CASE STUDY OXLEY HIGHWAY SLIP STABILISATION

Size: px
Start display at page:

Download "CASE STUDY OXLEY HIGHWAY SLIP STABILISATION"

Transcription

1 MAY 2015 CASE STUDY OXLEY HIGHWAY SLIP STABILISATION IRF & ROADS AUSTRALIA REGIONAL CONFERENCE ASIA AND AUSTRALASIA DR SUDAR ARYAL

2 LOCATION STOPPING BAY, OXLEY HIGHWAY 2 Armidale Nambucca Heads Tamworth Kempsey Port Macquarie The site Stopping Bay

3 CONTENT OF PRESENTATION 3! Project overview! Project/design requirements! Site conditions, challenges, design! Progress in construction! Conclusion! Questions

4 PROJECT BACKGROUND AND ISSUES 4 Tamworth Armidale Stopping Bay Nambucca Heads Kempsey Port Macquarie! Oxley Hwy originally existed since 1840 as a rural track, and from1935 exists as a road in its current alignment! Section through Stopping Bay upgraded/widened in 1963! Now Oxley Hway a major regional road with busy traffic! At the slip site, it is a single lane two way road section! Slip occurred on high and steep downhill slope after 2013 rainfall

5 5 PROJECT BACKGROUND AND ISSUES Source: Coffey report, 2013

6 PROJECT/DESIGN REQUIREMENTS 6! Reinstate slope to maintain the existing width of travel lanes as a minimum! Provide min 500mm clearance from the edge line to the safety barrier and 1m from the barrier to the crest of slope! Slope stability factor of safety >1.3 (long term), desirable 1.5! Design life, 50 years, desirable 100 years! Minimise earthworks where possible! At least one lane to be kept open for traffic.

7 SITE CONDITIONS 7! Regional geology Siliceous and argilitic rocks belonging to Woolomin Beds of Ordovician to Devonian Age, some serpentine bearing rocks associated with a NW striking fault structure. Therefore, naturally occurring asbestos (NOA) may be present in the area Source: Preliminary Geotechnical Assessment of Oxley Highway Sites, Coffey Geotechnics, June 2013! Eastbound lane underlain by a layer of fill over colluvium which overlies bedrock. Several tension cracks present, mostly along the outer edge of road, open to 40mm and depth up to 1.4m, steeper and long downhill slope! Inclinometers showed movement at 3m below the edge of pavement and 1m at about the middle of the EB lane

8 SITE CONDITIONS 8! 4 boreholes! 2 inclinometers! 1 piezometer

9 9 DESIGN CONSTRAINTS AND CHALLENGES! Side cut with steep high cut batter on one side and steep long (>10m) downslope on the other side limiting access to the slope for construction works without significant earthworks! Established trees and vegetation on the slope! Single carriageway divided road with traffic flow in both direction! Narrow road sections requiring lane widening to maintain the standard lane width where required! Regional arterial road busy with traffic with no alternative viable detour options, hence, no possibility for complete closure for the road for construction! Traffic management issues during construction! Limited space for construction works and facilities during construction! Constraints on type and size of construction plant due to limited space and requirement to maintain traffic flow at all times! Possible presence of naturally occurring asbestos (NOA).

10 DESIGN 10! 3 rows of piles, 350mm 1.5m spacing! Pile length: 7m (back row), 8.5m (middle and front rows) with 150UC37.2 sections, socket 2m (min) into > M strength rock! 500mm x 500mm concrete capping beam on front and back rows connected with 200x150mm reinforced concrete tie! Back row anchored into competent rock under the road with soil nails.! Soil nails 2m (min) embedded into > M strength rock, 150mm diameter, N25 3m spacing! Design to AS5100

11 CONSTRUCTION PROGRESS 11 Stopping Bay: Steel sections delivered to site Stopping Bay: Slope stabilising concrete piles installed Stopping Bay: Far view of work area with construction in progress Photos courtesy of Roads and Maritime Services

12 CONSTRUCTION PROGRESS 12 Drilling rig used to drill pile holes WSP Parsons Brinckerhoff are currently doing similar design works for 4 individual sites along this highway just few hundred meters east of Stopping Bay

13 CONCLUSIONS 13! The design was developed to suit the project requirements and site constraints.! A number of factors including: - regular consultations with a prospective contractor, - close liaison with Roads and Maritime Services at all phases of design development, and - a rigorous independent review of the design resulted in the most effective and desired design outcomes.! This project demonstrates the benefits of the adopted interactive design process: - in achieving design and safety requirements - in managing whole of life costs while minimising impact on road users.

14 ACKNOWLEDGEMENTS 14 WSP Parsons Brinckerhoff would like to thank Roads and Maritime Services for permission to present this project at this conference

15 15 THANK YOU! Thank you

Design Criteria. Design Criteria

Design Criteria. Design Criteria F Design Criteria Design Criteria Ministry of Transportation Ministère des Transports DESIGN CRITERIA Page: 1 of 13 WORK PROJECT NO. N/A GO Bloomington Station TYPE OF PROJECT LOCATION Bloomington Road

More information

3. Types of foundation

3. Types of foundation Foundation Engineering CE 48. Types of foundation & foundation materials Contents Introduction Shallow Foundations Deep Foundations Introduction Why different types of? General types of Introduction Why

More information

Non-Motorized Overpass at SR 5/US1

Non-Motorized Overpass at SR 5/US1 Non-Motorized Overpass at SR 5/US1 And SR 97/SW th Street (Bird Road) Executive Summary March 9, 17 Prepared By: MARLIN Engineering Inc 17 NW th Avenue, Ste. 1 Plantation, FL 33313 P: 35.77.7575 www.marlinengineering.com

More information

(HIGHWAY GEOMETRIC DESIGN -1)

(HIGHWAY GEOMETRIC DESIGN -1) LECTURE HOUR-19 TE-1(10CV56) UNIT-3 (HIGHWAY GEOMETRIC DESIGN -1) Width of carriage way: Width of the carriage way or the width of the pavement depends on the width of the traffic lane and number of lanes.

More information

Perched Box Caisson Overview. January 2014

Perched Box Caisson Overview. January 2014 Perched Box Caisson Overview January 2014 Why perched box caissons? Perched box caissons are used to construct the portion of the river piers that will support the steel arch spans Construction can occur

More information

Road Safety Audit training course. Motorways - safety issues of the motorway design

Road Safety Audit training course. Motorways - safety issues of the motorway design Road Safety Audit training course Motorways - safety issues of the motorway design Jesper Mertner, Road safety auditor, COWI A/S 1 ROAD SAFETY AUDITING COURSE Content 1. Safety 2. Cross sections 3. Horizontal

More information

Right Sizing VE Studies CSVA Conference. Markham, ON October 27, BRIAN RUCK, P. Eng., C.V.S. AECOM Canada

Right Sizing VE Studies CSVA Conference. Markham, ON October 27, BRIAN RUCK, P. Eng., C.V.S. AECOM Canada Right Sizing VE Studies 2008 CSVA Conference Markham, ON October 27, 2008 BRIAN RUCK, P. Eng., C.V.S. AECOM Canada Presentation Outline Traditional VE Approach Key VE Principles Sample Projects Conclusion

More information

Federal Railroad Administration. HUDSON TUNNEL PROJECT: WEEHAWKEN COMMUNITY MEETING January 18, 2018

Federal Railroad Administration. HUDSON TUNNEL PROJECT: WEEHAWKEN COMMUNITY MEETING January 18, 2018 HUDSON TUNNEL PROJECT: WEEHAWKEN COMMUNITY MEETING January 18, 2018 Agenda Near Term Activity Hudson Tunnel Project Revisions to the Project to Address Community Concerns Description of Construction Activities

More information

section 4 Existing Conditions, Issues, and Options

section 4 Existing Conditions, Issues, and Options section 4 Existing Conditions, Issues, and Options 4.0 Existing Conditions, Issues, and Options This section analyzes each segment of the corridor on a street to street basis. Each segment is discussed

More information

GROUND ANCHOR LOAD TESTING REPORT FOR WHITE POINT SLOPE STABILIZATION, PASEO DEL MAR, SAN PEDRO DISTRICT, LOS ANGELES, CALIFORNIA

GROUND ANCHOR LOAD TESTING REPORT FOR WHITE POINT SLOPE STABILIZATION, PASEO DEL MAR, SAN PEDRO DISTRICT, LOS ANGELES, CALIFORNIA ALASKA CALIFORNIA COLORADO FLORIDA MISSOURI OREGON WASHINGTON WISCONSIN June 27, 2014 Mr. Gene Edwards Geotechnical Engineering Group Department of Public Works, City of Los Angeles 1149 S. Broadway, Suite

More information

Lyndale Drive Retaining Wall. Study. Public Meeting Registration: 6:00-6:30 Presentation and Discussion: 6:30-8:30 pm Tuesday, February 2 nd, 2016

Lyndale Drive Retaining Wall. Study. Public Meeting Registration: 6:00-6:30 Presentation and Discussion: 6:30-8:30 pm Tuesday, February 2 nd, 2016 Study Public Meeting Registration: 6:00-6:30 Presentation and Discussion: 6:30-8:30 pm Tuesday, February 2 nd, 2016 2 Welcome Thank you for attending tonight s public meeting for the Lyndale Drive Retaining

More information

To position power poles a safe distance from the road to minimise the likelihood of being accidentally hit by vehicles.

To position power poles a safe distance from the road to minimise the likelihood of being accidentally hit by vehicles. Policy Statement Subject Placement of Rigid Distribution Poles Along Roads With Speed Limits Exceeding 70KM/H Approved by Robert Rogerson Signature & Date Distribution Standards and Policy Manager Authorised

More information

Trans-Canada Highway 1 RW Bruhn Bridge Replacement

Trans-Canada Highway 1 RW Bruhn Bridge Replacement Trans-Canada Highway 1 RW Bruhn Bridge Replacement May 2016 RW Bruhn Bridge Project Objectives Improve safety, traffic flow and movement of goods Improve safety for pedestrians and cyclists Replace the

More information

Policy Statement. Objective. Context. References and Supporting Documentation

Policy Statement. Objective. Context. References and Supporting Documentation Policy Statement Subject Placement of Distribution Poles Along Roads With Speed Limits Not Exceeding 70km/h Approved by Robert Rogerson Signature & Date Distribution Standards and Policy Manager Authorised

More information

SITE S7: EMBANKMENT FAILURE WEST OF MILLARVILLE

SITE S7: EMBANKMENT FAILURE WEST OF MILLARVILLE LANDSLIDE RISK ASSESSMENT SOUTHERN REGION SITE S7: EMBANKMENT FAILURE WEST OF MILLARVILLE LEGAL LOCATION: LSD 4-3-21-4 W5M and 1-4-21-4 W5M REFERENCE LOCATION ALONG HIGHWAY The slide area is located between

More information

RURAL HIGHWAY SHOULDERS THAT ACCOMMODATE BICYCLE AND PEDESTRIAN USE (TxDOT Project ) June 7, Presented by: Karen Dixon, Ph.D., P.E.

RURAL HIGHWAY SHOULDERS THAT ACCOMMODATE BICYCLE AND PEDESTRIAN USE (TxDOT Project ) June 7, Presented by: Karen Dixon, Ph.D., P.E. RURAL HIGHWAY SHOULDERS THAT ACCOMMODATE BICYCLE AND PEDESTRIAN USE (TxDOT Project 0-6840) June 7, 2016 Presented by: Karen Dixon, Ph.D., P.E., TTI Team: Kay Fitzpatrick, Raul Avelar, & Subasish Das Project

More information

BARRIER OFFSET 0" A 6" 6" A 12" 12" A 26" A 26" 3A OR 4A L OR S * ** L OR S L OR S

BARRIER OFFSET 0 A 6 6 A 12 12 A 26 A 26 3A OR 4A L OR S * ** L OR S L OR S ACCEPTABLE (TCB) TYPES AND ANCHORING DETAILS BASED ON UNDERLYING SURFACE TYPE AND BARRIER OFFSET FROM DROP-OFF BARRIER OFFSET UNDERLYING SURFACE 0" A 6" 6" A 12" 12" A 26" A 26" TCB TYPE DETAIL TCB TYPE

More information

ENGINEERING DESIGN STANDARDS TO ENSURE ROAD SAFETY: EXPERIENCES FROM INDIA

ENGINEERING DESIGN STANDARDS TO ENSURE ROAD SAFETY: EXPERIENCES FROM INDIA ENGINEERING DESIGN STANDARDS TO ENSURE ROAD SAFETY: EXPERIENCES FROM INDIA Atul Kumar 1 ABSTRACT The primary goal of designing roads with adequate standards is to achieve a safer transport facility for

More information

PUSH PIER SYSTEMS STABILITY. SECURITY. INTEGRITY. Push Pier Systems PN #MBPPT

PUSH PIER SYSTEMS STABILITY. SECURITY. INTEGRITY. Push Pier Systems PN #MBPPT PUSH PIER SYSTEMS STABILITY. SECURITY. INTEGRITY. PN #MBPPT Push Pier Systems About Foundation Supportworks is a network of the most experienced and knowledgeable foundation repair and new construction

More information

INGHAM COUNTY ROAD DEPARTMENT AUSTIN E. CAVANAUGH ADMINISTRATION BUILDING 301 Bush Street, P.O. Box 38, Mason, MI

INGHAM COUNTY ROAD DEPARTMENT AUSTIN E. CAVANAUGH ADMINISTRATION BUILDING 301 Bush Street, P.O. Box 38, Mason, MI INGHAM COUNTY ROAD DEPARTMENT AUSTIN E. CAVANAUGH ADMINISTRATION BUILDING 301 Bush Street, P.O. Box 38, Mason, MI 48854-0038 March 27, 2018 William M. Conklin, P.E. Managing Director FOR IMMEDIATE RELEASE:

More information

Review of Guidelines for Cycleway Safety Fencing

Review of Guidelines for Cycleway Safety Fencing Review of Guidelines for Cycleway 1.0 PURPOSE 1.1 This document is meant to provide a review of available reference documents for determining appropriate fencing requirements for cycleway paths and shared

More information

Existing conditions of each bridge and repair plan are presented in Table

Existing conditions of each bridge and repair plan are presented in Table 2.2.2.5 Drainage Structure (1) Bridge Along the concerned section of this project road, there are 4 constructed bridges. The carriageway widths of existing bridges are designed to fit with existing road

More information

Peter Jansson - MDOT Bridge Field Services Tia Klein - Fishbeck, Thompson, Carr & Huber Peter MacAskill Hubbell, Roth & Clark, Inc.

Peter Jansson - MDOT Bridge Field Services Tia Klein - Fishbeck, Thompson, Carr & Huber Peter MacAskill Hubbell, Roth & Clark, Inc. Peter Jansson - MDOT Bridge Field Services Tia Klein - Fishbeck, Thompson, Carr & Huber Peter MacAskill Hubbell, Roth & Clark, Inc. Timeline July 2012 Wall movement reported Initial investigation and monitoring

More information

Item 404 Driving Piling

Item 404 Driving Piling Item Driving Piling 1. DESCRIPTION Drive piling. 2. EQUIPMENT 2.1. Driving Equipment. Use power hammers for driving piling with specified bearing resistance. Use power hammers that comply with Table 1.

More information

NOT TO SCALE PUBLIC WORKS STANDARD DETAILS CURB DETAILS DATE: MARCH 2013 FILE NAME: CURB.DWG

NOT TO SCALE PUBLIC WORKS STANDARD DETAILS CURB DETAILS DATE: MARCH 2013 FILE NAME: CURB.DWG NOT TO SCALE PUBLIC WORKS STANDARD DETAILS CURB DETAILS DATE: MARCH 2013 FILE NAME: CURB.DWG NOT TO SCALE PUBLIC WORKS STANDARD DETAILS SIDEWALK RAMPS DATE: MARCH 2013 FILE NAME: SIDEWALK RAMPS.DWG NOT

More information

Guide to Road Design Part 3: Geometric Design Session I 18 October 2016

Guide to Road Design Part 3: Geometric Design Session I 18 October 2016 Guide to Road Design Part 3: Geometric Design Session I 18 October 2016 Today s moderator Angela Racz Online Training Coordinator Knowledge Transfer - ARRB Group P: +61 3 9881 1694 E: training@arrb.com.au

More information

Road Markings. Lecture Notes in Transportation Systems Engineering. Prof. Tom V. Mathew

Road Markings. Lecture Notes in Transportation Systems Engineering. Prof. Tom V. Mathew Road Markings Lecture Notes in Transportation Systems Engineering Prof. Tom V. Mathew 1 Overview The essential purpose of road markings is to guide and control traffic on a highway. They supplement the

More information

FY 2006 TRANSPORTATION CAPITAL PROGRAM

FY 2006 TRANSPORTATION CAPITAL PROGRAM Eden Lane Bridge over Whippany River NS9908 The existing structure was built in 1972 as a temporary single-span structure. The bridge consists of simply supported steel acrow panel trusses and is supported

More information

Safence. Wire Rope Safety Barrier. Product Manual

Safence.  Wire Rope Safety Barrier. Product Manual Safence Wire Rope Safety Barrier Product Manual Safence is licensed to Ingal Civil Products by Blue Systems Inc. of Sweden www.ingalcivil.co.nz Safence Wire Rope Safety Barrier 1.0 Introduction The superior

More information

Transportation Knowledge

Transportation Knowledge FE REVIEW COURSE SPRING 2017 Transportation Engineering 4/26/2017 Transportation Knowledge 8-12 problems Traffic safety Traffic capacity Traffic flow theory Traffic control devices Transportation planning

More information

Geometric designs for Safe Highways. Dr. Manoj M. Asst. Professor Department of Civil Engineering IIT Delhi

Geometric designs for Safe Highways. Dr. Manoj M. Asst. Professor Department of Civil Engineering IIT Delhi Geometric designs for Safe Highways Dr. Manoj M. Asst. Professor Department of Civil Engineering IIT Delhi WORKSHOP-CUM-TRAINING PROGRAMME ON ROAD SAFETY 17th 21st September 2018 Outline Introduction Cross

More information

coolaroo.com Protection all year round Installing your new Coolaroo all weather sail is simple, following our step-by-step instructions.

coolaroo.com Protection all year round Installing your new Coolaroo all weather sail is simple, following our step-by-step instructions. Protection all year round Installing your new Coolaroo all weather sail is simple, following our step-by-step instructions. Features Provides 100% UV block Water resistant M ade with UV stabilised knitted

More information

Traffic Control Inspection Checklist Segment:

Traffic Control Inspection Checklist Segment: Traffic Control Inspection Checklist Segment: Simon Contractors Simon Contractors Originator: Description Reviewed by: Initials Date Distribution: Traffic Quality Manager, Site Assistant Traffic Manager

More information

FLEXIBLE AND RELIABLE ANCHORING

FLEXIBLE AND RELIABLE ANCHORING Spiral rope anchor and FLEX Head FLEXIBLE AND RELIABLE ANCHORING 1 THE SMARTER ANCHOR FLEXES. The flexibility of the whole system is crucial for both rockfall barriers and other protection systems. Why?

More information

Friday, May 20, :46 PM Cambria N Armstrong Fw: Wolf Creek REV.pdf

Friday, May 20, :46 PM Cambria N Armstrong Fw: Wolf Creek REV.pdf David Johnson From: Sent: To: Cc: Subject: Attachments: Thomas Malecek Friday, May 20, 2011 12:46 PM david@westerneco.com Cambria N Armstrong Fw: Wolf Creek 05-16-11 REV.pdf David,

More information

H8 Signs, Supports and Poles

H8 Signs, Supports and Poles Alberta Infrastructure and Transportation Roadside Design Guide November 2007 H8 Signs, Supports and Poles H8.1 Introduction This section identifies the appropriate roadside safety treatment for signs,

More information

IH 20 RANGER HILL PUBLIC MEETING

IH 20 RANGER HILL PUBLIC MEETING IH 20 RANGER HILL PUBLIC MEETING AUGUST 25, 2015 IH 20, Eastland County, TX CSJ 0007-06-084 IH 20 from 3.5 mi. East of LP 254 to SH 16 (Ranger Hill) August 25, 2015 Agenda Introductions Purpose of the

More information

VEHICLE CROSSING AND PEDESTRIAN CUTDOWN SET OUT

VEHICLE CROSSING AND PEDESTRIAN CUTDOWN SET OUT Crossing Width 0 min./5 max. - Residential Vehicle Crossing 0 min./7 max. - Commercial/Industrial Vehicle Crossing 1800 min./2400 Des. - Pedestrian Cut Down Crossing Width 0 min./5 max. - Residential 0

More information

Appendix A Guiding Principles for Cycling Safety in Work Zones

Appendix A Guiding Principles for Cycling Safety in Work Zones Appendix A Guiding Principles for Cycling Safety in Work Zones 1. Identify Existing Cycling Facility and Requirements This step should be part of the permitting/approval processes for construction zones

More information

WYDOT DESIGN GUIDES. Guide for. Non-NHS State Highways

WYDOT DESIGN GUIDES. Guide for. Non-NHS State Highways WYDOT DESIGN GUIDES Guide for Non-NHS State Highways 2014 GUIDE FOR Non-NATIONAL HIGHWAY SYSTEM (Non-NHS) STATE HIGHWAYS PRESERVATION REHABILITATION RECONSTRUCTION INTRODUCTION This Guide is directed to

More information

Fall Protection at the Top of the Quarry Face

Fall Protection at the Top of the Quarry Face Fall Protection at the Top of the Quarry Face November 2017 Regulation 9 of the Safety, Health and Welfare at Work (Quarries) Regulations 2008 requires the Operator to ensure, as regards that quarry, that

More information

MIRABAY PILOT PROJECT REPORT

MIRABAY PILOT PROJECT REPORT MIRABAY PILOT PROJECT REPORT 9/25/2014 By: Ingenium, Inc./Carl A. Hazenberg, P.E. Seawalls along the MiraBay canal system started experiencing problems shortly after construction. Following the issues,

More information

h o l l o w poles for foundat i o n s

h o l l o w poles for foundat i o n s TTT Products Limited Feb 2016. 1 of 6 The MultiPole advantage Introducing the TTT MultiPole an incredibly versatile pole due to its unique hollow core. The MultiPole is a multifunctional pole suitable

More information

The Challenge of Wave Scouring Design for the Confederation Bridge

The Challenge of Wave Scouring Design for the Confederation Bridge 13: Coastal and Ocean Engineering ENGI.8751 Undergraduate Student Forum Faculty of Engineering and Applied Science, Memorial University, St. John s, NL, Canada MARCH 2013 Paper Code. (13 - walsh) The Challenge

More information

h o l l o w poles for foundat i o n s

h o l l o w poles for foundat i o n s TTT Products Limited July 2017. 1 of 6 The MultiPole advantage The TTT MultiPole is an incredibly versatile pole due to its unique hollow core. The MultiPole is a multifunctional pole suitable for structural

More information

CASTLE CREEK CORRIDOR PLANNING PUBLIC OPEN HOUSE

CASTLE CREEK CORRIDOR PLANNING PUBLIC OPEN HOUSE CASTLE CREEK CORRIDOR PLANNING PUBLIC OPEN HOUSE Wednesday, November 15, 2017 AGENDA Project Background and Today s Goals Corridor Constraints and Conflicts Usage Information Public Process Schedule Review

More information

A465 Heads of the Valleys Dualling Sections 5 and 6 Dowlais Top to Hirwaun SUMMARY PROOF OF EVIDENCE. Highways Engineering Document WG 1.3.

A465 Heads of the Valleys Dualling Sections 5 and 6 Dowlais Top to Hirwaun SUMMARY PROOF OF EVIDENCE. Highways Engineering Document WG 1.3. A465 Heads of the Valleys Dualling Sections 5 and 6 Dowlais Top to Hirwaun SUMMARY PROOF OF EVIDENCE Highways Engineering Document WG 1.3.2 by Jonathan Thirkettle MARCH 2018 1. Introduction 1.1 I am Jonathan

More information

Road Markings. Lecture Notes in Transportation Systems Engineering. Prof. Tom V. Mathew. 1 Overview 1. 2 Classification 2

Road Markings. Lecture Notes in Transportation Systems Engineering. Prof. Tom V. Mathew. 1 Overview 1. 2 Classification 2 Road Markings Lecture Notes in Transportation Systems Engineering Prof. Tom V. Mathew Contents 1 Overview 1 2 Classification 2 3 Longitudinal markings 2 3.1 Center line.....................................

More information

Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1]

Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1] Check Dams DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1] [1] Though not generally considered

More information

DUNBOW ROAD FUNCTIONAL PLANNING

DUNBOW ROAD FUNCTIONAL PLANNING DUNBOW ROAD FUNCTIONAL PLANNING Final Report August 3, 216 #31, 316 5th Avenue NE Calgary, AB T2A 6K4 Phone: 43.273.91 Fax: 43.273.344 wattconsultinggroup.com Dunbow Road Functional Planning Final Report

More information

Route 47 (North Main Street) Reconstruction

Route 47 (North Main Street) Reconstruction TOWN OF SUNDERLAND Route 47 (North Main Street) Reconstruction Presented by Lou Rabito, P.E. Presented to Town of Sunderland June 11, 2018 Project Overview MassDOT Project No. 607245 Resurfacing and Related

More information

WYDOT DESIGN GUIDES. Guide for. NHS Arterial (Non-Interstate)

WYDOT DESIGN GUIDES. Guide for. NHS Arterial (Non-Interstate) WYDOT DESIGN GUIDES Guide for NHS Arterial (Non-Interstate) 2014 GUIDE FOR NATIONAL HIGHWAY SYSTEM (NHS) HIGHWAYS (NHS ARTERIALS, Non-Interstate) PRESERVATION REHABILITATION RECONSTRUCTION INTRODUCTION

More information

Grade-separation for cyclists includes cycling bridges and cycling tunnels, specially built for cyclists and possibly co-used by pedestrians.

Grade-separation for cyclists includes cycling bridges and cycling tunnels, specially built for cyclists and possibly co-used by pedestrians. Infrastructure Give Cycling a Push INFRASTRUCTURE/ INTERSECTIONS AND CROSSINGS GRADE SEPARATION Overview Gradeseparation for cyclists includes cycling tunnels and cycling bridges. These are safe and direct

More information

General References Definitions. (1) Design Guidance. (2) Supporting Information

General References Definitions. (1) Design Guidance. (2) Supporting Information Chapter 1240 Turning Roadways 1240.01 General 1240.02 References 1240.03 Definitions 1240.04 Turning Roadway Widths 1240.05 Documentation 1240.01 General The roadway on a curve may need to be widened to

More information

I-264 CORRIDOR EVALUATION STUDY. September 7, 2016 Eric Stringfield VDOT Planning Director Chris Lawrence AECOM Senior Transportation Engineer

I-264 CORRIDOR EVALUATION STUDY. September 7, 2016 Eric Stringfield VDOT Planning Director Chris Lawrence AECOM Senior Transportation Engineer I-264 CORRIDOR EVALUATION STUDY September 7, 2016 Eric Stringfield VDOT Planning Director Chris Lawrence AECOM Senior Transportation Engineer Study Overview Interchange Locations Study Context Follow-up

More information

Alberta Infrastructure HIGHWAY GEOMETRIC DESIGN GUIDE AUGUST 1999

Alberta Infrastructure HIGHWAY GEOMETRIC DESIGN GUIDE AUGUST 1999 Alberta Infrastructure HIGHWAY GEOMETRIC DESIGN GUIDE AUGUST 1999,1'(; A ACCELERATION Data on acceleration from stop D-29 Effects of grade D-35 Intersections D-97, D-99 Lanes D-97, F-5, F-7, F-15, F-21,

More information

BIT User Manual. 1. About this manual. 2. Know your BIT 1.1. WARNING System Components

BIT User Manual. 1. About this manual. 2. Know your BIT 1.1. WARNING System Components BIT User Manual About this manual WARNING Know your BIT System Components Operation Methods Maintenance, charging 3.3.1. Cleaning General handling Software Setup Calibrating the BIT Inclinometer calibration

More information

Slope Stabilization at Mt. Alberta View SE, Calgary, Alberta

Slope Stabilization at Mt. Alberta View SE, Calgary, Alberta Slope Stabilization at Mt. Alberta View SE, Calgary, Alberta Luis A. Martinez, Dennis E. Becker Golder Associates Ltd., Calgary, Alberta, Canada Victor Cui City of Calgary, Calgary, Alberta, Canada ABSTRACT

More information

Cycle traffic and the Strategic Road Network. Sandra Brown, Team Leader, Safer Roads- Design

Cycle traffic and the Strategic Road Network. Sandra Brown, Team Leader, Safer Roads- Design Cycle traffic and the Strategic Road Network Sandra Brown, Team Leader, Safer Roads- Design Highways England A Government owned Strategic Highways Company Department for Transport Road Investment Strategy

More information

ENGINEERING STANDARD FOR GEOMETRIC DESIGN OF ROADS AND STREETS ORIGINAL EDITION MAR. 1996

ENGINEERING STANDARD FOR GEOMETRIC DESIGN OF ROADS AND STREETS ORIGINAL EDITION MAR. 1996 ENGINEERING STANDARD FOR GEOMETRIC DESIGN OF ROADS AND STREETS ORIGINAL EDITION MAR. 1996 This standard specification is reviewed and updated by the relevant technical committee on Dec. 2000(1) and July.

More information

City of Sammamish. Welcome. Issaquah-Fall City Road Improvements Project Phase I Design: 242nd Avenue SE to Klahanie Drive SE

City of Sammamish. Welcome. Issaquah-Fall City Road Improvements Project Phase I Design: 242nd Avenue SE to Klahanie Drive SE Welcome Welcome to the third community meeting for the Issaquah-Fall City Road Improvements Project. AGENDA 6:00 p.m. Welcome and sign-in 6:10 p.m. Presentation 6:50 p.m. Open house Learn about the roadway

More information

FINAL REPORT. Yonkers Creek Migration Barrier Removal Project Wonderstump Road Del Norte County. Submitted By:

FINAL REPORT. Yonkers Creek Migration Barrier Removal Project Wonderstump Road Del Norte County. Submitted By: FINAL REPORT Yonkers Creek Migration Barrier Removal Project Wonderstump Road Del Norte County Submitted By: Del Norte County Community Development Department Yonkers Creek Migration Barrier Removal Project

More information

Safety Barrier System Acceptance Conditions SMART Steel Crash Cushion

Safety Barrier System Acceptance Conditions SMART Steel Crash Cushion Safety Barrier System Acceptance Conditions SMART Steel Crash Cushion The SMART Steel Crash Cushion is accepted for use on the New South Wales classified road network. The acceptance is based on the determination

More information

OCTOBER 2017 ISSUE Page 1 of 7

OCTOBER 2017 ISSUE Page 1 of 7 Field testing is performed on fully assembled pipelines for the purpose of determining pipeline acceptability. Following visual acceptance of joints and pipeline components, pressure pipelines in their

More information

Access Management Standards

Access Management Standards Access Management Standards Section 1: Application of Access Standards This chapter describes the Department's access management standards for access connections on the county roadway system. The standards

More information

Montgomery County Life Sciences Center Loop Trail

Montgomery County Life Sciences Center Loop Trail Montgomery County Life Sciences Center Loop Trail Advisory Committee Meeting #1 February 10, 2015 Agenda 1. Project Background 2. Existing Conditions Analysis 3. Examples from Elsewhere 4. Discussion Project

More information

The Use and Performance of Geogrids in Kentucky

The Use and Performance of Geogrids in Kentucky Transportation Kentucky Transportation Center Research Report University of Kentucky Year 2003 The Use and Performance of Geogrids in Kentucky Aric Cowne Richard Reitenour David L. Allen R. Clark Graves

More information

Kennedy Bridge - Summary of Pier 6 Movement Records

Kennedy Bridge - Summary of Pier 6 Movement Records KENNEDY BRIDGE - SUMMARY OF PIER 6 MOVEMENT RECORDS TECHNICAL MEMORANDUM Kennedy Bridge - Summary of Pier 6 Movement Records PREPARED FOR: COPY TO: MnDOT Dale Thomas / CH2M HILL File PREPARED BY: DATE:

More information

City of Roseville Section 13 Design Standards. _Bikeways January 2016 SECTION 13 BIKEWAYS

City of Roseville Section 13 Design Standards. _Bikeways January 2016 SECTION 13 BIKEWAYS SECTION 13 BIKEWAYS 13-1 GENERAL The City of Roseville bikeway standards are designed to insure that transportation and recreational bikeways are constructed in a manner that would provide a safe and comfortable

More information

DESIGN CODE. Enterprise West Harlow London Road North Design Code 21

DESIGN CODE. Enterprise West Harlow London Road North Design Code 21 DESIGN CODE Enterprise West Essex @ Harlow London Road North Design Code 21 4 MAXIMUM BUILDING HEIGHTS 4.1 Table 4A sets out maximum building height standards for each character area within the LDO boundary.

More information

Page 1 of 1 04/19/13 SBR

Page 1 of 1 04/19/13 SBR Office of Roadway Engineering - Plan Insert Sheets Number Title Date Number Title Date Number Title Date 201015 Extension of Anchor Bolts 07/20/12 207000 Bikeway Pavement Marking Details 01/18/13 202010

More information

Capital Beltway HOT Lanes Project

Capital Beltway HOT Lanes Project Some things can t wait for traffic Capital Beltway HOT Lanes Project New Travel Choices Ahead Some things can t wait for traffic Overview Two new lanes in each direction Carpool/HOV-3 lanes on the Beltway

More information

ROAD OCCUPANCY PERMIT APPLICATION # Damascus Township, 60 Conklin Hill Road, Damascus, PA Tel Fax

ROAD OCCUPANCY PERMIT APPLICATION # Damascus Township, 60 Conklin Hill Road, Damascus, PA Tel Fax Instructions: For a driveway access permit, fill in sections 1, 2, 3 and 4, and the appropriate drawings and sign. For a Utility access, fill in sections 1, 2, 3 and 5, and figures 1 and 3. Prepare a detailed

More information

STAKING TRAFFIC CONTROL SIGNAL SYSTEMS

STAKING TRAFFIC CONTROL SIGNAL SYSTEMS Locating the components of a traffic control signal is not an exact science; many factors influence the location of the components. These factors include: lane widths, radii, pedestrian curb ramp requirements,

More information

Suction anchor foundations for tension and taut leg floaters in deep waters. Tension Leg Platform. Taut Leg Platform. upper chain. risers.

Suction anchor foundations for tension and taut leg floaters in deep waters. Tension Leg Platform. Taut Leg Platform. upper chain. risers. Case history: Soil investigation for offshore suction anchors anchor foundations for tension and taut leg floaters in deep waters Alternative anchors for floating structures pile Over last 5 - years anchoring

More information

PROJECT NO. 093 MA 199 H C. FEDERAL NO. xxxx WIKIEUP-WICKENBURG-PHOENIX HIGHWAY TEGNER STREET, ALTERNATIVE 10 PROJECT IMPROVEMENT

PROJECT NO. 093 MA 199 H C. FEDERAL NO. xxxx WIKIEUP-WICKENBURG-PHOENIX HIGHWAY TEGNER STREET, ALTERNATIVE 10 PROJECT IMPROVEMENT PROJECT NO. 093 MA 199 H 5807 01C FEDERAL NO. xxxx WIKIEUP-WICKENBURG-PHOENI HIGHWAY TEGNER STREET, ALTERNATIVE 10 PROJECT IMPROVEMENT (INTERSECTION IMPROVEMENT) US 93/US 60 FINAL PROJECT ASSESSMENT April

More information

DESIGN MEMORANDUM WITH DESIGN EXCEPTIONS SP SP

DESIGN MEMORANDUM WITH DESIGN EXCEPTIONS SP SP DRAFT NOT FINAL (Note: document was not finalized due to an eastbound stopping site distance design issue that requires more detailed bridge and roadway design considerations. This discussion starts on

More information

ENGINEERING AND PUBLIC WORKS. Transportation Improvements: Santa s Village Road (MR15) Public Meeting

ENGINEERING AND PUBLIC WORKS. Transportation Improvements: Santa s Village Road (MR15) Public Meeting ENGINEERING AND PUBLIC WORKS Transportation Improvements: Santa s Village Road (MR15) Public Meeting March 22, 2018 Agenda Welcome and Introductions Fred Jahn: Commissioner of Engineering and Public Works

More information

APPENDIX L: COST ESTIMATING TOOLS

APPENDIX L: COST ESTIMATING TOOLS APPENDIX L: COST ESTIMATING TOOLS Rural Arterial From LRE MOT * Mobilization * Subtotal Scope Contingency (25%) Total PE Design (15%) CEI (15%) Total Project ** New (2-Lane Roadway) with 5' Paved Shoulders

More information

(Revised February,2005) CULVERTS, BRIDGES, AND FORDS

(Revised February,2005) CULVERTS, BRIDGES, AND FORDS GUIDE TO STREAM CROSSINGS (Revised February,2005) CULVERTS, BRIDGES, AND FORDS Culverts, bridges, and fords are all methods used to cross-streams. Culverts are the most common stream crossing structure.

More information

Ancholt Bolt Design With Tension and Shear Using Anchor Reinforcement

Ancholt Bolt Design With Tension and Shear Using Anchor Reinforcement Page 1 of 8 ANCHOR BOLT DESIGN Combined Tension and Shear Result Summary Anchor Rod Embedment, Spacing and Edge Distance OK Min Rquired Anchor Reinft. Development Length ratio = 0.87 OK Overall ratio =

More information

FINALIZATION OF THE HAND DUG WELL. Version : April 2009 Published by : Foundation Connect International Autors : Henk Holtslag & John de Wolf

FINALIZATION OF THE HAND DUG WELL. Version : April 2009 Published by : Foundation Connect International Autors : Henk Holtslag & John de Wolf ST 1.6 FINALIZATION OF THE HAND DUG WELL Version : April 2009 Published by : Foundation Connect International Autors : Henk Holtslag & John de Wolf Disclaimer This manual is part of the main manual, named

More information

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Projects

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Projects Barclay Street Viaduct NS9807 NS9807 This project will provide for the rehabilitation of the Barclay Street Viaduct, from Route 19 to Marshall Street, in order to increase the weight load of the structure.

More information

Updated There is no park access points beyond the limit of the phase I work. roadway to be constructed Viewport has been along full limits of the park

Updated There is no park access points beyond the limit of the phase I work. roadway to be constructed Viewport has been along full limits of the park The signs will be installed as Temporary signs the color (Orange/White) have been added to the plans. Need to specify color to be used for stripes. Closures that may be in place for extended periods need

More information

WORK ZONE TRAFFIC CONTROL PROCEDURES AND GUIDELINES FOR SCDOT MAINTENANCE ACTIVITIES

WORK ZONE TRAFFIC CONTROL PROCEDURES AND GUIDELINES FOR SCDOT MAINTENANCE ACTIVITIES WORK ZONE TRAFFIC CONTROL PROCEDURES AND GUIDELINES FOR SCDOT MAINTENANCE ACTIVITIES April 1, 2017 WORK ZONE TRAFFIC CONTROL PROCEDURES AND GUIDELINES FOR SCDOT MAINTENANCE ACTIVITIES Table of Contents

More information

ANGLO AMERICAN S OPEN CUT COAL MINES IN AUSTRALIA. John Hoelle Ismet Canbulat

ANGLO AMERICAN S OPEN CUT COAL MINES IN AUSTRALIA. John Hoelle Ismet Canbulat A RISK RATING SYSTEM FOR ANGLO AMERICAN S OPEN CUT COAL MINES IN AUSTRALIA John Hoelle Ismet Canbulat ANGLO AMERICAN PLC Anglo American Metallurgical Coal is a wholly owned subsidiary of Anglo American

More information

Contents Threadbar anchors

Contents Threadbar anchors Threadbar Anchors Contents THREADBAR Anchors THREADBAR Anchor System... 4 Design Considerations... 5 THREADBAR System for Bar Anchors... 6 THREADBAR Anchors with Double Corrosion Protection (DCP)... 7

More information

Chapter III Geometric design of Highways. Tewodros N.

Chapter III Geometric design of Highways. Tewodros N. Chapter III Geometric design of Highways Tewodros N. www.tnigatu.wordpress.com tedynihe@gmail.com Introduction Appropriate Geometric Standards Design Controls and Criteria Design Class Sight Distance Design

More information

Welcome. Smart motorway M1 junctions 13 to 16 public information exhibition. Highways England Creative [XXXXX_XXXX_XXX]

Welcome. Smart motorway M1 junctions 13 to 16 public information exhibition. Highways England Creative [XXXXX_XXXX_XXX] Welcome Smart motorway junctions 13 to 16 public information exhibition Smart motorways Smart motorways are a technology driven approach to the use of our motorways, increasing capacity and relieving congestion

More information

W-BEAM Traffic Barriers

W-BEAM Traffic Barriers W-BEAM Traffic Barriers GENERAL TECHNICAL CHARACTERISTICS The main purpose of steel w-beam traffic barriers is to improve highway safety and to reduce the severity of accidents. Tecnovial w-beam traffic

More information

JAP Additional Information Sheet

JAP Additional Information Sheet JAP Additional Information Sheet Block 15: Purpose and Need The USACE purpose of the project is to provide a safe and reliable whitewater park for the recreational public in a city park, which will provide

More information

INDEX. Geometric Design Guide for Canadian Roads INDEX

INDEX. Geometric Design Guide for Canadian Roads INDEX Acceleration lane, see Lanes, Acceleration Access, 8.1 Access Management and Functional Classification 8.2 Access Management by Design Classification 8.3 Access Configuration 8.4 Building Set-Back Guidelines

More information

LAMINATED POLES. engineered to solve problems. Coastal Douglas-fir. Field Raked and Tangent Poles

LAMINATED POLES. engineered to solve problems. Coastal Douglas-fir. Field Raked and Tangent Poles Coastal Douglas-fir Field Raked and Tangent Poles LAMINATED POLES engineered to solve problems 1 Design Criteria Submission Form You can either fax this information to 253-627-4188 or submit your drawings

More information

TRANSPORTATION FACILITY PLANNING Waugh Chapel Road Maytime Drive to New Market Lane

TRANSPORTATION FACILITY PLANNING Waugh Chapel Road Maytime Drive to New Market Lane July 24, 2018 TRANSPORTATION FACILITY PLANNING Waugh Chapel Road Maytime Drive to New Market Lane DPWandYOU.com Making a difference, together Meeting Agenda Purpose of the project Overview of work conducted

More information

CONSTRUCTION SPECIFICATION

CONSTRUCTION SPECIFICATION CAPRICORN MUNICIPAL DEVELOPMENT GUIDELINES CONTROL OF TRAFFIC C201 CONSTRUCTION SPECIFICATION CAPRICORN MUNICIPAL DEVELOPMENT GUIDELINES C201 ISSUE: NO:1 October 2007 TABLE OF CONTENTS CLAUSE CONTENTS

More information

Mitigation of Abandoned Mine Entries at Swanbank Enterprise Development, Ipswich, Australia

Mitigation of Abandoned Mine Entries at Swanbank Enterprise Development, Ipswich, Australia Mitigation of Abandoned Mine Entries at Swanbank Enterprise Development, Ipswich, Australia 10 th Interstate Technical Group on Abandoned Underground Mines Workshop Harrisonburg, VA David L Knott, PE,

More information

Morphodynamics of Borssele Wind Farm Zone

Morphodynamics of Borssele Wind Farm Zone Morphodynamics of Borssele Wind Farm Zone Meeting Tender Borssele Hendrik Jan Riezebos Tommer Vermaas Robert Hasselaar Tim Raaijmakers 17 November 2014, SER Den Haag Contents of presentation Introduction

More information

Identification on Unknown Bridge Foundations Using Geophysical Inspecting Methods

Identification on Unknown Bridge Foundations Using Geophysical Inspecting Methods More Info at Open Access Database www.ndt.net/?id=18258 Identification on Unknown Bridge Foundations Using Geophysical Inspecting Methods Helsin WANG 1, Chih-Hsin HU 2 1 Institute of Bridge Engineering,

More information

LOS ANGELES COUNTY FIRE DEPARMENT APPARATUS OPERATOR 1C TILLERED EMERGENCY VEHICLE OPERATIONS

LOS ANGELES COUNTY FIRE DEPARMENT APPARATUS OPERATOR 1C TILLERED EMERGENCY VEHICLE OPERATIONS LOS ANGELES COUNTY FIRE DEPARMENT APPARATUS OPERATOR 1C TILLERED EMERGENCY VEHICLE OPERATIONS Los Angeles County Fire Dept. RODEO EXERCISES 1 FORWARD STOP / STRAIGHT LINE BACKING The driver and tiller

More information

CENGRS GEOTECHNICA PVT. LTD. Job No Sheet No. 1

CENGRS GEOTECHNICA PVT. LTD. Job No Sheet No. 1 CENGRS GEOTECHNICA PVT. LTD. Job No. 214030 Sheet No. 1 INTERIM REPORT ON GEOTECHNICAL INVESTIGATION FOR PROPOSED 66 KV GRID PLOT AT G-7, DWARKA, NEW DELHI. 1.0 INTRODUCTION 1.1 Project Description M/s.

More information