1 Sliding Hill Road - Widening (UPC ) Scored HB 2 Application Project Application ID: 434 General Project Information Project Title Sliding Hill Road - Widening (UPC ) Principal Improvement Highway Organization Name Hanover County Does this project include any improvements to non-vdot maintained roadways? False Project Hanover County, through an agreement with VDOT, is presently developing a project through the public involvement stage to widen Sliding Hill Rd (Rt. 656) (UPC ) from 2 to 4 lanes between Atlee Station Rd and New Ashcake Rd (approximately 1.2 miles). The improvements will also include pedestrian and bicycle facilities, turn lanes and access management. Functionally classified as a Minor Arterial, Sliding Hill Rd is a 2-lane facility caring approximately 15,000 VPD in the project segment and is forecast to increase to 20-25,000 VPD by The Sliding Hill Rd corridor provides access to large residential, commercial and industrial developments including the Hanover County Airport and Industrial Air Park (5,000 employees, Freight Dependent, Knowledge, Local Serving per VTrans 2040 Economic Conditions Summary). The corridor is currently at capacity for a 2-lane facility. Interim improvements including turn lanes, signalization and limited widening has extended the useful life of the corridor; however, without a project to widen the facility to 4 lanes significant deterioration of this significant transportation facility is certain. The PE phase of the project is partially funded with RSTP funds allocated through the Richmond Regional Transportation Planning Organization (RRTPO). This application seeks HB2 funding to augment local and anticipated state revenue sharing funding to complete the design, right of way, utilities and construction portion of the project. The project is coordinated with land use and transportation through the Hanover County Comprehensive Plan and the RRTPO and is identified in the Secondary Six-Year Plan, Six-Year Improvement Program, and is consistent with the RRTPO Long Range Transportation Plan. HB2 Need Categories Regional Network Application Program District Grant

2 How does this project address VTrans 2040 need? This project will address Richmond Regional Network Need G (I-95 Corridor Reliability for the Commonwealth of Virginia as identified in VTrans 2040 Statewide Multimodal Transportation Plan for Regional Networks for the Richmond Region) by providing a 4-lane facility on Sliding Hill Rd to provide congestion relief in the I-95 and 295 corridors. This project improves corridor reliability by providing an outlet to Route 301, which functions as an alternate to I-95 during peak periods. Additionally, the project is consistent with the VTrans2040 Vision Plan goals of Economic Competitiveness & Prosperity, Accessible & Connected Places, Safety for All Users, Proactive System Management, and Healthy & Sustainable Communities. Specifically, as a reliever corridor to I-95 and 295 (Corridor of Significance, Washington to rth Carolina, Corridor K, Section 2), the project will provide congestion relief and assist with reliability overflow to Route 301. Because of its proximity to I-95 and 295, failure of the corridor over time has the potential to impact corridors of statewide importance due to peak hour back up onto the northbound exit ramp. These corridors are already heavily impacted by the merge of I-95 and 295 at this location. Sliding Hill Rd corridor also serves an important regional network function by providing an important reliever and connecting function between the I-95 / 295 corridors and Route 301 during congested periods. Economic Competitiveness & Prosperity goal is being achieved as a result of the project's connection to the Hanover Industrial Air Park, a large (5,000 person) employment center, and the Hanover County Airport, which are located in the Sliding Hill Rd corridor. The Sliding Hill Rd corridor supports a broad array of business and industry which are heavily freight dependent. These businesses are primarily located in the Industrial Air Park; however, potential for economic development expansion exists along the corridor through the development of a number of existing zoned or planned industrial and business developments. The corridor supports locally over 5,000 jobs according to VTrans 2040 Economic Conditions Summary and that is expected to grow. In addition the corridor supports the movement of residences from over 3,500 residential homes to a wide array of employment centers throughout the region and surrounding communities which relates to the goal of Accessible & Connected Places. Bicycle and pedestrian facilities are also important to the corridor and will be designed to facilitate mobility where appropriate, which will contribute to the lifestyle goal of Healthy & Sustainable Communities. Accident history suggests the need for operational improvements, which will be addressed by the project and help achieve the goal of Safety for All Users. The project utilizes existing infrastructure to the extent possible while also making necessary upgrades to pavements, drainage, signals and other project features, which contributes to the goal of Proactive System Management. Location PDCs Served Richmond Regional MPOs Served Richmond Area MPO Jurisdictions Served Hanover County Districts Served Richmond

3 Features Project Improvements Highway Improvement Comments Add New Through Lanes(s) Add an additional lane in each direction (2 lanes) from Kings Charter Dr. (sta ) to the existing 4-lane section at New Ashcake Rd (sta ) (2 x 4,250 ft). Shoulder Improvement(s) Construct new 8 ft shoulders (4 ft paved) beginning at the transition from the urban section at Atlee Commerce Blvd (sta ) to the existing 4-lane section at New Ashcake Rd (sta ) (2 x 2,450 ft). Access Management MS2 medians from Atlee Station Rd (sta to Kings Charter Dr (sta ), from Kings Charter Dr. to Totopotomoy Tr. (sta ), from Totopotomoy Tr. to Atlee Commerce Blvd (sta ), from Atlee Commerce Blvd to Air Park Rd (sta ), from Air Park Rd to break at sta , from break at station to connection to existing 4-lane section at New Ashcake Rd. (sta ). Intersection Improvement(s) The following intersections are improved: Atlee Station Rd / Leadbetter Rd (east side), Kings Charter Dr., Totopotomy Tr., Atlee Commons Dr. / Atlee Commerce Blvd, Air Park Rd, King Braxton Ct. Turn Lane Improvement(s) Numerous right and left turn lane improvements which will reduce rear-end collisions and facilitate through movement of traffic in the corridor. Turn lane improvements include a continuous right turn lane from McDonald's through the intersection of Kings Charter Dr. Proposed right turn lane at Tototopomy Tr. Right turn lane maintained at Atlee Commerce Blvd. Proposed right turn lane at Atlee Commons Dr. Several left turn lanes along the corridor. New Traffic Signal/Signal Optimization Upgraded signal at intersection of Sliding Hill

4 Rd and Kings Charter Dr. to include pedestrian accommodations. Bike/Pedestrian Improvement Add/Construct Bike Lane Paved Shoulder (Minimum 4-Foot Ridable Surface) Construct Sidewalk Improve Bike/Pedestrian Crossing (At Grade) Comments Bike lane throughout commercial sections from sta to sta where bike facilities transition to paved shoulder (2 x 2,970 ft). (4 ft paved) beginning at the transition from the urban section at Atlee Commerce Blvd (sta ) to the existing 4-lane section at New Ashcake Rd (sta ) (2 x 2,450 ft). Sidewalk along commercial frontage approximately 2,650 ft providing access to residential areas. Pedestrian crossing added at intersection of Sliding Hill Rd and Kings Charter Dr. (sta ). Right of Way Improvement Right of Way/Easements acquisition required Comments Fee simple right of way and temporary construction, drainage and utility easements required throughout the corridor. Factors Accessibility Measure Response Additional tes Project includes transit system improvements or reduces delay on a roadway with scheduled peak service of one transit vehicle per hour. Project includes improvements to an existing or proposed park and ride lot (e.g., new lot, more spaces, entrance/exit, technology (payment, traveler information)). Project includes construction or replacement of bike facilities. For bicycle projects, off-road or on-road buffered or clearly delineated facilities are required. Yes The project includes approximately 5,940 ft of dedicated bike lane and 4,900 ft of 4 ft paved shoulder

5 Project includes construction or replacement of pedestrian facilities. For pedestrian projects, sidewalks, pedestrian signals, marked crosswalks, refuge islands, and other treatments are required (as appropriate). Project includes improvements to existing or new HOV/HOT lanes or ramps to HOV/HOT. Project provides real-time traveler information or wayfinding specifically for intermodal connections (access to transit station or park and ride lot). Provides traveler information or is directly linked to an existing TMC network/its architecture. Yes to accommodate bikes beyond the travel lanes. Sidewalk (2,650 ft) and signalized pedestrian crossing at Kings Charter Dr. and numerous ADA access points added. Land Use and Transportation Coordination Measure Response Additional tes Does the project promote walkable/bicycle friendly, mixed-use development? Yes The project includes bike and pedestrian facilities that will link existing commercial and retail shopping centers to approximately 3,200 adjacent Does the project promote in-fill development? Is there a locally/regionally adopted corridor/access management plan for the project area that addresses interparcel Yes residential homes There are a number of large pad ready sights available for infill in the development sites identified as Atlee Commerce Center and Atlee Commons. Several existing zoned parcels in excess of 200 acres are available for infill along and at the end of the corridor for Light Industrial and Industrial / Commercial. See the attached zoning map which identifies over 400 acres of undeveloped commercial and industrial zoned parcels in the corridor. On the map, Commercial designations are: O-S, B-O, B-1, B-2, B-3, MX. Industrial designations are: M-1, M-2, M-3.

6 connectivity and exceeds VDOT s minimum spacing standards? Environment Measure Response Additional tes Project includes construction or replacement of bike facilities. For bicycle projects, off-road or on-road buffered or clearly delineated facilities are required. Yes The project includes approximately 5,940 ft of dedicated bike lane and 4,900 ft of 4 ft paved shoulder to accommodate bikes Project includes construction or replacement of pedestrian facilities. For pedestrian projects, sidewalks, pedestrian signals, marked crosswalks, refuge islands, and other treatments are required (as appropriate). Project includes improvements to rail transit or passenger rail facilities. Project includes improvements to an existing or proposed park-and-ride lot (e.g., new lot, more spaces, entrance/exit, technology (payment, traveler information)). Project includes bus facility improvements or reduces delay on a roadway with scheduled peak service of one transit vehicle per hour.* Project includes improvements to freight rail network or intermodal (truck to rail) facilities/ports/terminals. Project include special accommodations for hybrid or electric vehicles, or space or infrastructure for electric vehicle parking/charging). Project includes energy efficient infrastructure or fleets, including: hybrid or electric buses, LED lights and signals, electronic/open road tolling, alternative energy infrastructure (e.g., roadside solar panels). Yes Yes beyond the travel lanes. Sidewalk (2,650 ft) and signalized pedestrian crossing at Kings Charter Dr. and numerous ADA access points added. Signal with LED lights Economic Development Factors Transportation project (consistency with Local Comprehensive Plan or Local Economic Development Strategy) Consistent With Transportation project (consistency with Regional Economic Development Strategy) Consistent With

7 Site Name Hanover County Industrial Air Park (consistent with locality Comprehensive Plan/Zoning) Consistent with comp. plan future land use/zoning (site plan status) Approved (site utilities status) (proposed (or projected) building square footage) Driving distance to development project from transportation project Does Transportation Project Provide Direct Access or Indirect Access to the Development Site? In place Provides Primary Access to the Site or is Adjacent to the Site Site Name Air Park Associates (consistent with locality Comprehensive Plan/Zoning) Consistent with comp. plan future land use/zoning (site plan status) N/A (site utilities status) (proposed (or projected) building square footage) Driving distance to development project from transportation project Does Transportation Project Provide Direct Access or Indirect Access to the Development Site? In place Provides Primary Access to the Site or is Adjacent to the Site Site Name Cedar Run (consistent with locality Comprehensive Plan/Zoning) Consistent with comp. plan future land use/zoning (site plan status) N/A (site utilities status) (proposed (or projected) building square footage) Driving distance to development project from transportation project Does Transportation Project Provide Direct Access or Indirect Access to the Development Site? In place Provides Primary Access to the Site or is Adjacent to the Site

8 Delivery/Funding Project Delivery Information Project Planning Transportation Element of Local Comprehensive Plan Planning/Safety Study Project Administered By Locality Existing Project UPCs or Project Numbers Project Delivery Method Design-bid-Build Please indicate who will be/was responsible for the design of this project VDOT: Locality: Consultant: N/A N/A 100% Phase Estimate and Schedule PE (Survey, Environmental, Design) Underway 60% Cost Estimate Start Date End Date $815,838 07/18/ /04/2017 RW (Right of Way and Easement Acquisition, Utility Relocation) t Started 0% Cost Estimate Start Date End Date $3,197,114 07/04/ /04/2019 CN (Construction, Oversight, Inspection, Contingencies) t Started 0%

9 Cost Estimate Start Date End Date $7,387,252 07/04/ /04/2021 Cost Estimate Start Date End Date Cost Estimate Start Date End Date Cost Estimate Start Date End Date Cost Estimate Start Date End Date Cost Estimate Start Date End Date Total Cost Estimate $11,400,204.00

10 Project Funding Sources SYIP Allocations Committed Funding Amount Requested Funding Amount HB2 Amount Requested Total Proposed Project Funding $1,078,146 $1,500,000 $1,500,000 $7,332,058 $11,410, Committed Funding Amount Requested Funding Amount Locality Funds VDOT Revenue Sharing Scoring Project Located in Typology Category B Congestion Mitigation Safety Accessibility Environment Economic Development Land Use Increase in Daily Person Throughput Decrease in Person Hours Delay Reduction in Fatal and Severe Injury Reduction in Fatal and Severe Injury Rate Increase in Access to Jobs Increase in Access to Jobs for Disadvantaged Populations Improved Access to Multimodal Choices (Users Benefit Value) Air Quality (Total Benefit Value) Acres of Natural/Cultural Resources Potentially Impacted Economic Development Support (Sq. ft.) Intermodal Access Improvements (Tons Benefit Value) Travel Time Reliability Improvement Transportation Efficient Land Use Measure Score

11 Measure Weight Weighted Measure Score Raw Factor Score Factor Weighting Weighted Factor Score Project Score Total Project Cost Score Divided by Total Cost 50 % 50 % 50 % 50 % 60 % 20 % 20 % 50 % 50 % 60 % 20 % 20 % 100 % % 20 % 25 % 10 % 20 % 10 % $11,410, HB2 Cost $7,332,058 Project Benefit Score / HB2 Cost 3.9 Supporting Documents Current Attachments Project Traffic Study sliding hill road corridor - draft report pdf Hanover Sliding Hill Corridor Business Properties Inventory

12 hanover sliding hill corridor buisness properties inventory august 2015.pdf Economic Development Strategic Plan final strategic plan- economic development 2009.pdf Comprehensive Plan - Econ Dev sec7 economic development pdf Cedar Run Site Plan cedar run site plan.png AirPark Associates Site Plan airpark associates concept 3-buildout layout1.pdf Crash Data (Jan. '08 - Dec. 12) sliding hill crash data jan 08-dec 10.xlsx

13 TPO Resolution of Support tpo resolution of support - sliding hill rd widening.pdf 60 Percent Plans Vol 1 of 5 sliding hill ph plans - volume 1.pdf 60 Percent Plans Vol 2 of 5 sliding hill ph plans - volume 2.pdf 60 Percent Plans Vol 3 of 5 sliding hill ph plans - volume 3.pdf 60 Percent Plans Vol 4 of 5 sliding hill ph plans - volume 4.pdf 60 Percent Plans Vol 5 of 5

14 sliding hill ph plans - volume 5.pdf Sliding Hill Construction Estimate Quantities sliding hill construction estimate quantities.pdf Sliding Hill Detailed Project Estimate sliding hill - detailed project estimate.pdf Project Sketch Map project sketch map ( ).pdf Zoning map zoning map - sliding hill rd corridor (3).pdf Richmon Regional Comprehensive Economic Development Strategy 2014 richmond reg. comp. econ. dev. strategy (pg & 83).pdf

15 Available Land Infill sliding hill rd corridor - available land-infill (1).pdf 434.Sliding_Hill_Road_Widening.01OCT2015.RN.B3 434.sliding_hill_road_widening.01oct2015.rn.b3.pdf

Rio Mills Rd/Berkmar Dr Extended Connection

Rio Mills Rd/Berkmar Dr Extended Connection SMART SCALE Application Rio Mills Rd/Berkmar Dr Extended Connection Status: Scored ID: F2-0000001408-R02 General Point of Contact Information Point of Contact Name Kevin McDermott Point of Contact Phone

More information

Route 28 Widening (PW County Line to Old. Old Centreville Road) Scored HB 2 Application

Route 28 Widening (PW County Line to Old. Old Centreville Road) Scored HB 2 Application Route 28 Widening (PW County Line to Old Centreville Road) Scored HB 2 Application Project Application ID: 432 General Project Information Project Title Route 28 Widening (PW County Line to Old Centreville

More information

New Commuter Parking Lot for Route 1 at Commonwealth Drive Scored HB 2 Application

New Commuter Parking Lot for Route 1 at Commonwealth Drive Scored HB 2 Application New Commuter Parking Lot for Route 1 at Commonwealth Drive Scored HB 2 Application Project Application ID: 591 General Project Information Project Title New Commuter Parking Lot for Route 1 at Commonwealth

More information

Viewing SMART SCALE Application

Viewing SMART SCALE Application Viewing SMART SCALE Application Route 15 Whites Ferry Road to Points of Rock Bridge Project Status: Submitted Organization: Loudoun County Project ID: 3593 Submitted: 08/06/2018 @ 3:18PM by Bob Brown Created:

More information

Project Description Form 8EE

Project Description Form 8EE Project Description Form 8EE Basic Project Information Submitting Jurisdiction/Agency: Town of Dumfries Project Title: Route 1 (Fraley Blvd) Widening: Brady's Hill Road to Dumfries Road Project Location:

More information

City of Gainesville Transportation/Roadway Needs PROJECT SUMMARY

City of Gainesville Transportation/Roadway Needs PROJECT SUMMARY A1 Roadway Resurfacing $23,846,000 TYPE: Preservation of existing system Roadway resurfacing A2 Signal Replacement $6,000,000 TYPE: Preservation of existing system Replace traffic signals. B1 W 6th St

More information

Access Management Regulations and Standards

Access Management Regulations and Standards Access Management Regulations and Standards January 2014 Efficient highway operation Reasonable property access Concept of Access Management The way to manage access to land development while preserving

More information

Project Description Form 8AA

Project Description Form 8AA Project Description Form 8AA Basic Project Information Submitting Jurisdiction/Agency: Fairfax County Project Title: Route 1 Widening: Mount Vernon Memorial Highway to Napper Road Project Location: US

More information

Highway 49, Highway 351 and Highway 91 Improvements Feasibility Study Craighead County

Highway 49, Highway 351 and Highway 91 Improvements Feasibility Study Craighead County Highway 49, Highway 351 and Highway 91 Improvements Feasibility Study Craighead County Executive Summary March 2015 Highway 49, Highway 351 and Highway 91 Improvements Feasibility Study Craighead County

More information

Route 7 Corridor Study

Route 7 Corridor Study Route 7 Corridor Study Executive Summary Study Area The following report analyzes a segment of the Virginia State Route 7 corridor. The corridor study area, spanning over 5 miles in length, is a multi

More information

APPENDIX G: INTERSECTION NEEDS AT OKEECHOBEE BOULEVARD

APPENDIX G: INTERSECTION NEEDS AT OKEECHOBEE BOULEVARD APPENDIX G: INTERSECTION NEEDS AT OKEECHOBEE BOULEVARD INTERSECTION NEEDS AT SR 7 and OKEECHOBEE BOULEVARD SR 7 Extension Project Development and Environment (PD&E) Study From Okeechobee Boulevard (SR

More information

West Dimond Blvd Upgrade Jodhpur Street to Sand Lake Road

West Dimond Blvd Upgrade Jodhpur Street to Sand Lake Road West Dimond Blvd Jodhpur St to Sand Lake CSS Transportation Project Summary Municipality of Anchorage Project # 05 005 Project Manager: John Smith, P.E. (MOA PM&E) Project Administrator: Julie Makela,

More information

MCTC 2018 RTP SCS and Madera County RIFP Multi-Modal Project Eval Criteria GV13.xlsx

MCTC 2018 RTP SCS and Madera County RIFP Multi-Modal Project Eval Criteria GV13.xlsx MCTC 8 RTP SCS and Madera County RIFP Multi-Modal Project Eval Criteria GV.xlsx Madera County Transportation Commission Regional Transportation Plan / Sustainable Communities Strategy Multi-Modal Project

More information

Proposed. City of Grand Junction Complete Streets Policy. Exhibit 10

Proposed. City of Grand Junction Complete Streets Policy. Exhibit 10 Proposed City of Grand Junction Complete Streets Policy Exhibit 10 1 City of Grand Junction Complete Streets Policy Vision: The Complete Streets Vision is to develop a safe, efficient, and reliable travel

More information

ARTINSVILLE ENRY OUNTY REA RANSPORTATION TUDY

ARTINSVILLE ENRY OUNTY REA RANSPORTATION TUDY ARTINSVILLE ENRY OUNTY REA RANSPORTATION TUDY DEVELOPED BY THE TRANSPORTATION AND MOBILITY PLANNING DIVISION OF THE VIRGINIA DEPARTMENT OF TRANSPORTATION IN COOPERATION WITH THE U.S. DEPARTMENT OF TRANSPORTATION,

More information

WELCOME TO OPEN HOUSE # 1 June 14, 2017

WELCOME TO OPEN HOUSE # 1 June 14, 2017 Langstaff Road Weston Road to Highway 7 Class Environmental Assessment Study WELCOME TO OPEN HOUSE # 1 June 14, 2017 Please sign in and join our mailing list Purpose of Open House #1 & Study Area York

More information

Project Description Form 6V

Project Description Form 6V Project Description Form 6V Basic Project Information Submitting Jurisdiction/Agency: Prince William County Project Title: Route 15 Widening: Route 55 to south of RR tracks & Construct RR Overpass Project

More information

TRASBURG RANSPORTATION

TRASBURG RANSPORTATION TRASBURG RANSPORTATION LAN DEVELOPED BY THE TRANSPORTATION PLANNING DIVISION OF THE VIRGINIA DEPARTMENT OF TRANSPORTATION IN COOPERATION WITH THE U.S. DEPARTMENT OF TRANSPORTATION, FEDERAL HIGHWAY ADMINISTRATION

More information

Regional Transportation Needs Within Southeastern Wisconsin

Regional Transportation Needs Within Southeastern Wisconsin Regional Transportation Needs Within Southeastern Wisconsin #118274 May 24, 2006 1 Introduction The Southeastern Wisconsin Regional Planning Commission (SEWRPC) is the official areawide planning agency

More information

Performance Criteria for 2035 Long Range Transportation Plan

Performance Criteria for 2035 Long Range Transportation Plan Minimizing Impacts on Natural, Historic, Cultural or Archeological Resources 2035 LRTP Weighting Factor: 7% Objective 1.1: Use appropriate planning and design criteria to protect and enhance the built

More information

Basalt Creek Transportation Refinement Plan Recommendations

Basalt Creek Transportation Refinement Plan Recommendations Basalt Creek Transportation Refinement Plan Recommendations Introduction The Basalt Creek transportation planning effort analyzed future transportation conditions and evaluated alternative strategies for

More information

Houma-Thibodaux Metropolitan Planning Organization STP<200K Funding Application APPLICATION

Houma-Thibodaux Metropolitan Planning Organization STP<200K Funding Application APPLICATION APPLICATION HOUMA-THIBODAUX METROPOLITAN PLANNING ORGANIZATION (HTMPO) FOR SURFACE TRANSPORTATION PROGRAM (STP

More information

Route 29 Solutions Projects

Route 29 Solutions Projects Route 29 Solutions Route 29 Solutions Projects www.route29solutions.org October 10, 2014 Route 29 Widening to Six Lanes Albemarle County This project will widen a 1.8-mile segment of Route 29 from four

More information

ACTIVE TRANSPORTATION

ACTIVE TRANSPORTATION ACTIVE TRANSPORTATION Mobility 2040 Supported Goals Improve the availability of transportation options for people and goods. Support travel efficiency measures and system enhancements targeted at congestion

More information

BETHEL ROAD AND SEDGWICK ROAD CORRIDOR STUDY

BETHEL ROAD AND SEDGWICK ROAD CORRIDOR STUDY DRAFT PLAN City Council Meeting August 14, 2017 STUDY AREA Sedgwick Corridor State Route 160, principal arterial with Class 3 access management designation, commuter and freight route, connection to SR

More information

JONESBORO HIGHWAY 63 HIGHWAY 18 CONNECTOR STUDY

JONESBORO HIGHWAY 63 HIGHWAY 18 CONNECTOR STUDY JONESBORO HIGHWAY 63 HIGHWAY 18 CONNECTOR STUDY Craighead County May 2007 JONESBORO HIGHWAY 63 HIGHWAY 18 CONNECTOR STUDY Craighead County May 2007 Prepared by Planning and Research Division Arkansas State

More information

INNER LOOP EAST. AIA Rochester Annual Meeting November 13, 2013 TRANSFORMATION PROJECT. Bret Garwood, NBD Erik Frisch, DES

INNER LOOP EAST. AIA Rochester Annual Meeting November 13, 2013 TRANSFORMATION PROJECT. Bret Garwood, NBD Erik Frisch, DES INNER LOOP EAST TRANSFORMATION PROJECT AIA Rochester Annual Meeting November 13, 2013 Bret Garwood, NBD Erik Frisch, DES Why? We are building a city that encourages walking, biking and enjoying the outdoor

More information

Corpus Christi Metropolitan Transportation Plan Fiscal Year Introduction:

Corpus Christi Metropolitan Transportation Plan Fiscal Year Introduction: Introduction: The Safe, Accountable, Flexible, Efficient Transportation Equity Act: A Legacy for Users (SAFETEA-LU) has continued the efforts started through the Intermodal Surface Transportation Efficiency

More information

Solana Beach Comprehensive Active Transportation Strategy (CATS)

Solana Beach Comprehensive Active Transportation Strategy (CATS) Solana Beach Comprehensive Active Transportation Strategy (CATS) 3.0 Goals & Policies The Solana Beach CATS goals and objectives outlined below were largely drawn from the Solana Beach Circulation Element

More information

Sixth Line Development - Transit Facilities Plan

Sixth Line Development - Transit Facilities Plan Memorandum Date: November 13, 2012 To: From: c.c. Subject: Rob Freeman (Freeman Planning) Kevin Phillips Sixth Line Development - Transit Facilities Plan 33016631 This memo was prepared to review the transit

More information

Feasibility Study of Pedestrian Crossings Along Route 7, East of Cascades Parkway and West of Dranesville Road. October 3, 2017

Feasibility Study of Pedestrian Crossings Along Route 7, East of Cascades Parkway and West of Dranesville Road. October 3, 2017 Feasibility Study of Pedestrian Crossings Along Route 7, East of Cascades Parkway and West of Dranesville Road October 3, 2017 Study Area (area within a ¼-mile radius of the study intersections) Route

More information

Attached for your reference please find project updates on ongoing VDOT construction projects in Southampton County.

Attached for your reference please find project updates on ongoing VDOT construction projects in Southampton County. SOUTHAMPTON COUNTY BOARD OF SUPERVISORS Regular Session i July 25, 2016 6. HIGHWAY MATTERS A. PLAN PROJECT UPDATES Attached for your reference please find project updates on ongoing VDOT construction projects

More information

Road Diets FDOT Process

Road Diets FDOT Process Florida Department of TRANSPORTATION Road Diets FDOT Process Humberto Castillero, PE, PTOE Roadway Design Office Purpose of Guide Develop a statewide lane elimination review process Balance state & local

More information

APPENDIX A: Complete Streets Checklist DRAFT NOVEMBER 2016

APPENDIX A: Complete Streets Checklist DRAFT NOVEMBER 2016 APPENDIX A: Complete Streets Checklist DRAFT NOVEMBER 2016 Complete Streets Checklist MetroPlan Orlando s Complete Streets Checklist is an internal planning tool for staff to further implementation of

More information

Overview. Illinois Bike Summit IDOT Complete Streets Policy Presentation. What is a Complete Street? And why build them? And why build them?

Overview. Illinois Bike Summit IDOT Complete Streets Policy Presentation. What is a Complete Street? And why build them? And why build them? Overview Illinois Bike Summit IDOT Complete Streets Policy Presentation Aren Kriks, P.E. District One Bicycle Coordinator and Bureau of Programming Project Engineer History of Complete Streets IDOT Policy

More information

5. RUNNINGWAY GUIDELINES

5. RUNNINGWAY GUIDELINES 5. RUNNINGWAY GUIDELINES These guidelines should be considered collectively when making runningway decisions. A runningway is the linear component of the transit system that forms the right-of-way reserved

More information

Chapter 5 Future Transportation

Chapter 5 Future Transportation Chapter 5 Future Transportation The Future Land Use Plan identifies the desired land use designations. The land uses desired for Crozet depend, in large part, on the success of the transportation system,

More information

C C C

C C C C-012-001 Thank you for your support for the creation of new public space and nonmotorized access between downtown and the waterfront through the Overlook Walk, the East-West Connections, and the Promenade.

More information

CHAPTER 5 TRANSPORTATION GOAL

CHAPTER 5 TRANSPORTATION GOAL CHAPTER 5 TRANSPORTATION GOAL Create and sustain a transportation system that meets the demands for existing and future traffic; skillfully integrates existing and planned development; and provides a safe

More information

M-58 HIGHWAY ACCESS MANAGEMENT STUDY Mullen Road to Bel-Ray Boulevard. Prepared for CITY OF BELTON. May 2016

M-58 HIGHWAY ACCESS MANAGEMENT STUDY Mullen Road to Bel-Ray Boulevard. Prepared for CITY OF BELTON. May 2016 M-58 HIGHWAY ACCESS MANAGEMENT STUDY Prepared for CITY OF BELTON By May 2016 Introduction Missouri State Highway 58 (M-58 Highway) is a major commercial corridor in the City of Belton. As development has

More information

DRAFT BUENA VISTA 2020 TRANSPORTATION PLAN

DRAFT BUENA VISTA 2020 TRANSPORTATION PLAN DRAFT BUENA VISTA 2020 TRANSPORTATION PLAN DEVELOPED BY THE TRANSPORTATION PLANNING DIVISION OF THE VIRGINIA DEPARTMENT OF TRANSPORTATION IN COOPERATION WITH THE U.S. DEPARTMENT OF TRANSPORTATION, FEDERAL

More information

TRAFFIC IMPACT ANALYSIS

TRAFFIC IMPACT ANALYSIS TRAFFIC IMPACT ANALYSIS FOR THE CHAMPAIGN UNIT#4 SCHOOL DISTRICT PROPOSED HIGH SCHOOL (SPALDING PARK SITE) IN THE CITY OF CHAMPAIGN Final Report Champaign Urbana Urbanized Area Transportation Study 6/24/2014

More information

Roadway Classification Design Standards and Policies. Pueblo, Colorado November, 2004

Roadway Classification Design Standards and Policies. Pueblo, Colorado November, 2004 Roadway Classification Design Standards and Policies Pueblo, Colorado November, 2004 Table of Contents Page Chapter 1. General Provisions 1.1 Jurisdiction 3 1.2 Purpose and Intent 3 1.3 Modification 3

More information

Chapter 4: Funding and Implementation

Chapter 4: Funding and Implementation Chapter 4: Funding and Implementation 83 84 Cost Estimating Cost estimating is an iterative process. When a project is in the conceptual stage, preliminary cost estimates are also provided conceptually,

More information

Access Management Regulations and Standards

Access Management Regulations and Standards Access Management Regulations and Standards Efficient highway operation Reasonable property access Concept of Access Management The way to manage access to land development while simultaneously preserving

More information

City of Wayzata Comprehensive Plan 2030 Transportation Chapter: Appendix A

City of Wayzata Comprehensive Plan 2030 Transportation Chapter: Appendix A A1. Functional Classification Table A-1 illustrates the Metropolitan Council s detailed criteria established for the functional classification of roadways within the Twin Cities Metropolitan Area. Table

More information

2018 Pedestrian and Bicycle and Safe Routes to School Application for Funding Page 1 of 31

2018 Pedestrian and Bicycle and Safe Routes to School Application for Funding Page 1 of 31 2018 Pedestrian and Bicycle and Safe Routes to School Application for Funding Page 1 of 31 2018 Pedestrian and Bicycle and Safe Routes to School Application for Funding Part 1: General Information Funding

More information

Welcome! San Jose Avenue Open House August 25, 2015

Welcome! San Jose Avenue Open House August 25, 2015 Welcome! San Jose Avenue Open House August 25, 2015 Vision Zero The City and County of San Francisco adopted Vision Zero San Francisco Vision Zero High Injury Network as a policy in 2014, committing an

More information

City of Fairfax, Virginia City Council Work Session

City of Fairfax, Virginia City Council Work Session City of Fairfax, Virginia City Council Work Session Agenda Item # City Council Meeting 12a 9/8/2015 TO: FROM: SUBJECT: ISSUE(S): SUMMARY: FISCAL IMPACT: RECOMMENDATION: ALTERNATIVE COURSE OF ACTION: RESPONSIBLE

More information

NJDOT Complete Streets Checklist

NJDOT Complete Streets Checklist Background The New Jersey Department of Transportation s Complete Streets Policy promotes a comprehensive, integrated, connected multi-modal network by providing connections to bicycling and walking trip

More information

Poor pavement condition Substandard Intersections. / Substandard bike/pedestrian/transit accommodations. Driveway access Environmental concerns

Poor pavement condition Substandard Intersections. / Substandard bike/pedestrian/transit accommodations. Driveway access Environmental concerns Public Informational Meeting University Avenue (Allen Boulevard Segoe Road) March 23, 2011 City of Madison City of Middleton Village of Shorewood Hills Dane County Existing Roadway Conditions Poor pavement

More information

MOBILITY RESULTS AREA. Budgeting For Outcomes Council Presentation January 12, 2007

MOBILITY RESULTS AREA. Budgeting For Outcomes Council Presentation January 12, 2007 MOBILITY RESULTS AREA Budgeting For Outcomes Council Presentation January 12, 2007 Mobility Results Team Members 2 Hammond Perot, OED, Co-Team Leader Bonnie Meeder, DEV (returning), Co-Team Leader Peer

More information

Multimodal Through Corridors and Placemaking Corridors

Multimodal Through Corridors and Placemaking Corridors 68 Multimodal Through Corridors and Placemaking Corridors Corridors have different functions in a region. Some corridors are used to get smoothly and rapidly through a region or to get quickly to major

More information

Arterial Management Plan for US Route 250 and State Route 623

Arterial Management Plan for US Route 250 and State Route 623 Arterial Management Plan for US Route 250 and State Route 623 June 25, 2014 Brad Shelton, AICP Access Management and Traffic Impact Analysis Programs Manager Transportation and Mobility Planning Division

More information

Exhibit 1 PLANNING COMMISSION AGENDA ITEM

Exhibit 1 PLANNING COMMISSION AGENDA ITEM Exhibit 1 PLANNING COMMISSION AGENDA ITEM Project Name: Grand Junction Circulation Plan Grand Junction Complete Streets Policy Applicant: City of Grand Junction Representative: David Thornton Address:

More information

Clackamas County Comprehensive Plan

Clackamas County Comprehensive Plan ROADWAYS The County s road system permits the movement of goods and people between communities and regions, using any of a variety of modes of travel. Roads provide access to virtually all property. They

More information

Final Sidewalk Feasibility Study

Final Sidewalk Feasibility Study Garfield Drive From Anastasia Drive to Elizabeth Place City of South Daytona July 23, 2009 Final Sidewalk Feasibility Study Prepared for: Prepared by: Final Sidewalk Feasibility Study Garfield Drive 2

More information

Public Information Meeting

Public Information Meeting Richmond Highway (U.S. Route 1) Corridor Improvements Public Information Meeting Tuesday, April 18, 2017 Mount Vernon High School 8515 Old Mt. Vernon Road, Alexandria, VA 22309 Amanda Baxter, VDOT, Special

More information

FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT 7 DISTRICT WIDE BICYCLE/PEDESTRIAN ACCESS TO TRANSIT SAFETY ASSESSMENT AND IMPROVEMENT PLAN

FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT 7 DISTRICT WIDE BICYCLE/PEDESTRIAN ACCESS TO TRANSIT SAFETY ASSESSMENT AND IMPROVEMENT PLAN FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT 7 DISTRICT WIDE BICYCLE/PEDESTRIAN ACCESS TO TRANSIT SAFETY ASSESSMENT AND IMPROVEMENT PLAN TRANSIT SAFETY ASSESSMENT SR 55/US 19 AT 80 TH AVE N DRAFT JUNE

More information

Active Transportation Facility Glossary

Active Transportation Facility Glossary Active Transportation Facility Glossary This document defines different active transportation facilities and suggests appropriate corridor types. Click on a facility type to jump to its definition. Bike

More information

New Measure A Expenditure Categories DEFINITIONS OF ELIGIBLE EXPENDITURES Adopted March 8, 2007

New Measure A Expenditure Categories DEFINITIONS OF ELIGIBLE EXPENDITURES Adopted March 8, 2007 New Measure A Expenditure Categories DEFINITIONS OF ELIGIBLE EXPENDITURES Adopted March 8, 2007 City Street and County Road Maintenance Program The preservation and keeping of public street and road rights-of-way

More information

Public Information Meeting. Orange Camp Road. Dr. Martin Luther King Jr. Beltway to I-4. Presented by: Volusia County August 2, 2018

Public Information Meeting. Orange Camp Road. Dr. Martin Luther King Jr. Beltway to I-4. Presented by: Volusia County August 2, 2018 Public Information Meeting Orange Camp Road Dr. Martin Luther King Jr. Beltway to I-4 Presented by: Volusia County August 2, 2018 1 Project Goals To improve the operations and safety for Orange Camp Road

More information

4. ENVIRONMENTAL IMPACT ANALYSIS 9. TRANSPORTATION AND TRAFFIC

4. ENVIRONMENTAL IMPACT ANALYSIS 9. TRANSPORTATION AND TRAFFIC 4. ENVIRONMENTAL IMPACT ANALYSIS 9. TRANSPORTATION AND TRAFFIC 4.9.1 INTRODUCTION The following section addresses the Proposed Project s impact on transportation and traffic based on the Traffic Study

More information

CITY OF SASKATOON COUNCIL POLICY

CITY OF SASKATOON COUNCIL POLICY ORIGIN/AUTHORITY Clause 1, Report No. 1-1980 and Clause 4, Report No. 22-1990 of the Works and Utilities Committee; Clause 6, Report No. 17-2004 of the Planning and Operations Committee; and Clause D5,

More information

3.0 Future Conditions

3.0 Future Conditions 3.0 Future Conditions In order to be able to recommend appropriate improvements to the transportation system of the Town, it is important to first understand the nature and volume of traffic that is expected

More information

Los Altos Hills Town Council - June 18, 2015 Palo Alto City Council June 22, AGENDA ITEM #2.B Presentation

Los Altos Hills Town Council - June 18, 2015 Palo Alto City Council June 22, AGENDA ITEM #2.B Presentation Los Altos Hills Town Council - June 18, 2015 Palo Alto City Council June 22, 2015 AGENDA ITEM #2.B Presentation Previous Presentations Los Altos Hills Town Council in May 2014 and February 2015 Palo Alto

More information

A. LETTERS OF SUPPORT ON THE WYTHE CREEK ROAD WIDENING PROJECT

A. LETTERS OF SUPPORT ON THE WYTHE CREEK ROAD WIDENING PROJECT ITEM #19: CORRESPONDENCE OF INTEREST A. LETTERS OF SUPPORT ON THE WYTHE CREEK ROAD WIDENING PROJECT Attached are five letters to Mayor Hunt of Poquoson in support of the Wythe Creek Road widening project.

More information

Eastern PA Trail Summit October 1, 2018

Eastern PA Trail Summit October 1, 2018 Eastern PA Trail Summit October 1, 2018 WHO WE ARE + WHY + WE RE * HERE * * * * * * Session Goals: Discuss how to coordinate planning and design in small, urbanized towns Consider how to develop alternative

More information

INDOT Complete Streets Guideline & Policy

INDOT Complete Streets Guideline & Policy INDOT Complete Streets Guideline & Policy INTRODUCTION The Complete Streets guidelines build upon multiple efforts and promote a multimodal transportation system that is integrated and sustains land use

More information

Long Island Rail Road Expansion Project Floral Park to Hicksville

Long Island Rail Road Expansion Project Floral Park to Hicksville Long Island Rail Road Expansion Project Floral Park to Hicksville Final Environmental Impact Statement Appendix 1-D Complete Streets Policy Checklist April 2017 0902ML PIN: Project Location: 18A-4 Floral

More information

Bike/Multipurpose Trail Study for Glynn County, Georgia MAY 16, 2016

Bike/Multipurpose Trail Study for Glynn County, Georgia MAY 16, 2016 Bike/Multipurpose Trail Study for Glynn County, Georgia MAY 16, 2016 Agenda» Project Status Update» Draft Recommendations Overview» Next Steps» Questions/Discussion Project Overview» Comprehensive Bikeway

More information

State Street and Pierce Park Lane Intersection Concept Report

State Street and Pierce Park Lane Intersection Concept Report State Street and Pierce Park Lane Intersection Prepared for September 2017 Prepared by CITATION Parametrix. 2017. State Street & Pierce Park Lane Intersection. Prepared by Parametrix, Boise, ID. September

More information

Executive Summary June 2015

Executive Summary June 2015 Executive Summary June 2015 Highway 112 Corridor Study Benton and Washington Counties Executive Summary June 2015 Prepared by Transportation Planning and Policy Division Arkansas State Highway and Transportation

More information

ARRENTON RANSPORTATION

ARRENTON RANSPORTATION ARRENTON RANSPORTATION LAN DEVELOPED BY THE TRANSPORTATION PLANNING DIVISION OF THE VIRGINIA DEPARTMENT OF TRANSPORTATION IN COOPERATION WITH THE U.S. DEPARTMENT OF TRANSPORTATION, FEDERAL HIGHWAY ADMINISTRATION

More information

Transform 66 Project February 4, 2016 Partnering Conference Michigan Department of Transportation American Council of Engineering Companies

Transform 66 Project February 4, 2016 Partnering Conference Michigan Department of Transportation American Council of Engineering Companies Transform 66 Project February 4, 2016 Partnering Conference Michigan Department of Transportation American Council of Engineering Companies Susan Shaw, PE, CCM, DBIA Megaprojects Director Northern Virginia

More information

Roundabouts are good for business

Roundabouts are good for business Roundabouts are good for business What is a roundabout Rules 0f Roundabouts 1. Slow down when approaching a roundabout 2. Yield to vehicles in the roundabout 3. When clear, proceed right into the roundabout

More information

ADOT Statewide Bicycle and Pedestrian Program Summary of Phase IV Activities APPENDIX B PEDESTRIAN DEMAND INDEX

ADOT Statewide Bicycle and Pedestrian Program Summary of Phase IV Activities APPENDIX B PEDESTRIAN DEMAND INDEX ADOT Statewide Bicycle and Pedestrian Program Summary of Activities APPENDIX B PEDESTRIAN DEMAND INDEX May 24, 2009 Pedestrian Demand Index for State Highway Facilities Revised: May 29, 2007 Introduction

More information

State Road 54/56 Tampa Bay s Northern Loop. The Managed Lane Solution Linking I-75 to the Suncoast Parkway

State Road 54/56 Tampa Bay s Northern Loop. The Managed Lane Solution Linking I-75 to the Suncoast Parkway State Road 54/56 Tampa Bay s Northern Loop The Managed Lane Solution Linking I-75 to the Suncoast Parkway SUNCOAST PARKWAY Both I 75 and the Suncoast Parkway are planning, or in the process of constructing,

More information

WELCOME! To the Centennial Neighbourhoods Secondary Plan and Transportation Management Plan Information Centre. City of Hamilton

WELCOME! To the Centennial Neighbourhoods Secondary Plan and Transportation Management Plan Information Centre. City of Hamilton WELCOME! To the Centennial Neighbourhoods Secondary Plan and Transportation Management Plan Information Centre City of Hamilton Public Information Centre #2 Dec 1, 2015 CENTENNIAL NEIGHBOURHOODS SECONDARY

More information

Providence Downtown Transit Connector STAKEHOLDER MEETING #2. Stakeholder Meeting #1 October 24, 2016

Providence Downtown Transit Connector STAKEHOLDER MEETING #2. Stakeholder Meeting #1 October 24, 2016 Providence Downtown Transit Connector STAKEHOLDER MEETING #2 Stakeholder Meeting #1 October 24, 2016 February 2017 1 AGENDA 1 DTC Goals and Expectations 2 Street Design Concepts 3 Potential Benefits and

More information

Bus Rapid Transit Plans

Bus Rapid Transit Plans Twin Cities Region Bus Rapid Transit Plans ULI Minnesota Workshop Connecting Bus Rapid Transit to the Community December 15, 2009 John Levin Director of Service Development Metro Transit Metropolitan Area

More information

Traffic Impact Memorandum. May 22, 2018

Traffic Impact Memorandum. May 22, 2018 BISHOP PROFESSIONAL DEVELOPMENT BUILDING Proposed Land-use Change & Parking Modification 3601 SW 31st Street Topeka, Kansas 66614 CFS Project No. 185077 Traffic Impact Memorandum May 22, 2018 Prepared

More information

GRTC Bus Rapid Transit: Semi-Final Design Phase Public Meetings: October 26 & 27, 2015

GRTC Bus Rapid Transit: Semi-Final Design Phase Public Meetings: October 26 & 27, 2015 GRTC Bus Rapid Transit: Semi-Final Design Phase Public Meetings: October 26 & 27, 2015 Welcome! Meeting Agenda Project update presentation Up to 15 minutes for Pulse Q&A about project design. (Please reserve

More information

FY Transportation Capital Improvement Plan Update Arlington Committee for Transportation Choices

FY Transportation Capital Improvement Plan Update Arlington Committee for Transportation Choices FY 2017-2026 Transportation Capital Improvement Plan Update Arlington Committee for Transportation Choices November 1, 2017 Forecasted Growth Arlington continues to grow with a shift towards multi-family

More information

Gwinnett County Department of Transportation SR 324 / Gravel Springs Road at I-85 / SR 403 Interchange Project Number F , PI No.

Gwinnett County Department of Transportation SR 324 / Gravel Springs Road at I-85 / SR 403 Interchange Project Number F , PI No. June 4, 2015 Dear Resident: Thank you for attending this public information meeting for the proposed SR 324 / Gravel Springs Road at I-85 Interchange. The purpose of this meeting is two-fold: to provide

More information

Attachment A: Columbus Area Metropolitan Transportation Plan Objectives, Performance Measures, and Targets

Attachment A: Columbus Area Metropolitan Transportation Plan Objectives, Performance Measures, and Targets OBJECTIVE: Reduce the percentage of commuters driving alone, and increase the percentage of commuters riding transit, ing Reducing single occupancy auto commutes and increasing commuters using alternative

More information

CITY OF COCOA BEACH 2025 COMPREHENSIVE PLAN. Section VIII Mobility Element Goals, Objectives, and Policies

CITY OF COCOA BEACH 2025 COMPREHENSIVE PLAN. Section VIII Mobility Element Goals, Objectives, and Policies CITY OF COCOA BEACH 2025 COMPREHENSIVE PLAN Section VIII Mobility Element Goals, Objectives, and Policies Adopted August 6, 2015 by Ordinance No. 1591 VIII MOBILITY ELEMENT Table of Contents Page Number

More information

Executive Summary Route 30 Corridor Master Plan

Executive Summary Route 30 Corridor Master Plan Route Corridor Master Plan Project Overview The Route Corridor Master Plan is a coordinated multimodal transportation and land use plan for the entire stretch of Route through East Whiteland Township,

More information

Circulation in Elk Grove includes: Motor vehicles, including cars and trucks

Circulation in Elk Grove includes: Motor vehicles, including cars and trucks Circulation, as it is used in this General Plan, refers to the many ways people and goods move from place to place in Elk Grove and the region. Circulation in Elk Grove includes: Motor vehicles, including

More information

Anne Arundel County BICYCLE, PEDESTRIAN, TRANSIT ASSESSMENT GUIDELINES

Anne Arundel County BICYCLE, PEDESTRIAN, TRANSIT ASSESSMENT GUIDELINES Anne Arundel County BICYCLE, PEDESTRIAN, TRANSIT ASSESSMENT GUIDELINES December 2018 TABLE OF CONTENTS I. Executive Summary 3 II. When Is A Bicycle Pedestrian Transit Assessment (BPTA) Required? 4 III.

More information

VDOT I-66 Inside the Beltway Eastbound Widening Environmental Assessment. Staff Recommendations

VDOT I-66 Inside the Beltway Eastbound Widening Environmental Assessment. Staff Recommendations VDOT I-66 Inside the Beltway Eastbound Widening Environmental Assessment Staff Recommendations Department of Environmental Services Transportation January 28, 2017 Timeline of Transform66 June 2012: I-66

More information

In station areas, new pedestrian links can increase network connectivity and provide direct access to stations.

In station areas, new pedestrian links can increase network connectivity and provide direct access to stations. The Last Mile Planning for Pedestrians Planning around stations will put pedestrians first. Making walking to stations safe and easy is important; walking will be a part of every rapid transit Accessible

More information

Truck Climbing Lane Traffic Justification Report

Truck Climbing Lane Traffic Justification Report ROUTE 7 (HARRY BYRD HIGHWAY) WESTBOUND FROM WEST MARKET STREET TO ROUTE 9 (CHARLES TOWN PIKE) Truck Climbing Lane Traffic Justification Report Project No. 6007-053-133, P 101 Ι UPC No. 58599 Prepared by:

More information

El Camino Real Specific Plan. TAC/CAC Meeting #2 Aug 1, 2018

El Camino Real Specific Plan. TAC/CAC Meeting #2 Aug 1, 2018 El Camino Real Specific Plan TAC/CAC Meeting #2 Aug 1, 2018 Land Use Alternatives Goals and Tradeoffs Parks & open space Housing Retail & services Civic spaces Parking Community gathering spaces 3 Alternatives

More information

Chapter 2: Standards for Access, Non-Motorized, and Transit

Chapter 2: Standards for Access, Non-Motorized, and Transit Standards for Access, Non-Motorized, and Transit Chapter 2: Standards for Access, Non-Motorized, and Transit The Washtenaw County Access Management Plan was developed based on the analysis of existing

More information

PEDESTRIAN ACTION PLAN

PEDESTRIAN ACTION PLAN ATTACHMENT 2 CITY OF SANTA MONICA PEDESTRIAN ACTION PLAN CITY OF SANTA MONICA PEDESTRIAN ACTION PLAN This page intentionally left blank EXECUTIVE SUMMARY CHAPTER 1 EXECUTIVE SUMMARY Setting the Stage

More information

Base Information. 1. Project Title Erie Parkway and WCR 7 Traffic Signal Project

Base Information. 1. Project Title Erie Parkway and WCR 7 Traffic Signal Project Part 1 Base Information 1. Project Title Erie Parkway and WCR 7 Traffic Signal Project 2. Project Start/End points or Geographic Area Provide a map with submittal, as appropriate 3. Project Sponsor (entity

More information

LANE ELIMINATION PROJECTS

LANE ELIMINATION PROJECTS PRESENTATION OUTLINE Lane Elimination Considerations Districts 4 & 7 Draft Lane Elimination Processes FDOT Lane Elimination Guidelines Example Projects D4 Case Study: SR A1A (Ft. Lauderdale) D7 Case Study:

More information

Bicycle and Pedestrian Connectivity Study Phase 2

Bicycle and Pedestrian Connectivity Study Phase 2 Connectivity Study Phase 2 Process PROCESS OUTCOMES Phase Prepared By STEP I Public Participation and Outreach 1. RTP Outreach activities, and development of the Bike and Ped Task Force Phase 1 2011 OCPC