LESSONS LEARNED AT THE TAUM SAUK REBUILD. Paul C. Rizzo, Ph.D., P.E. 1 Carl Rizzo 2 John Bowen 3 ABSTRACT INTRODUCTION

Size: px
Start display at page:

Download "LESSONS LEARNED AT THE TAUM SAUK REBUILD. Paul C. Rizzo, Ph.D., P.E. 1 Carl Rizzo 2 John Bowen 3 ABSTRACT INTRODUCTION"

Transcription

1 LESSONS LEARNED AT THE TAUM SAUK REBUILD Paul C. Rizzo, Ph.D., P.E. 1 Carl Rizzo 2 John Bowen 3 ABSTRACT The Authors served in key roles for the design and rebuild of the Dam for the Taum Sauk Rebuild Project between 2007 and Taum Sauk is the largest RCC Dam in the United States and has a symmetrical cross-section with conventional concrete faces upstream and downstream. The curvilinear shape and the cross-section presented a number of placement issues. In addition, a large number of Lessons were learned because of the rapid construction schedule, highly variable temperatures, highly confined working space, numerous details related to waterstops, construction joints and crest-to-gallery drains, foundation preparation, lift maturity, bedding mixes, crack repairs, and the conventional concrete upstream face. The authors discuss these issues from the perspective of the Designer, Construction Manager, and Contractor. INTRODUCTION The Taum Sauk Pump Storage Project is located in southeast Missouri in the central part of the USA. It is on the East Fork of the Black River, approximately 90 miles southwest of St. Louis, Missouri. It is a reversible pumped storage project used to supplement the generation and transmission facilities of AmerenUE, with 450-MW of capacity (Figure 1). The Project has an Upper Reservoir (Reservoir), originally designed as a concrete faced rockfill dam (CFRD) and a Lower Reservoir impounded by a concrete gravity Dam across the Black River. The Upper Reservoir impounding Dam is 6,562-ft long and kidney-shaped (Figure 2). Figure 1. Overall View of Taum Sauk Plant 1 President/CEO, Paul C. Rizzo Associates, Inc., Pittsburgh, PA 15235, Paul.Rizzo@rizzoassoc.com 2 Vice President of Construction Management, Paul C. Rizzo Associates, Inc., Pittsburgh, PA 15235, Carl.Rizzo@rizzoassoc.com 3 President, ASI Constructors, Inc., Pueblo West, CO 81007, john@asiconstructors.com

2 The original impounding CFRD was constructed with dumped rockfill, uncompacted but sluiced with monitors in an attempt to remove the fines. The Reservoir floor is generally at El ft and the 12-ft wide crest of the Dam is at El ft. A 10-fthigh, 1-ft-thick reinforced concrete Parapet Wall on the crest of the CFRD extended the maximum pool to El ft. The Upper Reservoir, which has no drainage area, was not designed with a spillway. Water fills the reservoir by pumping and direct rainfall. The powerhouse is located at the upstream end of the Lower Reservoir about 2 miles from the Upper Reservoir, in a narrow canyon through which a tailrace channel was excavated to connect to the Black River. A concrete and steel-lined shaft and tunnel connects the Powerhouse to the Upper Reservoir. The Taum Sauk Plant is a peaking and emergency reserve facility. A typical daily summer cycle involves generating power in the mid-morning by releasing water from the Upper Reservoir through the turbines to the Lower Reservoir, and pumping from the Lower Reservoir to the Upper Reservoir in the afternoon. In the fall, winter and spring, the plant typically generates once per day. The normal maximum level for the Upper Reservoir is El ft. Typically, the Upper Reservoir is drawn down less than 30 feet. A 30-foot drawdown represents 6 hours of single unit generation or 3 hours of double unit generation. The Upper Reservoir can be drawn down to El ft. without vortex problems at the morning glory outlet and to El ft. if only one turbine/generator unit is operating. The Project operates under the direction of the load dispatcher in St. Louis. Both units can be put on full load in a few minutes. The December 14, 2005 Incident Figure 2. Upper Reservoir at Taum Sauk At approximately 5:00 AM on December 14, 2005, the Upper Reservoir CFRD overtopped due to overpumping and the northwest corner of the CFRD breached over a width of approximately 700 feet, causing an uncontrolled, rapid release of water down the west slope of Proffit Mountain and into the East Fork of the Black River. An overall aerial view of the flow path is shown in Figure 3. The uncontrolled release flooded nearby Route N while truck traffic was underway, and produced significant property and environmental damage to the Johnson s Shut-Ins Campground.

3 Figure 3. Overall View of the Breached Dike Forensic Investigation and Root Cause Analysis A forensic investigation and root cause analysis of the failure was conducted under the direction of the lead Author to identify the failure mechanism and develop design parameters for a rebuild of the entire Upper Reservoir. Economic and technical analyses indicated remediation of the breach section was not practical. The investigation concluded that the original design of the CFRD in the early 1960 s was flawed and poor construction practices exacerbated the poor design and compromised the long-term integrity of the Dam. The details of the Forensic Investigation are available in ICOLD Meeting Proceedings (Brasilia, May 2009). NEW UPPER RESERVOIR DESIGN CRITERIA The Dam impounding the Upper Reservoir was rebuilt between October 2007 and April 2010 as an RCC Dam. Rapid, fast-track scheduling was employed to restore the operability of the Taum Sauk Project, a vital power source in the region. An aerial view of the new RCC Dam is shown in Figure 4. Figure 4. Aerial Photo of the New RCC Dam The new RCC Dam was constructed along the same alignment as the original CFRD. As the Upper Reservoir is founded on top of Proffit Mountain, it has no watershed. The Probable Maximum Flood (PMF) for the new RCC Dam is based on the rainfall on the reservoir surface. Therefore, the hydrologic and hydraulic criteria were defined

4 by two major factors: the elevation of the crest of the new RCC Dam (including freeboard), and the capacity of the proposed Overflow Release Structure (spillway). The overall design basis was to re-build the Upper Reservoir such that it would have the same storage capacity for power generation as the original Upper Reservoir with a normal pool and overall gross head, as established in the FERC License for the Taum Sauk Project. The original design of the Upper Reservoir did not include an overflow release structure to deal with an accidental over-pumping during the pumping mode of operation. On the other hand, the re-built Upper Reservoir includes an Overflow Release Structure designed to operate if the water level in the Upper Reservoir rises more than 2 ft above the maximum normal operating level. The Overflow Release Structure is an integral part of the overall Dam design as redundancy to prevent overtopping. The new RCC Dam section shown in Figure 5 has a symmetrical cross-section to accommodate the relatively poor rock condition in the foundation a rhyolite intruded by granite dikes with considerable thermal alteration which resulted in clay seams and weathered dikes at depth. These conditions led to considerable concern with sliding stability, especially under seismic conditions. Figure 5. Critical Design Section Consequently, each 100 ft cross section of the Dam was carefully examined and the base was adjusted so that the maximum foundation slope was 10 degrees or flatter and the foundation rock was cleared and cleaned of all clay seams and weathered dikes within a 30 ft interval beneath the Dam. Based on two-dimensional and threedimensional stability analyses, poor rock was removed to a depth of at least 30 ft below the dam/rock interface. The rock surfaces sloping between 10 degrees and 25 degrees were excavated to achieve an average slope of 10 degrees or less. As shown in Figure 5, Station was identified as the critical design section because it has the greatest height at the toe.

5 LESSONS LEARNED DURING CONSTRUCTION OF THE RCC DAM Because of the size of the new RCC Dam (largest in the USA at 2.8 million yd 3 ), the poor rock conditions and the rapid construction schedule, a number of lessons were learned (or relearned!) during construction at Taum Sauk. We summarize a few of these below: Foundation Preparation As mentioned previously, the foundation preparation work was intensive and comprehensive at Taum Sauk as illustrated in Figures The lessons learned from these photos are summarized as follows: The time and cost of foundation preparation is difficult to estimate and varies with each project as the predictability of conditions is exceptionally difficult. The use of pressurized water guns mounted on small excavators and long reach vacuum truck hoses are major time savers, are much safer for craftsmen to operate, and are significantly less strenuous for the craftsmen. Control of water associated with the cleaning operation and rainfall is a key factor to be addressed in planning the work. At Taum Sauk, the excavations always sloped downstream around the perimeter of the Dam foundation, making this aspect relatively easy to plan and execute. Foundation preparation needed to be a multiple shift operation in order to maintain schedule with a single shift RCC placement operation. Figure 6. New RCC Dam Typical Cross-section

6 Figure 7. Typical Foundation Preparation Rock Surface Excavation Figure 8. Typical Foundation Preparation Exposed Rock Surface Figure 9. RCC Placement at Rock Surface

7 Figure 10. RCC Placement at the Rock Surface Fines and Debris in the Rockfill Figure 11. Foundation Preparation Activities One of the fundamental tenets of the design of the new RCC Dam was the use of the rockfill from the old CFRD. The rock in the old CFRD was excavated and hauled to a crushing operation setup inside the perimeter of the Upper Reservoir where it was crushed and processed into an aggregate suitable for the Project RCC mix. We specified an aggregate with a maximum particle size of 1-1/2 inches and not more than 8% fines passing the No. 200 sieve. Also, we specified two stock piles of processed aggregate: one for plus 3/4 and one for minus 3/4. The lessons learned in processing the rockfill were basically two-fold: The percent fines after processing was significantly higher than anticipated. But based on the photo of the failed cross-section shown in Figure 12, we should have planned for this eventuality more comprehensively. Clearly Figure 12

8 Figure 12. North Side of the Breach shows a very high percentage of fines for a rockfill dam, indicating that the sluicing operation used during the original construction was not effective. The excavated rockfill contained pieces of steel left in the rockfill during the CFRD construction including teeth from dozer blades, pieces of sluicing pipe and drainage pipe, steel bolts, and other unrecognizable pieces of steel. These pieces of debris caused havoc with the crushing equipment and steel magnets had to be added to the system an expensive lesson learned and to be applied in future applications. Effect of Leaving RCC Lift Surfaces Exposed for Long Periods As mentioned above, the new RCC Dam has a perimeter of about 6800 ft. For construction planning and sequences, we divided the Dam into nine (9) monoliths, each having a length of about 700 ft to 800 feet, and each having about 100 RCC lifts approximately 1 foot thick. Monolith No. 2 was constructed from the foundation level at El 1500 ft up to El 1572 ft, 28 lifts short of the crest and left that particular lift surface exposed to the weather and equipment tracking for about a year or slightly longer to allow for stockpiling of aggregate against the upstream face. When work was resumed in that area, the exposed RCC lift surface was freshly cut and prepared in accordance with normal practice but nothing special was done to the 3 ft thick facing concrete (CVC). The lessons learned from this experience are as follows: Even with our extensive RCC batching operation, elaborate combined conveyortruck transport system, and extended working shifts (12 hours), we learned that a lift surface having a length of 565 ft to 820 ft is about the maximum that can be used. Incidentally, it was incumbent upon the placement crew to place an RCC lift over the entire length of the monolith which meant occasional long shifts or short shifts as no intermediate transverse unplanned construction joints were allowed. We had designed the project with Construction Joints at 90 ft centers and therefore, in those instances where it was simply not possible to complete a lift over the entire length of the monolith, we simply stopped the

9 RCC placement at a planned Construction Joint (CJ), which included a waterstop and crest-to-gallery drain. The lift surface in Monolith 2 at El 1572 ft was a major source of leakage during the initial refill with seepage observed on the downstream face. This behavior indicated that water had penetrated the concrete facing (which had not be green cut or specially prepared) into the horizontal RCC lift joint and then traveled the entire width of the lift surface from the upstream face to the downstream face. During the first drawdown after refill, we went back into the Upper Reservoir and ran a seal of waterproofing material along the lift joint line at El 1572 ft for the entire length of the Monolith. This stopped the leakage entirely as shown below in Figure 13. The lesson learned here is that when one has a lift surface exposed to the elements for a long period of time, special treatment of both the RCC and the CVC on the upstream face is required, including conventional green cutting, extensive cleaning, bedding mix on the RCC and a bonding agent for the CVC on the face. Downstream Monolith 2 Crest-to-Gallery Drains Figure 13. Monolith Before and After Sealing At Taum Sauk, we drilled the Crest-to-Gallery Drains from the Crest of the Dam down to the Gallery using a downhole hammer rig as opposed to either drilling upward from the gallery or forming the drains at each lift with a telescoping pipe. We found that drilling from the Crest led to drains that are significantly offset from the alignment of the Construction Joint/Waterstop and that they did not line up with the drainage trench in the gallery. The lesson learned here is that one simply cannot control the alignment of the Drain hole with adequate accuracy from the Crest-to- Gallery Drain to function as intended. These drains should be formed with telescoping pipe on each lift and not be drilled down from the Crest or up from the Gallery. Intermediate CJ s for the Upstream CVC Face The new RCC Dam at Taum Sauk includes a conventional sloping concrete face (CVC) designed to (1) protect the underlying RCC from weathering effects (the downstream face also has a stepped CVC Facing) and (2) provide a measure of

10 watertightness by preventing the water in the Reservoir from coming in direct contact with the upstream edge of a lift joint in the RCC. The RCC was designed with fullwidth Construction Joints (CJ s), including a waterstop, Crest-to-Gallery Drain, and plastic sheathing across the joint running from the upstream face to the downstream face. The 90-foot spacing of the CJ s was determined from a comprehensive thermal analysis. This same analysis indicated that intermediate CJ s in the concrete facing were required at 45 foot spacing. These CVC CJ s have a crack inducer plate and water stop only in the CVC and not in the RCC. The lesson learned here is that 90 ft spacing is too large, an observation that was made in our Construction Test pad early in the Project, but not taken into account when we laid out the CJ s for the first Monolith. During construction of the first Monolith, we quickly learned from the observed crack spacing that intermediate CJ s in the CVC face were required. We installed these with chamfered V notches, crack inducers and waterstops as shown in Figure 14. GIN Method for the Grout Curtain Figure 14. Waterstops at Monolith Joints The original CFRD at Taum Sauk had a short grout curtain for approximately 300 feet of the 6800 feet of perimeter. Generally, this was a single line construction with what we believe was a cement-bentonite mix. Judging from flow measurements at a downstream toe ditch, the grout curtain was not effective. The new RCC Dam was designed with foundation drains to the Gallery and a complete, two line grout curtain- - a belt and suspenders approach to minimize uplift on the gravity dam section and minimize leakage thought the fractured and jointed bedrock. We selected and implemented the GIN Method (Grouting Intensity Number) for constructing the Grout Curtain using the GIN curves coupled with a real time, computerized monitoring and control system. Layne GeoConstruction performed this work as a subcontractor. The lesson learned with the grouting program (actually learned again) is that the GIN Method is a valid and technically attractive approach for grouting in a controlled manner to virtually eliminate the potential for hydraulic fracturing while maximizing grout penetration. Setting the GIN parameters must be done in a careful step-by-step

11 manner, including some trial and error testing, to guard against hydrofracturing. The experience at Taum Sauk was exceptionally positive on this aspect of the Project. Water Stop Configuration As mentioned above, the primary CJ s at 90-foot centers and the intermediate CJ s at 22.5 foot spacing included a waterstop. As seen on Figure 14, the a plastic crack inducer sheet was attached to each waterstop on both sides in the case of the main CJ s to induce a crack in the CVC facing and in the RCC, but on the upstream side only on the intermediate CJ s to induce a crack in the CVC facing. The plastic inducer sheets were about 6 mm thick and fastened to the waterstops in the pre-formed ears at the centre shown in Figure 15. Figure 15. Original & Revised Waterstop Designs The waterstops for the CJ s in Monoliths 1 and 2 were of the original design in Figure 15 recommended by the supplier. With this design, we found that ears were not large enough or stiff enough to hold the plastic crack inducer sheet in place and movement occurred during RCC and CVC placement. The Revised Design shown in Figure 15 with the deeper and stiffer ears did not allow the inducer sheet to move even under rough placement conditions. A wider waterstop may also have been considered for better performance. The lesson learned here is that particular care should be taken with the waterstop detail design, and more specifically, the supplier should be challenged to assure performance under actual RCC placement conditions. RCC conditions tend to be more challenging than CVC placement conditions where reinforcing steel is available to tie off the waterstop. RCC Placement under Winter Conditions During the intense construction planning phase of the Project, we concluded that placing RCC during the winter months at Taum Sauk would be necessary to meet the schedule for completion. Winter conditions were assumed to be temperatures at the lower range of acceptability for RCC placement, less than 28 o F. We invoked the

12 following practices for RCC placement during the winter months (December through February): Place RCC on the day shifts only. Night shifts were used only for stripping and placing forms. Start placement in the morning when the temperature was at least 28 o F and predicted to rise and continue until the temperature began to drop back toward freezing. Monitor the lift surface continually with hand-held infrared thermal readers. Although there was a continuing debate as to whether the inspector should point the reader at the surface or to scratch the surface and read about 1 inch below the surface, we concluded that a surface reading was adequate and sufficient. We set the triggering temperature at freezing, provided the temperature was on the rise for approximately the next 8 hours. If the temperature was not expected to rise, we set the triggering temperature higher on a case by case basis. Immediately after placement and compaction, the lift surface should be covered with tarps. When starting a placement directly on rock, use heated thermal tarps placed on the rock surface for a few days in advance to raise the temperature of the rock surface. We left the downstream and upstream forms on the Monolith as long as practical and worked to strip the forms only on those days when the temperature was expected to be above about 35 o F. When this practice was not followed, we experienced cracking in the CVC facing due to thermal shock between the warm RCC on the inside face and cold air on the outside. The lesson learned here is that RCC can be successfully placed at or near freezing conditions with proper control. Production during the winter months was severely restrained because of the single shift operation and the lost days when the temperature never went higher than 28 o F. SUMMARY The Taum Sauk Rebuild Project is in many respects a milestone in the construction of RCC Dams. It is the largest RCC dam in the USA and is believed to be the largest symmetrical low-strength RCC Dam in the world. Because of its size, location on top of a mountain, difficult foundation conditions, and rapid construction schedule, many lessons were learned; a few of the more obvious and tangible are reported herein. We hope that the dam building profession will find these lessons helpful on future RCC Dam construction to allow for highly attractive technical solutions at lower cost.

Dams as Systems. Pat Regan Federal Energy Regulatory Commission (FERC)

Dams as Systems. Pat Regan Federal Energy Regulatory Commission (FERC) Dams as Systems Pat Regan Federal Energy Regulatory Commission (FERC) FERC >2,500 jurisdictional dams 770 feet to 0.5 feet high Five Regions Atlanta, Chicago, New York, Portland, San Francisco ~120 staff

More information

STRUCTURAL STABILITY ASSESSMENT

STRUCTURAL STABILITY ASSESSMENT STRUCTURAL STABILITY ASSESSMENT CFR 257.73(d) Fly Ash Reservoir II Cardinal Plant Brilliant, Ohio October, 2016 Prepared for: Cardinal Operating Company Cardinal Plant Brilliant, Ohio Prepared by: Geotechnical

More information

Huntington District. For More Information Contact (304)

Huntington District. For More Information Contact (304) Zoar Levee & Diversion Dam are located in the Muskingum River Basin highlighted in green to left. The Muskingum River Basin is the site of Ohio s first multiple purpose water management and land conservation

More information

Water Storage for Agriculture

Water Storage for Agriculture Water Storage for Agriculture Ted van der Gulik, P.Eng. Partnership for Water Sustainability in BC Water Storage Options Dam! usually constructed within a watercourse! must follow the dam safety regulation!

More information

HYDRAULIC JUMP AND WEIR FLOW

HYDRAULIC JUMP AND WEIR FLOW HYDRAULIC JUMP AND WEIR FLOW 1 Condition for formation of hydraulic jump When depth of flow is forced to change from a supercritical depth to a subcritical depth Or Froude number decreases from greater

More information

ANNUAL INSPECTION BY A QUALIFIED PROFESSIONAL ENGINEER ALL CCR IMPOUNDMENTS CCR Rule Section (b)

ANNUAL INSPECTION BY A QUALIFIED PROFESSIONAL ENGINEER ALL CCR IMPOUNDMENTS CCR Rule Section (b) ANNUAL INSPECTION BY A QUALIFIED PROFESSIONAL ENGINEER ALL CCR IMPOUNDMENTS ASBURY POWER PLANT 21133 Uphill Lane Asbury, Missouri 64832 January 18, 2017 EMPIRE DISTRICT ELECTRIC COMPANY Prepared by: Rachel

More information

USING A LABYRINTH WEIR TO INCREASE HYDRAULIC CAPACITY. Dustin Mortensen, P.E. 1 Jake Eckersley, P.E. 1

USING A LABYRINTH WEIR TO INCREASE HYDRAULIC CAPACITY. Dustin Mortensen, P.E. 1 Jake Eckersley, P.E. 1 USING A LABYRINTH WEIR TO INCREASE HYDRAULIC CAPACITY Dustin Mortensen, P.E. 1 Jake Eckersley, P.E. 1 Plum Creek Floodwater Retarding Structure No. 6 is located in an area of Kyle, Texas, that is currently

More information

Annex E Bridge Pier Protection Plan

Annex E Bridge Pier Protection Plan Annex E Bridge Pier Protection Plan Table E1 Bridge Types and Locations Table E2 Flow Conditions For River Sections Figure E1 Bridge Abutment Protection Figure E2 Bridge Pier Protection Figure E3 Central

More information

ITEM 400 STRUCTURAL EXCAVATION AND BACKFILL

ITEM 400 STRUCTURAL EXCAVATION AND BACKFILL AFTER MARCH 1, 2012 ITEM 400 STRUCTURAL EXCAVATION AND BACKFILL 400.1 Description. This item shall govern for all excavation required for the construction of all structures, except pipe or box sewers for

More information

HISTORY OF CONSTRUCTION

HISTORY OF CONSTRUCTION HISTORY OF CONSTRUCTION CFR 257.73(c)(1) West Boiler Slag Pond Clifty Creek Plant Madison, Indiana October, 2016 Prepared for: Indiana Kentucky Electric Corporation Prepared by: American Electric Power

More information

ANNUAL INSPECTION BY A QUALIFIED PROFESSIONAL ENGINEER ALL CCR IMPOUNDMENTS CCR Rule Section (b)

ANNUAL INSPECTION BY A QUALIFIED PROFESSIONAL ENGINEER ALL CCR IMPOUNDMENTS CCR Rule Section (b) ANNUAL INSPECTION BY A QUALIFIED PROFESSIONAL ENGINEER ALL CCR IMPOUNDMENTS ASBURY POWER PLANT 21133 Uphill Lane Asbury, Missouri 64832 January 18, 2019 LIBERTY UTILITIES Empire District Prepared by: Rachel

More information

Construction Dewatering

Construction Dewatering Construction Dewatering Introduction The control of groundwater is one of the most common and complicated problems encountered on a construction site. Construction dewatering can become a costly issue

More information

MANERI DAM D/S VIEW. Er. SANDEEP SINGHAL Director (Projects) UJVN Limited, Dehradun, (UK)

MANERI DAM D/S VIEW. Er. SANDEEP SINGHAL Director (Projects) UJVN Limited, Dehradun, (UK) COMPREHENSIVE REHABILITATION / REPAIR OF MANERI DAM IN DIST. UTTARKASHI MANERI DAM D/S VIEW Er. SANDEEP SINGHAL Director (Projects) UJVN Limited, Dehradun, (UK) sandysinghal14@hotmail.com ABSTRACT Severe

More information

TECHNICAL MEMORANDUM 002 EMORANNO. 001

TECHNICAL MEMORANDUM 002 EMORANNO. 001 TECHNICAL MEMORANDUM 002 EMORANNO. 001 To: Jack Synder, P.E. EES Consulting From: Mort McMillen, P.E. Paul Larson, SE Date: October 13, 2010 Project: Cc: Taylor Bowen Subject: Technical Memorandum (TM)

More information

Plan B Dam Breach Assessment

Plan B Dam Breach Assessment Plan B Dam Breach Assessment Introduction In support of the Local Sponsor permit applications to the states of Minnesota and North Dakota, a dam breach analysis for the Plan B alignment of the Fargo-Moorhead

More information

LoneStar Fiberglass Pools. Do-It-Yourself. Installation Manual

LoneStar Fiberglass Pools. Do-It-Yourself. Installation Manual LoneStar Fiberglass Pools Do-It-Yourself Installation Manual Chris 1/3/2008 Do-It-Yourself The installation of a LoneStar Fiberglass pool is a much simpler task than most people think. What is important

More information

SOUTH CAROLINA ELECTRIC & GAS COMPANY COLUMBIA, SOUTH CAROLINA

SOUTH CAROLINA ELECTRIC & GAS COMPANY COLUMBIA, SOUTH CAROLINA SOUTH CAROLINA ELECTRIC & GAS COMPANY COLUMBIA, SOUTH CAROLINA SALUDA HYDROELECTRIC PROJECT FERC PROJECT NO. 516 PROJECT DESCRIPTION EXHIBIT A DECEMBER 2007 Prepared by: SOUTH CAROLINA ELECTRIC & GAS COMPANY

More information

Sediment Basin 7E-12. Design Manual Chapter 7 - Erosion and Sediment Control 7E - Design Information for ESC Measures BENEFITS.

Sediment Basin 7E-12. Design Manual Chapter 7 - Erosion and Sediment Control 7E - Design Information for ESC Measures BENEFITS. 7E-12 Design Manual Chapter 7 - Erosion and Sediment Control 7E - Design Information for ESC Measures Sediment Basin BENEFITS Flow Control Erosion Control Sediment Control Runoff Reduction Flow Diversion

More information

NUMERICAL AND PHYSICAL MODELING

NUMERICAL AND PHYSICAL MODELING POINTE DU BOIS GENERATING STATION SPILLWAY REPLACEMENT PROJECT NUMERICAL AND PHYSICAL MODELING Kara Hurtig, Northwest Hydraulic Consultants, North Vancouver, BC, Canada David S. Brown, KGS Group, Winnipeg,

More information

Unique Challenges Influencing the Design and Construction Of Three Recent Australian RCC Dams

Unique Challenges Influencing the Design and Construction Of Three Recent Australian RCC Dams Unique Challenges Influencing the Design and Construction Of Three Recent Australian RCC Dams R. Herweynen Principal Consultant Civil, Entura, Australia richard.herweynen@entura.com.au T. Griggs Senior

More information

DIRECTIONAL DRILLING

DIRECTIONAL DRILLING DIRECTIONAL DRILLING 1. General. Installation of pipelines through the levee embankment using directional drilling technology is prohibited. Installation of pipelines through a flood control project foundation

More information

5th International Symposium on RCC Dams General Introduction

5th International Symposium on RCC Dams General Introduction OVERVIEW OF THE DESIGN, CONSTRUCTION, MATERIALS AND INNOVATIVE INSTRUMENTATION FOR ROLLER COMPACTED CONCRETE DAMS By Engr. Ch. Foad Hussain 1 Introduction to the Author Engr. Chaudhry Foad Hussain has

More information

Hard Hat Services ph: hardhatinc.com 932 N. Wright St., Suite 160 Naperville, IL 60563

Hard Hat Services ph: hardhatinc.com 932 N. Wright St., Suite 160 Naperville, IL 60563 Interstate Power and Light Company Ottumwa Generation Station CCR Surface Impoundment Annual Inspection Report 154.018.012.003 Report issued: December 21, 2016 Hard Hat Services ph: 877-630-7428 hardhatinc.com

More information

OTC MS. Free Span Rectification by Pipeline Lowering (PL) Method N. I. Thusyanthan, K. Sivanesan & G. Murphy

OTC MS. Free Span Rectification by Pipeline Lowering (PL) Method N. I. Thusyanthan, K. Sivanesan & G. Murphy OTC-24699-MS Free Span Rectification by Pipeline Lowering (PL) Method N. I. Thusyanthan, K. Sivanesan & G. Murphy Copyright 2014, Offshore Technology Conference This paper was prepared for presentation

More information

Inflatable Packers for Grouting 11/10/00

Inflatable Packers for Grouting 11/10/00 Introduction Inflatable Packers for Grouting 11/10/00 Inflatable packers are frequently used for grout injection in geotechnical applications for structural reinforcement and/or water-proofing of foundations,

More information

Mr. Michael Malone CPS Energy 145 Navarro Street, Mail Drop San Antonio, Texas Project No

Mr. Michael Malone CPS Energy 145 Navarro Street, Mail Drop San Antonio, Texas Project No October 17, 2016 Mr. Michael Malone CPS Energy 145 Navarro Street, Mail Drop 100406 San Antonio, Texas 78296 Project No. 0352436 Subject: Compilation of Construction History Calaveras Power Station San

More information

Hard Hat Services ph: hardhatinc.com 932 N. Wright St., Suite 160 Naperville, IL 60563

Hard Hat Services ph: hardhatinc.com 932 N. Wright St., Suite 160 Naperville, IL 60563 Interstate Power and Light Company Ottumwa Generation Station CCR Surface Impoundment Annual Inspection Report 154.018.015.003 Report issued: July 03, 2017 Hard Hat Services ph: 877-630-7428 hardhatinc.com

More information

Design and Construction of Cerro Del Águila Gravity Dam in Peru

Design and Construction of Cerro Del Águila Gravity Dam in Peru Design and Construction of Cerro Del Águila Gravity Dam in Peru Sayah S. M. 1, Bianco V. 2, Ravelli M. 1, and Bonanni S. 2 1, Lombardi Engineering Limited, 6648 Minusio, Switzerland, selim.sayah@lombardi.ch

More information

IMPACT OF MAKING THE CREST OF WEIR MULTIFACETED ON DISCHARGE COEFFICIENT OF MORNING GLORY SPILLWAY

IMPACT OF MAKING THE CREST OF WEIR MULTIFACETED ON DISCHARGE COEFFICIENT OF MORNING GLORY SPILLWAY IMPACT OF MAKING THE CREST OF WEIR MULTIFACETED ON DISCHARGE COEFFICIENT OF MORNING GLORY SPILLWAY Ali Bagheri 1 and *Ebrahim Nohani 2 1 Department of Water Engineering, Qaemshahr Branch, Islamic Azad

More information

Susitna-Watana Hydroelectric Project Document ARLIS Uniform Cover Page

Susitna-Watana Hydroelectric Project Document ARLIS Uniform Cover Page Alaska Resources Library & Information Services Susitna-Watana Hydroelectric Project Document ARLIS Uniform Cover Page Title: Watana Project, Briefing document on RCC considerations SuWa 109 Author(s)

More information

SOUTH CAROLINA ELECTRIC & GAS COMPANY COLUMBIA, SOUTH CAROLINA

SOUTH CAROLINA ELECTRIC & GAS COMPANY COLUMBIA, SOUTH CAROLINA SOUTH CAROLINA ELECTRIC & GAS COMPANY COLUMBIA, SOUTH CAROLINA SALUDA HYDROELECTRIC PROJECT FERC PROJECT NO. 516 DESCRIPTION OF SALUDA HYRDOELECTRIC PROJECT EXHIBIT A AUGUST 2008 Prepared by: SOUTH CAROLINA

More information

Earthen Embankments. turning into larger, more costly repairs. The following. The State Dam Safety Program has inspection

Earthen Embankments. turning into larger, more costly repairs. The following. The State Dam Safety Program has inspection TOPIC: COMMON PROBLEMS FOR SMALL DAMS WITH CONCRETE CHANNEL SPILLWAYS The State Dam Safety Program has inspection requirements for state regulated dams. A dam, like any man-made structure, will change

More information

Indiana LTAP Road Scholar Core Course #10 Culvert Drainage. Presented by Thomas T. Burke, Jr., PhD, PE Christopher B. Burke Engineering, Ltd.

Indiana LTAP Road Scholar Core Course #10 Culvert Drainage. Presented by Thomas T. Burke, Jr., PhD, PE Christopher B. Burke Engineering, Ltd. Indiana LTAP Road Scholar Core Course #10 Culvert Drainage Presented by Thomas T. Burke, Jr., PhD, PE Christopher B. Burke Engineering, Ltd. Objectives Review culvert shapes, end sections, and materials

More information

22. Specialty Valves.

22. Specialty Valves. 22. Specialty Valves. a. Types of Specialty Valves. 1) Use of the following specialty valves is covered in this section: Altitude Valve, Pressure Reducing Valve, Pressure Relief Valve, Swing Check Valve,

More information

VIRGINIA SOIL AND WATER CONSERVATION BOARD GUIDANCE DOCUMENT ON DAM BREAK INUNDATION ZONE AND INCREMENTAL DAMAGE ANALYSIS AND MAPPING PROCEDURES

VIRGINIA SOIL AND WATER CONSERVATION BOARD GUIDANCE DOCUMENT ON DAM BREAK INUNDATION ZONE AND INCREMENTAL DAMAGE ANALYSIS AND MAPPING PROCEDURES (Approved XXXXX, 2010) Working Draft Version January 14, 2010 VIRGINIA SOIL AND WATER CONSERVATION BOARD GUIDANCE DOCUMENT ON DAM BREAK INUNDATION ZONE AND INCREMENTAL DAMAGE ANALYSIS AND MAPPING PROCEDURES

More information

APPENDIX C VEGETATED EMERGENCY SPILLWAY. VERSION 1.0 March 1, 2011

APPENDIX C VEGETATED EMERGENCY SPILLWAY. VERSION 1.0 March 1, 2011 APPENDIX C VEGETATED EMERGENCY SPILLWAY VERSION 1.0 March 1, 2011 [NOTE: Could use a better photo more clearly showing the emergency spillway in the context of the dam.] SECTION C-1: DESCRIPTION OF PRACTICE

More information

Packwood Lake Intake Screen Velocity Test Report for Energy Northwest's Packwood Lake Hydroelectric Project FERC No Lewis County, Washington

Packwood Lake Intake Screen Velocity Test Report for Energy Northwest's Packwood Lake Hydroelectric Project FERC No Lewis County, Washington for Energy Northwest's Packwood Lake Hydroelectric Project FERC No. 2244 Lewis County, Washington Submitted to P.O. Box 968 Richland, Washington 99352-0968 Submitted by EES Consulting 1155 North State

More information

Innovative spillways. PK-weirs. Franska exempel 10/04/2018. Speaker : A. Chapuis,

Innovative spillways. PK-weirs. Franska exempel 10/04/2018. Speaker : A. Chapuis, Innovative spillways PK-weirs. Franska exempel 10/04/2018 Speaker : A. Chapuis, Member of CFBR - French Committee on Dams and Reservoirs Member of CFBR technical mirror group of ICOLD Committee C Hydraulic

More information

COST EFFECTIVE STORAGE CAPACITY INCREASE FOR ALUMINA TAILINGS DISPOSAL AREA THROUGH SPILLWAY OPTIMISATION

COST EFFECTIVE STORAGE CAPACITY INCREASE FOR ALUMINA TAILINGS DISPOSAL AREA THROUGH SPILLWAY OPTIMISATION COST EFFECTIVE STORAGE CAPACITY INCREASE FOR ALUMINA TAILINGS DISPOSAL AREA THROUGH SPILLWAY OPTIMISATION Abstract Lonie I * Tailings and Dams, GHD Brisbane, QLD, Australia Queensland Alumina Limited operates

More information

DAIVÕES DAM SPILLWAY: A NOVEL SOLUTION FOR THE STILLING BASIN

DAIVÕES DAM SPILLWAY: A NOVEL SOLUTION FOR THE STILLING BASIN DAIVÕES DAM SPILLWAY: A NOVEL SOLUTION FOR THE STILLING BASIN Elsa Alves *, Felix Hernando and Rafael Chacón * Laboratório Nacional de Engenharia Civil (LNEC) Av. do Brasil, 101, 1700-066 Lisboa, Portugal

More information

AMEC010570_0001. Via . Mt. Polley Mine Tailings Facility Optimization Potential- Follow Up from Dam Safety Review 1.

AMEC010570_0001. Via  . Mt. Polley Mine Tailings Facility Optimization Potential- Follow Up from Dam Safety Review 1. { TIME\@ "d MMMM yyyy" } AMEC Project Number VM00448 Via EMAIL Imperial Metals Corporation 200-580 Hornby Street Vancouver, B.C. V6C 3B6 Attention: Mr. Ron Martel Environmental Superintendent Reference:

More information

Akasison Flow phenomena of a siphonic roof outlet

Akasison Flow phenomena of a siphonic roof outlet Akasison Flow phenomena of a siphonic roof outlet Ir. Marc Buitenhuis MTD Hydraulic research engineer Akatherm BV, Panningen, The Netherlands 06-01-2011 Abstract So far the investigations on siphonic roof

More information

Perched Box Caisson Overview. January 2014

Perched Box Caisson Overview. January 2014 Perched Box Caisson Overview January 2014 Why perched box caissons? Perched box caissons are used to construct the portion of the river piers that will support the steel arch spans Construction can occur

More information

Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1]

Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1] Check Dams DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1] [1] Though not generally considered

More information

Beavers are particularly adept at manipulating their

Beavers are particularly adept at manipulating their Beavers are particularly adept at manipulating their environment to suit their needs. They instinctively build dams to raise water levels and increase the area covered by water. Beaver ponds provide security

More information

Lecture 8&9: Construction Dewatering

Lecture 8&9: Construction Dewatering Arab Academy for Science, Technology & Maritime Transport Colleague of Engineering & Technology Construction & Building Engineering CB 523 Methods and Equipment for Construction 1 Lecture 8&9: Construction

More information

INADVERTENT RETURN PLAN FOR HORIZONTAL DIRECTIONAL DRILLING (HDD)

INADVERTENT RETURN PLAN FOR HORIZONTAL DIRECTIONAL DRILLING (HDD) INADVERTENT RETURN PLAN FOR HORIZONTAL DIRECTIONAL DRILLING (HDD) FACILITY OPERATOR: NextEra Energy Resources, LLC 700 Universe Boulevard Juno Beach, FL 33408 For Horizontal Directional Drilling Contents

More information

OPERATION OF SPILLWAY GATES HOW TO AVOID THE PROBLEMS AND PITFALLS. Peter Allen. DERM Qld

OPERATION OF SPILLWAY GATES HOW TO AVOID THE PROBLEMS AND PITFALLS. Peter Allen. DERM Qld OPERATION OF SPILLWAY GATES HOW TO AVOID THE PROBLEMS AND PITFALLS Paper Presented by: Peter Allen Author: Peter Allen, Director Dam Safety DERM Qld 34th Annual Qld Water Industry Operations Workshop Indoor

More information

Advantages & Specifications for the Use of Perma-Patch for the Repair of Potholes

Advantages & Specifications for the Use of Perma-Patch for the Repair of Potholes Advantages & Specifications for the Use of Perma-Patch for the Repair of Potholes The Pothole Solution... p.2 Specifications... p.3 Using Perma-Patch in Severe Weather... p.4 www.permapatch.com Frequently

More information

Homework 2 PROBLEM No. 1

Homework 2 PROBLEM No. 1 PROBLEM No. 1 In accordance with the project requirements, the contractor has obtained a 4 diameter core from below the shaft bottom. The core run was 5.0 and the total rock recovered was 4.2. A total

More information

SAFE WALKS PROGRAM FREQUENTLY ASKED QUESTIONS

SAFE WALKS PROGRAM FREQUENTLY ASKED QUESTIONS SAFE WALKS PROGRAM FREQUENTLY ASKED QUESTIONS Why does the City have a Safe Walks Program? The Safe Walks program was initiated in 2006 at the request of City Council in order to address the increasing

More information

Components of a Barrage

Components of a Barrage Components of a Barrage Definition The only difference between a weir and a barrage is of gates, that is the flow in barrage is regulated by gates and that in weirs, by its crest height. Barrages are costlier

More information

Paper USSD Annual Meeting June 24-28, 2002 DESIGN OF THE RCC PORTION OF THE SALUDA DAM REMEDIATION PROJECT

Paper USSD Annual Meeting June 24-28, 2002 DESIGN OF THE RCC PORTION OF THE SALUDA DAM REMEDIATION PROJECT DESIGN OF THE RCC PORTION OF THE SALUDA DAM REMEDIATION PROJECT By Paul C. Rizzo * William Argentieri ** Jeffrey M. Bair * Kristina Massey ** Harold Moxley ** ABSTRACT Saluda Dam, part of the FERC regulated

More information

Stop Chasing & Start Managing Density

Stop Chasing & Start Managing Density Stop Chasing & Start Managing Density Session: TH-78 Presented by: Todd Mansell, Caterpillar Inc. What is chasing density Measuring, then thumbs up or thumbs down Roller move on www.conexpoconagg.com 2

More information

JAP Additional Information Sheet

JAP Additional Information Sheet JAP Additional Information Sheet Block 15: Purpose and Need The USACE purpose of the project is to provide a safe and reliable whitewater park for the recreational public in a city park, which will provide

More information

U.S. ARMY CORPS OF ENGINEERS INSTITUTE FOR WATER RESOURCES RISK MANAGEMENT CENTER PRELIMINARY LESSONS LEARNED FROM OROVILLE INCIDENT

U.S. ARMY CORPS OF ENGINEERS INSTITUTE FOR WATER RESOURCES RISK MANAGEMENT CENTER PRELIMINARY LESSONS LEARNED FROM OROVILLE INCIDENT U.S. ARMY CORPS OF ENGINEERS INSTITUTE FOR WATER RESOURCES RISK MANAGEMENT CENTER PRELIMINARY LESSONS LEARNED FROM OROVILLE INCIDENT BRIEFING FOR: Eric Halpin, Deputy DSO DATE: 7 April 2017 PURPOSE OF

More information

FINAL Caples Lake Fisheries Management Plan. Version 4.0

FINAL Caples Lake Fisheries Management Plan. Version 4.0 FINAL Caples Lake Fisheries Management Plan Version 4.0 August 15, 2008 Purpose The Caples Lake Fisheries Management Plan (Plan) outlines the stocking plan to reestablish a sport fishery in Caples Lake

More information

Broadly speaking, there are four different types of structures, each with its own particular function:

Broadly speaking, there are four different types of structures, each with its own particular function: 3 The selection of structures 3.1 Introduction In selecting a suitable structure to measure or regulate the flow rate in open channels, all demands that will be made upon the structure should be listed.

More information

Appendix J: Q1-Highway 35 Route Construction Plan

Appendix J: Q1-Highway 35 Route Construction Plan PSC REF#:150055 Wisconsin CPCN Appendix J Appendix J: Q1-Highway 35 Route Construction Plan Public Service Commission of Wisconsin RECEIVED: 06/29/11, 8:51:24 AM Hampton Rochester La Crosse 345 kv Transmission

More information

f Agricultural S c i e n c SMALL EARTH DAMS LLOYD N. BROWN ^ CALIFORNIA AGRICULTURAL CIRCULAR 467 \ Experiment Station Extension Service

f Agricultural S c i e n c SMALL EARTH DAMS LLOYD N. BROWN ^ CALIFORNIA AGRICULTURAL CIRCULAR 467 \ Experiment Station Extension Service f Agricultural S c i e n c SMALL EARTH DAMS LLOYD N. BROWN ^ CALIFORNIA AGRICULTURAL \ Experiment Station Extension Service CIRCULAR 467 Crest of dam Dry face slope 2 to 1 Downstream toe About 10,000 small

More information

Chutes Part 2: Synthetic linings

Chutes Part 2: Synthetic linings s Part 2: Synthetic linings DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control [1] Soil Treatment Permanent [2] [1] s can

More information

On-Site Leaching Chamber Specifications & Features. Design & Installation Manual Minnesota

On-Site Leaching Chamber Specifications & Features. Design & Installation Manual Minnesota On-Site Leaching Chamber Specifications & Features Design & Installation Manual Minnesota 1 This manual provides general design and installation information for use of plastic leaching chambers in the

More information

Item 404 Driving Piling

Item 404 Driving Piling Item Driving Piling 1. DESCRIPTION Drive piling. 2. EQUIPMENT 2.1. Driving Equipment. Use power hammers for driving piling with specified bearing resistance. Use power hammers that comply with Table 1.

More information

M EMORANDUM O CTOBER 6, 201 6

M EMORANDUM O CTOBER 6, 201 6 M EMORANDUM O CTOBER 6, 201 6 TO: FROM: SUBJECT: BOARD OF DIRECTORS ERIC KUHN, GENERAL MANAGER PETER FLEMING, ESQ. DON MEYER, P.E., RAY TENNEY, P.E. WOLFORD AND ELKHEAD RESERVOIR OPERATIONS This memo summarizes

More information

STRUCTURE S-65 PURPOSE SPILLWAY OPERATION

STRUCTURE S-65 PURPOSE SPILLWAY OPERATION STRUCTURE S-65 This structure is a reinforced concrete, gated spillway with discharge controlled by three cable operated, vertical lift gates, and a reinforced concrete lock structure with two pairs of

More information

Technical Report Culvert A Hydraulic Analysis

Technical Report Culvert A Hydraulic Analysis DATE: November 3, 2011 Technical Report Culvert A Hydraulic Analysis TO: FROM: RE: Jim Reiser, P.E. Project Manager Parsons Brinckerhoff, Inc. Kurt Killian, P.E., CFM Parsons Brinckerhoff, Inc. Design

More information

CLAIBORNE LOCK AND DAM PERTINENT DATA

CLAIBORNE LOCK AND DAM PERTINENT DATA CLAIBORNE LOCK AND DAM PERTINENT DATA GENERAL Location Clarke, Monroe, & Wilcox Counties, Alabama; Alabama River, river mile 72.5 Drainage area Millers Ferry to Claiborne sq. mi. 836 Total drainage area

More information

Siting and Installation Manual

Siting and Installation Manual Siting and Installation Manual B-Series Advanced Wastewater Treatment Units Revolutionary Waste Treatment Advanced Wastewater Treatment Units (ATUs) that deliver an unsurpassed performance at an unbeatable

More information

TECHNICAL SPECIFICATIONS SECANT CAISSON WALL TECHNICAL SPECIFICATIONS. October 19, Nanaimo Colliery Dam Auxiliary Spillway, Nanaimo, BC

TECHNICAL SPECIFICATIONS SECANT CAISSON WALL TECHNICAL SPECIFICATIONS. October 19, Nanaimo Colliery Dam Auxiliary Spillway, Nanaimo, BC SECANT CAISSON WALL TECHNICAL TECHNICAL Nanaimo Colliery Dam Auxiliary Spillway, Nanaimo, BC Submitted to: Toby Seward City of Nanaimo 455 Wallace Street Nanaimo, BC V9R 5J6 Report Number: Distribution:

More information

(Revised February,2005) CULVERTS, BRIDGES, AND FORDS

(Revised February,2005) CULVERTS, BRIDGES, AND FORDS GUIDE TO STREAM CROSSINGS (Revised February,2005) CULVERTS, BRIDGES, AND FORDS Culverts, bridges, and fords are all methods used to cross-streams. Culverts are the most common stream crossing structure.

More information

Historic dam failures and recent incidents. Tracey Williamson Associate Director Water (Dams & Reservoirs) British Dam Society Chairman

Historic dam failures and recent incidents. Tracey Williamson Associate Director Water (Dams & Reservoirs) British Dam Society Chairman Historic dam failures and recent incidents Tracey Williamson Associate Director Water (Dams & Reservoirs) British Dam Society Chairman 1 Agenda 1. Dams in all their beauty 2. Hazards associated with dams

More information

Testing Services Overview

Testing Services Overview 2 Jet Research Center JRC Jet Research Center Perforating Center of Excellence Testing Services Overview API RP19B Testing Advanced Testing Operational Testing API RP19B Testing The American Petroleum

More information

APPENDIX J HYDROLOGY AND WATER QUALITY

APPENDIX J HYDROLOGY AND WATER QUALITY APPENDIX J HYDROLOGY AND WATER QUALITY J-1 Technical Report on Airport Drainage, Northern Sector Airport and Ordinance Creek Watershed / Preliminary Creek Constructed Natural Channel Culvert J-2 Preliminary

More information

Hydraulic Modeling to Aid TDG Abatement at Boundary and Cabinet Gorge Dams

Hydraulic Modeling to Aid TDG Abatement at Boundary and Cabinet Gorge Dams Hydraulic Modeling to Aid TDG Abatement at Boundary and Cabinet Gorge Dams Joe Orlins, P.E., Ph.D. NWHA Technical Seminar May 15, 2014 Boundary and Cabinet Gorge Dams The Problem: Too Much Gas Boundary

More information

Fall Protection Resource Guide P AGE 1

Fall Protection Resource Guide P AGE 1 Fall Protection Resource Guide P AGE 1 As a Home Builder, we do not self-perform any work. This section is a resource guide only and is not intended to put any requirements on the company. All subcontractors,

More information

Large-scale Field Test

Large-scale Field Test Vaskinn 1 Large-scale Field Test Kjetil Arne Vaskinn kav@trh.statkraftgroner.no Statkraft Grøner AS SUMMARY The objective the controlled failure of large-scale embankment is to monitor and record the failure

More information

Design of Spillway Upgrades

Design of Spillway Upgrades USACE Dam Safety Program Design of Spillway Upgrades Sal Todaro, P.E. Senior Hydraulic Structures Engineer U.S. Army Corps of Engineers Risk Management Center 1 Presentation Overview 1. USACE (RMC) approach

More information

What I ve Learned About Dam Safety Good, Bad and Ugly

What I ve Learned About Dam Safety Good, Bad and Ugly What I ve Learned About Dam Safety Good, Bad and Ugly Ron Gruzesky Dam Safety and Floodplain Compliance Kentucky Division of Water Department for Environmental Protection August 26, 2015 What is a Dam?

More information

Hydraulic Evaluation of the Flow over Polyhedral Morning Glory Spillways

Hydraulic Evaluation of the Flow over Polyhedral Morning Glory Spillways World Applied Sciences Journal 9 (7): 712-717, 2010 ISSN 1818-4952 IDOSI Publications, 2010 Hydraulic Evaluation of the Flow over Polyhedral Morning Glory Spillways 1 2 2 A. Bagheri, M. Shafai Bajestan,

More information

Pre-Application Document Kaweah Project (FERC Project No. 298)

Pre-Application Document Kaweah Project (FERC Project No. 298) TABLE OF CONTENTS Page 3.12 Aesthetic Resources... 3.12-1 3.12.1 Information Sources... 3.12-1 3.12.2 Setting... 3.12-1 3.12.3 Project Facilities... 3.12-2 3.12.4 Previous Visual Resources Assessment...

More information

Federal Railroad Administration. HUDSON TUNNEL PROJECT: WEEHAWKEN COMMUNITY MEETING January 18, 2018

Federal Railroad Administration. HUDSON TUNNEL PROJECT: WEEHAWKEN COMMUNITY MEETING January 18, 2018 HUDSON TUNNEL PROJECT: WEEHAWKEN COMMUNITY MEETING January 18, 2018 Agenda Near Term Activity Hudson Tunnel Project Revisions to the Project to Address Community Concerns Description of Construction Activities

More information

Outlet Structures T-12

Outlet Structures T-12 Description This section provides guidance and details for outlet structures for use primarily with BMPs utilizing sedimentation, (i.e., extended detention basins (EDBs), retention ponds, and constructed

More information

Hydraulic and Economic Analysis of Real Time Control

Hydraulic and Economic Analysis of Real Time Control Hydraulic and Economic Analysis of Real Time Control Tom Walski 1, Enrico Creaco 2 1 Bentley Systems, Incorporated, 3 Brian s Place, Nanticoke, PA, USA 2 Dipartimento di Ingegneria Civile ed Architettura,

More information

SECTION [ ] [02730] STABILIZED DECOMPOSED GRANITE SURFACING

SECTION [ ] [02730] STABILIZED DECOMPOSED GRANITE SURFACING SECTION [32 15 40] [02730] STABILIZED DECOMPOSED GRANITE SURFACING EDIT SPECIFICATION: Edit the following guide specification to comply with project requirements. This document is available in word processing

More information

HEATEC TEC-NOTE. Setting Siemens Pressure Transmitter. Used on Heatec Vertical Asphalt Tanks. Publication No , Revised

HEATEC TEC-NOTE. Setting Siemens Pressure Transmitter. Used on Heatec Vertical Asphalt Tanks. Publication No , Revised HEATEC TEC-NOTE, Revised 1-5-15 Setting Siemens Pressure Transmitter Used on Heatec Vertical Asphalt Tanks This document provides information on setting Siemens pressure transmitters used on Heatec vertical

More information

CHAPTER 4: BEST MANAGEMENT PRACTICES FOR EROSION AND SEDIMENTATION CONTROL

CHAPTER 4: BEST MANAGEMENT PRACTICES FOR EROSION AND SEDIMENTATION CONTROL Figure 4.4m. Type III Floating Turbidity Barrier Source: American Boom and Barrier Corporation and Virginia Department of Transportation (DOT) Standard Sheets 71 4.4.6 Floating Turbidity Barrier Definition

More information

Green CCR Surface Impoundment

Green CCR Surface Impoundment Green CCR Surface Impoundment Disposal of Coal Combustion Residuals (CCR) from Electric Utilities Final Rule CCR Impoundment 2017 Annual Inspection Report January 11, 2018 Prepared By: Project ID: 170138A

More information

Barricades and Falling Object Protection Plans

Barricades and Falling Object Protection Plans Title: Barricades and Falling Object Protection Plans Freeport Site Function: Environmental, Health & Standard No.: BCF020.042 Rev 7 Page: 1 of 7 REVISION HISTORY Date Revision Number Details of Change

More information

TRENCH AND EXCAVATION COLLAPSE

TRENCH AND EXCAVATION COLLAPSE TRENCH AND EXCAVATION COLLAPSE A. GENERAL This guideline provides operational guidance at rescue incidents that involve the location, disentanglement and removal of victims from sub-surface trench and

More information

6 TH INTERNATIONAL SYMPOSIUM ON ROLLER COMPACTED CONCRETE (RCC) DAMS Zaragoza, October 2012

6 TH INTERNATIONAL SYMPOSIUM ON ROLLER COMPACTED CONCRETE (RCC) DAMS Zaragoza, October 2012 6 TH INTERNATIONAL SYMPOSIUM ON ROLLER COMPACTED CONCRETE (RCC) DAMS Zaragoza, 23 25 October 2012 HRB WALDBÄRENBURG: FIRST RCC DAM EXPERIENCE IN GERMANY Birgit LANGE LTV, Dam Authority of Saxony, Germany

More information

TABLE OF CONTENTS LEGAL NOTICE

TABLE OF CONTENTS LEGAL NOTICE Closure Plan for Existing CCR Rev. 0 Surface Impoundments Page No. i TABLE OF CONTENTS 1. INTRODUCTION AND PURPOSE... 1 2. CLOSURE PLAN NARRATIVE DESCRIPTION... 2 3. FINAL COVER SYSTEM DESCRIPTION... 3

More information

Perforating Center of Excellence TESTING SERVICES OVERVIEW

Perforating Center of Excellence TESTING SERVICES OVERVIEW Perforating Center of Excellence TESTING SERVICES OVERVIEW Jet Research Center (JRC) is the leader in energetic research and testing for the oil and gas industry. Since introducing jet perforators for

More information

DESIGN OF BELL-MOUTH SPILLWAY AT BARVI DAM

DESIGN OF BELL-MOUTH SPILLWAY AT BARVI DAM DESIGN OF BELL-MOUTH SPILLWAY AT BARVI DAM Akshay Haldankar 1, Mahesh Bhadra 2, Rahul Harad 3, Darpan Kapre 4, Dipali Patil 5 1,2,3,4 Under graduate,dept. of Civil Engineering, DRIEMS Neral. 5Assistant

More information

PRELIMINARY RISK ASSESSMENT RIDM PROJECT FOR A DAM WITH A VEGETATION- LINED SPILLWAY AND FERC PILOT

PRELIMINARY RISK ASSESSMENT RIDM PROJECT FOR A DAM WITH A VEGETATION- LINED SPILLWAY AND FERC PILOT PRELIMINARY RISK ASSESSMENT FOR A DAM WITH A VEGETATION- LINED SPILLWAY AND FERC PILOT RIDM PROJECT MAY 3, 2018 DAVID S. BOWLES AND LOREN R. ANDERSON RAC ENGINEERS AND ECONOMISTS, LLC AND UTAH STATE UNIVERSITY

More information

Khosla's theory. After studying a lot of dam failure constructed based on Bligh s theory, Khosla came out with the following;

Khosla's theory. After studying a lot of dam failure constructed based on Bligh s theory, Khosla came out with the following; Khosla's theory After studying a lot of dam failure constructed based on Bligh s theory, Khosla came out with the following; Following are some of the main points from Khosla's Theory From observation

More information

REMEDIATION OF SALUDA DAM RCC AND ROCKFILL DAMS. Abstract

REMEDIATION OF SALUDA DAM RCC AND ROCKFILL DAMS. Abstract REMEDIATION OF SALUDA DAM RCC AND ROCKFILL DAMS Paul C. Rizzo 1, Scott Newhouse 2, Jeff Bair 3 Abstract Saluda Dam, part of the FERC regulated Saluda Hydroelectric Project located near Columbia, South

More information

STRUCTURE 65-B PURPOSE SPILLWAY OPERATION

STRUCTURE 65-B PURPOSE SPILLWAY OPERATION STRUCTURE 65-B This structure is a reinforced concrete, gated spillway with discharge controlled by three cable operated vertical lift gates and a reinforced concrete lock structure with two pairs of sector

More information

Ermenek Dam and HEPP: Spillway Test & 3D Numeric-Hydraulic Analysis of Jet Collision

Ermenek Dam and HEPP: Spillway Test & 3D Numeric-Hydraulic Analysis of Jet Collision Ermenek Dam and HEPP: Spillway Test & 3D Numeric-Hydraulic Analysis of Jet Collision J.Linortner & R.Faber Pöyry Energy GmbH, Turkey-Austria E.Üzücek & T.Dinçergök General Directorate of State Hydraulic

More information

FACING SYSTEMS FOR ROLLER-COMPACTED CONCRETE DAMS &SPILLWAYS. Prepared by Gannett Fleming, Inc.

FACING SYSTEMS FOR ROLLER-COMPACTED CONCRETE DAMS &SPILLWAYS. Prepared by Gannett Fleming, Inc. FACING SYSTEMS FOR ROLLER-COMPACTED CONCRETE DAMS &SPILLWAYS Prepared by Gannett Fleming, Inc. P O R T L A N D C E M E N T A S S O C I A T I O N Facing Systems for Roller-Compacted Concrete Dams & Spillways

More information

UPDATE OF ICOLD BULLETIN 126 ON RCC DAMS

UPDATE OF ICOLD BULLETIN 126 ON RCC DAMS UPDATE OF ICOLD BULLETIN 126 ON RCC DAMS Shaw QHW 1 1, Director: ARQ (PTY) Ltd, +27 12 348 6669, Fax,quentin@arq.co.za Abstract: The original 2003 ICOLD Bulletin 126 on Roller Compacted Concrete dams proved

More information