C&P ENGINEERING SERVICES LTD. Hazard Identification, Risk Assessment & Safe Working Procedure for Installation of Unistrut, Ladder Rack and Cable Tray

Size: px
Start display at page:

Download "C&P ENGINEERING SERVICES LTD. Hazard Identification, Risk Assessment & Safe Working Procedure for Installation of Unistrut, Ladder Rack and Cable Tray"

Transcription

1 Hazard Identification, Risk Assessment & Safe Working Procedure for Installation of Unistrut, Ladder Rack and Cable Tray Project Title: Site Address: Client: PO Number: Work Location: Cardiff Road, Barry, South Glamorgan, CF63 2YL Dow Corning Ltd Assessed By: Print Name Signature Date Assessed Assessment Review Date Richard Jenkins 18/02/ /02/2015 Steve Tossell 18/02/ /02/2015 Approved By: Print Name Signature Date Approved Paul Bunyan C&P Engineering Services Ltd Ref Rev Page 1 of 15

2 Hazard Identification Physical Hazards Y Physical Hazards (Continued) Y Fire Hazards Y Airborne Dust / Fumes Explosive Materials Access / Egress Flammable / Combustible Materials Adverse Weather Conditions Flammable Atmospheres Aggression/Violence Pyrophoric Material Bullying Sources of Ignition Collapse of Equipment / Materials Static Electricity Confined Space Entry Crane Movements / Lifting Display Screen Equipment Drowning Electricity - Electric Shock / Burns Entanglement Equipment / Materials Other Hazards Specify Below Vulnerable Groups Falling Objects / Materials from Height Environment - Waste Disposal Falls from Height (Working at Height) Process Pipework Expectant and Nursing Mothers Gas Cylinders Impulse Lines / Tubing Lone Workers Gasses Young Persons High Pressures High Ambient Temperature Hot Surfaces Housekeeping / Slips, Trips& Falls Low Ambient Temperature Manual Handling / Ergonomic Biological Hazards Moving Equipment/Machinery Blood Borne Pathogens / Body Fluids Noise Hygiene/Welfare Operating / Driving MEWP s Legionella Oxygen Depletion / Enrichment Leptospirosis (Weils Disease) Pneumatics / Hydraulics Poor Lighting Radiation Sharp Objects Chemical Hazards Stress Asbestos Struck By / Against Corrosive Chemicals Trapping Points Harmful Chemicals Underground Services Irritant Chemicals Uneven Work Surfaces Odorous/Noxious Chemicals Use of Hand Tools / Power Tools Toxic Chemicals Vehicles/Transport Vibration C&P Engineering Services Ltd Ref Rev Page 2 of 15

3 Risk Assessment Task: - Installation of Unistrut, Ladder Racks & Cable Trays The following risk assessment has been completed to ensure adequate controls are in place to eliminate or reduce the risk to as low as is reasonably practicable. In considering who may be harmed we have included C&P, but for each task, depending on where it takes place, then further consideration should be given to others who may be affected by our activities e.g. other contractors. L = Likelihood C = Consequence HR = Hazard Rating (with NO controls in place). RR = Risk Rating (with controls in Place). 1. Airborne Dust - Some plants may expose employees to windborne dust C&P 2.Access and Egress on site C&P Safety glasses to be worn on site at all times. Safety goggles must be worn in designated red and white striped areas. All areas of plant require a comprehensive Permit to work form for all jobs undertaken on DCL site except when working within office buildings. When working within office buildings a Job Card may be issued by the permit issuer/custodian of the building in place of a Permit to work. Access and egress to each working area will be by roadways, fixed walkways and platforms at each process plant area. Access and egress to the individual working areas will be from the platform or will be by one of the safe working at height methods described in the C&P Engineering Services Ltd Ref Rev Page 3 of 15

4 3.Adverse Weather Conditions. Extremes of weather such as ice, snow, heavy rain, lightning storm etc. This is particularly important when working at height, using ladders, accessing/egressing steps and plant, driving on site C&P 4.Working in Confined Spaces C&P 5.Overhead Crane Movements causing struck by injuries. (Linked with working at height) 6.Electricity - Contact with live electrical components causing electrical shock, burns or electrocution C&P C&P working at height section. For working at height hazard controls please refer to C&P document reference Working at Height Policy. PPE in the form of warm clothing, good quality safety boots, water proof exterior clothing. Ability to postpone jobs in extreme weather conditions i.e. high winds, torrential rain when working at height Site Induction. Site Authorisation to Work Permit. Confined Spaces permit. C&P watchman. Emergency rescue plan in place. RPE available and to be worn depending on confined space. Resuscitation equipment on standby. Specific tools required (discuss with Plant personnel). Only trained and certified C&P operatives to enter confined spaces. Where overhead cranes move overhead, either isolate cranes (client to isolate or with their permission) or bellman required to alert employees to stop work and move away from area. Only qualified and competent persons to work on electrical equipment. All work on electrical equipment only to be carried out following isolation. C&P are competent to undertake the isolations. This must either be done at the local substation or at the fuse board C&P Engineering Services Ltd Ref Rev Page 4 of 15

5 7.Objects falling from Height C&P 8.Falling from Height (Working at Height) C&P For safe isolation please refer to C&P document reference Safe Isolation Procedure for DEAD working on LV and ELV. Permanent metal toe boards on process plant working platforms and on MEWP s. Good housekeeping across whole plant. When working at height area below to be cordoned off by use of bunting and signage to at least 10 metres. Items secured when being transported in a MEWP basket. Discussion to take place at Induction to prevent other workers/contractors working immediately above. Where overhead cranes move overhead, either isolate cranes (plant to isolate or with their permission) or bellman required to alert to stop work and move away from area. Where access to work area requires a step up of a few centimetres then this can be achieved on most levels. Where the need to work at height exposes the individual to a fall to danger then additional controls will need to be in place. These will involve scaffolding platforms. MEWP to be supplied and maintained to a high standard. Trained and certificated C&P operatives to operate the MEWP. Where work areas are at height and close to platform edges then scaffolding should be requested. The scaffolding should be erected by recognised Scaffolding Company C&P Engineering Services Ltd Ref Rev Page 5 of 15

6 9.Gas / Oxygen Depletion C&P 10.Hot Surfaces C&P 11.Slips, Trips and Falls due to poor housekeeping C&P 12.Manual Handling carrying of equipment ladders, tools etc C&P Stepladders with handrails and Fibre glass ladders can be used in many locations where the work is of short duration and the height to work at is relatively low, ladders can be secured or footed and supported. When working from stepladders near to platform edges and there has been NO scaffolding erected, then full body fall arrest harnesses should be worn. Full body fall arrest harnesses are a last resort and should be worn in conjunction with other controls for working at height. Individual gas monitors and procedures for evacuation from Process Areas. Regular Operational checks for gas leaks by trained and competent operators. Regular Planned Maintenance checks and repairs by client. Site Inductions. Hot pipe work lagged/insulated. Signage Good housekeeping practices across site by the client provides for a safe place of work. Clear concrete pathways, roadways and signage. Painted walkways. Good safety footwear. Audits by Plant personnel. C&P standards in housekeeping, safety contacts provided and more specific training. Removal of all waste. Hand tools are relatively lightweight (tools to be carried in single tool box). All Manual Handling tasks are individually Risk Assessed. Individuals trained in Manual Handling techniques. Large and awkward cable tray or ladder rack to be handled/carried by two operatives. Avoid Manual Handling where possible C&P Engineering Services Ltd Ref Rev Page 6 of 15

7 13.Moving Machinery / Entanglement / Trapping points - controlled by Client C&P 14.Noise C&P 15.Operating/driving MEWPS on site C&P Variety of operating machinery could be present in process areas. All moving parts to be guarded. No access beyond any guard or barrier protecting machinery. Permit to work in all plants. Certain areas of plant will require mandatory Hearing Protection in the form of Ear Defenders. Ear defenders to be worn prior to and during time spent in these areas. Signage. Trained and competent operators holding certificate for driving and operating MEWPS. Equipment to be fully maintained and inspected. Driver to use harness at all times when driving on site or when working from MEWP basket at height. When stationary prior to work commencing outriggers must be fully deployed on solid, level ground. If ground is soft or uneven, boards are to be placed under outrigger legs. Whilst working at height, operator is to control movement of basket from the basket and not the floor. Operators working from basket not to over-reach or lean out of basket. Under no circumstance are operators to exit the MEWP basket as a means of access to a place above ground level (except in an emergency). All loose equipment placed in the basket for use will be secured to ensure C&P Engineering Services Ltd Ref Rev Page 7 of 15

8 16.Lighting C&P 17.Use of hand tools and power tools/ Entanglement / Trapping points 18. Vehicles and Transport travel to site and use on site internal roads C&P C&P, other road users they cannot fall. The area around the base of a MEWP will be bunted and have cones to prevent collision from other vehicles and road users and also to prevent persons working or walking underneath. Good plant lighting. Where plant lighting is poor, obtain temporary lighting. If working in potentially explosive atmosphere, torch or headlamp may be used providing they are certified to be used in explosive atmospheres. Permission to be granted by Client personnel and hot work permit may also be required. Drills and other power tools will be battery operated. Where this is not reasonably practicable then low voltage mains will be required (110v workshop only)see electrical controls above. PAT testing of mains operated tools. Secure cables. No loose clothing or jewellery near to rotating chuck. All hand tools to be clean and in good working order, and checked daily. Use of company vehicles. Fully maintained vehicles with current MOT and insurance. Competent drivers holding appropriate licence for the vehicle. Vehicle preflight checks. All tools stored safely in vehicle. Restricted access to site only authorised vehicles. Road signs, road traffic standards, high way code. Pedestrian crossings. Park in designated parking areas only C&P Engineering Services Ltd Ref Rev Page 8 of 15

9 19. Legionella C&P 20.Contact with Dow Corning Chemicals on site Different Process areas manufacture and use different types of chemicals i.e. toxic, corrosive, harmful etc C&P 21.Fire- flammable atmospheres, sources of ignition C&P 22.Lone Workers - Lone Workers, if injured, are more likely to go undetected and could exacerbate the seriousness of the injury due to delays in rescue and treatment C&P Client to provide information on potential Legionella presence by providing COSHH risk assessments. Wearing of RPE. Comprehensive Permit to work form required for all jobs undertaken on DCL site except when working within office buildings. When working within office buildings a Job Card may be issued by the permit issuer/custodian of the building in place of a Permit to work. Dow Corning to provide details of hazards and precautions necessary for each process area including COSHH risk assessments. No sources of ignition to be used or taken on to plant areas without a valid Work Permit for the task Some situations may require minor hot work but it is very unlikely. Agree any hot work necessary with client agree permit required for hot work. Fire extinguishers and fire watchmen at area of hot work.trained competent operators. Familiarisation with Plant specific Emergency Procedures and assembly points. Trained and competent persons. Contact Protocol with C&P supervisor. Individual radio. Plant Alarms. Emergency assembly points. C&P lone worker policy C&P Engineering Services Ltd Ref Rev Page 9 of 15

10 23. Environment - waste disposal Environment Responsibly dispose of all generated waste by using client s on site recycling facilities C&P Engineering Services Ltd Ref Rev Page 10 of 15

11 Risk Matrix First Aid Injury no disruption of activity Minor Injury (preventing activity for one day) Suffering (preventing activity for 3 days or longer Major injury Fatal Certain Probable Likely Possible Unlikely Acceptable Adequate (1-5) No further action but ensure controls are maintained (6-15) Look to improve at next review Unacceptable (16-25) Stop activity and make immediate improvements Safe Working Procedure Final Risk Rating The risk rating for the activity of Installation of Unistrut, Cable Tray and Ladder Rack has a final risk rating of 10, if all the controls are applied at all times. Failure to implement the controls will lead to a higher risk of injury. The level of 10 is tolerable (yellow section 10-15) but improvements should be made to reduce the overall risk down to acceptable (Green section 1-4). This Risk assessment needs to be reviewed in the next 12 months (see review date). Persons and Competency All the C&P Engineering employees who install unistrut, cable trays and ladder racks must have been taken through this SWP and must sign the register to demonstrate that they understand the controls and how they are to be applied. Supervisor to plan the job by visiting site beforehand and calculating the size of cable trays and unistruts required so where reasonably practicable they can be cut to size and shape in the workshop before being taken to site. Planning of job is critical. PPE Requirements Safety Footwear with minimum 200 Joules toe cap. The ankles must be protected. General Proban treated overalls General purpose gloves over surgical nitrile gloves (depending on the task). Safety helmet centurion or equivalent C&P Engineering Services Ltd Ref Rev Page 11 of 15

12 Safety glasses or safety over-glasses to be worn if wearing their own prescription glasses. Goggles are mandatory in chemical splash areas. Ear Defenders are mandatory in certain process areas. High visibility waistcoat. Additional PPE dependent on local conditions. Plant Status Depending on where the job is being carried out, plant will quite likely be working. Electrical isolations may be required for installation of cable trays/ladder racks if live electrical cables present could be affected by the installation. These should be isolated and moved to an alternative position. Permits, Certificates or Registers A general permit to work is required for all work locations and access onto process plant. Any isolation will be recorded on this permit. A separate hot work permit is required for battery operated equipment. Access and Egress Before accessing any part of a process plant then an authorisation from the Client will be required and their permit to work procedure will be followed. Access and egress will be by recognised walkways, pavements, road crossings, stairways. Procedure 1. Wear the PPE that is required for the particular process area that you will be working in. N.B. There is minimum requirement as highlighted in the PPE section above for all areas. Ensure that PPE is in good condition and affords adequate protection. 2. Report to the permit office before accessing site. Obtain a Client permit to work and comply with all requirements stated and explained verbally by the issuer. Additional PPE stated must be worn. Agree access and egress routes. 3. Travel to the building/site area by company vehicle if necessary and park appropriately. 4. Where cable trays/ladder racks are delivered in bundles of six trays (3 metres long) by lorry, then arrangements must be made prior for off-loading. A HIAB or Fork Lift Truck may be required to offload. Ensure Lifting Plan and a competent person in charge of lifting operation has organised the lift. Ensure sufficient space created to off-load in a suitable accessible position as near to the site of work as possible. 5. Where a HIAB is used then a lifting Plan must be created prior to commencement of job. Driver/operator to be fully trained and competent in HIAB lifting operation. 6. Where a mobile crane is required to off-load ladder racks/cable trays at height then the load must be secured. Area around crane to be cordoned off. A banksman will ensure that all persons are clear during crane lift and that all other persons are aware of the lifting activity. Only a competent person trained in slinging techniques to attach lifting slings. Lifting equipment must be to the approved standard with certification of testing and thorough examination. Lifting Plan required for Mobile Crane and a competent person in charge of Lifting operation. C&P Engineering Services Ltd Ref Rev Page 12 of 15

13 7. Cut steel banding wire once the bundles of cable trays have been positioned on site. Stand clear as sections may spring open. 8. Two men to carry individual ladder racks into position. Where 3 metre smaller cable trays or flat plates are being used then two men are still required to carry cable trays especially if carrying them up stairways etc. Where cable trays have been purposely cut to size and are of short length then this can be done by one person. 9. When joining cable trays together four sets of bolts are required each side to secure them together. 10. All ladder racks and cable trays with return lips should be installed with return lip outermost. 11. If ladder racks are required to be positioned vertically and are of greater length than one piece (>3 metres) then they should be bolted together before lifting into position. Scaffolding should be erected at specific heights to allow easy handling of the length of trays. Where it is too difficult to erect scaffolding then two men should be positioned at height to help pull the trays into position using ropes tied to the cable trays whilst two men at ground level should help manipulate the trays and prevent them from swinging. Where anyone needs to lean over to manipulate the trays into position then they must wear a fall arrest harness, either over fixed hand railing, scaffold hand railing or MEWP hand railing. 12. The ladder racks /trays should be temporarily tied in position whilst the racks are bolted to permanent brackets to support the cable trays/ladder racks. Where no permanent brackets are in situ, then these need to be manufactured and welded in place, preferably before the cable trays are fitted. In some areas where it is difficult to attach permanent support brackets then pipe clamps can be used to clamp the unistruts to fixed hand railings with client s permission. 13. Small cable trays can be fitted from a stepladder providing the top of the ladder has handrails fitted. The step ladder must be erected on level, stable ground. If at height and close to a platform edge then a fall arrest harness must be worn. Scaffolding may also be erected on top of the handrail as an extension. 14. Where cable trays need to be fitted to walls or other permanent structures then rather than be bolted directly to the wall they must be attached to unistrut. This will enable easy access for cable installation at a later stage. The unistruts should be cut to length and mounted in positions by drilling holes in the structure and fitting with anchor bolts. 15. The cable trays/ladder racks must then be bolted to the unistruts. All drilling to use low voltage or battery operated drills. Check to make sure that any holes to be drilled do not contact any electrical cables. 16. The distance between Unistruts should be determined bearing in mind the width of the cable trays (150m 600mms wide) and/or the alarm or signal boxes to be fitted. 17. On completion of the job all waste material to be removed from site and re-used or disposed of responsibly. 18. The permit to work will be cancelled. C&P Engineering Services Ltd Ref Rev Page 13 of 15

14 Emergency Procedures Telephone 3333 Internally In the event of an emergency and depending on the site and access to such, the emergency services should be called using the internal emergency number. Raising the alarm is our first priority. All C&P employees must report to their appropriate place of safety, if the alarms aresounded. You must stay at this location and report to the Client representative. Follow the directions of the Client personnel in charge at the muster point. Lifting an eye wash station or stepping on a safety shower will raise alarm to DC Control, who will send assistance to the areaaccordingly. Dow Corning Alarm Signals Klaxon 3 seconds on 3 seconds off Major Incident All personnel to report to their nearest muster point indoors immediately. Swipe badge on Muster Reader. Fire Alarm Bells All personnel to report to their nearest fire assembly point outside immediately. Blue Flashing Light -Outside a Building No personnel to enter the building until advised by a DCL member. Audible Alarm and Red Flashing Light on Process Plant All personnel to make their work area safe and leave the area. No return until advised by a DCL Member. Note: If the last page of this document is not attached do not worry as it does not contain any relevant information regarding the SWP. The last page is a register of signatories and is intended to be detached and returned to Gorseinon head office for filing. C&P Engineering Services Ltd Ref Rev Page 14 of 15

15 Hazard Identification, Risk Assessment & Safe Working Procedure for Instrument Calibration on Client s Site in Situ (and at Client s Workshop). The above document has been read and explained to me by my supervisor. I the undersigned understand the controls and how they are to be applied. Print Name Signature Date The following comments/queries were raised and discussed with my supervisor (Please insert below any concerns, comments or views which may identify additional problems): ** THIS PAGE IS TO BE SIGNED, DATED, DETACHED AND RETURNED TO GORSEINON HEAD OFFICE A.S.A.P. (VIA FAX, , POST OR HAND) ** C&P Engineering Services Ltd Ref Rev Page 15 of 15

C&P ENGINEERING SERVICES LTD

C&P ENGINEERING SERVICES LTD Hazard Identification, Risk Assessment & Safe Working Procedure for Re-Lamping and Cleaning Light Fittings at Dow Corning Ltd, Barry Assessed By: Print Name Signature Date Assessed Assessment Review Date

More information

C&P ENGINEERING SERVICES LTD INSTRUMENTATION & ELECTRICAL ENGINEERS

C&P ENGINEERING SERVICES LTD INSTRUMENTATION & ELECTRICAL ENGINEERS Hazard Identification, Risk Assessment & Safe Working Procedure for Installing Containment, Cable, Glanding, Terminating, Testing, Instrumentation & Tubing Project Title: Site Address: Client: PO Number:

More information

C&P ENGINEERING SERVICES LTD. Hazard Identification, Risk Assessment & Safe Working Procedure for Hazardous Area Inspections

C&P ENGINEERING SERVICES LTD. Hazard Identification, Risk Assessment & Safe Working Procedure for Hazardous Area Inspections Hazard Identification, Risk Assessment & Safe Working Procedure for Hazardous Area Inspections Project Title: Site Address: Client: PO Number: Work Location: Cardiff Road, Barry, South Glamorgan, CF63

More information

Contractor handbook. Purpose

Contractor handbook. Purpose Page no: 1 / 6 Contractor handbook Purpose Mitie aims to ensure that the highest levels of performance are achieved by all persons working for us or on our behalf. We require the same level of performance

More information

EHS Workplace Inspection Checklist (Ref. SOP QMS-080; EHS-010)

EHS Workplace Inspection Checklist (Ref. SOP QMS-080; EHS-010) (Ref. SOP QMS-080; EHS-010) Form-445 Inspected by: Date of inspection Date of Report Report # Pages Area Manager: Area Inspected: General This EHS Workplace Inspection was conducted by: Scope of the Inspection:

More information

7 Hazard assessment 8 Worker participation 9 Hazard elimination and control

7 Hazard assessment 8 Worker participation 9 Hazard elimination and control This document is a guideline only. Employers have a responsibility of assessing all applicable occupational health and safety legislation, for the tasks they are performing. Businesses in this industry

More information

Instructions for the Use of the Excel Spreadsheet. There are Three tabs at the bottom of this worksheet. Instructions tab is the one you are reading

Instructions for the Use of the Excel Spreadsheet. There are Three tabs at the bottom of this worksheet. Instructions tab is the one you are reading Instructions for the Use of the Excel Spreadsheet There are Three tabs at the bottom of this worksheet Instructions tab is the one you are reading H&S Plan Tab The Plan Tab is the front cover pages of

More information

PLANNED LIGHTING MAINTENANCE LTD METHOD STATEMENT & RISK ASSESSMENT REPLACEMENT OF LAMPS OR REPAIRS TO HIGH LEVEL LIGHT UNITS

PLANNED LIGHTING MAINTENANCE LTD METHOD STATEMENT & RISK ASSESSMENT REPLACEMENT OF LAMPS OR REPAIRS TO HIGH LEVEL LIGHT UNITS PLANNED LIGHTING MAINTENANCE LTD METHOD STATEMENT & RISK ASSESSMENT REPLACEMENT OF LAMPS OR REPAIRS TO HIGH LEVEL LIGHT UNITS Project: (insert Client) Replacement/ Repair of high level light units/ high

More information

Contractor / Exhibitor Handbook

Contractor / Exhibitor Handbook Contractor / Exhibitor Handbook Health and Safety This booklet outlines the basic rules that must be followed by contractors and other visitors working on Live Promotions Events sites. The contractors

More information

B S Glass Ltd Safety procedures- outsourced Workplaces

B S Glass Ltd Safety procedures- outsourced Workplaces B S Glass Ltd Jan 17 B S Glass Ltd Safety procedures- outsourced Workplaces Index - - - - - - - - Page No On Site safety - - - - - - - - - - - - - - - - - - - Content 3. 1.00 Health and Safety Mission

More information

Temporary load-bearing support for structural alterations or repairs

Temporary load-bearing support for structural alterations or repairs CRITICAL NOTE This document only becomes a Safe Work Method Statement where the High Risk Construction Work section of this document is completed Company: ABN: Contact Person: Ph: Project/Site: Principal

More information

Staff Contractors. Public. Staff Contractors

Staff Contractors. Public. Staff Contractors 1. Vehicle movements In conjunction with the vehicle driver, venue management and the client, our staff should ensure the safe parking of vehicles for loading and unloading purposes. Depending upon circumstances

More information

WORK METHOD STATEMENT STRUCTURAL STEEL

WORK METHOD STATEMENT STRUCTURAL STEEL ORGANISATION DETAILS Organisation Name: Gedoun Constructions Pty Ltd Contact Name: Joe Gedoun ACN/ABN: 52 284 873 581 Contact Position: Director Address: PO Box 1138, Townsville QLD 4810 Contact Phone

More information

Recognition, Evaluation, and Control of Hazards

Recognition, Evaluation, and Control of Hazards Recognition, Evaluation, and Control of Hazards Latest revised date: October 26, 2011 Page 1 of 8 1.0 Introduction Memorial University has established a system for the recognition, evaluation, and control

More information

Pre-control risk estimate. Likelihood Risk

Pre-control risk estimate. Likelihood Risk Activity Consequence s mitigation measures Site Access & Egress Slips, trips & falls al injury by falling. Sprains & broken bones. Site operatives 3 4 12 Ensure access to site is kept clear of plant &

More information

CONSTRUCTION HEALTH AND SAFETY MANAGEMENT SYSTEM BASELINE HIRA

CONSTRUCTION HEALTH AND SAFETY MANAGEMENT SYSTEM BASELINE HIRA RECOMMENDED ADDITIONAL CONTROLS TASK / ACTIVITY/ EQUIPMENT/ FACILITY HAZARDS UNWANTED EVENT MINIMUM CONTROLS REQUIRED RISK NO. LIKELI-HOOD CONSE-QUENCE RISK VALUE Project Risk Assessment Page 1 of 16 All

More information

FIRE HYDRANT TESTING METHOD STATEMENT.

FIRE HYDRANT TESTING METHOD STATEMENT. SUBJECT: TASK: FIRE HYDRANT INSPECTION & TESTING. 1. Location....1 2. The Scope of Works.... 1 3. Description of Task.... 1 4. Access & Egress to & from Work Area.... 2 5. Safety Hazard Identification....

More information

CONSTRUCTSAFE TIER 1 HEALTH AND SAFETY COMPETENCY TEST FRAMEWORK

CONSTRUCTSAFE TIER 1 HEALTH AND SAFETY COMPETENCY TEST FRAMEWORK CONSTRUCTSAFE TIER 1 HEALTH AND SAFETY COMPETENCY TEST FRAMEWORK ConstructSafe Project Team March 2018 Version 1.3 1 Table of Contents 1. Introduction... 3 2. Candidate minimum required knowledge... 3

More information

Industry Code: Alberta Small Employer OHS Legislated Requirements

Industry Code: Alberta Small Employer OHS Legislated Requirements This document is a guideline only. Employers have a responsibility of assessing all applicable occupational health and safety legislation, for the tasks they are performing. Services in this industry can

More information

Method Statement Author

Method Statement Author Plan Bee Limited 3.3 Etna Industrial estate Clamp Road Motherwell Scotland ML2 7XQ Tel: 01698580572 Method Statement Method Statement Details Method Statement Number 7 Method Statement Date Monday 3rd

More information

SAFE WORK METHOD STATEMENT WORKING IN CONFINED SPACE HSE NET NAT SWMS APAND00030

SAFE WORK METHOD STATEMENT WORKING IN CONFINED SPACE HSE NET NAT SWMS APAND00030 SAFE WORK METHOD STATEMENT WORKING IN CONFINED SPACE HSE NET NAT SWMS APAND00030 HIGH RISK APT AM Holdings Pty. Ltd. [ABN] 95124754383 Principal Contractor (PC) APA Group Level 19, HSBC Building 580 George

More information

How severely could the risk hurt someone?

How severely could the risk hurt someone? Safe Work Method Statement No: WMS-08 Task: Install Drainage This WMS is submitted to: Project name and site address: Contact: Preparation of WMS by: Robert Raams Company: Enwon (Australia) Pty Ltd Authorised

More information

PLANNED LIGHTING MAINTENANCE LTD METHOD STATEMENT & RISK ASSESSMENT REPLACEMENT OF LAMPS OR REPAIRS TO LOW LEVEL LIGHT UNITS

PLANNED LIGHTING MAINTENANCE LTD METHOD STATEMENT & RISK ASSESSMENT REPLACEMENT OF LAMPS OR REPAIRS TO LOW LEVEL LIGHT UNITS PLANNED LIGHTING MAINTENANCE LTD METHOD STATEMENT & RISK ASSESSMENT REPLACEMENT OF LAMPS OR REPAIRS TO LOW LEVEL LIGHT UNITS Project: Insert Client Repair/ Replacement of low level light units/ low level

More information

SWMS documented by: Feb Bo Ceprnja Date Feb Feb Feb 2018

SWMS documented by: Feb Bo Ceprnja Date Feb Feb Feb 2018 Contractor Company Details: BUILDSAFE SAFE WORK METHOD STATEMENT 0002 (Void Platform Stairs) Part 1 (To be used in conjunction with SWMS 0001 General Site Activities & SWMS 0002 Void Platform) Additional

More information

SAFE WORK METHOD STATEMENT SWMS No Version

SAFE WORK METHOD STATEMENT SWMS No Version SAFE WORK METHOD STATEMENT SWMS No Version Company Name: Hunter Readymixed Concrete Pty Ltd 00 004 Location: Thornton Cessnock Tea Gardens Gateshead ABN: 6 076 08 695 SWMS Developed By: Duane Harrison

More information

Risk assessment. Assessment details. Task. Introduction. Please complete the form as fully and accurately as you can. Assessors job title

Risk assessment. Assessment details. Task. Introduction. Please complete the form as fully and accurately as you can. Assessors job title Risk assessment Introduction Please complete the form as fully and accurately as you can. Assessment details Name of organisation Assessor's name Assessors job title Any Company John Smith Manager Date

More information

S31 Opening Statement Working at Height

S31 Opening Statement Working at Height S31 Opening Statement Working at Height Falls from height are by far the most common cause of workplace deaths and one of the main causes of major injury in the workplace. Latest figures reveal that 46

More information

WHS OHS HAZARD REGISTER (SITE AND OFFICE OPERATIONS)

WHS OHS HAZARD REGISTER (SITE AND OFFICE OPERATIONS) WHS 017 - WHS 017 Hazard Register - Version 5.0 April 20 Doc No: WHS 017 Effective Date: 04/04/20 1 WORKING WITH EARTHMOVING PLANT/ TRUCKS/SITE VEHICLES COLLISIONS OTHER PLANT EQUIPMENT SITE VEHICLES PERSONNELL

More information

Risk Assessment. Appendix A contains

Risk Assessment. Appendix A contains Risk Assessment Department The Cockpit Risk Assessment number AM/09/01 Date. 1 st July 01 Review due date 0 th July 01 Activity Maintenance and support service working Location The Cockpit Name of Assessor/s

More information

Prevention of Falls and Working at Heights

Prevention of Falls and Working at Heights Workplace Safety Schools Cleaning Prevention of Falls and Working at Heights It is the policy of the Company to avoid working at heights above 2 metres wherever practical. When avoidance is not an option,

More information

Work Activity (e.g. Road Work): Work Location:.

Work Activity (e.g. Road Work): Work Location:. Working with Cranes Work Activity (e.g. Road Work): Work Location:. GENERAL INFORMATION Hinchinbrook Shire Council Lannercost Street Ingham Qld, 4850 ABN 46 291 971 168 Ph: 47764610 All personnel conducting

More information

Hampstead Hill School Health and Safety Policy: Confined Spaces

Hampstead Hill School Health and Safety Policy: Confined Spaces All Hampstead Hill School Policies are always to be read and considered in conjunction with Equal Opportunities, Race Equality and Inclusion Policies. This Policy of Hampstead Hill School applies to all

More information

Contractor Hazard Identification and Control Guide

Contractor Hazard Identification and Control Guide Exposure to Asbestos Containing Materials (ACM) Accidental disturbance or removal of ACM. Asbestos Containing Materials are to be removed outside school hours. No DET employees, students or visitors are

More information

2.0 Management Systems and Documentation

2.0 Management Systems and Documentation SHE Rules BOW142.3 1.0 Introduction This document details the safety, health and environment rules that apply to anyone accessing Arqiva sites and describes the standards of performance expected. This

More information

Specialists Window Cleaning Induction

Specialists Window Cleaning Induction Specialists Window Cleaning Induction Mobile Tower Scaffolds Mobile tower scaffolds are used on flat firm, stable ground to access higher levels. They have toe boards, mid rails & guard rails to prevent

More information

Health & Safety Contractor rules

Health & Safety Contractor rules Health & Safety Contractor rules Contents 1. Introduction... 1 2. The legal bit explaining our terminology... 1 2.1 Legal requirements... 1 3. Our health and safety requirements... 1 3.1 Access to BT premises...

More information

EXHIBITION Guide. Roles and Responsibilities OS11. A handbook for exhibitors and contractors

EXHIBITION Guide. Roles and Responsibilities OS11. A handbook for exhibitors and contractors Appendix 1 Health & Safety Declaration, Roles and Responsibilities Each exhibitor and Informa appointed contractor must complete the Health and Safety Declaration form provided below to confirm they have

More information

PLANT/EQUIPMENT/ASSET HAZARD REPORT

PLANT/EQUIPMENT/ASSET HAZARD REPORT Asset Description: EL-08001-011 : Harrison 550 CNC Lathe Large Sale Type For what use is this asset being sold? Re-Use þ Spare Parts Scrap Note 1: Assets are sold only for the use indicated. Any other

More information

Safe Work Method Statement (SWMS)

Safe Work Method Statement (SWMS) Safe Work Method Statement (SWMS) Organisation Details : Organisation Name Northern Plumbing Contact ABN 17 15 41 4 Position Director Address 47 Thomas Street Edgeworth 85 Phone Number 0411 10 4 Project

More information

JOB SAFETY ANALYSIS. How to use the Risk Assessment Charts. Likelihood A (Almost Certain) B (Likely) C (Possible)

JOB SAFETY ANALYSIS. How to use the Risk Assessment Charts. Likelihood A (Almost Certain) B (Likely) C (Possible) Page 1 of 6 How to use the Assessment Charts 1. Determine the Likelihood on the Qualitative Assessment Process Chart (pick a letter applicable to the task). 2. Determine the Consequence on the Qualitative

More information

Safety Risk Assessment Working at Height: Mobile Tower Scaffold

Safety Risk Assessment Working at Height: Mobile Tower Scaffold Persons at (Groups) Assessor Appointment Tel. No. Description of Task or Activity A One Direct employees Mark Bloxidge H&S Manager 0208 821 5197 Working at height from Mobile Tower B Contractors/Sub contractors

More information

Safety Risk Assessment Roofing Works / Surveying / Inspections

Safety Risk Assessment Roofing Works / Surveying / Inspections One Direct aintenance td Persons at (Groups) Assessor Appointment Tel. No. Description of Task or Activity A One Direct employees ark Bloxidge H&S anager 0208 821 5197 One Direct Operatives accessing roof

More information

University College Dublin Machinery/Equipment Risk Assessment Template

University College Dublin Machinery/Equipment Risk Assessment Template 1. General Information Name of Person(s) carrying out assessment and their position Principal Investigator / Supervisor / Head of School or Unit (Person responsible for ensuring safety) Date of assessment

More information

Rockhampton Office Brisbane Office Tarong Site. Barron Gorge Hydro PS Kareeya Hydro PS Mica Creek PS

Rockhampton Office Brisbane Office Tarong Site. Barron Gorge Hydro PS Kareeya Hydro PS Mica Creek PS Business Procedure Hot Work Document Number OHS-PROC-128 This document applies to the following sites: All Sites Rockhampton Office Brisbane Office Tarong Site Barron Gorge Hydro PS Kareeya Hydro PS Mica

More information

Safe Work Practices / Procedures / Instruction CONFINED SPACE

Safe Work Practices / Procedures / Instruction CONFINED SPACE CONFINED SPACE Entry into and work in a confined space poses health and safety problems which may include: Presence or possible build up of a hazardous atmosphere Unexpected movement of equipment or materials

More information

WORK METHOD STATEMENT CARPET LAYING

WORK METHOD STATEMENT CARPET LAYING ORGANISATION DETAILS Organisation Name: Gedoun Constructions Pty Ltd Contact Name: Joe Gedoun ACN/ABN: 52 284 873 581 Contact Position: Director Address: PO Box 1138, Townsville QLD 4810 Contact Phone

More information

Risk Assessment Form (Qualitative)

Risk Assessment Form (Qualitative) Assessment Form (Qualitative) Project / ocation:..d.a.s WATERS Contract No: RA & Issue No: 008 Prepared by:.r.smit Date: 10/10/16 Signature: ACTIVITY DESCRIPTION: Person (s) at risk: General Ground works

More information

PLANT HAZARD AND EQUIPMENT RISK ASSESSMENT

PLANT HAZARD AND EQUIPMENT RISK ASSESSMENT PLAT HAZARD AD EQUIPMET RISK ASSESSMET Plant Identification : HAULOTTE STAR 10 Potential Hazard Entanglement Can anything become entangled in moving parts? Crushing/Striking Can anyone be crushed or struck

More information

SAFETY MANAGEMENT SYSTEM

SAFETY MANAGEMENT SYSTEM Equipment Location: Hazard Hired From All Master Hire Stores Entanglement Can anyone s hair, clothing, gloves, necktie, jewellery, cleaning brushes, rags or other materials become entangled with moving

More information

Working at Height. Policy and Procedures. Author: Beth Webster Assistant Safety Advisor. On behalf of School Safety Committee.

Working at Height. Policy and Procedures. Author: Beth Webster Assistant Safety Advisor. On behalf of School Safety Committee. Working at Height Policy and Procedures Author: Beth Webster Assistant Safety Advisor Authorised by: Issued by: John Stephenson Safety Office On behalf of School Safety Committee Review Date: NO LATER

More information

Section J. How to develop safety elements for project safety management system. How to develop safety elements for project SMS

Section J. How to develop safety elements for project safety management system. How to develop safety elements for project SMS Section J How to develop safety elements for project safety management system 1. Once the project management has developed or adopted a safety policy, it needs to develop safety elements to meet the objectives

More information

Summary of Standards for Key Items of PPE

Summary of Standards for Key Items of PPE Summary of Standards for Key Items of PPE This is a guide to the selection of suitable PPE. In some cases certain PPE is mandatory and forms part of a safe system of work. These are the minimum requirements

More information

Confined Spaces. This procedure applies to all workers of the Diocese of Maitland Newcastle (DoMN).

Confined Spaces. This procedure applies to all workers of the Diocese of Maitland Newcastle (DoMN). Purpose To provide guidance in controlling the risks associated with confined spaces including identifying confined spaces, working in a confined space and issuing confined space entry permits. Scope This

More information

Potential risk of injury to staff

Potential risk of injury to staff Register Fire, Earthquake - other Emergencies Manual Handling and Repetitive Work Repetitive, Forceful Work Poor Housekeeping Not Wearing PPE (Personal Protective Equipment) Potential risk of injury to

More information

Title: Plant and Equipment Risk Management Form Issue Date: Review Date: Page Number: 1 of 11

Title: Plant and Equipment Risk Management Form Issue Date: Review Date: Page Number: 1 of 11 Issue Date: Review Date: Page Number: 1 of 11 1. Hazard Management Details General Plant/Equipment Item: WOOD LATHE Make/Model No.: Serial No.: School: Work Location: Name of Person(s) Conducting Activity:

More information

FLYING OBJECTS MANUAL HANDLING EXCESSIVE NOISE

FLYING OBJECTS MANUAL HANDLING EXCESSIVE NOISE JOB NO: PROJECT: DATE: SWMS NO: SWMS 002 PREPARED BY: Ian Hartley REVISED BY: Nick Bragg & Cameron McNeil ACTIVITY: STUMP REMOVAL SUPERVISED BY: REVISION DATE: April 2016 MINIMUM PERSONAL PROTECTIVE EQUIPMENT

More information

How severely could the risk hurt someone? Low/Insignificant First aid

How severely could the risk hurt someone? Low/Insignificant First aid Safe Work Method Statement No: WMS-02 Task: Concreting, Formwork and Steel Fixing This WMS is submitted to: Project name and site address: Contact: Preparation of WMS by: Robert Raams Company: Enwon (Australia)

More information

Working at Height - MEWPS & Ladders. Your company details Address Tel: Fax: Mobile:

Working at Height - MEWPS & Ladders. Your company details Address Tel: Fax: Mobile: Project/Contract Contractor Site Address Project Start Date Expected Duration Projected Completion Date Your company details Address Tel: Fax: Mobile: Document Author Authorised by Name Title Signature

More information

RISK RATING SAFE WORK METHOD STATEMENT 1 HIGH 2 MEDIUM 3LOW. I approve the use of this Safe Work Method Statement: NAME: POSITION: Department Manager

RISK RATING SAFE WORK METHOD STATEMENT 1 HIGH 2 MEDIUM 3LOW. I approve the use of this Safe Work Method Statement: NAME: POSITION: Department Manager RISK RATING 1 HIGH 2 MEDIUM 3LOW SAFE WORK METHOD STATEMENT Title: : Traineeship Ref No: 1 I approve the use of this Safe Work Method Statement: NAME: POSITION: Department Manager SIGNATURE: DATE: / /

More information

Safe Work Method Statement

Safe Work Method Statement TE CONTROLLED COPY OF TIS DOCUMENT IS ON TE COMPUTER NETWORK PRINTED COPIES ARE ONLY CURRENT FOR TE DATE AT TE BOTTOM OF TE PAGE. Title Working at eight SWMS No. 16 Authorized and email Signed by the (Managing

More information

Risk Assessment & Safe Working Practice

Risk Assessment & Safe Working Practice RA Ref Number: 32 Revision: 4 Project/Job Number Reference Insert Job Number Approval Date: 30/03/2018 RA Description: confined space Next Review Date: 01/04/2019 Notes: Please refer to Safe Working Practices

More information

PLANT HAZARD AND EQUIPMENT RISK ASSESSMENT

PLANT HAZARD AND EQUIPMENT RISK ASSESSMENT PLAT HAZARD AD EQUIPMET RISK ASSESSMET Plant Identification : HAULOTTE OPTIMUM 8.1 Potential Hazard Entanglement Can anything become entangled in moving parts? Crushing/Striking Can anyone be crushed or

More information

SCOPE OF WORK, SAFETY METHOD STATEMENT & RISK ASSESSMENT

SCOPE OF WORK, SAFETY METHOD STATEMENT & RISK ASSESSMENT SCOPE OF WORK, SAFETY METHOD STATEMENT & RISK ASSESSMENT Prepared for:- Date:- Work Scheduled:- SCOPE OF WORK Carry out installation of flow meters / pressure sensors. Installation of flow meter procedure

More information

Suitability of Work Equipment

Suitability of Work Equipment These regulations came into effect on the 5th December 1998 and replace PUWER 1992. They cover almost all equipment used at work, including tool box tools such as hammers, knives etc. They also cover machinery

More information

Generic Health and Safety Risk Assessment

Generic Health and Safety Risk Assessment Generic Health and Safety Risk Assessment Acheta Consulting Ltd Assessment completed by: Dr John Simmons (Managing Director), April 2017 Review date: May 2018 Introduction During the course of your work

More information

C-Consequence, P Probability, R-Risk Rating Value Page 2 of 2

C-Consequence, P Probability, R-Risk Rating Value Page 2 of 2 General Procedure SE-GEN-04 azard nalysis & ssessment, Identification of Environmental spect and Impact ssessment P-474 / R / 01 Rev : 02 Date: 0.01.2012 CTIVITY RISK SSESSMENT WORKSEET Work ctivity: ocation:

More information

Who Wants To Be a MEWP Millionaire?

Who Wants To Be a MEWP Millionaire? Who Wants To Be a MEWP Millionaire? The employer has a responsibility to provide: A Modifications to equipment B Exemption in respect to training if required C Information, instruction, training and supervision

More information

SAFETY MANAGEMENT SYSTEM

SAFETY MANAGEMENT SYSTEM Equipment Location: Hazard Hired From All Master Hire Stores Entanglement Can anyone s hair, clothing, gloves, necktie, jewellery, cleaning brushes, rags or other materials become entangled with moving

More information

Job Safety and Environmental Analysis (JSEA)/Safe Work Method Statement (SWMS)

Job Safety and Environmental Analysis (JSEA)/Safe Work Method Statement (SWMS) Job Safety and Environmental Analysis (JSEA)/Safe Work Method Statement (SWMS) Part 1: Project and Task Identification Process: Initiators of JSEAs are responsible for consulting the Project Supervisor,

More information

SH&E Work Method Statement Concrete Cutting & Drilling Fast Cut Qld Pty Ltd, 91 Basalt, GEEBUNG PH M ABN

SH&E Work Method Statement Concrete Cutting & Drilling Fast Cut Qld Pty Ltd, 91 Basalt, GEEBUNG PH M ABN SH&E Work Method Statement Concrete Cutting & Drilling Fast Cut Qld Pty Ltd, 91 Basalt, GEEBUNG PH 07 3265 6537 M 0411 756 719 ABN 45 081 359 613 OHS-FRM-100 Rev 11 (07/18) Page 1 SH&EWMS No.: F-C-QLD-30

More information

SAFETY MANAGEMENT SYSTEM

SAFETY MANAGEMENT SYSTEM Equipment Location: Hazard Entanglement Hired From All Master Hire Stores Can anyone s hair, clothing, gloves, necktie, jewellery, cleaning brushes, rags or other materials become entangled with moving

More information

Safe Work Method Statement LRB TREE SERVICES 6 Behland St, Kearneys Spring QLD, 4350 ABN

Safe Work Method Statement LRB TREE SERVICES 6 Behland St, Kearneys Spring QLD, 4350 ABN JOB NO: PROJECT: DATE: 1/1/2018 SWMS NO: SWMS 001.1 PREPARED BY: LUKE BLINCO REVISED BY: ACTIVITY: TREE REMOVAL & PRUNING SIGNED BY: REVISION DATE: MINIMUM PERSONAL PROTECTIVE EQUIPMENT (PPE) REQUIREMENTS

More information

WINDMILL (pre-start) HAZARD INSPECTION CHECKLIST

WINDMILL (pre-start) HAZARD INSPECTION CHECKLIST Windmill Hazard Inspection Checklist WINDMILL (pre-start) HAZARD INSPECTION CHECKLIST Authorised by: LOCATION OF INSPECTION...... Inspected By (1)........... (2)..... PRINT PRINT Signature (1):. (2)....

More information

Buchanan. Approved: John Downes

Buchanan. Approved: John Downes Severity Site triio Activity Vacuum Excavator Persons conducting assessment SHEQ DEPT Assessment No triio 21 Review Date 11/01/2021 Revision No. 10 Name: Paul Disley/Ian Buchanan Signature Date: 11/01/2019

More information

SAFETY MANAGEMENT SYSTEM

SAFETY MANAGEMENT SYSTEM Equipment Location: Hazard Hired From All Master Hire Stores Entanglement Can anyone s hair, clothing, gloves, necktie, jewellery, cleaning brushes, rags or other materials become entangled with moving

More information

Working safely in an engineering environment

Working safely in an engineering environment Unit 001 Working safely in an engineering environment Level: 2 Credit value: 5 NDAQ number: 500/9514/6 Unit aim This unit covers the skills and knowledge needed to prove the competences required to work

More information

TRADE AREA: ELECTRICAL INDUSTRY

TRADE AREA: ELECTRICAL INDUSTRY TRADE AREA: ELECTRICAL INDUSTRY Some possible workplace hazards and possible ways for Host employers and Apprentices/Trainees in controlling these hazards. What are possible hazards? What could be possible

More information

SWMS No 012 Samark North Qld Pty Ltd ABN : Electrical Contractors License C37121 Page 2 of 6

SWMS No 012 Samark North Qld Pty Ltd ABN : Electrical Contractors License C37121 Page 2 of 6 Samark North Qld Pty Ltd SWMS SWMS No 0 Samark North Qld Pty Ltd ABN : 99 08 98 87 Electrical Contractors License C37 Page of 6 Safe Work Method Statement Title: SWMS:0 INSTALLING LIGHT POLES Work Method

More information

Kennards Hire Building I, 22 Powers Road Seven Hills. NSW 2147

Kennards Hire Building I, 22 Powers Road Seven Hills. NSW 2147 Safety Audit / Risk Assessment Of Hino 2 Tonne Dutro Tipper Kennards Hire Building I, 22 Powers Road Seven Hills. NSW 2147 Mark Zimmer Unit 3, 16 Herbert St, Equipment manager Artarmon. NSW 2064 Ph: (02)

More information

Key Technology, Inc. Confined Space Entry Program. July, 2017

Key Technology, Inc. Confined Space Entry Program. July, 2017 Key Technology, Inc. Confined Space Entry Program July, 2017 Page 1 of 11 Key Technology, Inc. CONFINED SPACE ENTRY PROGRAM OVERVIEW Purpose: The purpose of this program is to ensure the protection of

More information

Safety at Work. Rules for Staying Alive

Safety at Work. Rules for Staying Alive Safety at Work Rules for Staying Alive Safety at Work Rules for Staying Alive Introduction The purpose of Dana Gas Rules For Staying Alive is to address the key causes of deaths in our industry. These

More information

Contractors' Code of Safe Practice

Contractors' Code of Safe Practice Contractors' Code of Safe Practice Introduction As the controller of premises, The University of Hong Kong has a duty to ensure, so far as is reasonably practicable, the health and safety of all its employees,

More information

HAZARD RECOGNITION EVALUATION and CONTROL

HAZARD RECOGNITION EVALUATION and CONTROL What is a hazard? HAZARD RECOGNITION EVALUATION and CONTROL Hazard - a dangerous object, event, behaviour or condition (in the workplace) which has the potential to cause injury, illness or property damage.

More information

CONTRACTOR WHS HAZARD STANDARD CONFINED SPACE EXTERNAL USE ONLY

CONTRACTOR WHS HAZARD STANDARD CONFINED SPACE EXTERNAL USE ONLY CONTRACTOR WHS HAZARD STANDARD CONFINED SPACE EXTERNAL USE ONLY Principles in the Optus Contractor WHS management process CONTRACTOR MANAGEMENT STAGES PRINCIPLES THIS STANDARD REQUISITION Requisition WHS

More information

SAFE WORK METHOD STATEMENT (SWMS) All Trades Abseiling ABN: Ph:

SAFE WORK METHOD STATEMENT (SWMS) All Trades Abseiling ABN: Ph: PCBU: ALL TRADES ABSEILING ABN: 42 137 576 035 PO Box 774 NEWPORT NSW 2106 LIC: 123517C P: 0412 227 578 Principal Contractor (PC): Date SWMS provided to PC: Work activity: Workplace location: High risk

More information

Potential hazards People at risk and how? Actions already in place Further action required Action by

Potential hazards People at risk and how? Actions already in place Further action required Action by Risk Assessment Flat Roof Repair Prepared by Oracle Managed Services For: BAM FM On: 24/02/2017 Review date: N/A Potential hazards People at risk and how? Actions already in place Further action required

More information

WORK METHOD STATEMENT ELECTRICAL

WORK METHOD STATEMENT ELECTRICAL ORGANISATION DETAILS Organisation Name: Gedoun Constructions Pty Ltd Contact Name: Joe Gedoun ACN/ABN: 52 284 873 581 Contact Position: Director Address: PO Box 1138, Townsville QLD 4810 Contact Phone

More information

Bogo Operations Pollution Incident Response Management Plan

Bogo Operations Pollution Incident Response Management Plan Bogo Operations Pollution Incident Response Management Plan Rhyolite Hard Rock Aggregate Quarry 134 Paynes Road BOOKHAM NSW 2582 PO Box 426 COWRA NSW 2794 p: 02 6227 7260 p: 02 6345 4253 e: info@bogoquarry.com.au

More information

CONTRACTOR SAFETY INDUCTION HANDBOOK

CONTRACTOR SAFETY INDUCTION HANDBOOK CONTRACTOR SAFETY INDUCTION HANDBOOK As a valued contractor for Total Group we would ask that you read and carefully consider the details included in this document. Total Group carry out work for a number

More information

SAFE WORK METHOD STATEMENT 0005 (Hang-On Platform) Part 1 (To be used in conjunction with SWMS 0001 General Site Activities)

SAFE WORK METHOD STATEMENT 0005 (Hang-On Platform) Part 1 (To be used in conjunction with SWMS 0001 General Site Activities) Contractor Company Details: BUILDSAFE SAFE WORK METHOD STATEMENT 0005 (Hang-On Platform) Part 1 (To be used in conjunction with SWMS 0001 General Site Activities) Additional Information (if required):

More information

1 AIM 2 4 REASONS FOR INCLUSION 3 6 PLANT AND EQUIPMENT REQUIREMENTS 4 7 SYSTEM AND PROCEDURAL REQUIREMENTS 4 8 PEOPLE REQUIREMENTS 6

1 AIM 2 4 REASONS FOR INCLUSION 3 6 PLANT AND EQUIPMENT REQUIREMENTS 4 7 SYSTEM AND PROCEDURAL REQUIREMENTS 4 8 PEOPLE REQUIREMENTS 6 CONTENTS PAGE 1 AIM 2 2 APPLICATION 2 3 DEFINITIONS 2 4 REASONS FOR INCLUSION 3 5 REQUIREMENTS 3 6 PLANT AND EQUIPMENT REQUIREMENTS 4 7 SYSTEM AND PROCEDURAL REQUIREMENTS 4 8 PEOPLE REQUIREMENTS 6 APPENDIX

More information

Job Safety & Environment Analysis

Job Safety & Environment Analysis Job Safety & Environment Analysis To be used when the risk is greater than LOW and / or Defined Hazardous Work and there is no standard procedure for the task. All sections of this JSEA form must be completed.

More information

PLANT HAZARD AND EQUIPMENT RISK ASSESSMENT

PLANT HAZARD AND EQUIPMENT RISK ASSESSMENT Plant Identification : HAULOTTE LIGHT BOOMS 3522A (HTA 13P); 4527A (HTA 16P); 5533A (HTA 19P) and 3632T (HTT 13) Potential Hazard Entanglement Can anything become entangled in moving parts? Crushing/Striking

More information

SASOL LIFE SAVING RULES (LSRs)

SASOL LIFE SAVING RULES (LSRs) SASOL LIFE SAVING RULES (LSRs) Zero harm by following Life Saving Rules Adhere to fall protection requirements at all times when WORKING AT HEIGHTS Obey all traffic rules while driving and walking for

More information

POLICY ON THE PROVISION & USE OF PERSONAL PROTECTIVE EQUIPMENT

POLICY ON THE PROVISION & USE OF PERSONAL PROTECTIVE EQUIPMENT POLICY ON THE PROVISION & USE OF PERSONAL PROTECTIVE EQUIPMENT June 2013 Lead Manager John Green, Health & Safety Service Manager Responsible Director Director of Human Resources Approved By Health and

More information

Powerplay Paintball Brighouse Risk Assessment

Powerplay Paintball Brighouse Risk Assessment Chemical Gas bottles Vehicles Physical Electricity Environment Machinery Powerplay Paintball Brighouse Risk Assessment Location Powerplay Paintball Wakefield and Brighouse Venues Carried out by: Steven

More information

SAFETY MANAGEMENT SYSTEM

SAFETY MANAGEMENT SYSTEM Equipment Location: Hazard Hired From All Master Hire Stores Entanglement Can anyone s hair, clothing, gloves, necktie, jewellery, cleaning brushes, rags or other materials become entangled with moving

More information

Risk Controls Proposed: (in hierarchy order from the most preferred control)

Risk Controls Proposed: (in hierarchy order from the most preferred control) are to be assessed and controlled by eliminating or minimising any risks to health and safety. Eliminate - Where the risk to health and safety is removed from the workplace. Minimise - Where the risk cannot

More information

CITB Construction site safety update

CITB Construction site safety update D: High risk activities Underground and overhead services This text replaces the text from the current GE700 2015, Section D, Chapter D08, Underground and overhead services, pages 133 to 136. 8.6 Overhead

More information

Safe work method statements

Safe work method statements Information about Safe work method statements How to prepare and use a safe work method statement (SWMS) for high risk construction work (HRCW) and who needs to prepare one. October 2018 Key concepts Hazard

More information