Water surface slope extending up to 20 channel widths up and downstream of crossing.

Size: px
Start display at page:

Download "Water surface slope extending up to 20 channel widths up and downstream of crossing."

Transcription

1 Site Evaluations Site Information Site Location: Mt ood NF, Forest Road 7 Year Installed: Pre-987 Lat/Long: 8 W Watershed rea (mi ): N Stream Slope (ft/ft) : Channel Type: Step-pool ankfull Width (ft): Survey Date: pril, 7 Water surface slope extending up to channel widths up and downstream of crossing Culvert Information Culvert Type: Open-bottom arch Culvert Material: nnular CMP Culvert Width: 9 ft Outlet Type: ybrid projecting/mitered Culvert Length: 7 ft Inlet Type: ybrid projecting/mitered Pipe Slope (structure slope): Culvert ed Slope: (First hydraulic control upstream of inlet to first hydraulic control downstream of outlet) Culvert width as a percentage of bankfull width: 8 lignment Conditions: ppears inline with natural channel ed Conditions: Scoured at upstream end of pipe Large cobbles to large boulders are creating steps in culvert Pipe Condition: Left footing severely undermined at upstream end May be some piping around sides of pipe where erosion has occurred ydrology Discharge (cfs) for indicated recurrence interval % -yr Q bf -year -year -year -year -year ankfull flow estimated by matching modeled water surface elevations to field-identified bankfull elevations 7

2 Culvert Scour ssessment Points represent survey points Figure Plan view map 8

3 Site Evaluations istory The exact installation date is unknown, but the culvert was included in the 987 Western Federal Lands ighway Division (WFLD) Oregon Culvert Fish Passage Survey The field survey for the WFLD study was conducted on November 7, 987 The study describes the culvert as an open bottom arch with boulders placed inside the barrel With respect to fish passage, Oregon Department of Fish and Wildlife (ODFW) staff described the culvert as an excellent open bottom arch installation; whereas WFLD staff noted that the culvert was in fair condition, the foundation was in poor condition, and there was moderate outlet scour The culvert hydraulics were considered compatible with the natural stream hydraulics They go on to note that open-bottom arches with shallow foundations are susceptible to scour and recommend that if foundation requirements cannot be met (ie, embedment depth), then closed-bottom pipes should be installed The following are photos from the WFLD study: Culvert inlet Typical stream channel Site Description The culvert is an open-bottom arch that projects from the roadfill The culvert is characterized by a deep scour pool at the inlet, primarily concentrated along the left side of the culvert where significant footing scour and undermining has occurred Downstream of the scour pool, the bed is aggraded and levels off forming a consistent riffle The channel is against the left side of the culvert for most of its length There has been deposition of material along the right footing at the inlet There is a large (greater than -foot diameter) log just upstream and inside of the culvert There is significant erosion at the sides of the culvert at the inlet and outlet The upstream representative reach consists of a moderate gradient step-pool channel The upstream segment sits in a fairly confined and narrow valley Channel banks are steep with high adjacent terraces that may only be active at infrequent floods Large boulders and fallen trees line both banks The reach consists of a series of steps and pools The downstream representative reach consists of a series of steep riffles interspersed with pools relatively extensive low (active) flood plain exists through this reach ed material was finer and there were small log jams 9

4 Culvert Scour ssessment Survey Summary Fourteen cross sections and a longitudinal profile were surveyed at the crossing in pril 7 to characterize the culvert, an upstream representative reach, and a downstream representative reach Representative cross sections in the culvert were taken through the downstream end of the pool and the riffle One additional cross section was surveyed upstream to characterize the inlet as well as the contraction of flow nother two cross sections were surveyed downstream of the culvert to characterize the outlet and the expansion of flow Four cross sections were surveyed to characterize the upstream representative reach; one at the upstream boundary, one at the downstream boundary, one through a step, and one through a pool Four cross sections were also surveyed to characterize the downstream representative reach; one at the upstream boundary, one at the downstream boundary, one through a pool, and one through a riffle Profile nalysis Segment Summary The profile analysis resulted in a total of eight profile segments The two consecutive segments downstream of the outlet, though similar in gradient, were not combined in order to separate out the transition area from the downstream representative channel The culvert consisted of two profile segments, the upstream one extending into the upstream transition area The upstream culvert segment was compared to two representative profile segments, one in the upstream channel and one in the downstream channel There was no suitable comparison for the downstream segment in the culvert The upstream transition segment was compared to a representative profile segment in the downstream channel The downstream transition segment was compared to two representative profile segments, one in the upstream channel and one in the downstream channel See figure and table Scour Conditions Observed conditions Footing scour The greatest amount of footing scour is at the upstream end on the left bank where the footing is undermined The base of the footing is suspended above the bed feet at the maximum depth of the scour pool The lateral extent of scour under the footing reaches feet at one location Some of this scour may be the result of a large log (greater than -foot diameter) located at the inlet pproximately percent of the footing on the left bank is undermined and all of it is exposed There is also scour around the sides of the pipe at the inlet and outlet and there may be some piping of flow around the culvert in these areas The poor foundation rating from the WFLD study and the suggestion regarding foundation requirements suggest that some foundation undermining may have been present in 987, but likely less than in 7 or there would have been more mention of it Culvert-bed adjustment The culvert bed has reduced its slope since installation (assuming the culvert bed was constructed at the same gradient as the structure) This flattening appears to be mostly due to scour in the upstream portion of the pipe There is still streambed material throughout the pipe and no bedrock is present on the bed Profile characteristics The profile has a concave shape through the crossing (figure ) This shape reflects scour at the inlet region There is a natural valley transition in this area Upstream is more confined with higher and less active floodplain terraces than the downstream reach Residual depths The single culvert residual depth is within the range of residual depths in corresponding profile segments in the natural channel ( and ) (figure ) The single residual depth in the downstream transition is also within the range of corresponding profile segments in the natural channel ( and ) There was no residual depth in the corresponding profile segment for the upstream transition

5 Site Evaluations Substrate ed-material distributions are similar between the culvert and channel sample sites The culvert has more coarse material than the downstream channel but similar abundance of coarse material as the upstream channel The downstream channel has the greatest abundance of fine material Sorting and skewness values in the culvert are within the range of those in the natural channel (table 7) Predicted conditions *Note: s estimated in the model, backwater from the culvert affects portions of the upstream reach (figure ) The backwater affects the upstream representative reach for the Q and Q For this reason, hydraulic metrics for these flows are not used in the comparisons with culvert values Cross-section characteristics The culvert appears to affect most of the cross-section metrics at the Q bf and above (figures through 9 and through 9) There is a dramatic reduction in top width and an increase in depth as flows rise The culvert exhibits characteristics of outlet control, with culvert characteristics (ie, barrel roughness, slope, and area) creating deep subcritical flow throughout most of the barrel length The flow passes through critical depth near the downstream end Cross-section characteristics at the upstream transition (F) are impacted by the culvert backwater at higher flows (Q and Q ) t lower flows, the flow has lower width and greater depth than the corresponding profile segments (), but this may be due partially to changes in valley confinement Cross-section characteristics in the downstream transition (C) are mostly within the range of corresponding profile segments ( and ) Shear stress The modeling suggests that shear stress is low in the culvert due to backwater conditions that reduce the energy grade Shear stress near the downstream end of the culvert is high where the flow passes through critical depth (figure ) Shear stress in the upstream transition (F) is greater than the corresponding profile segment () for flows up to the Q but is less at the Q and Q because of backwater effects (figures and 9) Shear stress in the downstream transition (C) is within the range of corresponding profile segments ( and ) Excess shear The excess shear analysis shows the culvert as having lower potential for bed mobilization when compared to the upstream and downstream channels (figure ) This is due to the backwater effect of the culvert that lowers the energy grade and therefore lowers the applied shear available to move material Velocity The modeling suggests that velocity is low in the culvert due to backwater conditions that reduce the energy grade Velocity near the downstream end of the culvert is high where the flow passes through critical depth (figure ) Velocity in the upstream transition (F) is similar to the corresponding channel segment () at the Q and below but is lower than the channel at the Q and Q (figure 8) due to backwater effects Velocity in the downstream transition (C) is within the range of corresponding channel segments ( and ) at all modeled flows Scour summary There is severe scour of the left bank footing at the inlet and extending downstream approximately feet This is a serious maintenance issue that needs to be addressed to ensure that the structural integrity of the crossing is not compromised This scour may be partially related to culvert capacity, deposition of coarse material upstream of the inlet, and a large (greater than -foot diameter) midchannel log just upstream and inside of the culvert The drop into the scour pool is larger than any drops observed in the reference reaches This has also resulted in the deposition of material along the right footing at the inlet and the shifting of the channel towards the left Downstream of the scour pool, the bed is aggraded and levels off forming a consistent riffle

6 Culvert Scour ssessment ed material at the inlet has likely eroded out and redeposited at the downstream portion of the culvert, contributing to bed flattening Modeling suggests that flow geometry and hydraulics are highly impacted by the culvert, especially at high flows that cause backwater within and upstream of the culvert The culvert appears to be under outlet control at high flows, with the length, roughness, and downstream conditions raising the elevation of the flow through much of the culvert This condition serves to reduce channel velocity and shear stress through most of the culvert at very high flows (Q and above) t these flows, the modeling shows flow passing through critical depth near the downstream end of the culvert, with associated high shear stress and velocity that could cause scour at this location Prior to the inlet scour, which widened the inlet area, the culvert may have exhibited inlet control conditions that contributed to the scour observed in the inlet area t more frequent flood events, inlet control conditions may still be a concern, especially with respect to the potential for increased scour of the footing at the inlet There is also significant erosion at the sides of the culvert at the inlet and outlet, possibly a result of flow contraction and expansion Erosion at the left bank upstream of the inlet is further exacerbated by the coarse material and logs that have deposited upstream of the inlet, thus initiating lateral boundary adjustment OP Conditions Cross-section complexity The sum of squared height differences in the culvert cross sections are both within the range of those in the channel cross sections (table ) Profile complexity Vertical sinuosity in the upstream culvert segment (E) is slightly greater than the values in the corresponding channel segments ( and ) (table ) Vertical sinuosity in the upstream transition segment (F) is slightly greater than the value in the corresponding channel segment () Vertical sinuosity in the downstream transition segment (C) is within the range of values in the corresponding channel segments ( and ) Depth distribution The upstream culvert cross section has less channel margin habitat than the natural channel but the downstream culvert cross section is within the range of the natural channel (table ) abitat units abitat-unit distribution in the culvert is within the range of that found in the natural channel upstream and downstream of the crossing (table ) Residual depths The single culvert residual depth is within the range of residual depths in corresponding profile segments in the natural channel ( and ) (figure ) The single residual depth in the downstream transition is also within the range of corresponding profile segments in the natural channel ( and ) There was no residual depth in the corresponding profile segment for the upstream transition Substrate ed-material distributions are similar between the culvert and channel sample sites The culvert has more coarse material than the downstream channel but similar abundance of coarse material as the upstream channel The downstream channel has the greatest abundance of fine material Sorting and skewness values in the culvert are within the range of those in the natural channel (table 7)

7 Site Evaluations Large woody debris There was one - to -footdiameter piece of LWD present at the inlet to the culvert The piece may have been a contributor to the scour present at the inlet The representative channel had high LWD abundance (table 8) LWD formed steps and scour pools in the channel outside the crossing and played a primary role in habitat-unit creation and complexity Features in the culvert did not mimic the role of wood in the natural channel OP summary Complexity measures and site observations suggest that this is a good installation with respect to OP There is good flow concentration in the culvert that would support fish passage at low flows The hydraulics at the Q bf and below are unaffected by the backwater effects described earlier and are assumed to be amenable to fish passage There is also a dry bank along the right side suitable for passage of terrestrial organisms There is also erosion on the sides of the culvert at the inlet and outlet These areas should be stabilized with rock or concrete (eg, wing-walls) to prevent erosion around the edges of the pipe Regular maintenance of the site is needed to remove woody debris, such as the large log that is located at the inlet and may be contributing to the inlet scour ased on the presence of log jams in the natural channel, wood transport is common through this portion of Maintenance needs to be conducted to manage for this wood or the crossing needs to be made wide enough to convey wood Design Considerations This site is a poor installation with respect to scour but appears to be suitable for OP There are serious concerns with the structural integrity of the structure that are primarily related to the undermining of the left-bank footing at the upstream end of the culvert dditionally, modeling suggests a severe effect on flow geometry and hydraulics at the Q and above that may create future scour problems within the pipe This design could be improved by use of a wider culvert with greater capacity to convey high flood flows It is also clear that the footing depth needs to be increased to extend below the depth of maximum potential scour

8 Culvert Scour ssessment 9 Relative 9 elevation (feet) 8 S e g m e n t XS S e g m e n t L e n g th ( f t) S e g m e n t G r a d ie n t C D 7 E 7 F G XS : Pebble count (riffle) XS : Pebble count (pool) XS C XS XS D C ulvert XS 7: Pebble count (riffle) E XS 8: Pebble count (pool) Large log in inlet XS 9 XS Representative Channel 8 Dis tance along bed (feet) Figure longitudinal profile Table Segment comparisons R epres en ta tiv e C h a n n el S egmen t % D ifferen c e in G ra dien t C u lv ert S egmen t E 7% E 9% U ps tream T rans ition F 97% D o w n s trea m T ra n s itio n C % C % F XS G XS XS : Pebble count (step) XS : Pebble count (pool) Representative Channel

9 Site Evaluations Table Summary of segments used for comparisons Segment Range of Manning's n values # of measured XSs # of interpolated XSs C 7 E F Obtained using equation from Jarrett (98): n = 9S8R-, where S=stream slope; R=hydraulic radius Jarrett s equation only applied within the following ranges: S = to 8, R = ft to 7 ft For cross-sections outside these ranges, n was computed either from adjacent sections that fell within the ranges, using the guidance of rcement and Schneider (987), or from the EC-RS recommendations for culvert modeling L e ge nd Culvert W S Q W S Q W S Q W S Qbf W S c fs Ground Elevation (ft) * * * * * 7 * * 7 7 * 7 * * Main Channel Dis tance (ft) Stations with decimal values are interpolated cross sections placed along the surveyed profile Figure EC-RS profile

10 Culvert Scour ssessment RS = RS = L e ge nd L e ge nd WS Q 8 WS Q WS Q WS Q 8 WS Q WS Q WS Qbf WS Qbf WS cfs WS cfs Ground 8 Ground ank St a ank St a l 8 i Station (ft) Station (ft) RS = RS = L e ge nd 8 WS Q WS Q WS Q 8 E WS Qbf l t a v e i Elevation (ft) Elevation (ft) ) t f ( n o L e ge nd WS Q WS Q WS Q WS Qbf WS c fs WS cfs 8 Elevation (ft) Elevation (ft) Ground Ground ank St a ank St a 8-8 Station (ft) Station (ft) Figure Cross-section plots Only measured cross sections are included Manning s n values are included at the top of the cross section The stationing (RS) corresponds to the stationing on the EC-RS profile Green arrows define the ineffective flow areas lack arrows represent points surveyed in as the bankfull channel boundary Only those points called out in the field and supported by further hydraulic and topographic analyses are marked below ) t f ( n o t a v e E

11 Site Evaluations RS = 9 RS = L e ge nd WS Q 8 WS Q 8 WS Q E WS Qbf WS cfs Elevation (ft) Ground 98 ank St a Station (ft) Station (ft) RS = 7 RS = 8 L e ge nd L e ge nd WS Q 9 WS Q 8 WS Q 8 WS Q WS Q l t a v e WS Q i ) t f ( n o L e g e n d W S Q W S Q W S Q W S Qb f WS cfs G rou nd Elevation (ft) Le ve e Ine ff an k S ta WS Qbf WS Qbf WS c fs WS cfs Elevation (ft) Elevation (ft) Ground Ground 98 ank St a 98 ank St a Station (ft) Station (ft) Figure Cross-section plots Only measured cross sections are included Manning s n values are included at the top of the cross section The stationing (RS) corresponds to the stationing on the EC-RS profile Green arrows define the ineffective flow areas lack arrows represent points surveyed in as the bankfull channel boundary Only those points called out in the field and supported by further hydraulic and topographic analyses are marked below (continued) 7

12 i l i l Culvert Scour ssessment RS = Station (ft) ) t f ( n o t a v e L e g e n d W S Q W S Q W S Q W S Qb f WS cfs G rou nd Ine ff an k S ta Elevation (ft) E L e g e n d W S Q W S Q W S Q W S Qb f RS = Station (ft) Elevation (ft) WS cfs G rou nd Ine ff an k S ta L e ge nd WS Q WS Q WS Q WS Qbf WS c fs Ground ank St a RS = Station (ft) Elevation (ft) L e ge nd WS Q WS Q WS Q WS Qbf WS c fs Ground ank St a RS = Station (ft) Elevation (ft) Figure Cross-section plots Only measured cross sections are included Manning s n values are included at the top of the cross section The stationing (RS) corresponds to the stationing on the EC-RS profile Green arrows define the ineffective flow areas lack arrows represent points surveyed in as the bankfull channel boundary Only those points called out in the field and supported by further hydraulic and topographic analyses are marked below (continued) 8 ) t f ( n o t a v e E

13 Site Evaluations RS = RS = L e ge nd WS Q WS Q WS Q WS Qbf WS c fs Ground ank St a Station (ft) Elevation (ft) L e g e n d W S Q W S Q W S Q W S Qb f WS cfs G rou nd Le ve e an k S ta Station (ft) Elevation (ft) Figure Cross-section plots Only measured cross sections are included Manning s n values are included at the top of the cross section The stationing (RS) corresponds to the stationing on the EC-RS profile Green arrows define the ineffective flow areas lack arrows represent points surveyed in as the bankfull channel boundary Only those points called out in the field and supported by further hydraulic and topographic analyses are marked below (continued) Main Channel Distance (ft) Figure Flow area (total) profile plot 9 ) t f q s ( a e r Legend Flow rea Q w o F l Flow C D E F G Culvert Flow rea Q Flow rea Q Flow rea Qbf Flow rea cfs Flow area (sq ft)

14 Culvert Scour ssessment Legend WP Total Q WP Total Q Flow C D E F G Culvert 8 Main Channel Distance (ft) Figure Wetted perimeter Flow 8 Main Channel Distance (ft) Figure 7 ydraulic radius WP Total Q WP Total Qbf WP Total cfs ) t f ( s u d a R r d y Legend ydr Radius Q C D E F G Culvert ydr Radius Q ydr Radius Q ydr Radius Qbf ydr Radius cfs i WP total (ft) ydraulic radius (ft)

15 Site Evaluations Legend Top Width Q Top Width Q Flow C D E F G Culvert 8 Top Width Q Top Width Qbf Top Width cfs Main Channel Distance (ft) Figure 8 Top width 8 Main Channel Distance (ft) Figure 9 Maximum depth ) t f ( h t p D h C x a M l Legend Max Chl Dpth Q Max Chl Dpth Q Max Chl Dpth Q Max Chl Dpth Qbf Max Chl Dpth cfs Top width (ft) Flow C D E F G Culvert Maximum channel depth (ft)

16 Culvert Scour ssessment Legend Shear Chan Q Shear Chan Q Shear Chan Q Shear Chan Qbf Shear Chan cfs Flow C D E F G Culvert l l Shear channel (lbs/sq ft) Main Channel Distance (ft) *Note: Shear at station for the Q and Q are greater than pounds per square foot and are therefore not shown Figure Shear stress (channel) profile Legend Vel Chnl Q Flow Main Channel Distance (ft) Figure Velocity (channel) profile plot s ) / t f ( C D E F G Culvert Vel Chnl Q Vel Chnl Q Vel Chnl Qbf Vel Chnl cfs Velocity channel (ft/sec) n h C e V

17 Site Evaluations ox Plot Explanation Maximum value 7th percentile Median (aka th percentile) % of the values % of the values th percentile Minimum value Flow rea (ft) Flow area (ft ) %Q Qbf Figure Flow area (total)

18 Culvert Scour ssessment 9 Wetted Perimeter (ft) Wetted perimeter (ft) %Q Qbf Figure Wetted perimeter ydraulic Radius (ft) ydraulic radius (ft) %Q Qbf Figure ydraulic radius

19 Site Evaluations 8 Top width (ft) Top Width (ft) %Q Qbf Figure Top width 8-8 Maximum Depth (ft) Maximum depth (ft) %Q Qbf Figure Maximum depth

20 Culvert Scour ssessment 8 Width-to-depth Ratio Width-to-depth ratio %Q Qbf Figure 7 Width-to-depth ratio 8 Velocity (ft/sec) Velocity (ft/sec) %Q Qbf Figure 8 Velocity (channel)

21 Site Evaluations Shear Stress (lbs/ft) Shear stress (lbs/ft ) %Q Qbf Figure 9 Shear stress (channel) US Channel (DS pebble count) - step Culvert (DS pebble count) - riffle DS Channel (DS pebble count) - riffle Excess Shear (pplied / tcrit) Discharge (cfs) Excess shear (pplied/tcrit) Excess shear stress is the channel shear divided by the critical shear for bed entrainment of the D 8 particle size Values of excess shear greater than indicate bed movement for the D 8 particle size Figure Excess shear stress 7

22 Culvert Scour ssessment Table Sum of squared height difference Reach XS Unit Sum of squared Within range of Location type height difference channel conditions? Culvert US Pool Yes DS Riffle Yes Upstream US Pool DS Step Downstream US Pool DS Riffle Table Vertical sinuosity Segment Location Vertical Sinuosity (ft/ft) DS channel DS channel 9 C DS transition 7 D Culvert E Culvert F US transition G US channel US channel 7 Table Depth distribution Reach XS % Q Within range of Location channel conditions? Culvert US No Upstream US DS Yes DS Downstream US DS 8 8

23 Table abitat unit composition Percent of surface area Reach Pool Glide Riffle Step Culvert % % % % Upstream Channel 8% % % % Downstream Channel % % 7% % Site Evaluations Residual Depth (ft) 8 Segment Segment Segment C DS Transition Segment D Culvert Segment E Culvert Segment F US Transition Segment G Segment Figure Residual depths Table 7 ed material sorting and skewness Reach XS Unit Sorting Within range Skewness Within range Location Type of channel of channel conditions? conditions? Culvert US Pool Yes Yes DS Riffle 7 Yes Yes Upstream US Pool 9 DS Step Downstream US Pool DS Riffle 7 9

24 Culvert Scour ssessment Table 8 Large woody debris Reach Pieces/Channel Width Culvert ` Upstream Downstream Terminology: US = Upstream DS = Downstream RR = Reference reach XS = Cross section

25 Site Evaluations View upstream through culvert View downstream through culvert View downstream of culvert inlet View of undercut left bank footing at upstream end of culvert Downstream reference reach Upstream reference reach

26 Culvert Scour ssessment Cross Section: Upstream Reference Reach Upstream Pebble Count Material S ize C las s (mm) C ount Item % C umulative % sand < % % very fine gravel - % % fine gravel - 7 % % fine gravel 7-8 % % medium gravel 8 - % % medium gravel - % 8% coarse gravel - % 9% coarse gravel - % % very coarse gravel - 8 9% % very coarse gravel - 9 % % small cobble % 9% medium cobble 9-8 % % large cobble % 9% very large cobble 8 - % 7% small boulder - % 8% small boulder - 9 % 9% medium boulder - % % large boulder - 8 % % very large boulder 8-9 % % bedrock edrock % % Frequency 8 < Particle Size Category (mm) edrock % 9% 8% 7% % % % % % % % Cumulative Frequency S ize C las s S ize perc ent finer than (mm) D D D D8 9 D9 D 9 Material P ercent C ompos ition Sand % Gravel % Cobble % oulder 9% edrock % Sorting Coefficient: 9 Skewness Coefficient:

27 Site Evaluations Cross Section: Upstream Reference Reach Downstream Pebble Count Material S ize C las s (mm) C ount Item % C umulative % sand < % % very fine gravel - % % fine gravel - 7 % % fine gravel 7-8 % % medium gravel 8 - % % medium gravel - % % coarse gravel - % % coarse gravel - % % very coarse gravel - % % very coarse gravel - % % small cobble % % medium cobble 9-8 7% 9% large cobble 8-8 % % very large cobble 8 - % 9% small boulder - % 7% small boulder - % 87% medium boulder - % % large boulder - 8 % % very large boulder 8-9 % % bedrock edrock % % Frequency 8 % 8% % % % % Cumulative Frequency < Particle Size Category (mm) edrock -% S ize C las s S ize perc ent finer than (mm) D D 78 D D8 D9 D 7 Material P ercent C ompos ition Sand % Gravel % Cobble 7% oulder % edrock % Sorting Coefficient: Skewness Coefficient:

28 Culvert Scour ssessment Cross Section: Culvert Upstream Pebble Count Material S ize C las s (mm) C ount Item % C umulative % sand < % % very fine gravel - % % fine gravel - 7 % % fine gravel 7-8 % % medium gravel 8 - % % medium gravel - % 8% coarse gravel - % % coarse gravel - % % very coarse gravel - 7 7% % very coarse gravel - 7 7% % small cobble % 9% medium cobble % 9% large cobble % 7% very large cobble 8-9 9% 8% small boulder - % 89% small boulder - 9 9% 98% medium boulder - % % large boulder - 8 % % very large boulder 8-9 % % bedrock edrock % % Frequency 8 8 < Particle Size Category (mm) edrock % 9% 8% 7% % % % % % % % Cumulative Frequency S ize C las s S ize perc ent finer than (mm) D D D D8 D9 7 D Material P ercent C ompos ition Sand % Gravel 9% Cobble % oulder % edrock % Sorting Coefficient: Skewness Coefficient:

29 Site Evaluations Cross Section: Culvert Downstream Pebble Count Material S ize C las s (mm) C ount Item % C umulative % sand < % % very fine gravel - % % fine gravel - 7 % % fine gravel 7-8 % % medium gravel 8 - % % medium gravel - % % coarse gravel - % 9% coarse gravel - % % very coarse gravel - % % very coarse gravel - 7 7% % small cobble % % medium cobble 9-8 % % large cobble 8-8 7% % very large cobble 8 - % % small boulder - % 8% small boulder - % 9% medium boulder - % % large boulder - 8 % % very large boulder 8-9 % % bedrock edrock % % Frequency 8 8 % 9% 8% 7% % % % % % % % Cumulative Frequency < Particle Size Category (mm) edrock S ize C las s S ize perc ent finer than (mm) D 8 D 9 D D8 8 D9 D 9 Material P ercent C ompos ition Sand % Gravel % Cobble % oulder % edrock % Sorting Coefficient: 7 Skewness Coefficient:

30 Culvert Scour ssessment Cross Section: Downstream Reference Reach Upstream Pebble Count Material S ize R ange (mm) C ount Item % C umulative % sand < % % very fine gravel - % % fine gravel - 7 % % fine gravel 7-8 % % medium gravel 8 - % % medium gravel - % % coarse gravel - % % coarse gravel - % % very coarse gravel - % 8% very coarse gravel - % 8% small cobble % % medium cobble 9-8 % % large cobble % 8% very large cobble 8 - % 9% small boulder - % 97% small boulder - % % medium boulder - % % large boulder - 8 % % very large boulder 8-9 % % bedrock > 9 % % % 8 9% Frequency 8 8% 7% % % % % Cumulative Frequency % % % < Particle Size Category (mm) edrock S ize C las s S ize perc ent finer than (mm) D D D D8 D9 D Material P ercent C ompos ition Sand % Gravel 8% Cobble % oulder 9% edrock % Sorting Coefficient: Skewness Coefficient:

31 Cross Section: Downstream Reference Reach Downstream Pebble Count Material S ize C las s (mm) C ount Item % C umulative % sand < 8 8% 8% very fine gravel - % 9% fine gravel - 7 % 9% fine gravel 7-8 % % medium gravel 8 - % % medium gravel - % % coarse gravel - 8 8% % coarse gravel - 9 9% % very coarse gravel - % % very coarse gravel - 9 9% % small cobble - 9 % 8% medium cobble 9-8 % % large cobble % 7% very large cobble 8-8 8% 78% small boulder - % 9% small boulder - 7 7% 97% medium boulder - % % large boulder - 8 % % very large boulder 8-9 % % bedrock edrock % % Site Evaluations Frequency 8 % 9% 8% 7% % % % % % % % Cumulative Frequency < Particle Size Category (mm) edrock S ize C las s S ize perc ent finer than (mm) D D 8 D D8 D9 D 7 Material P ercent C ompos ition Sand 8% Gravel 7% Cobble % oulder % edrock % Sorting Coefficient: Skewness Coefficient: 7 7

Culvert Design for Low and High Gradient Streams in the Midwest. Dale Higgins, Hydrologist Chequamegon-Nicolet National Forest

Culvert Design for Low and High Gradient Streams in the Midwest. Dale Higgins, Hydrologist Chequamegon-Nicolet National Forest Culvert Design for Low and High Gradient Streams in the Midwest Dale Higgins, Hydrologist Chequamegon-Nicolet National Forest Overview Culvert Design Considerations Hydraulic Terms Culvert Impacts Low

More information

Stream Assessment. Date. Data Collected by. Location. Name of Stream and River Basin. Stream Order. Streambank Materials. Streambank Vegetation

Stream Assessment. Date. Data Collected by. Location. Name of Stream and River Basin. Stream Order. Streambank Materials. Streambank Vegetation Stream Assessment Date Data Collected by Location Name of Stream and River Basin Stream Order Streambank Materials Streambank Vegetation Floodplain Soils Floodplain Vegetation Valley Type Valley Constraints

More information

Aquatic Organism Passage at Road-Stream Crossings CHUCK KEEPORTS FOREST HYDROLOGIST ALLEGHENY NATIONAL FOREST WARREN, PENNSYLVANIA

Aquatic Organism Passage at Road-Stream Crossings CHUCK KEEPORTS FOREST HYDROLOGIST ALLEGHENY NATIONAL FOREST WARREN, PENNSYLVANIA Aquatic Organism Passage at Road-Stream Crossings CHUCK KEEPORTS FOREST HYDROLOGIST ALLEGHENY NATIONAL FOREST WARREN, PENNSYLVANIA TOPICS COVERED Aquatic Organism Passage (AOP) Benefits of AOP Crossings

More information

HEC 26 Aquatic Organism Passage Design Manual Evolution & Application

HEC 26 Aquatic Organism Passage Design Manual Evolution & Application HEC 26 Aquatic Organism Passage Design Manual Evolution & Application Sven Leon, P.E., Hydraulics Engineer Federal Highway Administration 2015 Alaska Fish Passage Meeting October 13 14, 2015 VTRC, Juneau,

More information

Added Introduction: Comparing highway design and stream design

Added Introduction: Comparing highway design and stream design Added Introduction: Comparing highway design and stream design Highway width is sized for the traffic, the width expanding as volume and speed increase. The ROW width is also designed to handle the speed

More information

Great Lakes Stream Crossing Inventory Instructions

Great Lakes Stream Crossing Inventory Instructions Great Lakes Stream Crossing Inventory Instructions This document is a guide to completing the Stream Crossing Data Sheet (2/28/11 version). Careful attention to this guidance will ensure consistent crossing

More information

APPENDIX J HYDROLOGY AND WATER QUALITY

APPENDIX J HYDROLOGY AND WATER QUALITY APPENDIX J HYDROLOGY AND WATER QUALITY J-1 Technical Report on Airport Drainage, Northern Sector Airport and Ordinance Creek Watershed / Preliminary Creek Constructed Natural Channel Culvert J-2 Preliminary

More information

Massachusetts Stream Crossing Case Studies

Massachusetts Stream Crossing Case Studies Massachusetts Stream Crossing Case Studies Amy Singler Associate Director, River Restoration Program Carrie Banks River Continuity Coordinator Case Studies: Public Benefits: Movement of goods and people

More information

Rehabilitation of Grimes Creek, a Stream Impacted in the Past by Bucket-lined Dredge Gold Mining, Boise River Drainage, July 2008 to August 2011.

Rehabilitation of Grimes Creek, a Stream Impacted in the Past by Bucket-lined Dredge Gold Mining, Boise River Drainage, July 2008 to August 2011. Rehabilitation of Grimes Creek, a Stream Impacted in the Past by Bucket-lined Dredge Gold Mining, Boise River Drainage, July 2008 to August 2011. Pam Harrington TU,1020 W. Main Street Suite 440, Boise,

More information

(Revised February,2005) CULVERTS, BRIDGES, AND FORDS

(Revised February,2005) CULVERTS, BRIDGES, AND FORDS GUIDE TO STREAM CROSSINGS (Revised February,2005) CULVERTS, BRIDGES, AND FORDS Culverts, bridges, and fords are all methods used to cross-streams. Culverts are the most common stream crossing structure.

More information

STUDY PERFORMANCE REPORT

STUDY PERFORMANCE REPORT STUDY PERFORMANCE REPORT State: Michigan Project No.: F-80-R-4 Study No.: 702 Title: Effects of sediment traps on Michigan river channels Period Covered: October 1, 2002 to September 30, 2003 Study Objectives:

More information

Packwood Hydroelectric Project Barrier Analysis December 12, 2006

Packwood Hydroelectric Project Barrier Analysis December 12, 2006 Packwood Hydroelectric Project Barrier Analysis December 12, 2006 Study Area Natural barriers to upstream fish passage on Lake Creek at RM 1.03 and RM 1.95 Snyder Creek culvert under the Project tailrace

More information

BC Ministry of Forests. March Fish Stream Crossing Guidebook. Forest Practices Code of British Columbia.

BC Ministry of Forests. March Fish Stream Crossing Guidebook. Forest Practices Code of British Columbia. FRST 557 Lecture 7c Bridges and Culverts: Water Velocity and Discharge Lesson Background and Overview: The previous two lessons presented methods for estimating water volume flow at a particular site and

More information

CHAPTER 4 SPALDING COUNTY, GEORGIA 4.0 CULVERT DESIGN

CHAPTER 4 SPALDING COUNTY, GEORGIA 4.0 CULVERT DESIGN SPALDING COUNTY, GEORGIA CHAPTER 4 4.0 CULVERT DESIGN... 4-1 4.1 INTRODUCTION... 4-1 4.2 SYMBOLS AND DEFINITIONS... 4-1 4.3 ENGINEERING DESIGN CRITERIA... 4-2 4.3.1 FREQUENCY FLOOD... 4-2 4.3.2 VELOCITY

More information

Culvert Design An Overview of the NYS Highway Design Manual Chapter 8

Culvert Design An Overview of the NYS Highway Design Manual Chapter 8 Seventeenth Statewide Conference on Local Bridges Culvert Design An Overview of the NYS Highway Design Manual Chapter 8 Tuesday, October 25, 2011 Training Session: Culvert Design, Analysis - talk 2 Presented

More information

APPENDIX B HYDRAULIC DESIGN DATA FOR CULVERTS

APPENDIX B HYDRAULIC DESIGN DATA FOR CULVERTS TM 5-820-4/AFM 88-5, Chap 4 APPENDIX B HYDRAULIC DESIGN DATA FOR CULVERTS B-1. General. a. This appendix presents diagrams, charts, coefficients and related information useful in design of culverts. The

More information

CALIFORNIA SALMONID STREAM HABITAT RESTORATION MANUAL APPENDIX IX-A CULVERT CRITERIA FOR FISH PASSAGE INTRODUCTION

CALIFORNIA SALMONID STREAM HABITAT RESTORATION MANUAL APPENDIX IX-A CULVERT CRITERIA FOR FISH PASSAGE INTRODUCTION APPENDIX IX-A STATE OF CALIFORNIA RESOURCES AGENCY DEPARTMENT OF FISH AND GAME CULVERT CRITERIA FOR FISH PASSAGE For habitat protection, ecological connectivity should be a goal of stream-road crossing

More information

Interim Guidance Fish Presence Absence

Interim Guidance Fish Presence Absence Interim Guidance Fish Presence Absence Source: Forest Practices Act Guidance for Division 635 of the forest practices act dealing with stream classification when no fish surveys have been done (referenced

More information

CHAPTER 5 CULVERT DESIGN

CHAPTER 5 CULVERT DESIGN CHAPTER 5 CULVERT DESIGN HYDRAULICS OF CULVERTS There are two major types of culvert flow: 1) flow with inlet control, and 2) flow with outlet control. For each type, different factors and formulas are

More information

Indiana LTAP Road Scholar Core Course #10 Culvert Drainage. Presented by Thomas T. Burke, Jr., PhD, PE Christopher B. Burke Engineering, Ltd.

Indiana LTAP Road Scholar Core Course #10 Culvert Drainage. Presented by Thomas T. Burke, Jr., PhD, PE Christopher B. Burke Engineering, Ltd. Indiana LTAP Road Scholar Core Course #10 Culvert Drainage Presented by Thomas T. Burke, Jr., PhD, PE Christopher B. Burke Engineering, Ltd. Objectives Review culvert shapes, end sections, and materials

More information

HY-8 Version 7.2 Build Date January 17, Federal Highway Administration.

HY-8 Version 7.2 Build Date January 17, Federal Highway Administration. HY-8 Version 7.2 Build Date January 17, 2012 Federal Highway Administration http://www.fhwa.dot.gov/engineering/hydraulics/software/hy8/index.cfm SIMPLE Simple to use Use for simple culverts and bridges

More information

SELBY CREEK SILVERADO TRAIL CULVERT FISH PASSAGE ASSESSMENT

SELBY CREEK SILVERADO TRAIL CULVERT FISH PASSAGE ASSESSMENT SELBY CREEK SILVERADO TRAIL CULVERT FISH PASSAGE ASSESSMENT NAPA COUNTY, CALIFORNIA PREPARED BY NAPA COUNTY RESOURCE CONSERVATION DISTRICT 1303 JEFFERSON ST. SUITE 500B NAPA, CALIFORNIA 94559 WWW.NAPARCD.ORG

More information

Rock Ramp Design Guidelines. David Mooney MS Chris Holmquist-Johnson MS Drew Baird Ph.D. P.E. Kent Collins P.E.

Rock Ramp Design Guidelines. David Mooney MS Chris Holmquist-Johnson MS Drew Baird Ph.D. P.E. Kent Collins P.E. Rock Ramp Design Guidelines David Mooney MS Chris Holmquist-Johnson MS Drew Baird Ph.D. P.E. Kent Collins P.E. Rock Ramp Design Guidelines OUTLINE Local and System Interactions with Rock Ramps Ramp Geometry

More information

Assessment of Baseline Geomorphic Features at. Proposed Stream Crossings On The Proposed County Road 595. Marquette County, Michigan

Assessment of Baseline Geomorphic Features at. Proposed Stream Crossings On The Proposed County Road 595. Marquette County, Michigan Assessment of Baseline Geomorphic Features at Proposed Stream Crossings On The Proposed County Road 595 Marquette County, Michigan Prepared for: Kennecott Eagle Minerals Company Marquette, Michigan Prepared

More information

Cross-Vane Plan View FIN-UP Habitat Consultants, Inc. 220 Illinois Avenue Manitou Springs, CO (719) P.

Cross-Vane Plan View FIN-UP Habitat Consultants, Inc. 220 Illinois Avenue Manitou Springs, CO (719) P. STREAM CHANNEL STRUCTURE DRAWINGS ISIONS W (Channel Width) (Varies) Thalweg & Flow Direction Individually Placed Footer Rocks 5' to 6' by 2' thick (Min. 2 rows of footer rocks placed tightly together with

More information

Study Update Tailrace Slough Use by Anadromous Salmonids

Study Update Tailrace Slough Use by Anadromous Salmonids Study Update Tailrace Slough Use by Anadromous Salmonids Goals and Objectives Identify what anadromous salmonids use the tailrace slough by: Life Stage (Juvenile, migrating and spawning adults) Timing

More information

Presented by Fred Halterman, URS Jennie Agerton, URS

Presented by Fred Halterman, URS Jennie Agerton, URS Presented by Fred Halterman, URS Jennie Agerton, URS What is Eco Friendly Culvert Design? Culvert design that: Maintains connectivity for aquatic organism migration Maintains connectivity for gene flow

More information

Request Number IR1-12: Flow Passage. Information Request

Request Number IR1-12: Flow Passage. Information Request Request Number IR1-12: Flow Passage Information Request Provide additional information about the 100 metre flow passage channel scenario between the Westshore Terminals and the proposed Project terminal

More information

Summary of HEC 18, Evaluating Scour at Bridges FHWA NHI Should really follow HEC 18, but this summary will get you the main points.

Summary of HEC 18, Evaluating Scour at Bridges FHWA NHI Should really follow HEC 18, but this summary will get you the main points. Summary of HEC 18, Evaluating Scour at Bridges FHWA NHI 01-001 Should really follow HEC 18, but this summary will get you the main points. 1: Determine scour analysis variables 2: Analyze long-term bed

More information

MCCAW REACH RESTORATION

MCCAW REACH RESTORATION Final Report MCCAW REACH FISH RESTORATION PHASE B Jack McCaw Inland Empire Action Coalition http://www.wwccd.net/ Phone: 509-956-3777 Hours: 8:00-4:30 Walla Walla County Conservation District Snake River

More information

General Information for Culvert Design

General Information for Culvert Design Design Manual Chapter 2 - Stormwater 2E - Culvert Design 2E-1 General Information for Culvert Design A. Introduction A culvert is a conduit under an embankment that transports stormwater from one side

More information

ANSWERS TO QUESTIONS IN THE NOTES AUTUMN 2018

ANSWERS TO QUESTIONS IN THE NOTES AUTUMN 2018 ANSWERS TO QUESTIONS IN THE NOTES AUTUMN 2018 Section 1.2 Example. The discharge in a channel with bottom width 3 m is 12 m 3 s 1. If Manning s n is 0.013 m -1/3 s and the streamwise slope is 1 in 200,

More information

The Basics of Culvert and Inlet Design

The Basics of Culvert and Inlet Design PDHonline Course C619 (8 PDH) The Basics of Culvert and Inlet Design Jerry D. Morrow, PE 2013 PDH Online PDH Center 5272 Meadow Estates Drive Fairfax, VA 22030 6658 Phone & Fax: 703 988 0088 www.pdhonline.org

More information

Hydraulic Modeling of Stream Enhancement Methods

Hydraulic Modeling of Stream Enhancement Methods Hydraulic Modeling of Stream Enhancement Methods Matthew J. Curry John J. Levitsky Abstract Development within watersheds increases the amounts of runoff causing stream erosion and degradation of stream

More information

Habitat Conditions, Design Strategies,

Habitat Conditions, Design Strategies, Habitat Conditions, Design Strategies, Coho on Cedar Ck. five years after analog-based stream restoration work. and Stream Classification In river work, computer modeling is an insidious procedure in which

More information

LONGITUDINAL FIELD METHODOLOGY FOR THE ASSESSMENT OF TMDL SEDIMENT AND HABITAT IMPAIRMENTS

LONGITUDINAL FIELD METHODOLOGY FOR THE ASSESSMENT OF TMDL SEDIMENT AND HABITAT IMPAIRMENTS LONGITUDINAL FIELD METHODOLOGY FOR THE ASSESSMENT OF TMDL SEDIMENT AND HABITAT IMPAIRMENTS Montana Department of Environmental Quality 1520 East Sixth Avenue Helena, Montana 59620 June 2007 TABLE OF CONTENTS

More information

PENNDRAIN.rep. HEC-RAS Version May 2005 U.S. Army Corp of Engineers Hydrologic Engineering Center 609 Second Street Davis, California

PENNDRAIN.rep. HEC-RAS Version May 2005 U.S. Army Corp of Engineers Hydrologic Engineering Center 609 Second Street Davis, California HEC-RAS Version 3.1.3 May 2005 U.S. Army Corp of Engineers Hydrologic Engineering Center 609 Second Street Davis, California X X XXXXXX XXXX XXXX XX XXXX X X X X X X X X X X X X X X X X X X X XXXXXXX XXXX

More information

Fish Passage Assessment of Private Stream Crossings on Lower Stonybrook Creek

Fish Passage Assessment of Private Stream Crossings on Lower Stonybrook Creek Fish Passage Assessment of Private Stream Crossings on Lower Stonybrook Creek Prepared by: Michael Love & Associates In cooperation with: Center for Ecosystem Management and Restoration Funded by: Coastal

More information

Joe Rathbun Michigan DEQ Water Resources Division Nonpoint Source Unit * Thanks to The Nature Conservancy

Joe Rathbun Michigan DEQ Water Resources Division Nonpoint Source Unit * Thanks to The Nature Conservancy Joe Rathbun Michigan DEQ Water Resources Division Nonpoint Source Unit rathbunj@mi.gov * Thanks to The Nature Conservancy Road-stream intersections = 67,511 Culverts = 60,700 Bridges = 6,811 Perched Piping

More information

Study No. 18. Mystic Lake, Montana. PPL Montana 45 Basin Creek Road Butte, Montana 59701

Study No. 18. Mystic Lake, Montana. PPL Montana 45 Basin Creek Road Butte, Montana 59701 Study No. 18 Evaluation of the Current Fish Population and Habitat in West Rosebud Creek Downstream from Emerald Lake Mystic Lake Hydroelectric Project FERC No. 2301 Mystic Lake, Montana PPL Montana 45

More information

Geomorphic Stream Classification A Classification of Natural Rivers, Rosgen, D.L.

Geomorphic Stream Classification A Classification of Natural Rivers, Rosgen, D.L. Geomorphic Stream Classification A Classification of Natural Rivers, Rosgen, D.L. Why is Stream Classification Physical stream channel evolution Essential? Similar stream types manifest similar patterns

More information

Culvert Design Basics

Culvert Design Basics PDHonline Course C287 (4 PDH) Culvert Design Basics Instructor: George E. Thomas, PE 2012 PDH Online PDH Center 5272 Meadow Estates Drive Fairfax, VA 22030-6658 Phone & Fax: 703-988-0088 www.pdhonline.org

More information

Five Counties Salmonid Conservation Program - Fish Passage Design Workshop. February 2013

Five Counties Salmonid Conservation Program - Fish Passage Design Workshop. February 2013 Program - Aquatic Organisms and Stream Crossings Ecological Connectivity A watershed is a network of channels that drain a common boundary. Channel characteristics formed by interaction of precipitation,

More information

Washington State Fish Passage Barrier Removal Projects. Casey Kramer, PE WSDOT State Hydraulics Engineer

Washington State Fish Passage Barrier Removal Projects. Casey Kramer, PE WSDOT State Hydraulics Engineer Washington State Fish Passage Barrier Removal Projects Casey Kramer, PE WSDOT State Hydraulics Engineer 2014 National Hydraulic Engineering Conference Iowa City, IA August 20 th, 2014 WSDOT Fish Passage

More information

Understanding the Impacts of Culvert Performance on Stream Health

Understanding the Impacts of Culvert Performance on Stream Health Understanding the Impacts of Culvert Performance on Stream Health Kristin Thomas Aquatic Ecologist Michigan Trout Unlimited Transportation and the Environment Conference 12/5/2018 Importance of adequately

More information

Simulating Streams Through Culverts in Mat-Su, Alaska

Simulating Streams Through Culverts in Mat-Su, Alaska Simulating Streams Through Culverts in Mat-Su, Alaska Project Managers Bill Rice, P.E., USFWS Hydrologist Mary Price, USFWS Fishery Biologist The Team Approach US Fish and Wildlife Service Bill Rice, P.E.,

More information

Hydrologic, Hydraulic and Geomorphic Technical Memorandum

Hydrologic, Hydraulic and Geomorphic Technical Memorandum Appendix A Hydrologic, Hydraulic and Geomorphic Technical Memorandum 01054/8410233/14/Rohner_Alt_Analysis_Report Rohner Creek Flood Control, Habitat and Seismic Improvement Project Alternatives Analysis

More information

Annex E Bridge Pier Protection Plan

Annex E Bridge Pier Protection Plan Annex E Bridge Pier Protection Plan Table E1 Bridge Types and Locations Table E2 Flow Conditions For River Sections Figure E1 Bridge Abutment Protection Figure E2 Bridge Pier Protection Figure E3 Central

More information

Illinois State Water Survey

Illinois State Water Survey Illinois State Water Survey HYDROLOGY DIVISION SWS Contract Report 508 COMPARISON OF 1987 AND 1989 BED PROFILE SURVEYS OF THE LOWER CACHE RIVER by Richard Allgire Office of Sediment and Wetland Studies

More information

Stream Assessment Cut-block: For: Island Timberlands Limited Partnership, Cameron Operation

Stream Assessment Cut-block: For: Island Timberlands Limited Partnership, Cameron Operation Stream Assessment Cut-block: 171214 For: Island Timberlands Limited Partnership, Cameron Operation Tony Norris Area Engineer Island Timberlands Cameron Operation Port Alberni D.G. Rigets E.I.A. CTech.

More information

APPENDIX C VEGETATED EMERGENCY SPILLWAY. VERSION 1.0 March 1, 2011

APPENDIX C VEGETATED EMERGENCY SPILLWAY. VERSION 1.0 March 1, 2011 APPENDIX C VEGETATED EMERGENCY SPILLWAY VERSION 1.0 March 1, 2011 [NOTE: Could use a better photo more clearly showing the emergency spillway in the context of the dam.] SECTION C-1: DESCRIPTION OF PRACTICE

More information

Stream Crossings I: Engineering and Design Approaches to Provide Fish Passage at Culvert Slipline Projects in Connecticut

Stream Crossings I: Engineering and Design Approaches to Provide Fish Passage at Culvert Slipline Projects in Connecticut University of Massachusetts - Amherst ScholarWorks@UMass Amherst International Conference on Engineering and Ecohydrology for Fish Passage International Conference on Engineering and Ecohydrology for Fish

More information

Management of headwater streams in the White Mountain National Forest

Management of headwater streams in the White Mountain National Forest Management of headwater streams in the White Mountain National Forest White Mountain National Forest Weeks Act of 1911 authorized the federal government to purchase lands east of the Mississippi River

More information

Plan B Dam Breach Assessment

Plan B Dam Breach Assessment Plan B Dam Breach Assessment Introduction In support of the Local Sponsor permit applications to the states of Minnesota and North Dakota, a dam breach analysis for the Plan B alignment of the Fargo-Moorhead

More information

Fish Habitat Design, Operation and Reclamation Worksheets for

Fish Habitat Design, Operation and Reclamation Worksheets for Fish Habitat Design, Operation and Reclaation Worksheets for Appendix A Project Location Worksheet Applicant Nae: Strea Nae: Watershed Nae: Fish Habitat Suitability Classification Water Quality Zone Operation

More information

Quantifying Performance of Stream Simulation Culverts in the Chehalis Basin, WA

Quantifying Performance of Stream Simulation Culverts in the Chehalis Basin, WA Quantifying Performance of Stream Simulation Culverts in the Chehalis Basin, WA AUTHORS: Joe Richards, Environmental Science Associates Jane Atha, Washington Department of Fish & Wildlife Colin Thorne,

More information

2O-2 Open Channel Flow

2O-2 Open Channel Flow Iowa Stormwater Management Manual O- O- Open Channel Flow A. Introduction The beginning of any channel design or modification is to understand the hydraulics of the stream. The procedures for performing

More information

TOP:001.3 U.S. Fish and Wildlife Service TECHNICAL OPERATING PROCEDURE

TOP:001.3 U.S. Fish and Wildlife Service TECHNICAL OPERATING PROCEDURE TOP:001.3 March 12, 2015 U.S. Fish and Wildlife Service Marquette Biological Station 3090 Wright Street Marquette, Michigan 49855 U.S.A. and U.S. Fish and Wildlife Service Ludington Biological Station

More information

TREATING RIVERS RIGHT & EXAMPLES OF BEST USE OF WOOD IN RESTORATION

TREATING RIVERS RIGHT & EXAMPLES OF BEST USE OF WOOD IN RESTORATION TREATING RIVERS RIGHT & EXAMPLES OF BEST USE OF WOOD IN RESTORATION James Mac Cartney, TU River Restoration Specialist John Braico, MD, NY Council Resource Mgr Grassroots Trustee 1 Great Trout Streams

More information

Fish Passage Assessment Report Mare Brook Culverts

Fish Passage Assessment Report Mare Brook Culverts Fish Passage Assessment Report Mare Brook Culverts Fish Passage Assessment Component of Mare Brook Watershed Assessment and Community Engagement Project Prepared for: FB Environmental Associates 97A Exchange

More information

Minnesota Department of Natural Resources Division of Fish and Wildlife Section of Fisheries. Stream Survey Report. Luxemburg Creek.

Minnesota Department of Natural Resources Division of Fish and Wildlife Section of Fisheries. Stream Survey Report. Luxemburg Creek. Minnesota F-29-R(P)-24 Area 315 Study 3 March 2016 Minnesota Department of Natural Resources Division of Fish and Wildlife Section of Fisheries Stream Survey Report Luxemburg Creek 2015 Mark Pelham Sauk

More information

Minnesota Department of Natural Resources Division of Fish and Wildlife Section of Fisheries. Stream Survey Report. Three Mile Creek 2011

Minnesota Department of Natural Resources Division of Fish and Wildlife Section of Fisheries. Stream Survey Report. Three Mile Creek 2011 Minnesota Department of Natural Resources Division of Fish and Wildlife Section of Fisheries Stream Survey Report Three Mile Creek 2011 By Joseph D. Stewig Montrose Area Fisheries Office TABLE OF CONTENTS

More information

NOVEMBER 2006 FLOOD DOWNSTREAM OF THE KATSE DAM STRUCTURE

NOVEMBER 2006 FLOOD DOWNSTREAM OF THE KATSE DAM STRUCTURE THE LESOTHO HIGHLANDS DEVELOPMENT AUTHORITY (LHDA) NOVEMBER 2006 FLOOD DOWNSTREAM OF THE KATSE DAM STRUCTURE Effects of the November 2006 Flood THE DAMAGE CAUSED BY THE FLOOD AS IT PROPAGATES DOWNSTREAM

More information

Advanced Hydraulics Prof. Dr. Suresh A. Kartha Department of Civil Engineering Indian Institute of Technology, Guwahati

Advanced Hydraulics Prof. Dr. Suresh A. Kartha Department of Civil Engineering Indian Institute of Technology, Guwahati Advanced Hydraulics Prof. Dr. Suresh A. Kartha Department of Civil Engineering Indian Institute of Technology, Guwahati Module - 4 Hydraulics Jumps Lecture - 4 Features of Hydraulic Jumps (Refer Slide

More information

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH 4 OVER THE BEAVER RIVER ST. LOUIS COUNTY

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH 4 OVER THE BEAVER RIVER ST. LOUIS COUNTY UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 7635 CSAH 4 OVER THE BEAVER RIVER ST. LOUIS COUNTY JUNE 18, 2012 PREPARED FOR THE MINNESOTA DEPARTMENT OF TRANSPORTATION BY COLLINS ENGINEERS, INC. JOB

More information

JAP Additional Information Sheet

JAP Additional Information Sheet JAP Additional Information Sheet Block 15: Purpose and Need The USACE purpose of the project is to provide a safe and reliable whitewater park for the recreational public in a city park, which will provide

More information

Components of a Barrage

Components of a Barrage Components of a Barrage Definition The only difference between a weir and a barrage is of gates, that is the flow in barrage is regulated by gates and that in weirs, by its crest height. Barrages are costlier

More information

DRAFT. Stonybrook Creek Watershed

DRAFT. Stonybrook Creek Watershed DRAFT Stonybrook Creek Watershed A Strategic Plan for Eliminating Barriers to Steelhead Migration June 4, 2010 Prepared by: PO Box 4477, Arcata, CA 95518 mlove@h2odesigns.com / (707) 476 8938 Prepared

More information

HYDRAULIC JUMP AND WEIR FLOW

HYDRAULIC JUMP AND WEIR FLOW HYDRAULIC JUMP AND WEIR FLOW 1 Condition for formation of hydraulic jump When depth of flow is forced to change from a supercritical depth to a subcritical depth Or Froude number decreases from greater

More information

OFFICE OF STRUCTURES MANUAL FOR HYDROLOGIC AND HYDRAULIC DESIGN CHAPTER 13 CULVERTS APRIL 2011

OFFICE OF STRUCTURES MANUAL FOR HYDROLOGIC AND HYDRAULIC DESIGN CHAPTER 13 CULVERTS APRIL 2011 OFFICE OF STRUCTURES MANUAL FOR HYDROLOGIC AND HYDRAULIC DESIGN CHAPTER 13 CULVERTS APRIL 2011 APRIL 2011 Chapter 13 Culverts Table of Contents Foreword.3 13.1 Introduction.. 4 13.2 Policy 6 13.3 Passage

More information

OFFICE OF STRUCTURES MANUAL FOR HYDROLOGIC AND HYDRAULIC DESIGN CHAPTER 11 APPENDIX B TIDEROUT 2 USERS MANUAL

OFFICE OF STRUCTURES MANUAL FOR HYDROLOGIC AND HYDRAULIC DESIGN CHAPTER 11 APPENDIX B TIDEROUT 2 USERS MANUAL OFFICE OF STRUCTURES MANUAL FOR HYDROLOGIC AND HYDRAULIC DESIGN CHAPTER 11 APPENDIX B TIDEROUT 2 USERS MANUAL APRIL 2011 APRIL 2011 Page 1 Preface TIDEROUT 2, Build 1.22 dated June 29, 2006 is the current

More information

APPENDIX C ESTIMATING SCOUR IN BOTTOMLESS ARCH CULVERTS

APPENDIX C ESTIMATING SCOUR IN BOTTOMLESS ARCH CULVERTS OFFICE OF STRUCTURES MANUAL FOR HYDROLOGIC AND HYDRAULIC DESIGN CHAPTER 11, EVALUATING SCOUR AT BRIDGES APPENDIX C ESTIMATING SCOUR IN BOTTOMLESS ARCH CULVERTS APRIL 2011 APPENDIX C ESTIMATING SCOUR IN

More information

Fish Habitat Restoration and Monitoring in Southeast Washington. Andy Hill Eco Logical Research, Inc.

Fish Habitat Restoration and Monitoring in Southeast Washington. Andy Hill Eco Logical Research, Inc. Fish Habitat Restoration and Monitoring in Southeast Washington Andy Hill Eco Logical Research, Inc. Fish Habitat Restoration and Monitoring in Southeast Washington Talk overview: Restoration projects

More information

WMS 8.4 Tutorial Hydraulics and Floodplain Modeling HY-8 Modeling Wizard Learn how to model a culvert using HY-8 and WMS

WMS 8.4 Tutorial Hydraulics and Floodplain Modeling HY-8 Modeling Wizard Learn how to model a culvert using HY-8 and WMS v. 8.4 WMS 8.4 Tutorial Hydraulics and Floodplain Modeling HY-8 Modeling Wizard Learn how to model a culvert using HY-8 and WMS Objectives Define a conceptual schematic of the roadway, invert, and downstream

More information

Chadbourne Dam Repair and Fish Barrier

Chadbourne Dam Repair and Fish Barrier Chadbourne Dam Repair and Fish Barrier Final Report for the Western Native Trout Initiative Prepared by: Carol Endicott Yellowstone Cutthroat Trout Conservation Biologist Montana Fish, Wildlife & Parks

More information

Khosla's theory. After studying a lot of dam failure constructed based on Bligh s theory, Khosla came out with the following;

Khosla's theory. After studying a lot of dam failure constructed based on Bligh s theory, Khosla came out with the following; Khosla's theory After studying a lot of dam failure constructed based on Bligh s theory, Khosla came out with the following; Following are some of the main points from Khosla's Theory From observation

More information

Fish Passage Culvert Assessment for Cahilty Creek Watershed FIA Project #

Fish Passage Culvert Assessment for Cahilty Creek Watershed FIA Project # Fish Passage Culvert Assessment for Cahilty Creek Watershed FIA Project # 4602004 Prepared for Weyerhaeuser Company Ltd. Jason Ladyman R.P.F. 1550 Mission Flats Road PO Box 40 Kamloops BC V2C 5K3 Prepared

More information

Stevens Creek Corridor

Stevens Creek Corridor O F F I C E O F T H E D I R E C T O R O F P U B L I C W O R K S Stevens Creek Corridor Creek Restoration Project Volume Three Project Update: Creek Photos, Before & After BY GAIL SEEDS - PROJECT MANAGER,

More information

Technical Report Culvert A Hydraulic Analysis

Technical Report Culvert A Hydraulic Analysis DATE: November 3, 2011 Technical Report Culvert A Hydraulic Analysis TO: FROM: RE: Jim Reiser, P.E. Project Manager Parsons Brinckerhoff, Inc. Kurt Killian, P.E., CFM Parsons Brinckerhoff, Inc. Design

More information

FISH PASSAGE ALTERNATIVES ANALYSIS ON PENNYPACK CREEK AT VERREE ROAD DAM AND ROOSEVELT BOULEVARD DAM PHILADELPHIA, PENNSYLVANIA

FISH PASSAGE ALTERNATIVES ANALYSIS ON PENNYPACK CREEK AT VERREE ROAD DAM AND ROOSEVELT BOULEVARD DAM PHILADELPHIA, PENNSYLVANIA FISH PASSAGE ALTERNATIVES ANALYSIS ON PENNYPACK CREEK AT VERREE ROAD DAM AND ROOSEVELT BOULEVARD DAM PHILADELPHIA, PENNSYLVANIA Prepared for: One Parkway, 10 th Floor 1515 Arch Street Philadelphia, PA

More information

STRUCTURAL STABILITY ASSESSMENT

STRUCTURAL STABILITY ASSESSMENT STRUCTURAL STABILITY ASSESSMENT CFR 257.73(d) Fly Ash Reservoir II Cardinal Plant Brilliant, Ohio October, 2016 Prepared for: Cardinal Operating Company Cardinal Plant Brilliant, Ohio Prepared by: Geotechnical

More information

Exercise (4): Open Channel Flow - Gradually Varied Flow

Exercise (4): Open Channel Flow - Gradually Varied Flow Exercise (4): Open Channel Flow - Gradually Varied Flow 1) A wide channel consists of three long reaches and has two gates located midway of the first and last reaches. The bed slopes for the three reaches

More information

SUMMARY OF MOVEMENT AND HABITAT USED BY TAGGED BROOK TROUT IN THE MAIN BRANCH AND NORTH BRANCH AU SABLE RIVER DURING SUMMER Data Submitted to:

SUMMARY OF MOVEMENT AND HABITAT USED BY TAGGED BROOK TROUT IN THE MAIN BRANCH AND NORTH BRANCH AU SABLE RIVER DURING SUMMER Data Submitted to: SUMMARY OF MOVEMENT AND HABITAT USED BY TAGGED BROOK TROUT IN THE MAIN BRANCH AND NORTH BRANCH AU SABLE RIVER DURING SUMMER 2014 Data Submitted to: Anglers of the Au Sable Submitted by: Dr. Mark R. Luttenton

More information

Abundance of Steelhead and Coho Salmon in the Lagunitas Creek Drainage, Marin County, California

Abundance of Steelhead and Coho Salmon in the Lagunitas Creek Drainage, Marin County, California scanned for KRIS Abundance of Steelhead and Coho Salmon in the Lagunitas Creek Drainage, Marin County, California Prepared for: Marin Municipal Water District 220 Nellen Drive Corte Madera, California

More information

DESCRIPTION OF THE CHELAN RIVER

DESCRIPTION OF THE CHELAN RIVER DESCRIPTION OF THE CHELAN RIVER The following information contains excerpts from the Whitewater Boating Feasibility Study conducted on the Chelan River in July, 2000. The Chelan River begins below the

More information

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH 133 OVER A DITCH ST. LOUIS COUNTY

UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO CSAH 133 OVER A DITCH ST. LOUIS COUNTY UNDERWATER BRIDGE INSPECTION REPORT STRUCTURE NO. 7780 CSAH 133 OVER A DITCH ST. LOUIS COUNTY SEPTEMBER 27, 2012 PREPARED FOR THE MINNESOTA DEPARTMENT OF TRANSPORTATION BY COLLINS ENGINEERS, INC. JOB NO.

More information

Dam Modification Report Stingy Run Fly Ash Reservoir Appendix E Spillway System Design Calculations E1: Spillway/Energy Dissipater Design for 100-year Event CHE8273 8 September 4, 2014 Written by: CJW

More information

STREAM SURVEY File form No..

STREAM SURVEY File form No.. scanned for KRIS THE RESOURCES AGENCY OF CALIFORNIA California Department of Fish and Game STREAM SURVEY File form No.. Date: September 4, 1969. NAME: North Fork Schooner Gulch Creek COUNTY: Mendocino.

More information

Gaviota Creek Fish Passage and Geomorphic Assessment

Gaviota Creek Fish Passage and Geomorphic Assessment Gaviota Creek Fish Passage and Geomorphic Assessment Prepared for California Department of Fish and Game And Pacific States Marine Fisheries Commission Prepared by Michael Love and Associates PO Box 4477

More information

FINAL REPORT. Yonkers Creek Migration Barrier Removal Project Wonderstump Road Del Norte County. Submitted By:

FINAL REPORT. Yonkers Creek Migration Barrier Removal Project Wonderstump Road Del Norte County. Submitted By: FINAL REPORT Yonkers Creek Migration Barrier Removal Project Wonderstump Road Del Norte County Submitted By: Del Norte County Community Development Department Yonkers Creek Migration Barrier Removal Project

More information

Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1]

Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1] Check Dams DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1] [1] Though not generally considered

More information

Climate Change Adaptation and Stream Restoration. Jack Williams;

Climate Change Adaptation and Stream Restoration. Jack Williams; Climate Change Adaptation and Stream Restoration Jack Williams; jwilliams@tu.org 1 Goals for this presentation Develop strategies for adapting streams to climate impacts by Thinking like a watershed Understanding

More information

19.1 Problem: Maximum Discharge

19.1 Problem: Maximum Discharge 19.1 Problem: Maximum Discharge In partially full channel having an equilateral triangular cross section, the rate of discharge is Q = KAR/3 in which K is a constant, A flow area, R is the hydraulic mean

More information

Final Bull Trout Genetics Monitoring Plan for the Wallowa Falls Hydroelectric Project. (FERC No. P-308) June 2017

Final Bull Trout Genetics Monitoring Plan for the Wallowa Falls Hydroelectric Project. (FERC No. P-308) June 2017 Final for the Wallowa Falls Hydroelectric Project (FERC No. P-308) June 2017 Prepared by: Jeremiah Doyle PacifiCorp 825 NE Multnomah Street Portland, OR 97232 June, 2017 Page 1 of 8 Table of Contents 1.0

More information

Report prepared for: Prepared by: January 2002 BEAK Ref

Report prepared for: Prepared by: January 2002 BEAK Ref AQUATIC ENVIRONMENTAL STUDY KANATA WEST CONCEPT PLAN Report prepared for: ROBINSON CONSULTANTS Prepared by: BEAK INTERNATIONAL INCORPORATED 14 Abacus Road Brampton, Ontario L6T 5B7 January 2002 BEAK Ref.

More information

Fish Migration Barrier Severity and Steelhead Habitat Quality in the Malibu Creek Watershed

Fish Migration Barrier Severity and Steelhead Habitat Quality in the Malibu Creek Watershed Fish Migration Barrier Severity and Steelhead Habitat Quality in the Malibu Creek Watershed Produced for California State Coastal Conservancy and California Department of Parks and Recreation By: Heal

More information

HYDROLOGIC AND HYDRAULIC REPORT PROPOSED CULVERT STRUCTURES SR 194, SECTION 10

HYDROLOGIC AND HYDRAULIC REPORT PROPOSED CULVERT STRUCTURES SR 194, SECTION 10 HYDROLOGIC AND HYDRAULIC REPORT PROPOSED CULVERT STRUCTURES SR 194, SECTION 10 RACETRACK ROAD CULVERT OVER THE SPRING RUN & GREEN SPRINGS ROAD CULVERT OVER AN UNNAMED TRIBUTARY TO SPRING RUN BERWICK TOWNSHIP

More information

SECTION 2 HYDROLOGY AND FLOW REGIMES

SECTION 2 HYDROLOGY AND FLOW REGIMES SECTION 2 HYDROLOGY AND FLOW REGIMES In this section historical streamflow data from permanent USGS gaging stations will be presented and discussed to document long-term flow regime trends within the Cache-Bayou

More information

As temporary grade control facilities along waterways until final stabilization is established.

As temporary grade control facilities along waterways until final stabilization is established. Check Dams (CD) EC-12 Description Check dams are temporary grade control structures placed in drainage channels to limit the erosivity of stormwater by reducing flow velocity. Check dams are typically

More information

MEMORANDUM. TNC Fisher Slough Final Design and Permitting Subject: DRAFT Technical Memorandum: Levee Emergency Spillway Design

MEMORANDUM. TNC Fisher Slough Final Design and Permitting Subject: DRAFT Technical Memorandum: Levee Emergency Spillway Design MEMORANUM TNC Fisher Slough Final esign and Permitting Subject: RAFT Technical Memorandum: Levee Emergency Spillway esign To: From: Internal Memorandum For Record Yen Hsu Chen (Tetra Tech) avid Cline (Tetra

More information