1 OAI Model 200 Tabletop Mask Aligner Portland State University WARNING: This machine exposes users to ultraviolet radiation. Do not touch the lens underneath the lamp hood as it may damage the machine and cause sever burns. Exposure to pressurized gas, high voltage electricity and mercury vapor may result from improper use of this equipment. Recommended Apparel: Eyewear rated to 400nm, clean room suits and nitrile gloves are required in this lab environment. For additional safety and emergency information please reference the last page of this manual and the appropriate manufacturer documentation.
2 Preliminary Set Up: Image of pressure buttons Image of exhaust fan 1) Check that the primary systems are connected to a wall outlet and that any power strips or surge protectors in their path are activated. 2) Verify that the vacuum and compressed gas feeds are turned on. If either of these are not working then check that the vacuum pump is on, its valve is open and that the nitrogen gas pressure is at 60 psig. 3) Move the microscope platform to the back of the tabletop and mask aligner platform completely to the right by using the black pressure buttons. 4) Make sure that the ozone exhaust fan in the lamp hood is now on and that the vent tube is securely in place before continuing to the lamp warmup. 5) Set the timer to 1 second and turn it on to enable use of the mask assembly. The shutter will open momentarily. Keep the timer switch on throughout this tutorial. Warmup Procedure: 1) Power on the constant intensity controller, using the large switch. 2) Set Current-Voltage (CV) selector to VOLTS, Intensity-Power (IP) selector to WATTS and the mode to Constant Intensity (CI). 3) Briefly depress the Start switch to turn the lamp on, you will hear a clicking sound. 4) Allow the lamp to warm up for about 10 minutes before moving on with this section of the manual. Please take this time to work through the mask, substrate and alignment procedures. Cooling Diagnostic: 1) After 10 minutes have elapsed the lamp power indicator will probably read between somewhere between 375W-625W. 2) To check if the lamp is operating properly adjust the power knob to set the machine to 500W (rated wattage), flip the CV switch to measure VOLTS and verify that it reads
3 Rated Voltage: Check this out to make sure. 340V± 2.0V. This diagnostic indicates if the lamp is overcooled (<338V ) or undercooled (>342V). 3) In the unlikely event that a cooling problem is found then ask a professor or look in the OAI manuals for directions on adjusting the airflow damper. Open or close this damper to manipulate the voltage back into the proper 4V range before continuing with any experiments. 4) Set the power draw to 450W (idle rating) until ready to preform an exposure, at which point one should readjust this setting to meet experimental parameters. Mask Placement: *Nitrile gloves are mandatory for this section.* 1) Make sure that the mask is cleaned of particulates before installing. 2) Loosen the six placement screws on top of the mask assembly and remove any placeholder material. 3) Place the mask underneath the clamps with the emulsion side down and push it flush against all three alignment pins. 4) A square cutout slid between the mask and the placement brackets may be used to help keep the mask level, secure and limit the exposure area. 5) When the mask is in place, tighten the placement screws enough to mitigate movement but not so much that they bend the surface. 6) If the mask is set at an angle to the front of the module then loosen the thumbscrews on either side of the frame to rotate it until it is parallel to the front of the machine. 7) Push in the Mask Vacuum button to affix the mask to the frame. Intensity Reading: *All recommended apparel should be used in section.* 1) Flip the IP switch to mw/cm^2 and verify the reading of ) Set a UV probe in the center of the exposure plane (on top of the mask assembly). 3) Set exposure timer to 5-10 seconds and check that the CIC is on constant intensity mode.
4 4) Move the assembly and probe under the lamp to activate the shutter and get a baseline reading. 5) If the system has not been calibrated recently then continue with the steps 6-9, otherwise skip to step 10. 6) Set the CIC to CP mode and channel A. 7) Open the shutter and adjust corresponding CAL knob until that the intensity reading on the probe and CIC are approximately equal. 8) Switch back to CI mode and turn the SET knob both clockwise and counter clockwise (higher and lower intensity) to verify that the power supply is accurately tracking the changes seen on the probe. If the tracking is faulty then reattempt the previous step to obtain a better equivalency setting. 9) Switch to channel B and repeat steps 6 and 7 to finish calibrating the device. 10) Check that the readings are within experimental parameters and use the SET control to readjust the desired intensity as need. Both channels A and B can be preconfigured to different values if so desired. Substrate Placement: *Nitrile gloves mandatory for this section.* 1) Move the microscope arm to the far back corner of the bench and then the mask assembly to the far right. The microscope has two movement handles so be sure to use the one closest to the surface of the table top. The mask frame will not open if the microscope is near it. 2) Flip the Mask Frame switch to the Open position and it should automatically rise about 40º. If the frame does not open immediately then recheck that the timer switch is on and that the microscope/mask assemblies are in their proper storage positions. 3) Once the frame is open, place the substrate chip in the middle of the vacuum chuck completely covering the + sign in its center. 4) The chip, like the mask, should be set parallel to the front of the aligner. Any patterning from previous exposures should be oriented to match the current the mask.
5 5) Use the Sub. Vac switch to secure the substrate to the mask aligner. 6) Close the mask frame. Mask Alignment: 1) Rotate the lens selector on the microscope to the empty slot so that it has ample clearance when passing over the placement screws on the mask holder. 2) The microscope should not hit the mask frame when it is in use so adjust the height accordingly. 3) Move the mask assembly slightly to the left so that it is lines up with the microscope. 4) Using the lower movement handle on the microscope arm to pull it forward above the mask. 5) Flip the Ball Vac switch to the unlock position to allow for raising of the substrate. 6) Thee Chuck Z Adjust has a D.C. ammeter read out and is controlled by the belt equipped knob on the front of the alignment module. 7) Turn the Chuck Z Adjust knob clockwise until a reading of ma is had. 8) Select the lowest magnification on the microscope and set the light source to about 50% power. 9) Use the control handle on the upper arm of the microscope assembly to orient the microscope more precisely. The top and bottom buttons allow for small modifications in the Y and X direction respectively. Be careful when using these controls because the light and power sources may get damaged or disconnected if this piece too quickly or far from their initial position. 10) Adjust the microscope till the mask can be seen with both eyes and then focus the optics as needed. The lowest magnification is good for setup and to finding alignment features because it has the best field depth and view. Once the microscope is in focus it will remain that way regardless of magnification changes. 11) Turn the black knob on front of the alignment module (not the Chuck Z Adjust) and view the substrate raising and leveling through the microscope. 12) Once the substrate reaches the mask a significant resistance will be felt in the knob, the belt will stop moving and the chuck should become level. 13) Lock the Ball Vac into position and prepare for final alignment.
6 14) Use the three long stemmed adjustment bars around the outside of the assembly to lower and then precisely align the substrate and mask. The middle bar controls the Y- Axis, the right controls the X and the far left controls rotation, theta. The movements are on the scale of micrometers so it is most beneficial when the microscope is in focus during these adjustments. 15) Raise the substrate with the previously used black knob until contact is made. This is known as making soft contact. The hard contact switch can be thrown to increase resolution but it will cause a residue to form on the mask after exposure. 16) Turn on the Contact Vac to lock in the final changes and prepare for exposure. 17) Rotate microscope lens to the empty compartment and carefully return the arm to its storage position, this can probably be done without changing the elevation of the arm. 18) Turn off the alignment optic power unit. Exposure: *All recommended apparel should be used in this section.* 1) Set the timer to the desired exposure time. 2) Double check power and intensity settings. 3) Move the assembly completely underneath the hood to activate the lamp. To avoid severe burns, do not touch the lamp or hood while in operation or shortly thereafter. 4) Wait for the lamp to finish its exposure and then move the assembly back to its alignment position. Substrate Removal: *Nitrile gloves are mandatory for this section.* 1) Turn off the Hard Contact switch if it was used during the exposure. 2) Turn off the Contact Vac. Adjust switch. 3) Close the contact vacuum by fully rotating the Contact Vac. Adjust valve clockwise. 4) If the substrate is sticking to the mask then turn on the Nitrogen Purge switch and open the Nitrogen Purge Flow Valve for 5-10 seconds to break the adhesion.
7 5) Lower the substrate from the mask using the black knob to avoid accidental contact in later trials. 6) Check that the alignment optics are in storage position. 7) Open the mask frame and turn off the Sub. Vac. 8) Carefully remove the substrate and then close the mask frame. 9) Turn the timer off. Mask Removal: *Nitrile gloves are mandatory for this section.* 1) Loosen the six thumbscrews on top of the mask assembly. 2) Turn off the mask vacuum and remove the mask. Shutdown: 1) If the lamp is going to be use again with the hour then set its power the idle amount of 450W. 2) If the lamp is no longer needed then turn off the power switch on the constant intensity controller. 3) Close the vacuum valve and turn off the vacuum pump. 4) Turn off the compressed gas source. 5) Turn off the external power strip or surge protecter connecting to the main apparatus. Emergency Procedure: 1) The lab should be evacuated immediately whenever an explosion occurs, the lamp malfunctions or smoke can be detected. 2) Shut down electric and gas connections at their external source. 3) Notify an instructor or any other relevant authority of the situation and make mention of a possible mercury vapor leak. 4) If a clean up is to be attempted then use a chemical respirator, full body clean suit, proper lab goggles, double layered nitrile gloves and a syringe capable of picking up liquid mercury. Safety Measures: 1) Protective eyewear should be rated to 400nm (most sunglasses meet this specification).
8 2) Full body clean suits are both required in most cleanroom environments and ideal in use of this machine. In lieu of a ʻbunny suitʼ, lab coats and long pants can provide sufficient UV protection but may contaminate nearby experiments. 3) Nitrile gloves are appropriate at this work station and may be double layered for additional protection. 4) Cosmetics are strictly prohibited in the cleanroom but certain sunscreens may be permitted at instructor discretion. Please reference OAI manuals for more information pertaining to setup, experimental, safety and emergency procedures.
Warnings: Notes: Revised: January 8,
OAI Model 204IR Mask Aligner Standard Operating Procedure Faculty Supervisor: Prof. Robert White, Mechanical Engineering (x72210) Safety Office: Peter Nowak x73246 (Just dial this directly on any campus
More informationStandard Operating Manual
Standard Operating Manual AB-M Mask Aligner Version 1.1 Page 1 of 18 Contents 1. Picture and Location 2. Process Capabilities 2.1 Cleanliness Standard 2.2 Wafer Chuck Selection 2.3 Mask Holder Selection
More informationApproved by Principal Investigator Date: Approved by Super User: Date:
Approved by Principal Investigator Date: Approved by Super User: Date: Standard Operating Procedure BNC OAI 200 Lithographic Mask Aligner (Aligner 3) Version 2011 June 2 I. Purpose This Standard Operating
More informationSOP for Karl Suss MJB3 #1 Mask Aligner
SOP for Karl Suss MJB3 #1 Mask Aligner Rev. 5 (30/11/2016) Safety UV Exposure: The high-energy light produced by the high-pressure Mercury Xenon lamp can cause eye damage and skin burns. Be sure that the
More informationKARL SUSS MJB3 MASK ALIGNER STANDARD OPERATING PROCEDURE
KARL SUSS MJB3 MASK ALIGNER STANDARD OPERATING PROCEDURE Purpose of this Instrument: This instrument is for patterning photosensitive polymers with UV light. Location: White Hall 410 Cleanroom Primary
More informationKarl Suss MA6 Mask Aligner SOP
Page 1 of 11 Karl Suss MA6 Mask Aligner SOP Safety UV Exposure: The high energy light produced by the high pressure Mercury Xenon lamp can cause eye damage and skin burns. Be sure that the light guards
More informationMJB4 Mask Aligner Operating Procedure. Effective Date: 07/12/2012 Author(s): Jiong Hua Phone:
MJB4 Mask Aligner Operating Procedure Effective Date: 07/12/2012 Author(s): Jiong Hua Phone: 402-472-3773 Email: jhua2@unl.edu 1 1 Introduction 1.1 Key Words Karl Suss MJB4 Mask Aligner, Optical Lithography,
More informationWarnings: Notes: Revised: October 5, 2015
Karl Suss MA6 Mask Aligner Standard Operating Procedure Faculty Supervisor: Prof. Robert White, Mechanical Engineering (x72210) Safety Office: Peter Nowak x73246 (Just dial this directly on any campus
More informationApproved by Principal Investigator Date: Approved by Super User: Date:
Approved by Principal Investigator Date: Approved by Super User: Date: Standard Operating Procedure BNC OAI Lithographic Mask Aligner (Aligner 2) Version 2008 October 31 I. Purpose This Standard Operating
More informationKARL SUSS MJB3 UV400 Mask Aligner Standard Operating Procedure
KARL SUSS MJB3 UV400 Mask Aligner Standard Operating Procedure Version: 1.0 February 2014 UNIVERSITY OF TEXAS AT ARLINGTON Nanotechnology Research Center (NRC) 1 TABLE OF CONTENTS 1 Introduction 3 1.1
More informationMJB-3 Mask Aligner Property of TAU MNCF August 2012
MJB-3 Mask Aligner I. Power Up Sequence 1 LOG IN. Turn on Nitrogen & compressed air lines on the back wall. 2 Turn on the vacuum pump. 3 Flip the COMPRESSED AIR toggle on (up) Compressed air is used to
More informationUsage Policies Notebook for Karl Suss MA6 Mid / Deep UV Mask Aligner
Usage Policies Notebook for Karl Suss MA6 Mid / Deep UV Mask Aligner Revision date September 2014 2 Emergency Plan for Karl Suss MA6 Aligner Standard Operating Procedures for Emergencies Contact information
More informationABM MASK ALIGNERS. NanoFab 26 March 2009 A Micro Machining & Nanofabrication Facility
ABM MASK ALIGNERS LOCATION: Optical Lithography PRIMARY TRAINER: Stephanie Bozic (2-6724, sbozic@ualberta.ca) SECONDARY TRAINER: Jolene Chorzempa (2-4823, jolenec@ualberta.ca) 1. OVERVIEW The ABM Mask
More informationStandard Operating Manual
Standard Operating Manual Karl Suss MA6 Mask Aligner Version 1.1 Page 1 of 24 Contents 1. Picture and Location 2. Process Capabilities 2.1 Cleanliness Standard 2.2 Substrate Size 2.3 Photo Mask Size 2.4
More informationQuintel Mask Aligner
Quintel Mask Aligner (quintel) 1.0 1.0 Title Quintel Q4000 Mask Aligner 2.0 2.0 Purpose The Quintel Q4000 MA (Mask Aligner) is a top and bottom side contact lithography printer with the video-view split
More informationKarl Suss MJB4 Mask Aligner
Karl Suss MJB4 Mask Aligner Tool Manager: Yong Sun ( yongs@princeton.edu; Office 8-8234; Cell 609-917-5076 ) Backup: George Watson ( gwatson@princeton.edu; Office 8-4626; Cell 732-996-2713 ) ******************************************************************************
More informationEquipment Standard Operating Procedure Greg Allion and Kimberly Appel
Date Created: May 3, 2004 Date Modified: June 1, 2005 MA6/BA6 Mask Aligner Equipment Standard Operating Procedure Greg Allion and Kimberly Appel 1. Purpose 1.1. Photolithography involves transferring a
More informationCOBILT CA-800 Mask Aligner Equipment Operation
COBILT CA-800 Mask Aligner Equipment Operation For the Micro-Electronics Laboratory At University of Notre Dame Department of Electrical Engineering This user manual is not be removed from room 247A. This
More informationOperation of the contact mask aligner Canon PPC 210 Projection Print Camera
Operation of the contact mask aligner Canon PPC 210 Projection Print Camera Start-up Procedure: 1. Start the grey pump in the service corridor behind the aligner 2. Open the valve for the Nitrogen gas
More informationUniversity of Minnesota Nano Fabrication Center
Equipment name: Karl Suss Mask Aligners Badger name: MA6-P Revision number: 0 Model: MA6 Revisionist: Paul Kimani Location: Bay 4 PAN Date: September 17, 2015 1. Introduction The Karl Suss MA6-PAN is a
More informationOperation of the mask aligner MJB-55
John Paul Adrian Glaubitz Operation of the mask aligner MJB-55 Department of Physics Faculty of Mathematics and Natural Sciences University of Oslo 1 Introduction The mask aligner is an essential tool
More informationO P E R ATING INSTRUCTIONS FOR MODEL SPR-45 Automatic Screen and Stencil Printer
O P E R ATING INSTRUCTIONS FOR MODEL SPR-45 Automatic Screen and Stencil Printer TABLE OF CONTENTS I. SPECIFICATIONS...3. II. SAFETY INSTRUCTIONS...4. III. INSTALLATION...5. IV. SET-UP...6. V. SYSTEM OPERATION...9.
More informationSomnoSuite FAQ. Setup. Calibration 4. What are the calibration requirements for the SomnoSuite? Settings
SomnoSuite FAQ V1.3 January 2015 Setup 1. How do I connect the SomnoSuite to my oxygen source? 2. Is there a way to speed up the downward movement of the pusher block when setting the empty position? 3.
More informationUniversity of Minnesota Nano Fabrication Center
Equipment name: Karl Suss Mask Aligners Badger name: MA6 & Maba6 Revision number: 4 Models: Revisionist: Paul Kimani Location: Bay 2 Date: April 25, 2013 1. Introduction The Karl Suss MA6 and MABA6 are
More informationMisaligned Folds Paper Feed Problems Double Feeds Won t Feed FLYER Won t Run iii
Operator s Manual Table of Contents Operator Safety... 1 Introduction... 2 Unpacking and Setup... 3 Unpacking... 3 Setup... 4 FLYER Overview... 5 FLYER Diagram... 5 Capabilities... 5 Control Panel... 6
More informationStandard Operating Procedure #COE-SOP-0001 Chemical Fume Hood Operation
Standard Operating Procedure # Chemical Fume Hood Operation Facility: NMSU College of Engineering Laboratories Written by: Juanita Miller, Safety Specialist, miljgh@nmsu.edu (575)-646-1292 Scope: This
More informationKarl Suss Contact Aligner Operation
Karl Suss Contact Aligner Operation Roger Robbins 6/31/2008 2 nd ed. 3/12/2009 The University of Texas at Dallas Erik Jonsson Engineering School of Engineering TITLE: Karl Suss Contact Aligner Operation
More informationOerlikon Sputtering Evaporator SOP
Oerlikon Sputtering Evaporator SOP Short UNT Cleanroom 1. Taking out sample holder from Transport Chamber : Log in FOM to access the software Go to the software and log in with user1 and password user1
More informationLogin to ilab Kiosk. Revised 05/22/2018. Load your sample:
Login to ilab Kiosk Load your sample: 1. Check: The analysis chamber pressure is
More informationApproved by Principal Investigator Date: Approved by Super User: Date:
Approved by Principal Investigator Date: Approved by Super User: Date: Standard Operating Procedure BNC Commonwealth Dual Ion Beam Deposition System (CDIBS) Version 2010 February 14 I. Purpose This Standard
More informationUsage Policies Notebook for NanoFurnace Furnace (EasyTube 3000 System)
Usage Policies Notebook for NanoFurnace Furnace (EasyTube 3000 System) Revision date October 2014 2 Emergency Plan for Nano Furnace Standard Operating Procedures for Emergencies Contact information Person
More informationBASIC RULES OF USAGE, OLIS DSM-20 CD Management The instrument is currently managed by the Analytical Biophysics Core Facility.
Olis DSM-20 instructrions and rules p. 1 BASIC RULES OF USAGE, OLIS DSM-20 CD Management The instrument is currently managed by the Analytical Biophysics Core Facility. Signup On a first-come, first-served
More information5.1.3 Mechanical Hazards Drive assemblies have sufficient power to cause injury. Keep hands, fingers, clothing and tools clear of moving parts.
Approved by: Process Engineer / / / / Equipment Engineer 1 SCOPE The purpose of this document is to detail the use of the PE4400. All users are expected to have read and understood this document. It is
More informationInstructions for Assembly, Installation, and Operation of the Gas Addition Kit Accessory with the CEM Discover Systems
Corporation Issued: 5/09 P/N: 600104 Rev. 2 Instructions for Assembly, Installation, and Operation of the Gas Addition Kit Accessory with the CEM Discover Systems The Gas Addition Accessory permits the
More informationicreasepro Creaser Operators Manual
6-2013 Version 3.0 icreasepro Creaser Operators Manual WWW.MBMCORP.COM 800-223-2508 TABLE OF CONTENTS SPECIFICATIONS.1a SAFETY PROCEDURES/CARE & MAINTENANCE..1b COMPONENT IDENTIFICATION 2 TOUCH SCREEN
More informationSPUTTER STATION STANDARD OPERATING PROCEDURE
SPUTTER STATION STANDARD OPERATING PROCEDURE Purpose of this Instrument: This instrument is used for deposition of thin metal or oxide films. Source materials supplied by WVU Shared Research Facilities:
More informationSection 3- Repair and Calibration Procedures
Section 3- Repair and Calibration Procedures 1. Refrigerant Removal Procedures 2. Scale/PC Board Recalibration Procedure 3. PC Board Configuration Procedure of AR400 4. Scale Tare Procedure 5. Gauge Calibration
More informationStandard Operating Manual
Standard Operating Manual Fisher Scientific Isotemp TM Model 281A Vacuum Oven Version 1.1 Page 1 of 9 Contents 1. Picture and Location 2. Process Capabilities 2.1 Cleanliness Standard 2.2 Substrate Size
More informationOPERATION OF THE DIMPLER
OPERATION OF THE DIMPLER After thinning your sample to ~80 μm you can now do a dimpling process to thin the center up to 10 μm. When you walk in and use the DIMPLER it should already be calibrated and
More informationTitle: Xactix XeF2 Etcher Semiconductor & Microsystems Fabrication Laboratory Revision: A Rev Date: 03/23/2016
Approved by: Process Engineer / / / / Equipment Engineer 1 SCOPE The purpose of this document is to detail the use of the Xactix XeF2 Etcher. All users are expected to have read and understood this document.
More informationEquipment Operating Procedure Glove Box
Equipment Operating Procedure Glove Box Page 1 0.0 Changing the Compressed Gas Cylinder 1. Complete Compressed Gas Cylinder training from EHS website before manually exchanging gas cylinders. In order
More informationLAMINAR FLAME SPEED ANALYSIS USING PIV (PARTICLE IMAGE VELOCIMETRY)
LAMINAR FLAME SPEED ANALYSIS USING PIV (PARTICLE IMAGE VELOCIMETRY) OPERATIONAL PROCEDURES Venue: Project Room, Hopkinson Lab, CUED Experimental date: 25 March 2008 Prepared by: Cheng Tung Chong (ctc31@camacuk)
More information[USING THE VITROBOT April 9, Using the Vitrobot
Using the Vitrobot The Vitrobot Mk 3 (aka Mark III, Mark 3, etc.) can control both the local temperature and the local humidity during the process of plunge-freezing a grid for cryoem. It does require
More informationPRESSURE SENSOR - ABSOLUTE (0 TO 700 kpa)
Instruction Sheet for the PASCO Model CI-6532A PRESSURE SENSOR - ABSOLUTE (0 TO 700 kpa) 012-06859B 10/98 $1.00 polyurethane tubing syringe cable with DIN s to computer interface quick release s (4) pressure
More informationProduct Information News
Product Information News MMR SECOND STAGE REGULATOR VALVE CORE MSA has changed its recommended rebuilding of the MMR Second Stage Regulator s bypass sleeve assembly during the annual inspection. Based
More informationOPERATION MANUAL RTI RHS650 RTI TECHNOLOGIES, INC East Market Street York, PA Manual P/N
OPERATION MANUAL RTI RHS650 RTI TECHNOLOGIES, INC. 4075 East Market Street York, PA 17402 Manual P/N 035-80589-02 Table of Contents Components... 2 Test... 4 Recovery/Recycling... 5 Evacuation... 7 Charging...
More informationInside Front cover This page will remain blank.
Owner s Manual Inside Front cover This page will remain blank. 1 Table of Contents Parts of the AirCAT...3 Assembling the AirCAT...4 Attaching the wheels to the stand...4 Attaching the battery box to the
More informationACV-10 Automatic Control Valve
ACV-10 Automatic Control Valve Installation, Operation & Maintenance General: The Archer Instruments ACV-10 is a precision automatic feed rate control valve for use in vacuum systems feeding Chlorine,
More informationOperating Procedures for Metal Evaporator I
Operating Procedures for Metal Evaporator I Metal Evaporator I is intended as a tool and a training device. Understanding the operation of this equipment should give you a basic knowledge of vacuum and
More information632 AccuPro Set-up & Operation
632 AccuPro Set-up & Operation Always check: Reel & Roller bearings Bent or broken blades Make sure the reel spins freely in the frame Place the Reel Into the Machine There are three lifting options for
More informationTable of Contents. Operating Instructions. Resource v.2 Conserving Regulator
Operating Instructions Table of Contents Resource v.2 Conserving Regulator Safety Information Device Precautions Introduction Product Features Product Specifications Feature Illustrations Set Up Usage
More informationMoveRoll Conveyor Operating and Maintenance Manual
MoveRoll Conveyor Operating and Maintenance Manual 1. Read this first! This manual contains information for protection of personnel in the roll handling area from possible injury and/or equipment damage.
More informationStandard Operating Procedure. For. PVD E-Beam
P a g e 1 Standard Operating Procedure For PVD E-Beam P a g e 2 Introduction The PVD Electron-Beam Evaporator (E-Beam) thin film deposition machine uses a magnetically guided and collimated stream of electrons
More informationR2S Standard Sampling Assembly OPERATION PROCEDURE
PURPOSE 1 of 10 To describe the procedure to monitor for viable airborne bacteria with the Remote-Slit- Sampler Assembly (R2S) from EMTEK, LLC. Principle A 100 mm agar based test plate is placed on the
More informationBirck Nanotechnology Center
EFFECTIVE DATE: October 20, 2016 PAGE 1 of 8 This instruction covers the set-up and use of the bench-top for annealing and oxidizing samples within the cleanroom. 1. SAFETY REQUIREMENTS 1.1 Safety glasses
More informationSolvent System Walkthrough
v2.0 1 Solvent System Walkthrough The Contour Glass solvent system is designed to give you air-free anhydrous solvent with minimal effort. However, the system is only as good as its users so please read
More informationThe SPI Sputter Coater Handbook
The SPI Sputter Coater Handbook Coating of Specimens SPI-Module Sputter Coater with Etch Mode 1. Mount the specimens onto the SEM stub. Keep in mind that many adhesives have high vapor pressure solvents
More informationUSER MANUAL
C Cimarron Sports 1-888-816-6517 www.cimarronsports.com Combo Pitching Machine USER MANUAL TABLE OF CONTENTS Thank you for purchasing the Cimarron Combo Pitching Machine. The Cimarron Combo Pitching Machine
More informationChromat Calibration Updated October 27th, 2017
Chromat Calibration Updated October 27th, 2017 Calibrating the Chromatograph Performing the Chromat Calibration is highly recommended when starting a new well. The MLogger already has a default calibration
More informationRejuvenation Instructions
Rejuvenation Instructions #401 Air Systems UPR This NRI covers the following: Understanding the applications and operation of flow meters. Understand the application and operation of test pressure gauges.
More informationR I T. Title: Amray 1830 SEM Semiconductor & Microsystems Fabrication Laboratory Revision: A Rev Date: 09/29/03 1 SCOPE 2 REFERENCE DOCUMENTS
Fabrication Laboratory Revision: A Rev Date: 09/29/03 Approved by: Process Engineer / / / / Equipment Engineer 1 SCOPE The purpose of this document is to detail the use of the Amray 1830 SEM. All users
More informationApproved by BNC Managing Director Paul Lum Date: Approved by PI (s) /Super User (s): _Peter Hosemann/Andy Minor_Date:
Approved by BNC Managing Director Paul Lum Date: Approved by PI (s) /Super User (s): _Peter Hosemann/Andy Minor_Date: Standard Operating Procedure BNC FEI Quanta 3D FEG/FIB ESEM Version 2011 Aug 30 I.
More informationStandard Operating Manual
Standard Operating Manual Branson IPC 3000 O 2 Asher Copyright 2014 by Hong Kong University of Science & Technology. All rights reserved. Page 1 Contents 1. Picture and Location 2. Process Capabilities
More informationConcentrate Distribution System (Stand Mounted) A-CDS-70-X & A-CDS-TANK-X-ST Industrial Drive, Orlinda, TN 37141
0 Operation Manual Concentrate Distribution System (Stand Mounted) A-CDS-70-X & A-CDS-TANK-X-ST 615-654-4441 sales@specialtyh2o.com 615-654-4449 fax TABLE OF CONTENTS Section 1 GENERAL 1.1 Warnings and
More information1.1 Equipment: substrate, wafer tweezers, metal targets 1.2 Personal Protective Equipment: nitrile gloves, safety glasses 1.
Nanomaster NSC-3000 DC Magnetron Sputter Tool Standard Operating Procedure Faculty Supervisor: Prof. Robert White, Mechanical Engineering (x72210) Safety Office: Peter Nowak x73246 (Just dial this directly
More informationInstallation Instructions
Page 5750-S-1 Installation Instructions General These mounting instructions for Circular INCINO- PAK Burners are in addition to the specific instructions offered for other Maxon component items: Shut-Off
More informationWATER CONTROL SYSTEM QUICK START
SETTINGS MENU SYSTEM OPTIONS WATER LEVEL BAR GRAPH 3 DS SPRAY ON/OFF CS SPRAY ON/OFF BEACON WATER CONTROL SYSTEM QUICK START WWW.GFWORLDWIDE.COM +1 (208) 664-9291 SERVICE@GFWORLDWIDE.COM DISPLAY SCREEN
More informationRegulator for 2 MPa ARX 20. How to Order. Bracket. Pressure gauge. Port size 1/8 1/4. Panel nut
Regulator for 2 MPa RX 2 How to Order RX2 1 Regulator 1 Regulating pressure.5 to.85mpa {.51 to 8.7kgf/cm²}.5 to.3mpa {.51 to 3.1kgf/cm²} Thread type Nil N F Rc(PT) NPT (PF) Port size 1 2 ccessories/options
More informationABRASIVE REGULATOR II
ABRASIVE REGULATOR II 13096 Abrasive Regulator II TABLE OF CONTENTS Contact Information and Customer & Technical Service... 1 1 Introduction... 1 2 Abrasive Regulator... 1 Description:... 1 2.1 Regulator
More informationBASIC Z-STACK AND TIME SERIES SCAN ON THE ZEISS LIGHTSHEET Z. 1
BASIC Z-STACK AND TIME SERIES SCAN ON THE ZEISS LIGHTSHEET Z. 1 The front door of the main body of the instrument may be open when you arrive. Take the sample chamber and slide it into position with the
More informationJETFIRST 150 RTA SYSTEM OPERATING MANUAL Version: 2 Feb 2012
JETFIRST 150 RTA SYSTEM OPERATING MANUAL Version: 2 Feb 2012 UNIVERSITY OF TEXAS AT ARLINGTON Nanofabrication Research and Teaching Facility TABLE OF CONTENTS 1. Introduction....2 1.1 Scope of Work.....2
More informationModel Air Caddy Orig TABLE OF CONTENTS
92-0919 Orig. 020201 Model 75-0114 Air Caddy TABLE OF CONTENTS CUSTOMER MESSAGE Inside Front Cover SAFETY PRECAUTIONS 3 GENERAL DESCRIPTION 6 SPECIFICATIONS 7 MAINTENANCE 9 INSTALLATION AND OPERATION 11
More informationGV Standard X-Vent. Setup, Commissioning & Installation Guide
GV Standard X-Vent Setup, Commissioning & Installation Guide Technical experts in the design, manufacture and supply of precision engineered, architectural rooflights for residential and commercial buildings.
More informationSafety Powder Spray Systems
Instruction Sheet P/N 107 952C Safety Powder Spray Systems 1. Introduction This section contains general safety instructions for using your Nordson equipment. Task- and equipment-specific warnings are
More informationLEO 1525 FEG SEM Standard Operating Procedures Mar. 6, 2012 For additional assistance, please contact the facility manager.
LEO 1525 FEG SEM Standard Operating Procedures Mar. 6, 2012 For additional assistance, please contact the facility manager. Please contact in case of emergency: SEM microscopist: Mr. Eric Miller, 7-0789
More informationExercise 5-2. Bubblers EXERCISE OBJECTIVE DISCUSSION OUTLINE. Bubblers DISCUSSION. Learn to measure the level in a vessel using a bubbler.
Exercise 5-2 Bubblers EXERCISE OBJECTIVE Learn to measure the level in a vessel using a bubbler. DISCUSSION OUTLINE The Discussion of this exercise covers the following points: Bubblers How to measure
More informationPROPORTIONING VALVE. Model 150 INSTRUCTION MANUAL. March 2017 IMS Company Stafford Road
PROPORTIONING VALVE Model 150 INSTRUCTION MANUAL March 2017 IMS Company 10373 Stafford Road Telephone: (440) 543-1615 Fax: (440) 543-1069 Email: sales@imscompany.com 1 Introduction IMS Company reserves
More informationPhotolithography. Operating Instructions
Photolithography Operating Instructions The PR used during this laboratory session will be Microposit S1813 (from Shipley). Make sure everyone is following the laboratory protocol. Wear lab coats, safety
More informationNanofabrication Facility: ECR Etcher SOP Rev. 01b, March 06. Standard Operating Procedure for PlasmaQuest ECR II Etching
Standard Operating Procedure for PlasmaQuest ECR II Etching Authors: Rev. 00: Al Schmalz, Vighen Pacradouni and Jeff Young, December 21, 1998 Rev. 01: Dr. Andras G. Pattantyus-Abraham, May 24, 2005 Rev.
More informationAgilent 1220 Infinity II LC Mobile Upgrade Kit
Agilent 1220 Infinity II LC Mobile Upgrade Kit Note 1220 Infinity II LC Mobile Upgrade Kit This note describes the procedures to install an Mobile Upgrade kit to an existing Agilent 1220 Infinity II LC.
More informationPowder Measure. Care & Usage Instructions. Instructions # Product # Revision: A
Powder Measure Care & Usage Instructions Instructions #1048578 Product #909292 Revision: A 1 INFORMATION AND SAFETY INSTRUCTIONS Ammunition reloading can be dangerous if done improperly and should not
More informationGlove Box Installation Manual
Glove Box Installation Manual 1998 by M. Braun Company File: GB-UNI-INS.DOC! Edition 08-00 by M. Boutin! Subject to be changed without notice Glovebox Installation Your Glove box has been fully assembled,
More information6900 Maintenance Instruction System Flush
Equipment Required FA74005 Damper Drain Tube FA16005 Cover Removal Tool FA900005 Beaker 0.25 Litre FA900003 Solvent Cleaning Bottle FA940021 Syringe Polypropylene 50 ml as required FA999045 Gloves Latex
More informationRADIATION PROCEDURES MANUAL Procedure Cover Sheet
RADIATION PROCEDURES MANUAL Procedure Cover Sheet Procedure Title: Calibration of Eberline Portable Particulate Noble Gas Monitor Procedure Number: TSO-08-13-REV 1 Effective Date: July 1, 2008 Approved
More informationRAM 4021-DPX Operation Manual
RAM 4021-DPX Operation Manual Worldwide Manufacturer of Gas Detection Solutions TABLE OF CONTENTS ABL 4021-DPX / RAM 4021-DPX For Your Safety... 3 Description... 3 Setup Mode... 4 Lights/Alarms... 4 Operation...
More informationRG6000. Refrigerant Recovery Machine. Operating Manual. 99 Washington Street Melrose, MA Phone Toll Free
TM Refrigerant Recovery Machine RG6000 1 Operating Manual 99 Washington Street Melrose, MA 02176 Phone 781-665-1400 Toll Free 1-800-517-8431 Visit us at www.testequipmentdepot.com Safety Precautions WARNING
More informationOperating Instructions
Operating Instructions Before operating the thin film evaporator, please be aware of all safety concerns associated with this experiment: Burn hazard from the column and steam lines, Chemical hazards associated
More informationBlue River Technologies Port-A-Poly Mixer w/2.5 GPH LMI Pump And Secondary Water Dilution Line INSTALLATION AND OPERATION
Blue River Technologies Port-A-Poly Mixer w/2.5 GPH LMI Pump And Secondary Water Dilution Line INSTALLATION AND OPERATION Install your Blue River Technologies Port-A-Poly mixing system in a clean dry area.
More informationTire Inflation Cage Kit For servicing only single piece automotive, and most light truck tire/wheel assemblies
Tire Inflation Cage Kit 85608214 For servicing only single piece automotive, and most light truck tire/wheel assemblies This is a supplement to your operating manual and covers the setup and use of the
More informationTridak Model 1060 User Guide. Syringe Filling System
Tridak Model 1060 User Guide Syringe Filling System 2 Model 1060 Syringe Filler User Guide About Dymax Light-curable materials as well as systems for light curing, fluid dispensing, and fluid packaging.
More informationSuperconducting Susceptometer (MPMS-5S) Quantum Design Room 296 (MPMS)
Superconducting Susceptometer (MPMS-5S) Quantum Design Room 296 (MPMS) Sensitivity: 1x10 11 A m 2 Applied DC fields: 0 T to 5 T Applied AC fields: 0 G to 3 G (zero-to-peak), 0.01 Hz to 1000 Hz Temperatures
More informationUnaxis ICP/RIE SOP Revision 8 09/30/16 Page 1 of 5. NRF Unaxis ICP/RIE Etch SOP
Page 1 of 5 NRF Unaxis ICP/RIE Etch SOP Unaxis Shuttlelock Reactive Ion Etcher with Inductively Coupled Plasma Module. Etch Capabilities: SiO2, Si3N4, Al, dielectrics and other commonly used materials.
More informationOperating Instructions for Cobra and Lynx Duct Leakage Testers
Operating Instructions for Cobra and Lynx Duct Leakage Testers Table of Contents Introduction Introduction... 2 Safety Precautions Safety Precautions.. 2 Prior to Testing System Preparation.. 4 Power Requirements...
More informationInstallation, Operation, Maintenance Manual For Quick-Jaw Models AL363, L364 & AL366
Installation, Operation, Maintenance Manual For Quick-Jaw Models AL363, L364 & AL366 February 2014 Form FVC076 - Rev 07 IMPORTANT: KEEP THIS DOCUMENT WITH THE PRODUCT UNTIL IT REACHES THE END USER. 1.
More informationInstallation, Operation & Maintenance Manual for Flo-Max Coupler Bracket Model FM150
Installation, Operation & Maintenance Manual for Flo-Max Coupler Bracket Model FM150 January 2013 Form FVC 084 - Rev 02 IMPORTANT: KEEP THIS DOCUMENT WITH THE PRODUCT UNTIL IT REACHES THE END USER. 1.
More informationUSE AND MAINTENANCE LIGHT TOWER
USE AND MAINTENANCE LIGHT TOWER General Safety Information Allowed use The light tower has been designed to lighten the area in which it is positioned and oriented, after installing it on a generating
More informationTeacher s Assistant Laboratory Guide
Teacher s Assistant Laboratory Guide Joseph B. Hakanson 1, Warner Meeks 2, and Dr. Joshua L. Rovey 3 Missouri University of Science and Technology, Rolla, Missouri, 65409 These instructions will discuss
More informationUnifilm Technology PVD-300 Sputter Deposition Operation Instructions
Unifilm Technology PVD-300 Sputter Deposition Operation Instructions Contributors: Devin Brown, Kevin Klein, Ben King, Eric Woods Anything that is BOLD UNDERLINED ITALICS means that you should press that
More informationCover Page for Lab Report Group Portion. Flow Visualization in a Water Channel
Cover Page for Lab Report Group Portion Flow Visualization in a Water Channel Prepared by Professor J. M. Cimbala, Penn State University Latest revision: 08 September 2017 Name 1: Name 2: Name 3: [Name
More informationINSTALLATION & MAINTENANCE INSTRUCTION
ARCHON Industries, Inc Liquid Level Gauges Models: BT-LLG ND-LLG INSTALLATION & MAINTENANCE INSTRUCTION Instruction No.: 1014.2 Revision Issued: 3/01/03 Approved: Engineering Manager Warning ONLY QUALIFIED
More information