Viaduct and bridge construction methods adopted at MTR SIL(E) Contract 903. MTR SIL(E) 903 Viaduct Construction Team
|
|
- Silvia Black
- 5 years ago
- Views:
Transcription
1 Viaduct and bridge construction methods adopted at MTR SIL(E) Contract 903 MTR SIL(E) 903 Viaduct Construction Team MTR Corporation Limited 2013/8/29 Page 1
2 Content 1. About SIL(E) Contract Viaduct Construction 2.1 Value Engineering for Viaduct 2.2 Viaduct construction by Pre-cast segmental method 2.3 Stakeholder Management 3. Aberdeen Channel Bridge (ACB) Construction 3.1 Value Engineering for Aberdeen Channel Bridge 3.2 Bridge construction by in-situ balance cantilever 3.3 Stakeholder Management 4. Q&A MTR Corporation Limited 2013/8/29 Page 2
3 1. About SIL(E) Contract 903 MTR Corporation Limited 2013/8/29 Page 3
4 1. About SIL(E) Contract 903 ADM Works Contract 901 Works Contract 902 SOH LET WCH OCP Works Contract 903 Works Contract 904 Works Contract 907 / 908 MTR Corporation Limited 2013/8/29 Page 4
5 1. About SIL(E) Contract 903 Viaduct Wong Chuk Hang Station Viaduct Nullah Works Ocean Park Station Aberdeen Channel Bridge MTR Corporation Limited 2013/8/29 Page 5
6 1. About SIL(E) Contract 903 Ocean Park Station Viaduct B Wong Chuk Hang Station Ocean Park Station Viaduct C MTR Corporation Limited 2013/8/29 Page 6
7 1. About SIL(E) Contract 903 Wong Chuk Hang Station Viaduct D Aberdeen Channel Bridge MTR Corporation Limited 2013/8/29 Page 7
8 1. About SIL(E) Contract 903 Beauty of Target Cost Contract 1. 2 Contractors can be selected at an early stage to help the Employer to identify value engineering solutions 2. The selected Contractor will have more time to mobilise sufficient resources and plan the works well before the actual commencement of the Contract. 3. The Employer and his construction team will be more proactive to help the Contractor to use the cheapest method to complete the project. 4. This contract arrangement is beneficial to foster a genuine partnering relationship between the Employer and the Contractor. 5. This form of contract facilities early identification of risks and allows these risks to be better managed during the construction stage, thus increasing the certainty of project delivery. MTR Corporation Limited 2013/8/29 Page 8
9 1. About SIL(E) Contract main benefits to use elevated railway for this section of SIL(E) are: 1. Less spoil will be generated from this Contract; 2. The passenger will be able to enjoy the beautiful scenery from Ocean Park to Ap Lei Chau; 3. The connection details between the Ocean Park Station and the main railway line will be much simpler and user friendly; 4. The elevated railway requires less land during construction compared to a tunnel option, which addresses the lack of available land in Southern District; MTR Corporation Limited 2013/8/29 Page 9
10 2. Viaduct Construction MTR Corporation Limited 2013/8/29 Page 10
11 2. Key information of SIL(E) Viaduct Key information of SIL(E) Viaduct Length of the viaduct is approx. 2 km; Viaduct height is approx. 10 to 25m subject to topographical condition; There are 47 nos. of viaduct piers with span length from 21m to 50m; and 628 nos. of precast segments, tonnes each. Viaduct D Viaduct C Viaduct B Wong Chuk Hang Station Segmental construction Ocean Park Station casting in-situ construction MTR Corporation Limited 2013/8/29 Page 11
12 Noise Barrier - Integrated Approach Countershading Overhead Lines Coloured Translucent Panels Where Required Track-Side Op s Opaque Panels at Absorptive Parapet Barrier 2m Viaduct Pier Proposed Noise Barrier - Perspective Proposed Noise Barrier - Section MTR Corporation Limited 2013/8/29 Page 12
13 Typical Viaduct Section 4000 Profiled Capital m Rounded Piers Planting at Bottom Of Pier Consistent Approach for Portal Piers Front Elevation Side Elevation Front Elevation at Portal MTR Corporation Limited 2013/8/29 Page 13
14 2. Viaduct Construction 2.1 Value Engineering for Viaduct MTR Corporation Limited 2013/8/29 Page 14
15 Viaduct B Viaduct B MTR Corporation Limited 2013/8/29 Page 15
16 2.1.1 Value Engineering for Viaduct B Viaduct construction in the vicinity of the road with heavy traffic MTR Corporation Limited 2013/8/29 Page 16
17 2.1.1 Value Engineering for Viaduct B Change in piling design Use a large diameter pile to replace a group of smaller diameter piles Conforming design Alternative design Wong Chuk Hang Road Wong Chuk Hang Road Wong Chuk Hang Road Wong Chuk Hang Road 3 nos of 1.5m dia piles Single 2.8m Dia. Bored Pile MTR Corporation Limited 2013/8/29 Page 17
18 2.1.1 Value Engineering for Viaduct B Change in Pilecap Design Use a smaller rectangular pilecap to replace a larger irregular pilecap B3 Wong Chuk Hang Road Legend Piles Pile cap Traffic flow Carriageway Conforming design B3 Wong Chuk Hang Road Extent of works area required was greatly reduced Less impact on road traffic Alternative design MTR Corporation Limited 2013/8/29 Page 18
19 2.1.1 Value Engineering for Viaduct B Change in Pilecap Design Use a smaller rectangular pilecap to replace a larger irregular pilecap Minimize the conflict with the existing utilities Existing 132 kv HEC cables Original Pile Cap Conforming design Existing 132 kv HEC cables Revised Pile Cap Alternative design MTR Corporation Limited 2013/8/29 Page 19
20 2.1.1 Value Engineering for Viaduct B Comparison between conforming design and alternative design Number of bored piles Size of bored piles Pile caps Conforming design m 1) Volume of pile cap - Approx. 480 m 3 2) More construction and ELS required Alternative design m to 2.8 m 1) Volume of pile cap - Approx. 320 m 3 2) Less construction and ELS required Advantages of the alternative design over the conforming design 1) Extent of works area required was greatly reduced 2) Less impact on the road traffic 3) Minimize the conflict with the existing utilities 4) Cheaper and faster to construct the piling and pilecap works MTR Corporation Limited 2013/8/29 Page 20
21 Viaduct C Nullah Viaduct C MTR Corporation Limited 2013/8/29 Page 21
22 2.1.2 Value Engineering for Viaduct C Viaduct construction over nullah MTR Corporation Limited 2013/8/29 Page 22
23 2.1.2 Value Engineering for Viaduct C 1. Reduce the number of portal from 11 to 8 2. Change in piling design Use a large diameter pile to replace a group of smaller diameter piles Conforming design Alternative design MTR Corporation Limited 2013/8/29 Page 23
24 2.1.2 Value Engineering for Viaduct C Comparison between conforming design and alternative design Number of bored piles Size of bored piles Number of portals Span length Conforming design m (C1, C2 and C13 Piers) 1.8 m or 2.2 m (Portals) 11 Approx. 35 m Alternative design m (C1, C2 and C11 Piers) 2.0 m (Portals) 8 Approx. 50 m Advantages of the alternative design over the conforming design 1) Reduce construction time for bored piles and portals 2) Minimize construction activities inside the nullah - critical to programme 3) Less visual impact with wider spacing of portal structures 4) Minimize the conflicts with the existing utilities MTR Corporation Limited 2013/8/29 Page 24
25 Viaduct D Viaduct D MTR Corporation Limited 2013/8/29 Page 25
26 2.1.3 Value Engineering for Viaduct D (from D13 to D18) Viaduct construction in hilly area MTR Corporation Limited 2013/8/29 Page 26
27 2.1.3 Value Engineering for Viaduct D (from D13 to D18) Change in Foundation Design Replace bored pile by spread footing Conforming Design Alternatives Design 3 nos of 1.5m dia piles Inferred Rockhead Spread Footing found on Rock Rock Dowels MTR Corporation Limited 2013/8/29 Page 27
28 2.1.3 Value Engineering for Viaduct D (from D13 to D18) Change in viaduct design - Replace precast segmental deck by in-situ deck Hilly area Segmental construction Replace precast segmental deck by in-situ deck Advantage Precast segmental deck - Better quality control in casting yard - Environmental friendly - steel mould replace timber formwork In-situ Deck - More timber formworks Limitation - Difficult access at hilly area for erection of precast segment - Construction is relatively simple and faster with the use of a tower crane MTR Corporation Limited 2013/8/29 Page 28
29 2.1.3 Value Engineering for Viaduct D (from D13 to D18) Comparison between conforming design and alternative design Type of pile per column Viaduct type Conforming design 3 nos of 1.5m dia piles per column Precast segmental deck Alternative design Spread footing found on rock with rock dowels per column In-situ deck Advantages of the alternative design over the conforming design 1) No heavy piling plant is required in the hilly area 2) Less time to complete the foundation works as footing can be constructed simultaneously 3) The size of the haul road and the ELS works required can be reduced 4) The delivery of materials are relatively simple with the use of a tower crane or a mobile crane MTR Corporation Limited 2013/8/29 Page 29
30 2. Viaduct Construction 2.2 Viaduct Construction by Pre-cast Segmental Method MTR Corporation Limited 2013/8/29 Page 30
31 2.2 Pre-cast segmental method Two erection methods are being adopted: Erection by Crane Erection by Beam-and- Winch MTR Corporation Limited 2013/8/29 Page 31
32 2.2.1 Erection by Crane B4 B5 B4 Step 1 Step 2 MTR Corporation Limited 2013/8/29 Page 32
33 2.2.1 Erection by Crane B4 B5 B4 Closure beams B5 Step 3 Step 4 MTR Corporation Limited 2013/8/29 Page 33
34 2.2.2 Erection by Beam-and-Winch Beam-and-Winch technology was introduced in the SIL(E) project to enhance the merits of precast segment erection method B4 B5 B4 B5 Step 1 Step 2 MTR Corporation Limited 2013/8/29 Page 34
35 2.2.2 Erection by Beam-and-Winch B4 B5 B4 Closure beams B5 Step 3 Step 4 MTR Corporation Limited 2013/8/29 Page 35
36 2.2.2 Erection by Beam-and-Winch MTR Corporation Limited 2013/8/29 Page 36
37 2.2.3 Beam-and-Winch and Launching Gantry Scale Beam-and-Winch Approx. 8m in length and 10m wide Launching Gantry Approx. 100m in length and 10m wide More than 10 times larger than Beamand-Winch equipment in size Time required for machine assembly Approx. a week Approx. one month Beam-and-Winch Launching gantry MTR Corporation Limited 2013/8/29 Page 37
38 2.2.3 Beam-and-Winch and Launching Gantry Advantage and Limitation of Beam-and-Winch Advantage of Beam-and-Winch over Launching Gantry Less road space required, less disturbance to the traffic Less construction time required More flexibility and efficiency in works arrangement Limitation of Beam-and-Winch Allowance in Permanent Works Design Mobile Crane required for mobilization from pier to pier. MTR Corporation Limited 2013/8/29 Page 38
39 2.2.4 Safety Measures Independent checking system for segment erection Checklist of segment erection Checklist of B&W operation MTR Corporation Limited 2013/8/29 Page 39
40 2.2.5 Measures to minimize impacts on Road Traffic Key measures to minimize impacts on road traffic: 1. Adopt Pre-cast segmental method 2. Use Beam-and-Winch 3. Night-time erection to minimize traffic impact on the public 1) Pre-cast segmental method 2) Beam-and-Winch 3) Night time erection MTR Corporation Limited 2013/8/29 Page 40
41 2. Viaduct Construction 2.3 Stakeholder Management MTR Corporation Limited 2013/8/29 Page 41
42 2.3.1 Major Stakeholders around the Viaduct B & C TWGHs Wong Chuk Hang Complex Aberdeen Tunnel Bus Depot Ocean Park Station Viaduct San Wai Village Viaduct Police College Ocean Park MTR Corporation Limited 2013/8/29 Page 42
43 2.3.2 Major Stakeholders around the Viaduct D Holy Spirit Seminary Jockey Club Rehabilitatio n Centre Tai Wong Ye Temple Viaduct Wong Chuk Hang Little Sisters of the Poor St. Mary s Home for the Aged NLSR Cooked Food Market Station MTR Corporation Limited 2013/8/29 Page 43
44 2.3.3 Stakeholder Engagement Community Liaison Group Meeting Visit to the TWGHs Wong Chuk Hang Complex Painting activity in Little Sisters of the Poor JCRC visit and regular meeting Allowance for Tai Wong Ye Temple s Yu Lam Festival event Football Match with Police College MTR Corporation Limited 2013/8/29 Page 44
45 MTR Corporation Limited 2013/8/29 Page 45
46 3. Aberdeen Channel Bridge Construction MTR Corporation Limited 2013/8/29 Page 46
47 3. Aberdeen Channel Bridge N Aberdeen Channel Existing Ap Lei Chau Bridge SIL(E) Aberdeen Channel Bridge 58m 115m 73m A A Max 7m Total Length = 250m MTR Corporation Limited 2013/8/29 Page 47 Section A
48 3. Aberdeen Channel Bridge Aberdeen Channel Bridge (as of June 2013) Photomontage of Aberdeen Channel Bridge MTR Corporation Limited 2013/8/29 Page 48
49 3. Aberdeen Channel Bridge Construction 3.1 Value Engineering for Aberdeen Channel Bridge MTR Corporation Limited 2013/8/29 Page 49
50 E4 3.1 Value Engineering for Aberdeen Channel Bridge E3 E2 Conforming Arrangement E1 16 pairs segments (~3.5m long) 16 pairs segments (~3.5m long) Hill 12m insitu end span on falsework Temporary pier bracing E3 E2 Temporary pier bracing Alternative Arrangement Longer cantilever length for segment construction 10 pairs segments (~4.3m long) 14 pairs segments (~4.3m long) Hill Falsework eliminated One unbalanced cantilever segment E3 E2 Temporary pier bracing MTR Corporation Limited 2013/8/29 Page 50
51 3.1 Value Engineering for Aberdeen Channel Bridge Comparison between conforming design and alternative design Number of segments Period for segment construction Max. cantilever length Max. segment weight Number of strands per cantilever tendons Conforming design 32 pairs ~ 50 weeks 60 m 130 tons 12 Alternative design 24 pairs ~ 40 weeks 65 m 160 tons 19 Remark: 1) Segment weight in alternative design is heavier 2) One set of form traveller instead of two sets of form traveller is required to meet the programme 3) Temporary bracing at E3 pier eliminated 4) Scaffolding for end span near E1 eliminated 5) Advantage to construction programme 6) The alternative design can provide early access for P-way construction MTR Corporation Limited 2013/8/29 Page 51
52 3. Aberdeen Channel Bridge Construction 3.2 Bridge construction by in-situ balance cantilever MTR Corporation Limited 2013/8/29 Page 52
53 3.2 ACB Comparison of different construction methods Cast in-situ segments by balanced cantilever (Selected option) Pre-cast segmental method Cast in-situ span by span Description Cast in-situ segments by balanced cantilever method with form traveller Segment pre-cast and erection Cast bridge span by span with the support by falsework Advantage and disadvantage Advantage 1) Only one set of form traveller is required 2) Without affecting the marine traffic underneath the bridge 3) No heavy lifting involved 4) Cheapest and fastest way to build this bridge Disadvantage 1)Barge for segment erection is too large to gain access to the bridge 2) Segment (max 160T) too heavy for lifting 3) Disruption to Navigation Channel during segment erection Disadvantage 1) Falsework cannot be erected across the Aberdeen Channel MTR Corporation Limited 2013/8/29 Page 53
54 3.2.1 ACB Construction Sequence Stage 1 Pier Table construction at E2 Stage 2 Pier Table construction at E3 - Erect form traveller at E2 MTR Corporation Limited 2013/8/29 Page 54
55 3.2.1 ACB Construction Sequence Stage 3 Complete cantilever span at E2 by insitu balanced cantilever method Stage 4 Launch back form traveller & remove tower crane from E2 MTR Corporation Limited 2013/8/29 Page 55
56 3.2.1 ACB Construction Sequence Stage 5 Tower Crane & form traveller removed from E2 Stage 6 Erect tower crane & form traveller at E3 MTR Corporation Limited 2013/8/29 Page 56
57 3.2.1 ACB Construction Sequence Stage 7 Complete E3 cantilever span by insitu balanced cantilever method Stage 8 Cast Mid-span stitch MTR Corporation Limited 2013/8/29 Page 57
58 3.2.1 ACB Construction Sequence Stage 9 Cast unbalanced segment at E4 Stage 10 Cast End-span stitch at E4 MTR Corporation Limited 2013/8/29 Page 58
59 3.2.2 Modular Form Traveller (MFT) Major component: Modular Form Traveller Main Frame x 2 Front Transverse Truss x 1 Rear Transverse Truss x 1 Rear Anchorage x 2 Rail Beam x 2 Formwork system Inner Form Outer Form Bottom Form MTR Corporation Limited 2013/8/29 Page 59
60 3.2.2 Modular Form Traveller (MFT) General characteristics of Modular Form Traveller: Bridge alignment Gradient of +/-5% Cross-fall of +/-5% Minimum curve in plan of 500m radius Segment geometry Maximum length of 5m Maximum weight of 180 tons (with 2 main frames) Single or multiple cells Vertical or inclined webs System capacity: 180 tons Load test could be carried out prior to assembly MTR Corporation Limited 2013/8/29 Page 60
61 3.2.2 Modular Form Traveller (MFT) Main frames Front truss Wall Form Rear truss Bottom Form MTR Corporation Limited 2013/8/29 Page 61
62 3.2.2 Modular Form Traveller (MFT) MTR Corporation Limited 2013/8/29 Page 62
63 3. Aberdeen Channel Bridge Construction 3.3 Stakeholder Management MTR Corporation Limited 2013/8/29 Page 63
64 3.3.1 Stakeholders around Aberdeen Channel Bridge Aberdeen Channel Bridge Dragon Boat Association Kaito Aberdeen Channel Jumbo Restaurant Marine Police Port Sham Wan Aberdeen Boat Club Tai Shue Wan MTR Corporation Limited 2013/8/29 Page 64
65 3.3.2 Minimize impact on Marine Traffic Key measures to minimize marine traffic impact: 1. Use cast-insitu balanced cantilever method 2. Maintain navigation channel 3. Advance notice to all marine users about the construction works 4. Use of guard boat 1. Cast-insitu balanced cantilever method 2. Navigation Channel 14 m min. high 40m min. wide MTR Corporation Limited 2013/8/29 Page 65
66 3.3.2 Minimize impact on Marine Traffic 3. Early notice to all marine users about the construction works 4. Use of guard boat MTR Corporation Limited 2013/8/29 Page 66
67 3.3.3 Minimize impact on Marine Environment Key measures to minimize marine environment impact: 1. Use of silt curtain 2. Use of temporary steel formwork for pile cap construction Use of silt curtain Use of temporary steel formwork for pile cap construction MTR Corporation Limited 2013/8/29 Page 67
68 3.3.4 Entertain the need of Dragon Boat Association Relocate the existing dragon boats to the new permanent storage area for the Dragon Boat Association before the commencement of the construction on site Aberdeen Channel Bridge New permanent storage area for dragon boat Existing storage area for dragon boat before bridge construction MTR Corporation Limited 2013/8/29 Page 68
69 Q & A MTR Corporation Limited 2013/8/29 Page 73
KCRC Ma On Shan Line. Railway Development in Hong Kong. Tai Wai Station and Maintenance Centre
Railway Development in Hong Kong KCRC Ma On Shan Line Tai Wai Station and Maintenance Centre Overview of the Maintenance Centre of the Ma On Shan Line at Tai Wai, as seen in early 2002. The Centre is a
More informationEXCITING WORLD OF STEEL STRUCTURES
ENABLING STRUCTURES INNOVATIVE SOLUTIONS FOR COMPLEX CONSTRUCTION PROBLEMS BY ER. A.B. KARNIK CONSULTING ENGINEER EXCITING WORLD OF STEEL STRUCTURES 1 PART 1- INTRODUCTION PART 2 - CASE STUDIES FOR ENABLING
More informationApplication of Value Engineering The Crosstown Project
Application of Value Engineering The Crosstown Project Presented To: CSVA Conference, Toronto November 15, 2011 Presented by: Rick Thompson, Chief Project Manager SRT/Yards Agenda 1. Eglinton Scarborough
More informationPHASE 1 WIND STUDIES REPORT
PHASE 1 WIND STUDIES REPORT ENVIRONMENTAL STUDIES AND PRELIMINARY DESIGN FOR A SUICIDE DETERRENT SYSTEM Contract 2006-B-17 24 MAY 2007 Golden Gate Bridge Highway and Transportation District Introduction
More informationWelcome. Thank you for your interest in the Lewis & Clark Viaduct Concept Study
Welcome Thank you for your interest in the Lewis & Clark Viaduct Concept Study Please use the arrows in the upper left hand corner to navigate through the presentation. Use the envelope icon to ask a question
More informationCharmborough Bells Risk Assessment and Method Statement
Charmborough Bells Risk Assessment & Method Statement Charmborough Bells Risk Assessment and Method Statement Introduction This risk assessment and method statement has been prepared to outline the procedures
More informationNon-Motorized Overpass at SR 5/US1
Non-Motorized Overpass at SR 5/US1 And SR 97/SW th Street (Bird Road) Executive Summary March 9, 17 Prepared By: MARLIN Engineering Inc 17 NW th Avenue, Ste. 1 Plantation, FL 33313 P: 35.77.7575 www.marlinengineering.com
More informationsection 4 Existing Conditions, Issues, and Options
section 4 Existing Conditions, Issues, and Options 4.0 Existing Conditions, Issues, and Options This section analyzes each segment of the corridor on a street to street basis. Each segment is discussed
More informationREVISED SILT CURTAIN DEPLOYMENT PLAN
Contract No.: HY/2009/11 Central Wanchai Bypass, North Point Reclamation REVISED SILT CURTAIN DEPLOYMENT PLAN Name Prepared by: China Harbour Engineering Co., Ltd. China Road and Bridge Corporation Joint
More informationforce tension suspension bridge anchorage cables compression caissons Towers deck
Before bridges in New York City existed, people relied on the waterways to get around and transport goods. The Brooklyn Bridge was the first steel-wire suspension bridge to be built in the world. A suspension
More informationC-M Precast Traffic Islands Index
C-M Precast Traffic Islands Index Selecting Left or Right Hand Islands Product Range Splitter Islands Single Splitter Islands 1072 Chicane Splitter Islands 1075 Pedestrian Refuge 1082 Tweed Pedestrian
More informationSPECIAL LAUNCHING METHODS
CHAPTER 18 SPECIAL LAUNCHING METHODS Special launching methods are needed when a restricted site prevents normal roller layout and launching by the standard skeleton launchingnose method. Space on either
More informationN.Y. / REGION INFRASTRUCTURE Going Up! A Bridge Makes Way for Bigger Ships
N.Y. / REGION INFRASTRUCTURE Going Up! A Bridge Makes Way for Bigger Ships By KATE ASCHERMARCH 21, 2014 Advertisement When it opened in 1931, the Bayonne Bridge with its parabolic arch connecting Staten
More informationSupplementary Info. for FF3170 RHD HKSouth Addon with E400 traffic. Prepared by KT 4404
Supplementary Info. for FF3170 RHD HKSouth Addon with E400 traffic Prepared by KT 4404 Note KT 4404 and Winsome developed the addon. We are NOT the developer of the map. All information is for reference
More informationGANTRY CRANES CAPACITIES: SPANS: TRACKS: OPTIONS: Up to 5 tons Up to 30' Steel Fixed or Adjustable
GANTRY CRANES CAPACITIES: SPANS: TRACKS: OPTIONS: Up to 5 tons Up to 30' Steel Fixed or Adjustable Material Handling Solutions For Your Unique Applications Since 1977, Gorbel has been an innovator and
More informationRight Sizing VE Studies CSVA Conference. Markham, ON October 27, BRIAN RUCK, P. Eng., C.V.S. AECOM Canada
Right Sizing VE Studies 2008 CSVA Conference Markham, ON October 27, 2008 BRIAN RUCK, P. Eng., C.V.S. AECOM Canada Presentation Outline Traditional VE Approach Key VE Principles Sample Projects Conclusion
More informationPile Gripper Systems
Pile Gripper Systems Accurate positioning and restraint of offshore construction piles + + Accurate handling of piles up to 8.0m in diameter + + Pile positioning and adjustment within large envelopes +
More informationDevelopmental Products
Types of Ropes Courses Developmental Products Contents Types of Developmental Ropes Courses Page RCD Developmental Elements 2-3 RCD Linear Ropes Course 4-6 RCD All in One Ropes Course 7-9 RC D Free Standing
More informationRevisions to the Regulations for Agility Trials
Revisions to the Regulations for Agility Trials Effective January 2, 2018 Equipment changes may be done prior to January 2, 2018, but must be completed by January 2, 2018 This insert is issued as a supplement
More informationCAISSON SHAFT SYSTEM
CAISSON SHAFT SYSTEM Installation Guide INSTALLATION GUIDE FOR DN2000 TO DN3660 UNITS PLATE JOINTING SYSTEM This guide is to be used for the Installation of CPM Group Ltd caisson shaft units which use
More informationRoad Safety Audit training course. Motorways - safety issues of the motorway design
Road Safety Audit training course Motorways - safety issues of the motorway design Jesper Mertner, Road safety auditor, COWI A/S 1 ROAD SAFETY AUDITING COURSE Content 1. Safety 2. Cross sections 3. Horizontal
More informationFALL PROTECTION LADDERS ACCESSWAYS
FALL PROTECTION LADDERS ACCESSWAYS PORTABLE LADDERS Max. Height 20 Step Ladder For small hand tool use only Must have non-slip feet Top step is not to be stood on Wood ladders not to be painted See COE
More informationAppendix J: Q1-Highway 35 Route Construction Plan
PSC REF#:150055 Wisconsin CPCN Appendix J Appendix J: Q1-Highway 35 Route Construction Plan Public Service Commission of Wisconsin RECEIVED: 06/29/11, 8:51:24 AM Hampton Rochester La Crosse 345 kv Transmission
More informationPerched Box Caisson Overview. January 2014
Perched Box Caisson Overview January 2014 Why perched box caissons? Perched box caissons are used to construct the portion of the river piers that will support the steel arch spans Construction can occur
More informationAgenda Item # Page # RECOMMENDATION
TO: FROM: SUBJECT: CHAIR AND MEMBERS CIVIC WORKS COMMITTEE MEETING ON FEBRUARY 2, 2016 JOHN BRAAM, P. ENG. MANAGING DIRECTOR, ENVIRONMENTAL & ENGINEERING SERVICES AND CITY ENGINEER FIELD MARSHAL WOLSELEY
More informationBaseball Stadium Renovations at US Cellular Field
Baseball Stadium Renovations at US Cellular Field Authors: Terry R. McDonnell, P.E., S.E., Senior Project Engineer, Thornton Tomasetti, Inc., 14 E. Jackson Boulevard, Chicago, IL 60604, tmcdonnell@thorntontomasetti.com
More information2017 The first stage of the DFS was completed and Interim Public Consultation is launched Study Background
7 June 2017 Study Background 2012-2014 Public Consultation for PFS Public generally agreed that there was a need to enhance the connectivity in KE. However, there were diversified views on the proposed
More informationFall Protection. 29 CFR Appendix C 29 CFR 1926 Subpart M
Fall Protection 29 CFR 1910.66 Appendix C 29 CFR 1926 Subpart M Duty to Have Fall Protection Provide fall protection systems which meet the criteria of 1926 and 1910 Make fall protection an integral part
More informationAmerican Railway Engineering and Maintenance of Way Association Letter Ballot. Draft
American Railway Engineering and Maintenance of Way Association Letter Ballot 1. Committee and Subcommittee: Committee 5 Track Subcommittee 9 Road Crossings 2. Letter Ballot Number: 05-17-16 3. Assignment:
More informationBarricades and Falling Object Protection Plans
Title: Barricades and Falling Object Protection Plans Freeport Site Function: Environmental, Health & Standard No.: BCF020.042 Rev 7 Page: 1 of 7 REVISION HISTORY Date Revision Number Details of Change
More informationENTRY FORM. DVASE 2018 Excellence in Structural Engineering Awards Program
ENTRY FORM DVASE 2018 Excellence in Structural Engineering Awards Program PROJECT CATEGORY (check one): Buildings under $5M Buildings Over $100M Buildings $5M - $15M Other Structures Under $1M Buildings
More informationAppointed person Note: It is recommended that you read the Supporting Information page before you read this factsheet.
Appointed person Note: It is recommended that you read the Supporting Information page before you read this factsheet. Planning and regulatory requirements (Regulatory requirements) The role or duties
More informationROAD OCCUPANCY PERMIT APPLICATION # Damascus Township, 60 Conklin Hill Road, Damascus, PA Tel Fax
Instructions: For a driveway access permit, fill in sections 1, 2, 3 and 4, and the appropriate drawings and sign. For a Utility access, fill in sections 1, 2, 3 and 5, and figures 1 and 3. Prepare a detailed
More informationSingle slide rail system Linear shoring
E+S Trench shoring systems / Sliding rail systems Single slide rail system Linear shoring Single-rail linear shoring with U-type and rectangular roller unit Module length Length slide rail Panel height
More informationSection 16B. Fall Protection. Falls are the second leading cause of death in the workplace. Factors contributing to falling incidents:
Section 16B. Fall Protection Falls are the second leading cause of death in the workplace. Factors contributing to falling incidents: 1. Personal factors Lack of concentration. Use of medication. Poor
More informationsarens
sarens group www.sarens.com Sarens Climbing Tower SCT The SARENS CLIMBING TOWER is designed for lifting heavy loads in the construction, petrochemical and offshore industries. The system is suited to using
More informationCURBSIDE ACTIVITY DESIGN
5 CURBSIDE ACTIVITY DESIGN This chapter provides design guidance for separated bike lanes adjacent to curbside activities including parking, loading and bus stops. Typical configurations are presented
More informationLOCAL NOTICE TO MARINERS
USCG Notice to Mariners 3/26/15 (View full Notice here) LNM 12/15 Coast Guard District 1 : U.S. Department of Homeland Security United States Coast Guard LOCAL NOTICE TO MARINERS COASTAL WATERS FROM EASTPORT,
More informationISO INTERNATIONAL STANDARD. Cranes and lifting appliances Selection of wire ropes Part 1: General
INTERNATIONAL STANDARD ISO 4308-1 Third edition 2003-05-01 Cranes and lifting appliances Selection of wire ropes Part 1: General Grues et appareils de levage Choix des câbles Partie 1: Généralités Reference
More informationRoad Safety Facilities Implemented in Japan
Road Safety Facilities Implemented in Japan 1 Road Safety Facilities 1.Guard Fence 2.Road Lighting 3.Other Road Safety Facilities 2 Road Safety Facilities 1.Guard Fence 2.Road Lighting 3.Other Road Safety
More information2.2. Anchorage Point A secure point of attachment for Lifelines, lanyards or deceleration devices.
Title: Elevated Walking/Working Surfaces (Fall Protection) Site Function: Safety Procedure No.: MC032.122 Page: 1 of 16 McIntosh Site Reviewed: 02/2013 Effective: 03/2013 Supersedes: 08/2012 Preparer:
More informationDREW UNIVERSITY FALL PROTECTION PROCEDURE (DRAFT 12/11)
PURPOSE The objective of this policy & guideline is to eliminate the potential for injuries and fatalities to employees and contractors resulting from falls from elevated work areas at Drew University
More informationCompetent Person - Fall Protection Presented by Turner Safety- your instructor is Steve Turner
Competent Person - Fall Protection Presented by Turner Safety- your instructor is Steve Turner 1 Falls in Construction Falls are the leading cause of deaths in the construction industry. Most fatalities
More informationTECHNICAL MEMORANDUM 002 EMORANNO. 001
TECHNICAL MEMORANDUM 002 EMORANNO. 001 To: Jack Synder, P.E. EES Consulting From: Mort McMillen, P.E. Paul Larson, SE Date: October 13, 2010 Project: Cc: Taylor Bowen Subject: Technical Memorandum (TM)
More information2015 HDR, Inc., all rights reserved.
2015 HDR, Inc., all rights reserved. 2018 Michigan Bridge Conference INNOVATIVE ACCESS TECHNIQUES FOR BRIDGE INSPECTION HDR Engineering, Inc. - Tom Howell, PE & Jason Fogg, PE March 20, 2018 INTRODUCTION
More informationATLANTIC COAST OF LONG ISLAND, JONES INLET TO EAST ROCKAWAY INLET, LONG BEACH ISLAND, NY. Contract #2 Construction Scope. April 18th-19th 2018
ATLANTIC COAST OF LONG ISLAND, JONES INLET TO EAST ROCKAWAY INLET, LONG BEACH ISLAND, NY Contract #2 Construction Scope April 18th-19th 2018 New York District PLAN COMPONENTS Length of Beachfill 35,000
More informationFall Protection / Open Holes & Guardrail
Fall Protection / Open Holes & Guardrail 1. Leading Edges Policy Statement It is GW Communications policy that any worker exposed to a fall 6 or greater, shall be protected from coming into contact with
More informationContract HY/2011/09 Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road-Section between HKSAR Boundary and Scenic Hill. Dolphin Watching Plan
Dragages -China Harbour-VSL JV Contract HY/2011/09 Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road-Section between HKSAR Boundary and Scenic Hill Dolphin Watching Plan April 2013 (Version 4.0) Certified
More informationSouth King County High-Capacity Transit Corridor Study
HIGH-CAPACITY TRANSIT CORRIDOR STUDY South King County Corridor South King County High-Capacity Transit Corridor Study Corridor Report August 2014 South King County High Capacity Transit Corridor Report
More informationGEARY CORRIDOR BUS RAPID TRANSIT Environmental Analysis. Special Intersections: Preliminary Concepts
GEARY CORRIDOR BUS RAPID TRANSIT Environmental Analysis Special Intersections: Preliminary Concepts April 2, 2009 FILLMORE: Existing Conditions 3 lanes in underpass, 2 lanes in service road (each direction)
More informationTCML operate and control the 146 Km Railway line from Lake Magadi to Konza.
REQUEST OF A QUOTATION TO CARRY OUT STRUCTURAL ASSESSMENT OF BRIDGES, VIADUCT, BOX CULVERTS AND DRAINAGE STRUCTURES ON THE LAKE MAGADI AND KONZA RAILWAY LINE. Tata chemicals Magadi Limited, transport a
More informationUNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO OVER THE STRAIGHT RIVER DISTRICT 6 - RICE COUNTY
UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 66513 14 th STREET (MSAS NO. 103) OVER THE STRAIGHT RIVER DISTRICT 6 - RICE COUNTY PREPARED FOR THE MINNESOTA DEPARTMENT OF TRANSPORTATION BY COLLINS ENGINEERS,
More informationReplacement of N. Carlin Springs Road Bridge over George Mason Dr.
Replacement of N. Carlin Springs Road Bridge over George Mason Dr. Approximate schedule with phases and proposed Maintenance of Travel (MOT) plans February 2017 Project Elements Removal of existing bridge
More informationDr. Naveed Anwar Executive Director, AIT Consulting Affiliated Faculty, Structural Engineering Director, ACECOMS
Dr. Naveed Anwar Executive Director, AIT Consulting Affiliated Faculty, Structural Engineering Director, ACECOMS Overview Highway Functions and Classifications Highway Design Components Design Control
More informationBARRIER OFFSET 0" A 6" 6" A 12" 12" A 26" A 26" 3A OR 4A L OR S * ** L OR S L OR S
ACCEPTABLE (TCB) TYPES AND ANCHORING DETAILS BASED ON UNDERLYING SURFACE TYPE AND BARRIER OFFSET FROM DROP-OFF BARRIER OFFSET UNDERLYING SURFACE 0" A 6" 6" A 12" 12" A 26" A 26" TCB TYPE DETAIL TCB TYPE
More informationSILT SCREEN DEPLOYMENT PLAN
Contract No.: HY/2009/11 Central Wanchai Bypass, North Point Reclamation SILT SCREEN DEPLOYMENT PLAN Name Prepared by: China Harbour Engineering Co., Ltd. China Road and Bridge Corporation Joint Venture
More informationUNDERWATER BRIDGE INSPECTION REPORT DISTRICT 1 PINE COUNTY
UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 58551 CSAH NO. 41 OVER THE KETTLE RIVER DISTRICT 1 PINE COUNTY JULY 28, 2012 PREPARED FOR THE MINNESOTA DEPARTMENT OF TRANSPORTATION BY COLLINS ENGINEERS,
More informationRoute 245 over Broad Run. The recently replaced bridge links The Plains and other communities in northern Fauquier to Interstate 66.
28 VIRGINIA DEPARTMENT OF TRANSPORTATION \\ CULPEPER DISTRICT Route 245 over Broad Run. The recently replaced bridge links The Plains and other communities in northern Fauquier to Interstate 66. PROJECT
More informationDesign Criteria. Design Criteria
F Design Criteria Design Criteria Ministry of Transportation Ministère des Transports DESIGN CRITERIA Page: 1 of 13 WORK PROJECT NO. N/A GO Bloomington Station TYPE OF PROJECT LOCATION Bloomington Road
More informationFall Protection- Part 1
Optional Information Name of School: Date of Inspection: Vocational Program/Course/Room: Signature of Inspector: Fall Protection- Part 1 Self Inspection Checklist Instructions: This checklist covers some
More informationUS Route 24 Eastbound (Quincy Memorial Bridge) Over the Mississippi River
Purpose and Need March 2015 US Route 24 Eastbound (Quincy Memorial Bridge) Over the Mississippi River Adams County - Quincy, IL Marion County, MO Region 4 District 6 Table of Contents I. Purpose of the
More informationADA on Construction. Guidance for Section C Plan Preparers
ADA on Construction Guidance for Section C Plan Preparers Some impacts cannot be avoided and those impacts apply to residents, businesses, motorists, and pedestrians alike. However, good planning can minimize
More informationCITB Construction site safety update
D: High risk activities Underground and overhead services This text replaces the text from the current GE700 2015, Section D, Chapter D08, Underground and overhead services, pages 133 to 136. 8.6 Overhead
More informationAnchor Posts. *Patent Nos: Europe USA 12/372,965 2 ANCHOR SYSTEMS ANCHOR POSTS
Anchor Post System Anchor Posts Anchor Posts are an innovative patented* system designed by our founder, Ewan Smith, for lightweight foundations using hand held equipment. Ingeniously simple, they fulfil
More informationFederal Railroad Administration. HUDSON TUNNEL PROJECT: WEEHAWKEN COMMUNITY MEETING January 18, 2018
HUDSON TUNNEL PROJECT: WEEHAWKEN COMMUNITY MEETING January 18, 2018 Agenda Near Term Activity Hudson Tunnel Project Revisions to the Project to Address Community Concerns Description of Construction Activities
More informationAccommodating Pedestrians in the Work Zone
Accommodating Pedestrians in the Work Zone Guidance for Section C Plan Preparers Some impacts cannot be avoided and those impacts apply to residents, businesses, motorists, and pedestrians alike. However,
More informationTB 42. Low maintenance effort saves on time and costs. High variability for vehicle types, construction and expan- sion options
TB 42 TB 42 commercial vehicle wash for automatic exterior cleaning. The 3-brush gantry allows a washing height of 4.25 m and offers total flexibility for different vehicle sizes and types. 1 Low maintenance
More informationThe most versatile Fall Protection EVER
The most versatile Fall Protection System EVER In Brief Innovative Design 2 lifelines on separate spools Self Retracting, Self Locking Quick and Easy Installation Span up to 24m No Tensioning or Adjusting
More informationLOCAL NOTICE TO MARINERS
USCG Notice to Mariners 3/7/18 (View full Notice here) LNM 10/18 Coast Guard District 1: U.S. Department of Homeland Security United States Coast Guard LOCAL NOTICE TO MARINERS COASTAL WATERS FROM EASTPORT,
More informationSAFETY 101: FALL PROTECTION: REDUCING FALLS DURING RESIDENTIAL CONSTRUCTION: RE-ROOFING FACT SHEET
SAFETY 101: FALL PROTECTION: REDUCING FALLS DURING RESIDENTIAL CONSTRUCTION: RE-ROOFING FACT SHEET Re-roofing exposes workers to the hazards of demolition work at heights. With the proper fall protection,
More informationUser Instructions. Installing Fall Protection Void Formers. Please read carefully before fixing anchorage components into formwork
Installing Fall Protection Void Formers. Please read carefully before fixing anchorage components into formwork May 2016 Installing moulds into the formwork. Scissorsafe Insert Moulds are cast into the
More informationTemporary load-bearing support for structural alterations or repairs
CRITICAL NOTE This document only becomes a Safe Work Method Statement where the High Risk Construction Work section of this document is completed Company: ABN: Contact Person: Ph: Project/Site: Principal
More informationSafety in Precast Erection
Safety in Precast Erection C. Kirubakaran R Star Consultants Pte Ltd, Singapore Abstract: Construction industry is known to be one of the most hazardous among different industries all over the world. The
More informationUNDERWATER BRIDGE INSPECTION REPORT METRO DISTRICT - ANOKA COUNTY
UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 02545 CR NO. 116 OVER THE RUM RIVER METRO DISTRICT - ANOKA COUNTY SEPTEMBER 9, 2012 PREPARED FOR THE MINNESOTA DEPARTMENT OF TRANSPORTATION BY COLLINS
More informationReviewed: New Effective: 5/18/12 Supersedes: New Preparer: Owner: Approver: Team Member, Occupational Safety Industrial Hygiene
Procedure No.: BC032.027 Page: 1 of 15 Preparer: Owner: Approver: Team Member, Occupational Safety Industrial Hygiene Manager, Occupational Safety Industrial Hygiene Vice President, Ecology & Safety (Signature
More informationTOWN of CHEEKTOWAGA Permit Application for Swimming Pools, Hot Tubs, or Personal Spas
Permit Application for Swimming Pools, Hot Tubs, or Personal Spas / 20 - Date of Application Received By Permit No. APPLICANT to COMPLETE the PINK PORTION! ( ) ( ). Applicant s Name Daytime Phone No. Cell
More informationAt Home in the Urban Jungle Three WOLFF Cranes at the OMNITURM in Frankfurt's Banking District
At Home in the Urban Jungle Three WOLFF Cranes at the OMNITURM in Frankfurt's Banking District Frankfurt July 2017. The OMNITURM that is currently rising skywards in Frankfurt s banking district is adding
More informationMiller DuraHoist Safety Systems
Portable Confined Space System designed for manhole and confined space entry/ retrieval and fall arrest applications. Portable Fall Arrest Post provides three independent swivel tie-off points for fall
More informationFY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Projects
Barclay Street Viaduct NS9807 NS9807 This project will provide for the rehabilitation of the Barclay Street Viaduct, from Route 19 to Marshall Street, in order to increase the weight load of the structure.
More informationSwamp Road Residents Study
Swamp Road Residents Study SRRG Meeting with PennDot and Elected Officials Newtown and Wrightstown, PA April 25, 2008 Newtown Township Section of Swamp Road Limited Public Funds No reconstruction of a
More informationMission Bridge Reconstruction
Mission Bridge Reconstruction R. Larry McKee, P.E. Canadian Pacific Railway 2755 Lougheed Hwy Suite 760 Port Coquitlam, BC V3B 5Y9 Canada (604) 944-5116 James Klett Canadian Pacific Railway 401 9 th Avenue,
More informationPlanning of Major Recreational Boating Facilities at Shell Cove Boat Harbour
Planning of Major Recreational Boating Facilities at Shell Cove Boat Harbour B Morgan 1, Deborah Lam 1, Glenn Colquhoun 2 1 Advisian, Sydney, NSW 2 Frasers Property Australia, Shell Cove, NSW Abstract
More informationRoad Markings. Lecture Notes in Transportation Systems Engineering. Prof. Tom V. Mathew
Road Markings Lecture Notes in Transportation Systems Engineering Prof. Tom V. Mathew 1 Overview The essential purpose of road markings is to guide and control traffic on a highway. They supplement the
More informationDesign of Offshore Structures Prof. S. Nallayarasu Department of Ocean Engineering Indian Institute of Technology, Madras
(Refer Slide Time: 00:32) Design of Offshore Structures Prof. S. Nallayarasu Department of Ocean Engineering Indian Institute of Technology, Madras Module - 2 Lecture - 1 Concepts of Fixed Offshore Platform
More informationMenlo Park and San Mateo County:
Menlo Park and San Mateo County: Caltrain Elevated Tracks Grade Separations Mike Forster Palo Alto June 2017 v3.10 mike@mikeforster.net 6/14/2017 1 Menlo Park: 2 Elevated Track Options Elevated with arches
More informationMinimal Structures for Marginal Nova Scotia Developments
Minimal Structures for Marginal Nova Scotia Developments May 12, 2009 Cameron Dunn Martec is a member of the Lloyd s Register Group 1 2 Minimal Structures Project NSDOE working to make the Nova Scotia
More informationPILING RIGS DRILLING RIGS
PILING RIGS DRILLING RIGS PRODUCT range An introduction to Dieseko Group Foundation Equipment Established in1974, Dieseko Group represents several brands in the foundation equipment industry, in four product
More informationWelcome. Thank you for attending tonight s open house. The purpose of this open house is to give you an opportunity to:
Welcome Thank you for attending tonight s open house. The purpose of this open house is to give you an opportunity to: Review the circulation plan concept Give us your input Why a circulation plan? During
More informationMeeting Date 10/18/2005 Type Internal Team Progress Other Date of Issuance 10/25/05. Coordination See attached sign-in sheet
Meeting Date 10/18/2005 Type Internal Team Progress Other Date of Issuance 10/25/05 Coordination Attendees See attached sign-in sheet Location Great Hall, Holland Tunnel Route 139 Contract 2 PANYNJ Coordination
More informationInterstate Route 77 / US Route 62 / State Route 687 (Fulton Road) Transportation Improvement Project. Prepared September 6, 2017
EODOT Project: ODOT Project: STA-IR 77-.50; PID 00290 Interstate Route 77 / US Route 62 / State Route 687 (Fulton Road) Transportation Improvement Project Summary of Public Comments Received and Responses
More informationFINAL REPORT. Yonkers Creek Migration Barrier Removal Project Wonderstump Road Del Norte County. Submitted By:
FINAL REPORT Yonkers Creek Migration Barrier Removal Project Wonderstump Road Del Norte County Submitted By: Del Norte County Community Development Department Yonkers Creek Migration Barrier Removal Project
More informationField Manual. Simple by Design
Simple by Design US Patents No. 6,481,300; No. 6,837,120; others pending Field Manual The HydraSleeve is a simple tool. In keeping with the Simple by Design motto, these are the basic instructions. Please
More informationEvents At Ovolo Southside
Events At Ovolo Southside Features State-of-the-art AV System with 7.1 Surround Sound Stunning 18 meter video projection wall Industry, Artistry, Creativity, Interactivity, Let's GIG it ON!! 360 Turntable
More informationTonight is for you. Learn everything you can. Share all your ideas.
Strathcona Neighbourhood Renewal Draft Concept Design Tonight is for you. Learn everything you can. Share all your ideas. What is Neighbourhood Renewal? Creating a design with you for your neighbourhood.
More informationUNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH NO. 7 OVER THE SNAKE RIVER DISTRICT 1 - PINE COUNTY
UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 58506 CSAH NO. 7 OVER THE SNAKE RIVER DISTRICT 1 - PINE COUNTY PREPARED FOR THE MINNESOTA DEPARTMENT OF TRANSPORTATION BY COLLINS ENGINEERS, INC. JOB NO.
More informationSafe work method statements
Information about Safe work method statements How to prepare and use a safe work method statement (SWMS) for high risk construction work (HRCW) and who needs to prepare one. October 2018 Key concepts Hazard
More informationInstallation and Training Manual
AirForce1 Tower Kit Installation and Training Manual FuturEnergy Limited Ettington Park Business Centre Stratford upon Avon CV37 8BT +44 (0)1789 451070 Table of Contents Safety Notes... 3 Parts Supplied
More informationLondon 2012 Olympics The Green Build. Rachel Krzeminski Aggregate Industries UK Ltd
London 2012 Olympics The Green Build Rachel Krzeminski Aggregate Industries UK Ltd Aggregate Industries UK Ltd Aggregate Industries is an international aggregates, construction and building materials group
More informationDRAFT. October 17, 2014 File No Mr. Brendhan Zubricki Town Administrator Essex Town Hall 30 Martin Street Essex, MA.
GZA GeoEnvironmental, Inc. Engineers and Scientists October 17, 2014 File No. 18.0171857.00 Mr. Brendhan Zubricki Town Administrator Essex Town Hall 30 Martin Street Essex, MA. 01929 DRAFT Re: Essex River
More informationUNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH NO. 101 OVER THE MINNESOTA RIVER DISTRICT 8 - REDWOOD COUNTY
UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 7149 CSAH NO. 101 OVER THE MINNESOTA RIVER DISTRICT 8 - REDWOOD COUNTY PREPARED FOR THE MINNESOTA DEPARTMENT OF TRANSPORTATION BY COLLINS ENGINEERS, INC.
More information