Appendix B Safe Work Method Statements
|
|
- Aileen Willis
- 5 years ago
- Views:
Transcription
1 OH&S Manual Service Technicians Appendix B Safe Work Method Statements for A.G. Coombs NSW PTY LTD Version, 29-Mar-12
2 A.G. Coombs NSW AUTHORISATION OH&S Manual Service Technicians Safe Work Method Statements APPENDIX B Safe Work Method Statements A.G. Coombs NSW has produced a number of Safe Work Method Statements which relate to common tasks. Other SWMS may be required during the course of work and these would be developed as specific work tasks were identified. A suite of standard SWMS follows. Appendix
3 A.G. Coombs NSW AUTHORISATION OH&S Manual Service Technicians Safe Work Method Statements Table of Contents Section Version Date 1 General 1.1 Manual Handling.1 Oct Working in Public or Tenanted Areas.1 Oct Working from Extension Ladders.1 Oct Working in Plant Rooms (General).1 Oct Welding & Cutting.1 Oct Installation of Access Panels into Duct.1 Oct Reclaim of Refrigerant.1 Oct Replace Control Valves Chilled Water / Heating Water.1 Oct Stair Pressurisation - System Testing.1 Oct Fire & Smoke Mode System Testing for Air Handling Plant.1 Oct Changing Lamps.1 Oct Residual Current Devices (RCD).1 Oct-12 2 Pumps / Motors / Bearings 2.1 Work on Pumps.1 Oct Changing Pumps.1 Oct Replacing Seals.1 Oct Replacing Belts and/or Pulleys.1 Oct Changing Electric Motors.1 Oct Changing Bearings Fans.1 Oct-12 Cooling Towers.1 Cooling Towers General.1 Oct-12.2 Cooling Towers Fans.1 Oct-12 Chillers.1 Chillers General.1 Oct-12.2 Chillers Annual Maintenance.1 Oct-12. Chillers Annual Maintenance.1 Oct-12. Chillers Refrigerant Leak.1 Oct-12 5 Installation Work 5.1 Boilers General.1 Oct Boilers Annual Service.1 Oct-12 6 Air handling Units 6.1 AHU General.1 Oct AHU Filters.1 Oct-12 - i -
4 A.G. Coombs NSW AUTHORISATION OH&S Manual Service Technicians Safe Work Method Statements Table of Contents. continued 7 Package Units / Split Systems 7.1 Installation of Package Units / Split Systems.1 Oct Package Units / Split Systems Servicing.1 Oct Package Units / Split Systems Changing Compressors.1 Oct-12 8 Electrical 8.1 Switchboard maintenance.1 Oct Electrical Testing 1.0 Oct-12 Reference: System 10.. A.G. Coombs Servicing Pty Ltd - authorisations Version Update: November 2010 OH&S Manager Date Senior Contract Manager Date - ii -
5 A.G. Coombs Servicing Pty Ltd AUTHORISATION OH&S Manual Service Technicians Summary of Safe Work Method Statements Minimum PPE The minimum personal protective equipment which an employee of A.G. Coombs NSW should wear when required at an operating site are the five following items: - Hard Hat or bump caps (where required / appropriate) - Safety glasses or goggles - Hearing protection - Gloves - Safety shoes / boots All of the PPE items must be certified to the relevant Australian Standard for that product. This would be indicated by an Australian Product StandardsMark imprinted on the item or the packaging as per the adjacent stamp: Appendix
6 Risk & Consequence Assessment Table 1: Risk Rating Score Will not result in injury or illness First aid treatment only (no lost time) Medical treatment required (casualty treatment) Serious or multiple injury / illness (permanent disability) Death or multiple lifethreatening injuries CONSEQUENCE Insignificant Minor Moderate Major Catastrophic Expected to occur in most circumstances Almost Certain Will probably occur Might occur at some time LIKELIHOOD Likely Possible Not likely to occur in normal circumstances Unlikely May occur but only in exceptional circumstances Rare Table 2: Risk Score and Action RISK RATING SCORE SCORE Risk Likely Outcome There are two stages in defining Risk on a project site: INHERENT RISK: is the risk with no control measures in place The hazard has the potential to kill or cause a serious injury and has an > 7 High unacceptably high probability ( Might Occur ) of occurrence. TARGET RISK: is the assessed risk after the control measure/s have been implemented. 6 and 7 Medium 5 Low The hazard presents an unacceptable combination of the Likelihood of occurrence versus the seriousness of the resulting injury. The hazard is unlikely to cause significant injury or the probability of a serious injury is Rare or has Never occurred. A risk category of LOW is required before work proceeds. Appropriate control measure/s MUST be implemented until a LOW risk category (risk rating score of 5 or less) is achieved. To derive the Risk Rating Score, the following steps are followed: 1) Assess the Likelihood (ie Risk) 2) Establish the Consequences The intersection of the two provides the risk rating score. Issue Status: Version 2 Date: Nov-10
7 Job No. SWMS No. 1.1 Ver Project Name: ISPT C/o CBRE Date Oct-12 Site Address: Numbers 1 and 2 Julius Ave North Ryde Permit to Work required? Yes No x SWMS Name MANUAL HANDLING PPE Requirement: Safety Boots High Visibility Vest / Clothing Safety Glasses Gloves Hard Hat Other Specify Prepared by: Luke Snell Reviewed by: sign Legislation / Guidance Material: WH&S Act 2011 WH&S Regulations 2011 Code of Practice Manual Tasks 2010 CONSIDERATIONS 1) Plan the task. 2) Can mechanical aids to be used to perform the task (eg: forklift / duct hoist / chain block etc.)? ) Can the item be moved by rollers, skates, trolley etc. in preference to manual means? ) Ensure the path for the lift / move is clear and the final location is prepared. 5) Ensure adequate labour is available for the task. 6) Employees are to use correct lifting techniques bend knees, not the back. 7) Employees must wear appropriate PPE gloves, safety glasses, safety boots, etc. Activity Risks Inherent Risk Risk Control Measures (Always take into account the Hierarchy of Control Principles) Target Risk Who is Responsible? Pre-Start Planning (pre-start checks are to be conducted prior to beginning a new task and/or relocating) Inexperienced persons performing tasks resulting in personal injury and injury to others 7 1 st year apprentices, trainees or Work Experience staff are to work under direct supervision by an experience tradesman Only competent employees who are competent with a particular task are allocated that task Poor access resulting in slips, 7 Maintain good housekeeping practices eg. Ensure rubbish bins are accessible and materials are stored appropriately Ensure designated access points are clear and defined Ensure work area to be clear of debris Poor Lighting resulting in slips, 7 Ensure access lighting is adequate Ensure task lighting is adequate A.G. Coombs 2010 Form (Ver 2. Nov-10) S W M S N o 1. 1 P a g e 1 of
8 Materials Delivery Unknown Site Specific Hazards Supervisor to Liaise with gate house Ground Conditions Mobile Plant and vehicle 2 Hours Notice is to be given to representative from Client Movement etc. Site Restrictions All vehicles are to have hazards/flashing lights turned on Site Rules / Access Manual Handling Muscular Skeletal Disorder 5 Use mechanical aids where possible. 2 Provide adequate labour to assist. Follow correct lifting procedure. (taking into account) o o o o o Plan the Activity Posture and positions Duration and Frequency Weights and forces Loads and distances Bending to pick up Team Lift where required Injury to hands & feet Wearing safety glasses, protective gloves & safety footwear. Damage to surrounding fixtures, fittings & finished surfaces Bending places a lot of pressure on the spine and back muscles Provide protective decking, coverings etc. Erect barriers where necessary. Bend with bent knees and slightly angled back Lift up to waist with feet slightly apart, bend knees, lift with legs and support with arms and hands Lifting Up to Waist Lifting above Waist Lifting up to the waist, causing back muscle strain or damage Lifting above waist, causing back and shoulder muscle strain or damage. Lift above waist with feet slightly apart, straight back, lift with arms and hands then support with shoulder and avoid any twisting 2 A.G. Coombs 2010 Form (Ver 2. Nov-10) S W M S N o 1. 1 P a g e 2 of
9 Pushing an object Pulling an object Pushing and pulling objects, causing leg, arm and back muscle strain or damage 5 Pushing and pulling to be carried out as close as possible in the upright position. Carrying an Object Placing an Object Carrying and placing objects, causing stomach, forearm, back and leg muscle strain or damage 5 When carrying and placing objects the following must be followed Make Clear Path Size up the load Correct feet position, Bend knees to lift with legs Support with hands and arms then walk Bend knees to place load Moving Materials on site Falling Objects. Slips, Trips and Falls- Puncture and Crush injuries 5 When moving materials on site- the following must be considered Trolleys or pallet jacks are to be used to move large quantities of materials around the site 2 Materials should be well tied down with no sharp protruding edges Ensure safe access from storage area to workface Note load ratings on trolleys and pallet jacks and make sure they are in good working condition Ensure adequate access and egress before moving materials, Wears Gloves and protective clothing. A.G. Coombs 2010 Form (Ver 2. Nov-10) S W M S N o 1. 1 P a g e of
10 Qualification and experience required to complete task Personnel, Duties and Responsibilities(Supervisory staff and others) Equipment to be used Training Required to Complete Work All employees must have a Construction Industry Induction Card A.G. Coombs Site Foreman Hand Tools Pallet Trolley Duct Lifter Trolley Jack All Employees must have completed, A.G. Coombs Site Induction which includes reading and understanding the A.G. Coombs Site WH&S plan Client Site Induction All employees have been consulted on SWMS controls and inducted into SWMS and Site Specific Requirements (name, date & signature) SWMS No. 1.1 Page of A.G. Coombs 2010 Form (Ver 2. Nov-10) S W M S N o 1. 1 P a g e of
11 Job No. SWMS No. 1.2 Ver.1 Site Name: ISPT C/o CBRE Date Oct-12 Site Address: Numbers 1 and 2 Julius Ave North Ryde Permit to Work required? Yes No SWMS Name WORKING IN PUBLIC OR TENANTED AREAS PPE Requirement: Safety Boots High Visibility Vest / Clothing Safety Glasses Gloves Hard Hat Other Specify Prepared by: Luke Snell Reviewed by: sign Legislation / Guidance Material: WH&S Act 2011 Code of Practice Risk Management 2007 WH&S Regulations 2011 CONSIDERATIONS 1) Will the work pose a risk to the public? (Permit to work in public space required) 2) Can tools / equipment be safely transported to the Work Site? ) Is barricading required? ) Are additional resources required? 5) Can tools / equipment be stored safely? 6) Is power accessible? 7) Will the public be exposed to hazards e.g. chemicals, welding flash, etc Activity Risks Inherent Risk Risk Control Measures (Always take into account the Hierarchy of Control Principles) Target Risk Who is Responsible? Pre-Start Planning (pre-start checks are to be conducted prior to beginning a new task and/or relocating) Inexperienced persons performing tasks resulting in personal injury and injury to others 7 1 st year apprentices, trainees or Work Experience staff are to work under direct supervision by an experience tradesman Only competent employees who are competent with a particular task are allocated that task Poor access resulting in slips, 7 Maintain good housekeeping practices eg. Ensure rubbish bins are accessible and materials are stored appropriately Ensure designated access points are clear and defined Ensure work area to be clear of debris Poor Lighting resulting in slips, 7 Ensure access lighting is adequate Ensure task lighting is adequate A.G. Coombs 2010 Form (Ver 2. Nov-10) S W M S N o 1. 2 P a g e 1 of 2
12 Movement of Tools / Equipment Contact with / injury to public 6 Barricade area and use a spotter where required. Move tools/equipment outside public hours. Use of Equipment (eg: tools or scissor lift) Injury to public 7 Barricade area and use a spotter Use of Platform Ladders Fall from height 7 Barricade area. Use a spotter. Platform ladder to be inducted by LL Qualification and experience required to complete task Personnel, Duties and Responsibilities(Supervisory staff and others) Equipment to be used MSDS Required Training Required to Complete Work All employees must have a Industry Induction Card A.G. Coombs Site Foreman All Employees must have completed, All employees have been consulted on SWMS controls and inducted into SWMS and Site Specific Requirements (name, date & signature) A.G. Coombs Site Induction which includes reading and understanding the A.G. Coombs Site WH&S plan Client Site Induction A.G. Coombs 2010 Form (Ver 2. Nov-10) S W M S N o 1. 2 P a g e 2 of 2
13 Job No. SWMS No. 1. Ver.1 Site Name: ISPT C/o CBRE Date Oct-12 Site Address: Numbers 1 and 2 Julius Ave North Ryde Permit to Work required? Yes No SWMS Name WORKING FROM STEP LADDERS PPE Requirement: Safety Boots High Visibility Vest / Clothing Safety Glasses Gloves Hard Hat Other Specify Prepared by: Luke Snell Reviewed by: sign Legislation / Guidance Material: CONSIDERATIONS 1) The duration of the task. 2) The tools / equipment required for the task. WH&S Act 2011 WH&S Regulations 2011 Code of Practise- Risk Assessment ) If there are practical alternatives to using a ladder, ie: EWP s, scaffolding, work platforms. ) Inspect the ladder before use. Activity Risks Inherent Risk Risk Control Measures Target Risk Who is Responsible? Pre-Start Planning (pre-start checks are to be conducted prior to beginning a new task and/or relocating) Inexperienced persons performing tasks resulting in personal injury and injury to others 7 1 st year apprentices, trainees or Work Experience staff are to work under direct supervision by an experience tradesman Only competent employees who are competent with a particular task are allocated that task Poor access resulting in slips, 7 Maintain good housekeeping practices eg. Ensure rubbish bins are accessible and materials are stored appropriately Ensure designated access points are clear and defined Ensure work area to be clear of debris Poor Lighting resulting in slips, 7 Ensure access lighting is adequate Ensure task lighting is adequate Ladder check Ladder not in appropriate condition 9 Inspect ladder for defects prior to use A.G. Coombs 2010 Form (Ver 2. Nov-10) S W M S N o 1. P a g e 1 of
14 Ladder Placement Slipping / Falling 9 Ladder to be fully open. Ladder to be on a firm, level, non-slip surface. Public Safety 9 Cordon off doors or areas or areas where there is limited pedestrian traffic. Where significant pedestrian traffic, cordon off area and position a spotter. Climbing Ladders Slipping / Falling 9 Ensure footwear is clean and non slip. Always face towards the ladder. Never stand on or above the second top step. Working Falling 9 Work should be performed whilst facing the ladder Place and move ladder to ensure no over reaching Always work within stiles of ladder A.G. Coombs 2010 Form (Ver 2. Nov-10) S W M S N o 1. P a g e 2 of
15 Qualification and experience required to complete task Personnel, Duties and Responsibilities(Supervisory staff and others) Equipment to be used MSDS Required Training Required to Complete Work All employees must have a Industry Induction Card A.G. Coombs Site Foreman All Employees must have completed, All employees have been consulted on SWMS controls and inducted into SWMS and Site Specific Requirements (name, date & signature) A.G. Coombs Site Induction which includes reading and understanding the A.G. Coombs Site WH&S plan Client Site Induction A.G. Coombs 2010 Form (Ver 2. Nov-10) S W M S N o 1. P a g e of
16 Job No. SWMS No. 1. Ver.1 Site Name: ISPT C/o CBRE Date Oct-12 Site Address: Numbers 1 and 2 Julius Ave North Ryde Permit to Work required? Yes No SWMS Name WORKING IN PLANT ROOMS PPE Requirement: Safety Boots High Visibility Vest / Clothing Safety Glasses Gloves Hard Hat Other Specify Prepared by: Luke Snell Reviewed by: sign Legislation / Guidance Material: WH&S Act 2011 WH&S Regulations 2011 CONSIDERATIONS NOTE: This statement does not deal with specific tasks to be performed these are detailed in other Safe Work Method Statements. National Code of Practise- Induction for Construction Work Activity Risks Inherent Risk Risk Control Measures Target Risk Who is Responsible? Pre-Start Planning (pre-start checks are to be conducted prior to beginning a new task and/or relocating) Inexperienced persons performing tasks resulting in personal injury and injury to others Poor access resulting in slips, Poor Lighting resulting in slips, 7 1 st year apprentices, trainees or Work Experience staff are to work under direct supervision by an experience tradesman Only competent employees who are competent with a particular task are allocated that task 7 Maintain good housekeeping practices eg. Ensure rubbish bins are accessible and materials are stored appropriately Ensure designated access points are clear and defined Ensure work area to be clear of debris 7 Ensure access lighting is adequate Ensure task lighting is adequate A.G. Coombs 2010 Form (Ver 2. Nov-10) S W M S N o 1. P a g e 1 of
17 Entry to Plant Room Inadequate Lighting / trip, falls 7 Where necessary ensure supplementary lighting or torch is provided. Ensure walkways and areas of work are clear of loose impediments Exercise care when having to traverse pipes and other equipment Working in Plant Room Slips 8 Identify wet / slippery areas. Contract Manager / Tradesman Cordon off area. Contract Manager / Tradesman Provide warning signs where necessary. Contract Manager / Tradesman Have slippery area cleaned. Contract Manager / Tradesman Noise 7 Wear appropriate hearing protection ear muffs 0- db protection. Moving Parts of Machinery 8 Where possible isolate and tag machinery ensure company isolation procedures are followed. If working with operating machinery, exercise extreme caution wear appropriate clothing. Contract Manager / Tradesman Contract Manager / Tradesman Contract Manager / Tradesman Shafts / Falls 8 Ensure shafts are properly protected Contract Manager / Tradesman Restricted Access / soft tissue injuries Where inappropriate guarding is evident arrange correct protection. Contract Manager / Tradesman 7 Identify areas where there is restricted access. Contract Manager / Tradesman Look at other options to perform job. Contract Manager / Tradesman Use of Ladders 9 Ensure Ladder has current A.G Coombs Ladder Tag Ensure guidelines for use of ladders / step are followed. Contract Manager / Tradesman Contract Manager / Tradesman Consider other options to use of step / ladders. Contract Manager / A.G. Coombs 2010 Form (Ver 2. Nov-10) S W M S N o 1. P a g e 2 of
18 a) Ensure ladders / steps are appropriate for the task. b) Ensure ladder / steps are in good working condition. Tradesman Qualification and experience required to complete task Personnel, Duties and Responsibilities(Supervisory staff and others) Equipment to be used MSDS Required Training Required to Complete Work All employees must have a Industry Induction Card A.G. Coombs Site Foreman All Employees must have completed, All employees have been consulted on SWMS controls and inducted into SWMS and Site Specific Requirements (name, date & signature) A.G. Coombs Site Induction which includes reading and understanding the A.G. Coombs Site WH&S plan Client Site Induction A.G. Coombs 2010 Form (Ver 2. Nov-10) S W M S N o 1. P a g e of
19 Job No. SWMS No. 1.5 Ver.1 Site Name: ISPT C/o CBRE Date Oct-12 Site Address: Numbers 1 and 2 Julius Ave North Ryde Permit to Work required? Yes X No SWMS Name WELDING (Gas & Electric) CUTTING & BRAZING PPE Requirement: Safety Boots High Visibility Vest / Clothing Safety Glasses Gloves Hard Hat Other Specify Goggles Prepared by: Luke Snell Reviewed by: sign Legislation / Guidance Material: WH&S Act 2011 WH&S Regulations 2011 National Code of Practise- Induction for Construction Work CONSIDERATIONS 1) Protective flash screens to be erected around work area. 2) Welding curtains are required. ) Employees (welder) to have all the appropriate PPE. ) Dry powder type fire extinguisher to be available. 5) Electric welder power source must have earth leakage protection. 6) Oxy / acetylene hoses to be fitted with flash back arrestors and inspected prior to use. 7) Clear the welding work area of any flammable substances. 8) If applicable, smoke alarms / sensors are to be isolated. 9) Area to be well ventilated. Activity Risks Inherent Risk Risk Control Measures Target Risk Who is Responsible? Pre-Start Planning (pre-start checks are to be conducted prior to beginning a new task and/or relocating) Inexperienced persons performing tasks resulting in personal injury and injury to others 7 1 st year apprentices, trainees or Work Experience staff are to work under direct supervision by an experience tradesman Only competent employees who are competent with a particular task are allocated that task Poor access resulting in slips, 7 Maintain good housekeeping practices eg. Ensure rubbish bins are accessible and materials are stored appropriately Ensure designated access points are clear and defined Ensure work area to be clear of debris Poor Lighting resulting in slips, 7 Ensure access lighting is adequate Ensure task lighting is adequate A.G. Coombs 2010 Form (Ver 2. Nov-10) S W M S N o 1. 5 P a g e 1 of 2
20 Welding & Cutting (Oxy Acetylene & Electric) Injury to eyes, hands & limbs 7 Wear welding goggles or welding shield. Igniting adjacent flammable materials Wearing protective clothing (jackets, gloves, spats) Erect flash screens or curtains to protect adjacent personnel or public from flash burns. 8 Protect materials with welding blankets. Have fire extinguisher available Inhaling welding & cutting fumes 7 Use fans to improve ventilation. Use masks or breathing apparatus as necessary. Qualification and experience required to complete task Personnel, Duties and Responsibilities(Supervisory staff and others) Equipment to be used MSDS Required Training Required to Complete Work All employees must have a Industry Induction Card A.G. Coombs Site Foreman All Employees must have completed, All employees have been consulted on SWMS controls and inducted into SWMS and Site Specific Requirements (name, date & signature) A.G. Coombs Site Induction which includes reading and understanding the A.G. Coombs Site WH&S plan Client Site Induction A.G. Coombs 2010 Form (Ver 2. Nov-10) S W M S N o 1. 5 P a g e 2 of 2
21 Job No. SWMS No. 1.6 Ver.1 Site Name: ISPT C/o CBRE Date Oct-12 Site Address: Numbers 1 and 2 Julius Ave North Ryde Permit to Work required? Yes No SWMS Name INSTALLING ACCESS PANELS (into duct) PPE Requirement: Safety Boots High Visibility Vest / Clothing Safety Glasses Gloves Hard Hat Other Specify Prepared by: Luke Snell Reviewed by: sign Legislation / Guidance Material: WH&S Act 2011 WH&S Regulations 2011 CONSIDERATIONS 1) Identify the area where the panel needs to be inserted. 2) Check for obstructions wiring, pipework, etc. ) Isolate the fan to the area. ) Penetrate duct by drilling hole, using shears or power tools (mechanical or electrical). 5) Cut appropriate size hole. 6) Fix border in place. 7) Install access panel. 8) Clean area and dispose of waste to bin. National Code of Practise- Induction for Construction Work Activity Risks Inherent Risk Risk Control Measures Target Risk Who is Responsible? Pre-Start Planning (pre-start checks are to be conducted prior to beginning a new task and/or relocating) Inexperienced persons performing tasks resulting in personal injury and injury to others 7 1 st year apprentices, trainees or Work Experience staff are to work under direct supervision by an experience tradesman Only competent employees who are competent with a particular task are allocated that task Poor access resulting in slips, 7 Maintain good housekeeping practices eg. Ensure rubbish bins are accessible and materials are stored appropriately Ensure designated access points are clear and defined Ensure work area to be clear of debris Poor Lighting resulting in slips, 7 Ensure access lighting is adequate Ensure task lighting is adequate A.G. Coombs 2010 Form (Ver 2. Nov-10) S W M S N o 1. 6 P a g e 1 of
22 Accessing duct work Work at Height / falls 9 Use equipment appropriate for task, eg: ladder, scissor lift. See SWMS for use of ladders Work in vicinity of electrical cabling Electrocution 9 Ensure all electrical wiring is clear of work area Where wiring is in immediate vicinity tag and lock out electrical system. Ensure all electrical tools have current tags. Cutting duct work (hole) Cuts / Abrasions Sharp Edges Use of power tools 7 8 Wear gloves and eye protection Fix border of access area as early as possible. Use RCD and shields Work in a ceiling grid Dust from duct may agitate respiratory problems 7 Ensure safety glasses / goggles and P2 face mask are worn. Work at height / from ladders Falling 9 Work should be performed whilst facing the ladder Place and move ladder to ensure no over reaching Always work within stiles of ladder A.G. Coombs 2010 Form (Ver 2. Nov-10) S W M S N o 1. 6 P a g e 2 of
23 Qualification and experience required to complete task Personnel, Duties and Responsibilities(Supervisory staff and others) Equipment to be used MSDS Required Training Required to Complete Work All employees must have a Industry Induction Card A.G. Coombs Site Foreman All Employees must have completed, All employees have been consulted on SWMS controls and inducted into SWMS and Site Specific Requirements (name, date & signature) A.G. Coombs Site Induction which includes reading and understanding the A.G. Coombs Site WH&S plan Client Site Induction A.G. Coombs 2010 Form (Ver 2. Nov-10) S W M S N o 1. 6 P a g e of
24 Job No. SWMS No. 1.7 Ver.1 Site Name: ISPT C/o CBRE Date Oct-12 Site Address: Numbers 1 and 2 Julius Ave North Ryde Permit to Work required? Yes No SWMS Name RECLAIM OF REFRIGERANTS PPE Requirement: Safety Boots High Visibility Vest / Clothing Safety Glasses Gloves Hard Hat Other Specify Prepared by: Luke Snell Reviewed by: sign Legislation / Guidance Material: WH&S Act 2011 WH&S Regulations 2011 CONSIDERATIONS 1) RCD to be used. 2) Reclaim unit to be capped tested and tagged. ) Isolate, lock and tag system to be reclaimed. ) Fit service gauges to high and low sides. 5) Connect service line to inlet of reclaim unit. 6) Connect outlet of reclaim to appropriate cylinder. NOTE: Care must be taken when removing line between reclaim unit and bottle as liquid refrigerants may be present and gas is at high pressure. Code of Practise- Control of Workplace Hazardous Substances 7) If gas is to be re-used, purge all lines and install dryer on outlet side between reclaim unit and reclaim bottle. 8) With system pressures equal open lines and turn on reclaim unit. 9) Reclaim all gas from system, use L/P override fitted to reclaim units to assist. 10) Isolate all line valves and disconnect line hoses. Activity Risks Inherent Risk Risk Control Measures Target Risk Who is Responsible? Pre-Start Planning (pre-start checks are to be conducted prior to beginning a new task and/or relocating) Inexperienced persons performing tasks resulting in personal injury and injury to others 7 1 st year apprentices, trainees or Work Experience staff are to work under direct supervision by an experience tradesman Only competent employees who are competent with a particular task are allocated that task Poor access resulting in slips, 7 Maintain good housekeeping practices eg. Ensure rubbish bins are accessible and materials are stored appropriately Ensure designated access points are clear and defined Ensure work area to be clear of debris A.G. Coombs 2010 Form (Ver 2. Nov-10) S W M S N o 1. 7 P a g e 1 of 2
25 Poor Lighting resulting in slips, 7 Ensure access lighting is adequate Ensure task lighting is adequate Lifting gas bottles / reclaim unit Manual handling / sprain / strain 8 Refer to SWMS 1.1 Use mechanical assistance Use correct manual handling techniques Loss of refrigerant Injury / burn (frost) to eyes 8 Employee to have ARC accreditation Wear appropriate PPE safety glasses / goggles Injury / burn to hands 8 Wear appropriate PPE safety gloves Qualification and experience required to complete task Personnel, Duties and Responsibilities(Supervisory staff and others) Equipment to be used MSDS Required Training Required to Complete Work All employees must have a Industry Induction Card A.G. Coombs Site Foreman All Employees must have completed, All employees have been consulted on SWMS controls and inducted into SWMS and Site Specific Requirements (name, date & signature) A.G. Coombs Site Induction which includes reading and understanding the A.G. Coombs Site WH&S plan Client Site Induction A.G. Coombs 2010 Form (Ver 2. Nov-10) S W M S N o 1. 7 P a g e 2 of 2
26 Job No. SWMS No. 1.8 Ver.1 Site Name: ISPT C/o CBRE Date Oct-12 Site Address: Numbers 1 and 2 Julius Ave North Ryde Permit to Work required? Yes No SWMS Name PPE Requirement: CONTROL VALVES REPLACE CHILLED WATER / HEATING WATER Safety Boots High Visibility Vest / Clothing Safety Glasses Gloves Hard Hat Other Specify Prepared by: Luke Snell Reviewed by: sign Legislation / Guidance Material: CONSIDERATIONS 1) Isolate system water and electrical tag out / lock out. 2) Ensure adequate time for heating pipe to cool. ) Drain down system, close valve(s). ) Disconnect and remove valve. 5) Clear work area of excess water (ensure floor not slippery). WH&S Act 2011 WH&S Regulations 2011 National Code of Practise- Induction for Construction Work 6) Where necessary, use mechanical assistance to support / lower valve. 7) Install new valve. 8) Test for leaks. 9) Remove isolation / reinstate system. Activity Risks Inherent Risk Risk Control Measures Target Risk Who is Responsible? Pre-Start Planning (pre-start checks are to be conducted prior to beginning a new task and/or relocating) Inexperienced persons performing tasks resulting in personal injury and injury to others 7 1 st year apprentices, trainees or Work Experience staff are to work under direct supervision by an experience tradesman Only competent employees who are competent with a particular task are allocated that task Poor access resulting in slips, 7 Maintain good housekeeping practices eg. Ensure rubbish bins are accessible and materials are stored appropriately Ensure designated access points are clear and defined Ensure work area to be clear of debris Poor Lighting resulting in slips, 7 Ensure access lighting is adequate Ensure task lighting is adequate A.G. Coombs 2010 Form (Ver 2. Nov-10) S W M S N o 1. 8 P a g e 1 of 2
27 Isolate System Burns, scalding 7 Wear gloves and protective clothing. Drain down system Splashing from hot water causing scalding or burns, 8 Wear protective clothing (inc gloves and goggles) Avoid heating pipework Disconnect valve Strains, sprains 8 Support valve prior to disconnection Use mechanical lifting device. Use correct manual handing device or technique Spillage of water / slippery 8 Minimise excess water Mop up and dry excess water Install valve Strains, sprains 8 Use mechanical device. Working at height Falling / falls 9 Use appropriate equipment Refer to relevant SWMS Qualification and experience required to complete task Personnel, Duties and Responsibilities(Supervisory staff and others) Equipment to be used MSDS Required All employees have been consulted on SWMS controls and inducted into SWMS and Site Specific Requirements (name, date & signature) Training Required to Complete Work All employees must have a Industry Induction Card A.G. Coombs Site Foreman All Employees must have completed, A.G. Coombs Site Induction which includes reading and understanding the A.G. Coombs Site WH&S plan Client Site Induction A.G. Coombs 2010 Form (Ver 2. Nov-10) S W M S N o 1. 8 P a g e 2 of 2
28 Job No. SWMS No. 1.9 Ver.1 Site Name: ISPT C/o CBRE Date Oct-12 Site Address: Numbers 1 and 2 Julius Ave North Ryde Permit to Work required? Yes No SWMS Name STAIRWELL PRESSURISATION SYSTEM TESTING PPE Requirement: Safety Boots High Visibility Vest / Clothing Safety Glasses Gloves Hard Hat Other Specify Prepared by: Luke Snell Reviewed by: sign Legislation / Guidance Material: WH&S Act 2011 WH&S Regulations 2011 CONSIDERATIONS 1) Wear eye protection in case of dust. 2) Check operation / functioning of: a. Fans b. Bearings c. Variable Speed Drive (if applicable) d. Pressure control equipment (if applicable) e. Relief Damper (if applicable) Activity Pre-Start Planning (pre-start checks are to be conducted prior to beginning a new task and/or relocating) Risks Inexperienced persons performing tasks resulting in personal injury and injury to others Poor access resulting in slips, Poor Lighting resulting in slips, Inherent Risk National Code of Practise- Induction for Construction Work ) Check sound levels during fan operations ) Check door opening force and operation of door latch mechanism 5) Check door air velocity and static pressure 6) Where necessary, adjust equipment to ensure system settings meet the specification/s 7) Complete required documentation Risk Control Measures 7 1 st year apprentices, trainees or Work Experience staff are to work under direct supervision by an experience tradesman Only competent employees who are competent with a particular task are allocated that task 7 Maintain good housekeeping practices eg. Ensure rubbish bins are accessible and materials are stored appropriately Ensure designated access points are clear and defined Ensure work area to be clear of debris 7 Ensure access lighting is adequate Ensure task lighting is adequate Target Risk Who is Responsible? A.G. Coombs 2010 Form (Ver 2. Nov-10) S W M S N o 1. 9 P a g e 1 of 2
29 Access to Fan for inspection Lighting / slips / falls 8 Provide supplementary lighting or ensure appropriate torches are available Fan and plant inspection Awkward posture / sprains / strains Use appropriate equipment Work at height / fall from ladders 9 Use procedure for safe use of ladders 8 Position access equipment to limit bad posture Ensure regular breaks are taken to limit injury exposure Moving equipment 8 Ensure machine guards are fitted Sound Level tests Hearing damage 7 Decibel meter for used sound level testing Ear muffs to be worn Door force tests and latch inspection Fingers and limbs entrapped, squashed 8 Ensure use of correct scales for door force Air velocity tests Wear gloves where appropriate Checking equipment Moving parts / entanglement 9 Ensure guards are in place Qualification and experience required to complete task Personnel, Duties and Responsibilities(Supervisory staff and others) Equipment to be used MSDS Required All employees have been consulted on SWMS controls and inducted into SWMS and Site Specific Requirements (name, date & signature) Training Required to Complete Work All employees must have a Industry Induction Card A.G. Coombs Site Foreman All Employees must have completed, A.G. Coombs Site Induction which includes reading and understanding the A.G. Coombs Site WH&S plan Client Site Induction A.G. Coombs 2010 Form (Ver 2. Nov-10) S W M S N o 1. 9 P a g e 2 of 2
30 Job No. SWMS No Ver.1 Site Name: ISPT C/o CBRE Date Oct-12 Site Address: Numbers 1 and 2 Julius Ave North Ryde Permit to Work required? Yes No SWMS Name PPE Requirement: FIRE AND SMOKE MODE SYSTEM TESTING FOR AIR HANDLING PLANT Safety Boots High Visibility Vest / Clothing Safety Glasses Gloves Hard Hat Other Specify Prepared by: Luke Snell Reviewed by: sign Legislation / Guidance Material: CONSIDERATIONS 1) Check operation / functioning of: a. Fans (supply, return, spill, exhaust) b. Belts c. Bearings d. Variable Speed Drive (if applicable) e. Pressure control equipment (if applicable) f. Supply, return, spill, exhaust dampers (if applicable) WH&S Act 2011 WH&S Regulations 2011 National Code of Practise- Induction for Construction Work 2) Check switchboard operation and indication of fire mode ) Complete required documentation Activity Risks Inherent Risk Risk Control Measures Target Risk Who is Responsible? Pre-Start Planning (pre-start checks are to be conducted prior to beginning a new task and/or relocating) Inexperienced persons performing tasks resulting in personal injury and injury to others 7 1 st year apprentices, trainees or Work Experience staff are to work under direct supervision by an experience tradesman Only competent employees who are competent with a particular task are allocated that task Poor access resulting in slips, 7 Maintain good housekeeping practices eg. Ensure rubbish bins are accessible and materials are stored appropriately Ensure designated access points are clear and defined Ensure work area to be clear of debris A.G. Coombs 2010 Form (Ver 2. Nov-10) S W M S N o P a g e 1 of
31 Access to Fan and dampers for inspection Fan and plant inspection Poor Lighting resulting in slips, Lighting / slips / falls Work at height / fall from ladders Awkward posture / sprains / strains 7 Ensure access lighting is adequate Ensure task lighting is adequate 9 Provide supplementary lighting or ensure appropriate torches are available 8 Use appropriate equipment Use procedure for safe use of ladders Position access equipment to limit posture Ensure regular breaks are taken to limit injury exposure Moving equipment 8 Ensure machine guards are fitted Fingers and limbs entrapped, squashed 8 Wear gloves where appropriate Noise exposure 7 Wear hearing protection Switchboard inspection (external for lamp indication only) Electrocution if switchboard opened exposing electrical equipment 9 Access to switchboard by appropriately licensed personnel only Checking Equipment Moving parts / entanglement 8 Ensure guards are in place A.G. Coombs 2010 Form (Ver 2. Nov-10) S W M S N o P a g e 2 of
32 Qualification and experience required to complete task Personnel, Duties and Responsibilities(Supervisory staff and others) Equipment to be used MSDS Required Training Required to Complete Work All employees must have a Industry Induction Card A.G. Coombs Site Foreman All Employees must have completed, All employees have been consulted on SWMS controls and inducted into SWMS and Site Specific Requirements (name, date & signature) A.G. Coombs Site Induction which includes reading and understanding the A.G. Coombs Site WH&S plan Client Site Induction A.G. Coombs 2010 Form (Ver 2. Nov-10) S W M S N o P a g e of
33 Job No. SWMS No Ver.1 Site Name: ISPT C/o CBRE Date Oct-12 Site Address: Numbers 1 and 2 Julius Ave North Ryde Permit to Work required? Yes No SWMS Name CHANGING LAMPS PPE Requirement: Safety Boots High Visibility Vest / Clothing Safety Glasses Gloves Hard Hat Other Specify Prepared by: Luke Snell Reviewed by: sign Legislation / Guidance Material: WH&S Act 2011 WH&S Regulations 2011 Code of Practise- Electrical Practises for Construction Work CONSIDERATIONS 1) Set up traffic / pedestrian management as required. 2) Set up appropriate ladder ) Isolate and tag lighting circuit at local switch panel. ) Climb ladder. 5) Remove diffusers (if fitted). 6) Remove faulty lamp and or starter... 7) Replace lamp and or starter. 8) Replace diffuser (if fitted). 9) Re-energise light fitting and check for correct operation. 10) Pack up ladder 11) Remove traffic / pedestrian management provisions. Activity Risks Inherent Risk Risk Control Measures Target Risk Who is Responsible? Pre-Start Planning (pre-start checks are to be conducted prior to beginning a new task and/or relocating) Inexperienced persons performing tasks resulting in personal injury and injury to others 7 1 st year apprentices, trainees or Work Experience staff are to work under direct supervision by an experience tradesman Only competent employees who are competent with a particular task are allocated that task Poor access resulting in slips, 7 Maintain good housekeeping practices eg. Ensure rubbish bins are accessible and materials are stored appropriately Ensure designated access points are clear and defined Ensure work area to be clear of debris Poor Lighting resulting in slips, 7 Ensure access lighting is adequate Ensure task lighting is adequate A.G. Coombs 2010 Form (Ver 2. Nov-10) S W M S N o P a g e 1 of
34 Set up traffic / pedestrian management as required Trips / falls and items being dropped or bystanders 7 Use of appropriate pedestrian and traffic management provisions Vehicles / machinery coming into contact with access equipment 8 Wear hi-visibility vests, if exposed to a traffic risk Set up appropriate ladder Lifting injury 9 Check for hazards above Inspect ladder for defects Use safe lifting practices- Isolate and tag lighting circuit at local switch panel Electric check due to faulty light fitting or component 9 Isolate light fitting and tag local switch panel Climb ladder Slips / falls 9 Follow working at height guidelines Remove diffusers (if fitted) Particles being dislodged from light fitting and lodging into eye 8 Wear safety glasses Remove and replace faulty lamp and or starter and diffuser Faulty electrical components may expose live parts when lamps or starters are being removed or replaced. 9 Visually inspect all external components of fittings when replacing lamps and only proceed to the next step if all components are in good working order. All faults should be repaired by an Electrical Contractor prior to turning the light fitting back on. Re-energise light fitting and check for correct operation Electric shock due to faulty light fitting or component 9 Ensure that personnel are clear of the fitting when energised. Pack up ladder and remove traffic / pedestrian management provisions Lifting injury Vehicles / machinery coming into contact with personnel or access equipment 7 Use safe working practices Wear hi-visibility vests if exposed to a traffic risk. A.G. Coombs 2010 Form (Ver 2. Nov-10) S W M S N o P a g e 2 of
35 Qualification and experience required to complete task Personnel, Duties and Responsibilities(Supervisory staff and others) Equipment to be used MSDS Required Training Required to Complete Work All employees must have a Industry Induction Card A.G. Coombs Site Foreman All Employees must have completed, All employees have been consulted on SWMS controls and inducted into SWMS and Site Specific Requirements (name, date & signature) A.G. Coombs Site Induction which includes reading and understanding the A.G. Coombs Site WH&S plan Client Site Induction A.G. Coombs 2010 Form (Ver 2. Nov-10) S W M S N o P a g e of
36 Job No. SWMS No Ver.1 Site Name: ISPT C/o CBRE Date Oct-12 Site Address: Numbers 1 and 2 Julius Ave North Ryde Permit to Work required? Yes No SWMS Name RESIDUAL CURRENT DEVICES (RCD) PPE Requirement: Safety Boots High Visibility Vest / Clothing Safety Glasses Gloves Hard Hat Other Specify Prepared by: Luke Snell Reviewed by: sign Legislation / Guidance Material: WH&S Act 2011 WH&S Regulations 2011 Code of Practise- Electrical Practises for Construction Work CONSIDERATIONS 1) All RCDs are to be tested in accordance with AS ) All RCDs are to be tagged in accordance with the AS 760. ) Where an electrical lead or power tool is to be used an RCD MUST be used. No power tool or electrical equipment is to be used unless it is fully protected. Activity Use of power tool / electrical equipment Risks Inherent Risk Risk Control Measures Electrocution 9 No work to be carried out without an appropriately tagged RCD. Electric Shock 9 No work to be carried out without an appropriately tagged RCD. Target Risk Who is Responsible? All employees at the site are to be inducted (name, date & signature) A.G. Coombs 2010 Form (Ver 2. Nov-10) S W M S N o P a g e 1 of 1
37 Job No. SWMS No. 2.1 Ver.1 Site Name: ISPT C/o CBRE Date Oct-12 Site Address: Numbers 1 and 2 Julius Ave North Ryde Permit to Work required? Yes No SWMS Name WORK ON PUMPS PPE Requirement: Safety Boots High Visibility Vest / Clothing Safety Glasses Gloves Hard Hat Other Specify Prepared by: Luke Snell Reviewed by: sign Legislation / Guidance Material: WH&S Act 2011 WH&S Regulations 2011 CONSIDERATIONS 1) Isolate pump, water and electrical (tag out / lock out) 2) Check motor ) Check pump bearings ) Check pump couplings 5) Check gland or mechanical seal 6) Make adjustments as necessary 7) Remove and clean strainer 8) Re-instate pump then remove isolation National Code of Practise- Induction for Construction Work Activity Risks Inherent Risk Risk Control Measures Target Risk Who is Responsible? Pre-Start Planning (pre-start checks are to be conducted prior to beginning a new task and/or relocating) Inexperienced persons performing tasks resulting in personal injury and injury to others 7 1 st year apprentices, trainees or Work Experience staff are to work under direct supervision by an experience tradesman Only competent employees who are competent with a particular task are allocated that task Poor access resulting in slips, 7 Maintain good housekeeping practices eg. Ensure rubbish bins are accessible and materials are stored appropriately Ensure designated access points are clear and defined Ensure work area to be clear of debris Poor Lighting resulting in slips, 7 Ensure access lighting is adequate Ensure task lighting is adequate Work in Vicinity of Noisy Equipment Hearing Loss 8 Wear appropriate hearing protection A.G. Coombs 2010 Form (Ver 2. Nov-10) S W M S N o 2. 1 P a g e 1 of 2
38 ear muffs 0dB reduction. Work on Pump Contact with moving machinery / entanglement 9 Turn pump off and isolate (tag out / lock out). Wait for motor to cool down Wear appropriate fitting protective clothing. Work Near Pipes and / or Operating Machinery Heat / Burns / Scalding Entrapment 8 Wear appropriate protective clothing including gloves. Work Near Pipes Heating / Hot water pumps and pipes / burns, scalds Observe warning notices Treat all services as operational 8 Wear appropriate protective clothing Work on Pipes / Pump Water Spillage / Slippery Floor / Slips 8 Clean / dry / mop area where possible Barricade area where necessary Lifting / Manoeuvring pump Strain / Sprain 8 Ensure correct posture when working Where in static position, take regular breaks. Correct manual handling techniques Qualification and experience required to complete task Personnel, Duties and Responsibilities(Supervisory staff and others) Equipment to be used MSDS Required Training Required to Complete Work All employees must have a Industry Induction Card A.G. Coombs Site Foreman All Employees must have completed, All employees have been consulted on SWMS controls and inducted into SWMS and Site Specific Requirements (name, date & signature) A.G. Coombs Site Induction which includes reading and understanding the A.G. Coombs Site WH&S plan Client Site Induction A.G. Coombs 2010 Form (Ver 2. Nov-10) S W M S N o 2. 1 P a g e 2 of 2
39 Job No. SWMS No. 2.2 Ver.1 Site Name: ISPT C/o CBRE Date Oct-12 Site Address: Numbers 1 and 2 Julius Ave North Ryde Permit to Work required? Yes No SWMS Name CHANGING PUMPS PPE Requirement: Safety Boots High Visibility Vest / Clothing Safety Glasses Gloves Hard Hat Other Specify Prepared by: Luke Snell Reviewed by: sign Legislation / Guidance Material: WH&S Act 2011 WH&S Regulations 2011 National Code of Practise- Induction for Construction Work CONSIDERATIONS 1) Isolate water tag out 2) Isolate electricity tag and lock out. ) Disconnect wiring, pipework (support pipe if required). ) Remove coupling guard. 5) Disconnect coupling. 6) Drain pump clear excess water. 7) Remove pump from plinth and relocate to designated area. 8) Install new pump, connect pipework, realign coupling, connect wiring. 9) Refill system. 10) Reinstate guards. 11) Reinstate water and electric services. 12) Check for leaks and bleed system. 1) Restart pump. 1) Confirm correct position and operation. 15) Remove rubbish and dispose of appropriately. Activity Pre-Start Planning (pre-start checks are to be conducted prior to beginning a new task and/or relocating) Risks Inexperienced persons performing tasks resulting in personal injury and injury to others Poor access resulting in slips, Inherent Risk Risk Control Measures 7 1 st year apprentices, trainees or Work Experience staff are to work under direct supervision by an experience tradesman Only competent employees who are competent with a particular task are allocated that task 7 Maintain good housekeeping practices eg. Ensure rubbish bins are accessible and materials are stored appropriately Ensure designated access points are clear and defined Ensure work area to be clear of debris Target Risk Who is Responsible? Poor Lighting resulting in slips, 7 Ensure access lighting is adequate A.G. Coombs 2010 Form (Ver 2. Nov-10) S W M S N o 2. 2 P a g e 1 of
40 Isolate services (water / electricity) Disconnect pipe work Exposure to water (under pressure) and electricity. Electrocution Slips caused by water spillage to floor 9 9 Ensure task lighting is adequate Tag out / lock out services Appropriately qualified persons to perform work; eg: D grade Electrical licence holder. Support pipework to limit spillage 5 Clean up water spill 5 Burns 9 Wait for pipe to cool down Drain pump Slips / falls 7 Clear excess water / mop up / dry the area. Remove pump from plinth Strains / Sprains 8 Check weight of pump prior to lifting. Where necessary obtain mechanical lifting device prepare a SWMS. Crushing Injuries 9 Use correct manual handling technique (refer SWMS 1.1). Where necessary, obtain additional resources (people). Install new pump Strains / sprains 8 Use procedure developed for removal of pump Use mechanical lifting devices as necessary. Reinstate services ~ Use tag out / lock out procedure - A.G. Coombs 2010 Form (Ver 2. Nov-10) S W M S N o 2. 2 P a g e 2 of
SAFE WORK METHOD STATEMENT
SAFE WORK METHOD STATEMENT WATER PUMP - PETROL Prepared for Client: Rural Construction & Maintenance Pty Ltd Project No: 1 Site: 660 Great Ocean Road, Bellbrae Date Prepared: 29/07/2015 1. RESPONSIBILITIES
More informationSAFE WORK METHOD STATEMENT SWMS No Version
SAFE WORK METHOD STATEMENT SWMS No Version Company Name: Hunter Readymixed Concrete Pty Ltd 00 004 Location: Thornton Cessnock Tea Gardens Gateshead ABN: 6 076 08 695 SWMS Developed By: Duane Harrison
More informationTHE CONTROLLED COPY OF THIS DOCUMENT IS ON THE COMPUTER NETWORK PRINTED COPIES ARE ONLY CURRENT FOR THE DATE AT THE BOTTOM OF THE PAGE.
TE CONTROLLED COPY OF TIS DOCUMENT IS ON TE COMPUTER NETWORK PRINTED COPIES ARE ONLY CURRENT FOR TE DATE AT TE BOTTOM OF TE PAGE. Title Using Angle Grinders SWMS No. 8 Authorized and email Signed by the
More informationSafe Work Method Statement LRB TREE SERVICES 6 Behland St, Kearneys Spring QLD, 4350 ABN
JOB NO: PROJECT: DATE: 1/1/2018 SWMS NO: SWMS 001.1 PREPARED BY: LUKE BLINCO REVISED BY: ACTIVITY: TREE REMOVAL & PRUNING SIGNED BY: REVISION DATE: MINIMUM PERSONAL PROTECTIVE EQUIPMENT (PPE) REQUIREMENTS
More informationSAFE WORK METHOD STATEMENT Part B
SAFE WORK METHOD STATEMENT Part B SWMS No.: 01 WORK ACTIVITY DESCRIPTION: Door Installation All FORESEEABLE OHS & ENVIRONMENTAL HAZARDS & RISKS ASSOSSIATED WITH THE WORKS MUST BE ASSESSED & ALLOCATED CONTROLS
More informationWORK METHOD STATEMENT STRUCTURAL STEEL
ORGANISATION DETAILS Organisation Name: Gedoun Constructions Pty Ltd Contact Name: Joe Gedoun ACN/ABN: 52 284 873 581 Contact Position: Director Address: PO Box 1138, Townsville QLD 4810 Contact Phone
More informationHazard Identification and Risk Assessment Form. Risk Assessment
Identification and Assessment Form Assessment Tool & Machine Work General Various injuries (including potential fatalities) All staff complete safety induction programme at the start of the module. instructed
More informationSAFE WORK METHOD STATEMENT
SAFE WORK METHOD STATEMENT AUGER / POST HOLE DIGGER Prepared for Client: Rural Construction & Maintenance Pty Ltd Project No: 1 Site: 660 Great Ocean Road, Bellbrae Date Prepared: 29/07/2015 1. RESPONSIBILITIES
More informationUniversity College Dublin Machinery/Equipment Risk Assessment Template
1. General Information Name of Person(s) carrying out assessment and their position Principal Investigator / Supervisor / Head of School or Unit (Person responsible for ensuring safety) Date of assessment
More informationJOB SAFETY ANALYSIS. How to use the Risk Assessment Charts. Likelihood A (Almost Certain) B (Likely) C (Possible)
Page 1 of 6 How to use the Assessment Charts 1. Determine the Likelihood on the Qualitative Assessment Process Chart (pick a letter applicable to the task). 2. Determine the Consequence on the Qualitative
More informationSafe Work Method Statement
Company Name: Safe Work Method Statement Site Address: Other Details: Contractor: Activity/Trade: Electrician Date: TASKS List the tasks required to perform the activity in sequence carried out. Entry
More informationWORK METHOD STATEMENT CARPET LAYING
ORGANISATION DETAILS Organisation Name: Gedoun Constructions Pty Ltd Contact Name: Joe Gedoun ACN/ABN: 52 284 873 581 Contact Position: Director Address: PO Box 1138, Townsville QLD 4810 Contact Phone
More informationRisk assessment. Assessment details. Task. Introduction. Please complete the form as fully and accurately as you can. Assessors job title
Risk assessment Introduction Please complete the form as fully and accurately as you can. Assessment details Name of organisation Assessor's name Assessors job title Any Company John Smith Manager Date
More informationWHS OHS HAZARD REGISTER (SITE AND OFFICE OPERATIONS)
WHS 017 - WHS 017 Hazard Register - Version 5.0 April 20 Doc No: WHS 017 Effective Date: 04/04/20 1 WORKING WITH EARTHMOVING PLANT/ TRUCKS/SITE VEHICLES COLLISIONS OTHER PLANT EQUIPMENT SITE VEHICLES PERSONNELL
More informationHow severely could the risk hurt someone? Low/Insignificant First aid
Safe Work Method Statement No: WMS-02 Task: Concreting, Formwork and Steel Fixing This WMS is submitted to: Project name and site address: Contact: Preparation of WMS by: Robert Raams Company: Enwon (Australia)
More informationHazard Identification and Risk Assessment Form. Risk Assessment
Identification and Form Tool & Machine Work General Various (including potential fatalities) All staff complete safety induction programme at the start of the module. instructed in safe operation of each
More informationHow severely could the risk hurt someone? Low/Insignificant First aid
Safe Work Method Statement No: WMS-0 Task: Line Marking This WMS is submitted to: Project name and site address: Contact: Preparation of WMS by: Robert Raams Company: Enwon (Australia) Pty Ltd Authorised
More informationFLYING OBJECTS MANUAL HANDLING EXCESSIVE NOISE
JOB NO: PROJECT: DATE: SWMS NO: SWMS 002 PREPARED BY: Ian Hartley REVISED BY: Nick Bragg & Cameron McNeil ACTIVITY: STUMP REMOVAL SUPERVISED BY: REVISION DATE: April 2016 MINIMUM PERSONAL PROTECTIVE EQUIPMENT
More informationCONSTRUCTION HEALTH AND SAFETY MANAGEMENT SYSTEM BASELINE HIRA
RECOMMENDED ADDITIONAL CONTROLS TASK / ACTIVITY/ EQUIPMENT/ FACILITY HAZARDS UNWANTED EVENT MINIMUM CONTROLS REQUIRED RISK NO. LIKELI-HOOD CONSE-QUENCE RISK VALUE Project Risk Assessment Page 1 of 16 All
More informationSAFE WORK METHOD STATEMENT
SAFE WORK METHOD STATEMENT EXCAVATION OR TRENCHING Prepared for Client: Rural Construction & Maintenance Pty Ltd Project No: 1 Site: 660 Great Ocean Road, Bellbrae Date Prepared: 29/07/2015 1. RESPONSIBILITIES
More informationHazard Identification and Risk Assessment Form. Risk Assessment
Current Tool & Machine Work General Various injuries (including potential fatalities) All staff complete safety induction programme at the start of the module. instructed in safe operation of each tool/machine.
More informationSAFE WORK METHOD STATEMENT
SAFE WORK METHOD STATEMENT LOADING AND UNLOADING VEHICLES Prepared for Client: Rural Construction & Maintenance Pty Ltd Project No: 1 Site: 660 Great Ocean Road, Bellbrae Date Prepared: 29/07/2015 1. RESPONSIBILITIES
More informationHow severely could the risk hurt someone?
Safe Work Method Statement No: WMS-08 Task: Install Drainage This WMS is submitted to: Project name and site address: Contact: Preparation of WMS by: Robert Raams Company: Enwon (Australia) Pty Ltd Authorised
More informationQUEENSLAND UNIVERSITY OF TECHNOLOGY
QUEENSLAND UNIVERSITY OF TECHNOLOGY SITE SPECIFIC SAFETY MANAGEMENT PLAN FOR SAMFORD HOUSE SAMFORD ECOLOGICAL RESEARCH FACILITY SAMFORD VALLEY 2007 Dylan Randall SN: 06305466 dylan.randall@student.qut.edu.au
More informationAppendix 4C - Sample SWMS Trenching
Appendix 4C - Sample SWMS Trenching SAFE WORK METHOD STATEMENT SWMS Reference : Insert document number : Version A Date : Workplace / Project : Company Address: Work Activity / Job / Task or Process :
More informationSafe Work Method Statement
TE CONTROLLED COPY OF TIS DOCUMENT IS ON TE COMPUTER NETWORK PRINTED COPIES ARE ONLY CURRENT FOR TE DATE AT TE BOTTOM OF TE PAGE. Title Working at eight SWMS No. 16 Authorized and email Signed by the (Managing
More informationSAFETY MANAGEMENT SYSTEM
Equipment Location: Hazard Hired From All Master Hire Stores Entanglement Can anyone s hair, clothing, gloves, necktie, jewellery, cleaning brushes, rags or other materials become entangled with moving
More informationHow severely could the risk hurt someone? Low/Insignificant First aid
Safe Work Method Statement No: WMS-0 Task: Operate Diesel Road Saw This WMS is submitted to: Project name and site address: Contact: Preparation of WMS by: Robert Raams Company: Enwon (Australia) Pty Ltd
More informationEHS Workplace Inspection Checklist (Ref. SOP QMS-080; EHS-010)
(Ref. SOP QMS-080; EHS-010) Form-445 Inspected by: Date of inspection Date of Report Report # Pages Area Manager: Area Inspected: General This EHS Workplace Inspection was conducted by: Scope of the Inspection:
More informationWH&S Act 2011 & Regulations 2011, Environmental Protection Act and Regulations
Workplace Address: Page 1 of PART 1: TASK DETAILS Client: JOB/TASK: Using Water blaster PART 2: RESOURCES Relevant Legislation/Codes Practice: Training Required: Equipment Used: Materials Used: Substances
More informationThe Sample Company Pty Ltd
Job Safety and Environmental Analysis (JSEA) / Safe Work Method Statement (SWMS) Part 1: Project and Task Identification Process Initiators of SWMSs are responsible for consulting the Project Supervisor,
More informationHAZARD IDENTIFICATION AND RISK ANALYSIS RECORD
HAZARD IDENTIFICATION AND RISK ANALYSIS RECORD Location: Company Wide Date of Assessment: 04 April 2017 Revision No.: 0 Description of planned work or activity: HIRA Register Attendees: see attached tool-box
More informationSafe Work Method Statement
Title Skid Steer Operation (Bobcat) SWMS No. 14 Authorized and email Signed by the (Managing Director / CEO / Partner / Proprietor) on Date 01/08 /2016 Safe Work Procedure for the Work:- Yes No Employees
More informationSafe Work Method Statement (SWMS)
Safe Work Method Statement (SWMS) Organisation Details : Organisation Name Northern Plumbing Contact ABN 17 15 41 4 Position Director Address 47 Thomas Street Edgeworth 85 Phone Number 0411 10 4 Project
More informationSpecific Safety Legislation/Codes of Practice/Australian Standards applicable to this JSA (Tick those applicable).
OCCUPATIONAL HEALTH & SAFETY MANUAL Section OHS-005, Job Safety Analysis SCORESBY, VIC 3179 GEELONG, VIC 3218 MALAGA, WA 6090 DUDLEY PARK, SA 5008 MANSFIELD, QLD 4122 NORTH ROCKS, NSW, 2641 ACT 2609 LAVINGTON,
More informationSAFE WORK METHOD STATEMENT Part 1 CONCRETE SAWING
SAFE WORK METHOD STATEMENT Part 1 CONCRETE SAWING Personal Protective Equipment Foot Hearing High Visibility Head Eye Face Hand Protective Clothing Breathing Normal Requirements: Safety footwear, hearing
More informationSAFETY MANAGEMENT SYSTEM
Equipment Location: Hazard Hired From All Master Hire Stores Entanglement Can anyone s hair, clothing, gloves, necktie, jewellery, cleaning brushes, rags or other materials become entangled with moving
More informationTitle: Plant and Equipment Risk Management Form Issue Date: Review Date: Page Number: 1 of 11
Issue Date: Review Date: Page Number: 1 of 11 1. Hazard Management Details General Plant/Equipment Item: WOOD LATHE Make/Model No.: Serial No.: School: Work Location: Name of Person(s) Conducting Activity:
More informationHEALTH AND SAFETY METHOD STATEMENT AIR CONDITIONING/REFRIGERATION MAINTENANCE/SERVICE. 2. Clean filters and screens when necessary
HEALTH AND SAFETY METHOD STATEMENT AIR CONDITIONING/REFRIGERATION MAINTENANCE/SERVICE Air Conditioning Indoor/Outdoor Unit as applicable 1. Check Pressures 2. Clean filters and screens when necessary 3.
More informationTRADE AREA: ELECTRICAL INDUSTRY
TRADE AREA: ELECTRICAL INDUSTRY Some possible workplace hazards and possible ways for Host employers and Apprentices/Trainees in controlling these hazards. What are possible hazards? What could be possible
More informationSWMS No 012 Samark North Qld Pty Ltd ABN : Electrical Contractors License C37121 Page 2 of 6
Samark North Qld Pty Ltd SWMS SWMS No 0 Samark North Qld Pty Ltd ABN : 99 08 98 87 Electrical Contractors License C37 Page of 6 Safe Work Method Statement Title: SWMS:0 INSTALLING LIGHT POLES Work Method
More informationSAFETY MANAGEMENT SYSTEM
Equipment Location: Hazard Hired From All Master Hire Stores Entanglement Can anyone s hair, clothing, gloves, necktie, jewellery, cleaning brushes, rags or other materials become entangled with moving
More informationSAFETY MANAGEMENT SYSTEM
Equipment Location: Hazard Hired From All Master Hire Stores Entanglement Can anyone s hair, clothing, gloves, necktie, jewellery, cleaning brushes, rags or other materials become entangled with moving
More informationSAFE WORK METHOD STATEMENTS
Recips 11/56 Norcal Road Nunawading Vic. 11 ABN: 48 04 075 70 Contact Person: Dean Spicer Contact Number: 9878 9006 SAFE WORK METHOD STATEMENTS for Format 1 Various Service Clients for Service work and
More informationFIRE HYDRANT TESTING METHOD STATEMENT.
SUBJECT: TASK: FIRE HYDRANT INSPECTION & TESTING. 1. Location....1 2. The Scope of Works.... 1 3. Description of Task.... 1 4. Access & Egress to & from Work Area.... 2 5. Safety Hazard Identification....
More informationGarbex Drum Crusher Safe Work Procedure PTES_HSE_SWP_028. Name Date Signature. Author Jarred Hearle 30/11/2014. Reviewed John Nulty 30/11/2014
Garbex Drum Crusher Safe Work Procedure PTES_HSE_SWP_028 Name Date Signature Author Jarred Hearle 30/11/2014 Reviewed John Nulty 30/11/2014 Approved Geoff Selfe 01/12/2014 Key Safety Acts Complete a 5
More informationMethod Statement: Testing Dry Riser System
Method Statement: Testing Dry Riser System Page 1 of 6 Scope of work Test dry riser system in accordance with BS 5306. Definitions For the purposes of this document, the following definitions apply Rising
More informationRockhampton Office Brisbane Office Tarong Site. Barron Gorge Hydro PS Kareeya Hydro PS Mica Creek PS
Business Procedure Hot Work Document Number OHS-PROC-128 This document applies to the following sites: All Sites Rockhampton Office Brisbane Office Tarong Site Barron Gorge Hydro PS Kareeya Hydro PS Mica
More informationSafe Work Method Statement
TE CONTROLLED COPY OF TIS DOCUMENT IS ON TE COMPUTER NETWORK PRINTED COPIES ARE ONLY CURRENT FOR TE DATE AT TE BOTTOM OF TE PAGE. Title Dogging of Crane General Loading and Unloading SWMS No. 20 Authorized
More informationWORK METHOD STATEMENT ALUMINIUM WINDOWS AND DOORS
ORGANISATION DETAILS Organisation Name: Gedoun Constructions Pty Ltd Contact Name: Joe Gedoun ACN/ABN: 52 284 873 581 Contact Position: Director Address: PO Box 1138, Townsville QLD 4810 Contact Phone
More informationTemporary load-bearing support for structural alterations or repairs
CRITICAL NOTE This document only becomes a Safe Work Method Statement where the High Risk Construction Work section of this document is completed Company: ABN: Contact Person: Ph: Project/Site: Principal
More informationHazard Identification and Risk Assessment Form. Risk Assessment
Identification and Assessment Form Assessment Tool & Machine Work General Various injuries (including potential fatalities) All staff complete safety induction programme at the start of the module. instructed
More informationOperation of Embrey Excavator Shears Safe Work Procedure PTES_HSE_SWP_039. Name Date Signature. Author Jarred Hearle 27/11/2015
Operation of Embrey Excavator Shears Safe Work Procedure PTES_HSE_SWP_039 Name Date Signature Author Jarred Hearle 27/11/2015 Reviewed FMG Site Team 27/11/2015 ---------- Approved Geoff Selfe 27/11/2015
More informationWORK METHOD STATEMENT TERMITE PROTECTION
ORGANISATION DETAILS Organisation Name: Gedoun Constructions Pty Ltd Contact Name: Joe Gedoun ACN/ABN: 52 284 873 581 Contact Position: Director Address: PO Box 1138, Townsville QLD 4810 Contact Phone
More informationSAFE WORK METHOD STATEMENT CARPENTER
HOST EMPLOYER DECLARATION I declare the worker/s named on this work authority have been provided with a site specific safety induction that complies with the requirements of the Workplace Health & Safety
More informationJOB SAFETY ENVIRONMENT ANALYSIS (JSEA) Working With In Situ Testing Rigs
Personnel Involved Manager Project Operators Assistant Notes re Operator/Off-Sider Training Allan McConnell In situ testing is a niche business with very few rigs in Australia. There are no specific training
More informationSAFE WORK METHOD STATEMENT WORKING IN CONFINED SPACE HSE NET NAT SWMS APAND00030
SAFE WORK METHOD STATEMENT WORKING IN CONFINED SPACE HSE NET NAT SWMS APAND00030 HIGH RISK APT AM Holdings Pty. Ltd. [ABN] 95124754383 Principal Contractor (PC) APA Group Level 19, HSBC Building 580 George
More informationManual Handling Procedure
Manual Handling Procedure Table of Contents 1 Purpose... 3 2 Scope... 3 3 Definitions... 3 4 Responsibilities... 3 4.1 Managers And Supervisors... 3 4.2 Workers (Employees, Contractors And Visitors)...
More informationJob Safety and Environmental Analysis (JSEA)/Safe Work Method Statement (SWMS)
Job Safety and Environmental Analysis (JSEA)/Safe Work Method Statement (SWMS) Part 1: Project and Task Identification Process: Initiators of JSEAs are responsible for consulting the Project Supervisor,
More informationContractor Hazard Identification and Control Guide
Exposure to Asbestos Containing Materials (ACM) Accidental disturbance or removal of ACM. Asbestos Containing Materials are to be removed outside school hours. No DET employees, students or visitors are
More informationWORK METHOD STATEMENT ELECTRICAL
ORGANISATION DETAILS Organisation Name: Gedoun Constructions Pty Ltd Contact Name: Joe Gedoun ACN/ABN: 52 284 873 581 Contact Position: Director Address: PO Box 1138, Townsville QLD 4810 Contact Phone
More informationSH&E Work Method Statement Concrete Cutting & Drilling Fast Cut Qld Pty Ltd, 91 Basalt, GEEBUNG PH M ABN
SH&E Work Method Statement Concrete Cutting & Drilling Fast Cut Qld Pty Ltd, 91 Basalt, GEEBUNG PH 07 3265 6537 M 0411 756 719 ABN 45 081 359 613 OHS-FRM-100 Rev 11 (07/18) Page 1 SH&EWMS No.: F-C-QLD-30
More information75 Years of Health and Safety Guidance
H&S Guide: 60 Working Risks Personal Protective Equipment Personal Protective Equipment (also known as PPE) Employers have duties concerning the provision and use of personal protective equipment at work.
More informationBOILER MECHANIC//SR. BOILER MECHANIC
WORKING IN STEAM MANHOLES Activity Hazard Identification Required Precautions 1. Driving to and from work site. 1. Motor vehicle accident; striking pedestrians, bicyclists, or individuals using rollerblades.
More informationTo secure the health and safety of workers and workplaces; to ensure everyone goes home safely at the end of each day. To set minimum standards for the management of particular hazards where alternative
More informationCollision Repair Shop Inspection Checklist
Collision Repair Shop Inspection Checklist Note: This is a sample inspection chesklist only, and may mot include all appropriate inspection items. The Occupational Health and Safety Regulation specifies
More informationSH&EWMS No.: F-C-QLD-10 Revision Date: July 2018 Revision Due: July 2019
OHS-FRM-103 Rev11 (07/18) SH&E Work Method Statement Concrete Cutting & Drilling Fast Cut Qld Pty Ltd, 91 Basalt, GEEBUNG ABN 45 081 359 613 Phone: 07 3889 8827 Mobile: 0411 756 719 Page 1 SH&EWMS No.:
More informationSCOPE OF WORK, SAFETY METHOD STATEMENT & RISK ASSESSMENT
SCOPE OF WORK, SAFETY METHOD STATEMENT & RISK ASSESSMENT Prepared for:- Date:- Work Scheduled:- SCOPE OF WORK Carry out installation of flow meters / pressure sensors. Installation of flow meter procedure
More informationSAFE WORK METHOD STATEMENT Part 1. Company Details. Company Name: Contact Name, Position and Phone number: Address: Project details.
SAFE WORK METHOD STATEMENT Part 1 Company Details Company Name: ABN: Contact Name, Position and Phone number: Address: Project details Project: Area: Job Address: Job Description: Activity: Installation
More informationUniversity of Vermont Department of Physical Plant Personal Protective Equipment Program
University of Vermont Department of Physical Plant Personal Protective Equipment Program REVISED AND DISTRIBUTED BY: THE UNIVERSITY OF VERMONT DEPARTMENT OF PHYSICAL PLANT TRAINING AND COMPLIANCE OFFICE
More informationDocument: APA HSE GP Tx Version: 0.01 Date: 04/03/2013 Review by: 26/03/2014 Page 1 of 11 pages
SAFE WORK METHOD STATEMENT WORKSHOP FABRICATION HSE NET NAT SWMS APAND00033 APT AM Holdings Pty. Ltd. [ABN] 95124754383 APA Group Principal Contractor (PC) Level 19, HSBC Building Subcontractor 580 George
More informationPotential risk of injury to staff
Register Fire, Earthquake - other Emergencies Manual Handling and Repetitive Work Repetitive, Forceful Work Poor Housekeeping Not Wearing PPE (Personal Protective Equipment) Potential risk of injury to
More informationSAFE WORK METHOD STATEMENT (SWMS) GENERAL GARDENING with Blowers, Hedge Trimmers, Whipper Snippers, Pruners, Spray Units
Job Description/Task/: General Gardening such as using Blowers, Hedge Trimmers, Whipper Snippers, Pruners, Spray Units Name and Phone Number of Person Completing SWMS: Name and Phone Number of the Person
More informationYou must NOT touch any equipment unless you are authorised to work on or with that equipment and you have followed correct safety procedures.
SYDNEY TOWN HALL 1 HIRER & CONTRACTOR SAFETY FACT SHEET Issue 2 September 2013 www.sydneytownhall.com.au City of Sydney - Venue Management will provide and maintain a safe working environment for the health,
More informationLADDERS FIXED AND PORTABLE
CONTRACTOR WHS HAZARD STANDARD LADDERS FIXED AND PORTABLE EXTERNAL USE ONLY Principles in the Optus Contractor WHS management process CONTRACTOR MANAGEMENT STAGES PRINCIPLES THIS STANDARD REQUISITION Requisition
More informationPowerplay Paintball Brighouse Risk Assessment
Chemical Gas bottles Vehicles Physical Electricity Environment Machinery Powerplay Paintball Brighouse Risk Assessment Location Powerplay Paintball Wakefield and Brighouse Venues Carried out by: Steven
More informationPLANT HAZARD REPORT. Plant Description: Element Aspect Plant Hazards and Controls Advice. Circular Saw
PLANT HAZARD REPORT Plant Description: Circular Saw PLEASE NOTE This plant information has been prepared to assist the purchaser in identifying hazards associated with the plant prior to the purchaser
More informationSAFETY POLICY AND PROCEDURE MANUAL QUESTIONNAIRE
The following questionnaire is designed to aid us in the creation of your policy and procedure manual. Please place a checkmark in the boxes that correspond to the sections that you would like to be included
More informationU.S. CONCRETE, INC. SAFETY POLICY and PROCEDURE MANUAL
SAFE -14 Page 1 of 8 U.S. CONCRETE, INC. SAFETY POLICY and PROCEDURE MANUAL FUNCTION Safety TOPIC Hotwork Permit Program OBJECTIVE(S): GENERAL POLICY: To provide a work atmosphere that is conducive to
More informationSAFE WORK METHOD STATEMENT
Authorised by: Date: list individually, do not group, M or Installing Pipework in ground, M or Induction Take 5 review working area for hazards Falls, crushing, explosions, slips and trips MUST be inducted
More informationConducting An Effective. Welcome!
Conducting An Effective An introduction to the Five Step Process of Job Hazard Analysis JHA-JSA-SWMS-AHA Introductions Welcome! What do you know about Job Hazard Analysis (JHA s)? Does OSHA require JHA
More informationRisk Assessment Form (Qualitative)
Assessment Form (Qualitative) Project / ocation:..d.a.s WATERS Contract No: RA & Issue No: 008 Prepared by:.r.smit Date: 10/10/16 Signature: ACTIVITY DESCRIPTION: Person (s) at risk: General Ground works
More informationWINDMILL (pre-start) HAZARD INSPECTION CHECKLIST
Windmill Hazard Inspection Checklist WINDMILL (pre-start) HAZARD INSPECTION CHECKLIST Authorised by: LOCATION OF INSPECTION...... Inspected By (1)........... (2)..... PRINT PRINT Signature (1):. (2)....
More informationFaculty/School: Pharmacy Initial Issue Date: Oct 2016
Use this form to assist you to complete risk assessments for hazardous activities and processes. Any serious or ongoing hazards should be reported via RiskWare to ensure that appropriate corrective actions
More informationUGRacing Formula Student Garage Risk Assessment
UGRacing Formula Student Garage Risk Assessment University of Glasgow School of Engineering Location: Formula Student Workshop Building: Rankine Building, Oakfield Avenue Glasgow G12 8LT Summary of activities
More informationList all key terms and acronyms used in the procedure, and their definitions.
Purpose The purpose of this procedure is to provide guidelines for electrical safety in general within Seqwater in compliance with the Electrical Safety Act 2002, Industry Codes of Practice, Regulations,
More informationSAFE WORK METHOD STATEMENT Part 1
SAFE WORK METHOD STATEMENT Part 1 Company Details: Aztech Integrated Systems Pty Ltd ABN: 50 142 740 172 Director : Aaron Caruana +61 418 178 719 7/227A Brisbane Road, Labrador, QLD, 4215. Project Details:
More informationCENTRAL PLANT HEATING/CHILLED WATER OPERATOR Ref. Code: C-WO-4
CENTRAL PLANT HEATING/CHILLED WATER OPERATOR Ref. Code: C-WO-4 OPERATING OF AUXILIARY EQUIPMENT Activity Hazard Identification Required Precautions 1. Inspecting boilers. 1a. Slipping on oily or wet floor.
More informationSH&EWMS No: F-C-QLD-23 Revision Date: July 2018 Revision Due: July Brief Description of Work Activity: Use Petrol Hand Saw / Ring Saw
SH&E Work Method Statement Concrete Cutting & Drilling Fast Cut Qld Pty Ltd, 91 Basalt St, GEEBUNG 4034 ABN 45 081 359 613 Phone: 07 3265 6537 Mobile: 0411 756 719 OHS-FRM-100 Rev 11 (07/18) Page 1 SH&EWMS
More information1b. Slipping; tripping; getting knocked into by pedestrians.
MAINTAINING AND REPAIRING HYDRAULIC AND TRACTION PASSENGER AND FREIGHT ELEVATORS AND HANDICAP EQUIPMENT Activity Hazard Identification Required Precautions 1. Walking to and from work site. 1a. Back ache;
More informationHandout Activity: HA107
Engines: Motive Power Types: Handout Activity: HA107 Student/Intern information: Name Date Class Identifying hazards Summary A workshop is a hazardous environment. The objective of this procedure is to
More informationPLANNED LIGHTING MAINTENANCE LTD METHOD STATEMENT & RISK ASSESSMENT REPLACEMENT OF LAMPS OR REPAIRS TO HIGH LEVEL LIGHT UNITS
PLANNED LIGHTING MAINTENANCE LTD METHOD STATEMENT & RISK ASSESSMENT REPLACEMENT OF LAMPS OR REPAIRS TO HIGH LEVEL LIGHT UNITS Project: (insert Client) Replacement/ Repair of high level light units/ high
More informationCLUB RISK ASSESSMENT TEMPLATE
CLUB / VENUE (Guidance for clubs to adapt for their own use) 1. ALL AREAS Slips, trips and falls injury from slips trips and falls from uneven or damaged surfaces, holes etc. External ground surfaces,
More informationRisk Assessment. Appendix A contains
Risk Assessment Department The Cockpit Risk Assessment number AM/09/01 Date. 1 st July 01 Review due date 0 th July 01 Activity Maintenance and support service working Location The Cockpit Name of Assessor/s
More informationSafety Risk Assessment Roofing Works / Surveying / Inspections
One Direct aintenance td Persons at (Groups) Assessor Appointment Tel. No. Description of Task or Activity A One Direct employees ark Bloxidge H&S anager 0208 821 5197 One Direct Operatives accessing roof
More informationBondi Pipe Freezing PO Box 440 Bondi Jct NSW 1355 ABN SAFE WORK METHOD STATEMENT
Bondi Pipe Freezing PO Box 440 Bondi Jct NSW 1355 ABN 46 050 043 359 SAFE WORK METHOD STATEMENT Client: Project No: Site: Date Prepared: 7/10/2014 by P Molloy ABN: Authorised By: P Molloy 1. RESPONSIBILITIES
More informationRisk Assessment June Skirmish Paintball Games Exeter
Ve hicl Physical Electricity Environment Machiner y Risk Assessment June 2012. Skirmish Paintball Games Exeter Location Skirmish Paintball Exeter Carried out by: Martin Collins Date 10 th June 2012 Authorised
More informationRISK RATING SAFE WORK METHOD STATEMENT 1 HIGH 2 MEDIUM 3LOW. I approve the use of this Safe Work Method Statement: NAME: POSITION: Department Manager
RISK RATING 1 HIGH 2 MEDIUM 3LOW SAFE WORK METHOD STATEMENT Title: : Traineeship Ref No: 1 I approve the use of this Safe Work Method Statement: NAME: POSITION: Department Manager SIGNATURE: DATE: / /
More informationSafety Risk Assessment Working at Height: Mobile Tower Scaffold
Persons at (Groups) Assessor Appointment Tel. No. Description of Task or Activity A One Direct employees Mark Bloxidge H&S Manager 0208 821 5197 Working at height from Mobile Tower B Contractors/Sub contractors
More informationSafe Work Method Statement (SWMS) Worksheet
WORKPLACE / PROJECT NAME: AMS REF NO / TITLE: COMPANY NAME: NETWORK DIRECTIONAL DRILLING (GEELONG) P/L (if applicable) SWMS NO: (if applicable) WORK ACTIVITY / JOB / TASK OR PROCESS DESCRIPTION DATE SWMS
More information