1 Transportation Improvement Program Appendix H Non-regionally Significant Arterials in Mobility 2045 North Central Texas Council of Governments DFW Metropolitan Planning Organization

2 Revised June Dallas District NRSA1 DAL Improvement Whitlock Road IH 35E Old Denton Road Reconstruct 4 lane undivided to four lane divided with left turns $3,802,480 Minor Arterial NRSA1 DAL Conflans Road SH 161 Valley View lane NRSA1 DAL Addition of lanes Mckinney Street (Old FM 426) NRSA1 DAL Addition of lanes FM Miles west of SL Miles East of SL 288 NRSA1 DAL Addition of lanes FM 544 FM 2281 (Denton Drive) Construct 0 to 4 lane divided facility with new sidewalks and shared use path $30,952,202 Major Collector 1.4 Miles west of SL Miles East of SL 288 Widen 2 lane roadway to 4 lane divided urban $18,267,303 Minor Arterial 0.17 Miles West of Josey lane Widen from 2 lane roadway to 4 lane divided urban; Addition of lanes $682,697 Minor Arterial Reconstruct and widen two lane rural highway to six lane divided urban Facility $43,439,321 Minor Arterial NRSA1 DAL Improvement Daniel Dale Road IH 35E Houston School Road Recon. 2 Ln Undiv to 2 Ln Undiv urban from IH 35E Nb Fr Rd to Longhorn Trl & Recon. 2 Ln Undiv to 3 Ln Undiv with Contin. Cntr turn Ln W/Transition Lns, Signals, & add Combo Lns For Lt & Rt turn Lns from Longhorn Trl to Houston School Rd $6,194,242 Minor Arterial NRSA1 DAL Addition of lanes Pleasant Run Road Lancaster Hutchins Millers Ferry Road Widen 2 lane to 4 lane divided urban roadway $15,423,000 Minor Arterial NRSA1 DAL Addition of lanes, Reconstruction FM 3097 FM 740 East of Tubbs Road Reconstruct and Widen 2 lane undivided to 4 lane divided $14,049,455 Major Collector NRSA1 DAL Addition of lanes Medical District Drive IH 35E Harry Hines Blvd Reconstruct and widen from 4 lane to 6 lane divided $26,617,109 Major Collector NRSA1 DAL Addition of lanes FM 455 Wildwood Trail SH 121 Widen Facility to 4 lane urban divided (ultimate 6 lane divided) $82,910,295 Minor Arterial NRSA1 DAL Corporate Drive FM 544 Josey lane Construct four lane divided roadway segment 6 $20,898,278 Minor Arterial NRSA1 DAL FM 2514 FM 1378 East of Lavon Parkway Realign highway from FM 1378 southeast to near Lavon Parkway, Construct four lane divided highway (ultimate 6 lanes) $9,251,843 Major Collector NRSA1 DAL Addition of lanes FM 2514 FM 2551 West of FM 1378 Widen 2 lane rural to 4 lane (ultimate 6 lane) urban roadway including new pedestrian improvements and left/right turn lanes $26,454,250 Major Collector NRSA1 DAL Pleasant Valley Road Richfield Drive at Creek Meadow Lane Miles Road Construct a 4 lane divided roadway and bridge $26,845,032 Minor Arterial NRSA1 DAL Addition of lanes Gerault/ Morriss FM 2499 FM 407 Widen and reconstruct 4 to 6 lane divided urban arterial from FM 2499 to FM 3040 and Reconstruct 4 to 4 lane divided urban from FM 3040 to FM 407 with traffic signal and drainage improvements West of FM 2499/Gerault Road intersection $32,047,204 Minor Arterial H.2

3 Revised June Dallas District NRSA1 DAL Addition of lanes Mayhill Road IH 35E US 380 Expand 2 lane rural road to a 4 lane divided urban arterial (ultimate 6 lane), extension of FM 2499 $95,603,459 Minor Arterial NRSA1 DAL Improvement IH 20 At Bonnie View Road Improve approach, widen bridge to add turn lanes and replace traffic signal system $3,376,725 Minor Arterial NRSA1 DAL Interchange SP 557 At Las Lomas Parkway (CR 305) Construct Phase 1 (4 lanes) of ultimate 8 lane bridge Plus Connections to Las Lomas Parkway $2,961,583 Freeway/ Expressway NRSA1 DAL Addition of lanes SP 557 At Las Lomas Parkway (CR 305) Construct Phase 2 (Final 4 lanes) of ultimate 8 lane bridge plus connections to Las Lomas Parkway $6,021,704 Freeway/ Expressway NRSA1 DAL Addition of lanes Wildlife Parkway SH 161 Belt Line Road Construct 0/2 lane rural to 2/4 lane divided including bridge over Trinity River $35,121,000 Major Collector NRSA1 DAL Improvement, FM 2478 US 380 FM 1461 Addition of lanes Widen two lane rural highway to four lane divided; Realign intersection at FM 1461; Six lane ultimate $54,868,369 Minor Arterial NRSA1 DAL Improvement, Reconstruction, FM 2478 FM 1461 North of FM 1461 Addition of lanes Widen two lane rural highway to four lane divided; six lane ultimate; Realign intersection of FM 1461 $5,173,412 Minor Arterial NRSA1 DAL Addition of lanes FM 2551 FM 2514 FM 2170 Reconstruct and widen 2 lane rural to 6 lane urban divided $65,817,835 Minor Arterial (State NRSA1 DAL FM 3486 FM 986 SH 34 Reconstruct 2 lane County Road to 2 lane FM highway $6,311,958 Funded) NRSA1 DAL Addition of lanes FM 156 SH th Street Widen 2 to 4 lane divided urban cross section $45,201,856 Minor Arterial NRSA1 DAL Addition of lanes FM 2786 SH 5 NRSA1 DAL Addition of lanes FM 2786 East of Angel Parkway FM 1378 NRSA1 DAL Addition of lanes, , IH 35E/Dickerson Parkway East of Angel Parkway in Allen Sandy Lake Road/Whitlock lane PGBT (SH 190) Widen 2 to 4 lane divided (6 lane ultimate) with Improvements at SH 5 Reconstruct 2 lane roadway to a 4 lane (ultimate 6) divided roadway Lane ramp and 4 to 6 frontage road Construction along IH 35E and a new 6 lane overpass at Dickerson Parkway (part of phased implementation of the IH 35E corridor) $11,160,911 Minor Arterial $10,575,825 Minor Arterial $101,673,681 Minor Arterial NRSA1 DAL Addition of lanes FM 552 SH 205 SH 66 Widen from 2 lane rural to 4 lane urban section $60,527,989 Major Collector NRSA1 DAL Addition of lanes FM 549 SH 205 SH 276 Widen from 2 lane rural to 4 lane urban $28,194,287 Major Collector NRSA1 DAL Addition of lanes FM 664 IH 35E IH 45 Widen 2/4 lane rural to 6 lane urban $237,068,224 Minor Arterial NRSA1 DAL Addition of lanes FM 3549 IH 30 North of SH 66 Widen from 2 lane rural to 4 lane urban divided section $18,979,785 Minor Arterial H.3

4 Revised June Dallas District NRSA1 DAL Bike/Pedestrian Old town Transit Oriented Development NRSA1 DAL Bike/Pedestrian Thomasson Square Bounded By 100 N. Charles Street; 200 N. Charles Street Bounded By Karla Drive On The North, Moon Drive and; Whitson Way On The South 100 West to 500 E. Blocks Pedestrian amenities; Landscaping; Improvements; of Main Street and The 100 Bike Connection; traffic signalization; and Street Improvements N. to 500 S. Blocks of Mill on Main St and Mill St to reduce from 2 lanes to 1 lane In each Street direction to accomm. Pedestrian Impr. Forrest Drive On The East and The City Drainage Channel On The West Ped amen., Bike Ln/Trl, Lndscp, Int. Improv. incl Lt Trn Lns, Rt Trn Lns, Improv. to Int. Geom. and/or Lndscp on Gus Thomasson, & Traf. Sgnlztion & Str. Improv. incl 6 to 4 Lns on Gus Thomasson Rd B/W Karla Dr (N. Bndry) & Moon Dr & Whitson Way (S. Bndry) $3,750,000 Minor Arterial $3,749,421 Minor Arterial NRSA1 DAL Addition of lanes FM 455 West of FM 2450 East of Marion Road Reconstruct and widen two lane rural to four lane urban divided $66,770,314 Minor Arterial NRSA1 DAL Addition of lanes West Lucas Road FM 2551 FM 1378 NRSA1 DAL Addition of lanes FM 3038 Virginia Parkway NRSA1 DAL Frontier Parkway (CR 5) SH 289 (Preston Road) DNT Widen from 2 lanes to 3/4 lane section including traffic signal Modifications at FM 2551 and FM 1378 intersection $1,500,000 Minor Arterial West of Joplin Drive US 75 Widen 4 to 6 lane divided including a bridge over Wilson Creek $16,092,551 Major Collector Construct new 2 to 4 lane divided urban arterial with grade separation over BNRR, 2 Way service road north of grade separation, and quiet zones $24,586,700 Minor Arterial NRSA1 DAL Addition of lanes FM 148 South of US 80 SP 557 Widen existing highway from two lane rural to four lane divided $15,400,000 Major Collector NRSA1 DAL Addition of lanes Dallas Parkway SH 121 Lebanon Road NRSA1 DAL Addition of lanes Dallas Parkway Lebanon Road Eldorado Parkway NRSA1 DAL Addition of lanes FM 2514 North of Drain Drive Brown Street NRSA1 DAL Addition of lanes FM 2514 East of Lavon Parkway North of Drain Drive NRSA1 DAL Addition of lanes FM 2514 West of FM 1378 FM 1378 NRSA1 DAL Addition of lanes Hickory Creek Road FM 2181 Proposed FM 2499 NRSA1 DAL Kirkpatrick Lane (Phase III) Widen northbound and southbound Dallas Parkway from 2 lanes in each direction to 3 lanes in each direction Widen northbound and southbound Dallas Parkway from 2 lanes in each direction to 3 lanes in each direction Widen facility from 2 lane to 4 lane urban divided (ultimate 6 lane divided) Widen Facility from 2 lane to 4 lane urban divided (ultimate 6 lane divided) Reconstruct 2 lane rural to 4 lane urban (ultimate 6 lane urban divided) Construct and widen from 2 lane undivided to 4 lane undivided urban roadway $7,068,000 Major Collector $4,550,000 Major Collector $40,069,296 Major Collector $21,271,466 Major Collector $2,322,460 Major Collector $3,000,000 Major Collector FM 1171 Bellaire Blvd Construct 0 to 4 lane roadway $11,529,000 Major Collector NRSA1 DAL Addition of lanes Hickox Road Toler Road Merritt Road Widen from 2 lanes to 4 lanes (Phase 2) $3,000,000 Minor Arterial NRSA1 DAL Addition of lanes Lawson Road Milam Road Clay Mathis Road Widen from 2 lanes to 4 lanes $13,335,000 Minor Arterial NRSA1 DAL Addition of lanes Lebanon Road Coit Road Independence Parkway Widen from 2 lanes to 4 lanes $5,800,000 Major Collector NRSA1 DAL Addition of lanes Main Street FM 423 DNT Widen from 4 lanes to 6 lanes $1,200,000 Minor Arterial NRSA1 DAL Addition of lanes FM 548 North of US 80 at Walmart SH 205 Widen and reconstruct 2 lane rural to 4 lane urban divided (6 lane ultimate) $109,599,843 Major Collector NRSA1 DAL Addition of lanes Chaha Road Rowlett Road Kirby Road Widen from 2 lanes to 3 lanes $5,016,500 Major Collector NRSA1 DAL Addition of lanes N/A Ridgeview Drive Alma US 75 Widen from 2 lanes to 4 lanes $18,979,785 NRSA1 DAL FM 148 South of FM 3039 US 175 Construct 0 to 2 rural lane undivided $41,868,896 Minor Arterial H.4

5 Revised June Dallas District NRSA1 DAL Denton Creek Blvd At Graham Branch Build new location 0 to 4 lane bridge $8,967,000 Minor Arterial NRSA1 DAL Interchange Denton Creek Blvd At IH 35W Interchange $5,000,000 Minor Arterial NRSA1 DAL Improvement Skillern Road Flower Mound Road River Hill Drive Reconstruct 2 to 2 lanes $905,000 Minor Arterial NRSA1 DAL Valley Ridge Blvd Mill Street College Street Construct 0 to 4 lane divided urban arterial $17,770,000 Major Collector NRSA1 DAL Wheatland Road Dallas/Lancaster City Limit University Hills along The Construct 0 to 4 lane divided roadway and Bicycle/Pedestrian Dallas/Lancaster City Limits Facilities $4,809,552 Major Collector NRSA1 DAL Addition of lanes Hickory CreekRoad FM 2181 River Pass Widen from 2 lanes to 4 lanes (ultimate 6 lanes) $3,500,000 Major Collector NRSA1 DAL Bridge, Improvement, Bike/Pedestrian SH 114/Texas Plaza bridge SL 12 SS 482 Construct 0 to 4 lane signature bridge with bicycle lane, sidewalks, Improvements, and ramp modifications $54,413,449 Minor Arterial NRSA1 DAL Improvement/ Reconstruct Dolphin Road Spring Ave North of Haskell Ave/Military Parkway Reconstruct existing roadway from 4 lane undivided to 4 lane divided with intersection improvements at Haskell $4,694,450 Minor Arterial NRSA1 DAL Reconstruction FM 407 Gulf Ave Sage Drive Realign existing 2 to 2 lane roadway $2,890,927 Minor Arterial NRSA1 DAL Reconstruction, Addition of lanes FM 548 S of SH 205 (Kaufman County Line) NRSA1 DAL Addition of lanes Wintergreen Road Jefferson Street West of Carpenter Road SH 205 Widen and reconstruct 2 lane rural to 4 lane divided urban roadway (ultimate 6) Reconstruct and widen 2 lane undivided rural to 4 lane divided urban $13,126,932 Minor Arterial $18,885,938 Minor Arterial NRSA1 DAL Reconstruction Addition of lanes Jefferson Street from Wintergreen Road to Pleasant Run Road and Pleasant Run Road Jefferson Street Lancaster Hutchins Road Widen and reconstruct 2 lane undivided rural to 4 lane divided urban $11,295,657 Major Collector NRSA1 DAL Reconstruction, Addition of lanes FM 1387 Midlothian Parkway FM 664 Reconstruct and widen from 2 lane undivided rural to 4 lane urban divided (ultimate 6 lane) $54,840,610 Major Collector NRSA1 DAL FM 1171 IH 35W West of FM 156 Construct new 0 to 6 lane divided arterial $59,192,338 Major Collector NRSA1 DAL Bike/Pedestrian Denton Drive South of Walnut Hill lane North of Royal lane Reconstruct Denton Dr from 2 ln undivided rural into 3 ln urban transit oriented roadway with center turn ln, bike ln, sidewalks, and sidewalk connection to Harry Hines Blvd along both Walnut Hill Ln and Royal Ln connecting Dart LRT Station $10,253,616 Major Collector NRSA1 DAL NRSA1 DAL 200 NRSA1 DAL 201 Improvement Waketon Road FM 2499 Chinn Chapel Road of roadway (2 to 2 lanes) $5,876,000 New Collin County N/S Road #1 FM 1827/New Collin County N/S Road #1 SH 121/FM 455 FM 545/FM 1827 New 4 lane road (PA) FM 545/FM 1827 FM 1827/CR 470 Realign 4 lane road (PA) $8,587,037 $12,318,304 H.5

6 Revised June Dallas District NRSA1 DAL 202 NRSA1 DAL 203 NRSA1 DAL 204 NRSA1 DAL 205 NRSA1 DAL 206 NRSA1 DAL 207 NRSA1 DAL 210 NRSA1 DAL 211 NRSA1 DAL 212 NRSA1 DAL 213 NRSA1 DAL 214 NRSA1 DAL 215 NRSA1 DAL 217 NRSA1 DAL 218 NRSA1 DAL 219 NRSA1 DAL 221 NRSA1 DAL 222 NRSA1 DAL 223 NRSA1 DAL 224 NRSA1 DAL 225 NRSA1 DAL 226 NRSA1 DAL 227 NRSA1 DAL 229 WIdening WIdening WIdening WIdening New Collin County N/S Road #1 FM 1827/CR 470 CR 463 (North) New 4 lane road (PA) New Collin County N/S Road #1 CR 463 (North) US 380 Realign 4 lane road (PA) New Collin County N/S Road #1 US 380 FM 546/CR 447 New 4 lane road (PA) New Collin County N/S Road #1 FM 546/CR 447 FM 982/CR 444 Realign 4 lane road (MA) FM 982/Collin County N/S Road #1 FM 982/CR 444 FM 3286 Realign 4 lane road (MA) FM 3286 Lucas Road/Collin County N/S FM 982 FM 1378 Widen 2 to 4 lanes (MA) Road #1 McMillien Dr/Collin County E/W Road #2 McCreary Rd Country Club Rd Widen 2 to 6 lanes (MA) PArk Blvd/Collin County E/W Road #2 Country Club Rd SH 78/Kreymer Ln Widen 2 to 6 lanes (MA) Kreymer Ln/Collin County Collin County E/W Road SH 78/Kreymer Ln E/W Road #2 #3/Troy Rd Widen 2 to 4 lanes (MA) HenSLey Ln/New Collin County E/W Road #3 McCreary Rd Woodbridge Pkwy New 4 lane road (MA) $4,897,286 $8,981,690 $8,730,034 $8,839,204 $1,396,662 Minor Arterial $30,486,697 Major Collector $5,571,272 Major Collector $13,266,495 $3,934,743 $3,620,045 HenSLey Ln/New Collin Woodbridge Pkwy Sanden Blvd Widen 2 to 4 lanes (MA) County E/W Road #3 $2,794,349 Alanis Dr/New Collin Sanden Blvd Ballard St Realign 4 lane road (MA) w/ SH 78 grade separation County E/W Road #3 $7,199,601 New Collin County E/W FM 544 (Vinson Rd) SH 205 New 4 lane road (MA) Road #3 $41,314,032 Minor Arterial Campbell Road/Collin PGBT Murphy Rd Widen 2/4 to 6 lanes (PA) County E/W Road #4 $5,017,220 Minor Arterial Blackburn Rd/Collin Murphy Rd Dewitt Rd Widen 2 to 4 lanes (MA) County E/W Road #4 $2,822,539 Major Collector Sachse Rd/Collin County SH 78/Sachse Rd Sachse Rd/Elm Grove Rd Widen 2 to 4 lanes (MA) E/W Road #4 $7,185,250 Major Collector Elm Grove Rd/Collin Sachse Rd/Elm Grove Rd Vinson Rd Widen 2 to 4 lanes (MA) County E/W Road #4 $5,758,348 Major Collector FM 544 (Vinson Alanis Dr/Collin County E/W Rd)/Collin County N/S Elm Grove Rd Widen 2 to 4 lanes (MA) Road #3 Road #5 $7,812,594 FM 544 (Vinson Rd)/Collin County N/S Elm Grove Rd Merritt Rd/Hickox Rd New 4 lane road (MA) w/ diamond PGBT Road #5 $17,470,833 Major Collector Hickox Rd/Collin County Merritt Rd/Hickox Rd Castle Dr Widen 2 to 4 lanes (MA) N/S Road #5 $2,252,085 Hickox Rd/Collin County Castle Dr Centerville Rd New 4 lane road (MA) N/S Road #5 $4,535,436 Major Collector Castle Dr/Collin County Centerville Rd Country Club Rd Widen 2 to 4 lanes (MA) N/S Road #5 $3,022,428 Collin County E/W Road SH 5 (Greenville Ave)/Chaparral Chase Oaks Blvd (W of US New 4 lane road (C) w/ grade separation over US 75 mainlanes #7 Rd 75) & frontage roads $6,599,933 Major Collector H.6

7 Revised June Dallas District NRSA1 DAL 230 NRSA1 DAL 231 NRSA1 DAL 232 NRSA1 DAL 233 NRSA1 DAL 234 NRSA1 DAL 235 NRSA1 DAL 236 NRSA1 DAL 237 NRSA1 DAL 238 NRSA1 DAL 239 NRSA1 DAL 240 NRSA1 DAL 241 NRSA1 DAL 242 NRSA1 DAL 243 NRSA1 DAL 244 NRSA1 DAL 245 NRSA1 DAL 246 NRSA1 DAL 247 NRSA1 DAL 248 NRSA1 DAL 249 NRSA1 DAL 250 NRSA1 DAL 251 NRSA1 DAL 253 NRSA1 DAL 254 NRSA1 DAL 255 WIdening WIdening WIdening FM 6/Collin County E/W Road #8 SH 78 SH 66 Widen 2 to 4 lanes (MA) FM 6/Collin County E/W Road #8 SH 66 FM 35 (S of SH 66) New 4 lane road (MA) FM 35/Collin County E/W FM 35 (S of SH 66) Road #8 IH 30 Widen 2 to 4 lanes (MA) FM 2755/Collin County E/W Road #9 SH 78 FM 2755/Watkins Rd Widen 2 to 4 lanes (PA) Watkins Rd/Collin County FM 2755/Watkins Rd E/W Road #9 FM 1777/CR 590 Widen 2 to 4 lanes (PA) FM 2642/Collin County E/W Road #9 FM 1777/CR 590 SH 66/FM 2642 New 4 lane road (PA) FM 2642/Collin County E/W Road #9 SH 66/FM 2642 FM 35/FM 2642 Widen 2 to 4 lanes (PA) FM 35/Collin County E/W FM 35/FM 2642 Road #9 SH 276 Widen 2 to 4 lanes (PA) CR 482/Collin County E/W Road #10 SH 78 CR 483 (East) Widen 2 to 4 lanes (MA) Collin County E/W Road #10 CR 483 (East) FM 2755 (West) New 4 lane road (MA) FM 2755/Collin County Erby Campbell Rd/Collin FM 2755 (West) E/W Road #10 County N/S Road #13 Widen 2 to 4 lanes (MA) Collin County E/W Road Erby Campbell Rd/Collin County SH 66 #10 N/S Road #13 New 4 lane road (MA) FM 3549/Collin County N/S Road #11 FM 552/FM 3549 FM 2755 (West) New 4 lane road (MA) FM 2755/Collin County N/S Road #11 FM 2755 (West) FM 2755/Watkins Rd Widen 2 to 4 lanes (MA) FM 3549/Collin County N/S Road #11 FM 2755/Watkins Rd FM 6 New 4 lane road (MA) FM 1138/Collin County FM 1138 (S of FM 1138/Outer Loop N/S Road #12 Nevada/NETEX) Widen 2 to 4 lanes (MA) Collin County N/S Road #12 FM 1138 (S of Nevada/NETEX) FM 6/FM 1138 New 4 lane road (MA) FM 1138/Collin County N/S Road #12 FM 6/FM 1138 FM 1778/CR 643 Widen 2 to 4 lanes (MA) Collin County N/S Road #12 FM 1778/CR 643 CR 609 (North) Widen 2 to 4 lanes (MA) Collin County N/S Road #12 CR 609 (North) Main St/Josephine Rd New 4 lane road (MA) Main St/Collin County N/S Road #12 Main St/Josephine Rd US 380/Main St Widen 2 to 4 lanes (MA) Erby Campbell/Collin County N/S Road #13 Collin County E/W Road #10 SH 66 Realign 2 to 4 lanes (C) FM 1778/Collin County E/W Road #14 SH 78 CR 695 Widen 2 to 4 lanes (MA) FM 1778/Collin County E/W Road #14 CR 695 FM 6/FM 1777 Realign 2 to 4 lanes (MA) FM 1777/Collin County N/S Road #14 FM 6/FM 1777 SH 66 Widen 2 to 4 lanes (MA) $27,985,519 $3,620,045 Major Collector $7,926,890 Major Collector $11,571,025 Major Collector $8,411,237 $6,884,391 Major Collector $6,930,322 Minor Arterial $15,711,295 $3,136,724 $5,855,730 Major Collector $12,290,113 $7,909,464 $7,771,019 Major Collector $4,562,970 $9,030,894 Major Collector $6,386,718 $3,868,113 Major Collector $7,527,111 Minor Collector $11,975,416 $5,827,540 Minor Collector $1,281,854 $5,673,779 Minor Collector $19,018,180 $4,258,153 $17,250,442 H.7

8 Revised June Dallas District NRSA1 DAL 256 FM 1777/Collin County N/S Road #14 SH 66 FM 35/FM 2453 New 4 lane road (MA) w/ IH 30 interchange NRSA1 DAL 259 WIdening Rock Ridge Rd FM 1378 (Country Club Rd) Exchange Pkwy Widen 2 to 4 lanes (C) NRSA1 DAL 260 WIdening Rock Ridge Rd Exchange Pkwy FM 2170 (Estates Pkwy) Widen 2 to 4 lanes (C) NRSA1 DAL 261 McCReary Rd Lucas Rd/Lewis Ln FM 2514 (Parker Rd)/McCReary Rd New 4 lane road (C) NRSA1 DAL 263 Lucas Rd FM 2551 (angel Pkwy) FM 1378 (Country Club Rd) Widen 2 to 4 lanes (MA) NRSA1 DAL 264 Outer Loop/FM 548 Connector IH 30 FM 548 New 4 lane divided NRSA1 DAL 265 FM 548 Outer Loop/FM 548 Connector SH 276 Widen 2 to 4 lane divided $7,292,370 $1,853,342 $2,936,834 $7,913,051 $7,185,250 Minor Collector $9,100,000 Major Collector $8,400,000 Major Collector NRSA1 DAL 266 FM 548 SH 276 SH 205 Widen 2 to 4 lane divided $27,000,000 Major Collector NRSA1 DAL FM 1461 West of County Road 166 CR 123 Widen and reconstruct 2 lane rural to 4 lane urban (ultimate 6 lanes) $15,834,370 Major Collector NRSA1 DAL FM 1461 SH 289 West of County Road 166 Widen and reconstruct 2 lane rural to 4 lane urban (ultimate 6 lanes) $93,670,180 Minor Arterial NRSA1 DAL FM 1515/Airport Road Bonnie Brae Masch Branch Road Widen 2 lane rural section to 6 lane divided urban Minor/Major $34,751,182 Collector NRSA1 DAL Reconstruct College Street Mill Street Railroad Street Reconstruct from 2 to 2 lanes, add bicycle lanes, widen/expand sidewalks, and add on street parking $3,750,000 Major Collector NRSA1 DAL Reconstruct South Shady Shores Road West Shady Shores Road Swisher Road Reconstruct Road from 2 to 2 lanes to elevate out of flood plain with drainage improvements $19,110,000 Major Collector NRSA1 DAL Reconstruct and Widen FM 455 SH 5 Wildwood Trail Reconstruct and widen 2 to 4 lane urban divided (ultimate 6 lanes) $26,596,569 Minor Arterial NRSA1 DAL East Bear Creek Road Hampton Road IH 35E Reconstruct and widen from 2 lane rural undivided to 4 lane urban divided (ultimate 6) with bicycle/pedestrian accomodations with intersection improvements $25,825,442 Minor Arterial H.8

9 Revised June 19, 2018 Fort Worth District NRSA1 FTW Addition of lanes FM 156 US 81/287 Watauga Road (McElroy) Reconstruct and Widen 2 lane to 4 lane divided $61,509,400 Major Collector NRSA1 FTW Addition of lanes FM 3391 IH 35W East of CR 602 Widen from 2 lanes to 6 lanes from IH 35W to Hurst Avenue and 2 lanes to 4 lanes from Hurst Avenue to CR 602 $35,273,646 Minor Arterial NRSA1 FTW Chapel Creek Blvd At IH 30 Construct New 6 lane bridge with 4 Thru lanes, 2 Left turn lanes, a Separate U turn bridge to Include Rightturn lanes, approaches, Pedestrian Improvements, Signalization, Lighting, and Retaining Wall Improvements $12,685,953 Major Collector NRSA1 FTW Alsbury Hulen Street NRSA1 FTW White Settlement Road At Bypass Channel CR 1020 (approximately 0.2 Miles) Construction of a 4 lane extension of Alsbury Boulevard Construct 4 lane bridge at new location of proposed bypass channel for trinity river near CBD of Fort Worth $4,945,889 Minor Arterial $48,923,288 Major Collector NRSA1 FTW Rehabilitation FM 730 Approx. 3 Miles north of SH 114 SH 114 Widen and Reconst. from 2 lane to 2 lane urban For SHoulders and Safety, add turn lanes $15,845,000 Major Collector NRSA1 FTW Addition of lanes FM 1884 SH 171 South of B.B. Fielder Road Widen from 2 lane to 4 lane with raised median $12,103,299 Major Collector NRSA1 FTW Bike/Pedestrian Snider Street Extension Project On Main Street, Snider Street, and Northeast Parkway bounded by Main St to the south, Northeast Pkwy on the north, Davis Blvd on the east & Smithfield Rd on the west Main Street to the south, Northeast Parkway on the north, Davis Blvd on the east & Smithfield Road on the west Pedestrian amenities; Landscaping; traffic signalization; Street construction includes extending Snider Street north to connect to Northeast Parkway (2 lanes), and Northeast Parkway west to connect to Snider Street (2 lanes) $2,927,324 (RTR Funded) NRSA1 FTW Bike/Pedestrian Joshua Station T.O.D. Infrastructure Project Bounded By Hwy 174 on the East Cleburne Rail Corridor on the West Pedestrian amenities; Landscaping; Street Construction Includes Extending Plum Street (4 lanes) $829,019 N/A Railwayhighway grade crossing H.9

10 Revised June 19, 2018 Fort Worth District NRSA1 FTW Safety Peach Street area Peach Street Live Oak Connector Construct the Live Oak Connector; Close Peach Street and East 1St Street at Up crossing; and Install Fences to Restrict Pedestrian access across the RR Tracks $3,200,254 Major Collector NRSA1 FTW Bridge, grade separation, Improvement, Reconstruction Bailey Boswell At BUS 287P Improvement Construct 0 to 2 lane overpass/bridge over UPRR, BNSFRR, & BUS 287P $12,390,990 Major Collector NRSA1 FTW Bike/Pedestrian Meandering Road SH 183 to Gillham Road LTJG Barnett Road from Gillham Road to Military Parkway Realign and add traffic signal at Roberts Cut off, Construct Roundabout at LTJG Barnett, Reconstruct Meandering Road from 4 to 3 lanes, and add sidewalks and Bicycle lanes $17,334,010 Minor Arterial NRSA1 FTW Reconstruct Main Street (FM 1187 BUS) Crowley Road (FM 731) Beverly Street Reconstruct from 3 to 2 lanes, add bicycle lanes, new sidewalks, add on street parking, construct two roundabouts $11,677,376 Minor Arterial NRSA1 FTW Bike/Pedestrian Hurst Bellaire Sd Project Bounded By Pipeline On The North; Brown Trail On The West Pecan Street On The South; Bellaire On The East Pedestrian amenities; Landscaping; Improvements; Signalization; Street Construction Realigning 4 lane Brown Trail Ave $973,368 Major Collector/ Principal NRSA1 FTW Reconstruction, grade separation, US 81/US 287 Ramp Improvements At FM 3479/Harmon Road/North Tarrant Parkway Construct North Tarrant Parkway over US 287 with turnaround on eastside; Construct Harmon Rd over US 287; Reconstruct existing SB entrance ramp to US 287 W/auxiliary lane $8,068,892 Other Freeway/ Expressway NRSA1 FTW Reconstruction, grade separation, Int. of US 81/287 at FM FM 1810 East of Public Road Improvement of FM 1810 and grade separation and Retaining Walls at Realigned at US 81/287 & Bu 81D $41,709,417 Major Collector NRSA1 FTW Reconstruct Holiday lane IH 820 Lewis Drive Reconstruct 4 to 4 lane roadway $1,700,000 Major Collector H.10

11 Revised June 19, 2018 Fort Worth District NRSA1 FTW Addition of lanes, Bridge, Rail Transit, Reconstruction FM 157 Main Street 8TH Street 7th Street Realign roadway 2 lane rural to 2 lane urban with sidewalks and turn lanes $4,353,344 Major Collector NRSA1 FTW Addition of lanes, Bridge, Rail Transit, Reconstruction FM 157 US 67 8th Street Realign roadway 2 lane rural to 2 lane urban with sidewalks and turn lanes $9,928,344 Minor Arterial NRSA1 FTW Reconstruct Glade Road NB SH 360 Frtg West Airfield Drive Reconstruct from 2 to 2 lanes (add center turn lane and shoulders) $5,942,036 Minor Arterial NRSA1 FTW Improvement On Lakeshore Drive At US 180/IH 20 Improvements at Lakeshore Drive, US 180, and IH 20 frontage roads, construct turnaround Bridge, and widen existing Lakeshore Drive Bridge to accommodate turn lanes $9,632,465 Major Collector H.11

12 Revised June 19, 2018 Paris District NRSA1 PAR SS 1570 SH 66 US 380 Construct 2 lanes (4 lane ultimate) divided highway on new location $11,904,439 Major Collector NRSA1 PAR FM 2642 FM 35 SH 66 Widen 2 lane to 4 lane divided urban with sidewalks $23,728,088 Major Collector NRSA1 PAR FM 1570 IH 30 SH 66 Construct 2 lane to 4 lane divided with shoulders (HMAC Pavement and RR crossing) North Project $23,507,081 Major Collector H.12

13 Revised June 19, 2018 Frontage Roads TIP Code Project Type CSJ Facility From To Description , , NRSA , Reconstruction US 81/287 SH 114 Wise/Tarrant County Line Convert frontage roads to 4/6 One Way Operation $139,896,000 NRSA Rehabilitation US 287 On US 81/US 287 From FM 3479 (Harmon Road) South of North Tarrant Parkway Crossover Reconstruct Northbound Frontage Road And Exit Ramp South of FM 3479 $3,320,649 NRSA Rehabilitation US 287 On US 81/US 287 From FM 3479 (Harmon Road) Southbound Entrance Ramp Construct Turnaround from NB to SB at North Tarrant Parkway; Reconstruct existing southbound frontage road from FM 3479 to US 287 $3,313,133 NRSA Rehabilitation US 287 On US 81/US 287 From North Entrance/Exit Ramp North FM 3479 (Harmon Road) Reconstruct NB frontage road from FM 3479 to Ramp and southbound frontage road from ramp to FM 3479 $3,313,131 NRSA Rehabilitation US 81/287 North of FM 3479 North of IH 35W interchange Construct auxiliary lane from northbound entrance from FM 3479 and IH 35W to North Tarrant Parkway; auxiliary lane for southbound exit to FM 3479 and entrance from North Tarrant $3,352,548 NRSA Rehabilitation US 81/287 Tarrant/Wise County Line IH 35W Convert frontage roads from 4 disc. frtg roads to 4/6 con. frtg roads one way operation $47,783,614 NRSA New Roadway US 287 Heritage Pkwy Johnson County Line Construct 0 to 4 lane frontage roads NRSA New Roadway US 287 Tarrant County Line BU 287 Construct 0 to 4 lane frontage roads NRSA New frontage roads SH 114 FM 1938 Dove Road Construct 0 to 2 lane EB frontage road from FM 1938 to Solana/Kirkwood and construct 0 to 2 lane WB and 0 to 2 lane EB frontage roads from Solana/Kirkwood to Dove $1,657,177 $6,405,530 $37,301,365 NRSA New Roadway SH 114 Freeport Parkway Esters Blvd NRSA New Roadway IH 635 Royal lane West of Belt Line Rd NRSA New Roadway IH 635 South of Gross Rd US 80 Construct WB 0 to 2 lane Frontage Road and Ramp Modifications Construct 0 to 2 lane WB Frontage Road and Ramp Modifications Construct Northbound Frontage Road to Provide Access to Galloway Avenue, And Ramp Improvements at Gross Rd $4,350,854 $33,554,913 $10,924,920 NRSA New Roadway IH 30 SH 161 NW 7th Street Construct 0 to 4 lane frontage roads $31,640,353 NRSA New Roadway IH 30 NW 7th Street Belt Line Road Construct 0 to 2/3 lane WB Frontage Road And Ramp Modifications $21,977,250 NRSA New Roadway IH 30 Belt Line Rd Macarthur Blvd Construct 3 lane frontage roads On Each Side (Eb And WB) $32,731,618 H.13

14 Revised June 19, 2018 Frontage Roads TIP Code Project Type CSJ Facility From To Description NRSA Addition of lanes, New Roadway, Bridge, Interchange IH 30 Bass Pro Drive Dalrock Rd Construct 0 to 6 lane frontage roads, Bayside Bridge, And Ramp Modifications; Reconstruct Dalrock Interchange $148,954,586 NRSA New Roadway IH 30 Dalrock Horizon NRSA Interchange IH 30 At FM 3549 NRSA New Roadway, Reconstruction IH 20 On IH 20 frontage roads From Centerpoint Road Lakeshore Drive Construct 0/4 to 4/6 lane frontage roads; Reconstruct Horizon Rd interchange and ramp modifications Reconstruct Interchange at FM 3549 Including 2/3 lane Frontage Rds And Ramps Construction Construct New Eastbound 2/3 lane Frontage Road And Reconstruct Existing 2 lane Portion of Eastbound Frontage Road to 2/3 lane Frontage Road West of Lakeshore Drive (Phase 1B of 3) $89,889,572 $111,933,568 $14,379,742 NRSA Addition of lanes, Bridge, Reconstruction IH 20 Bankhead Highway Centerpoint Road Reconstruct 2 lane Bridge to 1 lane U Turn Bridge, Construct 0 to 4 lane Bridge at Centerpoint Rd, Construct 0 to 4/6 lane frontage roads on IH 20 and Ramps $27,615,937 NRSA Addition of lanes IH 20 West of Bankhead Highway East of Bankhead Highway NRSA , Reconstruct and widen 2 lane bridge to 4 lane bridge at Bankhead over IH 20, ramp modifications and 2 lane frontage roads in each direction with an auxiliary lane between ramps west of Bankhead, construct new U Turn bridge east of Bankhead New Roadway IH 20 Sh 161/Lakeridge Parkway East of Carrier Parkway Construct 0 to 6 lane frontage roads and ramp modifications $44,389,365 NRSA New Roadway IH 20 West of Haymarket Rd West of US 175 Construct 2 lane EB And WB frontage roads and new ramps $8,744,273 $250,000 NRSA New Roadway, Bike/Pedestrian IH 20 West of Carrier Parkway FM 1382 (Belt Line Road) Construct 0 to 6 lane frontage roads, ramp modifications, and sidewalks $35,543,589 NRSA New Roadway IH 20 North Main Street Camp Wisdom Road Construct 0 to 4 lane frontage roads $8,054,299 NRSA , New Roadway IH 20 West of Cockrellhill Rd Hampton Rd Construct 0 to 4 lane frontage roads $35,114,451 NRSA New Roadway IH 20 Lawson Road Kaufman County Line Add 0 to 4 lanes continuous frontage roads $77,263,210 NRSA New Roadway SP 557 FM 148 IH 20 New location two lane frontage road eastbound only $4,266,024 NRSA New Roadway US 175 FM 148 CR 4106 in Crandall Construct new 2 lane frontage roads; Convert existing frontage road from 2 lane 2 way to 2 lane 1 way frontage road & ramp modifications $19,922,969 H.14

15 Revised June 19, 2018 Frontage Roads TIP Code Project Type CSJ Facility From To Description NRSA New Roadway IH 35W Eagle Parkway SH 114 NRSA NRSA Bike/Pedestrian, New Roadway New Roadway, Bottleneck Removal IH 35E Manana Drive Royal lane Construct 2 lane southbound frontage roads with ramp modifications (Phase 1) Construct new 0 to 2 lane frontage roads northbound from Manana Dr to Royal lane and southbound from Walnut Hill Lane to Manana Dr and pedestrian improvements along Walnut Hill Lane $35,080,152 $21,882, IH 35E Lombardy lane Spur 482 (Storey Rd) Construct 0 to 2 SB frontage road and ramp modifications $11,689,762 H.15

0.17 Miles West of Josey lane Danieldale Road IH 35E Houston School Road

0.17 Miles West of Josey lane Danieldale Road IH 35E Houston School Road NRSA1-DAL- 8 TxDOT Dallas 11005 Improvement 0918-45-864 Whitlock Road IH 35E Old Denton Road Reconstruct 4 lane undivided to 4 lane divided with left turns $3,802,480 Minor Arterial NRSA1-DAL- 11 TxDOT

More information

Transportation Improvement Program. Appendix H. Non-regionally Significant Arterials in Mobility Update

Transportation Improvement Program. Appendix H. Non-regionally Significant Arterials in Mobility Update 2015-2018 Transportation Improvement Program Appendix H Non-regionally Significant Arterials in Mobility 2035 2014 Update North Central Texas Council of Governments DFW Metropolitan Planning Organization

More information

10 Year Plan Cost/Revenue Matrix for the Dallas Fort Worth Region FY 2017 FY 2028

10 Year Plan Cost/Revenue Matrix for the Dallas Fort Worth Region FY 2017 FY 2028 Collin 54005 2351 01 017 FM 2478 FM 1461 to US 380 Collin 54005.1 2351 02 014 FM 2478 Collin 55038 2679 03 015 FM 2514 FM 1461 to North of FM 1461 East of Lavon Parkway to North of Drain Drive Widen two

More information

GENERAL DESCRIPTION. Page 1 of 5

GENERAL DESCRIPTION. Page 1 of 5 38. SH 114/SH 121 Corridor The DFW Connector : FT1345, FT 1347, FT1424, FR1424, FT1425, FR1425, FT1440, FT1500, FR1500, FT1505, FR1505, FT1507, FR1507, FT1510, FR1510, FT1715, FR1715, FT2720, FR2720, HM8190

More information

TABLE OF CONTENTS 7.0 THOROUGHFARE PLAN. Analysis of Future Conditions Thoroughfare Plan Proposed Cross-Sections.. 7.

TABLE OF CONTENTS 7.0 THOROUGHFARE PLAN. Analysis of Future Conditions Thoroughfare Plan Proposed Cross-Sections.. 7. TABLE OF CONTENTS 7.0 THOROUGHFARE PLAN Analysis of Future Conditions.. 7.2 Thoroughfare Plan.. 7.3 Proposed Cross-Sections.. 7.4 Arterials Minor Arterials Collectors Local Streets Thoroughfare Plan Map

More information

FY STIP. Austin District. November Quarterly Revisions HIGHWAY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM

FY STIP. Austin District. November Quarterly Revisions HIGHWAY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM FY 2011-2014 STIP STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM HIGHWAY Austin District November Quarterly Revisions November 2011 FY 2011-2014 Transportation Improvement Program Amendments October 10,

More information

Regional Transportation Committee (RTC) 10-Year Project Milestone Policy. Transportation and Trinity River Project Committee October 26, 2015

Regional Transportation Committee (RTC) 10-Year Project Milestone Policy. Transportation and Trinity River Project Committee October 26, 2015 Regional Transportation Committee (RTC) 10-Year Project Milestone Policy Transportation and Trinity River Project Committee October 26, 2015 Purpose of Briefing Brief the Transportation and Trinity River

More information

Master Development Plan for the TxDOT North Tarrant Express Project, Segments 2-4. Chapter 3: Draft List of Facilities.

Master Development Plan for the TxDOT North Tarrant Express Project, Segments 2-4. Chapter 3: Draft List of Facilities. Table of Contents 3.1. Interim vs. Ultimate Configuration for the Remaining Segments of NTE... 1 3.2. Characteristics of Project Segments... 3 3.2.1. All Segments... 5 3.2.2. Segment 2E... 8 3.2.3. Segment

More information

BASS PRO DRIVE TO: WEST OF FARM-TO-MARKET ROAD (FM)

BASS PRO DRIVE TO: WEST OF FARM-TO-MARKET ROAD (FM) NOTICE OF PUBLIC MEETING INTERSTATE HIGHWAY 30 (Rockwall) FROM: BASS PRO DRIVE TO: WEST OF FARM-TO-MARKET ROAD (FM) 2642 CSJs: 0009-11-238; 0009-12-215; 0009-12-908 Dallas County and Rockwall County, Texas

More information

NEW BRAUNFELS SEGUIN AREA REGIONAL TRANSPORTATION DRAFT PLAN NEW BRAUNFELS CITY COUNCIL MEETING

NEW BRAUNFELS SEGUIN AREA REGIONAL TRANSPORTATION DRAFT PLAN NEW BRAUNFELS CITY COUNCIL MEETING NEW BRAUNFELS SEGUIN AREA REGIONAL TRANSPORTATION DRAFT PLAN NEW BRAUNFELS CITY COUNCIL MEETING February 13, 2012 This regional transportation plan will: 1. Review existing plans for the cities and counties,

More information

NCTCOG DALLAS-FORT WORTH-ARLINGTON CATEGORY 7 RECAP FY 2013

NCTCOG DALLAS-FORT WORTH-ARLINGTON CATEGORY 7 RECAP FY 2013 NCTCOG DALLAS-FORT WORTH-ARLINGTON CATEGORY 7 RECAP FY 2013 Total Uncommitted Funds FY 2013 A + B = C C + D = E E - F = G A B C D E F G Balance Carryover from FY 12 FY (includes all adjustments) Total

More information

TRANSPORTATION IMPROVEMENT PROGRAM MODIFICATIONS FEBRUARY 2009 REVISIONS

TRANSPORTATION IMPROVEMENT PROGRAM MODIFICATIONS FEBRUARY 2009 REVISIONS MOD TIP CODE 2008-274 12175.08, 12416.08, 12417.08, 12418.08, 12419.08, 12420.08, 12421.08, 12422.08 DENTON COUNTY TRANSPORTATION AUTHORITY (DCTA) - FY08 PROGRAM OF S - TRANSIT SECTION 5307 - URBANIZED

More information

Safety. Rural. District. Strategic Projects $4,150, to Maple Streett $6,117,000. west of Conway BNSF railroad. Georgia Street $549,080

Safety. Rural. District. Strategic Projects $4,150, to Maple Streett $6,117,000. west of Conway BNSF railroad. Georgia Street $549,080 Selected for $2 Billion Allocation Safety SLRTP Rural priority IH 35 Corridor Border and Port Trade 100 most congested Ports to Plains Corridor IH 69 Corridor Rural System Preservation Other High Corridors

More information

FY Transportation Improvement Program - DRAFT Alphabetical Listing of Roadway, Bicycle, Pedestrian and Rideshare Projects

FY Transportation Improvement Program - DRAFT Alphabetical Listing of Roadway, Bicycle, Pedestrian and Rideshare Projects -2022 Transportation Improvement Program - DRAFT Project Number Alamo Area Commute Solutions Pgm - FY 2017 5101.0 0915-12-547 AACOG Alamo Area Commute Solutions Pgm - FY 2018 5102.0 0915-12-543 AACOG Alamo

More information

Proposed Project I 35 from Denton to Cooke County Line

Proposed Project I 35 from Denton to Cooke County Line Proposed Project I 35 from Denton to Cooke County Line The existing I 35 facility is four lanes from I 35E/I 35W to Farm to Market Road (FM) 3002. The purpose of the proposed project is to increase capacity

More information

FY 2006 TRANSPORTATION CAPITAL PROGRAM

FY 2006 TRANSPORTATION CAPITAL PROGRAM Eden Lane Bridge over Whippany River NS9908 The existing structure was built in 1972 as a temporary single-span structure. The bridge consists of simply supported steel acrow panel trusses and is supported

More information

Short and Long Term Needs

Short and Long Term Needs Short and Long Term Needs The short- and long-term programs of proposed projects listed below have been designed to address the mobility issues in South Montgomery County. These improvements to the transportation

More information

North Central Texas Council of Governments

North Central Texas Council of Governments North Central Texas Council of Governments TO: Peggy Thurin, P.E. DATE: September 25, 2018 Texas Department of Transportation FROM: Jenny Narvaez Program Manager SUBJECT: Transmittal of the Draft Congestion

More information

EXHIBIT A. Revised List of Projects Originally Approved by the Commission in Minute Order Dated November 19, 2009.

EXHIBIT A. Revised List of Projects Originally Approved by the Commission in Minute Order Dated November 19, 2009. Value from &! M East HOU M East HOU M East HOU &! M East HOU &! M East HOU IH 45 0271-14-217 0271-14-218 0271-14-213 0271-14-228 0500-03-462 0500-03-550 0500-03-565 Reconstruct US /IH 610 IC. Construct

More information

APPENDIX D: SACRAMENTO URBAN AREA TRANSPORTATION PRIORITIES

APPENDIX D: SACRAMENTO URBAN AREA TRANSPORTATION PRIORITIES 1 County County County County 2 Yolo Arterial Roadway Collector Roadway Urban Residential Street Rural Residential Roadway I-80 / U.S. 50 Bus/Carpool Lanes in both directions Richards Blvd PM Yol 80 0.237

More information

EXHIBIT B. Bass Lake Rd US 50 to Hollow Oak Rd 2 Lanes with unimproved median and 4 foot paved shoulders. $ %

EXHIBIT B. Bass Lake Rd US 50 to Hollow Oak Rd 2 Lanes with unimproved median and 4 foot paved shoulders. $ % Fee Program Project List - 2004 General Plan Cost Estimate 2004 Alternative Route Study West Valley Condition 27 Alternative connection between, Feasibility study. Included in /White Rock Connector. south

More information

PLEASE BE ADVISED THAT SOME OF THE INFORMATION IN THIS PRESENTATION IS OUTDATED SO IT IS ABLE TO SHOW CHANGES IN THE PLAN OVER TIME.

PLEASE BE ADVISED THAT SOME OF THE INFORMATION IN THIS PRESENTATION IS OUTDATED SO IT IS ABLE TO SHOW CHANGES IN THE PLAN OVER TIME. 1 PLEASE BE ADVISED THAT SOME OF THE INFORMATION IN THIS PRESENTATION IS OUTDATED SO IT IS ABLE TO SHOW CHANGES IN THE PLAN OVER TIME. - SANDRA GREEN, CITY SECRETARY FARMERSVILLE CITY COUNCIL MEETING February

More information

A: PLANNED P ROJECTS PROJECTS

A: PLANNED P ROJECTS PROJECTS Appendix A: PLANNED PROJECTS Programming Study Sound Barrier along south side of for approx. 2100 feet. Construction Complete $850,000 5 8613.00 Y Y Y Sound Barrier along south side of for 500' west of

More information

ARTINSVILLE ENRY OUNTY REA RANSPORTATION TUDY

ARTINSVILLE ENRY OUNTY REA RANSPORTATION TUDY ARTINSVILLE ENRY OUNTY REA RANSPORTATION TUDY DEVELOPED BY THE TRANSPORTATION AND MOBILITY PLANNING DIVISION OF THE VIRGINIA DEPARTMENT OF TRANSPORTATION IN COOPERATION WITH THE U.S. DEPARTMENT OF TRANSPORTATION,

More information

APPENDIX D COST SUMMARY TABLES

APPENDIX D COST SUMMARY TABLES APPENDIX D COST SUMMARY TABLES Section 1 Between Route 50 and Evergreen Mills Road 3850 linear feet of one 12 foot wide additional lane in southbound direction of Rte 606; from north side of Rte 50 to

More information

Appendix C. NORTH METRO STATION AREA TRAFFIC IMPACT STATEMENT 88th Avenue Station

Appendix C. NORTH METRO STATION AREA TRAFFIC IMPACT STATEMENT 88th Avenue Station Appendix C NORTH METRO STATION AREA TRAFFIC IMPACT STATEMENT 88th Avenue Station Prepared for: Regional Transportation Department and URS Corporation as part of the North Metro EIS David Evans and Associates,

More information

"Mobility 2045" Alphabetical Listing of Roadway, Bicycle, Pedestrian and Rideshare Projects

Mobility 2045 Alphabetical Listing of Roadway, Bicycle, Pedestrian and Rideshare Projects Number Alamo Area Commute Alamo Area MPO: Bexar, Comal Guadalupe & partial Kendall County AACOG Solutions Program Alamo Area Commute Solutions Pgm - FY 2017 $100,000 5101.0 0915-12-547 7/2018 Bexar Alamo

More information

Legislative Update. Frederick County Fall Staunton District. Interstate 81 - Exit 300 at Interstate 66 Southbound Acceleration Lane Extension

Legislative Update. Frederick County Fall Staunton District. Interstate 81 - Exit 300 at Interstate 66 Southbound Acceleration Lane Extension Interstate 81 - Exit 300 at Interstate 66 Southbound Acceleration Lane Extension Application ID 1643 Northern Shenandoah Valley Regional Commission (NSVRC) $3,437,423 This project extends the Interstate

More information

Bluffdale/ UDOT South High-T Intersection Project Type Operations

Bluffdale/ UDOT South High-T Intersection Project Type Operations Bluffdale/ UDOT 14600 South High-T Intersection Project Type Operations 14600 South and Redwood Road $ 600,000 $ 550,000 This project is to install a new High-T intersection at Redwood Road and 14600 South

More information

TRASBURG RANSPORTATION

TRASBURG RANSPORTATION TRASBURG RANSPORTATION LAN DEVELOPED BY THE TRANSPORTATION PLANNING DIVISION OF THE VIRGINIA DEPARTMENT OF TRANSPORTATION IN COOPERATION WITH THE U.S. DEPARTMENT OF TRANSPORTATION, FEDERAL HIGHWAY ADMINISTRATION

More information

Town of Flower Mound Master Transportation Plan Update

Town of Flower Mound Master Transportation Plan Update Town of Flower Mound Master Transportation Plan Update Town Council January 5, 2009 Agenda Project Schedule Why we re here Recommended Changes to MTP; plus: Transportation Commission Recommendations (11/11/08)

More information

STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM FY

STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM FY 008-0 Austin District NOVEMBER 007 Quarterly Revisions CAMPO Capital Area Metropolitan Planning Organization October 5, 007 Mr. Robert Daigh, P.E. District

More information

Project Description Form 8EE

Project Description Form 8EE Project Description Form 8EE Basic Project Information Submitting Jurisdiction/Agency: Town of Dumfries Project Title: Route 1 (Fraley Blvd) Widening: Brady's Hill Road to Dumfries Road Project Location:

More information

Harrah s Station Square Casino

Harrah s Station Square Casino Transportation Analysis Harrah s Station Square Casino Pittsburgh, Pennsylvania Submitted To: City of Pittsburgh and Pennsylvania Gaming Control Board Prepared By: DKS Associates GAI Consultants December

More information

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Projects

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Projects ROUTE/ Project ID No. TIP No. Electrical Load Center Replacement - North 04324 04324 This project will provide for the betterment of the existing highway lighting facilities located along Routes 3, 17

More information

FAIRFIELD INN & SUITES HOTEL 135 THAD JOHNSON PRIVATE OTTAWA TRANSPORTATION BRIEF. Prepared for:

FAIRFIELD INN & SUITES HOTEL 135 THAD JOHNSON PRIVATE OTTAWA TRANSPORTATION BRIEF. Prepared for: FAIRFIELD INN & SUITES HOTEL 135 THAD JOHNSON PRIVATE OTTAWA TRANSPORTATION BRIEF Prepared for: Bona Building & Management Co. Ltd. Place Vanier, 333 North River Road Vanier, Ontario K1L 8B9 August 12,

More information

MEDICAL/OFFICE BUILDING 1637 BANK STREET OTTAWA, ONTARIO TRANSPORTATION OVERVIEW. Prepared for:

MEDICAL/OFFICE BUILDING 1637 BANK STREET OTTAWA, ONTARIO TRANSPORTATION OVERVIEW. Prepared for: MEDICAL/OFFICE BUILDING 1637 BANK STREET OTTAWA, ONTARIO TRANSPORTATION OVERVIEW Prepared for: 2434984 Ontario Inc. 13-5510 Canotek Road Ottawa, Ontario K1J 9J5 June 4, 2015 115-613 Report_2.doc D. J.

More information

Project Fact Sheet. August 1,

Project Fact Sheet. August 1, Fact Sheet City of Gainesville Transportation Master Plan In December 2012, the Mayor and City Council selected a consultant team of Pond & Company and Arcadis to prepare the City of Gainesville Transportation

More information

APPROVED PROJECTS RESCHEDULED FROM AUGUST TO SEPTEMBER :19 Thursday, June 13,

APPROVED PROJECTS RESCHEDULED FROM AUGUST TO SEPTEMBER :19 Thursday, June 13, APPROVED PROJECTS RESCHEDULED FROM AUGUST TO SEPTEMBER 2013 14:19 Thursday, June 13, 2013 1 ABILENE DISTRICT FUNC AUTHORIZED TOTAL EST OVER- TAYLOR 0034-01-124 US 83 C 34-1-124 5 3.2 P14BM $2,112,500 $3,721,952

More information

EXHIBIT B-1 PROJECT DESCRIPTION. Phase 1 of the Preferred Alternative

EXHIBIT B-1 PROJECT DESCRIPTION. Phase 1 of the Preferred Alternative EXHIBIT B-1 PROJECT DESCRIPTION Phase 1 of the Preferred Alternative The Transform 66 Public-Private Partnership (P3) Project (the Project ) means the Phase 1 of the Preferred Alternative components of

More information

I-264 CORRIDOR EVALUATION STUDY. September 7, 2016 Eric Stringfield VDOT Planning Director Chris Lawrence AECOM Senior Transportation Engineer

I-264 CORRIDOR EVALUATION STUDY. September 7, 2016 Eric Stringfield VDOT Planning Director Chris Lawrence AECOM Senior Transportation Engineer I-264 CORRIDOR EVALUATION STUDY September 7, 2016 Eric Stringfield VDOT Planning Director Chris Lawrence AECOM Senior Transportation Engineer Study Overview Interchange Locations Study Context Follow-up

More information

Design Criteria. Design Criteria

Design Criteria. Design Criteria F Design Criteria Design Criteria Ministry of Transportation Ministère des Transports DESIGN CRITERIA Page: 1 of 13 WORK PROJECT NO. N/A GO Bloomington Station TYPE OF PROJECT LOCATION Bloomington Road

More information

State Route 160 (Blue Diamond Highway)

State Route 160 (Blue Diamond Highway) State Route 160 (Blue Diamond Highway) ~ Multi-Year Expansion Program ~ Highway Improvement Projects in Clark and Nye Counties EXHIBIT G Treasures Document consists of 16 slides. Entire exhibit provided.

More information

FI-2 I-66 Between Route 29, Lee Highway and Route 15, James Madison Highway

FI-2 I-66 Between Route 29, Lee Highway and Route 15, James Madison Highway TRANSPORTATION PLAN INTENT Transportation is the key to the economic and social development of Prince William County and especially to the I 66/Route 29 Sector Plan area. This includes transportation for

More information

HILTON GARDEN INN HOTEL HOTEL EXPANSION 2400 ALERT ROAD, OTTAWA TRANSPORTATION BRIEF. Prepared for:

HILTON GARDEN INN HOTEL HOTEL EXPANSION 2400 ALERT ROAD, OTTAWA TRANSPORTATION BRIEF. Prepared for: HILTON GARDEN INN HOTEL HOTEL EXPANSION 2400 ALERT ROAD, OTTAWA TRANSPORTATION BRIEF Prepared for: Bona Building & Management Co. Ltd. Place Vanier, 333 North River Road Vanier, Ontario K1L 8B9 October

More information

APPENDIX G: INTERSECTION NEEDS AT OKEECHOBEE BOULEVARD

APPENDIX G: INTERSECTION NEEDS AT OKEECHOBEE BOULEVARD APPENDIX G: INTERSECTION NEEDS AT OKEECHOBEE BOULEVARD INTERSECTION NEEDS AT SR 7 and OKEECHOBEE BOULEVARD SR 7 Extension Project Development and Environment (PD&E) Study From Okeechobee Boulevard (SR

More information

4. ENVIRONMENTAL IMPACT ANALYSIS 9. TRANSPORTATION AND TRAFFIC

4. ENVIRONMENTAL IMPACT ANALYSIS 9. TRANSPORTATION AND TRAFFIC 4. ENVIRONMENTAL IMPACT ANALYSIS 9. TRANSPORTATION AND TRAFFIC 4.9.1 INTRODUCTION The following section addresses the Proposed Project s impact on transportation and traffic based on the Traffic Study

More information

Transportation Corridor Studies: Summary of Recommendations

Transportation Corridor Studies: Summary of Recommendations Transportation Corridor Studies: Summary of Recommendations Route 4 Corridor Study: Route 10 Corridor Study: Route 44 Corridor Study: Route 175 Corridor Study: Route 5/15 Corridor Study: Rentschler Field

More information

FI N A N C I A L RESOURCER S REVIEW AND UPDATE M I A M I-DADE LO N G R A N G E TRANSPORT T ATION PLAN UPDATE TO THE YE

FI N A N C I A L RESOURCER S REVIEW AND UPDATE M I A M I-DADE LO N G R A N G E TRANSPORT T ATION PLAN UPDATE TO THE YE Appendix B: Miami-Dade LRTP Cost Feasible Projects (Fully Funded and Partially Funded Projects) Fully Funded Projects Existing County roads O&M $317.9 $316.7 $811.5 Non Motorized set aside $27.9 $24.7

More information

FM 1092/Murphy Road Access Management Study Pulic Meeting #1. Wednesday, August 31, :00 p.m. 8:00 p.m.

FM 1092/Murphy Road Access Management Study Pulic Meeting #1. Wednesday, August 31, :00 p.m. 8:00 p.m. FM 1092/Murphy Road Access Management Study Pulic Meeting #1 Wednesday, August 31, 2011 6:00 p.m. 8:00 p.m. Introductions Agency Partners H-GAC Missouri City TxDOT Introductions Consulting Team In Association

More information

MOUNTAIN HOUSE SPECIFIC PLAN I 9.1 INTRODUCTION ASSUMPTIONS TRANSPORTATION FACILITIES TRANSPORTATION IMPROVEMENTS PHASING 9.

MOUNTAIN HOUSE SPECIFIC PLAN I 9.1 INTRODUCTION ASSUMPTIONS TRANSPORTATION FACILITIES TRANSPORTATION IMPROVEMENTS PHASING 9. CHAPTER NINE: TRANSPORTATION AND CIRCULATION 9.1 INTRODUCTION 9.1 9.2 ASSUMPTIONS 9.1 9.3 TRANSPORTATION FACILITIES 9.1 9.4 TRANSPORTATION IMPROVEMENTS PHASING 9.3 LIST OF FIGURES LIST OF TABLES Figure

More information

INDEX. Geometric Design Guide for Canadian Roads INDEX

INDEX. Geometric Design Guide for Canadian Roads INDEX Acceleration lane, see Lanes, Acceleration Access, 8.1 Access Management and Functional Classification 8.2 Access Management by Design Classification 8.3 Access Configuration 8.4 Building Set-Back Guidelines

More information

INTERSTATE 540 IMPROVEMENT STUDY

INTERSTATE 540 IMPROVEMENT STUDY INTERSTATE 540 IMPROVEMENT STUDY WASHINGTON COUNTY AND BENTON COUNTY APRIL, 2006 INTERSTATE 540 IMPROVEMENT STUDY WASHINGTON COUNTY AND BENTON COUNTY April, 2006 Prepared by Parsons Transportation Group

More information

Ave C to Ave J Repair and installation of sidewalks along eastern side of Main St

Ave C to Ave J Repair and installation of sidewalks along eastern side of Main St 2040 Metropolitan Transportation Plan Project Listing Short Range Funded (2014-2023) Projects with Allocated as of June 2017 and Listed in the Transportation Improvement Program (TIP) CATEGORY 7 PROJECTS

More information

I-20 ODESSA-MIDLAND CORRIDOR STUDY. Public Meeting for Schematic Design

I-20 ODESSA-MIDLAND CORRIDOR STUDY. Public Meeting for Schematic Design I-20 ODESSA-MIDLAND CORRIDOR STUDY Public Meeting for Schematic Design The environmental review, consultation, and other actions required by applicable Federal environmental laws for this project are being,

More information

3.0 Future Conditions

3.0 Future Conditions 3.0 Future Conditions In order to be able to recommend appropriate improvements to the transportation system of the Town, it is important to first understand the nature and volume of traffic that is expected

More information

Southwest Bus Rapid Transit (SW BRT) Functional Planning Study - Executive Summary January 19 LPT ATTACHMENT 2.

Southwest Bus Rapid Transit (SW BRT) Functional Planning Study - Executive Summary January 19 LPT ATTACHMENT 2. Southwest Bus Rapid Transit (SW BRT) Functional Planning Study - Executive Summary 2011 January 19 1 of 19 Introduction This executive summary presents the results of the Southwest Bus Rapid Transit (SW

More information

Northwest Corridor Project Interchange Modification, Interchange Justification and System Analysis Report Reassessment (Phase I)

Northwest Corridor Project Interchange Modification, Interchange Justification and System Analysis Report Reassessment (Phase I) Northwest Corridor Project Interchange Modification, Interchange Justification and System Analysis Report Reassessment (Phase I) Introduction The Georgia Department of Transportation (GDOT) prepared a

More information

FY Transportation Improvement Program Alphabetical Listing of Roadway, Bicycle, Pedestrian and Rideshare Projects

FY Transportation Improvement Program Alphabetical Listing of Roadway, Bicycle, Pedestrian and Rideshare Projects -2022 Transportation Improvement Program Project Number Alamo Area Commute Solutions Pgm - 5301.0 0915-00-195 AAMPO Alamo Area Commute Solutions Pgm - 5302.0 0915-00-196 AAMPO Alamo Area Commute Solutions

More information

2011 Capital Projects University Area - Community Council Priority List Municipality of Anchorage

2011 Capital Projects University Area - Community Council Priority List Municipality of Anchorage 2011 Capital Projects University Area - Community Council Priority List Municipality of Anchorage 2 Project Management and Engineering Projects on 40th Ave Extension - Lake Otis Pkwy to Dale St $18,103,000

More information

MEETING FACILITY 2901 GIBFORD DRIVE CITY OF OTTAWA TRANSPORTATION BRIEF. Prepared for: Holiday Inn Express 2881 Gibford Drive Ottawa, ON K1V 2L9

MEETING FACILITY 2901 GIBFORD DRIVE CITY OF OTTAWA TRANSPORTATION BRIEF. Prepared for: Holiday Inn Express 2881 Gibford Drive Ottawa, ON K1V 2L9 MEETING FACILITY 2901 GIBFORD DRIVE CITY OF OTTAWA TRANSPORTATION BRIEF Prepared for: Holiday Inn Express 2881 Gibford Drive Ottawa, ON K1V 2L9 December 18, 2012 112-566 Brief_1.doc D. J. Halpenny & Associates

More information

Proposed Action, Purpose and Need Technical Memorandum

Proposed Action, Purpose and Need Technical Memorandum Proposed Action, Purpose and Need Technical Memorandum MoPac (State Loop 1) Intersections, Austin District From North of Slaughter Lane to South of La Crosse Avenue CSJ: 3136-01-015 Travis County, Texas

More information

INDUSTRIAL BUILDING 3009 HAWTHORNE ROAD CITY OF OTTAWA TRANSPORTATION OVERVIEW REVISED. Prepared for: Canada Inc.

INDUSTRIAL BUILDING 3009 HAWTHORNE ROAD CITY OF OTTAWA TRANSPORTATION OVERVIEW REVISED. Prepared for: Canada Inc. INDUSTRIAL BUILDING 3009 HAWTHORNE ROAD CITY OF OTTAWA TRANSPORTATION OVERVIEW REVISED Prepared for: 7849648 Canada Inc. Octiober 1, 2015 114-598 Overview_2.doc D. J. Halpenny & Associates Ltd. Consulting

More information

Brooklyn Boulevard (County Road 152) Reconstruction Project Phase I. OPEN HOUSE June 20, 2017

Brooklyn Boulevard (County Road 152) Reconstruction Project Phase I. OPEN HOUSE June 20, 2017 Brooklyn Boulevard (County Road 152) Reconstruction Project Phase I OPEN HOUSE June 20, 2017 Brooklyn Boulevard (County Road 152) Phase I Project Partners Project Lead Other Project Partners include Brooklyn

More information

I-40 Maumelle New Interchange and new 2-lane facility 48 $10.4 $29.8 Highest. Full ITS Implementation 55 $63.3 $144.5 Highest

I-40 Maumelle New Interchange and new 2-lane facility 48 $10.4 $29.8 Highest. Full ITS Implementation 55 $63.3 $144.5 Highest PROJECT PRIORITIES: FREEWAYS 92 Freeway System ITS 60 $2.3 $2.3 Highest 94 Freeway System ITS 60 $7.9 $10.2 Highest 65 North Cabot Interchange - Hwy 38 State Hwy 367 and State Hwy 38 US Hwy 67 / 167 New

More information

Preliminary Engineering Study

Preliminary Engineering Study Preliminary Engineering Study Open House # 2 June 6, 2018 PREPARED FOR: PREPARED BY: Agenda Background and status of preliminary engineering study County Road 26 design summary County Road 63 design summary

More information

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Projects

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Projects Barclay Street Viaduct NS9807 NS9807 This project will provide for the rehabilitation of the Barclay Street Viaduct, from Route 19 to Marshall Street, in order to increase the weight load of the structure.

More information

DRAFT BUENA VISTA 2020 TRANSPORTATION PLAN

DRAFT BUENA VISTA 2020 TRANSPORTATION PLAN DRAFT BUENA VISTA 2020 TRANSPORTATION PLAN DEVELOPED BY THE TRANSPORTATION PLANNING DIVISION OF THE VIRGINIA DEPARTMENT OF TRANSPORTATION IN COOPERATION WITH THE U.S. DEPARTMENT OF TRANSPORTATION, FEDERAL

More information

Access Routes from US 101 to the Richmond San Rafael Bridge

Access Routes from US 101 to the Richmond San Rafael Bridge Access Routes from US 101 to the Richmond San Rafael Bridge TAM Board Meeting January 28, 2016 RSRB Project Elements Eastbound Third Lane: Sir Francis Drake Blvd. to Marine Street 10 ft Barrier Separated

More information

SIOUX FALLS MPO 2018 OBLIGATED TRANSPORTATION IMPROVEMENT PROJECTS

SIOUX FALLS MPO 2018 OBLIGATED TRANSPORTATION IMPROVEMENT PROJECTS TOTAL LETTING DATE AWARD DATE NOTES Interstate Maintenance s 2.00 IM 0020(155) 04X N McCook Minnehaha 0.0 Mitchell Region on I90 Scour Protection $873,000 $960,000 Cancelled $0 $0 Minor Arterial 1.00 Minor

More information

Appendix B. Summary of Public Comments Tri County Health Department Comments

Appendix B. Summary of Public Comments Tri County Health Department Comments Appendix B Summary of Public Comments Tri County Health Department Comments PUBLIC COMMENTS RECEIVED AT THE OPEN HOUSES HELD ON NOVEMBER 17, 2010, NOVEMBER 18, 2010 AND NOVEMBER 22, 2010, AND FROM THE

More information

Circulation and Mobility

Circulation and Mobility SECTION 4 Circulation and Mobility OVERVIEW The first phase of the circulation analysis is to address specific concerns regarding the circulation system in the vicinity of the Gateway Specific Plan area

More information

OFFICE/RETAIL DEVELOPMENT 1625 BANK STREET OTTAWA, ONTARIO TRANSPORTATION BRIEF. Prepared for: Canada Inc.

OFFICE/RETAIL DEVELOPMENT 1625 BANK STREET OTTAWA, ONTARIO TRANSPORTATION BRIEF. Prepared for: Canada Inc. OFFICE/RETAIL DEVELOPMENT 1625 BANK STREET OTTAWA, ONTARIO TRANSPORTATION BRIEF Prepared for: 9402209 Canada Inc. December 15, 2015 115-625 Report_2.doc D. J. Halpenny & Associates Ltd. Consulting Transportation

More information

Southwestern RPO Prioritization Local Input Points for Division Needs Funding

Southwestern RPO Prioritization Local Input Points for Division Needs Funding H172327 US 19 Business paved shoulders; include bicycle lanes and sidewalks. Location: extends 0.9 miles from Junaluska Road in Andrews to US 19/74. $ 6,100,000 9.20 H090251-AC R-3622AC NC 294 (southern

More information

OTTAWA TRAIN YARDS PHASE 3 DEVELOPMENT CITY OF OTTAWA TRANSPORTATION IMPACT STUDY. Prepared for:

OTTAWA TRAIN YARDS PHASE 3 DEVELOPMENT CITY OF OTTAWA TRANSPORTATION IMPACT STUDY. Prepared for: OTTAWA TRAIN YARDS PHASE 3 DEVELOPMENT CITY OF OTTAWA TRANSPORTATION IMPACT STUDY Prepared for: The Ottawa Train Yards Inc. 223 Colonnade Road South, Suite 212 Nepean, Ontario K2E 7K3 January 17, 2012

More information

Chapter 5 Future Transportation

Chapter 5 Future Transportation Chapter 5 Future Transportation The Future Land Use Plan identifies the desired land use designations. The land uses desired for Crozet depend, in large part, on the success of the transportation system,

More information

Trans-Canada Highway 1 RW Bruhn Bridge Replacement

Trans-Canada Highway 1 RW Bruhn Bridge Replacement Trans-Canada Highway 1 RW Bruhn Bridge Replacement May 2016 RW Bruhn Bridge Project Objectives Improve safety, traffic flow and movement of goods Improve safety for pedestrians and cyclists Replace the

More information

MPO PROPOSITION 1/CATEGORY 2 PROJECTS (METROPOLITAN CORRIDORS)

MPO PROPOSITION 1/CATEGORY 2 PROJECTS (METROPOLITAN CORRIDORS) 2040 Metropolitan Transportation Plan Project Listing Short Range Funded (2014-2023) Projects with Allocated as of December 2018 and Listed in the Transportation Improvement Program (TIP) MPO PROPOSITION

More information

INDUSTRIAL BUILDING 1660 COMSTOCK ROAD CITY OF OTTAWA TRANSPORTATION OVERVIEW. Prepared for:

INDUSTRIAL BUILDING 1660 COMSTOCK ROAD CITY OF OTTAWA TRANSPORTATION OVERVIEW. Prepared for: INDUSTRIAL BUILDING 1660 COMSTOCK ROAD CITY OF OTTAWA TRANSPORTATION OVERVIEW Prepared for: Simluc Contractors Limited 2550 Blackwell Street, Ottawa K1B 5R1 October 18, 2013 113-584 Overview_1.doc D. J.

More information

Agenda Item No. 6C ATTACHMENT 1

Agenda Item No. 6C ATTACHMENT 1 ATTACHMENT District Bike Plan Proposed s Hillside Ln Livermore D TAC

More information

FDOT Treasure Coast Traffic Report

FDOT Treasure Coast Traffic Report July 6, 2018 Barbara Kelleher, 954 777 4090 Barbara.Kelleher@dot.state.fl.us FDOT Treasure Coast Traffic Report July 6 through July 13, 2018 TREASURE COAST Construction and maintenance related lane closures

More information

San Tomas Expressway

San Tomas Expressway Implementation Plan San Tomas Expressway Roads and Airports Department August 19, 2003 Implementation Plan San Tomas Expressway County of Santa Clara Roads and Airports Department 101 Skyport Drive San

More information

Chapter 6 Transportation Plan

Chapter 6 Transportation Plan Chapter 6 Transportation Plan Transportation Plan Introduction Chapter 6 Transportation Plan Transportation Plan Introduction This chapter describes the components of Arvada s transportation system, comprised

More information

STREET AND HIGHWAY PLAN

STREET AND HIGHWAY PLAN STREET AND HIGHWAY PLAN Introduction The street and highway system in the Winston-Salem Urban Area consists of thousands of miles of traffic carrying facilities, ranging from short local residential streets

More information

CITY OF LANCASTER PROPOSED NEW PROJECTS

CITY OF LANCASTER PROPOSED NEW PROJECTS CITY OF LANCASTER 2013-2014 PROPOSED NEW PROJECTS Project Code 11 Facilities and Fixtures Project Title 1 11BS018 Main. Yard Storage Bldg, Phase 2 2 11GS007 Parks Improvements 3 11GS008 Dog Park AHP 4

More information

Quiet Zones: Silencing Train Horns at Railroad Crossings

Quiet Zones: Silencing Train Horns at Railroad Crossings Quiet Zones: Silencing Train Horns at Railroad Crossings Council Transportation and Environment Committee Prepared by Public Works and Transportation Transportation Programs - Planning January 12, 2009

More information

PRESENTATION WILL BEGIN AT APPROXIMATELY 6:05 P.M. I-90 EXIT 406 INTERCHANGE MODIFICATION STUDY AND ENVIRONMENTAL ASSESSMENT MARKET

PRESENTATION WILL BEGIN AT APPROXIMATELY 6:05 P.M. I-90 EXIT 406 INTERCHANGE MODIFICATION STUDY AND ENVIRONMENTAL ASSESSMENT MARKET PRESENTATION WILL BEGIN AT APPROXIMATELY 6:05 P.M. MARKET I-90 EXIT 406 INTERCHANGE MODIFICATION STUDY AND ENVIRONMENTAL ASSESSMENT JANUARY 23, 2017 Public Meeting & Open House #2 TODAY S MEETING Purpose:

More information

Houma-Thibodaux Metropolitan Planning Organization STP<200K Funding Application APPLICATION

Houma-Thibodaux Metropolitan Planning Organization STP<200K Funding Application APPLICATION APPLICATION HOUMA-THIBODAUX METROPOLITAN PLANNING ORGANIZATION (HTMPO) FOR SURFACE TRANSPORTATION PROGRAM (STP

More information

Mobility Greater Johnson County Transportation Coalition. May 23, 2018

Mobility Greater Johnson County Transportation Coalition. May 23, 2018 Mobility 2045 Greater Johnson County Transportation Coalition May 23, 2018 Agenda Regional Perspective Mobility Planning Overview Mobility 2045 Draft Recommendations Financial Planning Overview Schedule

More information

CHAPTER 3.0: TRANSPORTATION IMPACTS

CHAPTER 3.0: TRANSPORTATION IMPACTS CHAPTER 3.0: TRANSPORTATION IMPACTS Chapter 4.0 of the Final Environmental Impact Statement (FEIS) provided information about transportation impacts of the Light Trail Transit (LRT) alternative, including:

More information

APPENDIX E GRADE CROSSING LOCATIONS

APPENDIX E GRADE CROSSING LOCATIONS APPENDIX E GRADE CROSSING LOCATIONS 1 2 3 Citrus Avenue Riverside County and City Palmyrita Avenue Columbia Avenue MP 0.57 002X-0.6 027301Y MP 1.00 002X-1.0 027302F MP 1.24 002X-1.3 027303M 1. Existing

More information

Route 79/Davol Street Corridor Study

Route 79/Davol Street Corridor Study Route 79/Davol Street Corridor Study Fall River, MA Public Information Meeting #2 November 21, 2013 Fall River Heritage State Park Fall River, MA Agenda Welcome and Introductions Overview of Study Process

More information

Replace Bridge 51 on Blackiston Mill Dr. over Silver Creek,

Replace Bridge 51 on Blackiston Mill Dr. over Silver Creek, INDIANA PROJECTS 1558 Bridge 51 1601823 1601971 I 64 Blackiston Mill Road Phase II Charlestown Rd. Clark State Forest Road Maintenance E. Main Street Improvements to Blackiston Mill Road from just north

More information

Welcome to the Sellwood Bridge Project Open House!

Welcome to the Sellwood Bridge Project Open House! Welcome to the Sellwood Bridge Project Open House! 5:30 7:30 pm Please sign in here Information stations and project staff are located throughout the room. Goals for Tonight s Meeting: Learn how the Preferred

More information

Meadow Woods Elementary School

Meadow Woods Elementary School Drag and drop pic and stretch/crop to the limits of the blue rectangle (delete this text box) Meadow Woods Elementary School Drag and drop pic and stretch/crop to the limits of the blue rectangle (delete

More information

4.0 Recommended Transportation Plan

4.0 Recommended Transportation Plan 4.0 Recommended Transportation Plan The Town wants to provide a multi modal transportation system for its residents in order to provide them with options when making trips. The automobile has always been

More information

PEDESTRIAN ACCOMMODATIONS DPS 201 AT INTERCHANGES

PEDESTRIAN ACCOMMODATIONS DPS 201 AT INTERCHANGES PEDESTRIAN ACCOMMODATIONS DPS 201 AT INTERCHANGES UNDERSTANDING THE ISSUES Intersections of freeway ramp terminals at crossroads are the most critical components of an interchange Challenge: balance mobility

More information

Appendix E Transportation Plan Projects

Appendix E Transportation Plan Projects Appendix E Transportation Plan Projects THIS PAGE INTENTIONALLY LEFT BLANK 2035 Major Thoroughfare Plan & Multi Modal Connections Unincorporated Sumner County Road From To NORTHWEST US 31W/SR 41 SR 25

More information

State Road 54/56 Tampa Bay s Northern Loop. The Managed Lane Solution Linking I-75 to the Suncoast Parkway

State Road 54/56 Tampa Bay s Northern Loop. The Managed Lane Solution Linking I-75 to the Suncoast Parkway State Road 54/56 Tampa Bay s Northern Loop The Managed Lane Solution Linking I-75 to the Suncoast Parkway SUNCOAST PARKWAY Both I 75 and the Suncoast Parkway are planning, or in the process of constructing,

More information

ROAD PROJECTS. Primary and Interstate Roads LRTP; Southern- Western Neighborhoods MP

ROAD PROJECTS. Primary and Interstate Roads LRTP; Southern- Western Neighborhoods MP Desktop > Trans Priorities 0 >TRANPSORTATION PRIORITIES > new priority list format.doc ALBEMARLE COUNTY TRANSPORTATION PRIORITIES (DRAFT) April, 0: The following are the counties strategies priorities

More information