1 Developing a Portwide Asset Management Program American Association of Port Authorities Marine Terminal Management Training Program September 17, 2015 Colin Chung, PhD President, Kayuga Solution

2 Asset Management Program

3 Asset Management Program AM processes and practices Asset data Information systems Organizational leadership & support Staff understanding and acceptance Creating Balance!

4 Goal of Asset Management Customer Expectations Cost of Service Level of Service Risk

5 Asset Management Program Objectives To find out: Catch Up ($) Restoration Keep Up ($) Preservation Moving Forward ($) How? Document the assets owned and managed Understand the current state of assets Establish appropriate levels of service Prioritize the need by risk Understand what budget and resources are required to catch up, keep up, and move forward Calculate cost of service Communicate the infrastructure problem

6 Portwide Asset Management Program Port is a small city! 1. Roadway assets Pavement, sidewalks, curbs and gutter, lights, signage, etc. 2. Building assets Warehouses, office buildings, comfort stations 3. Underwater assets Wharfs, moorings, sheet piles, floating dock, etc. 4. Park assets Playgrounds, benches, picnic tables, gazebos, etc. 5. Water and wastewater assets Pipes, pumps, motors, MCCs, gensets, valves, hydrants, manholes, etc. 6. Drainage assets Pipes, channels, structures, BMPs 7. Fleet 8. Urban Forestry 9. And more

7 Asset Management Program Methodology Inventory and assess condition Project preservation and restoration costs and schedules Assess criticality and estimated asset replacement costs Determine the desired service levels Understand the finance and resources required to sustain the delivery of services Optimize and prioritize the critical needs based on risk Tell the infrastructure story

8 Asset Management Plan Development Process Create Asset Database Assess Asset Criticality Perform Life Cycle Cost Assessment Develop Risk Based Plan Asset Inventory Condition Assessment Asset Valuation Asset Hierarchy Criticality Ranking Asset Risk Catch Up Keep Up Moving Forward Risk Budget Resources Align with Strategic Direction

9 ASSET INVENTORY & CONDITION ASSESSMENT

10 Asset Inventory / Data Collection Activities

11 Roadway Condition Assessment

12 Underwater Condition Assessment

13 Building Inventory and Condition Assessment

14 Building Maintenance and Repair Challenges

15 Maintenance Needs

16 Condition Assessment

17 ADA Compliance Assessment Tight stall width Non-compliant faucets Needs grab rails

18 Assets are Recorded and Organized Port of Sunshine

19 Condition Assessment Results 19

20 Installation & Consumption Profiles

21 RISK ASSESSMENT

22 Risk PoF CoF Risk Probability of Failure (Timing to Failure) Mortality Capacity Level of Service Financial Efficiency Consequence of Failure (Impact of a failure) Economic Environment Social

23 Risk Profile

24 State of Facilities 100% 80% 60% 40% 20% 0% LS302 LS304 LS305 LS306 LS307 LS309 LS310 LS312 LS313 LS314 LS315 LS316 LS317 LS318 LS319 LS320 LS323 LS324 LS325 LS326 LS327 LS329 LS352 LS353 LS354 Total High Risk Medium Risk Low Risk

25 State of Pavement 25

26 Risk-Based Strategy

27 LIFE CYCLE COST ASSESSMENT

28 Condition Rating Calculating the Timing to Failure Year

29 Risk / Condition Asset Life Cycle Investment Logic Max Risk Risk Con PoF CoF Risk Min Risk Min Con Mn$ Op$ Cum$ CoF Cumulated Cost Condition Maintenance PoF Operation Min Cond Investment Time

30 Asset Management Tool IRIS (Infrastructure Reinvestment Intelligence System)

31 Asset Valuation (Parks)

32 Understanding the Need (Year By Year Asset By Asset )

33 Prioritize by Risk

34 Results are Mapped

35 Understanding the Impact of Funding $120,000, YEAR PROJECTED RENEWAL NEED $100,000,000 $80,000,000 $60,000,000 Projected Budget $40,000,000 Current Budget $20,000,000 $ General District Potable Water Recycled Water Sewer

36 Work Backlog Analysis $120,000, YEAR PROJECTED RENEWAL NEED Unfunded Portion $100,000,000 $80,000,000 $60,000,000 $40,000,000 Current Budget $20,000,000 $ General District Potable Water Recycled Water Sewer

37 What If We Don t Do Anything? $100,000,000 Current Budget $- 10 YEAR BACKLOGS AT CURRENT BUDGET $(100,000,000) $(200,000,000) $(300,000,000) $(400,000,000) $(500,000,000)

38 What If We Increase the Funds by 5%? $100,000,000 Increased Budget $- 10 YEAR WORK BACKLOGS AT 5% INCREASE $(100,000,000) $(200,000,000) $(300,000,000) $(400,000,000) $(500,000,000)

39 Scenario Comparison

40 Asset Management Data Flow GIS Work CMMS Budget Finance Continuous Improvement

41 Using Asset Management Results to Understand and Communicate Catch Up Keep Up Moving Forward Managing Risk & Planning for the Future

42 Thank you!

Incorporating Sidewalks into Transportation Asset Management. Presentation by Alan S. Kercher, P.E. Kercher Engineering, Inc.

Incorporating Sidewalks into Transportation Asset Management. Presentation by Alan S. Kercher, P.E. Kercher Engineering, Inc. Incorporating Sidewalks into Transportation Asset Management Presentation by Alan S. Kercher, P.E. Kercher Engineering, Inc. Integrated Management of Infrastructure Example: Urban Environment Pavements

More information

Asset Replacement Plan Town of Bradford West Gwillimbury

Asset Replacement Plan Town of Bradford West Gwillimbury Asset Replacement Plan Town of Bradford West Gwillimbury February 2012 11 Allstate Parkway, Suite 310, Markham, Ontario L3R 9T8 (Tel) 905.752.4300 (Fax) 905.752.4301 Town of Bradford West Gwillimbury Asset

More information

Building Great Neighbourhoods BELLEVUE AND VIRGINIA PARK

Building Great Neighbourhoods BELLEVUE AND VIRGINIA PARK Building Great Neighbourhoods BELLEVUE AND VIRGINIA PARK This is Meeting 2 Unfortunately, some residents in Bellevue and Virginia Park received the wrong information for this public open house (Meeting

More information

Public Transport Asset Management

Public Transport Asset Management Public Transport Asset Management 17 maintenance shops Bank 885 miles of track Workshop and Training on Urban Transport Planning and Reform. Baku, April 14-16, 2009 Key Public Transport Activities Service

More information

Business Plan Presentation

Business Plan Presentation 2019 Department of Water Resources Business Plan Presentation Wednesday, August 29, 2018 Mission To Provide Superior Water Services at an Excellent Value Vision To be widely recognized as a leader in the

More information

Building Great Neighbourhoods QUEEN ALEXANDRA

Building Great Neighbourhoods QUEEN ALEXANDRA Building Great Neighbourhoods QUEEN ALEXANDRA We are here today to Explain how the City is investing in improving your neighbourhood and how your neighbourhood will be improved to meet current City standards.

More information

2015 Business Plan September 2014

2015 Business Plan September 2014 2015 Business Plan September 2014 Mission To Provide Superior Water Services at an Excellent Value To Provide Superior Water Services at an Excellent Value Highly Performing Staff Well Maintained Assets

More information

Building Great Neighbourhoods LANSDOWNE

Building Great Neighbourhoods LANSDOWNE Building Great Neighbourhoods LANSDOWNE We are here today to Explain how the City is investing in improving your neighbourhood and how your neighbourhood will be improved to meet current City standards.

More information

The Corporation of the Town of Amherstburg, Ontario ASSET MANAGEMENT PLAN

The Corporation of the Town of Amherstburg, Ontario ASSET MANAGEMENT PLAN The Corporation of the Town of Amherstburg, Ontario ASSET MANAGEMENT PLAN December 2014 Asset Management Plan Preface An Asset Management Plan is a strategy that identifies how municipal assets will be

More information

Pedestrian, Bicycle and Traffic Calming Strategic Implementation Plan. January 18, 2011

Pedestrian, Bicycle and Traffic Calming Strategic Implementation Plan. January 18, 2011 Pedestrian, Bicycle and Traffic Calming Strategic Implementation Plan January 18, 2011 Tonight s Agenda Receive update on project Provide feedback on two policy issues Complete Streets Policy Project Prioritization

More information

Proposed. City of Grand Junction Complete Streets Policy. Exhibit 10

Proposed. City of Grand Junction Complete Streets Policy. Exhibit 10 Proposed City of Grand Junction Complete Streets Policy Exhibit 10 1 City of Grand Junction Complete Streets Policy Vision: The Complete Streets Vision is to develop a safe, efficient, and reliable travel

More information

East Downtown Tax Increment Reinvestment Zone (TIRZ) No. 15 Infrastructure Assessment Study

East Downtown Tax Increment Reinvestment Zone (TIRZ) No. 15 Infrastructure Assessment Study East Downtown Tax Increment Reinvestment Zone (TIRZ) No. 15 Infrastructure Assessment Study Houston, TX Technical Memorandum April 15 th, 2009 Prepare by: 2950 North Loop West, Ste. 900 Houston, TX 77092

More information

Corpus Christi Metropolitan Transportation Plan Fiscal Year Introduction:

Corpus Christi Metropolitan Transportation Plan Fiscal Year Introduction: Introduction: The Safe, Accountable, Flexible, Efficient Transportation Equity Act: A Legacy for Users (SAFETEA-LU) has continued the efforts started through the Intermodal Surface Transportation Efficiency

More information

83 AVENUE PRE-CONSTRUCTION MEETING

83 AVENUE PRE-CONSTRUCTION MEETING 83 AVENUE PRE-CONSTRUCTION MEETING April 6, 2017 5-8PM Please visit displays for project information Talk to staff, ask questions, visit website at: www.edmonton.ca/bike83avenue Pre-Construction Meeting

More information

New Measure A Expenditure Categories DEFINITIONS OF ELIGIBLE EXPENDITURES Adopted March 8, 2007

New Measure A Expenditure Categories DEFINITIONS OF ELIGIBLE EXPENDITURES Adopted March 8, 2007 New Measure A Expenditure Categories DEFINITIONS OF ELIGIBLE EXPENDITURES Adopted March 8, 2007 City Street and County Road Maintenance Program The preservation and keeping of public street and road rights-of-way

More information

City of West Des Moines PAVEMENT MANAGEMENT SYSTEM

City of West Des Moines PAVEMENT MANAGEMENT SYSTEM City of West Des Moines PAVEMENT MANAGEMENT SYSTEM 12/11/2018 Municipal Street Seminar (11-14-2018) JEFF NASH 1 City Background Information: - West Des Moines current census Population is around 66,000

More information

TULSA CITY COUNCIL CAPITAL IMPROVEMENT PROGRAM TASK FORCE MEETING JANUARY

TULSA CITY COUNCIL CAPITAL IMPROVEMENT PROGRAM TASK FORCE MEETING JANUARY CITY OF TULSA BICYCLE & PEDESTRIAN INFRASTRUCTURE TULSA CITY COUNCIL CAPITAL IMPROVEMENT PROGRAM TASK FORCE MEETING JANUARY 31, 2013 CITY OF TULSA ENGINEERING SERVICES DEPARTMENT CITY OF TULSA ADA TRANSITION

More information

DRAFT. Lecompton. Table of Contents. Background

DRAFT. Lecompton. Table of Contents. Background Lecompton Table of Contents Existing Infrastructure 98 Funding 100 Policy and Program Recommendations 102 Infrastructure Recommendations 104 Conclusion 109 Douglas County Lecompton Background Located at

More information

IMPLEMENTATION STRATEGIES

IMPLEMENTATION STRATEGIES GEORGETOWN SIDEWALK MASTER PLAN 34% of funding is dedicated to Downtown Overlay District sidewalks 28% of funding is recommended within 1/4 mile of Southwestern University 26% of funding is recommended

More information

Rhode Island Moving Forward Long-Range Transportation Plan 2040 Municipal Roundtable Providence County

Rhode Island Moving Forward Long-Range Transportation Plan 2040 Municipal Roundtable Providence County Rhode Island Moving Forward Long-Range Transportation Plan 2040 Municipal Roundtable Providence County www.planri.com PlanRI2040@gmail.com Municipal Roundtable Meeting Summary Date/time: Location: Tuesday,

More information

Active Transportation Infrastructure Investment A Business Case

Active Transportation Infrastructure Investment A Business Case Active Transportation Infrastructure Investment A Business Case In 2016, the Real Estate Foundation awarded the Capital Regional District a $50,000 grant for Shifting Gears: Land Use Change through Active

More information

CITY OF EPHRATA NAT WASHINGTON WAY OVERLAY TIB NO.: 3-E-164(003)-1 CITY OFFICIALS. Bruce Reim. Mayor. Tony Mora, Jr. City Council

CITY OF EPHRATA NAT WASHINGTON WAY OVERLAY TIB NO.: 3-E-164(003)-1 CITY OFFICIALS. Bruce Reim. Mayor. Tony Mora, Jr. City Council GRANT COUNTY WASHINGTON TIB NO.: 3-E-164(003)-1 CITY OFFICIALS Kathleen Allstot Bruce Reim Mayor William Coe Stephanie Knitter Valli Millard Matthew Moore Tony Mora, Jr. City Council Mark Wanke Leslie

More information

City Sidewalk Repair and Replacement Program

City Sidewalk Repair and Replacement Program City Sidewalk Repair and Replacement Program May 30, 2006 http://www.adventuregovernment.com Purpose Improve pedestrian safety Increase handicap accessibility Create a more walkable community Decrease

More information

Building Great Neighbourhoods BONNIE DOON

Building Great Neighbourhoods BONNIE DOON Building Great Neighbourhoods BONNIE DOON We Are Here Today To Explain the Neighbourhood Renewal Process Show you the Westwood Preliminary Design Ask for local knowledge Highlight the Local Improvement

More information

DEVELOPMENT OF A PAVEMENT REHABILITATION STRATEGY FOR NATIONAL ROADS IN QUEENSLAND

DEVELOPMENT OF A PAVEMENT REHABILITATION STRATEGY FOR NATIONAL ROADS IN QUEENSLAND DEVELOPMENT OF A PAVEMENT REHABILITATION STRATEGY FOR NATIONAL ROADS IN QUEENSLAND Presenter: Tyrone Toole, ARRB Group Scope Background Objectives Road network data and analysis Current and potential investment

More information

Resource Guide. Copyright 2017 Institute of Certified Management Accountants. Updated 8/30/17

Resource Guide. Copyright 2017 Institute of Certified Management Accountants. Updated 8/30/17 Resource Guide Copyright 2017 Institute of Certified Management Accountants Updated 8/30/17 RESOURCE GUIDE Institute of Certified Management Accountants Certified in Strategy and Competitive Analysis Exam

More information

Revision of maintenance quality requirements to promote cycling in the city of Kuopio. Winter Cycling Congress , Oulu Timo Perälä

Revision of maintenance quality requirements to promote cycling in the city of Kuopio. Winter Cycling Congress , Oulu Timo Perälä Revision of maintenance quality requirements to promote cycling in the city of Kuopio Winter Cycling Congress 13.2.2013, Oulu Timo Perälä The city of Kuopio 98 000 inhabitants Cycling modal split of 10

More information

Pre-Construction Meeting

Pre-Construction Meeting Pre-Construction Meeting Wednesday, March 21 Drop-in from 5 9pm Please visit displays for project information, talk to staff, and ask questions! Edmonton.ca/SouthsideBikeRoutes Objectives & Project Scope

More information

Goal 3: Foster an environment of partnerships and collaboration to connect our communities and regions to one another.

Goal 3: Foster an environment of partnerships and collaboration to connect our communities and regions to one another. Non-Motorized Transportation Plan (NMTP) Draft Vision, Goal and,, Tri-County Regional Planning Commission (TCRPC) Purpose The purpose of the Tri-County Regional Planning Commission (TCRPC) Non-Motorized

More information

CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF OCTOBER 30, 2012

CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF OCTOBER 30, 2012 CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF OCTOBER 30, 2012 Item 31, Report No. 39, of the Committee of the Whole, which was adopted without amendment by the Council of the City of Vaughan

More information

Safe Routes to School Action Plan Aberdeen, Idaho

Safe Routes to School Action Plan Aberdeen, Idaho Background Aberdeen, Idaho is a largely agricultural community of nearly 2,000 people and is located in the southeast portion of the state on the western edge of American Falls Reservoir. The community

More information

CITY OF ROSEVILLE DESIGN STANDARDS

CITY OF ROSEVILLE DESIGN STANDARDS CITY OF ROSEVILLE DESIGN STANDARDS Section 1 Purpose and Definitions 1-1 Purpose PD 1 1-2 Design Practice PD 1 1-3 Definitions PD 1 Section 2 General Requirements 2-1 Plans by an Appropriate Engineer GR

More information

DRAFT. Table of Contents. Background

DRAFT. Table of Contents. Background Douglas County Table of Contents Existing Infrastructure 86 Funding 89 Policy and Program Recommendations 90 Infrastructure Recommendations 92 Conclusion 95 Background Home to 4,500 residents and Baker

More information

Transportation Day at the Capitol. Charlie Zelle Commissioner, MnDOT Feb. 16, 2017

Transportation Day at the Capitol. Charlie Zelle Commissioner, MnDOT Feb. 16, 2017 Transportation Day at the Capitol Charlie Zelle Commissioner, MnDOT Feb. 16, 2017 State Transportation System Highways 59.1 billion annual vehicle miles traveled 33.1 billion on trunk highways Bridges

More information

ADA Transition Plan. City of Gainesville FY19-FY28. Date: November 5, Prepared by: City Of Gainesville Department of Mobility

ADA Transition Plan. City of Gainesville FY19-FY28. Date: November 5, Prepared by: City Of Gainesville Department of Mobility ADA Transition Plan FY19-FY28 Date: November 5, 2018 Prepared by: City Of Gainesville Department of Mobility 1.0 INTRODUCTION 1.1 BACKGROUND The federal statute known as the Americans with Disabilities

More information

Draft. Lecompton. Table of Contents. Background

Draft. Lecompton. Table of Contents. Background Lecompton Table of Contents Existing Infrastructure 80 Funding 82 Policy and Program Recommendations 83 Infrastructure Implementation Scenarios 84 Conclusion 85 Douglas County Lecompton Background Located

More information

STATE TRANSPORTATION COMMISSION HEARING

STATE TRANSPORTATION COMMISSION HEARING STATE TRANSPORTATION COMMISSION HEARING Twelve Year Program Update Tom Zilla: Centre County MPO Jim Saylor: SEDA-COG RPO Amy Kessler: North Central RPO PennDOT District 2-0 State College, PA October 8,

More information

Where Did the Road Go? The Straight and Narrow about Curves

Where Did the Road Go? The Straight and Narrow about Curves Where Did the Road Go? The Straight and Narrow about Curves Renae Kuehl, SRF Consulting Group October 23, 2018 What is a County Roadway Safety Plan or CRSP?" CRSP Identifies priority location-specific

More information

TANGIBLE CAPITAL ASSET (TCA) Reporting Guidelines for Land Development Projects

TANGIBLE CAPITAL ASSET (TCA) Reporting Guidelines for Land Development Projects January 2012 TANGIBLE CAPITAL ASSET (TCA) Reporting Guidelines for Land Development Projects 1. PURPOSE OF REPORTING The purpose of Tangible Capital Asset (TCA) reporting is to comply with PSAB 3150 reporting

More information

ACTIVE TRANSPORTATION

ACTIVE TRANSPORTATION ACTIVE TRANSPORTATION Mobility 2040 Supported Goals Improve the availability of transportation options for people and goods. Support travel efficiency measures and system enhancements targeted at congestion

More information

SECTION 5: PEER CITY REVIEW

SECTION 5: PEER CITY REVIEW SECTION 5: PEER CITY REVIEW 5.1 Introduction It is evident that the City of Lincoln continually strives to improve its operations and practices. To that end, a list of peer cities was developed to compare

More information

Fairfax County Transportation Funding and Roadway Service Delivery Study. Study Update Transportation Advisory Commission

Fairfax County Transportation Funding and Roadway Service Delivery Study. Study Update Transportation Advisory Commission Fairfax County Transportation Funding and Roadway Service Delivery Study Study Update Transportation Advisory Commission May 4, 2010 Past Studies Aug. 1965 The Financial Effects of the Incorporation of

More information

In station areas, new pedestrian links can increase network connectivity and provide direct access to stations.

In station areas, new pedestrian links can increase network connectivity and provide direct access to stations. The Last Mile Planning for Pedestrians Planning around stations will put pedestrians first. Making walking to stations safe and easy is important; walking will be a part of every rapid transit Accessible

More information

Preparing a Curb Ramp Project. December 15, 2010

Preparing a Curb Ramp Project. December 15, 2010 Preparing a Curb Ramp Project December 15, 2010 3 Tiers of Project Types Non-Signalized Curb Ramp Reconstruction - Typically utilizing standard plans and identifying ramp types at each quadrant Signalized

More information

Living Streets Policy

Living Streets Policy Living Streets Policy Introduction Living streets balance the needs of motorists, bicyclists, pedestrians and transit riders in ways that promote safety and convenience, enhance community identity, create

More information

AMERICANS WITH DISABILITIES ACT TRANSITION PLAN LEON COUNTY FOR CURB RAMPS AND SIDEWALKS DEPARTMENT OF PUBLIC WORKS. 1 P age

AMERICANS WITH DISABILITIES ACT TRANSITION PLAN LEON COUNTY FOR CURB RAMPS AND SIDEWALKS DEPARTMENT OF PUBLIC WORKS. 1 P age AMERICANS WITH DISABILITIES ACT TRANSITION PLAN FOR CURB RAMPS AND SIDEWALKS 2015 LEON COUNTY DEPARTMENT OF PUBLIC WORKS 1 P age INTRODUCTION The goal of the Americans with Disabilities Act (ADA) Transition

More information

CITY OF SOUTH DAYTONA

CITY OF SOUTH DAYTONA CITY OF SOUTH DAYTONA FIVE YEAR WORK PLAN for HALF-CENT SALES TAX FY 2020-2025 Table of Contents Executive Summary Purpose of the Work Program... 3 Project List Magnolia Avenue North Roadway, Drainage

More information

CHAPTER SIXTEEN THE MASTER PLAN. Oakland Alive

CHAPTER SIXTEEN THE MASTER PLAN. Oakland Alive CHAPTER SIXTEEN THE MASTER PLAN 191 THE MASTER PLAN To continue to preserve and restore Oakland for future generations requires a comprehensive program of strategies and recommendations; a commitment from

More information

Paving for Progress Municipal Streets Seminar

Paving for Progress Municipal Streets Seminar Paving for Progress Municipal Streets Seminar November 15, 2017 Doug Wilson, PE City of Cedar Rapids Paving for Progress Program Manager State and National Rankings $10,996,122 Prior Funding: General Obligation

More information

Public Transportation and Bicycle & Pedestrian Stakeholder Webinar. April 11, :30 PM

Public Transportation and Bicycle & Pedestrian Stakeholder Webinar. April 11, :30 PM Public Transportation and Bicycle & Pedestrian Stakeholder Webinar April 11, 2013 1:30 PM Public Transportation and Bicycle & Pedestrian Webinar April 11, 2013 1:30 PM MULTIMODAL TRANSPORTATION PLAN Vision,

More information

CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF NOVEMBER 21, 2017

CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF NOVEMBER 21, 2017 CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF NOVEMBER 21, 2017 Item 9, Report No. 39, of the Committee of the Whole, which was adopted without amendment by the Council of the City of Vaughan

More information

City of Madison: 2017 Capital Budget Capital Improvement Plan

City of Madison: 2017 Capital Budget Capital Improvement Plan Capital Improvement Plan Project Summary Bikeways Program 779,000 751,000 630,000 670,000 703,000 703,000 Cannonball Path 210,000 - - 730,000 - - Cap City Trail 1,140,000-360,000 - - 910,000 Ice Age Junction

More information

CITY MANUALS AND STANDARDS REVIEW

CITY MANUALS AND STANDARDS REVIEW GEORGETOWN SIDEWALK MASTER PLAN CITY MANUALS AND STANDARDS REVIEW RESOURCES AND STANDARDS As part of the Master Plan process, a review and evaluation of current City documents and policies relevant to

More information

City of Waterloo Complete Streets Policy

City of Waterloo Complete Streets Policy City of Waterloo Complete Streets Policy Chris Hodgson P. Eng City of Waterloo Complete Streets Forum 2011 April 28-29 Toronto Waterloo context: Current population Major employers Universities and student

More information

PEDESTRIAN ACTION PLAN

PEDESTRIAN ACTION PLAN ATTACHMENT 2 CITY OF SANTA MONICA PEDESTRIAN ACTION PLAN CITY OF SANTA MONICA PEDESTRIAN ACTION PLAN This page intentionally left blank EXECUTIVE SUMMARY CHAPTER 1 EXECUTIVE SUMMARY Setting the Stage

More information

Public Facilities & Services

Public Facilities & Services Public Facilities & Services This Chapter will inventory the municipal facilities and public services available to Windham residents, whether they are provided by the Town, a public utility like the Portland

More information

Americans with Disabilities Act Transition Plan for Public Right-of-Way Improvements

Americans with Disabilities Act Transition Plan for Public Right-of-Way Improvements Americans with Disabilities Act Transition Plan for Public Right-of-Way Improvements Prepared by: Public Works Department Engineering Division October 2015 Table of Contents Section I Introduction.. 3

More information

Lake Waterford Community Association Meeting. November 15, 2016

Lake Waterford Community Association Meeting. November 15, 2016 Lake Waterford Community Association Meeting November 15, 2016 Introduction Staff Introduction Project Overviews - Completed Projects - Pavement Management Program - Pasadena Road Sidewalk Improvements

More information

NM-POLICY 1: Improve service levels, participation, and options for non-motorized transportation modes throughout the County.

NM-POLICY 1: Improve service levels, participation, and options for non-motorized transportation modes throughout the County. Transportation PRINCE WILLIAM COUNTY 2008 COMPREHENSIVE PLAN NON-MOTORIZED PLAN CONTENTS Goals, Policies, and Action Strategies Table 4 (Bike Facility Classifications and Descriptions) Table 5 (Bike Facility

More information

Recommended Roadway Plan Section 2 - Land Development and Roadway Access

Recommended Roadway Plan Section 2 - Land Development and Roadway Access Recommended Roadway Plan Section 2 - Land Development and Roadway Access SECTION 2 Land Development and Roadway Access 2.1 Land Use and Access Management The Federal Highway Administration (FHWA) defines

More information

San Francisco s Capital Plan & the Mayor s Transportation Task Force 2030: Funding the next steps for transportation

San Francisco s Capital Plan & the Mayor s Transportation Task Force 2030: Funding the next steps for transportation San Francisco s Capital Plan & the Mayor s Transportation Task Force 2030: Funding the next steps for transportation San Francisco Capital Needs In 2006, the Mayor and Board of Supervisors approved San

More information

CURBSIDE ACTIVITY DESIGN

CURBSIDE ACTIVITY DESIGN 5 CURBSIDE ACTIVITY DESIGN This chapter provides design guidance for separated bike lanes adjacent to curbside activities including parking, loading and bus stops. Typical configurations are presented

More information

Fahmida Ahmed Director, Office of Sustainability Department of Sustainability & Energy Management Stanford University

Fahmida Ahmed Director, Office of Sustainability Department of Sustainability & Energy Management Stanford University Fahmida Ahmed Director, Office of Sustainability Department of Sustainability & Energy Management Stanford University Sustainability at Stanford: Research and Action The Initiative on Environment and Sustainability

More information

Engineering - Bicycle and Pedestrian

Engineering - Bicycle and Pedestrian Capital Improvement Plan Project Summary # Bikeways Program 781,000 860,000 900,000 933,000 933,000 933,000 # Cannonball Path 1,200,000-780,000 - - - # Capital City Trail - 70,000 - - 910,000 - # Goodman

More information

TRANSPORTATION ALTERNATIVES PROGRAM: SELECTED PROJECTS AND FUNDING ALLOCATIONS

TRANSPORTATION ALTERNATIVES PROGRAM: SELECTED PROJECTS AND FUNDING ALLOCATIONS ITEM #9: TRANSPORTATION ALTERNATIVES PROGRAM: SELECTED PROJECTS AND FUNDING ALLOCATIONS The Transportation Alternatives Program (TAP) created by MAP-21 requires that 50% of the program funds received by

More information

Operations -- Transit From: N/A To: N/A. Improvement Type: Regionally Significant: No

Operations -- Transit From: N/A To: N/A. Improvement Type: Regionally Significant: No Central Puget Sound Regional 2017-2020 Transportation Improvement Program Amendments and Corrections to be included in the 2017-20 STIP PSRC's Amendment 2017-08 County: King List of 17-08 Amendment Projects:

More information

limburg.be Quality monitoring of the tourist cycle network in Limburg

limburg.be Quality monitoring of the tourist cycle network in Limburg Quality monitoring of the tourist cycle network in Limburg Since 1995 Best overall cycling province in Belgium, 8 years Very important factors for users: - Width of cycle paths - Absence of motorised

More information

Access requests to County streets and roadways are processed through one of the following methods:

Access requests to County streets and roadways are processed through one of the following methods: 13.1 GENERAL APPLICATION PROCESS Access requests to County streets and roadways are processed through one of the following methods: A. Planned Developments may set general locations for access points.

More information

ADA TRANSITION PLAN 2013

ADA TRANSITION PLAN 2013 ADA TRANSITION PLAN 2013 TABLE OF CONTENTS Contents Introduction 1 Purpose 2 Identified Obstacles to the Public Right of Way 3 Criteria for Determining Impediments at Village Facilities 4 Removing Barriers

More information

Bicycle and Pedestrian Connectivity Study. Old Colony Planning Council

Bicycle and Pedestrian Connectivity Study. Old Colony Planning Council Bicycle and Pedestrian Connectivity Study Old Colony Planning Council Outline Why consider bike/peds in road designs? Why are measures needed? Connecting Land Use with Transportation Evaluation Tools:

More information

Paul Vraney Bureau of Project Development 02/11/2016

Paul Vraney Bureau of Project Development 02/11/2016 Paul Vraney Bureau of Project Development 02/11/2016 ADA background & alterations definition Design considerations Provide sufficient layout data Curb ramp selection Maximum curb ramp and gutter slopes

More information

Pedestrian Project List and Prioritization

Pedestrian Project List and Prioritization To: Kyle Wagenschutz, City of Memphis CC: From: Anne Conlon and John Cock, Alta Planning + Design Date: December, 2014 Re: Project List Development (Task 3.1-3.2) and Project List Prioritization (Task

More information

SIDEWALK INSPECTION AND MANAGEMENT SYSTEM

SIDEWALK INSPECTION AND MANAGEMENT SYSTEM SIDEWALK INSPECTION AND MANAGEMENT SYSTEM Department of Public Works City of Fort Lauderdale Page 1 of 23 Agenda Background and Current Challenges Sidewalk Assessment Results Sidewalk Assessment Costs

More information

First and Last Mile Plan. April 2016

First and Last Mile Plan. April 2016 First and Last Mile Plan April 2016 1 First and Last Mile refers to the portion of a transit trip between a transit stop and one s destination, and can include walking, biking, carpooling, rolling or driving,

More information

BYPAD. Bicycle Policy Audit CITY OF GENT March Summary. Tim Asperges Liesbeth Reekmans. Langzaam Verkeer

BYPAD. Bicycle Policy Audit CITY OF GENT March Summary. Tim Asperges Liesbeth Reekmans. Langzaam Verkeer BYPAD Bicycle Policy Audit CITY OF GENT March 2004 Summary Tim Asperges Liesbeth Reekmans Langzaam Verkeer 1. INTRODUCING THE CITY OF GENT The city of Ghent is a medium-sized Flemish city with 230 000

More information

Philip Schaffner Minnesota Department of Transportation October 22, 2013

Philip Schaffner Minnesota Department of Transportation October 22, 2013 Philip Schaffner Minnesota Department of Transportation October 22, 2013 Going beyond performance measures & targets MnDOT has been using performance-based planning and programming for 10 years, but CIMS

More information

[ Fundación PONS ] [ Fundación PONS ] [ Expertise PONS ] Investing in road safety

[ Fundación PONS ] [ Fundación PONS ] [ Expertise PONS ] Investing in road safety With more than 60 years experience, PONS is a leading company in the fields of road safety and sustainable transportation planning, providing worldwide support with auditing, consultancy and training services,

More information

Fiscal Year Budget Overview

Fiscal Year Budget Overview Fiscal Year 2015-2016 Budget Overview Investing in Transportation for Today and Tomorrow Ed Reiskin Director of Transportation APRIL 1, 2014 San Francisco: great city, excellent transportation choices

More information

Smoothing Out the Bumpy Road Ahead

Smoothing Out the Bumpy Road Ahead Julie Hannah, P.E. Technical Services and Asset Management May 11, 2017 Smoothing Out the Bumpy Road Ahead Nationwide D = Poor, At Risk Conditions & Capacity Pavement Condition & Congestion Nationwide

More information

FY 2016 TRANSPORTATION ALTERNATIVES PROGRAM PROJECT SELECTION

FY 2016 TRANSPORTATION ALTERNATIVES PROGRAM PROJECT SELECTION AGENDA ITEM #8: FY 2016 TRANSPORTATION ALTERNATIVES PROGRAM PROJECT SELECTION The Transportation Alternatives Program (TAP) created by MAP-21 requires that 50% of the program funds received by the state

More information

TOWN OF PORTLAND, CONNECTICUT COMPLETE STREETS POLICY

TOWN OF PORTLAND, CONNECTICUT COMPLETE STREETS POLICY TOWN OF PORTLAND, CONNECTICUT COMPLETE STREETS POLICY I. VISION, GOALS & PRINCIPLES VISION To improve the streets of Portland making them safer and more accessible for all users including pedestrians,

More information

TRAVEL PLAN: CENTRAL EUROPEAN UNIVERSITY CAMPUS REDEVELOPMENT PROJECT TRAVEL PLAN. Central European University Campus Redevelopment Project.

TRAVEL PLAN: CENTRAL EUROPEAN UNIVERSITY CAMPUS REDEVELOPMENT PROJECT TRAVEL PLAN. Central European University Campus Redevelopment Project. TRAVEL PLAN Central European University Campus Redevelopment Project Page 1 Table of Contents Introduction... 3 Background... 7 Building Users... 7 Transportation in Community Consultation... 7 Summary

More information

MOBILITY RESULTS AREA. Budgeting For Outcomes Council Presentation January 12, 2007

MOBILITY RESULTS AREA. Budgeting For Outcomes Council Presentation January 12, 2007 MOBILITY RESULTS AREA Budgeting For Outcomes Council Presentation January 12, 2007 Mobility Results Team Members 2 Hammond Perot, OED, Co-Team Leader Bonnie Meeder, DEV (returning), Co-Team Leader Peer

More information

Montclair s Complete Streets Experience

Montclair s Complete Streets Experience Presented by: Hon. Jerry Fried, Mayor Montclair Township About Montclair Six square miles Six commuter rail stations Four local bus routes (NJ Transit) Two private commuter bus routes Five business districts

More information

ADA Training Accessible Pedestrian Signal (APS) 2018 MnDOT

ADA Training Accessible Pedestrian Signal (APS) 2018 MnDOT ADA Training Accessible Pedestrian Signal (APS) 2018 MnDOT APS and ADA APS is not currently an ADA Standard and is provided at the discretion of the Title II entity APS is recognized in the MnMUTCD, but

More information

10.0 CURB EXTENSIONS GUIDELINE

10.0 CURB EXTENSIONS GUIDELINE 10.0 CURB EXTENSIONS GUIDELINE Road Engineering Design Guidelines Version 1.0 March 2017 City of Toronto, Transportation Services City of Toronto Page 0 Background In early 2014, Transportation Services

More information

East Burke Transportation, Safety and Capacity Improvements

East Burke Transportation, Safety and Capacity Improvements East Burke Transportation, Safety and Capacity Improvements The purpose of this project is to increase mobility and improve safety for pedestrians, cyclists, and motor vehicles along VT Route 114 in the

More information

Toronto Public Library

Toronto Public Library Toronto Public Library Capital Budget Board Meeting May 25, 2015 TPL Capital Budget Process Planning Framework Development of Capital Plan Approvals Debt Targets SOGR Capital Completion Rate 2016 Budget

More information

DRAFT MOVING FORWARD RHODE ISLAND BICYCLE MOBILITY PLAN 2018 PREPARED FOR PREPARED BY IN ASSOCIATION WITH

DRAFT MOVING FORWARD RHODE ISLAND BICYCLE MOBILITY PLAN 2018 PREPARED FOR PREPARED BY IN ASSOCIATION WITH RHODE ISLAND MOVING FORWARD BICYCLE MOBILITY PLAN 2018 PREPARED FOR PREPARED BY IN ASSOCIATION WITH T AF CHAPTER 1 D R INTRODUCTION CHAPTER 3 ARTICULATES VISION Bicycling is safe, fun and practical in

More information

Fulton Market Streetscape

Fulton Market Streetscape Fulton Market Streetscape Ogden Avenue to Halsted Street Public Meeting Recommended Improvements December 10th, 2014 Meeting Purpose and Goals Present Existing Conditions Community Input and Charrette

More information

Pavement Management Report. City Council Meeting of May 21, 2013

Pavement Management Report. City Council Meeting of May 21, 2013 Pavement Management Report City Council Meeting of May 21, 2013 Previous Meetings Summary In February, we presented the 2012 pavement survey and our consultant presented general pavement management strategies

More information

Delivering the. Strategy 7.0

Delivering the. Strategy 7.0 7.0 Delivering the Strategy 7.1 Introduction This chapter presents a framework for the delivery of the strategy. Key challenges and opportunities are identified that will have an impact on the successful

More information

ADA Operations Contact Info

ADA Operations Contact Info Intro ADA Operations Contact Info Todd Grugel ph: 651-366-3531 email: todd.grugel@state.mn.us Joe Zilka ph: 651-366-3311 email: joseph.zilka@state.mn.us Harvey Unruh ph: 651-216-2912 email: harvey.unruh@state.mn.us

More information

Community Development and Recreation Committee. General Manager, Parks, Forestry and Recreation. P:\2015\Cluster A\PFR\CD AFS#22685

Community Development and Recreation Committee. General Manager, Parks, Forestry and Recreation. P:\2015\Cluster A\PFR\CD AFS#22685 CD10.2 STAFF REPORT ACTION REQUIRED City of Toronto Outdoor Tennis Operations Date: February 19, 2016 To: From: Wards: Reference Number: Community Development and Recreation Committee General Manager,

More information

4. Mobility and Transportation Element. Page Bikes and Pedestrians

4. Mobility and Transportation Element. Page Bikes and Pedestrians Below are the specific General Plan text changes proposed for A-16-015 and the proposed changes to Figure MT-2 Paths and Trails. In general changes consist of removing references to the Bicycle, Pedestrian

More information

Welcome. Background. Goals. Vision

Welcome. Background. Goals. Vision Welcome The formal Public Information Centre (PIC) for the Transportation Master Plan How We GO will be held in early 2017. At that time we will present the recommended transportation system for Niagara

More information

CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF NOVEMBER 15, 2016

CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF NOVEMBER 15, 2016 CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF NOVEMBER 15, 2016 Item 6, Report No. 38, of the Committee of the Whole, which was adopted without amendment by the Council of the City of Vaughan

More information

HARRISON STREET/OAKLAND AVENUE COMMUNITY TRANSPORTATION PLAN

HARRISON STREET/OAKLAND AVENUE COMMUNITY TRANSPORTATION PLAN HARRISON STREET/OAKLAND AVENUE Community Workshop #4: Draft Plan Review December 3, 2009 D E S I G N, C O M M U N I T Y & E N V I R O N M E N T INTRODUCTIONS Key Project Staff: Alisa Shen, Project Manager,

More information

RZC Appendix 8A Marymoor Subarea Street Requirements

RZC Appendix 8A Marymoor Subarea Street Requirements RZC Appendix 8A Marymoor Subarea Street Requirements For additional design details for Marymoor Subarea infrastructure, refer to the 2017 Marymoor Subarea Infrastructure Planning Report. STREET REQUIREMENTS

More information

Trail Feasibility. 1. Introduction FINAL. October What s inside?

Trail Feasibility. 1. Introduction FINAL. October What s inside? VOLUSIA COUNTY MPO CITY OF PORT ORANGE FINAL Trail Feasibility October 2006 What s inside? 1 Introduction 2 Project Purpose & Scope 3 Physical Inventory & Assessment of Right-of- Way 4 Trail Concept Plan

More information