1 Hautbois Risk Assessment Activity: Estate Assessor: Rachel Jarman Date: January 2012 Tech Advisor: Martin Review Date: January 2013 Page: 1 of 8 Description: The Hautbois Estate comprises 28 acres of parkland, campsites, meadow, shrubbery, woodland, and activity areas. It is divided by a road. Significant Hazard Who Might be Harmed and Existing Controls How Use of Electrical Appliances Hautbois User and All employees are authorised to operate electrical appliances. All electrical appliances to be inspected and tested on a regular basis in accordance with safety policy. Any defects are reported to the manager. Employees are prohibited from carrying out any repairs or modifications to any electrical equipment. Employees are prohibited from bringing their own electrical appliances into the workplace unless they have been inspected and tested in accordance with statutory requirements. The correct type of equipment is purchased for use in offices and workshops and equipment is only used for the purpose it has been designed for. Employees are instructed on the correct and safe operation of equipment, in accordance with manufactures instructions. Occupational Driving Site visits are arranged to ensure the number of hours worked including those spent driving does not exceed 10 per day. If employees become drowsy whilst driving they should take a break. When necessary employees should stop at a hotel and continue their driving in the morning. All employees must hold a full and current driving license. Copies of driving licenses must be provided to the company annually. Employees do not give lifts to unknown persons whilst on company business.

2 Review Date: January 2013 Page: 2 of 8 Operating ride on lawn mowers and self driven petrol mowers; Impact with person. Operating ride on lawn mowers and self driven petrol mowers; Fire explosion from Petrol Fuel. Hautbois Users and Users and Eye protection to be worn Mower on planned preventive maintenance (PPM) regime as per manufactures instruction. Safety footwear to be worn Suitable eye protection to be worn and particle masks. Back fill rabbit holes Fuel is stored in an appropriate container and is marked accordingly. Re fuelling is carried out in a well ventilated area away from sources of ignition. Operating ride on lawn mowers and self driven petrol mowers; Injuries caused by noise and vibration Ear defenders to be worn at all times whilst machinery in operation, anti vibration gloves to be worn ensure that blades are balanced properly prior to fitting and during PPM. Operating Tractor -Overturning Tractor to be maintained to manufactures recommendation and serviced every year. Only designated and competent operatives to drive tractor. Over turning controlled by measures in step 9 of INDG185. Designated safe routes to be followed. Operating Tractor - Falls from Cab Operating Tractor - Entanglement with PTO Shaft Users and Only designated and competent operatives to drive tractor. Operatives trained in safe manual handling technique Driver trained and assessed per INDG 185. Tractor serviced and pre use checks carried out. Driver trained and assessed per INDG 185. Operating tractor - Whole body Vibration Hitching and coupling of trailer and other equipment carried out in accordance with set procedures utilising SAFE STOP. Log kept of hours use don work equipment which has the potential cause for whole body vibration. For prolonged use ear defenders to be warn.

3 Review Date: January 2013 Page: 3 of 8 Operating tractor - Impact with person Operating power take off. -entanglement with moving parts: acute physical injury Hautbois Users and Driver trained and assessed per INDG 185 Persons to be clear of potential line of travel of tractor and/or trailer. Designated safe routes to be followed. Keys to be removed to prevent third parties using the tractor. PTO Guarded and checks are made pre use. PTO shaft is guarded in its entirety All work is done in accordance with Power take offs and power take offs Drive shafts AS24 (included in folder) Restraining chain device is used at all times. Using Cutting Deck See general PTO section above in addition to this. Cutting deck checked before use. When jacked for blade change additional supports used to prevent entrapment. Blades changed as required. Using a chainsaw (petrol driven) All chain-saw operations are carried out in-line with : 2Using petrol driven chainsaws2 AGAG guide. De-buttressing carried out in accordance with, 2 Chainsaw de-buttressing of standard timer Tree felling carried out in accordance with felling large trees attached. Hearing protection (to EN352 or better) worn at all times. Use for short periods only. Appropriate gloves, with protective guarding to EN381-7 to be worn. Operator to be trained and certified for the type of chainsaw and for the task to be undertaken maximum refresher training three years. The chainsaw to be serviced to the manufacturers requirements.

4 Review Date: January 2013 Page: 4 of 8 A pre-use check to be carried out by user; with special attention to the stop control and the kick back chain protection. The chain to be sharp, adjusted and free from excessive wear. The chain saw to be started and operated only in the manner recommended by the manufacturer. Checking the seal of the fuel cap and starting only away from fuelling site. A safe zone shall be established for working in barriers and signs erected to protect the public as required. Eye protection and face protection consisting of a mesh visor to EN 1731 or better to be worn, Leg protection incorporating chain clogging material to EN and optionally depending on the task upper body protection jacket to EN to be worn. Protective boots with good grip and protective guarding to EN345-2 or gaiters to EN381-9 to be worn. Non snagging clothing appropriate to the conditions to be worn. A first aid kit, sufficient for large wound injury and control of bleeding, to be kept at hand, and a second person to be in attendance at all times. A full independent risk assessment will be carried out if temporary work at height is required.

5 Review Date: January 2013 Page: 5 of 8 Using a hedge trimmer and extension pole Using brush cutter and Strimmers All work carried out in line with hedge cutters guide Operatives to hi-vis vest if on road side working Signage at suitable points to make people aware of work in progress Operatives to wear appropriate gloves Operatives to wear ear defenders Regular job rotation, information form suppliers on exposure to levels of noise and vibration, log of hours to be kept. Equipment serviced and maintained in accordance with manufactures guide lines. Operatives trained in safe manual handling techniques. Weather conditions to be assessed prior to and during the time of operation. Operatives to wear safety footwear Good housekeeping to be undertaken All work is carried out in accordance with guide 2Clearing saws, brush cutters and strimmers Machine serviced and checked before use as per manufacturer s requirements. Operator trained how to operate the machine and carry out tasks. Noise levels require wearing of hearing protection (to EN352 or Better) Face and eye protection required a mesh visor (to EN1731 or better) or a face shield (BSEN 166 or better) Petrol is stored in a suitable container. Engine to be switched off for refuelling. Caps to be replaced securely and seal checked. Barriers and warning signs shall be set up where required to demarcate and control work area. Records kept regarding vibration exposure.

6 Review Date: January 2013 Page: 6 of 8 Erecting and working from Scaffold towers Operating MEWP s (mobile elevating work platforms) Workshop Storage/ activities Hautbois users and Hautbois Users and All work with mobile access tower or scaffold towers will be carried out in accordance with HSE construction information sheet 10 Tower Scaffolds. Operatives trained in safe erection and dismantling of mobile towers. Safe to use tag to be displayed when tower checked and ready to use. Weather conditions to be assessed prior to and during the time of operation. Operatives to wear safety foot wear. Good housekeeping maintained. Materials to be removed as work progresses. Working area demarcated, barriers and signs in place before work begins. All work using MEWP s is carried out in accordance with the guide MEWP s work tree work. Employees are trained and certified in the use of MEWP s and all work is carried out in line with this training. PPE worn as detailed within the above guide. All equipment with rotating parts must be suitable guarded to prevent contact or a suitable trip device fitted. Additional guards must be in place when in use to prevent ejected materials reaching the operator. Eye protection must be worn where instructed (signs) No lose clothing or hair. Wear hearing protection when carrying out noisy tasks. Keep immediate area clear. All equipment must be maintained and inspected in accordance with manufactures guidelines. CoSHH Assessments RCD or protected supply. Portable Appliance Tests Manual handling training.

7 Review Date: January 2013 Page: 7 of 8 Operating hand tools Visually inspect hand tools prior to use. Quarantine broken or damaged hand tools. When using weeding or cleaning tools make sure a good firm stance is maintained there is enough clear unimpeded space to swing the cutting tool safely. Do not swing the cutting tool directly towards the legs. When using a shorthandled hook keep your free hand well away form the cutting direction. Use of hand saws for brashing and pruning. Make sure there is a firm stance is maintained and there is enough clear, unimpeded space to use the saw safely. (Be alert to hazards such as wasps nests) Do not stand astride the saw Do not stand under branches when pruning them. Ensure any unknown mushrooms or plants do not come into contact with the skin. Using grinding wheel Machine served and checked before use as per manufactures requirements. Operator trained how to operate machine and carry out tasks. Noise level requires wearing of hearing protection to EN 352 or better. Face and eye protection required face shield to EN166B or better. Appropriate non-snag clothing to be warn Ensure that the floor area is free from loose materials and maintained in a safe condition without risks. Other operatives to be excluded from the work zone a minimum of 3 meters No temporary worker or other contractor shall operate the machine. Ensure the no flammables are in the vicinity if grinding creates sparks.

8 Review Date: January 2013 Page: 8 of 8 Application of Pesticides by hand held equipment AFAG1 leaflet 202 to be used as the standard for this work. Bunds if required and spillage kit. Storage to standards set out in HSE agriculture information sheet 16 Only spray when weather conditions permit. Do not spray when others in close proximity. Whenever possible only spray when free form distraction. Only trained and certified people to carry out spraying activities. Ensure spray applications are kept clear at all times. Add dye to spray mixture to show areas sprayed. Strong colours tend to put people off from entering areas.

CONSTRUCTION HEALTH AND SAFETY MANAGEMENT SYSTEM BASELINE HIRA

CONSTRUCTION HEALTH AND SAFETY MANAGEMENT SYSTEM BASELINE HIRA RECOMMENDED ADDITIONAL CONTROLS TASK / ACTIVITY/ EQUIPMENT/ FACILITY HAZARDS UNWANTED EVENT MINIMUM CONTROLS REQUIRED RISK NO. LIKELI-HOOD CONSE-QUENCE RISK VALUE Project Risk Assessment Page 1 of 16 All

More information

Risk assessment. Assessment details. Task. Introduction. Please complete the form as fully and accurately as you can. Assessors job title

Risk assessment. Assessment details. Task. Introduction. Please complete the form as fully and accurately as you can. Assessors job title Risk assessment Introduction Please complete the form as fully and accurately as you can. Assessment details Name of organisation Assessor's name Assessors job title Any Company John Smith Manager Date

More information

RISK INFORMATION SCHOOLS SCHOOL GROUNDS MAINTENANCE

RISK INFORMATION SCHOOLS SCHOOL GROUNDS MAINTENANCE The Risk Information contained in this paper is intended to assist schools in establishing safe procedures for maintaining school grounds. Schools owe a duty of care to employees and students to keep them

More information

Safe Work Method Statement LRB TREE SERVICES 6 Behland St, Kearneys Spring QLD, 4350 ABN

Safe Work Method Statement LRB TREE SERVICES 6 Behland St, Kearneys Spring QLD, 4350 ABN JOB NO: PROJECT: DATE: 1/1/2018 SWMS NO: SWMS 001.1 PREPARED BY: LUKE BLINCO REVISED BY: ACTIVITY: TREE REMOVAL & PRUNING SIGNED BY: REVISION DATE: MINIMUM PERSONAL PROTECTIVE EQUIPMENT (PPE) REQUIREMENTS

More information

SAFETY/RISK/HAZARD ASSESSMENT

SAFETY/RISK/HAZARD ASSESSMENT POLE CHAIN SAW SAFETY/RISK/HAZARD ASSESSMENT PLANT INFORMATION NHG Ref/Part No. Plant Name: Potential Noise Level in Db: Pole Chain Saw 110db to less than 115db Required hearing protection class: 5 Operator

More information

7 Hazard assessment 8 Worker participation 9 Hazard elimination and control

7 Hazard assessment 8 Worker participation 9 Hazard elimination and control This document is a guideline only. Employers have a responsibility of assessing all applicable occupational health and safety legislation, for the tasks they are performing. Businesses in this industry

More information

75 Years of Health and Safety Guidance

75 Years of Health and Safety Guidance H&S Guide: 60 Working Risks Personal Protective Equipment Personal Protective Equipment (also known as PPE) Employers have duties concerning the provision and use of personal protective equipment at work.

More information

SAFE WORK METHOD STATEMENT (SWMS) GENERAL GARDENING with Blowers, Hedge Trimmers, Whipper Snippers, Pruners, Spray Units

SAFE WORK METHOD STATEMENT (SWMS) GENERAL GARDENING with Blowers, Hedge Trimmers, Whipper Snippers, Pruners, Spray Units Job Description/Task/: General Gardening such as using Blowers, Hedge Trimmers, Whipper Snippers, Pruners, Spray Units Name and Phone Number of Person Completing SWMS: Name and Phone Number of the Person

More information

Hazard Identification and Risk Assessment Form. Risk Assessment

Hazard Identification and Risk Assessment Form. Risk Assessment Identification and Assessment Form Assessment Tool & Machine Work General Various injuries (including potential fatalities) All staff complete safety induction programme at the start of the module. instructed

More information

TOOL BOX TALK NO3. Use of P.P.E

TOOL BOX TALK NO3. Use of P.P.E Combined Technical Solutions Ltd TOOL BOX TALK NO3. Use of P.P.E OBJECTIVE: Why PPE is important and why it should be looked after Personal Protective Equipment is intended to protect you from risks, which

More information

SAFE WORK METHOD STATEMENT Part 1 CONCRETE SAWING

SAFE WORK METHOD STATEMENT Part 1 CONCRETE SAWING SAFE WORK METHOD STATEMENT Part 1 CONCRETE SAWING Personal Protective Equipment Foot Hearing High Visibility Head Eye Face Hand Protective Clothing Breathing Normal Requirements: Safety footwear, hearing

More information

What is an induction? Contribute to OH&S Processes

What is an induction? Contribute to OH&S Processes What is an induction? Session 2 Contribute to OH&S Processes Types of Induction New Employee Induction Site Inductions Equipment Inductions Activity 2.1 Induction Description What is a Hazard? Session

More information

LEVEL 2 CERTIFICATE OF COMPETENCE IN THE SAFE USE OF MOWERS ASSESSMENT SCHEDULE

LEVEL 2 CERTIFICATE OF COMPETENCE IN THE SAFE USE OF MOWERS ASSESSMENT SCHEDULE NPTC Registered Charity No. 1096429 STONELEIGH PARK, WARWICKSHIRE CV8 2LG Tel: 024 7685 7300 Fax: 024 7669 6128 Email: information@nptc.org.uk LEVEL 2 CERTIFICATE OF COMPETENCE IN THE SAFE USE OF MOWERS

More information

THICKNESSER RISK ASSESSMENT (U003ra)

THICKNESSER RISK ASSESSMENT (U003ra) Task Being Carried Out: Area: Persons at Risk: Operation of T500 Thicknesser Brindle Mill Operatives, Maintenance engineers Description of Equipment: Wadkin T500 Thicknesser Serial No.: T500 82240 (Machine

More information

RISK RATING SAFE WORK METHOD STATEMENT 1 HIGH 2 MEDIUM 3LOW. I approve the use of this Safe Work Method Statement: NAME: POSITION: Department Manager

RISK RATING SAFE WORK METHOD STATEMENT 1 HIGH 2 MEDIUM 3LOW. I approve the use of this Safe Work Method Statement: NAME: POSITION: Department Manager RISK RATING 1 HIGH 2 MEDIUM 3LOW SAFE WORK METHOD STATEMENT Title: : Traineeship Ref No: 1 I approve the use of this Safe Work Method Statement: NAME: POSITION: Department Manager SIGNATURE: DATE: / /

More information

Powerplay Paintball Brighouse Risk Assessment

Powerplay Paintball Brighouse Risk Assessment Chemical Gas bottles Vehicles Physical Electricity Environment Machinery Powerplay Paintball Brighouse Risk Assessment Location Powerplay Paintball Wakefield and Brighouse Venues Carried out by: Steven

More information

Suitability of Work Equipment

Suitability of Work Equipment These regulations came into effect on the 5th December 1998 and replace PUWER 1992. They cover almost all equipment used at work, including tool box tools such as hammers, knives etc. They also cover machinery

More information

PERSONAL PROTECTIVE EQUIPMENT GUIDANCE

PERSONAL PROTECTIVE EQUIPMENT GUIDANCE Legislation requires a workplace to identify and assess significant hazards (via a risk assessment) associated with workplace activities. The purpose of the assessment is to enable a valid decision about

More information

QUEENSLAND UNIVERSITY OF TECHNOLOGY

QUEENSLAND UNIVERSITY OF TECHNOLOGY QUEENSLAND UNIVERSITY OF TECHNOLOGY SITE SPECIFIC SAFETY MANAGEMENT PLAN FOR SAMFORD HOUSE SAMFORD ECOLOGICAL RESEARCH FACILITY SAMFORD VALLEY 2007 Dylan Randall SN: 06305466 dylan.randall@student.qut.edu.au

More information

HAZARDS AND RISKS ASSOCIATED WITH THE USE OF RIDE ON MOWERS

HAZARDS AND RISKS ASSOCIATED WITH THE USE OF RIDE ON MOWERS Safe Systems of Working Use of Ride on Mowers INTRODUCTION This Method Statement covers the safe working practices to be followed when using a ride on mower and should be used alongside the manufacturers

More information

BHC-P-07.2 Health Hazards in Construction

BHC-P-07.2 Health Hazards in Construction BHC-P-07.2 Health Hazards in Construction Contents 1.0 Purpose 2.0 Scope 3.0 Definitions 4.0 Main requirements 5.0 Guidance documents and references 6.0 Appendices Revision Register Date Version Description

More information

Risk Management Resources

Risk Management Resources Risk Management Resources Machine Guarding Name: Notes: Electrical Systems: Fire Prevention Are circuit breakers accessible to personnel, protected from physical damage, and located away from ignitable

More information

Risk Assessment June Skirmish Paintball Games Exeter

Risk Assessment June Skirmish Paintball Games Exeter Ve hicl Physical Electricity Environment Machiner y Risk Assessment June 2012. Skirmish Paintball Games Exeter Location Skirmish Paintball Exeter Carried out by: Martin Collins Date 10 th June 2012 Authorised

More information

You must NOT touch any equipment unless you are authorised to work on or with that equipment and you have followed correct safety procedures.

You must NOT touch any equipment unless you are authorised to work on or with that equipment and you have followed correct safety procedures. SYDNEY TOWN HALL 1 HIRER & CONTRACTOR SAFETY FACT SHEET Issue 2 September 2013 www.sydneytownhall.com.au City of Sydney - Venue Management will provide and maintain a safe working environment for the health,

More information

PART 4: IMPLEMENTATION & OP

PART 4: IMPLEMENTATION & OP TITLE PART 4: IMPLEMENTATION & OPERATION Prepared by: 4.2 Personal Protective Equipment (PPE) Learning Objectives To define what is Personal Protective Equipment (PPE). To describe the management & legal

More information

SAFETY MANAGEMENT SYSTEM

SAFETY MANAGEMENT SYSTEM Equipment Location: Hazard Hired From All Master Hire Stores Entanglement Can anyone s hair, clothing, gloves, necktie, jewellery, cleaning brushes, rags or other materials become entangled with moving

More information

LEVEL 2 CERTIFICATE OF COMPETENCE IN CHAINSAW AND RELATED OPERATIONS ASSESSMENT SCHEDULE

LEVEL 2 CERTIFICATE OF COMPETENCE IN CHAINSAW AND RELATED OPERATIONS ASSESSMENT SCHEDULE Registered Charity No. 1096429 STONELEIGH PARK, WARWICKSHIRE CV8 2LG Tel: 024 7685 7300 Fax: 024 7669 6128 Email: information@nptc.org.uk LEVEL 2 CERTIFICATE OF COMPETENCE IN CHAINSAW AND RELATED OPERATIONS

More information

Risk Assessment In accordance with the Management of Health and Safety Regulations 1999

Risk Assessment In accordance with the Management of Health and Safety Regulations 1999 Ref No 6.1 Task of Assessor Job Title Litter Picking on and around Streets and Highways Below 40mph Simon Foley Location Quality Health and Environmental Manager Bath Signature Issue Date 15 th July 2015

More information

University College Dublin Machinery/Equipment Risk Assessment Template

University College Dublin Machinery/Equipment Risk Assessment Template 1. General Information Name of Person(s) carrying out assessment and their position Principal Investigator / Supervisor / Head of School or Unit (Person responsible for ensuring safety) Date of assessment

More information

Collision Repair Shop Inspection Checklist

Collision Repair Shop Inspection Checklist Collision Repair Shop Inspection Checklist Note: This is a sample inspection chesklist only, and may mot include all appropriate inspection items. The Occupational Health and Safety Regulation specifies

More information

PLANT HAZARD REPORT. Plant Description: Element Aspect Plant Hazards and Controls Advice. Circular Saw

PLANT HAZARD REPORT. Plant Description: Element Aspect Plant Hazards and Controls Advice. Circular Saw PLANT HAZARD REPORT Plant Description: Circular Saw PLEASE NOTE This plant information has been prepared to assist the purchaser in identifying hazards associated with the plant prior to the purchaser

More information

FLYING OBJECTS MANUAL HANDLING EXCESSIVE NOISE

FLYING OBJECTS MANUAL HANDLING EXCESSIVE NOISE JOB NO: PROJECT: DATE: SWMS NO: SWMS 002 PREPARED BY: Ian Hartley REVISED BY: Nick Bragg & Cameron McNeil ACTIVITY: STUMP REMOVAL SUPERVISED BY: REVISION DATE: April 2016 MINIMUM PERSONAL PROTECTIVE EQUIPMENT

More information

The Sample Company Pty Ltd

The Sample Company Pty Ltd Job Safety and Environmental Analysis (JSEA) / Safe Work Method Statement (SWMS) Part 1: Project and Task Identification Process Initiators of SWMSs are responsible for consulting the Project Supervisor,

More information

POWER DELIVERY. Contractor Health & Safety General Terms and Conditions. Appendix B Personal Protective Equipment

POWER DELIVERY. Contractor Health & Safety General Terms and Conditions. Appendix B Personal Protective Equipment Personal Protective Equipment ( PPE ): All PPE worn on IPL job sites must have ANSI and/or approval ratings. Hard hats and safety glasses with side shields (including prescription eyewear) shall be worn

More information

PERSONAL PROTECTIVE EQUIPMENT

PERSONAL PROTECTIVE EQUIPMENT 13.0 The purpose of this program is to ensure that, where applicable, the appropriate and necessary personal protective equipment (PPE) is selected and provided to employees to protect from illness or

More information

Rail Grinding & support teams

Rail Grinding & support teams Working with On Track Machines Rail & Support Teams RCS No: TCS006 Issue: 1 Key Risks! in Possessions in Tunnels Fire in Electrified areas Working in the vicinity of OHL Noise/ Dust / Fumes Personnel Involved

More information

Contractor / Exhibitor Handbook

Contractor / Exhibitor Handbook Contractor / Exhibitor Handbook Health and Safety This booklet outlines the basic rules that must be followed by contractors and other visitors working on Live Promotions Events sites. The contractors

More information

Safe Work Procedure for installation of external cladding

Safe Work Procedure for installation of external cladding Safe Work Procedure for installation of external cladding This procedure has been formulated to cover safe systems of work for the installation of external cladding. This instruction will be used to reduce

More information

How severely could the risk hurt someone? Low/Insignificant First aid

How severely could the risk hurt someone? Low/Insignificant First aid Safe Work Method Statement No: WMS-02 Task: Concreting, Formwork and Steel Fixing This WMS is submitted to: Project name and site address: Contact: Preparation of WMS by: Robert Raams Company: Enwon (Australia)

More information

Risk Assessment Form (Qualitative)

Risk Assessment Form (Qualitative) Assessment Form (Qualitative) Project / ocation:..d.a.s WATERS Contract No: RA & Issue No: 008 Prepared by:.r.smit Date: 10/10/16 Signature: ACTIVITY DESCRIPTION: Person (s) at risk: General Ground works

More information

WADKIN OVER HEAD ROUTER RISK ASSESSMENT (U002ra)

WADKIN OVER HEAD ROUTER RISK ASSESSMENT (U002ra) Task Being Carried Out: Area: Persons at Risk: Operation of Over Head Router Brindle Mill Operatives, Maintenance engineers Description of Equipment: Wadkin Over Head Router Serial No.: LS 3891 Location

More information

Title: Plant and Equipment Risk Management Form Issue Date: Review Date: Page Number: 1 of 11

Title: Plant and Equipment Risk Management Form Issue Date: Review Date: Page Number: 1 of 11 Issue Date: Review Date: Page Number: 1 of 11 1. Hazard Management Details General Plant/Equipment Item: WOOD LATHE Make/Model No.: Serial No.: School: Work Location: Name of Person(s) Conducting Activity:

More information

Chairman: Doctor: Ambulance: Secretary: Gardai: Other: The Club will comply with Schedule 3 of the Safety, Health and Welfare at Work Act 2005 by:

Chairman: Doctor: Ambulance: Secretary: Gardai: Other: The Club will comply with Schedule 3 of the Safety, Health and Welfare at Work Act 2005 by: SAFETY STATEMENT SECTION 20 SAFETY, HEALTH AND WELFARE AT WORK ACT 2005 CLUB NAME: ADDRESS: This Safety Statement is our programme in writing to manage health and safety. It is aimed at protecting our

More information

How severely could the risk hurt someone? Low/Insignificant First aid

How severely could the risk hurt someone? Low/Insignificant First aid Safe Work Method Statement No: WMS-0 Task: Operate Diesel Road Saw This WMS is submitted to: Project name and site address: Contact: Preparation of WMS by: Robert Raams Company: Enwon (Australia) Pty Ltd

More information

Personal Protective Equipment Policy

Personal Protective Equipment Policy Summary of the Legal requirements: Personal Protective Equipment Policy Personal Protective Equipment should only be used as a last resort or as a short term emergency measure where other control measures

More information

SAFE WORK METHOD STATEMENT

SAFE WORK METHOD STATEMENT SAFE WORK METHOD STATEMENT AUGER / POST HOLE DIGGER Prepared for Client: Rural Construction & Maintenance Pty Ltd Project No: 1 Site: 660 Great Ocean Road, Bellbrae Date Prepared: 29/07/2015 1. RESPONSIBILITIES

More information

SAFE WORK METHOD STATEMENT Part B

SAFE WORK METHOD STATEMENT Part B SAFE WORK METHOD STATEMENT Part B SWMS No.: 01 WORK ACTIVITY DESCRIPTION: Door Installation All FORESEEABLE OHS & ENVIRONMENTAL HAZARDS & RISKS ASSOSSIATED WITH THE WORKS MUST BE ASSESSED & ALLOCATED CONTROLS

More information

PLANNED LIGHTING MAINTENANCE LTD METHOD STATEMENT & RISK ASSESSMENT REPLACEMENT OF LAMPS OR REPAIRS TO HIGH LEVEL LIGHT UNITS

PLANNED LIGHTING MAINTENANCE LTD METHOD STATEMENT & RISK ASSESSMENT REPLACEMENT OF LAMPS OR REPAIRS TO HIGH LEVEL LIGHT UNITS PLANNED LIGHTING MAINTENANCE LTD METHOD STATEMENT & RISK ASSESSMENT REPLACEMENT OF LAMPS OR REPAIRS TO HIGH LEVEL LIGHT UNITS Project: (insert Client) Replacement/ Repair of high level light units/ high

More information

Health & Safety Risk Assessment (RA) Use of Church facilities by/for: Working & Cleaning Parties

Health & Safety Risk Assessment (RA) Use of Church facilities by/for: Working & Cleaning Parties GJM/DTM Cole Street Assessment Assessment No: RA 008 Health & Safety Assessment (RA) Use of Church facilities by/for: Working & Cleaning Parties For completion by event/group organiser(s)/supervisor(s)

More information

How severely could the risk hurt someone? Low/Insignificant First aid

How severely could the risk hurt someone? Low/Insignificant First aid Safe Work Method Statement No: WMS-0 Task: Line Marking This WMS is submitted to: Project name and site address: Contact: Preparation of WMS by: Robert Raams Company: Enwon (Australia) Pty Ltd Authorised

More information

Safety Services Guidance. Hand Arm Vibration

Safety Services Guidance. Hand Arm Vibration Hand Arm Vibration Key word(s): Vibration, exposure action value, exposure action limit, machinery, hand held power tools, trigger times, maintenance, surveillance Target audience: Managers, staff who

More information

EHS Workplace Inspection Checklist (Ref. SOP QMS-080; EHS-010)

EHS Workplace Inspection Checklist (Ref. SOP QMS-080; EHS-010) (Ref. SOP QMS-080; EHS-010) Form-445 Inspected by: Date of inspection Date of Report Report # Pages Area Manager: Area Inspected: General This EHS Workplace Inspection was conducted by: Scope of the Inspection:

More information

Portable Electric Tools

Portable Electric Tools A Health and Safety Guideline for Your Workplace Types Portable electric tools commonly used in industry are: drills, saws, sanders, buffers, grinders, impact wrenches, planers. Hazards The hazards associated

More information

14. Personal Protection Chapter , WAC

14. Personal Protection Chapter , WAC 14. Personal Protection Chapter 296-800-160, WAC 1.0 Introduction PLU will provide most required personal protective equipment (PPE). The employee may be required to provide PPE that is of a personal nature

More information

FALL PROTECTION / ELEVATED WORK

FALL PROTECTION / ELEVATED WORK SEPTEMBER CORE REFRESHER HSE TOOL BOX FALL PROTECTION / ELEVATED WORK FALL PROTECTION Falls from elevations are one of the most common causes of death in this industry. OSHA requires fall protection when

More information

A short guide to the Personal Protective Equipment at Work Regulations 1992

A short guide to the Personal Protective Equipment at Work Regulations 1992 A short guide to the Personal Protective Equipment at Work Regulations 1992 Health and Safety A short guide to the Personal Protective Equipment at Work Regulations 1992 Employers have basic duties concerning

More information

Potential hazards People at risk and how? Actions already in place Further action required Action by

Potential hazards People at risk and how? Actions already in place Further action required Action by Risk Assessment Flat Roof Repair Prepared by Oracle Managed Services For: BAM FM On: 24/02/2017 Review date: N/A Potential hazards People at risk and how? Actions already in place Further action required

More information

Working at Height. Policy and Procedures. Author: Beth Webster Assistant Safety Advisor. On behalf of School Safety Committee.

Working at Height. Policy and Procedures. Author: Beth Webster Assistant Safety Advisor. On behalf of School Safety Committee. Working at Height Policy and Procedures Author: Beth Webster Assistant Safety Advisor Authorised by: Issued by: John Stephenson Safety Office On behalf of School Safety Committee Review Date: NO LATER

More information

WORKSHOP CARPENTRY/FENCING

WORKSHOP CARPENTRY/FENCING ELECTRICAL Power Cords 1. Check all power cords (extension leads) before use to ensure that the tag is current. Please Note: For all workshop areas and hostel, this is every year. For all office areas

More information

TRADE AREA: ELECTRICAL INDUSTRY

TRADE AREA: ELECTRICAL INDUSTRY TRADE AREA: ELECTRICAL INDUSTRY Some possible workplace hazards and possible ways for Host employers and Apprentices/Trainees in controlling these hazards. What are possible hazards? What could be possible

More information

The Yorkshire Waterways Museum, Dutch River Side, Goole, POND AND NATURE TRAIL RISK ASSESSMENT SHE/RA/00

The Yorkshire Waterways Museum, Dutch River Side, Goole, POND AND NATURE TRAIL RISK ASSESSMENT SHE/RA/00 The Sobriety Project The Yorkshire Waterways Museum, Dutch River Side, Goole, DN14 5TB POND AND NATURE TRAI RISK ASSESSMENT SHE/RA/00 Title of Activity: ocation(s) of Work: Using the pond area and nature

More information

Recognition, Evaluation, and Control of Hazards

Recognition, Evaluation, and Control of Hazards Recognition, Evaluation, and Control of Hazards Latest revised date: October 26, 2011 Page 1 of 8 1.0 Introduction Memorial University has established a system for the recognition, evaluation, and control

More information

CONTRACTOR SAFETY INDUCTION HANDBOOK

CONTRACTOR SAFETY INDUCTION HANDBOOK CONTRACTOR SAFETY INDUCTION HANDBOOK As a valued contractor for Total Group we would ask that you read and carefully consider the details included in this document. Total Group carry out work for a number

More information

POLICY ON THE PROVISION & USE OF PERSONAL PROTECTIVE EQUIPMENT

POLICY ON THE PROVISION & USE OF PERSONAL PROTECTIVE EQUIPMENT POLICY ON THE PROVISION & USE OF PERSONAL PROTECTIVE EQUIPMENT June 2013 Lead Manager John Green, Health & Safety Service Manager Responsible Director Director of Human Resources Approved By Health and

More information

SAFE WORK METHOD STATEMENT

SAFE WORK METHOD STATEMENT SAFE WORK METHOD STATEMENT WATER PUMP - PETROL Prepared for Client: Rural Construction & Maintenance Pty Ltd Project No: 1 Site: 660 Great Ocean Road, Bellbrae Date Prepared: 29/07/2015 1. RESPONSIBILITIES

More information

Safe Work Method Statement

Safe Work Method Statement Company Name: Safe Work Method Statement Site Address: Other Details: Contractor: Activity/Trade: Electrician Date: TASKS List the tasks required to perform the activity in sequence carried out. Entry

More information

Method Statement Author

Method Statement Author Plan Bee Limited 3.3 Etna Industrial estate Clamp Road Motherwell Scotland ML2 7XQ Tel: 01698580572 Method Statement Method Statement Details Method Statement Number 7 Method Statement Date Monday 3rd

More information

ERI Safety Videos Videos for Safety Meetings POWER SAW SAFETY. Leader s Guide 2001, SAFETY SOURCE PRODUCTIONS

ERI Safety Videos Videos for Safety Meetings POWER SAW SAFETY. Leader s Guide 2001, SAFETY SOURCE PRODUCTIONS ERI Safety Videos Videos for Safety Meetings 2111 POWER SAW SAFETY Leader s Guide 2001, SAFETY SOURCE PRODUCTIONS POWER SAW SAFETY This easy-to-use Leader s Guide is provided to assist in conducting a

More information

Woodlarks Camp Site Trust. Health and Safety Policy & Procedures. Amended Date Signature

Woodlarks Camp Site Trust. Health and Safety Policy & Procedures. Amended Date Signature Woodlarks Camp Site Trust Health and Safety Policy & Procedures 2017 Page/s Page/s Page/s Page/s Page/s Amended Date Signature 15-Apr-2017 Health and Safety Policy and Procedures_ Final 2017.doc Page 1

More information

SAFETY MANAGEMENT SYSTEM

SAFETY MANAGEMENT SYSTEM Equipment Location: Hazard Hired From All Master Hire Stores Entanglement Can anyone s hair, clothing, gloves, necktie, jewellery, cleaning brushes, rags or other materials become entangled with moving

More information

Job Hazard Analysis. JHA No. FBP-JHA Revision No. Draft General or Job-Specific Description of Work

Job Hazard Analysis. JHA No. FBP-JHA Revision No. Draft General or Job-Specific Description of Work JHA No. FBP-JHA-14-0014 Revision No. Draft General or Job-Specific Description of Work Clean X230 Outlet Basin Site Location PORTS Activity or Area Name Not listed Facility or Project [Unspecified] Specific

More information

Personal Protective Equipment Operating Standards

Personal Protective Equipment Operating Standards Personal Protective Equipment Operating Standards - 1 - Table of Contents 1. Background... 3 2. Aim/Purpose... 3 3. Definitions and an Explanation of Terms Used... 3 4. Full Details... 3 4.1 Hazard Assessment

More information

Job Hazard Analysis Analysis by:

Job Hazard Analysis Analysis by: Job Analysis Possible s or Task Machinery e.g. Mowers Chainsaws Grinders Floor polisher Power tools Weed trimmers Sweepers Snow blowers Hedge trimmer Tiller Auto scrubbers Burnishers Ford tractor Sand

More information

Composite Pistol-Type Air Needle Scaler OWNER S MANUAL

Composite Pistol-Type Air Needle Scaler OWNER S MANUAL Composite Pistol-Type Air Needle Scaler OWNER S MANUAL WARNING: Read carefully and understand all INSTRUCTIONS before operating. Failure to follow the safety rules and other basic safety precautions may

More information

BASIC HEALTH AND SAFETY MEASURES TO BE TAKEN INTO CONSIDERATION FOR STAND CONSTRUCTION AT MOBILE WORLD CONGRESS rev01

BASIC HEALTH AND SAFETY MEASURES TO BE TAKEN INTO CONSIDERATION FOR STAND CONSTRUCTION AT MOBILE WORLD CONGRESS rev01 BASIC HEALTH AND SAFETY MEASURES TO BE TAKEN INTO CONSIDERATION FOR STAND CONSTRUCTION AT MOBILE WORLD CONGRESS 2017 IMPORTANT! DURING BUILD-UP AND DISMANTLING ACCESS TO THE VENUE WILL ONLY BE GRANTED

More information

How severely could the risk hurt someone?

How severely could the risk hurt someone? Safe Work Method Statement No: WMS-08 Task: Install Drainage This WMS is submitted to: Project name and site address: Contact: Preparation of WMS by: Robert Raams Company: Enwon (Australia) Pty Ltd Authorised

More information

Rockhampton Office Brisbane Office Tarong Site. Barron Gorge Hydro PS Kareeya Hydro PS Mica Creek PS

Rockhampton Office Brisbane Office Tarong Site. Barron Gorge Hydro PS Kareeya Hydro PS Mica Creek PS Business Procedure Hot Work Document Number OHS-PROC-128 This document applies to the following sites: All Sites Rockhampton Office Brisbane Office Tarong Site Barron Gorge Hydro PS Kareeya Hydro PS Mica

More information

GENERAL MAINTENANCE & SAFETY GUIDANCE

GENERAL MAINTENANCE & SAFETY GUIDANCE GENERAL MAINTENANCE & SAFETY GUIDANCE GREAT BRITISH SPORTS EQUIPMENT DIRECT FROM THE MANUFACTURER 01502 711298 info@mhgoals.com www.mhgoals.com MH GOALS LTD, UNIT 7 10 WARWICK COURT, ELLOUGH INDUSTRIAL

More information

Safety Information for Engine Grass Trimmer/Brush Cutter

Safety Information for Engine Grass Trimmer/Brush Cutter Safety Information for Engine Grass Trimmer/Brush Cutter This page contains important safety information for those who handle engine grass trimmers/brush cutters. Please read this information carefully

More information

RISK ASSESSMENT A UNIVERSITY GUIDE TO PRACTICAL RISK ASSESSMENT UNDER THE MANAGEMENT OF HEALTH AND SAFETY AT WORK REGULATIONS 1992

RISK ASSESSMENT A UNIVERSITY GUIDE TO PRACTICAL RISK ASSESSMENT UNDER THE MANAGEMENT OF HEALTH AND SAFETY AT WORK REGULATIONS 1992 RISK ASSESSMENT A UNIVERSITY GUIDE TO PRACTICAL RISK ASSESSMENT UNDER THE MANAGEMENT OF HEALTH AND SAFETY AT WORK REGULATIONS 1992 PERSONNEL DIVISION REVIEWED AUTUMN 1999 CONTENTS Page 1 INTRODUCTION 1

More information

UGRacing Formula Student Garage Risk Assessment

UGRacing Formula Student Garage Risk Assessment UGRacing Formula Student Garage Risk Assessment University of Glasgow School of Engineering Location: Formula Student Workshop Building: Rankine Building, Oakfield Avenue Glasgow G12 8LT Summary of activities

More information

Example of an Occupational Health Risk Assessment

Example of an Occupational Health Risk Assessment SITE: ASSESSMENT DATE: EQUIPMENT/ AREA/TASK: Floor Manual ASSESSED BY: TASK/ EQUIPMENT floor manual sorting HAZARD RISK PERSONS RATING EXISITING CONTROL MEASURES AT RISK S L R FURTHER ACTION REQUIRED R

More information

Equipment Risk Assessment

Equipment Risk Assessment Equipment Risk Assessment 1 Page 0 Index Index Equipment Risk Assessment Pedestrian Mower significant risks... 1 Equipment Risk Assessment Strimmer significant risks... 2 Equipment Risk Assessment Hedge

More information

A Health & Safety Risk Management Tool that you can use today. Scott Norman, CIH, CSP Health & Safety Program Manager Bay West LLC

A Health & Safety Risk Management Tool that you can use today. Scott Norman, CIH, CSP Health & Safety Program Manager Bay West LLC A Health & Safety Risk Management Tool that you can use today Scott Norman, CIH, CSP Health & Safety Program Manager Bay West LLC I m a safety geek What are the hazards of your work environment? Who is

More information

Removing Frozen Clips

Removing Frozen Clips Removing Frozen Clips Warning You cannot undertake this activity in the rail corridor unless you have completed a pre work brief and work site protection plan. Reference should also be made to the Protocol

More information

INTENDED USE TECHNICAL SPECIFICATIONS

INTENDED USE TECHNICAL SPECIFICATIONS 1/2IN. HEAVY-DUTY AIR IMPACT WRENCH OWNER S MANUAL WARNING: Read carefully and understand all INSTRUCTIONS before operating. Failure to follow the safety rules and other basic safety precautions may result

More information

Contractor handbook. Purpose

Contractor handbook. Purpose Page no: 1 / 6 Contractor handbook Purpose Mitie aims to ensure that the highest levels of performance are achieved by all persons working for us or on our behalf. We require the same level of performance

More information

Basic Safety Orientation. University of Illinois at Urbana-Champaign

Basic Safety Orientation. University of Illinois at Urbana-Champaign Basic Safety Orientation Basic Safety Orientation This orientation is General Knowledge only. Further training is required to meet hazard specific training requirements. For more information, please contact

More information

Control of Energy - Isolation Process

Control of Energy - Isolation Process Issue Date: 24/03/17 Last Reviewed: 24/03/17 Next Review Date: 24/03/18 Authorised By: Mike Muir Safe Operating Procedure Control of Energy - Isolation Process Purpose: This SOP is based on a Generic 12-step

More information

Safety Risk Assessment Working at Height: Mobile Tower Scaffold

Safety Risk Assessment Working at Height: Mobile Tower Scaffold Persons at (Groups) Assessor Appointment Tel. No. Description of Task or Activity A One Direct employees Mark Bloxidge H&S Manager 0208 821 5197 Working at height from Mobile Tower B Contractors/Sub contractors

More information

Health & Safety Contractor rules

Health & Safety Contractor rules Health & Safety Contractor rules Contents 1. Introduction... 1 2. The legal bit explaining our terminology... 1 2.1 Legal requirements... 1 3. Our health and safety requirements... 1 3.1 Access to BT premises...

More information

WINDMILL (pre-start) HAZARD INSPECTION CHECKLIST

WINDMILL (pre-start) HAZARD INSPECTION CHECKLIST Windmill Hazard Inspection Checklist WINDMILL (pre-start) HAZARD INSPECTION CHECKLIST Authorised by: LOCATION OF INSPECTION...... Inspected By (1)........... (2)..... PRINT PRINT Signature (1):. (2)....

More information

Summary of Standards for Key Items of PPE

Summary of Standards for Key Items of PPE Summary of Standards for Key Items of PPE This is a guide to the selection of suitable PPE. In some cases certain PPE is mandatory and forms part of a safe system of work. These are the minimum requirements

More information

INSTRUCTIONS AND WARNING FOR SAFETY USE OF AIR TOOLS GENERAL RECOMMENDATIONS

INSTRUCTIONS AND WARNING FOR SAFETY USE OF AIR TOOLS GENERAL RECOMMENDATIONS INSTRUCTIONS AND WARNING FOR SAFETY USE OF AIR TOOLS GENERAL RECOMMENDATIONS SAFETY is a primary consideration when using the air tool. The tool should be used in the right way with good understanding

More information

Risk Controls Proposed: (in hierarchy order from the most preferred control)

Risk Controls Proposed: (in hierarchy order from the most preferred control) are to be assessed and controlled by eliminating or minimising any risks to health and safety. Eliminate - Where the risk to health and safety is removed from the workplace. Minimise - Where the risk cannot

More information

Safe Use of Pedestrian Controlled Mowers (2 Units)

Safe Use of Pedestrian Controlled Mowers (2 Units) Safe Use of Pedestrian Controlled Mowers (2 Units) Introduction This qualification is divided into two units: Unit 1 Operate a Mower Unit 2 Use of Pedestrian Controlled Mower The certificate will be endorsed

More information

Personal commitments you can live and work by:

Personal commitments you can live and work by: Personal commitments you can live and work by: I anticipate possible dangers in any given operation and make every effort to analyze and avoid them before starting work, including immediately communicating

More information

4.1 The Vice-Chancellor and University Executive Committee

4.1 The Vice-Chancellor and University Executive Committee UON Key Risk Area: KRA 1.4 Plant and Equipment 1. Purpose This procedure describes how the University meets its obligation to ensure the health and safety of people, through the processes of selection,

More information

Potential risk of injury to staff

Potential risk of injury to staff Register Fire, Earthquake - other Emergencies Manual Handling and Repetitive Work Repetitive, Forceful Work Poor Housekeeping Not Wearing PPE (Personal Protective Equipment) Potential risk of injury to

More information

RISK ASSESSMENT. Bobcat Excavator. Models , (Series D & G) For. Version 1.2

RISK ASSESSMENT. Bobcat Excavator. Models , (Series D & G) For. Version 1.2 PO Box 50, Hornsby, NSW 2077 Phone: 1800 643 853 Web: www.bobcat.com.au RISK ASSESSMENT For Bobcat Excavator Models 322 341, (Series D & G) CONTENTS Applicability Standards referenced in the preparation

More information