EL: ARKING ENTRY LOWER E. NORTH WATER REET 9575 West Higgins Road, Suite 400 Rosemont, Illinois : (847) F: (847) Kenig,Lindgren,O Hara,Aboona,Inc. ROJECT # DESIGNED DRAWN CHECKED DATE - 4/25/2012 SCALE: 1" = 20 ARK DRIVE/WATER REET MIXED-USE DEVELOMENT CHICAGO, ILLINOIS LOADING DOCK 1 OF 2 INBOUND FROM WE WB-50 TRUCK FIGURE NO. 1
26 EXIING 58 LOADING DOCK RS/F AFF T EL: +8 ROOM EU 0.00 RESID. TRASH GENERAL & LANDSCAE ORAGE SF LOADING +14-4" ATS ROOM LOADING DOCK S 3.00 WB-50 Tractor Width Trailer Width Tractor Track Trailer Track feet : 8.00 Lock to Lock Time : 8.50 Steering Angle : 8.00 Articulating Angle :8.50 :6.0 : 17.7 : YARD SELF CONTAINED COMACTOR W/ 2 YARD CHARGE BOX (25-0" x 8-0") TO TO 1 2 IN EL: ARKING ENTRY LOWER E. NORTH WATER REET 9575 West Higgins Road, Suite 400 Rosemont, Illinois : (847) F: (847) Kenig,Lindgren,O Hara,Aboona,Inc. ROJECT # DESIGNED DRAWN CHECKED DATE - 4/25/2012 SCALE: 1" = 20 ARK DRIVE/WATER REET MIXED-USE DEVELOMENT CHICAGO, ILLINOIS LOADING DOCK 2 OF 2 INBOUND FROM WE WB-50 TRUCK FIGURE NO. 2
27 ARKING EXHAU LOADING DOCK RS/F T EL: EU 3.00 WB-50 Tractor Width Trailer Width Tractor Track Trailer Track EL: +14-4" OEN TO feet BELOW : 8.00 Lock to Lock Time : 8.50 Steering Angle : 8.00 Articulating Angle :8.50 OUT EL: +14-4" :6.0 : 17.7 KITCHEN : 70.0 EXHAU AND SCRUBBER +13-0" GENERAL & LANDSCAE ORAGE SF LOADING YARD SELF CONTAINED COMACTOR W/ 2 YARD CHARGE BOX (25-0" x 8-0") +14-4" ATS ROOM TO TO RESIDEN LOADING 1 OUT IN IN EL: ARKING EXIT ARKING ENTRY/ EXIT ARKING ENTRY RESIDENT SERVIC ACCES LOWER E. NORTH WATER REET 9575 West Higgins Road, Suite 400 Rosemont, Illinois : (847) F: (847) Kenig,Lindgren,O Hara,Aboona,Inc. ROJECT # DESIGNED DRAWN CHECKED DATE - 4/25/2012 SCALE: 1" = 20 ARK DRIVE/WATER REET MIXED-USE DEVELOMENT CHICAGO, ILLINOIS LOADING DOCK 1 OF 2 OUTBOUND TO WE WB-50 TRUCK FIGURE NO. 3
28 ARKING EXHAU LOADING DOCK RS/F T EL: EU 3.00 WB-50 Tractor Width Trailer Width Tractor Track Trailer Track EL: +14-4" OEN TO feet BELOW : 8.00 Lock to Lock Time : 8.50 Steering Angle : 8.00 Articulating Angle :8.50 OUT EL: +14-4" :6.0 : 17.7 KITCHEN : 70.0 EXHAU AND SCRUBBER +13-0" GENERAL & LANDSCAE ORAGE SF LOADING YARD SELF CONTAINED COMACTOR W/ 2 YARD CHARGE BOX (25-0" x 8-0") +14-4" ATS ROOM TO TO RESIDEN LOADING 1 OUT IN IN EL: ARKING EXIT ARKING ENTRY/ EXIT ARKING ENTRY RESIDENT SERVIC ACCES LOWER E. NORTH WATER REET 9575 West Higgins Road, Suite 400 Rosemont, Illinois : (847) F: (847) Kenig,Lindgren,O Hara,Aboona,Inc. ROJECT # DESIGNED DRAWN CHECKED DATE - 4/25/2012 SCALE: 1" = 20 ARK DRIVE/WATER REET MIXED-USE DEVELOMENT CHICAGO, ILLINOIS LOADING DOCK 2 OF 2 OUTBOUND TO WE WB-50 TRUCK FIGURE NO. 4
29 EXIING TRASH GENERAL & LANDSCAE ORAGE SF LOADING +14-4" ATS ROOM LOADING DOCK S YARD SELF CONTAINED COMACTOR W/ 2 YARD CHARGE BOX (25-0" x 8-0") TO TO 1 2 IN EL: ARKING ENTRY LOWER E. NORTH WATER REET SU Width Track Lock to Lock Time Steering Angle feet : 8.00 : 8.00 : 6.0 : West Higgins Road, Suite 400 Rosemont, Illinois : (847) F: (847) Kenig,Lindgren,O Hara,Aboona,Inc. ROJECT # DESIGNED DRAWN CHECKED DATE - 4/25/2012 SCALE: 1" = 20 ARK DRIVE/WATER REET MIXED-USE DEVELOMENT CHICAGO, ILLINOIS LOADING DOCK 1 OF 2 INBOUND FROM EA SU TRUCK FIGURE NO. 1
30 EXIING TRASH GENERAL & LANDSCAE ORAGE SF LOADING +14-4" ATS ROOM LOADING DOCK S YARD SELF CONTAINED COMACTOR W/ 2 YARD CHARGE BOX (25-0" x 8-0") TO TO 1 2 IN EL: ARKING ENTRY LOWER E. NORTH WATER REET SU Width Track Lock to Lock Time Steering Angle feet : 8.00 : 8.00 : 6.0 : West Higgins Road, Suite 400 Rosemont, Illinois : (847) F: (847) Kenig,Lindgren,O Hara,Aboona,Inc. ROJECT # DESIGNED DRAWN CHECKED DATE - 4/25/2012 SCALE: 1" = 20 ARK DRIVE/WATER REET MIXED-USE DEVELOMENT CHICAGO, ILLINOIS LOADING DOCK 2 OF 2 INBOUND FROM EA SU TRUCK FIGURE NO. 2
31 EXIING TRASH GENERAL & LANDSCAE ORAGE SF LOADING +14-4" ATS ROOM LOADING DOCK S YARD SELF CONTAINED COMACTOR W/ 2 YARD CHARGE BOX (25-0" x 8-0") TO TO 1 2 IN EL: ARKING ENTRY LOWER E. NORTH WATER REET SU Width Track Lock to Lock Time Steering Angle feet : 8.00 : 8.00 : 6.0 : West Higgins Road, Suite 400 Rosemont, Illinois : (847) F: (847) Kenig,Lindgren,O Hara,Aboona,Inc. ROJECT # DESIGNED DRAWN CHECKED DATE - 4/25/2012 SCALE: 1" = 20 ARK DRIVE/WATER REET MIXED-USE DEVELOMENT CHICAGO, ILLINOIS LOADING DOCK 1 OF 2 INBOUND FROM WE SU TRUCK FIGURE NO. 3
32 EXIING TRASH GENERAL & LANDSCAE ORAGE SF LOADING +14-4" ATS ROOM LOADING DOCK S YARD SELF CONTAINED COMACTOR W/ 2 YARD CHARGE BOX (25-0" x 8-0") TO TO 1 2 IN EL: ARKING ENTRY LOWER E. NORTH WATER REET SU Width Track Lock to Lock Time Steering Angle feet : 8.00 : 8.00 : 6.0 : West Higgins Road, Suite 400 Rosemont, Illinois : (847) F: (847) Kenig,Lindgren,O Hara,Aboona,Inc. ROJECT # DESIGNED DRAWN CHECKED DATE - 4/25/2012 SCALE: 1" = 20 ARK DRIVE/WATER REET MIXED-USE DEVELOMENT CHICAGO, ILLINOIS LOADING DOCK 2 OF 2 INBOUND FROM WE SU TRUCK FIGURE NO. 4
33 EXIING TRASH GENERAL & LANDSCAE ORAGE SF LOADING +14-4" ATS ROOM LOADING DOCK S YARD SELF CONTAINED COMACTOR W/ 2 YARD CHARGE BOX (25-0" x 8-0") TO TO 1 2 IN IN EL: KING ARKING RY/ ENTRY IT LOWER E. NORTH WATER REET SU Width Track Lock to Lock Time Steering Angle feet : 8.00 : 8.00 : 6.0 : West Higgins Road, Suite 400 Rosemont, Illinois : (847) F: (847) Kenig,Lindgren,O Hara,Aboona,Inc. ROJECT # DESIGNED DRAWN CHECKED DATE - 4/25/2012 SCALE: 1" = 20 ARK DRIVE/WATER REET MIXED-USE DEVELOMENT CHICAGO, ILLINOIS LOADING DOCK 1 OF 2 OUTBOUND TO EA SU TRUCK FIGURE NO. 5
34 EXIING TRASH GENERAL & LANDSCAE ORAGE SF LOADING +14-4" ATS ROOM LOADING DOCK S YARD SELF CONTAINED COMACTOR W/ 2 YARD CHARGE BOX (25-0" x 8-0") TO TO 1 2 IN EL: ARKING ENTRY LOWER E. NORTH WATER REET SU Width Track Lock to Lock Time Steering Angle feet : 8.00 : 8.00 : 6.0 : West Higgins Road, Suite 400 Rosemont, Illinois : (847) F: (847) Kenig,Lindgren,O Hara,Aboona,Inc. ROJECT # DESIGNED DRAWN CHECKED DATE - 4/25/2012 SCALE: 1" = 20 ARK DRIVE/WATER REET MIXED-USE DEVELOMENT CHICAGO, ILLINOIS LOADING DOCK 2 OF 2 OUTBOUND TO EA SU TRUCK FIGURE NO. 6
35 EXIING TRASH GENERAL & LANDSCAE ORAGE SF LOADING +14-4" ATS ROOM LOADING DOCK S YARD SELF CONTAINED COMACTOR W/ 2 YARD CHARGE BOX (25-0" x 8-0") TO TO 1 2 IN EL: ARKING ENTRY LOWER E. NORTH WATER REET SU Width Track Lock to Lock Time Steering Angle feet : 8.00 : 8.00 : 6.0 : West Higgins Road, Suite 400 Rosemont, Illinois : (847) F: (847) Kenig,Lindgren,O Hara,Aboona,Inc. ROJECT # DESIGNED DRAWN CHECKED DATE - 4/25/2012 SCALE: 1" = 20 ARK DRIVE/WATER REET MIXED-USE DEVELOMENT CHICAGO, ILLINOIS LOADING DOCK 1 OF 2 OUTBOUND TO WE SU TRUCK FIGURE NO. 7
36 EXIING TRASH GENERAL & LANDSCAE ORAGE SF LOADING +14-4" ATS ROOM LOADING DOCK S YARD SELF CONTAINED COMACTOR W/ 2 YARD CHARGE BOX (25-0" x 8-0") TO TO 1 2 IN EL: ARKING ENTRY LOWER E. NORTH WATER REET SU Width Track Lock to Lock Time Steering Angle feet : 8.00 : 8.00 : 6.0 : West Higgins Road, Suite 400 Rosemont, Illinois : (847) F: (847) Kenig,Lindgren,O Hara,Aboona,Inc. ROJECT # DESIGNED DRAWN CHECKED DATE - 4/25/2012 SCALE: 1" = 20 ARK DRIVE/WATER REET MIXED-USE DEVELOMENT CHICAGO, ILLINOIS LOADING DOCK 2 OF 2 OUTBOUND TO WE SU TRUCK FIGURE NO. 8
Michael A. Werthmann, PE, PTOE Principal
9575 West Higgins Road, Suite 400 Rosemont, Illinois 60018 p: 847-518-9990 f: 847-518-9987 MEMORANDUM TO: FROM: Brian Lorenc GHB-630, LLC Michael A. Werthmann, E, TOE rincipal Luay R. Aboona, E rincipal
More informationTraffic Study North Shore School District 112
Traffic Study North Shore School District 112 Proposed Expansion of Northwood Junior High School Prepared By: May 1, 2015 1. Introduction Kenig, Lindgren, O Hara, Aboona, Inc. (KLOA, Inc.) has been retained
More informationTRAFFIC IMPACT ANALYSIS
TRAFFIC IMPACT ANALYSIS FOR THE CHAMPAIGN UNIT#4 SCHOOL DISTRICT PROPOSED HIGH SCHOOL (SPALDING PARK SITE) IN THE CITY OF CHAMPAIGN Final Report Champaign Urbana Urbanized Area Transportation Study 6/24/2014
More informationMagnolia Place. Traffic Impact Analysis. Prepared for: City of San Mateo. Prepared by: Hexagon Transportation Consultants, Inc.
Magnolia Place Traffic Impact Analysis Prepared for: City of San Mateo Prepared by: Hexagon Transportation Consultants, Inc. Updated January 4, 2010 Table of Contents 1. Introduction...1 2. Existing Conditions...6
More informationU.S. Equities Realty. Luay R. Aboona, PE Principal. Traffic and Parking Evaluation Fourth Presbyterian Church of Chicago Chicago, Illinois
9575 West Higgins Road, Suite 100 Rosemont, Illinois 60018 p: 847-518-9990 f: 847-518-9987 MEMORANDUM TO: FROM: Suzanne Kahle U.S. Equities Realty Kelly K. Conolly, PE Consultant Luay R. Aboona, PE Principal
More information5858 N COLLEGE, LLC N College Avenue Traffic Impact Study
5858 N COLLEGE, LLC nue Traffic Impact Study August 22, 2016 Contents Traffic Impact Study Page Preparer Qualifications... 1 Introduction... 2 Existing Roadway Conditions... 5 Existing Traffic Conditions...
More informationHENDERSON DEVELOPMENT 213, 217, 221, 221 ½, 223 HENDERSON AVENUE and 65 TEMPLETON STREET OTTAWA, ONTARIO TRANSPORTATION OVERVIEW.
HENDERSON DEVELOPMENT 213, 217, 221, 221 ½, 223 HENDERSON AVENUE and 65 TEMPLETON STREET OTTAWA, ONTARIO TRANSPORTATION OVERVIEW Prepared for: 2294170 Ontario Inc. February 2, 2017 117-652 Report_1.doc
More informationTRAFFIC IMPACT STUDY CRITERIA
Chapter 6 - TRAFFIC IMPACT STUDY CRITERIA 6.1 GENERAL PROVISIONS 6.1.1. Purpose: The purpose of this document is to outline a standard format for preparing a traffic impact study in the City of Steamboat
More informationAppendix C. NORTH METRO STATION AREA TRAFFIC IMPACT STATEMENT 88th Avenue Station
Appendix C NORTH METRO STATION AREA TRAFFIC IMPACT STATEMENT 88th Avenue Station Prepared for: Regional Transportation Department and URS Corporation as part of the North Metro EIS David Evans and Associates,
More informationTraffic Circulation Study for Neighborhood Southwest of Mockingbird Lane and Airline Road, Highland Park, Texas
ARIZONA TEXAS NEW MEXICO OKLAHOMA February 13, 2015 Mr. Meran Dadgostar P.E., R.S. Town of Highland Park 4700 Drexel Dr. Highland Park, Texas 75205 Re: Traffic Circulation Study for Neighborhood Southwest
More informationTRAFFIC ASSESSMENT River Edge Colorado
TRAFFIC ASSESSMENT River Edge Colorado Submitted by: Fehr & Peers 621 17th Street, Ste. 231 Denver, CO 8293 (33) 296-43 December, 21 App. M-2 Traffic Assessment River Edge Colorado December 21 TABLE OF
More informationTransportation Impact Study for Abington Terrace
Transportation Impact Study for Abington Terrace Abington Township, Montgomery County, PA Sandy A. Koza, P.E., PTOE PA PE License Number PE059911 Prepared by McMahon Associates, Inc. 425 Commerce Drive,
More informationHenderson Avenue Mixed-Use Development
Zoning Case: Z145-3 Traffic Impact Analysis Henderson Avenue Mixed-Use Development Dallas, TX October 26 th, 216 Kimley-Horn and Associates, Inc. Dallas, Texas Project #644827 Registered Firm F-928 Traffic
More informationD.13 Transportation and Traffic
This section addresses transportation and traffic issues and impacts related to the Proposed Project. Section D.13.1 provides a description of the affected environment for the Proposed Project. Applicable
More informationShockoe Bottom Preliminary Traffic and Parking Analysis
Shockoe Bottom Preliminary Traffic and Parking Analysis Richmond, Virginia August 14, 2013 Prepared For City of Richmond Department of Public Works Prepared By 1001 Boulders Pkwy Suite 300, Richmond, VA
More informationOFFICE/RETAIL DEVELOPMENT 1625 BANK STREET OTTAWA, ONTARIO TRANSPORTATION BRIEF. Prepared for: Canada Inc.
OFFICE/RETAIL DEVELOPMENT 1625 BANK STREET OTTAWA, ONTARIO TRANSPORTATION BRIEF Prepared for: 9402209 Canada Inc. December 15, 2015 115-625 Report_2.doc D. J. Halpenny & Associates Ltd. Consulting Transportation
More informationMEDICAL/OFFICE BUILDING 1637 BANK STREET OTTAWA, ONTARIO TRANSPORTATION OVERVIEW. Prepared for:
MEDICAL/OFFICE BUILDING 1637 BANK STREET OTTAWA, ONTARIO TRANSPORTATION OVERVIEW Prepared for: 2434984 Ontario Inc. 13-5510 Canotek Road Ottawa, Ontario K1J 9J5 June 4, 2015 115-613 Report_2.doc D. J.
More informationHighway 111 Corridor Study
Highway 111 Corridor Study June, 2009 LINCOLN CO. HWY 111 CORRIDOR STUDY Draft Study Tea, South Dakota Prepared for City of Tea Sioux Falls Metropolitan Planning Organization Prepared by HDR Engineering,
More informationVIVA RETIREMENT COMMUNITIES OAKVILLE TRAFFIC IMPACT STUDY
VIVA RETIREMENT COMMUNITIES OAKVILLE TRAFFIC IMPACT STUDY VIVA RETIREMENT COMMUNITIES OAKVILLE TRAFFIC IMPACT STUDY DECEMBER 2012 READ, VOORHEES & ASSOCIATES TORONTO, ONTARIO Read, Voorhees & Associates
More informationHarrah s Station Square Casino
Transportation Analysis Harrah s Station Square Casino Pittsburgh, Pennsylvania Submitted To: City of Pittsburgh and Pennsylvania Gaming Control Board Prepared By: DKS Associates GAI Consultants December
More informationTraffic Impact Analysis Chatham County Grocery Chatham County, NC
Chatham County Grocery Chatham County, NC TABLE OF CONTENTS 1. INTRODUCTION... 1 1.1. Location and Study Area... 1 1.2. Proposed Land Use and Access... 2 1.3. Adjacent Land Uses... 2 1.4. Existing ways...
More informationSubject: Solberg Avenue / I-229 Grade Separation: Traffic Analysis
MEMORANDUM Transportation Bill Troe, AICP Jason Carbee, AICP 12120 Shamrock Plaza Suite 300 Omaha, NE 68154 (402) 334-8181 (402) 334-1984 (Fax) To: Project File Date: Subject: Solberg Avenue / I-229 Grade
More informationTHIS PAGE LEFT BLANK INTENTIONALLY
GA SR 25 Spur at Canal Road Transportation Impact Analysis PREPARED FOR GLYNN COUNTY, GEORGIA 1725 Reynolds Street, Suite 300 Brunswick, Georgia 31520 PREPARED BY 217 Arrowhead Boulevard Suite 26 Jonesboro,
More informationChapter 4 Traffic Analysis
Chapter 4 Traffic Analysis PURPOSE The traffic analysis component of the K-68 Corridor Management Plan incorporates information on the existing transportation network, such as traffic volumes and intersection
More informationList of Attachments. Location Map... Site Plan... City of Lake Elsinore Circulation Element... City of Lake Elsinore Roadway Cross-Sections...
List of Attachments Exhibits Location Map... Site Plan... City of Lake Elsinore Circulation Element... City of Lake Elsinore Roadway Cross-Sections... Existing Lane Geometry and Traffic Controls... Existing
More information6060 North Central Expressway Mixed-Use Site Dallas, Texas
Volume 1 Traffic Impact Analysis 6060 North Central Expressway Mixed-Use Site Dallas, Texas April 30, 2018 Kimley-Horn and Associates, Inc. Dallas, Texas Project #063238300 Registered Firm F-928 Traffic
More informationGateway Transportation Study
Gateway Transportation Study Amherst, Massachusetts SUBMITTED TO University of Massachusetts Amherst Town of Amherst SUBMITTED BY Vanasse Hangen Brustlin, Inc. Watertown, Massachusetts March 213 Back of
More informationTRAFFIC IMPACT STUDY COMPREHENSIVE UPDATE TOWN OF THOMPSON S STATION, TENNESSEE PREPARED FOR: THE TOWN OF THOMPSON S STATION
TRAFFIC IMPACT STUDY COMPREHENSIVE UPDATE TOWN OF THOMPSON S STATION, TENNESSEE PREPARED FOR: THE TOWN OF THOMPSON S STATION Transportation Consultants, LLC 1101 17 TH AVENUE SOUTH NASHVILLE, TN 37212
More information1609 E. FRANKLIN STREET HOTEL TRAFFIC IMPACT STUDY EXECUTIVE SUMMARY
1609 E. FRANKLIN STREET HOTEL TRAFFIC IMPACT STUDY EXECUTIVE SUMMARY Prepared for: The Town of Chapel Hill Public Works Department Traffic Engineering Division Prepared by: HNTB North Carolina, PC 343
More informationWaterford Lakes Small Area Study
Waterford Lakes Small Area Study Existing Traffic Conditions PREPARED FOR: ORANGE COUNTY PUBLIC WORKS DEPARTMENT TRAFFIC ENGINEERING DIVISION ORLANDO, FLORIDA PREPARED WITH: INWOOD CONSULTING ENGINEERS
More informationFigure 1: Vicinity Map of the Study Area
ARIZONA TEXAS NEW MEXICO OKLAHOMA May 5, 2016 Mr. Anthony Beach, P.E. BSP Engineers 4800 Lakewood Drive, Suite 4 Waco, Texas 76710 Re: Intersection and Access Analysis along Business 190 in Copperas Cove
More informationCOMMERCIAL DEVELOPMENT 2015 ROBERTSON ROAD OTTAWA, ONTARIO TRANSPORTATION BRIEF. Prepared for:
COMMERCIAL DEVELOPMENT 2015 ROBERTSON ROAD OTTAWA, ONTARIO TRANSPORTATION BRIEF Prepared for: First Bay Properties Inc. 311 Richmond Road, Suite 203 Ottawa, ON K1Z 6X3 August 8, 2017 117-663 Brief_1.doc
More information3.9 - Transportation and Traffic
Transportation and Traffic 3.9 - Transportation and Traffic This section describes the potential transportation and traffic effects of project implementation on the project site and its surrounding area.
More informationQUICKIE C STORE AND GAS BAR 1780 HERON ROAD OTTAWA, ONTARIO TRANSPORTATION BRIEF. Prepared for:
QUICKIE C STORE AND GAS BAR 1780 HERON ROAD OTTAWA, ONTARIO TRANSPORTATION BRIEF Prepared for: Quickie Convenience Stores Larny Holdings Ltd. c/o PBC Group April 15, 2015 115-615 Report_1.doc D. J. Halpenny
More informationVolume 1 Traffic Impact Analysis. Texas Odyssey TIA Dallas, Texas. Kimley-Horn and Associates, Inc. Dallas, Texas. May 23, 2018
Volume 1 Traffic Impact Analysis Texas Odyssey TIA Dallas, Texas May 23, 2018 Kimley-Horn and Associates, Inc. Dallas, Texas Project #064529800 Registered Firm F-928 Traffic Impact Analysis Texas Odyssey
More informationGlenn Avenue Corridor Traffic Operational Evaluation
Glenn Avenue Corridor Traffic Operational Evaluation PREPARED FOR: THE CITY OF AUBURN PREPARED BY: DECEMBER 2007 Glenn Avenue Corridor Study--Auburn, Alabama TABLE OF CONTENTS Introduction... 1 Background
More informationNEW YORK CENTRAL PARK SUBDIVISION BLAIS STREET/ST-PIERRE STREET EMBRUN, ONTARIO TRAFFIC IMPACT STUDY. Prepared for:
NEW YORK CENTRAL PARK SUBDIVISION BLAIS STREET/ST-PIERRE STREET EMBRUN, ONTARIO TRAFFIC IMPACT STUDY Prepared for: Solidex Holdings Limited & Investissement Maurice Lemieux Investments Attn: Mr. Anthony
More informationFRONT RANGE CROSSINGS TRAFFIC IMPACT STUDY
FRONT RANGE CROSSINGS TRAFFIC IMPACT STUDY Prepared for: City of Thornton And Colorado Department of Transportation Prepared by: 11 Blake Street, Suite 2 Denver, Colorado 822 Contact: Brian Bern, PE, PTOE
More informationTraffic Impact Analysis Walton Acres at Riverwood Athletic Club Clayton, NC
Traffic Impact Analysis Walton Acres at Riverwood Athletic Club Clayton, NC 1. TABLE OF CONTENTS INTRODUCTION...1 1.1. Site Location and Study Area...1 1.2. Proposed Land Use and Site Access...2 1.3.
More informationDate: September 7, Project #: Re: Spaulding Youth Center Northfield, NH Property. Traffic Impact Study
To: Ms. Susan C. Ryan Spaulding Youth Center 72 Spaulding Road Northfield, NH 03276 Date: September 7, 2017 Project #: 52455.00 From: Robin Bousa Director of Transportation Systems Re: Spaulding Youth
More informationTraffic Impact Study WestBranch Residential Development Davidson, NC March 2016
Traffic Impact Study WestBranch Residential Development Davidson, NC March 216 TRAFFIC IMPACT STUDY FOR THE WestBranch Residential Development LOCATED IN DAVIDSON, NC Prepared For: Lennar Carolinas, LLC
More informationOTTAWA TRAIN YARDS PHASE 3 DEVELOPMENT CITY OF OTTAWA TRANSPORTATION IMPACT STUDY. Prepared for:
OTTAWA TRAIN YARDS PHASE 3 DEVELOPMENT CITY OF OTTAWA TRANSPORTATION IMPACT STUDY Prepared for: The Ottawa Train Yards Inc. 223 Colonnade Road South, Suite 212 Nepean, Ontario K2E 7K3 January 17, 2012
More informationChapter 16: Traffic and Parking A. INTRODUCTION
Chapter 6: Traffic and Parking A. ITRODUCTIO This chapter examines the potential traffic and parking impacts of the proposed Fresh Kills Park roads. The analysis of transit and pedestrians is presented
More informationMEETING FACILITY 2901 GIBFORD DRIVE CITY OF OTTAWA TRANSPORTATION BRIEF. Prepared for: Holiday Inn Express 2881 Gibford Drive Ottawa, ON K1V 2L9
MEETING FACILITY 2901 GIBFORD DRIVE CITY OF OTTAWA TRANSPORTATION BRIEF Prepared for: Holiday Inn Express 2881 Gibford Drive Ottawa, ON K1V 2L9 December 18, 2012 112-566 Brief_1.doc D. J. Halpenny & Associates
More informationTABLE OF CONTENTS TABLE OF CONTENTS... I APPENDICES... III LIST OF EXHIBITS... V LIST OF TABLES... VII LIST OF ABBREVIATED TERMS...
TABLE OF CONTENTS TABLE OF CONTENTS... I APPENDICES... III LIST OF EXHIBITS... V LIST OF TABLES... VII LIST OF ABBREVIATED TERMS... IX 1 INTRODUCTION... 1 1.1 Project Overview... 1 1.2 Analysis Scenarios...
More informationJACKSON PARK REVITALIZATION TRAFFIC IMPACT STUDY FINAL REPORT
JACKSON PARK REVITALIZATION TRAFFIC IMPACT STUDY FINAL REPORT Submitted to: Prepared by: February 2018 EXECUTIVE SUMMARY The City of Chicago and Chicago Park District are considering a large-scale revitalization
More informationAppendix B. Environmental Resource Technical Memorandum. Assessment on Travel Pattern and Access Impacts
Appendix B Environmental Resource Technical Memorandum Assessment on Travel Pattern and Access Impacts TECHNICAL MEMORANDUM ENVIRONMENTAL RE-EVALUATION FOR UNION STATION TO OAK CLIFF DALLAS STREETCAR To:
More informationPlace Vanier 250 Montreal Road Transportation Impact Study Addendum. Prepared for Broccolini Construction September 20 th, 2012
Update for the May 31 st, 2012 Traffic Impact Study Prepared for Broccolini Construction 111-23596-00 September 20 th, 2012 2611 Queensview Drive, Suite 300, Ottawa, Ontario CANADA K2B 8K2 Telephone: 613-829-2800
More informationMarina Loft (DRC 51-R-12)
Marina Loft (DRC 51-R-12) traffic study prepared for: Cymbal Development OCtober 2012 Traf Tech October 1, 2012 Mr. Asi Cymbal - President Cymbal Development 3470 North Miami Avenue Upper Suite Miami,
More informationTraffic Impact Study for Rolling Ridge Redevelopment
Traffic Impact Study for Rolling Ridge Redevelopment Webster Groves, Missouri October 19, 2018 Prepared For: Gershman Commercial Real Estate 150 North Meramec Avenue Suite 500 St. Louis, Missouri 63105
More informationTRANSPORTATION IMPACT STUDY
Dundas MEP Developments Inc. City of Toronto 219 and 231 Dundas Street East, Proposed Mixed-Use Development TRANSPORTATION IMPACT STUDY 9782/2 April 216 LEA Consulting Ltd. Consulting Engineers & Planners
More information3 ROADWAYS 3.1 CMS ROADWAY NETWORK 3.2 TRAVEL-TIME-BASED PERFORMANCE MEASURES Roadway Travel Time Measures
ROADWAYS Approximately 6 million trips are made in the Boston metropolitan region every day. The vast majority of these trips (80 to percent, depending on trip type) involve the use of the roadway network
More informationFAIRFIELD INN & SUITES HOTEL 135 THAD JOHNSON PRIVATE OTTAWA TRANSPORTATION BRIEF. Prepared for:
FAIRFIELD INN & SUITES HOTEL 135 THAD JOHNSON PRIVATE OTTAWA TRANSPORTATION BRIEF Prepared for: Bona Building & Management Co. Ltd. Place Vanier, 333 North River Road Vanier, Ontario K1L 8B9 August 12,
More informationSixth Line Development - Transit Facilities Plan
Memorandum Date: November 13, 2012 To: From: c.c. Subject: Rob Freeman (Freeman Planning) Kevin Phillips Sixth Line Development - Transit Facilities Plan 33016631 This memo was prepared to review the transit
More informationMission Street Medical Office Development
reet Medical Office Development Traffic Impact Analysis Prepared for: Palo Alto Medical Foundation February 23, 2012 Hexagon Office: 7888 Wren Avenue, Suite B121 Gilroy, CA 95020 Hexagon Job Number: 11RD11
More informationWalmart (Store # ) 60 th Street North and Marion Road Sioux Falls, South Dakota
Walmart (Store #4865-00) 60 th Street North and Marion Road Sioux Falls, South Dakota Prepared for: Wal-Mart Stores, Inc. Bentonville, Arkansas Prepared by: Kimley-Horn and Associates, Inc. ã2013 Kimley-Horn
More informationTRANSPORTATION ANALYSIS REPORT US Route 6 Huron, Erie County, Ohio
TRANSPORTATION ANALYSIS REPORT US Route 6 Huron, Erie County, Ohio December 12, 2012 Prepared for: The City of Huron 417 Main Huron, OH 44839 Providing Practical Experience Technical Excellence and Client
More informationALLEY 24 TRAFFIC STUDY
ALLEY 24 TRAFFIC STUDY in City of Frostburg, Maryland January 2013 3566 Teays Valley Road Hurricane, WV Office: (304) 397-5508 www.denniscorporation.com Alley 24 Traffic Study January 2013 Frostburg, Maryland
More informationAPPENDIX E: Transportation Technical Report
New Jersey Pennsylvania Lackawanna Cut-Off Passenger Rail Service Reston Project Environmental Assessment APPENDIX E: Transportation Technical Report E.1 Introduction As part of the overall environmental
More informationTAKOMA METRO STATION
TKOM METRO STTION Traffic nalysis Technical Memorandum Station Planning in Support of Joint evelopment Job No. 13-FQ165-LN-2 November 213 WSHINGTON METROPOLITN RE TRNSIT UTHORITY (WMT) Takoma Metro Station
More informationAPPENDIX H EXISTING TRAFFIC CONDITIONS ANALYSIS
APPENDIX H EXISTING TRAFFIC CONDITIONS ANALYSIS MEMO : Peter Steacy, P.Eng. Date: December 3, 2014 : Ian Borsuk, P.Eng. Job No.: 3414015-000 Subject: City of Ottawa O-Train Extension Planning & EA Study
More informationAPPENDIXB. Traffic Operations Technical Memorandum
APPENDIXB Traffic Operations Technical Memorandum Environmental Assessment - Lincoln County, SD 85 th Street: Sundowner Avenue to Louise Avenue November 2017 MEMORANDUM Transportation Jim Kollbaum, PE
More informationEmployment 8,881 17,975 9,094. Households 18,990 31,936 12,946
This section describes the future transportation environment of the UW Tacoma campus and surrounding area. A description of the future conditions on campus in terms of the street system, traffic and intersection
More informationHOLIDAY INN HOTEL 235 KING EDWARD AVENUE CITY OF OTTAWA TRANSPORTATION BRIEF. Prepared for:
HOLIDAY INN HOTEL 235 KING EDWARD AVENUE CITY OF OTTAWA TRANSPORTATION BRIEF Prepared for: Momentum Planning & Communications 1165 Greenlawn Crescent Ottawa, ON K1L 6C2 June 29, 2015 115-618 Brief_1.doc
More informationCity of Homewood Transportation Plan
City of Homewood Transportation Plan Prepared for: City of Homewood, Alabama Prepared by: Skipper Consulting, Inc. May 2007 TABLE OF CONTENTS INTRODUCTION... 1 BACKGROUND INFORMATION... 1 EXISTING TRANSPORTATION
More informationFigure 1: East West Connector Alignment Alternatives Concept Drawing
Page 2 of 9 Figure 1: East West Connector Alignment Alternatives Concept Drawing The Montebello Drive extension will run north south and connect Wilsonville Road to the Boones Ferry Road to Brown Road
More informationBLOSSOM AT PICKENS SIGNALIZED INTERSECTION IMPROVEMENT STUDY
BLOSSOM AT PICKENS SIGNALIZED INTERSECTION IMPROVEMENT STUDY Class Project Report for ECIV 542 Traffic Engineering Submitted by Omor Sharif Muchun Song Narges Kaveshgar Quyen Pham Chih-Yao Lin Submission
More informationCity of Wayzata Comprehensive Plan 2030 Transportation Chapter: Appendix A
A1. Functional Classification Table A-1 illustrates the Metropolitan Council s detailed criteria established for the functional classification of roadways within the Twin Cities Metropolitan Area. Table
More informationMEMORANDUM. Charlotte Fleetwood, Transportation Planner
MEMORANDUM Date: Updated August 22, 2017 To: Organization: Charlotte Fleetwood, Transportation Planner Boston Transportation Department From: Jason DeGray, P.E., PTOE, Regional Director of Engineering
More informationCarMax Auto Superstore/ Reconditioning Center #6002 Murrieta, California
CarMax Auto Superstore/ Reconditioning Center #6002 Murrieta, California TUSTIN 17782 17th Street Suite 200 Tustin, CA 92780-1947 714.665.4500 Fax: 714.665.4501 LOS ANGELES 145 S. Spring Street Suite 120
More informationEvaluation of M-99 (Broad Street) Road Diet and Intersection Operational Investigation
Evaluation of M-99 (Broad Street) Road Diet and Intersection Operational Investigation City of Hillsdale, Hillsdale County, Michigan June 16, 2016 Final Report Prepared for City of Hillsdale 97 North Broad
More informationTraffic Study. Chicago, Illinois. February The 601 W Companies, Inc. Prepared for:
AON CENTER ENTERTAINMENT + RESTAURANT DEVELOPMENT Traffic Study Chicago, Illinois Prepared for: The 601 W Companies, Inc. INTRODUCTION Kimley-Horn and Associates, Inc., (Kimley-Horn) was retained by The
More informationLyons Avenue/Dockweiler Road Extension Project Draft Environmental Impact Report. Appendix I Traffic Impact Study
Lyons Avenue/Dockweiler Road Extension Project Draft Environmental Impact Report Appendix I Traffic Impact Study Street 0 80-1947 500.4501 RITA ld Court 0 91355-1096 400.7401 LA n Avenue 0 590-3745 300-9301
More informationMETHODOLOGY. Signalized Intersection Average Control Delay (sec/veh)
Chapter 5 Traffic Analysis 5.1 SUMMARY US /West 6 th Street assumes a unique role in the Lawrence Douglas County transportation system. This principal arterial street currently conveys commuter traffic
More informationList of Exhibits...ii
One Brickell Traffic Study TABLE OF CONTENTS List of Exhibits...ii EXECUTIVE SUMMARY...1 1. INTRODUCTION...2 1.1 Study Area...2 1.2 Study Objective...5 2. EXISTING TRAFFIC CONDITIONS...6 2.1 Data Collection...6
More informationINDUSTRIAL BUILDING 1660 COMSTOCK ROAD CITY OF OTTAWA TRANSPORTATION OVERVIEW. Prepared for:
INDUSTRIAL BUILDING 1660 COMSTOCK ROAD CITY OF OTTAWA TRANSPORTATION OVERVIEW Prepared for: Simluc Contractors Limited 2550 Blackwell Street, Ottawa K1B 5R1 October 18, 2013 113-584 Overview_1.doc D. J.
More informationAPARTMENT BUILDING DEVELOPMENT 1161 HERON ROAD OTTAWA, ONTARIO TRANSPORTATION IMPACT STUDY. Prepared for:
APARTMENT BUILDING DEVELOPMENT 1161 HERON ROAD OTTAWA, ONTARIO TRANSPORTATION IMPACT STUDY Prepared for: 1649362 Ontario Inc. c/o Manor Park Management 231 Brittany Drive, Suite D Ottawa ON K1K 0R8 July
More informationTechnical Memorandum TRAFFIC IMPACT STUDY. RIDLEY ROAD CONVENIENCE STORE Southampton County, VA. Prepared for: Mr. David Williams.
Technical Memorandum TRFFIC IMPCT STUDY RIDLEY ROD CONVENIENCE STORE Southampton County, V Prepared for: Mr. David Williams By: Charles Smith, P.E., PTOE EPR Charlottesville, V July 2014 1 TBLE OF CONTENTS
More informationENHANCED PARKWAY STUDY: PHASE 2 CONTINUOUS FLOW INTERSECTIONS. Final Report
Preparedby: ENHANCED PARKWAY STUDY: PHASE 2 CONTINUOUS FLOW INTERSECTIONS Final Report Prepared for Maricopa County Department of Transportation Prepared by TABLE OF CONTENTS Page EXECUTIVE SUMMARY ES-1
More informationBridge Street Corridor Study Report
Bridge Street Corridor Study Report Prepared for: Prepared by: BRIDGE STREET CORRIDOR STUDY REPORT PREPARED FOR: CITY OF ARROYO GRANDE COMMUNITY DEVELOPMENT DEPARTMENT 300 EAST BRANCH STREET ARROYO GRANDE,
More informationINDUSTRIAL BUILDING 3009 HAWTHORNE ROAD CITY OF OTTAWA TRANSPORTATION OVERVIEW REVISED. Prepared for: Canada Inc.
INDUSTRIAL BUILDING 3009 HAWTHORNE ROAD CITY OF OTTAWA TRANSPORTATION OVERVIEW REVISED Prepared for: 7849648 Canada Inc. Octiober 1, 2015 114-598 Overview_2.doc D. J. Halpenny & Associates Ltd. Consulting
More informationEXECUTIVE SUMMARY. Page 1 of 6
EXECUTIVE SUMMARY The purpose of this report is to identify conformance with the original traffic impact study for the proposed retail development on Lot 5 of Riverdale Retail Filing No. 1 located on the
More information2. Existing Conditions
2. Existing Conditions The existing traffic and parking conditions on the site and the surrounding area were reviewed based on the study methodology in Section 1.2. 2.1 Existing Land Use The portion of
More information4. ENVIRONMENTAL IMPACT ANALYSIS 9. TRANSPORTATION AND TRAFFIC
4. ENVIRONMENTAL IMPACT ANALYSIS 9. TRANSPORTATION AND TRAFFIC 4.9.1 INTRODUCTION The following section addresses the Proposed Project s impact on transportation and traffic based on the Traffic Study
More informationTraffic Circulation & Pedestrian Safety Study
Lyons Township High School North Campus La Grange, Illinois Parking Lot Vaughan Building N Main Building Prepared for: Prepared by: July 23, 2015 Contents List of Figures, iii 1. Introduction...1 2. Existing
More informationAbrams Associates. Transportation Impact Analysis. City of Rocklin. Prepared for: David Mohlenbrok City of Rocklin 4081 Alvis Court Rocklin, CA 95677
Transportation Impact Analysis Sierra College Boulevard Commercial Project City of Rocklin Prepared for: David Mohlenbrok City of Rocklin 081 Alvis Court Rocklin, CA 95677 Prepared by: 1875 Olympic Boulevard,
More informationMultnomah County Courthouse Relocation. Transportation Alternatives Analysis Technical Memorandum: FINAL
Multnomah County Courthouse Relocation Portland, Oregon Transportation Alternatives Analysis Technical Memorandum: FIL Prepared for Multnomah County Facilities and Property Management Division 41 N Dixon
More information9 Leeming Drive Redevelopment Ottawa, ON Transportation Brief. Prepared By: Stantec Consulting Ltd.
9 Leeming Drive Redevelopment Ottawa, ON Transportation Brief Prepared By: Stantec Consulting Ltd. TIA GUIDELINES CHECKLIST Report Context Municipal Address Comment: Section 1.1 Location relative to major
More informationEAST AND SOUTH STREET CITY OF ANAHEIM, CALIFORNIA
T R A F F I C I M P A C T A N A LY S I S EAST AND SOUTH STREET CITY OF ANAHEIM, CALIFORNIA April 217 T R A F F I C I M P A C T A N A LY S I S EAST AND SOUTH STREET CITY OF ANAHEIM, CALIFORNIA Submitted
More informationTRAFFIC IMPACT STUDY And A TRAFFIC SIGNAL WARRANT ANALYSIS FOR A SENIOR LIVING AND APARTMENT DEVELOPMENT
TRAFFIC IMPACT STUDY And A TRAFFIC SIGNAL WARRANT ANALYSIS FOR A SENIOR LIVING AND APARTMENT DEVELOPMENT DEERFIELD TOWNSHIP, WARREN COUNTY, OHIO Nantucket Circle and Montgomery Road () Prepared for: ODLE
More informationTRAFFIC IMPACT ANALYSIS OF PROPOSED CHESTNUT HILL COLLEGE MASTER PLAN DEVELOPMENT
TRAFFIC IMPACT ANALYSIS OF PROPOSED CHESTNUT HILL COLLEGE MASTER PLAN DEVELOPMENT Prepared by Orth-Rodgers & Associates, Inc. December 14, 2009 Updated November 9, 2010 230 South Broad Street Philadelphia
More informationPrepared For: Shieldbay Developments Inc. c/o Matson, McConnell Ltd. 2430A Bloor Street West Toronto, Ontario M6S 1P9.
Prepared For: Shieldbay Developments Inc. c/o Matson, McConnell Ltd. 2430A Bloor Street West Toronto, Ontario M6S 1P9 Prepared By: URS Canada Inc. 4 th Floor, 30 Leek Crescent Richmond Hill, Ontario L4B
More informationComplete Street Analysis of a Road Diet: Orange Grove Boulevard, Pasadena, CA
Complete Street Analysis of a Road Diet: Orange Grove Boulevard, Pasadena, CA Aaron Elias, Bill Cisco Abstract As part of evaluating the feasibility of a road diet on Orange Grove Boulevard in Pasadena,
More informationWindy Ridge Elementary School
Windy Ridge Elementary School SCHOOL ROUTE PLAN For WINDY RIDGE ELEMENTARY SCHOOL LOCATION 54 ORANGE COUNTY Prepared for: ORANGE COUNTY SCHOOL ASSESSMENT PROGRAM ORANGE COUNTY PUBLIC WORKS Traffic Engineering
More informationREDEVELOPMENT TRAFFIC IMPACT STUDY
REDEVELOPMENT TRAFFIC IMPACT STUDY For Wendy s Parker, Colorado January 215 Prepared for: Sterling Design Associates, LLC 29 W. Littleton Boulevard #3 Littleton, Colorado 812 Prepared by: 1233 Airport
More information2136 And 2148 Trafalgar Road Townhouse Development Traffic Brief. Paradigm Transportation Solutions Limited
2136 And 2148 Trafalgar Road Townhouse Development Traffic Brief Paradigm Transportation Solutions Limited March 217 March 217 Project: 1627 Diana Vlasic, M.C.I.P., R.P.P Metropolitan Consulting 445 Paletta
More informationThe proposed development is located within 800m of an existing Transit Station where infill developments and intensification are encouraged.
Stantec Consulting Ltd. 1331 Clyde Avenue, Suite 4 Ottawa ON K2C 3G4 Tel: (613) 722-442 Fax: (613) 722-2799 May 14, 213 File: 1638823 Robinson Park Development Corp. 5699 Power Road Ottawa, ON, K1G 3N4
More informationCDOT s Transportation Plan for the Obama Presidential Center in Jackson Park
CDOT s Transportation lan for the Obama residential Center in Jackson ark May 10, 2018 repared for Jackson ark Watch JacksonarkWatch.org repared by at Hawley,.E. TOE rasmith 16745 West Bluemound Road Brookfield,
More informationHILTON GARDEN INN HOTEL HOTEL EXPANSION 2400 ALERT ROAD, OTTAWA TRANSPORTATION BRIEF. Prepared for:
HILTON GARDEN INN HOTEL HOTEL EXPANSION 2400 ALERT ROAD, OTTAWA TRANSPORTATION BRIEF Prepared for: Bona Building & Management Co. Ltd. Place Vanier, 333 North River Road Vanier, Ontario K1L 8B9 October
More informationThe current document is revised based on the comments received on:
General Overview 1 Introduction Over the last several years, the Waterford Lakes area has experienced increased congestion due to a substantial increase in residential and commercial development. The current