1 Transportation Outlook 2040 Project List Transportation Outlook 2040 is the metropolitan transportation plan (MTP) for the greater Kansas City region. A major component of the MTP is identifying a list of regionally important projects to improve the transportation of people and goods (highway, transit, etc.). This federally required project listing is intended to help the region identify and prioritize future transportation investments based on goals, strategies and estimated financial resources. The projects in Transportation Outlook 2040 were developed, prioritized, and ultimately selected through a comprehensive and coordinated process involving the general public, regional transportation stakeholders and MARC planning committees. Incorporation by Reference of the MARC Transportation Improvement Program The Transportation Improvement Program (TIP) is a detailed list of projects to be implemented in the next four to five years, and is developed for the metropolitan transportation planning process in accordance with federal regulations (CFR ). The TIP is incorporated into the MTP by reference, and therefore, upon adoption by the MARC Board, the MTP shall include all projects in the most recently approved TIP as well as any future TIP amendments approved before the next MTP update. Financial Constraint Federal planning regulations (CFR ) state that For the purpose of developing the metropolitan transportation plan, the MPO, public transportation operator(s), and State shall cooperatively develop estimates of funds that will be available to support metropolitan transportation plan implementation. The regulations also indicate for illustrative purposes, the financial plan may (but is not required to) include additional projects that would be included in the adopted transportation plan if additional resources beyond those identified in the financial plan were to become available. To demonstrate financial constraint in the plan, the costs to operate, maintain and preserve the transportation system, in the MARC MPO region, is deducted from available transportation revenues first, and the remaining balance is available for other transportation investments. The constrained project list includes examples of operations, management and preservation projects in addition to non-preservation roadway and transit projects. Transportation Outlook 2040 includes constrained and unconstrained project lists. The financial plan described in Appendix E: Financial Capacity demonstrates the availability of funding for projects in the constrained list. The unconstrained list includes those projects that would be included in the plan if additional resources beyond those identified in Appendix E become available. Appendix D: Project Listing preface D Plan Update

2 Category Time Period State Sponsor Project ID Facility / Program Location Description Capital Cost Roadway 2015 to 2020 KS City of Bonner Springs 744 Nettleton Avenue Extension The extension of Nettleton Avenue north from dead end on NE side of K-7 to Nettleton Avenue dead end south of Kansas Avenue. This project includes the construction of a standard width three lane curb and gutter street. Improvements include curb and gutter, sidewalks, storm $2,500,000 Roadway 2015 to 2020 KS City of Bonner Springs 573 South 134th Street 134th Street from Metropolitan to Kansas Avenue This project includes the widening of a narrow two lane ditched road to a standard width three lane curb and gutter street. Improvements include curb $4,050,000 Roadway 2015 to 2020 KS City of Bonner Springs 563 Metropolitan Avenue Improvement Project Metropolitan Avenue between Nettleton Avenue and Western City Limit line. This project includes the widening of a narrow two lane ditched road to a standard width two lane curb and gutter street. Improvements include curb a $1,900,000 Roadway 2015 to 2020 KS City of Bonner Springs 576 Kansas Avenue Improvements Kansas Avenue between 134th Street and 138th Street This project includes the widening of a wide three lane road to a standard width four lane curb and gutter street. Improvements include curb and gutters $2,700,000 Roadway 2015 to 2020 KS City of Bonner Springs th Street Improvements 138th Street between K-32 Highway and Kansas Avenue This project includes the widening of a narrow two lane ditched road to a standard width three lane curb and gutter street. Improvements include curb $8,100,000 Roadway 2015 to 2020 KS City of Edgerton 2010 Waverly Road Waverly Road Reconstruction from US-56 to 199th Street; Project includes additional capacity and grade separation at BNSF rail crossing $30,000,000 Roadway 2015 to 2020 KS City of Edwardsville th Street/Edwardsville Dr. 110th Street/Edwardsville Drive from I-70 to K-32 Reconstruct 110th Street/ Edwardsville Drive from I- 70 south to K-32. Current road is a substandard 2 lane road section with a typical roadway width $7,035,580 Roadway 2015 to 2020 KS City of Gardner th Street Improvements, I-35 to Clare Road 175th Street, I-35 to Clare Road The improvement will include 3250 lineal feet of divided arterial street with sidewalks, street lights, storm sewer and a traffic signal at the Clare $4,600,000 Roadway 2015 to 2020 KS City of Lansing 300 DeSoto Rd Ida St to Eisenhower Rd On DeSoto Road (C-3414), from Ida Street to Eisenhower Road, including intersection approaches Reconstruct rural-type 2-lane road to current standard 4-lane facility to accommodate growing traffic demand. Construct RCB. Construct 10 ft. bicycle $7,219,000

3 Roadway 2015 to 2020 KS City of Leavenworth 539 Eisenhower Road from 155th Street west to (future) 30th Street (County Road 29) Beginning at the existing intersection of Eisenhower Road and 155th Street, then continuing west for 4.3 mile The existing alignment of Eisenhower Road is approximately the City Limit Line between Leavenworth and Lansing. $30,000,000 Roadway 2015 to 2020 KS City of Leawood rd Street Nall to Kenneth Road This project includes the wideing of 143rd Street from a 2-lane ditch street to a 4- lane undivided curb and gutter street The project will improve the current 2-lane ditch street to a 4-lane street with curb and gutter, streetlights, stormsewer, sidewalk, bike/hike trail, $23,400,000 Roadway 2015 to 2020 KS City of Lenexa th & I th Street and I-435 interchange Improvements to the existing interchange to provide capacity on the interchange ramps and on 87th Street to meet the projected traffic demand. $5,000,000 Roadway 2015 to 2020 KS City of Lenexa 254 New at K- 10 & Lone Elm K-10 Highway and Lone Elm Road New interchange including street lights, sidewalks, storm sewers, landscaping and stormwater management, BMPs $20,000,000 Roadway 2015 to 2020 KS City of Lenexa th Street from Renner to I-35 95th Street from Renner to I-35 Improve and widen to 4-lane divided roadway with sidewalks, street lights storm sewers, landscaping and storm water management BMPs. This project $15,000,000 Roadway 2015 to 2020 KS City of Lenexa 256 K-10 & Ridgeview K-10 Highway and Ridgeview Road Improvements to the existing interchange to provide capacity on the interchange ramps and on Woodland Road under K-10 to meet the projected traffic de $12,000,000 Roadway 2015 to 2020 KS City of Olathe 323 K-7 (135th to Old 56) K-7 from 135th to Old 56 Hwy. Capacity improvement, widening from 4 to 5 lanes. $6,000,000 Roadway 2015 to 2020 KS City of Olathe 320 Roadway 2015 to 2020 KS City of Olathe 322 Roadway 2015 to 2020 KS City of Olathe 324 Roadway 2015 to 2020 KS City of Olathe 325 Roadway 2015 to 2020 KS City of Olathe 328 Roadway 2015 to 2020 KS City of Olathe th (Clairborne to Mur-Len) College Blvd and K-7 119th (Iowa to Woodland) 119th (Lone Elm to Iowa) Lone Elm (159th to 167th) Lone Elm (167th to 171st) 135th Street from Clairborne to Mur-Len. Capacity improvement, widening from 4 to 6 lanes. $8,000,000 College Blvd and K-7 capacity improvement, installing Roundabouts at the ramp junctions. Extend life of bridge. $2,000, th Street from Iowa to Woodland. Capacity improvements from 2 lane to 4 lane. $4,000, th Street from Lone Elm to Iowa. Capacity improvements from 2 lane to 4 lane. $4,000,000 Lone Elm from 159th Street to 167th Street. Lone Elm from 167th Street to 171st Street. Capacity improvement for future K-7 alignment, from a rural 2 lane to 4 lane divided arterial. Capacity improvement for future K-7 alignment, from a rural 2 lane to 4 lane divided arterial. $8,000,000 $8,000,000

4 Roadway 2015 to 2020 KS City of Olathe 332 Roadway 2015 to 2020 KS City of Olathe 330 Ridgeview and K-10 Lone Elm (Old 56 to 151st) Ridgeview and K-10 Lone Elm from Old 56 Hwy to 151st Street. capacity improvement, installing Roundabouts at the ramp junctions. Extend life of bridge. Capacity improvement for future K-7 alignment, from a rural 2 lane to 4 lane divided arterial. $2,000,000 $10,000,000 Roadway 2015 to 2020 KS City of 308 Blue Valley Pkwy, 123rd St. to US-69 Blue Valley Pkwy, 123rd St. to US-69 in The project includes widening Blue Valley Pkwy from a four-lane divided roadway to a six-lane divided thoroughfare with turn lanes, storm sewers, a $2,500,000 Roadway 2015 to 2020 KS City of 296 Metcalf Avenue, 119th St. to 135th St. Metcalf Avenue, 119th St. to 135th St. in The project includes widening Metcalf Avenue from a four-lane divided thoroughfare to a six-lane divided thoroughfare with turn lanes, storm sewers, a $8,000,000 Roadway 2015 to 2020 KS City of th Street, Metcalf to Kenneth 159th Street, Metcalf to Kenneth in The project includes reconstruction of 159th Street from an unimproved two-lane roadway to a four-lane divided thoroughfare with turn lanes, storm sew $15,000,000 Roadway 2015 to 2020 KS City of 249 Quivira Road, 151st St. to 159th St. Quivira Road, 151st St. to 159th St. in The project includes reconstruction of Quivira Road from an unimproved two-lane roadway to a four-lane divided thoroughfare with turn lanes, storm sew $6,000,000 Roadway 2015 to 2020 KS City of 280 Metcalf Avenue, 159th St. to 183rd St. Metcalf Avenue, 159th St. to 183rd St. in The project includes reconstruction of Metcalf Avenue from an unimproved two-lane roadway to a four-lane divided thoroughfare with turn lanes, storm s $15,000,000 Roadway 2015 to 2020 KS City of th Street, Pflumm to US th Street, Pflumm to US-69 in The project includes widening 119th Street from a four-lane divided thoroughfare to a six-lane divided thoroughfare with turn lanes, storm sewers, a r $8,000,000 Roadway 2015 to 2020 KS City of th Street, Pflumm to Quivira 159th Street, Pflumm to Quivira in The project includes reconstruction of 159th Street from an unimproved two-lane roadway to a four-lane divided thoroughfare with turn lanes, storm sew $6,000,000 Roadway 2015 to 2020 KS City of th Street, Pflumm to Switzer 135th Street, Pflumm to Switzer in The project includes widening 135th Street from a four-lane divided thoroughfare to a six-lane divided thoroughfare with turn lanes, storm sewers, a r $8,000,000

5 Roadway 2015 to 2020 KS City of th Street, Antioch to Metcalf 167th Street, Antioch to Metcalf in The project includes reconstruction of 167th Street from an unimproved two-lane roadway to a four-lane divided thoroughfare with turn lanes, storm sew $5,000,000 Roadway 2015 to 2020 KS City of 293 Quivira Road, 119th St. to 143rd St. Quivira Road, 119th St. to 143rd St. in The project includes widening Quivira Road from a four-lane divided thoroughfare to a six-lane divided thoroughfare with turn lanes, storm sewers, a r $12,000,000 Roadway 2015 to 2020 KS City of 294 Antioch Road, 119th St. to 135th St. Antioch Road, 119th St. to 135th St. in The project includes widening Antioch Road from a four-lane divided thoroughfare to a six-lane divided thoroughfare with turn lanes, storm sewers, a r $8,000,000 Roadway 2015 to 2020 KS City of 297 Metcalf Avenue, 135th St. to 159th St. Metcalf Avenue, 135th St. to 159th St. in The project includes widening Metcalf Avenue from a four-lane divided thoroughfare to a six-lane divided thoroughfare with turn lanes, storm sewers, a $12,000,000 Roadway 2015 to 2020 KS City of th Street, Nall to Roe 119th Street, Nall to Roe in The project includes widening east bound 119th Street to complete a six-lane divided thoroughfare with turn lanes, storm sewers, a raised median, side $1,000,000 Roadway 2015 to 2020 KS City of st Street, Chadwick to State Line 151st Street, Chadwick to State Line in The project includes reconstruction of 151st Street from an unimproved two-lane roadway to a four-lane divided thoroughfare with turn lanes, storm sew $5,000,000 Roadway 2015 to 2020 KS City of Shawnee 240 Johnson Drive and I-435 Johnson Drive and I-435 Roadway 2015 to 2020 KS City of Shawnee 238 Nieman Road 64th Street to Johnson Drive Roadway 2015 to 2020 KS City of Shawnee 235 Quivira Road 47th Street to 52nd Terrace This project will include signalization of the on/off ramps related to I-435 and Johnson Drive interchange. During peak times the ramps produce backups The existing Nieman Road is a 4-lane roadway adjacent to mixed-use development. The project will provide reconstruction of Nieman Road, from 64th Street The existing Quivira Road, from 47th Street to 52nd Terrace is a narrow 2-lane ditch section road. The project will provide reconstruction, widening, $2,000,000 $5,000,000 $1,800,000 Roadway 2015 to 2020 KS City of Tonganoxie 447 Laming Road Beginning at the intersection of Laming Road and Leavenworth County Road to 4th Street. This project will be built to comply with the planning done in the US 24/40 Corridor Access and Traffic Management Plan. $2,540,000

6 Roadway 2015 to 2020 KS City of Tonganoxie 446 1st Street Collector Beginning at the intersection of First and Ridge thence east to 206th Street The project is built to comply with the planning goals in US 24/40 Corridor Access and Traffic Management Plan $8,000,000 Roadway 2015 to 2020 KS City of Tonganoxie 445 Woodfield Drive Extension Starting at the intersection of Woodfield Drive and Leavenworth County Road 5 thence east to 193rd Street Comply with the planning provisions in the US 24/40 Corridor Access and Traffic Management Plan $8,100,000 Roadway 2015 to 2020 KS Johnson County, Kansas - Public Works st Street, Gardner Road to Four Corners Southwest Johnson County, south of US- Construction of 191st Street will provide access to 56 and north of I-35 between the cities of the Gardner Road on I-35 for the Gardner and Edgerton. proposed BNSF Intermodal site and logistics park. $14,000,000 Roadway 2015 to 2020 KS KDOT 1000 Replacement of Bridges 30 & 173 of the Lewis & I-70 Clark Viaduct Construct Phase 1 of the selected alternative from the completed study of Project No KA (Westbound I-70 River Truss over the Kansas River $57,500,000 Roadway 2015 to 2020 KS KDOT 704 Complete phases 2, 5, 6, 7, 8 and 16 of interchange improvements I-70/K-7 Reconstruction and capacity improvements of the I- 70/K-7. A current interchange concept was developed as part of the K-7 Corridor Management $101,500,000 Roadway 2015 to 2020 KS Leavenworth County 674 McIntyre Expressway (State Highway K-5 Realignment) State Highway K-5 from the intersection of State Highway K-7 and McIntyre Road (in Lansing, KS) to Interstate 435 at Wolcott Road (in Wyandotte County, KS). The current alignment and the prevailing conditions of K-5 between K-7 and I-435 do not facilitate efficient conveyance of traffic from the Lansing / $39,500,000 Roadway 2015 to 2020 KS Leavenworth County 684 Centennial Bridge (K-92 Bridge Over Missouri River) K-92 Bridge Over Missouri River. The Centennial Bridge provides a means of transport over the Missouri River from Kansas State Highway K- 92 in Leavenworth to Missouri State Highway M- $42,000,000 Roadway 2015 to 2020 MO City of Independence th Street Bridge Over the Little Blue River On 39th Street at the Little Blue River in Eastern Independence This project will replace an obsolete two lane bridge on 39th Street over the Little Blue River. The new bridge will have four through traffic lanes a $3,000,000 Roadway 2015 to 2020 MO City of Kansas City, MO 562 Green Hills NW 72nd Street to Barry Road Reconstruct existing road and widen to 3 lanes. $8,660,500 Roadway 2015 to 2020 MO City of Kansas City, MO 555 Englewood Rd Waukomis Drive TO US 169 Reconstruct existing road and widen to 4 lanes. $13,632,000 Roadway 2015 to 2020 MO City of Kansas City, MO 549 Cookingham Rd Platte Purchase Dr. TO Oak Trwy Reconstruct existing road and widen to 4 lanes. $14,910,000 Roadway 2015 to 2020 MO City of Kansas City, MO 646 Shoal Creek Pkwy Platte Purchase Dr. to Holly St. Reconstruct existing road and widen to 4 lanes and parkway standards $4,846,600 Roadway 2015 to 2020 MO City of Kansas City, MO 543 Congress Ave NW 112th Street to Cookingham Drive Reconstruct existing road and widen to 4 lanes. $7,497,600

7 Roadway 2015 to 2020 MO City of Kansas City, MO 618 Northwood City Limits (Riverside) to Prairie View Drive Reconstruct existing road and widen to 3 lanes. $7,668,000 Roadway 2015 to 2020 MO City of Kansas City, MO th Street MO-150 to Oak Reconstruct existing road and widen to 3 lanes. $7,000,000 Roadway 2015 to 2020 MO City of Kansas City, MO nd/23rd Street Brooklyn to I-70 Reconstruct existing road and widen to 4 lanes. $10,738,220 Roadway 2015 to 2020 MO City of Kansas City, MO 546 Congress Ave Ambassador Dr. TO NW 108th Street Reconstruct existing road and widen to 4 lanes. $7,497,600 Roadway 2015 to 2020 MO City of Kansas City, MO 577 Lees Summit Road Phelps Road to US 40 Reconstruct existing road and widen to 3 lanes. $12,833,250 Roadway 2015 to 2020 MO City of Kansas City, MO 696 Tiffany Springs Road Congress Ave to Skyview Ave New 4 lane facility on new alignment $9,230,000 Roadway 2015 to 2020 MO City of Kansas City, MO 689 Tiffany Springs Pkwy Amity to I-29 New 4 lane facility and interchange improvement $15,336,000 Roadway 2015 to 2020 MO City of Kansas City, MO 582 Lees Summit Road 85th Street to Gregory Reconstruct existing road and widen to 4 lanes. $13,216,650 Roadway 2015 to 2020 MO City of Kansas City, MO 729 NW 64th Street Cosby to Roanridge Capacity improvements to route 45/now 64th street and i-29 interchange including outer road relocation $16,655,000 Roadway 2015 to 2020 MO City of Kansas City, MO 578 Lees Summit Road Lakewood Blvd TO Phelps Road Reconstruct existing road and widen to 3 lanes. $11,498,095 Roadway 2015 to 2020 MO City of Lees Summit 208 Lees Summit Road - Colbern to West City Limits Lee s Summit Road from Colbern Road to Lee s Summit West City Limits Widen Lee s Summit Road from a two lane unimproved road to a four-lane urban standard with turn lanes and traffic signal improvements between the existing $8,660,000 Roadway 2015 to 2020 MO City of Lees Summit 118 Blackwell at US 50 Highway Intersection of Blackwell Road (Extension) and US 50 Highway The extension of Blackwell Road from Shenandoah Drive to the extension of Oldham Parkway (approx. 1 mile) with a diamond interchange at US 50 Highway $23,700,000 Roadway 2015 to 2020 MO City of Liberty 234 I-35 and Pleasant Valley Interim Improvements I-35 and Pleasant Valley Road/South Liberty Parkway affecting the cities of: Liberty, Claycomo, Pleasant Valley and Kansas City, Missouri The project area effects the Interstate 35 On- and Off- Ramps at US Highway 69 and Pleasant Valley Road, US Highway 69 between proposed Flintlock Road $0 Roadway 2015 to 2020 MO City of Pleasant Hill 600 Business 7 Highway Improvements Business 7 Highway in Pleasant Hill from 7 Highway to 58 Highway. This project will resurface Business 7 Highway, install bike lanes, and reconstruct sidewalks including ADA ramps. This is already a vital route in Pleasant Hill $2,000,000 Roadway 2015 to 2020 MO City of Raytown Highway & Blue Ridge Boulevard Intersection Improvements Missouri 350 Highway and Blue Ridge Boulevard Intersection, Raytown, Missouri. Modification of a limited access intersection to provide full access in all directions to support activity center, transit interconnectivity and metro $20,000,000

8 Roadway 2015 to 2020 MO City of Raytown 604 Raytown 350 Highway & Raytown Rd. Intersection Alignment 350 Hwy from Sterling to Maple The 350 Highway / Blue Parkway Corridor Plan was a collaboration between Raytown, Kansas City, and MoDOT. This study calls for the divided 350 highway $36,988,517 Roadway 2015 to 2020 MO TDD - Transportation Development District (Partners in Progress) 805 US 71 & Route 291 Improvements I-49/US-71 and MO 291 This project includes modifications to the I-49/US-71 & MO 291 and modifications to MO 291 in Harrisonville $23,200,000 Roadway 2021 to 2030 KS City of Gardner th Street, West of Waverly Road to City Limits 175th Street, West of Waverly Road to City Limits. This project includes the widening of 175th Street from a 2-lane ditch section to a 4-lane divided street section along with sidewalk, trail, street l $6,500,000 Roadway 2021 to 2030 KS City of Lansing 92 DeSoto Road, 4-H Road to Ida Street On DeSoto Road (C-3414), from 4-H Road to Ida Street, including intersection approaches. Reconstruct rural-type 2-lane road to current standard 4- lane facility to accommodate growing traffic demand. Replace functionally obsolete bridge. $7,988,750 Roadway 2021 to 2030 KS City of Lansing th Street, McIntyre Road to 4-H Road On 147th Street (C-3414), from McIntyre Road (Future regional West By-Pass submitted by Leavenworth County), to 4- H Road, including intersection approaches. Reconstruct 2 1/2 miles of rural-type 2-lane road to current standard 4-lane facility to accommodate growing traffic demand. Replace bridges. $16,967,500 Roadway 2021 to 2030 KS City of Leawood 65 Mission Road 135th to 151st The project is located in the City of Leawood and is a major north south corridor. This improvement is located between 135th Street and 151st Street. The current roadway is a 2-lane ditch street that will be improved to a 4-lane undivided curb and gutter street with LED streetlights, stormsewer, sidewalks $20,400,000 Roadway 2021 to 2030 KS City of Leawood st Street Nall to east City Limit 151st is the furthest south east west street crossing for Leawood. The improvement would begin at Nall and go east to our east City Limit The improvements would include widening 151st from a 2-lane ditch street to a 4-lane divided roadway with LED streetlights, traffic signal, sidewalk, $14,200,000 Roadway 2021 to 2030 KS City of Lenexa th & I th Street and I-435 interchange Improvements to the existing interchange to provide capacity on the interchange ramps and on the bridge over I-435 to meet the projected traffic demand $5,000,000 Roadway 2021 to 2030 KS City of Lenexa 267 Lackman from 107th to Santa Fe Trail Drive Lackman Road from 107th Street to Santa Fe Trail Drive Improve and widen to 4-lane divided roadway with sidewalks, street lights storm sewers, landscaping and storm water management BMPs. $6,000,000

9 Roadway 2021 to 2030 KS City of Lenexa 255 K-10 & Woodland K-10 Highway and Woodland Road Improvements to the existing interchange to provide capacity on the interchange ramps and on Woodland Road under K-10 to meet the projected traffic de $5,000,000 Roadway 2021 to 2030 KS City of Lenexa th from K-7 to Haven 87th Street from K-7 Highway to Haven Improve and widen to 4-lane divided roadway with sidewalks, street lights storm sewers, landscaping and storm water management BMPs. $26,000,000 Roadway 2021 to 2030 KS City of Lenexa 253 Lone Elm from Prairie Star Parkway to K-10 Lone Elm Road from Prairie Star Parkway to K-10 Highway. Improve and widen to 4-lane divided roadway with sidewalks, street lights storm sewers, landscaping and storm water management BMPs. $5,000,000 Roadway 2021 to 2030 KS City of Lenexa 268 College Boulevard from Renner to Pflumm College Boulevard from Renner Boulevard to Pflumm Road. Improve and widen to 6-lane divided roadway with sidewalks, street lights storm sewers, landscaping and storm water management BMPs. $12,000,000 Roadway 2021 to 2030 KS City of Olathe 498 Roadway 2021 to 2030 KS City of Olathe 482 Roadway 2021 to 2030 KS City of Olathe 136 Roadway 2021 to 2030 KS City of Olathe 355 Roadway 2021 to 2030 KS City of Olathe th (K-7 to Ridgeview) K-7 Future (171st to 183rd) 119th and K-7 Ridgeview (119th to 127th) 135th Bridge widening over I th Street from K-7 Hwy to Ridgeview Future K-7 Hwy from 171st Street to 183rd Street. 119th and K-7 interchange Ridgeview from 119th Street to 127th Street. 135th Street bridge over I-35. Roadway 2021 to 2030 KS City of Olathe 354 Old 56 (K-7 to Bridge) Old 56 Hwy from K-7 Hwy to Bridge. Roadway 2021 to 2030 KS City of Olathe 353 Old 56 (Bridge to 151st) Old 56 Hwy from Bridge to 151st. Roadway 2021 to 2030 KS City of Olathe 478 Roadway 2021 to 2030 KS City of Olathe 493 Roadway 2021 to 2030 KS City of Olathe 487 Ridgeview (College to 119th) Pflumm (143rd to 151st) 151st (Old 56 to Lone Elm) Ridgeview from College Blvd to 119th Street. Pflumm from 143rd Street to 151st Street. 151st Street from Old 56 Hwy to Lone Elm. Capacity improvement from a rural 2 lane to 4 lane divided arterial. Realignment of existing K-7 Hwy in compliance with the K-7 corridor plan. capacity improvement, installing Roundabouts at the ramp junctions. Extend life of bridge. $13,000,000 $0 $3,000,000 Capacity improvement, widening from 4 to 6 lanes. $6,000,000 Bridge widening and geometric modifications to serve increased traffic demand. Capacity improvement from a rural 2 lane to 4 lane divided arterial. Capacity improvement from a rural 2 lane to 4 lane divided arterial. $6,000,000 $6,000,000 $6,000,000 Capacity improvement, widening from 4 to 6 lanes. $6,000,000 Capacity improvements from 2 lane to 4 lane. $13,000,000 Construct missing link of 151st Street, including bridge over BNSF railroad and Cedar Creek. Construct 4 lane divided arterial. $15,000,000

10 Roadway 2021 to 2030 KS City of Olathe th (Ridgeview to Mur-Len) 159th Street Ridgeview to Mur-Len Roadway project to improve capacity from 2 lanes to four lanes. $13,000,000 Roadway 2021 to 2030 KS City of Olathe th (K-7 to Iowa) 127th Street from K-7 Hwy to Iowa. Capacity improvements from 2 lane to 4 lane. $7,000,000 Roadway 2021 to 2030 KS City of Olathe 492 College Blvd (West Limits to Clare) College Blvd from west city limits to Clare. Capacity improvements from 2 lane to 4 lane. $20,000,000 Roadway 2021 to 2030 KS City of Olathe 491 Black Bob (151st to Black Bob from 151st Street to 159th 159th) Street. Capacity improvements from 2 lane to 4 lane. $13,000,000 Roadway 2021 to 2030 KS City of Olathe 490 Black Bob (135th to Black Bob from 135th Street to 139th 139th) Street. Capacity improvement, widening from 4 to 6 lanes. $2,000,000 Roadway 2021 to 2030 KS City of Olathe 479 Ridgeview (K-10 to College) Ridgeview from K-10 to College Blvd. Capacity improvement, widening from 4 to 6 lanes. $6,000,000 Roadway 2021 to 2030 KS City of Olathe 480 Ridgeview (KC Road to 135th) Ridgeview from KC Road to 135th Street. Capacity improvement, widening from 4 to 6 lanes. $6,000,000 Roadway 2021 to 2030 KS City of Olathe 352 KC Road (Renner to Ridgeview) KC Road from Renner to Ridgeview. Capacity improvement, widening from 4 to 5 lanes. $11,000,000 Roadway 2021 to 2030 KS City of Olathe th (Woodland to 127th Street form Woodland to Ridgeview) Ridgeview. Capacity improvements from 2 lane to 4 lane. $19,000,000 Roadway 2021 to 2030 KS City of Olathe 494 Woodland and K-10 capacity improvement, installing Woodland and K-10 Roundabouts at the ramp junctions. $2,000,000 Roadway 2021 to 2030 KS City of Olathe th (Hedge to K-7) 135th Street Hedge Lane to K-7. Capacity improvement, widening from 4 to 6 lanes. $6,000,000 Roadway 2021 to 2030 KS City of Olathe 520 Roadway 2021 to 2030 KS City of Olathe 333 Roadway 2021 to 2030 KS City of Olathe 351 Roadway 2021 to 2030 KS City of Olathe 336 Roadway 2021 to 2030 KS City of Olathe th (MurLen to Black 135th Street from Mur-Len to Black Bob. Capacity improvement, widening from 4 to 6 lanes. $6,000,000 Bob) 119th (Black Bob to 119th Street from Black Bob to Pflumm. Capacity improvement, widening from 4 to 6 lanes. $6,000,000 Pflumm) College Blvd (Lone Elm College Blvd from Lone Elm to Woodland. Capacity improvements from 2 lane to 4 lane. $13,000,000 to Woodland) 135th (Black Bob to 135th Street from Black Bob to Pflumm. Capacity improvement, widening from 4 to 6 lanes. $6,000,000 Pflumm) 135th (Ridgeview to 135th Street from Ridgeview to Capacity improvement, widening from 4 to 6 lanes. $8,000,000 Clairborne) Clairborne. Roadway 2021 to 2030 KS City of Olathe th (K-7 to Lone Elm) 119th Street from K-7 to Lone Elm Increase from 2 lanes to 4 lanes $13,000,000 Roadway 2021 to 2030 KS City of Olathe th (Renner to I-35) 119th Street from Renner to I-35. Roadway 2021 to 2030 KS City of Olathe 511 Roadway 2021 to 2030 KS City of Olathe 510 Black Bob (127th to 135th) Black Bob (119th to 127th) Black Bob from 127th Street to 135th Street. Black Bob from 119th Street to 127th Street. Capacity improvement, widening eastbound lanes from 2 to 3 lanes. $2,500,000 Capacity improvement, widening from 4 to 6 lanes. $6,000,000 Capacity improvement, widening from 4 to 6 lanes. $6,000,000

11 Roadway 2021 to 2030 KS City of Olathe 347 Roadway 2021 to 2030 KS City of Olathe th (Ridgeview to Renner) 127th and K-7 119th Street from Ridgeview to Renner. Capacity improvement, widening from 4 to 6 lanes. $6,000, th and K-7 (future interchange) New Roundabout replacing an at-grade intersection. $2,000,000 Roadway 2021 to 2030 KS City of th/179th St, Lackman to Metcalf 175th/179th St, Lackman to Metcalf in The project includes widening 175th/179th Street from a two-lane roadway to a four-lane divided thoroughfare with turn lanes, storm sewers, a raised $25,000,000 Roadway 2021 to 2030 KS City of 3000 Quivira Road, 159th St. to 179th St. Quivira Road, 159th St. to 179th St. in The project includes reconstruction of Quivira Road from an unimproved two-lane roadway to a four-lane divided thoroughfare with turn lanes, storm sew $15,000,000 Roadway 2021 to 2030 KS City of 269 Quivira Road, 179th St. to 191st St. Quivira Road, 179th St. to 191st St. in The project includes reconstruction of Quivira Road from an unimproved two-lane roadway to a four-lane divided thoroughfare with turn lanes, storm sew $7,500,000 Roadway 2021 to 2030 KS City of 276 Antioch Road, 167th St. to 179th St. Antioch Road, 167th St. to 179th St. in The project includes reconstruction of Antioch Road from an unimproved two-lane roadway to a four-lane divided thoroughfare with turn lanes, storm sew $7,500,000 Roadway 2021 to 2030 KS City of 281 Kenneth Road, 143rd St. to 159th St. Kenneth Road, 143rd St. to 159th St. in The project includes reconstruction of Kenneth Road from an unimproved two-lane roadway to a four-lane divided thoroughfare with turn lanes, storm sew $10,000,000 Roadway 2021 to 2030 KS City of 295 Antioch Road, 135th St. to 167th St. Antioch Road, 135th St. to 167th St. in The project includes widening Antioch Road from a four-lane divided thoroughfare to a six-lane divided thoroughfare with turn lanes, storm sewers, a r $16,000,000 Roadway 2021 to 2030 KS City of st Street, Rosehill to Nall 151st Street, Rosehill to Nall in Overland Park The project includes widening 151st Street from a four-lane divided thoroughfare to a six-lane divided thoroughfare with turn lanes, storm sewers, a r $18,000,000 Roadway 2021 to 2030 KS City of th Street, Switzer to Nall 135th Street, Switzer to Nall in Overland Park The project includes widening 135th Street from a sixlane divided thoroughfare to a eight-lane divided thoroughfare with turn lanes, storm sewers, a $12,000,000

12 Roadway 2021 to 2030 KS City of 278 Antioch Road, 179th St. to 199th St. Antioch Road, 179th St. to 199th St. in The project includes reconstruction of Antioch Road from an unimproved two-lane roadway to a four-lane divided thoroughfare with turn lanes, storm sew $12,500,000 Roadway 2021 to 2030 KS City of th Street, Antioch to US th Street, Antioch to US-69 in Roadway 2021 to 2030 KS City of Shawnee 232 Renner Road 79th Street to Holliday Drive Roadway 2021 to 2030 KS City of Shawnee 228 Woodland Road 71st Street to 7900 Block The project includes widening 199th Street from a two-lane roadway to a four-lane divided thoroughfare with turn lanes, storm sewers, a raised median, The existing Renner Road varies from a 4-lane roadway adjacent to mixed development to a narrow 2-lane ditch section road that meanders through an und The existing Woodland Road is a narrow 2-lane ditch section road that has horizontal and vertical sight distance issues. The project will provide $2,500,000 $22,000,000 $6,700,000 Roadway 2021 to 2030 KS City of Shawnee th Street Monticello Road to Mize Road Roadway 2021 to 2030 KS City of Shawnee th Street Gleason Road to Mize Road The existing 75th Street is a narrow 2-lane ditch section road that bisected by K-7 Highway. The project will provide reconstruction and widening of The proposed 67th Street does not exist today but would extend 67th west of Gleason Road and connect to Mize Road. This project includes pedestrian s $13,700,000 $6,700,000 Roadway 2021 to 2030 KS City of Shawnee 231 Shawnee Mission Parkway K-7 Highway to I-435 Shawnee Mission Parkway, between I-435 and K-7 Highway is a 4- lane ditch section major arterial that is the City's main east-west trafficway. This pro $35,000,000 Roadway 2021 to 2030 KS City of Shawnee 233 Lackman Road 75th Street to Johnson Drive The existing Lackman Road varies from a 4-lane roadway adjacent to mixed development to a narrow 2-lane ditch section road that dead-ends at an existing $10,000,000 Roadway 2021 to 2030 KS City of Shawnee 236 Shawnee Mission Parkway Pflumm Road to I-435 Shawnee Mission Parkway, between Pflumm and I- 435 is a 4-lane ditch section major arterial that is the City's main east-west trafficway. This project w $15,000,000

13 Roadway 2021 to 2030 KS City of Shawnee 241 K-7 Highway s Intersections at 43rd Street, 47th Street, 71st Street, 75th Street, Shawnee Mission Parkway and 83rd Street. As part of the K-7 corridor study, KDOT has provided a guideline for intersections along K-7 Highway. A long range goal is to convert all at-grade in $75,000,000 Roadway 2021 to 2030 KS City of Shawnee 67 Monticello Road Midland Drive to 7900 Block The existing Monticello Road is a narrow 2-lane ditch section road that traverses through a residential neighborhood. The project will provide recons $13,700,000 Roadway 2021 to 2030 KS City of Tonganoxie 431 Roadway 2021 to 2030 KS City of Tonganoxie th Street Parkway Phase II 206th Street Parkway Phase III Roadway 2021 to 2030 KS City of Tonganoxie th Street Roadway 2021 to 2030 KS City of Tonganoxie 450 East Street Extension Roadway 2021 to 2030 KS City of Tonganoxie th Street Parkway Phase I Roadway 2021 to 2030 KS City of Tonganoxie 460 Washington Street Roadway 2021 to 2030 KS Johnson County, Kansas - Public Works Roadway 2021 to 2030 KS KDOT Roadway 2021 to 2030 KS KDOT th Street, Stilwell Community area to Mission Road K-7 upgrade to 4-lane freeway From I-435 to 67th Street, reconstruct to add lanes and implement operations strategies Starting at US 24/40 south to future Honey Creek Road alignment Beginning at the intersection of 206th Street and Honey Creek Road thence south and west to the to Leavenworth County Road 1 between Honey Creek Road and Hemphill Road Beginning at the intersection of 14th Street and US 24/40 thence east to 214 Street Beginning at the intersection of 4th Street and East Street, thence south Honey Creek Road Starting at Leavenworth County Road 5 thence south to US 24/40 beginning at the intersection of Washington Street and US 24/40 thence east along Washington Street to 198th Street. Southeast Johnson County comply with the planning in the US 24/40 Corridor Access and Traffic Management Plan $10,625,000 Comply with the Tonganoxie Comprehensive Plan $9,860,000 The construction of this route is planned in the US 24/40 Corridor Access and Traffic Management Plan This project is built to comply with the provisions of US 24/40 Corridor Access and Traffic Management Plan Comply with the planning goals in US 24/40 Corridor Access and Traffic Management Plan This project is planned in the US 24/40 Corridor Access and Traffic Management Plan. The project includes a new street and a new bridge over Tonganoxie Improvement of a rural standard roadway to a 40 wide street with curb and gutter. The project includes a railroad grade separation. $2,188,000 $8,500,000 $459,000 $12,750,000 $7,500,000 K-7 from 215th Street to 175th Street Modify to freeway design standards $60,500,000 I-35 Reconstruction and widening of approximately 5 miles of I-35 in order to meet the corridors needs and future expected travel demand. $140,000,000

14 Roadway 2021 to 2030 KS KDOT 3001 Roadway 2021 to 2030 KS KDOT 3002 Arterial street enhancements to existing K-7 in Olathe K-7 upgrade to a 4-lane freeway K-7 Construct arterial street enhancements along K-7 from the end of the 4 lane freeway at the signal at 127th south along Lone Elm to I-35. $47,300,000 K-7 from 43rd Street to K-10 Modify to freeway design standards $46,200,000 Roadway 2021 to 2030 KS KDOT 3003 K-7 intersection enhancements K-7 from Lansing to State Ave Construct expressway intersection enhancements from the City of Lansing to State Avenue. $21,000,000 Roadway 2021 to 2030 KS KDOT 3010 I-70/K-7 (phases 9-15) I-70/K-7 Complete phases 9-15 of interchange improvements. A current interchange concept was developed as part of the K-7 Corridor Management Plan. The $292,500,000 Roadway 2021 to 2030 KS Leavenworth County 698 West Leavenworth / Lansing K-7 Bypass Commencing at K-7 west of Fort Leavenworth, thence south and southeasterly around the west city limits of Leavenworth and Lansing to the intersection of K-7 and McIntyre Road The existing alignment of K-7 conveys traffic flow through the communities of Leavenworth and Lansing. Numerous cross-streets, curb cuts, and traffic $62,000,000 Roadway 2021 to 2030 KS Unified Government of WYCO/KCK 422 I-35 and Lamar Avenue I-35 and Lamar Avenue (24th St) in Kansas City, KS immediately adjacent to Mission, KS Project is proposed to reconstruct to modern geometrics and safety standards the last remaining interchange on I-35 from the original 1960s highway co $18,000,000 Roadway 2021 to 2030 KS Unified Government of WYCO/KCK 407 I-70 and Turner Diagonal Re-I-7configuration and Turner Diagonal Re-configuration and reconstruction of existing interchange that was originally built to accommodate turnpike traffic with room for toll booths and vehicles $20,000,000 Roadway 2021 to 2030 MO City of Gladstone 316 N. Broadway Street Improvement N. Broadway- Englewood Road to NW 76th Street The project will include improvements to N. Broadway from Englewood Road to NW 76th Street. Portions of the existing roadway are 2 lane in each directions $7,000,000 Roadway 2021 to 2030 MO City of Independence th Street, West City Limits to Crysler This project will be along existing 39th Street from the West City limits east to Crysler Avenue. The 39th Street, West City limits to Crysler Avenue, Project will improve the last section of 39th Street from two lanes to three lanes. The roadway w $4,000,000 Roadway 2021 to 2030 MO City of Independence 361 M-78 Highway This project is located on existing M-78 Improvements, Speck to Highway from Speck Road northeast to Truman Road Truman Road. The M-78 Highway Improvements, Speck to Truman Road, will improve the existing M-78 Highway from two lanes to four lanes in Eastern Independence. The $12,500,000

15 Roadway 2021 to 2030 MO City of Independence 372 Roadway 2021 to 2030 MO City of Independence 349 Winner Road, U.S. 24 Highway to Sterling Avenue M-7 Highway Improvements, Pink Hill Road to U.S. 24 Highway This project is located on existing Winner Road from U.S. 24 Highway southeast to Sterling Avenue. This project is located on existing M-7 Highway from its intersection with Pink Hill Road, north to U.S. 24 Highway. The Winner Road, U.S. 24 Highway to Sterling Avenue, Project will improve the existing Winner Road from two lanes to three lanes in most areas. The r The M-7 Highway Improvements, Pink Hill Road to U.S. 24 Highway, will improve approximately six miles of M-7 Highway into a four lane street with curb $7,200,000 $30,000,000 Roadway 2021 to 2030 MO City of Kansas City, MO 637 Pleasant Valley N Brighton to Searcy Creek Pkwy Reconstruct existing road and widen to 3 lanes. $19,880,000 Roadway 2021 to 2030 MO City of Kansas City, MO 541 North Brighton Avenue Pleasant Valley Road to NE 76th Street Reconstruct existing road and widen to 4 lanes. $14,049,125 Roadway 2021 to 2030 MO City of Kansas City, MO 557 Front Street I-35 TO Chouteau Reconstruct existing road and widen to 3 lanes. $47,925,000 Roadway 2021 to 2030 MO City of Kansas City, MO 642 Red Bridge Blue River to US 71 Reconstruct existing road and widen to 3 lanes. $23,004,000 Roadway 2021 to 2030 MO City of Kansas City, MO th Street Troost to Prospect Reconstruct existing road and widen to 4 lanes. $10,576,160 Roadway 2021 to 2030 MO City of Kansas City, MO 547 Cookingham Rd Woodland Ave TO I-435 Reconstruct existing road and widen to 4 lanes. $19,820,000 Roadway 2021 to 2030 MO City of Kansas City, MO 550 Cookingham Rd Oak Trwy TO Woodland Ave Reconstruct existing road and widen to 4 lanes. $13,951,500 Roadway 2021 to 2030 MO City of Kansas City, MO 522 Amity Rd MO-152 to Tiffany Springs Pkwy Reconstruct existing road and widen to 4 lanes. $13,206,000 Roadway 2021 to 2030 MO City of Kansas City, MO 673 Shoal Creek Pkwy I-435 to NE 108th New 4 lane parkway facility to replace unimproved road $49,940,000 Roadway 2021 to 2030 MO City of Kansas City, MO 551 Cookingham Rd I-435 TO Skyview Ave Reconstruct existing road and widen to 4 lanes. $13,632,000 Roadway 2021 to 2030 MO City of Kansas City, MO 420 Ambassador NW Plaza Circle to NW 128th Street New 4 lane facility $17,863,600 Roadway 2021 to 2030 MO City of Kansas City, MO 2000 Shoal Creek Pkwy NE 108th to Woodland Ave Additional 2 lanes to parkway standards $6,400,000 Roadway 2021 to 2030 MO City of Kansas City, MO 579 Lees Summit Road Gregory to Lakewood Blvd Reconstruct existing road and widen to 3 lanes. $16,614,000 Roadway 2021 to 2030 MO City of Kansas City, MO 609 Maplewoods Parkway M-1 to SPRUCE Reconstruct existing road and widen to 4 lanes and parkway standards $6,688,600 Roadway 2021 to 2030 MO City of Kansas City, MO 678 Skyview NW 108th Street to Cookingham Drive Reconstruct existing road and widen to 4 lanes. $14,200,000 Roadway 2021 to 2030 MO City of Kansas City, MO 605 Little Blue Road Woodson to Noland Reconstruct existing road and widen to 4 lanes. $14,995,200 Roadway 2021 to 2030 MO City of Kansas City, MO 620 NW 108th Congress Ave to Skyview Ave New 4 lane facility to replace unimproved road $8,990,000 Roadway 2021 to 2030 MO City of Kansas City, MO 680 Tiffany Springs Pkwy N. Revere to Green Hills Road New 4 lane parkway facility $11,400,000 Roadway 2021 to 2030 MO City of Kansas City, MO 608 Maplewoods Parkway NE 96th Street to Shoal Creek Pkwy Reconstruct existing road and widen to 4 lanes and parkway standards $24,360,000 Roadway 2021 to 2030 MO City of Kansas City, MO 2004 East Longview Pkwy MO-350 to E 82nd Street New 4 lane parkway facility $10,530,300 Roadway 2021 to 2030 MO City of Kansas City, MO 700 Woodland Shoal Creek Pkwy to I-435 Reconstruct existing road and widen to 4 lanes. $16,188,000 Roadway 2021 to 2030 MO City of Kansas City, MO 570 Indiana Ave Barry Road TO Shoal Creek Pkwy Widen improved facility to 4 lanes $7,313,000 Roadway 2021 to 2030 MO City of Kansas City, MO 567 Holmes Rd Martha Truman TO 115th Reconstruct existing road and widen to 4 lanes. $11,991,900

16 Roadway 2021 to 2030 MO City of Lees Summit 121 Todd George at US 50 Highway Intersection of Todd George Parkway/Ranson Road and US 50 Highway Reconstruct/widen the existing interchange at Todd George Parkway/Ranson Road and US 50 Highway. Capacity improvements will upgrade the existing 4-la $18,000,000 Roadway 2021 to 2030 MO City of Lees Summit 122 Pryor Road - Longview Road to M-150 Pryor Road from Longview Road to M- 150 Highway Widen Pryor Road from a two-lane interim road standard to a four-lane urban standard with turn lanes and warranted traffic signals between Longview Ro $14,250,000 Roadway 2021 to 2030 MO City of Liberty 585 I-35/M-291 Improvements I-35 / M-291 modifications at I-35 and M-291. By replacing the aging bridge, eliminating traffic signals, coordinating signals and expanding M291 with $12,500,000 Roadway 2021 to 2030 MO City of Liberty 631 Pleasant Valley I-35 Pleasant Valley Road / I-35 / US-69. modifications at I-35 & Pleasant Valley Road & US-69 $0 Roadway 2021 to 2030 MO City of Liberty 587 I-35/MO 152 I-35/MO 152 improvements including: bridge widening to accommodate necessary lanes and the improvement of left turn movements exiting off I-35; $10,000,000 Roadway 2021 to 2030 MO City of Peculiar th Street 211th Street from State Route J to State Route Y The 211th Street project is proposed in conjunction with a new interchange at 211th Street and I-49/U.S. 71 Highway. The interchange will be a separate $40,000,000 Roadway 2021 to 2030 MO City of Peculiar th Street & I-49/U.S. I-49/U.S 71 Highway at future 211th 71 Highway Street in northern Peculiar The 211th Street & I-49/U.S. 71 project is proposed in conjunction with a new 5-mile segment of 211th Street extending from State Route J $14,289,588 Roadway 2021 to 2030 MO City of Pleasant Hill 204 M-7 Highway Improvements M-7 Highway from 50 Highway to 163rd Street. This project will continue improvements already made to M-7 Highway in south Blue Springs and in Pleasant Hill south of 163rd Street. It will provide $20,000,000 Roadway 2021 to 2030 MO Platte County 653 Improvements to MO 92 - Phase 1 From Leavenworth to I-29 Safety Improvements, Widening to accommodate current capacity, Multi-modal shared use path, Park and Ride facility at MO-169. $40,000,000 Roadway 2031 to 2040 KS City of Gardner 720 US-56 Improvements - Moonlight Road to I-35 US-56, Moonlight Road to I-35 including improvements or modifications to the interchange at New Century Parkway Future capacity deficiencies of this section of US-56 have been identified in the Break-in-Access study and the draft Environmental Assessment for the $50,000,000

17 Roadway 2031 to 2040 KS City of Lansing 223 West Gilman Road, Willow Street to 147th Street On West Gilman Road (C-3413), from Willow Street to DeSoto Road. Extend Gilman Road (new location) per Lansing Comprehensive Plan. Currently shown on KDOT Functional Classification Map as proposed collector. $3,148,800 Roadway 2031 to 2040 KS City of Lansing H Road, DeSoto Road to K-7 Roadway 2031 to 2040 KS City of Leawood 74 Kenneth Road Widening On 4-H Road (C-3402), from DeSoto Road to K-7(US-73)(Main Street). The project scope is located between 138th to 143rd Street. North of 138th Kenneth is 4-lanes. This project would widen Kenneth from 2-lanes to 4-lanes from 138th to 143rd Street. Reconstruct rural-type 2-lane road to current standard 4-lane facility to accommodate growing traffic demand. Construct 10 ft. bicycle path and 5 ft. The project will widen the current 2-lane road to a 4- lane undivided roadway. The improvements will include relocating the existing sidewalks along $6,622,000 $3,200,000 Roadway 2031 to 2040 KS City of Lenexa rd Street Gleason to West City Limits 83rd Street from Gleason to West city limits Improve and widen to 4-lane divided roadway with sidewalks, street lights storm sewers, landscaping and storm water management BMPs. $20,000,000 Roadway 2031 to 2040 KS City of Lenexa 248 Roadway 2031 to 2040 KS City of Lenexa 247 New at Clare and K-10 Canyon Creek Blvd & K- 10 Clare Road and K-10 Highway Canyon Creek Boulevard and K-10 Highway New interchange at Clare and K-10 Highway to provide access and connectivity. Modify and improve the existing Canyon Creek Boulevard and K-10 interchange to provide the needed capacity to support the anticipated development $20,000,000 $5,000,000 Roadway 2031 to 2040 KS City of Lenexa 246 New at Prairie Star Parkway & K-Prairie Star Parkway and K Construction of a new interchange at Prairie Star Parkway and K-10 to provide access and connection to Prairie Star Parkway and areas in western Lenexa $20,000,000 Roadway 2031 to 2040 KS City of Lenexa 244 Prairie Star Parkway from Mize to K-10 Prairie Star Parkway from Mize Road to K- 10 Highway. New 4-lane divided roadway including sidewalks and a 10-foot wide bike/ped trail along one side. Also included are street lights, storm sewers, landscape $15,400,000 Roadway 2031 to 2040 KS City of Olathe th (Hedge to Lone Elm) 175th Street from Hedge Lane to Lone Elm. Capacity improvement from a rural 2 lane to 4 lane divided arterial. $13,000,000 Roadway 2031 to 2040 KS City of Olathe th (Lone Elm to K-7) 159th Street from Lone Elm to K-7 Hwy. Capacity improvements from 2 lane to 4 lane. $13,000,000 Roadway 2031 to 2040 KS City of Olathe 505 Roadway 2031 to 2040 KS City of Olathe th (Black Bob to Pflumm) 151st Bridge widening at I th Street from Black Bob to Pflumm. Capacity improvements from 2 lane to 4 lane. $13,000, st Street and I-35. Capacity improvement, widening bridge between ramps from 4 to 6 lanes. $15,000,000

Transportation Outlook 2040 Project List

Transportation Outlook 2040 Project List Transportation Outlook 2040 Project List Transportation Outlook 2040 is the metropolitan transportation plan (MTP) for the greater Kansas City region. A major component of the MTP is identifying a list

More information

Transportation Outlook 2040 Project List

Transportation Outlook 2040 Project List Transportation Outlook Project List Transportation Outlook is the metropolitan transportation plan (MTP) for the greater Kansas City region. A major component of the MTP is identifying a list of regionally

More information

In Collaboration with: City of Belton Cass County FHWA Johnson County KDOT MoDOT City of Olathe City of Overland Park

In Collaboration with: City of Belton Cass County FHWA Johnson County KDOT MoDOT City of Olathe City of Overland Park In Collaboration with: City of Belton Cass County FHWA Johnson County KDOT MoDOT City of Olathe City of Overland Park I. Background During the Johnson County Board of County Commissioner s (JCBOCC) meeting

More information

TTPC AGENDA REPORT Agenda Item No. 9 September 16, 2014

TTPC AGENDA REPORT Agenda Item No. 9 September 16, 2014 TTPC AGENDA REPORT Agenda Item No. 9 September 16, 2014 ISSUE: VOTE: Approve Committee Recommendations for CMAQ, STP and TAP BACKGROUND On February 3, 2014, MARC issued a call for projects for the federal

More information

KANSAS CITY METROPOLITAN REGION TRANSPORTATION IMPROVEMENT PROGRAM FISCAL YEARS Thursday, July 26, :29 PM. Description: Status:

KANSAS CITY METROPOLITAN REGION TRANSPORTATION IMPROVEMENT PROGRAM FISCAL YEARS Thursday, July 26, :29 PM. Description: Status: Kansas KANSAS CITY METROPOLITAN REGION TRANSPORTATION IMPROVEMENT PROGRAM FISCAL YEARS -2022 Thursday, July 26, TIP #: 397003 Juris: EDGERTON 207TH GRADE SEPARATION County: JOHNSON :.2 The 207th Street

More information

4. ENVIRONMENTAL IMPACT ANALYSIS 9. TRANSPORTATION AND TRAFFIC

4. ENVIRONMENTAL IMPACT ANALYSIS 9. TRANSPORTATION AND TRAFFIC 4. ENVIRONMENTAL IMPACT ANALYSIS 9. TRANSPORTATION AND TRAFFIC 4.9.1 INTRODUCTION The following section addresses the Proposed Project s impact on transportation and traffic based on the Traffic Study

More information

Basalt Creek Transportation Refinement Plan Recommendations

Basalt Creek Transportation Refinement Plan Recommendations Basalt Creek Transportation Refinement Plan Recommendations Introduction The Basalt Creek transportation planning effort analyzed future transportation conditions and evaluated alternative strategies for

More information

APPENDIX G: INTERSECTION NEEDS AT OKEECHOBEE BOULEVARD

APPENDIX G: INTERSECTION NEEDS AT OKEECHOBEE BOULEVARD APPENDIX G: INTERSECTION NEEDS AT OKEECHOBEE BOULEVARD INTERSECTION NEEDS AT SR 7 and OKEECHOBEE BOULEVARD SR 7 Extension Project Development and Environment (PD&E) Study From Okeechobee Boulevard (SR

More information

STUDY PROCESS & SCHEDULE

STUDY PROCESS & SCHEDULE STUDY PROCESS & SCHEDULE Route Centennial Bridge Study KDOT Project No. -52 KA-3229-01 STUDY OVERVIEW STUDY SCHEDULE The Kansas Department of Transportation (KDOT) has identified a future need to replace

More information

City of Wayzata Comprehensive Plan 2030 Transportation Chapter: Appendix A

City of Wayzata Comprehensive Plan 2030 Transportation Chapter: Appendix A A1. Functional Classification Table A-1 illustrates the Metropolitan Council s detailed criteria established for the functional classification of roadways within the Twin Cities Metropolitan Area. Table

More information

ARTINSVILLE ENRY OUNTY REA RANSPORTATION TUDY

ARTINSVILLE ENRY OUNTY REA RANSPORTATION TUDY ARTINSVILLE ENRY OUNTY REA RANSPORTATION TUDY DEVELOPED BY THE TRANSPORTATION AND MOBILITY PLANNING DIVISION OF THE VIRGINIA DEPARTMENT OF TRANSPORTATION IN COOPERATION WITH THE U.S. DEPARTMENT OF TRANSPORTATION,

More information

!!!!!!!!!!!!!!!!!! Metro!Denver!MTD!Governance!Committee! October!23,!2013!!9:00!AM!to!10:00!AM! Denver!Regional!Council!of!Governments!

!!!!!!!!!!!!!!!!!! Metro!Denver!MTD!Governance!Committee! October!23,!2013!!9:00!AM!to!10:00!AM! Denver!Regional!Council!of!Governments! MetroDenverMTDGovernanceCommittee October23,2013 9:00AMto10:00AM DenverRegionalCouncilofGovernments MeetingRecord MetroDenverMTDGovernanceCommittee October23,2013 9:00AM Agenda: 9:00AM Welcome&Introductions

More information

Transportation Element

Transportation Element Transportation Element (2015) Purpose Overland Park strives to create a street and highway network that balances the need for a safe, efficient and well-maintained street network with the desire for environmentally

More information

TRASBURG RANSPORTATION

TRASBURG RANSPORTATION TRASBURG RANSPORTATION LAN DEVELOPED BY THE TRANSPORTATION PLANNING DIVISION OF THE VIRGINIA DEPARTMENT OF TRANSPORTATION IN COOPERATION WITH THE U.S. DEPARTMENT OF TRANSPORTATION, FEDERAL HIGHWAY ADMINISTRATION

More information

City of Gainesville Transportation/Roadway Needs PROJECT SUMMARY

City of Gainesville Transportation/Roadway Needs PROJECT SUMMARY A1 Roadway Resurfacing $23,846,000 TYPE: Preservation of existing system Roadway resurfacing A2 Signal Replacement $6,000,000 TYPE: Preservation of existing system Replace traffic signals. B1 W 6th St

More information

Lee s Summit Road Improvement Study Public Open House June 7, 2007 Summary of Comment Card Responses

Lee s Summit Road Improvement Study Public Open House June 7, 2007 Summary of Comment Card Responses Lee s Summit Road Improvement Study Public Open House June 7, 2007 Summary of Comment Card Responses Introduction At the Lee s Summit Road Improvement Study Public Open House held Thursday, June 7, 2007

More information

STREET AND HIGHWAY PLAN

STREET AND HIGHWAY PLAN STREET AND HIGHWAY PLAN Introduction The street and highway system in the Winston-Salem Urban Area consists of thousands of miles of traffic carrying facilities, ranging from short local residential streets

More information

Appendix C. NORTH METRO STATION AREA TRAFFIC IMPACT STATEMENT 88th Avenue Station

Appendix C. NORTH METRO STATION AREA TRAFFIC IMPACT STATEMENT 88th Avenue Station Appendix C NORTH METRO STATION AREA TRAFFIC IMPACT STATEMENT 88th Avenue Station Prepared for: Regional Transportation Department and URS Corporation as part of the North Metro EIS David Evans and Associates,

More information

M-58 HIGHWAY ACCESS MANAGEMENT STUDY Mullen Road to Bel-Ray Boulevard. Prepared for CITY OF BELTON. May 2016

M-58 HIGHWAY ACCESS MANAGEMENT STUDY Mullen Road to Bel-Ray Boulevard. Prepared for CITY OF BELTON. May 2016 M-58 HIGHWAY ACCESS MANAGEMENT STUDY Prepared for CITY OF BELTON By May 2016 Introduction Missouri State Highway 58 (M-58 Highway) is a major commercial corridor in the City of Belton. As development has

More information

This page intentionally left blank.

This page intentionally left blank. This page intentionally left blank. COMMUNITY Coweta Community Overview Coweta Coweta, a residential community located in Wagoner County, is a suburb of Tulsa situated southeast of the metropolitan area

More information

Welcome. Thank you for your interest in the Lewis & Clark Viaduct Concept Study

Welcome. Thank you for your interest in the Lewis & Clark Viaduct Concept Study Welcome Thank you for your interest in the Lewis & Clark Viaduct Concept Study Please use the arrows in the upper left hand corner to navigate through the presentation. Use the envelope icon to ask a question

More information

BIKE/PEDESTRIAN ANALYSIS

BIKE/PEDESTRIAN ANALYSIS BIKE/PEDESTRIAN ANALYSIS TECHNICAL MEMORANDUM Prepared for the Kansas Department of Transportation and the K-7 Corridor Review Committee October 2013 TABLE OF CONTENTS Introduction...1 Technical Analysis

More information

NEW BRAUNFELS SEGUIN AREA REGIONAL TRANSPORTATION DRAFT PLAN NEW BRAUNFELS CITY COUNCIL MEETING

NEW BRAUNFELS SEGUIN AREA REGIONAL TRANSPORTATION DRAFT PLAN NEW BRAUNFELS CITY COUNCIL MEETING NEW BRAUNFELS SEGUIN AREA REGIONAL TRANSPORTATION DRAFT PLAN NEW BRAUNFELS CITY COUNCIL MEETING February 13, 2012 This regional transportation plan will: 1. Review existing plans for the cities and counties,

More information

This page intentionally left blank.

This page intentionally left blank. This page intentionally left blank. COMMUNITY Glenpool Community Overview Glenpool Glenpool is a city of nearly 12,000 residents located in Tulsa County southwest of Tulsa and Jenks. The city is growing

More information

MOUNTAIN HOUSE SPECIFIC PLAN I 9.1 INTRODUCTION ASSUMPTIONS TRANSPORTATION FACILITIES TRANSPORTATION IMPROVEMENTS PHASING 9.

MOUNTAIN HOUSE SPECIFIC PLAN I 9.1 INTRODUCTION ASSUMPTIONS TRANSPORTATION FACILITIES TRANSPORTATION IMPROVEMENTS PHASING 9. CHAPTER NINE: TRANSPORTATION AND CIRCULATION 9.1 INTRODUCTION 9.1 9.2 ASSUMPTIONS 9.1 9.3 TRANSPORTATION FACILITIES 9.1 9.4 TRANSPORTATION IMPROVEMENTS PHASING 9.3 LIST OF FIGURES LIST OF TABLES Figure

More information

Circulation in Elk Grove includes: Motor vehicles, including cars and trucks

Circulation in Elk Grove includes: Motor vehicles, including cars and trucks Circulation, as it is used in this General Plan, refers to the many ways people and goods move from place to place in Elk Grove and the region. Circulation in Elk Grove includes: Motor vehicles, including

More information

DESIGN MEMORANDUM WITH DESIGN EXCEPTIONS SP SP

DESIGN MEMORANDUM WITH DESIGN EXCEPTIONS SP SP DRAFT NOT FINAL (Note: document was not finalized due to an eastbound stopping site distance design issue that requires more detailed bridge and roadway design considerations. This discussion starts on

More information

Modal Interrelationships: A bicycle lane is proposed between Harrington Ave and Swanns Station Rd.

Modal Interrelationships: A bicycle lane is proposed between Harrington Ave and Swanns Station Rd. DRAFT PROJECT PAGE July 12, 2007 Main St / Broadway Rd (SR 1579) Project Statement Project Recommendation: From Avent Ferry Rd (NC 42) to the Harnett County line, Broadway Rd/Main St is recommended to

More information

Clackamas County Comprehensive Plan

Clackamas County Comprehensive Plan ROADWAYS The County s road system permits the movement of goods and people between communities and regions, using any of a variety of modes of travel. Roads provide access to virtually all property. They

More information

TABLE OF CONTENTS 7.0 THOROUGHFARE PLAN. Analysis of Future Conditions Thoroughfare Plan Proposed Cross-Sections.. 7.

TABLE OF CONTENTS 7.0 THOROUGHFARE PLAN. Analysis of Future Conditions Thoroughfare Plan Proposed Cross-Sections.. 7. TABLE OF CONTENTS 7.0 THOROUGHFARE PLAN Analysis of Future Conditions.. 7.2 Thoroughfare Plan.. 7.3 Proposed Cross-Sections.. 7.4 Arterials Minor Arterials Collectors Local Streets Thoroughfare Plan Map

More information

122 Avenue: 107 Street to Fort Road

122 Avenue: 107 Street to Fort Road : 107 Street to Fort Road November 24, 2015 4:30 8:00 p.m. Meeting Purpose Summarize project work completed to date Share results of public input from Phase 1 Share the draft concept plan and proposed

More information

Legislative Update. Frederick County Fall Staunton District. Interstate 81 - Exit 300 at Interstate 66 Southbound Acceleration Lane Extension

Legislative Update. Frederick County Fall Staunton District. Interstate 81 - Exit 300 at Interstate 66 Southbound Acceleration Lane Extension Interstate 81 - Exit 300 at Interstate 66 Southbound Acceleration Lane Extension Application ID 1643 Northern Shenandoah Valley Regional Commission (NSVRC) $3,437,423 This project extends the Interstate

More information

Chapter 5 Future Transportation

Chapter 5 Future Transportation Chapter 5 Future Transportation The Future Land Use Plan identifies the desired land use designations. The land uses desired for Crozet depend, in large part, on the success of the transportation system,

More information

Bluffdale/ UDOT South High-T Intersection Project Type Operations

Bluffdale/ UDOT South High-T Intersection Project Type Operations Bluffdale/ UDOT 14600 South High-T Intersection Project Type Operations 14600 South and Redwood Road $ 600,000 $ 550,000 This project is to install a new High-T intersection at Redwood Road and 14600 South

More information

Route 7 Corridor Study

Route 7 Corridor Study Route 7 Corridor Study Executive Summary Study Area The following report analyzes a segment of the Virginia State Route 7 corridor. The corridor study area, spanning over 5 miles in length, is a multi

More information

Summary: Mercer County Princeton Avenue & Spruce Street Study January 2009

Summary: Mercer County Princeton Avenue & Spruce Street Study January 2009 Summary: Several recent studies have assessed potential development and redevelopment opportunities in the Mercer Crossing area of Trenton, Ewing, and Lawrence. This Princeton Avenue and Spruce Street

More information

Transportation Analysis and Plan

Transportation Analysis and Plan The City of Waconia is a growing community that will need many miles of additional collector and local streets to serve the development that is forecast. This plan will examine ways to provide those improvements

More information

Appendix 3 Roadway and Bike/Ped Design Standards

Appendix 3 Roadway and Bike/Ped Design Standards Appendix 3 Roadway and Bike/Ped Design Standards OTO Transportation Plan 2040 4/20/2017 Page A3-1 Adopted Standards The adopted OTO Design Standards and Major Thoroughfare Plan are contained herein.

More information

Chapter 6 Transportation Plan

Chapter 6 Transportation Plan Chapter 6 Transportation Plan Transportation Plan Introduction Chapter 6 Transportation Plan Transportation Plan Introduction This chapter describes the components of Arvada s transportation system, comprised

More information

TRANSPORTATION & MOBILITY

TRANSPORTATION & MOBILITY TRANSPORTATION & MOBILITY ROADWAY SYSTEM There are approximately 40 miles of roadways in Manitou Springs. For planning purposes, roadways are typically assigned a functional classification which defines

More information

Project Fact Sheet. August 1,

Project Fact Sheet. August 1, Fact Sheet City of Gainesville Transportation Master Plan In December 2012, the Mayor and City Council selected a consultant team of Pond & Company and Arcadis to prepare the City of Gainesville Transportation

More information

Brooklyn Boulevard (County Road 152) Reconstruction Project Phase I. OPEN HOUSE June 20, 2017

Brooklyn Boulevard (County Road 152) Reconstruction Project Phase I. OPEN HOUSE June 20, 2017 Brooklyn Boulevard (County Road 152) Reconstruction Project Phase I OPEN HOUSE June 20, 2017 Brooklyn Boulevard (County Road 152) Phase I Project Partners Project Lead Other Project Partners include Brooklyn

More information

DES MOINES AREA MPO. Presentation to Iowa Commercial Real Estate Association. April 6, 2017

DES MOINES AREA MPO. Presentation to Iowa Commercial Real Estate Association. April 6, 2017 DES MOINES AREA MPO Presentation to Iowa Commercial Real Estate Association April 6, 2017 Presentation Outline MPO Overview Trends We re Watching Plans, Projects, Initiatives, Regional Transportation Priorities

More information

3.0 Future Conditions

3.0 Future Conditions 3.0 Future Conditions In order to be able to recommend appropriate improvements to the transportation system of the Town, it is important to first understand the nature and volume of traffic that is expected

More information

City of Madison, East Johnson Street North Baldwin Street to First Street Local Street Dane County

City of Madison, East Johnson Street North Baldwin Street to First Street Local Street Dane County City of Madison, East Johnson Street North Baldwin Street to First Street Local Street Dane County Public Involvement Meeting Thursday, April 28, 2016 6 to 8 P.M. Lapham Elementary School 1045 E. Dayton

More information

Feasibility Study of Pedestrian Crossings Along Route 7, East of Cascades Parkway and West of Dranesville Road. October 3, 2017

Feasibility Study of Pedestrian Crossings Along Route 7, East of Cascades Parkway and West of Dranesville Road. October 3, 2017 Feasibility Study of Pedestrian Crossings Along Route 7, East of Cascades Parkway and West of Dranesville Road October 3, 2017 Study Area (area within a ¼-mile radius of the study intersections) Route

More information

Lee s Summit, Missouri Thoroughfare Master Plan

Lee s Summit, Missouri Thoroughfare Master Plan Title Text Interstate Reg. 12 pt. Lee s Summit, Missouri Thoroughfare Master Plan April 2006 Lee s Summit, Missouri Thoroughfare Master Plan i Table of Contents Chapter 1 Introduction 1.1 Purpose of the

More information

Recommended Roadway Plan Section 2 - Land Development and Roadway Access

Recommended Roadway Plan Section 2 - Land Development and Roadway Access Recommended Roadway Plan Section 2 - Land Development and Roadway Access SECTION 2 Land Development and Roadway Access 2.1 Land Use and Access Management The Federal Highway Administration (FHWA) defines

More information

APPENDIX B Greater Kansas City Bikeways Plan

APPENDIX B Greater Kansas City Bikeways Plan APPENDIX B Greater Kansas City Bikeways Plan Existing Conditions Barriers and Gaps Analysis Crash Data Analysis Local government Survey and Report Card 15 16 This page intentionally left blank. 16 North

More information

INDEX. Geometric Design Guide for Canadian Roads INDEX

INDEX. Geometric Design Guide for Canadian Roads INDEX Acceleration lane, see Lanes, Acceleration Access, 8.1 Access Management and Functional Classification 8.2 Access Management by Design Classification 8.3 Access Configuration 8.4 Building Set-Back Guidelines

More information

SECTION 7 INVENTORY OF SELECTED INTERSECTIONS AND RECOMMENDATIONS FOR FURTHER STUDY

SECTION 7 INVENTORY OF SELECTED INTERSECTIONS AND RECOMMENDATIONS FOR FURTHER STUDY SECTION 7 INVEY OF SELECTED INTERSECTIONS AND RECOMMENDATIONS FOR FURTHER STUDY The study corridor includes a total of 19 signalized intersections. Through consultation with Campbell County and the KYTC,

More information

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Projects

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Projects ROUTE/ Project ID No. TIP No. Electrical Load Center Replacement - North 04324 04324 This project will provide for the betterment of the existing highway lighting facilities located along Routes 3, 17

More information

APPENDIX D: SACRAMENTO URBAN AREA TRANSPORTATION PRIORITIES

APPENDIX D: SACRAMENTO URBAN AREA TRANSPORTATION PRIORITIES 1 County County County County 2 Yolo Arterial Roadway Collector Roadway Urban Residential Street Rural Residential Roadway I-80 / U.S. 50 Bus/Carpool Lanes in both directions Richards Blvd PM Yol 80 0.237

More information

Replace Bridge 51 on Blackiston Mill Dr. over Silver Creek,

Replace Bridge 51 on Blackiston Mill Dr. over Silver Creek, INDIANA PROJECTS 1558 Bridge 51 1601823 1601971 I 64 Blackiston Mill Road Phase II Charlestown Rd. Clark State Forest Road Maintenance E. Main Street Improvements to Blackiston Mill Road from just north

More information

Transportation Corridor Studies: Summary of Recommendations

Transportation Corridor Studies: Summary of Recommendations Transportation Corridor Studies: Summary of Recommendations Route 4 Corridor Study: Route 10 Corridor Study: Route 44 Corridor Study: Route 175 Corridor Study: Route 5/15 Corridor Study: Rentschler Field

More information

Multi Modal Transit Access Plan KIPDA ID # 239. Project Type: STUDY

Multi Modal Transit Access Plan KIPDA ID # 239. Project Type: STUDY Multi Modal Transit Access Plan KIPDA ID # 239 Project Type: STUDY Description: In conjunction with the results from Project Gobility and the Transit LOS Analysis, TARC seeks to examine the possibilities

More information

Bay to Bay Boulevard Complete Streets Project

Bay to Bay Boulevard Complete Streets Project Bay to Bay Boulevard Complete Streets Project Dale Mabry Highway to Bayshore Boulevard February 08, 2018 Photo Source: Tampa Bay Times Alessandra Da Pra Meeting Format Introduction Resurfacing Information

More information

Staunton. Transportation Plan. Transportation Planning Division. Virginia Department of Transportation

Staunton. Transportation Plan. Transportation Planning Division. Virginia Department of Transportation 2020 Transportation Plan Developed for the Transportation Planning Division of the Virginia Department of Transportation in cooperation with the U.S. Department of Transportation, Federal Highway Administration

More information

Chapter 6: Transportation

Chapter 6: Transportation Chapter 6: Transportation I. INTRODUCTION The purpose of the Transportation Plan element of the Comprehensive Plan is to provide guidance to the City of North Mankato, as well as existing and future landowners

More information

EXHIBIT B. Bass Lake Rd US 50 to Hollow Oak Rd 2 Lanes with unimproved median and 4 foot paved shoulders. $ %

EXHIBIT B. Bass Lake Rd US 50 to Hollow Oak Rd 2 Lanes with unimproved median and 4 foot paved shoulders. $ % Fee Program Project List - 2004 General Plan Cost Estimate 2004 Alternative Route Study West Valley Condition 27 Alternative connection between, Feasibility study. Included in /White Rock Connector. south

More information

Gordon Proctor Director Policy on Accommodating Bicycle and Pedestrian Travel on ODOT Owned or Maintained Facilities

Gordon Proctor Director Policy on Accommodating Bicycle and Pedestrian Travel on ODOT Owned or Maintained Facilities Approved: Policy: 20-004(P) Responsible Office: Planning Gordon Proctor Director Policy on Accommodating Bicycle and Pedestrian Travel on ODOT Owned or Maintained Facilities I. POLICY STATEMENT: This policy

More information

Corridor Recommendations and Implementation

Corridor Recommendations and Implementation Corridor Recommendations and Implementation INTER-PARCEL CONNECTIVITY Both alternative Concept A and Concept B segments of the Community Core suggest a system of interconnected local streets and local

More information

3.0 PROJECT DESCRIPTION

3.0 PROJECT DESCRIPTION The following section of the Draft EIR contains a description of the proposed Elk Grove Boulevard/SR 99 Interchange Modification project, consistent with the requirements of CEQA Guidelines Section 15124.

More information

Purpose + Need. Connect: Thrive: Develop: < Strengthen the spine of our regional transportation system

Purpose + Need. Connect: Thrive: Develop: < Strengthen the spine of our regional transportation system Purpose + Need I-29 NW Barry Road 64/68/72 MAIN STREET Connect: < Strengthen the spine of our regional transportation system Leavenworth Road Parallel Parkway State Avenue 18th Street Expressway Shawnee

More information

EXHIBIT B-1 PROJECT DESCRIPTION. Phase 1 of the Preferred Alternative

EXHIBIT B-1 PROJECT DESCRIPTION. Phase 1 of the Preferred Alternative EXHIBIT B-1 PROJECT DESCRIPTION Phase 1 of the Preferred Alternative The Transform 66 Public-Private Partnership (P3) Project (the Project ) means the Phase 1 of the Preferred Alternative components of

More information

FI-2 I-66 Between Route 29, Lee Highway and Route 15, James Madison Highway

FI-2 I-66 Between Route 29, Lee Highway and Route 15, James Madison Highway TRANSPORTATION PLAN INTENT Transportation is the key to the economic and social development of Prince William County and especially to the I 66/Route 29 Sector Plan area. This includes transportation for

More information

DRAFT BUENA VISTA 2020 TRANSPORTATION PLAN

DRAFT BUENA VISTA 2020 TRANSPORTATION PLAN DRAFT BUENA VISTA 2020 TRANSPORTATION PLAN DEVELOPED BY THE TRANSPORTATION PLANNING DIVISION OF THE VIRGINIA DEPARTMENT OF TRANSPORTATION IN COOPERATION WITH THE U.S. DEPARTMENT OF TRANSPORTATION, FEDERAL

More information

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Projects

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Projects Barclay Street Viaduct NS9807 NS9807 This project will provide for the rehabilitation of the Barclay Street Viaduct, from Route 19 to Marshall Street, in order to increase the weight load of the structure.

More information

City of Madison, East Johnson Street North Baldwin Street to First Street Local Street Dane County

City of Madison, East Johnson Street North Baldwin Street to First Street Local Street Dane County City of Madison, East Johnson Street North Baldwin Street to First Street Local Street Dane County Public Involvement Meeting Thursday, November 10, 2016 5:30 to 7 P.M. Festival Foods 810 E. Washington

More information

Corpus Christi Metropolitan Transportation Plan Fiscal Year Introduction:

Corpus Christi Metropolitan Transportation Plan Fiscal Year Introduction: Introduction: The Safe, Accountable, Flexible, Efficient Transportation Equity Act: A Legacy for Users (SAFETEA-LU) has continued the efforts started through the Intermodal Surface Transportation Efficiency

More information

Zebulon Multimodal Transportation Plan Update

Zebulon Multimodal Transportation Plan Update Zebulon Multimodal Transportation Plan 2035 Update March 2014 This page intentionally left blank. Table of Contents Section 1: Introduction... 1-1 Study Purpose: Updating the Existing Plan... 1-1 Study

More information

Princeton Avenue and Spruce Street Transportation and Site Access Enhancements Project

Princeton Avenue and Spruce Street Transportation and Site Access Enhancements Project Princeton Avenue and Spruce Street Transportation and Site Access Enhancements Project Mercer County Planning Division AECOM Transportation (formerly DMJM Harris) January 29, 2009 Agenda Project Status

More information

TRAFFIC ACTION PLAN. Laurie Meadows Neighborhood CITY OF SAN MATEO

TRAFFIC ACTION PLAN. Laurie Meadows Neighborhood CITY OF SAN MATEO TRAFFIC ACTION PLAN Laurie Meadows Neighborhood CITY OF SAN MATEO Draft January 2017 Table of Contents Introduction... 2 The Traffic Forum Process... 5 Neighborhood Traffic Issues... 7 Neighborhood Recommendations

More information

RZC Appendix 8A Marymoor Subarea Street Requirements

RZC Appendix 8A Marymoor Subarea Street Requirements RZC Appendix 8A Marymoor Subarea Street Requirements For additional design details for Marymoor Subarea infrastructure, refer to the 2017 Marymoor Subarea Infrastructure Planning Report. STREET REQUIREMENTS

More information

CHAPTER 16 PEDESTRIAN FACILITIES DESIGN AND TECHNICAL CRITERIA TABLE OF CONTENTS

CHAPTER 16 PEDESTRIAN FACILITIES DESIGN AND TECHNICAL CRITERIA TABLE OF CONTENTS CHAPTER 16 PEDESTRIAN FACILITIES DESIGN AND TECHNICAL CRITERIA TABLE OF CONTENTS Section Title Page 16.1 General... 16-1 16.1.1 AASHTO Reference... 16-1 16.1.2 ADA Requirements... 16-1 16.2 Sidewalks...

More information

Building Great Neighbourhoods BELLEVUE AND VIRGINIA PARK

Building Great Neighbourhoods BELLEVUE AND VIRGINIA PARK Building Great Neighbourhoods BELLEVUE AND VIRGINIA PARK This is Meeting 2 Unfortunately, some residents in Bellevue and Virginia Park received the wrong information for this public open house (Meeting

More information

Engineering - Bicycle and Pedestrian

Engineering - Bicycle and Pedestrian Capital Improvement Plan Project Summary # Bikeways Program 781,000 860,000 900,000 933,000 933,000 933,000 # Cannonball Path 1,200,000-780,000 - - - # Capital City Trail - 70,000 - - 910,000 - # Goodman

More information

Project Description Form 8EE

Project Description Form 8EE Project Description Form 8EE Basic Project Information Submitting Jurisdiction/Agency: Town of Dumfries Project Title: Route 1 (Fraley Blvd) Widening: Brady's Hill Road to Dumfries Road Project Location:

More information

5.0 Roadway System Plan

5.0 Roadway System Plan Southwest Boise Transportation Study Page 16 5.0 Roadway System Plan The Roadway System Plan outlines roadway improvements in the Initial Study Area. It forecasts future deficiencies on the arterial system,

More information

Bridges and Arizona Crossings

Bridges and Arizona Crossings Circulation and Transportation 5-11 Discovery Street/Barham Drive. Discovery Street is planned 5.4.3 Specific Plan Circulation Improvements to be extended eastward from its terminus at Craven Road Circulation

More information

connections 2040 the waco metropolitan transportation plan amendment 2

connections 2040 the waco metropolitan transportation plan amendment 2 connections 2040 the waco metropolitan transportation plan amendment 2 developed by the waco metropolitan planning organization in cooperation with the following agencies: Adopted December 14, 2017 amendment

More information

STUDY ADVISORY COMMITTEE. October 8, 2015

STUDY ADVISORY COMMITTEE. October 8, 2015 STUDY ADVISORY COMMITTEE October 8, 2015 Study Purpose evaluate the long-term transportation strategies and investments needed to sustain the county s economic health and quality of life in the coming

More information

5 CIRCULATION AND STREET DESIGN

5 CIRCULATION AND STREET DESIGN 5 CIRCULATION AND STREET DESIGN This chapter describes circulation and streetscape improvements proposed for the Northwest Chico Specific Plan Area. It includes detailed design specifications for existing

More information

ARRENTON RANSPORTATION

ARRENTON RANSPORTATION ARRENTON RANSPORTATION LAN DEVELOPED BY THE TRANSPORTATION PLANNING DIVISION OF THE VIRGINIA DEPARTMENT OF TRANSPORTATION IN COOPERATION WITH THE U.S. DEPARTMENT OF TRANSPORTATION, FEDERAL HIGHWAY ADMINISTRATION

More information

Chapter 4 Traffic Analysis

Chapter 4 Traffic Analysis Chapter 4 Traffic Analysis PURPOSE The traffic analysis component of the K-68 Corridor Management Plan incorporates information on the existing transportation network, such as traffic volumes and intersection

More information

5. MODIFICATIONS AT JEANNE D ARC BOULEVARD/REGIONAL ROAD 174 INTERCHANGE INTERSECTION - PUBLIC HEARING COMMITTEE RECOMMENDATION

5. MODIFICATIONS AT JEANNE D ARC BOULEVARD/REGIONAL ROAD 174 INTERCHANGE INTERSECTION - PUBLIC HEARING COMMITTEE RECOMMENDATION 5. MODIFICATIONS AT JEANNE D ARC BOULEVARD/REGIONAL ROAD 174 INTERCHANGE INTERSECTION - PUBLIC HEARING COMMITTEE RECOMMENDATION Having held a public hearing, that Council approve the preliminary designs

More information

SECTION 1 - TRAFFIC PLANNING

SECTION 1 - TRAFFIC PLANNING SECTION 1 - TRAFFIC PLANNING 1.1 TRAFFIC OPERATIONS 1.1.1 Roadway Functional Classification The Multnomah County Comprehensive Framework Plan s Policy 34: Trafficways and the Functional Classification

More information

Project Update May 2018

Project Update May 2018 Project Update May 2018 Dakota County, in cooperation with the City of Lakeville, is planning to reconstruct 202 nd Street West (County Road 50) from Holyoke Avenue to Cedar Avenue (County Road 23). 202

More information

Highway 49, Highway 351 and Highway 91 Improvements Feasibility Study Craighead County

Highway 49, Highway 351 and Highway 91 Improvements Feasibility Study Craighead County Highway 49, Highway 351 and Highway 91 Improvements Feasibility Study Craighead County Executive Summary March 2015 Highway 49, Highway 351 and Highway 91 Improvements Feasibility Study Craighead County

More information

I-90 ALLSTON INTERCHANGE A MULTIMODAL TRANSPORTATION PROJECT MEPA CONSULTATION MEETING NOVEMBER 20, 2014 BRIGHTON HIGH SCHOOL

I-90 ALLSTON INTERCHANGE A MULTIMODAL TRANSPORTATION PROJECT MEPA CONSULTATION MEETING NOVEMBER 20, 2014 BRIGHTON HIGH SCHOOL I-90 ALLSTON INTERCHANGE A MULTIMODAL TRANSPORTATION PROJECT MEPA CONSULTATION MEETING NOVEMBER 20, 2014 BRIGHTON HIGH SCHOOL Today s Agenda 1. 2. 3. 4. 5. Overview of the MEPA Process Project Overview

More information

TRANSPORTATION TRAINING TOPICS. April 6, 2010

TRANSPORTATION TRAINING TOPICS. April 6, 2010 TRANSPORTATION TRAINING TOPICS April 6, 2010 Roles of Transportation Providers Context and Policy Makers Division of Transportation and Traffic Other City Operations Other Transportation Operators CMA

More information

Giles Run Connector Road

Giles Run Connector Road Giles Run Connector Road Laurel Hill Adaptive Reuse Area to Laurel Crest Drive South County Federation Meeting June 14, 2016 History Connector road included in the Laurel Hill Comprehensive Plan amendment

More information

4.0 ACCESS CONTROL PLAN - SH 14 (JEFFERSON STREET/RIVERSIDE AVENUE)

4.0 ACCESS CONTROL PLAN - SH 14 (JEFFERSON STREET/RIVERSIDE AVENUE) 4.1 Existing Conditions Roadway Physical Characteristics Typical Sections Jefferson Street 4.0 ACCESS CONTROL PLAN - SH 14 (JEFFERSON STREET/RIVERSIDE AVENUE) The existing typical cross-section for SH

More information

WYDOT DESIGN GUIDES. Guide for. NHS Arterial (Non-Interstate)

WYDOT DESIGN GUIDES. Guide for. NHS Arterial (Non-Interstate) WYDOT DESIGN GUIDES Guide for NHS Arterial (Non-Interstate) 2014 GUIDE FOR NATIONAL HIGHWAY SYSTEM (NHS) HIGHWAYS (NHS ARTERIALS, Non-Interstate) PRESERVATION REHABILITATION RECONSTRUCTION INTRODUCTION

More information

West Dimond Blvd Upgrade Jodhpur Street to Sand Lake Road

West Dimond Blvd Upgrade Jodhpur Street to Sand Lake Road West Dimond Blvd Jodhpur St to Sand Lake CSS Transportation Project Summary Municipality of Anchorage Project # 05 005 Project Manager: John Smith, P.E. (MOA PM&E) Project Administrator: Julie Makela,

More information

WYDOT DESIGN GUIDES. Guide for. Non-NHS State Highways

WYDOT DESIGN GUIDES. Guide for. Non-NHS State Highways WYDOT DESIGN GUIDES Guide for Non-NHS State Highways 2014 GUIDE FOR Non-NATIONAL HIGHWAY SYSTEM (Non-NHS) STATE HIGHWAYS PRESERVATION REHABILITATION RECONSTRUCTION INTRODUCTION This Guide is directed to

More information

City of Homewood Transportation Plan

City of Homewood Transportation Plan City of Homewood Transportation Plan Prepared for: City of Homewood, Alabama Prepared by: Skipper Consulting, Inc. May 2007 TABLE OF CONTENTS INTRODUCTION... 1 BACKGROUND INFORMATION... 1 EXISTING TRANSPORTATION

More information

Los Altos Hills Town Council - June 18, 2015 Palo Alto City Council June 22, AGENDA ITEM #2.B Presentation

Los Altos Hills Town Council - June 18, 2015 Palo Alto City Council June 22, AGENDA ITEM #2.B Presentation Los Altos Hills Town Council - June 18, 2015 Palo Alto City Council June 22, 2015 AGENDA ITEM #2.B Presentation Previous Presentations Los Altos Hills Town Council in May 2014 and February 2015 Palo Alto

More information

ACTIVE TRANSPORTATION

ACTIVE TRANSPORTATION ACTIVE TRANSPORTATION Mobility 2040 Supported Goals Improve the availability of transportation options for people and goods. Support travel efficiency measures and system enhancements targeted at congestion

More information

Urban Planning and Land Use