1 University of Nottingham University Park Campus Masterplan Strategy 13 th February 2009

2 Purpose of this Document The purpose of this document is to set out a new masterplan strategy for University Park Campus that addresses key pedestrian, cycle and vehicle routes. Through the analysis of existing traffic flows across the site, this document proposes ways of reducing the impact of vehicular traffic whilst placing a greater emphasis on cyclist and pedestrian priority. This site wide review also identifies potential development sites across the campus, for either new buildings or additional car parking. Finally landscaping strategies are proposed for the central campus zone, (the area behind Trent and Portland Buildings) and also the central area of Science and Engineering. This report presumes that Lenton House and grounds fall under the ownership of the University of Nottingham and also the ISG carpark has been developed. Jubilee Avenue i

3 Summary This report demonstrates that it is possible to successfully pedestrianise central academic areas, whilst retaining most of the existing car parks. The creation of new pedestrian priority boulevards along the central section of and the central area within Science and Engineering improves pedestrian experience, whilst the new cycle path network offers dedicated routes across the campus. New and remodelled vehicle routes maintain accessibility to the Trent Building, however the link between East Drive and Jubilee Avenue will be removed. The direction of traffic along Jubilee Avenue is therefore reversed and a new road up to the Western section of Cut Through Lane is proposed to make a loop. Also Keighton Hill becomes two directional and includes a cycle path to complete the connection between North and South entrances. The re-organised traffic flows present new development opportunities for buildings or car parks, especially in and around the central campus zone. The open area of land to the West of the Trent Building would help balance development about it. Hallward Library Car Park These proposals set out a long term vision for University Park Campus, which reaffirms the core design principles that have shaped campus development. Highfield House Re-landscape site of demolished building New Landscape Portland Building Car Park Trent Building Car Park Jubilee Avenue East Drive Pedestrian Desire Lines Vehicle Routes Service Access Permitted Central Campus Zone Landscape Strategy ii

4 Contents Introduction 1 Brief 2 University Park Campus Core Design Principles 3 Site Analysis - Issues to be addressed 4 Concept Development 5 Emerging Masterplan Strategy 6 Establishing Designated Pedestrian Routes 7 Proposed Vehicle Strategy 8 Proposed Bus Routes 9 Proposed Cycle Strategy 10 Development Opportunities 13 Central Campus Zone - Landscape Strategy 14 Science & Engineering - Landscape Strategy 15 Conclusion 16 iii

5 Introduction In September 2008 HAL were commissioned by the University of Nottingham to produce concept ideas for a new masterplanning strategy for University Park Campus. The University has identified a need to improve pedestrian experience, to improve cyclist safety and finally to reduce impact of cars and car parking in sensitive areas around the campus. This masterplan looks to learn and build upon the key campus design principles that have informed University Park Campus development. Aerial of campus 1

6 Brief To create a masterplan for the University Park Campus, with focus on the following; To review pedestrian, cycle and vehicular routes across the campus. To re-organise the different traffic flows, with emphasis on pedestrians and cyclists. Propose a landscape strategy for the central campus area behind the Trent and Portland Buildings. Consideration to be given to removing Cut Through Lane as a vehicular route. NORTH Look at ways of increasing the pedestrianised central campus area. Retain the number of car park spaces (any lost must be replaced). THE DOWNS Lenton Hall Drive Lenton House & Grounds Hallward Library Library Road Visitor Car Park ISG SCIENCE AND ENGINEERING CENTRAL CAMPUS ZONE Keighton Hill TO WEST Highfield House Trent Portland Portland Hill Jubilee Avenue East Drive TO SOUTH N University Park Campus 2

7 University Park Campus Core Design Principles The development of University Park Campus has been shaped by a number of key moves, building on Morley Horder s decision to site the University College Building (Now Trent Building) to set up a dramatic contrast to the informal landscape of the Highfields Estate. The most notable of these is the way in which different building types are grouped together. Academic buildings are clustered around the Trent building, while the halls of residence wrap around the edge of the Downs. The halls of residence inside, and the academic buildings are generally well connected by dedicated pedestrian routes A later development was the positioning of Science and Engineering to the North East of the Campus. Pedestrian links connecting this area rely on paths adjacent to heavily trafficked vehicle routes. Campus Masterplan 1949 Campus Masterplan 1955 The Downs Science and Engineering Trent Portland Halls of Residence Academic and other University support facilities Primary Campus Buildings N Campus Masterplan circa 1960 Current Campus Layout 3

8 Site Analysis Issues to be addressed Cars and Car Parking Vehicle routes and especially car parking dominate the campus environment, most notably around: Science and Engineering Trent Building is the main thoroughfare linking the North and West entrances runs around the perimeter of the campus linking the North and West entrances. Most of the halls or residence are accessed via. The approach to the Trent Building by car is only possible along East Drive. East Drive and Jubilee Avenue are linked via the service route cut into the landscape behind the Trent Building. Car Parking pervades the central academic areas, such as the centre of Science and Engineering. Cut through lane connects West and North entrances. It is the most direct vehicle route accross the campus and is frequently used by non University related traffic Public Transport The campus is served by a number of public bus routes linking the University with the city. The majority of buses enter the campus via the North entrance. The long straight section of East drive beneath Kneighton Hill is used as the main bus stop. ISG Hopper bus services linking the University s 3 main campuses all run along the length of cut through lane. Cyclists Dedicated pedestrian paths are laid out across the campus, but they are disparate and unconnected The city of Nottingham has a number of cycle routes close to university park. However, few dedicated cycle paths are provided within University Park Campus. The majority of cycle parking is located close to each building, generally accessed via pavements. Very few cycle paths are provided across the campus The Humanities Building and administrative block under consideration for demolition The long straight section of road along East Drive can accommodate a number of bus stops Pedestrians Pedestrian access across the campus is generally good except for routes between Science and Engineering, the Central Campus Zone and the Westgate Lodges. Connections appear disjointed, relying on paths adjacent to heavily trafficked vehicle routes Existing cycle paths Existing vehicle routes Routes taken by students across landscaped areas Public / Hopper Bus Stop Main Car Parks N Existing main pedestrian only routes Extension to ISG Building 4

9 Concept Development 5

10 Emerging Masterplan Strategy Our emerging masterplan strategy involves removing cars from central academic areas and establishing a pedestrian friendly environment. New routes connecting Westgate Lodges and Science and Engineering will pick up the existing network of paths as well as re-use a car free section of. These routes will open up potential development sites, which could help to balance the campus around the Trent Building, for example. Perimeter Vehicle Link Vehicles The Downs Vehicles Vehicles Concept Diagram Central Campus Zone Science and Engineering Academic and other University support facilities Halls of Residence Primary Campus Buildings Pedestrian Links Conceptual Approach 6

11 Establishing Designated Pedestrian Routes One of the primary aims of this masterplan strategy is to establish car free zones within central academic areas. Across the campus pedestrianised routes are created linking science and engineering, through the central campus zone and on to the halls of residence beyond the West Gate Lodges. New pedestrian routes will connect existing paths to form continuous thoroughfares. Two main pedestrian routes through the central campus area are proposed: The newly pedestrianised Route Along Cut Through Lane, Portland Hill and Library Road This new shared surface facilitates easy transition along the primary routes linking academic facilities with Halls of Residence. In the future it would be possible to make a new link through Lenton House and grounds providing easy access to Cavendish and Willoughby Halls. Along the rear of Portland and Trent buildings THE DOWNS Lenton Hall Drive NORTH to improving this route is to continue the route to the west of Trent linking into the path running parallel with. A more direct route across Keighton Hill is also suggested. This will enhance pedestrian safety for students heading to and from Biology and Science & Engineering. Hallward Library Library Road ISG SCIENCE AND ENGINEERING Highfield House CENTRAL CAMPUS ZONE Portland Hill Keighton Hill TO WEST Trent Portland Jubilee Avenue East Drive University Park Campus TO SOUTH N Primary Routes Shared Surface (Cars permitted) Secondary Routes Extension to ISG Building Potential New Routes Pedestrian Boulevard Pedestrian Routes 7

12 Proposed Vehicle Strategy Proposed Pedestrianisation of Central Academic Areas The proposed pedestrainisation of the central section of and Portland Hill will significantly improve pedestrian safety as well as enhancing the peaceful landscaped environment that chacterises University Park Campus. Vehicle access will not be permitted through this area except for service vehicles and buses. The central area within Science and Enigineering will also exclude vehicle access and parking (currently around the Chemistry and Tower building). Breaking the link between East Drive and Jubilee Avenue The Trent Building will once again become a destination, rather than a through route. However service access around the rear of the Trent building will be permitted. THE DOWNS Lenton Hall Drive NORTH As a consequence the traffic direction along Jubilee Avenue will be changed so that vehicles approach the Trent Building re-affirming its primacy. Maintaining Routes around the perimeter of the Campus Lenton House & Grounds Hallward Library Library Road Visitor Car Park Consideration should be given to transforming Keighton Hill onto a 2 way route for vehicles. This will become the only link between the North and South Entrances. will remain as the only link between West and North Entrances. As the main route accross the campus, consideration should be given to traffic calming measures. TO WEST Highfield House Trent CENTRAL CAMPUS ZONE Portland Portland Hill Keighton Hall SCIENCE AND ENGINEERING Car Parking Jubilee Avenue East Drive The proposed pedestrianisation of the central academic areas will result in some loss of spaces; Between the LSS building and Hallward Library. Around the chemistry and Tower buildings The 2 way portion of Jubilee avenue University Park Campus TO SOUTH N These lost spaces will have to be found else where a campus. Access to the car park opposite the Hallward Library is now from Library road, which is a shared surface with pedestrian priority. Proposed Vehicle Routes Direction of Traffic Service Access Permitted Shared Surface (Cars permitted) Main Car Parks Existing Buildings to be removed Car Parks to be Removed Pedestrian Boulevard Extension to ISG Building Proposed Vehicle Routes 8

13 Proposed Bus Routes Hopper Bus Service The Hopper bus service is a vital link between the University of Nottingham s 4 campuses. It is therefore important to maintain ease of access and use for the student body. and Portland Hill are to remain accessible to the Hopper buses. Public Bus Service Currently public buses are allowed through the campus, connecting the University with the City of Nottingham. The main bus stop along East Drive works well allowing numerous buses to pick up at the same time. It is therefore necessary to allow buses to travel down Portland Hill. THE DOWNS Lenton Hall Drive NORTH Hallward Library Library Road SCIENCE AND ENGINEERING Keighton Hall Highfield House Portland Hill TO WEST CENTRAL CAMPUS ZONE Trent Portland Jubilee Avenue East Drive University Park Campus TO SOUTH N Public Bus Service (No.34 & L12) Public / Hopper Bus Stop Shared Surface (Cars permitted) Hopper Bus Service Public Bus Stop Extension to ISG Building Pedestrian Boulevard Hopper Bus Stop Proposed Bus Routes 9

14 Proposed Cycle Strategy Clearly defined cycle routes are proposed throughout the campus. These routes connect to the wider cycle path networks providing easy access to and from the city. A new shared surface along the central section of will form the primary route across the campus. All other cycle routes will feed into it. Encorporating cycle routes along the trafficked parts of, Lenton Hall Drive and Library Road is considered in more detail on the following pages. Portland Hill and Keighton Hill As Portland Hill remains a one way bus route down the hill, cyclists can follow the same path. To complete the link between North and South Entrances cyclists must be permitted to travel up Keighton Hill. Lenton Hall Drive THE DOWNS Lenton Hall Drive NORTH New cycle / pedestrian paths either side of the road should be considered. Across the Downs A new route across the edge of the downs will better connect the Halls of Residence with the central academic facilities. Hallward Library Library Road SCIENCE AND ENGINEERING A new dedicated route linking North and West Entrances is proposed to pick up the main routes across the Downs. TO WEST Jubilee Avenue Highfield House CENTRAL CAMPUS ZONE Trent Portland East Drive Portland Hill Keighton Hall Lenton House and Grounds To complete the radial connections across the campus a new route through Lenton House Grounds, along the drive, should be considered in the future. University Park Campus TO SOUTH N Proposed Cycle Route Shared Surface (Cars permitted) Future Cycle Route Extension to ISG Building Cycle Entrance Points Existing cycle paths Pedestrian Boulevard Proposed Cycle Routes 10

15 Road Pavement Road Pavement Pavement Road Existing - Cars and cyclists share the same routes. Existing - Cars and cyclists share the same routes. Separate pavements either side. Existing - Cars and cyclists share the same routes. Pavement on one side only. Cycle Lane Cycle Lane One Way Road Shared Surface Pavement Road Cycle Lane Buses and cyclists in central area only Suggested alternative - One way traffic permits dedicated cycle paths. Section AA Suggested alternative - Shared surface with pedestrian priority. Buses and cyclists are permitted to use the central section only. Section BB Suggested alternative - New cycle paths cut into hill. Section CC New cycle path adjacent to road C Boulevard Cycle path sharing road with one way traffic A New cycle path through trees B : Cycle Path Design Suggestions Proposed Route Pedestrian Boulevard Considering the implications of a designated cycle route along 11

16 Library Road Hopkins Architects Road Pavement Existing - Cars and cyclists share the same routes. Pavement on one side only. Shared Surface Lenton Hall Drive E Suggested alternative - Shared surface permitting car access. Section DD Road Pavement D Hallward Library Existing - Cars and cyclists share the same routes. Pavement on one side only. Pavement One Way Cycle Path Road One Way Cycle Path Pavement Suggested alternative - Separate cycle and pedestrian routs ither side of road. Section EE Proposed Route Shared Surface (Cars permitted) Lenton Hall Drive and Library Road: Cycle Path Design Suggestions Considering the implications of designated cycle routes along Lenton Hall Drive and Library Road 12

17 Development Opportunities Our analysis of the Campus has identified a number of development opportunities, which could be considered for new buildings or as sites for additional car parking. In line with the core masterplan design principles, the development sites close to the central academic areas should be considered for academic or administrative functions. The sites along at the bottom of the Downs are more suited for halls of residence of car parks. THE DOWNS Lenton Hall Drive NORTH Hallward Library Library Road SCIENCE AND ENGINEERING TO WEST Highfield House CENTRAL CAMPUS ZONE Trent Portland Portland Hill Keighton Hall Jubilee Avenue East Drive University Park Campus TO SOUTH N Development Sites for either new buildings or additional carparking Extension to ISG Building Pedestrianised Boulevard Shared Surface (Cars permitted) Development Opportunities 13

18 Hallward Library Car Park Boulevard Re-landscape site of demolished building New Landscape Keighton Hill Highfield House Portland Hill Viewing Terrace Portland Building Car Park Trent Building Car Park Jubilee Avenue East Drive Existing bus route Pedestrian Route Pedestrianised Boulevard (Cars permitted) Landscaping Existing Building to be Removed Central Campus Zone Landscape Strategy Cars are no longer permitted in the central campus zone creating a more pedestrian friendly environment. Car access to the Trent Building remains. Both Jubilee Avenue and East Drive approach the University s most important building making it a destination in its own right. back to the Boulevard via the pedestrianised Portland Hill and a new path from the Trent Building around Highfields House upper terrace. Other perpendicular routes are employed to complete intermediate links, which also provide connections to the wider campus facilities. A new route across Keighton Hill also provides an easier and safer route from the Portland Building towards Biology and Science and Engineering. Vehicle Routes Pedestrian Desire Lines Desire Lines The space behind the Trent Building is opened up, with the removal of the Administration and Classics Buildings, re-establishing a green heart within the central academic facilities. The two main pedestrian routes are along boulevard and paths connecting the Portland and Trent buildings. This second route connects The steep slope behind the Portland building should be re-landscaped, making it more accessible to the student body, linking the vibrant colonnade with the boulevard above. The natural rake of this new landscaped space could make for an interesting external performance space. A simple water feature would also benefit from the level changes. Landscape Strategy 14

19 Routes / Desire Lines Science and Engineering - Landscape Strategy A new landscaped boulevard linking the Library and the Tower Building will help orientate students within the centre of Science and Engineering. Consider a new PV covered canopy that would run the length of the boulevard under which cycle parking and seating areas would be located. New signage and lighting would also help improve way finding within the central zone. The boulevard would help enclose the 4 th side of the quadrangle, raising its status as a more formal green space. Location Plan Showing Routes In / Out 15

20 Conclusion Pedestrianising central academic areas, whilst retaining the majority of existing car parking spaces is possible. New and improved routes across the campus will promote greater connectivity between core academic facilities for pedestrians. Central to this is the creation of new pedestrian boulevards along the central section of and the central area within Science and Engineering. The new cycle path network offers dedicate routes across the campus providing clear delineation between cyclists, pedestrians and cars. All bus routes and service vehicle access are unaffected by the proposals. Unlike cars they are permitted to use pedestrianised areas, but speed will be restricted. Traffic flows are significantly altered and for vehicle routes to work new and remodelled links are required. The direction of traffic along Jubilee Avenue needs to be reversed and a new road will be constructed to link Jubilee Avenue with the Western section of Cut Through Lane. Also Keighton Hill requires substantial modification. Two way traffic and a cycle path are required to complete vehicle connections between the North and South entrances. We have suggested that the only route cars and pedestrians share is the upper section of Library Road. This shared surface will permit car access to the Library Road car park, which has been identified as a potential development site. If in the future the car park is developed then the whole of Library road could become pedestrian only. The revised road network does open up other possibilities for development especially in and around the central campus zone which would help balance academic facilities about the Trent Building. It is important to note that these proposals can be divided into separate independent elements, facilitating phased development. University Park Campus can therefore continue to develop organically, incorporating or adapting to suit future building development proposals. 16

Your views are important. Please fill in a form before you leave. Or alternatively

Your views are important. Please fill in a form before you leave. Or alternatively Drum Property Group is delighted to welcome you to this exhibition which sets out our initial proposals for a mixed-use development at Stead s Place, Edinburgh. We are keen to hear the views of local people

More information

Tonight is for you. Learn everything you can. Share all your ideas.

Tonight is for you. Learn everything you can. Share all your ideas. Strathcona Neighbourhood Renewal Draft Concept Design Tonight is for you. Learn everything you can. Share all your ideas. What is Neighbourhood Renewal? Creating a design with you for your neighbourhood.

More information

Dowling/Beaty Cycling Route

Dowling/Beaty Cycling Route Public Meeting #2 Dowling/Beaty Cycling Route May 17, 2017 6:00 p.m. 8:00 p.m. Parkdale Public Library - Auditorium 1303 Queen Street West How to Participate Share your questions, ideas and concerns We

More information

Welcome. If you have any questions or comments on the project, please contact:

Welcome. If you have any questions or comments on the project, please contact: Welcome This drop-in public open house is intended to provide information about the Bay Street bike lanes project. This project proposes a dedicated cycling facility along Bay Street between Aberdeen Avenue

More information

Welcome! Public Open House on UBC s Transportation Plan

Welcome! Public Open House on UBC s Transportation Plan 1 Welcome! Public Open House on UBC s Transportation Plan Public open house hours: to When it comes to on-campus transportation, what do you think is working well and what are some opportunities for improvement?

More information

Roads and Vehicular Traffic Design Principles. Roads and Vehicular Traffic Recommendations

Roads and Vehicular Traffic Design Principles. Roads and Vehicular Traffic Recommendations CIRCULATION AND PARKING roads and vehicular traffic The Campus Master Plan updates the campus transportation network through a multi-modal approach that encourages walking and biking while improving vehicular

More information

BYRES ROAD: PUBLIC REALM Public Consultation

BYRES ROAD: PUBLIC REALM Public Consultation Public Consultation Introduction As a vibrant commercial, shopping and residential location within the heart of the West End Byres Road is an important destination. Its proximity to the University of Glasgow

More information

DESIGN CODE. Enterprise West Harlow London Road North Design Code 21

DESIGN CODE. Enterprise West Harlow London Road North Design Code 21 DESIGN CODE Enterprise West Essex @ Harlow London Road North Design Code 21 4 MAXIMUM BUILDING HEIGHTS 4.1 Table 4A sets out maximum building height standards for each character area within the LDO boundary.

More information

University of Victoria Campus Cycling Plan Terms of Reference. 1.0 Project Description

University of Victoria Campus Cycling Plan Terms of Reference. 1.0 Project Description University of Victoria Campus Cycling Plan Terms of Reference 1.0 Project Description The Campus Cycling Plan, a first for the University, will provide a comprehensive and coordinated approach to support

More information

Pennsylvania Avenue (CR 484) Design Alternatives Study

Pennsylvania Avenue (CR 484) Design Alternatives Study MEMORANDUM Pennsylvania Avenue (CR 484) Design Alternatives Study Prepared for: APRIL 2016 Prepared By TABLE OF CONTENTS Project Background... 2 Previous Concept... 2 Existing Conditions... 4 New Alternatives...

More information

A CHANGING CITY. of Edmonton, it is essential that it reflects the long-term vision of the City.

A CHANGING CITY. of Edmonton, it is essential that it reflects the long-term vision of the City. A CHANGING CITY By the year 2040, Edmonton will be home to more than 1 million people. To accommodate growth and support a healthy and compact city, we need a new approach to development/redevelopment

More information

TRAVEL PLAN: CENTRAL EUROPEAN UNIVERSITY CAMPUS REDEVELOPMENT PROJECT TRAVEL PLAN. Central European University Campus Redevelopment Project.

TRAVEL PLAN: CENTRAL EUROPEAN UNIVERSITY CAMPUS REDEVELOPMENT PROJECT TRAVEL PLAN. Central European University Campus Redevelopment Project. TRAVEL PLAN Central European University Campus Redevelopment Project Page 1 Table of Contents Introduction... 3 Background... 7 Building Users... 7 Transportation in Community Consultation... 7 Summary

More information

FOCUS AREA 1 - Alberta Avenue Pocket Park 3 (121 Ave and 92 St)

FOCUS AREA 1 - Alberta Avenue Pocket Park 3 (121 Ave and 92 St) FOCUS AREA 1 - Alberta Avenue Pocket Park 3 (121 Ave and 92 St) New benches Plant evergreen trees Widen existing sidewalk from 1.5m to 1.8m Marked crosswalk 1.8m wide sidewalk Add pedestrian oriented lights

More information

ENFIELD TOWN THE REVISED DESIGN

ENFIELD TOWN THE REVISED DESIGN TOWN THE REVISED DESIGN We re turning Enfield into a borough that encourages walking and cycling, a place that s easy for all of us to get around however we choose to travel. A greener place, with safer

More information

Have your say on the transformation of Oxford Street West

Have your say on the transformation of Oxford Street West Have your say on the transformation of Oxford Street West About Living Streets We are Living Streets, the UK charity for everyday walking. We want to create a walking nation, free from congested roads

More information

EXECUTIVE SUMMARY Callan Park accommodates travel from a wide range of transport modes, including walking, cycling, bus and light rail.

EXECUTIVE SUMMARY Callan Park accommodates travel from a wide range of transport modes, including walking, cycling, bus and light rail. TRANSPORT AND ACCESS EXECUTIVE SUMMARY Callan Park accommodates travel from a wide range of transport modes, including walking, cycling, bus and light rail. Whilst there are some walking facilities within

More information

Frome Street Bicycle Route

Frome Street Bicycle Route The Adelaide City Council invites engagement from the community about Frome Street Bicycle Route Project Summary Adelaide City Council is seeking feedback on design options to construct bicycle facilities

More information

Executive Summary Route 30 Corridor Master Plan

Executive Summary Route 30 Corridor Master Plan Route Corridor Master Plan Project Overview The Route Corridor Master Plan is a coordinated multimodal transportation and land use plan for the entire stretch of Route through East Whiteland Township,

More information

Green Streets and Urban Greenways

Green Streets and Urban Greenways 127 11 Green Streets and Urban Greenways 11. Green Streets and Urban Greenways 128 11 Green Streets and Urban Greenways Once the traffic-free section of a route has come to an end, then comes the remaining

More information

Bristol City Council has produced a draft Bristol Transport Strategy document.

Bristol City Council has produced a draft Bristol Transport Strategy document. Bristol Transport Strategy Summary Document Introduction Bristol City Council has produced a draft Bristol Transport Strategy document. The Strategy fills a gap in transport policy for Bristol. We have

More information

Public Consultation on Braintree Integrated Transport Package (ITP) HAVE YOUR. Consultation open from 24 September to 5 November 2018 SAY

Public Consultation on Braintree Integrated Transport Package (ITP) HAVE YOUR. Consultation open from 24 September to 5 November 2018 SAY Public Consultation on Braintree Integrated Transport Package (ITP) HAVE YOUR SAY Consultation open from 24 September to 5 November 2018 Contents Introduction 3 Background 4 Springwood Drive Roundabout

More information

IAN WHITE ASSOCIATES. Crawley Station Gateway Public Realm

IAN WHITE ASSOCIATES. Crawley Station Gateway Public Realm IAN WHITE ASSOCIATES Crawley Station Gateway Public Realm contents 1. objectives & client brief 2. site appraisal 3. best practice guidance 4. design concept 1. objectives & client brief Crawley Train

More information

LEA BRIDGE ROAD - A STREET FOR EVERYONE Public consultation document

LEA BRIDGE ROAD - A STREET FOR EVERYONE Public consultation document LEA BRIDGE ROAD - A STREET FOR EVERYONE Public consultation document TELL US Bakers Arms to Leyton Green Road (Section D, E, F) Leyton Green Road to Whipps Cross Roundabout (Section G) YOUR VIEWS www.enjoywalthamforest.co.uk

More information

Guide to the Cycle Enfield Public Consultation on Enfield Town. Produced by the Save Our Enfield Town Campaign Group

Guide to the Cycle Enfield Public Consultation on Enfield Town. Produced by the Save Our Enfield Town Campaign Group Guide to the Cycle Enfield Public Consultation on Enfield Town Produced by the Save Our Enfield Town Campaign Group What s in this guide? Introduction Page 3 What Enfield Council says about Option 1 Page

More information

Streetscape: Core Shopping District

Streetscape: Core Shopping District Streetscape: Core Shopping District DRAFT DRAFT DRAFT May 00 Core Shopping District: Phase Blue Island s Core Shopping District is located along Western Avenue, between Grove and Union Streets. Streetscape

More information

Bikeway action plan. Bicycle Friendly Community Workshop March 5, 2007 Rochester, MN

Bikeway action plan. Bicycle Friendly Community Workshop March 5, 2007 Rochester, MN Bikeway action plan Summary The was held on March 5, 2007 at the Rochester Mayo Civic Center. The workshop was hosted by Rochester-Olmsted County Planning Department in collaboration with the League of

More information

NM-POLICY 1: Improve service levels, participation, and options for non-motorized transportation modes throughout the County.

NM-POLICY 1: Improve service levels, participation, and options for non-motorized transportation modes throughout the County. Transportation PRINCE WILLIAM COUNTY 2008 COMPREHENSIVE PLAN NON-MOTORIZED PLAN CONTENTS Goals, Policies, and Action Strategies Table 4 (Bike Facility Classifications and Descriptions) Table 5 (Bike Facility

More information

NEWMARKET UPHAM S CORNER

NEWMARKET UPHAM S CORNER SOUTH STATION Planning Initiative NEWMARKET UPHAM S CORNER COLUMBIA ROAD (P) FOUR CORNERS/GENEVA Working Advisory Group (WAG) Meeting #5 TALBOT AVENUE MORTON STREET BLUE HILL AVE/CUMMINS HWY (P) RIVER

More information

RESOLUTION NO ?? A RESOLUTION OF THE CITY OF NEPTUNE BEACH ADOPTING A COMPLETE STREETS POLICY

RESOLUTION NO ?? A RESOLUTION OF THE CITY OF NEPTUNE BEACH ADOPTING A COMPLETE STREETS POLICY RESOLUTION NO. 2018-?? A RESOLUTION OF THE CITY OF NEPTUNE BEACH ADOPTING A COMPLETE STREETS POLICY WHEREAS, safe, convenient, and accessible transportation for all users is a priority of the City of Neptune

More information

CAMBOURNE TO CAMBRIDGE BETTER PUBLIC TRANSPORT PROJECT PHASE 2 PUBLIC CONSULTATION MADINGLEY MULCH ROUNDABOUT TO CAMBOURNE

CAMBOURNE TO CAMBRIDGE BETTER PUBLIC TRANSPORT PROJECT PHASE 2 PUBLIC CONSULTATION MADINGLEY MULCH ROUNDABOUT TO CAMBOURNE CAMBOURNE TO CAMBRIDGE BETTER PUBLIC TRANSPORT PROJECT PHASE 2 PUBLIC CONSULTATION MADINGLEY MULCH ROUNDABOUT TO CAMBOURNE Have your say on proposals for a new public transport link and Park & Ride facility

More information

New Brunswick Strategic Planning Proposal

New Brunswick Strategic Planning Proposal New Brunswick Strategic Planning Proposal Proposal Title: Rutgers University Crosswalk Enhancement Project Proposal Initiator: Rutgers University Division of Administration and Public Safety Executive

More information

Coquitlam Cross-town Bike Route Improving Bicycle Facilities in a Mature Suburban Environment

Coquitlam Cross-town Bike Route Improving Bicycle Facilities in a Mature Suburban Environment Coquitlam Cross-town Bike Route Improving Bicycle Facilities in a Mature Suburban Environment Sarah Rocchi, Vice-President, Projects, Opus International Consultants (Main Presenter) Catherine Mohoruk,

More information

sessions. The opinions of local people will help decide which of these two options is taken forward to be built.

sessions. The opinions of local people will help decide which of these two options is taken forward to be built. A4018 FAQs Why are no bus lanes proposed north of Crow Lane? Inbound and outbound bus lanes were considered north of the Crow Lane junction, but they took away capacity from other traffic on the approach

More information

Report on MEPS Přerov TH MIDDLE EUROPEAN PROJECT SEMINAR LAURA ENJUANES NOGUERO E

Report on MEPS Přerov TH MIDDLE EUROPEAN PROJECT SEMINAR LAURA ENJUANES NOGUERO E 2017 Report on MEPS Přerov 2017 28TH MIDDLE EUROPEAN PROJECT SEMINAR LAURA ENJUANES NOGUERO E01650478 Table of Content 1. Introduction... 1 2. Problem definition... 1 3. Proposed solution in the presentation...

More information

Table #6 VISION CHARACTERISTICS

Table #6 VISION CHARACTERISTICS Table #6 VISION White Flint is a place to live, work, play, shop, and walk with sufficient density to encourage quality redevelopment. Vibrant streets and consistent streetscapes are important. CHARACTERISTICS

More information

Miami Health District

Miami Health District Miami Health District Streetscapes, Gateways, and Signage Basis of Design Report Study Miami Partnership Meeting July 21, 2008 Gannett Fleming EDAW The Corradino Group Sponsored by the Miami Partnership:

More information

River Road - Proposed Road Safety Enhancement Measures

River Road - Proposed Road Safety Enhancement Measures City of Richmond Report to Committee To: From: Re: Public Works and Transportation Committee Victor Wei, P. Eng. Director, Transportation Date: June 6, 2017 River Road - Proposed Road Safety Enhancement

More information

STONY PLAIN ROAD STREETSCAPE

STONY PLAIN ROAD STREETSCAPE Jasper Place Revitalization Strategy: Vision The people involved in the Jasper Place Revitalization Strategy envision: Goal 1: Feeling safe in our community Create a community where feeling safe is common--where

More information

Cabinet Member for Highways & Streetscene. Highway Infrastructure Manager

Cabinet Member for Highways & Streetscene. Highway Infrastructure Manager LONDON BOROUGH OF RICHMOND UPON THAMES DATE: AUGUST 2015 DECISION MAKER: LEAD OFFICER: SUBJECT: WARDS: Cabinet Member for Highways & Streetscene Highway Infrastructure Manager PROPOSED CYCLING IMPROVEMENTS

More information

COWETA HIGH SCHOOL AND EAST HIGHWAY 51

COWETA HIGH SCHOOL AND EAST HIGHWAY 51 COWETA HIGH SCHOOL AND EAST HIGHWAY 51 Lack of sidewalks along Ben Lumpkin Rd. Lack of crosswalks and ramps at intersection. Hwy 51 is wide to cross as a pedestrian. No ADA compliance or connection to

More information

CPC Parking Lot Riverside Drive. Transportation Rationale

CPC Parking Lot Riverside Drive. Transportation Rationale CPC Parking Lot Transportation Rationale Prepared By: NOVATECH Suite 200, 240 Michael Cowpland Drive Ottawa, Ontario K2M 1P6 September 2015 Novatech File: 114093 Ref: R-2015-153 Table of Contents 1.0 INTRODUCTION...

More information

MILTON ROAD LLF PROJECT UPDATE

MILTON ROAD LLF PROJECT UPDATE Greater Cambridge City Deal MILTON ROAD LLF PROJECT UPDATE 9 th May 2017 Project objectives Comprehensive priority for buses in both directions wherever practicable; Additional capacity for sustainable

More information

4 Goals, Objectives & Actions

4 Goals, Objectives & Actions Chapter4 4 This chapter presents goals, objectives, and recommended actions to support the vision of making Overland Park a safer and easier place to ride a bicycle. 35 4.1 Recommendations Structure The

More information

STREET AND HIGHWAY PLAN

STREET AND HIGHWAY PLAN STREET AND HIGHWAY PLAN Introduction The street and highway system in the Winston-Salem Urban Area consists of thousands of miles of traffic carrying facilities, ranging from short local residential streets

More information

Introduction. Prince Street Cycling Ambition Fund Public Realm Project

Introduction. Prince Street Cycling Ambition Fund Public Realm Project Introduction The (CAF) project will create a high quality, 8-80 s cycle route up the west side of Prince Street from Cumberland Road, over Prince Street bridge to the Centre. This is part of the City Centre

More information

Sixth Line Development - Transit Facilities Plan

Sixth Line Development - Transit Facilities Plan Memorandum Date: November 13, 2012 To: From: c.c. Subject: Rob Freeman (Freeman Planning) Kevin Phillips Sixth Line Development - Transit Facilities Plan 33016631 This memo was prepared to review the transit

More information

City of Perth Cycle Plan 2029

City of Perth Cycle Plan 2029 Bicycling Western Australia s response City of Perth Cycle Plan 2029 2012-2021 More People Cycling More Often ABOUT BICYCLING WESTERN AUSTRALIA Bicycling Western Australia is a community based, not-for-profit

More information

Chapter 5 Future Transportation

Chapter 5 Future Transportation Chapter 5 Future Transportation The Future Land Use Plan identifies the desired land use designations. The land uses desired for Crozet depend, in large part, on the success of the transportation system,

More information

Rethinking Transportation

Rethinking Transportation Rethinking Transportation We have some innovative ideas about a local transportation sharing network. car share and a bike share could mean that future residents would not need to own either a car or a

More information

2014/2015 BIKE ROUTE PLAN 83 AVENUE PROTECTED BIKE LANE

2014/2015 BIKE ROUTE PLAN 83 AVENUE PROTECTED BIKE LANE About the Project The City of Edmonton is planning a major bike route on the southside of Edmonton. The Strathcona Bike Route will connect the communities of Strathcona, Garneau and the University area,

More information

Broad Street Bicycle Boulevard Design Guidelines

Broad Street Bicycle Boulevard Design Guidelines Broad Street Bicycle Boulevard Design Guidelines Building from the strategies introduced in the 2013 Bicycle Transportation Plan and community input received thus far, City Transportation Staff have identified

More information

York Boulevard Streetscape Master Plan

York Boulevard Streetscape Master Plan York Boulevard Streetscape Master Plan October 24 th, 2008 The Story of York Boulevard Streetscape Master Plan Design. Chapter 126 Dealing with Engineers. 2 1 Today s Presentation Topics: 1. Show the streetscape

More information

2014/2015 BIKE ROUTE PLAN 83 AVENUE PROTECTED BIKE LANE

2014/2015 BIKE ROUTE PLAN 83 AVENUE PROTECTED BIKE LANE About the Project 2014/2015 BIKE ROUTE PLAN The City of Edmonton is planning a major bike route on the south side of Edmonton. This bike route is one part of a plan to provide citizens with transportation

More information

Design Workshops Summary of all Feedback January 2017

Design Workshops Summary of all Feedback January 2017 Histon Road Corridor Design Workshops Summary of all Feedback January 2017 CITY DEAL AND GROWTH Commitment to Growth: Government, County, City and District Emerging Local Plans: 33,000 new homes 45,000

More information

Chapter 3 DESIGN SPECIFICATIONS

Chapter 3 DESIGN SPECIFICATIONS Brampton PathWays Planning and Design Guidelines 27 Chapter 3 DESIGN SPECIFICATIONS 3.1 CLASS 1 MULTI-USE PATH Off-road multi-use trails are the backbone of the Brampton PathWays Network. They are typically

More information

REF. PE01595: MORATORIUM ON SHARED SPACE SCHEMES

REF. PE01595: MORATORIUM ON SHARED SPACE SCHEMES PE1595/RRR Sustrans submission of 17 March 2017 Following the Public Petitions Committee meeting on 9 th February 2017 you wrote to Sustrans Scotland requesting a clarification on our position on the use

More information

CITY OF SEATTLE RESOLUTION. WHEREAS, the Washington State Department of Transportation (WSDOT) led the Seattle

CITY OF SEATTLE RESOLUTION. WHEREAS, the Washington State Department of Transportation (WSDOT) led the Seattle SDOT SR0 Design Refinements RES August, 0 Version #D 0 CITY OF SEATTLE RESOLUTION..title A RESOLUTION relating to the State Route 0, Interstate to Medina Bridge Replacement and High Occupancy Vehicle Project;

More information

WELCOME. Purpose of the Open House. Update you on the project. Present a draft recommended plan. Receive your input

WELCOME. Purpose of the Open House. Update you on the project. Present a draft recommended plan. Receive your input WELCOME Purpose of the Open House The Town of Smiths Falls has initiated the Beckwith Street Redevelopment Plan that includes the preparation of a streetscape functional design for the renewal of Beckwith

More information

Living Streets Policy

Living Streets Policy Living Streets Policy Introduction Living streets balance the needs of motorists, bicyclists, pedestrians and transit riders in ways that promote safety and convenience, enhance community identity, create

More information

5 CIRCULATION AND STREET DESIGN

5 CIRCULATION AND STREET DESIGN 5 CIRCULATION AND STREET DESIGN This chapter describes circulation and streetscape improvements proposed for the Northwest Chico Specific Plan Area. It includes detailed design specifications for existing

More information

Design of Stanley Park S-Curve

Design of Stanley Park S-Curve ADMINISTRATIVE REPORT Date: May 4, 2001 TO: FROM: Author/Local: F. Klotzbach/7118 RTS NO. 01644 CC File No. Standing Committee on Transportation and Traffic General Manager of Engineering Services, in

More information

Derby Cycling Group, c/o 126, Station road, Mickleover, Derby, DE3 9FN. Date: 20 th November, 2018.

Derby Cycling Group, c/o 126, Station road, Mickleover, Derby, DE3 9FN. Date: 20 th November, 2018. Your Ref: Derby City Council Air Quality - Preferred Option Nov 2018 Derby Cycling Group, c/o 126, Station road, Mickleover, Derby, DE3 9FN Date: 20 th November, 2018. 1. Introduction: 1.1. Derby Cycling

More information

Part B Design Guidance / Principles _

Part B Design Guidance / Principles _ Part B Design Guidance / Principles www. landlab.co.nz Queenstown Town Centre Public Realm Design Guidelines Version 7 14 June 2018 Page 006 B1 Design Guidance & Best Practice The Queenstown Town Centre

More information

Transit boulevard: A new road type for Sydney s Growth Centres

Transit boulevard: A new road type for Sydney s Growth Centres Transit boulevard: A new road type for Sydney s Growth Centres Cleaver, M. A., de Roos, M. P., NSW Centre for Road Safety, Roads and Traffic Authority, NSW Collins, G., Network Services, Roads and Traffic

More information

Contents Location Map Welcome and Introduction Travel Plan Management Science Park Accessibility Walking Cycling Bus Rail Car Sharing Contact Details

Contents Location Map Welcome and Introduction Travel Plan Management Science Park Accessibility Walking Cycling Bus Rail Car Sharing Contact Details Contents Contents Location Map Welcome and Introduction Travel Plan Management Science Park Accessibility Walking Cycling Bus Rail Car Sharing Contact Details 1 2 3 5 7 9 11 13 15 17 19 Thames Valley Science

More information

East Burke Transportation, Safety and Capacity Improvements

East Burke Transportation, Safety and Capacity Improvements East Burke Transportation, Safety and Capacity Improvements The purpose of this project is to increase mobility and improve safety for pedestrians, cyclists, and motor vehicles along VT Route 114 in the

More information

PUBLIC REALM MASTER PLAN

PUBLIC REALM MASTER PLAN WESTSHORE BUSINESS DISTRICT PUBLIC REALM MASTER PLAN MASTER PLAN COMMITTEE MEETING MARCH 20, 2013 WESTSHORE BUSINESS DISTRCT PUBLIC REALM MASTER PLAN MACRO-SCALE CONCEPT: A PUBLIC REALM FRAMEWORK DEFINED

More information

CHURCH ROAD. Public consultation document TELL US YOUR VIEWS.

CHURCH ROAD. Public consultation document TELL US YOUR VIEWS. CHURCH ROAD Public consultation document YOUR TELL US VIEWS www.enjoywalthamforest.co.uk CHURCH ROAD Introduction Waltham Forest Council was one of three boroughs to be awarded 27million of funding from

More information

CONNECTING PEOPLE TO PLACES

CONNECTING PEOPLE TO PLACES CONNECTING PEOPLE TO PLACES 82 EAST BENCH MASTER PLAN 07 Introduction The East Bench transportation system is a collection of slow moving, treelined residential streets and major arteries that are the

More information

Vision: Traditional hamlet with an attractive business/pedestrian friendly main street connected to adjacent walkable neighborhoods

Vision: Traditional hamlet with an attractive business/pedestrian friendly main street connected to adjacent walkable neighborhoods N D. Focus Area II Vision: Traditional hamlet with an attractive business/pedestrian friendly main street connected to adjacent walkable neighborhoods Transit Road Focus Area II is located in the Hamlet

More information

2. NORTEL CARLING CAMPUS EXPANSION - PROPOSED MODIFICATIONS TO MOODIE DRIVE (REGIONAL ROAD 59) AND HIGHWAY 417 INTERCHANGE

2. NORTEL CARLING CAMPUS EXPANSION - PROPOSED MODIFICATIONS TO MOODIE DRIVE (REGIONAL ROAD 59) AND HIGHWAY 417 INTERCHANGE 2. NORTEL CARLING CAMPUS EXPANSION - PROPOSED MODIFICATIONS TO MOODIE DRIVE (REGIONAL ROAD 59) AND HIGHWAY 417 INTERCHANGE COMMITTEE RECOMMENDATIONS AS AMENDED That Council approve: 1. The endorsement

More information

Active Transportation Facility Glossary

Active Transportation Facility Glossary Active Transportation Facility Glossary This document defines different active transportation facilities and suggests appropriate corridor types. Click on a facility type to jump to its definition. Bike

More information

Complete Streets for Niagara A working method to visualize the creation of a complete street June 20th, 2013

Complete Streets for Niagara A working method to visualize the creation of a complete street June 20th, 2013 Complete Streets for Niagara A working method to visualize the creation of a complete street June 20th, 2013 C O N T E N T S Introduction and background of the report What is a complete street? What can

More information

Yorkhill & Kelvingrove Community Council Cycling Village Proposal. Yorkhill Kelvingrove Cycling Village (1.3)

Yorkhill & Kelvingrove Community Council Cycling Village Proposal. Yorkhill Kelvingrove Cycling Village (1.3) Yorkhill Kelvingrove Cycling Village (1.3) 1) Introduction In recent years our community has been transformed. We have seen additional student and residential accommodation constructed. The redevelopment

More information

TRANSPORTATION COMMISSION Agenda Staff Report

TRANSPORTATION COMMISSION Agenda Staff Report TRANSPORTATION COMMISSION Agenda Staff Report Agenda Item No. 5.a DATE: JULY 31, 2014 TO: FROM: SUBJECT: TRANSPORTATION COMMISSION COMMUNITY DEVELOPMENT DEPARTMENT - PLANNING DRAFT OLYMPIC CORRIDOR PREFERRED

More information

Ajax: The Road to Complete Streets

Ajax: The Road to Complete Streets Ajax: The Road to Complete Streets Hubert Ng, Senior Transportation Planner Elysia Leung, Transportation Demand Management Coordinator Complete Streets Forum October 1, 2015 Overview 1 2 Introduction to

More information

High frequency bus services operating to Little Island; Creation of a new Park and Ride site and train station at North Esk;

High frequency bus services operating to Little Island; Creation of a new Park and Ride site and train station at North Esk; Cork County Council 7 th December 2018 Dear Adrian O Neill (aoneill@jbbarry.ie) The Transport and Mobility Forum, Cork (TMF) is a representative group of organisations who have a common interest in sustainable

More information

GLEN EIRA CITY COUNCIL. MURRUMBEENA Transforming our neighbourhood together our concepts based on your ideas

GLEN EIRA CITY COUNCIL. MURRUMBEENA Transforming our neighbourhood together our concepts based on your ideas GLEN EIRA CITY COUNCIL MURRUMBEENA Transforming our neighbourhood together our concepts based on your ideas 1 WHAT HAVE WE HEARD? WHAT NOW? Stage one Tell us what you love about your shopping strip November

More information

TRANSPORT AND MOVEMENT

TRANSPORT AND MOVEMENT TRANSPORT AND MOVEMENT Movement Strategy Public Transport Cycling and Walking Road Network Parking Standards Transport Impact Assessments Traffic Management Policies DRAFT POOLBEG PLANNING SCHEME Movement

More information

Pocatello Regional Transit Master Transit Plan Draft Recommendations

Pocatello Regional Transit Master Transit Plan Draft Recommendations Pocatello Regional Transit Master Transit Plan Draft Recommendations Presentation Outline 1. 2. 3. 4. What is the Master Transit Plan? An overview of the study Where Are We Today? Key take-aways from existing

More information

Southside Pilot Proposal

Southside Pilot Proposal To improve bicycle access and mobility to UC Berkeley, Downtown Berkeley, and the Southside area, a pilot project could include a two-way parking-protected cycle track. Turn pockets and island bus stops

More information

Newcastle Racecourse Masterplan. 1 Introduction. Completing the vision of a redeveloped Newcastle Racecourse Welcome to our exhibition.

Newcastle Racecourse Masterplan. 1 Introduction. Completing the vision of a redeveloped Newcastle Racecourse Welcome to our exhibition. 1 Introduction Completing the vision of a redeveloped Newcastle Racecourse Welcome to our exhibition. Please take a look at our information boards and feel free to ask members of the project team any questions

More information

FONTAINE AVENUE STUDY Final Report

FONTAINE AVENUE STUDY Final Report FONTAINE AVENUE STUDY Final Report March 28, 2005 FONTAINE AVENUE STUDY City of Charlottesville March 28, 2005 Renaissance Planning Group Kenneth Schwartz, FAIA, AICP Director of Design Leigh Wilkerson,

More information

APPENDIX A: Complete Streets Checklist DRAFT NOVEMBER 2016

APPENDIX A: Complete Streets Checklist DRAFT NOVEMBER 2016 APPENDIX A: Complete Streets Checklist DRAFT NOVEMBER 2016 Complete Streets Checklist MetroPlan Orlando s Complete Streets Checklist is an internal planning tool for staff to further implementation of

More information

4 DISRUPTION MANAGEMENT PLAN HIGHWAY 7 RAPIDWAY CONSTRUCTION BETWEEN BAYVIEW AVENUE AND WARDEN AVENUE TOWNS OF MARKHAM AND RICHMOND HILL

4 DISRUPTION MANAGEMENT PLAN HIGHWAY 7 RAPIDWAY CONSTRUCTION BETWEEN BAYVIEW AVENUE AND WARDEN AVENUE TOWNS OF MARKHAM AND RICHMOND HILL 4 DISRUPTION MANAGEMENT PLAN HIGHWAY 7 RAPIDWAY CONSTRUCTION BETWEEN BAYVIEW AVENUE AND WARDEN AVENUE TOWNS OF MARKHAM AND RICHMOND HILL The Transportation Services Committee recommends the adoption of

More information

CURRENT ORIGINAL REFERENCE SECTIONS. (Typical Section) (Typical Section) The Parade Island Bay : Concept Option Summary Sheets.

CURRENT ORIGINAL REFERENCE SECTIONS. (Typical Section) (Typical Section) The Parade Island Bay : Concept Option Summary Sheets. ORIGINAL (Typical Section) CURRENT (Typical Section) 3,900 3,000 2,000 1,500 3,100 1,600 3,100 1,500 2,000 2,500 3,900 3,000 1,800 600 2,000 3,000 3,000 2,000 600 1,800 2,500 Existing Planting Traffic

More information

MOBYCON. week) rather than average volumes. 5 Decision Tools

MOBYCON. week) rather than average volumes. 5 Decision Tools 5 Decision Tools Determining which tools and strategies are most context appropriate is often the most challenging component of integrating modes successfully. As the University of Victoria has many pedestrian

More information

Memorandum. Sunday, July 13, Saturday, July 19, 2014

Memorandum. Sunday, July 13, Saturday, July 19, 2014 Memorandum To: David Lowin, Brooklyn Bridge Park Corporation From: Daniel Schack, AICP, PTP Date: Re: Brooklyn Bridge Park Pier 5/6 Loop Road Traffic Study Project No: 14-01-2407 At the request of Brooklyn

More information

Welcome. Welcome to the second open house on the Downtown Transportation Study.

Welcome. Welcome to the second open house on the Downtown Transportation Study. Welcome 1 Welcome to the second open house on the Downtown Transportation Study. The purpose of this meeting is to: Recap the study objectives Summarize feedback to date Present information on the alternatives

More information

Ocean Park Boulevard Green Street Project Alternatives & Trade Offs

Ocean Park Boulevard Green Street Project Alternatives & Trade Offs Planning Commission March 4, 2009 Ocean Park Boulevard Green Street Project Alternatives & Trade Offs Purpose of Tonight s Meeting Review concept plans and options Provide input on alternatives and trade-offs

More information

Chapter 3: Multi-Modal Circulation and Streetscapes

Chapter 3: Multi-Modal Circulation and Streetscapes CHAPTER 3: MULTI-MODAL CIRCULATION AND STREETSCAPES Chapter 3: Multi-Modal Circulation and Streetscapes Overview Streetscape improvements have already been completed for Depot Street between Main Avenue

More information

5 Circulation & Parking

5 Circulation & Parking 5 Circulation & Parking Downtown Parking & Circulation Strategy. Downtown Wayne has a somewhat disconnected system of local public streets to connect downtown with the residential neighborhoods, and primary

More information

1 st and 2 nd Street Couplet FAQ s

1 st and 2 nd Street Couplet FAQ s 1 st and 2 nd Street Couplet FAQ s Q. Will the proposed roundabout at Flume/2nd/1 st Streets affect access to businesses nearby?... 2 Q. What if the project isn t received well by the community after construction?...

More information

US 41 COMPLETE STREETS CORRIDOR PLANNING STUDY from University Parkway to Whitfield Avenue

US 41 COMPLETE STREETS CORRIDOR PLANNING STUDY from University Parkway to Whitfield Avenue 41 US 41 COMPLETE STREETS CORRIDOR PLANNING STUDY from University Parkway to Whitfield Avenue EXECUTIVE SUMMARY DRAFT FEBRUARY 2019 Project Overview The US 41 Complete Streets Corridor Planning Study,

More information

Monroe Street Reconstruction Business Focus Group Notes July 18, 2016, HotelRED

Monroe Street Reconstruction Business Focus Group Notes July 18, 2016, HotelRED Monroe Street Reconstruction Business Focus Group Notes July 18, 2016, HotelRED Total participants: 31 Focus Group Conversation #1: During this exercise, participants talked in small table groups in response

More information

Frascati Road and Temple Hill Route Improvements. Outline Design Report to Accompany Public consultation

Frascati Road and Temple Hill Route Improvements. Outline Design Report to Accompany Public consultation Frascati Road and Temple Hill Route Improvements Outline Design Report to Accompany Public consultation September 2013 Background: Dún Laoghaire-Rathdown is committed to providing high quality pedestrian

More information

Outreach Approach RENEW SF served as the primary liaison with the North Beach community; the Chinatown. Executive Summary

Outreach Approach RENEW SF served as the primary liaison with the North Beach community; the Chinatown. Executive Summary Executive Summary Executive Summary The Columbus Avenue Neighborhood Transportation Study s objective is to identify changes to transportation infrastructure and policies that could enhance the livability

More information

15 April CAMPUS MASTER PLAN UPATE F o c us G r o up M o b ility

15 April CAMPUS MASTER PLAN UPATE F o c us G r o up M o b ility 15 April 2016 CAMPUS MASTER PLAN UPATE F o c us G r o up M o b ility AGENDA What We Heard Campus Framework & Open Space Network Mobility Approach Supporting the Pedestrian Environment Mobility & Sustainability

More information

ARLINGTON COUNTY, VIRGINIA

ARLINGTON COUNTY, VIRGINIA ARLINGTON COUNTY, VIRGINIA County Board Agenda Item Meeting of October 15, 2016 DATE: October 7, 2016 SUBJECT: Adoption of amendments to the Master Transportation Plan (MTP) to create a new Pedestrian

More information

Durham Region Long Term Transit Strategy

Durham Region Long Term Transit Strategy Durham Region Long Term Transit Strategy An adaptive, safe, reliable, frequent, accessible and desirable transit system that shapes and connects Durham Region and beyond in an economically and environmentally

More information